Alec Kimber Australian Nuclear Science & Technology Organisation

Size: px
Start display at page:

Download "Alec Kimber Australian Nuclear Science & Technology Organisation"

Transcription

1 Decommissioning and Dismantling of the Moata Reactor Alec Kimber Australian Nuclear Science & Technology Organisation

2 A History of Moata Constructed at ANSTO in 1961 ARGONAUT type reactor Built as a 10 kw reactor, but modified in 1972 to 100 kw Graphite moderator / reflector Cooled by light water Shielding - high density and low density concrete

3 The Moata Reactor From 1961 to 1995: Neutron radiography Training Soil analysis Cancer treatment research Quality Control for HIFAR

4 Shutdown & Decommissioning Shutdown after 4,519 start-ups Fuel unloaded Primary coolant (light water) drained Reactor Control System removed 2000 Decommissioning Licence Planning for Moata Dismantling Two phases of dismantling: Preliminary Dismantling the removal of the internal components of the reactor, including the steel core structures, graphite moderator and beam line facilities Structural (Biological Shield) Dismantling the cutting and removal of the concrete shielding and the floor area below the shielding. Containment tent installed Preliminary Dismantling July 2009 Biological Shield Dismantling began Biological Shield Dismantling Complete

5 Characterisation Survey Core samples extracted Radiological surveys carried out Determine dose rates Allow for waste reduction Data used to prepare a dose estimate for dismantling Internal reactor components Biological shield Radiological surveys allowed estimation of maximum individual and collective doses

6 Reactor Internals - Dismantling Control rod & drive assemblies Graphite moderator core & N, S, E & W cavities [approx 12 tonne] Aluminium core tanks Pipe work Steel framework graphite support Gamma curtain lead sheet [approx 750kg]

7 Structural (Biological Shield) Dismantling MOATA housed in a building used for AMS for C-14 dating A containment tent with HEPA filtered extraction system built around the reactor

8 Biological Shield - Dismantling

9 Challenge 1 An Australian first Challenge Nothing similar had ever been attempted previously Challenging to project team Slow start Mitigation Identifying and developing on-site expertise Explored use of external companies estimates: Turn key ($12M) Implementation ($8M) Partnership ($6M) Detailed planning we can do this

10 Challenge 2 Regulatory Challenge ARPANSA had never dealt with a reactor decommission / dismantle Regulatory caution Mitigation Communication Start early (Identification of requirements) Continuous Detailed planning Development of knowledge Developing organisational confidence They can do this

11 Challenge 3 Internal management Challenge Does ANSTO have the skills? Never undertaken a reactor decommission Easy to be less constructive Mitigation Project champion Staff training and expertise Detailed planning Development of knowledge Developing organisational confidence ANSTO can do this Stakeholder management Early communication Continual information

12 Challenge 4 External interest Challenge Pressures from external interest groups and stakeholders Politicians / government ANSTO Board IAEA Public Media Mitigation Communication Continuous Factual Managed Detailed planning Development of knowledge Developing organisational confidence Lets see if ANSTO can do this

13 Challenge 5 Project financial Challenge Decommissioning estimate developed from UK and US reactor dismantling Inherited a budget (AUS$3.8M) Minimal contingency Decommission within budget Mitigation Earned value analysis employed Job number allocation and control Early communication of cost overrun

14 Challenge 6 Tandem Accelerator Challenge Adjacent Tandem accelerator Sensitivity to carbon14 (1x10-14 ) [12 Tonne of graphite in MOATA] Risk to future of carbon dating program and research at LH Mitigation Localised tent and extract Fully enclosed and tented work area Double skinned Air inflow through tent skin Extract filtration Primary dust Secondary HEPA extract filtration

15 Challenge 7 Technology Challenge What methods were applicable? What technology was available and suitable? Lack of knowledge by project team Mitigation Research into methods Consultant advice sought Detailed planning Development of knowledge Developing organisational confidence ANSTO can do this

16 Challenge 8 Drawing inaccuracies Challenge 1950 s drawings Imperial measurements Mitigation Expert draughtsman 3D CAD drawings produced Physical 3D model Uncertainty of asbuilt drawings Unknown details Known inaccuracies

17 Challenge 9 Radiation protection Challenge Doses likely to be encountered Shielding methods Self shielding Distance No dose-sharing ALARA Mitigation Characterisation Dose modelling Physical measurements Detailed planning Tooling PPE Shielding Contingency planning What if? Identification & removal of hottest items

18 Challenge 10 Safety Challenge Industrial safety Working at heights Wire cutting Manual handling Dust Mechanical plant Mobile crane Excavator Mitigation In-house safety expert OHS + Radiation PPE 3-day contractor safety training Daily safety checks walkabout Daily safety talks Contractor ANSTO personnel

19 Interfacing Challenge 11 Contractor Challenge ANSTO safety procedures ANSTO systems Fear of radiation Understanding the decommissioning process An Australian first Keeping the cost realistic engagement Mitigation Initial contractor evaluation Presentation to eligible contractors Detailed Specification Responsibilities table detailing contractor interfaces with ANSTO Final contractor evaluation

20 Challenge 12 Work systems methodology Challenge Day to day safe working Contamination minimisation Waste clearance methods Communication Mitigation Site function plan Safe Work Method Statements Commitment to safety Full time, on-site supervisor Daily safety checks ANSTO supplied PPE Health physics on call Daily safety meetings Weekly project meetings

21 Challenge 13 Waste removal and Challenge clearance Mitigation Waste handling processes Waste types Quantities Handling and transport Packaging Availability of staff Project vs operational needs Clearance processes Methods & Instrumentation location Knowledge of reactor Materials, characterisation, size and location Understand demolition processes Consultant advice Contractor advice Consult Waste Management Team Utilise suitable methods Model and calibrate instruments and processes

22 Challenge 14 Records Challenge Preparation ( ) Operational records, drawings Preliminary planning incl DP Dismantling Project Project planning records Daily project records (log books, waste assessment and clearance, Health Physics) A story to be shared Mitigation Identified and collected all available historical records Team included former operators Engaged technical writer who also collated records Waste management group - Radioactive Waste Tracking System Contractor provides records of all wastes cleared from site. Project DVD

23 Final Survey Dose surveys carried out in grid pattern as per original survey Acceptance criteria of 0.5uSv/hr was met Samples taken and analysed for activity < clearance criteria Guides to determine the exemption and clearance criteria for the site IAEA No. RS-G.1.7 ARPANSA Reg 1999, Schedule 2, Part 2

