Ref: Response to request for review Hubei Yuquanhe 25.2MW Hydropower Project with the Reference Number 2188

Size: px
Start display at page:

Download "Ref: Response to request for review Hubei Yuquanhe 25.2MW Hydropower Project with the Reference Number 2188"

Transcription

1 Trading Emissions PLC Third Floor, Exchange House, 54/62 Athol Street, Douglas, Isle of Man, IM1 1JD, British Isles t: +44 (0) f: +44 (0) w: Ref: Response to request for review Hubei Yuquanhe 25.2MW Hydropower Project with the Reference Number 2188 December 30, 2008 UNFCCC Secretariat Martin-Luther-King-Strasse 8 D Bonn Germany Attention: CDM Executive Board Dear Sir or Madam, We were informed that our project Hubei Yuquanhe 25.2MW Hydropower Project (reference number 2188) was requested for review by CDM Executive Board. As required by the Executive Board and on behalf of the project participants, we would like to answer the questions and clarify the issues raised in the requests for review as follows: Question 1: The DOE should clarify how it has validated the sensitivity analysis, in particular the probability of variations in tariff and electricity generation. Response by PP According to the sensitivity analysis guidance set out in Annex 45, EB41, we clarify how the sensitivity analysis was conducted for the project and how assessment of the probability of variations was made: Only variables that constitute more than 20% of either total project costs or total project revenues should be subjected to reasonable variation. Based on this guidance, we selected four parameters to conduct sensitivity analysis: total investment, electricity tariff and operation hours.

2 The total investment is the fundanmental cost of the project. The tariff and operation hours together will determine the total project revenues. So the chosen parameters adopted in sensitivity analysis is in accordance with EB guidance and thus appropriate. The range of variations shall be reasonable in the project context and past trends may be guide to determine the reasonable range. The PPs used two different approaches to the sensitivity analysis: The selected parameters were adjusted within the range of positive 10% and negative 10%. The result is provided in the table below: -10% -5% 0% 5% 10% Total Investment 7.27% 6.71% 6.19% 5.72% 5.27% Tariff 5.18% 5.69% 6.19% 6.69% 7.17% Operation Hours 5.18% 5.69% 6.19% 6.69% 7.17% The project IRR remained below the benchmark 8% in each instance. To further confirm the additionality of the project, the PPs also identified the scenarios under which the project IRR will reach the benchmark 8% as follows: When total investment 27.34% below the assumption All the data adopted for project costs in calculation of IRR are from the project FSR completed by Hubei Hydrology and Hydropower Science Institute Hubei Jinlang Survey and Design Institute in December Four months later the project started construction. Given this short period of time, it has been concluded that material changes on project costs are unlikely and the input estimations in the FSR are still valid at the time of project start date. As the total investment is mostly made during the first two years of construction, and given the high rate of inflation in the past three years in China, it cannot be expected a decrease on estimated assumption by 27.34%. When income from electricity sales 17.49% higher than the assumption This scenario means either increasing the tariff or operation hours of the project by 17.49%, the project IRR can meet the benchmark. Such an increase in operating hours and tariff are not considered reasonable for the following reasons: Probability of tariff variation The tariff adopted in the investment analysis of the PDD was from the Electricity On-grid Commitment Letter issued by Shennongjia Linqu Electric Power Company in January In the Letter the tariff for Yuquanhe was indicated as RMB 0.213yuan/kwh including VAT. This - 2 -

3 can be now further confirmed by the signed Power Purchase Agreement between the project owner and Shennongjia Linqu Electric Power Company dated on December 2, From the project construction in 2006 to date, the tariff remains the same. It shall be noted that at the time of investment decision by the project owner, probability of a large tariff variation in the future was difficult to predict given the Chinese tariff setting process. An increase in tariff is entirely a decision by the Government weighing up various economic and social factors such as Consumer Price Index(CPI), inflation, fuel costs and power needs. 1 After 2006, since the CPI is soaring up in China, the government has decided to strengthen its administrative execution on price. In early 2008, it was confirmed by the government that to control the rapid CPI increase, the current tariff shall be maintained. 2 Although tariff did not increase, CPI will impact O&M and capital costs for the project. In addition, the tariff increase mechanism in China is especially designed for the thermal power plants whose power generation requires fossil fuels and the pre-condition of any increase is the increase on production costs. However, as hydropower plants require natural resources for power generation and there will be small fluctuation on the water resource charge, it is very unlikey to expect big variation on tariff offered to hydropower projects. Probabilty of electricity generation variation The electricity generation of the project is determined by the operation hours. The annual net electricity delivered to the grid adopted in the PDD was calculated on the basis of annual operation hour of 4450 provided in the FSR. This annual operation hour was calculated from hydrographical data covering 25 years from 1973 to Therefore it is not possible in terms of water resources to have the annual operation hour of the project realize an average annual increase of 17.49%. This increase also cannot be expected in terms of power generation as the estimated power generation was calculated on the basis of 100% reliability operation level throughout the year, which is unlikely to be realized

4 To conclude, PPs have identified the scenarios carefully, under which the project might be financially feasible. However the PPs do not believe in the long term the project IRR can reach the industry benchmark within the reasonable possible variations given the past experience and future trends in China, in particular in tariff and electricity generation. Question 2: The DOE should clarify how it has validated the common practice analysis, in particular the selection of similar activities considering that the total capacity of the project activity is 25.2MW and comparison to hydropower projects in range between 15-35MW (corresponds to approximately +/-50%) would have been more appropriate. Response by PP According to the Additionality Tool, the common practice shall provide an analysis of any other activities that are similar to the project. Projects are considered similar if they are in the same country/region and/or rely on a broadly similar technology, are of a similar scale, and take place in a comparable environment with respect to regulatory framework, investment climate, access to technology, access to financing, etc. Moreover, other CDM project actitivities are not to be included in this analysis. Based on this guidance, we provide further clarification on projects identified in the common practice of the PDD is as follows: Limiting to hydropower projects in Hubei province Limiting projects to the province level is widely adopted when identifying similar projects in terms of location as it is more likely those projects have been taken place in a comparable environment in terms of regulatory framework, investment climate, access to technology, access to financing, etc. Limiting to projects operational or under construction since 2000 To choose projects operational or under construction since 2000 is conservative as usually 2002 is the year that was adopted for common practice in China because of similar regulatory framework, investment climate and access to financing. The power industry in China undertook a significant policy reform in , under which the investment environment and tariff setting mechanism were changed. On 10 th February 2002 the State Council issued the Notice on Issuing Electric Power Sector Reform Programme (Guofa [2002] No.5) and the monopoly of the electricity investment was broken down by separating electric power plants from electric power grids and netting by price-bidding. Diversification of investment body was realized, which brought the private enterprises and private funds investment into power industry. For this change in China s power industry, hydropower projects in Hubei province under construction after February 10, 2002 were usually selected as similar projects for common practice in the registered PDDs. The project PDD was 3 Please see Electric Power Reform, 2003 Yearbook of China Electric Power, page

