Delay in Government Project Delivery in Kedah, Malaysia

Size: px
Start display at page:

Download "Delay in Government Project Delivery in Kedah, Malaysia"

Transcription

1 Delay in Government Project Delivery in Kedah, Malaysia AZLAN OTHMAN a AND SYUHAIDA ISMAIL b a Faculty of Civil Engineering Universiti Teknologi Malaysia Johor Bahru Johor MALAYSIA irazlan@gmail.com b Razak School of Engineering and Advanced Technology Universiti Teknologi Malaysia Kuala Lumpur Kuala Lumpur MALAYSIA syuhaida_ismail@yahoo.com Abstract: In construction industry, delays have become a norm and global phenomenon which led to many negative effects of lawsuits, claims, loss of productivity and revenue and also contract termination between all parties involved, and Malaysia is of no exception. All of these factors retard the development of construction industry, where in Malaysia, only 46.8 percent of the public sector projects completed within the budget whilst 70.3 percent of government s contract were delayed or abandoned for more than three months. Hence, this paper aims at appraising the delay factor of Government project delivery in Kedah, Malaysia through its objectives of identifying of the main causes of construction delay, determining the impact of delay factors in the construction project and ranking the delay factors in government project delivery. A structured questionnaire was distributed to various respondents from within the Kedah State, which include the contractors, clients and consultants. Findings from this study revealed that the most contributing factors and categories to delays were delays in sub contractor s works, ineffective planning and scheduling, delay in approval shop drawing and sample materials and difficulties in financing project. This serves as a guide to the relevant parties to mitigate and alleviate the delay in construction project particularly in government projects in the State of Kedah, Malaysia. KeyWords: Delay, government project, project delivery, Kedah, Malaysia 1 Introduction In today s world of globalization, the construction industry plays an important and integral role to enhance the nation s competitiveness. Malaysian Government has moved forward under the 10 th Malaysia Plan ( ), which has been formulated with various new approaches towards becoming a high income and high productivity economy, in line with the New Economic Model. 52 highimpact projects worth of RM63 billion has been identified for the implementation. To effectively deliver these projects, the government has recognized the need to improve their capacity and competency [1]. In a construction project, completion on time is extremely important because time is essential and time is money. Although timely completion is seen as one of the important criteria of the project success, late completion is a common problem in construction projects not only in Malaysia but worldwide as reported by [2], [3] and [4]. An example of project delayed in Malaysia as reported by [5] is the Bakun hydro project that experienced a huge delay in completing civil works, which in turn caused delays to the implementation of the electromechanical works. According to [6], an audit ISBN: reveals that the performance of activities undertaken in relation to the Bakun project were not satisfactory as there was delay in four major packages. The contractor concerned was allowed one to three extension of time ranging from 555 to 1403 days. Refinery and Petrochemical Integrated Development (RAPID) was also reported delay by [7], which is supposed to start operation in 2016 but can only operate in early 2017 and many more. Delay gives rise to disruption of work and loss of productivity, late completion of project, increased time related cost, third party claims and abandonment or termination of contract [8]. In many cases, construction projects suffer from delay will cause suspension, which means stoppage of works directed to the contractor by a formal form from the client. However, delay when slowing down of work does not mean entire stop to the project. There are many causes, which must be identified in order to control delay in the early stages of the project. Delay could be a result of low performance of contractor, inadequacies or defaults in early planning and design, poor owner administration and involvement in construction, problem in supervision, restriction in government laws and regulations or obstructions at the site [9].

2 Any of these factors could cause problems in the progress of the construction project leading to delay. As Malaysia moves from developing country status towards a developed and industrialized nation as envisaged in Vision 2020, her construction industry needs to respond to the changes in construction demand. This has resulted in rapid implementation of several largescale infrastructure and building projects. However, Malaysian construction industry also faced many problems which affect this industry in terms of manpower, quality of productivity, time and payment issues especially during the closing of final accounts in the construction projects [10]. Like other developing countries, such as Saudi Arabia [11], Libya [12] and Nigeria [13] construction industry has suffered many setback in terms of completion of the project at stipulated period within the predetermined sum. [14] find out that only 46.8 percent and 37.2 percent of public sector and private sector projects out of 259 projects in Malaysia were completed within the budget respectively with an average cost deviation of 2.08 percent. It is also revealed that 90 percent of MARA large construction project experienced delay since 1984 due to time and cost overrun [15]. [16] also report that in 2005, about 70.3 percent of 417 government s contract in Malaysia were delayed or abandoned for more than three months. Since majority of the construction projects in Malaysia experienced time and cost overrun, which in turn lead to the abandonment of project, the delay would definitely jeopardize the government s agenda or policies in setting up their vision to develop projects for the public interest and also retard the national progress with regards to investment. The state of Kedah is not exceptional from the construction delay. Based on SKALA JKR Kubang Pasu Kedah, the Proposed Technical Laboratory for Politeknik Sultan Abdul Halim Mua adzam Shah Jitra, has been delayed for four months. Its original completion was in July 2010, whereas the project only completed in November Another project, under Kementerian Kesihatan Malaysia (KK3) at Tunjang Kedah, was also delay by 9 months [17]. Several crucial questions that have been addressed to understand these phenomena are: what are the main causes of the delay and what are the impacts and consequences that affect the relevant parties especially the users? Hence, in this study, there is a need to identify the causes of actual delay, the frequency and extent of delay in the government project and also ranking the delay factors to mitigate the problems and delays from recurring in construction projects. This will eventually assist various parties involved in the construction industry to determine the severity of delay, improve their involvement in the construction phase while avoiding the cause of delay. It is also important to ISBN: identify the most crucial delay factors that need to be addressed especially in the government project delivery. These challenges are the motivating factor in this study because completion on time of construction projects is in the interest of all construction parties involved including the public. Hence, this paper aims to appraise the delay factor of Government construction project delivery in Kedah. To achieve the aim of this paper, the objectives identified are (1) To identify the main causes of construction delay in Kedah; (2) To determine the impact of delay factors in the construction project; (3) To rank the delay factors in government project delivery. 2 Causes of Delay in Construction Project According to [18], delay has been acknowledged as one of the most common, costly, complex and risky problems. Many studies have been conducted to identify and overcome the causes of delay in construction projects both locally and internationally. [11] identify 56 causes of scheduled delay that existed in Saudi Arabia construction projects, where the most important causes of delay were approval of shop drawings, delays in payment to contractors and the resulting cash problems, design changes, conflict in works schedules of subcontractors, slow decision making and executive bureaucracy in owner s organizations, design errors, labour shortage and inadequate skill. A decade later, the delay causes have increased to 73 [19]. The delay factors were grouped into nine major categories with different levels of importance to different parties. These groups comprise of owner/client related, consultant related, contractor related, project related, design team related, material related, labour related, external related and plant/equipment related delay factors. The results from the survey indicated 76 percent from the contractor and 56 percent from the consultant contributed between 10 percent and 30 percent from the original duration. The survey also found that 45 out of 76 projects are considered delay. The main causes of delays related by the owners are slowness in decisionmaking, delay in progress payments, late in reviewing and approving and change orders. Causes of delay related to consultants are mistakes and discrepancies in design, inflexibility (rigidity) of consultants and late reviewing and approving and delay in producing design, whereas delays contributed by contractor are late procurement of materials and difficulties in financing project. On the other hand, [10] identify and classify 60 causes of delay which occurred frequently in