24 Radiation Protection - outcomes Dismantling was completed safely and without incident Dose estimates higher than those recorded Overly conservative estimations Very detailed planning [ what if scenarios ] Concrete dismantling self shielding and greater distance Time taken to dismantle less than anticipated No surface or airborne contamination detected throughout the project No personal contamination events

25 Radiation Protection Dose results Estimated doses vs. actual doses: Dose ANSTO Estimated ARPANSA Constraint ANSTO Constraint Actual Collective 10,400 personμsv 13,000 personμsv 10,400 personμsv 1,679 personμsv Max. Individual 1444 μsv 1750 μsv 1500 μsv 252 μsv Daily μSv 46μSv (max)

26 Project - lessons learned Bridging the gap Telling the safety story in a way that the contractor can easily understand Documents The level playing field use of a single set of documents suitable for all purposes (regulator, contractor etc) Stakeholder A project champion Required to ensure early commitment from departments Operational v Project needs project requires rapid responses to maintain workflow. Thorough planning leads to success and constant review!

27 Project Achievements Setting Trends Ownership / Extending ANSTO department capabilities Procurement Adjusting their mandate to be more responsive to project requirements Survived it being a very high profile project Developed high quality stakeholder communication Regulatory approval and commendation Internal & External QA Audit incl Environmental Awards including National Best Small Project 2010 (Australian Institute of Project Management)

28 Project Achievements Site Function Plan Engagement of expert advice Comprehensive understanding of the project scope High quality specification of works Enhanced ability to deal with demolition contractor Significant savings on demolition contract Highly informed project team Development of in-house expertise Development of confidence for future needs Final cost within approximately 10% of budget

29 Project Achievements 3D Modelling including Physical Model Extremely powerful visualisation tool Aid to contractor understanding Enabled good understanding of the tasks ahead

30 Physical Model Project Achievements

31 Moving forward to HIFAR Experienced and highly informed project team in-house expertise now developed Engagement of expert advice Have a comprehensive understanding of the project scope Enhanced ability to deal with demolition contractor Organisation + project confidence in capabilities Proceed with detailed planning whilst local knowledge is available

32

A Radiation Protection Perspective- Decommissioning of the Moata Reactor. Biological Shield Dismantling

A Radiation Protection Perspective- Decommissioning of the Moata Reactor. Biological Shield Dismantling A Radiation Protection Perspective- Decommissioning of the Moata Reactor Biological Shield Dismantling Australian Nuclear Science & Technology Organisation IAEA Workshop (R2D2) Sydney Australia 7 th -11

More information

ANSTO s POLICY for MOATA & HIFAR. Prepared by John Rowling November 2007

ANSTO s POLICY for MOATA & HIFAR. Prepared by John Rowling November 2007 ANSTO s POLICY for MOATA & HIFAR Prepared by John Rowling November 2007 Content Australian Nuclear Regulatory Systems Compare to International Recommendations Licencing Transition Period Major Issues Requirements

More information

PLAN FOR MOATA REACTOR DECOMMISSIONING, ANSTO

PLAN FOR MOATA REACTOR DECOMMISSIONING, ANSTO PLAN FOR MOATA REACTOR DECOMMISSIONING, ANSTO Sungjoong (Shane) KIM Australian Nuclear Science and Technology Organisation New Illawarra Road, Lucas Heights, N.S.W., 2234, Australia Email: skx@ansto.gov.au

More information

RESEARCH REACTOR FRJ-1 (MERLIN) THE CORE STRUCTURES OF THE REACTOR BLOCK ARE DISMANTLED

RESEARCH REACTOR FRJ-1 (MERLIN) THE CORE STRUCTURES OF THE REACTOR BLOCK ARE DISMANTLED RESEARCH REACTOR FRJ-1 (MERLIN) THE CORE STRUCTURES OF THE REACTOR BLOCK ARE DISMANTLED B. Stahn, R. Printz, K. Matela, C. Zehbe Forschungszentrum Jülich GmbH 52425 Jülich, Germany J. Pöppinghaus Gesellschaft

More information

Best practices for preparing vessel internals segmentation projects

Best practices for preparing vessel internals segmentation projects Best practices for preparing vessel internals segmentation projects Joseph BOUCAU a*, Per SEGERUD b, Moisés SANCHEZ c a Westinghouse Electric Company, 43 rue de l Industrie, 1400 Nivelles, Belgium b Westinghouse

More information

Decommissioning Group Ketut Kamajaya

Decommissioning Group Ketut Kamajaya Decommissioning Group Ketut Kamajaya Contents of presentation Briefly history of Bandung TRIGA reactor Location of the facility Decommissioning options Characterization of System, Structure and Component

More information

Pham Hoai Phuong and Pham Van Lam NUCLEAR RESEARCH INSTITUTE, VAEC

Pham Hoai Phuong and Pham Van Lam NUCLEAR RESEARCH INSTITUTE, VAEC IAEA RESEARCH REACTOR DECOMMISSIONING DEMONSTRATION PROJECT Regional Workshop on Release of Sites and Building Structure, Karlsruhe,, GERMANY, 27 September 01 October 2010 THE IMPROVEMENTS MADE ON THE

More information

PRESENT STATUS OF LEGAL & REGULATORY FRAMEWORK AND DECOMMISSIONING PLANNING FOR DNRR. Prepared by NUCLEAR RESEARCH INSTITUTE, VAEC.

PRESENT STATUS OF LEGAL & REGULATORY FRAMEWORK AND DECOMMISSIONING PLANNING FOR DNRR. Prepared by NUCLEAR RESEARCH INSTITUTE, VAEC. TECHNICAL MEETING ON THE RESEARCH REACTOR DECOMMISSIONING DEMONSTRATION PROJECT: CHARACTERIZATION SURVEY PHILIPPINES, 3 7 DECEMBER 2007 PRESENT STATUS OF LEGAL & REGULATORY FRAMEWORK AND DECOMMISSIONING

More information

Mark Ramsay BEng MSc MSRP, CRadP

Mark Ramsay BEng MSc MSRP, CRadP Mark Ramsay BEng MSc MSRP, CRadP Radiation Protection Adviser Chartered Radiation Protection Professional Qualified Expert in Radiation Protection Personal Information Profile Nationality: British Age:

More information

International Perspective on non-heu Mo-99 Production

International Perspective on non-heu Mo-99 Production International Perspective on non-heu Mo-99 Production International Symposium on HEU Minimisation Vienna 23-25 January 2012 Dr Adrian Paterson Michael Druce Australian Nuclear Science and Technology Organisation

