Navigating the Maze of Schedule Delay Analysis Methods

Size: px
Start display at page:

Download "Navigating the Maze of Schedule Delay Analysis Methods"

Transcription

1

2 Navigating the Maze of Schedule Delay Analysis Methods W. Stephen Dale, SVP and General Counsel, WSP Parsons Brinckerhoff Raymond L. DeLuca, Partner, Pepper Hamilton LLP Robert M. D Onofrio, P.E., Principal, Capital Project Management, Inc.

3 Schedule Delay Analysis Methods Total time/as-planned versus as-built (pre-1960 s) Impacted as-planned (by 1972) As-built critical path (by 1969) Collapsed as-built (by 1972) Time impact analysis (early 1960 s) Prospective time impact analysis Adjusted time impact analysis Windows method Windows with wide periods

4 US Case Law Acceptance of methods in case law Methods all accepted and not accepted Individual decision case/fact specific However, overall acceptance rates are instructive

5 US Case Law Dale, W.S. and D Onofrio, R.M., 2015, Construction Schedule Delays, Thomson Reuters West. Identified 133 cases where a method was accepted or not accepted by a legal tribunal Broken out by method type Accepted, not accepted, rejected, supported, other reference

6 Frequency of Delay Analysis Methods in Case Law: United States Method: Time Impact Analysis Collapsed As-built As-built Critical Path Impacted As-planned As-planned v. As-built Source: W. Stephen Dale and Robert M. D Onofrio, Construction Schedule Delays, Thomson Reuters (2015). (133 total)

7 Total Time / As-Planned v As-Built The device of comparing the as-built progress with the original planning is a worthy and time-honored method of identifying critical delays. Norair Engineering Corp., ENG BCA 3804, et al., 90-1 BCA 22,327, at 112,204

8 Total Time / As-Planned v As-Built Not a CPM method Does not consider: Causation Concurrency Acceleration Float

9 Total Time / As-Planned v As-Built It is well settled that this total time theory of proving delay is insufficient to meet the contractor's burden to prove that government-caused delay actually delayed the overall completion of the project. The total time approach to proving delay is as unsatisfactory as the 'total cost' method of proving damages, because it assumes that the government is responsible for all of the delay. Morganti Nat l, Inc. v. United States, 49 Fed. Cl. 110, 134 (2001)

10 Total Time / As-Planned v As-Built When has it been accepted? Liability for delay is clear Equities favor recovery despite proof problems Awards based on jury verdict approach

11 Total Time / As-Planned v As-Built The ascertainment of damages is not an exact science, and where responsibility for damage is clear, it is not essential that the amount thereof be ascertainable with absolute exactness or mathematical precision: It is enough if the evidence adduced is sufficient to enable a court or jury to make a fair and reasonable approximation. Bath Iron Works Corp., ASBCA No , B.C.A. 33,158 (citations omitted)

12 Total Time / As-Planned v As-Built [C]ategorical statements that where delays are caused on both sides there is no way to apportion damages are an absurdity. Damages are not being apportioned. Damages are liquidated. Quantum of delay in terms of time is all that is being apportioned. That is an uncomplicated fact finding process. That is what courts are for. Nomellini Constr. Co. v. California, 19 Cal.App.3d 240, 246 (1971)

13 Impacted As-Planned The purpose of his As-Adjusted Schedule is to show the time extension that Teer asserts it should have received for the easement delays if it had continued to perform pursuant to the original schedule and had maintained, to the extent [Teer s expert] considered possible, the durations, restraints, and sequence of activities contained in the original schedule. Appeal of Nello L. Teer Co., 86-3 BCA P (1986).

14 Impacted As-Planned Analyses made after project completion, however, that make adjustments to attain new and revised projected scheduling depend on theoretical contingencies. They are of limited value. The calculations reflect a theoretical application to a CPM as-planned schedule that was not intended to be followed. The calculations disregard the facts that actually existed in on-site operations. Titan Pacific Construction Corp. v. United States, 17 Cl. Ct. 630, (1989)

15 Impacted As-Planned Disfavored (4C s not present) Not credible does not consider what actually happened on the project Not consistent - does not consider own party s delays Not comprehensive does not consider shifts in the critical path does not consider or masks concurrency

16 Impacted As-Planned Can be Cogent and Credible: Gulf Contracting, Inc. ASBCA Nos , 30195, 33867, 89-2 BCA 21,812, aff d, Gulf Contracting, Inc. v. United States, 23 Cl. Ct. 525, 526 (1991) aff d, 972 F.2d 1353 (Fed. Cir. 1992). Prevailed over As-built analysis Contractor analysis inherently biased ignored known contractor delays Government presentation Expert with advanced technical and construction management degrees. took into account all of the time extensions granted by modifications supported by the extensive record before us

17 Impacted As-Planned Disfavored George Sollitt Const. Co. v. U.S., 64 Fed.Cl. 229 (2005). Contractor s expert prepared 2 analyses Contractor considered the IAP more reliable Both updates & baseline were known to be inaccurate Updates win: there was no evidence presented that indicated that these updated CPM schedules were less accurate than the baseline CPM schedules.

18 Impacted As-Planned Disfavored Craft Machine Works, Inc., ASBCA No , 97-1 BCA 28,651. Impacted As-planned v. As-planned/as-built Both rejected Deviated from the CPM updates Did not incorporate the contemporaneous schedule updates Failed to accurately reflect the progress of the work Board performed its own analysis

19 As-Built Critical Path We find ourselves in the rather unique situation of being asked to determine the number of days of additional Contract performance time to which PJD is entitled by referencing a CPM that both parties agree was properly constituted in its logic and assiduously and properly maintained throughout Contract performance. This circumstance is in sharp contrast to the usual problems we encounter in dealing with CPMs where warring as built schedules are constructed by the parties after the fact because the CPM was either never properly or timely prepared or was not updated in accordance with contract scheduling requirements. P.J. Dick Inc., VABCA-5597, , , , , , 6483, BCA 31,647

20 As-Built Critical Path The Good: Based on known facts an historic analysis of the project and its delays Identifies the actual, longest path of activities that can be traced from project start to project finish Highlights events that, in hindsight, delayed the actual progress of the work Along with the baseline schedule, the as-built schedule, more specifically the as-built schedule data, is one of the most important source data for most types of forensic schedule analysis methods. Even methods that do not directly use the as-built schedule, such as the modeled additive methods, often refer to the as-built schedule data to test the reasonableness of the model. AACEI 2.2 at 23 (2011).

21 As-Built Critical Path The Bad: At the mercy of existing data Poor, inaccurate, or incomplete records can make the sequencing suspect and conclusions drawn from that sequencing doubtful Cost and time involved in accurately recreating a project from available records Can ignore float and the logic of CPM schedules Loss of context Can elevate a delay to critical status that, at the time of performance, was not considered critical or only became critical

22 As-Built Critical Path Concerns: In the absence of a schedule or other standard for performance, the as built does not depict a critical path, float, or critical delay. It does not depict how much work was done only that some was done on the date entered. It does not depict the contract completion date. It does not list the original contract schedule, the revised contract schedule, or any dates upon which work was planned in the CPM schedules. It depicts that work was done but does not indicate what manning or manpower appellant used to accomplish that work or indicate what subcontractor performed that work. It does not indicate whether the work conformed to the contract or how efficiently it was performed. It does not indicate whether appellant s workers were standing by if they performed no work. Santa Fe Engineers, Inc., ASBCA Nos , 24578, 25838, 94-2 BCA 26, 872

23 As-Built Critical Path Cogefar-Impresit USA, DOTCAB No. 2721, 97-2 BCA 29,188 As-Built v. Windows approach Windows loses not indictment of method Failure of analyst to account for known impacts As-Built ignored concurrency We are not convinced that this is a valid method of assessing responsibility for delay in contract performance.

