Report of Monitoring Visit to 6 Projects Conducted April and May Jonas Mugabe & Clesensio Tizikara. July 2016

Size: px
Start display at page:

Download "Report of Monitoring Visit to 6 Projects Conducted April and May Jonas Mugabe & Clesensio Tizikara. July 2016"

Transcription

1 Report of Monitoring Visit to 6 Projects Conducted April and May 2016 by Jonas Mugabe & Clesensio Tizikara July 2016

2 Monitoring & Evaluation visit background The structured field monitoring of the implementation of activities of MKTPlace started in 2014 (conducted by FARA in Africa). In July 2014, FARA and Embrapa agreed to regularly carry out M&E visits to sampled projects selected randomly by Embrapa. The discussions with the project teams are structured around a pre-filled standard questionnaire. The FARA team carries out the M&E activity and shares the report. Objectives of the M&E field visit The first M&E field visit was conducted from 13 th September to 1 st October 2014 covering 5 projects implemented in Kenya, Ethiopia, Uganda and Benin. The second visit to another set of 5 projects in Ghana, Mali, Ethiopia, Tanzania and Cameroon was conducted in May/June The objectives of the April/May 2016 visit were: To assess the progress made in implementing activities of 6 Africa-Brazil Agricultural Innovation Marketplace projects; To assess key issues and constraints faced during the implementing period, the exit strategies set up; To draw lessons learned that will inform other projects and the next calls for proposals in the frame of Africa-Brazil Agricultural Innovation Marketplace To capture experiences and lessons to feed into the side-event being organised during the AASW in Kigali June. The assessment was limited to levels of the implementation of the activities, the constraints/challenges faced by implementers and drawing lessons that can be learnt and shared to all partners for the MKTPlace and other initiatives. Six projects in Mali, Ethiopia, Ghana and Uganda were covered. Methodology used in the field visit The M&E tool/questionnaire (Annex 1) was sent to the teams who were requested to respond. Field visits by the FARA team followed, during which discussions were held with the project teams and other stakeholders (where it was possible) at the project sites. The project teams made presentations that served as the basis for discussion. Major findings of M&E field visit The major findings of the M&E field visit are summarized in the following bullets. However these elements are developed in one or another section of this report. Most of the projects have generated (or are likely to generate) impressive outputs. Most projects working with a diverse array of value chain actors have generated high expectations that may neither be satisfied in the current phase, nor achieve a scale that can achieve meaningful impact. The 2-year implementation period seems to be inadequate to generate research technologies and scale them out to end users. Some activities could not even be brought to final conclusion. The collaboration between African and Brazilian partners was highly appreciated and judged positive by African partners as mutually beneficial for both sides. However some Brazilian partners were not able to undertake all the planned visits to Africa. Although exit strategy is not clear for some of the projects, a number are linked to other institutional initiatives/projects with secured funding to continue/develop further project Africa-Brazil M&E visit (April - May 2016) 1

3 activities therefore guaranteeing some continuity. The projects show significant promise in terms of impacting on beneficiaries and sustainability is assured given the strong commitment of the host institutions and additional funding that is being leveraged from other sources. The involvement of policy-makers in the visited projects is still relatively low. Overall, the projects demonstrate that significantly important research outputs can be achieved with small investment provided it is properly managed. Africa-Brazil MKTPlace should think on the scaling up/out of outputs generated. There is need to integrate the capacity development thrusts of the innovation platform approach with use of modern ICTs and business incubation to speed up technology adoption and commercialization. Famer knowledge may be underappreciated in some instances. There is a strong need to bring knowledge at field level into the research programmes, harmonization of policies and interventions in the field; and to set up more concerted networks of stakeholders to provide an environment conducive to innovation and experimentation. The partnership between FARA- Embrapa and partner institutions should move beyond individuals. Building strong ties/partnerships between FARA- Embrapa -Partner institutions should be one of the objectives of Embrapa-Brazil. Visitation from Brazilian partners to Africa and the movement of germplasm out of Brazil continue to be big bottlenecks. This coupled with the seasonality of operations of some of the projects, cause delays in effective project start-up and completion within the stipulated periods. African students and scientists attached to the projects have been to Embrapa for training to gain skills in using new lab equipment acquired from project funds and other professional skill sets. M&E Team Field Notes The team at the Université des Sciences, des Techniques et des Technologies de Bamako (USTTB) LaboREM Biotech is implementing two projects aiming at improving soils. Those projects are: Enhancing smallholder maize production through the promotion of Tilemsi rock phosphate combinated with phosphate-solubilizing and nitrogen-fixing bacteria as P-fertilizer in Mali. Transfer of Embrapa s On-Farm AM-fungi inoculum production technology to enhance rock phosphate use efficiency and crop production of smallholders in Africa. Africa-Brazil M&E visit (April - May 2016) 2

4 The FARA team met and interacted with: Prof Bernard Sodio, Vice-Doyen chargé de l Enseignement et de la Recherche; Prof Moussa Karambe, Chef Departement Biologie; Madame Prof Nah Traore, Chef Departement Chimie; Prof Sekou Bouare, Departement de Chimie; Prof Amadou Hamadou Babana, Chef Laboratoire de Microbiologie et Biotechnologie Microbienne (LaboREM Biotech); Prof Diakaridia Traoré, LaboREM Biotech; Mr Amadou Hamadoun Dicko, PhD student in LaboREM Biotech and Mr Ibrahima Mallé, MSC student. The team also visited the WAPP Mali office and met with Mr Yaya Traoré, Coordinateur Technique and Mrs Mariam Keita, Chargée de questions Sociales et Genre. The two projects in Mali have made a good progress as they take advantage of students doing their postgraduate studies. Impressive outputs have been generated on station. The last phase is on farm research that is waiting for the rains around July The two projects may require an extension to allow them validate the technologies on-farm. The two students working on projects in Mali (USTTB) have been to Embrapa for training to gain skills in using new lab equipment acquired from project funds. Also in case of Mali, the projects have strong links with the WAAPP and other partners involved in similar initiatives. This ensures the sustainability of the projects. However, none of Brazilian partners has visited Africa. Improving poultry production in Ethiopia through production system studies, breed characterization and implementation of improved practices - implemented by the Ethiopian Institute for Agricultural Research (EIAR). The team met Dr Zemelak Sahlegorags of the Ethiopian Institute of Agricultural Research (EIAR), Debreizet Station and also poultry farmers groups. The poultry project has conducted pre-surveys and a full survey to establish baselines on poultry production systems. The improved commercial Africa-Brazil M&E visit (April - May 2016) 3

5 free-range production model being introduced from Brazil is being implemented with a charitable NGO that has started to build facilities on a new site. Africa-Brazil M&E visit (April - May 2016) 4

6 High quality effective rhizobium inoculants for grain legumes in northern Ghana CSIR-SARI, Nyankpala, Tamale, Ghana The team was guided through the project achievements by the project co-leaders (Mr. Benjamin AHIABOR & Mr. Luc Rouws). A total of 5,541 farmers have been reached through video on inoculants technology. Eight lowly effective, 19 effective and one highly effective strain of rhizobia were isolated based on their symbiotic effectiveness on groundnut. A highly elite local rhizobium strain has been selected for groundnut and cowpea. Two SARI technicians trained in modern microbiology methods, inoculants production and quality control and molecular biology methods at Embrapa Agrobiologia, Brazil and have produced a set of quality control protocols on inoculants. Major difficulties were experienced in obtaining travel authorization to visit SARI for Brazilian team members. There was a major delay in the procurement of a laminar flow cabinet for sterile work. An inoculants production laboratory is being constructed with sponsorship from AGRA. There were no Africa-Brazil M&E visit (April - May 2016) 5

7 activities in the field as this was off-season but the team met participating farmers who showed enthusiasm and satisfaction with the project activities. Exchange of banana and plantain (Musa spp.) varieties and hybrids between IITA and Embrapa - widening the genetic base for the development of new cultivars and direct use by farmers NARO Banana programme Kawanda & IITA sub-station, Sendusu-Namulonge, Uganda The project plan was to evaluate the pest/disease, agronomic and palatability performance of banana hybrids developed by Embrapa (Brazil) and assist Embrapa with IITA s expertise in plantain breeding. 12 Embrapa hybrids were installed in the experimental area of NARO (Uganda) on 2 October 2015 and artificially infected with Fusarium, and will be planted in Nigeria in June There was an excessive delay in sending the hybrids from Brazil (15 months after the first import permit was issued!!!) due to excessive bureaucratic issues (legal analysis of the project and signing of the SMTA, basically). In Uganda, the Embrapa hybrids were multiplied and shipped to Nigeria. 13 IITA improved plantain hybrids have been sent to Brazil but are yet to be planted. Whereas the proposed plan cannot be finalized by the end of the project, both IITA/NARO and Embrapa will proceed with the germplasm evaluation as planned after the end of the project, as both parties see a great potential of Embrapa hybrids by smallholders in Africa, especially in Uganda and Nigeria, and Brazilian plantain farmers. This was the first time there was an export of banana germplasm from Brazil. The FARA team was conducted through and briefed by Dr. Brigitte Uwimana, Dr. Tendo and Dr. Edson Perito Amorim. Africa-Brazil M&E visit (April - May 2016) 6