More information

ADVANCED DECOMMISSIONING COSTING CALCULATION TOOLS FOR PILOT VIENNA TRIGA MARK-II RESEARCH REACTOR

ADVANCED DECOMMISSIONING COSTING CALCULATION TOOLS FOR PILOT VIENNA TRIGA MARK-II RESEARCH REACTOR ADVANCED DECOMMISSIONING COSTING CALCULATION TOOLS FOR PILOT VIENNA TRIGA MARK-II RESEARCH REACTOR K. KRISTOFOVA, M. HORNACEK, V. SLUGEN Institute of Nuclear and Physical Engineering, Faculty of Electrical

More information

New Swedish Regulations for Clearance of Materials, Rooms, Buildings and Land Efraimsson, Henrik Swedish Radiation Safety Authority, SWEDEN

New Swedish Regulations for Clearance of Materials, Rooms, Buildings and Land Efraimsson, Henrik Swedish Radiation Safety Authority, SWEDEN New Swedish Regulations for Clearance of Materials, Rooms, Buildings and Land Efraimsson, Henrik Swedish Radiation Safety Authority, SWEDEN Abstract The Swedish Radiation Safety Authority (SSM) has developed

More information

Environmental Regulator's RWA Syllabus mapped to PHE's RPTS courses. RPTS coverage EA. No

Environmental Regulator's RWA Syllabus mapped to PHE's RPTS courses. RPTS coverage EA. No Environmental Regulator's mapped to PHE's RPTS courses EA. No RPTS Sylalbus/Course RPA Reference requirement 1 Basic atomic and nuclear physics Atomic structure and composition of the nucleus Yes F DU

More information

C. Kennes - C. Mommaert - M. Van haesendonck (Bel V) H. Libon - A. De Backer (Belgonucleaire) Decommissioning of Belgonucleaire MOX plant

C. Kennes - C. Mommaert - M. Van haesendonck (Bel V) H. Libon - A. De Backer (Belgonucleaire) Decommissioning of Belgonucleaire MOX plant C. Kennes - C. Mommaert - M. Van haesendonck (Bel V) H. Libon - A. De Backer (Belgonucleaire) Decommissioning of Belgonucleaire MOX plant Content Regulatory framework Strategy Status of the project Role

More information

Planning for the Decommissioning of the ASTRA-Reactor

Planning for the Decommissioning of the ASTRA-Reactor Planning for the Decommissioning of the ASTRA-Reactor Konrad Mück, Jörg Casta Austrian Research Center Seibersdorf Introduction The ASTRA Reactor, a 10 MW multipurpose MTR research reactor at the Austrian

More information

Decommissioning Planning

Decommissioning Planning Decommissioning Planning Ingemar Lund - Swedish Radiation Protection Authority, SSI, Sweden IAEA Regional Workshop: Legal and Regulatory Aspects of Decommissioning of Research Reactors Manila, Philippines,

More information

Development of Decommissioning Plan in Indonesia

Development of Decommissioning Plan in Indonesia Development of Decommissioning Plan in Indonesia Endang Kurnia and Berthie Isa R²D ²P: Review of a Decommissioning Plan Bucharest, Romania, 4-8 July 2011 IAEA International Atomic Energy Agency Legal and

More information

2007 ANS Topical Meeting on Decommissioning, Decontamination and Reutilization September 2007, Chattanooga, TN, United States of America

2007 ANS Topical Meeting on Decommissioning, Decontamination and Reutilization September 2007, Chattanooga, TN, United States of America 2007 ANS Topical Meeting on Decommissioning, Decontamination and Reutilization 16-19 September 2007, Chattanooga, TN, United States of America Safety of Decommissioning of Nuclear Facilities B. Batandjieva,

More information

STRUCTURAL RADIATION SAFETY AT A NUCLEAR FACILITY

STRUCTURAL RADIATION SAFETY AT A NUCLEAR FACILITY GUIDE YVL C.1 / 15 November 2013 STRUCTURAL RADIATION SAFETY AT A NUCLEAR FACILITY 1 Introduction 3 2 Scope of application 3 3 General design requirements 3 4 Radiation safety aspects in the layout design

More information

The EnBW Strategyfor Decommissioningand DismantlingofNuclearPower Plants»

The EnBW Strategyfor Decommissioningand DismantlingofNuclearPower Plants» The EnBW Strategyfor Decommissioningand DismantlingofNuclearPower Plants» 40 th MPA-Seminar Stuttgart, 6 th & 7 th October2014 Peter Daiß, EnBW Kernkraft GmbH Content 1. Introduction and Company Profile

More information

IAEA SAFETY STANDARDS for protecting people and the environment. Predisposal Management of Radioactive Waste from Nuclear Fuel Cycle Facilities

IAEA SAFETY STANDARDS for protecting people and the environment. Predisposal Management of Radioactive Waste from Nuclear Fuel Cycle Facilities DS447 Date: September 2014 IAEA SAFETY STANDARDS for protecting people and the environment STATUS: SPESS STEP 11 MS comments incorporated Review Committee Member comments due 31 Oct Predisposal Management

More information

Experiences on a Regulatory Clearance of the Radioactive Wastes at KAERI

Experiences on a Regulatory Clearance of the Radioactive Wastes at KAERI Experiences on a Regulatory Clearance of the Radioactive Wastes at KAERI - 8323 D.S. Hong, Y. Y. Ji, J. S. Shon, S. B. Hong Korea Atomic Energy Research Institute 1045 Daedeokdaero, Yuseong, Daejeon, Korea

More information

WM'99 CONFERENCE, FEBRUARY 28 - MARCH 4, 1999 RESEARCH REACTOR DECOMMISSIONING POTENTIAL BACK END OPTIONS

WM'99 CONFERENCE, FEBRUARY 28 - MARCH 4, 1999 RESEARCH REACTOR DECOMMISSIONING POTENTIAL BACK END OPTIONS RESEARCH REACTOR DECOMMISSIONING POTENTIAL BACK END OPTIONS ABSTRACT M England, BNFL, Risley, Warrington, Cheshire, England As with all nuclear facilities, research reactors will, at some stage, reach

More information

RADIOACTIVE GRAPHITE MANAGEMENT AT UK MAGNOX NUCLEAR POWER STATIONS. G. HOLT British Nuclear Fuels plc, Berkeley, United Kingdom 1.

