PERFORMANCE BASED PRACTICAL DESIGN

Similar documents
Transcription:

PERFORMANCE BASED PRACTICAL DESIGN

DOT S FACE INCREASING CHALLENGES

ENGINEERING CULTURE We learned from those who taught us how and why we follow the standards There are valid reasons that tell us we now need to work differently: Funding Staff Resources Aging infrastructure Environmental considerations Availability of reliable data and information Technology

WHAT IS PBPD? PBPD is a decision making approach that helps agencies better manage transportation investments and serve system-level needs and performance priorities with limited resources.

PBPD IS NOT: New Policy, Regulation, or Requirement Opportunity to disregard long-term needs: For short term cost savings Overlooking future development Compromising on safety, user needs (bike, ped, etc.), or accommodation of freight to save money

COMMON THEMES OF PBPD: Project decisions are based on critical examination of geometric elements Select/size elements that serve priority needs Reduce or eliminate those that don t Utilizes relevant, objective data to inform decisions Choices made to serve project priorities while trying to save money Project savings benefit System Needs

NOTABLE ATTRIBUTES PBPD focuses on performance improvements that benefit both project and system needs. Agencies make sound decisions based upon performance analysis. By scrutinizing each element of a project s scope relative to value, need, and urgency, a PBPD approach seeks a greater return on infrastructure investments.

PBPD OVERLAPPING Context Sensitive Solutions Value Engineering System Performance

PRACTICAL DESIGN EXAMPLE Existing Typical 9 Lanes 3 Shoulders Proposed Initial Typical 12 Lanes 4 Paved Shoulder 4 Aggregate Shoulder 11 Lane 2 Paved Shoulder 1 Aggregate Shoulder

Pavement Design Practical Design Savings Item Original Cost Practical Cost Savings Reduce driving lane from 12' to 11' $3,600,000 $3,300,000 $300,000 Minimize Underdrain Depth and locations $120,000 $60,000 $60,000 Shoulder Design Reducing shoulder Aggregate width 4' to 1' $160,000 $40,000 $120,000 Reduce to 3:1 Side Slopes and V-bottom ditches $775,000 $525,000 $250,000 Utilities Relocate 8" gas line to lower elevation $3,000,000 $500,000 $2,500,000 Move OH utilities inside Clear Zone: Reduce trees to be removed $232,000 $132,000 $100,000 Reduce area of mitigated wetlands $500,000 $400,000 $100,000 Reduce number of mitigated trees $50,000 $10,000 $40,000 Structures Modify instead of replace most large structures $700,000 $200,000 $500,000 Structure Removal $120,000 $20,000 $100,000 Minimizing Cover Depth at Crest Curves $40,000 Structure Backfill $60,000 $20,000 $40,000 TOTAL PROJECT SAVINGS: $4,150,000

PERFORMANCE BASED PRACTICAL DESIGN EXAMPLE

PERFORMANCE BASED PRACTICAL DESIGN EXAMPLE

PERFORMANCE BASED PRACTICAL DESIGN EXAMPLE

TEST YOUR GUESS: RECONFIGURING FREEWAY FOR CAPACITY How would you choose to reallocate the width for adding a lane? 16

TEST YOUR GUESS: RECONFIGURING FREEWAY FOR CAPACITY Out of alternatives 1-5, which predicted crash performance comes out on top? Alternative No. of General Purpose Lanes NoBuild 3 Inside Shoulder Width 12 Lane Width 12 12 12 12 Outside Shoulder Width Alt. 1 4 4 11 11 12 12 10 Alt. 2 4 8 11 11 11 11 8 Alt. 3 4 6 11 11 11 11 10 Alt. 4 4 4 11 11 11 11 12 Alt. 5 4 2 11 11 11 11 14 Full Build 4 12 12 12 12 12 12

K at least one fatality occurs A at least one disabling injury occurs B at least one evident, non-disabling injury occurs C at least one possible injury occurs PDO Out of no alternatives injury occurs 1-5, but which property predicted damage crash in excess of performance the state s minimum comes reporting out on top? threshold occurs TEST YOUR KNOWLEDGE: RECONFIGURING FREEWAY FOR CAPACITY Which One Would You Choose? Alternative No. of General Purpose Lanes NoBuild 3 Inside Shoulder Width 12 Lane Width 12 12 12 12 Outside Shoulder Width Estimated Crash Statistics Estimated average crash freq. during Study Period, crashes/yr: Total K A B C PDO 293.6 0.8 2.3 16.8 63.4 210.1 Alt. 1 4 4 11 11 12 12 10 293.9 1.3 3.1 22.9 65.3 201.3 Alt. 2 4 8 11 11 11 11 8 281.2 1.5 3.1 23.1 64.3 189.3 Alt. 3 4 6 11 11 11 11 10 286.4 1.5 3.0 22.9 63.8 195.2 Alt. 4 4 4 11 11 11 11 12 292.2 1.4 3.0 22.9 63.6 201.3 Alt. 5 4 2 11 11 11 11 14 298.5 1.4 3.0 22.9 63.6 207.5 Full Build 4 12 12 12 12 12 12 254.4 0.9 2.6 18.6 54.2 178.1

