1 Dear Sirs Project Name Appointment of Project Architect On behalf of the University, I am pleased to offer you a formal appointment as Project Architect of the captioned project responsible to the Campus Development Office (CDO) of the University on the following terms and conditions:- 1.0 Scope of Project 2.0 Scope of Services 2.1 Architectural Services To provide full architectural services normally rendered by an architect for a building project such as outlined below for the subject development: Inception Receiving an initial statement of requirements and budget. Assessing development potential as allowed by statutory regulations. Outlining possible course of action and determining the brief in sufficient detail for subsequent works Feasibility Studies Receiving amended statement of requirements, budget etc. making a detailed investigation into the restrictions imposed by relevant authorities and government statutes. Preparing sketches illustrating the overall form of the project. Advising on an approximation of the cost of meeting the client s requirements, a statement on the need for consultants, an outline timetable and a suggested contract procedure Outline Schematic Proposals Analysing the client s requirements and where necessary instructing the Quantity Surveyor and consultants. Preparing, describing and illustrating outline proposals, including an approximation of the cost of meeting them. Informing the client of any major decisions which are needed and receiving any amended instructions Project Design Preparing in collaboration with the Quantity Surveyor and consultants, if appropriate, a scheme design consisting of drawings, and outline specification sufficient to indicate spatial arrangements, materials and appearance. Presenting a report on the project, the estimated cost and preliminary timetable for the project, for the client s approval. Making submissions of these plans to any relevant statutory bodies. Preparing all the necessary plans, calculations etc. ready for submission to the Building Authority in respect of general drawings, site formation, demolition and hoardings etc.
2 2.1.5 Contract Documents Submitting general building plans to the Building Authority and making any amendments necessary in order to obtain approval. Completing a detailed design and specification as necessary, incorporating any design work done by consultants, specialist subcontractors and suppliers. Obtaining estimates and other information from specialist subcontractors and suppliers. Preparing information necessary for the preparation of bills of quantities if Quantity Surveyor is appointed, carrying out cost checks as necessary, preparing production drawings, and, for UGC subvented project, making submissions to Architectural Services Department (ASD) for pretender vetting via CDO. Recommending suitable contractors for inclusion in a tenderer list, obtaining and advising on tenders, preparing and advising on the contract documentation and the appointment of contractors Building Construction 2.2 Responsibilities Obtaining the clients instructions regarding the acceptance of tenders. Obtaining consent to commence work from the Building Authority. Supplying information to the contractor and arranging for him to take possession of the site and examining his programme. Making periodic visits to the site and carrying out the statutory duties of the architect as required under the provisions of the Building Ordinance. Making periodic valuations of work done and materials on site (if a Quantity Surveyor is not employed) and issuing certificates and other administrative duties under the building contracts. Accepting the building on behalf of the client, providing scaled drawings showing the main lines of drainage and obtaining drawings of other services as executed, and giving initial guidance on maintenance. Preparing schedules of defects and supervising rectification to clients satisfaction. Issuing a certificate on making good the defects and final accounts The architect must obtain the authority of CDO before initiating any service or Work Stage The architect shall not make any material alteration, addition to or omission from the approved design without the knowledge and consent of the client, except if found necessary for constructional reasons in which case he shall inform the client without delay The architect shall inform the client if he has reason to believe the total authorised expenditure or contract period are likely to be materially varied The architect shall advise on the selection and appointment of the contractor and shall make such periodic visits to the site as he considers necessary to inspect generally the progress and quality of the work and to determine in general if the work is proceeding in accordance with the contract documents During his on-site inspections, the architect shall endeavour to guard the client against defects and deficiencies in the work of the contractor.
3 2.3 Plumbing and Drainage To provide the design of internal and external plumbing and drainage system including connection to existing systems at the vicinity of the site compound as well as any internal design that may be assigned in future. In this connection, the University will not be liable for further fees charged by any sub-consultants engaged by you.. Works included: - Rainwater Disposal Systems - Soil and Waste Water Drainage Systems and Sanitary Fittings - Cold and hot water services 2.4 Authorized Person To be the Authorized Person under the Buildings Ordinance for the project. 2.5 Co-ordination To co-ordinate the works of all other Consultants. 2.6 Meetings, Presentations To attend meetings, produce minutes, and give presentations as necessary during the processing of the project. 2.7 Documentation for Client Notwithstanding Clause 5.2 below, the Project Architect shall provide free of charge the following record documents/items for use by the Campus Development Office within 2 weeks after issuance of Occupation Permit or termination of this Agreement. - 1 no. bound Certified True Copy of each of the construction contracts. - Computer disk copy of all current CAD drawing files of AutoCAD version 2000 and 1 copy of polyester film plot of each drawing. - 2 copies of current detail drawings up to A3 size. - 1 sepia copy of all other current non-cad drawings larger than A3 size. - Up-to-date drawing index - computer disk copy of file plus 2 no. print-outs. - Up-to-date drawing register showing issue of all drawings to various parties - computer disk copy of file plus 2 no. print-outs. - Any other documents, drawings, and information as required by the Campus Development Office. The Architect shall surrender or cause other members of the consultant team to surrender to the University all Authorities (BD, FSD, DLO, WA, GEO etc.) approved drawings including Site Formation Plans, GBP, P&D, Structural Framing Plans, etc. within 2 weeks after the issuance of Occupation Permit or termination of this Agreement. 2.8 Works excluded from the appointment The inception works and part of the feasibility studies described earlier in (2.1.1) and (2.1.2) have been completed by others already.
