Centraflow Introduction

Size: px
Start display at page:

Download "Centraflow Introduction"

Transcription

1 Centraflow Introduction Company established in September 2015 ipark, Stavanger Two office locations: Blackburn, Aberdeen Centraflow is focused on the design and development of downhole flow diversion technology

2 Problem Definition Cementing casing or liner with poor stand off (~below 67 %) can lead to mud channeling and lack of zonal isolation leading to sustained casing pressure, formation X flow or loss of production. Good casing centralization is key, rotation is preferred. BUT: often we can t rotate casing and actual stand off is often less than 50%. If we have an eccentric annulus with greater flow area on the high side, fluid will follow the path of least resistance. This leads to a velocity imbalance velocity on the high side of the wellbore is much greater than the velocity on the low side. If fluid moves too slowly on the low side, residual cuttings and filter cake cannot be removed and effective cement displacement cannot take place.

3 Downhole Flow Diversion Introducing a restriction into the casing wellbore annulus on the high side of the wellbore creates a velocity inversion effect. Increasing the low side velocity above the critical transportation rate removes residual cuttings and filter cake from underneath the casing. Low side channels are eliminated and full circumferential cement displacement can be achieved.

4 The theory in practice Please refer to flow loop video on our homepage:

5 Physical Flow Loop Cement Testing The flow loop represents a scaled 12 1/4" hole (perspex) with 9 5/8" casing (PVC pipe). This setup had a standoff of 51% in both cases with pump rates and cuttings volume matched throughout the testing regime (6.7 mm cuttings bed height). The test clearly showed that with CE Bond, the low side of the well had excellent cement displacement which generated an optimal bond between the Perspex and PVC. In comparison, the run without CE Bond was unable to clear all of the cuttings (as proved in our previous flow loop testing), and was therefore unable to get a good cement coverage. This led to multiple channels on the low side caused by a combination of cuttings beds and poor low side fluid velocities (poor displacement).

6 What does a downhole flow diverter look like? Design brief: Flow diverter needs to function autonomously and be able to differentiate between low side and high side. Should be simple to install and should should not impact normal casing running & cementing operations. Needs to be suitably robust (axial, torsional, abrasion & impact loadings). Centraflow has designed & built a novel casing accessory to meet this brief: Installed between stop collars in the same way as a regular solid body centralizer. Functions autonomously via an atmospheric buoyancy chamber self orientates the diverter element to face highside when wellbore inclination exceeds ±5.

7 Computational Fluid Dynamics (CFD) Centraflow uses in house CFD capabilities to model well specific scenarios, taking into account: Average hole diameter (under gauge or over gauge). Wellbore inclination. Centralization scheme and associated stand off. Flow rates. Mud, spacer & cement properties. Distance taken to return to high side steady flow. Turbulence. The effect of downhole fluid diversion can then be assessed: Velocity inversion effects and flow regime. Distance taken downstream to return to high side steady state flow. Turbulence effects. Optimal spacing for fluid diverter tools on the casing.

8 Velocity Inversion 12.5 ppg OBM, 12 bbl/min 9 5/8ˮ Casing inside 12 1/4ˮ hole Wellbore inclination: 90 Steady state (upstream): High side: 0.95 m/s Low side: 0.55 m/s High side & Low side flow equalized for 3m downstream of the flow diverter pseudo vertical hole. Velocity inversion (downstream): Low side: >3 m/s (peak)

9 Velocity Inversion different fluid types

10 Reciprocation

11 Pressure Drop & ECD Representative pressure drop for a flow diverter on 9 5/8 casing inside 12 1/4 gauge hole: ANSYS Fluent CFD Solver. Scenario #1: 12.5 ppg (1.497 S.G.) OBM, pumped at 12 bbl/min (1,908 L/min). Pressure drop of 3.5 psi (0.241 bar) created by each flow diverter tool. Scenario #2: ppg (1.9 S.G.) tail cement slurry, pumped at 8 bbl/min (1,272 L/min). Pressure drop of 1.4 psi (0.097 bar) created by each flow diverter tool. If you were to run 50x flow diverter tools at a frequency of one tool per casing joint, in order to deliver effective cement bond across 600m of wellbore the associated total annular pressure loss would be 70 psi (4.83 bar) while pumping cement at 8 bpm. Potential to deliver a net reduction in ECD if residual cuttings beds are removed during pre circulation prior to cementing.

12 Applications for downhole flow diversion Well Types: Deviated wellbore + unable to rotate casing/liner + stand off <70%. Key Applications: Long deviated openhole sections (60 plus wellbore inclination). Under reamed hole sections (requires expandable flow diverters). Cemented completions. Unconventionals. ECD critical applications (potential to lower flow rate and still achieve better cement displacement). Functionality: Elimination of cement channelling effects (mitigating against potential influx and Sustained Casing Pressure). Zonal Isolation (hydrocarbon & water bearing zones). Shoe Isolation. Groundwater protection. Fraccing optimisation.

13 Development Status CE BOND tools built & tested. Upcoming trial wells (9 5/8ˮ casing): NCS shallow TVD reservoir. UAE ERD wells 11,000 ft openhole section of 12 1/4ˮ hole, inclination ranging from degrees. KSA need to address cement channeling in deep vertical gas wells (wellbore inclination of up to 20 ) Actively scouting for trial wells with deviated 13 3/8ˮ casing and Operator willing to run an ultrasonic cement bond log to verify results.

14 FAQ s

15 FAQ s Is CE-BOND a replacement for casing centralizers? No, not at all. CE Bond is designed to be run in conjunction with casing centralisers. The Operator can choose to run bow spring or solid body centralizers of their choice as normal. CE BOND will be installed using the same "slip on" method and retained between two stop collars. But CE BOND does not centralise a casing string it optimises circumferential fluid displacement by altering the velocity profile in the casing to wellbore annulus.

16 FAQ s How many CE BOND s are used per joint? Are they used all the way to surface? Each well is different and multiple factors come in to play such as: calliper data, hole angle, geology, etc. This information is used to provide space out requirements on a well by well basis. On average, CE BOND will be spaced one per joint with the shoe track possibly having two per joint. CE BOND is only suggested for use in areas of critical cement requirements such as the shoe, isolating formations, future abandonment zones and structural areas.

