consultation with government and other Project stakeholders to understand their views on the likely significant impacts.

Size: px
Start display at page:

Download "consultation with government and other Project stakeholders to understand their views on the likely significant impacts."

Transcription

1 4 Scoping and Stakeholder Engagement 4.1 Introduction This chapter describes the approach that was taken to scoping the impact assessment, including activities undertaken to understand the views of stakeholders on the Project and its potential impacts. It also sets out the plans for future stakeholder engagement as the Project moves from the SEIA stage into implementation. 4.2 Scoping Overview As set out in Chapter 1: Introduction, the principal purpose of scoping is to identify the impacts of a project which are considered likely to be significant, so that the assessment can be planned and focussed on the important issues. Scoping is a crucial first step in a SEIA and involves: systematic examination of the potential for interaction between activities involved in developing the Project and aspects of the physical, natural, cultural, social and socio-economic environment that may be affected; consideration of which of these are likely to be significant; and consultation with government and other Project stakeholders to understand their views on the likely significant impacts. The overall scope of work required for the Simandou Project SEIA was developed based on the requirements of the Guinean EIA Decree and Order (1), IFC s Performance Standards and Rio Tinto s internal policies and standards. These are introduced in Chapter 1: Introduction and further details are provided in Annex 1C: Legislation, Standards and Administrative Framework. The type of assessment required for a project will vary depending on the significance of potential impacts. Under the Guinean EIA Decree an assessment may be either a detailed (approfondie) or simplified (simplifiée) assessment. IFC s Policy on Social and Environmental Sustainability also categorises projects according to the magnitude of risks and impacts as Category A, B, C or FI and typically the level of assessment will reflect the categorisation assigned to a project. The Simandou Project is judged to fall within the class of projects requiring detailed assessment under Guinean law, and within IFC Category A, as it is likely to have significant adverse impacts which are diverse, irreversible and / or unprecedented. As such, a detailed assessment of impacts and risks is required and has been undertaken. As part of this process the Project has engaged with stakeholders, including authorities and communities affected by the Project, so that their views can be understood and taken into account in the assessment and the development of the Project. The approach to and findings from this engagement are described in the remainder of this Section 4.2. The results of the assessment are presented in the SEIA and therefore will be disclosed to stakeholders for review and comment. The process that will be followed is described in Section Approach The initial phase of work to develop the scope for the Simandou SEIA involved identifying the components of the Project and the activities involved in construction, operation and closure, and considering how these could be expected to interact with known environmental and social conditions in the vicinity of the Project. (1) Décret 199/PRG/SGG/89 du 8 novembre 1989 codifiant les études d impact sur l environnement (the EIA Decree) and Arrêté 990/ NRNE/SGG/90 du 15 mars 1990 fixant contenu, méthodologie et procédure de l étude d impact sur l environnement 4-1

2 This process was guided by reference to the IFC Performance Standards (1) and to the EU Guidance on EIA Scoping (2). A draft Simandou Project SEIA Terms of Reference was prepared and submitted to the Government in August The purpose of the Terms of Reference was to define the Project and its potential impacts on the environment and communities, set out the proposed approach and methods for the impact assessment, identify the expertise that is needed to prepare the study, and present the timetable for its completion. The Terms of Reference were reviewed and approved by the Minister of the Environment in October A copy of the approved Terms of Reference, the minutes of the meeting with the Bureau Guinéen des Etudes et Evaluations Environnementales (BGEEE) on the draft Terms of Reference and the letter of approval are presented in Annex 1B: SEIA Terms of Reference Stakeholder Engagement To inform the scope of the assessment, the SEIA Team also undertook a programme of consultations on the Project and the SEIA Terms of Reference. Details were set out in a Stakeholder Engagement Plan published in August 2011 (see covering stakeholder engagement activities during the SEIA study. The Plan included an analysis and identification of potential stakeholders which was used to inform the development of the programme. Details of the engagement activities and the materials used are presented in Annex 4A: Simandou Project Stakeholder Engagement Report, together with an analysis of the comments received Engagement with the National Guinean Authorities National authorities were provided with information about the Simandou Project during scoping of the SEIA Terms of Reference over the period from May to September Various meetings were held with government authorities during preparation of the draft Terms of Reference and all relevant ministries were invited to attend the SEIA conference about the Project that took place in Conakry on September 19th, The Project continues to engage with government authorities through BGEEE, the Comité Technique d Analyse Environnementale (CTAE) and the inter-ministerial group set up to oversee consideration of the Simandou Project and to ensure that the Government of the Republic of Guinea is kept informed on progress and is in a position to consider the Project activities in its policy-making, regulatory and other duties and activities Stakeholder Conferences A conference was organised in Conakry on September 19 th 2011 attended by an invited audience from national, regional, prefectural and local government, non-governmental organisations, academic and research institutions, community representatives and the media. Following this, two rounds of stakeholder events were held in the ten prefectures affected by the Simandou Project. At least two weeks prior to each event, local leaders including Governors and Prefects were formally invited to attend and were asked to invite relevant stakeholders, including Sub-Prefects and village and traditional leaders, within their respective communities. The prefectural events were also open to members of the public, and were publicised by local leaders and through announcements on local rural radio stations. At each event, participants were provided with brochures describing the proposed developments and the scope of the SEIA together with information on how to obtain the detailed Terms of Reference (on the web or in hard copy). Participants were invited to make comments and ask questions during the meetings and were also provided with a feedback form on which they could submit written comments. Feedback forms could be handed in on the day, submitted on-line or returned by or by hand to Simfer and to Simandou Project (1) International Finance Corporation Sustainability Framework - available at (2) Available at 4-2

3 offices and info-shops. Feedback regarding the Simandou Project Terms of Reference was requested within 30 days of the first round of events. The locations and dates for the events are listed in Table 4.1, with an estimate of the number of attendees at each event and the number of feedback forms received. Participants typically included representatives from national, regional, prefectural and local government, community leaders, non-governmental organisations, members of the public (men and women) and representatives from the local media. Table 4.1 Stakeholder Consultation Events Prefecture Location Date FIRST ROUND Approx. Number of Participants Number of Comment Forms Conakry Conakry 19 Sep Beyla Beyla Centre 18 Oct Faranah Faranah Centre 11 Oct Forécariah Forécariah Centre 22 Sep Kankan Tokonou 4 Oct Kérouané Kérouané Centre 11 Oct Kindia Kindia Centre 4 Oct Kissidougou Albadaria 5 Oct Kouroussa Douako 6 Oct Macenta Macenta Centre 13 Oct Mamou Mamou Centre 6 Oct First Round TOTAL SECOND ROUND Beyla Beyla Centre 14 Feb Faranah Faranah Centre 2 Feb Forécariah Moussayah 9 Feb Kankan Tokonou 7 Feb Kérouané Kérouané Centre 31 Jan Kindia Kindia Centre 7 Feb Kissidougou Albadaria 8 Feb Kouroussa Douako 9 Feb Macenta Macenta Centre 2 Feb Mamou Mamou Centre 31 Jan Second Round TOTAL As shown in Table 4.1, approximately individuals attended the first series of consultation events and 3 170, the second series. A wide variety of issues was raised during the events and nearly feedback forms were received. Full details of the programme, copies of the materials used, minutes of the meetings and a review of the issues raised by stakeholders are presented in Annex 4A: Simandou Project Stakeholder Engagement Report. A summary of the issues raised is provided in Section

