Factors affecting construction cost performance in project management projects: Case of MARA large projects

Size: px
Start display at page:

Download "Factors affecting construction cost performance in project management projects: Case of MARA large projects"

Transcription

1 International Journal of Civil Engineering and Built Environment Vol.1, No.1, 2014; ISSN Published by YSI Publisher Factors affecting construction cost performance in project management projects: Case of MARA large projects Aftab Hameed Memon 1, Ismail Abdul Rahman 1, Mohd Razaki Abdullah 2,Ade Asmi Abdu Azis 3 1 Faculty of Civil and Environmental Engineering, University Tun Hussein Onn Malaysia, Malaysia 2 Majlis Amanah Rakyat (MARA) 3 Universiti Tun Hussein Onn Malaysia, Parit Raja - Batu Pahat Corresponding Author:aftabm78@hotmail.com Abstract Aim of Study This study has focused on investigating procurement strategies adopted in MARA large construction projects. It also identified various factor affecting construction cost performance of MARA large construction projects. Need of Study Very rarely MARA projects are finished within estimated project cost. For improving cost performance, it is very important to identify the reasons affecting cost performance of MARA projects. Hence, there is a need of study in understanding the reasons and factors affecting project cost performance of construction projects. Research Approach The project was carried out through interviews and survey using the questionnaire among the personnel involved in handling MARA large projects. Gathered data was analyzed statistically using SPSS software package. Research Findings This study revealed that fluctuation in price of the material, cash flow and financial difficulties faced by contractors, shortage of site workers, lack of communication between parties, incorrect planning and scheduling by contractors are most severe factors while frequent design changes and owner interference are least affecting factors on construction cost performance in MARA large projects. Limitations This study was limited to large construction projects administrated by Majlis Amanah Rakyat (MARA) Malaysia. Importance and Contribution This study has highlighted various issues causing poor project performance in MARA large projects. Ranking of the factors will enable the MARA engineers for taking appropriate actions in improving the performance of cost in construction projects. Keywords: Construction Industry, Construction Cost, MARA Projects, Cost performance, Cost Overrun I. INTRODUCTION In recent years, Malaysian construction industry has recorded an average growth rate of 0.7% [1] compared to GDP growth of 5.46%. However, the industry is facing a lot of challenges in achieving satisfactory cost performance [2-4]. Government formed MARA (Majlis Amanah Rakyat) to strengthen the Bumiputera (Malays and other indigenous Malaysians) in the areas of business and industry. MARA currently placed under the Rural and Regional Development Ministry after briefly controlled by the Entrepreneur and Cooperation Development Ministry plays an important role in implementing the government policy. MARA has spent about RM 12 billion in its development since 1 st Malaysian plan [5]. A portion of this allocation was spent on construction. The major issue in MARA large construction project is the delay in completing its projects. An interview with Tech Art Executive Director revealed that more that 90% of large MARA construction project experienced delay since Most frequent effects of delay in MARA projects are time overrun and cost overrun. Studies revealed that time and cost overrun has a linear relationship with each other [6]. Keeping construction projects within estimated costs and schedules requires sound strategies, good practices, and careful judgment. To the dislike of owners, contractors and consultants, however, many projects experience extensive delays and thereby exceed initial time and cost estimates. This problem is more obvious in the traditional or adversarial type of contracts in which the contract is awarded to the lowest bidder, which is the strategy in the majority of public projects in developing countries [7]. In order to manage and control construction projects, there are various procurements strategies being adopted. Most popular strategies include traditional, management, integrated services and in-house teams [8]. These strategies contain various methods of managing projects as shown in Table 1. TABLE I. TYPES OF PROCUREMENT METHODS &THEIR VARIATIONS Procurement Strategy Methods/Techniques Procurement Strategy Management Integrated Traditional Lump Sum System/Traditional System/ Design- Bid- Build/Open Tender Contracts Negotiated Contracts Best Value Procurement Incentives Contracts Construction Project Management/Contract Management Construction Management at Risk/Management Contracting Design and Build Turnkey System 30

2 International Journal of Civil Engineering and Built Environment Vol. 1 No. 1, 2014 In-house Self-Performance In-House Teams Job-Orderr Contract Separate Contracts In Malaysian, traditional lump sum system, design and build/ /turnkey system and Construction Project Management/Contract Management are commonly adopted in procurement strategies [1, 9]. This study has been conducted to (1) examine various procurement strategies adopted in MARAA Projects, (ii) identifying factors affecting construction cost performance in MARA projects. However, the limitations of this study include, firstly this paper focus large constructionn projects only. Although, it is difficult to define large constructions, but in a study of Vietnam projects with a total budget of $1 million were considered as large projects [10]. In this study, project of budget RM 5 million and above is considered as large construction project, secondly, this study focuses on projects with projects management procurement strategies only. Thirdly, targeted respondent included in dataa collection were personnel of contractor firms and client. II. RELATED WORKS W A. Budget Planning and Control Procurement method is a strategy to manage the entiree construction process. There are a number of proven strategiess that are used to manage the process where each has its own distinct advantages and disadvantages. Initially, four procurement approaches are widely discussed; traditional, management, integrated services and in house teams [9]. 1) Traditional Procurement: Basically, this procurement is applied to ordinary projects of moderate size and complexity. A client employs an architect (for a building) or engineer (for civil engineering works or other structures) and contractors for the construction separately. A designer is hired earlier to produce drawings and specification while contractors will be selected after a client is satisfied with the drawings and specification. Normally, an architect or engineer will be appointed on fee basis as a leader to coordinate the activities of other members and have direct access to the client. In orderr to get the best possible result, it is normal for the client to choose any suitable variations that suits to their plan. Variations such as design-bid-build, negotiated contracts, best value procurement, incentives contracts are widely used in USA, while variations such as open tender contracts and negotiated contracts in UK. In Malaysia, both open tender and negotiated contracts are extensively adopted and this is similar to UK. Sometimes, a client incorporates Project Management Consultant (PMC) into this procurement to assist the client in administering the project [9]. The typical contractual relationship and sequence of operation is shown in Figure 1 and Figure 2. 2) Management Procurement: Basically Compared to traditional procurement which is focusing on moderate size and complexity, management procurement is preferred to be adopted for large or complex projects. A person or company is appointed by client on a fee basis to organize and manage the whole construction process. A construction management (CM) is hired earlier or together with the designer before any substantial design work is done and before any substantial work begun. The CM (on client s behalf) works with the designer during the design phase and representing client during the construction phase. The typical contractual relationship and sequence of operation is shown in Figure 3 and Figure 4. Figure 1. Typical Contractual Relationships under Traditional Method Figure 2. Typical Sequences of Operations Figure 3. Typical Contractual Relationships under Management Procurement Figure 4. Typical Sequences of Operations of Management Procurement 3) Integrated Procurement: Basically Integrated procurement is where design and construction, as well as several other subtasks on the project, are performed by a single organization, often a large contracting firm. Sometimes, professionals such as construction managers, architect, quantity surveyors and engineers combined together to form a consortium to provide integrated services. This procurement is mainly adopted on technically sophisticated projects of which prospective contractors have special experience, or time is of 31

