EPR Projects: Updates
|
|
- Donald Norman
- 6 years ago
- Views:
Transcription
1 Nissen M. Burstein Technical Consultant Presented at SC-2, Meeting June 15-17, 2011, Gothenburg, Sweden EPR is a trademark of the AREVA Group.
2 Overview of U.S. EPR Reactor Redundant safety systems are physically separated into four divisions, which protect the individual integrity of the electrical and mechanical safety systems. The four divisions of safety systems are consistent with an N+2 safety concept. One division can be out of service for maintenance One division can fail to operate The remaining two divisions are available to perform the necessary safety functions even if one of the two remaining trains becomes inoperable due to the initiating event.
3 Overview of the U.S. EPR Design Evolutionary 4-loop PWR designed for a rated core thermal power level of 4590 MWt. The U.S. EPR unique design features include: Four redundant trains of emergency core cooling. Containment and shield building. Core melt retention system for severe accident mitigation. The plant design objective is 60 years. The design provides for the replaceability of major components, including the steam generators. The Reactor Building is an integrated structure consisting of an inner Reactor Containment Building, an outer building called the Reactor Shield Building, and an annular space between the two buildings that separates them for protection against external hazards (including aircraft impact).
4 Highlights of Recent U.S. EPR Activity General The U.S. EPR design application is currently under NRC review. A total of 4140 formal RAIs and 180 open items have been received as of April 22. AREVA has responded to 3846 questions and 130open items. Phase 1 review of the application, i.e., preliminary SER and all RAIs issued, was completed on 1/28/09. Phase 2 review (i.e., development of the SER with open items) and Phase 4 (i.e., development of the Advanced SER with no open items) on some sections is currently in progress. A total of eleven chapter SERs with open items and three partial SERs with open items have been received to date and thirteen associated ACRS meetings completed. Schedule date for NRC approval of the design application is June Key issues involve Seismic and Structural Analysis, I&C, and resolution of GSI-191 related to sump strainer clogging. Of the 11 active topical reports, 6 have been approved, 4 have been issued a draft SER, and 1 is under active review.
5 Regulatory Status Regarding ASME QME NRC issued revision 3 of RG in September 2009 which endorses ASME QME with exceptions and clarifications (e.g., use of either earthquake experience data or test experience data for seismic qualification needs to be submitted for NRC review and approval). AREVA uses ASME QME as guidance for qualifying active mechanical equipment with the exception that a separate mechanical equipment qualification (MEQ) program for the U.S. EPR design will not be maintained as noted in U.S. EPR FSAR Tier 2, Section for nonmetallic subcomponents.
6 Engineering Implementation of ASME QME IEEE Standards , , , and are used for qualification. Environmental Qualification (EQ) EQ of electrical appurtenances meets the requirements of IEEE EQ of the valve actuator meets the requirements of IEEE EQ of the pump motor meets the requirements of IEEE EQ of the valve is limited to the nonmetallic parts of the valve. EQ follows the guidance of non-mandatory Appendix QR-B of QME-1 for nonmetallic parts of the valve.
7 Engineering Implementation of ASME QME The AREVA position regarding QME has been documented in an internal AREVA NP position paper. Design Specifications ensure consistency with regard to the application of QME Examples of design specifications that refer to QME : ASME Class 1 Valves ASME Class 2 and 3 Valves ASME Section III Pump/Motor Assemblies Control Rod Drive Mechanism Main Steam and Full-Load Feedwater Isolation Valves Pressurizer Safety Relief Valves Pressurizer Solenoid Spray Valve
8 FSAR Incorporation of ASME QME Elements Elements of QME have been incorporated into the U.S. EPR FSAR. U.S. EPR FSAR Tier 2, Table was revised to change the reference from RG 1.100, Revision 2 to Revision 3. The following FSAR Sections have been revised to indicate that the functional design and qualification testing of safety-related pumps, valves, and snubbers is performed in accordance with ASME QME as endorsed by RG 1.100, Revision 3, with clarifications regarding the non-mandatory appendices of ASME QME : 3.9.3, ASME Code Class 1, 2, and 3 Components, Component Supports, and Core Support Structures , Functional Design and Qualification of Pumps, Valves, and Dynamic Restraints 3.10, Seismic and Dynamic Qualification of Mechanical and Electrical Equipment 3.11, Environmental Qualification of Mechanical and Electrical Equipment
9 FSAR Incorporation of ASME QME Elements Consistent with RG Rev. 3, U.S. EPR FSAR Tier 2, Section 3.10 addresses the applicability of the non-mandatory appendices of QME Examples are listed below: Non-mandatory Appendix QR-A is not utilized because seismic qualification is in accordance with IEEE , which is consistent with QME Additionally, Section 10.2, Earthquake Experience Data, QR-A7400 and QR-A7500, is not utilized by AREVA. Qualification of non-metallic parts is consistent with non-mandatory Appendix QR-B as described in FSAR Section The provisions for the design and qualification of snubbers is consistent with Section QDR and non-mandatory Appendices QDR-A, QDR-B, and QDR-C. Snubbers in safety-related systems include provisions to allow access for IST program activities. AREVA is not utilizing non-mandatory Appendices QP-A through QP-E, because pump and motor assemblies are designed and qualified in accordance with applicable standards (e.g., ASME B&PV Code, QME-1, ASME B16, IEEE 323, IEEE 334, IEEE 344, RG 1.84, ASME NQA-1). Non-mandatory Appendix QV-A, Functional Specification for Active Valves for Nuclear Power Plants, is used as guidance in the development of valve specifications to demonstrate that lessons learned from industry experience are included in the specifications.
