Digital Photogrammetry in Fire Testing Procedure for Concrete Tunnel Linings

Size: px
Start display at page:

Download "Digital Photogrammetry in Fire Testing Procedure for Concrete Tunnel Linings"

Transcription

1 295 Digital Photogrammetry in Fire Testing Procedure for Concrete Tunnel Linings Chlepková, M. Department of Surveying, Faculty of Civil Engineering, Slovak University of Technology in Bratislava, Radlinského 11, Bratislava, Slovak Republic Tel.: , Miroslava.chlepkova@stuba.sk Abstract Digital photogrammetry as a measuring method is more frequently used in different applications of engineering practice. Especially high accuracy, low costs and short measuring and processing time are the main advantages which help photogrammetry to compete with methods like laser scanning and common surveying methods. This paper provides information about using digital photogrammetry in the process of fire testing for concrete tunnel linings where the main task is to measure geometric parameters of concrete samples before and after spalling test and to obtain the quantity information about loss of material in each sample. The result helps to choose the best concrete mixture with the best attributes to build the tunnel lining to protect the tunnel from fatal damage in case of fire. Key words: digital photogrammetry, fire test, concrete tunnel lining 1 INTRODUCTION In recent years some very serious fires happened in tunnels where in addition to serious structural damage, the loss of human lives occurred as well. Reconstruction work may be very expensive and also requires the closure of tunnel for a long time. Moreover, such incidents can damage the buildings or structures built above the tunnel. Therefore, the question of effective fire protection of tunnel linings comes to the fore during the construction or reconstruction of existing tunnel. Active fire protection as water sprinklers, water mists or foam systems are used next to passive fire protection systems. Passive fire protection is designed to be installed as a shield protecting the tunnel structure from fire all the time, creating a permanent part of the tunnel and does not require external activation in case of fire (Clement et al., 2007 and Promat Tunel, 2008). In connection with the issue of passive fire protection of tunnels several tests are used in practice to obtain the most accurate information about the behaviour of the structure in case of fire. Within the frame of the spalling test the loss of material during a simulated fire is one of the studied parameters. This article discusses the exploitation of digital photogrammetry to determine the geometric parameters of samples tested in the process of passive fire protection systems testing. TS 7 Underground Structures INGEO th International Conference on Engineering Surveying Brijuni, Croatia, September 22-24, 2011

2 296 2 INGEO 2011 PASSIVE FIRE PROTECTION Passive fire protection is a permanent part of the tunnel and requires no activation in case of fire. Passive systems are not used to fight the fire but they are the last line of defence and maintain the stability of the tunnel structure in order to safe escape for the public and secure access to the fire brigade. They keep ventilation systems in use separated from traffic part of the tunnel by inner concrete structures. Primarily, passive systems prevent the tunnel from the collapse and the catastrophic loss of lives and property. The role of passive fire protection in tunnels is to (Efnarc, 2006): x minimise the rate of temperature rise within the concrete and structural steel reinforcement (if present) so that structural integrity is retained during and after the fire, x to reduce or eliminate the risk of explosive spalling and loss of the concrete surface resulting from a build-up of vapour pressure within the concrete. There are three common types of passive fire protection: x an applied protective coating or render, x a preformed thermal barrier or board fixed to the concrete surface, x integral protection incorporated into the structural concrete, usually based on polypropylene fibres. Especially the third option provides an optimal solution for the construction of new tunnel projects. The fibre modified concrete shows no or less spalling losses than the unmodified concrete. This type of passive fire protection was the subject of testing during the construction of Airport Link tunnel in Brisbane, Australia, using the spalling test. 2.1 SPALLING TEST Typical response of concrete exposed to fire is explosive spalling, which lasts until total damage of concrete slab or fire lies down. The explosive concrete spalling is a complex system of actions involving a combination of physical, chemical and mechanical processes, influencing each other. That is the reasons why scale tests or computer modelling is considered insufficient to define risks of the explosive concrete spalling. Test samples should be designed according to real situation in the tunnel together with the identical concrete mixture and possible fire control systems installed. The quality of tunnel linings depends on several parameters and is determined by various tests. One of these tests is spalling test where the sample material is exposed to the temperature up to 1300 C in a special oven and the occurred changes are exanimated. The sample of the concrete panel after the test is shown in Figure1. Figure1 Concrete sample after the test

3 Chlepková, M.: Digital Photogrammetry in Fire Testing Procedure 297 These tests are necessary for evaluating the suitability of concrete structure for application in practice and determine the probability of non-acceptable damage to concrete structures during possible fire based on the explosive spalling of the concrete surface. Among other parameters studied after spalling test, very important part is to determine the depth, resp. the amount of the material loss from the surface of concrete samples. 3 DIGITAL PHOTGRAMMETRY USED IN SPALLING TESTS Together 16 standard size concrete samples (2600 mm x 1000mm x 250mm) were tested in CSIRO (Commonwealth Scientific and Industrial Research Organisation) area in Sydney, Australia. The concrete mixture of the samples varied as well as the percentage of polypropylene fibres used as anti-blasting component of the concrete. The aim of our measurements was to determine the geometry of the panels before and after spalling test, to compare created digital models before and after and to determine the depth of spalled material during the test. Two methods have been proposed for geodetic measurements: reflectless measurement using Leica TCRP1201 (2 +2 ppm accuracy) total station with additional software allowing automatic measuring the points on a predefined grid (similar to laser scanner) and photogrammetric measurement using a Canon 500D digital SLR camera and software PhotoModeler Scanner (PMS) (submillimeter accuracy in the circumstances). As digital photogrammetry seemed to be faster, more accurate and efficient method with possibility of increasing the density of points according to the individual requirements in postprocessing, it was used in all tests. 3.1 FIELD WORK The measurement was carried out in two phases, before and after the test. Using a crane, each sample panel was positioned enabling to capture the surface to be tested. Within the testing area there were subsequently installed special surveying nails resistant to high temperature with a length of min. 80 mm (max. estimated value of material loss was 50 mm) which were used to determine the identical reference system before and after the test. The distribution on the nails is shown in Figure 2. They were used for scale definition as well. Figure 2 Distribution of the control points In addition these control points were signalized by coded targets for speeding up the subsequent processing in PMS software. Up to additional coded targets were located on each sample framing the measured area to increase the accuracy of model. Images were captured using digital camera Canon 500D EF-S mm, which was calibrated before measurement using calibration grid supplied by the PMS software for a focal length of 18 mm at a distance roughly comparable to imaging one. Camera positions for images taking were selected to fulfil the condition of the highest accuracy for both convergent photogrammetry and automatic generation of point cloud photogrammetric scanner:

4 298 INGEO 2011 x for convergent photogrammetry: the optimal angle of ray intersection (to determine the exact model using control and tie points signalised by coded targets), x for photogrammetric scanner: Baseline should be ¼ of the object distance and the angle of ray intersection less than 30 (for the automatically generation of points based on the principle of image correlation). Figure 3 Distribution of the camera stations Photogrammetric measurements were complemented by measuring minimum of 3 distances using steel tape, one to define the scale of the model and the other two for the control. 3.2 PROCESSING OF PHOTOGRAMMETRIC MEASUREMENTS As mentioned above, the Photomodeller Scanner software was used for photogrammetry measurements processing, which in addition to the measurement of discrete points allows the automatic generation of point cloud using the image correlation. The condition for generating high-quality point cloud is to create very accurate model based on subpixel measuring all control and tie points signalised by coded targets. Their spatial position in the model was estimated with the precision mm. Subsequently there was point cloud (grid 10x10mm) generated in the testing area of the panel and created a 3D TIN model (Figure 4). Figure 4 TIN model created from the point cloud

5 Chlepková, M.: Digital Photogrammetry in Fire Testing Procedure COMPARISON Digital surface models "before" and "after" test were exported from PMS software to exchange formats (.dxf and.txt) and then processed using the graphical software AutoCAD Civil 3D The after test measurement data were affected by deflections, which occurred due to warm-up of concrete panels together with its own weight action. Data of the deflection has been provided directly from the executor of the test and also checked by measuring position of control points 2, 5 and 7. Deflections were numerically removed using software Terramodel. The aim was to determine the quantity of material loss on the exposed surface of the sample. As the coordinate systems of digital models "before" and "after" test were identical using the same control points, the result is a differential model of two surface models. 3.4 DATA VISUALISATION The results were visualized as both the differential hypsometric models (Figre 5) where the colours represent the value range of material loss (Tab. 1) as well as the plan with the differences values (depth of material loss) on the grid 100x100mm (Figure 6). Tab.1 Spalling Values Table Figure 5 Hypsometric represantation of differential model Figure 6 Numerical interpretation of differential model

6 300 INGEO 2011 Graphical results were supplemented by a statistical data with the values of minimum, average and maximum values of material loss (Tab.2). Tab.2 Statistic results As can be seen on the graphical results as well as in the table, the measurement also indicates positive values, material gain. This phenomenon can be explained by the fact that at a certain temperature with horizontal position of concrete samples over the oven, the concrete began to melt and drain slightly, as evidenced by the visible stalactites on the sample surface. 4 CONCLUSION The digital photogrammetry is progressively becoming used in wide variety of engineering practical applications. High accuracy, low cost and relatively high efficiency of field and office works are the main characteristics in competition with other methods. Digital photogrammetry has also found its application in testing the passive fire protection of tunnels. Here it should be noted that the determination of depth of spalled concrete using digital photogrammetry is only a partial tasks throughout the whole testing procedure and its results are an integral part of the decision-making process on the suitability of the concrete for the construction. When measuring irregular surfaces, as was the case of concrete samples after the fire test measurements, where the surface is irregular, the photogrammetry again appears in advantage comparing to terrestrial geodetic methods. Main reason is the possibility of choosing the grid of measured points in post-processing to ensure to identify and measure all the details of measured surface. Acknowledgement The article has been written within the solving the granted project VEGA 1/0142/10. REFERENCES CLEMENT, F. - ZÁME NÍK, M.: Alternatívy protipožární ochrany betonového ost ní tunelú. Tunel, Vol.16,No.1/2007. PROMAT TUNEL: Centre for fire safety: Fire testing procedure for concrete tunnel linings, EfectisR0695_Fire_testing_procedure_concrete_tunnel.pdf EFNARC: Specification and guidelines for testing of passive fire protection for concrete tunnels linings, March

Measurements of geometry of internal flues in multi-flue chimneys

Measurements of geometry of internal flues in multi-flue chimneys Measurements of geometry of internal flues in multi-flue chimneys Edyta PUNIACH AGH University of Science and Technology, Faculty of Mining Surveying and Environmental Engineering, Krakow, Poland E-mail:

More information

As-built documentation of anchor blocks of facade elements using TLS

As-built documentation of anchor blocks of facade elements using TLS As-built documentation of anchor blocks of facade elements using TLS Ján ERDÉLYI, Alojz KOPÁČIK, Peter KYRINOVIČ Slovak University of Technology in Bratislava, Faculty of Civil Engineering Bratislava,

More information

Higher National Unit Specification. General information for centres. Construction Site Surveying C. Unit code: DW44 35

Higher National Unit Specification. General information for centres. Construction Site Surveying C. Unit code: DW44 35 Higher National Unit Specification General information for centres Unit title: Construction Site Surveying C Unit code: DW44 35 Unit purpose: To develop candidate knowledge and skills in a range of more

More information

GEOSPATIAL ENGINEERING. Land and Engineering Surveying

GEOSPATIAL ENGINEERING. Land and Engineering Surveying GOSPATIAL NGINRING Land and ngineering Surveying The measurement, definition and portrayal, either digitally or graphically in the form of maps or plans, of the physical features of, and the structures

More information

GRP System FX. The «all in one» railway surveying solution

GRP System FX. The «all in one» railway surveying solution GRP System FX The «all in one» railway surveying solution Rail traffic without limits New challenges for railway construction and operation Borders open, centres of economic activity spread, people and

