EPR Projects: Updates

Size: px
Start display at page:

Download "EPR Projects: Updates"

Transcription

1 Nissen M. Burstein Technical Consultant Presented at SC-2, Meeting June 15-17, 2011, Gothenburg, Sweden EPR is a trademark of the AREVA Group.

2 Overview of U.S. EPR Reactor Redundant safety systems are physically separated into four divisions, which protect the individual integrity of the electrical and mechanical safety systems. The four divisions of safety systems are consistent with an N+2 safety concept. One division can be out of service for maintenance One division can fail to operate The remaining two divisions are available to perform the necessary safety functions even if one of the two remaining trains becomes inoperable due to the initiating event.

3 Overview of the U.S. EPR Design Evolutionary 4-loop PWR designed for a rated core thermal power level of 4590 MWt. The U.S. EPR unique design features include: Four redundant trains of emergency core cooling. Containment and shield building. Core melt retention system for severe accident mitigation. The plant design objective is 60 years. The design provides for the replaceability of major components, including the steam generators. The Reactor Building is an integrated structure consisting of an inner Reactor Containment Building, an outer building called the Reactor Shield Building, and an annular space between the two buildings that separates them for protection against external hazards (including aircraft impact).

4 Highlights of Recent U.S. EPR Activity General The U.S. EPR design application is currently under NRC review. A total of 4140 formal RAIs and 180 open items have been received as of April 22. AREVA has responded to 3846 questions and 130open items. Phase 1 review of the application, i.e., preliminary SER and all RAIs issued, was completed on 1/28/09. Phase 2 review (i.e., development of the SER with open items) and Phase 4 (i.e., development of the Advanced SER with no open items) on some sections is currently in progress. A total of eleven chapter SERs with open items and three partial SERs with open items have been received to date and thirteen associated ACRS meetings completed. Schedule date for NRC approval of the design application is June Key issues involve Seismic and Structural Analysis, I&C, and resolution of GSI-191 related to sump strainer clogging. Of the 11 active topical reports, 6 have been approved, 4 have been issued a draft SER, and 1 is under active review.

5 Regulatory Status Regarding ASME QME NRC issued revision 3 of RG in September 2009 which endorses ASME QME with exceptions and clarifications (e.g., use of either earthquake experience data or test experience data for seismic qualification needs to be submitted for NRC review and approval). AREVA uses ASME QME as guidance for qualifying active mechanical equipment with the exception that a separate mechanical equipment qualification (MEQ) program for the U.S. EPR design will not be maintained as noted in U.S. EPR FSAR Tier 2, Section for nonmetallic subcomponents.

6 Engineering Implementation of ASME QME IEEE Standards , , , and are used for qualification. Environmental Qualification (EQ) EQ of electrical appurtenances meets the requirements of IEEE EQ of the valve actuator meets the requirements of IEEE EQ of the pump motor meets the requirements of IEEE EQ of the valve is limited to the nonmetallic parts of the valve. EQ follows the guidance of non-mandatory Appendix QR-B of QME-1 for nonmetallic parts of the valve.

7 Engineering Implementation of ASME QME The AREVA position regarding QME has been documented in an internal AREVA NP position paper. Design Specifications ensure consistency with regard to the application of QME Examples of design specifications that refer to QME : ASME Class 1 Valves ASME Class 2 and 3 Valves ASME Section III Pump/Motor Assemblies Control Rod Drive Mechanism Main Steam and Full-Load Feedwater Isolation Valves Pressurizer Safety Relief Valves Pressurizer Solenoid Spray Valve

8 FSAR Incorporation of ASME QME Elements Elements of QME have been incorporated into the U.S. EPR FSAR. U.S. EPR FSAR Tier 2, Table was revised to change the reference from RG 1.100, Revision 2 to Revision 3. The following FSAR Sections have been revised to indicate that the functional design and qualification testing of safety-related pumps, valves, and snubbers is performed in accordance with ASME QME as endorsed by RG 1.100, Revision 3, with clarifications regarding the non-mandatory appendices of ASME QME : 3.9.3, ASME Code Class 1, 2, and 3 Components, Component Supports, and Core Support Structures , Functional Design and Qualification of Pumps, Valves, and Dynamic Restraints 3.10, Seismic and Dynamic Qualification of Mechanical and Electrical Equipment 3.11, Environmental Qualification of Mechanical and Electrical Equipment

9 FSAR Incorporation of ASME QME Elements Consistent with RG Rev. 3, U.S. EPR FSAR Tier 2, Section 3.10 addresses the applicability of the non-mandatory appendices of QME Examples are listed below: Non-mandatory Appendix QR-A is not utilized because seismic qualification is in accordance with IEEE , which is consistent with QME Additionally, Section 10.2, Earthquake Experience Data, QR-A7400 and QR-A7500, is not utilized by AREVA. Qualification of non-metallic parts is consistent with non-mandatory Appendix QR-B as described in FSAR Section The provisions for the design and qualification of snubbers is consistent with Section QDR and non-mandatory Appendices QDR-A, QDR-B, and QDR-C. Snubbers in safety-related systems include provisions to allow access for IST program activities. AREVA is not utilizing non-mandatory Appendices QP-A through QP-E, because pump and motor assemblies are designed and qualified in accordance with applicable standards (e.g., ASME B&PV Code, QME-1, ASME B16, IEEE 323, IEEE 334, IEEE 344, RG 1.84, ASME NQA-1). Non-mandatory Appendix QV-A, Functional Specification for Active Valves for Nuclear Power Plants, is used as guidance in the development of valve specifications to demonstrate that lessons learned from industry experience are included in the specifications.

10 4 EPR Reactors under construction EPR Projects Olkiluoto 3 Flamanville 3 Taishan 1&2

11 Olkiluoto 3 Project Update March 2011 EPR is a trademark of the AREVA Group.

12 General Orientation Olkiluoto Island

13 Benefits for the local region s economy Benefits during construction works On employment: 3,500-6,000 people employed directly or indirectly Unemployment rate halved in comparison with 2004 Eurajoki: 6,4%, among the lowest unemployment rates in Finland On production: million euros Gross Domestic Product of the region increased by 2,6% 180 companies in Satakunta region involved Annual turnover increase in construction sector over 2006/ ,4% Permanent benefits Yearly increase of procurement amounts and needs for external services Larger yearly NPP revisions hundreds of external subcontractors Increase in knowledge and other human values Impact on taxation (Eurajoki see also next page)

14 Benefits for the local region s economy Taxes, services and housing sector Increased estimate of municipal tax (workforce needed for operations) by ~ 60% in Rauma and 25% in Eurajoki for a national average of 5% Income taxes represent around millions, which is over 30% of the total collected taxes Estimated increase of real estate tax of nuclear power from ~ 3 million to ~ 7-8 million by 2011 Clear current national boom in housing industry Utilization rates in region s hotels exceeding +60% Significant increase in services such as: restaurants, retail trade, etc.