10 4 EPR Reactors under construction EPR Projects Olkiluoto 3 Flamanville 3 Taishan 1&2
11 Olkiluoto 3 Project Update March 2011 EPR is a trademark of the AREVA Group.
12 General Orientation Olkiluoto Island
13 Benefits for the local region s economy Benefits during construction works On employment: 3,500-6,000 people employed directly or indirectly Unemployment rate halved in comparison with 2004 Eurajoki: 6,4%, among the lowest unemployment rates in Finland On production: million euros Gross Domestic Product of the region increased by 2,6% 180 companies in Satakunta region involved Annual turnover increase in construction sector over 2006/ ,4% Permanent benefits Yearly increase of procurement amounts and needs for external services Larger yearly NPP revisions hundreds of external subcontractors Increase in knowledge and other human values Impact on taxation (Eurajoki see also next page)
14 Benefits for the local region s economy Taxes, services and housing sector Increased estimate of municipal tax (workforce needed for operations) by ~ 60% in Rauma and 25% in Eurajoki for a national average of 5% Income taxes represent around millions, which is over 30% of the total collected taxes Estimated increase of real estate tax of nuclear power from ~ 3 million to ~ 7-8 million by 2011 Clear current national boom in housing industry Utilization rates in region s hotels exceeding +60% Significant increase in services such as: restaurants, retail trade, etc.
15 NI/TI Buildings Buildings of Nuclear Island - NI Buildings of Turbine Island - TI Waste Building Auxiliary Building Fuel Building Diesels 2+1 Building Access Building Electrical Building Safeguard Building 4 Reactor Building Safeguard Building 1 Turbine Building Diesels 2+1 Building Safeguard Buildings 2+3 Circulating Water Pump Building Ducts & channels Essential Service Water Pump Building
16 General view of NI
17 Turbine Hall (UMA)
18 NI Progress Construction ~ 57% completed External dome to be completed by June Total of 270,000m³ to be poured (NI + TI: 336,000m³) Pre-stressing completed 80% backfilling completed Electro-mechanical activities 580km of cables pulled 64% progress for HVAC 42% of piping installation completed 87% piping-related equipment installed Primary components installation completed: Reactor Pressure Vessel and closure head, Pressurizer, 4 Steam Generators Tests and commissioning ramping-up Documentation: 137 System Commissioning Programmes out of 158 issued Polar crane and auxiliary crane pre-operational tests completed
19 OL3 I&C Overall status Architecture accepted by STUK, regulator, with application of conditions Systems independency for safety and process functions Hardwire Back-up System (HBS) Overall test concept to be approved by TVO, utility, as soon as possible I&C time schedule under reassessment Local platforms on site for modifications during Commissioning Full scope simulator Delivery to site Spring 2011
20 Electro-mechanical installation Electrical installation progress
21 Electro-mechanical installation Battery Room
22 Electro-mechanical installation TELEPERM XS Cabinets
23 Primary Circuit Complete loop Pressurizer Steam Generator Hot Leg Reactor Pressure Vessel Cross Over Leg Cold Leg
24 Primary circuit Welding completed Welding completed Welding ongoing
25 Primary components Installation of Steam Generators
26 Manpower/Nationality February 2011 Country % of site population Finland 29% Germany 19% Poland 18% Croatia 9% France 6% Estonia 4% Bosnia and Herzegovina 2% Others 12%
27 OL3 General time schedule Civil Work Finishing Electro-mechanical installation Commissioning Primary Components installed Essential water service lines Flooding Full Scope Simulator Operating License Fuel Loading
28 Next steps 2011 Completion of outer dome Completion of the primary circuit Completion of electro-mechanical installation Pre-operational tests & Commissioning ramping up Configuration management implementation Integration of TVO staff in Operation Integrated Organization 86% of System Commissioning Program issued Objectives: Fuel loading end of 2012
29 AREVA and the companies operating in the background are still the world s leading nuclear suppliers. They have the best and safest product. We have no reason to doubt it and we have no reason to doubt their honesty either. Jukka Laaksonen, STUK Director, on Finnish TV channel MTV3, August 22, 2008 The EPR TM is the most advanced technology worldwide. Martin Landtman, Senior Vice President, Project OL3, TVO, in Handelsblatt, Germany, August 13, 2007
30 Flamanville 3 Project Progress of the works April 2011 EPR is a trademark of the AREVA Group.
31 EPR Flamanville 3 Project
32 FA 3 Site Progress April 2011
33 Scope of Work AREVA is responsible for the turnkey NSSS, including design, procurement, erection and commissioning work Similar scope compared to previous series (N4 was a reference for contractual aspect) Civil works awarded to Bouygues, turbine island to Alstom April 11, 2007: Contract signed between EDF and AREVA April 10, 2007: Approval of the construction permit December 3, 2007: First concrete pouring 2014: Start of commercial operation
34 Project progress Achieved and ongoing deliveries: IRWST lines Primary anchors Embedded excore tubes & tanks RPV support ring and reactor vessel-to-cavity seal ring Auxiliary racks Venturi Tubes (diameter: 250mm et 500mm) Various sensors SIS Pumps Valves SIS Accumulators SIS Exchangers Some valves Flamanville site, April 2011 Installation: Installation of the first embedded tanks (RPE, Pressurizer Relief Tank), first pumps (SIS pumps) and first exchangers (SIS exchangers) Welding of the first supports at the end of The Safety Analysis Report (SAR) for the Operating License Application has been delivered in October Manufacturing of primary components is on going. Engineering and procurement are on track with the customer s schedule.
35 Reactor building Civil Work progress Civil work under EDF responsibility Tenth lift of the outer containment done since august th lift of the inner containment done. The walls of the pools are almost finished The Reactor Building re opened. Current progress: Vessel, Steam Generators and Pressurizer are under manufacturing in AREVA Chalon/St Marcel, France First supports welded end of Concrete done Reinforcement ongoing
36 Main components Steam generator / AREVA Chalon/St Marcel, France Pressurizer / AREVA Chalon/St Marcel, France Main coolant pump / AREVA JSPM, France Main coolant line / AREVA Creusot Forge, France Reactor pressure vessel (RPV) / AREVA Chalon/St Marcel, France
37 Equipment Manufacturing: Reactor Pressure Vessel AREVA Chalon/Saint Marcel
38 Heat exchanger in the auxiliary safeguard building
39 welding of supports for cable paths in auxiliary safeguard building
40 Cables in the electrical building
41 Pipes coming in and out of the turbine
42 Taishan 1&2 Project
43 Taishan Project - General View Taishan 1&2 September 2009 The largest contract ever signed in the civil nuclear industry
44 Taishan 1&2 Project Progress of the works 台山 February 2011 Validated for internal communication EPR is a trademark of the AREVA Group.