3 medium and large projects and considered severe in small projects on public water and sewage projects. There are many important causes of delay related to owner involvement, contractor performance and the early planning and design of the project. The most important causes were financial problems, delay in making decision and approval by the owner, difficulties in obtaining permit of work, poor coordination and communication and changes in the design and scope. In Lebanon, [20] reveal that there are 60 causes of delay which has been grouped into 10 major groups and the cause of delay from the survey showed that project management issues, financial issues and contractual matters were the most important factors that contribute to the delay. In Jordan, a quantitative analysis on 130 public building projects has identified that the main causes of delay in construction projects were related to weather, site conditions, late deliveries, user changes, designers, economic conditions and increase in quantities [3]. Meanwhile, [21] who conduct a survey to identify the factors contributing to the delay and cost overrun in Ghana groundwater construction projects concluded 26 factors were responsible for project delays and cost overrun, which then been listed and ranked. The results of the study indicate that the main causes of delay and cost overrun includes poor contractor s management, poor technical performance, escalation of material prices, improper material procurement and difficulties in payment by the agencies. In Egypt, [22] conduct a survey to identify the causes of delay in the construction projects. The focus was from the point of view of the owners, consultants and contractors. The researchers identify 32 causes of delay, which were grouped into nine and contributed to the causes of delay in the construction industries in Egypt. These groups were financing, contractual relationships, scheduling and control, materials, equipment, manpower, changes, rules and regulations and environmental related causes. In the construction industry in Malaysia, [23] highlights the main factor for causing delay is financial followed by coordination problem. According to [16], 17.3 percent of Malaysian public sector projects in 2005 were considered sick projects with more than three months delay or been abandoned. [24] on the other hand claims that 80 percent of the government projects in Malaysia were delayed. [25] indicate that 90 percent of MARA (Malaysian Government Agency) projects exceeded scheduled of the completion dates. Table 1 shows theoretical framework on causes of delay in construction industry some of the countries in the world including Malaysia. Referring to the studies conducted by various researchers as highlighted in the problem ISBN: statements, delay is vital and problems arising from this delay should be mitigated. [26] summarize some of the survey conducted by various researchers to determine the causes of delay in construction industries, which is also regarded as a theoretical framework to be further used and improvised as a conceptual as a part of key findings of this study. However, the major causes or ranking of the delay may differ across the region. The ranking of the delay when identified will assist in alleviating or mitigating the delay factor throughout the construction process. 3 Research Methodology This paper is mainly focused on the government project delivery in Kedah. Kedah state is chosen for this paper because no study has been conducted previously and furthermore, the State Government also has the social responsibility towards the development of the nation for the interest of the public at large. This is also to accomplish the Malaysian Government s vision to achieve highincome nation in The cause of delay factors was conducted on both ongoing and completed projects because the data is easily accessible. Questionnaire surveys were designed based on the causes of construction delays, where the ranking of the delay factors are carried out based on various categories of key players in the construction industry. The categories involved in the distribution of the questionnaires are the clients, consultants (architects, quantity surveyors and engineers) and contractors because they are directly involved in the government project. This paper began with a comprehensive literature review on the construction delay phenomena. Questionnaires were designed based on the issues as highlighted in the problem statement to address the objectives of the paper. Initially, a pilot study was conducted on 15 respondents, which is 10 percent of the 150 respondents in this paper. The Cronbach Alpha results generated via pilot study to test the reliability of questionnaires were recorded between and which indicates that the questionnaire survey were appropriate and reliable for the actual survey. Subsequently, the data was analyzed via Statistical Package for Social Science (SPSS) Version 17 using Relative Importance Index (RII). A focus group with five experts in construction industry was selected to validate the data. All the experts agreed that the findings of this paper were acceptable as the delay factors of the government project delivery in Kedah. 4 Findings The findings, as illustrated in Table 1, show that the delay factors for the government project delivery in

4 Kedah are categorized into seven groups of causes, namely client/owner, consultant, contractor, manpower, material, equipment and external factors. Three important respondents, who are clients/owners, consultants and contractors, have evaluated causes of delay under those seven groups. The highest Relative Importance Index (RII) is the delay, which has been caused by sub contractor s work giving the value of This high percentage was due to the inexperienced and incompetent subcontractor to carry out the work. In addition, the top three ranking of delays was dominating by the contractor which is common in construction industry elsewhere that is due to ineffective planning and scheduling of project as well as difficulties in financing the project. Slowness in decisionmaking process and delay in progress payment caused by client/owner are also in the top list with the RII of Other causes contributing to the delay are shortage of, late procurement of material and late material delivery, escalation of material prices and delay in approving major changes in scope of work are in the top 10 list as illustrated in Table 1. Table 1. Ranking of delay factors for overall sample (n = 96) Category RII Delay in sub contractor s work Contractor Ineffective planning and scheduling of project Contractor Difficulties in financing project Contractor Shortage of Manpower Slowness in process of making decision Delay in progress payment Delay in material delivery Material Late procurement of materials Material Escalation material prices Material Delay in approving major changes in scope of work Consultant Change orders by owner Delay in site mobilization Contractor Shortage of construction materials in market Material Mistakes and discrepancies in design Consultant Changes in material types and specifications during construction Delay in manufacturing special building materials Delay in producing design Incompetent or unskilled Rework due to errors Material Material Consultant Manpower Contractor ISBN: Conflicts in subcontractors schedule in execution of project Poor coordination Delay in approving shop drawing and sample materials Effects of subsurface conditions (soil, high water table, etc) Frequent change of subcontractors Contractor External Contractor Poor coordination Contractor Shortage of equipment Equipment Poor communication and coordination Poor qualification of contractor s technical staff Contractor Low productivity level of Suspension of works Manpower Improper construction methods implementation Contractor Poor quality of construction materials Material Price fluctuation External Working permit of Manpower Delay to furnish and deliver the site Low productivity and efficiency of equipment Equipment Late in approving design Damage of sorted materials while they are needed urgently Material Equipment breakdown Equipment Unclear details in drawing Consultant Conflicts between contractors Delay in performing final inspection and certification by a third party Contractor External Inadequate details in drawing Consultant Poor communication Contractor Insufficient data collection and survey before design Consultant Inadequate contractor s work Lack of high technology mechanical equipment Low level of equipment operator skills Inadequate experience of consultant Late in revising design Slow mobilization of equipment Delay in obtaining permit of work from local council Conflicts between consultant and design Contractor Equipment Equipment Consultant Equipment External Consultant

5 engineer Conflict between consultant and owner Delay in performing Contractor Consultant inspection and testing Poor coordination Consultant Unreliable suppliers Material Poor communication Consultant Global financial crisis External Lack of experience of owner in construction projects Changes in government regulations and laws Delay in providing services from utilities (water, electricity, telecommunication) External External Delay in performing testing Consultant Accident during construction External Inadequate project management assistance Consultant Traffic control and restriction at job site External Conflicts between joint ownership Personal conflicts among Manpower Conflict, war and public enemy External Neighbours problem External Unused advanced engineering software Consultant Hot weather effect on construction activities External On the other hand, Table 2 shows the top 10 ranking causes of delay from the client s/owner, contractor and consultant s perspective. Ineffective planning and scheduling of projects are in the top list giving the RII value of followed by delay in sub contractor s work. Other factors contributing to the delay are traffic control and restriction of job site, difficulties in financing, escalation of material prices, shortage of, mistakes and discrepancies in design, poor qualification of technical staff, changes in material type and specifications and price fluctuation. The RII values are ranging from to The owners/clients dominated top three ranking from the contractor s view giving the RII of that contribute to the delay in the construction. They are delay in approving shop drawing and sample materials, change orders by owner during construction and slowness in process of making decision. The contractor also agreed that delay due sub contractor s work caused the delay to the project. Others are related to consultant, materials and which give the RII values ranging from 0.810to Survey also showed that difficulties in financing project by the contractor gave the highest value of RII that is 0.859, which records the top most rank from the consultant s view and dominates top ISBN: three from the lists causes of delay. Others contributing factors of delay are from owner/client manpower and material, giving the RII values from to Table 2. Ranking of delay factors from different categories Owner s / s perspective Category RII Ineffective planning and scheduling of project Contractor Delay in sub contractor s work Contractor Traffic control and restriction at job site External Difficulties in financing project Contractor Escalation material prices Material Shortage of Manpower Mistakes and discrepancies in design Consultant Poor qualification of contractor s technical staff Changes in material types and specifications Contractor Material Price fluctuation External Contractor s perspective Category RII Delay in approving shop drawing and sample materials Change orders by owner Slowness in process of making decision Delay in sub contractor s work Delay in producing design Mistakes and discrepancies in design Contractor Consultant Consultant Escalation material prices Material Shortage of Manpower Shortage of construction materials in market Material Delay in material delivery Material Consultant s perspective Category RII Difficulties in financing project Contractor Delay in sub contractor s work Contractor Ineffective planning and scheduling of project Contractor Shortage of Manpower Delay in progress