24 As-Built Critical Path Yet, these experts of impeccable credentials, attempt to convince the Board that their methods of delay analysis are scientific and precise. Given this evidence, we question the precision and value of CPM analysis. We find that there is some merit to each side s position. Our analysis takes into account the experts contrary opinions, but we give most weight to the other evidence in the record, and draw the logical conclusions flowing therefrom. Cogefar -Impresit USA, DOTCAB No. 2721, 97-2 BCA 29,188.

25 As-Built Critical Path Found valid when the 4 C s are present: provided a reliable, comprehensive analysis regarding the sequence of contract performance. cogent and credible testimony was helpful, because no documents, including plaintiff s updates, or witnesses presented as coherent a picture of the EC/L Project s work sequence. The extant documentary record is consistent with [defendant s delay expert] s as-built analysis. Sunshine Const. & Engineering, Inc. 64 Fed Cl. 346 (2005).

26 As-Built Critical Path Word of Warning The Necessity of Documentary Evidence Appellant s failure to prepare and maintain these records is clearly inexcusable in light of the clear contract requirement that this type of information be provided to maintain the accuracy of the CPM schedule. Santa Fe Engineers, Inc. ASBCA Nos , 25838, 28687, 94-2 BCA 26,872.

27 As-Built Critical Path Word of Warning The Necessity of Documentary Evidence We are unable to accept appellant s delay expert s opinion as being reliable because for the most part we were unable to verify his opinions by looking at the factual data he relied upon. His analysis was in most part based upon unidentified information in change order and claims issue files and an analysis of his as built schedule without demonstrating how he utilized that schedule in reaching his conclusions for particular issues. Santa Fe Engineers, Inc. ASBCA Nos , 25838, 28687, 94-2 BCA 26,872.

28 Collapsed As-Built Summary of Legal Concerns: Hindsight only Contemporaneous thinking irrelevant Often based on recreated events Contingent on quality of the records Relies on the analyst s judgment Can mask Work sequences Concurrency Acceleration

29 Collapsed As-Built A cautionary tale: Youngdale & Sons Const. Co., Inc. v. U.S 27 Fed.Cl. 516 (1993) Problems aplenty: Underbid Differing site conditions (water, rock) Total Cost claim

30 Collapsed As-Built Youngdale & Sons: Schedule analysis Collapsed As-Built Based on three schedules the As Planned Schedule, the As Built Schedule, and the As Built No Delays Schedule Riddled with errors questionable as a tool to prove plaintiff's entitlement

31 Collapsed As-Built Accordingly, based on the record as a whole, the court is compelled to conclude that plaintiff's expert's report is not sufficiently credible to carry its burden by the requisite quantum of proof in light of (i) the manner in which various aspects of the report were prepared, (ii) the inability of the court to determine the precise effect the errors in plaintiff's report had on the overall delay claim of 206 days, and (iii) the lack of probative evidence as to what delays were specifically attributable to the defendant or to the plaintiff, given that plaintiff's but-for schedule was discredited by plaintiff's own expert witness. 27 Fed.Cl. at 553.

32 Collapsed As-Built How to discredit an analysis: I did not put a lot of care into this I didn't evaluate it, I didn't look at it. I just took a very rough approach to it. The result is that we have these errors. I apologize. Since I submitted this to the Court, I should have double checked for these errors. Youngdale & Sons Const. Co., Inc. v. U.S 27 Fed.Cl. 516 (1993)

33 Collapsed As-Built Donohoe Construction Co. No objection from the Board on method Adopted most of the method for its own analysis Concern from the Board about conclusions Ignored float Obscured resequencing

34 Collapsed As-Built ADT Construction Group, Inc. ASBCA No , BCA 34,200. Refers expressly to the as-built collapsed schedule analysis methodology Succeeded only by comparison Government used impacted as-planned approach Board used comparators more credible and more persuasive Modified some of the collapsed as-built findings

35 Collapsed As-Built There are circumstances where the use of [collapsed as-built method] is not only proper, but necessary, for example, where no contemporaneous schedules exist. Kenji Hoshino (Comments on the AACE Recommended Practice for Forensic Schedule Analysis, at ABA Forum 2010 Annual Meeting) But see, Amelco Electric, VABCA 3785, 96-2 BCA (1996) Contractor failed to submit schedule updates Board rejected as-built critical path and collapsed as-built analyses

36 Time Impact Analysis (Prospective) George Sollitt Constr. Co. v. United States. 64 Fed. Cl. 229 (2005). Contractor did not provide CPM updates Where updates were provided, not always useful.

37 Time Impact Analysis (Prospective) Submitting monthly updated CPM schedules was a contract requirement. Sollitt may not excuse its failure to enter delaying events on the CPM schedule updates because of the Navy s alleged failure to grant timely extensions based on those delays. If Sollitt s updated CPM schedules are of limited use in meeting its burden of establishing the critical path of the project, Sollitt is now facing the consequences of its own performance of the contract requirement to provide updated CPM schedules. George Sollitt Const. Co. v. U.S., 64 Fed.Cl. 229, 251 (2005).

38 Time Impact Analysis (Prospective) Judicial preference for retrospective Harrison Western Corp. And Franki Denys, Inc. (JV) ENGBCA Nos. 5556, 5576, 93-1 BCA What the cases say is that changes in the work and time extensions must be incorporated promptly in the progress analysis, or the critical path chart will not accurately reflect current project status. This is a statement of the obvious. What the cases say further, and what Appellant ignores, is that the successive CPM documents must reflect actual events to be useful.

39 Time Impact Analysis (Prospective) Appellant's theory would permit a claimant to establish entitlement to delay compensation as of a time months or, perhaps years, before contract completion. The fundamental requirement of contract law to mitigate damages, and thus avoid social waste, would apparently not apply because the right to compensation would be fixed. Harrison Western Corp. And Franki Denys, Inc. (JV) ENGBCA Nos. 5556, 5576, 93-1 BCA

40 Time Impact Analysis (Prospective) The utility of the scheduling provision drafted by WMATA and included in the contract is to resolve such disputes when the information is fresh and clear, not looking backward through the haze of months and years. By any standard, it is fair to the parties to adhere to such a scheduling provision. Harrison Western Corp. And Franki Denys, Inc. (JV) ENGBCA Nos. 5556, 5576, 93-1 BCA

41 Time Impact Analysis (Prospective) It is not fair, particularly for the party which drafted the provision, to use it only when it perceives that such use is to its advantage and discard it when the perception is otherwise. It is clear to me that such is what has happened in this case. Harrison Western Corp. And Franki Denys, Inc. (JV) ENGBCA Nos. 5556, 5576, 93-1 BCA

42 Time Impact Analysis (adjusted) Project Scheduling is Dynamic A contractor's initial network analysis is not cast in bronze; it is constantly changing; that is the advantage of the critical path method of scheduling. The impact of each change, or delay, on the previously charted sequences must be fitted into the network. The effect may be far-reaching. Norair Eng g. Corp., ENG BCA 3804, et al., 90-1 BCA 22,327, at 112,205

43 Time Impact Analysis (adjusted) Timing is important - Activities which were not critical prior to the new event may be rendered critical; and conversely, formerly critical activities may develop float. Whether the change or delay affects the critical path must be determined on the basis of conditions existing immediately prior to its occurrence. Norair Eng g. Corp., ENG BCA 3804, et al., 90-1 BCA 22,327, at 112,205

44 Time Impact Analysis (adjusted) [T]he only way to accurately assess the effect of the delays alleged [on the] project's progress is to contrast updated CPM schedules prepared immediately before and immediately after each purported delay. Blinderman Const. Co., Inc. v. U.S., 39 Fed.Cl. 529 (1997)

