PART A - INSPECTION INSTRUCTIONS TO VENDORS

Size: px
Start display at page:

Download "PART A - INSPECTION INSTRUCTIONS TO VENDORS"

Transcription

1 PART A - INSPECTION INSTRUCTIONS TO VENDORS 1. GENERAL 1.1 This instruction covers the general requirements for shop inspection and testing of equipment and materials (GOODS) to be supplied by the Contractor. Contractor shall be responsible for inclusion of inspection requirements herein and requirements of applicable individual specification as contractual requirements of Sub vendors. 1.2 In addition to the general requirements contained in this specification, the Contractor shall be responsible for all other inspection requirements as defined by documents included in or referenced by the Purchase Order, Requisition, Specification or Data sheets applicable to the Order. 1.3 GOODS for which no individual specification is issued can be inspected and tested in accordance with this instruction and Contractor's standards approved by the Purchaser 1.4 All deviations from this instruction and related inspection specifications shall be previously proposed to the Purchaser in writing and shall be approved by the Purchaser before placement of the order. 1.5 The word "specification(s)" used in this instruction and related inspection specifications often collectively means all technical specifications, drawings, and other technical documents supplied b^ the Purchaser and also specifications and technical documents as may be agreed and/or made by the Contractor and the Purchaser. 2. DEFINITIONS Words used in this instruction and related inspection specifications shall have the following meanings, unless the context requires otherwise : Test Report: Means the individual record or certificate for respective test or inspection. QC Dossier: means the compiled document package consisting of prescribed Purchaser's cover sheet for QC Dossier, Contractor's cover sheet, table of contents, Test Reports, and other necessary documents. Purchaser: means Gujarat Narmada Valley Fertilizer Company limited Purchaser's Inspector: Means inspector(s) dispatched by the Purchaser or inspector(s) of inspection agencies designated by the Purchaser. Owner s Inspector: Means one or combination of inspector(s) dispatched by the Owner and inspector(s) of the inspection agency (agencies) designated by the Owner. Contractor: Sub vendor: Means a supplier or manufacturer of GOODS. Means an organization, company or individual under contract to Contractor for the supply of material, equipment sub-assemblies or services necessary to the completion of Contractor s scope of work. 1

2 3. CODES AND STANDARDS All codes and standards for the inspection of GOODS shall be in accordance with those specified in section 6.1 of the ITB. 4. CLARIFICATION OF CONFLICTS If there is any conflict between the related specifications, codes and standards, the Contractor shall immediately consult with the Purchaser in writing for clarification. Failure of Contractor to seek, in writing, clarification of conflicting requirements prior to acceptance of the Purchase Order shall constitute obligation of Contractor to comply with all of the conflicting requirements at no additional cost, even to the extent that rework and/or retesting may be required. 5. RESPONSIBILITY FOR QUALITY 5.1 Inspection or non-inspection by the Purchaser shall not relieve the Contractor of its obligation for quality control activities and guarantees for the workmanship or performance of the GOODS. 5.2 The Contractor shall be responsible for inspection and testing of the GOODS, including parts and materials supplied by Sub vendors. 5.3 The Contractor shall carry out all inspections and testing specified in the purchase documents. 5.4 All Contractor's fabrication documents, including, but not limited to, welding, nondestructive examination, heat treatment, and major repair procedures, specified in the requisition shall be reviewed and approved by the Purchaser prior to start of fabrication. 6. PRE-INSPECTION MEETING The Purchaser may require holding a pre-inspection meeting(s) at Contractor and/or Sub vendors to resolve questions concerning the compliance with the purchase documents, specifically inspection requirements and related specifications. Final inspection items shall also be defined at the meeting. Contractor shall arrange to provide the following documents for this meeting; 1) Copy (Copies) of Purchaser's requisitions, drawings, specifications of the latest revision and other documents necessary for discussion at the meeting. 2) List of missing documents such as specifications referenced in the Purchaser's requisition, but not received by the Contractor. 3) Questionnaire about Purchaser's documents. 4) Contractor's drawings, diagrams, and schedules. 5) Fabrication procedure 6) Inspection procedure including NDE procedure 7) Written welding documents 8) Major repair procedure 9) Sample of inspection record(s) for a similar jab previously done by the Contractor 10) Other documents considered necessary Contractor shall also arrange for meeting attendance by all Contractor representatives necessary to achieve resolution of technical questions, schedules, 2

3 and inspection requirements. 7. WITNESS INSPECTION NOTICE 7.1 The Contractor shall notify the Purchaser of readiness for witness inspection in writing at least 4 calendar weeks prior to the date when the GOODS will be ready for inspection. The Contractor shall also inform the Purchaser of the definite witness inspection date and time at least 10 working days in advance of the date of the witness inspection. 7.2 Verbal inspection notice is not acceptable. Notice shall be sent to Purchaser by Facsimile (telefax) OR . The inspection notice shall also include the map or the necessary information to reach Contractor's shop, if such information was not given in advance. 7.3 Work shall not proceed beyond "Inspection Hold Points" established by contract correspondence, Specifications or Pre-Inspection Meeting without written authorization of Purchaser. 8. WITNESS INSPECTION Purchaser's and/or Owner's Inspector shall have free entry to those parts or areas of manufacturing shops of the Contractor or its sub vendors where and when work, testing or inspection on the GOODS is being performed. Access shall not be limited to "normal office hours" and escort shall not be required except when agreed for reasons of safety or proprietary work. Where escort restriction is agreed, Contractor and/or Sub vendor shall make escort available during all hours of shop fabrication, testing or inspection. 8.2 Purchaser's and Owner's Inspector reserve the right to monitor, audit, and visit plants or other inspection locations with or without prior notice to the Contractor or Sub vendor. 8.3 For inspection items designated for witness of Purchaser's and/or Owner's inspector, but not designated as inspection hold points, Contractor may, at Contractor's cost and risk, elect to proceed with fabrication after completion of Contractor's in-house inspection, provided that the witness inspection is repeated for witness of the Purchaser's and/or Owner's inspector at time of next inspection visit. 8.4 The Contractor, when so requested, shall provide one additional copy of the latest approved drawings for the use of Owner's Inspector prior to the start of inspection. 8.5 The Contractor shall furnish Purchaser's and/or Owner's Inspector with shop test data, mill certificates, and other materials to verify that each GOODS meets the requirements of the applicable specifications. Free copy, telex, facsimile (tele - fax), and telephone service by the Contractor shall be made available to Purchaser's and/or Owner's Inspector. 8.6 Safety equipment and inspection tools as necessary to safely and expeditiously demonstrate compliance with applicable specifications, as well as assistance from 3

4 Contractor's or Sub vendor's inspection representative shall be made available to Contractor's and/or Owner's Inspectors. 8.7 When requested by the Purchaser, the Contractor shall prepare the required number of QC Dossier, its part, or other documents for Owner's Inspector by the requested date. 8.8 Nothing herein shall preclude Contractor's inspection or contracts representative from accompanying Contractor's and/or Owner's Inspector to Sub vendor locations for inspection purpose. 9. RELEASE FOR SHIPMENT 9.1 Purchaser's Inspector will issue "Inspection Release Note" to the Contractor shortly after the final inspection and review of QC Dossier prepared by the Contractor. 9.2 The Contractor shall not ship any GOODS without securing the Inspection Release Note. 9.3 When the Contractor is permitted to ship on condition to perform the additional work at the work site, the Contractor shall bear all costs and expenses incurred by such work. (1) Special provision for storage or proper care (2) Repair and/or Inspection 10. DOCUMENTATION Incomplete, inaccurate or illegible documentation shall be the cause for rejection of GOODS until such time as satisfactory rectification has been effected Documents to be Submitted All Contractor's inspection and test procedures, including, but not limited to, welding, nondestructive examination, heat treatment, definition of major repairs, and major repair procedures, required for submittal in the requisition shall be reviewed and approved by the Purchaser prior to start of fabrication or prior to use, whichever is the earlier. (1) The Contractor shall submit to the Purchaser 5 white copies for documents such as Contractor's shop inspection and test procedure and welding procedure specification as required. Unless otherwise specified, all these documents shall be prepared in English. The Contractor will be requested to submit these documents prior to fabrication. (2) The Purchaser will need a maximum of fifteen (15) working days, excluding mailing time, from the receipt of the Contractor document to study and accept or give alternative decisions Submittal of QC Dossier (1) The Contractor shall prepare QC Dossier in English and submit 5 white copies to the Purchaser within seven (7) working days after completion of the final inspection of the GOODS. (2) For details of QC Dossier preparation, refer to section 11 of this specification. 4

5 11. PREPARATION OF QC DOSSIER 11.1 Unit of Preparation (1) The QC Dossier of individual pressure vessels, heat exchangers, tanks, and towers shall be prepared for each equipment. (2) The QC Dossier of unit or packaged items such as boiler units, compressor units, etc. shall be prepared for each unit or package including subsidiary equipment and accessories. (3) The QC Dossier of materials, pumps, valves, fittings, instruments, and electrical equipment, which are not included in (1) and (2) above, may be prepared for each order. In case of partial shipment, the QC Dossier may be divided for each shipment Forms To prepare the QC Dossier, the Contractor may use its standard forms Compilation (1) As far as possible, A4 (210mm X 297mm) or 8-1/2 in. x 11 in. size paper shall be used for the test report sheet. For larger sizes, A3 ( 297 mm X 420 mm) may be used, folded to A4 size. When thickness of the QC Dossier is too thick to compile in one package, it can be divided into two or more packages. (2) Construction of QC Dossier As far as possible, Test Reports in the QC Dossier shall be in the following order : (a) List of material certificates with part Nos. and part names (b) Material certificates (c) Nondestructive examination records (d) Visual inspection certificates (e) Dimensional inspection records (f) PWHT chart and thermocouple location map (g) Hydrostatic test records, Leak test records (h) Running test records, Performance test records, Operation test records (i) Nameplate rubbing (j) Cross Sectional Drawings / GA Drawings / Fabrication Drawings, Tolerances for precision parts, etc. (j ) Operation & Maintenance Instructions for machinery Signature Requirements (1) Each document in QC Dossier shall have the verification signature by the Contractor. (2) Signature by Purchaser's Inspector When witness inspection or review of documents is done by Purchaser's Inspector, each respective sheet of the QC Dossier shall bear either witness signature or review signature of Purchaser's Inspector. (3) Each test report sheet shall have the following data or information in addition to signatures : Test data and/or results Date of test Identification of components tested 5