3 International Journal of Civil Engineering and Built Environment Vol. 1 No. 1, 2014 the essence. It provides a single point of contact and responsibility throughout the project. Design and build or design-build variation is popularly used in USA. Similarly in UK, design and build variation is also widely used. Apparently, design and build or turnkey system was introduced to Malaysia 1983 [9] and still widely adopted in Malaysia construction project. The typical contractual relationship and sequence of operation is shown in Figure 5 and Figure 6. Figure 5. Typical Contractual Relationships under Integrated Procurement Figure 6. Typical Sequences of Operations of Integrated Procurement 4) In House Procurement: Basically In house procurement is self perform construction. Normally, large clients such as large public organization or large private companies that have their own continuous construction projects have directly employ their own people such as engineers, architects, workers, etc. However, the client may choose to subcontract a substantial portion of the project to outside consultants and contractors for both design and construction, but it retains centralized decision making to integrate all efforts in project implementation. B. Cost Performance Cost Performance is the fundamental norm of measuring project success. Unfortunately, many of construction projects worldwide are experiencing poor cost performance. This is reflected in the cost overrun problem whichh now days is associated with almost every project [11]. Cost overruns dilemma is very serious and is faced in both developing and developed countries. It requires careful attention to improve this matter [12]. This problem of cost overrun is more rigorous in developing countries. Overrun in cost is occurred because of several factors as highlighted by numerous research works carried out worldwide. Among these, use of low quality materials is a common factor which results in higher construction cost compared to the estimated cost because of the significant amount of loss of materials during construction. It happens mostly because of lack of availability of standards for materials and management systems. Further, a major problem in the construction industry is the project managers have not adequate ability of preventing cost overruns. This has resulted poor cost performance and led many Thai construction to fail [13]. Similarity, in Kuwait it was highlighted by research work of Koushki [14] time and cost increases were significant issuess in private residential projects in Kuwait. The major time increase for these included frequent change orders, financial constraints and owners lack of experience in construction. While, the issues to related contractor, material and owner s financial conditions were major contributors to cost increase. Besides these, design changes, inadequate planning, unpredictable weather conditions; and fluctuations in the cost of building materials are frequently occurring factors leading to cost overruns [15, 16]. In Ghana, contractors and consultants mentioned that monthly payments difficulties is a major issue faced in construction projects that lead to delay in works and consequently project faces overrun in cost. While, client representatives highlighted that the poor contractor management is the most critical factors in causing cost overrun. Overall, in groundwater projects of Ghana, major factors recorded were found poor contractor management, monthly payment difficulties, material procurement, poor technical performances, and escalation of material prices [17]. III. DATA COLLECTION AND ANALYSIS Data collection was carried out in two phases where first phase focused on field study and interviews. It aimed to assess various procurement strategies adopted in MARA projects and identify common causes of cost overrun. In the second phase, survey was conductedd for identifying significant factors affecting construction cost performance among contractors, consultants and contractors for assessing significance of the factors. A five point likert-scale of 1 to 5 was adopted to assess the degree of agreement of each cause where 1 represented strongly disagree, 2 disagree, 3 moderately agree, 4 agree and 5 strongly agree. A total of 36 respondents participated in interviews and questionnaire survey process. Statistical Package for Social Sciencee (SPSS) version 17 was used to analyze the data. Data was checked for reliability prior to ranking the factors. Reliability describes the stability of the data collected measured using Cronbach α coefficient value. It is considered low and unacceptable if Cronbach α value is less than 0.3. Reliability is considered satisfactory if Cronbach α is more than 0.7 [18]. Distribution of respondents in terms of experience is shown in figure 11. Figure 11 indicates thatt majority of respondents i.e. 21 out of 36 (58.33%) were experienced more than 10 years in the construction industry, 7 out of 36 (19.44%) had experience between 6-10 years, while 4 respondents (11.11%) had 2-5 years experience and only 4 (11.11%) respondents had experience less than 2 years. Figure 7. Respondents working experience 32

4 International Journal of Civil Engineering and Built Environment Vol. 1 No. 1, 2014 IV. RESULTS AND DISCUSSION A. Classification of MARA projects MARA construction projects are classified into 2; small and large projects. Most of the small projects are adopting traditional procurement while the majority of large projects are adopting management procurement. In some cases, small projects which are complex and need special knowledge are also adopting management procurement. Therefore, the classification of the project is based on its contract cost but its delivery methods are based on its size and complexity. The project worth less than five million ringgit (RM 5 million) is normally considered as a small project. As mention earlier, normally MARA is adopting the traditional procurement wheree an architect is appointed as the leader to organize the construction at the construction site. The leader has direct contact with MARA. Contrast to small project, the project worth more than RM 5 million is considered as large project. This large project normally highly complicated and needs special knowledge and expertise to handle it. Most of the time, MARA is adopting management procurement for this kind of project and as a matter of fact, MARA engages PMC to supervise and administer the entiree project. B. MARA Construction Procurement Studies revealed that MARA is adopting 2 types of procurement; traditional and management. For traditional, MARA is organizing its own technical teams to administer the whole the project. However, if MARA decides to adopt management procurement,approval from LPM A must be granted first before a PMC is appointed. Figure 8 and Figure 9 show the contractual relationship of MARA traditional and management procurement while Figure 10 and Figure 111 shows their sequence of operation. Figure 8. Contractual Relationship of MARA Traditional Procurement Figure 9. Sequencee of Operation of MARA Traditional Procurement Figure 10. Contractual Relationship of MARA Management Procurement Figure 11. Sequence of Operation of MARAA Management Procurement C. Factors Affecting Construction Cost Performance During interview process, a total of 15 common factors affecting project cost performance in MRA large project were identified. Literature showed that the identified factors are common factors affecting cost performance worldwide as shown in figure II. These factors weree investigated for ranking purpose. Data collected through questionnaire was test for reliability. Cronbach's Alpha of the gathered data was found as which means dataa collected in acceptable for analysis. In order to identify the ranks of factors affecting construction cost performance, data was analyzed with SPSS 17. Results are presented in table III. Based on table III, Fluctuation in prices of materials is the most significant factor affecting construction cost performance followed by Cash flow and financial difficulties faced by contractors as second ranked factors. Shortage of site workers, lack of communication among parties were 3 rd major factor and incorrect planning & scheduling by contractors were found as 4 th ranked factor. Fluctuation in prices of materials: Table III shows that the fluctuation of material is the most dominant factor affecting construction cost. However, it is very interesting to know that according to client fluctuation in price was ranked as 6 th rank while contractor ranked as 1 st. Cash flow and financial difficulties faced by contractors: Contractors rankled cash flow and financial difficulties as 2 nd factor while client ranked same as 5 th. Contractors believe this issue is very critical where it may influencee other causes such as site management, shortage of site workers and ineffective planning and scheduling. This may be faced due to delay approval of work completed by consultant and late in monthly payment from client. Settling this issue may as well settle other issues simultaneously. Shortage of site workers: This factor is significant as perceived by Client. It is 3 rd ranked factor by overall respondents. However, client ranked this factor as most dominant while contractors ranked it as 12 th rank. Client respondents claim thatt the problem between contractor and subcontractor seems largely contribute to this cause. As most of the works are contracted to subcontractors, most of the workers are hired by these sub-contractor. If there are disputes between contractor and subcontractor, automatically this issue prevails. Lack of communication between parties: Lack of communication between parties is also ranked as third highest affecting factor. Clients ranked this factor as 3rd while contractor ranked as 4 th. Lack of coordination may result in poor management, selection of proper material and problems between the contractor and other parties. 33

5 International Journal of Civil Engineering and Built Environment Vol. 1 No. 1, 2014 TABLE II. RANKING OF FACTORS AFFECTING CONSTRUCTION COST PERFORMANCE S.No Causes [10] [`11] [17] [19] [20] [21] [22] [23] [24] [25] [26] [27] [28] [29] [30] 1 Incorrect planning and scheduling by contractors 2 Fluctuation in prices of materials 3 Frequent design changes 4 Unforeseen ground conditions 5 Inadequate contractor experience 6 Change in the scope of the project 7 Low speed of decisions making 8 Cash flow and financial difficulties faced by contractors 9 Contractor's poor site management and supervision 10 Practice of assigning contract to lowest bidder 11 Lack of communication among parties 12 Shortage of site workers 13 Delay in Material procurement 14 Underestimate project duration resulting Schedule Delay 15 Incompetent Project team (designers and contractors) TABLE III. RANKING OF FACTORS AFFECTING CONSTRUCTION COST PERFORMANCE S.No. Factors Overall Client Respondents Contractor Respondents Mean S.D Rank Mean S.D Rank Mean S.D Rank 1 Fluctuation in prices of materials Cash flow and financial difficulties faced by contractors Shortage of site workers Lack of communication among parties Incorrect planning and scheduling by contractors Contractor's poor site management and supervision Delay in Material procurement Underestimate project duration resulting Schedule Delay Unforeseen ground conditions Low speed of decisions making Inadequate contractor experience Change in the scope of the project Practice of assigning contract to lowest bidder Frequent design changes Owner interference

