1 The Canadian EIA Process: The Purpose, The Process, The Players and The Pitfalls Part I The Purpose and Process Presented by: Teresa Meadows, Senior Associate TODAY S SESSION 1. Why does a project engineer need to know this stuff? 2. Why do we do environmental impact assessments? 3. What are some key concepts in environmental impact assessment? 4. What are the recent changes to the environmental impact assessment process in Canada and Alberta? 1

2 Why Do Project Engineers Need to Know This? As the Keystone Pipeline and Prosperity Gold-Copper Mine Project have indicated until an EIA has been concluded and regulatory approvals granted you may not have a project When approvals are given the basis for limits, design criteria, operating parameters and monitoring are the EIA report and recommendations EI, EI, EIA Environmental Impact Assessment Regimes 2

3 Why Do We Do Environmental Assessment? the problems to be addressed, from the beginning to the end, should not be limited to problems of engineering and construction. Social, economic and environmental considerations should be addressed at this early stage and throughout, with the same intensity and concern as technical and engineering questions. Thomas Berger, Mackenzie Valley Pipeline Inquiry: Synopsis of Volume Two. (Online version available from the National Energy Board website) The Conceptual Basis for EAs The basic concepts behind environmental assessment are simply stated: (1) early identification and evaluation of all potential environmental consequences of a proposed undertaking; (2) decision making that both guarantees the adequacy of this process and reconciles, to the greatest extent possible, the proponent's development desires with environmental protection and preservation. [Purpose of EA in an early textbook discussing the subject as cited with approval by the Supreme Court of Canada in Friends of the Oldman River Society v. Canada (Minister of Transport), 1992 CanLII 110 (S.C.C.)] 3

4 Key Concepts: Environmental Assessment Adaptive Management In the face of uncertainty AM is an iterative process of decisionmaking that involves making initial decisions based on the existing data, monitoring and evaluating the effectiveness of decisions made (including things like mitigation measures) and adjusting the future actions to reflect the monitoring data and the consideration of the effectiveness of the measures taken Key Concepts: Environmental Assessment Precautionary Principle Where there are threats of serious or irreversible damage, a lack of scientific certainty should not be used as a reason for postponing measures to prevent environmental degradation To see a practical example of how the precautionary principle and adaptive management can play out in an EIA check out the Nunavut Impact Review Board s decision in the Mary River Project 4

5 Key Concepts -- Significance no significant impact In Environmental Assessment, a finding of no significant impact is NOT the same as stating zero impact or zero negative impact no significant impact means that the impacts are manageable, capable of being limited, managed, mitigated or responded to in a way that does not result in significant, permanent, irreversible environmental effects/impacts Key Concepts Cumulative Effects Must consider this project in the context of other impacts in the area, and in general, cumulative effects assessment requires an understanding of: The resources that will likely be affected directly or indirectly The geographic scale where the projected impacts are anticipated to accrue The timeframe in which the effects of the projected impacts will occur These considerations should lead to an overall assessment of the impacts that can be expected if the individual impacts are allowed to accumulate over time 5

6 The Canadian Environmental Assessment Act, S.C. 1992, c. 37 Federal Environmental Assessment: CEAA 2012 Introduces Sweeping Changes In the first omnibus budget bill introduced April 26, 2012 and came into force on July 6, 2012, the Federal Government replaced the Canadian Environmental Assessment Act (CEAA) with an entirely new Act, CEAA, 2012 Key changes: CEAA 2012 changes from requiring EA if triggered to only applying to designated projects as defined under the Regulations Designating Physical Activities, SOR/ and the RA assessing whether EA is required 6

7 Sweeping Changes (cont d) Reduces the number of Federal agencies responsible for reviews conducted by a panel from more than 40 to just 3, the Canadian Environmental Assessment Agency, the National Energy Board and the Canadian Nuclear Safety Agency The types of assessment have been reduced from 4 to 2: general EA and review panel There are cost recovery provisions for the responsible authorities conducting a general EA or the parties conducting a Panel Review Sweeping Changes (cont d) Establishes that the Canadian Environmental Assessment Agency must screen the project and decide whether a federal environmental assessment is required of designated projects within 45 days of receipt of a complete project description Also establishes time limits in which EA must be concluded (exclusive of time where authority awaits response from Proponent): General EA 365 days from the date the notice of commencement is posted Review Panel 24 months from establishment of panel (Minister has authority to vary) NEB Review: months CNSC Review: No prescribed timeline 7