17 FAQ s Does CE BOND increase pack off risk? No. Pack off risk is defined by the size of discrete flow areas in the casing to wellbore annulus, and the fluid velocity within these flow areas. If CE BOND is compared to a conventional solid body casing centralizer, CE BOND represents a lower pack off risk. This is because the flow area on CE BOND is larger than the discrete flow areas between blades on a solid body centralizer, and for identical flow rates the fluid velocity within the CE BOND flow area is significantly higher. Solid Body Centraliser CE BOND

18 FAQ s Does CE BOND work in wash outs? CE BOND functions also in wash outs, as it has choking effect on the high side flow, leading to better flow distribution. CFD modelling shows that the CE BOND is effective in improving cement displacement for up to a 1 wash out.

19 FAQ s How can we be sure that CE BOND will self orientate? CE BOND has been designed with a strong upwards buoyancy force (around 10kg equivalent). To put this into perspective, picture a 10 kg weight hanging from a casing joint the force required to rotate this weight is significant. It should be noted that this buoyancy force comes into play as soon as the wellbore builds angle, so CE BOND will self orientate onto the high side as soon as wellbore angle exceeds around 5. This self orientation will therefore normally take place during cased hole. Once CE BOND is orientated onto the high side, the tendency of the casing to lay on the low side (due to gravity) and the elliptical geometry of CE BOND mean that it is almost impossible for CE BOND to be forced onto the low side. It should also be noted that as long as multiple CE BOND tools are run on a casing string, it is not essential for them all to be perfectly orientated onto the high side. A step change in hole cleaning and cement displacement will still be observed if only 80% of the CE BOND tools on the casing string are correctly orientated for example. Due to the unique design, CE-BOND, once orientated, is limited to remain in a zone on the high-side of the well only being able to rotate roughly 70 degrees maximum off top which still ensures effective displacement.

20 FAQ s Will CE BOND increase the risk of casing becoming stuck? In comparison to a solid body centraliser, the maximum OD on CE Bond is only 1/8" (3mm) larger than the centralizer blade height. In gauge hole, CE BOND is intended to lightly contact the high side of the wellbore only if the casing is 100% centralized. Regardless of the centralizer programme in use, achieving more than 80% casing stand off is effectively impossible to achieve in deviated hole. CE BOND also has the freedom to rotate. It can therefore rotate itself clear of a high side (below gauge) restriction using it's plough shaped nose and then flip back to the high side under buoyancy force to be correctly orientated. CE BOND is extremely robust, and will be physically tested to withstand 100,000 lbs (45 T) overpull force without damage (in case stuck casing is being worked or jarred free).

21 FAQ s Is there a risk that CE-BOND tools become damaged whilst RIH? CE-BOND uses state of the art composite materials (the space industries material of choice). With a combination of Carbon Fibre and Kevlar, CE-BOND is stronger than steel and has a high resistance to impact and abrasion. CE-BOND was designed using advanced composite Finite Element Analysis (FEA) techniques to ensure the capability to withstand all possible downhole forces and service loads that occur while installing casing. A physical testing programme is also used to categorically demonstrate the ability of CE-BOND to withstand all possible downhole load conditions. CE-Bond will also be tested for impact resistance which simulates the casing string travelling at running speed while coming into contact with a solid restriction.

22 FAQ s Can the composite material that CE BOND is manufactured from be damaged by H2S, CO2, OBM, or other wellbore fluids or gases? Composite materials are extremely inert and are highly resistant to ph, H2S, CO2 and oil based chemicals. Ironically, since water molecules are so small, designing a composite material to be fully water resistant under high pressure is the big challenge! The finished product will have an almost indefinite shelf life in a cool, dry warehouse. Due to surfaces finishes, it can be completely protected against UV. An extensive physical testing programme has been developed to categorically demonstrate the compatibility of CE BOND with all fluids and gasses that may be encountered downhole.

23 FAQ s Does CE BOND increase drag while running casing? Typically no; in gauge hole, CE BOND will only come into contact with the wellbore if the casing is 100% centralized. Since no centralizer programme can achieve 100% standoff, this scenario will only occur through areas with high dogleg severity. The composite material that CE BOND is manufactured from has a very low coefficient of friction, so if CE BOND does contact the wellbore, drag is not significantly impacted. The length of each CE BOND is short, so even a scenario where multiple CE BOND tools are contracting the wellbore will not significantly affect the friction factor seen by the casing string.

24 FAQ s Can Casing be rotated and reciprocated if CE BOND is being used? Casing can be freely reciprocated with CE BOND installed. In fact, reciprocation while circulating prior to cementing operations increases the wellbore cleaning efficiency of CE BOND so is a recommend step in the operational procedures. Casing can also be rotated with CE BOND installed if required.

25 FAQ s How can we verify the effectiveness of CE BOND? Ultrasonic cement bond logs provide a high resolution 'image' of cement bond quality around the casing circumference, and the ability to identify channels and assess overall cement bond quality. If an ultrasonic cement bond log is performed after installing casing with CE BOND, the log data will normally have sufficient resolution to identify the depth and orientation of the CE BOND tools, as well as qualifying the circumferential cement bond that has been achieved. If relevant offset well data is available from the same field, a direct comparison can be made between ultrasonic cement bond logs from similar wells, with and without CE BOND. If an ultrasonic cement bond log is not planned, the effectiveness of CE BOND can be physically confirmed by the increase in hole cleaning efficiency that is observed while circulating before the cement job (increased cuttings returns at surface). The improvement in well integrity that is associated with full circumferential cement bond will also be observed and recorded throughout the well lifecycle as part of routine well integrity management.