5 conducted in a conservative manner to take the year consideration starting from Limiting to projects with installed capacity under 50MW and not applying for CDM The small hydropower project in China was set at an installed capacity between 50MW and 0.5MW by the Government 4. This standard was further confirmed by Standard for Classification and Flood Control of Water Resources and Hydroelectric Project (SL ) issued by the Ministry of Water Resources of the People s Republic of China and the Classification & Design Safety Standard of Hydropower Projects (DL ) issued by the State Economic and Trade Commission of People s Republic of China. Therefore projects below 50MW are deemed to be small scale hydropower projects in China. PPs therefore considered projects under 50MW as the similar projects to the project, which is over the range between 15MW and 35MW and therefore conservative. It shall be noted that projects listed in the table of the PDD are all projects other than those applying for CDM we can obtain from the public available hydropower projects information in Hunbei province in China Hydro Statistic Yearbooks. This is in line with EB guidance on common practice in Additionality Tool version 05.2, which states that if necessary data/information of some similar projects are not accessible for PPs to conduct the analysis, such projects can be excluded from this analysis. Question 3: The DOE should clarify how it has validated that real action were taken to secure CDM status for the project in parallel with its implementation in line with EB41, Annex 46, para.5(b). Response by PP The reference of serious CDM consideration and its development has been provided in the PDD. In the below table we have included several events and milestones in terms of CDM development and project implementation to demonstrate that besides early CDM consideration before the start of the project activity, the project entity has continued to take real and concrete actions parallel with the project implementation towards registration as a CDM project. The key milestones in the development of the project are listed below: Date April 2005 Milestone EIA Approval issued by Hubei Province Environmental Protection Bureau 4 Please see Almanac of China s Water Power - 5 -

6 December 2005 FSR Completion 20 January 2006 FSR Approval by Hubei Development and Reform Commission 25 January 2006 Tariff Letter from Shennongjia Linqu Electric Power Company 10 February 2006 Board Meeting Resolution to apply the project for CDM 17 April 2006 Bank Loan Commitment Letter 26 April 2006 Equipment Supply Agreement Execution Project Start Date 15 May 2006 Project Construction Command June 2006 CDM Consulting Agreement (with individual) June 2006 Start construction of water diversion system September 2006 CDM Exclusive Consultancy Agreement (with company) October 2006 Start construction of dam October 2006 NDA signed between the Buyer and the project owner November 2006 Start construction of power house April 2007 Termsheet Signed with the CER buyer 17 August 2007 Project was approved at NDRC meeting and published at its website 5 20 August 2007 Validation Agreement with DOE October 2007 On-site valiation and PDD for GSP 6 November 2007 Host Nation Approval (paper document) December 2007 Emission Reduction Purchase Agreement Execution 15 July 2008 Draft Validation Report In line with EB41, Annex 46, para.5(b), we provided the following explanation: Continuing and real actions were taken to secure CDM status in parallel with its implementation Since the board meeting resolution to apply the project for CDM, continuing and real actions have been made to secure the CDM status for the project along with its implementation. The CDM Consulting Agreement was signed in June 2006 with an individual, two months after the project start date. In September 2006 the CDM Exclusive Consulting Agreement was reached between this individual s newly established company and the project owner. One month later NDA was signed between the CER Buyer and the project owner. Since the execution of NDA, the project owner and the CER Buyer have been in negotiation with the termsheet for the project, which was finally agreed by parties in April After the confirmation of the Buyer, the PDD work was started right away

7 In August 2007 the project was approved at China NDRC meeting and the validation agreement was signed with the DOE. In October PDD was published at UNFCCC in the following month along with the on-site visit of the project. The following month Host Nation Approval in paper was obtained. In December 2007 the final binding Emission Reduction Purchase Agreement ( ERPA ) was signed between the CER Buyer and the project owner. It can be seen clearly from above that concrete steps were taken for the project development towards registration as CDM, which is in line with EB41, Annex 46, para.5(b). In addition, the PP s believe it is reasonable that commericial negotiation with the CER Buyer delayed the project PDD development work. Market practice in China is typically that the Buyer will pay all the upfront fees such as consultancy, DOE fees etc.and so usually the consultant will not start work until a buyer for the project is secured. That s why PDD development was not started immediately after the signing of consulting agreement. In addition the host nation approval process in China typically requires a buyer to be in place as the letter of approval includes an approval to transfer the CERs to a named Annex 1 participant. Therefore securing an Annex I project participant before application for host nation approval is common practice but sometimes causes delay between project start date and CDM application. From the timeline it can be seen that the project owner worked continuously and steadily towards submission of the project for registration since the start date.. Progress had been sometimes slower than anticipated but at the time the investment decision was made the owner did not foresee the length of time it takes to register a project under the CDM. Despite the difficulties described above, the project participants remained determined in their intention to register the project activity for CDM as this had remained an essential precondition making the project actitivy financially attractive. Yours faithfully, Philip Scales Director and Company Secretary - 7 -

Your reference/letter of Our reference/name Tel. extension/ Fax extension Date/Document Page.

Your reference/letter of Our reference/name Tel. extension/ Fax extension Date/Document Page. TÜV SÜD Industrie Service GmbH 80684 Munich Germany DAP-PL-2885.99 DAP-IS-2886.00 DAP-PL-3089.00 DAP-PL-2722 DAP-IS-3516.01 DPT-ZE-3510.02 ZLS-ZE-219/99 ZLS-ZE-246/99 Your reference/letter of Our reference/name

More information

Your reference/letter of Our reference/name Tel. extension/ Fax extension Date/Document Page

Your reference/letter of Our reference/name Tel. extension/ Fax extension Date/Document Page TÜV SÜD Industrie Service GmbH 80686 Munich Germany DAP-PL-2885.99 DAP-IS-2886.00 DAP-PL-3089.00 DAP-PL-2722 DAP-IS-3516.01 DPT-ZE-3510.02 ZLS-ZE-219/99 ZLS-ZE-246/99 Your reference/letter of Our reference/name

More information

CLEAN DEVELOPMENT MECHANISM PROJECT DESIGN DOCUMENT FORM (CDM-PDD) Version 03 - in effect as of: 28 July 2006 CONTENTS

CLEAN DEVELOPMENT MECHANISM PROJECT DESIGN DOCUMENT FORM (CDM-PDD) Version 03 - in effect as of: 28 July 2006 CONTENTS page 1 CLEAN DEVELOPMENT MECHANISM PROJECT DESIGN DOCUMENT FORM (CDM-PDD) Version 03 - in effect as of: 28 July 2006 CONTENTS A. General description of project activity B. Application of a baseline and

More information

Your Our reference/name Tel. Fax extension Date/Document Page

Your Our reference/name Tel. Fax extension Date/Document Page TÜV SÜD Industrie Service GmbH 80684 Munich Germany DAP-PL-2885.99 DAP-IS-2886.00 DAP-PL-3089.00 DAP-PL-2722 DAP-IS-3516.01 DPT-ZE-3510.02 ZLS-ZE-219/99 ZLS-ZE-246/99 Your Our reference/name Tel. Fax extension

More information

Your reference/letter of Our reference/name Tel. extension/ Fax extension Date/Document Page.