4 They are therefore omitted from your services and entitlement of fees accordingly. Your fees receivable shall only be up to a maximum of 90% of the full professional services. 3.0 Work Programme and General Communications 3.1 Work Programme To produce detailed Works Schedules and Programs indicating the time required for the processing of each stage of detail planning and design, submission to the Building Authority and other relevant Government bodies, and preparation of specifications and detail drawings, including the works of all consultants of the professional team. To observe and comply with the time programme set out by the University and agreed by you for the completion of the development. 3.2 Correspondence/Communication All correspondence between the relevant parties, including Project Architect, the Consultant Team and contractors shall be copied to the University Campus Development Office. The Campus Development Office will where possible provide all necessary or requested information regarding University s requirements and users requests. Any direct communication taken place between the Consultant and individual users or Departments/Units should be made only with the full knowledge and attendance of the Campus Development Office. All users requests must be instructed or authorized in writing by the Campus Development Office prior to being incorporated into your design/works. Progress reports in written format should be submitted to the Campus Development Office at intervals not longer than quarter-yearly. 3.3 Sketches & Preliminary Design The development construction floor areas together with outline sketches sufficient to demonstrate the design and layout of the proposed building shall be prepared by the Project Architect for submission to the Campus Development Office for approval. No preparation of site formation plans, general building plans, structural plans, building services plans, installation details, working and tender drawings, etc. shall be proceeded without the authorization of the Campus Development Office, or otherwise, any abortive design due to necessary revisions/modifications shall be at the Project Architect s sole risk and expenses. 3.4 Estimate Upon approval of the schedule of floor areas and the sketches, the Project Architect in consultation with the Campus Development Office shall instruct the Quantity Surveyor jointly with the B.S. Engineers and geotechnical consultant as appropriate to prepare an estimate of the construction cost of the project, and likewise upon completion of detail design and working drawings.
5 3.5 Drawings & Specifications All drawings and specifications including those prepared by other Consultants shall first be co-ordinated by the Project Architect before submission to the Campus Development Office for approval. 4.0 Remuneration and Payment Schedule 4.1 Remuneration The remuneration of services described above shall be % of the construction cost based on the lower of the following but shall not exceed HK$ in any case. Any additional fees shall be subject to separate agreement and confirmation from CDO. a) Budget estimate of the constructional cost less the cost of furniture and equipment, contingencies and provisional sums. b) Awarded contract sum, or the lowest tender price received and not subsequently withdrawn, excluding costs of furniture and equipment, contingencies and provisional sums. No adjustment of fees shall be made on the final account of the construction contracts for the variation within 10% of the awarded contract sum. Until formal instruction/confirmation by the CDO, no work should proceed from one stage to another; otherwise it would be at the Project Architect s own risk. The CDO/University would not be liable for any such services rendered.
6 4.2 Payment Schedule Payment of fees shall follow the schedule shown below on completion of each stage of services and out-of-pocket expenses by disbursement shall be paid at bi-monthly intervals: (A) (B) Inception ( or 0% if already undertaken by the University) Assessment of development potential. Determination of brief in sufficient detail. Feasibility Studies ( or 0% if already undertaken by the University) Feasibility & assessment of proposed development. Conceptual design including advice on cost and options 2% 3% 2% 3% (C) Outline Schematic Proposal (3%) Approval of Schematic Design. 3% (D) Project Design (17%) Approval of Initial Sketch Design 2% Initial appointment up to this stage for PPFS submission only. Subtotal: 1 Approval of Final Sketch Design Approval of General Building Plans and Completion of Design Details. (E1) Submission of Building Plans (1) Submission of General Building Plans, Structural Plans, Plumbing & Drainage Plans. Approval of Submitted Plans and Amendments. (E2) Contract Documents (2) Approval of all tender drawings and specifications including Bills of Quantities. Award of Foundation Contract and issue of Construction Drawings. Award of Main Contract and issue of Construction Drawings. (F) Building Construction (30%) Completion of sub-structural work Completion of all reinforced concrete structure work Completion of door frames, all internal non-structural walls and plastering works Completion of all external wall finishes and window installation works Issuance of Occupation Permit Upon Expiration of the Defects Liability Period and on completion of all outstanding contract and remedial works 10% 10% % ====
7 Interim fees payment shall be based on the estimated construction cost less provisional sums and contingencies, to be adjusted when the contract sum is available. 5.0 General 5.1 The University will appoint separately BSE/RSE/GE/QS Consultants to provide necessary services for other works associated with the subject project. The architect s services shall include landscape/lighting/acoustic/graphic consultancies unless otherwise specifically required by the University for areas of special importance; as well as provision of Technical Competent Persons under AP s stream for Site Safety Supervision and supervisory personnel for Quality Supervision. 5.2 In addition to professional fees, you will be reimbursed for all reasonable out-of-pocket expenses actually and properly incurred in connection with the commission, following the general practice of the ASD. These include printing, reproduction or purchase of documents and drawings. Printing reimbursements are to be at cost or in accordance with the attached ASD schedule of standard charges, whichever is the lowest. In case that no reference price in the printing charge schedule attached herewith for the type and size of printing subject to reimbursement, printing reimbursements are to be at cost. All in-house xerox copy for general correspondence (except for contract documentation), travelling expenses, postage, costs for presentation materials, unless extra copies requested by the University, and courier costs will not be reimbursed. 5.3 Any additional services required shall be charged in a manner to be agreed with and authorized in writing by the Director of the Campus Development Office or his authorized representative in advance. The University will not accept hourly charge rates, and the fee quoted above shall serve as pro-rata basis for calculation of additional fee for additional services and/or variation of the scope of consultancy services. 5.4 The University will appoint Clerk-of-Works to supervise the progress on both engineering and architectural works. Any site instructions to be given by any Consultants must have a cost valuation and be issued in writing through the Project Architect after duly authorized by the Campus Development Office. 5.5 The copyright of all drawings, reports, calculations and other similar documents produced by the Architect shall be vested with the University which, however, shall use such drawings and documents only for purposes relating to the construction of the subject project, including its future operation, maintenance, alteration, and relevant University functions. 5.6 Any additional services required shall be charged in a manner to be agreed with and authorized in writing by the Director of the Campus Development Office or his authorized representative in advance. In any case, the lump sum fee quoted above shall serve as pro-rata basis for calculation of additional fee due to additional services and/or variation of the scope of consultancy services. The University does not accept hourly charge rates for calculation of additional fee due to additional services and/or variation of the scope of consultancy services.