26 Thank You

Optimising Cementing. Rev: /04/01. Author: Peter Aird Ref:

Optimising Cementing. Rev: /04/01. Author: Peter Aird  Ref: Optimising Cementing Rev: 1.0 21/04/01 Purpose To ensure minimal operational time and risk exposure to personnel, process, production and equipment during cementing operations The following operational

More information

Recommendations to Ensure Proper Cement Placement. Bryce London Tech. Professional-Lead

Recommendations to Ensure Proper Cement Placement. Bryce London Tech. Professional-Lead Recommendations to Ensure Proper Cement Placement Bryce London Tech. Professional-Lead Ideal Conditions 6 Market Challenge 7 Market Challenge 8 Industry Best Practices Top Five: 1. Condition the drilling

More information

I ndependent D rilling E ngineering A xel S perber

I ndependent D rilling E ngineering A xel S perber I ndependent D rilling E ngineering A xel S perber Ing.-Büro Axel Sperber Eddesser Straße 1 D-31234 Edemissen Drilling Consulting & -Engineering Supervision Project Management most important factor for

More information

PowerFlex PowerEcho. Annular barrier evaluation services

PowerFlex PowerEcho. Annular barrier evaluation services PowerFlex PowerEcho Annular barrier evaluation services Powering Well Integrity Reliable barrier evaluation for assuring well integrity 1 Assuring the integrity of the well from well construction to abandonment

More information

MACKERAL OIL TOOLS PVT. LTD. PRODUCT CATALOGUE RIGID CENTRALIZERS & STOP RING CATALOGUE

MACKERAL OIL TOOLS PVT. LTD. PRODUCT CATALOGUE RIGID CENTRALIZERS & STOP RING CATALOGUE Mackeral centralizer designed to withstand the most extreme down hole conditions. Manufactured form mechanical stock tubing, the centralizer designed to perform in wells containing tight clearances and

More information

MACKERAL OIL TOOLS PVT. LTD.

MACKERAL OIL TOOLS PVT. LTD. CEMENT FLOAT SHOE Product Code:- MI 2102 Float shoe have a back-pressure valve that prevents fluids from entering the casing while the pipe is lowered into hole and prevents cement from flowing back into

More information

Finite Element Analysis of Casing Threaded Connectors

Finite Element Analysis of Casing Threaded Connectors White Paper Designing threaded connectors for steel casing pipes is a highly challenging problem, requiring designers to optimize multiple parameters such as taper angle, pitch, load and stab flank angles

More information

Swellpacker Technology Bests Zonal Isolation Challenge in High-Pressure Wells

Swellpacker Technology Bests Zonal Isolation Challenge in High-Pressure Wells E A S Y W E L L Swellpacker Technology Bests Zonal Isolation Challenge in High-Pressure Wells R e d Te c h PA P E R Part of the RedTech Learning Series O c t o b e r 2 0 0 7 HALLIBURTON E A S Y W E L L

More information

Seal 9 barrier verification by xlot and Communication test

Seal 9 barrier verification by xlot and Communication test Seal 9 barrier verification by xlot and Communication test P&A Forum 18 th Oktober 2017 Daniel Tomczak and Roar Flatebø Content Valhall overview and P&A Strategy Qualifying External Barriers Coil Tubing

More information

3/5/2014. Key Topics for Consideration

3/5/2014. Key Topics for Consideration Hole Cleaning in Deviated Wellbores Terry Hemphill Global Advisor, Wellbore Management Halliburton-Baroid Houston, Texas AADE Fluids Management Group 27 February 2014 terry.hemphill@halliburton.com Key

More information

Plugs and Profiles. Types Running Pulling Problems

Plugs and Profiles. Types Running Pulling Problems Plugs and Profiles Types Running Pulling Problems Plugs are set for many reasons but mostly for isolation of pressures. Not all plugs are a permanent seal. Sand plugs, cement plugs and inflatables have

More information

HTHP Gas Production Casing Cementing Michael Davis, SPE, Drill Science Corp.

HTHP Gas Production Casing Cementing Michael Davis, SPE, Drill Science Corp. HTHP Gas Production Casing Cementing Michael Davis, SPE, Drill Science Corp. Abstract A good cement bond on the production casing of a new wellbore is always the desired result yet until now there hasn

More information

COMPLETIONS WFXØ VØ-RATED OPENHOLE GRAVEL- PACK SYSTEM

COMPLETIONS WFXØ VØ-RATED OPENHOLE GRAVEL- PACK SYSTEM COMPLETIONS WFXØ VØ-RATED OPENHOLE GRAVEL- PACK SYSTEM Improving multizone gravel-pack reliability with single-trip efficiency REDUCE RIG TIME, ENHANCE SAFETY, AND ADD FLEXIBILITY IN YOUR OPENHOLE GRAVEL-PACKING

More information

HOLE CLEANING IN DIRECTIONAL WELLS

HOLE CLEANING IN DIRECTIONAL WELLS HOLE CLEANING IN DIRECTIONAL WELLS 1 ❶ Welcome to this presentation about Hole Cleaning in Directional Wells. It has been prepared by Sedco Forex, to give you a better understanding of the cuttings-transport

More information

DEEPWATER DRILLING LATIN AMERICA REGIONAL REPORT. Gas flow after cementing Modeling a CT intervention stack. Flat-rheology mud system

DEEPWATER DRILLING LATIN AMERICA REGIONAL REPORT. Gas flow after cementing Modeling a CT intervention stack. Flat-rheology mud system Defining Technology for Exploration, Drilling and Production January 2010 WELL CONTROL AND INTERVENTION Gas flow after cementing Modeling a CT intervention stack DEEPWATER DRILLING Flat-rheology mud system

More information

Well Integrity Master Class Well Cementing The most critical operation in achieving the ultimate well integrity

Well Integrity Master Class Well Cementing The most critical operation in achieving the ultimate well integrity Well Integrity Master Class Well Cementing The most critical operation in achieving the ultimate well integrity Keys to Successful Cementation Experience, Best practices, Technology, Job design and implementation

More information

Use of Swellable Elastomers to Enhance Cementation in Deep Water Applications

Use of Swellable Elastomers to Enhance Cementation in Deep Water Applications Use of Swellable Elastomers to Enhance Cementation in Deep Water Applications Bob Brooks, Tim Davis, Frank DeLucia TAM International This paper was prepared for presentation at the Deep Offshore Technology

More information

Application of a Unique Loss Circulation Curing Cement Spacer during Cement Placement in Geothermal Wells

Application of a Unique Loss Circulation Curing Cement Spacer during Cement Placement in Geothermal Wells Application of a Unique Loss Circulation Curing Cement Spacer during Cement Placement in Geothermal Wells Abraham S Samuel (Consultant) Kenya, Chike Uchendu, Francis Okoto (Consultant), Johnstone Maleche,

More information

ERD Hole Cleaning Best Practices

ERD Hole Cleaning Best Practices ERD Hole Cleaning Best Practices 1 Speaker Information Meghan Paulson Engineering Manager November 1, 2017 K&M Technology Group 2 Speaker Bio Introduction K&M Technology Group 18 years in Oil & Gas (Drilling

More information

Project report on a deep well construction

Project report on a deep well construction Project report on a deep well construction The Project The client GCO is in the process of assembling the world s biggest dredge mining operation at Senegal s coast. The Mining Concession comprises of