6 payment Slowness in process of making decision Rework due to errors Late procurement of materials Delay in site mobilization Frequent change of subcontractors Contractor Material Contractor Contractor Based on the survey results as shown in Table 1 and Table 2, there are two main common causes of delay, which has been agreed by the professional respondents, which are delay in sub contractor s work and shortage of. However, other causes of delay cannot be neglected since they are still in the top 10 causes of delay which also contribute to the delay in the construction industry. While in Table 3, the most frequent impact due to construction delay is time overrun, giving the frequency value of 32.3 percent, followed by cost overrun and dispute which occurred occasionally but still recorded a high frequency value of 31.3 percent and 32.3 percent. Arbitration, total abandonment and litigation rarely happened and gave a frequency value of 36.5 percent, 42.7 percent and 43.8 percent respectively. Table 3. Summary results of descriptive analysis on impact of construction delays Time overrun Cost overrun Dispute 9 (9.4) Arbitration Total abandonment Litigation Frequency (%) N R O S F Impact of Construction Delays (16.7) 13 (13.5) 20 (20.8) (15.6) 15 (15.6) 22 (22.9) 35 (36.5) 41 (42.7) 42 (43.8) (26.0) 30 (31.3) 31 (32.3) 29 (30.2) 23 (24.0) 20 (20.8) (32.3) 26 (27.1) 8 (8.3) 2 (2.1) 5 Conclusion This paper has successfully achieved its aim of appraising the delay factors in government project delivery in Kedah by identifying the main causes of construction delay consisting of 72 causes, determining the impact of delay factors which encompassed of six impacts and finally ranking the top 10 causes of delay factors in government project delivery. As a conclusion, the top 10 delay factors identified in Malaysian context of government project particularly with high rankings are contributed mainly from the contractor, manpower, owner/client and materials categories. With regards to the impact of delays in construction, the most frequent occurrence is due to time overrun with cost overrun and dispute (26.0) 25 (26.0) 26 (27.1) 14 (14.6) 19 (19.8) 14 (14.6) ISBN: occurring occasionally. Hence, these findings is which have been listed in the top 10 ranking is very useful and will enable relevant parties to focus and mitigate or alleviate the delay in construction project particularly in government projects in the State of Kedah, Malaysia. 6 Acknowledgement The authors would like to express their sincere gratitude to Ministry of Education Malaysia, Universiti Teknologi Malaysia (UTM) and the Research Management Centre (RMC) of UTM for providing the financial support for this paper to be published. This study is financed by the Grant for Research University (GUP) of UTM for research funding under Cost Centre No. Q.K H87. References: [1] The Star Online, (June2010) le%3d/2010/6/10/nation/ [2] Arditi, D. and Robinson, M.A. (1995) Concurrent Delays in Construction Litigation. Cost Engineering, Vol. 37(7), pp [3] Al Momani, H.A. (2000) Construction Delay: A Quantitative Analysis, International Journal of Project Management, Vol. 18, pp.519 [4] Chan, D.W., Kumaraswamy, M.M.(1996) An Evaluation of Construction Time Performance in the Building Industry in Hong Kong. Building and Environmental Journal, Vol.31, No. 6 pp [5] Shanmugam, N. (2013) agsreportrevealsstartlingclaimsfrombakuncontractors.html [6] Auditor General (2012). Definisi Projek Perumahan Terbengkalai, (n,d) Retrieved August 12,2011, from Portal Rasmi KementerianPerumahan&KerajaanTempatan:htt p:// [7] Zurairi, AR (2013), Petronas blames RAPID delay on Johor The Malaysian Insider. rticle/petronasblamerapiddelayonjohor [8] Tumi, S.A.H., H. Omran, and A.H.K. Pakir, Cause of Delay in Construction Industry in Libya, in The International Conference on Administration and Business, 2009: University of Bucharest, Romania. [9] AlGhafly, M.A. (1995) Delays in the Construction of Public Utility Projects in Saudi Arabia. Master Thesis, CEM Dept., KFUPM, Dhahran, Saudi Arabia. [10] Zarabizan Zakaria, Syuhaida Ismail and Aminah MdYusof (2012). Cause and Impact of Dispute

7 and Delay the Closing of Final Account in Malaysia Construction Industry. Journal of Southeast Asian Research. Vol. 2012(2012), Article ID , DOI: / [11] Assaf, S.A., AlKhalil, M. and AlHazmi, M. (1995) Causes of Delay in Large Building Construction Projects; Journal of Project Management in Engineering ASCE, 2; 4550 [12] Saleh A T. (2009) Causes of Delay in Construction Projects in Libya, The International Conference on Economics & Administration, Faculty of Administration and Business University of Bucharest Romania; ICEAFAA Bucharest, 1415 Nov [13] Mohamed and Isah (2012) Causes of Delay in Nigeria Construction Industry, Interdisciplinary Journal of Contemporary Research in Business, Vol.4, No.2. [14] Endut, I.R., A. Akintoye and J. Kelly, (2009) Cost and Time Overrun of Projects in Malaysia. pp f [15] Abdullah M.R., Abdul Rahman, I. and Abdul Aziz A.S. (2010). Causes of Delay in MARA Management Procurement Construction Projects. Journal of Surveying, Construction & Property.1(1). [16] Sambasivan, M and Soon, Y. (2007) Causes and Effects of Delays in Malaysian Construction Industry, International Journal of Project Management, Vol. 25 Issue 5, pp [17] SKALA JKR Kubang Pasu Kedah (2011). [18] Ahmed, S.M. Salman Azhar, Mauricio Castillo and Pragnya Kappagantula (2002) Construction Delays in Florida; an empirical study: [19] Assaf, S.A. and AlHeiji (2006) Causes of Delays in Large Construction Projects, International Journal of Project Management, Vol. 24, [20] Mezher, T.M., and Tawil W. (1998), Causes of Delays in the Construction Industry in Lebanon. Engineering Construction and Architectural Management, 5(3): [21] Frimpong, Y., Oluwoye, J. and Crawford, L. (2003) Causes of Delay and Cost Overruns in Construction of Groundwater Projects in Developing Countries: Ghana as a Case Study. International Journal of Project Management, Elsevier, 21: [22] El Razek, M.E., Basssioni, H.A., Mobarak, A.M. (2008) Causes of Delay in Building Construction Projects in Egypt, Construction Engineering and Management, ASCE. 134: [23] Alaghbari, W.A.M, Razali, M.A.K, Salim, A and Ernawati (2005), Factors Affecting Construction Speed of Industrialized Building Systems in Malaysia, Universiti Putra Malaysia, Master Thesis ISBN: [24] Joshi, M. (2009) 80 percent of Malaysian Government Projects Delayed, Minister says, (available online governmentprojectsdelayedministersays [accessed on 01/10/2009] [25] Abdullah, M.R, A.A.A. Aziz and I.A. Rahman (2009). Potential Effects on Large MARA Construction Projects Due to Construction Delay. International Journal of Integrated Engineering, 1:5362 [26] Lo, T.Y. Ivan W.H. Fung and Karen C.F. Tung (2006) Construction Delays in Hong Kong Civil Engineering Projects. Journal of Construction Engineering and Management, ( : ).

CONSTRUCTION PROFESSIONALS PERCEPTION ON THE CAUSES AND EFFECTS OF PROJECT DELAY IN LUSAKA, ZAMBIA

CONSTRUCTION PROFESSIONALS PERCEPTION ON THE CAUSES AND EFFECTS OF PROJECT DELAY IN LUSAKA, ZAMBIA CONSTRUCTION PROFESSIONALS PERCEPTION ON THE CAUSES AND EFFECTS OF PROJECT DELAY IN LUSAKA, ZAMBIA MJ Mukuka 1, CO Aigbavboa 2, and WD Thwala 3 Department of Construction Management & Quantity Surveying,

More information

Assessment of Factors Causing Delay on Building Construction Projects in Enugu, Nigeria

Assessment of Factors Causing Delay on Building Construction Projects in Enugu, Nigeria Assessment of Factors Causing Delay on Building Construction Projects in Enugu, Nigeria Agu. N. N1 and Ibe, B. O. Department of Quantity Survey, Nnamdi, Azikiwe University, Awka, Anambra State, Nigeria

More information

A Brief Study on Residential Construction Projects from View of Delay Causes Ranking

A Brief Study on Residential Construction Projects from View of Delay Causes Ranking International Journal of Humanities and Management Sciences (IJHMS) Volume 4, Issue 4 () ISSN 44 (Online) A Brief Study on Residential Construction Projects from View of Delay Causes ing Siamak Hajiyakhchali,

More information

CONSTRUCTION DELAY FACTORS IN GENERAL AND ESPECIALLY IN DEVELOPED COUNTRIES

CONSTRUCTION DELAY FACTORS IN GENERAL AND ESPECIALLY IN DEVELOPED COUNTRIES Int. J. Struct. & Civil Engg. Res. 2014 Basim Khadier Khadim and Pramila Adavi, 2014 Research Paper ISSN 2319 6009 www.ijscer.com Vol. 3, No. 4, November 2014 2014 IJSCER. All Rights Reserved CONSTRUCTION

More information

Analysis and Identification of Critical Factors of Delay in Construction Projects

Analysis and Identification of Critical Factors of Delay in Construction Projects Analysis and Identification of Critical Factors of Delay in Construction Projects 83 Analysis and Identification of Critical Factors of Delay in Construction Projects M.P.Venkatesh*, C.Umarani**, S. M.