8 6.0 Termination 6.1 This appointment does not construe an irrevocable commitment for full service. The University reserves the right to suspend/postpone the project and/or to terminate the Appointment at anytime by serving a 14-calender days written notice, in which case no claims for loss or damage by the Project Architect would be entertained. 6.2 The fees shall then be calculated in accordance with the payment schedule in Section (4.0) up to the date of suspension/termination. Upon payment of fees due, the University shall be entitled to use all drawings and documents produced by the Architect to continue the construction of the project to completion without further payment of copyrights or any other fees/charges whatsoever. 6.3 Should either party of this agreement substantially fail to perform to the terms and conditions stated herein, this agreement may be terminated immediately by either party serving the other a written notice. Upon termination, the University shall be entitled to use all designs, drawings, and documents produced by the Architect to continue the construction of the project to completion. The Architect s fee shall then be calculated in accordance with the payment schedule in section (4.0) up to the date of termination, but the University reserves the right to recover from the Architect loss and damages due to his failure to perform, if any. 6.4 You are required to observe specifically the time programme as timely provision of your services is extremely important. 7.0 Special Conditions The following conditions of appointment specified by University Grants Committee and the University Administration also shall apply: You shall act in compliance with the directions of the University, taking into consideration its decisions and views channelled through its representatives in the Campus Development Office, viz., the Director and/or his delegated officers. You shall keep the Campus Development Office informed of all matters relating to the project within your knowledge, answer all reasonable enquiries received, render reports at reasonable intervals when asked to do so, and assist the Office to form an opinion as to the manner in which works on the project should proceed. You shall permit authorized public officers to inspect records, measurements books, accounts, etc. in connection with the project and answer queries or supply information reasonably requested by such officers. Where the development is located within the Hospital precinct, liaison with the Hospital Authority and compliance with its rules and regulations for works at the hospital compound will be requisite. Your performance will be regularly assessed by the Campus Development Office. The performance appraisals are to be recorded to facilitate evaluation of consultants for appointment or shortlisting for other University projects, and the University reserves the right to circulate them to all other University Grants Committee funded institutions and Government Authorities.
9 You and your agents, i.e. persons acting for or on behalf of another, are prohibited from offering, soliciting and accepting advantages, as defined in the Prevention of Bribery Ordinance, in connection with the performance of their duties under this agreement. You shall, when considered necessary by the Campus Development Office, attend or be represented at all meetings to which you may be summoned in connection with the project and shall advise and assist the Office on all matters relating to the duties you have assumed following the appointment. Any dispute or difference arising out of or in connection with this contract shall be referred to and determined by arbitration at the Hong Kong International Arbitration Centre and in accordance with its domestic Arbitration Rules. For the sake of regularity, please acknowledge receipt by signing both copies of this letter and return one set to us within 10 days from the date of this letter. Yours faithfully, For and on behalf of The Chinese University of Hong Kong David S. W. Lim Director, Campus Development Office Enc. cc: DL/ To: Director, Campus Development Office The Chinese University of Hong Kong I/We acknowledge receipt of this appointment letter. For and on behalf of Signature with Company s chop Date:
10 Schedule of Standard Printing Charges with effect from 1 June 2004 (Note : The standard charges under this schedule will be reviewed and revised if necessary.) (a) Printing Charges Size Type A0 Print A0 Sepia A0 Polyester A1 Print A1 Sepia A1 Polyester A2 Print A2 Sepia A2 Polyester A3 Print A3 Sepia A3 Polyester A3 Photostat A4 Photostat Printing Charge Per Sheet $6.21 $18.75 $45.62 $3.11 $9.95 $25.50 $1.67 $5.29 $13.46 $1.55 $4.54 $8.86 $0.35 $0.22 Monochromatic Computer Plotted A0 Paper A0 Tracing A1 Paper A1 Tracing $26.07 $39.10 $14.95 $21.47 Note: The above standard printing charges shall include the material costs and any other expenses such as manpower costs, cost of equipment, administration costs etc. that are incurred by the consultant for the supply, printing, sorting, checking and delivery of the respective printed documents. (b) Standard charges of electronic storage media for the supply and submission of drawings and documents Electronic storage media 1.44MB Floppy Diskette 100MB Zip Diskette 650MB CD-R Charge Per No $1.58 $73.22 $4.22 Note: The above standard unit charges of electronic storage media shall include the material costs of the electronic storage media and any other expenses such as manpower costs, cost of computer equipment, cost pf processing information by computer, administration costs etc, that are incurred by the consultant for the supply, production, checking and delivery of the respective electronic storage media. The consultant shall maximize the usage of the storage capacity of each electronic storage media. (ASD Revision Date: 10 September 2004)
HKIS QSD PQSL Series 2014
HKIS QSD PQSL Series 2014 by Sr. TANG Ki-cheung FHKIS RPS(QS) FSZCEA MHKIVM Director of K C Tang Consultants Ltd. Quantity Surveyors. Construction Cost and Contract Consultants Ltd. on 9 May 2014 (Friday)
More informationTHIS PART DEALS WITH GENERAL CONDITIONS OF ENGAGEMENT AND WILL APPLY IRRESPECTIVE OF THE NATURE OR EXTENT OF SERVICES TO BE PROVIDED.
GENERAL PART:1 THIS PART DEALS WITH GENERAL CONDITIONS OF ENGAGEMENT AND WILL APPLY IRRESPECTIVE OF THE NATURE OR EXTENT OF SERVICES TO BE PROVIDED. 1.01 RESPONSIBILITIES OF THE ARCHITECT 1.01.01 The work
More informationANNEXURE A SCOPE OF WORK FOR PROFESSIONAL SERVICES: RESTORATION OF NON PAREILLE BUILDINGS. Principal Agent and Professional Architectural Services
T: +27 21 462 4502 F: +27 21 462 4509 E: info@sahra.org.za South African Heritage Resources Agency - Head Office 111 Harrington Street Cape Town P.O. Box 4637 Cape Town 8001 ANNEXURE A SCOPE OF WORK FOR
More informationATLANTIC PROVINCES ASSOCIATION OF LANDSCAPE ARCHITECTS
ATLANTIC PROVINCES ASSOCIATION OF LANDSCAPE ARCHITECTS CONSULTANT FEE SCHEDULE FOR LANDSCAPE ARCHITECTURAL CONSULTING SERVICES A GUIDELINE NOV 2008 TABLE OF CONTENTS Table Of Contents... 2 INTRODUCTION...
More informationChapter 2 Parties to the Contract
Chapter 2 Parties to the Contract 2.1 Introduction Construction work may include building of a new structure, additions, alterations, expansion, replacement, dismantling, erection, commissioning, rehabilitation,
More information1997 Part 2. Document B141. Standard Form of Architect's Services: Design and Contract Administration TABLE OF ARTICLES
TM Document B141 Standard Form of Architect's Services: Design and Contract Administration 1997 Part 2 TABLE OF ARTICLES 2.1 PROJECT ADMINISTRATION SERVICES 2.2 SUPPORTING SERVICES 2.3 EVALUATION AND PLANNING
More informationDocument B252TM 2007
Document B252TM 2007 Standard Form of Architect s Services: Architectural Interior Design for the following PROJECT: (Name and location or address) This document has important legal consequences. Consultation
More informationBank of India Jamshedpur Zonal Office Bank of India Bldg., Main Road,Bistupur,Jamshdpur, (Phone No , ) Ref. No.