4 Other Consultation Activities The brochures, the Terms of Reference and the feedback form were also made available on the Simandou SEIA website and copies were provided to national ministries and agencies, governorate and prefectural authorities, and national and international non-governmental organisations. A number of meetings were held with government authorities and non-governmental organisations were contacted in writing requesting their views on the scope of the SEIA. The minutes of meetings and a list of non-governmental organisations contacted are included in Annex 4A: Simandou Project Stakeholder Engagement Report. As the Project progresses, contact will be maintained with stakeholders who have expressed an interest in the Project by issuing regular updates on the website, in the press, in Info-Shops and Info-Posts, and through other communications. Regular contact will be maintained with national, regional and local regulatory authorities and follow-up meetings will be held with other stakeholders as needed. Village level consultations have also commenced as part of planning for land acquisition. These are focussing initially on localities affected by advance works and will then be extended out to the wider Project area. Whilst the focus is on consulting affected communities about land acquisition and the resettlement and compensation planning process, opportunities have also been taken to invite comments about the wider social and environmental impacts of the Project for input to the SEIA studies. Village, user group and household surveys carried out during baseline studies have also provided valuable information Summary of Stakeholder Comments A detailed analysis of the comments made during the stakeholder engagement programme is provided in Annex 4A: Simandou Project Stakeholder Engagement Report. The level of interest in different topics is illustrated in Figure 4.1 and a summary of the main issues raised by stakeholders is provided in Table 4.2. Figure 4.1 Overview of Stakeholder Concerns 4-4

5 Table 4.2 Issues Raised Summary of Stakeholder Concerns During the stakeholder engagement programme the principal questions and concerns raised by communities and others related to the following topics. Community Development: support to local development, local organisations and associations, and to income generating activities; and support for the development of new infrastructure (roads, schools, health services, electricity, communications, sports facilities etc). Social Impacts: employment opportunities, particularly for the young and for those who are less-educated; and concerns over the loss of community ties within and between settlements The Resettlement and Compensation Process: the compensation process and the nature of the compensation in case of resettlement; whether compensation will be financial or in-kind; how compensation rates are to be set; when compensation is to be provided and for how long; whether community infrastructure will be reinstated; how loss of productive agricultural land and plantations will be compensated; and how host sites are to be selected in case of resettlement, whether people will have a choice and whether new sites will be similar to the original locations. Protection of the Environment: the protection of the environment, in particular classified forests and protected species (chimpanzees and elephants were the most cited); impacts of dust and noise on communities and the health of people and animals; and rehabilitation measures to restore vegetation cover and whether any gaps will remain at the end of the Project. Health and Safety: the impacts of dust, noise, smoke and odours on the communities and on the health of people and animals; and the protection of cattle near the railway line. The Impacts of the Railway: concerns over crossing the railway, especially for cattle and children; the exact rail alignment and the list of villages that will be impacted; the potential for local use of the railway; the impact from the train, especially noise, on people, livestock and wild animals; the impact of noise on animals which are important for hunting; and the proximity of the rail alignment to the Sierra Leone border and safety issues that it could create. Community Engagement: the need to use local radio stations to communicate and inform on the Simandou Project Scoping Findings The scoping study and stakeholder engagement identified a wide range of potential impacts and concerns relating to construction and operation of the Simandou Ore Railway (1). The details are presented in the Terms of Reference in Annex 1B: SEIA Terms of Reference and the impacts have been grouped for the purposes of this report under the following headings: (1) As noted in Chapter 1 closure of the railway is not included as it is envisaged as remaining in operation once mining has finished. 4-5

6 impacts on soils and geology and management of mineral waste; impacts on the water environment; impacts from noise and vibration; impacts on air quality; greenhouse gas emissions; resources use and non-mineral waste management; impacts on biodiversity ; impacts on cultural heritage; landscape impacts; impacts on the national economy; employment and economic development; in-migration; impacts on land use and land-based livelihoods; impacts on social structures and community life; impacts on community health, safety and security; labour and working conditions; impacts on ecosystem services; and impacts on human rights. The remainder of this report is organised according to these topics and the details of impacts considered under each heading are introduced at the start of each of these chapters. 4.3 Stakeholder Engagement the Next Steps Engagement Principles International best practice recommends the active engagement of stakeholders throughout a Project lifecycle, commencing with scoping. As outlined above, stakeholder engagement has formed an important part of the social and environmental impact studies leading up to this report but it is the intention that this will continue as a crucial aspect of the way social and environmental impacts and risks are managed in the future. This will be undertaken in accordance with IFC guidance and Rio Tinto s policy with regard to engagement. In line with current international good practice the Project will ensure that engagement: is free of manipulation, interference, coercion and intimidation; is free of charges for participation; takes place prior to decisions being made so that views expressed can be taken into account; is conducted on the basis of timely, relevant, understandable and accessible information; is undertaken in a culturally appropriate manner; includes all those interested in or affected by the Project, and in particular, vulnerable groups; achieves a two-way dialogue; and is responsive, and includes explicit mechanisms for receiving, documenting and addressing comments received. Rio Tinto standards require that consultation and engagement are carried out in good faith with mutual obligation. Approaches and procedures must be transparent, inclusive and culturally appropriate, and must ensure that: people and organisations who may be affected by or interested in the Project are as fully informed as practically possible about the Project and its possible effects before they occur and have access to reliable independent advice; 4-6

7 two-way discussions cover stakeholder issues and priorities as well as the concerns and needs of the company; discussions occur in a language and format that is understandable to local stakeholders; stakeholders participate to the greatest extent possible in social and environmental impact assessments; a record is kept of all formal and informal meetings that involve commitments, including how views of both the company and stakeholders may have changed and where agreements have been reached, and of action items with dates for completion; and discussions and community decision-making reflect established local conventions and protocols, including gender considerations, supplemented if necessary by additional processes for inadequately represented and marginalised groups. The programme of engagement activities undertaken during scoping, described in Section 4.2.3, was designed to accord with the above principles and the Simandou Project is committed to continuing this through the lifetime of the Project. The Stakeholder Engagement Plan for the Project has been updated to describe the next steps in this process and the new plan is presented in Annex 1F: Simandou Project Stakeholder Engagement Plan. The remainder of this section outlines the activities planned for the next stage. This focusses on the plan for disclosure of this report and consultation on its findings with Project stakeholders. The processes for enabling and responding to feedback from stakeholders and for managing any grievances that may arise are also described SEIA Disclosure and Consultation A programme of disclosure and stakeholder engagement is planned to run for 3 months from the date of submission of this report to the Republic of Guinea. The aim of this is to provide directly affected communities and other project stakeholders with an opportunity to understand and comment on the results of the assessment and the proposed mitigation measures. This will include the following activities. The SEIA Report and accompanying leaflets and summary material will be published on the Simandou website at (French) and (English) and will be available to download at no cost (a CD copy may also be requested). It will also be available on the IFC website in accordance with its policy on access to information. Hard copies of the report will be available for inspection at the following locations in Guinea and internationally: Simfer SA Immeuble Kankan Cité chemin de fer BP Conakry République de Guinée ; The Simandou InfoShopin Beyla and at further InfoShops as these are developed; Rio Tinto Iron Ore Europe 17, Place de Reflets La Défense Courbevoie Paris France; or 4-7