RADIOACTIVE GRAPHITE MANAGEMENT AT UK MAGNOX NUCLEAR POWER STATIONS. G. HOLT British Nuclear Fuels plc, Berkeley, United Kingdom 1. RADIOACTIVE GRAPHITE MANAGEMENT AT UK MAGNOX NUCLEAR POWER STATIONS G. HOLT British Nuclear Fuels plc, Berkeley, United Kingdom Abstract. The UK nuclear power industry is predominantly based on gas-cooled,

More information

Legislative Framework for the Regulation of Decommissioning at Egypt. Prof. Dr. Farouk M. A. Rahman

Legislative Framework for the Regulation of Decommissioning at Egypt. Prof. Dr. Farouk M. A. Rahman Legislative Framework for the Regulation of Decommissioning at Egypt Prof. Dr. Farouk M. A. Rahman Egypt Framework for Decommissioning Legal Decree of the president of the United Arab Republic, law 59

More information

Applicability of EPRI Decommissioning Pre-Planning Manual to International Decommissioning Projects

Applicability of EPRI Decommissioning Pre-Planning Manual to International Decommissioning Projects Applicability of EPRI Decommissioning Pre-Planning Manual to International Decommissioning Projects Leo Lessard Manager, Commercial Decommissioning Operations, AREVA Inc. 16th February 2016 International

More information

IAEA SAFETY STANDARDS for protecting people and the environment. Predisposal Management of Radioactive Waste from Nuclear Fuel Cycle Facilities

IAEA SAFETY STANDARDS for protecting people and the environment. Predisposal Management of Radioactive Waste from Nuclear Fuel Cycle Facilities DS447 Date: 20 February 2015 IAEA SAFETY STANDARDS for protecting people and the environment STATUS: SPESS STEP 12 For submission to CSS Predisposal Management of Radioactive Waste from Nuclear Fuel Cycle

More information

Uranium mining legal and regulatory framework

Uranium mining legal and regulatory framework South Australia s Environment Protection Authority Uranium mining legal and regulatory framework An Australian perspective Keith Baldry Director Mining Radiation and Regulatory Support IAEA Seminar on

More information

The Chernobyl shelter industrial site, where the New Safe Confinement will be constructed (Photos: PMU)

The Chernobyl shelter industrial site, where the New Safe Confinement will be constructed (Photos: PMU) The Chernobyl shelter industrial site, where the New Safe Confinement will be constructed (Photos: PMU) Chernobyl 25 years on: Time for a giant leap forward BY DICK KOVAN After 25 years, the construction

More information

Decommissioning of Nuclear Facilities. Waste Management

Decommissioning of Nuclear Facilities. Waste Management Decommissioning of Nuclear Facilities Waste Management Lesson Objectives Describe the requirements and methods for managing waste from decommissioning Review IAEA and US waste classification systems Review

More information

RESEARCH REACTOR DECOMMISSIONING PLAN

RESEARCH REACTOR DECOMMISSIONING PLAN RESEARCH REACTOR DECOMMISSIONING PLAN Clédola Cássia O. de Tello Pablo Andrade Grossi Brazil Contents General Aspects Ongoing Activities Decommissioning Plan Conclusion 1 TRIGA IPR-R1 REACTOR Four research

More information

Packaging for Transport of the ILW-LL of EDF First Generation Power Plant Dismantling 16517

Packaging for Transport of the ILW-LL of EDF First Generation Power Plant Dismantling 16517 Packaging for Transport of the ILW-LL of EDF First Generation Power Plant Dismantling 16517 Aurélie Brasch-Serres*, Mathias Chazot** * EDF-DP2D, 154 avenue Thiers, CS 60018, 69458 LYON CEDEX 06, FRANCE

More information

PROGRESS ON ANSTO S OPAL REACTOR PROJECT AND ITS FUTURE IMPORTANCE AS THE CENTREPIECE OF ANSTO S FACILITIES

PROGRESS ON ANSTO S OPAL REACTOR PROJECT AND ITS FUTURE IMPORTANCE AS THE CENTREPIECE OF ANSTO S FACILITIES PROGRESS ON ANSTO S OPAL REACTOR PROJECT AND ITS FUTURE IMPORTANCE AS THE CENTREPIECE OF ANSTO S FACILITIES Smith, I.O. Executive Director Australian Nuclear Science and Technology Organisation, Lucas

More information

Decommissioning and Site Release Problems for Georgian Nuclear Research Reactor IRT-M

Decommissioning and Site Release Problems for Georgian Nuclear Research Reactor IRT-M Decommissioning and Site Release Problems for Georgian Nuclear Research Reactor IRT-M Giorgi Nabakhtiani Grigol Kiknadze Nuclear and Radiation Safety Service Ministry of Environment Protection and Natural

More information

Ghent University Research Reactor THETIS: Unloading and Conditioning of Spent Fuel

Ghent University Research Reactor THETIS: Unloading and Conditioning of Spent Fuel Ghent University Research Reactor THETIS: Unloading and Conditioning of Spent Fuel Myriam Monsieurs, Hubert Thierens, Isabelle Meirlaen, Karel Strijckmans, Ghent University, Luc Noynaert, Luc Ooms, Patrick

More information

Berkeley Boilers Project. Studsvik Symposium April 2014

Berkeley Boilers Project. Studsvik Symposium April 2014 Berkeley Boilers Project Studsvik Symposium April 2014 Berkeley NPP Twin Magnox Reactors Operating 1962 1989 First UK commercial reactor to enter decommissioning Currently managed on behalf of the Nuclear

More information

AUSTRALIA S NATIONAL RADIOACTIVE WASTE MANAGEMENT STRATEGY

AUSTRALIA S NATIONAL RADIOACTIVE WASTE MANAGEMENT STRATEGY AUSTRALIA S NATIONAL RADIOACTIVE WASTE MANAGEMENT STRATEGY C. Perkins Department of Education, Science and Training GPO Box 9880, Canberra, ACT 2601, Australia ABSTRACT The Australian Government is committed

More information

Australia s Regulation of Low and Intermediate Level Radioactive Waste

Australia s Regulation of Low and Intermediate Level Radioactive Waste Australia s Regulation of Low and Intermediate Level Radioactive Waste NEA Workshop on the Management of Non-Nuclear Radioactive Waste Legnaro, Italy, 2-4 May 2017 John Templeton Acting Manager, Facility