45 Time Impact Analysis (adjusted) SAE/Americon - Mid Atlantic, Inc., GSBCA Nos , 12523, 12690, 12710, 12841, 12842, 12907, 98-2 BCA 30,084. Contract requirement for time impact analysis Government rejected SAE s updates, revisions, and workarounds during performance Government provided no schedule expert at trial [D]etailed, comprehensive analysis that also accounted for concurrency

46 Time Impact Analysis (Windows) Bell / BCI Company v. United States, Bell / BCI Company V. United States, 81 Fed.Cl. 617 (2008). Contract requirement for time impact analysis Contractor expert provided framework for court s decision Government schedule expert not credible with unsupported conclusions Impact of good faith and fair dealing issues

47 Time Impact Analysis (Windows) Cogefar-Impresit U.S.A., Inc., DOTCAB No. 2721, 97-2 BCA 29,188. Government prepared Windows analysis Dispute regarding updated schedules Government-approved updates were not used to manage the project Approach overlooked a significant and well-known delay event

48 Time Impact Analysis (Windows) [The Government s expert] failed to use a current CPM schedule to evaluate the delay on the project. This is mandatory to achieve an accurate assessment of whether an item of delay affects the overall completion of the project. Cogefar-Impresit U.S.A., Inc., DOTCAB No. 2721, 97-2 BCA 29,188 (citations omitted).

49 Time Impact Analysis (Windows) Old Dominion Electric Coop. v. Ragnar Benson, Inc., Civil Action No. 3:05cv34, 2006 U.S. Dist. LEXIS (E.D. Va 2006). Initial schedule submittals suffered from significant logic problems 3rd scheduler found the schedule so flawed that it would have been easier to throw it out and start from scratch. In a windows analysis, the windows are selected on a subjective basis. One can affect the outcome of the analysis by how one chooses the windows. By selectively choosing the milestones and windows, the results can be controlled.

50 Impacted As-planned As-built critical Collapsed asbuilt Time Impact Analysis Original Plan Schedule Schedule Updates As-Built Schedule Chronology of the Delay Delay Absorbing Float Concurrent Delay Offsetting delay Pushed into a Non-Work Period Shift in the critical path Resequencing / Acceleration Constructive Acceleration Methodology Comparison Methodology TIA (adjusted) Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Windows (unadjusted) Yes Yes Yes Yes Yes Yes No Yes Yes Yes Yes Prospective TIA Yes Yes Yes Yes Yes No Yes Yes Yes Yes Yes Window wide periods Yes Yes Yes No No No No No No No No Multiple period using updates No Yes Yes No No No No Yes Yes No No Collapse stepped removal No No Yes No No No No No No No No Remove owner No No Yes No No No No No No No No Remove contractor No No Yes No No No No No No No No path using No Yes Yes Yes No No No No Yes No No updates pathcritical As-built path No No Yes No No No No No No No No Stepped insertion Yes No No No No No No Yes No No No Total time Global Yes No No No No No No No No No No Compare owner/contractor Yes No No No No No No No No No No As-planned v as-built Yes No Yes No No No No No No No No Source: W. Stephen Dale and Robert M. D Onofrio, Construction Schedule Delays, Thomson Reuters (2015).

51 Acceptance Percentage of Delay Methods - United States 100% 90% 80% 70% 60% 60% 50% 40% 30% 30% 20% 10% 0% 14% 15% 7% Method: Time Impact Analysis Collapsed As-built As-built Critical Path Impacted As-planned As-planned v. As-built Source: W. Stephen Dale and Robert M. D Onofrio, Construction Schedule Delays, Thomson Reuters (2015).

52 Frequency of Delay Analysis Methods in Case Law: United States Method: Time Impact Analysis Collapsed As-built As-built Critical Path Impacted As-planned As-planned v. As-built Source: W. Stephen Dale and Robert M. D Onofrio, Construction Schedule Delays, Thomson Reuters (2015). (133 total)

53 Frequency of Delay Analysis Methods in Case Law: Global Time Impact Analysis Time Impact Analysis Windows Prospective TIA Collapsed As-built As-built Critical Path Impacted As-planned As-planned v. As-built (177 total) Source: W. Stephen Dale and Robert M. D Onofrio, Construction Schedule Delays, Thomson Reuters (2015).

54 Acceptance Percentage of Delay Methods All Global Jurisdictions 100% Time Impact Analysis 90% 80% 70% 70% 64% 60% 50% 50% 40% 30% 20% 10% 21% 14% 23% 13% 0% Time Impact Analysis Windows Prospective TIA Collapsed As-built As-built Critical Path Impacted As-planned As-planned v. As-built (177 total) Source: W. Stephen Dale and Robert M. D Onofrio, Construction Schedule Delays, Thomson Reuters (2015).

55 W. Stephen Dale, SVP and General Counsel, WSP Parsons Brinckerhoff Raymond L. DeLuca, Partner, Pepper Hamilton LLP Robert M. D Onofrio, P.E., Principal, Capital Project Management, Inc.

56

Consulting Newsletter

Consulting Newsletter : Spring Our Spring, newsletter, contains two articles. The first is an article titled Productivity and Efficiency. The article, as the name implies, gives an insight into these two important subjects.

More information

FORENSIC PLANNING DELAY ANALYSIS, EXPERT WITNESS, CLAIMS AND CONTRACT ADMINISTRATION SERVICES

FORENSIC PLANNING DELAY ANALYSIS, EXPERT WITNESS, CLAIMS AND CONTRACT ADMINISTRATION SERVICES FEARNSIDES AND ASSOCIATES FORENSIC PLANNING DELAY ANALYSIS, EXPERT WITNESS, CLAIMS AND CONTRACT ADMINISTRATION SERVICES File Note- 001-Delay Methodology-18-July-16 Subject: Delay Analysis Methodology 1.

More information

COST LOADED CONSTRUCTION SCHEDULES PART 1 - GENERAL

COST LOADED CONSTRUCTION SCHEDULES PART 1 - GENERAL SECTION 01310 COST LOADED CONSTRUCTION SCHEDULES PART 1 - GENERAL 1.01 SCOPE: A. COST LOADED CONSTRUCTION SCHEDULE (Construction Schedule): The WORK under this Contract shall be planned, scheduled, executed,

More information

FORENSIC SCHEDULE ANALYSIS CHAPTER 2: DELAY ANALYSIS ON NON-CPM SCHEDULED PROJECTS 1

FORENSIC SCHEDULE ANALYSIS CHAPTER 2: DELAY ANALYSIS ON NON-CPM SCHEDULED PROJECTS 1 GLOBAL CONSTRUCTION FORENSIC SCHEDULE ANALYSIS CHAPTER 2: DELAY ANALYSIS ON NON-CPM SCHEDULED PROJECTS 1 By Steven A. Collins 2 and James G. Zack, Jr., CCM, CFCC, FAACE, FRICS, PMP 3 Association for the

More information

Andrew Avalon, P.E., PSP

Andrew Avalon, P.E., PSP Andrew Avalon, P.E., PSP LONG INTERNATIONAL Long International, Inc. 5265 Skytrail Drive Littleton, Colorado 80123-1566 USA Telephone: (303) 972-2443 Fax: (303) 200-7180 www.long-intl.com Andrew Avalon,

More information

Forensic Schedule Analysis and Discretionary Logic

Forensic Schedule Analysis and Discretionary Logic TECHNICAL ARTICLE Forensic Schedule Analysis and Discretionary Logic John C. Livengood Esq., CCP CFCC PSP FAACE Abstract: Forensic Schedule Analysis (FSA) and real time schedule reviews do not handle CPM