8 Rio Tinto plc 2 Eastbourne Terrace London W2 6LG United Kingdom. Publication of the report will be announced in newspaper advertisements and through press and media announcements in Conakry and across the prefectures affected by the Project. A national stakeholder conference and series of local stakeholder conferences will be held in each of the prefectures through which the Project passes. These will be widely publicised in local media and invitations will be sent to the regional, prefectural, sub-prefectural and local administrative authorities, to community leaders, and to community-based and non-governmental organisations. The SEIA Team will make direct contact with government departments and non-governmental organisations inviting their comment on the Project and its impacts. In addition to these activities, a programme of mobile exhibition visits led by the Simandou Communities Department and field studies associated with planning for land acquisition, resettlement and compensation will be undertaken, visiting settlements throughout the Project area. These visits will provide the opportunity for communities affected by the Project to be consulted on the SEIA findings and allow local people to comment on the Project and its impacts prior to final decisions on design and construction. Meetings will be held in all villages directly affected by the Project. Local leaders, affected households and businesses, and special sectors within the community including women and other potentially vulnerable groups will be invited and encouraged to attend. The Project will also assist the Ministry of the Environment in organising formal public hearings as required by the Guinean EIA Regulations Managing Stakeholder Feedback Throughout the period of consultation a formal comment and feedback system will operate. Comments and questions can be submitted to the Project Team by various routes: by to simandou.eise@riotinto.com; by writing to: Equipe Communautés - EISE Simfer S.A Immeuble Kankan, Cité Chemin de Fer BP 848 Conakry, République de Guinée or to: Simandou SEIA ERM Exchequer Court 33 St Mary Axe London, EC3A 8AA United Kingdom; by raising a point or asking a question at a stakeholder event; by leaving a written comment at a stakeholder event or at a Simandou Info-shop or Info-post; or by raising an issue with the land acquisition planning team during village level consultations. 4-8

9 Comments can be submitted by any means (in person, in writing, by ) including on the pre-printed feedback form which will be made widely available. A copy of the feedback form is included in Annex 1F: Simandou Project Stakeholder Engagement Plan and is available on the website. All comments made by stakeholders, whether in person, by mail or , will be recorded in a Stakeholder Register and will be considered by the Project Team in completing detailed design, finalising the methods for construction and operation, and updating and implementing the Social and Environmental Management Plan. Where questions are raised that require an individual response, this will be provided and if any parties raise a grievance or complaint this will be managed through the Simandou Grievance Procedure (see Section 4.3.4). A report on the outcome of the consultation process will be prepared and published Grievance Procedure A Grievance Procedure has been established to receive and facilitate resolution of concerns and grievances about the Project s environmental and social performance. The Grievance Procedure is set out in Annex 1G: Simandou Project Grievance Procedure. It has been designed to resolve concerns promptly, using an understandable and transparent process that is culturally appropriate and readily accessible. Grievances will be addressed with no cost to the party that raised the concern and without retribution. The mechanism will also not impede access to other judicial or administrative remedies available to affected parties Future Stakeholder Engagement On completion of the SEIA regulatory procedure the Project will move forward into the implementation phase. A full programme of stakeholder engagement will continue during detailed design and construction phases and then throughout the lifetime of the Project. Details of this will be provided in an update of the Stakeholder Engagement Plan which will be published at the time of Project approval. This will be regularly updated thereafter. The long term programme of engagement will include: on-going liaison with regulatory authorities concerned with environmental and social issues; establishment of local community liaison groups which will be used to keep people informed of Project activities and seek their participation in decisions affecting their communities; publication of regular reports on Project progress, implementation of mitigation measures, compliance with the SEMP and overall performance; and sharing of monitoring results and consultation on responses to unforeseen impacts that may occur. 4-9

consultation with government and other Project stakeholders to determine their views on the likely significant impacts.

consultation with government and other Project stakeholders to determine their views on the likely significant impacts. 4 Scoping and Stakeholder Engagement 4.1 Introduction This chapter describes the approach that was taken to scoping the impact assessment, including activities undertaken to understand the views of stakeholders

More information

EBRD Performance Requirement 10

EBRD Performance Requirement 10 EBRD Performance Requirement 10 Information Disclosure and Stakeholder Engagement Introduction 1. This Performance Requirement (PR) recognises the importance of an open and transparent engagement between

More information

DRAFT FOR PUBLIC COMMENT Guidance Note for ESS10 Stakeholder Engagement and Information Disclosure

DRAFT FOR PUBLIC COMMENT Guidance Note for ESS10 Stakeholder Engagement and Information Disclosure The Guidance Notes provide guidance for the Borrower on the application of the Environmental and Social Standards (ESSs), which form part of the World Bank s 2016 Environmental and Social Framework. The

More information

DRAFT GUIDELINE ON PUBLIC PARTICIPATION IN MYANMAR S EIA PROCESSES CONSULTATION DRAFT

DRAFT GUIDELINE ON PUBLIC PARTICIPATION IN MYANMAR S EIA PROCESSES CONSULTATION DRAFT DRAFT GUIDELINE ON PUBLIC PARTICIPATION IN MYANMAR S EIA PROCESSES CONSULTATION DRAFT 5 April 2017 This Draft Guideline is made possible by the generous support of the American people through the United

More information

Annex A. Stakeholder Engagement Plan

Annex A. Stakeholder Engagement Plan Annex A Stakeholder Engagement Plan A1 LIST OF ACRONYMS Table 1-A Acronyms Abbreviation BID CBO CLO EIA ESIA ERM EP ESMP FGDs IA&Ps IFC KII NGOs NTS SEP Full Definition Background Information Document

More information

Mining & Communities

Mining & Communities Mining & Communities Supporting human rights-based development in the context of industrial mining in Guinea Abridged version of the Practical guide for civil society organizations and local authorities

More information

Stakeholder Engagement Plan Code Of Practice

Stakeholder Engagement Plan Code Of Practice a Stakeholder Engagement Plan Code Of Practice COP 302 Revision 00 A Revisions Paragraph Revision Change Date - 00 Created 20/02/2014 B Approval Name Signature Date Compiled by Dieter Klingenberg 20/02/2014

More information

Environmental and Social Policy

Environmental and Social Policy Environmental and Social Policy Contents Foreword 2 Purpose 2 Commitments 2 Environmental and Social Assessment 3 Operations financed directly 4 Operations financed through Financial Intermediaries 4 Environmental

More information

ANNEXE 2: THE TERMS OF REFERENCE FOR ESIA AND RAP. 1. Objectives. The aim of the study is to achieve the following objectives:

ANNEXE 2: THE TERMS OF REFERENCE FOR ESIA AND RAP. 1. Objectives. The aim of the study is to achieve the following objectives: ANNEXE 2: THE TERMS OF REFERENCE FOR ESIA AND RAP 1. Objectives The aim of the study is to achieve the following objectives: Review of existing EIA and RAP reports on sections of the line which are not

More information

22C Summary of Legislation and Standards Relevant to Labour and Working Conditions

22C Summary of Legislation and Standards Relevant to Labour and Working Conditions 22C Summary of Legislation and Standards Relevant to Labour and Working Conditions Categories Human resource policies and procedures Working conditions and terms of employment Hours of work and leave Working

More information

Employee grievance mechanism Guidance note

Employee grievance mechanism Guidance note EBRD Performance Requirement 2 Labour and working conditions Employee grievance mechanism Guidance note This document contains references to good practices; it is not a compliance document. It should be

More information

ACWA Power Zarqa CCGT Power Plant Zarqa, Jordan

ACWA Power Zarqa CCGT Power Plant Zarqa, Jordan ACWA Power Zarqa CCGT Power Plant Zarqa, Jordan Stakeholder Engagement Plan Prepared For: ACWA Power July 2016 5 Capitals Environmental and Management Consulting PO Box 119899, Sheikh Zayed Road, Dubai,

More information

Child and Family Agency. Research Ethics Committee Guidelines

Child and Family Agency. Research Ethics Committee Guidelines 1 Child and Family Agency Research Ethics Committee Guidelines June 2015 1. Overview 1.1 The Child and Family Agency s commitment to high-quality, ethical research guides the Agency s first Research Strategy

More information

Annex A. Stakeholder Engagement Plan

Annex A. Stakeholder Engagement Plan Annex A Stakeholder Engagement Plan Draft Stakeholder Engagement Plan Environmental &Social Impact Assessment Proposed Yara Dallol Potash Project, Dallol, Ethiopia Version 3 April 2014 www.erm.com The

More information

Joint Framework for Action Ghana

Joint Framework for Action Ghana Joint Framework for Action Ghana 1. Preamble Recognizing the vital role of the cocoa sector in Ghana in bringing jobs and wealth to local communities, while at the same time seeking to be environmentally

More information

Chapter 20: Social Structures and Community Life Introduction

Chapter 20: Social Structures and Community Life Introduction 20 Social Structures and Community Life 20.1 Introduction This chapter considers the Simandou Mine s impacts on social structures and community life. Impacts have been assessed for the construction, operation

More information

Developing a Feedback and Grievance Redress Mechanism (FGRM) for the Fiji National REDD+ Programme TERMS OF REFERENCE

Developing a Feedback and Grievance Redress Mechanism (FGRM) for the Fiji National REDD+ Programme TERMS OF REFERENCE FIJI REDD+ Readiness Program supported by FCPF/World Bank Developing a Feedback and Grievance Redress Mechanism (FGRM) for the Fiji National REDD+ Programme TERMS OF REFERENCE 1. INTRODUCTION Fiji has

More information

Multilateral Investment Guarantee Agency. Performance Standards on Environmental and Social Sustainability

Multilateral Investment Guarantee Agency. Performance Standards on Environmental and Social Sustainability Multilateral Investment Guarantee Agency Performance Standards on Environmental and Social Sustainability Performance Standard on Environmental and Social Sustainability TABLE OF CONTENTS Overview i Performance

More information

5 PUBLIC PARTICIPATION PROCESS 5.1 INTRODUCTION

5 PUBLIC PARTICIPATION PROCESS 5.1 INTRODUCTION 5 PUBLIC PARTICIPATION PROCESS 5.1 INTRODUCTION This Chapter presents a summary of the stakeholder engagement activities planned as part of the EIA process. It serves as a summary of a more detailed Stakeholder

More information

Principles for environmental and social responsibility

Principles for environmental and social responsibility issued by: Principles for environmental and social responsibility Sustainable development is dependent on a balance between economic considerations, social responsibility and environmental protection.

More information

Table A1 - Environmental and Social Safeguard Policies Policy Objectives and Operational Principles

Table A1 - Environmental and Social Safeguard Policies Policy Objectives and Operational Principles Operational Manual - Table A1 - Environmental and Social Safeguard Policies Policy and Staff Connections- World Bank Intranet WB External Site WBG Directory Help Site Map Feedback Home News & Events Countries

More information

Greece Stakeholder Engagement Plan

Greece Stakeholder Engagement Plan Greece Stakeholder Engagement Plan Table of contents List of Acronyms and Abbreviations 4 1. Introduction 5 1.1 Purpose and Objectives of the SEP 5 1.2 TAP Engagement Commitments 5 2. Project Stakeholders

More information

SCHEME OF THE DEPARTMENT OF CHILDREN AND YOUTH AFFAIRS UNDER SECTION 11 OF THE OFFICIAL LANGUAGES ACT

SCHEME OF THE DEPARTMENT OF CHILDREN AND YOUTH AFFAIRS UNDER SECTION 11 OF THE OFFICIAL LANGUAGES ACT SCHEME OF THE DEPARTMENT OF CHILDREN AND YOUTH AFFAIRS UNDER SECTION 11 OF THE OFFICIAL LANGUAGES ACT 2003 2013-2016 1 Table of Contents Chapter 1 Introduction 3 Chapter 2 Overview of the Department of

More information

Chapter 21: Social Structures and Community Life Introduction

Chapter 21: Social Structures and Community Life Introduction 21 Social Structures and Community Life 21.1 Introduction This chapter considers the Simandou Port s impacts on social structures and community life during construction and operation (1). Potential impacts

More information

Performance Requirements

Performance Requirements Environmental and Social Policy 15 Performance Requirements PR 1: Environmental and Social Appraisal and Management Introduction 1. The EBRD considers it important that all companies receiving EBRD financing

More information

7.1 Constitutional Requirement for Environmental Protection in Madagascar

7.1 Constitutional Requirement for Environmental Protection in Madagascar 7. MADAGASCAR 7.1 Constitutional Requirement for Environmental Protection in Madagascar The Constitution of the Republic of Madagascar was passed on 19th August 1992. In relation to the environment, Article

More information

CHAPTER 7 STAKEHOLDER ENGAGEMENT

CHAPTER 7 STAKEHOLDER ENGAGEMENT CHAPTER 7 STAKEHOLDER ENGAGEMENT TABLE OF CONTENTS 7 STAKEHOLDER ENGAGEMENT PROCESS... 7-1 7.1 INTRODUCTION... 7-1 7.2 STAKEHOLDERS IDENTIFIED... 7-2 7.3 STAKEHOLDER ENGAGEMENT PROCESS... 7-4 7.3.1 Stakeholder

More information

International Finance Corporation Activities Related to Indigenous Peoples Issues

International Finance Corporation Activities Related to Indigenous Peoples Issues International Finance Corporation Activities Related to Indigenous Peoples Issues January 2014 IFC ACTIVITIES RELATED TO INDIGENOUS PEOPLES ISSUES EXECUTIVE SUMMARY 1. The International Finance Corporation