Bank of India Jamshedpur Zonal Office Bank of India Bldg., Main Road,Bistupur,Jamshdpur, (Phone No.0657-2438339, 2436469) Ref. No.ZO/JSR/CS/14-15: 07-06-2014 N O T I C E I N V I T I N G Q U O T A T I O
More informationSCOPE OF WORK FOR PROFESSIONAL SERVICES: HET POSTHUYS ELECTRICAL UPGRADE
ANNEXURE A T: +27 21 462 4502 F: +27 21 462 4509 E: info@sahra.org.za South African Heritage Resources Agency - Head Office 111 Harrington Street Cape Town P.O. Box 4637 Cape Town 8001 SCOPE OF WORK FOR
More informationRIAI Agreement between Client and Architect for the Provision of Architectural Services Edition 1 (2014)
RIAI Agreement between Client and Architect for the Provision of Architectural Services Edition 1 (2014) Note: In the event that the Architect is appointed as Assigned Certifier this is a separate agreement
More informationReference No. RAMP/C/03-10/CQ
REPUBLIC OF CROATIA MINISTRY OF FINANCE TAX ADMINISTRATION REVENUE ADMINISTRATION MODERNIZATION PROJECT Reference No. RAMP/C/03-10/CQ Terms of Reference Technical Supervision of reconstruction and construction
More informationDesign Team Procedures Practice Note 1, February DESIGN TEAM PROCEDURES PRACTICE NOTE 1 (Revision 2)
DESIGN TEAM PROCEDURES PRACTICE NOTE 1 (Revision 2) CHANGES TO STAGE 2b, STAGE 3 & STAGE 4 ARISING FROM AMENDMENTS TO THE PUBLIC WORKS CONTRACTS 1. Introduction 1.1 Changes to Public Works Contracts (a)
More informationAttachment 1 Architectural Services
A. Phase 1, Programming and Schematic Design: 1. Ascertain the requirements for each project through a meeting with the COUNTY, and a review of an existing schematic layout of each project, if such layout
More informationRIAI Agreement between Client and Architect for Commercial Small Works Edition 1 ( 2014)
RIAI Agreement between Client and Architect for Commercial Small Works Edition 1 ( 2014) Note: In the event that the Architect is appointed as Assigned Certifier this is a separate agreement for which
More informationInvitation to Tender. Development Legal Services. August 2015
Development Legal Services August Contents 1. Important notices... 3 1.1. Confidentiality... 3 1.2. Accuracy of information and liability of SLH... 3 1.3. Canvassing... 4 1.4. Non-collusion... 5 1.5. Copyright...
More informationAppendix 3. POLICY & PROCEDURE No
DEPARTMENT OF PUBLIC WORKS DIVISION: ENGINEERING SERVICES SECTION: ADMINISTRATIVE PAGE NO: 1 OF 10 REVISION NO: 3 DATE: 1995 05 01 ESTABLISHED: 1986 03 03 Appendix 3 POLICY & PROCEDURE No. 2.3.1-020 TITLE:
More informationREGISTRATION OF ENGINEERS ACT 1967 NOTIFICATION OF SCALE OF FEES
REGISTRATION OF ENGINEERS ACT 1967 NOTIFICATION OF SCALE OF FEES IN exercise of the powers conferred by paragraph 4(1)(d) of the Registration of Engineers Act 1967 [Act 138], the Board of Engineers, with
More informationInvitation to Tender. External Audit Services. July 2015
External Audit Services July Contents 1. Important notices... 3 1.1. Confidentiality... 3 1.2. Accuracy of information and liability of SLH... 3 1.3. Canvassing... 4 1.4. Non-collusion... 4 1.5. Copyright...
More informationDocument B101 TM. Standard Form of Agreement Between Owner and Architect
Document B101 TM 2007 Standard Form of Agreement Between Owner and Architect AGREEMENT made as of the day of in the year (In words, indicate day, month and year.) BETWEEN the Architect s client identified
More informationDocument B Standard Form of Agreement Between Owner and Architect, Construction Manager as Adviser Edition
Document B132 2009 Standard Form of Agreement Between Owner and Architect, Construction Manager as Adviser Edition AGREEMENT made as of the in the year (In words, indicate day, month and year.) BETWEEN
More informationSTATE BANK OF PATIALA REGION -IV,CHANDIGARH
STATE BANK OF PATIALA REGION -IV,CHANDIGARH FURNISHING OF CHAMKAUR SAHIB BRANCH DISTRICT ROPAR INVITATION OF COMPETITIVE QUOTATION FOR SELECTION OF ARCHITECT PERFORMA OF QUOTATION Sealed quotation in prescribed
More informationSPECIMEN. The Architect warrants that s/he is a Registered Architect and a Member of the RIAI.
