CONSTRUCTION SPECIFICATION FOR EXCAVATING, BACKFILLING AND COMPACTING FOR MAINTENANCE HOLES, CATCH BASINS, DITCH INLETS AND VALVE CHAMBERS

Similar documents
CONSTRUCTION SPECIFICATION FOR TRENCHING, BACKFILLING AND COMPACTING

CONSTRUCTION SPECIFICATION FOR TRENCHING, BACKFILLING, AND COMPACTING

CONSTRUCTION SPECIFICATION FOR TRENCHING, BACKFILLING, AND COMPACTING

CONSTRUCTION SPECIFICATION FOR TRENCHING, BACKFILLING, AND COMPACTING

CONSTRUCTION SPECIFICATION FOR TRENCHING, BACKFILLING, AND COMPACTING

Construction Specification for Trenching, Backfilling and Compacting

CONSTRUCTION SPECIFICATION FOR SUPPORT SYSTEMS

CONSTRUCTION SPECIFICATION FOR SITE RESTORATION FOLLOWING INSTALLATION OF PIPELINES, UTILITIES, AND ASSOCIATED STRUCTURES

CONSTRUCTION SPECIFICATION FOR EXCAVATING AND BACKFILLING - STRUCTURES

CONSTRUCTION SPECIFICATION FOR PRECAST REINFORCED CONCRETE BOX CULVERTS AND BOX SEWERS IN OPEN CUT

Construction Specification for General Excavation

CONSTRUCTION SPECIFICATION FOR SITE PREPARATION FOR PIPELINES, UTILITIES, AND ASSOCIATED STRUCTURES

CONSTRUCTION SPECIFICATION FOR INSTALLATION OF ELECTRICAL CHAMBERS

CONSTRUCTION SPECIFICATION FOR PRECAST REINFORCED CONCRETE BOX CULVERTS AND BOX SEWERS IN OPEN CUT

CONSTRUCTION SPECIFICATION FOR CLEARING, CLOSE CUT CLEARING, GRUBBING, AND REMOVAL OF SURFACE AND PILED BOULDERS

SITE SERVICES GUELPH TRANSIT OPERATIONS & MAINTENANCE SECTION WATSON ROAD FACILITY PAGE 1 OF 6 WATER RECLAMATION PROJECT JUNE 2013

CONSTRUCTION SPECIFICATION FOR NEW MAINTENANCE HOLE, CATCH BASIN, DITCH INLET, AND VALVE CHAMBER INSTALLATION

CONSTRUCTION SPECIFICATION FOR SITE PREPARATION FOR PIPELINES, UTILITIES, AND ASSOCIATED STRUCTURES

CONSTRUCTION SPECIFICATION FOR THE INSTALLATION OF ELECTRICAL CHAMBER

CONSTRUCTION SPECIFICATION FOR PRECAST REINFORCED CONCRETE BOX CULVERTS IN OPEN CUT

CONSTRUCTION SPECIFICATION FOR INSTALLATION OF ELECTRICAL CHAMBERS

Construction Specification for Utility Adjustments

EXCAVATION, TRENCHING & BACKFILLING..1 The section refers to excavation, trenching, backfilling and all Work pertaining thereto.

CONSTRUCTION SPECIFICATION FOR ADJUSTING OR REBUILDING MAINTENANCE HOLES, CATCH BASINS, DITCH INLETS, AND VALVE CHAMBERS

CONSTRUCTION SPECIFICATION FOR PIPE SUBDRAINS

CONSTRUCTION SPECIFICATION FOR COMPACTING

Amendment to OPSS 416 (Nov 2013) Construction Specification for Pipeline and Utility Installation by Jacking and Boring