6 International Journal of Civil Engineering and Built Environment Vol. 1 No. 1, 2014 V. CONCLUSION Study was carried out to investigate various procurement strategies adopted in MARA large construction projects. Results showed that MARA projects are classified as small and large project based on cost of project cost. Project worth contract amount above 5 Million Ringgit were regarded as large construction projects. In order to manage projects, traditional and management procurement strategies are adopted. Also, comprehensive study was conducted to identify the factors affecting construction cost performance. Through a questionnaire survey amongst contractor and client personnel, it was perceived that fluctuation of material prices was the most dominant factor affecting construction cost performance followed by cash flow and financial difficulties faced by contractors. Shortage of site workers and lack of communication between parties were found as third major factors affecting construction cost performance. REFERENCES [1] CIMP, Construction Industry Master Plan , CIDB, Malaysia [2] CIDB news issue 3, 2007 [3] A. H. Memon, I. A. Rahman, A. A. A. Azis, S. Nagapan, and Q. B. A. I. Latif, Time and Cost Perfomance in Construction Projects, IEEE Colloquium on Humanities, Science and Engineering Research (CHUSER 2012), held on 3-4 December 2012, Kota Kinabalu, Malaysia, 2012 [4] I. A. Rahman, A. H. Memon, A. T. A. Karim, Relationship between factors of Construction Resources Affecting Project, Modern Applied Science, 7 (1), p , 2013 [5] sejarah_ mara_dari_rida_ke_marahtm [6] M. R. Abdullah, A. A. A. Azis, and I. A. Rahman, Potential effects on large MARA projects due to construction delay, International journal of Integrated Engineering (Issue on Civil and Environmental Engineering), 1(2), p , 2009 [7] A. Enshassi, J. Al-Najjar, and M. Kumaraswamy, "Delays and cost overrunsin the construction projects in the Gaza Strip", Journal of Financial Management of Property and Construction, 14 (2), p , 2009 [8] G. Ofori, The Construction Industry; aspects of its economics and management, Singapore University Press, 1990 [9] K. A. Rashid, Construction Procurement in Malaysia, International Islamic University Malaysia, 2002 [10] L. Le-Hoai, Y. D. Lee, and J. Y. Lee, Delay and cost overruns in Vietnam large construction projects: A comparison with other selected countries,. KSCE journal of civil engineering, 12 (6), p , 2008 [11] N. Azhar, R. U. Farooqui, and S. M. Ahmed, Cost overrun factors in construction industry in Pakistan, First international conference on construction in developing countries (ICCIDC-I, advancing and integrating construction education, research and practice), 2008 [12] W. J. Angelo, and P. Reina, Mega projects Need More Study Up Front to Avoid Cost Overruns, [13] E. Sriprasert, Assessment of Cost Control System: A Case Study of Thai Construction Organizations, M.S. thesis, Bangkok: Asian Institute of Technology, 2000 [14] P. A. Koushki, K. Al-Rashid, and N. Kartam, Delays and cost increases in the construction of private residential projects in Kuwait, Construction Management and Economics, 23, p , 2005 [15] P. F. Kaming, P. O. Olomolaiye, G. D. Holt, and F. C. Harris, Factors Influencing Construction Time and Cost Overruns on High-rise Projects in Indonesia, Construction Management and Economics, 15 (1), p , 1997 [16] K. D. Chimwaso, An Evaluation of Cost Performance of Public Projects; Case of Botswana, Department of Architecture and Building Services, Gaborone, 2001 [17] Y. Frimpong, J. Oluwoye, and L. Crawford, Causes of delay and cost overruns in construction of groundwater projects in a developing countries; Ghana as a case study, International Journal of project management, 21, p , 2003 [18] S. Meepol, and S. O. Ogunlana, Factors affecting cost and time performance on highway construction projects: evidence from Thailand, Journal of Financial Management of Property and Construction, 11(1), p. 3-20, 2006 [19] O. J. Ameh, A. D. Soyingbe, and K. T. Odusami, "Significant factors causing cost overruns in telecommunication projects in Nigeria", Journal of Construction in Developing Countries, 15, 2010 [20] G. Creedy, "Risk factors leading to cost overrun in highway projects". Sidwell, A. C. (Ed.). Proceeding of Queenland University of Technology Research Week International Conference, Brisbane, Australia, 4-8 July, 2005 [21] S. Jackson, Project cost overrun and risk management, Proceedings of Association of Researchers in Construction Management 18th Annual ARCOM Conference, Newcastle, Northumber University, UK, 2-4 September, 2002 [22] A. S. T. Chang, "Reasons for Cost and Schedule Increase for Engineering Design Projects", Journal of Management in Engineering, 18 (1), p , 2002 [23] Y. A. Al-Juwairah, "Factors Affecting Construction Costs in Saudi Arabia", Thesis of MSc in construction Management, Faculty of the college of Graduate Studies, King Fahad University of Petroleum & Minerals Dhahran, Saudi Arabia, 1997 [24] A. Enshassi, J. Al-Najjar, and M. Kumaraswamy, "Delays and cost overruns in the construction projects in the Gaza Strip", Journal of Financial Management of Property and Construction, 14 (2), p , 2009 [25] Harisweni, "The Framework for Minimizing Construction time and Cost Overruns in Padding and Pekanbaru, Indonesia", A thesis submitted in fulfilment of the requirements for the award of the degree of Master of Science (Quantity Surveying), Faculty of Built Environment, Universiti Teknologi Malaysia, 2007 [26] A. Omoregie, and D. Radford, Infrastructure delays and cost escalation: causes and effects in Nigeria, Proceeding of sixth international postgraduate research conference, Delft University of Technology and TNO, the Netherlands. 3rd-7th April., 2006 [27] N. D. Long, S. Ogunlana, T. Quang, and K. C. Lam, "Large construction projects in developing countries: a case study from Vietnam", International Journal of Project Management, 22, p , 2004 [28] M. R. Abdullah, A. A. A. Azis, and I. A. Rahman, Potential effects on large MARA projects due to construction delay, International journal of Integrated Engineering (Issue on Civil and Environmental Engineering) 2009, 1(2): 53-62, 2009 [29] M. Sambasivan, Y. W. Soon, "Causes and effects of delays in Malaysian construction industry", International Journal of Project Management, 25, p , 2007 [30] I. A. Majid Causes and Effects of delays in ACEH Construction Industry, Thesis of MSc in construction management, Faculty of Civil Engineering, University Technology Malaysia,

THE CAUSE FACTORS OF LARGE PROJECT S COST OVERRUN: A SURVEY IN THE SOUTHERN PART OF PENINSULAR MALAYSIA

THE CAUSE FACTORS OF LARGE PROJECT S COST OVERRUN: A SURVEY IN THE SOUTHERN PART OF PENINSULAR MALAYSIA International Journal of Real Estate Studies, Volume 7, Number 2 2012 THE CAUSE FACTORS OF LARGE PROJECT S COST OVERRUN: A SURVEY IN THE SOUTHERN PART OF PENINSULAR MALAYSIA Aftab Hameed Memon 1, Ismail

More information

DELAY IN LARGE MARA CONSTRUCTION PROJECTS BASED ON PROJECT MANAGEMENT CONSULTANT PERSPECTIVE.