More information

Market studies. Guidance on the OFT approach

Market studies. Guidance on the OFT approach Market studies Guidance on the OFT approach Crown copyright 2010 This publication (excluding the OFT logo) may be reproduced free of charge in any format or medium provided that it is reproduced accurately

More information

Terms of Reference for a Gender Analysis

Terms of Reference for a Gender Analysis Terms of Reference for a Gender Analysis 1. BACKGROUND The European Commission defines a gender analysis as the study of differences in the conditions, needs, participation rates, access to resources and

More information

Peer Review Report. Peer Review on Corporate Social Responsibility Helsinki (Finland), 7 November 2013

Peer Review Report. Peer Review on Corporate Social Responsibility Helsinki (Finland), 7 November 2013 Peer Review Report Peer Review on Corporate Social Responsibility Helsinki (Finland), 7 November 2013 Introduction The Finnish Ministry of Employment and the Economy hosted a Peer Review (PR) on Corporate

More information

Information Disclosure

Information Disclosure Information Disclosure What s in this section? 28 28 30 31 Be transparent Apply good practice principles Weigh the risks and benefits Manage information on sensitive and controversial issues Adopting a

More information

Minerals Policy Country Profile CYPRUS

Minerals Policy Country Profile CYPRUS Minerals Policy Country Profile CYPRUS Minerals Policy Country Profile CYPRUS POLICY 1 Mines and Quarries (Regulation) Law Cap. 270 POLICY 2 Town and Country Planning Laws POLICY 3 al Impact Assessment

More information

Roles and functions of Ombudsman and current complaint mechanisms in Pacific Islands

Roles and functions of Ombudsman and current complaint mechanisms in Pacific Islands Roles and functions of and current complaint mechanisms in Pacific Islands This paper details of how and non- complaint handling mechanism varies between different Pacific Islands. Key themes for consideration

More information

Staffing the departments for Voters List and IT in the SEC in order to increase the efficiency of the Commission

Staffing the departments for Voters List and IT in the SEC in order to increase the efficiency of the Commission 04.07.2017 Government of the Republic of Macedonia Plan 3-6-9 The course of the reforms proposed by the Government of the Republic of Macedonia, presented in the "Plan 3-6-9", are based on the Government

More information

EBRD Performance Requirement 1

EBRD Performance Requirement 1 EBRD Performance Requirement 1 Assessment and Management of Environmental and Social Impacts and Issues Introduction 1. This Performance Requirement (PR) establishes the importance of integrated assessment

More information

Armenia: ENA-Modernisation of Distribution Network Stakeholder Engagement Plan: Draft Final Report

Armenia: ENA-Modernisation of Distribution Network Stakeholder Engagement Plan: Draft Final Report Armenia: ENA-Modernisation of Distribution Network Stakeholder Engagement Plan: Draft Final Report Prepared by June 2017 EBRD Armenia: ENA - Modernisation of Distribution Network Stakeholder Engagement

More information

Information on the focal point for the Convention. Information on the point of contact for the Convention

Information on the focal point for the Convention. Information on the point of contact for the Convention Questionnaire for the REPORT OF MONTENEGRO ON THE IMPLEMENTATION OF THE CONVENTION ON ENVIRONMENTAL IMPACT ASSESSMENT IN A TRANSBOUNDARY CONTEXT in the period 2006 2009 Information on the focal point for

More information

Name Organisation under review: Institute for Migration and Ethnic Studies (IMIN)

Name Organisation under review: Institute for Migration and Ethnic Studies (IMIN) TEMPLATE 1 GAP ANALYSIS Name Organisation under review: Institute for Migration and Ethnic Studies (IMIN) Organisation s contact details: Trg Stjepana Radića 3 10000 Zagreb Phone: +385 1 61 11 586, 61

More information

[Extract from HRI/GEN/2/Rev.6]

[Extract from HRI/GEN/2/Rev.6] UNITED NATIONS HRI International Human Rights Instruments [Extract from HRI/GEN/2/Rev.6] HARMONIZED GUIDELINES ON REPORTING UNDER THE INTERNATIONAL HUMAN RIGHTS TREATIES, INCLUDING GUIDELINES ON A CORE

More information

1 PROJECT OVERVIEW. Quantum Power Ghana Gas Limited 1 Knight Piésold Consulting GMF

1 PROJECT OVERVIEW. Quantum Power Ghana Gas Limited 1 Knight Piésold Consulting GMF 1 PROJECT OVERVIEW Quantum Power Ghana Gas Limited (hereinafter referred to as Quantum Power) is a developer, owner and operator of electricity generation assets and power-related infrastructure throughout

More information

DECISION ADOPTED BY THE CONFERENCE OF THE PARTIES TO THE CONVENTION ON BIOLOGICAL DIVERSITY AT ITS NINTH MEETING

DECISION ADOPTED BY THE CONFERENCE OF THE PARTIES TO THE CONVENTION ON BIOLOGICAL DIVERSITY AT ITS NINTH MEETING CBD Distr. GENERAL UNEP/CBD/COP/DEC/IX/16 9 October 2008 CONFERENCE OF THE PARTIES TO THE CONVENTION ON BIOLOGICAL DIVERSITY Ninth meeting Bonn, 19 30 May 2008 Agenda item 4.5 ORIGINAL: ENGLISH DECISION

More information

PEACE IV PROGRAMME ( ) European Territorial Cooperation Programme United Kingdom-Ireland (Ireland - Northern Ireland) EVALUATION PLAN

PEACE IV PROGRAMME ( ) European Territorial Cooperation Programme United Kingdom-Ireland (Ireland - Northern Ireland) EVALUATION PLAN PEACE IV PROGRAMME (2014-2020) European Territorial Cooperation Programme United Kingdom-Ireland (Ireland - Northern Ireland) EVALUATION PLAN 23 NOVEMBER 2016 CONTENTS 1. INTRODUCTION 2. OVERVIEW OF PLANNED

More information

Termoelektrarna Šoštanj. Stakeholder Engagement Plan

Termoelektrarna Šoštanj. Stakeholder Engagement Plan October 2009 Table of Contents INTRODUCTION... 4 1. REQUIREMENTS FOR STAKEHOLDERS ENGAGEMENT... 4 1.1 THE PUBLIC PARTICIPATION PROVISIONS OF SLOVENE LEGISLATION... 4 1.1.1 1.1.2 Public Engagement/Consultations

More information

Terms of Reference Governance Committee

Terms of Reference Governance Committee 1. Purpose Terms of Reference Governance Committee The Governance Committee is responsible for ensuring that BC Assessment and its Board develop and implement an effective approach to corporate governance.