More information

Analysis Of Critical Causes Of Delays In Indian Infrastructure Projects

Analysis Of Critical Causes Of Delays In Indian Infrastructure Projects ISSN: 2278 0211 (Online) Analysis Of Causes Of Delays In Indian Infrastructure Projects Prof: Siddesh K Pai DME, DBM, BE Mech, PGP PEM,MIM Assistant professor, National Institute of construction Management

More information

CONTRACTOR PERSPECTIVE ON TIME OVERRUN FACTORS IN MALAYSIAN CONSTRUCTION PROJECTS

CONTRACTOR PERSPECTIVE ON TIME OVERRUN FACTORS IN MALAYSIAN CONSTRUCTION PROJECTS International Journal of Science, Environment and Technology, Vol. 3, No 3, 2014, 1184 1192 ISSN 2278-3687 (O) CONTRACTOR PERSPECTIVE ON TIME OVERRUN FACTORS IN MALAYSIAN CONSTRUCTION PROJECTS Aftab Hameed

More information

CAUSES OF THE TIME DELAY IN CONSTRUCTION HOUSING PROJECTS IN GWALIOR DIVISION

CAUSES OF THE TIME DELAY IN CONSTRUCTION HOUSING PROJECTS IN GWALIOR DIVISION CAUSES OF THE TIME DELAY IN CONSTRUCTION HOUSING PROJECTS IN GWALIOR DIVISION Pawan Hari 1, Dr. Mukesh Pandey 2 1M.Tech. Student, Civil Engineering Department, ITM University, Gwalior 2Professor and Head

More information

Study and Assessment of Causes and Effects of Delay in Large Public Construction Projects in Jordan

Study and Assessment of Causes and Effects of Delay in Large Public Construction Projects in Jordan Study and Assessment of Causes and Effects of Delay in Large Public Construction Projects in Jordan Ghanim A. Bekr Associate Professor, Civil Engineering Dept., Zarqa University, Jordan. Abstract In Jordan,

More information

Causes and Effects of Construction Project Delays in Nigerian Construction Industry

Causes and Effects of Construction Project Delays in Nigerian Construction Industry IJISET - International Journal of Innovative Science, Engineering & Technology, Vol. 3 Issue 5, May 016. ISSN 348 7968 Causes and Effects of Construction Project Delays in Nigerian Construction Industry

More information

Study of Delay Factors in Construction Projects

Study of Delay Factors in Construction Projects Study of Delay Factors in Construction Projects Shabbab Al Hammadi 1, M. Sadique Nawab 2 Assistant Professor, Civil Engineering Department, Shaqra University, Al Dawadmi, KSA 1 Lecturer, Civil Engineering

More information

Identification of the Causes of Construction Delay in Malaysia

Identification of the Causes of Construction Delay in Malaysia Identification of the Causes of Construction Delay in Malaysia N. Hamzah, M.A. Khoiry, I. Arshad, W.H.W. Badaruzzaman, and N. M. Tawil International Science Index, Civil and Environmental Engineering Vol:6,

More information

Schedule Delay in Saudi Arabia Road Construction Projects: Size, Estimate, Determinants and Effects

Schedule Delay in Saudi Arabia Road Construction Projects: Size, Estimate, Determinants and Effects International Journal of Architecture, Engineering and Construction Vol 6, No 3, September 2017, 51-58 Schedule Delay in Saudi Arabia Road Construction : Size, Estimate, Determinants and Effects Ibrahim

More information

Identification of Critical Construction Delay Factors

Identification of Critical Construction Delay Factors Identification of Critical Construction Delay Factors Ashwini Arun Salunkhe Post Graduate Student, Department of Civil Engineering, Padmashree Dr. D.Y.Patil Institute of Engineering & Technology. Pimpri,

More information

Major Mitigation Measures for Delays in Construction Projects

Major Mitigation Measures for Delays in Construction Projects 1Major Mitigation Measures Major Mitigation Measures for Delays in Construction Projects Mohammad Abedi, PhD Candidate, Department of Civil Engineering, RAZAK School of Engineering & Advanced Technology,

More information

Ranking of Delay Factors for Makkah s Construction Industry

Ranking of Delay Factors for Makkah s Construction Industry Ranking of Delay Factors for Makkah s Construction Industry Nashwan Al-Emad 1,*, Ismail Abdul Rahman 2, Sasitharan Nagapan 1, and Yaser Gamil 1 1 Faculty of Civil and Environmental Engineering, Universiti

More information

CAUSE OF DELAY IN CONSTRUCTION PROJECTS IN

CAUSE OF DELAY IN CONSTRUCTION PROJECTS IN International Journal of Civil Engineeringg and Technology (IJCIET) Volume 8, Issue 7, July 2017, pp. 30 36, Article ID: IJCIET_08_07_004 Available online at http://www.ia aeme.com/ijc CIET/issues.a asp?jtype=ijciet&vtyp

More information

CONSTRUCTION PROJECT DELAYS IN EASTERN PROVINCE OF SRI LANKA: PERSPECTIVES OF CONTRACTORS AND CONSULTANTS

CONSTRUCTION PROJECT DELAYS IN EASTERN PROVINCE OF SRI LANKA: PERSPECTIVES OF CONTRACTORS AND CONSULTANTS CONSTRUCTION PROJECT DELAYS IN EASTERN PROVINCE OF SRI LANKA: PERSPECTIVES OF CONTRACTORS AND CONSULTANTS A.L.M.Risath 1, K.M.Rifas 2 &A.J.Thamboo 2 1,2 Department of Civil Engineering, South Eastern University

More information

DELAY IN LARGE MARA CONSTRUCTION PROJECTS BASED ON PROJECT MANAGEMENT CONSULTANT PERSPECTIVE.

DELAY IN LARGE MARA CONSTRUCTION PROJECTS BASED ON PROJECT MANAGEMENT CONSULTANT PERSPECTIVE. Proceedings of MUCEET2009 Malaysian Technical Universities Conference on Engineering and Technology June 20-22, 2009, MS Garden,Kuantan, Pahang, Malaysia MUCEET2009 DELAY IN LARGE MARA CONSTRUCTION PROJECTS

More information

CHAPTER 2 LITERATURE REVIEW

CHAPTER 2 LITERATURE REVIEW 10 CHAPTER 2 LITERATURE REVIEW 2.1 GENERAL One of the most important problems in the construction industry is Time overrun. Time overrun occur in every construction project and the magnitude of these delays

More information

Investigating Causes of Construction Delay in Ethiopian Construction Industries

Investigating Causes of Construction Delay in Ethiopian Construction Industries Journal of Civil, Construction and Environmental Engineering 2016; 1(1): 18-29 http://www.sciencepublishinggroup.com/j/jccee doi: 10.11648/j.jccee.20160101.13 Investigating Causes of Construction Delay

More information

AFRICAN JOURNAL OF APPLIED RESEARCH (AJAR) Vol.1, No.1 ISSN January 2015

AFRICAN JOURNAL OF APPLIED RESEARCH (AJAR)   Vol.1, No.1 ISSN January 2015 DELAY AND ITS EFFECT ON THE DELIVERY OF CONSTRUCTION PROJECTS IN GHANA Addo J.N.T. Department of Building Technology, Cape Coast Polytechnic, Cape Coast- Ghana ABSTRACT It is common knowledge that our

More information

Contributions of Construction Project Team to Cost Overruns: The Contractors Perspective. Nigeria; PH (234) ;

Contributions of Construction Project Team to Cost Overruns: The Contractors Perspective. Nigeria; PH (234) ; 1528 Contributions of Construction Project Team to Cost Overruns: The Contractors Perspective Olusegun AKINSIKU 1, Adeyemi AKINTOLA 1, Oko AMEH 1 and Ayokunle IGE 1 1 Department of Building, Faculty of

More information

Causes of Final Account Closing Delay: A Theoretical Framework Zarabizan Zakaria, Syuhaida Ismail, Aminah Md. Yusof

Causes of Final Account Closing Delay: A Theoretical Framework Zarabizan Zakaria, Syuhaida Ismail, Aminah Md. Yusof Causes of Final Account Closing Delay: A Theoretical Framework Zarabizan Zakaria, Syuhaida Ismail, Aminah Md. Yusof International Science Index, Economics and Management Engineering waset.org/publication/9996561

More information

Understanding construction projects schedule overruns in South Africa

Understanding construction projects schedule overruns in South Africa Understanding construction projects schedule overruns in South Africa Mulenga MUKUKA 1, Clinton AIGBAVBOA 2 and Wellington THWALA 3 1 MTECH, Department of Construction Management and Quantity Surveying,

More information

Causes and Effects of Delays in Construction of Medium Scale Drinking Water Supply Projects in Sri Lanka

Causes and Effects of Delays in Construction of Medium Scale Drinking Water Supply Projects in Sri Lanka Annual Transactions of IESL, pp. [ 151-159], 2012 The Institution of Engineers, Sri Lanka Causes and Effects of Delays in Construction of Medium Scale Drinking Water Supply Projects in Sri Lanka W.D.A.