More information

FIRE RESISTANCE OF CONCRETE WITH FLY ASH CONTENT EXPERIMENTAL ANALYSIS

FIRE RESISTANCE OF CONCRETE WITH FLY ASH CONTENT EXPERIMENTAL ANALYSIS Engineering MECHANICS, Vol. 21, 2014, No. 3, p. 159 165 159 FIRE RESISTANCE OF CONCRETE WITH FLY ASH CONTENT EXPERIMENTAL ANALYSIS Michal Šejnoha*, Miroslav Brouček* The paper presents results from three

More information

Very Low Seismicity Areas

Very Low Seismicity Areas Vol. XIX, 2011, No. 3, 1 9 M. Sokol, L. Konečná, M. Čuhák, M. Dallemule Very Low Seismicity Areas in Slovakia and Comparison of Seismic Risks in Central European Countries Milan SOKOL milan.sokol@stuba.sk

More information

3D Modelling of Shukhov Tower

3D Modelling of Shukhov Tower ARTICLE USING LASER SCANNING TO MODEL A RUSSIAN RADIO TOWER 3D Modelling of Shukhov Tower The 90-year-old Shukhov Tower in Moscow, Russia, is not only in a state of severe disrepair but the 150m-high steel

More information

Construction. Fully bonded FPO sheet membrane waterproofing system for basement and other below ground structures. Product Description.

Construction. Fully bonded FPO sheet membrane waterproofing system for basement and other below ground structures. Product Description. Product Data Sheet Version 2014-05-27 Identification no: 020704103000000001 SikaProof A SikaProof A Fully bonded FPO sheet membrane waterproofing system for basement and other below ground structures Construction

More information

Research activities of the AdMaS Centre are very close to the main topics of HORIZON Key advantages of the centre:

Research activities of the AdMaS Centre are very close to the main topics of HORIZON Key advantages of the centre: Research activities of the AdMaS Centre are very close to the main topics of HORIZON 2020. Key advantages of the centre: New excellent equipment and large laboratory facilities, Highly specialized research

More information

SEISMIC REHABILITATION OF TRADITIONAL UN-REINFORCED MASONRY BUILDINGS IN IRAN

SEISMIC REHABILITATION OF TRADITIONAL UN-REINFORCED MASONRY BUILDINGS IN IRAN COMPDYN 2011 III ECCOMAS Thematic Conference on Computational Methods in Structural Dynamics and Earthquake Engineering M. Papadrakakis, M. Fragiadakis, V. Plevris (eds.) Corfu, Greece, 26 28 May 2011

More information

II. Presentation of the Project

II. Presentation of the Project I. Introduction The Royal Canadian Mounted Police started using Unmanned Aerial Vehicles to help with their work on collision and crime scene investigations. It allows the investigations to be conducted

More information

Measuring Technology during Reconstruction of Prestressed Gagarin Bridge

Measuring Technology during Reconstruction of Prestressed Gagarin Bridge 229 Measuring Technology during Reconstruction of Prestressed Gagarin Bridge Bureš, J. 1, Klusá ek,. 2, Ne as, R. 2 and Švábenský, O. 1 1 Brno University of Technology, Faculty of Civil Engineering, Institute

More information

Transverse Reinforcement in Reinforced Concrete Columns

Transverse Reinforcement in Reinforced Concrete Columns SSP - JOURNAL OF CIVIL ENGINEERING Vol. 8, Issue 2, 2013 DOI: 10.2478/sspjce-2013-0017 Transverse Reinforcement in Reinforced Concrete Columns Štefan Gramblička, Peter Veróny Slovak University of Technology

More information

Development of bottom ash and PP fiber added fire protection coating mortar for NATM tunnel concrete lining

Development of bottom ash and PP fiber added fire protection coating mortar for NATM tunnel concrete lining Development of bottom ash and PP fiber added fire protection coating mortar for NATM tunnel concrete lining J. H. J. Kim Department of Civil & Environmental Engineering, Sejong University, Seoul, Korea

More information

THE INFLUENCE OF THE AMOUNT OF FIBRE REINFORCEMENT ON THE AIR PERMEABILITY OF HIGH PERFORMANCE CONCRETE

THE INFLUENCE OF THE AMOUNT OF FIBRE REINFORCEMENT ON THE AIR PERMEABILITY OF HIGH PERFORMANCE CONCRETE 2009/2 PAGES 1 7 RECEIVED 10. 1. 2009 ACCEPTED 9. 4. 2009 P. PAULÍK, I. HUDOBA THE INFLUENCE OF THE AMOUNT OF FIBRE REINFORCEMENT ON THE AIR PERMEABILITY OF HIGH PERFORMANCE CONCRETE ABSTRACT Peter Paulík

More information

PRODUCT DATA SHEET SikaProof A

PRODUCT DATA SHEET SikaProof A FULLY BONDED FPO SHEET MEMBRANE WATERPROOFING SYSTEM FOR BASEMENTS AND OTHER BELOW GROUND STRUCTURES DESCRIPTION is a fully and permanently bonded, selfadhesive, composite sheet membrane waterproofing

More information

Amberg Tunnel. Measuring gives you perspective. Why choose Amberg Tunnel surveying solutions?

Amberg Tunnel. Measuring gives you perspective. Why choose Amberg Tunnel surveying solutions? Amberg Tunnel Measuring gives you perspective Why choose Amberg Tunnel surveying solutions? Cooperation Ease of use Modularity Innovation Swiss quality AMBERG TUNNEL Measuring gives you perspective Tunnel

More information

Measurement methods of building structures deflections

Measurement methods of building structures deflections Measurement methods of building structures deflections Magdalena Wróblewska 1,* 1 Silesian University of Technology, Faculty of Civil Engineering, Department of Geotechnics and Roads, Gliwice, Poland Abstract.