45 Site location TAISHAN EPR Projects:
46 Taishan 1 & 2 Progress update TSN 1&2 Key Facts AREVA scope Procurement: 80% orders made Engineering: 60% completed All main components are being manufactured Engineering JV with CGNPC set up successfully Outside AREVA scope Unit 1: Liner up to +43,90m Almost ready for dome lifting Inner wall concreted up to m Unit 2: common raft poured in April 2010 Liner installed up to+12m Piping prefabrication started by the Client based on AREVA design More than 12,000 people are working on site every day
47 Taishan Reactor Building Progress February 2011 Unit 1 February 2011 Unit 2
48 Achievements to date Engineering PSAR & licensing activities are well on track with NNSA Project is now more than mid way and more than 60% of engineering activities are completed Basic Design is in an ending phase and gives path to the detail design currently under progress within the JDO organization set-up in China mid 2009 (for Piping and Electrical) Civil work detail design for Reinforcements & Formworks very close to Nov forecast Procurement Order placement is about to be finished by first months of 2011 Polar Crane manufacturing activities at DHI/DCW. CNPEC is improving its efficiency in terms of expediting & inspection. Site activities The AREVA NP site related activities are evolving with the mobilization of Design Liaison Team and ongoing discussions on possible technical assistance for installation and commissioning.
49 Project overview Customer CGNPC CGNPC China Guangdong Nuclear Power Holding Corp. Ltd. One of the 5 Chinese Electrical Companies Developing a nuclear program historically in the Guangdong province (Daya Bay, Ling Ao I&II ) and now in other provinces Capital: CNNC (45%), Guangdong Province (45%) & China Power Investment (10%) Today, CGNPC wants to create its own nuclear industry to position itself as the major player of the electronuclear development in China CGNPC involves many of its own subsidiaries into the Taishan Project, among them; China Nuclear Power Engineering Company (CNPEC) and China Nuclear Power Design Company (CNPDC)
50 Overview of NI EP Contract Contract signed between TNPJVC & AREVA/CNPEC/CNPDC Consortium Contract structure and principles based on Ling Ao phase I Scope Design & Engineering of NI FOB Supply of the Equipment (or Ex-Works for China) Technical Assistance (upon demand) Civil work detailed design (confirmed at contract's signature) First options to be confirmed Primary loop erection and commissioning (EM2/EM11.2 package) Civil construction, Installation & Commissioning performed by TNPJVC Technical Assistance (upon demand) on installation, commissioning, civil, maintenance, operation, etc. Turbine island: Consortium Dongfang/Alstom Reference power plant: mainly FA3 Project duration: 76 months (24+52 months) with 10 months difference between the 2 units
51 Primary Loop for Taishan Unit 1 Contrat Chalon Saint-Marcel JSPM Creusot Forge Steam Generator Control Rod Drive Mechanisms Pressurizer RPV MHI Reactor Cooling Pumps (SAFAS/DFEM) Internals Skoda IMS TSN Primary Lines
52 Primary Loop for Taishan Unit 2 Contrat Chalon Saint-Marcel JSPM Creusot Forge Pressurizer DFHM Steam Generator SENPEC / DFHM Control Rod Drive Mechanisms JSPM / Shangai Number One Reactor Cooling Pumps RPV DFHM JSPM / ADJV / DFEM / SAFAS Internals Shangai Number 1 IMS TSN Primary Lines
53 Key figures 125,000 documents 7,000 civil works drawings 400 technical files for requisition 220 system Design Manuals 500 installation instructions 150 working procedures Piping 72 Km Large Bore / 150 Km Small Bore Electrical 45,000 cables / 90,000 heads 400,000 connections points 3,500 Km cables 60 Km Main Cable Trays / 20 Local Cable Trays 14,000 supports Total weight equipments: 10,000 T
54 Great amount of resource is mobilized More than 1,500 people working for the NI EP Consortium 1,000 AREVA and more than 500 CNPDC/CNPEC On site, TNPJVC responsibility: 12,000 peop Data
55 Next steps 2011 Deadlines Next steps May 2011 Delivery of Civil Dependant equipment for Dome Lifting (Polar crane, RCP / RIS...) July 2011 Dome Lifting October 2011 Reactor Pressure Vessel (FOB) boarding from MHI Japan to Taishan China End 2011 Primary Loop installation starts
Welcome to Taishan NP site
Welcome to Taishan NP site 1 Content Project Introduction Project Progress Main Tasks in 2011 2 Site Conditions TSNP is situated at Yaogu village of Chixi town in Taishan city, Guangdong province, 70km,
More informationPoland Nuclear Program EPR Flamanville 3
Poland Nuclear Program EPR Flamanville 3 Project Organization Design & Manufacturing activities On Site activities What We Are Learning from New Construction Experience September 29 th, 2010 Gilles Zask
More informationWestinghouse AP1000. Reactor
Westinghouse AP1000 A Third Generation Nuclear Reactor International Council on Systems Engineering (INCOSE) September 18, 2013 Andrew Drake, PMP Director, AP1000 Engineering Completion Engineering, Equipment
More informationThe Westinghouse Advanced Passive Pressurized Water Reactor, AP1000 TM. Roger Schène Director,Engineering Services
The Westinghouse Advanced Passive Pressurized Water Reactor, AP1000 TM Roger Schène Director,Engineering Services 1 Background Late 80: USA Utilities under direction of EPRI and endorsed by NRC : Advanced
More informationA canter around the nuclear jumps..