8 Inoculation of efficient rhizobial strains as an approach to increase the pigeonpea production of smallholders in Uganda NaCCRI, Namulonge, Uganda The project, led by Mr. Charles Kasozi of NARO-NaCCRI Uganda was to evaluate the efficiency of the Brazilian semiarid Rhizobia (plus a strain already recommended by the ministry of agriculture) in at least three eco-regions of Uganda. Besides the evaluation of the Brazilian strains, a culture collection with Rhizobia from Uganda would be structured. The field evaluations would be performed according the official protocol of the Brazilian Agriculture Ministry to indicate a bacterial strain to field inoculation of pigeonpea seeds. The project was not able to import Rhizobium strains from Brazil and opted for morphological selection. Fifteen Rhizobial strains were used and laboratory and field work rum concurrently. Thirtytwo distinct strains have been isolated through PCR techniques and are to be sent to the Netherlands for sequencing. Field trials are conducted in Namulonge, Serere, Ngetta and Abi. CONCLUSION AND RECOMMENDATIONS a) The MKTPlace serves to promote investments in agricultural research and development; strengthen South-South Cooperation through new, innovative and effective mechanisms to satisfy a large demand for tropical agricultural technology. It is run through inclusive governance mechanisms and access to a large group of stakeholders using online platforms. b) The M&E exercise is one way for implementers and evaluators to learn some lessons from the project. One recurring lesson from the visits is that projects are often too ambitious in terms of Africa-Brazil M&E visit (April - May 2016) 7

9 anticipated impact. Projects, once selected should be assisted to refine their results frameworks and set realistic indicators. c) All research projects involve researchers from the two divides (Africa and Brazil). It is amazing to see how small amounts of money (maximum US$ 80,000) have generated high/visible outputs. This model has to be deeply documented and shared with other initiatives. All of them have involved national universities with students who carried out MSc thesis research. d) All partners expressed their satisfaction on the partnerships with Embrapa. In almost all projects visited this time, Brazilian partners visited the African partners. Similarly African scientists visited Embrapa or stayed there for training (at least two weeks). In a number of cases, germplasm and other technologies were exchanged between participating institutions. e) Considering the fact that almost all projects start with delay because of fund disbursement (which is common in projects), and that all projects (even those visited last year) requested for a no cost extension, it may be more prudent to set a new time horizon of 30 months for project implementation instead of the current 24 months. This will avoid the request by all projects of a no cost-extension. f) Some partners don t know the role of FARA in the initiative. There is need of streamline the reporting system so as to make FARA more visible in the action. g) M&E exercise should be undertaken routinely for all commissioned projects to assess the level of progress, discuss with implementers and report to donors. There is need to have a uniform format for reporting. APPRECIATION We would like to express our sincere gratitude to the project leaders and their institutions for the kind cooperation extended during our visits. We would also like extend our appreciation to Embrapa for the trust and the role it is playing in Africa-Brazil MKTPlace. Africa-Brazil M&E visit (April - May 2016) 8

10 ANNEX 1: MONITORING QUESTIONS The key question for process monitoring is are activities happening according to plan and, if not, what are the reasons? a) Status of Planned Activities As activities are executed, schedule variances often occur (activities can finish earlier or later than originally planned). What is the status of planned activities (as per the project work plan) and level of achievement of key milestones? What interventions have been completed and with what resources? Which activities are on schedule/delaying/proceeding as originally planned? What modifications were made and why? b) Outputs and Outcomes For the major activities undertaken during the reporting period, what outputs/products (both quantitative and qualitative) have been generated or developed and what has changed (outcomes achieved) as a result of your activities? What accomplishments or events do you consider newsworthy and would like to publicise to other project stakeholders? c) Development of stakeholder capacity What organisational and technical abilities has the project imparted on stakeholders to enhance their capacities and competencies in implementing project interventions (e.g. training and mentoring; clarity of roles, responsibilities and rights; institutional structures; partnerships and linkages)? What support mechanism has the project provided to facilitate the implementation of the action and enhance the participatory monitoring of processes, outputs and impact of the project? d) Project performance rating What is your overall rating of the performance of your project on the critical success factors of meeting project objectives, timeliness, functional involvement of stakeholders, and dissemination of outputs? Is the partnership arrangement still the right one to carry out the implementation? Were the processes used to create the necessary conditions and capacity the right ones to implement the project successfully? Is the project still appropriate to bring about sustainable benefits addressing the specific identified needs of the target beneficiaries? Is the project being implemented with fidelity and consistency and is the period of time sufficient for change to occur? Is the size and duration of the investment sufficient to reach the threshold level of change in the outcome? e) Key issues and Constraints What were the key issues and constraints that you faced during the reporting period; what you did to overcome them? Do the assumptions made during the planning process still hold true? Is the original implementation strategy still appropriate and should be continued or should it be modified? Is it necessary to make adjustments to resources and partnership arrangements? f) Lessons Learned List at least THREE key lessons you have learned during the reporting period (these could relate to working with partners, functional involvement of stakeholders, good practice, innovation, project management, communication, etc.). What would you do differently if you were to start all over again (from project design, finding co-leader in Brazil, to current state of project implementation)? Africa-Brazil M&E visit (April - May 2016) 9

11 Annex 2: M&E Report: banana and plantain (Musa spp.) varieties and hybrids The key question for process monitoring is are activities happening according to plan and, if not, what are the reasons? a) Status of Planned Activities As activities are executed, schedule variances often occur (activities can finish earlier or later than originally planned). What is the status of planned activities (as per the project work plan) and level of achievement of key milestones? What interventions have been completed and with what resources? Which activities are on schedule/delaying/proceeding as originally planned? What modifications were made and why? The plan was to evaluate the pest/disease, agronomic and palatability performance of banana hybrids developed by Embrapa (Brazil) and assist Embrapa with IITA s expertise in plantain breeding. The Embrapa hybrids were installed in the experimental area of NARO (Uganda) on 2 October 2015 and artificially infected with Fusarium, and will be planted in Nigeria in June There was an excessive delay in sending the hybrids from Brazil (15 months after the first import permit was issued!!!) due to excessive bureaucratic issues (legal analysis of the project and signing of the SMTA, basically). In Uganda, the Embrapa hybrids were multiplied and shipped to Nigeria. IITAs improved plantain hybrids have been sent to Brazil but need still to be planted. Again administration was delaying shipment of germplasm. All this was funded by the Marketplace budget. The proposed plan can thus not be finalized by the end of the project. Yet both IITA/NARO and Embrapa will proceed with the germplasm evaluation as planned after the end of the project, as both parties see a great potential of Embrapa hybrids by smallholders in Africa, especially in Uganda and Nigeria, and Brazilian plantain farmers. b) Outputs and Outcomes For the major activities undertaken during the reporting period, what outputs/products (both quantitative and qualitative) have been generated or developed and what has changed (outcomes achieved) as a result of your activities? What accomplishments or events do you consider newsworthy and would like to publicise to other project stakeholders? 12 Embrapa hybrids and have been imported to Uganda and Nigeria. These were planted in Uganda and will be planted next month in Nigeria. 13 PITA (black sigatoka resistant plantain hybrids) were sent to Brazil but are yet to be planted. The work is executed as planned with a large delay due to administrative issues linked to germplasm exchange. We need to await the reconfirmation of disease resistance in the 3 countries concerned as well acceptability by consumers. If positive, this will be very newsworthy. c) Development of stakeholder capacity What organisational and technical abilities has the project imparted on stakeholders to enhance their capacities and competencies in implementing project interventions (e.g. training and mentoring; clarity of roles, responsibilities and rights; institutional structures; partnerships and linkages)? What support mechanism has the project provided to facilitate the implementation of the action and enhance the participatory monitoring of processes, outputs and impact of the project? The technical partnership between Embrapa and IITA was efficient. The contacts between the leaders of the current proposal were frequent (via Skype, telephone or during Congress / Meetings / Workshops / etc.) and the actions necessary to implement the project were executed. Exchange of information between the collaborating partners has strengthened in-house capacity in breeding and field evaluation. Africa-Brazil M&E visit (April - May 2016) 10