More information

CEMENT EVALUATION ITS NOT JUST ABOUT A BOND LOG GLEN BENGE SENIOR ADVISOR CEMENTING PRESSURE PUMPING

CEMENT EVALUATION ITS NOT JUST ABOUT A BOND LOG GLEN BENGE SENIOR ADVISOR CEMENTING PRESSURE PUMPING CEMENT EVALUATION ITS NOT JUST ABOUT A BOND LOG GLEN BENGE SENIOR ADVISOR CEMENTING PRESSURE PUMPING CEMENT EVALUATION OBJECTIVES Is the material behind the pipe a solid or liquid - Solids can t be fixed

More information

CLEARMAX Wellbore Cleaning Services

CLEARMAX Wellbore Cleaning Services CLEARMAX Wellbore Cleaning Services Drilling Evaluation Completion Production Intervention Wellbore cleaning services Chemicals Hydraulic systems Mechanical tools Engineering a clearer path to optimize

More information

Liner Hanger Selection. A Guide for Drilling and Completion Engineers

Liner Hanger Selection. A Guide for Drilling and Completion Engineers Liner Hanger Selection A Guide for Drilling and Completion Engineers Disclaimer This document has been developed to help drilling and completion engineers identify the liner hanger equipment best suited

More information

Best Practices for Cementing Job Software

Best Practices for Cementing Job Software Drilling Software Sophisticated Yet Simple White Paper Best Practices for Cementing Job Software CONTENTS I. Introduction... 3 II. Modeling... 1. Hydraulics modeling... 2. Displacement efficiency... 3.

More information

Cement Plug Placement and Integrity Mechanical Cementing Service

Cement Plug Placement and Integrity Mechanical Cementing Service Cement Plug Placement and Integrity Mechanical Cementing Service Technology, Technique, Trust When it becomes necessary to plug and abandon a well or sections of the wellbore with multiple cement barriers,

More information

Frequently Asked Questions

Frequently Asked Questions Frequently Asked Questions Directive 083: Hydraulic Fracturing Subsurface Integrity January 2016 Q1. How does the AER differentiate between a dual- and single-barrier system? A1. A dual-barrier system

More information

Challenges of Cementing Olkaria Geothermal Field

Challenges of Cementing Olkaria Geothermal Field GRC Transactions, Vol. 39, 2015 Challenges of Cementing Olkaria Geothermal Field Nahashon Karanja KenGen Olkaria Geothermal Projects, Naivasha nnzioka@kengen.co.ke Keywords Thickening time, ECD (equivalent

More information

Permian Basin ERD Development: The 15k Project

Permian Basin ERD Development: The 15k Project Permian Basin ERD Development: The 15k Project Permian Basin ERD Wells 0 2000 4000 6000 8000 10000 12000 14000 16000 Est. Horiz. Disp. Laredo Offset Permian operators are pushing lateral lengths further

More information

Drilling and Completion of Horizontal Wells in a Diatomite Formation A Systematic Approach to Addressing Challenges

Drilling and Completion of Horizontal Wells in a Diatomite Formation A Systematic Approach to Addressing Challenges PETROLEUM SOCIETY CANADIAN INSTITUTE OF MINING, METALLURGY & PETROLEUM PAPER 2002-246 Drilling and Completion of Horizontal Wells in a Diatomite Formation A Systematic Approach to Addressing Challenges

More information

Perforating for Hydraulic Fracturing Next Generation Technologies for Unconventional Completions

Perforating for Hydraulic Fracturing Next Generation Technologies for Unconventional Completions Perforating for Hydraulic Fracturing Next Generation Technologies for Unconventional Completions 2018-NAPS-07 AUTHOR: Jim Gilliat Perforating Product Champion BakerHughes, a GE Company Introduction The

More information

Offshore Drilling Ltd. Primary Cementing Products

Offshore Drilling Ltd. Primary Cementing Products Primary Cementing Products ENEROIL BEYOND ENGINEERING EXCELLENCE Eneroil welcomes you to its world of precision, quality and service. A world which has existed for the last two decades providing excellence

More information

Isolating Potential Flow Zones During Well Construction

Isolating Potential Flow Zones During Well Construction Isolating Potential Flow Zones During Well Construction API Standard 65 Part 2 Glen Benge http://publications.api.org/ API Standard 65-2 Document highlights industry recommended cementing and well construction

More information

Msc Drilling Engineering. HPHT Cementing Coursework

Msc Drilling Engineering. HPHT Cementing Coursework Msc Drilling Engineering HPHT Cementing Coursework Peter Aird. Kingdom Drilling Services Ltd. Kingdom drilling services Ltd Page 1 TABLE OF CONTENTS TABLE OF CONTENTS...2 REFERENCES...2 1 SUMMARY...3 INTRODUCTION...4

More information

Well abandonment procedures and perforation with a slotted charge for cement squeeze applications

Well abandonment procedures and perforation with a slotted charge for cement squeeze applications Well abandonment procedures and perforation with a slotted charge for cement squeeze applications European and West African Perforating Symposium (EWAPS) 7 9 th November 2012 Presented by Co-Author Frank

More information

AADE-05-NTCE-77. Preventing Annular Flow After Cementing: Pulse It! John Aslakson, W&T Offshore; Dale Doherty, BJ Services and Ed Smalley, CTES, L.P.

AADE-05-NTCE-77. Preventing Annular Flow After Cementing: Pulse It! John Aslakson, W&T Offshore; Dale Doherty, BJ Services and Ed Smalley, CTES, L.P. AADE-05-NTCE-77 Preventing Annular Flow After Cementing: Pulse It! John Aslakson, W&T Offshore; Dale Doherty, BJ Services and Ed Smalley, CTES, L.P. This paper was prepared for presentation at the AADE

More information

Unconventional Reservoirs

Unconventional Reservoirs Unconventional Reservoirs Efficiency and Execution Meet the Challenges of US Land Cementing Agenda Displacement Practices for Horizontal Cementing Fluid Optimization Fluid Solutions Job Execution 2 DEPTH

More information

Overview of Completions

Overview of Completions Overview of Completions PESA Oil & Gas 101 21 May 2015 Nick Clem, Applications Engineering Director Ganesh Subbaraman, Engineering Manager Outline Background Drivers affecting selection of completion types