6 11.5 SOFT COPIES Apart from Hard Copies, Soft Copies as per following descriptions shall be submitted by the Contractor: No. Of Copies: 2 Sets. Medium: CD R of reputed make viz. SONY / SAMSUNG / MOSER BAER Formats: All Drawings shall be in AUTO CAD All reports shall be in Editable Format Measuring Units (1) In principle, measuring units on QC Dossier documents shall be metric unit except English unit may be applied for pipe, fitting, flange, flange bolts/nuts, and rating. (2) Units for mill certificates of raw materials may be in accordance with specified codes and standards applicable to such materials Retention of Test Report Contractor shall retain original sheets of Test Report for at least 5 years after shipment of GOODS. 6

7 PART B - INSPECTION PHILOSOPHY FOR PRESSURE VESSELS AND HEAT EXCHANGERS 1. CODES AND STANDARDS The requirements in the following codes and standards also form a part of the requirements of this specification. (1) ASME Code, Section II (2) ASME Code, Section VIII, Division 1 (3) ASME Code, Section V (4) ASME Code, Section IX (5) TEMA (6) Codes, standards & regulations listed at Section 6.1 of the ITB. (7) Other codes, standards and regulations specified in each individual specification 2. Main materials shall be verified to conform to the specified materials by mill test reports. The mill test reports shall include chemical analysis of each lot or heat of material and a statement that it has been tested in accordance with and meets the physical and mechanical requirements of the applicable specification. 3. WITNESS INSPECTION 3.1 Pressure vessels for which ASME official code stamps (U) is required shall be inspected by the ASME Authorized Inspector in accordance with the requirements of ASME Code, Section VIII, Division In addition, all pressure vessels shall be subject to inspection, at the option of the Purchaser or representatives of the Purchaser at all reasonable times and places before, during and/or after fabrication. 3.3 Witness test and inspection agenda shall be in accordance with Table The Owner has the right of access to the Contractor's or Sub vendor's shop for inspection matters. If the Contractor received any instruction from the Owner's Inspector, the Contractor should report to the Purchaser before making any changes. 4. PRINCIPAL REQUIREMENTS All inspection and tests shall conform to the requirements of ASME Code, Section VIII, Division ADDITIONAL REQUIREMENTS TO ASME CODE The following inspections shall be carried out in addition to, but not be limited to, the requirements of ASME Codes. 5.1 Material 1) The following materials for the pressure parts shall be inspected by ultrasonic examination method in accordance with SA-578 Level B of ASME Code, Section II. Test results shall be described in mill test reports. (a) Carbon steel plates of 50 mm (2 inches) thick and over 7

8 (b) (c) Low-alloy steel plates of 25 mm (1 inch) thick and over Low temperature service carbon steel plates of 19 mm (3/4 inch) thick and over Pressure Parts having thickness from 16 mm to 50 mm shall be ultrasonically tested as per SA ) For heat treated materials, test specimens shall be prepared from actual vessel material which has been subjected to an equivalent total thermal treatment as the vessel material in the final fabricated condition. 3) Chemical analysis of weld filler metal shall be certified by the weld filler metal supplier. 5.2 Radiographic Examination 1) In addition to radiographic examination required by the ASME Code or design drawings, the Purchaser reserves the right to take additional exposures as desired to check weld quality. 2) When spot radiography is specified, the radiographic examination shall be made as follows: - For cylindrical vessels, one spot radiograph shall be taken in each circumferential joint and in each longitudinal joint between adjacent circumferential joints at locations designated by the Purchaser's Inspector. - All T joints shall be radiographed. When 100 % or Full Radiography is specified, radiography shall be taken for 100 % of the Butt Joints, including those of Nozzles of all sizes. 3) If any part of a shell or head seam will be covered by a nozzle reinforcing pad or other structural overlay, that portion of the seam shall be spot radio graphed before it is covered. 5.3 Magnetic Particle Examination 1) Magnetic particle examination shall be carried out for all welded joints of low-alloy steel and lifting lugs in accordance with Appendix 6 of ASME Code, Section VIII, Division 1. 2) For 100% radio graphed vessels, all welded joints between nozzles and vessel shell and between nozzles and flanges shall be examined by the magnetic particle method prior to the installation of any reinforcing pads. This examination shall include: - The back side of the root area after the root pass has been back gouged or ground in preparation for the welding required to complete the joint. - Both sides of the complete weld. 3) Final nozzle welds shall be examined by the magnetic particle method after post weld heat treatment, unless these welds are inaccessible. 4) When magnetic particle examination is specified, the DC prod method shall be used prior to final post weld heat treatment, and the AC yoke or coil method after final post weld heat treatment. 8

9 5) Nonmagnetic materials shall be examined by the liquid penetrant method in accordance with Appendix 8 of ASME Code, Section VIII, Division 1 for the same weld joints as defined in above paragraphs, instead of magnetic particle examination. 6) For materials having either: a) a minimum specified tensile strength of 551 MPa (80,000 psi) or greater, or b) a total nominal alloy content greater than 4 percent, or c) a thickness of 38 mm (1-1/2 inches) or greater, All attachment welds and all areas where fit up bars, etc. are temporarily attached shall be examined by magnetic particle method, before final post weld heat treatment (PWHT), and after hydrostatic testing. Austenitic steels and nickel steels are exceptions. 5.4 All forgings except for flanges as per ANSI shall be UT tested as per ASTM A 388 for the thickness greater than 100 mm and shall be procured in normalized/annealed condition. Acceptance standards shall be as per AM of ASME Section VIII Div. 2. In case any defect is found, no repair by welding shall be allowed. 5.5 All forgings including nozzle flanges shall be examined for surface defects by MP/PT testing after machining as per ASTM A Tube sheet and Girth flanges shall of forged quality & ultrasonic tested not have any segmental weld joint. 5.7 All heat exchanger tubes shall be 100% eddy current tested in addition to hydro testing 5.8 Hydrostatic Tests 1) Vessels fabricated in shop shall be subject to hydrostatic test in horizontal position in the fabricator's shop. Water temperature for hydrostatic test shall not be lower than 15 C during the test. Where the ductile-to-brittle transition temperature of steel is known to be, or suspected to be 4 C or higher, it is the fabricator's responsibility to raise the temperature of the water to at least 15 C higher than the transition temperature. Vessels fabricated from solid, clad or lined austenitic stainless steel shall be tested with potable water containing minimum concentration of chloride and not more than 50 ppm chloride. Test gaskets for nozzles connecting to piping or instruments may be of asbestos or other materials. Test gaskets for other than the above shall be of same specification as service gaskets. Such gaskets used for hydrostatic tests shall be shipped in place. In addition, two sets of service gaskets (one for replacing at site and another for construction spare) shall be shipped loose together with the equipment. 2) The test pressure shall be held for one hour or one hour per inch of vessel thickness, whichever longer. 9

10 3) When austenitic stainless steel materials will be exposed to water during hydro testing or water washing, the following shall apply: a) Only treated water or freshwater with less than 50 ppm total chlorides and ph greater than 7 shall be used. b) The water shall be drained immediately after testing or washing and the vessel shall be dried by blowing with dry air or dry nitrogen. 4) Heat Exchanger Testing a) Hydrostatic test methods and sequence shall be established before fabrication and submitted for the approval of the Purchaser. b) Heat exchangers shall be alternately hydro tested on each side with no water in the other side being exposed. c) Girth flange joints taken apart after hydrostatic test shall be reassembled with unused gaskets and retested for tightness by air at the design pressure. 5.9 Leak Tests 1) When specified, pressure vessels shall be leak tested at the air pressure specified on the individual specification and/or drawing. 2) All reinforcing plates shall be tested at air pressure of 1 to 1.4 Kg/cm^ (15 to 20 psig) unless otherwise specified. 3) All tube to tubesheet weld joints of heat exchangers shall be leak tested at the air & with pressure specified on the drawings Impact Tests 1) Materials of each pressure-containing component, welding procedure qualification test plates and production impact test plates shall be impact tested on the basis of individual material specification (class of steel), thickness, and design temperature specified for each item in the individual specification in accordance with ASME Code, Section VIII, Division 1. 2) Shells, heads, nozzles, man ways, reinforcing pads, flanges, skirts, tube sheets, flat cover plates, support lugs, etc., shall be treated as separate components. 3) Results of impact tests shall be incorporated into the vessel records and submitted to the Purchaser. The data shall include specimen size, direction in which material being tested (longitudinal or transverse), test temperature, breaking energy of each specimen, and average values of breaking energy for a set of three specimens Hardness Tests 1) If post weld heat treatment is required, Brinell hardness tests of the base metal, weld metal and heat affected zone (HAZ) shall be made for weld seams of pressure vessels of P-l, P-3, P-4, P-5, P-6, P-7, p-1oa and P-10B materials listed in ASME Code Section IX. The Brinell hardness shall not exceed the limits set in Table