Your reference/letter of Our reference/name Tel. extension/ Fax extension Date/Document Page. TÜV SÜD Industrie Service GmbH 80684 Munich Germany DAP-PL-2885.99 DAP-IS-2886.00 DAP-PL-3089.00 DAP-PL-2722 DAP-IS-3516.01 DPT-ZE-3510.02 ZLS-ZE-219/99 ZLS-ZE-246/99 Your reference/letter of Our reference/name

More information

Mr. Rajesh Kumar Sethi Chair, CDM Executive Board UNFCCC Secretariat 16 th December 2008

Mr. Rajesh Kumar Sethi Chair, CDM Executive Board UNFCCC Secretariat 16 th December 2008 Mr. Rajesh Kumar Sethi Chair, CDM Executive Board UNFCCC Secretariat CDMinfo@unfccc.int 16 th December 2008 Dear Mr. R. K. Sethi, Re: Request for review for request for registration of Ceran's 14 de Julho

More information

Your reference/letter of Our reference/name Tel. extension/ Fax extension Date/Document Page

Your reference/letter of Our reference/name Tel. extension/ Fax extension Date/Document Page TÜV SÜD Industrie Service GmbH 80684 Munich Germany DAP-PL-2885.99 DAP-IS-2886.00 DAP-PL-3089.00 DAP-PL-2722 DAP-IS-3516.01 DPT-ZE-3510.02 ZLS-ZE-219/99 ZLS-ZE-246/99 Your reference/letter of Our reference/name

More information

VALIDATION REPORT. Liaoning Changtu Quantou Wind Power Project in China. REPORT NO REVISION NO. 03 Deleted: 2

VALIDATION REPORT. Liaoning Changtu Quantou Wind Power Project in China. REPORT NO REVISION NO. 03 Deleted: 2 Liaoning Changtu Quantou Wind Power Project in China REPORT NO. 2007-1246 REVISION NO. 03 Deleted: 2 Date of first issue: Project No.: 2007-08-16 63602308 Approved by: Michael Lehmann, Technical Director

More information

Modalities of Communication Form

Modalities of Communication Form F-CDM-MOC Modalities of Communication Form This form is to be used by project participants in order to submit the statement of Modalities of Communication. Date of submission: day/month/year SECTION 1:

More information

Appendix 1 Interview Questions for CDM-Related Officials

Appendix 1 Interview Questions for CDM-Related Officials Appendix 1 Interview Questions for CDM-Related Officials 1. Would you please let me know the current situation of the development of CDM projects in China? 2. What do you think is the most important factor

More information

Subject: Answer to Request for review Saldanha Small Hydroelectric Project (1526)

Subject: Answer to Request for review Saldanha Small Hydroelectric Project (1526) Members of the CDM Executive Board UNFCCC Secretariat Martin-Luther-King-Strasse 8 D-53153 Bonn Germany 30 October 2008 1st Floor Park Central 40/41 Park End Street Oxford OX1 1JD UK Tel +44 (0)1865 202

More information

Response to requests for review Aços Villares Natural gas fuel switch project (0474)

Response to requests for review Aços Villares Natural gas fuel switch project (0474) UNFCCC Secretariat Martin-Luther-King-Strasse 8 D-53153 Bonn Germany Att: CDM Executive Board Your ref.: Our ref.: Date: CDM Ref 0474 MLEH/SUHA 11 September 2006 Response to requests for review Aços Villares

More information

CLEAN DEVELOPMENT MECHANISM PROJECT DESIGN DOCUMENT FORM (CDM-PDD) Version 03 - in effect as of: 28 July 2006 CONTENTS

CLEAN DEVELOPMENT MECHANISM PROJECT DESIGN DOCUMENT FORM (CDM-PDD) Version 03 - in effect as of: 28 July 2006 CONTENTS page 1 CLEAN DEVELOPMENT MECHANISM PROJECT DESIGN DOCUMENT FORM (CDM-PDD) Version 03 - in effect as of: 28 July 2006 CONTENTS A. General description of project activity B. Application of a baseline and

More information

CLEAN DEVELOPMENT MECHANISM PROJECT DESIGN DOCUMENT FORM (CDM-PDD) Version 03 - in effect as of: 28 July 2006 CONTENTS

CLEAN DEVELOPMENT MECHANISM PROJECT DESIGN DOCUMENT FORM (CDM-PDD) Version 03 - in effect as of: 28 July 2006 CONTENTS page 1 CLEAN DEVELOPMENT MECHANISM PROJECT DESIGN DOCUMENT FORM (CDM-PDD) Version 03 - in effect as of: 28 July 2006 CONTENTS A. General description of project activity B. Application of a baseline and

More information

Modalities of Communication Form

Modalities of Communication Form F-CDM-MOC Modalities of Communication Form This form is to be used by project participants in order to submit the statement of Modalities of Communication. Date of submission: day/month/year SECTION 1:

More information

Validation Report. Gansu Jieyuan Wind Power Co., Ltd. 2008, August 12

Validation Report. Gansu Jieyuan Wind Power Co., Ltd. 2008, August 12 Validation Report Gansu Jieyuan Wind Power Co., Ltd VALIDATION OF THE CDM-PROJECT: GANSU YUMEN SANSHILIJINGZI WIND POWER PROJECT REPORT NO. 1159769 2008, August 12 TÜV SÜD Industrie Service GmbH Carbon

More information

Validation Report VALIDATION OF THE CDM-PROJECT: SHABA 30MW HYDRO POWER PROJECT IN GUIZ- HOU PROVINCE CHINA REPORT NO

Validation Report VALIDATION OF THE CDM-PROJECT: SHABA 30MW HYDRO POWER PROJECT IN GUIZ- HOU PROVINCE CHINA REPORT NO Validation Report 1000842 VALIDATION OF THE CDM-PROJECT: SHABA 30MW HYDRO POWER PROJECT IN GUIZ- HOU PROVINCE CHINA REPORT NO. 1000842 2008, April 21 TÜV SÜD Industrie Service GmbH Carbon Management Service

More information

Description of the Bundle and the subbundles:

Description of the Bundle and the subbundles: CDM Executive Board Version 2, page 1 CLEAN DEVELOPMENT MECHANISM FORM FOR SUBMISSION OF BUNDLED SMALL SCALE PROJECT ACTIVITIES (SSC-CDM-BUNDLE) SECTION A. General description of the Bundle A.1. Title

More information

Your reference/letter of Our reference/name Tel. extension/ Fax extension Date/Document Page

Your reference/letter of Our reference/name Tel. extension/ Fax extension Date/Document Page TÜV SÜD Industrie Service GmbH Westendstrasse 199 80686 Munich Germany CDM Team DAP-PL-2885.99 DAP-IS-2886.00 DAP-PL-3089.00 DAP-PL-2722 DAP-IS-3516.01 DPT-ZE-3510.02 ZLS-ZE-219/99 ZLS-ZE-246/99 Your reference/letter

More information

.CLEAN DEVELOPMENT MECHANISM PROJECT DESIGN DOCUMENT FORM (CDM-PDD) Version 03 - in effect as of: 28 July 2006 CONTENTS

.CLEAN DEVELOPMENT MECHANISM PROJECT DESIGN DOCUMENT FORM (CDM-PDD) Version 03 - in effect as of: 28 July 2006 CONTENTS page 1.CLEAN DEVELOPMENT MECHANISM PROJECT DESIGN DOCUMENT FORM (CDM-PDD) Version 03 - in effect as of: 28 July 2006 CONTENTS A. General description of project activity B. Application of a baseline and

More information

Post Registration Changes How to Address? Sustainable Development Mechanisms, UNFCCC secretariat

Post Registration Changes How to Address? Sustainable Development Mechanisms, UNFCCC secretariat Post Registration Changes How to Address? Sustainable Development Mechanisms, UNFCCC secretariat Procedures available for Post registration changes Four (4) procedures have been developed to facilitate