Case Study: Evaluation of PennDOT I-70 Project using IHSDM

Case Study Alt. 3: Local road improvements (No Interchange) Alt. 2a: New Interchange

Case Study

Is this a Rutting Issue? A Cross-Slope Issue? Or Some Combination of Both?

Hydroplaning Speed (mph) Hydroplaning Predictive Analysis Results 51 50 49 48 47 46 45 44 43 0 100 200 300 400 500 600 700 800 900 1000 Section Length (ft) Rainfall Intensity: 6 in/hr Rainfall Intensity: 6.972in/hr Speed Limit 1100 1200 1300 1400 1500

LIDAR WITH DRAINAGE PATH LENGTH MODELED

FIXING THIS IS COMPLICATED ESPECIALLY WHEN BRIDGES ARE INVOLVED

Variable Speed Limits

RISK AND UNCERTAINTY Usually we tend to focus on a single value or set of estimates to describe our projections into the future What about error? How sensitive are our results to potential changes in input? What sort of confidence can we assume? What is the probability of success?

WHEN YOU CONSIDER THE RISK OF BEING OFF ON YOUR PREDICTED PERFORMANCE CALCULATIONS What if the following assumptions are off? Traffic data Crash predictions User costs Construction/materials costs The chances the alternative will UNDERPERFORM the calculated B/C is greater than 89%. The chances the alternative will outperform the calculated B/C are about 10%. 0 1 2 2.1 3 Calculated Benefit/Cost

ALL ENGINEERING CHOICES HAVE TRADE-OFFS Which One Would You Choose? Below Design Criteria Meets or Exceeds Design Criteria Value (Operations, Safety, Efficiency etc.) Same Value, Lower Cost Minimum Standards Same Cost, Better Value Cost 29

TEST YOUR KNOWLEDGE: WIDENING FREEWAY FOR CAPACITY Which One Would You Choose? Out of alternatives 1-5, which predicted crash performance comes out on top? Alternative No. of General Purpose Lanes NoBuild 3 Inside Shoulder Width 12 Lane Width 12 12 12 12 Outside Shoulder Width Estimated Crash Statistics Estimated average crash freq. during Study Period, crashes/yr: Total K A B C PDO 293.6 0.8 2.3 16.8 63.4 210.1 Alt. 1 4 4 11 11 12 12 10 293.9 1.3 3.1 22.9 65.3 201.3 Alt. 2 4 8 11 11 11 11 8 281.2 1.5 3.1 23.1 64.3 189.3 Alt. 3 4 6 11 11 11 11 10 286.4 1.5 3.0 22.9 63.8 195.2 Alt. 4 4 4 11 11 11 11 12 292.2 1.4 3.0 22.9 63.6 201.3 Alt. 5 4 2 11 11 11 11 14 298.5 1.4 3.0 22.9 63.6 207.5 Full Build 4 12 12 12 12 12 12 254.4 0.9 2.6 18.6 54.2 178.1

KEY REPORTS

THE 13 CONTROLLING CRITERIA ARE PROPOSED TO CHANGE 32

WWW.REGULATIONS.GOV FHWA proposes to eliminate the following controlling criteria: Bridge Width Vertical Alignment Lateral Offset to Obstruction To improve clarity, FHWA proposes to rename the following existing controlling criteria: Horizontal Alignment Horizontal Curve Radius Grade Maximum Grade Structural Capacity Design Loading Structural Capacity

WWW.REGULATIONS.GOV Controlling Criteria FHWA Proposes To Retain for Roadways on the NHS With a Design Speed Equal to or Greater Than 50 mph (80 km/h): 1. Design Speed* 2. Lane Width 3. Shoulder Width 4. Horizontal Curve Radius 5. Superelevation 6. Stopping Sight Distance 7. Maximum Grade 8. Cross Slope 9. Vertical Clearance 10.Design Loading Structural Capacity* *Design Speed & Design Loading Structural Capacity is proposed to apply to all NHS roads regardless of Design Speed Comments must be received on or before December 7, 2015

FHWA WILL BE A GOOD PARTNER FHWA is prepared to support States as they develop projects with a system performance mindset using data-driven methods

QUESTIONS