15 NI/TI Buildings Buildings of Nuclear Island - NI Buildings of Turbine Island - TI Waste Building Auxiliary Building Fuel Building Diesels 2+1 Building Access Building Electrical Building Safeguard Building 4 Reactor Building Safeguard Building 1 Turbine Building Diesels 2+1 Building Safeguard Buildings 2+3 Circulating Water Pump Building Ducts & channels Essential Service Water Pump Building

16 General view of NI

17 Turbine Hall (UMA)

18 NI Progress Construction ~ 57% completed External dome to be completed by June Total of 270,000m³ to be poured (NI + TI: 336,000m³) Pre-stressing completed 80% backfilling completed Electro-mechanical activities 580km of cables pulled 64% progress for HVAC 42% of piping installation completed 87% piping-related equipment installed Primary components installation completed: Reactor Pressure Vessel and closure head, Pressurizer, 4 Steam Generators Tests and commissioning ramping-up Documentation: 137 System Commissioning Programmes out of 158 issued Polar crane and auxiliary crane pre-operational tests completed

19 OL3 I&C Overall status Architecture accepted by STUK, regulator, with application of conditions Systems independency for safety and process functions Hardwire Back-up System (HBS) Overall test concept to be approved by TVO, utility, as soon as possible I&C time schedule under reassessment Local platforms on site for modifications during Commissioning Full scope simulator Delivery to site Spring 2011

20 Electro-mechanical installation Electrical installation progress

21 Electro-mechanical installation Battery Room

22 Electro-mechanical installation TELEPERM XS Cabinets

23 Primary Circuit Complete loop Pressurizer Steam Generator Hot Leg Reactor Pressure Vessel Cross Over Leg Cold Leg

24 Primary circuit Welding completed Welding completed Welding ongoing

25 Primary components Installation of Steam Generators

26 Manpower/Nationality February 2011 Country % of site population Finland 29% Germany 19% Poland 18% Croatia 9% France 6% Estonia 4% Bosnia and Herzegovina 2% Others 12%

27 OL3 General time schedule Civil Work Finishing Electro-mechanical installation Commissioning Primary Components installed Essential water service lines Flooding Full Scope Simulator Operating License Fuel Loading

28 Next steps 2011 Completion of outer dome Completion of the primary circuit Completion of electro-mechanical installation Pre-operational tests & Commissioning ramping up Configuration management implementation Integration of TVO staff in Operation Integrated Organization 86% of System Commissioning Program issued Objectives: Fuel loading end of 2012

29 AREVA and the companies operating in the background are still the world s leading nuclear suppliers. They have the best and safest product. We have no reason to doubt it and we have no reason to doubt their honesty either. Jukka Laaksonen, STUK Director, on Finnish TV channel MTV3, August 22, 2008 The EPR TM is the most advanced technology worldwide. Martin Landtman, Senior Vice President, Project OL3, TVO, in Handelsblatt, Germany, August 13, 2007

30 Flamanville 3 Project Progress of the works April 2011 EPR is a trademark of the AREVA Group.

31 EPR Flamanville 3 Project

32 FA 3 Site Progress April 2011

33 Scope of Work AREVA is responsible for the turnkey NSSS, including design, procurement, erection and commissioning work Similar scope compared to previous series (N4 was a reference for contractual aspect) Civil works awarded to Bouygues, turbine island to Alstom April 11, 2007: Contract signed between EDF and AREVA April 10, 2007: Approval of the construction permit December 3, 2007: First concrete pouring 2014: Start of commercial operation

34 Project progress Achieved and ongoing deliveries: IRWST lines Primary anchors Embedded excore tubes & tanks RPV support ring and reactor vessel-to-cavity seal ring Auxiliary racks Venturi Tubes (diameter: 250mm et 500mm) Various sensors SIS Pumps Valves SIS Accumulators SIS Exchangers Some valves Flamanville site, April 2011 Installation: Installation of the first embedded tanks (RPE, Pressurizer Relief Tank), first pumps (SIS pumps) and first exchangers (SIS exchangers) Welding of the first supports at the end of The Safety Analysis Report (SAR) for the Operating License Application has been delivered in October Manufacturing of primary components is on going. Engineering and procurement are on track with the customer s schedule.

35 Reactor building Civil Work progress Civil work under EDF responsibility Tenth lift of the outer containment done since august th lift of the inner containment done. The walls of the pools are almost finished The Reactor Building re opened. Current progress: Vessel, Steam Generators and Pressurizer are under manufacturing in AREVA Chalon/St Marcel, France First supports welded end of Concrete done Reinforcement ongoing

36 Main components Steam generator / AREVA Chalon/St Marcel, France Pressurizer / AREVA Chalon/St Marcel, France Main coolant pump / AREVA JSPM, France Main coolant line / AREVA Creusot Forge, France Reactor pressure vessel (RPV) / AREVA Chalon/St Marcel, France

37 Equipment Manufacturing: Reactor Pressure Vessel AREVA Chalon/Saint Marcel

38 Heat exchanger in the auxiliary safeguard building

39 welding of supports for cable paths in auxiliary safeguard building

40 Cables in the electrical building

41 Pipes coming in and out of the turbine

42 Taishan 1&2 Project

43 Taishan Project - General View Taishan 1&2 September 2009 The largest contract ever signed in the civil nuclear industry

44 Taishan 1&2 Project Progress of the works 台山 February 2011 Validated for internal communication EPR is a trademark of the AREVA Group.

45 Site location TAISHAN EPR Projects:

46 Taishan 1 & 2 Progress update TSN 1&2 Key Facts AREVA scope Procurement: 80% orders made Engineering: 60% completed All main components are being manufactured Engineering JV with CGNPC set up successfully Outside AREVA scope Unit 1: Liner up to +43,90m Almost ready for dome lifting Inner wall concreted up to m Unit 2: common raft poured in April 2010 Liner installed up to+12m Piping prefabrication started by the Client based on AREVA design More than 12,000 people are working on site every day

47 Taishan Reactor Building Progress February 2011 Unit 1 February 2011 Unit 2

48 Achievements to date Engineering PSAR & licensing activities are well on track with NNSA Project is now more than mid way and more than 60% of engineering activities are completed Basic Design is in an ending phase and gives path to the detail design currently under progress within the JDO organization set-up in China mid 2009 (for Piping and Electrical) Civil work detail design for Reinforcements & Formworks very close to Nov forecast Procurement Order placement is about to be finished by first months of 2011 Polar Crane manufacturing activities at DHI/DCW. CNPEC is improving its efficiency in terms of expediting & inspection. Site activities The AREVA NP site related activities are evolving with the mobilization of Design Liaison Team and ongoing discussions on possible technical assistance for installation and commissioning.