12 d) Project performance rating What is your overall rating of the performance of your project on the critical success factors of meeting project objectives, timeliness, functional involvement of stakeholders, and dissemination of outputs? The project has fully met objectives it was set to achieve with full involvement of the community and other stakeholders as planned. Outputs are being disseminated through different channels including MSc theses, scientific papers, trainings and workshops. Is the partnership arrangement still the right one to carry out the implementation? Yes Were the processes used to create the necessary conditions and capacity the right ones to implement the project successfully? Yes, but the science and evaluation delivery were seriously delayed by bureaucracy. Is the project still appropriate to bring about sustainable benefits addressing the specific identified needs of the target beneficiaries? Yes Is the project being implemented with fidelity and consistency and is the period of time sufficient for change to occur? No. Two years were not enough to complete the proposed activities Is the size and duration of the investment sufficient to reach the threshold level of change in the outcome? No. once the hybrids are found to be resistant and acceptable by consumers, these hybrids needs to be multiplied at a very large scale and distributed at a very large scale. In addition, similar tests needs to be executed in different African countries. e) Key issues and Constraints What were the key issues and constraints that you faced during the reporting period; what you did to overcome them? Do the assumptions made during the planning process still hold true? Is the original implementation strategy still appropriate and should be continued or should it be modified? Is it necessary to make adjustments to resources and partnership arrangements? The main problem observed in the project concerns the Brazilian bureaucratic issues associated with the germplasm exchange. Anything else is straightforward and needs to continue in an unchanged matter. f) Lessons Learned List at least THREE key lessons you have learned during the reporting period (these could relate to working with partners, functional involvement of stakeholders, good practice, innovation, project management, communication, etc.). What would you do differently if you were to start all over again (from project design, finding co-leader in Brazil, to current state of project implementation)? Three key lessons: 1. Better understanding of the bureaucratic issues (legal) associated with germplasm exchange in Brazil 2. Key people at Embrapa Headquarters to facilitate germplasm exchange process identified 3. Germplasm import in Nigeria from Brazil is impossible due to absolutely lack of knowledge of correct quarantine requirements Africa-Brazil M&E visit (April - May 2016) 11

13 Annex 3: Monitoring Report - Improving poultry production in Ethiopia The key question for process monitoring is are activities happening according to plan and, if not, what are the reasons? g) Status of Planned Activities As activities are executed, schedule variances often occur (activities can finish earlier or later than originally planned). What is the status of planned activities (as per the project work plan) and level of achievement of key milestones? What interventions have been completed and with what resources? Which activities are on schedule/delaying/proceeding as originally planned? What modifications were made and why? Activities listed from A to K were accomplished as planned however, L & M, not as we need to wait construction of house for the proposed model free range production system at selected site " Mekedonia home for elderly and mentally disabled" which is located in Addis Ababa. Link: A) Signing project contract agreement B) Attending 2015's MKTPlace forum in Brasilia, meet Brazilian project coordinator & present project proposal (Sep15-18, 2015) C) Visiting free range poultry production systems at Concordia, Brazil (Sep8-9, 2015) D) Project launching meeting at DZARC, project team formation E) Input purchased: equipments, supplies, breed from local market F) Conducting a preliminary survey with a one page questionnaire to identify target respondents G) Training data collectors H) Structured questionnaire preparation for final data collection, testing questionnaires I) Collecting data on characterization of poultry production, status, challenges, and opportunities at small, medium and large scales level in Ethiopia J) Collecting information package on alternative free range layers production systems K) Selecting target households for introducing a model free range layers production system L) Input purchase for introducing a model free range layers production system M) Establishing model free range production system at selected households Africa-Brazil M&E visit (April - May 2016) 12

14 h) Outputs and Outcomes For the major activities undertaken during the reporting period, what outputs/products (both quantitative and qualitative) have been generated or developed and what has changed (outcomes achieved) as a result of your activities? What accomplishments or events do you consider newsworthy and would like to publicise to other project stakeholders? Linkage was established with Brazilian poultry breeding company: Poultry breed technologies such as EMRAPA 051, and C431A/CPK were identified as important source technology for future importation into Ethiopia Seminars were conducted at Debrezeit Agricultural Research Center and EIAR to create awareness on the planned project activities and also introduce Brazilian poultry technologies Enumerators were trained on data collection Researchers and technical assistants were trained on data recording Software: Micro-soft access database A useful production guideline on free range poultry management practices was obtained from Embrapa swine and poultry Contact was established with Brazilian Ambassador and other colleagues in Addis Ababa, Ethiopia, for further collaborations Field data have been collected on poultry husbandry, performance, production systems, opportunities and challenges Appropriate site was selected to introduce a model Brazilian free range layers production system in Ethiopia. A contract agreement was prepared for the proposed free range production system i) Development of stakeholder capacity What organisational and technical abilities has the project imparted on stakeholders to enhance their capacities and competencies in implementing project interventions (e.g. training and mentoring; clarity of roles, responsibilities and rights; institutional structures; partnerships and linkages)? What support mechanism has the project provided to facilitate the implementation of the action and enhance the participatory monitoring of processes, outputs and impact of the project? A seminar was conducted to create awareness field level data collectors were trained on data collection methods Researchers and technical assistants were trained on data recording Software Networking was established with different Embrapa researchers, African researchers, and partners from funding organizations at 2015 MKTPlace forum Office equipments were purchased: laptop, farm boots, clothing Laboratory inputs were ordered for purchase Project progress reports were submitted monthly and quarterly Africa-Brazil M&E visit (April - May 2016) 13

15 j) Project performance rating What is your overall rating of the performance of your project on the critical success factors of meeting project objectives, timeliness, functional involvement of stakeholders, and dissemination of outputs? The project has fully met objectives it was set to achieve with full involvement of the community and other stakeholders as planned. Outputs are being disseminated through different channels including MSc theses, scientific papers, trainings and workshops. Is the partnership arrangement still the right one to carry out the implementation? yes Were the processes used to create the necessary conditions and capacity the right ones to implement the project successfully? Yes Is the project still appropriate to bring about sustainable benefits addressing the specific identified needs of the target beneficiaries? Yes Is the project being implemented with fidelity and consistency and is the period of time sufficient for change to occur? We need extension time to implement the free range poultry production system and collect data on birds performance Is the size and duration of the investment sufficient to reach the threshold level of change in the outcome? Not enough, budget and time are limited k) Key issues and Constraints What were the key issues and constraints that you faced during the reporting period; what you did to overcome them? Do the assumptions made during the planning process still hold true? Is the original implementation strategy still appropriate and should be continued or should it be modified? Is it necessary to make adjustments to resources and partnership arrangements? - Delay of the Brazilian visit to Ethiopia - Government's lengthy procedure for input purchase, It might take a year to buy inputs, it might await the bid process - Office bureaucracy l) Lessons Learned List at least THREE key lessons you have learned during the reporting period (these could relate to working with partners, functional involvement of stakeholders, good practice, innovation, project management, Africa-Brazil M&E visit (April - May 2016) 14

16 communication, etc.). What would you do differently if you were to start all over again (from project design, finding co-leader in Brazil, to current state of project implementation)? - Involve people starting from pre-proposal writing stage - Already established linage is very important to easily get a co-leader for new projects - There are always challenges and bureaucracies in the process of project implementation - having good results make you more confident Annex 4: Monitoring Report - Rhizobium The key question for process monitoring is are activities happening according to plan and, if not, what are the reasons? m) Status of Planned Activities As activities are executed, schedule variances often occur (activities can finish earlier or later than originally planned). What is the status of planned activities (as per the project work plan) and level of achievement of key milestones? What interventions have been completed and with what resources? Which activities are on schedule/delaying/proceeding as originally planned? What modifications were made and why? i) Implementation of objective 1 has delayed due to the delay in building the inoculants production lab ii) Objective 2 is 60% achieved: A highly effective strain has been isolated for cowpea and groundnut. Isolation of rhizobium strains for Bambara groundnut is on-going at EMBRAPA n) Outputs and Outcomes For the major activities undertaken during the reporting period, what outputs/products (both quantitative and qualitative) have been generated or developed and what has changed (outcomes achieved) as a result of your activities? What accomplishments or events do you consider newsworthy and would like to publicise to other project stakeholders? 5541 farmers were reached through video on inoculants technology in Northern Region The inquiry about and demand for inoculants have greatly increased this year Eight lowly effective, 19 effective and one highly effective strains of rhizobia were isolated based on their symbiotic effectiveness on groundnut A highly elite local rhizobium strain has been selected for groundnut and cowpea. This strain will be authenticated in the field this season in replicated trials across northern Ghana Newsworthy: Inoculants technology can be disseminated successfully with active participation of the private sector. A survey revealed that 78 percent of the input dealers sampled were willing to expand their business to contain the legume inoculants business The revelation by the survey that farmers preferred inoculating soybean to cowpea & groundnut o) Development of stakeholder capacity Africa-Brazil M&E visit (April - May 2016) 15