More information

1997 Part 2. Document B141. Standard Form of Architect's Services: Design and Contract Administration TABLE OF ARTICLES

1997 Part 2. Document B141. Standard Form of Architect's Services: Design and Contract Administration TABLE OF ARTICLES TM Document B141 Standard Form of Architect's Services: Design and Contract Administration 1997 Part 2 TABLE OF ARTICLES 2.1 PROJECT ADMINISTRATION SERVICES 2.2 SUPPORTING SERVICES 2.3 EVALUATION AND PLANNING

More information

LONG INTERNATIONAL. Richard J. Long, P.E., Andrew Avalon, P.E., PSP and Ronald J. Rider, MBA

LONG INTERNATIONAL. Richard J. Long, P.E., Andrew Avalon, P.E., PSP and Ronald J. Rider, MBA Richard J. Long, P.E., Andrew Avalon, P.E., PSP and Ronald J. Rider, MBA LONG INTERNATIONAL Long International, Inc. 5265 Skytrail Drive Littleton, Colorado 80123-1566 USA Telephone: (303) 972-2443 Fax:

More information

Principles of Schedule Contingency Management

Principles of Schedule Contingency Management Principles of Schedule Contingency Management Ted Douglas, CCC, PSP ACTPMA, LLC Consulting 2014 Construction CPM Conference Orlando, Florida Schedule Contingency Management Background Outline of Presentation

More information

Scott M. Francis, P.E., PSP

Scott M. Francis, P.E., PSP Scott M. Francis, P.E., PSP LONG INTERNATIONAL Long International, Inc. 5265 Skytrail Drive Littleton, Colorado 80123-1566 USA Telephone: (303) 972-2443 Fax: (303) 200-7180 www.long-intl.com Scott M. Francis,

More information

SCHEDULE DELAY IN CONSTRUCTION PROJECT USING TIME IMPACT ANALYSIS

SCHEDULE DELAY IN CONSTRUCTION PROJECT USING TIME IMPACT ANALYSIS International Journal of Civil, Structural, Environmental and Infrastructure Engineering Research and Development (IJCSEIERD) ISSN(P): 2249-6866; ISSN(E): 2249-7978 Vol. 3, Issue 5, Dec 2013, 53-64 TJPRC

More information

Managing Schedule Change

Managing Schedule Change Managing Schedule Change Ted Douglas, CCP, PSP, FAACE CPM Construction Conference Orlando, Florida January 11, 2017 Managing Schedule Change Outline Change Drivers Contract Changes Clause Schedule Change

More information

Document B101 TM. Standard Form of Agreement Between Owner and Architect

Document B101 TM. Standard Form of Agreement Between Owner and Architect Document B101 TM 2007 Standard Form of Agreement Between Owner and Architect AGREEMENT made as of the day of in the year (In words, indicate day, month and year.) BETWEEN the Architect s client identified

More information

Consulting Newsletter

Consulting Newsletter Spring 2014 Newsletter In this, our 2014 Spring newsletter, are 2 articles. The first article is Programme Review and Acceptance. Our second article is titled, Acceleration Roger Gibson June 2014 PROGRAMME

More information

Questions And Answers. Conducting Effective Internal Investigations

Questions And Answers. Conducting Effective Internal Investigations Questions And Answers Conducting Effective Internal Investigations Kevin J. Smith and Lindsay R. Colvin Stone Conducting internal investigations in the wake of an employee complaint can be an overwhelming

More information

Foreword Acknowledgments Introduction to Second Edition

Foreword Acknowledgments Introduction to Second Edition Contents Foreword Acknowledgments Introduction to Second Edition xi xiii xv Chapter 1: Project Scheduling 1 The Project Schedule 1 The Purpose of a Project Schedule 2 Types of Project Schedules 3 What

More information

UNITED STATES DISTRICT COURT DISTRICT OF MASSACHUSETTS

UNITED STATES DISTRICT COURT DISTRICT OF MASSACHUSETTS Amgen Inc. v. F. Hoffmann-LaRoche LTD et al Doc. 976 Case 1:05-cv-12237-WGY Document 976 Filed 09/03/2007 Page 1 of 5 UNITED STATES DISTRICT COURT DISTRICT OF MASSACHUSETTS AMGEN INC., Plaintiff, v. CIVIL

More information

CRF News. Vendors sometimes enter into consignment. Credit Research Foundation. 2nd Qtr.

CRF News. Vendors sometimes enter into consignment. Credit Research Foundation. 2nd Qtr. Credit Research Foundation CRF News www.crfonline.org 2016 The Benefits of Properly Documenting a Consignment Transaction and the Potential For Recovery By Creditors that Don t! By Bruce S. Nathan, David

More information

Ronald J. Rider, MBA

Ronald J. Rider, MBA Ronald J. Rider, MBA LONG INTERNATIONAL Long International, Inc. 5265 Skytrail Drive Littleton, Colorado 80123-1566 USA Telephone: (303) 972-2443 Fax: (303) 200-7180 www.long-intl.com Ronald J. Rider,

More information

Richard J. Long, P.E.

Richard J. Long, P.E. Richard J. Long, P.E. LONG INTERNATIONAL Long International, Inc. 5265 Skytrail Drive Littleton, Colorado 80123-1566 USA Telephone: (303) 972-2443 Fax: (303) 200-7180 www.long-intl.com Construction Contract

More information

Professional Practice 544

Professional Practice 544 February 22, 2016 February 29, 2016 Professional Practice 544 AIA-B101 Owner - Architect Agreement Michael J. Hanahan Schiff Hardin LLP 233 S. Wacker, Ste. 6600 Chicago, IL 60606 312-258-5701 mhanahan@schiffhardin.com

More information

STATEMENT OF AUDITING STANDARDS 500 AUDIT EVIDENCE

STATEMENT OF AUDITING STANDARDS 500 AUDIT EVIDENCE STATEMENT OF AUDITING STANDARDS 500 AUDIT EVIDENCE (Issued January 2004) Contents Paragraphs Introduction 1-2 Concept of Audit Evidence 3-6 Sufficient Appropriate Audit Evidence 7-14 The Use of Assertions

More information

IN THE UNITED STATES DISTRICT COURT FOR THE EASTERN DISTRICT OF PENNSYLVANIA. Goldberg, J. July 10, 2014 MEMORANDUM OPINION

IN THE UNITED STATES DISTRICT COURT FOR THE EASTERN DISTRICT OF PENNSYLVANIA. Goldberg, J. July 10, 2014 MEMORANDUM OPINION IN THE UNITED STATES DISTRICT COURT FOR THE EASTERN DISTRICT OF PENNSYLVANIA DAVID VERDERAME, : CIVIL ACTION Plaintiff, : : v. : No. 2:13-2539 : RADIOSHACK CORPORATION, : Defendant. : : Goldberg, J. July

More information

Measuring Effectiveness of Regulatory Agencies

Measuring Effectiveness of Regulatory Agencies Measuring Effectiveness of Regulatory Agencies Legitimacy, Credibility and Transparency Seminário de Regulação do Cone Sul Foz do Iguaçú, PR, Brazil March 27, 2006 Ashley C. Brown Executive Director, Harvard

More information

THE CONTRACTS GROUP LTD. THE SOCIETY OF CONSTRUCTION LAW DELAY & DISRUPTION PROTOCOL 2 nd Edition

THE CONTRACTS GROUP LTD. THE SOCIETY OF CONSTRUCTION LAW DELAY & DISRUPTION PROTOCOL 2 nd Edition THE CONTRACTS GROUP LTD. THE SOCIETY OF CONSTRUCTION LAW DELAY & DISRUPTION PROTOCOL 2 nd Edition 18 January 2017 SCL Delay & Disruption Protocol 2 nd Edition INTRODUCTION TIME - Methods of Delay Analysis