Agreement between Client and Architect for Domestic Works Edition 2 (September 2016) Note: In the event that the Architect is appointed as Assigned Certifier there is a separate agreement for which there
More informationINVITATION OF EXPRESSION OF INTEREST FOR EMPANELMENT OF ARCHITECT
MAHARASHTRA RAJYA SAHAKARI DUDH MAHASNGH MARYADIT, MUMBAI. INVITATION OF EXPRESSION OF INTEREST FOR EMPANELMENT OF ARCHITECT Page 1 of 13 EMPANELMENT OF ARCHITECT Maharashtra Rajya Sahakari Dudh Mahasangh
More informationArchitectural Design and Build Process. A Client Guide
Architectural Design and Build Process A Client Guide This guide has been prepared to summarise the various stages of a new-build residential design & construction process. It identifies important tasks
More informationJK 1. RIBA stages JK START OF MAIN CONTRACT WORKS 1. DEFINITION 2. PURPOSE 3. PROCEDURE 3.1 PROJECT MANAGEMENT TEAM ROLE
THE UNIVERSITY of EDINBURGH Estates & Buildings ESTATE DEVELOPMENT ISSUE/REVISION JK 1 LAST MODIFIED 12 October 2011 DATE PRINTED RIBA stages JK JK 1 START OF MAIN CONTRACT WORKS 1. DEFINITION The Main
More informationList of Financial Regulations
HEPTONSTALL PARISH COUNCIL FINANCIAL REGULATIONS List of Financial Regulations 1. General 25 2. Annual Estimates 25 3. Budgetary Controls 25 4. Accounting and Audit 26 5. Banking Arrangements and Cheques
More informationAttachment to Standard Form of Agreement Between Owner and Architect AIA Document B (Date)
Attachment to Standard Form of Agreement Between Owner and Architect AIA Document B103 2007 () Appropriation Year(s): Cost Center: Object Codes: Fee: Reimbursement: Amounts Fee: $ Reimbursables: $ Vendor
More informationAppendix C Having used FIDIC 99 as the basis for identifying the modifications made within the analyzed contracts, it was necessary to understand the
Appendix C Having used FIDIC 99 as the basis for identifying the modifications made within the analyzed contracts, it was necessary to understand the differences between FIDIC 87 and FIDIC 99. The below
More informationTEXAS WOMAN'S UNIVERSITY AND ABC Design Firm
PROFESSIONAL SERVICES AGREEMENT BETWEEN TEXAS WOMAN'S UNIVERSITY AND ABC Design Firm This Agreement made the (spell out day ) day of Month, Year, by and between TEXAS WOMAN'S UNIVERSITY, Denton, Texas,
More informationInvitation to tender. Provision of External Audit Services
Invitation to tender for the Provision of External Audit Services Tender return date: 10.00 am on 2 nd May 2017 Return to: Enquiries to: Address: Clerk to the Corporation Alison Rowland (arowland@sussexcoast.ac.uk)
More informationCode of Practice. for Inspecting and Certifying Buildings and Works. Building Control Regulations 1997 to 2015
for Inspecting and Certifying Buildings and Works Building Control Regulations 1997 to 2015 September, 2016 Table of Contents 1. Introduction 1 1.1 Status and Purpose of Code 1 1.2 Overview of Code 1
More informationEYNSFORD PARISH COUNCIL
EYNSFORD PARISH COUNCIL FINANCIAL REGULATIONS These Financial Regulations were adopted by the Council at its Meeting held on 20 September 2007, last amended on 20 th July 2017. 1. GENERAL 1.1 These financial
More informationRef no.zo/csd/bps/ /452 Date: NOTICE INVITING QUOTATION
ZONAL OFFICE GHAZIABAD ZONE SANDIPANI B-32 SECTOR-62, NOIDA PHONE-0120-2404136,2400088 E-mail: zo.ghaziabad@bankofindia.co.in Ref no.zo/csd/bps/2017-18/452 Date: 17.03.2018 NOTICE INVITING QUOTATION Quotation
More informationNOTICE FOR SELECTION OF ARCHITECT FOR ALTERATION / ADDITIONAL CONSTRUCTION WORK ON THE EXISITING BUILDING OF BHUBANESWAR CHAPTER OF ICSI
NOTICE FOR SELECTION OF ARCHITECT FOR ALTERATION / ADDITIONAL CONSTRUCTION WORK ON THE EXISITING BUILDING OF BHUBANESWAR CHAPTER OF ICSI The Institute of Company Secretaries of India (ICSI) has its own
More informationCONSTRUCTION MANAGER
The South African Council for the Project and Construction Management Professions CONSTRUCTION MANAGER IDENTIFICATION OF WORK AND SCOPE OF SERVICES FOR CONSTRUCTION MANAGERS REGISTERED IN TERMS OF THE
More informationProfessional Practice 544
February 22, 2016 February 29, 2016 Professional Practice 544 AIA-B101 Owner - Architect Agreement Michael J. Hanahan Schiff Hardin LLP 233 S. Wacker, Ste. 6600 Chicago, IL 60606 312-258-5701 mhanahan@schiffhardin.com
More informationa) Hostel 50 Capacity with twin sharing basis b) Common room for Hostel c) Dean s Residence d) Care taker residence
NOTICE FOR SELECTION OF ARCHITECT FOR CONSTRUCTION OF PREMISES FOR INSTITUTE S CENTRE OF EXCELLENCE (CoE) AT PLOT NO. IIA/3, ACTION AREA- IIA, NEW TOWN, KOLKATA 70017 The Institute of Company Secretaries
More informationInvitation For Expression Of Interest For Providing Project Management Consultancy Services At Vidyasagar Industrial Park at Kharagpur In West Bengal
Invitation For Expression Of Interest For Providing Project Management Consultancy Services At Vidyasagar Industrial Park at Kharagpur In West Bengal INTRODUCTION West Bengal Industrial Development Corporation
More informationZONAL OFFICE GHAZIABAD ZONE QUOTATION FORM FOR
ZONAL OFFICE GHAZIABAD ZONE QUOTATION FORM FOR Appointment of Architect/Consultant for proposed Renovation/ Repair works in Aligarh Main branch in Ghaziabad Zone Last Date of submission of quotation 01.08.2018
More informationApplication Pack 2. Dŵr Cymru Welsh Water s Guidance on how to apply to Requisition Water Mains and Services July 2015
Application Pack 2 Dŵr Cymru Welsh Water s Guidance on how to apply to Requisition Water Mains and Services July 2015 This guidance applies where a developer decides to requisition water mains and services
More informationTender Document and Specification
Tender Document and Specification for Council Property Assorted Painting and Decorating between Parks and Recreation and Contractor CONTRACT 2014-02 March 2014 CONTENTS Instruction to Tenderers... 3 Foreword
More informationAGREEMENT FOR ARCHITECTURAL SERVICES
AGREEMENT FOR ARCHITECTURAL SERVICES This Agreement for ( Agreement ) is dated XX XX, 20XX for reference purposes only and is made by and between SANTA MONICA-MALIBU UNIFIED SCHOOL DISTRICT, a California
More informationChapter 4 State Requirements for Educational Facilities Section 4.1
providential cause, other impending danger to life safety, or pursuant to Section 1013.46(1)(b), F.S., the board can declare an emergency, can negotiate a contract with a design-build firm, design professional,
More informationRYDE TOWN COUNCIL QUOTATION DOCUMENTATION TOWN MAP AND EVENTS POSTER
RYDE TOWN COUNCIL QUOTATION DOCUMENTATION TOWN MAP AND EVENTS POSTER November 2017 Ryde Town Council Town Map and Events Quotation Documentation November 2017 Page 1 RYDE TOWN COUNCIL TOWN MAP AND EVENTS
More informationAppendix 2: Term Sheet. SECTION 37 TERM SHEET FOR CITY SPACE AT THE CONDOMINIUM TO BE CONSTRUCTED AT 200 DUNDAS STREET EAST (the "Project")
September 10, 2013 Appendix 2: Term Sheet SECTION 37 TERM SHEET FOR CITY SPACE AT THE CONDOMINIUM TO BE CONSTRUCTED AT 200 DUNDAS STREET EAST (the "Project") 1. Owner: The term "Owner" in the term sheet
More informationTender Document and Specifications for Council Property Assorted Painting and Decorating between Parks and Recreation and Contractor.