More information

A METHODOLOGY TO IDENTIFY THE DELAYS AND RANK ITS CAUSATIVE FACTORS IN INDIAN CONSTRUCTION INDUSTRY

A METHODOLOGY TO IDENTIFY THE DELAYS AND RANK ITS CAUSATIVE FACTORS IN INDIAN CONSTRUCTION INDUSTRY A METHODOLOGY TO IDENTIFY THE DELAYS AND RANK ITS CAUSATIVE FACTORS IN INDIAN CONSTRUCTION INDUSTRY Anup Wilfred 1, Muhamad Sharafudeen 2 1 Associate Professor, Civil Engineering Department, MIT, Karnataka,

More information

International Journal of Modern Trends in Engineering and Research e-issn No.: , Date: April, 2016

International Journal of Modern Trends in Engineering and Research   e-issn No.: , Date: April, 2016 International Journal of Modern Trends in Engineering and Research www.ijmter.com e-issn No.:2349-9745, Date: 28-30 April, 2016 Identifying the Cause of Delay in Construction Industry in Mumbai Region

More information

Causes of Delay in Public Building Construction Projects: A Case of Addis Abeba Administration, Ethiopia

Causes of Delay in Public Building Construction Projects: A Case of Addis Abeba Administration, Ethiopia Asian Journal of Managerial Science ISSN: 2249-6300 Vol.8 No.2, 2019, pp. 4-9 The Research Publication, www.trp.org.in Causes of Delay in Public Building Construction Projects: A Case of Addis Abeba Administration,

More information

CAUSES OF DELAYS IN CONSTRUCTION PROJECTS IN TURKEY

CAUSES OF DELAYS IN CONSTRUCTION PROJECTS IN TURKEY JOURNAL OF CIVIL ENGINEERING AND MANAGEMENT ISSN 1392-3730 print/issn 1822-3605 online 2012 Volume 18(3): 426 435 doi:10.3846/13923730.2012.698913 CAUSES OF DELAYS IN CONSTRUCTION PROJECTS IN TURKEY Aynur

More information

Assessment of Extension of Time Claims in Hydropower Projects of Pakistan

Assessment of Extension of Time Claims in Hydropower Projects of Pakistan International Journal of Engineering and Advanced Technology (IJEAT) Assessment of Extension of Time Claims in Hydropower Projects of Pakistan Hashim Hanif, Yasar Saleem, Zuhaib Aslam Shahid, Abdullah

More information

VOL. 5, NO. 2, February 2015 ISSN ARPN Journal of Science and Technology All rights reserved.

VOL. 5, NO. 2, February 2015 ISSN ARPN Journal of Science and Technology All rights reserved. A Conceptual Model of Delay Factors affecting Government Construction Projects 1 Luu Truong Van, 2 Nguyen Minh Sang, 3 Nguyen Thanh Viet 1 Associate Professor, Department of Civil Engineering, International

More information

Investigation of Significant Factors Influencing Time and Cost Overruns in Indian Construction Projects

Investigation of Significant Factors Influencing Time and Cost Overruns in Indian Construction Projects Investigation of Significant Factors Influencing Time and Cost Overruns in Indian Construction Projects S. Shanmugapriya 1, Dr. K. Subramanian 2 1 Assistant Professor, 2 Professor and Head, Department

More information

Analyzing Causes of Delay in Construction Projects

Analyzing Causes of Delay in Construction Projects IJIRST - International Journal for Innovative Research in Science & Technology Volume 2 Issue 12 May 2016 ISSN (online): 2349-6010 Analyzing Causes of Delay in Construction Projects Kartik Kalkani Student

More information

Available online at ScienceDirect. Procedia Engineering 77 (2014 )

Available online at  ScienceDirect. Procedia Engineering 77 (2014 ) Available online at www.sciencedirect.com ScienceDirect Procedia Engineering 77 (2014 ) 196 204 Fourth International Symposium on Infrastructure Engineering in Developing Countries, IEDC 2013 Time Extension

More information

Construction Experts Perception on the Causes and Effects of Cost Overruns in Johannesburg, Gauteng Province, South Africa

Construction Experts Perception on the Causes and Effects of Cost Overruns in Johannesburg, Gauteng Province, South Africa Construction Experts Perception on the Causes and Effects of Cost Overruns in Johannesburg, Gauteng Province, South Africa Abstract Mukuka MJ 1, Clinton Aigbavboa 2, and Wellington Thwala 3 The construction

More information

Effects of construction projects schedule overruns: A case of the Gauteng Province, South Africa

Effects of construction projects schedule overruns: A case of the Gauteng Province, South Africa Available online at www.sciencedirect.com ScienceDirect Procedia Manufacturing 00 (2015) 000 000 www.elsevier.com/locate/procedia 6th International Conference on Applied Human Factors and Ergonomics (AHFE

More information

Significant Factors Causing Time Overrun in Construction Projects of Peninsular Malaysia

Significant Factors Causing Time Overrun in Construction Projects of Peninsular Malaysia Modern Applied Science; Vol. 8, No. 4; 2014 ISSN 1913-1844 E-ISSN 1913-1852 Published by Canadian Center of Science and Education Significant Factors Causing Time Overrun in Construction Projects of Peninsular

More information

Feasibility Study on Delay Factors Influencing Construction Projects in India

Feasibility Study on Delay Factors Influencing Construction Projects in India Volume-7, Issue-3, May-June 2017 International Journal of Engineering and Management Research Page Number: 391-398 Feasibility Study on Delay Influencing Construction Projects in India Sakthi Ganesh G

More information

INVESTIGATING THE CAUSES OF DELAY WITHIN OIL AND GAS PROJECTS IN THE U.A.E.

INVESTIGATING THE CAUSES OF DELAY WITHIN OIL AND GAS PROJECTS IN THE U.A.E. INVESTIGATING THE CAUSES OF DELAY WITHIN OIL AND GAS PROJECTS IN THE U.A.E. Mohamed Salama 1, Moustafa Abd El Hamid and Bill Keogh School of Management and Languages, Heriot-Watt University, Riccarton,

More information

Simulating The Impact Of The Material Flow In The Jordanian Construction Supply Chain And Its Impact On Project Performance

Simulating The Impact Of The Material Flow In The Jordanian Construction Supply Chain And Its Impact On Project Performance Simulating The Impact Of The Material Flow In The Jordanian Construction Supply Chain And Its Impact On Project Performance Dr. Ghaith Al-Werikat Abstract: With the new developments and challenges within

More information

AN ASSESSMENT OF THE CAUSATIVE FACTORS AND EFFECTS OF DELAYS IN BUILDING CONSTRUCTION PROJECTS IN OSUN STATE, NIGERIA.