More information

Post Registration Changes How to Address? Nitin Arora Sustainable Development Mechanisms, UNFCCC secretariat

Post Registration Changes How to Address? Nitin Arora Sustainable Development Mechanisms, UNFCCC secretariat Post Registration Changes How to Address? Nitin Arora Sustainable Development Mechanisms, UNFCCC secretariat Procedures available for Post registration changes. Four (4) procedures have been developed

More information

VALIDATION REPORT SAIHANBA EAST MW WINDFARM PROJECT IN CHINA REPORT NO REVISION NO. 01 DET NORSKE VERITAS

VALIDATION REPORT SAIHANBA EAST MW WINDFARM PROJECT IN CHINA REPORT NO REVISION NO. 01 DET NORSKE VERITAS VALIDATION REPORT SAIHANBA EAST 45.05 MW WINDFARM PROJECT IN CHINA REPORT NO. 2006-1309 REVISION NO. 01 DET NORSKE VERITAS DET NORSKE VERITAS VALIDATION REPORT Date of first issue: Project No.: 2006-05-26

More information

The Austrian JI/CDM Programme

The Austrian JI/CDM Programme Martin Gauss Kommunalkredit Public Consulting GmbH The Austrian JI/CDM Programme UNFCCC/UNIDO Training of trainers workshop on preparing technology transfer projects for financing 1 October 2008 Austrian

More information

Landfill Gas (LFG) Emission Reduction Purchase Agreements (ERPAs) in China. Case Study: Tianjin

Landfill Gas (LFG) Emission Reduction Purchase Agreements (ERPAs) in China. Case Study: Tianjin Landfill Gas (LFG) Emission Reduction Purchase Agreements (ERPAs) in China Case Study: Tianjin Methane Greenhouse Gases (GHGs) 23% GHGs from non-co 2 emissions Human related activities 15% of GHGs from

More information

Camco China Camco 国际碳资产信息咨询 ( 北京 ) 有限公司中国北京市朝阳区东三环北路 3 号幸福大厦 A 座 14 层,100027

Camco China Camco 国际碳资产信息咨询 ( 北京 ) 有限公司中国北京市朝阳区东三环北路 3 号幸福大厦 A 座 14 层,100027 Clarifications on issues associated with validation requirements for project activity Request for review Shanxi Taigang Stainless Steel Co., Ltd. Waste Saturated Steam Recovery and Generation Project (1711)

More information

1. The PP/DOE are requested to justify prior consideration of the CDM following EB 41 guidance, Annex 46, paragraph 5 and 6.

1. The PP/DOE are requested to justify prior consideration of the CDM following EB 41 guidance, Annex 46, paragraph 5 and 6. Response to Request for Review for Abatement of Green House Gas (GHG) emissions through biomass residue based cogeneration at Claris Lifesciences Limited (UNFCCC Ref. No.: 00001852) 1. The PP/DOE are requested

More information

Validation Report. Datang Zhangzhou Wind Power Co., Ltd. VALIDATION OF THE CDM-PROJECT: Fujian Zhangpu Liuao 45MW Wind Power Project.

Validation Report. Datang Zhangzhou Wind Power Co., Ltd. VALIDATION OF THE CDM-PROJECT: Fujian Zhangpu Liuao 45MW Wind Power Project. Validation Report Datang Zhangzhou Wind Power Co., Ltd VALIDATION OF THE CDM-PROJECT: Fujian Zhangpu Liuao 45MW Wind Power Project REPORT NO. 948571 2007, August 30 TÜV SÜD Industrie Service GmbH Carbon

More information

Revision to the methodological tool. Combined tool to identify the baseline scenario and demonstrate additionality (Version 02.

Revision to the methodological tool. Combined tool to identify the baseline scenario and demonstrate additionality (Version 02. UFCCC/CCUCC demonstrate additionality (Version 02.1) Revision to the methodological tool demonstrate additionality (Version 02.1) 1 I. SCOPE AD APPLICABILIT This tool provides for a step-wise approach

More information

GUIDELINES FOR COMPLETING THE FORM FOR SUBMISSION OF BUNDLED SMALL-SCALE CDM PROJECT ACTIVITIES (F-CDM-SSC-BUNDLE) (Version 01) CONTENTS

GUIDELINES FOR COMPLETING THE FORM FOR SUBMISSION OF BUNDLED SMALL-SCALE CDM PROJECT ACTIVITIES (F-CDM-SSC-BUNDLE) (Version 01) CONTENTS GUIDELINES FOR COMPLETING THE FORM FOR SUBMISSION OF BUNDLED SMALL-SCALE CDM PROJECT ACTIVITIES (F-CDM-SSC-BUNDLE) (Version 01) CONTENTS I. Information note on bundling of Small-Scale project activities

More information

Subject: Call for public comments on Clean Development Mechanism Validation and Verification Manual (CDM-VVM)

Subject: Call for public comments on Clean Development Mechanism Validation and Verification Manual (CDM-VVM) CDM Executive Board UNFCCC Secretariat Martin Luther King Strasse 8 P.O.Box 260124 D-53153, Bonn Germany Attention: Mr. Rajesh Kumar Sethi 13 June 2008 Subject: Call for public comments on Clean Development

More information

Gold Standard Validation Report

Gold Standard Validation Report Gold Standard Validation Report CARBON ASSET MANAGEMENT SWEDEN AB Gold Standard Validation of the Ningxia Yinyi 49.50 MW Wind-farm Project, China Report No. 1053561 04 April 2008 TÜV SÜD Industrie Service

More information

Carbon Resource Management Ltd. IN CHINA. 2008, October May 0624

Carbon Resource Management Ltd. IN CHINA. 2008, October May 0624 Validation Report Carbon Resource Management Ltd. VALIDATION OF THE CDM-PROJECT: ZHEJIANG CIXI WIND FARM PROJECT IN CHINA REPORT NO. 1055098 2008, October May 0624 TÜV SÜD Industrie Service GmbH Carbon

More information

Request for review Project 1141 : Amurang Biomass Cogeneration Project

Request for review Project 1141 : Amurang Biomass Cogeneration Project Members of the CDM Executive Board UNFCCC Secretariat Martin-Luther-King-Strasse 8 D-53175 Bonn Germany 24 October 2007 1st Floor Park Central 40/41 Park End Street Oxford OX1 1JD UK Tel +44 (0) 1865 202

More information

Annex 21. Methodological tool. Tool for the demonstration and assessment of additionality. (Version )

Annex 21. Methodological tool. Tool for the demonstration and assessment of additionality. (Version ) Page 1 Methodological tool Tool for the demonstration and assessment of additionality (Version 06.0.0) 1. The use of the Tool for the demonstration and assessment of additionality is not mandatory for

More information

VALIDATION REPORT SHAOYANG TRIUMPH BILLION YUZITANG POWER STATION DEVELOPMENT LTD, CO. VALIDATION OF CHINA HUNAN YUZITANG SMALL HYDROPOWER PROJECT