DELAY IN LARGE MARA CONSTRUCTION PROJECTS BASED ON PROJECT MANAGEMENT CONSULTANT PERSPECTIVE. Proceedings of MUCEET2009 Malaysian Technical Universities Conference on Engineering and Technology June 20-22, 2009, MS Garden,Kuantan, Pahang, Malaysia MUCEET2009 DELAY IN LARGE MARA CONSTRUCTION PROJECTS

More information

Time and Cost Performance of Costruction Projects in Southern and Cenrtal Regions of Penisular Malaysia

Time and Cost Performance of Costruction Projects in Southern and Cenrtal Regions of Penisular Malaysia Time and Cost Performance of Costruction Projects in Southern and Cenrtal Regions of Penisular Malaysia Ismail Abdul Rahman, Aftab Hameed Memon, Sasitharan Nagapan, Qadir Bux Alias Imran Latif Faculty

More information

Preliminary Study on Causative Factors Leading to Construction Cost Overrun

Preliminary Study on Causative Factors Leading to Construction Cost Overrun Preliminary Study on Causative Factors Leading to Construction Cost Overrun Aftab Hameed Memon *1, Ismail Abdul Rahman 2, Ade Asmi Abdul Azis 3 1,2,3 Faculty of Civil and Environmental Engineering Universiti

More information

Significant Factors Causing Cost Overruns in Large Construction Projects in Malaysia

Significant Factors Causing Cost Overruns in Large Construction Projects in Malaysia Journal of Applied Sciences 13 (2): 286-293, 201 3 ISSN 1812-5654 / DOI: 10.3923ljas.2013.286.293 O 201 3 Asian Network for Scientific Information Significant Factors Causing Cost Overruns in Large Construction

More information

Schedule Delay in Saudi Arabia Road Construction Projects: Size, Estimate, Determinants and Effects

Schedule Delay in Saudi Arabia Road Construction Projects: Size, Estimate, Determinants and Effects International Journal of Architecture, Engineering and Construction Vol 6, No 3, September 2017, 51-58 Schedule Delay in Saudi Arabia Road Construction : Size, Estimate, Determinants and Effects Ibrahim

More information

Investigation of Significant Factors Influencing Time and Cost Overruns in Indian Construction Projects

Investigation of Significant Factors Influencing Time and Cost Overruns in Indian Construction Projects Investigation of Significant Factors Influencing Time and Cost Overruns in Indian Construction Projects S. Shanmugapriya 1, Dr. K. Subramanian 2 1 Assistant Professor, 2 Professor and Head, Department

More information

Construction Experts Perception on the Causes and Effects of Cost Overruns in Johannesburg, Gauteng Province, South Africa

Construction Experts Perception on the Causes and Effects of Cost Overruns in Johannesburg, Gauteng Province, South Africa Construction Experts Perception on the Causes and Effects of Cost Overruns in Johannesburg, Gauteng Province, South Africa Abstract Mukuka MJ 1, Clinton Aigbavboa 2, and Wellington Thwala 3 The construction

More information

Time and Cost Perfomance in Costruction Projects in Southern and Cenrtal Regions of Penisular Malaysia

Time and Cost Perfomance in Costruction Projects in Southern and Cenrtal Regions of Penisular Malaysia International Journal of Advances in Applied Sciences (IJAAS) Vol.1, No.1, March 2012, pp. 45~52 ISSN: 2252-8814 45 Time and Cost Perfomance in Costruction Projects in Southern and Cenrtal Regions of Penisular

More information

Significant Factors Causing Time Overrun in Construction Projects of Peninsular Malaysia

Significant Factors Causing Time Overrun in Construction Projects of Peninsular Malaysia Modern Applied Science; Vol. 8, No. 4; 2014 ISSN 1913-1844 E-ISSN 1913-1852 Published by Canadian Center of Science and Education Significant Factors Causing Time Overrun in Construction Projects of Peninsular

More information

AFRICAN JOURNAL OF APPLIED RESEARCH (AJAR) Vol.1, No.1 ISSN January 2015

AFRICAN JOURNAL OF APPLIED RESEARCH (AJAR)   Vol.1, No.1 ISSN January 2015 DELAY AND ITS EFFECT ON THE DELIVERY OF CONSTRUCTION PROJECTS IN GHANA Addo J.N.T. Department of Building Technology, Cape Coast Polytechnic, Cape Coast- Ghana ABSTRACT It is common knowledge that our

More information

CONTRACTOR PERSPECTIVE ON TIME OVERRUN FACTORS IN MALAYSIAN CONSTRUCTION PROJECTS

CONTRACTOR PERSPECTIVE ON TIME OVERRUN FACTORS IN MALAYSIAN CONSTRUCTION PROJECTS International Journal of Science, Environment and Technology, Vol. 3, No 3, 2014, 1184 1192 ISSN 2278-3687 (O) CONTRACTOR PERSPECTIVE ON TIME OVERRUN FACTORS IN MALAYSIAN CONSTRUCTION PROJECTS Aftab Hameed

More information

Ranking of Delay Factors for Makkah s Construction Industry

Ranking of Delay Factors for Makkah s Construction Industry Ranking of Delay Factors for Makkah s Construction Industry Nashwan Al-Emad 1,*, Ismail Abdul Rahman 2, Sasitharan Nagapan 1, and Yaser Gamil 1 1 Faculty of Civil and Environmental Engineering, Universiti

More information

CAUSAL ATTRIBUTES OF COST OVERRUN IN CONSTRUCTION PROJECTS OF PAKISTAN

CAUSAL ATTRIBUTES OF COST OVERRUN IN CONSTRUCTION PROJECTS OF PAKISTAN International Journal of Civil Engineering and Technology (IJCIET) Volume 8, Issue 6, June 2017, pp. 477 483, Article ID: IJCIET_08_06_052 Available online at http://www.iaeme.com/ijciet/issues.asp?jtype=ijciet&vtype=8&itype=6

More information

Contributions of Construction Project Team to Cost Overruns: The Contractors Perspective. Nigeria; PH (234) ;

Contributions of Construction Project Team to Cost Overruns: The Contractors Perspective. Nigeria; PH (234) ; 1528 Contributions of Construction Project Team to Cost Overruns: The Contractors Perspective Olusegun AKINSIKU 1, Adeyemi AKINTOLA 1, Oko AMEH 1 and Ayokunle IGE 1 1 Department of Building, Faculty of

More information

Study of Factors Causing Time and Cost Overrun throughout Life Cycle of Construction Project

Study of Factors Causing Time and Cost Overrun throughout Life Cycle of Construction Project Proceedings of Malaysian Technical Universities Conference on Engineering & Technology (MUCET) 3-4 December 2013, Kuantan, Pahang Study of Factors Causing Time and Cost Overrun throughout Life Cycle of

More information

Critical Determinants of Public Construction Tendering Costs

Critical Determinants of Public Construction Tendering Costs International Journal of Architecture, Engineering and Construction Vol 7, No 1, March 2018, 34-42 Critical Determinants of Public Construction Tendering Costs Ibrahim Mahamid Department of Civil Engineering,

More information

Enhancing the Quality of Construction Environment by Minimizing the Cost Variance

Enhancing the Quality of Construction Environment by Minimizing the Cost Variance Available online at www.sciencedirect.com ScienceDirect Procedia - Social and Behavioral Sciences 153 ( 2014 ) 70 78 AicQoL2014Kota Kinabalu AMER International Conference on Quality of Life The Pacific

More information

CAUSE OF DELAY IN CONSTRUCTION PROJECTS IN

CAUSE OF DELAY IN CONSTRUCTION PROJECTS IN International Journal of Civil Engineeringg and Technology (IJCIET) Volume 8, Issue 7, July 2017, pp. 30 36, Article ID: IJCIET_08_07_004 Available online at http://www.ia aeme.com/ijc CIET/issues.a asp?jtype=ijciet&vtyp

More information

EVALUATION OF CONSTRUCTION COST AND TIME ATTRIBUTES

EVALUATION OF CONSTRUCTION COST AND TIME ATTRIBUTES EVALUATION OF CONSTRUCTION COST AND TIME ATTRIBUTES T.M.S. Elhag and A.H. Boussabaine School of Architecture and Building Engineering, The University of Liverpool, Liverpool L69 3BX, UK Understanding the

More information

Analysis of Cost Overrun Factors for Small Scale Construction Projects in Malaysia Using PLS-SEM Method

Analysis of Cost Overrun Factors for Small Scale Construction Projects in Malaysia Using PLS-SEM Method Modern Applied Science; Vol. 7, No. 8; 2013 ISSN 1913-1844 E-ISSN 1913-1852 Published by Canadian Center of Science and Education Analysis of Cost Overrun Factors for Small Scale Construction Projects

