INSPECTION AND TEST. PROCEDURE Total Page 13

Size: px
Start display at page:

Download "INSPECTION AND TEST. PROCEDURE Total Page 13"

Transcription

1 PROCEDURE Total Page 13 Client : Project Name: P/O No. : Item No. : FOR APPROVAL Rev Description Date Prepared By Checked By Approved By

2 PROCEDURE Page 1 of 8 1. General 1.1 Scope This specification covers the requirement of inspection for quality control during shop fabrication of the filters. 1.2 Applicable codes and standards This codes and standards shall be of the latest editions unless otherwise specified in specific job requirement. ASTM:American Society for Testing Materials ASTM:American Society for Mechanical Engineers < ASME Code Sec. VIII Div.1 `95Ed `96Add. > ANSI:American National Standard Institute AWS:American Welding Society SSPC:Steel Structure Painting Council API :American Petroleum Institute 1.3 Specification and drawings 1) Inspection and tests shall be carried out and based on fabrication drawing, procedure as approved by purchaser. 2) Where there are conflicts between the specification and drawings, they shall be promptly notified to purchaser. 1.4 Witness 1) Witness inspection shall, as a rule, be carried out at K-Flow shop. 2) Witness inspection shall mean inspection by inspector of purchaser, his designated representative, customers.(herein after referred to as purchaser s inspector) 3) At any time during manufacturing is under way, purchaser s inspector shall have free access to any K-Flow shop concerned with manufacture of filters. 4) K-Flow shall provide to purchaser s inspector with suitable facilities during the project performance. 5) Witness inspection shall be performed by way of interim inspection and final inspection as deemed necessary by purchaser s inspector. 6) K-Flow shall inform application for inspection by fax. at least 10 working days prior to actual inspection or test date. When a change of the inspection date occurs due to the fabrication progress,

3 PROCEDURE Page 2 of 8 K-Flow shall promptly submit the revised application in an appropriate manner for action. 7) K-Flow shall, at the time of witness inspection, submit to purchaser s inspector one copy of record his own inspection and tests. 1.5 K-Flow responsibility 1) K-Flow shall carry out all inspection and tests specified in this specification and shall prepare the records for each item to show that the filters have been constructed in accordance with the specification. 2) Witness by purchaser s inspector shall in no way relieve vendor of his responsibility to meet purchaser s specification. 2. Inspection and test record 2.1 K-Flow shall provide following information in the first page of all the record inspection tests. 1) P/O No. 2) Name of client and plant location 3) Job No., Item No., and inspection 4) Name of manufacturer 5) Date of manufacture and inspection 6) Project name 2.2 The following records of filters shall be included. 1) Material check list 2) Material mill certificate 3) Dimension inspection report 4) Nondestructive examination report a) Liquid penetration or magnetic particle examination b) Radiographic examination 5) Pressure test report a) Air leak test of nozzle reinforcing pads b) Hydrostatic test 6) Rubbing sheet of name plate 7) Shop painting report

4 PROCEDURE Page 3 of 8 3. General requirement of inspection 3.1 Dimensional tolerance of filter Dimensional tolerance of filter are referred to attachment # Inspection & test plan Inspection & test procedure and acceptance standards 3.3 Material inspection K-Flow shall submit the material mill test certificates for he followings a) Shell, head and nozzle (flange, neck pipe/plate) b) Pressure retaining bolts & nuts, alloy steel bolts & nuts 1) K-Flow shall check the charge number and following items for the materials prior to fabrication of filter a) Chemical composition b) Mechanical properties c) Heat treatment d) Other items specified in the applicable cods, and purchaser s spec. 2) Inspection of materials shall be carried out in accordance with the related ASTM material code. 3.4 Visual inspection of material 1) The name or brand of the manufacturer 2) Heat No. 3) Specification number and grade, class and type 4) Quantity 5) Dimension (Include permissible variation in dimension and thickness) 6) No harmful defects on surfaces of material

5 PROCEDURE Page 4 of 8 4. Welding procedure qualification 4.1 Test procedures and acceptance standards of the welding procedure qualification shall be in accordance with the following codes and standards: ASME Sec. IX "welding qualification" and purchaser's specification 4.2 WPS & PQR shall be approved by purchaser prior to start of any welding fabrication 4.3 Welder and welding operators shall be qualified in accordance with ASME Sec. IX and Welder / Welding operator list shall be submitted to purchaser. 5. Welding control 5.1 Preheat The preheat shall be taken to ensure through thickness preheating of thick sections to prevent and excessive weld cooling rate. Surface temperature shall be measured by using of check chalk in the weld joint and 25mm on reverse side of the joint immediately before initiation of weld arc. 5.2 Interpass temperature Temperature shall be measured by digital thermometer or tempilsticks (check chalk) 5.3 Welding electrode 1) A filler metal qualification report listing the test results and the applicable filler metal heat, lot andbatch numbers must be prepared and attached to the applicable PQR. 2) Filler metals used in production must be from the same heat, lot and batch that were requalified by the steps listed above. Welder shall confirm the above item before welding 3) Storage The storage keeper shall be responsible for storage, drying and issuance of welding materials. Welding materials shall be stored in such a manner as to prevent intermingling with materials of different specifications and non-identified materials 4) The inspector shall check electrodes to minimize the moisture absorption after issuance from the welding material control room.

6 PROCEDURE Page 5 of 8 6. Inspection of welding parts Edge preparation & fit-up 1) The edge or surface of parts to be jointed by welding shall be confirmed to be uniform, smooth and clean of scale, rust, oil, grease, and other deleterious foreign material for a distance of at least 13mm from the welding joint preparation for ferrous materials and at least 51mm for non materials. 2) The inspector shall check the welding groove dimensions by angle gage in accordance with fabrication drawings under the tack welded condition prior to welding. 3) Tack welds that are to be cooperated into the final welds shall have their starting and stopping and cascaded by further grinding and/or chipping to insure corrplete fusing at the root of the joint. Alignment of section at edge to be butt welded shall be in accordance with table 1. Table 1. Nominal thickness of thinner Joint Category section at joint(t)(mm) "A"(mm) "B, C & D"(mm) t < t < t < t < t 0.25 t lesser of t or t 0.25 t t lesser of t or After completion of welding the following items shall be visually inspected. (See Sec. V of ASME Code for treatment of surface irregularities on radiographer examined welds) a) Crack not permitted, repair b) Overlap remove smoothly c) Incomplete penetration and lack of fusion not permitted, repair d) Crated remove e) Bead dripping remove, repair if necessary f) Spatter remove g) Slag and porosity non exposed h) Fitting and welded spots for temporary remove i) Under cut not exceed 0.3mm