More information

UNITED STATES DISTRICT COURT EASTERN DISTRICT OF WASHINGTON. Defendant. BEFORE THE COURT is Defendant s Motion and Memorandum for

UNITED STATES DISTRICT COURT EASTERN DISTRICT OF WASHINGTON. Defendant. BEFORE THE COURT is Defendant s Motion and Memorandum for Case :-cv-000-tor Document Filed 0// UNITED STATES DISTRICT COURT EASTERN DISTRICT OF WASHINGTON 0 MARK WHITE, v. Plaintiff, AG SUPPLY COMPANY OF WENATCHEE, Defendant. NO: :-CV-00-TOR ORDER GRANTING DEFENDANT

More information

Kurniawan v. Atty Gen USA

Kurniawan v. Atty Gen USA 2006 Decisions Opinions of the United States Court of Appeals for the Third Circuit 12-18-2006 Kurniawan v. Atty Gen USA Precedential or Non-Precedential: Non-Precedential Docket No. 05-4593 Follow this

More information

John F. Myers, Attorney at Law

John F. Myers, Attorney at Law John F. Myers, Attorney at Law Title VII of the Civil Rights Act of 1964 makes it illegal for an employer to discriminate in the workplace on basis of race, sex, national origin, religion, or national

More information

Compilation Engagements

Compilation Engagements SINGAPORE STANDARD ON RELATED SERVICES SSRS 4410 (REVISED) Compilation Engagements This revised Singapore Standard on Related Services (SSRS) 4410 supersedes SSRS 4410 Engagements to Compile Financial

More information

Concise Case Analysis & Evaluation Tool

Concise Case Analysis & Evaluation Tool International Mediation Institute www.imimediation.org Concise Case Analysis & Evaluation Tool Olé is a process to help you to analyze and assess specific disputes in order to determine the best possible

More information

Report on Inspection of Deloitte LLP (Headquartered in Toronto, Canada) Public Company Accounting Oversight Board

Report on Inspection of Deloitte LLP (Headquartered in Toronto, Canada) Public Company Accounting Oversight Board 1666 K Street, N.W. Washington, DC 20006 Telephone: (202) 207-9100 Facsimile: (202) 862-8433 www.pcaobus.org Report on 2014 (Headquartered in Toronto, Canada) Issued by the Public Company Accounting Oversight

More information

SPECIFICATIONS - DETAILED PROVISIONS Section Project Control Schedule C O N T E N T S

SPECIFICATIONS - DETAILED PROVISIONS Section Project Control Schedule C O N T E N T S SPECIFICATIONS - DETAILED PROVISIONS Section 01310 - Project Control Schedule C O N T E N T S PART 1 - SCHEDULE REQUIREMENTS PROGRESS SCHEDULE... 1 PART 2 - SUBMITTAL PROCEDURES... 2 PART 3 - DEFINITIONS...

More information

Claims. Calvey Consulting, LLC Settlers Passage Cleveland, OH

Claims. Calvey Consulting, LLC Settlers Passage Cleveland, OH Managing Construction Claims Calvey Consulting, LLC 8473 Settlers Passage Cleveland, OH 44141 440-740-1132 Managing Construction Claims Why are Claims are disputed. What is Typical Claim What does a Consultant

More information

WORKPLACE RELATIONS REFORM

WORKPLACE RELATIONS REFORM WORKPLACE RELATIONS REFORM Introduction The Minister for Jobs, Enterprise and Innovation, Mr Richard Bruton T.D. proposes to replace the current complex and outdated workplace relations employment rights

More information

Report on Inspection of KPMG Auditores Consultores Ltda. (Headquartered in Santiago, Republic of Chile)

Report on Inspection of KPMG Auditores Consultores Ltda. (Headquartered in Santiago, Republic of Chile) 1666 K Street, N.W. Washington, DC 20006 Telephone: (202) 207-9100 Facsimile: (202) 862-8433 www.pcaobus.org Report on 2016 (Headquartered in Santiago, Republic of Chile) Issued by the Public Company Accounting

More information

CONTEMPORARY APPROACHES TO PROJECT RISK MANAGEMENT: ASSESSMENT & RECOMMENDATIONS

CONTEMPORARY APPROACHES TO PROJECT RISK MANAGEMENT: ASSESSMENT & RECOMMENDATIONS CONTEMPORARY APPROACHES TO PROJECT RISK MANAGEMENT: ASSESSMENT & RECOMMENDATIONS Prepared by: Mohamed Noordin Yusuff IT Security Officer Dip.ECC, SDip.IS, M.IntSecMgmt(Distinction) 1 INTRODUCTION In order

More information

NATIONAL ARBITRATION BEFORE IMPARTIAL ARBITRATOR STEPHEN B. GOLDBERG. U. S. POSTAL SERVICE ) Case No. Q10C-4Q-C

NATIONAL ARBITRATION BEFORE IMPARTIAL ARBITRATOR STEPHEN B. GOLDBERG. U. S. POSTAL SERVICE ) Case No. Q10C-4Q-C NATIONAL ARBITRATION BEFORE IMPARTIAL ARBITRATOR STEPHEN B. GOLDBERG In the Matter of Arbitration ) between ) U. S. POSTAL SERVICE ) Case No. Q10C-4Q-C 15206043 and ) AMERICAN POSTAL WORKERS ) UNION, AFL-CIO

More information

Case5:12-cv LHK Document737 Filed08/14/13 Page1 of 7 UNITED STATES DISTRICT COURT NORTHERN DISTRICT OF CALIFORNIA SAN JOSE DIVISION

Case5:12-cv LHK Document737 Filed08/14/13 Page1 of 7 UNITED STATES DISTRICT COURT NORTHERN DISTRICT OF CALIFORNIA SAN JOSE DIVISION Case:-cv-000-LHK Document Filed0// Page of 0 0 APPLE INC., a California corporation v. Plaintiff, SAMSUNG ELECTRONICS CO. LTD., a Korean business entity; SAMSUNG ELECTRONICS AMERICA, INC., a New York corporation;

More information

SACKETT v. SPINDLER California Court of Appeal 248 Cal. App. 2d 220, 56 Cal. Rptr. 435 (1967)

SACKETT v. SPINDLER California Court of Appeal 248 Cal. App. 2d 220, 56 Cal. Rptr. 435 (1967) SACKETT v. SPINDLER California Court of Appeal 248 Cal. App. 2d 220, 56 Cal. Rptr. 435 (1967) MOLINARI, P. J. SIMS, J., and BRAY, J., concurred. MOLINARI, P. J. Plaintiff and cross-defendant, Sheldon Sackett,

More information

Decision. Contrack International, Inc.-Costs. Matter of: B File: Date: February 17, 2010

Decision. Contrack International, Inc.-Costs. Matter of: B File: Date: February 17, 2010 United States Government Accountability Office Washington, DC 20548 Decision Comptroller General of the United States DOCUMENT FOR PUBLIC RELEASE The decision issued on the date below was subject to a

More information

Exhibit B - A/E Scope of Services (General Contracting Project) State of Ohio Professional Services Agreements for Public Facility Construction

Exhibit B - A/E Scope of Services (General Contracting Project) State of Ohio Professional Services Agreements for Public Facility Construction - State of Ohio Professional Services Agreements for Public Facility Construction TABLE OF CONTENTS ARTICLE 1 - BASIC SERVICES... 1 ARTICLE 2 - PROGRAM VERIFICATION STAGE... 2 ARTICLE 3 - SCHEMATIC DESIGN

More information

GENERAL ASSEMBLY OF NORTH CAROLINA SESSION 2017 H 1 HOUSE BILL 366. Short Title: Retail Workers' Bill of Rights. (Public)

GENERAL ASSEMBLY OF NORTH CAROLINA SESSION 2017 H 1 HOUSE BILL 366. Short Title: Retail Workers' Bill of Rights. (Public) GENERAL ASSEMBLY OF NORTH CAROLINA SESSION 0 H 1 HOUSE BILL Short Title: Retail Workers' Bill of Rights. (Public) Sponsors: Referred to: Representatives Brockman, Fisher, Harrison, and Holley (Primary

More information

How do I dismiss an employee who is not performing?