8 Sweeping Changes (cont d) If the Minister is of the opinion that a provincial EA process would be an appropriate substitute for the Federal process (e.g. Prosperity Mine in BC), the Minister must, upon request of the Province substitute the Provincial process and no federal EA is conducted Note: substitution does not apply if the CNSC or NEB are the responsible authorities for the project or if the project has been sent to a panel review already Significant change in public participation, as definition changes from broad CEAA def n of interested party (essentially having an interest in the outcome that is not frivolous or vexatious) to those who are directly affected by the carrying out of the project Developing Issues CEAA 2012 It is anticipated that challenges to the interested parties determinations will be forthcoming, particularly for aboriginal groups that were not consulted about the repeal of CEAA and replacement with CEAA 2012 (see the recent approach of the Joint Review Panel in Shell s Jackpine Mine Expansion Hearing) and Idle No More protests The Regulations Designating Physical Activities remove several types of activities related to National Parks that formerly required comprehensive study level assessments from the definition of designated projects in response, Parks Canada is indicating that to fulfill their mandate they may require their own form of EA 8

9 So WHAT? There will be very little Federal EA estimates that of the 2950 projects that had a trigger for a screening level EA under the former CEAA, 0 will meet definition of designated project and of the 39 projects sent for comprehensive study under the former CEAA only 7 would now likely be required to proceed under CEAA 2012 The Provincial process will be under much more scrutiny AND this process for energy developments is undergoing a massive overhaul after the passage of Alberta s Bill 2: The Responsible Energy Development Act including the addition of a new regulator, the Alberta Energy Regulator There are court challenges to these amendments on the basis of a lack of consultation with aboriginal persons (a constitutionally protected right to nation-to-nation consultation) BOTTOM LINE: Uncertainty abounds for regulators, proponents, aboriginal participants and, yes, even lawyers, as we all attempt to figure out the new rules Provincial EIA Requirements Consult: EPEA ss ; Mandatory and Exempted Activities Reg. A.R. 111/93 Environmental Assessment Reg. A.R. 112/93 9

10 What Does A Provincial EIA Currently Look Like? Key areas included in most Alberta EIAs: Public Engagement and Aboriginal Consultation; Project Description (including evaluation of alternatives to the project and measures for preventing environmental impacts); Environmental Assessment (baselines, projection of impacts and monitoring mechanisms); Historical Resources; Traditional Ecological Knowledge and Land Use; Key areas in Alberta EIAs (cont d) Public Health and Safety Assessment; Socio-Economic Assessment (baselines and projected impacts); Mitigation Measures; Residual Impacts; and Monitoring See for example Guide to Preparing Environmental Impact Assessment Reports in Alberta (updated February 2011) available online at: the Standardized Terms of Reference for EIAs provided by Alberta Environment for in situ projects, oilsands, coal mines and industrial plants (updated January 2013) and available on-line at: 10

11 Added experience. Added clarity. Added value. Follow us... 11

Canada s New Federal Environmental Assessment Process

Canada s New Federal Environmental Assessment Process Canada s New Federal Environmental Assessment Process Publication No. 2012-36-E 28 August 2012 Penny Becklumb Tim Williams Industry, Infrastructure and Resources Division Parliamentary Information and

More information

Canadian Environmental Assessment Act, Newfoundland Environmental Industry Association November 21, 2012

Canadian Environmental Assessment Act, Newfoundland Environmental Industry Association November 21, 2012 Canadian Environmental Assessment Act, 2012 Newfoundland Environmental Industry Association November 21, 2012 Overview of Changes CEAA 2003 EA Process Driven by federal involvement in a project Applies

More information

The Past, Present, and Future of Environmental Assessment in Canada. Professor Martin Olszynski University of Calgary Faculty of Law 23 February 2016

The Past, Present, and Future of Environmental Assessment in Canada. Professor Martin Olszynski University of Calgary Faculty of Law 23 February 2016 The Past, Present, and Future of Environmental Assessment in Canada Professor Martin Olszynski University of Calgary Faculty of Law 23 February 2016 Overview The Past: EA as decision-making process in

More information

THE proposed IMPACT ASSESSMENT SYSTEM. A Technical Guide

THE proposed IMPACT ASSESSMENT SYSTEM. A Technical Guide THE proposed IMPACT ASSESSMENT SYSTEM A Technical Guide 1 A GUIDE TO THE PROPOSED NEW IMPACT ASSESSMENT SYSTEM A clean environment and a strong economy go hand in hand. The Government of Canada is putting

More information

THE proposed IMPACT ASSESSMENT SYSTEM

THE proposed IMPACT ASSESSMENT SYSTEM THE proposed IMPACT ASSESSMENT SYSTEM A Technical Guide Updated August 14, 2018 1 A GUIDE TO THE PROPOSED NEW IMPACT ASSESSMENT SYSTEM A clean environment and a strong economy go hand in hand. The Government

More information

Environmental Assessment Program

Environmental Assessment Program Environmental Assessment Program Frequently Asked Questions Updated February 2010 Introduction The following is a list of questions that are commonly asked by both project Proponents and the public regarding