More information

International Journal of Advance Engineering and Research Development

International Journal of Advance Engineering and Research Development Scientific Journal of Impact Factor (SJIF): 5.71 International Journal of Advance Engineering and Research Development Volume 5, Issue 04, April -2018 e-issn (O): 2348-4470 p-issn (P): 2348-6406 A COMPARATIVE

More information

CAUSES OF DELAYS IN CONSTRUCTION PROJECTS IN TURKEY

CAUSES OF DELAYS IN CONSTRUCTION PROJECTS IN TURKEY JOURNAL OF CIVIL ENGINEERING AND MANAGEMENT ISSN 1392-3730 print/issn 1822-3605 online 2012 Volume 18(3): 426 435 doi:10.3846/13923730.2012.698913 CAUSES OF DELAYS IN CONSTRUCTION PROJECTS IN TURKEY Aynur

More information

Factors Affecting Construction Cost in the Pakistani Construction Industry

Factors Affecting Construction Cost in the Pakistani Construction Industry Third International Conference on Construction in Developing Countries (ICCIDC III) Advancing Civil, Architectural and Construction Engineering & Management July 4-6, 2012, Bangkok, Thailand Factors Affecting

More information

Study and Assessment of Causes and Effects of Delay in Large Public Construction Projects in Jordan

Study and Assessment of Causes and Effects of Delay in Large Public Construction Projects in Jordan Study and Assessment of Causes and Effects of Delay in Large Public Construction Projects in Jordan Ghanim A. Bekr Associate Professor, Civil Engineering Dept., Zarqa University, Jordan. Abstract In Jordan,

More information

Study of Delay Factors in Construction Projects

Study of Delay Factors in Construction Projects Study of Delay Factors in Construction Projects Shabbab Al Hammadi 1, M. Sadique Nawab 2 Assistant Professor, Civil Engineering Department, Shaqra University, Al Dawadmi, KSA 1 Lecturer, Civil Engineering

More information

Assessment of Factors Causing Delay on Building Construction Projects in Enugu, Nigeria

Assessment of Factors Causing Delay on Building Construction Projects in Enugu, Nigeria Assessment of Factors Causing Delay on Building Construction Projects in Enugu, Nigeria Agu. N. N1 and Ibe, B. O. Department of Quantity Survey, Nnamdi, Azikiwe University, Awka, Anambra State, Nigeria

More information

JFMPC 14,2. Jomah Al-Najjar Islamic University of Gaza, Gaza Strip, Palestinian Authority, and

JFMPC 14,2. Jomah Al-Najjar Islamic University of Gaza, Gaza Strip, Palestinian Authority, and The current issue and full text archive of this journal is available at www.emeraldinsight.com/1366-4387.htm JFMPC 14,2 126 Delays and cost overruns in the construction projects in the Gaza Strip Adnan

More information

Understanding construction projects schedule overruns in South Africa

Understanding construction projects schedule overruns in South Africa Understanding construction projects schedule overruns in South Africa Mulenga MUKUKA 1, Clinton AIGBAVBOA 2 and Wellington THWALA 3 1 MTECH, Department of Construction Management and Quantity Surveying,

More information

Analysis of Improper Material Management Affecting Cost in Construction Projects

Analysis of Improper Material Management Affecting Cost in Construction Projects Analysis of Improper Material Management Affecting Cost in Construction Projects P.Lenin *, L.Krishnaraj *, D.Narendra Prasad *, V.R Prasath Kumar *, Assistant Professor, Civil Engineering Department,

More information

Major Mitigation Measures for Delays in Construction Projects

Major Mitigation Measures for Delays in Construction Projects 1Major Mitigation Measures Major Mitigation Measures for Delays in Construction Projects Mohammad Abedi, PhD Candidate, Department of Civil Engineering, RAZAK School of Engineering & Advanced Technology,

More information

Investigation of Factors Influencing Cost Overrun in High-Rise Building Constructions

Investigation of Factors Influencing Cost Overrun in High-Rise Building Constructions Investigation of Factors Influencing Cost Overrun in High-Rise Building Constructions Prof. Yogini K. Patil Professor, G. C.O.E.Jalgaon, Maharashtra, India. Prof. Pankaj P. Bhangale Head of Civil Dept,

More information

IDENTIFYING KEY RISKS IN BUILDING PERFORMANCE

IDENTIFYING KEY RISKS IN BUILDING PERFORMANCE IDENTIFYING KEY RISKS IN BUILDING PERFORMANCE Chen Jia Woon, Azlan Shah Ali and Faizul Ali Mohd Rahim Faculty of Built Environment, University of Malaya, 50603 Kuala Lumpur Correspondence: jiawoon_chen@ymail.com

More information

CONSTRUCTION PROFESSIONALS PERCEPTION ON THE CAUSES AND EFFECTS OF PROJECT DELAY IN LUSAKA, ZAMBIA

CONSTRUCTION PROFESSIONALS PERCEPTION ON THE CAUSES AND EFFECTS OF PROJECT DELAY IN LUSAKA, ZAMBIA CONSTRUCTION PROFESSIONALS PERCEPTION ON THE CAUSES AND EFFECTS OF PROJECT DELAY IN LUSAKA, ZAMBIA MJ Mukuka 1, CO Aigbavboa 2, and WD Thwala 3 Department of Construction Management & Quantity Surveying,

More information

Causes and Effects of Construction Project Delays in Nigerian Construction Industry

Causes and Effects of Construction Project Delays in Nigerian Construction Industry IJISET - International Journal of Innovative Science, Engineering & Technology, Vol. 3 Issue 5, May 016. ISSN 348 7968 Causes and Effects of Construction Project Delays in Nigerian Construction Industry

More information

Impact of Cost and Time Overrun on Building Construction Projects

Impact of Cost and Time Overrun on Building Construction Projects Impact of Cost and Time Overrun on Building Construction Projects Santosh Kumar Prajapati, 1 Rakesh Gupta, 2 Dr.Mukesh Pandey, 3 B.Tech+M.tech (INT) P.G student, Construction technology & Management, I.T.M

More information

Prediction of Construction Cost Overrun in Tamil Nadu- A Statistical Fuzzy Approach

Prediction of Construction Cost Overrun in Tamil Nadu- A Statistical Fuzzy Approach International Journal of Engineering and Technical Research (IJETR) Prediction of Construction Cost Overrun in Tamil Nadu- A Statistical Fuzzy Approach Shreenaath.A., Arunmozhi.S., Sivagamasundari.R Abstract

More information

Assessment of Extension of Time Claims in Hydropower Projects of Pakistan

Assessment of Extension of Time Claims in Hydropower Projects of Pakistan International Journal of Engineering and Advanced Technology (IJEAT) Assessment of Extension of Time Claims in Hydropower Projects of Pakistan Hashim Hanif, Yasar Saleem, Zuhaib Aslam Shahid, Abdullah

More information

Construction Waste Generation Factors throughout Construction Life Cycle Case study of Peninsular Malaysia

Construction Waste Generation Factors throughout Construction Life Cycle Case study of Peninsular Malaysia AENSI Journals Australian Journal of Basic and Applied Sciences ISSN:1991-8178 Journal home page: www.ajbasweb.com Construction Waste Generation Factors throughout Construction Life Cycle Case study of

More information

Qualitative Approach on Investigating Failure Factors of Yemeni Mega Construction Projects

Qualitative Approach on Investigating Failure Factors of Yemeni Mega Construction Projects Qualitative Approach on Investigating Failure Factors of Yemeni Mega Construction Projects Yaser Gamil 1,*, Ismail Abdul Rahman 1, Sasitharan Nagapan 1, and Nashwan Alemad 1 1 Faculty of Civil and Environmental

More information

Critical Factors Influencing Construction Productivity in Thailand

Critical Factors Influencing Construction Productivity in Thailand Critical Factors Influencing Construction Productivity in Thailand Arun Makulsawatudom,* Margaret Emsley* and Kuldej Sinthawanarong** Abstract Factors affecting construction in Thailand were disclosed