How do I dismiss an employee who is not performing? How do I dismiss an employee who is not performing? The above question is one of the most common questions asked by our clients at CoLaw Employment Law Consultants. Most companies shy away from dealing

More information

Public Company Accounting Oversight Board

Public Company Accounting Oversight Board 1666 K Street, N.W. Washington, DC 20006 Telephone: (202) 207-9100 Facsimile: (202) 862-8433 www.pcaobus.org Report on 2008 (Headquartered in New York, New York) Issued by the Public Company Accounting

More information

Case 1:15-cv BCW Document 2 Filed 08/31/15 Page 1 of 9

Case 1:15-cv BCW Document 2 Filed 08/31/15 Page 1 of 9 Case 1:15-cv-00112-BCW Document 2 Filed 08/31/15 Page 1 of 9 Mark F. James (5295) Mitchell A. Stephens (11775) Justin L. James (15167) Hatch, James & Dodge, P.C. 10 West Broadway, Suite 400 Salt Lake City,

More information

A Structured Approach to Minimum Cost Recovery Scheduling

A Structured Approach to Minimum Cost Recovery Scheduling A Structured Approach to Minimum Cost Recovery Scheduling Chris Carson, PSP Project Controls Manager Alpha Corporation Norfolk, Virginia Email: chris.carson@alphacorporation.com Background Project management

More information

Compilation Engagements

Compilation Engagements IFAC Board Final Pronouncement March 2012 International Standard on Related Services ISRS 4410 (Revised), Compilation Engagements The International Auditing and Assurance Standards Board (IAASB) develops

More information

AGS 10. Joint Audits AUDIT GUIDANCE STATEMENT

AGS 10. Joint Audits AUDIT GUIDANCE STATEMENT AUDIT GUIDANCE STATEMENT AGS 10 Joint Audits This Audit Guidance Statement was approved by the Council of the Institute of Singapore Chartered Accountants (formerly known as Institute of Certified Public

More information

Law Firm of Keller W. Allen, P.C S. Regal St., Suite 211 Spokane, WA

Law Firm of Keller W. Allen, P.C S. Regal St., Suite 211 Spokane, WA The Problem Employee Who Abuses FMLA Intermittent Leave Presentation by Keller W. Allen 5915 S. Regal St., Suite 211 Spokane, WA 99223 Tel: 509-777-2211 Fax: 509-777-2215 kwa@kellerallen.com www.kellerallen.com

More information

TOWARDS A LIABILITY REGIME FOR ROAD CARRIAGE THE EUROPEAN EXPERIENCE: THE CMR CONVENTION

TOWARDS A LIABILITY REGIME FOR ROAD CARRIAGE THE EUROPEAN EXPERIENCE: THE CMR CONVENTION TOWARDS A LIABILITY REGIME FOR ROAD CARRIAGE THE EUROPEAN EXPERIENCE: THE CMR CONVENTION Stevens, F. AntwerpLaw Advocates. ABSTRACT Road transportation is, in most European countries, governed by the "CMR"

More information

construction solutions asia pacific

construction solutions asia pacific construction solutions asia pacific The outlook of the construction industry within the Asia Pacific region remains strong, however pressures to successfully deliver projects against a backdrop of finite

More information

Report on Inspection of KPMG AG Wirtschaftspruefungsgesellschaft (Headquartered in Berlin, Federal Republic of Germany)

Report on Inspection of KPMG AG Wirtschaftspruefungsgesellschaft (Headquartered in Berlin, Federal Republic of Germany) 1666 K Street, N.W. Washington, DC 20006 Telephone: (202) 207-9100 Facsimile: (202) 862-8433 www.pcaobus.org Report on 2016 (Headquartered in Berlin, Federal Republic of Germany) Issued by the Public Company

More information

Guidance for Rating Each Performance Category on Contractor Performance Evaluation

Guidance for Rating Each Performance Category on Contractor Performance Evaluation Guidance for Rating Each Performance Category on Contractor Performance Evaluation Section 1: KNOWLEDGE Knowledge of WSSC Standards (Details/Specifications) Extremely knowledgeable of WSSC standards. Contractor

More information

ARMED SERVICES BOARD OF CONTRACT APPEALS

ARMED SERVICES BOARD OF CONTRACT APPEALS ARMED SERVICES BOARD OF CONTRACT APPEALS Appeal of-- ) ) Dragados USA, Inc. ) ) Under Contract No. W912EP-08-C-0011 ) APPEARANCES FOR THE APPELLANT: APPEARANCES FOR THE GOVERNMENT: ASBCA No. 57664 Donald

More information

Joint Seminar on Project Management Techniques

Joint Seminar on Project Management Techniques Joint Seminar on Project Management Techniques. Scheduling Testing, Balancing & Commissioning. Thomas Carcaterra, P.E., LLC 1375 Piccard Drive Suite 225 Rockville, MD 20850 Tel: 301.330.6044 Presented

More information

CODE OF ETHICS AND CONDUCT

CODE OF ETHICS AND CONDUCT THE INTERNATIONAL SOCIETY OF AIR SAFETY INVESTIGATORS ISASI CODE OF ETHICS AND CONDUCT October 1983 15 19 Appendix A ISASI CODE OF ETHICS AND CONDUCT PREAMBLE As noted in the ISASI Bylaws, the purpose

More information

by Ron Winter Consulting LLC January 6, 2015

by Ron Winter Consulting LLC January 6, 2015 Schedule Analyzer by Ron Winter Consulting LLC January 6, 2015 Schedule Analyzer P6 version released in 2003 Over 150 updates since then Over 1,000 licenses sold Works with Oracle/Primavera P6 & EPPM Looks

More information

System Management Forum. Conformance Program Issue Tracking Process

System Management Forum. Conformance Program Issue Tracking Process 1 2 3 4 Document Number: Date: 2016-04-15 Version: 1.0.0 5 6 System Management Forum Conformance Program Issue Tracking Process 7 8 9 10 11 Supersedes: None Document Class: Informative Document Status:

More information

MTA EMPLOYMENT RELATIONS FACT SHEET

MTA EMPLOYMENT RELATIONS FACT SHEET MTA EMPLOYMENT RELATIONS FACT SHEET FAIR WORK ACT 2009 UNFAIR AND UNLAWFUL DISMISSAL 18 September 2009 Operative: On and from 1 July 2009 A fair go all round The Fair Work Act 2009 Part 3-2 Unfair dismissal

More information

What is the Department of Public Works Project Labor Agreement (DPW-PLA)?