11 Table 5.7 Material P-Number Maximum Brinell Hardness P-l 200 P-3, P P-5, P P P-10a, P-10B 225 2) When hardness test is required by Paragraph 1) above, the detailed requirements for the hardness test shall be in accordance with the following procedure. a) The hardness testing shall be conducted following the completion of all post weld heat treatments. b) The surface hardness test shall be made with a Brinell testing machine or a portable hardness tester such as a Telebrineller using a 10 mm ball. c) The hardness tests for the HAZ shall be made with the ball centered in the HAZ (representing a composite of weld metal, HAZ, and base metal). d) Surface preparation shall consist of filing, grinding, machining, or polishing with abrasive material the areas to be tested so that the edge of the impression shall be clearly defined to permit the measurement of the diameter to mm. Care should be taken to avoid overheating or cold working the surface. Adjacent reading shall be at least 2-1/2 diameter apart, edge to edge. e) Should surface preparation or instrument applicable be difficult, a mockup with identical condition shall be used. f) Where hardness values are determined to be in excess of the allowable limit, sufficient additional reading shall be taken to fully delineate the extent of the deficiency. g) Verification of hardness value shall be performed on the following points. - Each cylinder circumferential seam: one hardness test per seam - Each cylinder longitudinal seam: one hardness test per seam - Sphere seams: - One hardness test per seam at weld line intersection - Fillet weld seam tested by mockup: one hardness test per order for each welding process, filler metal, and technique used 5.12 Dimensional Inspection 1) Dimensional tolerance other than specified in ASME Code Section VIII, Division 1 shall be in accordance with the attached drawings in Figure 1. In addition to the above, the dimensional tolerances specified in TEMA shall be applied to heat exchangers. 2) Nozzle flange dimensions shall be within the tolerance of the pertinent standards for flanges. 3) Agitator mounting flanges shall be machined after welding to shell and the flange face shall be parallel with the indicated plane in any direction Welding Procedure Specifications and Procedure Qualification Records 1) Before starting to weld, welding procedure specification (WPS) and procedure 11

12 qualification record (PQR) shall be submitted to the Purchaser for approval. The formats shall be Form QW-482 and QW-483 of ASME Code Section IX or equivalent. 2) PQR on carbon steel and other materials for which hardness limit is specified shall include hardness measurement across the weld metal, HAZ and base metal to assure that the WPS is adequate for producing the allowable hardness. 3) The WPS/PQR shall meet the requirements of ASME Code Section IX. 4) Weld maps shall be attached to WPS and PQR. The maps shall show the traceability of WPS No. to the weld line of each vessel. 5) Weld repair procedures shall be submitted to the Purchaser for approval, before starting of repair work Surface Finishing When surface finishing such as buff finishing and electro polishing is specified, the finishing of each component shall be visually inspected before assembling by comparing with sample pieces accepted in advance by the Purchaser. Three sample pieces shall be submitted for approval. (Sample piece size : 100 mm x 100 mm x 3 or 6 mm thick, or 4 in. x 4 in. x 1/8 or 1/4 in. thick) 5.15 Tubular Heat Exchangers 1) Actual inside diameter of exchanger shells shall be measured completely around three cross sections of the shell. Maximum diameter shall not exceed design diameter by more than 3.2 mm (1/8 inch) as determined by circumferential measurement. 2) Transverse baffle to shell clearances greater than specified in TEMA Table R-4.3 shall not be used. 3) A template consisting of two discs with diameters equal to baffle diameters, rigidly fixed on a shaft and spaced not less than 304 mm (12 inches) apart, shall pass completely through the shell after completion of all welds and post weld heat treatment(pwht). 4) After fabrication and PWHT, the deviation from a plane for tubesheet and girth flange gasket surface, including peripheral and pass partition sections, shall not exceed 0.8 mm, as measured with dial indicators. 5) All matching nozzle of stacked exchangers must be within 3.2 mm (1/8 inch) in any direction. Matching gasket faces including tubesheet surface must be parallel to within 0.8 mm (1/32 inch). 6) All nondestructive examinations for final welds required by the purchaser shall be performed after PWHT, if PWHT is specified. 7) Shell flanges, channel flanges, channel covers, tube sheets and split rings shall have the manufacturer's serial number applied with steel stencils. 8) Seal welds or strength welds between tubes and tube sheets shall be examined by the liquid penetrant method according to Appendix 8 of the ASME Code, Section VIII, Division PNEUMATIC TESTING All reinforcing plates shall be tested at the air pressure not less than 3.4 bar g. Reinforcing plates and other attachments with vent holes on vessels subject to 12

13 post weld heat treatment shall be pneumatically tested before and after post weld heat treatment Sleeve lined nozzles in clad vessels shall be tested at the air pressure not less than 3.4 bar g Strip lined plates shall be tested at the air pressure specified in the data sheets If specified in the data sheets, vessels shall be subject to a leakage test at the air pressure specified in the data sheets after hydrostatic test. 6. DOCUMENT SUBMITTAL The documents prescribed in the Section A above. 6.1 Detailed Inspection and Test Procedure Unless otherwise specified, the Contractor shall submit the Detailed Inspection and Test Procedure for the Purchaser's approval within 12 weeks after the date of purchase order or by 8 weeks in advance of the date of the first inspection, whichever is earlier. The Procedure shall cover at least the following items and shall meet requirements of all inquiry and purchase documents, including related Contractor's and Purchaser's correspondence. 1) Inspection and test agenda 2) Specific test methods including test equipment 3) Acceptance criteria 4) Test report and test certificate to be submitted (See Table 3) 6.2 Welding Procedure Specifications and Procedure Qualification Records Welding procedure specifications including for the applicable equipment and the procedure qualification records shall be prepared in accordance with Paragraph 5.9 of this specification by the manufacturer. WPS/PQR with Weld Map shall be submitted and approved before starting fabrication and not necessary to be included in QC Dossier. For welding procedures already qualified, the certified records may only be reviewed. 6.3 Fabrication Procedure Fabrication procedure including hot forming procedure and post weld heat treatment procedure shall be submitted for approval of the Purchaser prior to the start of fabrication. 6.4 Welder Qualification Records Welder qualification records and qualified welders list for this job shall be prepared by the manufacturer. They shall be available to Purchaser's Inspector at fabrication shop. 6.5 QC Dossier (Test and Inspection Reports) After final inspection, all test records and/or test certificates for inspection and test given in Table 3 shall be issued as a form of QC Dossier. 13

14 Figure 1a STANDARD TOLERANCES FOR PRESSURE VESSELS (EXCEPT SHELL AND TUBE HEAT EXCHANGERS) 1 PASS 14

15 TRAY SUPPORT Unit. Figure Ib STANDARD TOLERANCES FOR PRESSURE VESSELS (EXCEPT SHELL AND TUBE HEAT EXCHANGERS) DIMENSION TO BE MEASURED TOLERANCES (UNIT mm) (NOTE1) 1. FROM T.L. TO T.L. LARGER OF ± 13 OR 1.5/m MAX. ± FROM T.L. TO C.L. OF MANHOLES INCLINES OF MANHOLE FLANGES FROM 1 Deg INDICATED PLANE IN ANY DIRECTION 4. FROM INSIDE OF VESSELS TO MANHOLE + 10 FLANGES 5. FROM T.L. TO C.L. OF NOZZLES INCLINES OF NOZZLE FLANGES FROM ½ Deg INDICATED PLANE IN ANY DIRECTION 7. FROM OUTSIDE OF VESSELS TO NOZZLE + 5 FLANGES 8. FROM BOTTOM OF DOWNCOMER TO + 3 TRAY FLOORS 9. HEIGHT OF WEIR (ABOVE DOWNCOMER SUPPORT) 10. FROM C.L. OF HEAD TO C.L. OF NOZZLES ORIENTATION OF NOZZLES AND OTHER + 6 ATTACHMENTS 12. FROM TRAY TO TRAY LEVEL OF SUPPORT RINGS (NOTE 2) Upto 1200 mm ID INCL 2 From 1201 to From 2101 to From 4001 to From 6001 to From 8001 to FROM T.L. TO TRAY SUPPORT RINGS FROM TRAYS TO NOZZLE C.L. OF NOZZLES OUT-OF-ROUNDNESS OF CYLINDRICAL SHELL a. VESSELS WITH TRAYS % ID b. VESSELS WITH TIE-ROD TRAYS % ID min + 3 c. VESSELS WITHOUT TRAYS +1 % (Note 3) INSIDE DIAMETER AS MEASURED BY EXTERNAL STRAPPING Upto 1200 mm ID INCL + 3 From 1201 to From 2101 to From 4001 to From 6001 to From 8001 to Head A & B Outside I.D. X

16 Inside I.D. X 0.625% 18. Deviation from Straight applied to LESS THAN 6 PER 6000 AND Shell. LESS THAN 20 PER TOTAL LENGTH 19. Skirt Length From TL to Lug +6 Figure Ic STANDARD TOLERANCES FOR PRESSURE VESSELS (EXCEPT SHELL AND TUBE TYPE SHELL AND TUBE HEAT EXCHANGERS) DIMENSION TO BE MEASURED TOLERANCES (UNIT mm) (NOTE 1) 21. LEVEL OF BASE PATE & SUPPORT Up to 1200 mm ID INCL 3 From 1201 to From 2101 to From 4001 to From 6001 to From 8001 to B.C.D. OF ANCHOR BOLTS UPTO 2100 INCL + 3 Over SUPPORT FOR HORIZONTAL VESSELS a. PITCH OF BOLT HOLES UPTO 2100 INCL + 3 Over b. FROM T.L. TO CENTER OF ANCHOR + 3 BOLTS c. HEIGHT OF SUPPORT FROM T.L. TO FLANGE OF BOTTOM OR TOP NOZZLES FOR LEVEL GAUGES a. PITCH + 2 b. ALIGNMENT LESS THAN 1 c. ALIGNMENT OF ORIENTATION LESS THAN ROTATION OF FLANGES LOCATION OF PLATFORMS, LADDERS, ELE + 10 PIPE SUPPORTS AND LUGS (E.L.) 28. DEVIATION FROM VERTICAL PLANE ON + 20 TRUE CENTER LINE FROM BASE TO TOP OF VESSEL NOTE 1: NOTE 2: NOTE 3: TOLERANCES ARE NOT CUMULATIVE MAX. 6 FOR THE PORTION OF SUPPORT RING THAT WEIR IS ATTACHED. WHEN THE CROSS SECTION PASSES THROUGH AN OPENING, THE PERMISSIBLE DIFFERENCE IN INSIDE DIAMETERS MAY BE INCREASED BY TWO PERCENT OF THE DIAMETER OF OPENING. 16