More information

LINEAR PROJECT SOFTWARE IMPROVING SCHEDULING OUTCOMES USING TIME LOCATION CHARTING

LINEAR PROJECT SOFTWARE IMPROVING SCHEDULING OUTCOMES USING TIME LOCATION CHARTING IMPROVING SCHEDULING OUTCOMES USING TIME LOCATION CHARTING January 20-23 2019 San Diego, USA Overview Outcomes Gain understanding of Time Location charts Demonstration of a practical application Realise

More information

Static and dynamic analysis of high-rise building with consideration of two different values of subsoil stiffness coefficients

Static and dynamic analysis of high-rise building with consideration of two different values of subsoil stiffness coefficients Static and dynamic analysis of high-rise building with consideration of two different values of subsoil stiffness coefficients Olga Ivankova 1,*, Janka Kovacikova 1 and Lenka Konecna 1 1 Slovak University

More information

WHOLE BUILDING BEHAVIOUR RESULTS FROM A SERIES OF LARGE SCALE TESTS

WHOLE BUILDING BEHAVIOUR RESULTS FROM A SERIES OF LARGE SCALE TESTS Proceedings of the CIB-CTBUH International Conference on Tall Buildings, 8-10 May 2003, Malaysia WHOLE BUILDING BEHAVIOUR RESULTS FROM A SERIES OF LARGE SCALE TESTS T. LENNON Principal Consultant, FRS,

More information

(AdMaS: Advanced Materials, Structures and Technologies)

(AdMaS: Advanced Materials, Structures and Technologies) The AdMaS Centre (AdMaS: Advanced Materials, Structures and Technologies) The AdMaS Centre is modern science centre and multidisciplinary civil engineering research institution affiliated to the Faculty

More information

Fire behaviour of HPLWC hollow core slabs: full scale furnace tests and numerical modelling

Fire behaviour of HPLWC hollow core slabs: full scale furnace tests and numerical modelling Fire behaviour of HPLWC hollow core slabs: full scale furnace tests and numerical modelling Annibale Luigi MATERAZZI Professor University of Perugia Perugia, ITALY Marco BRECCOLOTTI Assistant Researcher

More information

Large scale fire test on tunnel segment: Real boundary conditions in order to evaluate spalling sensitivity and fire resistance

Large scale fire test on tunnel segment: Real boundary conditions in order to evaluate spalling sensitivity and fire resistance MATEC Web of Conferences 6, 04001 (2013) DOI: 10.1051/matecconf/20130604001 C Owned by the authors, published by EDP Sciences, 2013 Large scale fire test on tunnel segment: Real boundary conditions in

More information

The Successful use of HDS for Nuclear Power Generating Plant Applications

The Successful use of HDS for Nuclear Power Generating Plant Applications AREVA NP Inc. Metrology Services The Successful use of HDS for Nuclear Power Generating Plant Applications SPAR 2006 Lona Shaw Supervisor, CAD Unit Who is AREVA? > AREVA group has 70,000 + employees world

More information

Moisture problems of functional joints of wooden windows causes analysis

Moisture problems of functional joints of wooden windows causes analysis Moisture problems of functional joints of wooden windows causes analysis Adela Palková 1,*, Milan Palko 1, and Peter Buday 1 1 Department of Building Constructions, Slovak University of Technology in Bratislava,

More information

Detecting Fire Damaged Concrete Using Laser Scanning

Detecting Fire Damaged Concrete Using Laser Scanning Craig Matthew HANCOCK, UK, Gethin Wyn ROBERTS, China, Luke BISBY, UK, Martin CULLEN, UK, James ARBUCKLE, UK Key words: Laser Scanning, Concrete, Deformation Monitoring, Fire SUMMARY Concrete is the single

More information

Fire resistance design guidelines for high strength concrete columns. Kodur, V.K.R. NRCC-46116

Fire resistance design guidelines for high strength concrete columns. Kodur, V.K.R. NRCC-46116 Fire resistance design guidelines for high strength concrete columns Kodur, V.K.R. NRCC-46116 A version of this document is published in / Une version de ce document se trouve dans : ASCE/SFPE Specialty

More information

Use of Hand-Held Thermographic Camera for Condition TPF-5(152)

Use of Hand-Held Thermographic Camera for Condition TPF-5(152) Use of Hand-Held Thermographic Camera for Condition TPF-5(152) Glenn A.Washer, Ph.D. Department of Civil and Environmental Engineering University of Missouri washerg@missouri.edu Midwest Bridge Preservation

More information

Higher Energy Efficiency thanks to Camera- Based 3D In-Line Inspection of Solar Parabolic Mirrors

Higher Energy Efficiency thanks to Camera- Based 3D In-Line Inspection of Solar Parabolic Mirrors Fast, simple, precise and extremely reliable Higher Energy Efficiency thanks to Camera- Based 3D In-Line Inspection of Solar Parabolic Mirrors The demand for solar parabolic mirrors being put into operation

More information

Surface Transport Master Plan Addendum 3 Transit Corridor Safeguarding Basis of Design. Revision A

Surface Transport Master Plan Addendum 3 Transit Corridor Safeguarding Basis of Design. Revision A Surface Transport Master Plan Addendum 3 Transit Corridor Safeguarding Basis of Design Revision A October 2008 Department of Transport PO Box 20 Abu Dhabi United Arab Emirates Surface Transport Master

More information

Construction. SikaProof A. Fully bonded FPO sheet waterproofing membrane system for basement and other below ground structures. Product Description

Construction. SikaProof A. Fully bonded FPO sheet waterproofing membrane system for basement and other below ground structures. Product Description Construction Product Data Sheet Edition 17 April 2012 SikaProof A Fully bonded FPO sheet waterproofing membrane system for basement and other below ground structures Product Description SikaProof A is

More information

An Investigation of the Behaviour of Steel and Polypropylene Fibre Reinforced Concrete Slabs

An Investigation of the Behaviour of Steel and Polypropylene Fibre Reinforced Concrete Slabs University of Wollongong Research Online Faculty of Engineering - Papers (Archive) Faculty of Engineering and Information Sciences 28 An Investigation of the Behaviour of Steel and Polypropylene Fibre

More information

Analysis of Shear Wall Transfer Beam Structure LEI KA HOU

Analysis of Shear Wall Transfer Beam Structure LEI KA HOU Analysis of Shear Wall Transfer Beam Structure by LEI KA HOU Final Year Project report submitted in partial fulfillment of the requirement of the Degree of Bachelor of Science in Civil Engineering 2013-2014