Tender Document and Specifications for Council Property Assorted Painting and between Parks and Recreation and Contractor. CONTRACT 2014-02 November 2014 CONTENTS Instruction to Tenderers... 3 Foreword
More informationWhy Use an Architect?
Architects Can Help Interpret Your Dreams Into A Built Reality Architects provide a service that extends well beyond producing a set of drawings. An architect will listen to your dreams, your aspirations,
More informationFORM OF APPOINTMENT AS CONSULTANT (CDM CO-ORDINATOR) (FOAC
Form of Appointment Shaping and sharing best practice in construction health and safety risk management FORM OF APPOINTMENT AS CONSULTANT (CDM CO-ORDINATOR) (FOAC 2011) Under the Construction (Design and
More informationUniversity Architect & VP for Facilities Policy & Procedure #14
University Architect & VP for Facilities Policy & Procedure #14 TITLE: OBJECTIVE AND PURPOSE: RESPONSIBILITY: ADMINISTRATION OF AGREEMENT BETWEEN OWNER AND ARCHITECT/ENGINEER (MAJOR PROJECTS) To establish
More informationBuilding Control (Amendment) Regulations MBCA Guidance Document
Building Control (Amendment) Regulations 2014 Contents 1. Introduction 4 2. Legislative Background 5 3. Definitions 6 4. Process 7 5. Documents at tender stage 8 6. Building Control Management System 9
More informationREQUEST FOR PROPOSALS FOR PROFESSIONAL ENGINEERING SERVICES FOR CITY OF NANTICOKE
REQUEST FOR PROPOSALS FOR PROFESSIONAL ENGINEERING SERVICES FOR CITY OF NANTICOKE Proposals Solicited by: City of Nanticoke 15 East Ridge Street Nanticoke, PA 18634 C:\Users\jim\Desktop\Nanticoke City\07222013professionalengservices\Engineer
More informationREQUEST FOR PROPOSALS FOR PROFESSIONAL ENGINEERING SERVICES
SEDA-COUNCIL OF GOVERNMENTS REQUEST FOR PROPOSALS FOR PROFESSIONAL ENGINEERING SERVICES ENGINEERING, DESIGN, AND BIDDING 119 SOUTH LOCUST STREET DEMOLITION BOROUGH OF MOUNT CARMEL NORTHUMBERLAND COUNTY,
More information1. This Section includes administrative and procedural requirements for contract closeout including, but not limited to, the following:
SECTION 01700 - CONTRACT CLOSEOUT PART 1 - GENERAL 1.01 RELATED DOCUMENTS 1. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division 1 Specification
More informationQUALITY MANUAL. January PO Box 14659, Zayed Bin Sultan Street, Al Ain, U.A.E.., Tel: , Fax
January 2009 PO Box 14659, Zayed Bin Sultan Street, Al Ain, U.A.E.., Tel: 03-7640177, Fax 03-7640188 Fittons Engineering Consultancy L.L.C Page 1 INDEX Contents QP0 QP1 QP2 QP3 QP4 QP5 QP6 QP7 QP8 QP9
More informationGuideline for Services and Processes for Estimating Fees for Persons Registered in terms of the Engineering Profession Act, 2000, (Act No.
Page 1 BOARD NOTICE... OF 2015 Engineering Council of South Africa Guideline for Services and Processes for Estimating Fees for Persons Registered in terms of the Engineering Profession Act, 2000, (Act
More informationFORMAT FOR PROFESSIONAL FEES ON LETTER HEAD
FORMAT FOR PROFESSIONAL FEES ON LETTER HEAD TO ZONAL MANAGER ZONAL OFFICE,LIC BUILDING, IST FLOOR SANAY PLACE,AGRA E-mail : Premises.agra@bankofindia.co.in Sub: Notice for Appointment of Architect /consultant
More informationSCHEDULE 2 DESIGN AND CONSTRUCTION PROTOCOLS TABLE OF CONTENTS 1. INTERPRETATION Definitions... 1
SCHEDULE 2 DESIGN AND CONSTRUCTION PROTOCOLS TABLE OF CONTENTS 1. INTERPRETATION... 1 1.1 Definitions... 1 2. PARTIES DESIGN AND CONSTRUCTION REPRESENTATIVES... 2 2.1 Appointment of Representatives...
More informationREGISTRATION OF ENGINEERS ACT 1967 NOTIFICATION OF SCALE OF FEES FOR HOUSING DEVELOPMENT
REGISTRATION OF ENGINEERS ACT 1967 NOTIFICATION OF SCALE OF FEES FOR HOUSING DEVELOPMENT IN exercise of the powers conferred by paragraph 4(1)(d) of the Registration of Engineers Act 1967, the Board of
More informationTelephone Head Office North East North West
Telephone Head Office 01422 357707 North East 0191 303 7746 North West 0161 660 7578 Now you don't just have to hope for the best when you're using temporary nursing and care staff. Estio Healthcare is
More informationSchedule 3 Services Schedule Equipment and Equipment-Related Supplies
Equipment and Equipment-Related Supplies Services Schedule Equipment and Supplies Template LHIN Version June 2017 Schedule 3 Services Schedule Equipment and Equipment-Related Supplies TABLE OF CONTENTS
More informationMECHANICAL & ELECTRICAL ENGINEER S SERVICES SCOPE
ROYAL BOROUGH OF GREENWICH MECHANICAL & ELECTRICAL ENGINEER S SERVICES SCOPE PROJECT xxx status: R1 purpose: For information version: 1.0 date: 07/03/2016 1 This version Authored by: name: role: signed:
More informationSTRUCTURAL ENGINEER S SERVICES SCOPE
ROYAL BOROUGH OF GREENWICH STRUCTURAL ENGINEER S SERVICES SCOPE WOOLWICH CREATIVE DISTRICT PROJECT status: R1 purpose: For information version: 1.0 date: 07/03/2016 1 This version Authored by: name: Nick
More informationTruckSafe Operator Business Rules and Code of Conduct
Operator Business Rules and Code of Conduct Contents 1.0 Business Rules and Code of Conduct 3 2.0 Decision Making Bodies 4-6 3.0 Purpose 6 4.0 How the Rules will be amended 6 5.0 Introduction 6 6.0 Entry
More informationPRACTICE NOTES FOR QUANTITY SURVEYORS
PRACTICE NOTES FOR QUANTITY SURVEYORS Pre-Contract Estimates And Cost Plans Preface Preface A Working Committee with representatives from The Hong Kong Institute of Surveyors, Association of Consultant
More informationTender Document and Specifications for Council Property Assorted Painting and Decorating between the Council and Contractor.