17 Table 3 INSPECTION & TEST AGENDA AND DOCUMENTS TO BE ISSUED TEST & INSPECTION TEST TEST AGENDA CATEGORY REPORT REMARKS MATERIAL TEST (INCLUDING R REQD BY MILL TEST UT & IMPACT) REPORT (Note 2) FORMED VISUAL INSP & W - TOGETHER WITH HEAD DIMENSIONAL MEAS SHELL ULTRASONIC EXAM R REQD ONLY FOR CLAD WELDED FIT UP, EDGE PREP, W - BY SAMPLING JOINT BACK CHIPPING RADIOGRAPHIC EXAM R REQD FILM CHECK LIQ PEN EXAM W REQD BY SAMPLING M.P. EXAM W REQD BY SAMPLING IMPACT TEST W REQD HARDNESS TEST W REQD VISUAL INSP & DIMENSIONAL MEASUREMENT OF BODY W REQD NOTE 3 VISUAL INSP & DIMENSIONAL MEASUREMENT OF INTERNAL W REQD POST WELD HEAT TREATMENT R REQD BY CHART PNEUMATIC TEST FOR REINF PAD R REQD HYDROSTATIC TESTING W REQD PNEUMATIC TEST W REQD MANUFACTURER S DATA REPORT R REQD ASME FORM RUBBING (COPY) OF NAMEPLATE R REQD. Table 3 INSPECTION AND TEST AGENDA AND DOCUMENTS TO BE ISSUED (Cont'd) Note Note 1) W: Witness Inspection R: Review of the manufacturing test report Test Category: Purchaser's inspection 2) Provide "Sketch of Materials" or "List of Materials" Mill test reports for the following parts, but not limited to, shall be submitted. - Shells, shell flanges, shell covers, channels, and channel flanges - Tube sheets, Tubes - Nozzles, nozzle flanges, and reinforcing plates for nozzles -Parts integrated with the pressure parts 17

18 FEED STOCK CONVERSION SECTION INSPECTION PHILOSOPHY Note -Bolts and nuts for shells, shell covers and channel flanges 3) The following inspection shall be conducted as the interim witness inspection for shell and tube heat exchangers: - Use of specified gaskets and means of holding them in place - Ease of bundle insertion - Bolt makeup and loading - Assembly of stacked exchangers, if any. PART C - INSPECTION PHILOSOPHY FOR COLUMN TRAYS 1. GENERAL Inspection Philosophy for trays shall be read in conjunction with Section A & Section B of the Inspection Philosophy, Section of the ITB. 2 CODES AND STANDARDS 2.1 Only the latest editions of regulations, codes, and standards in force at the time of order placement shall be applied, unless otherwise specified. 2.2 The requirements in the following codes and standards form a part of the requirements of this specification: (1) National standards in regard to materials of the countries from which the materials are supplied. These standards shall, however, be previously approved by the Purchaser. (2) Other codes and standards specified in each individual specification. 3. WITNESS INSPECTION 3.1 All trays shall be subject to inspection, at the option of the Purchaser, under witness by the Purchaser or designated representative of the Purchaser at any reasonable time and place before, during, and after manufacture/fabrication. 3.2 Witness inspection and test agenda shall be in accordance with Table 1, 3.3 The owner has the right of access to the Vendor's or Subvendor's shops for inspection matters. If the vendor received any instruction from the Owner's Inspector, the Vendor should report to the Purchaser before making any changes. 4. INSPECTION AND TEST AGENDA 4.1 Material 1) Material shall be verified to conform to the specified materials by mill test reports or material certificates. 2) Mill test reports or material certificates for such main parts as tray floor, down comer, weir, seal pan and tray support beam and for other specified parts shall be submitted. 3) For other parts than specified above, mill test report or material certificates for corrosion resistant austenitic stainless steel and higher grade material shall be also submitted. 4.2 Visual Inspection 1) All parts shall be visually checked for workmanship. 2) Surface shall be confirmed to have no harmful effect such as creases or chap. 3) Cutting face and punched hole shall be confirmed not to be stripped greatly. 4) Slag and spatter caused by welding shall be confirmed to be removed 5) When surface finishing such as buff finishing and electro polishing is specified, the

19 FEED STOCK CONVERSION SECTION INSPECTION PHILOSOPHY finishing shall be visually inspected by comparing with sample pieces accepted in advance by the Purchaser. Three sample pieces shall be submitted for approval. (Sample piece size : 100 mm x 100 mm x 3 or 6 mm thick, or 4 in. x 4 in. x 1/8 or 1/4 in. thick) 4.3 Dimensional Inspection Dimensional measurement shall be performed against certified dimensional drawings. Unless otherwise specified, tolerances shall be as follows: (1) Tray Floor (a) Length Up to 1000 mm, incl. ±2.0 mm Over 1000 mm - up to 2000 mm, incl. ±2.5 mm Over 2000 mm ±3.5 mm (b) Width ±2 mm (c) Flatness (2) Downcomer and Weir (a) Straightness for upper line of weir and lower line of down comer ±1.5 mm per 1000 mm at any place ±1 mm (b) Length Up to 1500 mm, incl. Over 1500 mm (c) Width (d) Flatness at any place ±2.5mm ±4.5 mm ±1.5 mm ±1.5 mm per 1000 mm (3) Punched hole for perforated tray Diameter +0.3 mm 4.4 Temporary Assembly Inspection All stages of tray shall be temporarily assembled at the Vendor's or Sub vendor's shop to confirm fit-up without trouble about pitch of bolt holes. Main dimensions shall be within the following tolerances. Diameter of Tray (1) Inside diameter specified of tower Up to 2000 mm, incl. +0 mm -4 mm 2001 mm and over +0 mm -5 mm (2) Flatness of tray floor +1.5 mm per 1000 mm at any place (3) Height of weir above the upper surface of tray floor ±1.5 mm 5. DOCUMENT SUBMITTAL The documents prescribed in the following paragraphs shall be submitted in accordance with Section A Inspection Instruction to the Vendors above. 5.1 Detailed Inspection and Test Procedure Unless otherwise specified, the vendor shall submit Detailed Inspection and Test Procedure for the Purchaser's approval within 12 weeks after the date of purchase order or 8 weeks in advance of the date of the first inspection, whichever is earlier

20 FEED STOCK CONVERSION SECTION INSPECTION PHILOSOPHY The procedure shall cover at least the following items and shall meet requirements of all inquiry and purchase documents, including related vendor's and Purchaser's correspondence. 1) Inspection and test agenda 2) Specific test methods including test equipment 3) Acceptance criteria 4) Test report and test certificate to be submitted 5.2 QC Dossier (Test and Inspection Reports) After final inspection, all test records and/or test certificates for inspection and test given in Table 1 shall be issued as a form of QC Dossier. Table 1 INSPECTION AND TEST AGENDA AND DOCUMENTS TO BE ISSUED Inspection & Test Test Category Test Report Remarks Material Test R Required By Mill Test Report/Material Certificate Visual Inspection W Required Incl.inspection of Buff Finishing Dimensional Insp. W Required Temp. Assembly Insp. W Required Note: 1) W: Witness R: Review of manufacturing test report Test Category : Purchaser s Inspection

INSPECTION AND TEST. PROCEDURE Total Page 13

INSPECTION AND TEST. PROCEDURE Total Page 13 PROCEDURE Total Page 13 Client : Project Name: P/O No. : Item No. : 3 2 1 0 FOR APPROVAL Rev Description Date Prepared By Checked By Approved By PROCEDURE Page 1 of 8 1. General 1.1 Scope This specification

More information

PART UF REQUIREMENTS FOR PRESSURE VESSELS FABRICATED BY FORGINGS

PART UF REQUIREMENTS FOR PRESSURE VESSELS FABRICATED BY FORGINGS p 1 of 6 UF-1 UF-12 PART UF REQUIREMENTS FOR PRESSURE VESSELS FABRICATED BY FORGING the test temperature be higher than 20 F ( 29 C). Certification is required. An ultrasonic examination shall be made

More information

1.0 INTRODUCTION GENERAL SUPPLIER S RESPONSIBILITY CODES AND STANDARDS... 4

1.0 INTRODUCTION GENERAL SUPPLIER S RESPONSIBILITY CODES AND STANDARDS... 4 TABLE OF CONTENTS 1.0 INTRODUCTION... 3 1.1 GENERAL... 3 1.2 SUPPLIER S RESPONSIBILITY... 3 2.0 CODES AND STANDARDS... 4 2.1 CODES, STANDARDS AND REGULATIONS... 4 2.2 NEPTUNE ENERGY NETHERLANDS B.V. SPECIFICATIONS...

More information

QUALITY ASSURANCE PROTOCOL (QAP)

QUALITY ASSURANCE PROTOCOL (QAP) PREFACE This Standard details the level of documentation that PVT.LTD (IET) will provide during a contract for fabricating tank(s) or portable equipment s. Extensive documentation is required for this

More information

SECTION III DIVISIONS 1 AND 2

SECTION III DIVISIONS 1 AND 2 SECTION III DIVISIONS 1 AND 2 Subject Interpretation File No. Division 1 Appendix N, Table N-1230-1; Damping Values (1998 Edition)... III-1-04-27 NI03-025 Code Cases 2142-1 and 2143-1... III-1-04-22 NI03-019

More information

REVISION CONTROL SHEET DOCUMENT TYPE : TECHNICAL SPECIFICATION TITLE : TECHNICAL SPECIFICATION FOR AUSTENITIC STAINLESS STEEL PIPES

REVISION CONTROL SHEET DOCUMENT TYPE : TECHNICAL SPECIFICATION TITLE : TECHNICAL SPECIFICATION FOR AUSTENITIC STAINLESS STEEL PIPES REVISION CONTROL SHEET DOCUMENT TYPE : TECHNICAL SPECIFICATION NO. : PC-M-308 TITLE : AUSTENITIC STAINLESS STEEL PIPES REV. NO. & DATE DESCRIPTION OF REVISION PREPARED BY CHECKED BY REVIEWED BY APPROVED

More information

Standard Specification for Ferritic/Austenitic (Duplex) Stainless Steel Pipe Electric Fusion Welded with Addition of Filler Metal 1