17 What organisational and technical abilities has the project imparted on stakeholders to enhance their capacities and competencies in implementing project interventions (e.g. training and mentoring; clarity of roles, responsibilities and rights; institutional structures; partnerships and linkages)? What support mechanism has the project provided to facilitate the implementation of the action and enhance the participatory monitoring of processes, outputs and impact of the project? Two SARI technicians trained in modern microbiology methods, inoculants production and quality control and molecular biology methods at Embrapa Agrobiologia, Brazil. They produced a set of quality control protocols on inoculants. Training of farmers, input dealers, AEAs, Field officers of agriculture-base NGOs This project has a very strong partnership or linkage with the AGRA Soil Health project. Certain activities under the AGRA project which have limited budget were financed from the MktPlace project, e.g. radio broadcasts and community video screenings on inoculants technology. Project performance rating What is your overall rating of the performance of your project on the critical success factors of meeting project objectives, timeliness, functional involvement of stakeholders, and dissemination of outputs? The project has fully met the human resource training objective The objective on the isolation of local elite Rhizobium strains for soybean, cowpea and groundnut is generally about 65% complete. No appreciable progress has been made on the isolation of local elite Rhizobium strains for Bambara groundnut Outputs achieved so far are being disseminated through different channels including MSc theses, production of inoculants quality control protocol,, trainings and workshops. Is the partnership arrangement still the right one to carry out the implementation? Yes Were the processes used to create the necessary conditions and capacity the right ones to implement the project successfully? Yes Is the project still appropriate to bring about sustainable benefits addressing the specific identified needs of the target beneficiaries? Very appropriate Is the project being implemented with fidelity and consistency and is the period of time sufficient for change to occur? Yes. But the period of time is not sufficient for long-term real and observable changes to occur. But the little changes can be built on in subsequent projects. e.g. Out-scaling the benefits that will be derived from this project. Is the size and duration of the investment sufficient to reach the threshold level of change in the outcome? No p) Key issues and Constraints Africa-Brazil M&E visit (April - May 2016) 16

18 What were the key issues and constraints that you faced during the reporting period; what you did to overcome them? Do the assumptions made during the planning process still hold true? Is the original implementation strategy still appropriate and should be continued or should it be modified? Is it necessary to make adjustments to resources and partnership arrangements? From the Brazilian side, major difficulties were experienced to obtain travelling authorization to visit SARI for Brazilian team members. Since these visits have to be planned during, or close to, the planting period for cowpea, proper planning was difficult or impossible because field experiments depended on rainfall which was unpredictable. One visit planned in May, 2015 had to be cancelled because authorization by Embrapa was not obtained in time. From the Ghanaian side, there was a major delay in the procurement of a laminar flow cabinet for sterile work. This equipment is essential for microbiology work and for inoculant production. This delay affected the capacity of SARI to produce some minimum amounts of inoculants for use during the 2015 cropping season as proposed. The incidence of drought destroyed one of the field trials at Gbulahigu in the Tolon District. The assumption that the inoculants production laboratory being sponsored by AGRA would have been completed in time for some inoculants to be produced for the 2016 cropping season did not hold true due to constructional delays. q) Lessons Learned List at least THREE key lessons you have learned during the reporting period (these could relate to working with partners, functional involvement of stakeholders, good practice, innovation, project management, communication, etc.). What would you do differently if you were to start all over again (from project design, finding co-leader in Brazil, to current state of project implementation)? There is the need to understand very well the application processes involved in the proposal submission process The importance of constant and frequent communication between partners Farmers and agro-input dealers are increasingly getting interested in inoculants so project activities (especially dissemination by way of awareness creation and also making the inoculants available) should be carried out rigorously to achieve milestones in order to meet farmers and input dealers expectations Africa-Brazil M&E visit (April - May 2016) 17

MONITORING & EVALUATION

MONITORING & EVALUATION MONITORING & EVALUATION Clesensio Tizikara (FARA) Luciano Nass (Embrapa) 7 th Africa Agriculture Science Week Kigali, Rwanda, 14 th June 2016 Why focus on M&E? Essential to ensure quality and improve performance,

More information

Monitoring and Evaluation Report

Monitoring and Evaluation Report Monitoring and Evaluation Report 1 1. Introduction On April 20 th, 2016, as part of the M&E strategy of the Agricultural Innovation Marketplace MKTPlace, the in situ M&E of the project ID 1004 took place

More information

Putting nitrogen fixation to work for smallholder legume farmers in Africa (N2Africa) An effort in international partnerships

Putting nitrogen fixation to work for smallholder legume farmers in Africa (N2Africa) An effort in international partnerships 2012 Global Pulse Researchers Meeting Kigali, Rwanda February 13 17, 2012 Ken Dashiell Putting nitrogen fixation to work for smallholder legume farmers in Africa (N2Africa) An effort in international partnerships

More information

Update on Inoculant production by cooperating laboratories. Milestone reference number: Abdullahi Bala. Submission date: 20 October 2011

Update on Inoculant production by cooperating laboratories. Milestone reference number: Abdullahi Bala. Submission date: 20 October 2011 Update on Inoculant production by cooperating laboratories Milestone reference number: 3.4.3 Abdullahi Bala Submission date: N2Africa Putting nitrogen fixation to work for smallholder farmers in Africa

More information

Policy on Advanced Training Grants. Ken Giller and Saidou Koala. Submission date: 10/6/2010. N2Africa

Policy on Advanced Training Grants. Ken Giller and Saidou Koala. Submission date: 10/6/2010. N2Africa Policy on Advanced Training Grants Ken Giller and Saidou Koala Submission date: 10/6/2010 N2Africa Putting nitrogen fixation to work for smallholder farmers in Africa N2Africa is a project funded by The

More information

Facilitating local level dairy innovation platforms for smallholder farmers Report

Facilitating local level dairy innovation platforms for smallholder farmers Report Facilitating local level dairy innovation platforms for smallholder farmers Report Call For Report Call for final report Africa-Brazil Projects funded in the 2011/12 Report Status Submitted Title Facilitating

More information

ENHANCING COWPEA PRODUCTION AND NUTRITION THROUGH DEVELOPING DROUGHT TOLERANT AND HIGH PROTEIN LINES Report

ENHANCING COWPEA PRODUCTION AND NUTRITION THROUGH DEVELOPING DROUGHT TOLERANT AND HIGH PROTEIN LINES Report ENHANCING COWPEA PRODUCTION AND NUTRITION THROUGH DEVELOPING DROUGHT TOLERANT AND HIGH PROTEIN LINES Report Call For Report Call for final report Africa-Brazil Projects funded in the 2011/12 Report Status

More information

Pigeonpea in ESA: A story of two decades. Said Silim

Pigeonpea in ESA: A story of two decades. Said Silim Pigeonpea in ESA: A story of two decades Said Silim In 1991: Pigeonpea was not a crop of importance Farmers growing traditional low yielding varieties as intercrop Preference was for bold seeded fast cooking

More information

Bridging Research and Development Practice by Khalid Bomba, CEO, Agricultural Transformation Agency, Ethiopia

Bridging Research and Development Practice by Khalid Bomba, CEO, Agricultural Transformation Agency, Ethiopia Bridging Research and Development Practice by Khalid Bomba, CEO, Agricultural Transformation Agency, Ethiopia Keynote Address given at Research to Feed Africa Policy Dialogue, Addis Ababa September 2014

More information

N2Africa Project Zimbabwe Exit Strategy. Regis Chikowo and Isaac Chabata. October N2Africa

N2Africa Project Zimbabwe Exit Strategy. Regis Chikowo and Isaac Chabata. October N2Africa Regis Chikowo and Isaac Chabata October 2017 N2Africa Putting nitrogen fixation to work for smallholder farmers in Africa N2Africa is a project funded by The Bill & Melinda Gates Foundation by a grant

More information

Seed Value Chain Analysis

Seed Value Chain Analysis ISSD Technical Notes. Issue No. 3 Seed Value Chain Analysis WHAT is value chain analysis? A value chain is a chain of activities that are undertaken in the production, processing, marketing and sales of