49 Project overview Customer CGNPC CGNPC China Guangdong Nuclear Power Holding Corp. Ltd. One of the 5 Chinese Electrical Companies Developing a nuclear program historically in the Guangdong province (Daya Bay, Ling Ao I&II ) and now in other provinces Capital: CNNC (45%), Guangdong Province (45%) & China Power Investment (10%) Today, CGNPC wants to create its own nuclear industry to position itself as the major player of the electronuclear development in China CGNPC involves many of its own subsidiaries into the Taishan Project, among them; China Nuclear Power Engineering Company (CNPEC) and China Nuclear Power Design Company (CNPDC)

50 Overview of NI EP Contract Contract signed between TNPJVC & AREVA/CNPEC/CNPDC Consortium Contract structure and principles based on Ling Ao phase I Scope Design & Engineering of NI FOB Supply of the Equipment (or Ex-Works for China) Technical Assistance (upon demand) Civil work detailed design (confirmed at contract's signature) First options to be confirmed Primary loop erection and commissioning (EM2/EM11.2 package) Civil construction, Installation & Commissioning performed by TNPJVC Technical Assistance (upon demand) on installation, commissioning, civil, maintenance, operation, etc. Turbine island: Consortium Dongfang/Alstom Reference power plant: mainly FA3 Project duration: 76 months (24+52 months) with 10 months difference between the 2 units

51 Primary Loop for Taishan Unit 1 Contrat Chalon Saint-Marcel JSPM Creusot Forge Steam Generator Control Rod Drive Mechanisms Pressurizer RPV MHI Reactor Cooling Pumps (SAFAS/DFEM) Internals Skoda IMS TSN Primary Lines

52 Primary Loop for Taishan Unit 2 Contrat Chalon Saint-Marcel JSPM Creusot Forge Pressurizer DFHM Steam Generator SENPEC / DFHM Control Rod Drive Mechanisms JSPM / Shangai Number One Reactor Cooling Pumps RPV DFHM JSPM / ADJV / DFEM / SAFAS Internals Shangai Number 1 IMS TSN Primary Lines

53 Key figures 125,000 documents 7,000 civil works drawings 400 technical files for requisition 220 system Design Manuals 500 installation instructions 150 working procedures Piping 72 Km Large Bore / 150 Km Small Bore Electrical 45,000 cables / 90,000 heads 400,000 connections points 3,500 Km cables 60 Km Main Cable Trays / 20 Local Cable Trays 14,000 supports Total weight equipments: 10,000 T

54 Great amount of resource is mobilized More than 1,500 people working for the NI EP Consortium 1,000 AREVA and more than 500 CNPDC/CNPEC On site, TNPJVC responsibility: 12,000 peop Data

55 Next steps 2011 Deadlines Next steps May 2011 Delivery of Civil Dependant equipment for Dome Lifting (Polar crane, RCP / RIS...) July 2011 Dome Lifting October 2011 Reactor Pressure Vessel (FOB) boarding from MHI Japan to Taishan China End 2011 Primary Loop installation starts

Welcome to Taishan NP site

Welcome to Taishan NP site Welcome to Taishan NP site 1 Content Project Introduction Project Progress Main Tasks in 2011 2 Site Conditions TSNP is situated at Yaogu village of Chixi town in Taishan city, Guangdong province, 70km,

More information

Poland Nuclear Program EPR Flamanville 3

Poland Nuclear Program EPR Flamanville 3 Poland Nuclear Program EPR Flamanville 3 Project Organization Design & Manufacturing activities On Site activities What We Are Learning from New Construction Experience September 29 th, 2010 Gilles Zask

More information

Westinghouse AP1000. Reactor

Westinghouse AP1000. Reactor Westinghouse AP1000 A Third Generation Nuclear Reactor International Council on Systems Engineering (INCOSE) September 18, 2013 Andrew Drake, PMP Director, AP1000 Engineering Completion Engineering, Equipment

More information

The Westinghouse Advanced Passive Pressurized Water Reactor, AP1000 TM. Roger Schène Director,Engineering Services

The Westinghouse Advanced Passive Pressurized Water Reactor, AP1000 TM. Roger Schène Director,Engineering Services The Westinghouse Advanced Passive Pressurized Water Reactor, AP1000 TM Roger Schène Director,Engineering Services 1 Background Late 80: USA Utilities under direction of EPRI and endorsed by NRC : Advanced

More information

A canter around the nuclear jumps..

A canter around the nuclear jumps.. A canter around the nuclear jumps.. Robert Davies Vice President New Build, AREVA UK Cambridge MPhil 8 th February 2012 Who are we? World leader in CO 2 -free power generation 9.1Bn in Annual Revenues

More information

Concepts and Features of ATMEA1 TM as the latest 1100 MWe-class 3-Loop PWR Plant

Concepts and Features of ATMEA1 TM as the latest 1100 MWe-class 3-Loop PWR Plant 8 Concepts and Features of ATMEA1 TM as the latest 1100 MWe-class 3-Loop PWR Plant KOZO TABUCHI *1 MASAYUKI TAKEDA *2 KAZUO TANAKA *2 JUNICHI IMAIZUMI *2 TAKASHI KANAGAWA *3 ATMEA1 TM is a 3-loop 1100

More information

PRESS CONFERENCE. 3 September Jean-Bernard LÉVY Chairman and CEO. Xavier URSAT Group Senior Executive VP - New Nuclear Projects and Engineering

PRESS CONFERENCE. 3 September Jean-Bernard LÉVY Chairman and CEO. Xavier URSAT Group Senior Executive VP - New Nuclear Projects and Engineering PRESS CONFERENCE 3 September 2015 Jean-Bernard LÉVY Chairman and CEO Xavier URSAT Group Senior Executive VP - New Nuclear Projects and Engineering EDF, A RESPONSIBLE ELECTRICITY COMPANY, A CHAMPION OF

More information

NPP-Nuclear Island Design From conceptual design to Project execution

NPP-Nuclear Island Design From conceptual design to Project execution NPP-Nuclear Island Design From conceptual design to Project execution Atoms for the Future Paris SFEN - October 14, 2014 D. Lanchet NPP-Nuclear Island Design From conceptual design to Project execution

More information

Nuclear Power Plant Safety Basics. Construction Principles and Safety Features on the Nuclear Power Plant Level

Nuclear Power Plant Safety Basics. Construction Principles and Safety Features on the Nuclear Power Plant Level Nuclear Power Plant Safety Basics Construction Principles and Safety Features on the Nuclear Power Plant Level Safety of Nuclear Power Plants Overview of the Nuclear Safety Features on the Power Plant

More information

DESIGN AND SAFETY PRINCIPLES LEONTI CHALOYAN DEPUTY CHIEF ENGINEER ON MODERNIZATION

DESIGN AND SAFETY PRINCIPLES LEONTI CHALOYAN DEPUTY CHIEF ENGINEER ON MODERNIZATION DESIGN AND SAFETY PRINCIPLES LEONTI CHALOYAN DEPUTY CHIEF ENGINEER ON MODERNIZATION VIENNA OKTOBER 3-6, 2016 1 ANPP * ANPP is located in the western part of Ararat valley 30 km west of Yerevan close to

More information

Olkiluoto Infrastructure

Olkiluoto Infrastructure OL3 Olkiluoto Infrastructure 2 30.9.2008 Arguments for a New Nuclear Plant Unit - Covers partly the additional electricity demand and replaces old power plants - Enables, together with renewables, the

More information

AND SITE LICENSING OF THE EPR FOR THE HINKLEY POINT C PROJECT

AND SITE LICENSING OF THE EPR FOR THE HINKLEY POINT C PROJECT DESIGN ASSESSMENT AND SITE LICENSING OF THE EPR FOR THE HINKLEY POINT C PROJECT 10/2016 Stephen J Walls, EDF Energy Nuclear New Build 1 Olivier Bard, EDF HINKLEY POINT C (HPC) 2 HPC Financial Investment