7 PROCEDURE Page 6 of The thickness of the weld reinforcement on each face shall not exceed the value in Table 2. Material thickness Allowable thickness of t (mm) reinforcement (mm) t < t < t 3 7. Radiographic examination The welding joint of the main seams, longitudinal & circumferential joint, retaining pressure shall be performed with the radiographic examination on the base of the fabrication drawings prior to PWHT and following additional requirements. 1) When full RT is specified, the following welded joint shall be examined for their full length. a) All butt welds of category "A" and "B" in the shell and head of filters. b) Categories "B" and "C" butt welds in nozzle that exceed nps 10 inch. 2) When spot RT is specified, at least one spot for the following welded joint shall be examined. a) All welded seams defined as category "A" or "B" spots shall be selected to examine welds representing each welding procedure specification utilized each filter. b) Category "A" and "C" butt welds in nozzles that exceed nps 10 inch. 7.1 Radiographic examination procedures, techniques shall be in accordance with ASME Sec. V. Article 2. and the supplementary requirement specified in relevant specification. 7.2 The evaluation of indications and the acceptance criteria for radiographic examination shall be in accordance with ASME Sec. VIII Div. 1, para UW-51 for full radiography and spot radiography. 8. Magnetic particle or liquid penetrate examination 8.1 Magnetic particle or liquid penetrate examination of the following items shall be carried out before hydrostatic test. 1) The reverse side of double welded butt joint to be back chipped or ground 2) The removing parts of temporary weldment to the pressure retaining parts

8 PROCEDURE Page 7 of Application parts of MT or PT PT and MT shall be carried out in accordance with article 6(PT), 7(MT) of ASME Sec. V 8.3 Other defects showing any of the following which are specified in appendix 6(MT) and appendix 8(PT) of ASME Sec. VIII, Div. 1. 1) Crack and relevant linear indications 2) Length of indication exceeding 4.8mm 3) Four or more rounded defects in line separated by 1.6mm or less (edge to edge) 4) Ten or more rounded indication in any 37.5cm² or area whose major dimension is not more than 150mm with the dimensions taken in the location most unfavorable for the indications 9. Visual inspection The Visual inspection shall be carried out as follows: 1) Number, size and rating of nozzle, manhole and other fitting of filter shall be checked. 2) Deformation of filter shall be checked. 3) Machined surface such as flange face shall be checked. 4) Internal cleanliness of filter shall be checked before & after hydrostatic test. 5) Defect of filter surface shall be checked. 10. Dimensional inspection 1) Dimensions of the filter and its parts shall be checked to meet data sheet, shop drawing and their records shall be submitted to purchaser. 2) Dimensional tolerances for filter shall be as shown in the attachment #1. 3) The measurement of plate thickness shall be as follows. a) The thickness of the cylindrical shell shall be measured at min.4 point per each rolled plate. b) The thickness shall be checked after forming of head. Hydrostatic and pneumatic test 10.1 Scope of apply shall be as follows: 1) Hydrostatic test shall normally be carried out for all filters by use of clean fresh water prior to painting. The filter shall be cleaned of dirt, debris, welding slag and weld spatter prior to hydrostatic test. 2) Pneumatic test shall be carried out for reinforcement pads of nozzle.

9 PROCEDURE Page 8 of Test procedure and holding time shall be as follows: 1) The hydrostatic test pressure shall be maintained for a period of one hour. 2) The hydrostatic test pressure shall be shown on the drawing. 3) For reinforcement pads, the test shall be using shop compressed dry air. - Holding time at least 5 minutes -Holding pressure min. 5~7 kg/cm².g All welds insides and outsides shall be inspected with soap solution, and any leakage shall not be permitted 10.3 The water temperature of hydrostatic test shall be higher than 0 C 11. Painting inspection External surface of the filter shall be shop painted with anticorrosive paint and finish paint. When painting procedure is described in the specification, painting shall be performed in accordance with the specifications Surface of the filter to be painted shall be cleaned of rust, oil, dust deposits, slag, and etc Painted surfaces shall be finished evenly and smoothly, with out uneven painting portion in accordance with drawing. 12. Attachment 1. Attachment # Tolerances of Vessel (2 Sheet) 2. Attachment # Inspection and Test Plan (2 Sheet)

10 FIGURE 1a Orientation of nozzle and other attachments shall be within ±3 Longitudinal center line of vessel 3 Max. lateral translation Nozzle flange 1.5 Max. rotation of flanges from the indicated position. measured as shown FIGURE 1b Saddle height ±5 Diagonal length ±3 Distance between the centers of the anchor bolt holes ±3 Distance between the saddle center lines ±3

QC Inspection and Qualification Procedure- TX-EDU-VT-1-07, Revision # by Richard J DePue, Supersedes IW-VT-1 Visual Inspection Procedure

QC Inspection and Qualification Procedure- TX-EDU-VT-1-07, Revision # by Richard J DePue, Supersedes IW-VT-1 Visual Inspection Procedure 1.0 Scope: QC Inspection and Qualification Procedure- TX-EDU-VT-1-07, Revision #6 03-04-2016 by Richard J DePue, Supersedes IW-VT-1 Visual Inspection Procedure The purpose of this procedure is to define

More information

PART UF REQUIREMENTS FOR PRESSURE VESSELS FABRICATED BY FORGINGS

PART UF REQUIREMENTS FOR PRESSURE VESSELS FABRICATED BY FORGINGS p 1 of 6 UF-1 UF-12 PART UF REQUIREMENTS FOR PRESSURE VESSELS FABRICATED BY FORGING the test temperature be higher than 20 F ( 29 C). Certification is required. An ultrasonic examination shall be made

More information

1. Poor attitude toward any of the other students, instructors, or judges. 2. Failure to use personal protective equipment (PPE).