More information

Analysis Of Critical Causes Of Delays In Indian Infrastructure Projects

Analysis Of Critical Causes Of Delays In Indian Infrastructure Projects ISSN: 2278 0211 (Online) Analysis Of Causes Of Delays In Indian Infrastructure Projects Prof: Siddesh K Pai DME, DBM, BE Mech, PGP PEM,MIM Assistant professor, National Institute of construction Management

More information

The Problem of Quality of Electrical Work in Malaysian Construction Projects

The Problem of Quality of Electrical Work in Malaysian Construction Projects Pertanika J. Soc. Sci. & Hum. 25 (S): 105-110 (2017) SOCIAL SCIENCES & HUMANITIES Journal homepage: http://www.pertanika.upm.edu.my/ The Problem of Quality of Electrical Work in Malaysian Construction

More information

Analysis and Identification of Critical Factors of Delay in Construction Projects

Analysis and Identification of Critical Factors of Delay in Construction Projects Analysis and Identification of Critical Factors of Delay in Construction Projects 83 Analysis and Identification of Critical Factors of Delay in Construction Projects M.P.Venkatesh*, C.Umarani**, S. M.

More information

Examining factors affecting budget overrun of construction projects undertaken through management procurement method using PLS-SEM approach

Examining factors affecting budget overrun of construction projects undertaken through management procurement method using PLS-SEM approach Available online at www.sciencedirect.com ScienceDirect Procedia - Social and Behavioral Sciences 107 ( 2013 ) 120 128 ELPIIC 2013 Evaluation of Learning for Performance Improvement International Conference,

More information

Construction Projects Cost Overrun: What Does the Literature Tell Us?

Construction Projects Cost Overrun: What Does the Literature Tell Us? International Journal of Innovation, Management and Technology, Vol., No., April 0 Construction Projects Cost Overrun: What Does the Literature Tell Us? Abdulelah Aljohani, Dominic Ahiaga-Dagbui, and David

More information

CHAPTER 2 DEVELOPMENT AND ORGANIZATION OF PROJECTS

CHAPTER 2 DEVELOPMENT AND ORGANIZATION OF PROJECTS CHAPTER 2 DEVELOPMENT AND ORGANIZATION OF PROJECTS 1) THE LIFE CYCLE OF A CONSTR. PROJECT: 1.1:CONCEPT AND FEASIBILITY STUDIES: THE START Recognition of a need for a new facility conceptual analyses Technical

More information

45. Feedlot construction delivery

45. Feedlot construction delivery Client Des i gn/ Builder Design Consultant Construction Sub-contractors and suppliers FEEDLOT DESIGN AND CONSTRUCTION 45. Feedlot construction delivery AUTHORS: Rod Davis and Ross Stafford Introduction

More information

INVESTIGATING THE CAUSES OF DELAY WITHIN OIL AND GAS PROJECTS IN THE U.A.E.

INVESTIGATING THE CAUSES OF DELAY WITHIN OIL AND GAS PROJECTS IN THE U.A.E. INVESTIGATING THE CAUSES OF DELAY WITHIN OIL AND GAS PROJECTS IN THE U.A.E. Mohamed Salama 1, Moustafa Abd El Hamid and Bill Keogh School of Management and Languages, Heriot-Watt University, Riccarton,

More information

A Brief Study on Residential Construction Projects from View of Delay Causes Ranking

A Brief Study on Residential Construction Projects from View of Delay Causes Ranking International Journal of Humanities and Management Sciences (IJHMS) Volume 4, Issue 4 () ISSN 44 (Online) A Brief Study on Residential Construction Projects from View of Delay Causes ing Siamak Hajiyakhchali,

More information

Causes of Cost Overruns of Municipal Infrastructure Grant Funded Projects at the OR Tambo District Municipality

Causes of Cost Overruns of Municipal Infrastructure Grant Funded Projects at the OR Tambo District Municipality Causes of Cost Overruns of Municipal Infrastructure Grant Funded Projects at the OR Tambo District Municipality Emmanuel Mulenga & Michiel C Bekker University of Pretoria Abstract -, Introduction Journal

More information

CHAPTER 1 INTRODUCTION

CHAPTER 1 INTRODUCTION 1 CHAPTER 1 INTRODUCTION 1.1 BACKGROUND In India, Construction Industry plays a key role in both economic growth and poverty reduction. The industry consumes about 40 to 50% of the national five year plan

More information

Incentive Based Compensation for Public Sector Construction Projects in India

Incentive Based Compensation for Public Sector Construction Projects in India Incentive Based Compensation for Public Sector Construction Projects in India A. Rushi Nandan M.Tech (Construction Management) student, Department of Civil Engineering, Visvesvaraya National Institute

More information

Causes and Effects of Delays in Construction of Medium Scale Drinking Water Supply Projects in Sri Lanka

Causes and Effects of Delays in Construction of Medium Scale Drinking Water Supply Projects in Sri Lanka Annual Transactions of IESL, pp. [ 151-159], 2012 The Institution of Engineers, Sri Lanka Causes and Effects of Delays in Construction of Medium Scale Drinking Water Supply Projects in Sri Lanka W.D.A.

More information

ALTERNATIVE CONTRACTING METHODS

ALTERNATIVE CONTRACTING METHODS ALTERNATIVE CONTRACTING METHODS Conventional Design-Bid-Build Design/Build Negotiated General Contractor By Jeff Warner, AIA, LEED AP Principal, ALSC Architects CONVENTIONAL DESIGN-BID-BUILD The most traditional

More information

Controlling Of Variation Orders in Highway Projects in Jordan

Controlling Of Variation Orders in Highway Projects in Jordan Journal of Engineering and Architecture December 15, Vol.,., pp. 95-1 ISSN: -98 (Print), -99 (Online) Copyright The Author(s). All Rights Reserved. Published by American Research Institute for Policy Development

More information

Subcontractor's Selection Practice in the Gaza Strip

Subcontractor's Selection Practice in the Gaza Strip Subcontractor's Selection Practice in the Gaza Strip Adnan Enshassi School of Civil Engineering, IUG, Palestine aenshassi@gmail.com Younis Shoman Ministry of Public Works and Housing, Palestine Abstract

More information

Evaluation of the Factors Influencing Time and Cost. Tower Construction in Ghana

Evaluation of the Factors Influencing Time and Cost. Tower Construction in Ghana Evaluation of the Factors Influencing Time and Cost Overruns in Telecom Tower Construction in Ghana Humphrey Danso 1*, John Kobina Antwi 2 1. Design and Technology Education Department, University of Education,

More information

Study on Change Order Impact on Project Lifecycle

Study on Change Order Impact on Project Lifecycle Study on Change Order Impact on Project Lifecycle R. Karthick P.G student, Department of Civil Engineering, CEG Anna University, Chennai, Balasubramanian Malathi Research Scholar, Department of Civil Engineering,

More information

ASIAN JOURNAL OF MANAGEMENT RESEARCH Online Open Access publishing platform for Management Research

ASIAN JOURNAL OF MANAGEMENT RESEARCH Online Open Access publishing platform for Management Research Online Open Access publishing platform for Management Research Copyright by the authors - Licensee IPA- Under Creative Commons license 3.0 Research Article ISSN 2229 3795 Stakeholders perspective on cost

More information

Design-Bid-Build Vs Design Build Projects: Performance Assessment of Commercial Projects In Sri Lanka

Design-Bid-Build Vs Design Build Projects: Performance Assessment of Commercial Projects In Sri Lanka Design-Bid-Build Vs Design Build Projects: Performance Assessment of Commercial Projects In Sri Lanka S. Ratnasabapathy and R. Rameezdeen Department of Building Economics, University of Moratuwa, Sri Lanka.

More information

VOL. 5, NO. 2, February 2015 ISSN ARPN Journal of Science and Technology All rights reserved.