A canter around the nuclear jumps.. Robert Davies Vice President New Build, AREVA UK Cambridge MPhil 8 th February 2012 Who are we? World leader in CO 2 -free power generation 9.1Bn in Annual Revenues
More informationConcepts and Features of ATMEA1 TM as the latest 1100 MWe-class 3-Loop PWR Plant
8 Concepts and Features of ATMEA1 TM as the latest 1100 MWe-class 3-Loop PWR Plant KOZO TABUCHI *1 MASAYUKI TAKEDA *2 KAZUO TANAKA *2 JUNICHI IMAIZUMI *2 TAKASHI KANAGAWA *3 ATMEA1 TM is a 3-loop 1100
More informationPRESS CONFERENCE. 3 September Jean-Bernard LÉVY Chairman and CEO. Xavier URSAT Group Senior Executive VP - New Nuclear Projects and Engineering
PRESS CONFERENCE 3 September 2015 Jean-Bernard LÉVY Chairman and CEO Xavier URSAT Group Senior Executive VP - New Nuclear Projects and Engineering EDF, A RESPONSIBLE ELECTRICITY COMPANY, A CHAMPION OF
More informationNPP-Nuclear Island Design From conceptual design to Project execution
NPP-Nuclear Island Design From conceptual design to Project execution Atoms for the Future Paris SFEN - October 14, 2014 D. Lanchet NPP-Nuclear Island Design From conceptual design to Project execution
More informationNuclear Power Plant Safety Basics. Construction Principles and Safety Features on the Nuclear Power Plant Level
Nuclear Power Plant Safety Basics Construction Principles and Safety Features on the Nuclear Power Plant Level Safety of Nuclear Power Plants Overview of the Nuclear Safety Features on the Power Plant
More informationDESIGN AND SAFETY PRINCIPLES LEONTI CHALOYAN DEPUTY CHIEF ENGINEER ON MODERNIZATION
DESIGN AND SAFETY PRINCIPLES LEONTI CHALOYAN DEPUTY CHIEF ENGINEER ON MODERNIZATION VIENNA OKTOBER 3-6, 2016 1 ANPP * ANPP is located in the western part of Ararat valley 30 km west of Yerevan close to
More informationOlkiluoto Infrastructure
OL3 Olkiluoto Infrastructure 2 30.9.2008 Arguments for a New Nuclear Plant Unit - Covers partly the additional electricity demand and replaces old power plants - Enables, together with renewables, the
More informationAND SITE LICENSING OF THE EPR FOR THE HINKLEY POINT C PROJECT
DESIGN ASSESSMENT AND SITE LICENSING OF THE EPR FOR THE HINKLEY POINT C PROJECT 10/2016 Stephen J Walls, EDF Energy Nuclear New Build 1 Olivier Bard, EDF HINKLEY POINT C (HPC) 2 HPC Financial Investment
More informationExperiences with the construction of EPR at Flamanville and Taishan
Experiences with the construction of EPR at Flamanville and Taishan OECD/ Nuclear Energy Agency Workshop : Project and Logistics Management in Nuclear New Build NEA Headquarters, Issy-les-Moulineaux March
More informationSEVERE ACCIDENT FEATURES OF THE ALTERNATIVE PLANT DESIGNS FOR NEW NUCLEAR POWER PLANTS IN FINLAND
SEVERE ACCIDENT FEATURES OF THE ALTERNATIVE PLANT DESIGNS FOR NEW NUCLEAR POWER PLANTS IN FINLAND Risto Sairanen Radiation and Nuclear Safety Authority (STUK) Nuclear Reactor Regulation P.O.Box 14, FI-00881
More informationEPR: Steam Generator Tube Rupture analysis in Finland and in France
EPR: Steam Generator Tube Rupture analysis in Finland and in France S. ISRAEL Institut de Radioprotection et de Sureté Nucléaire BP 17 92262 Fontenay-aux-Roses Cedex, France Abstract: Different requirements
More informationThe EPR Reactor: Evolution to Gen III+ based on proven technology. Andrew Teller, Senior Technical Advisor, AREVA
The EPR Reactor: Evolution to Gen III+ based on proven technology Andrew Teller, Senior Technical Advisor, AREVA Building on the Achievements of the N4 and Konvoi Reactors N4 KONVOI High output (1475MWe)
More informationFlamanville 3 EPR, safety assessment and on-site inspections
Flamanville 3 EPR, safety assessment and on-site inspections Corinne. PIEDAGNEL, François TARALLO, Bernard MONNOT Institut de Radioprotection et de Sûreté Nucléaire, DSR/SAMS 92262 Fontenay-aux-Roses Cedex,
More informationEDF & the nuclear renewal : the Flamanville 3 model. Jean-Claude Prenez Director for International Projects EDF Nuclear Engineering Division
EDF & the nuclear renewal : the Flamanville 3 model Jean-Claude Prenez Director for International Projects EDF Nuclear Engineering Division Varna, 27-29 May 2009 Contents 1.The french context and EDF nuclear
More informationWestinghouse s plant for the Nuclear Renaissance : AP1000. AP1000 Advanced Passive Plant
Westinghouse s plant for the Nuclear Renaissance : AP000 Fernando Naredo Milan, January 30, 006 AP000 Advanced Passive Plant Designed to compete with other sources in deregulated power markets - Two loop,
More informationOverview for a feasibility study
Overview for a feasibility study What, Why & Objectives of Feasibility Study? International Atomic Energy Agency Nuclear power option included within the national energy strategy MILESTONE 1 Ready to
More informationFRANCE LWR activities
FRANCE LWR activities Norbert NICAISE with contributions from AREVA-NP ASN French Nuclear Safety Authority, IRSN French Institute for Radiation Protection and Nuclear Safety (TSO of ASN), CEA French Atomic
More informationHPR1000: ADVANCED PWR WITH ACTIVE AND PASSIVE SAFETY FEATURES
HPR1000: ADVANCED PWR WITH ACTIVE AND PASSIVE SAFETY FEATURES D. SONG China Nuclear Power Engineering Co., Ltd. Beijing, China Email: songdy@cnpe.cc J. XING China Nuclear Power Engineering Co., Ltd. Beijing,
More informationApplication for Permission to Extend the Operating Period and Application for Approval of Construction Plans of Unit 3 at Mihama Nuclear Power Station
November 26, 2015 The Kansai Electric Power Co., Inc. Application for Permission to Extend the Operating Period and Application for Approval of Construction Plans of Unit 3 at Mihama Nuclear Power Station
More informationNuScale SMR Technology
NuScale SMR Technology UK IN SMR; SMR IN UK Conference - Manchester, UK Tom Mundy, EVP Program Development September 25, 2014 Acknowledgement & Disclaimer This material is based upon work supported by