More information

Radiation Protection Adviser (RPA) Register

Radiation Protection Adviser (RPA) Register Radiation Protection Adviser (RPA) Register Guidelines for Creating a Portfolio of Evidence for those Seeking Category II (Industrial & Educational Practices and Work Activities) Approval by the EPA for

More information

STURGIS Barge Decommissioning Project

STURGIS Barge Decommissioning Project STURGIS Barge Decommissioning Project U.S. Army Corps of Engineers Nov. 17, 2014 US Army Corps of Engineers Today s Presentation History of the STURGIS Environmental Assessment Decommissioning Waste Segregation

More information

Preliminary Lessons Learned from the Fukushima Daiichi Accident for Advanced Nuclear Power Plant Technology Development

Preliminary Lessons Learned from the Fukushima Daiichi Accident for Advanced Nuclear Power Plant Technology Development Preliminary Lessons Learned from the Fukushima Daiichi Accident for Advanced Nuclear Power Plant Technology Development A. Introduction The IAEA Report on Reactor and Spent Fuel Safety in the Light of

More information

Radiation Protection of the Public and Protection of the Environment

Radiation Protection of the Public and Protection of the Environment DS432 IAEA SAFETY STANDARDS Date: March 2015 for protecting people and the environment Status: Step 8 120 day Member States consultation Deadline for comments: 20 July 2015 Radiation Protection of the

More information

during Normal Operations

during Normal Operations Hitachi-GE Nuclear Energy, Ltd. UK ABWR GENERIC DESIGN ASSESSMENT Resolution Plan for RI-ABWR-0001 Definition and Justification for the Radioactive Source Terms in UK ABWR during Normal Operations Definition

More information

- 1 - Ingenieurgesellschaft für wissenschaftlich technischen Umweltschutz

- 1 - Ingenieurgesellschaft für wissenschaftlich technischen Umweltschutz - 1 - Strategies for Radiological Characterisation in Decommissioning S. Thierfeldt, K. Haneke - Brenk Systemplanung GmbH, Aachen OECD/NEA Workshop on Radiological Characterisation for Decommissioning

More information

Decommissioning three main strategies: Immediate dismantling, Safe enclosure (Deferred dismantling), Entombment

Decommissioning three main strategies: Immediate dismantling, Safe enclosure (Deferred dismantling), Entombment : Immediate dismantling, Safe enclosure (Deferred dismantling), Entombment Dr. M Knaack TÜV NORD GmbH, Hamburg / Germany Overwiew Decommissioning when and why? Law, regulations and guidelines Three main

More information

Decommissioning of Nuclear Facilities. The Decommissioning Process. Lesson Objectives. Decommissioning. Decontamination. Decommissioning Objective

Decommissioning of Nuclear Facilities. The Decommissioning Process. Lesson Objectives. Decommissioning. Decontamination. Decommissioning Objective Lesson Objectives International Atomic Energy Agency Define specific decommissioning terms of Nuclear Facilities The Process Understand the decommissioning process Review the various decommissioning strategies

More information

NUCLEAR FUEL AND REACTOR

NUCLEAR FUEL AND REACTOR NUCLEAR FUEL AND REACTOR 1 Introduction 3 2 Scope of application 3 3 Requirements for the reactor and reactivity control systems 4 3.1 Structural compatibility of reactor and nuclear fuel 4 3.2 Reactivity

More information

Radioactive Waste Management at the NCSR Demokritos - Greece

Radioactive Waste Management at the NCSR Demokritos - Greece Radioactive Waste Management at the NCSR Demokritos - Greece Anastasia Savidou Radioactive Materials Management Laboratory Institute of Nuclear & Radiological Sciences & Technology, Energy & Safety, National

More information

Nuclear decommissioning challenges in the UK a rough guide for roboticists

Nuclear decommissioning challenges in the UK a rough guide for roboticists Nuclear decommissioning challenges in the UK a rough guide for roboticists Rustam Stolkin University of Birmingham, UK With some slides provided by Jeffrey A. Kuo National Nuclear Lab, UK Caveat: I am

More information

Optimization of Reactor Pressure Vessel Internals Segmentation in Korea

Optimization of Reactor Pressure Vessel Internals Segmentation in Korea DECOMMISSIONING AND WASTE MANAGEMENT 654 Optimization of Reactor Pressure Vessel Internals Segmentation in Korea Byung-Sik Lee 1 Introduction The decommissioning of Kori unit 1, which is the first commercial

More information

TOPICAL SESSION MANAGEMENT OF DECOMMISSIONING WASTES

TOPICAL SESSION MANAGEMENT OF DECOMMISSIONING WASTES TOPICAL SESSION MANAGEMENT OF DECOMMISSIONING WASTES Waste Technology Section WATEC 2004, 18-22 Oct 2004 Presentation Objectives Highlight the interactions between decommissioning and waste management

More information

Radiation Protection and ALARA Program Highlights at Ontario Power Generation

Radiation Protection and ALARA Program Highlights at Ontario Power Generation 2017 International ISOE ALARA Symposium 10-Jan-2017 Radiation Protection and ALARA Program Highlights at Ontario Power Generation Josip Zic Radiation Protection Manager Pickering Nuclear Generating Station

More information

SAFETY ANALYSIS AND ENVIRONMENTAL IMPACT ASSESSMENT FOR FOTON RTC DECOMMISSIONING

SAFETY ANALYSIS AND ENVIRONMENTAL IMPACT ASSESSMENT FOR FOTON RTC DECOMMISSIONING SAFETY ANALYSIS AND ENVIRONMENTAL IMPACT ASSESSMENT FOR FOTON RTC DECOMMISSIONING S.V. Komarov, A.Z. Gaiazov, A.A. Rozhnovskaia, I.V. Kuzmin, O.E. Polovnikov Sosny Research and Development Company (Sosny

More information

SoftWall Enclosures. Flexible In-plant Enclosure Systems An Excellent Alternative to Rigid Wall Systems

SoftWall Enclosures. Flexible In-plant Enclosure Systems An Excellent Alternative to Rigid Wall Systems SoftWall Enclosures Flexible In-plant Enclosure Systems An Excellent Alternative to Rigid Wall Systems An Excellent Alternative Soper s Softwall Enclosures are easy to install, dismantle and relocate.