Tender Document and Specifications for Council Property Assorted ing and Decorating between the Council and Contractor. CONTRACT 2017-16 1 December 2017 1 CONTENTS Instruction to Tenderers... 3 Foreword
More informationBuilding Terms & Construction Jargon Explained. CLPM Glossary of Terms
Building Terms & Construction Jargon Explained Building terms and construction jargon can be bewildering! If you are busy carrying out research for your building project, you ve probably already been bombarded
More informationProject monitor services
Corporate Professional Local Project monitor services For use with the RICS Short form of consultant s appointment The mark of property professionalism worldwide www.rics.org Project Monitor Services For
More informationGuidelines for the Preparation of Case Studies
Guidelines for the Preparation of Case Studies Applicants for initial registration are required to demonstrate the following. Principle 1 The applicant must demonstrate that he or she is able to practise
More informationGovernment Gazette Staatskoerant
Government Gazette Staatskoerant REPUBLIC OF SOUTH AFRICA REPUBLIEK VAN SUID-AFRIKA Vol. 570 Pretoria, 7 December Desember 2012 No. 35944 N.B. The Government Printing Works will not be held responsible
More informationBUILDING CONTROL (AMENDMENT) REGULATIONS 2013
BUILDING CONTROL (AMENDMENT) REGULATIONS 2013 MIND THE GAP ARCHITECT PRACTITIONER PERSPECTIVE IEI SEMNAR January 2014 Orla Fitz.Gerald MRIAI FCIArb Member COP WG & Architect in Practice Code of Practice
More informationTHE MANCHESTER COLLEGE CONTRACT OF EMPLOYMENT OFFENDER LEARNING
THE MANCHESTER COLLEGE CONTRACT OF EMPLOYMENT OFFENDER LEARNING TIMETABLED SESSIONAL TRAINER / TUTOR - ANNUALISED HOURS CONTRACT DATE OF ISSUE: [DATE] [EMPLOYEE'S NAME] And The Manchester College DATE
More informationFIDIC Contracts. Training Course in English language. May, 25-26, Two days course on:
FIDIC Contracts Training Course in English language May, 25-26, 2018 Two days course on: FIDIC Module 4 - FIDIC Contracts Management and Administration FIDIC 99 EDITIONS ESSENTIALS FOR WORKING IN INTERNATIONAL
More informationCoordination of Consultants
Coordination of Consultants Ontario Association of Architects Practice Tip PT.27 Version 1.0 May 21, 2012 2012 OAA, all rights reserved. Persons who are not members of the OAA must obtain written permission
More informationinstitutions and Public Sector Undertakings for similar works.
Limited Cuffe Parade, Mumbai 400 005 Ph: (022) 6655 3355; Fax: (022) 2218 0411 Notice inviting tender for Architects / Consultants for Electrical, HVAC and Allied Works at IDBI Office building at CBD Belapur,
More informationMINUTES OF PRE-BID CONFERENCE. INVITATION TO BID INTERIOR FITTING-OUT WORKS FOR NEW UNDP CAMBODIA COUNTRY OFFICE Process No:
I. Background MINUTES OF PRE-BID CONFERENCE INVITATION TO BID INTERIOR FITTING-OUT WORKS FOR NEW UNDP CAMBODIA COUNTRY OFFICE Process No: 35-46214 The United Nations Development Programme (UNDP) would
More informationDocument B101 TM. Standard Form of Agreement Between Owner and Architect
Document B101 TM 2007 Standard Form of Agreement Between Owner and Architect AGREEMENT made as of the day of in the year Two Thousand and BETWEEN the Architect s client identified as the Owner: Capitol
More informationNTA Metropolitan Mass Transit System. To: All Bidders Re: Tender 055/2017 for the Signaling and Train Control of the Red Line Project. Addendum No.
Date: 12 th July 2017 #1069265 To: All Bidders Re: Tender 055/2017 for the Signaling and Train Control of the Red Line Project Addendum No. 5 Addendum no. 5 is issued for inclusion into the tender documents.