More information

2017 Archaeology Audit Program Procedure Manual. April 2017

2017 Archaeology Audit Program Procedure Manual. April 2017 2017 Archaeology Audit Program Procedure Manual April 2017 Table of Contents Contents Table of Contents... 2 1.0 Introduction and Scope... 3 2.0 Audit Objectives... 3 3.0 Audit Procedures... 4 3.1 Audit

More information

Stakeholder Engagement Plan

Stakeholder Engagement Plan Stakeholder Engagement Plan South Stream Offshore Pipeline Bulgarian Sector, July 2014 Abbreviations Abbreviation EEZ EIA ESIA ESMP ESMS IFC IFC PSs MoEW NGO PAC NTS SCD SEP ToR Description Exclusive

More information

INTEGRATED SAFEGUARDS DATA SHEET APPRAISAL STAGE. Project ID:

INTEGRATED SAFEGUARDS DATA SHEET APPRAISAL STAGE. Project ID: Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Copy Public Disclosure Copy Date ISDS Prepared/Updated: 05-Mar-2014

More information

APEC Occupational Standards Framework. Draft 1.2

APEC Occupational Standards Framework. Draft 1.2 APEC Occupational Standards Framework Draft 1.2 January 2016 Table of Contents List of acronyms... 3 Background... 4 Chronological development... 4 Structure... 5 Scope... 5 Purpose... 5 Principles...

More information

Contents. 3 Introduction. 5 Our values 6 Safety 7 Teamwork 8 Respect 9 Integrity 10 Excellence

Contents. 3 Introduction. 5 Our values 6 Safety 7 Teamwork 8 Respect 9 Integrity 10 Excellence The way we work Contents 3 Introduction 5 Our values 6 Safety 7 Teamwork 8 Respect 9 Integrity 10 Excellence 13 Our code of conduct 14 Safety and health 15 Employment and inclusion 16 Human rights 17 Data

More information

2007/40 Non-legally binding instrument on all types of forests

2007/40 Non-legally binding instrument on all types of forests Recognizing the call made in the Monterrey Consensus of the International Conference on Financing for Development 4 for the strengthening of international tax cooperation through enhanced dialogue among

More information

Environmental and Social Data Sheet

Environmental and Social Data Sheet Environmental and Social Data Sheet Overview Project Name: Project Number: 2013-0342 OUARZAZATE II (PARABOLIC) Country: MOROCCO Project Description: Construction and operation of a 200 MW CSP Parabolic

More information

Summary of Preparatory Study

Summary of Preparatory Study Summary of Preparatory Study 1. Title of the Cooperation Project, Relevant Project Report Preparatory Survey on the Project for the Establishment of Rural Water Supply System in Kambia Town in the Republic

More information

JAPAN BANK FOR INTERNATIONAL COOPERATION GUIDELINES FOR CONFIRMATION OF ENVIRONMENTAL AND SOCIAL CONSIDERATIONS

JAPAN BANK FOR INTERNATIONAL COOPERATION GUIDELINES FOR CONFIRMATION OF ENVIRONMENTAL AND SOCIAL CONSIDERATIONS JAPAN BANK FOR INTERNATIONAL COOPERATION GUIDELINES FOR CONFIRMATION OF ENVIRONMENTAL AND SOCIAL CONSIDERATIONS January 2015 JAPAN BANK FOR INTERNATIONAL COOPERATION 1 Preface Japan Bank for International

More information

NATIONAL INSTITUTE FOR HEALTH AND CARE EXCELLENCE. Health and Social Care Directorate. Indicator Process Guide. Published December 2017

NATIONAL INSTITUTE FOR HEALTH AND CARE EXCELLENCE. Health and Social Care Directorate. Indicator Process Guide. Published December 2017 NATIONAL INSTITUTE FOR HEALTH AND CARE EXCELLENCE Health and Social Care Directorate Indicator Process Guide Published December 2017 Please note that this is an interim factual update to the NICE Indicator

More information

PUBLIC November Dogger Bank Stakeholder Engagement Plan

PUBLIC November Dogger Bank Stakeholder Engagement Plan PUBLIC November 2011 Dogger Bank Stakeholder Engagement Plan Dogger Bank Stakeholder Engagement Plan PUBLIC November 2011 Dogger Bank Stakeholder Engagement Plan Document no. : Contract no. (if applicable):

More information

G4 DEVELOPMENT. Document 2 of 12 Statistics: Quantitative Online Feedback. Second G4 Public Comment Period: Submissions.

G4 DEVELOPMENT. Document 2 of 12 Statistics: Quantitative Online Feedback. Second G4 Public Comment Period: Submissions. G4 DEVELOPMENT Document 2 of 12 Statistics: Quantitative Online Feedback February 2013 INTRODUCTION ABOUT THE SUBMISSIONS DOCUMENTS In 2010 GRI began the development of the fourth generation of its Sustainability

More information

MAURITANIA CHEF DE PROJET

MAURITANIA CHEF DE PROJET MAURITANIA CHEF DE PROJET International Dispute Resolution Centre 70 Fleet Street London EC4Y 1EU United Kingdom Tel: +44 (0)20 7936 7014 office@concordis-international.org www.concordis-international.org

More information

The assessment is based upon the design ore production of 95 million tonnes / annum.

The assessment is based upon the design ore production of 95 million tonnes / annum. 9A Air Quality Assessment Supporting Information This annex sets out the detailed methodology, input data and criteria for the assessment. The overarching assessment approach is detailed in Chapter 9:

More information

Protocol for Developing Multi-Stakeholder Group Terms of Reference and Internal Governance Rules and Procedures

Protocol for Developing Multi-Stakeholder Group Terms of Reference and Internal Governance Rules and Procedures Protocol for Developing Multi-Stakeholder Group Terms of Reference and Internal Governance Rules and Procedures February 2015 Protocol for Developing Multi-Stakeholder Group Terms of Reference and Internal

More information

Sustainable Development Verified Impact Standard

Sustainable Development Verified Impact Standard Sustainable Development Verified Impact Standard Terms of Reference 1. Introduction It can be challenging to consistently and transparently assess and communicate the economic, social and environmental

More information

The Hashemite Kingdom of Jordan

The Hashemite Kingdom of Jordan The Hashemite Kingdom of Jordan Union Pour la Méditerranée DOC. DE SÉANCE N :09/17 REV1 EN DATE DU : 20/04/2017 ORIGINE : UfM Co-presidency Ministerial Declaration of the Union for the Mediterranean (UfM)

More information

GRI Second G4 Public Comment Period

GRI Second G4 Public Comment Period GRI Second G4 Public Comment Period OVERVIEW INTRODUCTION GRI is issuing, for public comment, an exposure draft of the next generation of its reporting Guidelines (G4). The document will be available for

More information

Stakeholder Engagement Strategy

Stakeholder Engagement Strategy Stakeholder Engagement Strategy Contents List of Acronyms and Abbreviations 4 1. Introduction 5 1.1 Purpose and Objectives 5 1.2 Applicable Standards and Guidelines 6 1.3 Articulation with TAP Management

More information

SOCIALIST REPUBLIC OF VIETNAM Independence - Freedom - Happiness No.: 19/2015/ND-CP Hanoi, 14 February 2015 DECREE

SOCIALIST REPUBLIC OF VIETNAM Independence - Freedom - Happiness No.: 19/2015/ND-CP Hanoi, 14 February 2015 DECREE THE GOVERNMENT ------- SOCIALIST REPUBLIC OF VIETNAM Independence - Freedom - Happiness --------------- No.: 19/2015/ND-CP Hanoi, 14 February 2015 DECREE DETAILING THE IMPLEMENTATION OF A NUMBER OF ARTICLES