More informationNDE SOLUTIONS INTERCONTRÔLE NONDESTRUCTIVE EXAMINATION
INTERCONTRÔLE NONDESTRUCTIVE EXAMINATION Specialists in nondestructive examination has specialized in automated nondestructive testing of nuclear reactor primary components and more specifically on steam
More informationFROG Owners Group A Worldwide Network of Experience. April 2012
FROG Owners Group A Worldwide Network of Experience April 2012 Origin FROG founded in 1991 Founding Members = utilities operating or building Nuclear Power Plants with Framatome supplying Nuclear Steam
More informationFull Steam ahead for Flamanville 3 EPR turbine island construction
May 2010 Full Steam ahead for Flamanville 3 EPR turbine island construction POWER The 1750 MWe ARABELLE turbine generator is the world s largest engine. The first such machine in Europe is currently under
More informationPreliminary Lessons Learned from the Fukushima Daiichi Accident for Advanced Nuclear Power Plant Technology Development
Preliminary Lessons Learned from the Fukushima Daiichi Accident for Advanced Nuclear Power Plant Technology Development A. Introduction The IAEA Report on Reactor and Spent Fuel Safety in the Light of
More informationDesign Features, Economics and Licensing of the 4S Reactor
PSN Number: PSN-2010-0577 Document Number: AFT-2010-000133 rev.000(2) Design Features, Economics and Licensing of the 4S Reactor ANS Annual Meeting June 13 17, 2010 San Diego, California Toshiba Corporation:
More informationRELAP5/MOD3.2 INVESTIGATION OF A VVER-440 STEAM GENERATOR HEADER COVER LIFTING
Science and Technology Journal of BgNS, Vol. 8, 1, September 2003, ISSN 1310-8727 RELAP5/MOD3.2 INVESTIGATION OF A VVER-440 STEAM GENERATOR HEADER COVER LIFTING Pavlin P. Groudev, Rositsa V. Gencheva,
More informationJoint ICTP-IAEA Essential Knowledge Workshop on Deterministic Safety Analysis and Engineering Aspects Important to Safety. Trieste,12-23 October 2015
Joint ICTP- Essential Knowledge Workshop on Deterministic Safety Analysis and Engineering Aspects Important to Safety Trieste,12-23 October 2015 Safety classification of structures, systems and components
More informationRegulatory Approach to Radiation Protection in new NPPs in Finland
Regulatory Approach to Radiation Protection in new NPPs in Finland ISOE European Workshop in Prague 20.-22. 6. 2012 Veli Riihiluoma Radiation and Nuclear Safety Authority (STUK) RADIATION AND NUCLEAR SAFETY
More informationAngra 3 Current status and challenges to continue
Angra 3 Current status and challenges to continue Vienna February 2017 Introduction Brazilian Transmission Network Integrated electric power system: continental dimensions Manaus Fortaleza Itaipu Brasília
More informationPost-Fukushima Assessment of the AP1000 Plant
ABSTRACT Post-Fukushima Assessment of the AP1000 Plant Ernesto Boronat de Ferrater Westinghouse Electric Company, LLC Padilla 17-3 Planta 28006, Madrid, Spain boronae@westinghouse.com Bryan N. Friedman,
More informationTechnology Development, Design and Safety Features of the CNP300 and A New Small PWR
Technology Development, Design and Safety Features of the CNP300 and A New Small PWR and A New Small PWR By LIN Qian Shanghai Nuclear Engineering Research and Design Institute (SNERDI) Content SNERDI and
More informationEuropean level recommendations Sect. in NAcP 2 Generic recommendation for WENRA, Finland participates and follows the work.
Cross reference table of ENSREG and Extraordinary CNS recommendations and national actions 1(16) 2.1 European guidance on assessment of natural hazards and margins The peer review Board recommends that
More informationAdvanced Design of Mitsubishi PWR Plant for Nuclear Renaissance
Advanced Design of Mitsubishi PWR Plant for Nuclear Renaissance October 28, 2009 Etsuro SAJI General Manager, Reactor Core Engineering Department Mitsubishi Heavy Industries, Ltd. GEN-HSW-9102-0 Contents
More informationWestinghouse Small Modular Reactor. Passive Safety System Response to Postulated Events
Westinghouse Small Modular Reactor Passive Safety System Response to Postulated Events Matthew C. Smith Dr. Richard F. Wright Westinghouse Electric Company Westinghouse Electric Company 600 Cranberry Woods
More informationAPR1400 Safe, Reliable Technology
APR1400 Safe, Reliable Technology OECD/NEA Workshop on Innovations in Water-cooled Reactor Technology Paris, Feb 11 12, 2015 Presented by Shin Whan Kim Contents 1. Introduction 2. Major Safety Design Characteristics
More informationThe Westinghouse AP1000 : Passive, Proven Technology to Meet European Energy Demands
BgNS TRANSACTIONS volume 20 number 2 (2015) pp. 83 87 The Westinghouse AP1000 : Passive, Proven Technology to Meet European Energy Demands N. Haspel Westinghouse Electric Germany GmbH, Dudenstraße 6, 68167
More informationHeavy Component Replacement in Nuclear Power Plants
Heavy Component Replacement in Nuclear Power Plants Steve Sills, Vice President Business Development, SGT Darren Wood, Manager Component Replacements, AREVA Purpose and Process Goal Recent successes and
More informationOE Supply-Chain in Nuclear Dr. Boris Gehring March 2017
OE Supply-Chain in Nuclear Dr. Boris Gehring March 2017 2015-02-12 It should not finally look like this! Owners Engineers and Supply-Chain services In NPP New build, OE and SCS will help to keep: -Time-line
More informationUKEPR Issue 04
Title: PCSR Sub-chapter 9.2 Water Systems Total number of pages: 65 Page No.: I / IV Chapter Pilot: M. LACHAISE Name/Initials Date 23-11-2012 Approved for EDF by: A. MARECHAL Approved for AREVA by: G.
More informationPlant Life Management in Transition from Operation to Decommissioning of Nuclear Power Plants. National experience, Finland.