More information

Experiences with the construction of EPR at Flamanville and Taishan

Experiences with the construction of EPR at Flamanville and Taishan Experiences with the construction of EPR at Flamanville and Taishan OECD/ Nuclear Energy Agency Workshop : Project and Logistics Management in Nuclear New Build NEA Headquarters, Issy-les-Moulineaux March

More information

SEVERE ACCIDENT FEATURES OF THE ALTERNATIVE PLANT DESIGNS FOR NEW NUCLEAR POWER PLANTS IN FINLAND

SEVERE ACCIDENT FEATURES OF THE ALTERNATIVE PLANT DESIGNS FOR NEW NUCLEAR POWER PLANTS IN FINLAND SEVERE ACCIDENT FEATURES OF THE ALTERNATIVE PLANT DESIGNS FOR NEW NUCLEAR POWER PLANTS IN FINLAND Risto Sairanen Radiation and Nuclear Safety Authority (STUK) Nuclear Reactor Regulation P.O.Box 14, FI-00881

More information

EPR: Steam Generator Tube Rupture analysis in Finland and in France

EPR: Steam Generator Tube Rupture analysis in Finland and in France EPR: Steam Generator Tube Rupture analysis in Finland and in France S. ISRAEL Institut de Radioprotection et de Sureté Nucléaire BP 17 92262 Fontenay-aux-Roses Cedex, France Abstract: Different requirements

More information

The EPR Reactor: Evolution to Gen III+ based on proven technology. Andrew Teller, Senior Technical Advisor, AREVA

The EPR Reactor: Evolution to Gen III+ based on proven technology. Andrew Teller, Senior Technical Advisor, AREVA The EPR Reactor: Evolution to Gen III+ based on proven technology Andrew Teller, Senior Technical Advisor, AREVA Building on the Achievements of the N4 and Konvoi Reactors N4 KONVOI High output (1475MWe)

More information

Flamanville 3 EPR, safety assessment and on-site inspections

Flamanville 3 EPR, safety assessment and on-site inspections Flamanville 3 EPR, safety assessment and on-site inspections Corinne. PIEDAGNEL, François TARALLO, Bernard MONNOT Institut de Radioprotection et de Sûreté Nucléaire, DSR/SAMS 92262 Fontenay-aux-Roses Cedex,

More information

EDF & the nuclear renewal : the Flamanville 3 model. Jean-Claude Prenez Director for International Projects EDF Nuclear Engineering Division

EDF & the nuclear renewal : the Flamanville 3 model. Jean-Claude Prenez Director for International Projects EDF Nuclear Engineering Division EDF & the nuclear renewal : the Flamanville 3 model Jean-Claude Prenez Director for International Projects EDF Nuclear Engineering Division Varna, 27-29 May 2009 Contents 1.The french context and EDF nuclear

More information

Westinghouse s plant for the Nuclear Renaissance : AP1000. AP1000 Advanced Passive Plant

Westinghouse s plant for the Nuclear Renaissance : AP1000. AP1000 Advanced Passive Plant Westinghouse s plant for the Nuclear Renaissance : AP000 Fernando Naredo Milan, January 30, 006 AP000 Advanced Passive Plant Designed to compete with other sources in deregulated power markets - Two loop,

More information

Overview for a feasibility study

Overview for a feasibility study Overview for a feasibility study What, Why & Objectives of Feasibility Study? International Atomic Energy Agency Nuclear power option included within the national energy strategy MILESTONE 1 Ready to

More information

FRANCE LWR activities

FRANCE LWR activities FRANCE LWR activities Norbert NICAISE with contributions from AREVA-NP ASN French Nuclear Safety Authority, IRSN French Institute for Radiation Protection and Nuclear Safety (TSO of ASN), CEA French Atomic

More information

HPR1000: ADVANCED PWR WITH ACTIVE AND PASSIVE SAFETY FEATURES

HPR1000: ADVANCED PWR WITH ACTIVE AND PASSIVE SAFETY FEATURES HPR1000: ADVANCED PWR WITH ACTIVE AND PASSIVE SAFETY FEATURES D. SONG China Nuclear Power Engineering Co., Ltd. Beijing, China Email: songdy@cnpe.cc J. XING China Nuclear Power Engineering Co., Ltd. Beijing,

More information

Application for Permission to Extend the Operating Period and Application for Approval of Construction Plans of Unit 3 at Mihama Nuclear Power Station

Application for Permission to Extend the Operating Period and Application for Approval of Construction Plans of Unit 3 at Mihama Nuclear Power Station November 26, 2015 The Kansai Electric Power Co., Inc. Application for Permission to Extend the Operating Period and Application for Approval of Construction Plans of Unit 3 at Mihama Nuclear Power Station

More information

NuScale SMR Technology

NuScale SMR Technology NuScale SMR Technology UK IN SMR; SMR IN UK Conference - Manchester, UK Tom Mundy, EVP Program Development September 25, 2014 Acknowledgement & Disclaimer This material is based upon work supported by

More information

NDE SOLUTIONS INTERCONTRÔLE NONDESTRUCTIVE EXAMINATION

NDE SOLUTIONS INTERCONTRÔLE NONDESTRUCTIVE EXAMINATION INTERCONTRÔLE NONDESTRUCTIVE EXAMINATION Specialists in nondestructive examination has specialized in automated nondestructive testing of nuclear reactor primary components and more specifically on steam

More information

FROG Owners Group A Worldwide Network of Experience. April 2012

FROG Owners Group A Worldwide Network of Experience. April 2012 FROG Owners Group A Worldwide Network of Experience April 2012 Origin FROG founded in 1991 Founding Members = utilities operating or building Nuclear Power Plants with Framatome supplying Nuclear Steam

More information

Full Steam ahead for Flamanville 3 EPR turbine island construction

Full Steam ahead for Flamanville 3 EPR turbine island construction May 2010 Full Steam ahead for Flamanville 3 EPR turbine island construction POWER The 1750 MWe ARABELLE turbine generator is the world s largest engine. The first such machine in Europe is currently under

More information

Preliminary Lessons Learned from the Fukushima Daiichi Accident for Advanced Nuclear Power Plant Technology Development

Preliminary Lessons Learned from the Fukushima Daiichi Accident for Advanced Nuclear Power Plant Technology Development Preliminary Lessons Learned from the Fukushima Daiichi Accident for Advanced Nuclear Power Plant Technology Development A. Introduction The IAEA Report on Reactor and Spent Fuel Safety in the Light of

More information

Design Features, Economics and Licensing of the 4S Reactor

Design Features, Economics and Licensing of the 4S Reactor PSN Number: PSN-2010-0577 Document Number: AFT-2010-000133 rev.000(2) Design Features, Economics and Licensing of the 4S Reactor ANS Annual Meeting June 13 17, 2010 San Diego, California Toshiba Corporation:

More information

RELAP5/MOD3.2 INVESTIGATION OF A VVER-440 STEAM GENERATOR HEADER COVER LIFTING

RELAP5/MOD3.2 INVESTIGATION OF A VVER-440 STEAM GENERATOR HEADER COVER LIFTING Science and Technology Journal of BgNS, Vol. 8, 1, September 2003, ISSN 1310-8727 RELAP5/MOD3.2 INVESTIGATION OF A VVER-440 STEAM GENERATOR HEADER COVER LIFTING Pavlin P. Groudev, Rositsa V. Gencheva,