More information

GCP/RAF/448/EC STRENGTHENING LINKAGES BETWEEN SMALL ACTORS AND BUYERS IN THE ROOTS AND TUBERS SECTOR IN AFRICA PROJECT IMPLEMENTATION PLAN GHANA

GCP/RAF/448/EC STRENGTHENING LINKAGES BETWEEN SMALL ACTORS AND BUYERS IN THE ROOTS AND TUBERS SECTOR IN AFRICA PROJECT IMPLEMENTATION PLAN GHANA STRENGTHENING LINKAGES BETWEEN SMALL ACTORS AND BUYERS IN THE ROOTS AND TUBERS SECTOR IN AFRICA PROJECT IMPLEMENTATION PLAN GHANA Project background and context The roots and tubers sector (R&T) is one

More information

Facilitating Access to and Uptake of Appropriate Technologies by Smallholder Farmers in Sub-Saharan Africa

Facilitating Access to and Uptake of Appropriate Technologies by Smallholder Farmers in Sub-Saharan Africa Facilitating Access to and Uptake of Appropriate Technologies by Smallholder Farmers in Sub-Saharan Africa Dr. Denis T. Kyetere Executive Director African Agricultural Technology Foundation Global Food

More information

Soybean breeding in Africa

Soybean breeding in Africa Soybean breeding in Africa H. Agrama Soybean Breeder International Institute of Tropical Agriculture (IITA) Soybean in Africa Improve human nutrition Major animal feed source Improve soil fertility Increase

More information

AGRA Support to Seed. Augustine Langyintuo. Presented at the FARNPAN Organized seed security Network. South Africa May 2010

AGRA Support to Seed. Augustine Langyintuo. Presented at the FARNPAN Organized seed security Network. South Africa May 2010 AGRA Support to Seed Security in Africa Augustine Langyintuo AGRA-Nairobi Presented at the FARNPAN Organized seed security Network. South Africa 20-21 May 2010 Introduction Low crop productivity in Africa

More information

N2Africa. Putting Nitrogen Fixation to Work for Smallholder Farmers in Africa Project. Final Report

N2Africa. Putting Nitrogen Fixation to Work for Smallholder Farmers in Africa Project. Final Report 1 N2Africa Putting Nitrogen Fixation to Work for Smallholder Farmers in Africa Project Final Report 2 Reporting Period: 1st May 2016 to 31st March 2017 Partner: URBANET Contents 1. Introduction... 3 2.

More information

This note presents methods that can be used to

This note presents methods that can be used to THEMATIC NOTE 2 Methods for Organizational Assessments in Agricultural Innovation Systems Regina Birner, University of Hohenheim SYNOPSIS This note presents methods that can be used to assess individual

More information

Centre International de Recherche et de Développement

Centre International de Recherche et de Développement Centre International de Recherche et de Développement Publication UNGANA 557 CIDR Tous droits de reproduction réservés Value chain promotion - Concept Paper - Cereal Banks promotion and access to market

More information

West Africa Centre for Crop Improvement. New Four Year Ph D Programme In Plant Breeding f or West Africa Centre For Crop Improvement

West Africa Centre for Crop Improvement. New Four Year Ph D Programme In Plant Breeding f or West Africa Centre For Crop Improvement West Africa Centre for Crop Improvement New Four Year Ph D Programme In Plant Breeding f or West Africa Centre For Crop Improvement Introduction The West Africa Centre for Crop Improvement (WACCI), a partnership

More information

USAID Rice Activities

USAID Rice Activities USAID Rice Activities CARD Steering Committee Meeting Freetown, Sierra Leone February 23-24, 2011 Eric Witte, Bureau for Food Security Feed the Future renews our commitment to invest in sustainably reducing

More information

Enhancing rice and maize production by small-holders using bacteria-plant extract biopesticide Report

Enhancing rice and maize production by small-holders using bacteria-plant extract biopesticide Report Enhancing rice and maize production by small-holders using bacteria-plant extract biopesticide Report Call For Report Call for final report Africa-Brazil Projects funded in the 2011/12 Report Status Submitted

More information

USAID s Feed the Future Research Programs: A Focused Set of Choices. Rob Bertram, PhD USAID Bureau for Food Security

USAID s Feed the Future Research Programs: A Focused Set of Choices. Rob Bertram, PhD USAID Bureau for Food Security USAID s Feed the Future Research Programs: A Focused Set of Choices Rob Bertram, PhD USAID Bureau for Food Security The Global Challenge Climate change already impacting yields - drought, high temperatures

More information

Feed the Future Innovation Lab for Small-Scale Irrigation Cooperative Agreement No. AID-OAA-A

Feed the Future Innovation Lab for Small-Scale Irrigation Cooperative Agreement No. AID-OAA-A Year 1 Reporting Period October 1, 2013 thru March 31, 2014 Feed the Future Innovation Lab for Small-Scale Irrigation Cooperative Agreement No. AID-OAA-A-13-00055 Due Date: April 30, 2014 I. Feed the Future

More information

Managing and implementing impact evaluations: lessons from 3ie agricultural innovation grants

Managing and implementing impact evaluations: lessons from 3ie agricultural innovation grants Learning brief 2 Agricultural innovation Neil Palmer / CIAT Managing and implementing impact evaluations: lessons from 3ie agricultural innovation grants The World Bank s World Development Report 2008:

More information

Is seeing really better than listening? The impact of inoculant technology dissemination via video and radio listening clubs in northern Ghana

Is seeing really better than listening? The impact of inoculant technology dissemination via video and radio listening clubs in northern Ghana Is seeing really better than listening? The impact of inoculant technology dissemination via video and radio listening clubs in northern Ghana Fred Dzanku, ISSER, University of Ghana fdzanku@gmail.com

More information

Concept note 3. (e.g. NZ and Purdue mail groups).

Concept note 3. (e.g. NZ and Purdue mail groups). PhAction annual meeting 2001 Linking Farmers to Markets : Developing a Global Post-Harvest Initiative Montpellier, France 11-14 June 2001 ======================================================= Concept

More information

17. Enabling Fertilizer Use Optimization in Sub-Saharan Africa

17. Enabling Fertilizer Use Optimization in Sub-Saharan Africa 17. Enabling Fertilizer Use Optimization in Sub-Saharan Africa Harrison Rware h.rware@cabi.org 1, Kayuki C. Kaizzi 2, Catherine J. Senkoro 3, Wondimu Bayu 1, George Oduor 1 and James Watiti 1 1 CABI, P.O.

More information

Launch Plan Spring 2015

Launch Plan Spring 2015 Launch Plan Spring 2015 A proposal for setting up a pilot Innovation Farm in Ghana to raise awareness and adoption rates of improved varieties and farming practices among small scale farmers Executive

More information

Teagasc s Role in Reducing Hunger and Under Nutrition in Underdeveloped Countries

Teagasc s Role in Reducing Hunger and Under Nutrition in Underdeveloped Countries Teagasc s Role in Reducing Hunger and Under Nutrition in Underdeveloped Countries Statement made by Professor Gerry Boyle, Director of Teagasc, to the Joint Committee on Foreign Affairs and Trade and Defence

More information

M&E Workstream report. Milestone reference number: and J.J. de Wolf. Submitted Resubmission date: 12 September 2013.

M&E Workstream report. Milestone reference number: and J.J. de Wolf. Submitted Resubmission date: 12 September 2013. M&E Workstream report Milestone reference number: 1.5.1 and 1.5.2 J.J. de Wolf Submitted 2011 Resubmission date: 12 September 2013 N2Africa Putting nitrogen fixation to work for smallholder in Africa M&E

More information

African Chicken Genetic Gains

African Chicken Genetic Gains African Chicken Genetic Gains ACGG Ethiopia Overview Solomon Abegaz, EIAR ACGG Ethiopia Second National Innovation Platform Meeting, Debre Zeit, Ethiopia, 22-23 March 2016 National program design The Ethiopian

More information

COMPLETION OF THE REPORT ON COCOA PRODUCTIVITY AND QUALITY IMPROVEMENT: A PARTICIPATORY APPROCH SUMMARY OF THE PROJECT COMPLETION REPORT (PCR)

COMPLETION OF THE REPORT ON COCOA PRODUCTIVITY AND QUALITY IMPROVEMENT: A PARTICIPATORY APPROCH SUMMARY OF THE PROJECT COMPLETION REPORT (PCR) EX/143/10 10 January 2011 Original: ENGLISH Distr: RESTRICTED Executive Committee One hundred and forty third meeting London, 22-25 March 2011 COMPLETION OF THE REPORT ON COCOA PRODUCTIVITY AND QUALITY