CONSTRUCTION SPECIFICATION FOR BORROW

CONSTRUCTION SPECIFICATION FOR PIPELINE INSTALLATION BY TUNNELLING

STANDARD SPECIFICATIONS JULY 2012 S-11 CULVERTS, HEADWALLS AND ROADSIDE DRAINAGE TABLE OF CONTENTS

CONSTRUCTION SPECIFICATION FOR PIPE SUBDRAINS

CONSTRUCTION SPECIFICATION FOR CEMENT MORTAR LINING OF WATERMAINS

Special Provision No. 405F03 March 2005

CONSTRUCTION SPECIFICATION FOR UNTREATED GRANULAR, SUBBASE, BASE, SURFACE SHOULDER AND STOCKPILING

CONSTRUCTION SPECIFICATION FOR SITE RESTORATION FOR UNDERGROUND UTILITIES

CONSTRUCTION SPECIFICATION FOR TUNNELLING

CONSTRUCTION SPECIFICATION FOR UNTREATED GRANULAR SUBBASE, BASE, SURFACE, SHOULDER, AND STOCKPILING

CONSTRUCTION SPECIFICATION FOR CONCRETE CURB AND GUTTER SYSTEMS

CONSTRUCTION SPECIFICATION FOR INSTALLATION OF GABIONS

406 - PIPE SEWERS - MTC FORM 406

CONSTRUCTION SPECIFICATION FOR PIPELINE AND UTILITY INSTALLATION BY JACKING AND BORING

CONSTRUCTION SPECIFICATION FOR CONCRETE CURB AND GUTTER SYSTEMS

CONSTRUCTION SPECIFICATION FOR GROUNDING

CONSTRUCTION SPECIFICATION FOR CONCRETE SIDEWALK

CONSTRUCTION SPECIFICATION FOR BORROW

The Regional Municipality of Peel Basis of Payment

CONSTRUCTION SPECIFICATION FOR EARTH BORROW

CONSTRUCTION SPECIFICATION FOR CONCRETE CURB AND GUTTER SYSTEMS

CONSTRUCTION SPECIFICATION FOR DEWATERING

SECTION TRENCHING

Special Provision No. 421F01 April 2006

CITY OF GUELPH CONTRACT NO SUPPLEMENTAL SPECIAL PROVISIONS

CONSTRUCTION SPECIFICATION FOR UNTREATED SUBBASE, BASE, SURFACE, SHOULDER, SELECTED SUBGRADE, AND STOCKPILING

CONSTRUCTION SPECIFICATION FOR PIPELINE AND UTILITY INSTALLATION BY JACKING AND BORING

CONSTRUCTION SPECIFICATION FOR CONCRETE UNIT PAVERS

AMENDMENTS TO OPSS 408 (OCT 89) CONSTRUCTION SPECIFICATION FOR ADJUSTING OR REBUILDING MANHOLES, CATCH BASINS, DITCH INLETS AND VALVE CHAMBERS

Amendment to OPSS 518 (Nov 2011) Construction Specification for Control of Water from Dewatering Operations

Division IV Section 4100 Measurement and Payment PUBLIC WORKS DEPARTMENT

CONSTRUCTION SPECIFICATION FOR BORROW

Special Provision No. 421S01 November 2006

CONSTRUCTION SPECIFICATION FOR GRADING

Special Provision No. 599S22 March 2018 REQUIREMENTS FOR RETAINED SOIL SYSTEMS (RSS)

CONSTRUCTION SPECIFICATION FOR FOOTINGS AND PADS FOR ELECTRICAL EQUIPMENT

CITY OF LETHBRIDGE SECTION Construction Specifications SIDEWALK CONSTRUCTION PAGE 1 of 5

CONSTRUCTION SPECIFICATION FOR BORROW

(SIZE) MANHOLES CATCH BASINS AND DITCH INLETS -Item No. ADJUSTING AND REBUILDING MANHOLES, CATCH BASINS AND DITCH INLETS - Item No.

Special Provision No. 399F01 December 2014

CONSTRUCTION SPECIFICATION FOR THE INSTALLATION OF INTERLOCKING CONCRETE PAVERS

B701 WATERMAINS- OPSS 701

CONSTRUCTION SPECIFICATION FOR PIPE CULVERT INSTALLATION IN OPEN CUT

CONSTRUCTION SPECIFICATION FOR CONCRETE FOOTINGS AND MAINTENANCE PLATFORMS FOR HIGH MAST LIGHTING POLES

CONSTRUCTION SPECIFICATION FOR INSTALLATION OF GABIONS

B441 - WATERMAINS - OPSS GENERAL

SPECIFICATIONS FOR BRIDGE CONSTRUCTION SECTION 2 BACKFILL. 2.1 General...2-1

CONSTRUCTION SPECIFICATION FOR THE CLEANING AND FLUSHING OF PIPE SEWERS, CATCHBASINS, MAINTENANCE HOLES, DITCH INLETS, AND OIL-GRIT SEPARATORS

SECTION 303 CULVERTS

CONSTRUCTION SPECIFICATION FOR PIPE CULVERT INSTALLATION IN OPEN CUT

Construction Specification for Concrete Unit Pavers

CITY OF GUELPH CONTRACT NO SUPPLEMENTAL SPECIAL PROVISIONS

Construction Specification for Unshrinkable Fill

CONSTRUCTION SPECIFICATION FOR IN-PLACE FULL DEPTH RECLAMATION OF BITUMINOUS PAVEMENT AND UNDERLYING GRANULAR

MATERIAL SPECIFICATION FOR CIRCULAR AND ELLIPTICAL CONCRETE PIPE

Special Provision No. 799F01 March 2012 CONSTRUCTION SPECIFICATION FOR THE INSTALLATION OF NOISE BARRIER TABLE OF CONTENTS