Plant Life Management in Transition from Operation to Decommissioning of Nuclear Power Plants. National experience, Finland. Jari Tuunanen, 30 Aug.2016 Contents Background Status of decommissioning plans
More informationANTICIPATED ANALYSIS OF FLAMANVILLE 3 EPR OPERATING LICENSE - STATUS AND INSIGHTS FROM LEVEL 1 PSA REVIEW
ANTICIPATED ANALYSIS OF FLAMANVILLE 3 EPR OPERATING LICENSE - STATUS AND INSIGHTS FROM LEVEL 1 PSA REVIEW Gabriel Georgescu, Patricia Dupuy and Francois Corenwinder Institute for Radiological Protection
More informationModule 05 WWER/ VVER (Russian designed Pressurized Water Reactors)
Module 05 WWER/ VVER (Russian designed Pressurized Water Reactors) 1.3.2016 Prof.Dr. Böck Technical University Vienna Atominstitut Stadionallee 2, 1020 Vienna, Austria ph: ++43-1-58801 141368 boeck@ati.ac.at
More informationWhat Nuclear Reactor Companies Need
September 6, 2017 What Nuclear Reactor Companies Need Scott Bailey Vice President, Supply Chain NuScale Nonproprietary Copyright 2017 NuScale Power, LLC Acknowledgement & Disclaimer This material is based
More informationVerification of the MELCOR Code Against SCDAP/RELAP5 for Severe Accident Analysis
Verification of the Code Against SCDAP/RELAP5 for Severe Accident Analysis Jennifer Johnson COLBERT 1* and Karen VIEROW 2 1 School of Nuclear Engineering, Purdue University, West Lafayette, Indiana 47907-2017,
More informationNUCLEAR Untitled /7/11 12:29 PM
NUCLEAR Untitled-16 1 IMI NUCLEAR - A POWERFUL COMBINATION TRUST IMI Nuclear brings together a powerful combination of brands you know and trust. In fact, over half of the nuclear power plants worldwide
More informationRESULTS OF THE GRADUAL UPGRADING AT BOHUNICE WWER - 440/230 NPP
RESULTS OF THE GRADUAL UPGRADING AT BOHUNICE WWER - 440/230 NPP P. Krupa Ingeneer, e-mail: Krupa_Peter@ebo.seas.sk Bohunice NPPs Introduction The centre of upgrading activities in VVER NPP is clearly in
More informationFrom the Safety Approach of a Nuclear Power Plant, to the Manufacturing and Welding of Mechanical Components in line with RCC-M Code
From the Safety Approach of a Nuclear Power Plant, to the Manufacturing and Welding of Mechanical Components in line with RCC-M Code Philippe Malouines AREVA RCC-M Sub-Committee Chairman Presented by Marcello
More informationNSSS Design (Ex: PWR) Reactor Coolant System (RCS)
NSSS Design (Ex: PWR) Reactor Coolant System (RCS) Purpose: Remove energy from core Transport energy to S/G to convert to steam of desired pressure (and temperature if superheated) and moisture content
More informationWM2014 Conference, March 2 6, 2014, Phoenix, Arizona, USA
Reactor D&D: AREVA French and German Latest Experiences - 14458 (1) Stephan Krüger, AREVA GmbH, Kaiserleistr. 29, 63067 Offenbach, Germany; stephan.krueger@areva.com (2) Xavier de Brimont, AREVA NC, 1
More informationNPP Simulators Workshop for Education - Passive PWR NPP & Simulator Overview
NPP Simulators Workshop for Education - Passive PWR NPP & Simulator Overview Wilson Lam (wilson@cti-simulation.com) CTI Simulation International Corp. www.cti-simulation.com Sponsored by IAEA Modified
More informationQUALITY AUDIT AND QUALITY IMPROVEMENT PLAN at AREVA NP Le Creusot forging facility. London - September 12 th, 2017
QUALITY AUDIT AND QUALITY IMPROVEMENT PLAN at AREVA NP Le Creusot forging facility London - September 12 th, 2017 RPV Shell Core plate AREVA NP Creusot Forge RCP casing Monobloc closure head 220 people
More informationSafety Implication for Gen-IV SFR based on the Lesson Learned from the Fukushima Dai-ichi NPPs Accident. Ryodai NAKAI Japan Atomic Energy Agency
Safety Implication for Gen-IV SFR based on the Lesson Learned from the Fukushima Dai-ichi NPPs Accident Ryodai NAKAI Japan Atomic Energy Agency Contents Introduction Japanese Government Report to the IAEA
More informationImplementation of SQUG Experience-Based Methods for Seismic Qualification of Equipment
Implementation of SQUG Experience-Based Methods for Seismic Qualification of Equipment Presentation for: 2006 MCEER Annual Meeting June 29 ~ 30, 2006 Prepared by: Steve Eder & John Dizon Facility Risk
More informationSafety enhancement of NPPs in China after Fukushima Accident
Safety enhancement of NPPs in China after Fukushima Accident CHAI Guohan 29 June 2015, Brussels National Nuclear Safety Administration, P. R. China Current Development of Nuclear Power Mid of year 2015
More informationLessons learned from Angra 1 & Angra 2 NPP s Outages
Lessons learned from Angra 1 & Angra 2 NPP s Outages DO Diretoria de Operação SM.O Superintendência de Manutenção Preparado por: Luciano Junqueira Calixto Email: lucical@eletronuclear.gov.br Angra 1: Angra
More informationAPPROACH TO PRACTICAL ELIMINATION IN FINLAND
M-L. JÄRVINEN et al. APPROACH TO PRACTICAL ELIMINATION IN FINLAND M-L. JÄRVINEN Radiation and Nuclear Safety Authority (STUK) Helsinki, Finland Email: marja-leena.jarvinen@stuk.fi N. Lahtinen Radiation
More informationExample Pressurized Water Reactor Defense-in-Depth Measures For GSI-191, PWR Sump Performance
Example Pressurized Water Reactor Defense-in-Depth Measures For GSI-191, PWR Sump Performance ATTACHMENT Introduction This paper describes a range of defense-in-depth measures that either currently exist
More informationUK ABWR Generic Design Assessment Generic PCSR Chapter 8 : Structural Integrity
Form10/00 Document ID Document Number Revision Number : : : GA91-9101-0101-08000 RE-GD-2043 C Generic Design Assessment Generic PCSR Chapter 8 : Structural Integrity Hitachi-GE Nuclear Energy, Ltd. Form01/03