Standard Specification for Ferritic/Austenitic (Duplex) Stainless Steel Pipe Electric Fusion Welded with Addition of Filler Metal 1 Designation: A 928/A 928M 04 www.tubingchina.com Standard Specification for Ferritic/Austenitic (Duplex) Stainless Steel Pipe Electric Fusion Welded with Addition of Filler Metal 1 This standard is issued

More information

(Name and address of Manufacturer) (Name and address of Purchaser) (Name and address)

(Name and address of Manufacturer) (Name and address of Purchaser) (Name and address) FORM U-3P MANUFACTURER'S CERTIFICATE OF COMPLIANCE FOR PLATE HEAT ECHANGERS COVERING PRESSURE VESSELS TO BE STAMPED WITH THE UM DESIGNATOR [SEE U-1(j)] As Required by the Provisions of the ASME Boiler

More information

AMENDMENTS TO OPSS 1802 (JAN 95) MATERIAL SPECIFICATION FOR SMOOTH WALLED STEEL PIPE SUPPLY, STORAGE, AND DELIVERY OF WELDED STEEL PIPE

AMENDMENTS TO OPSS 1802 (JAN 95) MATERIAL SPECIFICATION FOR SMOOTH WALLED STEEL PIPE SUPPLY, STORAGE, AND DELIVERY OF WELDED STEEL PIPE Works and Emergency Services CITY OF TORONTO WATER AND WASTEWATER SERVICES STANDARD CONSTRUCTION SPECIFICATIONS TS 1802 June 2001 AMENDMENTS TO OPSS 1802 (JAN 95) MATERIAL SPECIFICATION FOR SMOOTH WALLED

More information

GUJARAT NARMADA VALLEY FERTILIZERS & CHEMICALS LIMITED

GUJARAT NARMADA VALLEY FERTILIZERS & CHEMICALS LIMITED CONTENTS 1. Scope 2. Referenced Documents 3. Abbreviations 4. Materials and Manufacture 5. Dimensions 6. Inspections and Tests 7. Markings 8. Preparation for Shipment - 1 - 1. Scope 1.1 This specification

More information

BODY OF KNOWLEDGE API-653 ABOVEGROUND STORAGE TANK INSPECTOR CERTIFICATION EXAMINATION

BODY OF KNOWLEDGE API-653 ABOVEGROUND STORAGE TANK INSPECTOR CERTIFICATION EXAMINATION BODY OF KNOWLEDGE API-653 ABOVEGROUND STORAGE TANK INSPECTOR CERTIFICATION EXAMINATION October 2009 (Replaces November 2008) API Authorized Aboveground Storage Tank Inspectors must have a broad knowledge

More information

OIL TECH SERVICES, INC.

OIL TECH SERVICES, INC. OIL TECH SERVICES, INC. 800 Wilcrest, Suite 100 Houston, TX 77042-1359 (310)-527-2695 (713) 789-5144 E Mail: mlombard@itmreps.com Website: www.itmreps.com WELDING Weld Procedure Specifications (WPS): Welding

More information

Specification for Pipe Fittings

Specification for Pipe Fittings Specification for Pipe Fittings Specification for Pipe Fittings Page 1 of 11 Table of Contents 1.0 SCOPE...3 2.0 DEFINITIONS...3 3.0 REFERENCES, CODES AND STANDARDS...3 4.0 CONTRACTOR'S RESPONSIBILITIES...4

More information

Open Art, Coke Drum Specification

Open Art, Coke Drum Specification Open Art, Coke Drum Specification COKE DRUM SPECIFICATION Contents 1. General 2. Code 3. Dimensions and Quantities 4. Operating Conditions 5. Design Conditions 6. Materials 7. Hydrotest Pressure 8. Maximum

More information

K. ASTM F436- Standard Specification for Hardened Steel Washers; 2011.

K. ASTM F436- Standard Specification for Hardened Steel Washers; 2011. DIVISION 05 METALS 05 12 00 STRUCTURAL STEEL FRAMING PART 1 GENERAL 1.1 SECTION INCLUDES A. Structural steel framing members, support members. 1.2 RELATED REQUIREMENTS A. Section 05 50 00 - Metal Fabrications:

More information

Technical Specification for Fabrication, Testing & Supply of Back plate assembly mock-up

Technical Specification for Fabrication, Testing & Supply of Back plate assembly mock-up INSTITUTE FOR PLASMA RESEARCH (An Autonomous Institute of Department of Atomic Energy, Government of India) Near Indira Bridge; Bhat; Gandhinagar-382428; India PART-I (B) Technical Specification for Fabrication,

More information

ACCREDITATION OF MANUFACTURERS AND INSTALLERS OF PRESSURE PIPING PARTS AND SYSTEMS

ACCREDITATION OF MANUFACTURERS AND INSTALLERS OF PRESSURE PIPING PARTS AND SYSTEMS ACCREDITATION OF MANUFACTURERS AND INSTALLERS OF PRESSURE PIPING PARTS AND SYSTEMS TSSA GUIDE FOR SURVEY TEAMS The Technical Standards and Safety Authority Boilers and Pressure Vessels Safety Division

More information

ASTM A420-Standard Specification for Piping Fittings of Wrought Carbon Steel and Alloy Steel for Low-Temperature Service

ASTM A420-Standard Specification for Piping Fittings of Wrought Carbon Steel and Alloy Steel for Low-Temperature Service ASTM A420-Standard Specification for Piping Fittings of Wrought Carbon Steel and Alloy Steel for Low-Temperature Service 1. Scope 1.1 This specification 2 covers wrought carbon steel and alloy steel fittings

More information

TABLE OF CONTENTS. 1.0 INTRODUCTION Page SCOPE Page REFERENCES Page REQUIREMENTS Page QUALITY ASSURANCE Page 8

TABLE OF CONTENTS. 1.0 INTRODUCTION Page SCOPE Page REFERENCES Page REQUIREMENTS Page QUALITY ASSURANCE Page 8 TABLE OF CONTENTS 1.0 INTRODUCTION Page 3 2.0 SCOPE Page 3 3.0 REFERENCES Page 4 4.0 REQUIREMENTS Page 5 5.0 QUALITY ASSURANCE Page 8 6.0 SUBMITTALS Page 9 7.0 PREPARATION FOR SHIPMENT Page 10 Page 2 of

More information

Technical Inquiries for API Standard 620, Design & Construction of Large, Welded, Low-Pressure Storage Tanks Last updated February 2014

Technical Inquiries for API Standard 620, Design & Construction of Large, Welded, Low-Pressure Storage Tanks Last updated February 2014 1.2.1 620-I-10/00 1: Does Section 1.2.1 prevent tanks with umbrella roofs and eccentric cones, from being marked as being in accordance with API Standard 620? 1: 4.2 Table 4-1 620-I-13/02 2: Does Section

More information

INSULATED JOINTS. Monolithic Joints for Electrically Isolating Pipelines

INSULATED JOINTS. Monolithic Joints for Electrically Isolating Pipelines INSULATED JOINTS Monolithic Joints for Electrically Isolating Pipelines INSULATED JOINTS TUBE TURNS INSULATED JOINTS are a pre-fabricated, non-separable, union used to isolate specific sections of pipelines

More information

NTPEP. Mill: Name: Physical Address: Mailing Address: SAME AS ABOVE (if different from above) Primary Contact Name: Title: Telephone: Cell:

NTPEP. Mill: Name: Physical Address: Mailing Address: SAME AS ABOVE (if different from above) Primary Contact Name: Title: Telephone: Cell: Mill: Name: Physical Address: Mailing Address: SAME AS ABOVE (if different from above) Primary Contact Name: Title: Telephone: Cell: Email: Management QC Manager: Plant Manager: Auditor Contact Name: Telephone:

More information

SQAR-1. SUPPLIER QUALITY ASSURANCE REQUIREMENTS for DESIGN AND PROCUREMENT SERVICES Revision Date: 2/1/2018

SQAR-1. SUPPLIER QUALITY ASSURANCE REQUIREMENTS for DESIGN AND PROCUREMENT SERVICES Revision Date: 2/1/2018 SUPPLIER QUALITY ASSURANCE REQUIREMENTS for DESIGN AND PROCUREMENT SERVICES Revision Date: 2/1/2018 1.0 SCOPE This document establishes the quality program requirements for an organization providing engineering

More information

CONTENTS. Foreword... xiii Statements of Policy... xv Personnel... xvii Organization of Section III... xxvii Summary of Changes...

CONTENTS. Foreword... xiii Statements of Policy... xv Personnel... xvii Organization of Section III... xxvii Summary of Changes... CONTENTS Foreword... xiii Statements of Policy... xv Personnel... xvii Organization of Section III... xxvii Summary of Changes... xxxi Article NB-1000 Introduction... 1 NB-1100 Scope... 1 NB-1110 Aspects

More information

Guide for the preparation of quality programs for licensing of companies performing BPE regulated work.

Guide for the preparation of quality programs for licensing of companies performing BPE regulated work. Labour and Advanced Education Guide for the preparation of quality programs for licensing of companies performing BPE regulated work. Company Name: QC Program issue#: Revision# Overview: 1. This guideline

More information

SECTION GROUND STORAGE TANK

SECTION GROUND STORAGE TANK SECTION 13210 GROUND STORAGE TANK PART 1 GENERAL 1.01 Summary A. Section Includes: Provision for welded steel storage tank design, fabrication, construction and erection, including tank accessories. B.