C. Foundation stabilization for pipe and utility structures.

CONSTRUCTION SPECIFICATION FOR GRADING

CONSTRUCTION SPECIFICATION FOR WICK DRAIN INSTALLATION

Special Provision No. 599F01 May 2004 CONSTRUCTION SPECIFICATION FOR THE INSTALLATION OF NOISE BARRIER TABLE OF CONTENTS

1.01 GENERAL. l.02 PIPELINE TRENCH EXCAVATION PIPELINES AND STRUCTURES REVISION: SECTION 1 PAGE : 1-1

B351 - CONCRETE SIDEWALK - OPSS 351

1.02 RELATED WORK: Refer to the following sections for related work: Section 4000-Concrete Materials and Methods

CONSTRUCTION SPECIFICATION FOR REMOVAL

CONSTRUCTION SPECIFICATION FOR WICK DRAIN INSTALLATION

CONSTRUCTION SPECIFICATION FOR IN-PLACE FULL DEPTH RECLAMATION OF BITUMINOUS PAVEMENT AND UNDERLYING GRANULAR

CONSTRUCTION SPECIFICATION FOR IN-PLACE FULL DEPTH RECLAMATION OF BITUMINOUS PAVEMENT AND UNDERLYING GRANULAR

CONSTRUCTION SPECIFICATION FOR WICK DRAIN INSTALLATION

Construction Specification for Concrete Curb and Concrete Curb and Gutter

Transcription:

ONTARIO PROVINCIAL STANDARD SPECIFICATION METRIC OPSS 516 APRIL 1999 CONSTRUCTION SPECIFICATION FOR EXCAVATING, BACKFILLING AND COMPACTING FOR MAINTENANCE HOLES, CATCH BASINS, DITCH INLETS AND VALVE CHAMBERS TABLE OF CONTENTS 516.01 SCOPE 516.02 REFERENCES 516.03 DEFINITIONS 516.04 SUBMISSION AND DESIGN REQUIREMENTS - Not Used 516.05 MATERIALS 516.06 EQUIPMENT - Not Used 516.07 CONSTRUCTION 516.08 QUALITY ASSURANCE - Not Used 516.09 MEASUREMENT FOR PAYMENT 516.10 BASIS OF PAYMENT 516.01 SCOPE This specification covers the requirements for excavating, backfilling and compacting for the installation of storm and sanitary pipe sewer maintenance holes, storm sewer catch basins and ditch inlets, and valve chambers for watermains and forcemains. 516.02 REFERENCES This specification refers to the following standards, specifications or publications: Ontario Provincial Standard Specifications, General: OPSS 180 Management and Disposal of Excess Material Page 1 Rev. Date: 04/1999 OPSS 516

Ontario Provincial Standard Specifications, Construction: OPSS 206 OPSS 501 OPSS 503 OPSS 504 OPSS 507 OPSS 510 OPSS 515 OPSS 517 OPSS 538 Grading Compacting Site Preparation for Pipelines, Utilities and Associated Structures in Open Cut Preservation, Protection and Reconstruction of Existing Facilities Site Restoration Following Installation of Pipelines, Utilities and Associated Structures in Open Cut Removal Rock Excavation for Pipelines, Utilities and Associated Structures in Open Cut Dewatering of Pipeline, Utility and Associated Structure Excavation Support Systems Ontario Provincial Standard Specifications, Material: OPSS 1010 OPSS 1359 Aggregates - Granular A, B, M and Select Subgrade Material Unshrinkable Backfill 516.03 DEFINITIONS For this specification the following definitions apply: Additional Excavation: means all excavation ordered in writing by the Contract Administrator beyond that specified. Backfilling: means the operation of filling the excavation with bedding and backfill material. Backfill Material: means approved fill material used above the bedding and below the lower of the subgrade or finished grade or original ground. Bedding Material: means the material used to support the maintenance hole, catch basin, ditch inlet or valve chamber. Excavation, Earth and Rock: means the excavation classified as earth and rock according to OPSS 206. Imported Material: means material obtained from a source other than the Work Area. Maximum Dry Density: means the definition as provided in OPSS 501. Native Material: means the material removed to form an excavation within the Work Area for return to the same or other excavation. Over-Excavation: means all excavation beyond that specified, performed without the written order of the Contract Administrator. Structure: means maintenance hole, catch basin, ditch inlet or valve chamber. Unshrinkable Fill: means a controlled density cement treated aggregate material. Page 2 Rev. Date: 04/1999 OPSS 516