1. Poor attitude toward any of the other students, instructors, or judges. 2. Failure to use personal protective equipment (PPE). Welding Contest Rules and Score Sheet 2016 4G Rules: 1. Be Safe & Have Fun 2. Can tack in any position but groove welding must be in accordance with your WPS. 3. Can use wire brush, chipping hammer, and

More information

WELDING PROCEDURE SPECIFICATION. Shielded Metal Arc Welding-SMAW

WELDING PROCEDURE SPECIFICATION. Shielded Metal Arc Welding-SMAW WELDING PROCEDURE SPECIFICATION Shielded Metal Arc Welding-SMAW WPS Number: WPS-SMAW-CS Revision: 0 Company Name & Address ABC WELDING & FABRICATING 123 WeldProc Boulevard Toronto, ON A1B 2C3 CWB Approval

More information

API-582. a practical approach for industrial welding practices. All rights reserved to thepetrostreet team

API-582. a practical approach for industrial welding practices. All rights reserved to thepetrostreet team Recommended Welding Guidelines API-582 a practical approach for industrial welding practices By The PetroStreet Team CONTENTS Key Sections: Θ Section 6 WELDING CONSUMABLES Θ Section 7 SHIELDING AND PURGING

More information

UNIFIED FACILITIES GUIDE SPECIFICATIONS

UNIFIED FACILITIES GUIDE SPECIFICATIONS USACE / NAVFAC / AFCEC / NASA UFGS-40 17 26.00 20 (April 2006) -------------------------------- Preparing Activity: NAVFAC Replacing without change UFGS-15216N (September 1999) UNIFIED FACILITIES GUIDE

More information

M. F. Sullivan. 9/27/2016 Dr. Sandor Somogyi

M. F. Sullivan. 9/27/2016 Dr. Sandor Somogyi The Code is a large document and it is sometimes very difficult to understand. Even for many of us who work with it every day. In my opinion there is no one person who could be termed as a Code Expert.

More information

ASME B31.3 Process Piping

ASME B31.3 Process Piping ASME B31.3 Process Piping Charles Becht IV, PhD, PE Don Frikken, PE Instructors BECHT ENGINEERING COMPANY, INC. Fabrication and Installation - 1 Piping Development Process 1. Establish applicable system

More information

Cast Steel Propellers W27. (May 2000) (Rev.1 May 2004)

Cast Steel Propellers W27. (May 2000) (Rev.1 May 2004) (May 2000) (Rev.1 May 2004) Cast Steel Propellers 1. Scope 1.1 These unified requirements are applicable to the manufacture of cast steel propellers, blades and bosses. 1.2 Where the use of alternative

More information

METHOD STATEMENT FOR PIPE WELDING WORKS

METHOD STATEMENT FOR PIPE WELDING WORKS METHOD STATEMENT FOR PIPE WELDING WORKS Introduction This Method statement describes in detail the welding process for pipe work and the welder s qualification test procedures. This includes addressing

More information

Welding Inspection Defects/Repairs Course Reference WIS 5

Welding Inspection Defects/Repairs Course Reference WIS 5 Copy from Welding Inspection Defects/Repairs Course Reference WIS 5 Weld Defects Defects which may be detected by visual inspection can be grouped under five headings Cracks Surface irregularities Contour

More information

Inspection and Welding Repairs of Pressure Vessels

Inspection and Welding Repairs of Pressure Vessels Inspection and Welding Repairs of Pressure Vessels BY S. V. GUPTE B.E., D.M.E. ASNT LEVEL III - RT,MT,PT,VT PRESSURE VESSEL INSPECTOR (API 510), (CCOE) PAINT AND COATING INSPECTOR (NACE INDIA) LEAD AUDITOR

More information

Standard Specification for Piping Fittings of Wrought Carbon Steel and Alloy Steel for Low-Temperature Service 1

Standard Specification for Piping Fittings of Wrought Carbon Steel and Alloy Steel for Low-Temperature Service 1 Designation: A 420/A 420M 07 Standard Specification for Piping Fittings of Wrought Carbon Steel and Alloy Steel for Low-Temperature Service This standard is issued under the fixed designation A 420/A 420M;

More information

INSPECTION OF FIELD WELDING

INSPECTION OF FIELD WELDING INSPECTION OF FIELD WELDING Objective Types of Projects Involving Welding Common Welding Terms & Symbols Welder Qualifications Common Welding Requirements Welding Inspection Types of Projects Involving

More information

AWS B1.10:1999 An American National Standard. Guide for the Nondestructive Examination of Welds

AWS B1.10:1999 An American National Standard. Guide for the Nondestructive Examination of Welds AWS B1.10:1999 An American National Standard Guide for the Nondestructive Examination of Welds Key Words Guide, eddy current examination, magnetic particle examination, nondestructive examination, penetrant

More information

STANDARD SPECIFICATIONS FOR PIPING - WELDING DOCUMENT NO : Z SS 005 PREVIOUS DOC. NO. : BSS-26-03/1

STANDARD SPECIFICATIONS FOR PIPING - WELDING DOCUMENT NO : Z SS 005 PREVIOUS DOC. NO. : BSS-26-03/1 Page 1 of 1 STANDARD SPECIFICATIONS FOR PIPING - WELDING DOCUMENT NO : Z SS 005 PREVIOUS DOC. NO. : BSS-26-03/1 Rev No. Issue Date Pages Rev Description Prepared By Checked By Approved By 0 02.11.2001

More information

PART 5 WELDING. 5.1 General 5.2 Preparation 5.3 Dimensions of welds 5.4 Materials 5.5 Aluminium alloys 5.6 Welding details 5.

PART 5 WELDING. 5.1 General 5.2 Preparation 5.3 Dimensions of welds 5.4 Materials 5.5 Aluminium alloys 5.6 Welding details 5. PART 5 WELDING PART 5 WELDING SECTION SUBJECT 5.1 General 5.2 Preparation 5.3 Dimensions of welds 5.4 Materials 5.5 Aluminium alloys 5.6 details 5.7 Symbols WELDING Section 5.1 General 5.1.1 of structures

More information

WELDER S. Visual Inspection HANDBOOK. May 2013

WELDER S. Visual Inspection HANDBOOK. May 2013 WELDER S Visual Inspection HANDBOOK May 2013 -- NOTE -- This handbook is NOT intended to serve as a work procedure or to replace any existing procedures. It is solely intended to provide basic information

More information

ANSI/AWS D An American National Standard. Structural Welding Code Sheet Steel

ANSI/AWS D An American National Standard. Structural Welding Code Sheet Steel ANSI/AWS D1.3-98 An American National Standard Structural Welding Code Sheet Steel Key Words Sheet steel, allowable stresses, details of welded joints, workmanship qualification, visual acceptance criteria,

More information

North Atlantic ENGINEERING STANDARD SPECIFICATION 1/7 REV. QUALITY SLAG BOWL WELDING AND QUALITY REQUIREMENTS. Approved by.