More information

ASTM Standards for Pipe & Fittings

ASTM Standards for Pipe & Fittings for Pipe & Fittings There are many International Standards for stainless and carbon steel pipes and fittings. The list below is a basic overview of some of these. For more in-depth details of these Standards

More information

C. Miscellaneous Metal Fabricators are specified elsewhere in Division 5.

C. Miscellaneous Metal Fabricators are specified elsewhere in Division 5. SECTION 05 1200 - STRUCTURAL STEEL FRAMING PART 1 - GENERAL 1.01 SUMMARY A. Extent of structural steel work is shown on drawings, including schedules, notes and details to show size and location of members,

More information

Contents EN 14015:2004 (E) page

Contents EN 14015:2004 (E) page Contents page Foreword... 11 1 Scope... 12 2 Normative references... 13 3 Terms, definitions, symbols and abbreviations... 15 3.1 Terms and definitions... 15 3.2 Symbols... 19 3.3 Abbreviations... 21 4

More information

Stainless Steel Aeration Equipment Specification

Stainless Steel Aeration Equipment Specification Section 15 Stainless Steel Aeration Equipment Specification Part 1 - General 1.01 Description A. Scope of Work 1. Furnish, install and test aeration system including air mains, drop pipes, valves, expansion

More information

PART PG GENERAL REQUIREMENTS FOR ALL METHODS OF CONSTRUCTION

PART PG GENERAL REQUIREMENTS FOR ALL METHODS OF CONSTRUCTION CONTENTS Foreword... xv Statements of Policy... xvii Personnel... xix Preamble... xxxi Summary of Changes... xxxiii List of Changes in BC Order... xxxvi PART PG GENERAL REQUIREMENTS FOR ALL METHODS OF

More information

Facility Repairs - MCAS Cherry Point - Tank Farm A SECTION STRUCTURAL STEEL 05/14

Facility Repairs - MCAS Cherry Point - Tank Farm A SECTION STRUCTURAL STEEL 05/14 SECTION 05 12 00 STRUCTURAL STEEL 05/14 PART 1 GENERAL 1.1 REFERENCES The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the

More information

Section 4. Annex to IAEA Request for Proposal STATEMENT OF WORK. Primary/Secondary cooling water Heat Exchangers

Section 4. Annex to IAEA Request for Proposal STATEMENT OF WORK. Primary/Secondary cooling water Heat Exchangers Section 4 Annex to IAEA Request for Proposal 25919 STATEMENT OF WORK Primary/Secondary cooling water Heat Exchangers WWR-SM Research Reactor, UZBEKISTAN Page 1 of 17 1. Scope 1.1 This Statement of Work

More information

SECTION STRUCTURAL METAL FRAMING

SECTION STRUCTURAL METAL FRAMING SECTION 05100 STRUCTURAL METAL FRAMING PART 1 GENERAL 1.01 SUMMARY A. Section Includes: Structural steel framing including lintels, shelf angles, bearing plates, anchor bolts and other items as shown on

More information

STANDARD SPECIFICATION FOR ALUMINUM FRAMING FOR RAILROAD PASSENGER SHELTERS

STANDARD SPECIFICATION FOR ALUMINUM FRAMING FOR RAILROAD PASSENGER SHELTERS SOUTHEASTERN PENNSYLVANIA TRANSPORTATION AUTHORITY 1234 MARKET STREET, PHILADELPHIA, PA 19107 STANDARD SPECIFICATION FOR ALUMINUM FRAMING FOR RAILROAD PASSENGER SHELTERS REVISION DATE SPECIFICATION # F-S-304_

More information

SPECIFICATION FOR SPHERICAL VESSELS (PROJECT STANDARDS AND SPECIFICATIONS)

SPECIFICATION FOR SPHERICAL VESSELS (PROJECT STANDARDS AND SPECIFICATIONS) Page : 1 of 1 April 01 #03-1 Block Aronia, TABLE OF CONTENTS 1. GENERAL 1.1 Scope. DESIGN.1 Shell Design. Support Column Design.3 Opening Reinforcement. Nozzles and Manholes.5 Internals and Externals.

More information

Regardless of any alternative pricing provided, a quotation for the items specified herein shall be provided.

Regardless of any alternative pricing provided, a quotation for the items specified herein shall be provided. 1/5 1.0 PURPOSE This specification describes the minimum requirements for design, material and construction requirements for Expansion tanks. Ensure the design and fabrication of equipment and associated

More information

HOW TO CONSTRUCT ASME BOILER BY THAI ASSOCIATION OF BOILOER AND PRESSURE VESSEL

HOW TO CONSTRUCT ASME BOILER BY THAI ASSOCIATION OF BOILOER AND PRESSURE VESSEL HOW TO CONSTRUCT ASME BOILER BY THAI ASSOCIATION OF BOILOER AND PRESSURE VESSEL WHAT IS ASME The American Society of Mechanical Engineers set up a committee in 1911 for the purpose of formulating standard

More information

Regardless of any alternative pricing provided, a quotation for the items specified herein shall be provided.

Regardless of any alternative pricing provided, a quotation for the items specified herein shall be provided. 1/5 1.0 PURPOSE This specification describes the minimum requirements for design, material and construction requirements for air receivers. Ensure the design and fabrication of equipment and associated

More information

SECTION METAL WELDING

SECTION METAL WELDING SECTION 05222 - METAL WELDING PART 1 - GENERAL 1.01 SECTION INCLUDES A. Welding Rod/Electrodes B. Stud Shear Connectors C. Shop Welding D. Inspections and Tests by the Contractor E. Inspections and Test

More information

ACCREDITATION OF MANUFACTURERS OF BOILERS & PRESURE VESSELS

ACCREDITATION OF MANUFACTURERS OF BOILERS & PRESURE VESSELS ACCREDITATION OF MANUFACTURERS OF BOILERS & PRESURE VESSELS [Not applicable to ASME Sec. IV, Cast Iron and Aluminum Boilers, ASME Sec. VIII Div 1, UG-90 (c) (2) and Graphite Vessels, ASME Sec. VIII, Div.

More information

2. REFERENCE SPECIFICATIONS

2. REFERENCE SPECIFICATIONS TABLE OF CONTENTS 1. Scope 2. Reference Specifications 3. Ordering Information 4. Source Inspection at Foundry 5. Shipping Preparation for Castings 6. Incoming Inspection at Farris All Material 7. Incoming

More information

ACCREDITATION OF FITTING MANUFACTURERS

ACCREDITATION OF FITTING MANUFACTURERS ACCREDITATION OF FITTING MANUFACTURERS TSSA GUIDE FOR REVIEW TEAMS The Technical Standards and Safety Authority Boilers and Pressure Vessels Safety Division 3300 Bloor Street West 14th Floor, Centre Tower

More information

1. Cast-in-place concrete is specified in Section

1. Cast-in-place concrete is specified in Section SECTION 03 38 00 PART 1 - GENERAL 1.01 DESCRIPTION A. This Section describes the requirements for furnishing and installing post-tensioned slabs, jacks, jacking and anchors at Parking Structure, and record

More information

SPECIFICATION FOR SEAMLESS AND WELDED ZIRCONIUM AND ZIRCONIUM ALLOY PIPE

SPECIFICATION FOR SEAMLESS AND WELDED ZIRCONIUM AND ZIRCONIUM ALLOY PIPE Company Website: www.metalspiping.com Your Reliable Supplier of Special Alloys! SPECIFICATION FOR SEAMLESS AND WELDED ZIRCONIUM AND ZIRCONIUM ALLOY PIPE SB-658/SB-658M (Identical with ASTM Specification

More information

REVISION CONTROL SHEET DOCUMENT TYPE : TECHNICAL SPECIFICATION

REVISION CONTROL SHEET DOCUMENT TYPE : TECHNICAL SPECIFICATION REVISION CONTROL SHEET DOCUMENT TYPE : TECHNICAL SPECIFICATION NO. : PC-M-309 TITLE : REV. NO. & DATE DESCRIPTION OF REVISION PREPARED BY CHECKED BY REVIEWED BY APPROVED BY PAGE NO : 1 of 16 1. SCOPE This

More information

Reinforced Thermoset Plastic Corrosion-Resistant Equipment

Reinforced Thermoset Plastic Corrosion-Resistant Equipment ASME RTP-1 2007 (Revision of ASME RTP-1 2005) Reinforced Thermoset Plastic Corrosion-Resistant Equipment AN AMERICAN NATIONAL STANDARD Three Park Avenue New York, NY 10016 Date of Issuance: April 9, 2008

More information

GENERAL CONTENTS SECTION I - NUCLEAR ISLAND COMPONENTS

GENERAL CONTENTS SECTION I - NUCLEAR ISLAND COMPONENTS - June 2013 Addendum GENERAL CONTENTS SECTION I - NUCLEAR ISLAND COMPONENTS SUBSECTION "A" : GENERAL RULES SUBSECTION "B" : CLASS 1 COMPONENTS SUBSECTION "C" : CLASS 2 COMPONENTS SUBSECTION "D" : CLASS

More information

SECTION LAGUNA SERIES TOP HUNG SLIDING DOOR SYSTEM

SECTION LAGUNA SERIES TOP HUNG SLIDING DOOR SYSTEM Page 1 of 6 SECTION 08 32 20 LAGUNA SERIES TOP HUNG SLIDING DOOR SYSTEM USE THIS SECTION WHEN SPECIFYING OVERHEAD SUPPORTED GLASS SLIDING DOORS. SECTION INCLUDES OVERHEAD SLIDING TUBE ASSEMBLY, MOUNTING

More information

MATERIAL REQUISITION FOR BOLTS AND NUTS

MATERIAL REQUISITION FOR BOLTS AND NUTS Title: MATERIAL REQUISITION FOR BOLTS AND NUTS Page: 1 of 12 MATERIAL REQUISITION FOR BOLTS AND NUTS 6 5 4 3 2 1 0 08-JUN-2013 ISSUED FOR APPROVAL M. KAMALOU A.MOHAMADIZADE A.MOHAMADIZADE REV. DATE STATUS

More information

Monolithic Isolation Fittings

Monolithic Isolation Fittings Monolithic Isolation Fittings The ElectroStop TM monolithic isolation fittings will serve as a positive leak proof, long lasting block against the flow of electric current in all piping systems. When you

More information

SECTION WELDING

SECTION WELDING SECTION 05050 WELDING PART 1 GENERAL 1.1 REFERENCES A. The following is a list of standards which may be referenced in this section: 1.2 DEFINITIONS 1. American Society of Mechanical Engineers (ASME):

More information

SECTION HANDRAILS AND RAILINGS. A. Section Cast-In-Place Concrete; coordination with substrate.

SECTION HANDRAILS AND RAILINGS. A. Section Cast-In-Place Concrete; coordination with substrate. SECTION 05520 HANDRAILS AND RAILINGS PART 1 GENERAL 1.1 SECTION INCLUDES A. Welded stainless steel railing systems. 1.2 RELATED SECTIONS A. Section 03300 - Cast-In-Place Concrete; coordination with substrate.