More information

Joint ICTP-IAEA Essential Knowledge Workshop on Deterministic Safety Analysis and Engineering Aspects Important to Safety. Trieste,12-23 October 2015

Joint ICTP-IAEA Essential Knowledge Workshop on Deterministic Safety Analysis and Engineering Aspects Important to Safety. Trieste,12-23 October 2015 Joint ICTP- Essential Knowledge Workshop on Deterministic Safety Analysis and Engineering Aspects Important to Safety Trieste,12-23 October 2015 Safety classification of structures, systems and components

More information

Regulatory Approach to Radiation Protection in new NPPs in Finland

Regulatory Approach to Radiation Protection in new NPPs in Finland Regulatory Approach to Radiation Protection in new NPPs in Finland ISOE European Workshop in Prague 20.-22. 6. 2012 Veli Riihiluoma Radiation and Nuclear Safety Authority (STUK) RADIATION AND NUCLEAR SAFETY

More information

Angra 3 Current status and challenges to continue

Angra 3 Current status and challenges to continue Angra 3 Current status and challenges to continue Vienna February 2017 Introduction Brazilian Transmission Network Integrated electric power system: continental dimensions Manaus Fortaleza Itaipu Brasília

More information

Post-Fukushima Assessment of the AP1000 Plant

Post-Fukushima Assessment of the AP1000 Plant ABSTRACT Post-Fukushima Assessment of the AP1000 Plant Ernesto Boronat de Ferrater Westinghouse Electric Company, LLC Padilla 17-3 Planta 28006, Madrid, Spain boronae@westinghouse.com Bryan N. Friedman,

More information

Technology Development, Design and Safety Features of the CNP300 and A New Small PWR

Technology Development, Design and Safety Features of the CNP300 and A New Small PWR Technology Development, Design and Safety Features of the CNP300 and A New Small PWR and A New Small PWR By LIN Qian Shanghai Nuclear Engineering Research and Design Institute (SNERDI) Content SNERDI and

More information

European level recommendations Sect. in NAcP 2 Generic recommendation for WENRA, Finland participates and follows the work.

European level recommendations Sect. in NAcP 2 Generic recommendation for WENRA, Finland participates and follows the work. Cross reference table of ENSREG and Extraordinary CNS recommendations and national actions 1(16) 2.1 European guidance on assessment of natural hazards and margins The peer review Board recommends that

More information

Advanced Design of Mitsubishi PWR Plant for Nuclear Renaissance

Advanced Design of Mitsubishi PWR Plant for Nuclear Renaissance Advanced Design of Mitsubishi PWR Plant for Nuclear Renaissance October 28, 2009 Etsuro SAJI General Manager, Reactor Core Engineering Department Mitsubishi Heavy Industries, Ltd. GEN-HSW-9102-0 Contents

More information

Westinghouse Small Modular Reactor. Passive Safety System Response to Postulated Events

Westinghouse Small Modular Reactor. Passive Safety System Response to Postulated Events Westinghouse Small Modular Reactor Passive Safety System Response to Postulated Events Matthew C. Smith Dr. Richard F. Wright Westinghouse Electric Company Westinghouse Electric Company 600 Cranberry Woods

More information

APR1400 Safe, Reliable Technology

APR1400 Safe, Reliable Technology APR1400 Safe, Reliable Technology OECD/NEA Workshop on Innovations in Water-cooled Reactor Technology Paris, Feb 11 12, 2015 Presented by Shin Whan Kim Contents 1. Introduction 2. Major Safety Design Characteristics

More information

The Westinghouse AP1000 : Passive, Proven Technology to Meet European Energy Demands

The Westinghouse AP1000 : Passive, Proven Technology to Meet European Energy Demands BgNS TRANSACTIONS volume 20 number 2 (2015) pp. 83 87 The Westinghouse AP1000 : Passive, Proven Technology to Meet European Energy Demands N. Haspel Westinghouse Electric Germany GmbH, Dudenstraße 6, 68167

More information

Heavy Component Replacement in Nuclear Power Plants

Heavy Component Replacement in Nuclear Power Plants Heavy Component Replacement in Nuclear Power Plants Steve Sills, Vice President Business Development, SGT Darren Wood, Manager Component Replacements, AREVA Purpose and Process Goal Recent successes and

More information

OE Supply-Chain in Nuclear Dr. Boris Gehring March 2017

OE Supply-Chain in Nuclear Dr. Boris Gehring March 2017 OE Supply-Chain in Nuclear Dr. Boris Gehring March 2017 2015-02-12 It should not finally look like this! Owners Engineers and Supply-Chain services In NPP New build, OE and SCS will help to keep: -Time-line

More information

UKEPR Issue 04

UKEPR Issue 04 Title: PCSR Sub-chapter 9.2 Water Systems Total number of pages: 65 Page No.: I / IV Chapter Pilot: M. LACHAISE Name/Initials Date 23-11-2012 Approved for EDF by: A. MARECHAL Approved for AREVA by: G.

More information

Plant Life Management in Transition from Operation to Decommissioning of Nuclear Power Plants. National experience, Finland.

Plant Life Management in Transition from Operation to Decommissioning of Nuclear Power Plants. National experience, Finland. Plant Life Management in Transition from Operation to Decommissioning of Nuclear Power Plants. National experience, Finland. Jari Tuunanen, 30 Aug.2016 Contents Background Status of decommissioning plans

More information

ANTICIPATED ANALYSIS OF FLAMANVILLE 3 EPR OPERATING LICENSE - STATUS AND INSIGHTS FROM LEVEL 1 PSA REVIEW

ANTICIPATED ANALYSIS OF FLAMANVILLE 3 EPR OPERATING LICENSE - STATUS AND INSIGHTS FROM LEVEL 1 PSA REVIEW ANTICIPATED ANALYSIS OF FLAMANVILLE 3 EPR OPERATING LICENSE - STATUS AND INSIGHTS FROM LEVEL 1 PSA REVIEW Gabriel Georgescu, Patricia Dupuy and Francois Corenwinder Institute for Radiological Protection

More information

Module 05 WWER/ VVER (Russian designed Pressurized Water Reactors)

Module 05 WWER/ VVER (Russian designed Pressurized Water Reactors) Module 05 WWER/ VVER (Russian designed Pressurized Water Reactors) 1.3.2016 Prof.Dr. Böck Technical University Vienna Atominstitut Stadionallee 2, 1020 Vienna, Austria ph: ++43-1-58801 141368 boeck@ati.ac.at

More information

What Nuclear Reactor Companies Need

What Nuclear Reactor Companies Need September 6, 2017 What Nuclear Reactor Companies Need Scott Bailey Vice President, Supply Chain NuScale Nonproprietary Copyright 2017 NuScale Power, LLC Acknowledgement & Disclaimer This material is based

More information

Verification of the MELCOR Code Against SCDAP/RELAP5 for Severe Accident Analysis