More information

Environmental and Social Data Sheet

Environmental and Social Data Sheet Environmental and Social Data Sheet Overview Project Name: S3 EXPRESSWAY Project Number: 2012-0666 Country: POLAND Project Description: The project consists of two components, as follows: (i) construction,

More information

Report for Agenda Item: 2

Report for Agenda Item: 2 QLDC Council 28 September 2017 Department: Planning & Development Report for Agenda Item: 2 Stage 2 Proposed District Plan Notification Purpose The purpose of this paper is to present those parts of Stage

More information

A SUSTAINED COMMITMENT TO IMPROVED INDUSTRY PERFORMANCE

A SUSTAINED COMMITMENT TO IMPROVED INDUSTRY PERFORMANCE A SUSTAINED COMMITMENT TO IMPROVED INDUSTRY PERFORMANCE PRINCIPLES REPORTING ASSURANCE The Challenge for the Mining and Metals Industry Minerals and metals lie at the foundation of today s world. But the

More information

IN FOCUS. MATERIAL ISSUES continued ISSUES. Engaging with stakeholders for mutual benefit and building trust

IN FOCUS. MATERIAL ISSUES continued ISSUES. Engaging with stakeholders for mutual benefit and building trust Engagement is an opportunity for us to listen to our stakeholders, and to initiate proactive and meaningful dialogue that captures the voices of all concerned. We continuously seek to be inclusive and

More information

PHILIPPINES: SOCIAL INCLUSION AND ALTERNATIVE LIVELIHOOD FOR THE INFORMAL WASTE SECTOR

PHILIPPINES: SOCIAL INCLUSION AND ALTERNATIVE LIVELIHOOD FOR THE INFORMAL WASTE SECTOR Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized PHILIPPINES: SOCIAL INCLUSION AND ALTERNATIVE LIVELIHOOD FOR THE INFORMAL WASTE SECTOR

More information

Analysis of the final version of Cameroon s R-PP

Analysis of the final version of Cameroon s R-PP Analysis of the final version of Cameroon s R-PP CAMEROON presented its Readiness Preparation Proposal (R-PP) for assessment by the FCPF Participants Committee (PC) at its 13 th meeting held in October

More information

Sustainable Resource Extraction in the Arctic Finnish Network for Sustainable Mining Vienna, 4 October 2016

Sustainable Resource Extraction in the Arctic Finnish Network for Sustainable Mining Vienna, 4 October 2016 Sustainable Resource Extraction in the Arctic Finnish Network for Sustainable Mining Vienna, 4 October 2016 Problem setting: from crisis to cooperation Mining boom in early 2000 => strong investments in

More information

European Agency for Special Needs and Inclusive Education

European Agency for Special Needs and Inclusive Education European Agency for Special Needs and Inclusive Education Multi-Annual Work Programme 2014 2020 www.european-agency.org MULTI- ANNUAL WORK PROGRAMME 2014 2020 European Agency for Special Needs and Inclusive

More information

GLENVEAGH PROPERTIES PLC REMUNERATION AND NOMINATION COMMITTEE TERMS OF REFERENCE

GLENVEAGH PROPERTIES PLC REMUNERATION AND NOMINATION COMMITTEE TERMS OF REFERENCE GLENVEAGH PROPERTIES PLC REMUNERATION AND NOMINATION COMMITTEE TERMS OF REFERENCE Contents Page 1. Purpose and Role 1 2. Membership and attendees 1 3. Secretary and administration 2 4. Quorum 2 5. Frequency

More information

18 Cumulative Impacts and Interaction of Effects

18 Cumulative Impacts and Interaction of Effects 18 Cumulative Impacts and Interaction of Effects 18.1 Introduction This chapter addresses the cumulative impacts and main interactions between different aspects of the environment likely to be significantly

More information

Environmental and social sustainability services

Environmental and social sustainability services Environmental and social sustainability services Protecting our planet and your bottom line Environmental & social sustainability PRECISE. PROVEN. PERFORMANCE. 1 Environmental & social sustainability Environmental

More information

Sections 14.4 to describe baseline conditions in the study area with reference to the following:

Sections 14.4 to describe baseline conditions in the study area with reference to the following: 14 Socio-Economic and Community Baseline 14.1 Introduction This chapter provides a common baseline for subsequent chapters of the SEIA report that address the socio-economic and community impacts of the

More information

HUMAN RESOURCES COMMITTEE CHARTER

HUMAN RESOURCES COMMITTEE CHARTER HUMAN RESOURCES COMMITTEE CHARTER Objective The objective of the Human Resources Committee is to assist the Board in discharging its duty to oversee the establishment of appropriate human resources policies

More information

Summary Report. 1st meeting of the Single European Railway Area Committee (SERAC) Brussels,

Summary Report. 1st meeting of the Single European Railway Area Committee (SERAC) Brussels, EUROPEAN COMMISSION DIRECTORATE-GENERAL FOR MOBILITY AND TRANSPORT Directorate B - European mobility network Summary Report 1st meeting of the Single European Railway Area Committee (SERAC) Brussels, 31.1.2013

More information

THE ENERGY DEVELOPMENT CYCLE

THE ENERGY DEVELOPMENT CYCLE THE ENERGY DEVELOPMENT CYCLE PRE-PROJECT EXPLORATION APPRAISAL & DEVELOPMENT OPERATION CLOSURE USE Risks & Opportunities Across the Development Cycle Activities prior to the start of the individual project

More information

IGF Geneva 2016 MPF-SDG Comparative Analysis. Perrine Toledano CCSI, Head: Extractive Industries

IGF Geneva 2016 MPF-SDG Comparative Analysis. Perrine Toledano CCSI, Head: Extractive Industries IGF Geneva 2016 MPF-SDG Comparative Analysis Perrine Toledano CCSI, Head: Extractive Industries SDG and MPF: Can they connect? The Sustainable Development Goals (SDGs) form the post-2015 global development

More information

FRAMEWORK CONVENTION ON THE PROTECTION AND SUSTAINABLE DEVELOPMENT OF THE CARPATHIANS

FRAMEWORK CONVENTION ON THE PROTECTION AND SUSTAINABLE DEVELOPMENT OF THE CARPATHIANS FRAMEWORK CONVENTION ON THE PROTECTION AND SUSTAINABLE DEVELOPMENT OF THE CARPATHIANS 2 The Parties, ACKNOWLEDGING that the Carpathians are a unique natural treasure of great beauty and ecological value,

More information

AIA Group Limited. Terms of Reference for the Remuneration Committee

AIA Group Limited. Terms of Reference for the Remuneration Committee AIA Group Limited Terms of Reference for the Remuneration Committee AIA Restricted and Proprietary Information Issued by : Board of AIA Group Limited Date : 15 November 2013 Version : 4.0 Definitions 1.