More information

SECTION MISCELLANEOUS METALS

SECTION MISCELLANEOUS METALS PART 1 GENERAL 1.1 WORK OF THIS SECTION A. Contractor shall provide all labor, materials, equipment and incidentals as shown, specified and required to furnish and install all miscellaneous metal fabrications

More information

XI'AN LINKUN STEEL PIPE CO., LTD

XI'AN LINKUN STEEL PIPE CO., LTD Designation: A 50 0 (Reapproved 2005) Standard Specification for Hot-Formed Welded and Seamless Carbon Steel Structural Tubing This standard is issued under the fixed designation A 50; the number immediately

More information

Standard Specification for Centrifugally Cast Ferritic Alloy Steel Pipe for High- Temperature Service 1

Standard Specification for Centrifugally Cast Ferritic Alloy Steel Pipe for High- Temperature Service 1 Designation: Standard Specification for Centrifugally Cast Ferritic Alloy Steel Pipe for High- Temperature Service 1 This standard is issued under the fixed designation A 426/A 426M; the number immediately

More information

1. Base plates, setting plates and anchor rods for columns. 8. Lintels if connected to structural steel columns.

1. Base plates, setting plates and anchor rods for columns. 8. Lintels if connected to structural steel columns. PAGE 051200-1 SECTION 051200 PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 01 Specification sections,

More information

SPECIFICATIONS - DETAILED PROVISIONS Section Stainless Steel Sluice Gates C O N T E N T S

SPECIFICATIONS - DETAILED PROVISIONS Section Stainless Steel Sluice Gates C O N T E N T S SPECIFICATIONS - DETAILED PROVISIONS Section 11294 - Stainless Steel Sluice Gates C O N T E N T S PART 1 - GENERAL... 1 1.01 SUMMARY... 1 1.02 REFERENCES... 1 1.03 DEFINITIONS... 1 1.04 DESIGN REQUIREMENTS...

More information

Specification for the Fabrication of Tower Structures

Specification for the Fabrication of Tower Structures Ergon Energy Corporation Limited Specification for the Fabrication of Tower Structures This material is made available on the basis that it may be necessary for a Registered Professional Engineer of Queensland

More information

SECTION GROUND WATER STORAGE TANKS

SECTION GROUND WATER STORAGE TANKS SECTION 33 16 13 GROUND WATER STORAGE TANKS PART 1: GENERAL 1.01 SCOPE A. Section includes requirements for designing, fabricating, and erecting a welded steel ground storage tank. 1.02 SYSTEM DESCRIPTION

More information

GFIRA12001 WBS: Energy Efficiency in Key Industrial Sectors

GFIRA12001 WBS: Energy Efficiency in Key Industrial Sectors 1 July 2014 GFIRA12001 WBS: 120506-1-01-04 Energy Efficiency in Key Industrial Sectors This Terms of Reference will be used for the preparation of the bid for the provision of equipment and services required

More information

ASME BPVC.CC.BPV.S Approval Date: October 7, 2015

ASME BPVC.CC.BPV.S Approval Date: October 7, 2015 CASE Approval Date: October 7, 2015 Code Cases will remain available for use until annulled by the applicable Standards Committee. Case Manufacture of a Hoop-Wrapped, Wire-Reinforced Cylindrical Pressure

More information

BODY OF KNOWLEDGE API-570 AUTHORIZED PIPING INSPECTOR CERTIFICATION EXAMINATION

BODY OF KNOWLEDGE API-570 AUTHORIZED PIPING INSPECTOR CERTIFICATION EXAMINATION BODY OF KNOWLEDGE API-570 AUTHORIZED PIPING INSPECTOR CERTIFICATION EXAMINATION 2018 (Replaces February 2017) API Authorized Piping Inspectors must have a broad knowledge base relating to maintenance,

More information

Corrosion Resistant Bolting for Use in the Petroleum and Natural Gas Industries

Corrosion Resistant Bolting for Use in the Petroleum and Natural Gas Industries Corrosion Resistant Bolting for Use in the Petroleum and Natural Gas Industries API SPECIFICATION 20F FIRST EDITION, XXX 201X 1 1. Scope 1.1 Purpose This API specification specifies requirements for the

More information

PIP VESST002 Supplemental Design and Fabrication Specification for Shell and Tube Heat Exchangers ASME Code Section VIII, Divisions 1 and 2

PIP VESST002 Supplemental Design and Fabrication Specification for Shell and Tube Heat Exchangers ASME Code Section VIII, Divisions 1 and 2 March 2012 Process Industry Practices Vessels PIP VESST002 Supplemental Design and Fabrication Specification for Shell and Tube Heat Exchangers ASME Code Section VIII, Divisions 1 and 2 PURPOSE AND USE

More information

ASTM B363-06a Standard Specification for Seamless and Welded Unalloyed

ASTM B363-06a Standard Specification for Seamless and Welded Unalloyed Standard Specification for Seamless and Welded Unalloyed Titanium and Titanium Alloy Welding Fittings 1. Scope :- 1.1 This specification cover fittings intended for general corrosion resisting and elevated

More information

M. F. Sullivan. 9/27/2016 Dr. Sandor Somogyi

M. F. Sullivan. 9/27/2016 Dr. Sandor Somogyi The Code is a large document and it is sometimes very difficult to understand. Even for many of us who work with it every day. In my opinion there is no one person who could be termed as a Code Expert.

More information

PIP VESST002 Supplemental Design and Fabrication Specification for Shell and Tube Heat Exchangers ASME Code Section VIII, Divisions 1 and 2

PIP VESST002 Supplemental Design and Fabrication Specification for Shell and Tube Heat Exchangers ASME Code Section VIII, Divisions 1 and 2 April 2018 Vessel Supplemental Design and Fabrication Specification for Shell and Tube Heat Exchangers ASME Code Section VIII, Divisions 1 and 2 PURPOSE AND USE OF PROCESS INDUSTRY PRACTICES In an effort

More information

Insulating Cellular Concrete Steel Joists Painting. A. America Society for Testing and Materials (ASTM):

Insulating Cellular Concrete Steel Joists Painting. A. America Society for Testing and Materials (ASTM): SECTION 05120 STRUCTURAL STEEL PART 1 GENERAL 1.01 SUMMARY A. Related Sections: 1. 03342 - Insulating Cellular Concrete. 2. 05210 - Steel Joists. 3. 09900 - Painting. 1.02 REFERENCES A. America Society

More information

Specification for the Fabrication of Structural Steel Pipe API SPECIFICATION 2B SIXTH EDITION, JULY 2001 EFFECTIVE DATE: JANUARY 1, 2002

Specification for the Fabrication of Structural Steel Pipe API SPECIFICATION 2B SIXTH EDITION, JULY 2001 EFFECTIVE DATE: JANUARY 1, 2002 Specification for the Fabrication of Structural Steel Pipe API SPECIFICATION 2B SIXTH EDITION, JULY 2001 EFFECTIVE DATE: JANUARY 1, 2002 Specification for the Fabrication of Structural Steel Pipe Upstream

More information

EEMUA Publication Construction specification for fixed offshore structures

EEMUA Publication Construction specification for fixed offshore structures Contents Preface... iv Principal changes in the 3 rd Edition... 1 1 Introduction and objectives... 3 1.1 Scope... 3 1.2 Definitions... 3 1.3 Abbreviations... 4 1.4 Units... 6 1.5 Glossary of technical

More information

ASME B31.3 CUMULATIVE INDEX INTERPRETATIONS VOLS SUBJECT INDEX. Assembly and Erection Authorized Inspector (see Owner s Inspector)

ASME B31.3 CUMULATIVE INDEX INTERPRETATIONS VOLS SUBJECT INDEX. Assembly and Erection Authorized Inspector (see Owner s Inspector) SUBJECT INDEX Acceptance Criteria pressure tests 1-2 weld 1-1 1-9 1-14 1-41 2-8 5-09 5-13 5-17 5-18 5-20 6-04 7-06 8-32 12-22 13-16 14-02 14-07 24-03 24-26 Additive Manufacturing 25-39 25-40 Allowable

More information

Standard Specification for Seamless and Welded Ferritic and Martensitic Stainless Steel Tubing for General Service

Standard Specification for Seamless and Welded Ferritic and Martensitic Stainless Steel Tubing for General Service SA-268/SA-268M ASME BPVC.II.A-2015 Standard Specification for Seamless and Welded Ferritic and Martensitic Stainless Steel Tubing for General Service 1. Scope 1.1 This specification covers a number of

More information

Reinforced Thermoset Plastic Corrosion-Resistant Equipment

Reinforced Thermoset Plastic Corrosion-Resistant Equipment ASME RTP-1 2013 (Revision of ASME RTP-1 2011) Reinforced Thermoset Plastic Corrosion-Resistant Equipment AN AMERICAN NATIONAL STANDARD ASME RTP-1 2013 (Revision of ASME RTP-1 2011) Reinforced Thermoset

More information

SECTION COMPOSITE METAL DECKING

SECTION COMPOSITE METAL DECKING PART 1 GENERAL 1.1 DESCRIPTION SECTION 05 36 00 1. Use this section only for NCA projects. 2. Delete between // ---- // if not applicable to project. Also delete any other item or paragraph not applicable

More information

UNIFIED FACILITIES GUIDE SPECIFICATIONS

UNIFIED FACILITIES GUIDE SPECIFICATIONS USACE / NAVFAC / AFCEC / NASA UFGS-40 17 30.00 40 (May 2016) ----------------------------------- Preparing Activity: NASA Superseding UFGS-40 17 30.00 40 (August 2010) UFGS-23 31 13.20 40 (February 2009)

More information

XI'AN LINKUN STEEL PIPE CO., LTD

XI'AN LINKUN STEEL PIPE CO., LTD Designation: A 358/A 358M 01 An American National Standard Used in USDOE-NE Standards Standard Specification for Electric-Fusion-Welded Austenitic Chromium-Nickel Alloy Steel Pipe for High-Temperature