More information

C H E M I X. Delivering Cesium Formate to the Oil & Gas Industry. Stocks available immediately for direct sale S.G. 2.20

C H E M I X. Delivering Cesium Formate to the Oil & Gas Industry. Stocks available immediately for direct sale S.G. 2.20 Delivering Cesium Formate to the Oil & Gas Industry Stocks available immediately for direct sale S.G. 2.20 Monovalent, non-scaling & solids free Reduce drilling & completion costs Increase reservoir productivity

More information

Cased Hole Sand Control Essentials. Fluids, Equipment, Tools, and Displacement Services

Cased Hole Sand Control Essentials. Fluids, Equipment, Tools, and Displacement Services Cased Hole Sand Control Essentials Fluids, Equipment, Tools, and Displacement Services Cased Hole Sand Control Essentials Fluids, Equipment, Tools, and Displacement Services The essentials of cased hole

More information

Well Design and Well Workover to Land Deep Production Casings in the Menengai Field

Well Design and Well Workover to Land Deep Production Casings in the Menengai Field GRC Transactions, Vol. 39, 2015 Well Design and Well Workover to Land Deep Production Casings in the Menengai Field Abraham W. Khaemba Nakuru, Kenya akhaemba@gdc.co.ke Keywords Production casings, cement

More information

Improving Late Life Well Integrity through Sustained Casing Pressure Remediation

Improving Late Life Well Integrity through Sustained Casing Pressure Remediation Improving Late Life Well Integrity through Sustained Thore Andre Stokkeland Archer the well company Alex Lucas and Michael Cowling Total E&P Danmark SPE Aberdeen Well Late Life And Well Abandonment Conference

More information

SteadyState Continuous Flow System

SteadyState Continuous Flow System SteadyState Continuous Flow System Ultimate Wellbore Protection. Achieve greater control through continuous circulation of drilling fluids. Continuous Pressure, Along the Entire Wellbore Managing downhole

More information

DEFINITIONS. A shallow bored hole under the derrick substructure in which the kelly is temporarily stored during tripping operations.

DEFINITIONS. A shallow bored hole under the derrick substructure in which the kelly is temporarily stored during tripping operations. DEFINITIONS 1. Conductor Hole A large diameter hole bored to facilitate steel pipe. May be cemented in place to allow conventional oil and gas well drilling operations,and also allows fluid returns to

More information

Drilling-with-Liner (DwL ) System Drill the Undrillable

Drilling-with-Liner (DwL ) System Drill the Undrillable Drilling-with-Liner (DwL ) System Drill the Undrillable One-trip liner system cuts cost and risk. Drill, run, set and cement your liner system all in one trip as you mitigate drilling hazards, increase

More information

Acoustics and Ultrasonics for Downhole Oil and Gas Logging

Acoustics and Ultrasonics for Downhole Oil and Gas Logging Acoustics and Ultrasonics for Downhole Oil and Gas Logging Eric Molz MSS Piezo Technologies 2015 Meggitt PLC. Presentation Roadmap Method of Well Drilling Method of Well Completion Questions Sonic Formation

More information

SCHOOL OF COMPUTING, ENGINEERING AND MATHEMATICS SEMESTER 1 EXAMINATIONS 2015/2016 ME257. Fluid Dynamics

SCHOOL OF COMPUTING, ENGINEERING AND MATHEMATICS SEMESTER 1 EXAMINATIONS 2015/2016 ME257. Fluid Dynamics s SCHOOL OF COMPUTING, ENGINEERING AND MATHEMATICS SEMESTER 1 EXAMINATIONS 2015/2016 ME257 Fluid Dynamics Time allowed: TWO hours Answer: Answer TWO from THREE questions in section A and TWO from THREE

More information

By Kimbal A. Hall, PE. Submitted to: WESTFALL MANUFACTURING COMPANY. May ALDEN RESEARCH LABORATORY, INC. 30 Shrewsbury Street Holden, MA 01520

By Kimbal A. Hall, PE. Submitted to: WESTFALL MANUFACTURING COMPANY. May ALDEN RESEARCH LABORATORY, INC. 30 Shrewsbury Street Holden, MA 01520 COMPUTATIONAL FLOW MODEL OF WESTFALL'S 36 3050 THREE STAGE MIXER TO BE INSTALLED IN THE PERCHLORATE BLENDING STATION FOR THE CITY OF REDLANDS, CALIFORNIA GFS-411507-1R2 By Kimbal A. Hall, PE Submitted

More information

Sand Control. Gravel packing is the oldest and simplest method of sand control. Works in both on and off shore wells.

Sand Control. Gravel packing is the oldest and simplest method of sand control. Works in both on and off shore wells. Sand Control Marine deposited sands, most oil and gas reservoir sands, are often cemented with calcareous or siliceous minerals and may be strongly consolidated. In contrast, Miocene or younger sands are

More information

Hydraulic Fracturing Operations Well Construction and Integrity Guidelines API GUIDANCE DOCUMENT HF1 FIRST EDITION, OCTOBER 2009

Hydraulic Fracturing Operations Well Construction and Integrity Guidelines API GUIDANCE DOCUMENT HF1 FIRST EDITION, OCTOBER 2009 Hydraulic Fracturing Operations Well Construction and Integrity Guidelines API GUIDANCE DOCUMENT HF1 FIRST EDITION, OCTOBER 2009 Hydraulic Fracturing Operations Well Construction and Integrity Guidelines

More information

performed during initial months of incorporation in addition to sourcing and qualifying of suppliers and sub-contractors

performed during initial months of incorporation in addition to sourcing and qualifying of suppliers and sub-contractors DRK OILTOOLS Incorporated April 2011 Product design for shoes, collars and casing attachments performed during initial months of incorporation in addition to sourcing and qualifying of suppliers and sub-contractors

More information

Gap analysis between OLF s Summary report to Deepwater Horizon (Macondo) accident and NORSOK D-010, Rev.4 Draft

Gap analysis between OLF s Summary report to Deepwater Horizon (Macondo) accident and NORSOK D-010, Rev.4 Draft Gap analysis between OLF s Summary report to Deepwater Horizon (Macondo) accident and NORSOK D-010, Rev.4 Draft 20.12.2012 The table below shows where and how NORSOK D-010 rev. 4 responds to the recommendations