More information

Peer Review of the RPII s Environmental Monitoring Programme Foundation Document. F. Exposure from Natural Sources in Ireland

Peer Review of the RPII s Environmental Monitoring Programme Foundation Document. F. Exposure from Natural Sources in Ireland Peer Review of the RPII s Environmental Monitoring Programme 2009 Foundation Document F. Exposure from Natural Sources in Ireland 1. Introduction The European Commission is currently in the process of

More information

News this quarter. Environment, Safety&Health Quarterly Performance Report. Reporting period: 1 April to 30 June 2015

News this quarter. Environment, Safety&Health Quarterly Performance Report. Reporting period: 1 April to 30 June 2015 Environment, Safety&Health Quarterly Performance Report Reporting period: 1 April to 30 June 2015 Welcome to AWE s second quarterly performance report for 2015. This document is designed to inform you

More information

Setting up the Medical Cyclotron Facility at Cochin, Kerala. M.R.A. Pillai Ph.D; D.Sc Molecular Cyclotrons Ltd. Cochin

Setting up the Medical Cyclotron Facility at Cochin, Kerala. M.R.A. Pillai Ph.D; D.Sc Molecular Cyclotrons Ltd. Cochin Setting up the Medical Cyclotron Facility at Cochin, Kerala M.R.A. Pillai Ph.D; D.Sc Molecular Cyclotrons Ltd. Cochin 682 508 Pillai.m.r.a@gmail.com AERB Approval Stagewise Site Assessment and Approval

More information

WM2012 Conference, February 26 March 1, 2012, Phoenix, Arizona, USA

WM2012 Conference, February 26 March 1, 2012, Phoenix, Arizona, USA Modular Design of Processing and Storage Facilities for Small Volumes of Low and Intermediate Level Radioactive Waste including Disused Sealed Sources - 12372 David R. Keene*, Susanta Kumar Samanta** and

More information

Radiation Environment and Shielding Design Optimization at MEIC

Radiation Environment and Shielding Design Optimization at MEIC Radiation Environment and Shielding Design Optimization at MEIC Pavel Degtiarenko Radiation Physics Group Radiation Control Department, JLab October, 2015 Contents Brief review of MEIC Radiation Protection

More information

Occupational Radiation Protection in Radioactive Waste Management

Occupational Radiation Protection in Radioactive Waste Management ISOE 2014 Asian ALARA Symposium The-K Hotel Gyeongju, Republic of Korea, 23-25 September 2014 Occupational Radiation Protection in Radioactive Waste Management 24 Sept., 2014 Byeongsoo KIM KINS 1 Contents

More information

BAE SYSTEMS Marine Ltd s strategy for the decommissioning of the Barrow nuclear licensed site

BAE SYSTEMS Marine Ltd s strategy for the decommissioning of the Barrow nuclear licensed site Health and Safety Executive HM Nuclear Installations Inspectorate BAE SYSTEMS Marine Ltd s strategy for the decommissioning of the Barrow nuclear licensed site A Review by HM Nuclear Installations Inspectorate

More information

WM2014 Conference, March 2 6, 2014, Phoenix, Arizona, USA

WM2014 Conference, March 2 6, 2014, Phoenix, Arizona, USA Reactor D&D: AREVA French and German Latest Experiences - 14458 (1) Stephan Krüger, AREVA GmbH, Kaiserleistr. 29, 63067 Offenbach, Germany; stephan.krueger@areva.com (2) Xavier de Brimont, AREVA NC, 1

More information

Decommissioning Worldwide and NEA Activities

Decommissioning Worldwide and NEA Activities Decommissioning Worldwide and NEA Activities Claudio Pescatore - Ivo Tripputi NEA Principal Administrator - NEA CPD Management Board Chair WM Symposia, Phoenix, 2-6 March 2014 Decommissioning: what does

More information

Low-Level Waste and Radiation Management

Low-Level Waste and Radiation Management Low-Level Waste and Radiation Management Program Description Program Overview Nuclear power plants face significant regulatory, economic, environmental, and public perception pressures with respect to

More information

Joint ICTP-IAEA School on Nuclear Energy Management. 15 July - 3 August, Lecture Notes. I. Mele IAEA, Vienna, Austria

Joint ICTP-IAEA School on Nuclear Energy Management. 15 July - 3 August, Lecture Notes. I. Mele IAEA, Vienna, Austria 2473-9 Joint ICTP-IAEA School on Nuclear Energy Management 15 July - 3 August, 2013 Lecture Notes I. Mele IAEA, Vienna, Austria The IAEA Nuclear Energy Management School ICTP, Trieste, 15-2 August 2013

More information

Nuclear Aircraft Carrier Inactivation Approach for Waste Management and Exposure Reduction 14201

Nuclear Aircraft Carrier Inactivation Approach for Waste Management and Exposure Reduction 14201 Nuclear Aircraft Carrier Inactivation Approach for Waste Management and Exposure Reduction 14201 ABSTRACT Irin P. Hall, Kimberly Grubb and Ashley Williams Newport News Shipbuilding Since 2007, Newport

More information

P. Brennecke, S. Steyer Bundesamt für Strahlenschutz Willy-Brandt-Strasse 5, D Salzgitter, Germany

P. Brennecke, S. Steyer Bundesamt für Strahlenschutz Willy-Brandt-Strasse 5, D Salzgitter, Germany WASTE CERTIFICATION, ACCEPTANCE AND DISPOSAL FOR LLW/ILW/MW/HW MANAGEMENT OF RADIOACTIVE WASTE IN GERMANY: QUALITY ASSURANCE OF WASTE PACKAGES WITH RESPECT TO IAEA RECOMMENDATIONS P. Brennecke, S. Steyer

More information

Joint ICTP-IAEA Essential Knowledge Workshop on Deterministic Safety Analysis and Engineering Aspects Important to Safety. Trieste,12-23 October 2015

Joint ICTP-IAEA Essential Knowledge Workshop on Deterministic Safety Analysis and Engineering Aspects Important to Safety. Trieste,12-23 October 2015 Joint ICTP- Essential Knowledge Workshop on Deterministic Safety Analysis and Engineering Aspects Important to Safety Trieste,12-23 October 2015 Safety classification of structures, systems and components

More information

WM2015 Conference, March 15-19, 2015, Phoenix, Arizona, USA

WM2015 Conference, March 15-19, 2015, Phoenix, Arizona, USA An Integrated Equipment for Massive Segmentation and Packaging of Control Rod Guide Tubes 15161 Joseph Boucau*, Patrick Gobert** Sébastien Bonne *** * Westinghouse Electric Company, 43 rue de l Industrie,

More information

DRAFT National Framework for Radioactive Waste Management

DRAFT National Framework for Radioactive Waste Management DRAFT National Framework for Radioactive Waste Management Contents 1 Forward... 2 2 The National Framework... 3 2.1 Management of Radioactive Waste Regulations... 4 2.2 Radioactive Waste Regulators...