Verification of the MELCOR Code Against SCDAP/RELAP5 for Severe Accident Analysis Verification of the Code Against SCDAP/RELAP5 for Severe Accident Analysis Jennifer Johnson COLBERT 1* and Karen VIEROW 2 1 School of Nuclear Engineering, Purdue University, West Lafayette, Indiana 47907-2017,

More information

NUCLEAR Untitled /7/11 12:29 PM

NUCLEAR Untitled /7/11 12:29 PM NUCLEAR Untitled-16 1 IMI NUCLEAR - A POWERFUL COMBINATION TRUST IMI Nuclear brings together a powerful combination of brands you know and trust. In fact, over half of the nuclear power plants worldwide

More information

RESULTS OF THE GRADUAL UPGRADING AT BOHUNICE WWER - 440/230 NPP

RESULTS OF THE GRADUAL UPGRADING AT BOHUNICE WWER - 440/230 NPP RESULTS OF THE GRADUAL UPGRADING AT BOHUNICE WWER - 440/230 NPP P. Krupa Ingeneer, e-mail: Krupa_Peter@ebo.seas.sk Bohunice NPPs Introduction The centre of upgrading activities in VVER NPP is clearly in

More information

From the Safety Approach of a Nuclear Power Plant, to the Manufacturing and Welding of Mechanical Components in line with RCC-M Code

From the Safety Approach of a Nuclear Power Plant, to the Manufacturing and Welding of Mechanical Components in line with RCC-M Code From the Safety Approach of a Nuclear Power Plant, to the Manufacturing and Welding of Mechanical Components in line with RCC-M Code Philippe Malouines AREVA RCC-M Sub-Committee Chairman Presented by Marcello

More information

NSSS Design (Ex: PWR) Reactor Coolant System (RCS)

NSSS Design (Ex: PWR) Reactor Coolant System (RCS) NSSS Design (Ex: PWR) Reactor Coolant System (RCS) Purpose: Remove energy from core Transport energy to S/G to convert to steam of desired pressure (and temperature if superheated) and moisture content

More information

WM2014 Conference, March 2 6, 2014, Phoenix, Arizona, USA

WM2014 Conference, March 2 6, 2014, Phoenix, Arizona, USA Reactor D&D: AREVA French and German Latest Experiences - 14458 (1) Stephan Krüger, AREVA GmbH, Kaiserleistr. 29, 63067 Offenbach, Germany; stephan.krueger@areva.com (2) Xavier de Brimont, AREVA NC, 1

More information

NPP Simulators Workshop for Education - Passive PWR NPP & Simulator Overview

NPP Simulators Workshop for Education - Passive PWR NPP & Simulator Overview NPP Simulators Workshop for Education - Passive PWR NPP & Simulator Overview Wilson Lam (wilson@cti-simulation.com) CTI Simulation International Corp. www.cti-simulation.com Sponsored by IAEA Modified

More information

QUALITY AUDIT AND QUALITY IMPROVEMENT PLAN at AREVA NP Le Creusot forging facility. London - September 12 th, 2017

QUALITY AUDIT AND QUALITY IMPROVEMENT PLAN at AREVA NP Le Creusot forging facility. London - September 12 th, 2017 QUALITY AUDIT AND QUALITY IMPROVEMENT PLAN at AREVA NP Le Creusot forging facility London - September 12 th, 2017 RPV Shell Core plate AREVA NP Creusot Forge RCP casing Monobloc closure head 220 people

More information

Safety Implication for Gen-IV SFR based on the Lesson Learned from the Fukushima Dai-ichi NPPs Accident. Ryodai NAKAI Japan Atomic Energy Agency

Safety Implication for Gen-IV SFR based on the Lesson Learned from the Fukushima Dai-ichi NPPs Accident. Ryodai NAKAI Japan Atomic Energy Agency Safety Implication for Gen-IV SFR based on the Lesson Learned from the Fukushima Dai-ichi NPPs Accident Ryodai NAKAI Japan Atomic Energy Agency Contents Introduction Japanese Government Report to the IAEA

More information

Implementation of SQUG Experience-Based Methods for Seismic Qualification of Equipment

Implementation of SQUG Experience-Based Methods for Seismic Qualification of Equipment Implementation of SQUG Experience-Based Methods for Seismic Qualification of Equipment Presentation for: 2006 MCEER Annual Meeting June 29 ~ 30, 2006 Prepared by: Steve Eder & John Dizon Facility Risk

More information

Safety enhancement of NPPs in China after Fukushima Accident

Safety enhancement of NPPs in China after Fukushima Accident Safety enhancement of NPPs in China after Fukushima Accident CHAI Guohan 29 June 2015, Brussels National Nuclear Safety Administration, P. R. China Current Development of Nuclear Power Mid of year 2015

More information

Lessons learned from Angra 1 & Angra 2 NPP s Outages

Lessons learned from Angra 1 & Angra 2 NPP s Outages Lessons learned from Angra 1 & Angra 2 NPP s Outages DO Diretoria de Operação SM.O Superintendência de Manutenção Preparado por: Luciano Junqueira Calixto Email: lucical@eletronuclear.gov.br Angra 1: Angra

More information

APPROACH TO PRACTICAL ELIMINATION IN FINLAND

APPROACH TO PRACTICAL ELIMINATION IN FINLAND M-L. JÄRVINEN et al. APPROACH TO PRACTICAL ELIMINATION IN FINLAND M-L. JÄRVINEN Radiation and Nuclear Safety Authority (STUK) Helsinki, Finland Email: marja-leena.jarvinen@stuk.fi N. Lahtinen Radiation

More information

Example Pressurized Water Reactor Defense-in-Depth Measures For GSI-191, PWR Sump Performance

Example Pressurized Water Reactor Defense-in-Depth Measures For GSI-191, PWR Sump Performance Example Pressurized Water Reactor Defense-in-Depth Measures For GSI-191, PWR Sump Performance ATTACHMENT Introduction This paper describes a range of defense-in-depth measures that either currently exist

More information

UK ABWR Generic Design Assessment Generic PCSR Chapter 8 : Structural Integrity

UK ABWR Generic Design Assessment Generic PCSR Chapter 8 : Structural Integrity Form10/00 Document ID Document Number Revision Number : : : GA91-9101-0101-08000 RE-GD-2043 C Generic Design Assessment Generic PCSR Chapter 8 : Structural Integrity Hitachi-GE Nuclear Energy, Ltd. Form01/03

More information

Regulatory oversight of nuclear safety in Finland

Regulatory oversight of nuclear safety in Finland STUK-B 214 / JUNE 2017 B Regulatory oversight of nuclear safety in Finland Annual report 2016 Erja Kainulainen (ed.) Säteilyturvakeskus Strålsäkerhetscentralen Radiation and Nuclear Safety Authority STUK-B

More information

Best practices for preparing vessel internals segmentation projects

Best practices for preparing vessel internals segmentation projects Best practices for preparing vessel internals segmentation projects Joseph BOUCAU a*, Per SEGERUD b, Moisés SANCHEZ c a Westinghouse Electric Company, 43 rue de l Industrie, 1400 Nivelles, Belgium b Westinghouse

More information

Review of Generation III Reactors

Review of Generation III Reactors Review of Generation III Reactors Dr. Helmut Hirsch Scientific Consultant for Nuclear Safety Neustadt, Germany 1 Status of Nuclear Power Today (I) Future of nuclear power uncertain. No significant growth