What is the Department of Public Works Project Labor Agreement (DPW-PLA)? City of Los Angeles Department of Public Works PLA / Public Works Infrastructure Stabilization Policy Frequently Asked Questions for Project Labor Agreement 2015-2020 Please note: This document is meant

More information

Report on Inspection of KPMG SAS (Headquartered in Bogota, Republic of Colombia) Public Company Accounting Oversight Board

Report on Inspection of KPMG SAS (Headquartered in Bogota, Republic of Colombia) Public Company Accounting Oversight Board 1666 K Street, N.W. Washington, DC 20006 Telephone: (202) 207-9100 Facsimile: (202) 862-8433 www.pcaobus.org Report on 2016 (Headquartered in Bogota, Republic of Colombia) Issued by the Public Company

More information

EEOC Pay Equity Enforcement

EEOC Pay Equity Enforcement EEOC Pay Equity Enforcement January 24, 2013 Paul C. Evans Blair J. Robinson www.morganlewis.com Agenda EEOC Strategic Enforcement Plan Enforcing equal pay laws EEOC Investigations and Enforcement Investigative

More information

PS.08. Let s Scrap the Precedence Diagramming Method

PS.08. Let s Scrap the Precedence Diagramming Method 2004 AACE International Transactions PS.08 Let s Scrap the Precedence Diagramming Method Earl T. Glenwright Jr. THE STATE OF CONSTRUCTION SCHEDULING PRACTICES AND SCHEDULES WHY PRECEDENCE DIAGRAMMING WAS

More information

Report on Inspection of Grant Thornton Auditores Independentes (Headquartered in Sao Paulo, Federative Republic of Brazil)

Report on Inspection of Grant Thornton Auditores Independentes (Headquartered in Sao Paulo, Federative Republic of Brazil) 1666 K Street, N.W. Washington, DC 20006 Telephone: (202) 207-9100 Facsimile: (202) 862-8433 www.pcaobus.org Report on 2016 Auditores Independentes (Headquartered in Sao Paulo, Federative Republic of Brazil)

More information

A BUSINESS GUIDE TO THE ROBINSON-PATMAN ACT

A BUSINESS GUIDE TO THE ROBINSON-PATMAN ACT A BUSINESS GUIDE TO THE ROBINSON-PATMAN ACT MARK P. EDWARDS MORGAN, LEWIS & BOCKIUS LLP 1701 Market Street Philadelphia, PA 19103-2921 Direct: 215.963.5769 Main: 215.963.5000 Fax: 215.963.5001 medwards@morganlewis.com

More information

UNITED STATES COURT OF APPEALS FOR THE SECOND CIRCUIT. August Term (Argued: June 15, 2016 Decided: August 15, 2016) Docket No.

UNITED STATES COURT OF APPEALS FOR THE SECOND CIRCUIT. August Term (Argued: June 15, 2016 Decided: August 15, 2016) Docket No. 15 2776 Mago Int l, LLC v. LHB AG UNITED STATES COURT OF APPEALS FOR THE SECOND CIRCUIT August Term 2015 (Argued: June 15, 2016 Decided: August 15, 2016) Docket No. 15 2776 MAGO INTERNATIONAL, Plaintiff

More information

Report of the Court on the development of performance indicators for the International Criminal Court

Report of the Court on the development of performance indicators for the International Criminal Court 12 November 2015, 19:45 Report of the Court on the development of performance indicators for the International Criminal Court I. Introduction 1. The Assembly of States Parties 1 has requested the ICC to

More information

Report on Inspection of Deloitte & Associes (Headquartered in Neuilly-sur-Seine, French Republic) Public Company Accounting Oversight Board

Report on Inspection of Deloitte & Associes (Headquartered in Neuilly-sur-Seine, French Republic) Public Company Accounting Oversight Board 1666 K Street, N.W. Washington, DC 20006 Telephone: (202) 207-9100 Facsimile: (202) 862-8433 www.pcaobus.org Report on 2015 (Headquartered in Neuilly-sur-Seine, French Republic) Issued by the Public Company

More information

Open Access Transmission Tariff ATTACHMENT K

Open Access Transmission Tariff ATTACHMENT K ATTACHMENT K PART I Introduction The Transmission Provider s (herein referred to as Tacoma Power) local transmission planning process will include open planning meetings that Tacoma Power will conduct

More information

In a labor arbitration hearing recently conducted before Arbitrator Gutman, the parties collective bargaining agreement provided a three month

In a labor arbitration hearing recently conducted before Arbitrator Gutman, the parties collective bargaining agreement provided a three month In a labor arbitration hearing recently conducted before Arbitrator Gutman, the parties collective bargaining agreement provided a three month probationary period for all new hires which gave the employer

More information

Report on Inspection of KPMG Audit Limited (Headquartered in Hamilton, Bermuda) Public Company Accounting Oversight Board

Report on Inspection of KPMG Audit Limited (Headquartered in Hamilton, Bermuda) Public Company Accounting Oversight Board 1666 K Street, N.W. Washington, DC 20006 Telephone: (202) 207-9100 Facsimile: (202) 862-8433 www.pcaobus.org Report on 2015 (Headquartered in Hamilton, Bermuda) Issued by the Public Company Accounting

More information

Disciplinary actions made easy

Disciplinary actions made easy Disciplinary actions made easy Give appropriate recognition to employees behavior whether it is good, bad, ugly or indifferent. Set rules or boundaries If rule is unique to your worksite, make sure employee

More information

Commencement of Works vs commencement of Works Program (FIDIC Rainbow Conditions of Contracts)

Commencement of Works vs commencement of Works Program (FIDIC Rainbow Conditions of Contracts) Volume (5) Number (8) August 2015 J. Appl. Environ. Biol. Sci., 5(8)55-69, 2015 2015, TextRoad Publication ISSN: 2090-4274 Journal of Applied Environmental and Biological Sciences www.textroad.com Commencement

More information

NRA INSTRUCTOR TRAINING SEMINAR CANDIDATE SHOTGUN REGISTRATION FORM

NRA INSTRUCTOR TRAINING SEMINAR CANDIDATE SHOTGUN REGISTRATION FORM NRA INSTRUCTOR TRAINING SEMINAR CANDIDATE SHOTGUN REGISTRATION FORM NRA Master Training Counselor: Bernard W. Hostrop (540-347-3263) or E-Mail gbhg@comcast.net NRA SHOTGUN INSTRUCTOR DISCIPLINES: BIT &

More information

AIA C-Series Agreements

AIA C-Series Agreements AIA C-Series Agreements Dennis J. Stryker 1 Stryker Slev Law Group 1 Dennis Stryker is a principal of Stryker Slev Law Group and serves as the General Counsel for Glenn A. Rick Engineering & Development

More information

00010ACT CARRIER BROKER CONTRACT

00010ACT CARRIER BROKER CONTRACT 00010ACT CARRIER BROKER CONTRACT I. IDENTIFICATION OF PARTIES AGREEMENT Made this day of 2011 by and between. hereinafter referred to as a CARRIER, and USA LOGISTICS, INC. with address at: P.O. Box 666,

More information

September 18, HIRE Vets Medallion Program, RIN 1293 AA21; Notice of Proposed Rulemaking

September 18, HIRE Vets Medallion Program, RIN 1293 AA21; Notice of Proposed Rulemaking SUBMITTED ELECTRONICALLY VIA HTTPS://WWW.REGULATIONS.GOV Mr. Randall Smith Veterans Employment and Training Service U.S. Department of Labor Room S-1325 200 Constitution Avenue, NW Washington, DC 20210

More information

DECISION AND ORDER AFFIRMING DENIAL OF CERTIFICATION

DECISION AND ORDER AFFIRMING DENIAL OF CERTIFICATION U.S. Department of Labor Office of Administrative Law Judges O'Neill Federal Building - Room 411 10 Causeway Street Boston, MA 02222 (617) 223-9355 (617) 223-4254 (FAX) Issue Date: 25 August 2016 BALCA

More information

LICHT V. STORAGE TECHNOLOGY CORP WL (Del.Ch., May 13, 2005) *

LICHT V. STORAGE TECHNOLOGY CORP WL (Del.Ch., May 13, 2005) * LICHT V. STORAGE TECHNOLOGY CORP. 2005 WL 1252355 (Del.Ch., May 13, 2005) * The Plaintiff, Dr. Seymour Licht (the "Plaintiff"), challenges the widely-accepted notion that, under 8 Del. C. 216, when the