VOL. 5, NO. 2, February 2015 ISSN ARPN Journal of Science and Technology All rights reserved. A Conceptual Model of Delay Factors affecting Government Construction Projects 1 Luu Truong Van, 2 Nguyen Minh Sang, 3 Nguyen Thanh Viet 1 Associate Professor, Department of Civil Engineering, International

More information

FACTORS AFFECTING RELATIONSHIP BETWEEN CONTRACTOR AND SUBCONTRACTORS

FACTORS AFFECTING RELATIONSHIP BETWEEN CONTRACTOR AND SUBCONTRACTORS International Journal of Civil Engineering and Technology (IJCIET) Volume 9, Issue 3, March 2018, pp. 126 131, Article ID: IJCIET_09_03_014 Available online at http://www.iaeme.com/ijciet/issues.asp?jtype=ijciet&vtype=9&itype=3

More information

5/21/13 PROCUREMENT 5/21/13. Agenda. Common Tendering Systems Procurement Methods

5/21/13 PROCUREMENT 5/21/13. Agenda. Common Tendering Systems Procurement Methods PROCUREMENT 5/21/13 Agenda Common Tendering Systems Procurement Methods 1 Agenda Common Tendering Systems Procurement Methods Common Tendering Systems Competitive / Open-bid: (Qualified) contractors are

More information

Investigation of Major Success Factors on Building Construction Projects Management System in Addis Ababa, Ethiopia

Investigation of Major Success Factors on Building Construction Projects Management System in Addis Ababa, Ethiopia American Journal of Civil Engineering 2017; 5(3): 155-163 http://www.sciencepublishinggroup.com/j/ajce doi: 10.11648/j.ajce.20170503.15 ISSN: 2330-8729 (Print); ISSN: 2330-8737 (Online) Investigation of

More information

AC : THE EFFECT OF SUB-CONTRACTING ON CONSTRUCTION TIME FOR COMMERCIAL PROJECTS IN CHENNAI, INDIA

AC : THE EFFECT OF SUB-CONTRACTING ON CONSTRUCTION TIME FOR COMMERCIAL PROJECTS IN CHENNAI, INDIA AC 2007-2479: THE EFFECT OF SUB-CONTRACTING ON CONSTRUCTION TIME FOR COMMERCIAL PROJECTS IN CHENNAI, INDIA I. Choudhury, Texas A&M University IFTE CHOUDHURY Ifte Choudhury is an Associate Professor in

More information

Unit 3: The Traditional Procurement Route

Unit 3: The Traditional Procurement Route Unit 3: The Traditional Procurement Route 3.1 Introduction This Unit briefly introduces the main features of the traditional procurement route as a widely used route that provides a good basis for examining

More information

International Journal of Modern Trends in Engineering and Research e-issn No.: , Date: 2-4 July, 2015

International Journal of Modern Trends in Engineering and Research   e-issn No.: , Date: 2-4 July, 2015 International Journal of Modern Trends in Engineering and Research www.ijmter.com e-issn No.:2349-9745, Date: 2-4 July, 2015 Study of Pros and Cons of Subcontracting System Adopted in Executing Indian

More information

CHAPTER 2 LITERATURE REVIEW

CHAPTER 2 LITERATURE REVIEW 10 CHAPTER 2 LITERATURE REVIEW 2.1 GENERAL One of the most important problems in the construction industry is Time overrun. Time overrun occur in every construction project and the magnitude of these delays

More information

An Assessment of Performance of Construction Projects on South Africa

An Assessment of Performance of Construction Projects on South Africa Abstract An Assessment of Performance of Construction Projects on South Africa Mandisa Sibiya 1, Clinton Aigbavboa 2 and Wellington Thwala 3 The South African construction industry, like most construction

More information

Delay in Government Project Delivery in Kedah, Malaysia

Delay in Government Project Delivery in Kedah, Malaysia Delay in Government Project Delivery in Kedah, Malaysia AZLAN OTHMAN a AND SYUHAIDA ISMAIL b a Faculty of Civil Engineering Universiti Teknologi Malaysia Johor Bahru 81310 Johor MALAYSIA irazlan@gmail.com

More information

Critical Factors behind Construction Delay in Petrochemical Projects in Saudi Arabia

Critical Factors behind Construction Delay in Petrochemical Projects in Saudi Arabia energies Article Critical Factors behind Construction Delay in Petrochemical Projects in Saudi Arabia Abdullah Rasheed Alhajri 1, * and Adel Alshibani 2 1 Construction Engineering and Management, KFUPM,

More information

Factors Influencing the Construction Cost of Industrialised Building System (IBS) Projects

Factors Influencing the Construction Cost of Industrialised Building System (IBS) Projects Available online at www.sciencedirect.com Procedia - Social and Behavioral Sciences 35 ( 2012 ) 689 696 AicE-Bs 2011 Famagusta Asia Pacific International Conference on Environment-Behaviour Studies, Salamis

More information

SEPARATED PROJECT DELIVERY SYSTEMS

SEPARATED PROJECT DELIVERY SYSTEMS SEPARATED PROJECT DELIVERY SYSTEMS Separated (aka Traditional) The traditional delivery method typically involves three sequential project phases: The design phase, which requires the services of a designer

More information

Progressive Design Build

Progressive Design Build Progressive Design Build July 19, 2018 Ash Dhingra P.E.,S.E TRADITIONAL PROCUREMENT Design-Bid-Build (DBB) Design to 100%, procurement (bid), and construction proceed sequentially Construction contract

More information

ANALYSIS OF DELAY IN EXECUTION OF CONSTRUCTION PROJECTS

ANALYSIS OF DELAY IN EXECUTION OF CONSTRUCTION PROJECTS ANALYSIS OF DELAY IN EXECUTION OF CONSTRUCTION PROJECTS P. Muralidhar 1, Rahul Kumar Jain 1, B. Srivasta 1, V. Poorna Chandra Rao 1 1 National Institute of Construction Management and Research (NICMAR),

More information

ISSN: [Mohammed* et al., 6(11): November, 2017] Impact Factor: 4.116

ISSN: [Mohammed* et al., 6(11): November, 2017] Impact Factor: 4.116 IJESRT INTERNATIONAL JOURNAL OF ENGINEERING SCIENCES & RESEARCH TECHNOLOGY FACTORS CAUSING VARIATION ORDERS IN BUILDING PROJECTS IN KHARTOUM STATE- SUDAN Eltahir Abu Elgassim Mohammed 1 *, Salma Yahia

More information

Evaluating the factors affecting Quality of Residential projects in Construction Industry

Evaluating the factors affecting Quality of Residential projects in Construction Industry Evaluating the factors affecting Quality of Residential projects in Construction Industry Ashish Mutha Sardar Patel college of Engineering, Mumbai Dr. Anil Ghadge Sardar Patel college of Engineering, Mumbai

More information

NATURE OF THE CRITICAL RISK FACTORS AFFECTING PROJECT PERFORMANCE IN INDONESIAN BUILDING CONTRACTS

NATURE OF THE CRITICAL RISK FACTORS AFFECTING PROJECT PERFORMANCE IN INDONESIAN BUILDING CONTRACTS NATURE OF THE CRITICAL RISK FACTORS AFFECTING PROJECT PERFORMANCE IN INDONESIAN BUILDING CONTRACTS I Putu Artama Wiguna and Stephen Scott 1 School of Civil Engineering and Geosciences, University of Newcastle

More information

An Assessment of Major Factors Affecting Construction, Project Cost in Nigeria

An Assessment of Major Factors Affecting Construction, Project Cost in Nigeria International Journal of Sciences: Basic and Applied Research (IJSBAR) ISSN 2307-4531 (Print & Online) http://gssrr.org/index.php?journal=journalofbasicandapplied ------------------------------------------------------------------------------------------------------

More information

ANALYSIS OF SAFETY MANAGEMENT IN CONSTRUCTION INDUSTRY USING SPSS AND RII

ANALYSIS OF SAFETY MANAGEMENT IN CONSTRUCTION INDUSTRY USING SPSS AND RII ANALYSIS OF SAFETY MANAGEMENT IN CONSTRUCTION INDUSTRY USING SPSS AND RII K. Lalithapriya 1, S. Deepalakshmi 2, TR.Arthi 3,G.Karthiga 4 1 Assistant Professor. Civil Engg. Mookambigai college of Engineering,Trichy,