More information

Deep Drilling Problems

Deep Drilling Problems A Noble Drilling Corporation Subsidiary Deep Drilling Problems Dr. William C. Maurer DOE Deep Trek Workshop Houston, TX March 20, 2001 TT01-26 1 TROUBLE TIME 4.00% TESTING & LOGGING 6.79% WAIT TIME 2.70%

More information

OINTRODUCTION. Technology Overview for Oil Services Companies: Using Flow Modeling to Lower Costs, Increase Reliability, and Reduce Risks

OINTRODUCTION. Technology Overview for Oil Services Companies: Using Flow Modeling to Lower Costs, Increase Reliability, and Reduce Risks W H I T E P A P E R - 1 1 9 Technology Overview for Oil Services Companies: Using Flow Modeling to Lower Costs, Increase Reliability, and Reduce Risks David Schowalter, PhD, ANSYS, Inc. OINTRODUCTION Oil

More information

RHADIANT Ultra-high-temperature non-aqueous drilling fluid

RHADIANT Ultra-high-temperature non-aqueous drilling fluid RHADIANT Ultra-high-temperature non-aqueous drilling fluid Rhadiant components engineered to take the heat The components of the RHADIANT fluid system are specially engineered to work synergistically to

More information

Well Design and Well Workover to Land Deep Production Casings in the Menengai Field

Well Design and Well Workover to Land Deep Production Casings in the Menengai Field PROCEEDINGS, Fourtieth Workshop on Geothermal Reservoir Engineering Stanford University, Stanford, California, January 26-28, 2015 SGP-TR-204 Well Design and Well Workover to Land Deep Production Casings

More information

SUDELAC. SLIDER Centraliser Range with Gauge Protection System

SUDELAC. SLIDER Centraliser Range with Gauge Protection System SUDELAC SLIDER Centraliser Range with Gauge Protection System (Patent Pending) Products: ScreenSLIDER Centraliser c/w GPS PackerPROTECTOR Centraliser c/w GPS Cemented LinerSLIDER Centraliser c/w GPS Cemented

More information

Multiple Zone Geothermal Stimulation Case Study: Fluid Diversion Using Thermo-Degradable Zonal Isolation Materials

Multiple Zone Geothermal Stimulation Case Study: Fluid Diversion Using Thermo-Degradable Zonal Isolation Materials GRC Transactions, Vol. 37, 2013 Multiple Zone Geothermal Stimulation Case Study: Fluid Diversion Using Thermo-Degradable Zonal Isolation Materials Y. Nordin, S. Petty, T. Cladouhos, M. Swyer, and T. DeRocher

More information

NORSOK Standard D-010 Rev. 4 ( )

NORSOK Standard D-010 Rev. 4 ( ) The table below shows where and how NORSOK D-010 rev. 4 responds to the recommendations in the OLF s Summary report to Deepwater Horizon (Macondo) accident. Color denotes that OLF comment..; 1 : is fully

More information

Introduction. High Performance, Streamline Connections for 4 in. Drill Pipe

Introduction. High Performance, Streamline Connections for 4 in. Drill Pipe Advanced Drill Pipe With Streamline Connections Enhances Slim-hole Drilling Performance Michael J. Jellison, Grant Prideco; Guillaume Plessis, Grant Prideco; Andre Glowacz, Total; John M. Pasnak, Saudi

More information

COPYRIGHT. Sand Control Fundamentals. Virtual Instructor Led Session #2

COPYRIGHT. Sand Control Fundamentals. Virtual Instructor Led Session #2 Sand Control Fundamentals Non-Gravel Pack Applications Virtual Instructor Led Session #2 Open Hole with Slotted Liner Open Hole with Screen or Prepacked Screen Slotted liners and screens in a non-gravel

More information

ENDURA DUAL-STRING SECTION MILL. Set a rock-to-rock barrier and know that it s done right. WELL ABANDONMENT

ENDURA DUAL-STRING SECTION MILL. Set a rock-to-rock barrier and know that it s done right. WELL ABANDONMENT WELL ABANDONMENT ENDURA DUAL-STRING SECTION MILL Set a rock-to-rock barrier and know that it s done right. DRILLING & FORMATION EVALUATION WELL CONSTRUCTION COMPLETION PRODUCTION MILL ADJACENT STRINGS

More information

Flow assurance with ANSYS CFD

Flow assurance with ANSYS CFD Flow assurance with ANSYS CFD Lubeena, R Muralikrishnan, R Mohan Srinivasa 2010 ANSYS, Inc. All rights reserved. 1 ANSYS, Inc. Proprietary Agenda Introduction Flow assurance with ANSYS Risk avoidance Hydrates

More information

SPE DISTINGUISHED LECTURER SERIES is funded principally through a grant of the SPE FOUNDATION

SPE DISTINGUISHED LECTURER SERIES is funded principally through a grant of the SPE FOUNDATION SPE DISTINGUISHED LECTURER SERIES is funded principally through a grant of the SPE FOUNDATION The Society gratefully acknowledges those companies that support the program by allowing their professionals

More information

Computational Fluid Dynamics (CFD) Simulations of Dispersed Flow of Viscous Oil in Water in a Horizontal Pipe

Computational Fluid Dynamics (CFD) Simulations of Dispersed Flow of Viscous Oil in Water in a Horizontal Pipe Computational Fluid Dynamics (CFD) Simulations of Dispersed Flow of Viscous Oil in Water in a Horizontal Pipe *Robin Yap Miao Sin, Cary K Turangan Institute of High Performance Computing, 1 Fusionopolis

More information

seismicvision Real-time borehole seismic imaging for productive drilling

seismicvision Real-time borehole seismic imaging for productive drilling Real-time borehole seismic imaging for productive drilling Seismic-while-drilling service accomplishes the world s first successful real-time salt proximity survey BENEFITS Saves rig time and cost Improves

More information

Foamed cement successfully applied in shallow water environment in Caspian Sea

Foamed cement successfully applied in shallow water environment in Caspian Sea Foamed cement successfully applied in shallow water environment in Caspian Sea By Rufat Mammadbayli, Jon Greener, BP Exploration; Dale Doherty, Jose Reyes, Patricio Torres, BJ Services THE GIANT Azeri-Chirag-Gunashli

More information

Petroleum Production Systems

Petroleum Production Systems Petroleum Production Systems SECOND EDITION Michael J. Economides A. Daniel Hill Christine Ehlig-Economides Ding Zhu PRENTICE HALL Upper Saddle River, NJ Boston Indianapolis San Francisco New York Toronto

More information

Optimizing Drilling Operations with Solid Expandable Tubulars. Enventure Global Technology, L.L.C.