North Atlantic ENGINEERING STANDARD SPECIFICATION 1/7 REV. QUALITY SLAG BOWL WELDING AND QUALITY REQUIREMENTS. Approved by. 1/7 Rev Description Revision by Approved by Issue Date YYYY/MM/DD 1 Update from Job 497-01 KLR 015/04/01 Updated 1.0 and 4.3 PB 016/03/09 KLR 015/04/01 PB 016/03/09 015/04/01 016/03/09 Sud = Sudbury, Ontario,

More information

QUALIFICATION TESTING OF FIELD WELDERS

QUALIFICATION TESTING OF FIELD WELDERS Page 1 of 9 Oklahoma DOT Materials & Testing December 5, 2003 (Updated to Reference 2009 Specifications 11/26/2012) (Added paragraph to the bottom of Roles and Responsibilities section. 11/14/2017) Publication:

More information

AWS B1.10M/B1.10:2009 An American National Standard. Guide for the Nondestructive Examination of Welds

AWS B1.10M/B1.10:2009 An American National Standard. Guide for the Nondestructive Examination of Welds An American National Standard Guide for the Nondestructive Examination of Welds An American National Standard Approved by the American National Standards Institute July 1, 2009 Guide for the Nondestructive

More information

MATERIAL REQUISITION FOR BOLTS AND NUTS

MATERIAL REQUISITION FOR BOLTS AND NUTS Title: MATERIAL REQUISITION FOR BOLTS AND NUTS Page: 1 of 12 MATERIAL REQUISITION FOR BOLTS AND NUTS 6 5 4 3 2 1 0 08-JUN-2013 ISSUED FOR APPROVAL M. KAMALOU A.MOHAMADIZADE A.MOHAMADIZADE REV. DATE STATUS

More information

A. Submit submittal packages in accordance with Standard Specification Section B. Submit an affidavit of compliance with AWWA C200 and C205.

A. Submit submittal packages in accordance with Standard Specification Section B. Submit an affidavit of compliance with AWWA C200 and C205. STANDARD SPECIFICATION SECTION 15061 STEEL TRANSMISSION PIPE PART 1 - GENERAL 1.01 DESCRIPTION This section includes materials, design, fabrication, and testing of cement mortar lined and di-electric coated

More information

Standard Specification for Piping Fittings of Wrought Carbon Steel and Alloy Steel for Moderate and High Temperature Service 1

Standard Specification for Piping Fittings of Wrought Carbon Steel and Alloy Steel for Moderate and High Temperature Service 1 Designation: A 234/A 234M 02 Used in USDOE-NE Standards An American National Standard Standard Specification for Piping Fittings of Wrought Carbon Steel and Alloy Steel for Moderate and High Temperature

More information

welder certification welder performance qualification

welder certification welder performance qualification Chapter 29 Welder Certification OBJECTIVES After completing this chapter, the student should be able : Explain welder qualification and certification. Outline the steps required certify a welder. Make

More information

SPECIFICATION FOR SPHERICAL VESSELS (PROJECT STANDARDS AND SPECIFICATIONS)

SPECIFICATION FOR SPHERICAL VESSELS (PROJECT STANDARDS AND SPECIFICATIONS) Page : 1 of 1 April 01 #03-1 Block Aronia, TABLE OF CONTENTS 1. GENERAL 1.1 Scope. DESIGN.1 Shell Design. Support Column Design.3 Opening Reinforcement. Nozzles and Manholes.5 Internals and Externals.

More information

American Welding Society Nashville Section. Welding Procedure Development

American Welding Society Nashville Section. Welding Procedure Development American Welding Society Nashville Section Welding Procedure Development AWS & ASME Welding Procedures Welding Procedure Specification (WPS) Written document that provides direction to the welder for making

More information

MILITARY SPECIFICATION WELDING, ARC AND GAS; FOR FABRICATING GROUND EQUIPMENT FOR ROCKETS AND GUIDED MISSILES

MILITARY SPECIFICATION WELDING, ARC AND GAS; FOR FABRICATING GROUND EQUIPMENT FOR ROCKETS AND GUIDED MISSILES INCH-POUND 30 June 1992 SUPERSEDING MIL-W-47091 (MI) 24 May 1974 MILITARY SPECIFICATION WELDING, ARC AND GAS; FOR FABRICATING GROUND EQUIPMENT FOR ROCKETS AND GUIDED MISSILES This specification is approved

More information

SECTION REINFORCING STEEL

SECTION REINFORCING STEEL SECTION REINFORCING STEEL 1. DESCRIPTION This specification shall govern the furnishing and placing of reinforcing steel, deformed and smooth, of the size and quantity designated on the plans and in accordance

More information

Stainless Steel Aeration Equipment Specification

Stainless Steel Aeration Equipment Specification Section 15 Stainless Steel Aeration Equipment Specification Part 1 - General 1.01 Description A. Scope of Work 1. Furnish, install and test aeration system including air mains, drop pipes, valves, expansion

More information

ANSI/AWS D R An American National Standard. Recommended Practices for Root Pass Welding of Pipe Without Backing

ANSI/AWS D R An American National Standard. Recommended Practices for Root Pass Welding of Pipe Without Backing ANSI/AWS D10.11-87R An American National Standard Recommended Practices for Root Pass Welding of Pipe Without Backing Key WordS Root pass welding, pipe, gas purging, consumable inserts, gas tungsten arc,

More information

ASME B31.3 Process Piping. 19. What s Different in B31.1

ASME B31.3 Process Piping. 19. What s Different in B31.1 ASME B31.3 Process Piping Charles Becht IV, PhD, PE Don Frikken, PE Instructors BECHT ENGINEERING COMPANY, INC. What s Different in B31.1-1 19. What s Different in B31.1 Scope Organization of the Code