More information

THE ROLE OF THE WORLD'S LARGEST INTERIM STORAGE FOR WASTE AND FUEL WITHIN THE DECOM PROJECT OF 6 WWER REACTORS IN GREIFSWALD AND RHEINSBERG (GERMANY)

THE ROLE OF THE WORLD'S LARGEST INTERIM STORAGE FOR WASTE AND FUEL WITHIN THE DECOM PROJECT OF 6 WWER REACTORS IN GREIFSWALD AND RHEINSBERG (GERMANY) THE ROLE OF THE WORLD'S LARGEST INTERIM STORAGE FOR WASTE AND FUEL WITHIN THE DECOM PROJECT OF 6 WWER REACTORS IN GREIFSWALD AND RHEINSBERG (GERMANY) Hartmann, Burkhard Leushacke, Dieter F. Dr Energiewerke

More information

TROJAN DECOMMISSIONING STATUS. OPUC Meeting March 8, 2005 (draft)

TROJAN DECOMMISSIONING STATUS. OPUC Meeting March 8, 2005 (draft) TROJAN DECOMMISSIONING STATUS OPUC Meeting March 8, 2005 (draft) 1 Meeting Agenda Trojan Decommissioning Overview History Major Projects Overall Performance Remaining Major Activities Current Issues USDOE

More information

S. Reyes. Lawrence Livermore National Laboratory. ARIES Meeting April 22-23, 2002 U. Wisconsin, Madison

S. Reyes. Lawrence Livermore National Laboratory. ARIES Meeting April 22-23, 2002 U. Wisconsin, Madison S. Reyes Lawrence Livermore National Laboratory ARIES Meeting April 22-23, 2002 U. Wisconsin, Madison Work performed under the auspices of the U. S. Department of Energy by University of California Lawrence

More information

Lessons Learned from Shut-Down to Decommissioning Plan at the Army Pulse Radiation Facility

Lessons Learned from Shut-Down to Decommissioning Plan at the Army Pulse Radiation Facility Lessons Learned from Shut-Down to Decommissioning Plan at the Army Pulse Radiation Facility Hans Honerlah US Army Corps of Engineers & Gurvis Davis US Army Development Test Command ABSTRACT The Army Pulse

More information

RADIOLOGICAL PROTECTION

RADIOLOGICAL PROTECTION Title of document ONR GUIDE RADIOLOGICAL PROTECTION Document Type: Unique Document ID and Revision No: Nuclear Safety Technical Assessment Guide Date Issued: November 2017 Review Date: November 2020 Approved

More information

ENVIRONET Network on Environmental Management and Remediation. Terms of Reference

ENVIRONET Network on Environmental Management and Remediation. Terms of Reference ENVIRONET Network on Environmental Management and Remediation Terms of Reference 1. Background Radiologically contaminated sites continue to exist all over the world. They were originated by past activities

More information

Experiments Carried-out, in Progress and Planned at the HTR-10 Reactor

Experiments Carried-out, in Progress and Planned at the HTR-10 Reactor Experiments Carried-out, in Progress and Planned at the HTR-10 Reactor Yuliang SUN Institute of Nuclear and New Energy Technology, Tsinghua University Beijing 100084, PR China 1 st Workshop on PBMR Coupled

More information

German contribution on the safety assessment of research reactors

German contribution on the safety assessment of research reactors German contribution on the safety assessment of research reactors S. Langenbuch J. Rodríguez Gesellschaft für Anlagen- und Reaktorsicherheit (GRS) mh. Schwertnergasse 1, D-50667 Köln, Federal Republic

More information

KIPT ADS Facility. Yousry Gohar 1, Igor Bolshinsky 2, Ivan Karnaukhov 3. Argonne National Laboratory, USA 2. Idaho National Laboratory, USA 3

KIPT ADS Facility. Yousry Gohar 1, Igor Bolshinsky 2, Ivan Karnaukhov 3. Argonne National Laboratory, USA 2. Idaho National Laboratory, USA 3 KIPT ADS Facility Yousry Gohar 1, Igor Bolshinsky 2, Ivan Karnaukhov 3 1 Argonne National Laboratory, USA 2 Idaho National Laboratory, USA 3 Kharkov Institute of Physics & Technology, Ukraine EuCARD 2

More information

Irradiated Hardware Characterization and Packaging During Decommissioning of the Ford Nuclear Reactor at University of Michigan

Irradiated Hardware Characterization and Packaging During Decommissioning of the Ford Nuclear Reactor at University of Michigan Irradiated Hardware Characterization and Packaging During Decommissioning of the Ford Nuclear Reactor at University of Michigan A. Freitag, J. Sullivan, G.Tombari WMG, Inc. Peekskill, NY 10566 USA ABSTRACT

More information

Gerhart Grinanger, NOELL GmbH, Postfach 6260, D-8700 Wizrzburg, Germany

Gerhart Grinanger, NOELL GmbH, Postfach 6260, D-8700 Wizrzburg, Germany 861 REMOTELY-OPERATED DISMANTLING OF THE REACTOR INTERNALS AT NIEDERAICHBACH POWER PLANT USING MANIPULATORS Gerhart Grinanger, NOELL GmbH, Postfach 6260, D-8700 Wizrzburg, Germany ABSTRACT The joint venture

More information

Safety Assessment for Decommissioning of a Nuclear Power Plant

Safety Assessment for Decommissioning of a Nuclear Power Plant SAFETY ASSESSMENT FOR DECOMMISSIONING Annex I, Part A Safety Assessment for Decommissioning of a Nuclear Power Plant INTERNATIONAL ATOMIC ENERGY AGENCY VIENNA CONTENTS 1. INTRODUCTION... 1 1.1. Background...