VALIDATION REPORT SHAOYANG TRIUMPH BILLION YUZITANG POWER STATION DEVELOPMENT LTD, CO. VALIDATION OF CHINA HUNAN YUZITANG SMALL HYDROPOWER PROJECT TÜV Rheinland Japan Ltd. TÜV Rheinland Group VALIDATION REPORT SHAOYANG TRIUMPH BILLION YUZITANG POWER STATION DEVELOPMENT LTD, CO. VALIDATION OF CHINA HUNAN YUZITANG SMALL HYDROPOWER PROJECT P.R. CHINA

More information

European Investment Bank (EIB) Guidelines for the Climate Change Technical Assistance Facility (CCTAF) Operations

European Investment Bank (EIB) Guidelines for the Climate Change Technical Assistance Facility (CCTAF) Operations European Investment Bank (EIB) Guidelines for the Climate Change Technical Assistance Facility (CCTAF) Operations March 2006 CONTENTS CONTENTS...2 INTRODUCTION...3 1 BACKGROUND...4 1.1 The concept of CDM

More information

Introduction to Emission Reduction Purchase Agreement (ERPA)

Introduction to Emission Reduction Purchase Agreement (ERPA) Introduction to Emission Reduction Purchase Agreement (ERPA) Definition and transaction type Parties seller and buyer Object CER, VER or other formal of emission reduction Type Forward contract Spot contract

More information

CLEAN DEVELOPMENT MECHANISM PROJECT DESIGN DOCUMENT FORM (CDM-PDD) Version 03 - in effect as of: 28 July 2006 CONTENTS. Annexes

CLEAN DEVELOPMENT MECHANISM PROJECT DESIGN DOCUMENT FORM (CDM-PDD) Version 03 - in effect as of: 28 July 2006 CONTENTS. Annexes page 1 CLEAN DEVELOPMENT MECHANISM PROJECT DESIGN DOCUMENT FORM (CDM-PDD) Version 03 - in effect as of: 28 July 2006 CONTENTS A. General description of project activity B. Application of a baseline and

More information

Validation Report. Xinjiang Tianfu Thermoelectric Co., Ltd

Validation Report. Xinjiang Tianfu Thermoelectric Co., Ltd Validation Report Xinjiang Tianfu Thermoelectric Co., Ltd VALIDATION OF THE CDM-PROJECT: Manasi River Stage I Hydropower Project of Hongshanzui Hydropower Plant, Xinjiang Tianfu Thermoelectric REPORT NO.

More information

CLEAN DEVELOPMENT MECHANISM PROJECT DESIGN DOCUMENT FORM (CDM-PDD) Version 03 - in effect as of: 28 July 2006 CONTENTS

CLEAN DEVELOPMENT MECHANISM PROJECT DESIGN DOCUMENT FORM (CDM-PDD) Version 03 - in effect as of: 28 July 2006 CONTENTS page 1 CLEAN DEVELOPMENT MECHANISM PROJECT DESIGN DOCUMENT FORM (CDM-PDD) Version 03 - in effect as of: 28 July 2006 CONTENTS A. General description of project activity B. Application of a baseline and

More information

CLEAN DEVELOPMENT MECHANISM PROJECT DESIGN DOCUMENT FORM (CDM-PDD) Version 03 - in effect as of: 28 July 2006 CONTENTS. Annexes

CLEAN DEVELOPMENT MECHANISM PROJECT DESIGN DOCUMENT FORM (CDM-PDD) Version 03 - in effect as of: 28 July 2006 CONTENTS. Annexes CDM Executive Board page 1 CLEAN DEVELOPMENT MECHANISM PROJECT DESIGN DOCUMENT FORM (CDM-PDD) Version 03 - in effect as of: 28 July 2006 CONTENTS A. General description of project activity B. Application

More information

Clean Development Mechanism CDM

Clean Development Mechanism CDM Workshop on Improving the Regional Distribution of CDM Projects in Asia and the Pacific 8-9 September 2010, ADB Headquarters, Manila, Philippines Clean Development Mechanism CDM Xeset 2 Hydropower Project

More information

Clean Development Mechanism

Clean Development Mechanism Clean Development Mechanism Srikanth Subbarao Regional CDM Expert for the Pacific Islands (Consultant) Technical Support Facility (TSF) /Carbon Market Initiative Energy, Transport and Water Division Why

More information

Zafarana Wind Power Plants AS CDM Projects. Eng. Rafik Youssef Georgy Consultant, NREA

Zafarana Wind Power Plants AS CDM Projects. Eng. Rafik Youssef Georgy Consultant, NREA Zafarana Wind Power Plants AS CDM Projects Eng. Rafik Youssef Georgy Consultant, NREA ا ORGANIZATION CHART OF MINISTRY OF ELECTRICITY & ENERGY Egyptian Electricity Holding Company Nuclear Materials Authority

More information

Validation of CDM Projects Real life examples of what a DOE looks for

Validation of CDM Projects Real life examples of what a DOE looks for Validation of CDM Projects Real life examples of what a DOE looks for Jonathan Avis, CDM Business Manager ERM Certification and Verification Services 2nd Floor, Exchequer Court 33 St Mary Axe London EC3A

More information

Annex 33 IMPLEMENTATION PLAN FOR THE CLEAN DEVELOPMENT MECHANISM PROJECT STANDARD, VALIDATION AND VERIFICATION STANDARD AND PROJECT CYCLE PROCEDURE

Annex 33 IMPLEMENTATION PLAN FOR THE CLEAN DEVELOPMENT MECHANISM PROJECT STANDARD, VALIDATION AND VERIFICATION STANDARD AND PROJECT CYCLE PROCEDURE Page 1 IMPLEMENTATION PLAN FOR THE CLEAN DEVELOPMENT MECHANISM PROJECT STANDARD, VALIDATION AND VERIFICATION STANDARD AND PROJECT CYCLE PROCEDURE (Version 02.0) I. Background 1. The Executive Board of

More information

CLEAN DEVELOPMENT MECHANISM PROJECT DESIGN DOCUMENT FORM (CDM-SSC-PDD) Version 03 - in effect as of: 22 December 2006 CONTENTS.

CLEAN DEVELOPMENT MECHANISM PROJECT DESIGN DOCUMENT FORM (CDM-SSC-PDD) Version 03 - in effect as of: 22 December 2006 CONTENTS. CLEAN DEVELOPMENT MECHANISM PROJECT DESIGN DOCUMENT FORM (CDM-SSC-PDD) Version 03 - in effect as of: 22 December 2006 CONTENTS A. General description of the small scale project activity B. Application

More information

Report No: QT-CDM /11

Report No: QT-CDM /11 VALIDATION REPORT ZHONGFANG COUNTY PAILOU HYDRO PROJECT, CHINA Report No: QT-CDM04-06 07/11 TÜV NORD CERT GmbH JI/CDM Certification Program Langemarckstrasse 20 45141 Essen, Germany Phone: +49-201-825-3335

More information

CDM AND VER VALIDATION PROTOCOL

CDM AND VER VALIDATION PROTOCOL APPENDIX A CDM AND VER VALIDATION PROTOCOL SAYALAR 30.4 MW WIND FARM PROJECT TURKEY FINAL REPORT NO. 2007-44003 REVISION NO. 01 Table 1 Mandatory Requirements for High Standard Voluntary Emission Reduction

More information

CLEAN DEVELOPMENT MECHANISM PROJECT DESIGN DOCUMENT FORM (CDM-PDD) Version 03 - in effect as of: 28 July 2006 CONTENTS. Annexes