AN ASSESSMENT OF THE CAUSATIVE FACTORS AND EFFECTS OF DELAYS IN BUILDING CONSTRUCTION PROJECTS IN OSUN STATE, NIGERIA. AN ASSESSMENT OF THE CAUSATIVE FACTORS AND EFFECTS OF DELAYS IN BUILDING CONSTRUCTION PROJECTS IN OSUN STATE, NIGERIA. ASA, Olusola Adekunle and KAREEM Ajibola W. 1** Department of Architectural Technology,

More information

ANALYSIS OF THE RELATIONSHIPS BETWEEN CAUSES OF DELAY IN CONSTRUCTION PROJECTS IN BANGLADESH

ANALYSIS OF THE RELATIONSHIPS BETWEEN CAUSES OF DELAY IN CONSTRUCTION PROJECTS IN BANGLADESH ANALYSIS OF THE RELATIONSHIPS BETWEEN CAUSES OF DELAY IN CONSTRUCTION PROJECTS IN BANGLADESH M. A. Salam 1, H. J. Staines 2, D. J. Blackwood 1 and S. Sarkar 1 1 School of Science and Engineering, and 2

More information

Performance Appraisal amongst Contractors in Construction Project in Malaysia Siti Hafiza Mat Yahya 1, a and Syuhaida Ismail 2,b

Performance Appraisal amongst Contractors in Construction Project in Malaysia Siti Hafiza Mat Yahya 1, a and Syuhaida Ismail 2,b Performance Appraisal amongst Contractors in Construction Project in Malaysia Siti Hafiza Mat Yahya 1, a and Syuhaida Ismail 2,b 1 UTM Razak School of Engineering and Advanced Technology, UTM Kuala Lumpur,

More information

Investigating Causes of Delay in U.S. Construction Projects

Investigating Causes of Delay in U.S. Construction Projects Investigating Causes of Delay in U.S. Construction Projects Mohammadsoroush Tafazzoli Ph.D. Candidate, LEED AP, and Pramen P. Shrestha Ph.D., PE University of Nevada, Las Vegas Las Vegas, Nevada Delays

More information

Available online at ScienceDirect. Procedia Manufacturing 3 (2015 )

Available online at  ScienceDirect. Procedia Manufacturing 3 (2015 ) Available online at www.sciencedirect.com ScienceDirect Procedia Manufacturing 3 (2015 ) 1690 1695 6th International Conference on Applied Human Factors and Ergonomics (AHFE 2015) and the Affiliated Conferences,

More information

Factors affecting construction cost performance in project management projects: Case of MARA large projects

Factors affecting construction cost performance in project management projects: Case of MARA large projects International Journal of Civil Engineering and Built Environment Vol.1, No.1, 2014; ISSN 2289-6317 Published by YSI Publisher Factors affecting construction cost performance in project management projects:

More information

Effects of Delay in construction Projects of Punjab-Pakistan: An Empirical Study

Effects of Delay in construction Projects of Punjab-Pakistan: An Empirical Study 2014, TextRoad Publication ISSN 2090-4304 Journal of Basic and Applied Scientific Research www.textroad.com Effects of Delay in construction Projects of Punjab-Pakistan: An Empirical Study Saiful Haq 1,

More information

IDENTIFYING KEY RISKS IN BUILDING PERFORMANCE

IDENTIFYING KEY RISKS IN BUILDING PERFORMANCE IDENTIFYING KEY RISKS IN BUILDING PERFORMANCE Chen Jia Woon, Azlan Shah Ali and Faizul Ali Mohd Rahim Faculty of Built Environment, University of Malaya, 50603 Kuala Lumpur Correspondence: jiawoon_chen@ymail.com

More information

JFMPC 14,2. Jomah Al-Najjar Islamic University of Gaza, Gaza Strip, Palestinian Authority, and

JFMPC 14,2. Jomah Al-Najjar Islamic University of Gaza, Gaza Strip, Palestinian Authority, and The current issue and full text archive of this journal is available at www.emeraldinsight.com/1366-4387.htm JFMPC 14,2 126 Delays and cost overruns in the construction projects in the Gaza Strip Adnan

More information

Perceptions of Skilled Labour Attributes on Delays in Construction Projects in India

Perceptions of Skilled Labour Attributes on Delays in Construction Projects in India Perceptions of Skilled Labour Attributes on Delays in Construction Projects in India Dillip Kumar Das Department of Civil Engineering, Central University of Technology, Free state, South Africa Email:

More information

Qualitative Approach on Investigating Failure Factors of Yemeni Mega Construction Projects

Qualitative Approach on Investigating Failure Factors of Yemeni Mega Construction Projects Qualitative Approach on Investigating Failure Factors of Yemeni Mega Construction Projects Yaser Gamil 1,*, Ismail Abdul Rahman 1, Sasitharan Nagapan 1, and Nashwan Alemad 1 1 Faculty of Civil and Environmental

More information

ANALYSIS OF DELAY IN EXECUTION OF CONSTRUCTION PROJECTS

ANALYSIS OF DELAY IN EXECUTION OF CONSTRUCTION PROJECTS ANALYSIS OF DELAY IN EXECUTION OF CONSTRUCTION PROJECTS P. Muralidhar 1, Rahul Kumar Jain 1, B. Srivasta 1, V. Poorna Chandra Rao 1 1 National Institute of Construction Management and Research (NICMAR),

More information

Causes of Delay in Construction of Bridge Girders

Causes of Delay in Construction of Bridge Girders IOSR Journal of Mechanical and Civil Engineering (IOSR-JMCE) e-issn: 2278-1684,p-ISSN: 2320-334X, Volume 12, Issue 1 Ver. IV (Jan- Feb. 2015), PP 08-12 www.iosrjournals.org Causes of Delay in Construction

More information

Project Management for Construction Projects: Improving Project Performance

Project Management for Construction Projects: Improving Project Performance Project Management for Construction Projects: Improving Project Performance Ashish D. Joshi 1, Prof. Dr. S.D. Khandekar 2 1 Student, Construction & Management, RMD Sinhgad School of Engineering, Maharashtra,

More information

International Journal of Advance Engineering and Research Development

International Journal of Advance Engineering and Research Development Scientific Journal of Impact Factor (SJIF): 5.71 International Journal of Advance Engineering and Research Development Volume 5, Issue 04, April -2018 e-issn (O): 2348-4470 p-issn (P): 2348-6406 A COMPARATIVE

More information

[Sharafadeen, 2(10): October, 2015] ISSN Impact Factor (PIF): 2.243

[Sharafadeen, 2(10): October, 2015] ISSN Impact Factor (PIF): 2.243 DELAY OF BUILDING CONSTRUCTION PROJECTS IN NIGERIA-A REVIEW OF CAUSES, EFFECTS AND SOLUTIONS Olanrewaju Sharafadeen, Babatunde Owolabi and Ajetomobi Oludare Olayinka Department of Building Technology,

More information

CHAPTER 1 INTRODUCTION

CHAPTER 1 INTRODUCTION 1 CHAPTER 1 INTRODUCTION 1.1 BACKGROUND In India, Construction Industry plays a key role in both economic growth and poverty reduction. The industry consumes about 40 to 50% of the national five year plan

More information

Investigation of Factors Influencing Cost Overrun in High-Rise Building Constructions

Investigation of Factors Influencing Cost Overrun in High-Rise Building Constructions Investigation of Factors Influencing Cost Overrun in High-Rise Building Constructions Prof. Yogini K. Patil Professor, G. C.O.E.Jalgaon, Maharashtra, India. Prof. Pankaj P. Bhangale Head of Civil Dept,

More information

Critical Factors behind Construction Delay in Petrochemical Projects in Saudi Arabia

Critical Factors behind Construction Delay in Petrochemical Projects in Saudi Arabia energies Article Critical Factors behind Construction Delay in Petrochemical Projects in Saudi Arabia Abdullah Rasheed Alhajri 1, * and Adel Alshibani 2 1 Construction Engineering and Management, KFUPM,

More information

Analysis of Improper Material Management Affecting Cost in Construction Projects

Analysis of Improper Material Management Affecting Cost in Construction Projects Analysis of Improper Material Management Affecting Cost in Construction Projects P.Lenin *, L.Krishnaraj *, D.Narendra Prasad *, V.R Prasath Kumar *, Assistant Professor, Civil Engineering Department,

More information

THE CAUSE FACTORS OF LARGE PROJECT S COST OVERRUN: A SURVEY IN THE SOUTHERN PART OF PENINSULAR MALAYSIA

THE CAUSE FACTORS OF LARGE PROJECT S COST OVERRUN: A SURVEY IN THE SOUTHERN PART OF PENINSULAR MALAYSIA International Journal of Real Estate Studies, Volume 7, Number 2 2012 THE CAUSE FACTORS OF LARGE PROJECT S COST OVERRUN: A SURVEY IN THE SOUTHERN PART OF PENINSULAR MALAYSIA Aftab Hameed Memon 1, Ismail

More information

Factors Affecting Construction Cost in the Pakistani Construction Industry

Factors Affecting Construction Cost in the Pakistani Construction Industry Third International Conference on Construction in Developing Countries (ICCIDC III) Advancing Civil, Architectural and Construction Engineering & Management July 4-6, 2012, Bangkok, Thailand Factors Affecting

More information

International Journal of Modern Trends in Engineering and Research e-issn No.: , Date: 2-4 July, 2015

International Journal of Modern Trends in Engineering and Research   e-issn No.: , Date: 2-4 July, 2015 International Journal of Modern Trends in Engineering and Research www.ijmter.com e-issn No.:2349-9745, Date: 2-4 July, 2015 Study of Pros and Cons of Subcontracting System Adopted in Executing Indian