More information

An Overview of the ACR Design

An Overview of the ACR Design An Overview of the ACR Design By Stephen Yu, Director, ACR Development Project Presented to US Nuclear Regulatory Commission Office of Nuclear Reactor Regulation September 25, 2002 ACR Design The evolutionary

More information

AP1000 European 15. Accident Analysis Design Control Document

AP1000 European 15. Accident Analysis Design Control Document 15.2 Decrease in Heat Removal by the Secondary System A number of transients and accidents that could result in a reduction of the capacity of the secondary system to remove heat generated in the reactor

More information

Regulatory Actions and Follow up Measures against Fukushima Accident in Korea

Regulatory Actions and Follow up Measures against Fukushima Accident in Korea Int Conference on Effective Nuclear Regulatory Systems, April 9, 2013, Canada Regulatory Actions and Follow up Measures against Fukushima Accident in Korea Seon Ho SONG* Korea Institute of Nuclear Safety

More information

Flamanville 3 EPR Safety assessment and on-site inspections

Flamanville 3 EPR Safety assessment and on-site inspections Corine PIEDAGNEL - François TARALLO Bernard MONNOT Institut de Radioprotection et de Sûreté Nucléaire Flamanville 3 EPR Safety assessment and on-site inspections Flamanville 3 EPR Safety assessment and

More information

WM2010 Conference, March 7-11, 2010, Phoenix, AZ MODULAR CONSTRUCTION FOR EVENTUAL DECONSTRUCTION AND DECOMMISSIONING

WM2010 Conference, March 7-11, 2010, Phoenix, AZ MODULAR CONSTRUCTION FOR EVENTUAL DECONSTRUCTION AND DECOMMISSIONING MODULAR CONSTRUCTION FOR EVENTUAL DECONSTRUCTION AND DECOMMISSIONING - 10300 1 ABSTRACT Dr. Jas S. Devgun, Ph.D., CHMM Manager Nuclear Power Technologies Sargent & Lundy LLC 55 E. Monroe St Chicago, IL

More information

CONTAINMENT STRUCTURES

CONTAINMENT STRUCTURES CONTAINMENT STRUCTURES M. Ragheb 11/16/2017 INTRODUCTION A misconception about nuclear power plants containment structures is that their massive concrete construction is a protection against the release

More information

GenIII/III+ Nuclear Reactors

GenIII/III+ Nuclear Reactors OL1&2 GenII GenIII OL3 TVO s Olkiluoto Nuclear Power Plant in Finland GenIII/III+ Nuclear Reactors RESEARCH NEEDES AND CHALLENGES FISA 2009, Prague Contents What are the GenIII features Evolutionary development

More information

Challenges & Successes of Candu Energy (former AECL) in Nuclear Construction: Case Study of China and Romania

Challenges & Successes of Candu Energy (former AECL) in Nuclear Construction: Case Study of China and Romania IAEA Workshop on Construction Technologies for Nuclear Power Plants: A Comprehensive Approach Paris, France 12 16 December, 2011 Challenges & Successes of Candu Energy (former AECL) in Nuclear Construction:

More information

Small Modular Reactors: A Call for Action

Small Modular Reactors: A Call for Action Small Modular Reactors: A Call for Action Overview of Five SMR Designs by Dr. Regis A. Matzie Executive Consultant Adapted May 2015 for the Hoover Institution's Reinventing Nuclear Power project from a

More information

National Status on Life Management of NPPs in Finland Meeting of the IAEA TWG-LMNPP February th 2017 Vienna, Jyrki Kohopää

National Status on Life Management of NPPs in Finland Meeting of the IAEA TWG-LMNPP February th 2017 Vienna, Jyrki Kohopää National Status on Life Management of NPPs in Finland 2017 Meeting of the IAEA TWG-LMNPP February 22-24 th 2017 Vienna, Jyrki Kohopää NUCLEAR POWER IN FINLAND Teollisuuden Voima Oyj, Olkiluoto: OL1/2:

More information

ENSA ENWESA SERVICES INDEX

ENSA ENWESA SERVICES INDEX ENSA ENWESA SERVICES INDEX 1. ENGINEERING, DESIGN AND TECHNOLOGY SERVICES (Ensa / ENWESA) Ensa has extensive experience designing nuclear components and pressure vessels since 1973 according to international

More information

ENSREG ACTION PLAN FACT FINDING SITE VISITS. France s Report. September 2012

ENSREG ACTION PLAN FACT FINDING SITE VISITS. France s Report. September 2012 - ENSREG ACTION PLAN FACT FINDING SITE VISITS France s Report September 2012 1 1 INTRODUCTION AND BRIEF DESCRIPTION OF PLANTS VISITED... 3 2 SUMMARY OF OBSERVATIONS... 5 3 2.1 Description of measures already

More information

EDF Training in Support of a New Nuclear Project

EDF Training in Support of a New Nuclear Project EDF Training in Support of a New Nuclear Project Jean-Luc His EDF Engineering and Generation Training Unit IAEA TM on Human Resources Roadmaps and Capacity Building for New and Expanding Nuclear Power

More information

DEVELOPMENT AND APPLICATION OF PROBABILISTIC SAFETY ASSESSMENT PSA IN DAYA BAY NUCLEAR POWER STATION

DEVELOPMENT AND APPLICATION OF PROBABILISTIC SAFETY ASSESSMENT PSA IN DAYA BAY NUCLEAR POWER STATION 18th International Conference on Structural Mechanics in Reactor Technology (SMiRT 18) Beijing, China, August 7-12, 2005 SMiRT18-A01-2 DEVELOPMENT AND APPLICATION OF PROBABILISTIC SAFETY ASSESSMENT PSA

More information

DESIGN, SAFETY FEATURES & PROGRESS OF HTR-PM. Yujie DONG INET, Tsinghua University, China January 24, 2018

DESIGN, SAFETY FEATURES & PROGRESS OF HTR-PM. Yujie DONG INET, Tsinghua University, China January 24, 2018 DESIGN, SAFETY FEATURES & PROGRESS OF HTR-PM Yujie DONG INET, Tsinghua University, China January 24, 2018 Meet the Presenter Dr. Dong is a Professor in Nuclear Engineering at the Tsinghua University, Beijing,

More information

Design of Traditional and Advanced CANDU Plants. Artur J. Faya Systems Engineering Division November 2003

Design of Traditional and Advanced CANDU Plants. Artur J. Faya Systems Engineering Division November 2003 Design of Traditional and Advanced CANDU Plants Artur J. Faya Systems Engineering Division November 2003 Overview Canadian Plants The CANDU Reactor CANDU 600 and ACR-700 Nuclear Steam Supply Systems Fuel

More information

2/24/2012. Generation mpower LLC. Major Complexity. Design & Manufacturing Complexities in SMR Technology

2/24/2012. Generation mpower LLC. Major Complexity. Design & Manufacturing Complexities in SMR Technology 2/2/2012 Design & Manufacturing Complexities in SMR Technology Regulatory Information Conference March 1, 2012 Ali Azad President & CEO Generation mpower LLC Generation mpower LLC Formal alliance between