More informationPOSITION DESCRIPTION DIRECTOR TECHNICAL & DEVELOPMENT SERVICES MANAGER ENGINEERING AND OPERATIONS
POSITION DESCRIPTION POSITION: DESIGN OFFICER CLASSIFICATION: BAND 4 DEPARTMENT: SECTION: OCCUPANT: TECHNICAL & DEVELOPMENT SERVICES ENGINEERING & OPERATIONS VACANT DATE: DECEMBER 2006 REVISED: AUGUST
More informationTownship of Severn REQUEST FOR PROPOSAL. Architectural & Professional Services Fire Station Replacement
Township of Severn REQUEST FOR PROPOSAL Architectural & Professional Services Fire Station Replacement Deadline for proposal submission is June 15, 2017 at 2:00 p.m. Contact Person: Tim Cranney Director
More informationCHAPTER 3: DESIGN. TN Higher Education Designers Manual October 2018 Page 1 of 12
3.01 GENERAL A. Design the project to meet the authorized scope, budget, and schedule. B. Upon initiation of the project, arrange to review with the Owner the service and administrative requirements as
More informationAGREEMENT BETWEEN DESIGNING ARCHITECT AND THE DISTRICT BOARD OF TRUSTEES OF PALM BEACH STATE COLLEGE
AGREEMENT BETWEEN DESIGNING ARCHITECT AND THE DISTRICT BOARD OF TRUSTEES OF PALM BEACH STATE COLLEGE THIS AGREEMENT, is made and entered into this day of, between the DISTRICT BOARD OF TRUSTEES OF PALM
More informationREQUEST FOR PROPOSAL. HRIS Human Resources Information Software Fort Morgan, Colorado
REQUEST FOR PROPOSAL HRIS Human Resources Information Software Fort Morgan, Colorado October 7, 2014 Michael Boyer Director, Human Resources and Risk Management CITY OF FORT MORGAN P.O. BOX 100 FORT MORGAN,
More informationINDIAN INSTITUTE OF TECHNOLOGY INDORE
INDIAN INSTITUTE OF TECHNOLOGY INDORE Notice Inviting Tender 1.0 Tenders are invited on the behalf of the Director, IIT Indore, for the following work from eligible contractors registered/enlisted with
More information1.1. In these Terms of Business the following definitions apply:
Page 1 CONTRACT WITH THE CLIENT (SUPPLYING TEMPORARY STAFF SERVICES/CLIENT TERMS OF BUSINESS) 1. DEFINITIONS 1.1. In these Terms of Business the following definitions apply: Assignment Client means the
More informationCIVIL AND STRUCTURAL ENGINEERING SERVICES TENDER
CIVIL AND STRUCTURAL ENGINEERING SERVICES TENDER 14 HYBRID OFFICE/INDUSTRIAL UNITS At Plots 11 & 12,Cornwall Business Park (West) For JAD Developments (Redruth) Ltd 1 Introduction 1.1 Project Information
More informationDoES-QW1 Suitability Assessment Questionnaire and Declaration
SECTION 1: PROJECT PARTICULARS: Project Title as EU/eTenders Contract Notice: Description as EU/eTenders Contract Notice: Address: Form of Contract: Contractor s Role: Project Category: Areas of work involving
More informationThe Application in-principle (AIP) was approved by the LSC on the 9 th May 2007 for the following buildings:
GRAVESEND CAMPUS 1.0 LEARNING & SKILLS COUNCIL 1.1 Application In Principle The Application in-principle (AIP) was approved by the LSC on the 9 th May 2007 for the following buildings: Gravesend Campus;
More informationDRAFT AGREEMENT BETWEEN OWNER AND PROJECT ARCHITECT
DRAFT AGREEMENT BETWEEN OWNER AND PROJECT ARCHITECT This Agreement is made as of, 20 (the Effective Date ) MD ANDERSON AGREEMENT No. By and between The Owner: The University of Texas M. D. Anderson Cancer
More informationRequest for Proposals for: Construction Management Services For The ADDISON PUBLIC LIBRARY INTERIOR RENOVATION
Request for Proposals for: Construction Management Services For The ADDISON PUBLIC LIBRARY INTERIOR RENOVATION May 19, 2015 The Addison Public Library invites you to submit a reply to this Request for
More informationARCHITECTURAL SERVICES TENDER
ARCHITECTURAL SERVICES TENDER 14 HYBRID OFFICE/INDUSTRIAL UNITS At Plots 11 & 12, Cornwall Business Park (West) For JAD Developments (Redruth) Ltd 1 Introduction 1.1 Project Information Project Title:
More informationNOTICE INVITING TENDER FOR APPOINTMENT OF ARCHITECT/CONSULTANT INTERIOR AND CIVIL RENOVATION WORKS AT OPENING OF RACPC-IV, NAGAR ROAD, PUNE
STATE BANK OF INDIA PREMISES AND ESTATE DEPARTMENT, 3rd FLOOR, ZONAL OFFICE,ZONE-I SHARADA COMPLEX, PUNE - 37 NOTICE INVITING TENDER FOR APPOINTMENT OF ARCHITECT/CONSULTANT INTERIOR AND CIVIL RENOVATION
More informationBANK OF INDIA PUNE ZONAL OFFICE CORPORATE SERVICES DEPT., 1162/6 Shivaji Nagar, University Road, Pune
BANK OF INDIA PUNE ZONAL OFFICE CORPORATE SERVICES DEPT., 1162/6 Shivaji Nagar, University Road, Pune- 411005 NOTICE FOR PREQUALIFICATION OF ARCHITECTURAL CONSULTANCY FIRM BANK OF INDIA invites applications
More informationFIDIC PROCUREMENT OPTIONS, Clause 3 and Clause 20
FIDIC PROCUREMENT OPTIONS, Clause 3 and Clause 20 PATRIZIA PALMITESSA-SAVRIC BSc Arch Eng MArch Arch.BW RIBA MAAB FCIArb FAArb FBIArb Head Contracts & Dispute Resolution GINDER PALMITESSA PTY LTD T: +267
More informationModel Employment Contract
Model Employment Contract Adapt this Model Employment Contract for use at your own workplace. MODEL EMPLOYMENT CONTRACT HR managers in any part of the country can adapt this Model Employment Contract for
More information1.1 Your employment with [ ] Council began on... ( the commencement date ).
CONTRACT OF EMPLOYMENT for LOCUM CLERK This contract of employment ( the contract ) contains the main terms and conditions of your employment with [ ] Council ( the Council ). It includes all the written
More informationSINGLE BID TENDER DOCUMENT FOR ARCHITECTURAL SERVICES FOR TAKING UP RENOVATION WORKS OF SBLC, MASULIPATNAM.
STATE BANK OF INDIA PREMISES & ESTATE DEPARTMENT AMARVATI, LOCAL HEAD OFFICE SINGLE BID TENDER DOCUMENT FOR ARCHITECTURAL SERVICES FOR TAKING UP RENOVATION WORKS OF SBLC, MASULIPATNAM. From Architects
More informationGOVERNMENT OF RAJASTHAN URBAN DEVELOPMENT DEPARTMENT
GOVERNMENT OF RAJASTHAN URBAN DEVELOPMENT DEPARTMENT SECTION 5 - TERMS OF REFERENCE Background Information and Outline Terms of Reference for consulting firms for Construction Supervision & Design Consultancy
More informationDesign Build: CCDC
Ontario Association of Architects Practice Tip PT.23.6 Version 2.0 August 14, 2018 Design Build: CCDC 14-2013 2018, 2015 Ontario Association of Architects (OAA). OAA members in good standing may reproduce
More informationADVERTISING TERMS AND CONDITIONS
ADVERTISING TERMS AND CONDITIONS NZME Publishing Limited, NZME Radio Limited and their related companies ( NZME ) accept all advertisements and notices from the Customer for publication in all publications
More informationAPPENDIX D CONSTRUCTION PHASE CRITERIA
A. GENERAL REQUIREMENTS CONSTRUCTION PHASE CRITERIA For the Construction Phase of the Project, the Architect/Engineer (A/E) is responsible for providing project administration for the Owner in accordance