More information

ORDINANCE ON TECHNICAL REQUIREMENTS FOR CABLE DUCTS

ORDINANCE ON TECHNICAL REQUIREMENTS FOR CABLE DUCTS Pursuant to Article 12, paragraph 1, item 1 and Article 24, paragraph 8 of the Electronic Communications Act (Official Gazette No. 73/08), the Council of the Croatian Post and Electronic Communications

More information

Summary Technical Specification. In-vessel Survey Development

Summary Technical Specification. In-vessel Survey Development Version 1.3 Summary Technical Specification In-vessel Survey Development Page 1 of 8 BACKGROUND Background ITER is a joint international research and development project that aims to demonstrate the scientific

More information

Degree Programme in Civil Engineering and Urban Management Civilingenjörsutbildning i samhällsbyggnad credits

Degree Programme in Civil Engineering and Urban Management Civilingenjörsutbildning i samhällsbyggnad credits Programme syllabus Degree Programme in Civil Engineering and Urban Management Civilingenjörsutbildning i samhällsbyggnad 270.0 credits Valid for students admitted to the education from autumn 05 (HT -

More information

Optimization of Tendon Geometry of Post-Tensioned Concrete Bridges using Genetic Algorithms

Optimization of Tendon Geometry of Post-Tensioned Concrete Bridges using Genetic Algorithms Paper 60 Optimization of Tendon Geometry of Post-Tensioned Concrete Bridges using Genetic Algorithms L. Dlouhý 1 and M. Lepš 2 1 Faculty of Civil Engineering Brno University of Technology, Czech Republic

More information

Control Survey Procedures

Control Survey Procedures Chapter 13 Control Survey Procedures 13-01 General 13-02 Policy Control surveys establish a common, consistent network of physical points that are the basis for controlling the horizontal and vertical

More information

DESIGN OF BUILDINGS OVER OR NEAR RAILWAYS

DESIGN OF BUILDINGS OVER OR NEAR RAILWAYS Civil Engineering Technical Requirement CIVIL-SR-005 DESIGN OF BUILDINGS OVER OR NEAR RAILWAYS Revision: D Updated: 30/05/2011 Queensland Rail 2011 Reproduction by any means (including electronic, mechanical,

More information

Servo electric bending technology by Prima Power. The Bend The Combi The Laser The Punch The System The Software

Servo electric bending technology by Prima Power. The Bend The Combi The Laser The Punch The System The Software Servo electric bending technology by Prima Power The Bend The Combi The Laser The Punch The System The Software Servo electric ep-1030 press brake Prima Power has been a true pioneer in applying servo

More information

SEARs climate change risk and adaptation

SEARs climate change risk and adaptation 25 Climate change risk and adaptation The NSW Government has acknowledged that, despite efforts to reduce greenhouse gas emissions, some climate change is now inevitable. The Government aims to minimise

More information

Computer Models For Fire and Smoke

Computer Models For Fire and Smoke Computer Models For Fire and Smoke Model Name: KAMELEON FIREEX KFX Version: KAMELEON FIREEX KFX 2010 Date: August 6 th, 2013 Classification: Very Short Description: Field model KAMELEON FIREEX KFX is an

More information

NONDESTRUCTIVE EVALUATION BY ANALYSIS FOR DENSITY OF CRACK IN TUNNEL & UNDERGROUND STRUCTURES WITH TUNNEL SCANNER

NONDESTRUCTIVE EVALUATION BY ANALYSIS FOR DENSITY OF CRACK IN TUNNEL & UNDERGROUND STRUCTURES WITH TUNNEL SCANNER XVIII IMEKO WORLD CONGRESS Metrology for a Sustainable Development September, 17 22, 2006, Rio de Janeiro, Brazil NONDESTRUCTIVE EVALUATION BY ANALYSIS FOR DENSITY OF CRACK IN TUNNEL & UNDERGROUND STRUCTURES

More information

Surveying the I-35W Bridge Collapse

Surveying the I-35W Bridge Collapse Surveying the I-35W Bridge Collapse Minnesota Society of Professional Surveyors 57 th Annual Meeting January 28-30, 2009 St. Cloud Civic Center St. Cloud, Minnesota Where were you? Do you remember where

More information

FIBRE REINFORCED CONCRETE FOR PRECAST TUNNEL SEGMENTS

FIBRE REINFORCED CONCRETE FOR PRECAST TUNNEL SEGMENTS FIBRE REINFORCED CONCRETE FOR PRECAST TUNNEL SEGMENTS Jan L. Vítek 1, Matouš Hilar 2, Petr Vítek 3 Abstract: Fibre reinforced concrete is a promising material for application in precast concrete tunnel

More information

Design, Experiment and Analysis of Protective Structures

Design, Experiment and Analysis of Protective Structures Design, Experiment and Analysis of Protective Structures Proceedings of the 5th International Conference on Protective Structures ICPS5 19-23 August 2018, Poznan, Poland Poznan University of Technology

More information

ScienceDirect. Analysis and design of steel bridges with ballastless track

ScienceDirect. Analysis and design of steel bridges with ballastless track Available online at www.sciencedirect.com ScienceDirect Procedia Engineering 111 (2015 ) 702 708 XXIV R-S-P seminar, Theoretical Foundation of Civil Engineering (24RSP) (TFoCE 2015) Analysis and design

More information

STEW0LS INDIA (P) LTD. An ISO 9001:2008 Certified Company 5-8B, Nagpur Industrial Estate, Kamptee Road, Uppalwadi, Nagpur India.

STEW0LS INDIA (P) LTD. An ISO 9001:2008 Certified Company 5-8B, Nagpur Industrial Estate, Kamptee Road, Uppalwadi, Nagpur India. STEW0LS INDIA (P) LTD. An ISO 9001:2008 Certified Company 5-8B, Nagpur Industrial Estate, Kamptee Road, Uppalwadi, Nagpur-440 026. India. Tel : +91-712-2641040, 2640613, 3291281, 2641750. Fax : +91-712-2641760.