More information

Status of the FRM-II Project at Garching. Hans-Jürgen Didier, Gunter Wierheim Siemens AG, Power Generation (KWU), D Erlangen

Status of the FRM-II Project at Garching. Hans-Jürgen Didier, Gunter Wierheim Siemens AG, Power Generation (KWU), D Erlangen IGORR7 7 th Meeting of the International Group on Research Reactors October 26-29, 1999 Bariloche, Argentina Status of the FRM-II Project at Garching Hans-Jürgen Didier, Gunter Wierheim Siemens AG, Power

More information

M. Laraia International Atomic Energy Agency Wagramerstrasse 5 P.O. Box 100 A-1400 Vienna Austria

M. Laraia International Atomic Energy Agency Wagramerstrasse 5 P.O. Box 100 A-1400 Vienna Austria The History and Evolution of the IAEA Technical Assistance Programme on Decommissioning and the International Decommissioning Network as its Highest Point-9000 ABSTRACT M. Laraia International Atomic Energy

More information

Dismantling Techniques applied at MZFR

Dismantling Techniques applied at MZFR Wiederaufarbeitungsanlage Karlsruhe Rückbau- und Entsorgungs- GmbH The Decommissioning Project Multi-Purpose Research Reactor ( MZFR ) Dismantling Techniques applied at MZFR E. Prechtl Projekt MZFR WAK

More information

Excellence in Control of Radiation Exposures

Excellence in Control of Radiation Exposures Excellence in Control of Radiation Exposures Kenneth W. Crase Abstract Savannah River Site (SRS) operating contractors have continuously maintained excellence in the control of radiation exposures to both

More information

Dismantling of nuclear facilities in France: what is at stake?

Dismantling of nuclear facilities in France: what is at stake? Decommissioning of nuclear facilities Feedback from France L. Vaillant ISPRA, Italy, 16 th September 2015 Content Dismantling of nuclear facilities in France: what is at stake? Radioactive Waste Management

More information

Texas A&M University, Department of Nuclear engineering, Ph.D. Qualifying Examination, Fall 2016

Texas A&M University, Department of Nuclear engineering, Ph.D. Qualifying Examination, Fall 2016 Part 2 of 2 100 points of the total exam worth of 200 points Research Area Specific Problems Select and answer any 4 problems from the provided 15 problems focusing on the topics of research tracks in

More information

Radiation becomes dangerous when it becomes concentrated in some way by human activity.

Radiation becomes dangerous when it becomes concentrated in some way by human activity. NORM Naturally occurring radioactive material (NORM): Is radiation that exists naturally in the environment Is also known as background radiation Has many sources, such as soil and rocks Can be found in

More information

Services for professional procurement. Be better informed, make better decisions. RISQS Audit Questions Network Rail On-Track Plant Operations

Services for professional procurement. Be better informed, make better decisions. RISQS Audit Questions Network Rail On-Track Plant Operations Services for professional procurement. Be better informed, make better decisions. RISQS Audit Questions Network Rail On-Track Plant Operations Contents Contents... 2 Preface... 3 Issue Record... 3 Assessment

More information

The Evolution of System Safety in the Canadian Nuclear Industry

The Evolution of System Safety in the Canadian Nuclear Industry Canadian Nuclear Safety Commission Commission canadienne de sûreté nucléaire The Evolution of System Safety in the Canadian Nuclear Industry System Safety Society, Eastern Canada Chapter, June 18, 2009

More information

2/14/2017. Introduction & Objectives. Radiation Safety Program Structure. Massachusetts DPH Radiation Control Program

2/14/2017. Introduction & Objectives. Radiation Safety Program Structure. Massachusetts DPH Radiation Control Program Annual Radiation Safety Refresher 1 Environmental Health & Safety Radiation Safety Program Q1 2017 Introduction & Objectives Introduction 1. Tufts University has been licensed to handle radioactive materials

More information

Transporting radioactive material - Guidance on radiation and contamination monitoring requirements, and determining a Transport Index

Transporting radioactive material - Guidance on radiation and contamination monitoring requirements, and determining a Transport Index Transporting radioactive material - Guidance on radiation and contamination monitoring requirements, and determining a Transport Index Who is this guide for? This guide has been prepared primarily to help

More information

ANSTO Nuclear Medicine: Reliable and Timely Mo-99 Supply Globally

ANSTO Nuclear Medicine: Reliable and Timely Mo-99 Supply Globally Presentation 8 Session 3 ANSTO Nuclear Medicine: Reliable and Timely Mo-99 Supply Globally Jayne Senior General Manager, ANSTO Nuclear Medicine Pty Ltd (ANM) Biography Jayne Senior is General Manager for

More information

Radiation Protection Challenges associated with the dismantling of Nuclear Power Plant

Radiation Protection Challenges associated with the dismantling of Nuclear Power Plant Radiation Protection Challenges associated with the dismantling of Nuclear Power Plant Ludovic Vaillant ISOE International Symposium Rio de Janeiro, May 2015 Context (1/2) For various reasons - economical,

More information

Accidental Melting of Radioactive Sources

Accidental Melting of Radioactive Sources Accidental Melting of Radioactive Sources K. Baldry 1, D. S. Harvey 2, A. Bishop 3 1 RWE NUKEM Limited, Windscale, Cumbria CA20 1PF, UK Email: keith.baldry@rwenukem.co.uk 2 Corus RD&T, Rotherham, S60 3AR,

More information

EVALUATION OF SAFETY CULTURE IN WANO PRE-STARTUP REVIEWS

EVALUATION OF SAFETY CULTURE IN WANO PRE-STARTUP REVIEWS EVALUATION OF SAFETY CULTURE IN WANO PRE-STARTUP REVIEWS Todd Brumfield World Association of Nuclear Operators (WANO) Atlanta, Georgia, USA ABSTRACT: The requirements for performance of pre-startup reviews

More information

ACCESS CONTROL AND WORK AREA SETUP RCT STUDY GUIDE State responsibilities in using or initiating a RWP.

ACCESS CONTROL AND WORK AREA SETUP RCT STUDY GUIDE State responsibilities in using or initiating a RWP. LEARNING OBJECTIVES: 2.10.01 State the purpose of and information found on a Radiological Work Permit (RWP) including the different classifications at your site. 2.10.02 State responsibilities in using

More information

Niagara Falls Storage Site Safety Measures During Remediation

Niagara Falls Storage Site Safety Measures During Remediation Niagara Falls Storage Site Safety Measures During Remediation On-Site Worker Protection Community and Environmental Protection Transportation and Disposal Safety Fully enclosed Retrieval Facility Regular

More information

Interim Guidance on the Regulation of In-situ Disposals of Radioactive Waste and Residual Radioactive Contamination on Nuclear Authorised Premises

Interim Guidance on the Regulation of In-situ Disposals of Radioactive Waste and Residual Radioactive Contamination on Nuclear Authorised Premises Interim Guidance on the Regulation of In-situ Disposals of Radioactive Waste and Residual Radioactive Contamination on Nuclear Authorised Premises Issue 1 May 2014 Contents 1.1 Introduction... 2 1.2 Site

More information