516.05 MATERIALS 516.05.01 Granular Material Granular material shall be according to OPSS 1010. 516.05.02 Backfill Material Backfill material shall be as specified. 516.05.02.01 Native and Imported Material Native and imported material shall be material approved by the Contract Administrator. All material shall be free from frozen lumps, cinders, ashes, refuse, vegetable or organic matter, rocks and boulders over 150 mm in any dimension and other deleterious material. 516.05.03 Unshrinkable Fill Unshrinkable fill shall be according to OPSS 1359. 516.07 CONSTRUCTION 516.07.01 General Excavations shall be stable and dry unless designated as subaqueous work. 516.07.02 Site Preparation Site preparation shall be according to OPSS 503. 516.07.03 Preservation and Protection of Existing Facilities Preservation and protection of existing facilities shall be according to OPSS 504. 516.07.04 Removals Removals shall be according to OPSS 510. 516.07.05 Dewatering Dewatering shall be according to OPSS 517. 516.07.06 Support Systems Support systems shall be according to OPSS 538. 516.07.07 Removal of Frozen Ground Written permission shall be obtained from the Contract Administrator before starting an excavation in frozen ground. The method used for removal of frozen ground shall not cause damage to adjacent structures or utilities. Page 3 Rev. Date: 04/1999 OPSS 516

516.07.08 Excavation Excavation shall be performed to the lines, grades and dimensions specified plus an allowance for support systems where required. Structures shall not be placed or constructed on an unsuitable foundation as may be determined by the Contract Administrator. Corrective measures ordered by the Contract Administrator to rectify deficiencies caused by over-excavation shall be performed. Weakened or disturbed soil shall be removed and replaced with granular material compacted to 95% maximum dry density where the excavated surface below or beside the proposed structure is disturbed or weakened by construction methods or procedures. Rock excavation for maintenance holes, catch basins, ditch inlets or valve chambers shall be according to OPSS 515. 516.07.09 Backfilling and Compacting 516.07.09.01 Bedding A 150 mm layer of granular bedding material shall be placed on the bottom of the excavation and compacted to 95% of the maximum dry density prior to the placing of the structures. 516.07.09.02 Backfill Backfill material shall be placed simultaneously on the sides of the structures in layers not exceeding 300 mm in thickness, loose measurement, and compacted to 95% of the maximum dry density before a subsequent layer is placed. Backfill material shall not commence around cast-in-place concrete structures until approval has been obtained from the Contract Administrator. 516.07.10 Additional Excavating, Backfilling and Compacting Additional excavating, backfilling and compacting shall be according to clauses under the Excavation, and Backfilling and Compacting subsections. Unsuitable materials shall be excavated and the resulting excavation shall be backfilled and compacted to obtain a suitable foundation. 516.07.11 Site Restoration Site restoration shall be according to OPSS 507. 516.07.12 Management and Disposal of Excess Material Management and disposal of excess material shall be according to OPSS 180. Page 4 Rev. Date: 04/1999 OPSS 516

516.09 MEASUREMENT FOR PAYMENT 516.09.01 Actual Measurement 516.09.01.01 Additional Excavating, Backfilling and Compacting Additional excavating, backfilling and compacting shall be based on the volume of the additional excavation. Additional excavation shall be measured in cubic metres prior to installation of the structure. The volume of the additional excavation shall be determined beyond the limits specified. 516.10 BASIS OF PAYMENT 516.10.01 Excavating, Backfilling and Compacting for Maintenance Holes, Catch Basins, Ditch Inlets and Valve Chambers Payment at the Contract price for the appropriate tender items for the installation of maintenance holes, catch basins, ditch inlets and valve chambers shall be full compensation for all labour, equipment and material to do the work. When the Contract contains separate items for work required by this specification, payment shall be at the contract prices and according to the specifications for such work. Any expenses for remedial work resulting from unauthorized over-excavation shall be borne by the Contractor. 516.10.02 Additional Excavating, Backfilling and Compacting - Item Payment at the contract price for the above item shall be full compensation for all labour, equipment and material to do the work. 516.10.03 Rock Excavation for Maintenance Holes, Catch Basins, Ditch Inlets and Valve Chambers Payment for rock excavation for maintenance holes, catch basins, ditch inlets and valve chambers shall be according to OPSS 515. Page 5 Rev. Date: 04/1999 OPSS 516