More information

PROJECT KCIL-FORMALDEHYDE DESCRIPTION GENERAL ENGINEERING SPECIFICATION PRESSURE VESSELS DOCUMENT NO MQ-UGS-0001

PROJECT KCIL-FORMALDEHYDE DESCRIPTION GENERAL ENGINEERING SPECIFICATION PRESSURE VESSELS DOCUMENT NO MQ-UGS-0001 A company of ThyssenKrupp Technologies Uhde India PROJECT KCIL-FORMALDEHYDE UAN 66-6481-700 3. REFERENCE UHDE STANDARDS DESCRIPTION GENERAL ENGINEERING SPECIFICATION PRESSURE VESSELS DOCUMENT NO. 6481-MQ-UGS-0001

More information

IGS-M-PL-033(1) April Approved مصوب IGS. Hot Tapping Split Tee. Fax:(9821)

IGS-M-PL-033(1) April Approved مصوب IGS. Hot Tapping Split Tee. Fax:(9821) IGS-M-PL-033(1) April. 2016 Approved مصوب شركت ملي گازايران مديريت پژوهش و فنĤوري امورتدوين استانداردها IGS مشخصات فني خريد اتصال سه راهي انشعاب گرم Hot Tapping Split Tee Fax:(9821)-8487-5032 براي استفاده

More information

AASHTO/AWS D1.5M/D1.5:2008. Table of Contents

AASHTO/AWS D1.5M/D1.5:2008. Table of Contents Table of Contents Personnel...v Foreword...ix List of Tables... xviii List of Figures...xix List of Forms...xxi 1. General Provisions...1 1.1 Application...1 1.2 Base Metal...1 1.3 Welding Processes...1

More information

Section 906. STRUCTURAL STEEL

Section 906. STRUCTURAL STEEL 906.01 Section 906. STRUCTURAL STEEL 906.01. General Requirements. Finished rolled shapes must be free from imperfections that affect strength and durability in accordance with ASTM A 6. Rolled shapes

More information

WELDING PROCEDURE SPECIFICATION NO

WELDING PROCEDURE SPECIFICATION NO NATIONAL CERTIFIED PIPE WELDING BUREAU WELDING PROCEDURE SPECIFICATION NO. 45-32-1 FOR GAS TUNGSTEN ARC WELDING (GTAW) AND SHIELDED METAL ARC WELDING (SMAW) OF NICKEL ALLOY 20 (UNS N08020) PIPE, VALVES,

More information

DIVISION: METALS SECTION: STRUCTURAL STEEL FRAMING REPORT HOLDER: CAST CONNEX CORPORATION

DIVISION: METALS SECTION: STRUCTURAL STEEL FRAMING REPORT HOLDER: CAST CONNEX CORPORATION 0 Most Widely Accepted and Trusted ICC ES Evaluation Report ICC ES 000 (800) 423 6587 (562) 699 0543 www.icc es.org ESR 3031 Reissued 12/2017 This report is subject to renewal 12/2019. DIVISION: 05 00

More information

BODY OF KNOWLEDGE API-570 AUTHORIZED PIPING INSPECTOR CERTIFICATION EXAMINATION

BODY OF KNOWLEDGE API-570 AUTHORIZED PIPING INSPECTOR CERTIFICATION EXAMINATION BODY OF KNOWLEDGE API-570 AUTHORIZED PIPING INSPECTOR CERTIFICATION EXAMINATION 2018 (Replaces February 2017) API Authorized Piping Inspectors must have a broad knowledge base relating to maintenance,

More information

GENERAL CONTENTS SECTION I - NUCLEAR ISLAND COMPONENTS

GENERAL CONTENTS SECTION I - NUCLEAR ISLAND COMPONENTS - June 2013 Addendum GENERAL CONTENTS SECTION I - NUCLEAR ISLAND COMPONENTS SUBSECTION "A" : GENERAL RULES SUBSECTION "B" : CLASS 1 COMPONENTS SUBSECTION "C" : CLASS 2 COMPONENTS SUBSECTION "D" : CLASS

More information

Module 4 Design for Assembly

Module 4 Design for Assembly Module 4 Design for Assembly Lecture 2 Design for Welding-I Instructional Objective By the end of this lecture, the student will learn: (a) how a weld joint should be designed to improve the joint performance,

More information

PART 2 REPAIR WELDING CONSIDERATIONS FOR Cr-Mo STEEL PRESSURE VESSELS ARTICLE 2.15 Guide for Selection of Repair Technique. Local wall Pitting

PART 2 REPAIR WELDING CONSIDERATIONS FOR Cr-Mo STEEL PRESSURE VESSELS ARTICLE 2.15 Guide for Selection of Repair Technique. Local wall Pitting Proposed Supplement to PCC-2 2015 Repair of Pressure Equipment and Piping Tentative Subject to Revision or Withdrawal Specific Authorization Required for Reproduction or Quotation ASME Codes and Standards

More information

WELDING PROCEDURE SPECIFICATION NO

WELDING PROCEDURE SPECIFICATION NO NATIONAL CERTIFIED PIPE WELDING BUREAU WELDING PROCEDURE SPECIFICATION NO. 1-7-1 FOR GAS METAL ARC WELDING WITH FLUXCORE WIRE (GMAW-FC) SEMI-AUTOMATIC OR MACHINE OF CARBON STEEL PIPE, VALVES, FITTINGS

More information

welding equipment Prepare and use manual TIG or plasma-arc Performance evidence required You must be able to:

welding equipment Prepare and use manual TIG or plasma-arc Performance evidence required You must be able to: 006 UNIT 028 Preparing and using manual TIG or plasma-arc Learning outcomes 1 2 Know how to prepare and use manual TIG or plasma-arc Performance evidence must be the main form of evidence gathered. Candidates

More information

Owner: Purchaser: Unit No.:

Owner: Purchaser: Unit No.: Owner: KPIC Costumer: Namvaran namvaran Consulting Engineers Managers Stack-4201 Location: Kermanshah- Iran K.P.I.C. Document No.: SEC-PJ045-ST-IFP-0008-3 SEC-Project No.: PJ045 Radiography Test Procedure

More information

Comparison of BS and BS EN for steel materials

Comparison of BS and BS EN for steel materials Comparison of BS and BS EN for steel materials Appendix This table only highlights the comparison of BS and BS EN on steel materials, which are relevant to plan approval. Title of BS BS BS EN Title of

More information

API 653 Training Course

API 653 Training Course API 653 Training Course The API 653 Classes consist of "Pre-Course Home Study" materials and "5 days of Classroom" instructor lead training. Registration for the API 653 Training Course should be received