More information

Standard Specification for Seamless and Welded Ferritic and Martensitic Stainless Steel Tubing for General Service 1

Standard Specification for Seamless and Welded Ferritic and Martensitic Stainless Steel Tubing for General Service 1 Designation: A 268/A 268M 0 An American National Standard Standard Specification for Seamless and Welded Ferritic and Martensitic Stainless Steel Tubing for General Service This standard is issued under

More information

SECTION STRUCTURAL STEEL

SECTION STRUCTURAL STEEL SECTION 051200 STRUCTURAL STEEL PART 1 GENERAL 1.01 SECTION INCLUDES A. Structural steel framing members and support members. B. Base plates, shear stud connectors. C. Grouting under base plates. 1.02

More information

BUREAU OF INDIAN STANDARDS Draft Indian Standard

BUREAU OF INDIAN STANDARDS Draft Indian Standard For Comments Only BUREAU OF INDIAN STANDARDS Draft Indian Standard STEEL PLATES FOR PRESSURE VESSEL FOR INTERMEDIATE AND HIGH TEMPERATURE SERVICE INCLUDING BOILERS (Third Revision of IS 2002) ICS 77.140.30

More information

ACCREDITATION OF PRESSURE RELIEF VALVE REPAIR ORGANIZATIONS

ACCREDITATION OF PRESSURE RELIEF VALVE REPAIR ORGANIZATIONS ACCREDITATION OF PRESSURE RELIEF VALVE REPAIR ORGANIZATIONS TSSA GUIDE FOR SURVEY TEAMS The Technical Standards and Safety Authority Boilers and Pressure Vessels Safety Division 3300 Bloor Street West

More information

Standard Specification for Seamless and Welded Ferritic/Austenitic Stainless Steel Pipe

Standard Specification for Seamless and Welded Ferritic/Austenitic Stainless Steel Pipe SA-790/SA-790M ASME BPVC.II.A-2015 Standard Specification for Seamless and Welded Ferritic/Austenitic Stainless Steel Pipe 1. Scope 1.1 This specification covers seamless and straight-seam welded ferritic/austenitic

More information

CONSTRUCTION SPECIFICATION FOR STRUCTURAL STEEL

CONSTRUCTION SPECIFICATION FOR STRUCTURAL STEEL ONTARIO PROVINCIAL STANDARD SPECIFICATION METRIC OPSS 906 FEBRUARY 1993 CONSTRUCTION SPECIFICATION FOR STRUCTURAL STEEL 906.01 SCOPE 906.02 REFERENCES 906.03 DEFINITIONS TABLE OF CONTENTS 906.04 SUBMISSION

More information

ASTM A105/A105M-10. Standard Specification for Carbon Steel Forgings for. Piping Applications ¹

ASTM A105/A105M-10. Standard Specification for Carbon Steel Forgings for. Piping Applications ¹ Standard Specification for Carbon Steel Forgings for Piping Applications ¹ 1. Scope :- 1.1 This specification covers forged carbon steel piping components for ambient and higher temperature service in

More information

This procedure applies to Pike construction activities. This procedure may also be applied to Subcontractors when invoked by Contract documents.

This procedure applies to Pike construction activities. This procedure may also be applied to Subcontractors when invoked by Contract documents. Project Procedure SPECIAL PROCESS CONTROL 09/21/2012 PAGE 1 OF 7 1.0 PURPOSE The purpose of this procedure is to ensure that welding, post weld heat treatment, and nondestructive examination activities

More information

PART UIG THE ASME CODE FOR IMPREGNATED GRAPHITE PRESSURE VESSELS

PART UIG THE ASME CODE FOR IMPREGNATED GRAPHITE PRESSURE VESSELS PART UIG THE ASME CODE FOR IMPREGNATED GRAPHITE PRESSURE VESSELS Presented by: Ed Soltow Engineering and Design Manager SGL Carbon Technic LLC Member ASME Standards Committee on Pressure Vessels (BPV VIII)

More information

QUALITY ASSURANCE SPECIFICATION WELDING HEAT TREATMENT PAGE 1 OF 6

QUALITY ASSURANCE SPECIFICATION WELDING HEAT TREATMENT PAGE 1 OF 6 QUALITY ASSURANCE SPECIFICATION REVISION: 0 DATE: 08/29/14 WELDING HEAT TREATMENT PAGE 1 OF 6 1.0 Purpose The purpose of this specification is to establish the minimum quality assurance requirements for

More information

SECTION COLD-FORMED METAL TRUSSES

SECTION COLD-FORMED METAL TRUSSES SECTION 054400 COLD-FORMED METAL TRUSSES PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 01 Specification

More information

UFGS (February 2009) UNIFIED FACILITIES GUIDE SPECIFICATIONS

UFGS (February 2009) UNIFIED FACILITIES GUIDE SPECIFICATIONS USACE / NAVFAC / AFCESA / NASA UFGS-40 17 30.00 40 (August 2010) Change 1-11/12 ----------------------------------- Preparing Activity: NASA Superseding UFGS-23 31 13.20 40 (February 2009) UNIFIED FACILITIES

More information

SUPPLIER QUALITY SCOPE AND FACILITY QUESTIONNAIRE. Bantrel Co. Project #:

SUPPLIER QUALITY SCOPE AND FACILITY QUESTIONNAIRE. Bantrel Co. Project #: Bantrel Co. Project #: COMPLETED BY: DATE: SUPPLIER NAME: D & B NUMBER: CONTENTS 1.0 GENERAL INFORMATION 2.0 PERSONNEL 3.0 QUALITY PROGRAM 4.0 SUPPLIER / CONTRACTOR INFORMATION 5.0 SCOPE OF FABRICATION

More information

INSPECTION PROCEDURE FOR SHELL AND TUBE HEAT EXCHANGERS

INSPECTION PROCEDURE FOR SHELL AND TUBE HEAT EXCHANGERS APPROVED: DATE APPROVED: DATE EFFECTIVE: Technical Writer: Content Expert: Purpose References Establish inspection guidelines to ensure mechanical integrity and continued reliable operation of shell and

More information

SPECIFICATION FOR NICKEL ALLOY FORGINGS

SPECIFICATION FOR NICKEL ALLOY FORGINGS SPECIFICATION FOR NICKEL ALLOY FORGINGS 01 (Identical with ASTM Specification B 564-00 except that certification has been made mandatory.) 1. Scope 1.1 This specification covers forgings of nickel alloy

More information

SECTION WELDED STEEL PICKET FENCE. 1. Fusion welded and rackable ornamental steel picket fence system.

SECTION WELDED STEEL PICKET FENCE. 1. Fusion welded and rackable ornamental steel picket fence system. PART 1 - GENERAL 1.1 SUMMARY A. Section includes: 1. Fusion welded and rackable ornamental steel picket fence system. B. Related sections: 1. Section 03310 Concrete Work for post support. 2. Section 09960

More information

SECTION HANGERS AND SUPPORTS FOR ELECTRICAL SYSTEMS

SECTION HANGERS AND SUPPORTS FOR ELECTRICAL SYSTEMS SECTION 26 05 29 HANGERS AND SUPPORTS FOR ELECTRICAL SYSTEMS PART 1 GENERAL 1.1 DESCRIPTION A. Scope: 1. CONTRACTOR shall provide all labor, materials, equipment, and incidentals as shown, specified, and

More information

Welding Performance Qualification Test Administrators GUIDE FOR APPLICANTS

Welding Performance Qualification Test Administrators GUIDE FOR APPLICANTS TECHNICAL SAFETY BC Welding Performance Qualification Test Administrators GUIDE FOR APPLICANTS Date: October 12, 2017 Controlled Document: MAN-4018-02 MAN-4018-02 Page 1 of 27 Contents 1.0 Introduction...

More information

TECHNICAL REQUIREMENTS FOR PRECIPITATION HARDENING (SS 17-4 PH and PH 13-8 MO) STAINLESS STEEL BARS

TECHNICAL REQUIREMENTS FOR PRECIPITATION HARDENING (SS 17-4 PH and PH 13-8 MO) STAINLESS STEEL BARS TECHNICAL REQUIREMENTS FOR PRECIPITATION HARDENING (SS 17-4 PH and PH 13-8 MO) STAINLESS STEEL BARS 1.0 SCOPE This Specification establishes the requirements for manufacture, inspection, testing and supply

More information

UNIFIED FACILITIES GUIDE SPECIFICATIONS

UNIFIED FACILITIES GUIDE SPECIFICATIONS USACE / NAVFAC / AFCESA / NASA UFGS-05 05 23 (November 2008) ----------------------------- Preparing Activity: USACE Superseding UFGS-05 05 23 (July 2007) UNIFIED FACILITIES GUIDE SPECIFICATIONS References

More information

05510: TAPERED STEEL TROLLEY POLES AND ACCESSORIES

05510: TAPERED STEEL TROLLEY POLES AND ACCESSORIES PART 1 GENERAL 1.01 DESCRIPTION A. The Vendor shall fabricate, furnish, test and deliver tapered steel trolley poles, including base plates, reinforced hand holes, anchor bolts, nuts and washers, and accessories

More information

SECTION CRL70 HEAVY GLASS TOP HUNG SLIDING DOOR SYSTEMS

SECTION CRL70 HEAVY GLASS TOP HUNG SLIDING DOOR SYSTEMS Page 1 of 6 SECTION 08 32 20 CRL70 HEAVY GLASS TOP HUNG SLIDING DOOR SYSTEMS USE THIS SECTION WHEN SPECIFYING OVERHEAD SUPPORTED GLASS [OR WOOD] PANEL PARTITIONS. SECTION INCLUDES OVERHEAD TRACK ASSEMBLY,

More information

UNIFIED FACILITIES GUIDE SPECIFICATIONS

UNIFIED FACILITIES GUIDE SPECIFICATIONS USACE / NAVFAC / AFCEC / NASA UFGS-05 05 23.16.16 (May 2014) ----------------------------- Preparing Activity: USACE Superseding UFGS-05 05 23 (November 2008) UNIFIED FACILITIES GUIDE SPECIFICATIONS References

More information