More information

WDCM Training Course for Microbiome Data Sharing

WDCM Training Course for Microbiome Data Sharing WDCM Training Course for Microbiome Data Sharing 15 October 31 October 2017 WDCM, Chinese Academy of Science, Institue of Microbiology Personal Information Participant: Ahmed Idris Hassen An Ethiopian

More information

Harvesting Nutrition Contest

Harvesting Nutrition Contest 2015 Harvesting Nutrition Contest WINNING PROJECT DESCRIPTIONS SECURENUTRITIONPLATFORM.ORG Harvesting Nutrition Award Profile» Most Scalable Approach N2Africa Putting Nitrogen Fixation to Work for Smallholder

More information

Building Sustainable Rice Data and Information System in Africa: A Multi-Actors Partnership Efforts

Building Sustainable Rice Data and Information System in Africa: A Multi-Actors Partnership Efforts Building Sustainable Rice Data and Information System in Africa: A Multi-Actors Partnership Efforts Aliou Diagne Program Leader & Impact Assessment Economist Policy, Innovation Systems and Impact Assessment

More information

Brief. Regional Soil Fertility Specialist (West Africa) Optimising Fertiliser Recommandations in Africa (OFRA)

Brief. Regional Soil Fertility Specialist (West Africa) Optimising Fertiliser Recommandations in Africa (OFRA) Brief Regional Soil Fertility Specialist (West Africa) Optimising Fertiliser Recommandations in Africa (OFRA) August 2013 2 CABI BACKGROUND The Optimising Fertilizer Recommendations in Africa (OFRA) aims

More information

Tropentag 2009 University of Hamburg, October 6-8, 2009

Tropentag 2009 University of Hamburg, October 6-8, 2009 Tropentag 2009 University of Hamburg, October 6-8, 2009 Conference on International Research on Food Security, Natural Resource Management and Rural Development The changing roles of international agricultural

More information

Achieving a forage revolution through improved varieties and seed systems

Achieving a forage revolution through improved varieties and seed systems Achieving a forage revolution through improved varieties and seed systems Chris Jones and Jean Hanson International Livestock Research Institute GLOBAL NUTRITION SYMPOSIUM 24 January 2018 Addis Ababa,

More information

Communiqué on the Regional Workshop on the Aflatoxin Challenge in West African States

Communiqué on the Regional Workshop on the Aflatoxin Challenge in West African States Communiqué on the Regional Workshop on the Aflatoxin Challenge in West African States Alisa Hotel, Accra, Ghana 18-20 November 2013 On 18-20 November 2013, approximately 40 experts from agriculture, health,

More information

The final level of our Results Management Framework measures how well we manage our own

The final level of our Results Management Framework measures how well we manage our own Level 4: How efficient AfDB is as an organisation in Ethiopia The final level of our Results Management Framework measures how well we manage our own organisation, using 14 indicators to assess our progress.

More information

The Nou Joint Forest Management Project

The Nou Joint Forest Management Project The Nou Joint Forest Management Project a model for conservation in partnership SOS Sahel Ethiopia European Union FARM-Africa Tanzania s Nou Joint Forest Management (JFM) Project has been running since

More information

Seed Systems Analysis (SSA)

Seed Systems Analysis (SSA) ISSD Technical Notes. Issue No. 2 Seed Systems Analysis (SSA) WHAT is seed systems analysis? The seed systems analysis (SSA) is a multi-stakeholders process oriented tool to understand the composition,

More information

N2Africa Podcaster no. 11

N2Africa Podcaster no. 11 Introduction We close the year with a number of good news items from N2Africa. As you will see there is growing confidence in our approach and ability to put nitrogen fixation to work for the African farmer.

More information

THE INTER-SESSIONAL PANEL OF THE UNITED NATIONS COMMISSION ON SCIENCE AND TECHNOLOGY FOR DEVELOPMENT December 2010 Geneva UGANDA CONTRIBUTION

THE INTER-SESSIONAL PANEL OF THE UNITED NATIONS COMMISSION ON SCIENCE AND TECHNOLOGY FOR DEVELOPMENT December 2010 Geneva UGANDA CONTRIBUTION THE INTER-SESSIONAL PANEL OF THE UNITED NATIONS COMMISSION ON SCIENCE AND TECHNOLOGY FOR DEVELOPMENT 15-17 December 2010 Geneva UGANDA CONTRIBUTION "Technologies to address challenges in the Agriculture

More information

Technology Solutions and Opportunities available for Abating the Aflatoxin Challenge

Technology Solutions and Opportunities available for Abating the Aflatoxin Challenge Regional Workshop on the Aflatoxin Challenges in Eastern and Southern Africa: Improving Health, Trade & Food Security through Regional Efforts to Mitigate Aflatoxin Contamination, Lilongwe, 11-13 March,

More information

AFRICAN SEED AND BIOTECHNOLOGY PROGRAMME TABLE OF CONTENTS

AFRICAN SEED AND BIOTECHNOLOGY PROGRAMME TABLE OF CONTENTS AFRICAN SEED AND BIOTECHNOLOGY PROGRAMME TABLE OF CONTENTS I BACKGROUND... 5 International Agreements and the Seed Sector Development... 5 Informal Seed System... 6 Formal Seed System... 6 Biotechnology

More information

20 TH MEETING OF COMSATS COORDINATING COUNCIL

20 TH MEETING OF COMSATS COORDINATING COUNCIL 20 TH MEETING OF COMSATS COORDINATING COUNCIL COUNCIL FOR SCIENTIFIC AND INDUSTRIAL RESEARCH (CSIR-GHANA) by Prof. Victor Agyeman Esq Director-General 14-15 May 2017 Presentation outline: 1. Introduction

More information

Agriculture Working Group

Agriculture Working Group Agriculture Working Group *Ayesha Hakeem, African Connections *Tola Sunmonu, Doreo Partners *Amadou Lamine Senghor, Crop Protection, Senegal *Tetteh Abraham *Richard Awuah *Sam Kanyarukuga, COMESA *Martha

More information

2.1 Specific objectives of the evaluation The specific evaluation objectives are:

2.1 Specific objectives of the evaluation The specific evaluation objectives are: TERMS OF REFERENCE FOR A CONSULTANCY TO CONDUCT END OF PROJECT EVALUATION FOR THE AGRICULTURAL TECHNOLOGY AND AGRIBUSINESS ADVISORY SERVICES (ATAAS) PROJECT 1.0 Background and context The Agricultural

More information

WEST AFRICA SEED PROJECT WASP MID-TERM EVALUATION

WEST AFRICA SEED PROJECT WASP MID-TERM EVALUATION WEST AFRICA SEED PROJECT WASP MID-TERM EVALUATION June 13, 2017 Outline Background Evaluation Purpose and Scope Findings Recommendations Conclusion Way Forward Challenges in WA Seed Sector Background Limited

More information

REVISED TERMS OF REFERENCE

REVISED TERMS OF REFERENCE REVISED TERMS OF REFERENCE Revised sections are highlighted in red Consultancy: Baseline study for the Enhancing crop yields and profitability in Kenya through biological plant protection project 1. Background

More information

PROJECT PREPARATION GRANT (PPG) PROJECT TYPE: Full-sized Project TYPE OF TRUST FUND: GEF Trust Fund

PROJECT PREPARATION GRANT (PPG) PROJECT TYPE: Full-sized Project TYPE OF TRUST FUND: GEF Trust Fund PROJECT PREPARATION GRANT (PPG) PROJECT TYPE: Full-sized Project TYPE OF TRUST FUND: GEF Trust Fund Submission date: 07/09/2012 Resubmission date: 11/15/2012 Resubmission date: 01/18/2013 GEF PROJECT ID:

More information

Japan s Support to Development and Dissemination of NERICA. Economic Cooperation Bureau Ministry of Foreign Affairs of Japan March 2006

Japan s Support to Development and Dissemination of NERICA. Economic Cooperation Bureau Ministry of Foreign Affairs of Japan March 2006 Japan s Support to Development and Dissemination of NERICA Economic Cooperation Bureau Ministry of Foreign Affairs of Japan March 2006 Japan s basic approach to agricultural and rural development in Africa

More information

ISPC Assessment of the Wheat Agri-Food System (WHEAT) CRP-II revised proposal ( )

ISPC Assessment of the Wheat Agri-Food System (WHEAT) CRP-II revised proposal ( ) 14 September 2016 ISPC Assessment of the Wheat Agri-Food System (WHEAT) CRP-II revised proposal (2017-2022) ISPC CRP RATING 1 : A- 1. Summary The CRP aims to increase the annual rate of yield increase

More information

This presentation. CCRP Communities of Practice (CoP) Sustainable Legume Intensification in CCRP.