More information

PART PG GENERAL REQUIREMENTS FOR ALL METHODS OF CONSTRUCTION

PART PG GENERAL REQUIREMENTS FOR ALL METHODS OF CONSTRUCTION CONTENTS Foreword... xv Statements of Policy... xvii Personnel... xix Preamble... xxxi Summary of Changes... xxxiii List of Changes in BC Order... xxxvi PART PG GENERAL REQUIREMENTS FOR ALL METHODS OF

More information

Inspection and Test Plan for Gas Turbine

Inspection and Test Plan for Gas Turbine and Test Plan for Gas Turbine No. and Test Plan Reference Document Acceptance Criteria Verifying Document Activity By Remark Manuf. TPI Client 1 Pre Meeting Spec. Spec. MOM H H H Before Manufacturing 2

More information

Pipeline Systems PIP PLSC0013 Non-Destructive Examination of ASME B31.4 and B31.8 Metallic Pipelines

Pipeline Systems PIP PLSC0013 Non-Destructive Examination of ASME B31.4 and B31.8 Metallic Pipelines February 2017 Pipeline Systems PIP PLSC0013 Non-Destructive Examination of ASME B31.4 and B31.8 Metallic Pipelines PURPOSE AND USE OF PROCESS INDUSTRY PRACTICES In an effort to minimize the cost of process

More information

Subsection B REQUIREMENTS PERTAINING TO METHODS OF FABRICATION OF PRESSURE VESSELS

Subsection B REQUIREMENTS PERTAINING TO METHODS OF FABRICATION OF PRESSURE VESSELS Subsection B REQUIREMENTS PERTAINING TO METHODS OF FABRICATION OF PRESSURE VESSELS PART UW General UW-1 Scope... 113 UW-2 Service Restrictions... 113 UW-3 Welded Joint Category... 114 Materials UW-5 General...

More information

Weld Imperfections and Preventive Measures

Weld Imperfections and Preventive Measures FOURTH EDITION Weld Imperfections and Preventive Measures Published by FOURTH EDITION Weld Imperfections and Preventive Measures Kita-Shinagawa, Shinagawa-Ku, Tokyo, 141-8688 Japan Published by KOBE STEEL,

More information

UNIFIED FACILITIES GUIDE SPECIFICATIONS

UNIFIED FACILITIES GUIDE SPECIFICATIONS USACE / NAVFAC / AFCEC / NASA UFGS-05 05 23.16.16 (May 2014) ----------------------------- Preparing Activity: USACE Superseding UFGS-05 05 23 (November 2008) UNIFIED FACILITIES GUIDE SPECIFICATIONS References

More information

Draft - For Committee Use Only

Draft - For Committee Use Only Draft for SCAST Ballot Agenda Item 6-292 Revisions to App Q and R to Coordinate with New API 625 Standard Revision: 0 Date: August, 08 Handled by: Doug Miller RTTG Chair Chicago Bridge and Iron Company

More information

REMOVAL OF CAST LIP STEP 1 STEP 2. Layout cut lines, based on existing welds and verify with dimension taken from new lip. STEP 3

REMOVAL OF CAST LIP STEP 1 STEP 2. Layout cut lines, based on existing welds and verify with dimension taken from new lip. STEP 3 REMOVAL OF CAST LIP STEP 1 fig. 1-1 Brace clam from cheek plate to cheek plate (A). Brace clam from bucket floor, (just behind back of lip joint), to upper cheek plate on both sides (B). The purpose of

More information

Item 448 Structural Field Welding

Item 448 Structural Field Welding Item 448 Structural Field Welding 1. DESCRIPTION 2. MATERIALS Field-weld metal members using the shielded metal arc or flux cored arc welding processes. Provide electrodes for shielded metal arc welding

More information

LAGUARDIA COMMUNITY COLLEGE - CUNY August 3, 2009

LAGUARDIA COMMUNITY COLLEGE - CUNY August 3, 2009 SECTION 051200 - STRUCTURAL STEEL FRAMING PART 1 - GENERAL 1.01 SUMMARY A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division 1 Specification

More information

Standard Specification for Wrought Austenitic Stainless Steel Piping Fittings 1

Standard Specification for Wrought Austenitic Stainless Steel Piping Fittings 1 Designation: A 403/A 403M 06 Standard Specification for Wrought Austenitic Stainless Steel Piping Fittings 1 This standard is issued under the fixed designation A 403/A 403M; the number immediately following

More information

BOOK OF SPECIFICATIONS

BOOK OF SPECIFICATIONS American Welding Society CERTIFICATION www.aws.org CERTIFIED WELDING INSPECTOR (CWI) PART B PRACTICAL EXAMINATION BOOK OF SPECIFICATIONS JANUARY 1, 2016 January 1, 2016 This page is intentionally blank.

More information

CONCRETE STEPS, HANDRAILS, AND SAFETY RAIL

CONCRETE STEPS, HANDRAILS, AND SAFETY RAIL SUDAS Standard Specifications Division 9 - Site Work and Landscaping Section 9080 - Concrete Steps, Handrails, and Safety Rail CONCRETE STEPS, HANDRAILS, AND SAFETY RAIL PART - GENERAL.0 SECTION INCLUDES

More information

Project Execution Tender to Design to Fabrication

Project Execution Tender to Design to Fabrication Project Execution Tender to Design to Fabrication Brief Overview of the Main Activities from Tender stage to Fabrication of ASME VIII Vessel Presented By: HS Compression & Process Pte Ltd (Member of Hiap

More information

Materials and Qualification Procedures for Ships

Materials and Qualification Procedures for Ships Materials and Qualification Procedures for Ships Approval of Works for the Manufacture of Fusion Welded Pressure Vessels Revision 4, July 2015 Page 1 of 17 Lloyd s Register Group Limited, its subsidiaries

More information

Design for welding: Design recommendations

Design for welding: Design recommendations Design for welding: Design recommendations Arc welding can be used to weld almost any kind of assembly, including even complex structures. Arc weldments use a wide variety of ferrous and non ferrous metals.