CLEAN DEVELOPMENT MECHANISM PROJECT DESIGN DOCUMENT FORM (CDM-PDD) Version 03 - in effect as of: 28 July 2006 CONTENTS. Annexes CDM Executive Board page 1 CLEAN DEVELOPMENT MECHANISM PROJECT DESIGN DOCUMENT FORM (CDM-PDD) Version 03 - in effect as of: 28 July 2006 CONTENTS A. General description of project activity B. Application

More information

Small-Scale CDM & Bundling: Criteria, Advantages & Status

Small-Scale CDM & Bundling: Criteria, Advantages & Status Small-Scale CDM & Bundling: Criteria, Advantages & Status Need for Small-Scale CDM introduced by CDM EB to encourage the development of smaller CDM projects typically would have been less attractive in

More information

CDM Validation Report

CDM Validation Report Project Title Qinghai Jingneng Ge'ermu Solar PV Power Project ERM CVS Project Reference Client Name 2401.v1 Qinghai Jingneng Construction Investment Co., Ltd. Client Address Floor 3, Jingfa Building, Kunlun

More information

VALIDATION REPORT NINGXIA TIANJING MW WIND-FARM PROJECT IN CHINA REPORT NO REVISION NO. 01 DET NORSKE VERITAS

VALIDATION REPORT NINGXIA TIANJING MW WIND-FARM PROJECT IN CHINA REPORT NO REVISION NO. 01 DET NORSKE VERITAS VALIDATION REPORT NINGXIA TIANJING 50.25 MW WIND-FARM PROJECT IN CHINA REPORT NO. 2006-1769 REVISION NO. 01 DET NORSKE VERITAS VALIDATION REPORT Date of first issue: Project No.: 2006-10-23 45010012-9

More information

Legal Issues around Carbon Credit Transactions and Introduction to Emission Reduction Purchase Agreement (ERPA) Yisong Guan

Legal Issues around Carbon Credit Transactions and Introduction to Emission Reduction Purchase Agreement (ERPA) Yisong Guan Legal Issues around Carbon Credit Transactions and Introduction to Emission Reduction Purchase Agreement (ERPA) Yisong Guan Easy Carbon Consultancy Co. Ltd. Definition and transaction type Parties seller

More information

Outline. Hydro potential in CDM Issues in new hydro projects Case studies Next step? Short brief on EcoSecurities

Outline. Hydro potential in CDM Issues in new hydro projects Case studies Next step? Short brief on EcoSecurities The Clean Development Mechanism: Emission down, profit up Paul Butarbutar Senior Project Manager EcoSecurities Indonesia EcoSecurities Group plc Outline Hydro potential in CDM Issues in new hydro projects

More information

(20-MW Geothermal Power Generation)

(20-MW Geothermal Power Generation) MOEJ/GEC JCM Project Feasibility Study (FS) 2014 Summary of the Final Report (20-MW Geothermal Power Generation) (Implementing Entity: Mizuho Information and Research Institute, Inc.) 1.Overview of the

More information

Annex 1 CLEAN DEVELOPMENT MECHANISM VALIDATION AND VERIFICATION MANUAL. (Version 01.2) CONTENTS ABBREVIATIONS... 3 I. INTRODUCTION...

Annex 1 CLEAN DEVELOPMENT MECHANISM VALIDATION AND VERIFICATION MANUAL. (Version 01.2) CONTENTS ABBREVIATIONS... 3 I. INTRODUCTION... Page 1 CLEAN DEVELOPMENT MECHANISM VALIDATION AND VERIFICATION MANUAL (Version 01.2) CONTENTS Paragraphs Page ABBREVIATIONS... 3 I. INTRODUCTION... 1 5 4 A. Updates to the Manual... 6 4 II. TERMS FOR VALIDATING

More information

Validation Report. Beijing Guotou Energy Conservation Company. Validation of The 30 MW Tuoli Wind Farm Project in Urumqi, Xinjiang of China

Validation Report. Beijing Guotou Energy Conservation Company. Validation of The 30 MW Tuoli Wind Farm Project in Urumqi, Xinjiang of China Validation Report Beijing Guotou Energy Conservation Company Validation of The 30 MW Tuoli Wind Farm Project in Urumqi, Xinjiang of China Report No. 712740 rev. 1 17 July 2006 TÜV SÜD ndustrie Service

More information

A rating of Designated Operational Entities (DOEs) Accredited under the Clean Development Mechanism (CDM)

A rating of Designated Operational Entities (DOEs) Accredited under the Clean Development Mechanism (CDM) A rating of Designated Operational Entities (DOEs) Accredited under the Clean Development Mechanism (CDM) Scope, methodology and results Report for WWF Berlin, 27 May 2009 Lambert Schneider Lennart Mohr

More information

Gold Standard Passport CONTENTS

Gold Standard Passport CONTENTS Gold Standard Passport CONTENTS A. Project title B. Project description C. Proof of project eligibility D. Unique Project Identification E. Outcome stakeholder consultation process F. Outcome sustainability

More information

CLEAN DEVELOPMENT MECHANISM PROJECT DESIGN DOCUMENT FORM (CDM-SSC-PDD) Version 03 - in effect as of: 22 December 2006 CONTENTS

CLEAN DEVELOPMENT MECHANISM PROJECT DESIGN DOCUMENT FORM (CDM-SSC-PDD) Version 03 - in effect as of: 22 December 2006 CONTENTS CLEAN DEVELOPMENT MECHANISM PROJECT DESIGN DOCUMENT FORM (CDM-SSC-PDD) Version 03 - in effect as of: 22 December 2006 CONTENTS A. General description of the small scale project activity B. Application

More information

(GS-VER-PDD) THE GOLD STANDARD: Project Design Document for Gold Standard Voluntary Offset projects

(GS-VER-PDD) THE GOLD STANDARD: Project Design Document for Gold Standard Voluntary Offset projects THE GOLD STANDARD: Project Design Document for Gold Standard Voluntary Offset projects (GS-VER-PDD) For more information, please contact The Gold Standard: http://www.cdmgoldstandard.org info@cdmgoldstandard.org

More information

Below, IETA provides a number of comments and views that will allow the Secretariat to further refine the current draft.

Below, IETA provides a number of comments and views that will allow the Secretariat to further refine the current draft. September 3, 2008 CDM Executive Board UNFCCC Secretariat Martin Luther King Strasse 8 P.O.Box 260124 D-53153 Germany Dear Mr. Sethi, I write to you on behalf of the International Emissions Trading Association

More information

How to develop a Carbon Finance project?