More information

Terms of Reference. Quality and Value Audits

Terms of Reference. Quality and Value Audits Terms of Reference Quality and Value Audits Table of Contents SECTION 1 General 3 1.1 Introduction 3 1.2 Statutory authority 3 1.3 Purpose and Scope 4 SECTION 2 Methodology 6 2.1 The audit programme 6

More information

COMPLIANCE WITH THE INTERNATIONAL COUNCIL FOR MINING AND METALS ASSURANCE PROCEDURE 2017

COMPLIANCE WITH THE INTERNATIONAL COUNCIL FOR MINING AND METALS ASSURANCE PROCEDURE 2017 COMPLIANCE WITH THE INTERNATIONAL COUNCIL FOR MINING AND METALS ASSURANCE PROCEDURE 2017 As a member of the International Counsel on Mining and Metals (ICMM), Anglo American adheres to the ICMM Assurance

More information

Environmental and Social Considerations in Detailed Planning Survey. (Technical Cooperation for Development Planning)

Environmental and Social Considerations in Detailed Planning Survey. (Technical Cooperation for Development Planning) Page: 1 Date: May 27, 2014 Environmental and Social Considerations in Detailed Planning Survey (Technical Cooperation for Development Planning) 1. Full Title of the Project 2. Type of the study (e.g. Master

More information

JAPAN BANK FOR INTERNATIONAL COOPERATION GUIDELINES FOR CONFIRMATION OF ENVIRONMENTAL AND SOCIAL CONSIDERATIONS

JAPAN BANK FOR INTERNATIONAL COOPERATION GUIDELINES FOR CONFIRMATION OF ENVIRONMENTAL AND SOCIAL CONSIDERATIONS JAPAN BANK FOR INTERNATIONAL COOPERATION GUIDELINES FOR CONFIRMATION OF ENVIRONMENTAL AND SOCIAL CONSIDERATIONS APRIL 2002 JAPAN BANK FOR INTERNATIONAL COOPERATION Preface Japan Bank for International

More information

Stakeholder Engagement paper

Stakeholder Engagement paper R-PP Finalization Project Climate Compatible Development Agency 17 September 01 Stakeholder Engagement paper Introduction REDD+ readiness in the context of the Forest Carbon Partnership Facility (FCPF)

More information

The Effluent Permitting Process under the Environmental Management Act. An Overview for Mine Project Applicants

The Effluent Permitting Process under the Environmental Management Act. An Overview for Mine Project Applicants The Effluent Permitting Process under the Environmental Management Act An Overview for Mine Project Applicants APRIL 2013 Disclaimer This document does not replace the Environmental Management Act or its

More information

This document is meant purely as a documentation tool and the institutions do not assume any liability for its contents

This document is meant purely as a documentation tool and the institutions do not assume any liability for its contents 2001L0018 EN 21.03.2008 003.001 1 This document is meant purely as a documentation tool and the institutions do not assume any liability for its contents B DIRECTIVE 2001/18/EC OF THE EUROPEAN PARLIAMENT

More information

Environmental Policy and Guide December 2010

Environmental Policy and Guide December 2010 Environmental Policy and Guide December 2010 Page 1 of 11 ENVIRONMENTAL POLICY A responsible and forward-looking approach to environmental issues is an important factor in Intu Properties plc s continuing

More information

Collaborative Partnership on Mediterranean Forests

Collaborative Partnership on Mediterranean Forests Collaborative Partnership on Mediterranean Forests between the Food and Agriculture Organization of the United Nations (FAO) on behalf of the Committee on Mediterranean Forestry Questions - Silva Mediterranea

More information

Network Rail Limited (the Company ) Terms of Reference. for. The Audit and Risk Committee of the Board

Network Rail Limited (the Company ) Terms of Reference. for. The Audit and Risk Committee of the Board Network Rail Limited (the Company ) Terms of Reference for The Audit and Risk Committee of the Board Membership of the Audit and Risk Committee 1 The Audit and Risk Committee (the Committee ) shall comprise

More information

STAFF DISCIPLINE CONDUCT AND GRIEVANCE POLICY

STAFF DISCIPLINE CONDUCT AND GRIEVANCE POLICY Hampton Wick Infant & Nursery School STAFF DISCIPLINE CONDUCT AND GRIEVANCE POLICY This policy was adopted/updated: Dec 2009 This policy was reviewed: Jan 2014 This policy will be reviewed: Sep 2016 (or

More information

ICGN Response to Revision of Japan s Corporate Governance Code based on the proposal of the Council

ICGN Response to Revision of Japan s Corporate Governance Code based on the proposal of the Council TSE Listing Department Japan Exchange Group E-Mail: jojo-kikaku@jpx.co.jp 29 April 2018 To Whom this May Concern ICGN Response to Revision of Japan s Corporate Governance Code based on the proposal of

More information

AMDAL Procedure. Flowchart of Indonesian Environmental Clearance 1

AMDAL Procedure. Flowchart of Indonesian Environmental Clearance 1 AMDAL Procedure (This is only indicative and for reference purposes. This is not exhaustive and therefore, the Consultants are requested to familiarize themselves with all the laws, rules, regulations,

More information

Case of MIGA s Guarantee Linked to the Engineering and Feasibility Phase of Developing the PT Weda Bay Nickel Project. Summary

Case of MIGA s Guarantee Linked to the Engineering and Feasibility Phase of Developing the PT Weda Bay Nickel Project. Summary APPRAISAL REPORT CAO Appraisal for Audit of MIGA CAO Compliance October 3, 2011 PT Weda Bay Nickel Indonesia Case of MIGA s Guarantee Linked to the Engineering and Feasibility Phase of Developing the PT

More information

PROJECT CONCEPT PRELIMINARY QUESTIONAIRE PART I: GENERAL INFORMATION. GEF: OTHER(S) (Specify)

PROJECT CONCEPT PRELIMINARY QUESTIONAIRE PART I: GENERAL INFORMATION. GEF: OTHER(S) (Specify) PROJECT CONCEPT PRELIMINARY QUESTIONAIRE PART I: GENERAL INFORMATION Interested Organization Name: Project Location: Projected amount of required project funding ($ /USD): TOTAL: Project Sector or Similar:

More information

LAO PEOPLE S DEMOCRATIC REPUBLIC PEACE INDEPENDENCE DEMOCRACY UNITY PROSPERITY. Report on International Year of Biodiversity 2010

LAO PEOPLE S DEMOCRATIC REPUBLIC PEACE INDEPENDENCE DEMOCRACY UNITY PROSPERITY. Report on International Year of Biodiversity 2010 LAO PEOPLE S DEMOCRATIC REPUBLIC PEACE INDEPENDENCE DEMOCRACY UNITY PROSPERITY Report on International Year of Biodiversity 2010 As we are all aware, the year 2010 is significant because the United Nations

More information

GRI Greenhouse Gas (GHG) Emissions Working Group

GRI Greenhouse Gas (GHG) Emissions Working Group GRI TERMS OF REFERENCE These (hereafter ToR ) outline the G4 Working Group ( WG ) workstream on Greenhouse Gas (GHG) Emissions. GRI will select WG members to participate in the development of the next

More information