More information

STANDARD TECHNICAL SPECIFICATION FOR FLOW NOZZLE ASSEMBLY with ACCESSORIES

STANDARD TECHNICAL SPECIFICATION FOR FLOW NOZZLE ASSEMBLY with ACCESSORIES STANDARD TECHNICAL SPECIFICATION FOR FLOW NOZZLE ASSEMBLY with ACCESSORIES VOLUME - IIB SECTIONS-C & D SPECIFICATION No: PE-TS-XXX-145-I105B BHARAT HEAVY ELECTRICALS LIMITED POWER SECTOR PROJECT ENGINEERING

More information

Specification for Welding Earthmoving, Construction, and Agricultural Equipment

Specification for Welding Earthmoving, Construction, and Agricultural Equipment Key Words Structural welds, field repair, welding, earthmoving equipment, construction equipment, agricultural equipment AWS D14.3/D14.3M:2005 An American National Standard Approved by American National

More information

FABRICATION OF HEAVY WALL Cr-Mo / Cr-Mo-V REACTORS CHALLENGES AND TECHNOLOGY UPGRADATION AT LARSEN & TOUBRO LIMITED INDIA

FABRICATION OF HEAVY WALL Cr-Mo / Cr-Mo-V REACTORS CHALLENGES AND TECHNOLOGY UPGRADATION AT LARSEN & TOUBRO LIMITED INDIA FABRICATION OF HEAVY WALL Cr-Mo / Cr-Mo-V REACTORS CHALLENGES AND TECHNOLOGY UPGRADATION AT LARSEN & TOUBRO LIMITED INDIA Pallav Chattopadhyay, B K Rai & Y S Trivedi Larsen & Toubro Limited India Abstract:

More information

UNIFIED FACILITIES GUIDE SPECIFICATIONS

UNIFIED FACILITIES GUIDE SPECIFICATIONS USACE / NAVFAC / AFCEC / NASA UFGS-40 17 30.00 40 (May 2016) ----------------------------------- Preparing Activity: NASA Superseding UFGS-40 17 30.00 40 (August 2010) UFGS-23 31 13.20 40 (February 2009)

More information

Guidelines To Gas Metal Arc Welding (GMAW)

Guidelines To Gas Metal Arc Welding (GMAW) Guidelines To Gas Metal Arc Welding (GMAW) WARNING ARC WELDING can be hazardous. This document contains general information about the topics discussed herein. This document is not an application manual

More information

NAVIGATING ASME SECTION VIII (DIV.1): MANAGING YOUR PRESSURE VESSELS - PART 1 FEATURING:

NAVIGATING ASME SECTION VIII (DIV.1): MANAGING YOUR PRESSURE VESSELS - PART 1 FEATURING: January/February 2014 Volume 20, Issue 1 Since 1995, Inspectioneering Journal has provided the oil & gas and chemical industries with information to help optimally manage equipment risk and reliability,

More information

The Impact Testing Enigma A Review of ASME Section VIII, Division 1, Subsection C, Part UCS, Impact Testing Requirements

The Impact Testing Enigma A Review of ASME Section VIII, Division 1, Subsection C, Part UCS, Impact Testing Requirements the pressure equipment safety authority The Impact Testing Enigma A Review of ASME Section VIII, Division 1, Subsection C, Part UCS, Impact Testing Requirements AB-511 Edition 2, Revision 1 Issued 2017-05-03

More information

INSPECTION OF PRESSURE VESSELS TO ASME Section VIII Div. 1

INSPECTION OF PRESSURE VESSELS TO ASME Section VIII Div. 1 TAKING PRESSURE VESSELS FROM CRADLE TO GRAVE SEMINAR INSPECTION OF PRESSURE VESSELS TO ASME Section VIII Div. 1 Manish Waghare ABSG Consulting Inc., Singapore January 28, 2011 May 29, 2011 1 Presentation

More information

WLD 152 Wire Welding Certification Practice

WLD 152 Wire Welding Certification Practice WLD 152 Wire Welding Certification Practice Index Course Information Accessing ebook and coursemate info. 3 4 Science on Steel 6-10 Craftsmanship Expectations 11 Welding Projects with Information Sheets

More information

Conformity Assessment. Dan Cheetham Welding and NDE 4/12/16

Conformity Assessment. Dan Cheetham Welding and NDE 4/12/16 Conformity Assessment Dan Cheetham Welding and NDE 4/12/16 Welding & NDE requirements Welding What is required for compliance with AMSE Code? -Welding Procedures and welder/welding operators qualified

More information

UNIFIED FACILITIES GUIDE SPECIFICATIONS

UNIFIED FACILITIES GUIDE SPECIFICATIONS USACE / NAVFAC / AFCEC / NASA UFGS-34 11 19.00 20 (April 2006) -------------------------------- Preparing Activity: NAVFAC Replacing without change UFGS-05652N (September 1999) UNIFIED FACILITIES GUIDE

More information

QW-482 WELDING PROCEDURE SPECIFICATION (WPS)

QW-482 WELDING PROCEDURE SPECIFICATION (WPS) QW-482 WELDING PROCEDURE SPECIFICATION (WPS) Company Name: J.T. Thorpe & Son, Inc. By: J. Jacob Dupree, P.E., Q.C. Manager Welding Procedure Specification No.: JTT-22-STUD Revision No. 0 Date: 4/15/2009

More information

INSULATED JOINTS. Monolithic Joints for Electrically Isolating Pipelines

INSULATED JOINTS. Monolithic Joints for Electrically Isolating Pipelines INSULATED JOINTS Monolithic Joints for Electrically Isolating Pipelines INSULATED JOINTS TUBE TURNS INSULATED JOINTS are a pre-fabricated, non-separable, union used to isolate specific sections of pipelines

More information

RULES FOR THE CLASSIFICATION OF SHIPS

RULES FOR THE CLASSIFICATION OF SHIPS RULES FOR THE CLASSIFICATION OF SHIPS 2009 Part 26 - WELDING Amendments No.1 CROATIAN REGISTER OF SHIPPING Hrvatska (Croatia) 21000 Split Marasovićeva 67 P.O.B. 187 Tel.: (...) 385 (0)21 40 81 11 Fax.:

More information

Preparing and using manual TIG or plasma-arc welding equipment

Preparing and using manual TIG or plasma-arc welding equipment Unit 028 Preparing and using manual TIG or plasma-arc welding equipment Level: 2 Credit value: 15 NDAQ number: 500/9514/6 Unit aim This unit covers the skills and knowledge needed to prove the competences

More information

UFGS (February 2009) UNIFIED FACILITIES GUIDE SPECIFICATIONS

UFGS (February 2009) UNIFIED FACILITIES GUIDE SPECIFICATIONS USACE / NAVFAC / AFCESA / NASA UFGS-40 17 30.00 40 (August 2010) Change 1-11/12 ----------------------------------- Preparing Activity: NASA Superseding UFGS-23 31 13.20 40 (February 2009) UNIFIED FACILITIES