More information

The Effect of Winner s Curse on Post-Contract Management

The Effect of Winner s Curse on Post-Contract Management The Effect of Winner s Curse on Post-Contract Management Himal Suranga Jayasena, Faculty of Architecture, University of Moratuwa, Sri Lanka (email: suranga@becon.mrt.ac.lk) Ruwandika Uhanowitage, State

More information

Identification of the Causes of Construction Delay in Malaysia

Identification of the Causes of Construction Delay in Malaysia Identification of the Causes of Construction Delay in Malaysia N. Hamzah, M.A. Khoiry, I. Arshad, W.H.W. Badaruzzaman, and N. M. Tawil International Science Index, Civil and Environmental Engineering Vol:6,

More information

Factors Constraining Labour Productivity: Case Study of Turkmenistan

Factors Constraining Labour Productivity: Case Study of Turkmenistan DOI: 10.7763/IPEDR. 2012. V55. 1 Factors Constraining Labour Productivity: Case Study of Turkmenistan Serdar Durdyev 1, Syuhaida Ismail 11 and Nooh Abu Bakar 1 1 Razak School of Engineering and Advanced

More information

Exploring the Opportunities of Design and Build Contracts for the Construction Projects in Pakistan.

Exploring the Opportunities of Design and Build Contracts for the Construction Projects in Pakistan. Sixth International Conference on Construction in the 21 st Century (CITC-VI) Construction Challenges in the New Decade July 5-7 2011, Kuala Lumpur, Malaysia Exploring the Opportunities of Design and Build

More information

EVALUATION AND MANAGEMENT OF CONSTRUCTION MATERIAL AND TIME WASTE BY PARETO ANALYSIS METHOD

EVALUATION AND MANAGEMENT OF CONSTRUCTION MATERIAL AND TIME WASTE BY PARETO ANALYSIS METHOD EVALUATION AND MANAGEMENT OF CONSTRUCTION MATERIAL AND TIME WASTE BY PARETO ANALYSIS METHOD V.Rajeshkumar 1, P.Indhiradevi 2, D.Karthik 3 1 Assistant Professor, Department of Civil Engineering, KPR Institute

More information

CONSTRUCTION DELAY FACTORS IN GENERAL AND ESPECIALLY IN DEVELOPED COUNTRIES

CONSTRUCTION DELAY FACTORS IN GENERAL AND ESPECIALLY IN DEVELOPED COUNTRIES Int. J. Struct. & Civil Engg. Res. 2014 Basim Khadier Khadim and Pramila Adavi, 2014 Research Paper ISSN 2319 6009 www.ijscer.com Vol. 3, No. 4, November 2014 2014 IJSCER. All Rights Reserved CONSTRUCTION

More information

Effects of Change Orders through Technical Programs on Construction Projects in Jordan

Effects of Change Orders through Technical Programs on Construction Projects in Jordan Journal of Civil Engineering and Architecture 10 (2016) 1213-1219 doi: 10.17265/1934-7359/2016.11.002 D DAVID PUBLISHING Effects of Change Orders through Technical Programs on Construction Projects in

More information

A Various Factors Affecting Labour Productivity and Method to Improve It

A Various Factors Affecting Labour Productivity and Method to Improve It A Various Factors Affecting Labour Productivity and Method to Improve It Sandeep singh Mukesh panday Abstract: - As we know India is a very developing country and there are many modern and developing cities.

More information

Perceptions of Skilled Labour Attributes on Delays in Construction Projects in India

Perceptions of Skilled Labour Attributes on Delays in Construction Projects in India Perceptions of Skilled Labour Attributes on Delays in Construction Projects in India Dillip Kumar Das Department of Civil Engineering, Central University of Technology, Free state, South Africa Email:

More information

CHAPTER 1 INTRODUCTION

CHAPTER 1 INTRODUCTION CHAPTER 1 INTRODUCTION 1.1 Background Studies Construction projects can best be understood in the context of the whole industry which is technological complexity ranges from the familiar, well known materials

More information

TIME AND COST OPTIMISATION IN PROJECT EXECUTION

TIME AND COST OPTIMISATION IN PROJECT EXECUTION TIME AND COST OPTIMISATION IN PROJECT EXECUTION Shamsul Haque Hamidullah, Chitranjan kumar (assistant professor ) M. Tech (construction technology & management), Civil Engineering, Al-Falah University,

More information

This document describes how Austin implements projects using The Austin Method. Step 1 Preliminary Design and Engineering

This document describes how Austin implements projects using The Austin Method. Step 1 Preliminary Design and Engineering The Austin Company offers multiple approaches in implementing a project. These generally can be classified into either a design-bid-construct or design-build project approach. In addition, Austin offers

More information

CAUSES OF THE TIME DELAY IN CONSTRUCTION HOUSING PROJECTS IN GWALIOR DIVISION

CAUSES OF THE TIME DELAY IN CONSTRUCTION HOUSING PROJECTS IN GWALIOR DIVISION CAUSES OF THE TIME DELAY IN CONSTRUCTION HOUSING PROJECTS IN GWALIOR DIVISION Pawan Hari 1, Dr. Mukesh Pandey 2 1M.Tech. Student, Civil Engineering Department, ITM University, Gwalior 2Professor and Head

More information

Effects of construction projects schedule overruns: A case of the Gauteng Province, South Africa

Effects of construction projects schedule overruns: A case of the Gauteng Province, South Africa Available online at www.sciencedirect.com ScienceDirect Procedia Manufacturing 00 (2015) 000 000 www.elsevier.com/locate/procedia 6th International Conference on Applied Human Factors and Ergonomics (AHFE

More information

A COMMON PROCESS FOR SELECTING A CONSTRUCTION-PROJECT DELIVERY SYSTEM

A COMMON PROCESS FOR SELECTING A CONSTRUCTION-PROJECT DELIVERY SYSTEM A COMMON PROCESS FOR SELECTING A CONSTRUCTION-PROJECT DELIVERY SYSTEM Anat Chantemduang School of Civil Engineering, Faculty of Engineering, King Mongkut s Institute of Technology Ladkrabang, Bangkok,

More information

Effect of Scheduling towards increase agricultural production in Libya.

Effect of Scheduling towards increase agricultural production in Libya. International Refereed Journal of Engineering and Science (IRJES) ISSN (Online) 2319-183X, (Print) 2319-1821 Volume 1, Issue 1 (September 2012), 65-70 Effect of Scheduling towards increase agricultural

More information

ANALYSIS OF THE RELATIONSHIPS BETWEEN CAUSES OF DELAY IN CONSTRUCTION PROJECTS IN BANGLADESH

ANALYSIS OF THE RELATIONSHIPS BETWEEN CAUSES OF DELAY IN CONSTRUCTION PROJECTS IN BANGLADESH ANALYSIS OF THE RELATIONSHIPS BETWEEN CAUSES OF DELAY IN CONSTRUCTION PROJECTS IN BANGLADESH M. A. Salam 1, H. J. Staines 2, D. J. Blackwood 1 and S. Sarkar 1 1 School of Science and Engineering, and 2

More information

Gaji Abubakar Usman* & Rosli Bin Mohamad Zin

Gaji Abubakar Usman* & Rosli Bin Mohamad Zin Malaysian Journal of Civil Engineering 29(1):42-58(2017) CRITICAL FACTORS AFFECTING QUALITY IN PUBLIC CONSTRUCTION PROJECTS IN BORNO STATE Gaji Abubakar Usman* & Rosli Bin Mohamad Zin Faculty of Civil

More information

Step 1 Preliminary Design and Engineering

Step 1 Preliminary Design and Engineering The Austin Company offers a variety of approaches in implementing a project. These generally can be classified into either a design-bid-construct or design-build project approach. In addition, Austin offers

More information