More information

CGN's Nuclear Energy Capabilities

CGN's Nuclear Energy Capabilities Business Overview NPP Construction Achievements NPP Operating Performance Overseas Business Core Nuclear Power Technologies CGN's Nuclear Energy Capabilities Nuclear Project Construction Capabilities Operations

More information

V.C. Summer Nuclear Station Units 2 & 3

V.C. Summer Nuclear Station Units 2 & 3 V.C. Summer Nuclear Station Units 2 & 3 Quarterly Report to the South Carolina Office of Regulatory Staff Submitted by South Carolina Electric & Gas Company Pursuant to Public Service Commission Order

More information

NUCLEAR. Nuclear Reactor Pressure Vessel Seals

NUCLEAR. Nuclear Reactor Pressure Vessel Seals NUCLEAR Nuclear Reactor Pressure Vessel Seals SEALING CONCEPT Technetics Group is the world s leading manufacturer of Nuclear Reactor Pressure Vessel (RPV) Closure Head Seals. In addition, Technetics Group

More information

Olli Vilkamo; Kirsi Alm-Lytz Radiation and Nuclear Safety Authority, STUK. Radiation Safety in New Build

Olli Vilkamo; Kirsi Alm-Lytz Radiation and Nuclear Safety Authority, STUK. Radiation Safety in New Build Olli Vilkamo; Kirsi Alm-Lytz Radiation and Nuclear Safety Authority, STUK Radiation Safety in New Build STUK - Radiation and Nuclear Safety Authority Mission: Protecting people, society, environment, and

More information

Revenue and data for the first nine months of 2008

Revenue and data for the first nine months of 2008 Paris, October 23, 2008 Revenue and data for the first nine months of 2008 9-month revenue for 2008 up sharply to 9.103B, for a +12.9% increase (+13.9% like-for-like 1 ) The group cleared revenue of 9.1

More information

ALSTOM Atomenergomash LLC developing ARABELLE based Turbine Islands for newly constructed and retrofitted nuclear power plants.

ALSTOM Atomenergomash LLC developing ARABELLE based Turbine Islands for newly constructed and retrofitted nuclear power plants. ALSTOM Atomenergomash LLC developing ARABELLE based Turbine Islands for newly constructed and retrofitted nuclear power plants. 26.10.2011 A.M. Tsvetkov, ALSTOM Atomenergomash LLC ALSTOM Atomenergomash

More information

EPR FLAMANVILLE 3 Site Management *** Atoms for the future*** - 14th October Antoine Ménager, Site Manager

EPR FLAMANVILLE 3 Site Management *** Atoms for the future*** - 14th October Antoine Ménager, Site Manager EPR FLAMANVILLE 3 Site Management *** Atoms for the future*** - 14th October 2014 - Antoine Ménager, Site Manager EDF Group NUCLEAR GENERATION: LEADERSHIP CONFIRMED Over 487 TWh generated, including :

More information

ELETRONUCLEAR s Response to the Fukushima Dai-ichi Nuclear Accident

ELETRONUCLEAR s Response to the Fukushima Dai-ichi Nuclear Accident s Response to the Fukushima Dai-ichi Nuclear Accident Rio de Janeiro, July 3 rd, 2012 Paulo Vieira First Actions Taken by Eletronuclear Establishment of a Corporate Working group Follow up of the event,

More information

TECHNICAL CENTER Focus on Technology

TECHNICAL CENTER Focus on Technology TECHNICAL CENTER Focus on Technology AREVA s worldwide Technical Center Technical Center serves as the bridge from basic research to industrial application with main focus on basic technologies organized

More information

Thermal Hydraulic Simulations of the Angra 2 PWR

Thermal Hydraulic Simulations of the Angra 2 PWR Thermal Hydraulic Simulations of the Angra 2 PWR Javier González-Mantecón, Antonella Lombardi Costa, Maria Auxiliadora Fortini Veloso, Claubia Pereira, Patrícia Amélia de Lima Reis, Adolfo Romero Hamers,

More information

Nuclear Power A Journey of Continuous Improvement

Nuclear Power A Journey of Continuous Improvement Nuclear Power A Journey of Continuous Improvement Westinghouse Non Proprietary Class 3 Our Place in Nuclear History Innovation 1886 and forever Implementation & Improvement 1957 through Today Renaissance

More information

Enhancement of Nuclear Safety

Enhancement of Nuclear Safety Enhancement of Nuclear Safety Soon Heung Chang Handong Global University May 6, 2015 Contents 1 2 3 4 Importance of Energy Fundamentals of Nuclear Safety How to Enhance Nuclear Safety Closing Remarks 2

More information

-30- QUEBEC GENTILLY 2 NUCLEAR POWER STATION' J.A. Labbé. Hydro Quebec

-30- QUEBEC GENTILLY 2 NUCLEAR POWER STATION' J.A. Labbé. Hydro Quebec -30- QUEBEC GENTILLY 2 NUCLEAR POWER STATION' by J.A. Labbé Hydro Quebec INTRODUCTION Since our previous progress report, delivered at last year's conference in Montreal, work in the nuclear energy field

More information

CLASSIFICATION OF SYSTEMS, STRUCTURES AND COMPONENTS OF A NUCLEAR FACILITY

CLASSIFICATION OF SYSTEMS, STRUCTURES AND COMPONENTS OF A NUCLEAR FACILITY CLASSIFICATION OF SYSTEMS, STRUCTURES AND COMPONENTS OF A NUCLEAR FACILITY 1 Introduction 3 2 Scope of application 3 3 Classification requirements 3 3.1 Principles of safety classification 3 3.2 Classification

More information

AP1000: The PWR Revisited

AP1000: The PWR Revisited AP1000: The PWR Revisited IAEA International Conference on Opportunities and Challenges for Water Cooled Reactors in the 21st Century aolo Gaio estinghouse Electric Company tober 27, 2009 1 Background

More information

Reactor Technology: Materials, Fuel and Safety. Dr. Tony Williams

Reactor Technology: Materials, Fuel and Safety. Dr. Tony Williams Reactor Technology: Materials, Fuel and Safety Dr. Tony Williams Course Structure Unit 1: Reactor materials Unit 2. Reactor types Unit 3: Health physics, Dosimetry Unit 4: Reactor safety Unit 5: Nuclear

More information

South African nuclear industry overview Van Zyl de Villiers R&D Division Necsa

South African nuclear industry overview Van Zyl de Villiers R&D Division Necsa South African nuclear industry overview Van Zyl de Villiers R&D Division Necsa ASME Nuclear Codes and Standards Workshop 7 October 2008 Contents South African energy challenges South African Nuclear Energy

More information

Preparedness at PFBR Kalpakkam to meet the challenges due to Natural events Prabhat Kumar, Project Director, PFBR, Director construction BHAVINI

Preparedness at PFBR Kalpakkam to meet the challenges due to Natural events Prabhat Kumar, Project Director, PFBR, Director construction BHAVINI BHARATIYA NABHIKIYA VIDYUT NIGAM LIMITED (A Government of India Enterprise) Preparedness at PFBR Kalpakkam to meet the challenges due to Natural events Prabhat Kumar, Project Director, PFBR, Director construction

More information