This presentation. CCRP Communities of Practice (CoP) Sustainable Legume Intensification in CCRP. This presentation Sustainable Legume Intensification in CCRP CCRP overview Framework for grant making Legume priorities for 2014-18 Legume Lab complementarity Charlie Riches http://www.ccrp.org Plant Biology

More information

Innovative Farmer Advisory Services using ICTs. François STEPMAN Forum for Agricultural Research in Africa Ghana

Innovative Farmer Advisory Services using ICTs. François STEPMAN Forum for Agricultural Research in Africa Ghana Innovative Farmer Advisory Services using ICTs François STEPMAN Forum for Agricultural Research in Africa Ghana Motivation, problem area The past 10 years have seen remarkable progress in the use of information

More information

TRADE FARM AFRICA S APPROACH

TRADE FARM AFRICA S APPROACH TRADE FARM AFRICA S APPROACH CONTENTS Farm Africa s vision Preface What s the issue? Theory of change Farm Africa s approach Methodology How to use Farm Africa s approach papers FARM AFRICA S VISION FOR

More information

Farmers call the tune:

Farmers call the tune: Farmers call the tune: initial experiences with Local Innovation Support Funds Ann Waters-Bayer and others in PROLINNOVA International Support Team ETC EcoCulture www.prolinnova.net Seeking to enhance

More information

Disseminating Innovative Resources and Technologies to Smallholders (DIRTS)

Disseminating Innovative Resources and Technologies to Smallholders (DIRTS) Disseminating Innovative Resources and Technologies to Smallholders (DIRTS) Newsletter April June 2015 The DIRTS project is entering another exciting period as the 2015 agricultural season is about to

More information

Ranajit Bandyopadhyay IITA, Ibadan, Nigeria. Aflatoxins and Their Management

Ranajit Bandyopadhyay IITA, Ibadan, Nigeria. Aflatoxins and Their Management Ranajit Bandyopadhyay IITA, Ibadan, Nigeria Aflatoxins and Their Management P Outline Aflatoxin facts Impact of aflatoxins in people s lives Prevalence and exposure Aflatoxins and trade Aflatoxin management

More information

TERMS OF REFERENCE FOR THE FINAL EVALUATION OF HAKI MKONONI RIGHTS IN OUR HANDS

TERMS OF REFERENCE FOR THE FINAL EVALUATION OF HAKI MKONONI RIGHTS IN OUR HANDS TERMS OF REFERENCE FOR THE FINAL EVALUATION OF HAKI MKONONI RIGHTS IN OUR HANDS January 2017 Programme/project title /affiliate identification code Haki Mkononi Rights in our hands / R05168 PAFA35 Geographical

More information

Africa-Brazil Agricultural Innovation Marketplace

Africa-Brazil Agricultural Innovation Marketplace Africa-Brazil Agricultural Innovation Marketplace FINAL EVALUATION OF THE PROJECT ID: 200 Title: Introduction of Napier grass elite lines for screening for stunt resistance to provide feed for improved

More information

Co-Chairs Summary of the Fourth General Meeting of CARD. Kampala, Uganda, 8 9 November 2011

Co-Chairs Summary of the Fourth General Meeting of CARD. Kampala, Uganda, 8 9 November 2011 Co-Chairs Summary of the Fourth General Meeting of CARD Kampala, Uganda, 8 9 November 2011 The Fourth General Meeting of the Coalition for African Rice Development (CARD) convened in Kampala, Uganda on

More information

Type of Review: Annual Review

Type of Review: Annual Review Type of Review: Annual Review Project Title: WaterAid Programme Partnership Arrangement (PPA) Date started: 01 April 2012 Date review undertaken: 10 September 2013 Instructions to help complete this template:

More information

BACK TO OFFICE REPORT

BACK TO OFFICE REPORT BACK TO OFFICE REPORT Report on International course on: The Integration between Research, Extension and Applied Agriculture Sponsored by MASHAV (Israel s Agency for International Development Cooperation)

More information

POLICY BRIEF: Background Context

POLICY BRIEF: Background Context SUSTAINING GOVERNMENTS S PLANTING FOR FOOD AND JOBS (PFJ) INITIATIVE: KEY ISSUES FOR CONSIDERATION AFTER A YEAR OF IMPLEMNTATION 1.0 Background Context Agriculture has long provided a firm foothold for

More information

Government of Uganda, United Nations Development Programme (UNDP) And World Bank

Government of Uganda, United Nations Development Programme (UNDP) And World Bank Government of Uganda, United Nations Development Programme (UNDP) And World Bank Brief description Project title: The Poverty and Social Impact Analysis (PSIA) of the Proposed National Land Use Policy

More information

Responsibilities Key Performance Indicators Competencies Skills, Knowledge & Experience Required. Strategy and Signature Program Development

Responsibilities Key Performance Indicators Competencies Skills, Knowledge & Experience Required. Strategy and Signature Program Development VSO ETHIOPIA JOB DESCRIPTION Job title: Technical Advisor Livelihoods Responsible to: Head of Programs Direct reports: Program Officers Duty Station/Location: Addis Ababa Service duration: One year with

More information

CARD Coalition for African Rice Development

CARD Coalition for African Rice Development CARD Coalition for African Rice Development An Innovative Attempt for Agri. Dev t in Africa August 17, 2015 at JICA Tsukuba Center Takanori SATOYAMA General Coordinator CARD Secretariat Outline 1. Context

More information

Coalition for African Rice Development:CARD

Coalition for African Rice Development:CARD As of 21 st January 2009 JICA Coalition for African Rice Development:CARD 1. Background and Necessity of CARD Since the latter half of 1990s, rice demand in Sub-Saharan Africa (hereafter referred to as

More information

Trade-Related Assistance: What Do Recent Evaluations Tell Us?

Trade-Related Assistance: What Do Recent Evaluations Tell Us? 3-4 NOVEMBER 2008 CONFERENCE CENTRE, PARIS Background Document for Session III Trade-Related Assistance: What Do Recent Evaluations Tell Us? MAIN FINDINGS AND KEY RECOMMENDATIONS 1 Identify the most adequate

More information

Overview of CARD: Coalition for African Rice Development & NRDS: National Rice Development Strategy

Overview of CARD: Coalition for African Rice Development & NRDS: National Rice Development Strategy Overview of CARD: Coalition for African Rice Development & NRDS: National Rice Development Strategy May 14 th, 2018 at JICA Tsukuba Center Takanori SATOYAMA General Coordinator CARD Secretariat Outline

More information

Feed Africa Agriculture and Agroindustry

Feed Africa Agriculture and Agroindustry Feed Africa Agriculture and Agroindustry Target by 2025 Status Today Goals Goals, Status and Targets Become a net exporter Contribute to the end Eliminate hunger and of agricultural of extreme poverty

More information

Seed Intervention Landscape Analysis (SILA)

Seed Intervention Landscape Analysis (SILA) ISSD Technical Notes. Issue No. 4 Seed Intervention Landscape Analysis (SILA) WHAT is seed sector intervention landscape analysis? Seed intervention analysis (SILA) is the mapping tool for the projects

More information

Law-Growth Nexus - A Mapping of Labour Law and Micro and Small Enterprise (MSE) Development

Law-Growth Nexus - A Mapping of Labour Law and Micro and Small Enterprise (MSE) Development Law-Growth Nexus - A Mapping of Labour Law and Micro and Small Enterprise (MSE) Development Quick Facts Countries: Sub Saharan Africa: Burkina Faso, Cameroon, Ghana, Kenya, Mali, Mozambique, Namibia, Rwanda,

More information

Curriculum Vitae. I. Personal information. II. Education. III. Other trainings. CV_Nigist Haile

Curriculum Vitae. I. Personal information. II. Education. III. Other trainings. CV_Nigist Haile I. Personal information Curriculum Vitae Full name: Nigist Haile Abreha Sex: Female Nationality: Ethiopian Current Address: Ethiopian Agricultural Transformation Agency (ATA) M: +251 91 4745992 E: nhaileabreha@yahoo.com

More information

Presentation outline Water Operators partnerships-a case of three East African Water utilities. Benefits of adopting WSP approach

Presentation outline Water Operators partnerships-a case of three East African Water utilities. Benefits of adopting WSP approach Presentation outline Water Operators partnerships-a case of three East African Water utilities Jane Mumbi NAIROBI CITY WATER AND SEWERAGE COMPANY, KENYA Introduction Definition of a WOP Description of

More information

2. Relevant operational framework(s)

2. Relevant operational framework(s) Inputs provided by: International Center of Insect Physiology and Ecology (ICIPE), Nairobi, Kenya 1. General description of mandates and objective(s) of your organization / associated network with institutional