Optimizing Drilling Operations with Solid Expandable Tubulars. Enventure Global Technology, L.L.C. Optimizing Drilling Operations with Solid Expandable Tubulars Tony Furniss Enventure Global Technology, L.L.C. Abstract Deep water and extensive lengths are no longer an anomaly for drilling conditions

More information

State of Colorado Oil and Gas Conservation Commission 1120 Lincoln Street, Suite 801, Denver, Colorado Phone: (303) Fax: (303)

State of Colorado Oil and Gas Conservation Commission 1120 Lincoln Street, Suite 801, Denver, Colorado Phone: (303) Fax: (303) FORM 2 Rev 08/16 State of Colorado Oil and Gas Conservation Commission 1120 Lincoln Street, Suite 801, Denver, Colorado 80203 Phone: (303) 894-2100 Fax: (303) 894-2109 APPLICATION FOR PERMIT TO: Document

More information

Granite Wash Casing Profile. Texas Panhandle (District 10) Western Oklahoma

Granite Wash Casing Profile. Texas Panhandle (District 10) Western Oklahoma Granite Wash Casing Profile Texas Panhandle (District 10) Western Oklahoma OKC Granite Wash Conference March 6, 2008 Surface Casing Regulations District 10 Office is located in Pampa, Texas Texas Railroad

More information

CT Reverse Circulating - Basics

CT Reverse Circulating - Basics CT Reverse Circulating - Basics Reverse circulating with aqueous fluid to unload frac sand from large wellbores If sufficient annular velocities are possible with normal circulation, usually don t use

More information

Structural Analysis of the Casings in Deep Geothermal Wells

Structural Analysis of the Casings in Deep Geothermal Wells Structural Analysis of the Casings in Deep Geothermal Wells Gunnar Skúlason Kaldal 1,2, Magnús Þ. Jónsson 1, Halldór Pálsson 1, Sigrún Nanna Karlsdóttir 1 1Faculty of Industrial Engineering, Mechanical

More information

Unconventional Resources

Unconventional Resources Houston, Texas (World Headquarters) 4620 Southerland Road Houston, TX, 77092 Phone: 1-800-462-7617 or 713-462-7617 E-mail: info@tamintl.com Aberdeen, Scotland Phone: 44-1224-875105 E-mail: info@tam-northsea.com

More information

New Technologies, Innovations

New Technologies, Innovations New Technologies, Innovations Drilling New Technologies, Innovations Advances in technologies used for well drilling and completion have enabled the energy industry to reach new sources of oil and natural

More information

Drilling and Integrity of Geothermal Wells - Issues and Challenges. Parveen Sachdeva Blade Energy Partners

Drilling and Integrity of Geothermal Wells - Issues and Challenges. Parveen Sachdeva Blade Energy Partners Drilling and Integrity of Geothermal Wells - Issues and Challenges Parveen Sachdeva Blade Energy Partners Geothermal Well Integrity Slide 2 Geothermal wells generally present as high temperature, low pressure

More information

ASSESSMENT OF THE EFFECTIVENESS OF CLEANING PROGRAMMES

ASSESSMENT OF THE EFFECTIVENESS OF CLEANING PROGRAMMES ASSESSMENT OF THE EFFECTIVENESS OF CLEANING PROGRAMMES By: David Russell, Project Manager, Reserach and Development, Pipeline Engineering Chris Marshall, Project Manager, Pipeline Engineering Abstract

More information

Remotely Operated Cementing Methods for Drilling with Liner Installations. Steve Rosenberg, Global Drilling Reliability Manager

Remotely Operated Cementing Methods for Drilling with Liner Installations. Steve Rosenberg, Global Drilling Reliability Manager Remotely Operated Cementing Methods for Drilling with Liner Installations Steve Rosenberg, Global Drilling Reliability Manager Outline Valhall Field history Drilling and completion challenges Drilling

More information

A Case Study in Evaluating Technical Options for Well Abandonment in an Aging Offshore Field

A Case Study in Evaluating Technical Options for Well Abandonment in an Aging Offshore Field A Case Study in Evaluating Technical Options for Well Abandonment in an Aging Offshore Field Tom Leeson: Reverse Engineering Stewart Buchan: Quadrant Energy Aberdeen: June 2017 www.resleng.com HARRIET

More information

FUNDAMENTALS OF THE PETROLEUM INDUSTRY CERTIFICATION

FUNDAMENTALS OF THE PETROLEUM INDUSTRY CERTIFICATION FUNDAMENTALS OF THE PETROLEUM INDUSTRY CERTIFICATION CORPORATE COLLEGE SEMINAR SERIES Date: November 1 December 15 In partnership with: For more information, contact: Michael Burns Director Michael.Burns@LoneStar.edu

More information

Investigation on Core Downward Flow by a Passive Residual Heat Removal System of Research Reactor

Investigation on Core Downward Flow by a Passive Residual Heat Removal System of Research Reactor Investigation on Core Downward Flow by a Passive Residual Heat Removal System of Research Reactor W.K. Lee 1, S.J. Kim 1, D.Y. Lee 1, W.K. Hwang 1, K.Y. Lee 1 1) Department of Mechanical and Control Engineering,

More information

The Effect of Wellbore Centralization in Geothermal Wells

The Effect of Wellbore Centralization in Geothermal Wells PROCEEDINGS, 43rd Workshop on Geothermal Reservoir Engineering Stanford University, Stanford, California, February 12-14, 2018 SGP-TR-213 The Effect of Wellbore Centralization in Geothermal Wells Michael

More information

Coiled Tubing for Downhole Applications

Coiled Tubing for Downhole Applications Coiled Tubing for Downhole Applications Tenaris Tubular technologies. Innovative services. Tenaris is the leading global manufacturer and supplier of tubular products and services used in the drilling,

More information

MUD ROTARY TECHNIQUES. MUD Rotary Drilling Method 12/11/2017. Roger E. Renner, MGWC MUD ROTARY DRILLING. Rotary Well Rig

MUD ROTARY TECHNIQUES. MUD Rotary Drilling Method 12/11/2017. Roger E. Renner, MGWC MUD ROTARY DRILLING. Rotary Well Rig Roger E. Renner, MGWC MUD ROTARY TECHNIQUES Presenter: Roger E. Renner Master Groundwater Contractor President of E.H. RENNER & SONS, INC. Past President of NGWA 2001 Past President of Minnesota Water