More information

Medical Centre, University of Müns Laboratory of Biophysics Optical Imaging Techniques for Archeology Profilometry and Holography G. von Bally EUREGIO-Center of Expertise for Art Conservation Technology

More information

The Reaction of Cylinder Fibrous Cover to Explosion of Charge with Fragments

The Reaction of Cylinder Fibrous Cover to Explosion of Charge with Fragments The Reaction of Cylinder Fibrous Cover to Explosion of Charge with Fragments 137 Central European Journal of Energetic Materials, 2009, 6(2), 137-148. ISSN 1733-7178 The Reaction of Cylinder Fibrous Cover

More information

GTT Pluto II Subsea Cryogenic Pipeline

GTT Pluto II Subsea Cryogenic Pipeline GTT Pluto II Subsea Cryogenic Pipeline Approved by As the market is growing continuously, elements of the value chain have to adapt constantly to new needs. Some new import and export terminals have to

More information

The concept of statical determinacy

The concept of statical determinacy Appendix 3 The concept of statical determinacy 140 A3.1 Introduction It has been shown that the conditions for equilibrium of a set of coplanar forces can be summarised in the three equations of equilibrium

More information

Modelling a temperature regime of a railway track structure and its comparison with the results of experimental measurements

Modelling a temperature regime of a railway track structure and its comparison with the results of experimental measurements Computers in Railways XIV 253 Modelling a temperature regime of a railway track structure and its comparison with the results of experimental measurements S. Hodas & L. Ižvolt Department of Railway Engineering

More information

Emerging problem for immersed tunnels: fire induced concrete cracking

Emerging problem for immersed tunnels: fire induced concrete cracking Emerging problem for immersed tunnels: fire induced concrete cracking ir. Leander.M. Noordijk, ing. P.G. Scholten, ir. A.J. Breunese & dr.ir. C.Both Efectis Nederland Rijswijk, The Netherlands ABSTRACT

More information

ArcelorMittal Europe - Long Products Sections and Merchant Bars. Office Building ArcelorMittal in Esch Alzette

ArcelorMittal Europe - Long Products Sections and Merchant Bars. Office Building ArcelorMittal in Esch Alzette ArcelorMittal Europe - Long Products Sections and Merchant Bars Office Building ArcelorMittal in Esch Alzette Location the country, at the heart of the iron and steel region. It has good access to the

More information

The impact of the geometry of rail welds on noise level in urban environments

The impact of the geometry of rail welds on noise level in urban environments The impact of the geometry of rail welds on noise level in urban environments Stjepan Lakusic (1), Roman Kecur (2) (1) University of Zagreb, Faculty of Civil Engineering, Kaciceva 26, Zagreb, Croatia (2)

More information

Precision forestry in Finland

Precision forestry in Finland Precision forestry in Finland ICT Smart Precision Forestry with Laser Scanning, Finland Japan Joint Symposium (3 rd edition), Tokyo Associate Professor Mikko Vastaranta, School of Forest Sciences, Faculty

More information

REQUIREMENTS FOR SERVICES UNDER THE RAILWAY CORRIDOR (NON-QR SERVICES)

REQUIREMENTS FOR SERVICES UNDER THE RAILWAY CORRIDOR (NON-QR SERVICES) SYSTEMS AND CAPABILITY TECHNICAL REQUIREMENT NO: MCE-SR-16 ISSUE: Initial DATE: 14-10-2009 PAGE: 1 of 19 REQUIREMENTS FOR SERVICES UNDER THE RAILWAY CORRIDOR (NON-QR SERVICES) ISSUE DATE DESCRIPTION /

More information

Role of Automation in Traffic Management: Towards a digital infrastructure and classification of infrastructure

Role of Automation in Traffic Management: Towards a digital infrastructure and classification of infrastructure Role of Automation in Traffic Management: Towards a digital infrastructure and classification of infrastructure November 2017 Table of Contents 1. Introduction... 2 2. Digital infrastructure requirements...

More information

HEXAGON METROLOGY WLS400A

HEXAGON METROLOGY WLS400A CASE STUDY HEXAGON METROLOGY WLS400A Driving better solutions for automotive With time at a premium but quality crucial, a global vehicle manufacturing group has used white light scanning to improve productivity.

More information

Complete structural arrangements

Complete structural arrangements Chapter 5 Complete structural arrangements 5.1 Introduction Most structures are assemblies of large numbers of elements and the performance of the complete structure depends principally on the types of

More information

Jinfeng Zhang 1, Wangsheng Liu 1, Ming Zhao 1 1. College of Civil Engineering, Tongji University, Shanghai , China.

Jinfeng Zhang 1, Wangsheng Liu 1, Ming Zhao 1 1. College of Civil Engineering, Tongji University, Shanghai , China. 7th European Workshop on Structural Health Monitoring July 8-11, 2014. La Cité, Nantes, France More Info at Open Access Database www.ndt.net/?id=17265 THE REAL-TIME MONITORING SYSTEM FOR METRO SHIELD TUNNELS:

More information

IMPACT

IMPACT www.strusoft.com Project Project Management Scheduling Erection Planning Erection Simulation Design Production AutoCAD - Revit Precast Cast/Bed Planning Resource Handling Design - Detailing Shop Drawings

More information

Public Housing Estates in Hong Kong. Building Monitoring Survey of. Hong Kong Housing Authority. Winnie SHIU, Ricky CHEUNG. Development and Practices

Public Housing Estates in Hong Kong. Building Monitoring Survey of. Hong Kong Housing Authority. Winnie SHIU, Ricky CHEUNG. Development and Practices First International FIG Workshop on Monitoring High Rise and Tall Engineering Structures Development and Practices Building Monitoring Survey of Public Housing Estates in Hong Kong Winnie SHIU, Ricky CHEUNG

More information

Erosion Behaviour of Stainless Steel Grade-316

Erosion Behaviour of Stainless Steel Grade-316 PP 58-63 Erosion Behaviour of Stainless Grade-316 Sourabh Dhawan, Harinder Singh, Ranjit Singh 1,2,3 (Mechanical Engineering, BBSBEC (FGS) / PTU, India) Abstract: Erosion of the hydro turbine steels is

More information

Sustainable Intelligent Mining Systems World Class Demonstrations Bergforsk. Morgan Rody