More informationRegulatory oversight of nuclear safety in Finland
STUK-B 214 / JUNE 2017 B Regulatory oversight of nuclear safety in Finland Annual report 2016 Erja Kainulainen (ed.) Säteilyturvakeskus Strålsäkerhetscentralen Radiation and Nuclear Safety Authority STUK-B
More informationBest practices for preparing vessel internals segmentation projects
Best practices for preparing vessel internals segmentation projects Joseph BOUCAU a*, Per SEGERUD b, Moisés SANCHEZ c a Westinghouse Electric Company, 43 rue de l Industrie, 1400 Nivelles, Belgium b Westinghouse
More informationReview of Generation III Reactors
Review of Generation III Reactors Dr. Helmut Hirsch Scientific Consultant for Nuclear Safety Neustadt, Germany 1 Status of Nuclear Power Today (I) Future of nuclear power uncertain. No significant growth
More informationAn Overview of the ACR Design
An Overview of the ACR Design By Stephen Yu, Director, ACR Development Project Presented to US Nuclear Regulatory Commission Office of Nuclear Reactor Regulation September 25, 2002 ACR Design The evolutionary
More informationAP1000 European 15. Accident Analysis Design Control Document
15.2 Decrease in Heat Removal by the Secondary System A number of transients and accidents that could result in a reduction of the capacity of the secondary system to remove heat generated in the reactor
More informationRegulatory Actions and Follow up Measures against Fukushima Accident in Korea
Int Conference on Effective Nuclear Regulatory Systems, April 9, 2013, Canada Regulatory Actions and Follow up Measures against Fukushima Accident in Korea Seon Ho SONG* Korea Institute of Nuclear Safety
More informationFlamanville 3 EPR Safety assessment and on-site inspections
Corine PIEDAGNEL - François TARALLO Bernard MONNOT Institut de Radioprotection et de Sûreté Nucléaire Flamanville 3 EPR Safety assessment and on-site inspections Flamanville 3 EPR Safety assessment and
More informationWM2010 Conference, March 7-11, 2010, Phoenix, AZ MODULAR CONSTRUCTION FOR EVENTUAL DECONSTRUCTION AND DECOMMISSIONING
MODULAR CONSTRUCTION FOR EVENTUAL DECONSTRUCTION AND DECOMMISSIONING - 10300 1 ABSTRACT Dr. Jas S. Devgun, Ph.D., CHMM Manager Nuclear Power Technologies Sargent & Lundy LLC 55 E. Monroe St Chicago, IL
More informationCONTAINMENT STRUCTURES
CONTAINMENT STRUCTURES M. Ragheb 11/16/2017 INTRODUCTION A misconception about nuclear power plants containment structures is that their massive concrete construction is a protection against the release
More informationGenIII/III+ Nuclear Reactors
OL1&2 GenII GenIII OL3 TVO s Olkiluoto Nuclear Power Plant in Finland GenIII/III+ Nuclear Reactors RESEARCH NEEDES AND CHALLENGES FISA 2009, Prague Contents What are the GenIII features Evolutionary development
More informationChallenges & Successes of Candu Energy (former AECL) in Nuclear Construction: Case Study of China and Romania
IAEA Workshop on Construction Technologies for Nuclear Power Plants: A Comprehensive Approach Paris, France 12 16 December, 2011 Challenges & Successes of Candu Energy (former AECL) in Nuclear Construction:
More informationSmall Modular Reactors: A Call for Action
Small Modular Reactors: A Call for Action Overview of Five SMR Designs by Dr. Regis A. Matzie Executive Consultant Adapted May 2015 for the Hoover Institution's Reinventing Nuclear Power project from a
More informationNational Status on Life Management of NPPs in Finland Meeting of the IAEA TWG-LMNPP February th 2017 Vienna, Jyrki Kohopää
National Status on Life Management of NPPs in Finland 2017 Meeting of the IAEA TWG-LMNPP February 22-24 th 2017 Vienna, Jyrki Kohopää NUCLEAR POWER IN FINLAND Teollisuuden Voima Oyj, Olkiluoto: OL1/2:
More informationENSA ENWESA SERVICES INDEX
ENSA ENWESA SERVICES INDEX 1. ENGINEERING, DESIGN AND TECHNOLOGY SERVICES (Ensa / ENWESA) Ensa has extensive experience designing nuclear components and pressure vessels since 1973 according to international
More informationENSREG ACTION PLAN FACT FINDING SITE VISITS. France s Report. September 2012
- ENSREG ACTION PLAN FACT FINDING SITE VISITS France s Report September 2012 1 1 INTRODUCTION AND BRIEF DESCRIPTION OF PLANTS VISITED... 3 2 SUMMARY OF OBSERVATIONS... 5 3 2.1 Description of measures already
More informationEDF Training in Support of a New Nuclear Project
EDF Training in Support of a New Nuclear Project Jean-Luc His EDF Engineering and Generation Training Unit IAEA TM on Human Resources Roadmaps and Capacity Building for New and Expanding Nuclear Power
More informationDEVELOPMENT AND APPLICATION OF PROBABILISTIC SAFETY ASSESSMENT PSA IN DAYA BAY NUCLEAR POWER STATION
18th International Conference on Structural Mechanics in Reactor Technology (SMiRT 18) Beijing, China, August 7-12, 2005 SMiRT18-A01-2 DEVELOPMENT AND APPLICATION OF PROBABILISTIC SAFETY ASSESSMENT PSA
More informationDESIGN, SAFETY FEATURES & PROGRESS OF HTR-PM. Yujie DONG INET, Tsinghua University, China January 24, 2018
DESIGN, SAFETY FEATURES & PROGRESS OF HTR-PM Yujie DONG INET, Tsinghua University, China January 24, 2018 Meet the Presenter Dr. Dong is a Professor in Nuclear Engineering at the Tsinghua University, Beijing,
More informationDesign of Traditional and Advanced CANDU Plants. Artur J. Faya Systems Engineering Division November 2003
Design of Traditional and Advanced CANDU Plants Artur J. Faya Systems Engineering Division November 2003 Overview Canadian Plants The CANDU Reactor CANDU 600 and ACR-700 Nuclear Steam Supply Systems Fuel