More information

Implementation Status & Results Africa West Africa Agricultural Productivity Program (WAAPP) (P094084)

Implementation Status & Results Africa West Africa Agricultural Productivity Program (WAAPP) (P094084) losure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized The World Bank Implementation Status & Results Africa West Africa Agricultural Productivity Program

More information

6 Rice Varietal Release

6 Rice Varietal Release 6 Rice Varietal Release Systems in Africa Kayode Abiola Sanni, 1 * Ali A. Touré, 1 Aliou Diagne, 1 Fatimata Bachabi, 1 Rosemary Murori, 2 Rakesh Kumar Singh 2 and Moussa Sié 1 1 Africa Rice Center (AfricaRice),

More information

MAINSTREAMING GENDER IN ENERGY SECTOR PRACTICE AND POLICY

MAINSTREAMING GENDER IN ENERGY SECTOR PRACTICE AND POLICY MAINSTREAMING GENDER IN ENERGY SECTOR PRACTICE AND POLICY LESSONS FROM THE ENERGIA INTERNATIONAL NETWORK Report prepared by Joy Clancy 1, Nthabi Mohlakoana 2 and Yacine Diagne Gueye 3 Together with Lydia

More information

LINKING FARMERS TO MARKETS IN AFRICA

LINKING FARMERS TO MARKETS IN AFRICA ANNOUNCES AN INTERNATIONAL TRAINING PROGRAM ON LINKING FARMERS TO MARKETS IN AFRICA NAIROBI, KENYA JULY 20-24, 2015 REGISTRATION FEES: Early Bird Registration and Payment by May 20 Regular Registration

More information

Terms of Reference. Final Evaluation ALERT Project

Terms of Reference. Final Evaluation ALERT Project Terms of Reference Final Evaluation ALERT Project The ALERT consortium has designed technology for improving the way humanitarian agencies prepare for and respond to disasters. ALERT is a three-year initiative

More information

Terms of Reference (ToR)

Terms of Reference (ToR) Terms of Reference (ToR) Final Evaluation Project/Programme Title: Country: Coffee Alliances for Ethiopia (CAFÈ) Ethiopia Project/Programme Number: 2550-14/2014 Name of Partner Organisation: Austrian Development

More information

Climate Smart Maize Hybrids for Better Agriculture in Africa

Climate Smart Maize Hybrids for Better Agriculture in Africa Climate Smart Maize Hybrids for Better Agriculture in Africa Gospel Omanya, Ph.D., Dip. (Mgt) African Seed Trade Association Congress Laico Regency, Nairobi, Kenya 3 th March, 2015 Overview AATF - Who

More information

Case Study in using the DCED Standard Seeds and Markets Project (SAMP) 20 th April 2012

Case Study in using the DCED Standard Seeds and Markets Project (SAMP) 20 th April 2012 Case Study in using the DCED Standard Seeds and Markets Project (SAMP) 20 th April 2012 This case study shows how Seeds and Markets Project (SAMP) is working to integrate the different elements of the

More information

About AGRA. The Scaling Seed &Technologies Partnership of the Alliance for a Green Revolution in Africa. PASS Results. PASS Model

About AGRA. The Scaling Seed &Technologies Partnership of the Alliance for a Green Revolution in Africa. PASS Results. PASS Model The Scaling Seed &Technologies Partnership of the Alliance for a Green Revolution in Africa Itai Makanda Presented at the Legume Innovation Lab 2014 Global Researchers Meeting May 12-16, 2014, Radisson

More information

Training on Project Cycle Management for Researchers Ethiopian Academy of Sciences May 2016, Ghion Hotel, Addis Ababa

Training on Project Cycle Management for Researchers Ethiopian Academy of Sciences May 2016, Ghion Hotel, Addis Ababa Training on Project Cycle Management for Researchers Ethiopian Academy of Sciences 25-27 May 2016, Ghion Hotel, Addis Ababa To increase participants understanding of the concepts used in designing M&E

More information

Soya Ni Pesa. Steady progress in building the soybean sector in Tanzania. Meet Mr. Nyigu Melkiard

Soya Ni Pesa. Steady progress in building the soybean sector in Tanzania. Meet Mr. Nyigu Melkiard ISSUE 3, APRIL 2015 Soya Ni Pesa Steady progress in building the soybean sector in Tanzania Entering the third year of Soya ni Pesa (SnP), CRS sponsored a mid-term evaluation which affirmed that the project

More information

The Partnership for Agricultural Water for Africa

The Partnership for Agricultural Water for Africa The Partnership for Agricultural Water for Africa TABLE OF CONTENTS The Partnership SDC Project Support to sustainable agricultural water management and the pre- and post-caadp compact process in Burkina

More information

Support implementing partners to design effective Monitoring and Evaluation Plans and tools, which involve and empower the community.

Support implementing partners to design effective Monitoring and Evaluation Plans and tools, which involve and empower the community. SomRep DME Manager Location: [Africa] [Somalia] Town/City: Doolow Category: Programme Effectiveness Job Type: Fixed term, Full-time PURPOSE OF POSITION: To develop, lead, and manage joint Monitoring &

More information

Making the Connection: Value Chains for Transforming Smallholder Agriculture

Making the Connection: Value Chains for Transforming Smallholder Agriculture Making the Connection: Value Chains for Transforming Smallholder Agriculture An International Conference Concept note April 2012 Background The ways in which developing country agricultural production

More information

Ensuring food security by promoting uptake and scaling up the application of agricultural lime to combat soil acidity in Kenya

Ensuring food security by promoting uptake and scaling up the application of agricultural lime to combat soil acidity in Kenya Ensuring food security by promoting uptake and scaling up the application of agricultural lime to combat soil acidity in Kenya S.K. Kimani, P.M. Njeru, J.K. Lekasi and J.M. Miriti Abstract Kenya Agricultural

More information

Horticulture Collaborative Research Support Program (Horticulture CRSP)

Horticulture Collaborative Research Support Program (Horticulture CRSP) Horticulture Collaborative Research Support Program (Horticulture CRSP) Request for Trellis Fund Project Proposals Date of Release: April 06, 2012 Applications Due: June 06, 2012 Funding decisions: July

More information

Stakeholder Consultation Workshop Report: Ethiopia, Ghana and Tanzania Identifying and prioritizing constraints and opportunities

Stakeholder Consultation Workshop Report: Ethiopia, Ghana and Tanzania Identifying and prioritizing constraints and opportunities Innovation Lab for Small Scale Irrigation (ILSSI) Stakeholder Consultation Workshop Report: Ethiopia, Ghana and Tanzania - 2016 Identifying and prioritizing constraints and opportunities Contents 1 Introduction

More information

World Bank Africa Gender Innovation Lab (GIL) Call for Expressions of Interest: About the World Bank Africa Region Gender Innovation Lab (GIL)

World Bank Africa Gender Innovation Lab (GIL) Call for Expressions of Interest: About the World Bank Africa Region Gender Innovation Lab (GIL) World Bank Africa Gender Innovation Lab (GIL) Call for Expressions of Interest: Seeking NGOs, governments, donors, and private sector firms with interventions designed to improve women s land tenure security

More information

INDEPENDENT ASSURANCE STATEMENT

INDEPENDENT ASSURANCE STATEMENT INDEPENDENT ASSURANCE STATEMENT Assurance Scope, Objectives and Methodology Objectives Natural Capital Ltd (referred to as Natural Capital throughout the rest of this statement) was commissioned by Fujitsu

More information

Job pack: Monitoring Evaluation and Learning Manager

Job pack: Monitoring Evaluation and Learning Manager Job pack: Monitoring Evaluation and Learning Manager Country Nigeria Employer VSO Nigeria Report Direct report to Head of Programs Job purpose The MEL Manager will provide programme research, monitoring,

More information

President s Report on a Proposed Grant under the Global/Regional Grants Window to WorldFish for Advancing Climate-smart Aquaculture Technologies

President s Report on a Proposed Grant under the Global/Regional Grants Window to WorldFish for Advancing Climate-smart Aquaculture Technologies Document: EB 2018/LOT/G.20 Date: 22 November 2018 Distribution: Public Original: English E President s Report on a Proposed Grant under the Global/Regional Grants Window to WorldFish for Advancing Climate-smart

More information

GLDC PIM information

GLDC PIM information GLDC PIM information Contents PIM A TABLE: GLDC Contributions to the SRF targets in 2017-2022... 2 PIM A TABLE: GLDC Contributions to the SRF targets in 2017-2022... 2 PIM TABLE B - Flagship 1: Priority

More information