More information

EVALUATION AND MANAGEMENT OF CONSTRUCTION MATERIAL AND TIME WASTE BY PARETO ANALYSIS METHOD

EVALUATION AND MANAGEMENT OF CONSTRUCTION MATERIAL AND TIME WASTE BY PARETO ANALYSIS METHOD EVALUATION AND MANAGEMENT OF CONSTRUCTION MATERIAL AND TIME WASTE BY PARETO ANALYSIS METHOD V.Rajeshkumar 1, P.Indhiradevi 2, D.Karthik 3 1 Assistant Professor, Department of Civil Engineering, KPR Institute

More information

Evaluation on the Application of Quality Management System in Tanzania Building Construction Projects

Evaluation on the Application of Quality Management System in Tanzania Building Construction Projects American Journal of Management Science and Engineering 2017; 2(6): 170-175 http://www.sciencepublishinggroup.com/j/ajmse doi: 10.11648/j.ajmse.20170206.12 ISSN: 2575-193X (Print); ISSN: 2575-1379 (Online)

More information

Evaluating the factors affecting Quality of Residential projects in Construction Industry

Evaluating the factors affecting Quality of Residential projects in Construction Industry Evaluating the factors affecting Quality of Residential projects in Construction Industry Ashish Mutha Sardar Patel college of Engineering, Mumbai Dr. Anil Ghadge Sardar Patel college of Engineering, Mumbai

More information

FACTORS AFFECTING LABOUR PRODUCTIVITY IN ROAD CONSTRUCTION

FACTORS AFFECTING LABOUR PRODUCTIVITY IN ROAD CONSTRUCTION FACTORS AFFECTING LABOUR PRODUCTIVITY IN ROAD CONSTRUCTION Mr. D.Sukumar1, Mr. S.Saravanan2 Assistant Prof, Dept of Civil Engineering, Erode Sengunthar Engineering College, Thudupathi-6807, India1 Assistant

More information

CURRENT PRACTICE OF COAL DISCHARGING OPERATION IN MALAYSIAN PORT. Amli Mohamed Amin * Syuhaida Ismail * Khairul Zahreen Mohd Arof *

CURRENT PRACTICE OF COAL DISCHARGING OPERATION IN MALAYSIAN PORT. Amli Mohamed Amin * Syuhaida Ismail * Khairul Zahreen Mohd Arof * CURRENT PRACTICE OF COAL DISCHARGING OPERATION IN MALAYSIAN PORT Amli Mohamed Amin * Syuhaida Ismail * Khairul Zahreen Mohd Arof * * Universiti Teknologi Malaysia, Malaysia. http://doi.org/10.31039/jomeino.2019.3.1.2

More information

Preliminary Study on Causative Factors Leading to Construction Cost Overrun

Preliminary Study on Causative Factors Leading to Construction Cost Overrun Preliminary Study on Causative Factors Leading to Construction Cost Overrun Aftab Hameed Memon *1, Ismail Abdul Rahman 2, Ade Asmi Abdul Azis 3 1,2,3 Faculty of Civil and Environmental Engineering Universiti

More information

EVALUATION OF CONSTRUCTION COST AND TIME ATTRIBUTES

EVALUATION OF CONSTRUCTION COST AND TIME ATTRIBUTES EVALUATION OF CONSTRUCTION COST AND TIME ATTRIBUTES T.M.S. Elhag and A.H. Boussabaine School of Architecture and Building Engineering, The University of Liverpool, Liverpool L69 3BX, UK Understanding the

More information

ANALYSIS OF SAFETY MANAGEMENT IN CONSTRUCTION INDUSTRY USING SPSS AND RII

ANALYSIS OF SAFETY MANAGEMENT IN CONSTRUCTION INDUSTRY USING SPSS AND RII ANALYSIS OF SAFETY MANAGEMENT IN CONSTRUCTION INDUSTRY USING SPSS AND RII K. Lalithapriya 1, S. Deepalakshmi 2, TR.Arthi 3,G.Karthiga 4 1 Assistant Professor. Civil Engg. Mookambigai college of Engineering,Trichy,

More information

Time and Cost Performance of Costruction Projects in Southern and Cenrtal Regions of Penisular Malaysia

Time and Cost Performance of Costruction Projects in Southern and Cenrtal Regions of Penisular Malaysia Time and Cost Performance of Costruction Projects in Southern and Cenrtal Regions of Penisular Malaysia Ismail Abdul Rahman, Aftab Hameed Memon, Sasitharan Nagapan, Qadir Bux Alias Imran Latif Faculty

More information

Enhancing the Quality of Construction Environment by Minimizing the Cost Variance

Enhancing the Quality of Construction Environment by Minimizing the Cost Variance Available online at www.sciencedirect.com ScienceDirect Procedia - Social and Behavioral Sciences 153 ( 2014 ) 70 78 AicQoL2014Kota Kinabalu AMER International Conference on Quality of Life The Pacific

More information

ISSN: [Mohammed* et al., 6(11): November, 2017] Impact Factor: 4.116

ISSN: [Mohammed* et al., 6(11): November, 2017] Impact Factor: 4.116 IJESRT INTERNATIONAL JOURNAL OF ENGINEERING SCIENCES & RESEARCH TECHNOLOGY FACTORS CAUSING VARIATION ORDERS IN BUILDING PROJECTS IN KHARTOUM STATE- SUDAN Eltahir Abu Elgassim Mohammed 1 *, Salma Yahia

More information

NOVATEUR PUBLICATIONS INTERNATIONAL JOURNAL OF INNOVATIONS IN ENGINEERING RESEARCH AND TECHNOLOGY [IJIERT] ISSN: VOLUME 4, ISSUE

NOVATEUR PUBLICATIONS INTERNATIONAL JOURNAL OF INNOVATIONS IN ENGINEERING RESEARCH AND TECHNOLOGY [IJIERT] ISSN: VOLUME 4, ISSUE STUDY ON DELAY CONSTRUCTION PROJECT IN INDIA MR. KARTIK BAGRECHA Department of Project and construction Management, MITADT University, MIT- College of Management, Pune, Maharashtra, India *kartikbagrecha@gmail.com

More information

INVESTIGATION INTO THE CAUSES OF CLAIMS IN EGYPTIAN BUILDING CONSTRUCTION

INVESTIGATION INTO THE CAUSES OF CLAIMS IN EGYPTIAN BUILDING CONSTRUCTION INVESTIGATION INTO THE CAUSES OF CLAIMS IN EGYPTIAN BUILDING CONSTRUCTION Mohamed Emam Abd El-Razek 1, Hesham Bassioni 2 and Wael Abd El-Salam 3 1 College of Engineering and Technology, Arab Academy for

More information

Critical Factors Affecting the Implementation of Total Quality Management in the Construction Industry in U.A.E

Critical Factors Affecting the Implementation of Total Quality Management in the Construction Industry in U.A.E Critical Factors Affecting the Implementation of Total Quality Management in the Construction Industry in U.A.E Firas Mohamad Al-Sabek Abstract The purpose of the paper is to examine the most critical

More information

Designing Guidelines to Discover Causes of Delays in Construction Projects: The Case of Lebanon

Designing Guidelines to Discover Causes of Delays in Construction Projects: The Case of Lebanon International Business Research; Vol. 8, No. 6; 2015 ISSN 1913-9004 E-ISSN 1913-9012 Published by Canadian Center of Science and Education Designing Guidelines to Discover Causes of Delays in Construction

More information

EVALUTION OF FACTORS AFFECTING PROJECT MANAGEMENT PHASES IN PUBLIC HOUSING PROJECTS

EVALUTION OF FACTORS AFFECTING PROJECT MANAGEMENT PHASES IN PUBLIC HOUSING PROJECTS EVALUTION OF FACTORS AFFECTING PROJECT MANAGEMENT PHASES IN PUBLIC HOUSING PROJECTS Sudhir G. Vekaria 1, Bhavin K. Kashiyani 2 Student, M.E.Civil, S.N.P.I.T.&R.C.,Umrakh/ GTU, Bardoli/Surat, Gujarat, India

More information

THE EFFECT OF DESIGN KNOWLEDGE TOWARDS THE PERFORMANCE OF REFURBISHMENT PROJECTS IN MALAYSIA

THE EFFECT OF DESIGN KNOWLEDGE TOWARDS THE PERFORMANCE OF REFURBISHMENT PROJECTS IN MALAYSIA 034 THE EFFECT OF DESIGN KNOWLEDGE TOWARDS THE PERFORMANCE OF REFURBISHMENT PROJECTS IN MALAYSIA Azlan Shah Ali CEBUS, Faculty of Built Environment, University of Malaya 50603 Kuala Lumpur Email: asafab@um.edu.my