Sustainable Intelligent Mining Systems World Class Demonstrations Bergforsk. Morgan Rody Sustainable Intelligent Mining Systems World Class Demonstrations Bergforsk Morgan Rody Horizon 2020 Horizon 2020 is the biggest EU Research and Innovation program ever with nearly 80 billion of funding

More information

airsight NextGen Airfield Inspections

airsight NextGen Airfield Inspections airsight NextGen Airfield Inspections airsight takes airfield inspection services to the next level with the utilisation of light Unmanned Aerial Vehicles (UAV). airsight UAVs, equipped with a GPS and

More information

LIGHTWEIGHT WOOD-BASED WALLS WITH VARIOUS THERMAL INSULATIONS: LONG-TIME MEASUREMENT AND SUBSEQUENT COMPARISON WITH HAM SIMULATION

LIGHTWEIGHT WOOD-BASED WALLS WITH VARIOUS THERMAL INSULATIONS: LONG-TIME MEASUREMENT AND SUBSEQUENT COMPARISON WITH HAM SIMULATION LIGHTWEIGHT WOOD-BASED WALLS WITH VARIOUS THERMAL INSULATIONS: LONG-TIME MEASUREMENT AND SUBSEQUENT COMPARISON WITH HAM SIMULATION Pavol Durica 1, Peter Juras 2, Vladimir Gaspierik 1, Jan Rybarik 1, Daniela

More information

THE HAZARDS OF TRYING TO IMPROVE THE SAFETY OF TUNNELS

THE HAZARDS OF TRYING TO IMPROVE THE SAFETY OF TUNNELS - 234 - THE HAZARDS OF TRYING TO IMPROVE THE SAFETY OF TUNNELS Day J.R. CEng FIMechE Pöyry Infra Ltd, Zurich, Switzerland ABSTRACT In recent years a number of countries have updated their requirements

More information

MOVABLE REFUGEE SHELTERS

MOVABLE REFUGEE SHELTERS MOVABLE REFUGEE SHELTERS Your success is: economical, ecological and innovative approach to construction industry. EUROPEAN QUALITY MOVABLE REFUGEE SHELTERS OUR COMPANY HAS DESIGNED SOLUTIONS THAT PROVIDE

More information

As-Built Modelling and Assessment

As-Built Modelling and Assessment As-Built Modelling and Assessment Ioannis Brilakis, Ph.D. Laing O Rourke Lecturer in Construction Engineering Civil, Structural and Environmental Engineering Restoring and Improving Urban Infrastructure

More information

Application of Fiber Model for Progressive Collapse Analysis of Reinforced Concrete Frames *

Application of Fiber Model for Progressive Collapse Analysis of Reinforced Concrete Frames * Application of Fiber Model for Progressive Collapse Analysis of Reinforced Concrete Frames * Xinzheng Lu, Yi Li, Lieping Ye and Yi Liang Department of Civil Engineering, Tsinghua University, Beijing 100084,

More information

EPAM. The 4 th EPAM conference Conclusions. Sweden th European Pavement and Asset Management Conference 5-7 September 2012 Malmö, Sweden

EPAM. The 4 th EPAM conference Conclusions. Sweden th European Pavement and Asset Management Conference 5-7 September 2012 Malmö, Sweden 4 th European Pavement and Asset Management Conference 5-7 September 2012 Malmö, Sweden EPAM Sweden 2012 The 4 th EPAM conference Conclusions Sigurdur Erlingsson Pavement Engineering VTI - The Swedish

More information

roofing ROOFING Design of the base ROOFING DETAILS

roofing ROOFING Design of the base ROOFING DETAILS DETAILS The general arrangement details and the principles to be followed at skirtings, upstands, abutments, verges, gutters and expansion joints are as details illustrated. SELECTION PARAMETERS It is

More information

The Passive Fire Protection Handbook

The Passive Fire Protection Handbook The Passive Fire Protection Handbook The UK s comprehensive guide to passive fire protection Chapter Ceilings, Floors and Roofs AUGUST 0 The Passive Fire Protection Handbook Contents Chapter : Introduction

More information

Removable diagnostic tools of the railway track and rails developed by INFOTRANS

Removable diagnostic tools of the railway track and rails developed by INFOTRANS Removable diagnostic tools of the railway track and rails developed by INFOTRANS Manual automated diagnostic complex RPI in the basic packaging RPI with established receiver GLONASS/GPS, spatial scanning

More information

Injection Systems RASCOtec

Injection Systems RASCOtec Injection Systems RASCOtec Injection System RASCOtec Injection System From a technical point of view, injection systems are widely recognized as the number-one solution for waterproofing buildings exposed

More information

Qualification Specification. Level 3 Diploma in Engineering Surveying

Qualification Specification. Level 3 Diploma in Engineering Surveying Qualification Specification Level 3 Diploma in Engineering Surveying ProQual 2017 Contents Page Introduction 3 Qualification profile 3 Centre requirements 4 Support for candidates 4 Assessment 5 Internal

More information

Achieving the nearly zero energy building concept - A study based on practical experience

Achieving the nearly zero energy building concept - A study based on practical experience Achieving the nearly zero energy building concept - A study based on practical experience SIMON PESCARI, VALERIU STOIAN, DANIEL DAN, DAN STOIAN Department of Civil Engineering and Equipment, Faculty of

More information

Optimum Design of the Box Frame Tunnel of the Underground Line Palma-UIB

Optimum Design of the Box Frame Tunnel of the Underground Line Palma-UIB X INTERNATIONAL CONGRESS ON PROJECT ENGINEERING Optimum Design of the Box Frame Tunnel of the Underground Line Palma-UIB Perea, Alcalá, Martínez, Yepes (p) and González-Vidosa Group of Methods of Construction,

More information

Waterproof membrane can be applied safely on sprayed concrete reinforced with Dramix steel fibre type 3D 65/35BG

Waterproof membrane can be applied safely on sprayed concrete reinforced with Dramix steel fibre type 3D 65/35BG Dramix Waterproof membrane can be applied safely on sprayed concrete reinforced with Dramix steel fibre type 3D 65/35BG In double shell tunnel construction, a waterproof membrane combined with a geotextile,