How to develop a Carbon Finance project? How to develop a Carbon Finance project? Assessment of tool - Is this landfill project feasible? Source: www.unescap.org/esd Minimum Project Requirements 1 2 3 4 5 7 8 9 10 11 12 Type of Project CER Volume

More information

CDM project review - technology and regulation aspects

CDM project review - technology and regulation aspects Pacific Regional CDM Capacity Building Workshop CDM project review - technology and regulation aspects Xianli Zhu 24-28, Jan 2011, Suva, Fiji Outline DNA Approval Expert support as part of the host country

More information

CDM Risks and Mitigation

CDM Risks and Mitigation CDM Risks and Mitigation Carbon Markets Asia 23-24 June 2009, Meliá Hotel, Kuala Lumpur, Malaysia Arul Joe Mathias B.E., M.Engg., MBA (Managing Director) Dr. Balasankari B.E., M.Engg., Ph.D (Executive

More information

China s CDM Policy & Progress

China s CDM Policy & Progress China s CDM Policy & Progress For 2006 Japan Carbon Investors Forum Wang Shu March, 2006 Tokyo Presentation Contents Brief of DNA CDM projects Progress National Approval Process Requirements for Approval

More information

Overview of the CDM in the agriculture sector

Overview of the CDM in the agriculture sector Overview of the CDM in the agriculture sector Grant A. Kirkman Team Leader CDM Methodologies Methane to Markets 30 October 1 November 2007 Beijing China United Nations Framework Convention on Climate Change

More information

Registration - Information and reporting checklist (Version 2.0) The main changes between version 1.0 and version 2.0 are the following:

Registration - Information and reporting checklist (Version 2.0) The main changes between version 1.0 and version 2.0 are the following: Registration - Information and reporting checklist (Version 2.0) Version 1.0 of the information and reporting checklist was published in June 2010. The enclosed version 2.0 of this checklist represents

More information

Tips on PDD Preparation

Tips on PDD Preparation Tips on PDD Preparation What is PDD for? The PDD (Project Design Document) was developed by the CDM Executive Board in conformity with the relevant modalities and procedures for the Project Design Document

More information

Validation Report. Kalpataru Energy Venture Pvt. Ltd. Validation of the Biomass Power Project at Kalpataru Energy Venture Private Limited

Validation Report. Kalpataru Energy Venture Pvt. Ltd. Validation of the Biomass Power Project at Kalpataru Energy Venture Private Limited Validation Report Kalpataru Energy Venture Pvt. Ltd. Validation of the Biomass Power Project at Kalpataru Energy Venture Private Limited Report No. 806970, Revision 01 2006, April 12 TÜV ndustrie Service

More information

Call for CDM proposals Frequent Asked Questions (FAQ)

Call for CDM proposals Frequent Asked Questions (FAQ) EM2000 W-4.0, 2010-11-17 1 (5) International Carbon Market Unit climateprojects@swedishenergyagency.se Call for CDM proposals Frequent Asked Questions (FAQ) 1. What are the objectives of the Swedish CDM

More information

Financing Programmes for CDM Projects

Financing Programmes for CDM Projects Financing Programmes for CDM Projects November 2003 European Commission (Directorate-General for Energy and Transport) Contract no. NNE5/2002/52: OPET CHP/DH Cluster TITLE: Financing Programmes for CDM

More information

This document replaces Annex F dated 23 November 2009 in the rule updates section.

This document replaces Annex F dated 23 November 2009 in the rule updates section. PoA Rules and Guidance Annex F (revised on 23 December, 2010) This document replaces Annex F dated 23 November 2009 in the rule updates section. 1 PoA eligibility Where a group of project activities is

More information

Overview of CDM Documentation and Procedures

Overview of CDM Documentation and Procedures Overview of CDM Documentation and Procedures 19-20 April 2006 London, England John Kessels CDM Documentation Project Design Document CDM Institutions CDM New Methodology Baseline (CDM NMB) CDM New Monitoring

More information

A CASE STUDY: ASJA S BELO HORIZONTE CDM PROJECT BRAZIL / KYOTO PROTOCOL

A CASE STUDY: ASJA S BELO HORIZONTE CDM PROJECT BRAZIL / KYOTO PROTOCOL Fordham University School of Law February 22nd, 2010 A CASE STUDY: ASJA S BELO HORIZONTE CDM PROJECT BRAZIL / KYOTO PROTOCOL Agostino Re Rebaudengo President arr@asja.biz INDEX KYOTO PROTOCOL AND EMISSION

More information

DAK PSI 3 AND 4 HYDROPOWER PROJECT

DAK PSI 3 AND 4 HYDROPOWER PROJECT DAK PSI 3 AND 4 HYDROPOWER PROJECT Document Prepared By Kyoto Energy Pte. Ltd. Project Title Dak Psi 3 and 4 Hydropower Project Version 2.3 Date of Issue Prepared By Contact 27-February-2013 Kyoto Energy

More information

Request for Review 15 MW grid-connected wind power project by MMTC in Karnataka (1797)

Request for Review 15 MW grid-connected wind power project by MMTC in Karnataka (1797) TÜV NORD CERT GmbH P.O. Box 10 32 61 45032 Essen CDM Executive Board TÜV NORD CERT GmbH Langemarckstrasse 20 45141 Essen Phone: +49 201 825-0 Fax: +49 201 825-2517 Info.tncert@tuev-nord.de www.tuev-nord-cert.com

More information

CLEAN DEVELOPMENT MECHANISM PROJECT DESIGN DOCUMENT FORM (CDM-PDD) Version 03 - in effect as of: 28 July 2006 CONTENTS. Annexes

CLEAN DEVELOPMENT MECHANISM PROJECT DESIGN DOCUMENT FORM (CDM-PDD) Version 03 - in effect as of: 28 July 2006 CONTENTS. Annexes CDM Executive Board page 1 CLEAN DEVELOPMENT MECHANISM PROJECT DESIGN DOCUMENT FORM (CDM-PDD) Version 03 - in effect as of: 28 July 2006 CONTENTS A. General description of project activity B. Application

More information

Comments on the Draft CDM Validation and Verification Manual

Comments on the Draft CDM Validation and Verification Manual 13 th June 2008 Comments on the Draft CDM Validation and Verification Manual Submitted by Asia Carbon Global, Singapore w w w. a s i a c a r b o n. c o m Asia Carbon Global Asia Carbon Global (2008) Comments

More information

Methodological tool. Combined tool to identify the baseline scenario and demonstrate additionality. (Version 02.2)

Methodological tool. Combined tool to identify the baseline scenario and demonstrate additionality. (Version 02.2) Page 1 Methodological tool Combined tool to identify the baseline scenario and demonstrate additionality I. SCOPE AD APPLICABILIT (Version 02.2) This tool provides for a step-wise approach to identify

More information

CLEAN DEVELOPMENT MECHANISM PROJECT DESIGN DOCUMENT FORM (CDM-PDD) Version 03 - in effect as of: 28 July 2006 CONTENTS

CLEAN DEVELOPMENT MECHANISM PROJECT DESIGN DOCUMENT FORM (CDM-PDD) Version 03 - in effect as of: 28 July 2006 CONTENTS page 1 CLEAN DEVELOPMENT MECHANISM PROJECT DESIGN DOCUMENT FORM (CDM-PDD) Version 03 - in effect as of: 28 July 2006 CONTENTS A. General description of project activity B. Application of a baseline and

More information

UNFCCC Secretariat CDM Mr. Grant Kirkman UNFCCC Secretariat Martin-Luther-King-Strasse 8 D Bonn Germany. Dear Mr. Kirkman,

UNFCCC Secretariat CDM Mr. Grant Kirkman UNFCCC Secretariat Martin-Luther-King-Strasse 8 D Bonn Germany. Dear Mr. Kirkman, UNFCCC Secretariat CDM Mr. Grant Kirkman UNFCCC Secretariat Martin-Luther-King-Strasse 8 D-53153 Bonn Germany Project Developer Forum Ltd. 100 New Bridge Street UK London EC4V 6JA Mailing address: Schulstrasse