More information

Joint Surface Preparation Standard. NACE No. 3/SSPC-SP 6 Commercial Blast Cleaning

Joint Surface Preparation Standard. NACE No. 3/SSPC-SP 6 Commercial Blast Cleaning Item No. 21067 Joint Surface Preparation Standard NACE No. 3/SSPC-SP 6 Commercial Blast Cleaning This NACE International (NACE)/SSPC: The Society for Protective Coatings standard represents a consensus

More information

SECTION III DIVISIONS 1 AND 2

SECTION III DIVISIONS 1 AND 2 SECTION III DIVISIONS 1 AND 2 Subject Interpretation File No. Division 1 Appendix N, Table N-1230-1; Damping Values (1998 Edition)... III-1-04-27 NI03-025 Code Cases 2142-1 and 2143-1... III-1-04-22 NI03-019

More information

Piping at Static Cryogenic Vessels according to EN and EN / AD2000 Merkblatt IGV Position Paper IGV-PP-05B-Rev1-E

Piping at Static Cryogenic Vessels according to EN and EN / AD2000 Merkblatt IGV Position Paper IGV-PP-05B-Rev1-E Piping at Static Cryogenic Vessels according to EN 13458 and EN 13480 / AD2000 Merkblatt IGV Position Paper Ind Industriegaseverband e.v. Französische Str. 8 10117 Berlin Telefon: 030 206 458-800 Telefax:

More information

SECTION STRUCTURAL STEEL

SECTION STRUCTURAL STEEL SECTION 05120 PART I - GENERAL 1.01 DESCRIPTION A. Scope: Work under this Section shall include all materials and installation necessary to provide Structural Steel as shown and detailed on the Drawings

More information

5. POST-EARTHQUAKE INSPECTION

5. POST-EARTHQUAKE INSPECTION 5. POST-EARTHQUAKE INSPECTION When required by the building official, or recommended by the Interim Guidelines in Chapter 4, post-earthquake inspections of buildings may be conducted in accordance with

More information

SSPC: The Society for Protective Coatings. Commercial Blast Cleaning

SSPC: The Society for Protective Coatings. Commercial Blast Cleaning SSPC: The Society for Protective Coatings Joint Surface Preparation Standard SSPC-SP 6/NACE No. 3 Commercial Blast Cleaning This The Society for Protective Coatings (SSPC)/NACE International (NACE) standard

More information

Preparing and using manual metal arc welding equipment

Preparing and using manual metal arc welding equipment Unit 827 Preparing and using manual metal arc welding equipment UAN: J/600/5889 Level: Level 2 Credit value: 15 GLH: 68 Relationship to NOS: Endorsement by a sector or regulatory body: Aim: This unit has

More information

Application Guidelines

Application Guidelines Application Guidelines 1.0 SCOPE This document contains general instructions and recommended practices for the application of the SERVIWRAP cold applied tape coating system. The various coating grades

More information

QUALITY ASSURANCE SPECIFICATION WELDING HEAT TREATMENT PAGE 1 OF 6

QUALITY ASSURANCE SPECIFICATION WELDING HEAT TREATMENT PAGE 1 OF 6 QUALITY ASSURANCE SPECIFICATION REVISION: 0 DATE: 08/29/14 WELDING HEAT TREATMENT PAGE 1 OF 6 1.0 Purpose The purpose of this specification is to establish the minimum quality assurance requirements for

More information

SUPPLIER QUALITY ASSURANCE REQUIREMENTS

SUPPLIER QUALITY ASSURANCE REQUIREMENTS The following supplier quality assurance requirements, referenced by number on the Purchase Order, are an integral part of each order placed by Groth Corporation or Groth Continental Manufacturing Private

More information

Reinforced Thermoset Plastic Corrosion-Resistant Equipment

Reinforced Thermoset Plastic Corrosion-Resistant Equipment ASME RTP-1 2007 (Revision of ASME RTP-1 2005) Reinforced Thermoset Plastic Corrosion-Resistant Equipment AN AMERICAN NATIONAL STANDARD Three Park Avenue New York, NY 10016 Date of Issuance: April 9, 2008

More information

SPECIFICATION FOR PRESSURE VESSEL PLATES, CARBON STEEL, FOR MODERATE- AND LOWER-TEMPERATURE SERVICE

SPECIFICATION FOR PRESSURE VESSEL PLATES, CARBON STEEL, FOR MODERATE- AND LOWER-TEMPERATURE SERVICE Technical Literature: ASME SA-516 [ASTM A516] Company Website: www.metalspiping.com SA-516/SA-516M Carbon & Low Alloy Steels From Hebei Metals Industrial Limited SPECIFICATION FOR PRESSURE VESSEL PLATES,

More information

REFERENCE SYLLABUS. for WELDING EXAMINER & WELDING EXAMINER IN TRAINING CERTIFICATES OF COMPETENCY EXAMINATIONS

REFERENCE SYLLABUS. for WELDING EXAMINER & WELDING EXAMINER IN TRAINING CERTIFICATES OF COMPETENCY EXAMINATIONS WELDING EXAMINER & CERTIFICATES OF COMPETENCY S AB-94 Edition 1, Revision 6, 2016-05-01 This syllabus is being phased out and will be discontinued on April 30, 2018. GENERAL INFORMATION INTRODUCTION: This

More information

A Comparison: ASME B31.1 Power Piping versus ASME B31.3 Process Piping

A Comparison: ASME B31.1 Power Piping versus ASME B31.3 Process Piping A Comparison: ASME B31.1 Power Piping versus ASME B31.3 Process Piping Don Frikken, PE BECHT ENGINEERING COMPANY, INC. 1 Topics Discussed B31 History Scopes Organization of the Codes Bases for Allowable

More information

71T1 - Gas Shielded Flux Cored Welding Wire Provides excellent performance in all position welding. Weld Metal - Chemistry

71T1 - Gas Shielded Flux Cored Welding Wire Provides excellent performance in all position welding. Weld Metal - Chemistry Flux Cored Wire 71T1 - Gas Shielded Flux Cored Welding Wire Provides excellent performance in all position welding Description: Provides a stable arc, low spatter, easy to remove slag, and neat weld metal.

More information