More information

Internal Audit Policy and Procedures Internal Audit Charter

Internal Audit Policy and Procedures Internal Audit Charter Mission Statement Internal Audit Policy and Procedures Internal Audit Charter The mission of the Internal Audit Department is to provide independent and objective reviews and assessments of the business

More information

Doing the Footwork: Preparing for Arbitration

Doing the Footwork: Preparing for Arbitration Doing the Footwork: Preparing for Arbitration By Ginger Staton, PHR Your agency has a grievance that is going to arbitration... now what? Even the inexperienced can do the footwork necessary to prepare

More information

Awarding Extensions of Time Christopher Miers. 23rd October 2013

Awarding Extensions of Time Christopher Miers. 23rd October 2013 Awarding Extensions of Time Christopher Miers 23rd October 2013 an extension of time provision confers benefits on both parties; in particular it enables a contractor to recover reasonable extensions

More information

Planning & Scheduling CSTM 102

Planning & Scheduling CSTM 102 Planning & Scheduling CSTM 102 Items Big A Project on Website Thursday Discuss Big A Project next Tuesday April 18, 2011 CPM Scheduling You were the successful bidder! What s next? Procurement/Buy

More information

Procurement Guidelines

Procurement Guidelines Reference 21 CM@Risk Procurement Guidelines Draft June 5, 2014 Purpose: These guidelines are intended to provide (1) assistance to those who may be responsible for implementation, processing and/or management

More information

INTERNATIONAL STANDARD ON AUDITING 580 WRITTEN REPRESENTATIONS CONTENTS

INTERNATIONAL STANDARD ON AUDITING 580 WRITTEN REPRESENTATIONS CONTENTS INTERNATIONAL STANDARD ON AUDITING 580 WRITTEN REPRESENTATIONS (Effective for audits of financial statements for periods beginning on or after December 15, 2009) CONTENTS Paragraph Introduction Scope of

More information

2016 INSPECTION OF BHARAT PARIKH & ASSOCIATES CHARTERED ACCOUNTANTS. Preface

2016 INSPECTION OF BHARAT PARIKH & ASSOCIATES CHARTERED ACCOUNTANTS. Preface 2016 INSPECTION OF BHARAT PARIKH & ASSOCIATES CHARTERED ACCOUNTANTS Preface In 2016, the Public Company Accounting Oversight Board ("PCAOB" or "the Board") conducted an inspection of the registered public

More information

REQUEST FOR PROPOSAL. Construction Management Services Not at Risk

REQUEST FOR PROPOSAL. Construction Management Services Not at Risk REQUEST FOR PROPOSAL Construction Management Services Not at Risk The St. Charles County Ambulance District proposes to retain a qualified firm/team for the Construction Management Services Not at Risk

More information

Sagar Khadka, MBP, Fairfax, VA Tom Hyland, Ohio DOT, Garfield Heights, OH. Tuesday, October 27, :00 AM 11:30 AM

Sagar Khadka, MBP, Fairfax, VA Tom Hyland, Ohio DOT, Garfield Heights, OH. Tuesday, October 27, :00 AM 11:30 AM Project Risk Management: Integrating it in Transportation Projects from Planning through Design and Construction to Minimize Cost and Schedule Overruns Session 15 Room: C120 122 Tuesday, October 27, 2015

More information

OFFICE OF THE GENERAL COUNSEL. MEMORANDUM GC May 09, 2016

OFFICE OF THE GENERAL COUNSEL. MEMORANDUM GC May 09, 2016 OFFICE OF THE GENERAL COUNSEL MEMORANDUM GC 16-03 May 09, 2016 TO: FROM: SUBJECT: All Regional Directors, Officers-in-Charge, and Resident Officers Richard F. Griffin, Jr., General Counsel /s/ Seeking

More information

Two Recent Decisions Analyze Topics Important to All In-House Lawyers: Carefully Identifying Their Clients and Internally Communicating by

Two Recent Decisions Analyze Topics Important to All In-House Lawyers: Carefully Identifying Their Clients and Internally Communicating by Two Recent Decisions Analyze Topics Important to All In-House Lawyers: Carefully Identifying Their Clients and Internally Communicating by E-Mail Thomas E. Spahn August 27, 2007 Two very recent cases should

More information

... Noes: Supervisors:-N_o_n&...

... Noes: Supervisors:-N_o_n&... Click Hereto Return to AgeTM BOARD OF SUPERVISORS OF THE COUNTY OF STANISLAUS ACTION AGENDA SUMMARY DEPT: Planning & Communitv Development BOARD AGENDA # 9:30 a.m. Urgent Routine X AGENDA DATE: March 30,

More information

Report on. Issued by the. Public Company Accounting Oversight Board. June 16, 2016 THIS IS A PUBLIC VERSION OF A PCAOB INSPECTION REPORT

Report on. Issued by the. Public Company Accounting Oversight Board. June 16, 2016 THIS IS A PUBLIC VERSION OF A PCAOB INSPECTION REPORT 1666 K Street, N.W. Washington, DC 20006 Telephone: (202) 207-9100 Facsimile: (202) 862-8433 www.pcaobus.org Report on 2015 Inspection of Paredes, Zaldívar, Burga & Asociados Sociedad Civil de (Headquartered

More information

UNITED STATES PATENT AND TRADEMARK OFFICE BEFORE THE PATENT TRIAL AND APPEAL BOARD

UNITED STATES PATENT AND TRADEMARK OFFICE BEFORE THE PATENT TRIAL AND APPEAL BOARD UNITED STATES PATENT AND TRADEMARK OFFICE ------------------------------------- BEFORE THE PATENT TRIAL AND APPEAL BOARD ------------------------------------- FRESENIUS KABI USA, LLC, Petitioner, v. HOSPIRA,

More information

CONTRACTOR PREQUALIFICATION REQUIREMENTS DATA CONTRACTORS FOR THE

CONTRACTOR PREQUALIFICATION REQUIREMENTS DATA CONTRACTORS FOR THE CONTRACTOR PREQUALIFICATION REQUIREMENTS DATA CONTRACTORS FOR THE AZUSA UNIFIED SCHOOL DISTRICT 1 TABLE OF CONTENTS Filing of PreQualifications Submittals 3 PREQUALIFICATION QUESTIONNAIRE 6 Page Part I:

More information

Technical factsheet Disciplinary, dismissal and grievance procedures

Technical factsheet Disciplinary, dismissal and grievance procedures Technical factsheet Disciplinary, dismissal and grievance procedures This factsheet is part of a suite of employment factsheets and a pro forma contract that are updated regularly. These are: The contract

More information

Terms of Reference. Quality and Value Audits

Terms of Reference. Quality and Value Audits Terms of Reference Quality and Value Audits Table of Contents SECTION 1 General 3 1.1 Introduction 3 1.2 Statutory authority 3 1.3 Purpose and Scope 4 SECTION 2 Methodology 6 2.1 The audit programme 6

More information

Getting Started with Risk in ISO 9001:2015

Getting Started with Risk in ISO 9001:2015 Getting Started with Risk in ISO 9001:2015 Executive Summary The ISO 9001:2015 standard places a great deal of emphasis on using risk to drive processes and make decisions. The old mindset of using corrective

More information

DOES CARMACK PREEMPTION APPLY TO CROSS-BORDER SHIPMENTS? Since more and more TIA members are involved with, or interested in, brokering

DOES CARMACK PREEMPTION APPLY TO CROSS-BORDER SHIPMENTS? Since more and more TIA members are involved with, or interested in, brokering DOES CARMACK PREEMPTION APPLY TO CROSS-BORDER SHIPMENTS? 3.5.14 Since more and more TIA members are involved with, or interested in, brokering shipments into Canada from US, or from Canada to US, I believe

More information