More information2/24/2012. Generation mpower LLC. Major Complexity. Design & Manufacturing Complexities in SMR Technology
2/2/2012 Design & Manufacturing Complexities in SMR Technology Regulatory Information Conference March 1, 2012 Ali Azad President & CEO Generation mpower LLC Generation mpower LLC Formal alliance between
More informationCGN's Nuclear Energy Capabilities
Business Overview NPP Construction Achievements NPP Operating Performance Overseas Business Core Nuclear Power Technologies CGN's Nuclear Energy Capabilities Nuclear Project Construction Capabilities Operations
More informationV.C. Summer Nuclear Station Units 2 & 3
V.C. Summer Nuclear Station Units 2 & 3 Quarterly Report to the South Carolina Office of Regulatory Staff Submitted by South Carolina Electric & Gas Company Pursuant to Public Service Commission Order
More informationNUCLEAR. Nuclear Reactor Pressure Vessel Seals
NUCLEAR Nuclear Reactor Pressure Vessel Seals SEALING CONCEPT Technetics Group is the world s leading manufacturer of Nuclear Reactor Pressure Vessel (RPV) Closure Head Seals. In addition, Technetics Group
More informationOlli Vilkamo; Kirsi Alm-Lytz Radiation and Nuclear Safety Authority, STUK. Radiation Safety in New Build
Olli Vilkamo; Kirsi Alm-Lytz Radiation and Nuclear Safety Authority, STUK Radiation Safety in New Build STUK - Radiation and Nuclear Safety Authority Mission: Protecting people, society, environment, and
More informationRevenue and data for the first nine months of 2008
Paris, October 23, 2008 Revenue and data for the first nine months of 2008 9-month revenue for 2008 up sharply to 9.103B, for a +12.9% increase (+13.9% like-for-like 1 ) The group cleared revenue of 9.1
More informationALSTOM Atomenergomash LLC developing ARABELLE based Turbine Islands for newly constructed and retrofitted nuclear power plants.
ALSTOM Atomenergomash LLC developing ARABELLE based Turbine Islands for newly constructed and retrofitted nuclear power plants. 26.10.2011 A.M. Tsvetkov, ALSTOM Atomenergomash LLC ALSTOM Atomenergomash
More informationEPR FLAMANVILLE 3 Site Management *** Atoms for the future*** - 14th October Antoine Ménager, Site Manager
EPR FLAMANVILLE 3 Site Management *** Atoms for the future*** - 14th October 2014 - Antoine Ménager, Site Manager EDF Group NUCLEAR GENERATION: LEADERSHIP CONFIRMED Over 487 TWh generated, including :
More informationELETRONUCLEAR s Response to the Fukushima Dai-ichi Nuclear Accident
s Response to the Fukushima Dai-ichi Nuclear Accident Rio de Janeiro, July 3 rd, 2012 Paulo Vieira First Actions Taken by Eletronuclear Establishment of a Corporate Working group Follow up of the event,
More informationTECHNICAL CENTER Focus on Technology
TECHNICAL CENTER Focus on Technology AREVA s worldwide Technical Center Technical Center serves as the bridge from basic research to industrial application with main focus on basic technologies organized
More informationThermal Hydraulic Simulations of the Angra 2 PWR
Thermal Hydraulic Simulations of the Angra 2 PWR Javier González-Mantecón, Antonella Lombardi Costa, Maria Auxiliadora Fortini Veloso, Claubia Pereira, Patrícia Amélia de Lima Reis, Adolfo Romero Hamers,
More informationNuclear Power A Journey of Continuous Improvement
Nuclear Power A Journey of Continuous Improvement Westinghouse Non Proprietary Class 3 Our Place in Nuclear History Innovation 1886 and forever Implementation & Improvement 1957 through Today Renaissance
More informationEnhancement of Nuclear Safety
Enhancement of Nuclear Safety Soon Heung Chang Handong Global University May 6, 2015 Contents 1 2 3 4 Importance of Energy Fundamentals of Nuclear Safety How to Enhance Nuclear Safety Closing Remarks 2
More information-30- QUEBEC GENTILLY 2 NUCLEAR POWER STATION' J.A. Labbé. Hydro Quebec
-30- QUEBEC GENTILLY 2 NUCLEAR POWER STATION' by J.A. Labbé Hydro Quebec INTRODUCTION Since our previous progress report, delivered at last year's conference in Montreal, work in the nuclear energy field
More informationCLASSIFICATION OF SYSTEMS, STRUCTURES AND COMPONENTS OF A NUCLEAR FACILITY
CLASSIFICATION OF SYSTEMS, STRUCTURES AND COMPONENTS OF A NUCLEAR FACILITY 1 Introduction 3 2 Scope of application 3 3 Classification requirements 3 3.1 Principles of safety classification 3 3.2 Classification
More informationAP1000: The PWR Revisited
AP1000: The PWR Revisited IAEA International Conference on Opportunities and Challenges for Water Cooled Reactors in the 21st Century aolo Gaio estinghouse Electric Company tober 27, 2009 1 Background
More informationReactor Technology: Materials, Fuel and Safety. Dr. Tony Williams
Reactor Technology: Materials, Fuel and Safety Dr. Tony Williams Course Structure Unit 1: Reactor materials Unit 2. Reactor types Unit 3: Health physics, Dosimetry Unit 4: Reactor safety Unit 5: Nuclear
More informationSouth African nuclear industry overview Van Zyl de Villiers R&D Division Necsa
South African nuclear industry overview Van Zyl de Villiers R&D Division Necsa ASME Nuclear Codes and Standards Workshop 7 October 2008 Contents South African energy challenges South African Nuclear Energy
More informationPreparedness at PFBR Kalpakkam to meet the challenges due to Natural events Prabhat Kumar, Project Director, PFBR, Director construction BHAVINI
BHARATIYA NABHIKIYA VIDYUT NIGAM LIMITED (A Government of India Enterprise) Preparedness at PFBR Kalpakkam to meet the challenges due to Natural events Prabhat Kumar, Project Director, PFBR, Director construction
More information