More information

PRODUCT DATA SHEET Sikalastic -501 Roofseal Plus

PRODUCT DATA SHEET Sikalastic -501 Roofseal Plus PRODUCT DATA SHEET ECONOMICAL LIQUID APPLIED ROOF WATERPROOFING SOLUTION DESCRIPTION is a cold-applied, onecomponent waterborne liquid applied waterproofing membrane, highly elastic and UV resistant. USES

More information

RCDC V6.0. Release Notes

RCDC V6.0. Release Notes Release Notes RCDC V6 is here with numerous new features delivering greater accuracy and flexibility to the design, detailing, drawing and reporting experience. The new features introduced are: No Module

More information

Fire protection of tunnels - options and solutions

Fire protection of tunnels - options and solutions Fire protection of tunnels - options and solutions Dr. Claus K. Larsen Technology dep, Tunnel and concrete div. Fatal catastrophic fires has increased the focus on fire safety in tunnels Fires in road

More information

For more information on ordering from Federal Supply Schedules click on the

For more information on ordering from Federal Supply Schedules click on the GENERAL SERVICES ADMINISTRATION Federal Supply Service AUTHORIZED FEDERAL SUPPLY SCHEDULE PRICE LIST SCIENTIFIC EQUIPMENT AND SERVICES SCHEDULE #66 Leica Geosystems Phone number: (770) 326-9500 Fax number:

More information

Recommendations for additional fire protection of structural elements

Recommendations for additional fire protection of structural elements ANNEX 6 Recommendations for additional fire protection of structural elements 1 Scope This Annex contains a series of recommendations applicable to structural concrete structures which, for general fire

More information

Blaxland Bridge Bearing Replacement

Blaxland Bridge Bearing Replacement Blaxland Bridge Bearing Replacement Marcia Prelog, Associate, Aurecon ABSTRACT The bearing replacement design for the bridge crossing Nepean River at Blaxland s Crossing, Wallacia, was initially presented

More information

Reconstruction of Space Steel Constructions

Reconstruction of Space Steel Constructions 28 September 2 October 2009, Universidad Politecnica de Valencia, Spain Alberto DOMINGO and Carlos LAZARO (eds.) Reconstruction of Space Steel Constructions Jan BRODNIANSKY*, Zoltán AGÓCS, Rudolf ÁROCH,

More information

Sarnavap 5000E SA Vapour Control Layer

Sarnavap 5000E SA Vapour Control Layer Roofing Product Data Sheet Edition 09.2008 Identification no. 02 09 01 05 402 0 000007 Version no. 02 Sarnavap 5000E SA Vapour Control Layer Product Description Sarnavap 5000E SA is a multi-layer self-adhesive

More information

84 Lapping & Jointing 86 Service Pipe Penetrations 87 Sealing to Cavity Wall Constructions 88 protecting Membranes 90 System Components.

84 Lapping & Jointing 86 Service Pipe Penetrations 87 Sealing to Cavity Wall Constructions 88 protecting Membranes 90 System Components. 84 Lapping & Jointing 86 Service Pipe Penetrations 87 Sealing to Cavity Wall Constructions 88 protecting Membranes 90 System Components installation/ SYSTEM COMPONENTS INSTALLATION ADVICE LAPPING and JOINTING

More information

TENSILE TESTING AT HIGH STRAIN RATES USING DIC METHOD. Martina MAREŠOVÁ, Pavel KONOPÍK

TENSILE TESTING AT HIGH STRAIN RATES USING DIC METHOD. Martina MAREŠOVÁ, Pavel KONOPÍK TENSILE TESTING AT HIGH STRAIN RATES USING DIC METHOD Martina MAREŠOVÁ, Pavel KONOPÍK COMTES FHT a.s., Průmyslová 995, 334 41 Dobřany, Czech Republic, EU, martina.maresova@comtesfht.cz, pavel.konopik@comtesfht.cz

More information

TRACC. Product Manual. Crash attenuation cushion. Release 10/14

TRACC.  Product Manual. Crash attenuation cushion. Release 10/14 TRACC Crash attenuation cushion Product Manual Release 10/14 TRACC is licensed to Ingal Civil Products by Trinity Industries Inc. of the U.S.A. www.ingalcivil.com.au TRACC Crash attenuation cushion 1.0

More information

MAXIMUS. for free. 5 years LIGHTWAY. High Performance Skylight. Daytime lighting for industrial halls, offices, sales areas, and warehouses

MAXIMUS. for free. 5 years LIGHTWAY. High Performance Skylight. Daytime lighting for industrial halls, offices, sales areas, and warehouses LIGHTWAY MAXIMUS 5000 High Performance Skylight Daytime lighting for industrial halls, offices, sales areas, and warehouses Industrial halls lighted for free return on investment 5 years Lights halls with

More information

AG MONITORING CURRENT MEMBERS

AG MONITORING CURRENT MEMBERS MONITORING AG MONITORING CURRENT MEMBERS Currently the following companies are members of the AG Monitoring itmsoil, France Soldata, France Geodata, Austria Amberg Technologies, Switzerland Babendererde

More information

.Jan NEMCIK *, Ernest BAAFI and Ian PORTER

.Jan NEMCIK *, Ernest BAAFI and Ian PORTER Acta Geodyn. Geomater., Vol. 10, No. 2 (170), 207 213, 2013 DOI: 10.13168/AGG.2013.0021 STABILISING ROCK SURFACES WITH A GLASS REINFORCED POLYMER SKIN.Jan NEMCIK *, Ernest BAAFI and Ian PORTER School of

More information

An introduction to Part L U-values

An introduction to Part L U-values December 2010 An introduction to Part L This document provides a wide selection of building fabric constructions with their associated. It has been produced a support to our publication An introduction

More information

Alisply-M Walls (Handset)

Alisply-M Walls (Handset) Alisply-M Walls (Handset) Product brochure Encofrados J. Alsina S.A. Pol. Ind. Pla d en Coll Camí de la Font Freda, 1 08110 Montcada i Reixac (Barcelona - Spain) Tel.: (+34) 935 753 000 Fax: (+34) 935

More information