More information

SHIELD BOND Cementing Spacers. Spacer Systems for Wellbore Shielding & Stabilization

SHIELD BOND Cementing Spacers. Spacer Systems for Wellbore Shielding & Stabilization SHIELD BOND Cementing Spacers Spacer Systems for Wellbore Shielding & Stabilization Solving Complex Wellbore Challenges Worldwide Impact Fluid Solutions is a premier provider of specialty additives for

More information

COOLING OF ROLLS USED IN HOT ROLLING OF LONG PRODUCTS

COOLING OF ROLLS USED IN HOT ROLLING OF LONG PRODUCTS COOLING OF ROLLS USED IN HOT ROLLING OF LONG PRODUCTS M. Raudensky, J. Horsky, P. Kotrbacek, M. Pohanka Brno University of Technology, Heat Transfer and Fluid Flow Laboratory, Technicka 2896/2, 616 69

More information

SPE DISTINGUISHED LECTURER SERIES is funded principally SPE FOUNDATION

SPE DISTINGUISHED LECTURER SERIES is funded principally SPE FOUNDATION SPE DISTINGUISHED LECTURER SERIES is funded principally through a grant of the SPE FOUNDATION The Society gratefully acknowledges those companies that support the program by allowing their professionals

More information

Tubing-Conveyed Perforating Systems

Tubing-Conveyed Perforating Systems WIRELINE SERVICES Tubing-Conveyed Perforating Systems Full-Service Support, Complete Optimization Delivering downhole perforating solutions through our expertise, innovation, and collaboration Onshore

More information

impact Integrated wellbore preparation service

impact Integrated wellbore preparation service impact Integrated wellbore preparation service impact: Debris removal made easy - combining fluid, tools and equipment Coiled tubing offers a host of economic and HSE advantages for post-stimulation cleanup

More information

INTERNATIONAL PERFORATING SYMPOSIUM 2014

INTERNATIONAL PERFORATING SYMPOSIUM 2014 INTERNATIONAL PERFORATING SYMPOSIUM 2014 Completion evolution: The role of perforating in horizontal shale wells Kerry Daly, Global BD Manager- DST TCP WELL FLOW MANAGEMENT TM Introduction The first horizontal

More information

Debris Management and Cleanout

Debris Management and Cleanout Debris Management and Cleanout Debris Categorization Solids Gunk (sludges, emulsions, viscous liquids, PIPE DOPE!) Junk introduced into the hole www.gekengineering.com Source: Wellcert 1 Photograph (from

More information

Benefits of Aluminum Drill Pipe FuchsRohr AluDrill in Deviated Wells

Benefits of Aluminum Drill Pipe FuchsRohr AluDrill in Deviated Wells Benefits of Aluminum Drill Pipe FuchsRohr AluDrill in Deviated Wells OTTO FUCHS Drilling Solutions August, 2014 1 Outline of the presentation Problematic Torque & Drag Basics Friction & Contact Forces

More information

Centralizer Selection and Placement Basis for Overcoming Liner Running Challenges in Extended-Reach Horizontal Three Forks Shale Completions

Centralizer Selection and Placement Basis for Overcoming Liner Running Challenges in Extended-Reach Horizontal Three Forks Shale Completions Volant Products Inc. t +1 78.49.5185 411 56 Avenue NW f +1 78.437.2187 Edmonton AB T6B 3R8 info@volantproducts.ca Canada www.volantproducts.ca URTeC Control I.D. Number: 246231 Centralizer Selection and

More information

Artificial Lift Technique (VI Semester)

Artificial Lift Technique (VI Semester) Artificial Lift Technique (VI Semester) Q.1. What do you mean by artificial lift technique in Petroleum industry? Answer. Artificial lift is a means of overcoming bottomhole pressure so that a well can

More information

Well-Based Monitoring

Well-Based Monitoring Rick Chalaturnyk Petroleum Geomechanics Research Group Department of Civil and Environmental Engineering University of Alberta Well-Based Monitoring IEA MONITORING and VERIFICATION NETWORK Meeting 2006

More information

Joint Industry Project on Deliquification

Joint Industry Project on Deliquification on Deliquification Predicting the gains for European wells Jordy de Boer Erik Nennie 2 Project structure and goals Overall goal: Transfer US knowledge on deliquification to Europe Three phases: 1. Literature

More information

Down Hole Flow Assurance

Down Hole Flow Assurance Down Hole Flow Assurance Ferhat Erdal Senior Advisor - Flow Assurance Steve Cochran Senior Advisor - Flow Assurance SPE GCS Annual Drilling Symposium Spring, TX April 13, 2017 Flow Assurance Key Words

More information

ANSYS, Inc. March 31, Phase Change Models in FLUENT

ANSYS, Inc. March 31, Phase Change Models in FLUENT 1 2016 ANSYS, Inc. March 31, 2016 Phase Change Models in FLUENT Phase Change Models in ANSYS FLUENT In ANSYS Fluent the following are available for modeling phase change Boiling models RPI Non equilibrium

More information

WELL CEMENTING C o n t a c t U s f o r S p e c i a l C o r p o r a t e R a t e N o w!

WELL CEMENTING C o n t a c t U s f o r S p e c i a l C o r p o r a t e R a t e N o w! C o n t a c t U s f o r S p e c i a l C o r p o r a t e R a t e N o w! Course Overview This course has been written for Drilling Engineers (typically graduate level) who require an understanding of cement

More information

CFD Simulations in the Ocean Engineering Department Daniel Carvalho Marcelo Martinelli Paulo Roberto Pagot Raphael Coelho

CFD Simulations in the Ocean Engineering Department Daniel Carvalho Marcelo Martinelli Paulo Roberto Pagot Raphael Coelho CFD Simulations in the Ocean Engineering Department Daniel Carvalho Marcelo Martinelli Paulo Roberto Pagot Raphael Coelho Introduction The Ocean Engineering CFD Group works on multidisciplinary simulation

More information

Numerical analysis of eccentric orifice plate using ANSYS Fluent software

Numerical analysis of eccentric orifice plate using ANSYS Fluent software IOP Conference Series: Materials Science and Engineering PAPER OPEN ACCESS Numerical analysis of eccentric orifice plate using ANSYS Fluent software To cite this article: D Zahariea 2016 IOP Conf. Ser.:

More information