More information

Approved consolidated baseline and monitoring methodology ACM0013

Approved consolidated baseline and monitoring methodology ACM0013 Approved consolidated baseline and monitoring methodology ACM0013 Consolidated baseline and monitoring methodology for new grid connected fossil fuel fired power plants using a less GHG intensive technology

More information

VALIDATION REPORT RENEWAL OF CREDITING PERIOD

VALIDATION REPORT RENEWAL OF CREDITING PERIOD VALIDATION REPORT RENEWAL OF CREDITING PERIOD Kanfeng 15MW Hydropower Station Project, Min County, Dingxi City Prefecture, Gansu province, China REPORT NO. CDM-0111-RCP1 No distribution without permission

More information

CLEAN DEVELOPMENT MECHANISM. PROJECT DESIGN DOCUMENT FORM (CDM-PDD) Version 03 - in effect as of: 28 July 2006 CONTENTS

CLEAN DEVELOPMENT MECHANISM. PROJECT DESIGN DOCUMENT FORM (CDM-PDD) Version 03 - in effect as of: 28 July 2006 CONTENTS page 1 CLEAN DEVELOPMENT MECHANISM PROJECT DESIGN DOCUMENT FORM (CDM-PDD) Version 03 - in effect as of: 28 July 2006 CONTENTS A. General description of project activity B. Application of a baseline and

More information

Response to the Request for Review BK Energia Itacoatiara Project

Response to the Request for Review BK Energia Itacoatiara Project CDM Executive Board Secretariat of the UNFCCC Haus Carstanjen Martin-Luther-King-Strasse 8 P.O. Box 260124 D-53153 Bonn Germany Itacoatiara, March 29, 2007 Response to the Request for Review - 0168 BK

More information

UNFCCC/CCNUCC DRAFT STANDARD FOR THE DEVELOPMENT OF ELIGIBILITY CRITERIA FOR THE INCLUSION OF A PROJECT ACTIVITY AS A CPA UNDER THE POA. I.

UNFCCC/CCNUCC DRAFT STANDARD FOR THE DEVELOPMENT OF ELIGIBILITY CRITERIA FOR THE INCLUSION OF A PROJECT ACTIVITY AS A CPA UNDER THE POA. I. Page 1 STANDARD FOR THE DEVELOPMENT OF ELIGIBILITY CRITERIA FOR THE INCLUSION OF A PROJECT ACTIVITY AS A CPA UNDER THE POA I. Background 1. In decision 3/CMP.1 paragraph 4, Parties requested the clean

More information

Stakeholders Consultation Process -

Stakeholders Consultation Process - Session 6 Stakeholders Consultation Process - Latest developments and the possible role of DNAs 13 th DNA Forum Bonn, Germany, 22-23 March, 2012 UNFCCC secretariat SDM Programme Structure CDM Stakeholder

More information

Validation Report. Matrix Power Pvt. Ltd. (MPPL)

Validation Report. Matrix Power Pvt. Ltd. (MPPL) Validation Report Matrix Power Pvt. Ltd. (MPPL) Validation of the 4.5 MW Biomass (Agricultural Residues) Based Power Generation Unit of M/s Matrix Power Pvt. Ltd. (MPPL) project Report No. 6589 Revision

More information

Annex 3 CLEAN DEVELOPMENT MECHANISM VALIDATION AND VERIFICATION MANUAL. (Version 01) CONTENTS I. INTRODUCTION

Annex 3 CLEAN DEVELOPMENT MECHANISM VALIDATION AND VERIFICATION MANUAL. (Version 01) CONTENTS I. INTRODUCTION page 1 CLEAN DEVELOPMENT MECHANISM VALIDATION AND VERIFICATION MANUAL (Version 01) CONTENTS Paragraphs Page ABBREVIATIONS... 4 I. INTRODUCTION... 1 5 5 A. Updates to the Manual... 6 4 II. TERMS FOR VALIDATING

More information

CLEAN DEVELOPMENT MECHANISM PROJECT DESIGN DOCUMENT FORM (CDM-SSC-PDD) Version 03 - in effect as of: 22 December 2006 CONTENTS

CLEAN DEVELOPMENT MECHANISM PROJECT DESIGN DOCUMENT FORM (CDM-SSC-PDD) Version 03 - in effect as of: 22 December 2006 CONTENTS CLEAN DEVELOPMENT MECHANISM PROJECT DESIGN DOCUMENT FORM (CDM-SSC-PDD) Version 03 - in effect as of: 22 December 2006 CONTENTS A. General description of the small scale project activity B. Application

More information

CDM Carbon Finance Workshop. Session 9: Discussion of project risks and mitigation strategies. Accra, June

CDM Carbon Finance Workshop. Session 9: Discussion of project risks and mitigation strategies. Accra, June CDM Carbon Finance Workshop Session 9: Discussion of project risks and mitigation strategies Accra, June 24-26 2009 Contents Introductory quiz CDM and project risk explained Key concepts covered Case study

More information

Landfill Gas (LFG) Clean Development Mechanism (CDM) Projects in China Case Study: Tianjin. Washington International Renewable Energy Conference

Landfill Gas (LFG) Clean Development Mechanism (CDM) Projects in China Case Study: Tianjin. Washington International Renewable Energy Conference Landfill Gas (LFG) Clean Development Mechanism (CDM) Projects in China Case Study: Tianjin Washington International Renewable Energy Conference March 4, 2008 Presentation Topics Global Warming - Greenhouse

More information

Becoming Green and Gold: Applying the CDM to Wind Energy

Becoming Green and Gold: Applying the CDM to Wind Energy Becoming Green and Gold: Applying the CDM to Wind Energy Introductory document Renewable Energy City Summit 13 14 May 2008 This report is solely for the use of client personnel. No part of it may be circulated,

More information

Financing the CDM through international climate finance institutions

Financing the CDM through international climate finance institutions Financing the CDM through international climate finance institutions CDM EB 88 Bonn, Germany, 7 to 11 March 2016 UNFCCC Secretariat SDM programme Procedural background The Conference of the Parties serving

More information

Chapter 1 Introduction

Chapter 1 Introduction Chapter 1 Introduction 1.1 Programme rationale and objective 1.1.1 Programme Rationale Provincial Electricity Authority (PEA) is a state enterprise established under Provincial Electricity Authority Act

More information

CLEAN DEVELOPMENT MECHANISM PROJECT DESIGN DOCUMENT FORM (CDM-PDD) Version 03 - in effect as of: 28 July 2006 CONTENTS

CLEAN DEVELOPMENT MECHANISM PROJECT DESIGN DOCUMENT FORM (CDM-PDD) Version 03 - in effect as of: 28 July 2006 CONTENTS CDM Executive Board page 1 CLEAN DEVELOPMENT MECHANISM PROJECT DESIGN DOCUMENT FORM (CDM-PDD) Version 03 - in effect as of: 28 July 2006 CONTENTS A. General description of project activity B. Application

More information

ANI OJSC. Validation of the Jradzor Small Hydroelectric CDM project. May 2008 This report contains 37 pages. 1May08.doc

ANI OJSC. Validation of the Jradzor Small Hydroelectric CDM project. May 2008 This report contains 37 pages. 1May08.doc ABCD ANI OJSC Validation of the Jradzor Small Hydroelectric CDM project This report contains 37 pages project 1May08.doc 2008 KPMG Sustainability B.V., a Dutch limited liability company and a member firm

More information