More information

NATURE OF THE CRITICAL RISK FACTORS AFFECTING PROJECT PERFORMANCE IN INDONESIAN BUILDING CONTRACTS

NATURE OF THE CRITICAL RISK FACTORS AFFECTING PROJECT PERFORMANCE IN INDONESIAN BUILDING CONTRACTS NATURE OF THE CRITICAL RISK FACTORS AFFECTING PROJECT PERFORMANCE IN INDONESIAN BUILDING CONTRACTS I Putu Artama Wiguna and Stephen Scott 1 School of Civil Engineering and Geosciences, University of Newcastle

More information

The Problem of Quality of Electrical Work in Malaysian Construction Projects

The Problem of Quality of Electrical Work in Malaysian Construction Projects Pertanika J. Soc. Sci. & Hum. 25 (S): 105-110 (2017) SOCIAL SCIENCES & HUMANITIES Journal homepage: http://www.pertanika.upm.edu.my/ The Problem of Quality of Electrical Work in Malaysian Construction

More information

Architecture Information in Construction Environment in Malaysia

Architecture Information in Construction Environment in Malaysia Available online at www.sciencedirect.com ScienceDirect Procedia - Social and Behavioral Sciences 153 ( 2014 ) 36 43 AicQoL2014Kota Kinabalu AMER International Conference on Quality of Life The Pacific

More information

Study factors affecting of delay in residential construction projects for Nashik city

Study factors affecting of delay in residential construction projects for Nashik city Study factors affecting of delay in residential construction projects for Nashik city Desai madhura.c Department of civil Engineering Ndmvp s kbt coe,nashik, maharashtra, india Prof.s.v.desale Department

More information

Critical Factors Influencing Construction Productivity in Thailand

Critical Factors Influencing Construction Productivity in Thailand Critical Factors Influencing Construction Productivity in Thailand Arun Makulsawatudom,* Margaret Emsley* and Kuldej Sinthawanarong** Abstract Factors affecting construction in Thailand were disclosed

More information

The Weaknesses of OSHA 1994 Implementation in Malaysian Construction Industry

The Weaknesses of OSHA 1994 Implementation in Malaysian Construction Industry The Weaknesses of OSHA 1994 Implementation in Malaysian Construction Industry Rohaida Affandi 1 and Hock Tai Chia 2 Abstract Statistics from Department of Occupational Safety and Health (DOSH) Malaysia

More information

AN OVERVIEW OF THE CONCEPT OF LEAN CONSTRUCTION AND THE BARRIERS IN ITS IMPLEMENTATION Radhika R *1, S.Sukumar 2

AN OVERVIEW OF THE CONCEPT OF LEAN CONSTRUCTION AND THE BARRIERS IN ITS IMPLEMENTATION Radhika R *1, S.Sukumar 2 IJETMR AN OVERVIEW OF THE CONCEPT OF LEAN CONSTRUCTION AND THE BARRIERS IN ITS IMPLEMENTATION Radhika R *1, S.Sukumar 2 *1 P.G Student of Civil Engineering Department, Nehru Institute of Technology, Coimbatore,

More information

Impact of Cost and Time Overrun on Building Construction Projects

Impact of Cost and Time Overrun on Building Construction Projects Impact of Cost and Time Overrun on Building Construction Projects Santosh Kumar Prajapati, 1 Rakesh Gupta, 2 Dr.Mukesh Pandey, 3 B.Tech+M.tech (INT) P.G student, Construction technology & Management, I.T.M

More information

Analysis of Delay due to Material Supply by Tower Crane at different Height of High Rise Buildings in Mumbai

Analysis of Delay due to Material Supply by Tower Crane at different Height of High Rise Buildings in Mumbai IOSR Journal of Engineering (IOSRJEN) e-issn: 2250-3021, p-issn: 2278-8719 Vol. 3, Issue 11 (November. 2013), V2 PP 19-26 Analysis of Delay due to Material Supply by Tower Crane at different Height of

More information

Delays in Construction Projects: Causes and Mitigation

Delays in Construction Projects: Causes and Mitigation Delays in Construction Projects: Causes and Mitigation Aleksander Srdić, Ph.D. University of Ljubljana, Faculty of Civil and Geodetic Engineering, Slovenia aleksander.srdic@fgg.uni-lj.si Assoc. Prof. Jana

More information

Gaji Abubakar Usman* & Rosli Bin Mohamad Zin

Gaji Abubakar Usman* & Rosli Bin Mohamad Zin Malaysian Journal of Civil Engineering 29(1):42-58(2017) CRITICAL FACTORS AFFECTING QUALITY IN PUBLIC CONSTRUCTION PROJECTS IN BORNO STATE Gaji Abubakar Usman* & Rosli Bin Mohamad Zin Faculty of Civil

More information

CAUSES OF CONSTRUCTION DELAYS IN IRAN: PROJECT MANAGEMENT, LOGISTICS, TECHNOLOGY AND ENVIRONMENT

CAUSES OF CONSTRUCTION DELAYS IN IRAN: PROJECT MANAGEMENT, LOGISTICS, TECHNOLOGY AND ENVIRONMENT CAUSES OF CONSTRUCTION DELAYS IN IRAN: PROJECT MANAGEMENT, LOGISTICS, TECHNOLOGY AND ENVIRONMENT Ehsan Asnaashari 1, Andrew Knight, Alan Hurst, Saeed Shahrabi Farahani School of Architecture, Design and

More information

Available online at ScienceDirect. Procedia Engineering 125 (2015 ) 32 39

Available online at   ScienceDirect. Procedia Engineering 125 (2015 ) 32 39 Available online at www.sciencedirect.com ScienceDirect Procedia Engineering 125 (2015 ) 32 39 The 5th International Conference of Euro Asia Civil Engineering Forum (EACEF-5) The practice of time management

More information

COST AND TIME CONTROL FACTORS FOR HIGH RISE RESIDENTIAL CONSTRUCTION PROJECTS

COST AND TIME CONTROL FACTORS FOR HIGH RISE RESIDENTIAL CONSTRUCTION PROJECTS COST AND TIME CONTROL FACTORS FOR HIGH RISE RESIDENTIAL CONSTRUCTION PROJECTS Miss. Suwarna Jape PG student (Construction and Management), DYPIET, Ambi Savitribai Phule Pune University, Pune, Maharashtra,

More information

FACTORS AFFECTING RELATIONSHIP BETWEEN CONTRACTOR AND SUBCONTRACTORS

FACTORS AFFECTING RELATIONSHIP BETWEEN CONTRACTOR AND SUBCONTRACTORS International Journal of Civil Engineering and Technology (IJCIET) Volume 9, Issue 3, March 2018, pp. 126 131, Article ID: IJCIET_09_03_014 Available online at http://www.iaeme.com/ijciet/issues.asp?jtype=ijciet&vtype=9&itype=3

More information

Exploratory Analysis of Factors Influencing Delay in EPC Contracts of Iranian Power Development Company

Exploratory Analysis of Factors Influencing Delay in EPC Contracts of Iranian Power Development Company Proceedings of the International MultiConference of Engineers and Computer Scientists 20 Vol II Exploratory Analysis of Factors Influencing Delay in EPC Contracts of Iranian Power Development Company Hamid

More information

Factors Constraining Labour Productivity: Case Study of Turkmenistan

Factors Constraining Labour Productivity: Case Study of Turkmenistan DOI: 10.7763/IPEDR. 2012. V55. 1 Factors Constraining Labour Productivity: Case Study of Turkmenistan Serdar Durdyev 1, Syuhaida Ismail 11 and Nooh Abu Bakar 1 1 Razak School of Engineering and Advanced

More information

Life Science Journal 2014;11(3s) Delay-based Reliability Analysis on Construction Projects. Shahryar Sorooshian

Life Science Journal 2014;11(3s)  Delay-based Reliability Analysis on Construction Projects. Shahryar Sorooshian Delay-based Reliability Analysis on Construction Projects Shahryar Sorooshian Faculty of Technology, University Malaysia Pahang, 26300, Malaysia sorooshian@gmail.com Abstract: The construction industry

More information

Namakkal, Tamilnadu, India

Namakkal, Tamilnadu, India A Study on Factors Influencing Quality of Construction Projects Davidkumar.C #1, Kathirvel.P #2 1# Post Graduate Student, Department of Civil Engineering, Mahendra Institute of Engineering and Technology,

More information