More information

NWMO BACKGROUND PAPERS 7. INSTITUTIONS AND GOVERNANCE

NWMO BACKGROUND PAPERS 7. INSTITUTIONS AND GOVERNANCE February 2004 NWMO BACKGROUND PAPERS 7. INSTITUTIONS AND GOVERNANCE 7-8 REVIEW OF THE CANADIAN ENVIRONMENTAL ASSESSMENT ACT (CEAA) PROCESS IN RELATION TO NUCLEAR WASTE MANAGEMENT Robert S. Boulden Boulden

More information

Bill C-38 Part Three Questions and Answers on Changes to Environmental Laws

Bill C-38 Part Three Questions and Answers on Changes to Environmental Laws Bill C-38 Part Three Questions and Answers on Changes to Environmental Laws Introduction The Assembly of First Nations (AFN) is the representative body for over 630 First Nations across Canada. As part

More information

A Study of Public Participation under the Canadian Environmental Assessment Act 2012

A Study of Public Participation under the Canadian Environmental Assessment Act 2012 FACULTY OF LAW A Study of Public Participation under the Canadian Environmental Assessment Act 2012 Shaun Fluker Nitin Kumar Srivastava June 5, 2015 Designated project EA by panel review Interested party

More information

Environmental Assessment in Canada

Environmental Assessment in Canada Environmental Assessment in Canada 1. International Building Blocks for Environmental Assessment 2. Role of the Canadian Environmental Assessment Act 3. The Ontario Environmental Assessment Act 4. Procedures

More information

Environmental Assessment Process Review

Environmental Assessment Process Review Environmental Assessment Process Review CANADIAN BAR ASSOCIATION ENVIRONMENT, ENERGY AND RESOURCES LAW SECTION AND ABORIGINAL LAW SECTION December 2016 500-865 Carling Avenue, Ottawa, ON, Canada K1S 5S8

More information

ENVIRONMENTAL LAW CENTRE. April 19, 1999

ENVIRONMENTAL LAW CENTRE. April 19, 1999 CEAA, as well as Alberta resource and environmental protection legislation, serves the interests of Albertans, and, consequently, its terms must be met as framed. AWA, et al. v. Minister of Fisheries and

More information

Changes to Federal Environmental Assessment and Regulatory Legislation

Changes to Federal Environmental Assessment and Regulatory Legislation Changes to Federal Environmental Assessment and Regulatory Legislation EnviroTech Regulatory Workshop April 3, 2018 Shailaz Dhalla BUSINESS LAW Why are we here today? February 6, 2018 - Bill C-68, An Act

More information

Reconciling the duty to consult with other law

Reconciling the duty to consult with other law Reconciling the duty to consult with other law Lexpert Aboriginal Law Consultation and Other Emerging Issues Robin Junger Partner and National Co-Chair, First Nations and Aboriginal Law Group November

More information

Section 1.2 Guiding Principles Page 6

Section 1.2 Guiding Principles Page 6 Section 1.2 Guiding Principles Page 6 1.2 GUIDING PRINCIPLES The EIS Guidelines outline a number of principles to guide the preparation and content of this EIS. The principles adopted and incorporated

More information

ENVIRONMENTAL ASSESSMENT REVITALIZATION DISCUSSION PAPER

ENVIRONMENTAL ASSESSMENT REVITALIZATION DISCUSSION PAPER ENVIRONMENTAL ASSESSMENT REVITALIZATION DISCUSSION PAPER TABLE OF CONTENTS BACKGROUND Introduction Reconciliation What We Have Done and What is Next Summary of Engagements to Date REVITALIZATION FOCUS

More information

Canad~ Record of Decision. In the Matter of. Canadian Nuclear Laboratories

Canad~ Record of Decision. In the Matter of. Canadian Nuclear Laboratories Canadian Nuclear Safety Commission Commission canadienne de sorete nucleaire Record of Decision In the Matter of Applicant Canadian Nuclear Laboratories Subject Decision on the Scope of Environmental Assessments

More information

SOCIO-ECONOMIC EFFECTS MANAGEMENT PLANNING IN BRITISH COLUMBIA, CANADA A NEW ERA

SOCIO-ECONOMIC EFFECTS MANAGEMENT PLANNING IN BRITISH COLUMBIA, CANADA A NEW ERA IAIA17 Conference Proceedings IA s Contribution in Addressing Climate Change 37 th Annual Conference of the International Association for Impact Assessment 4-7 April 2017 Le Centre Sheraton Montréal Canada

More information

Obtaining and Securing Project Approvals North of 60: Understanding the Environmental Regulatory Regime by W.K. McNaughton; Summary by Duncan Finley

Obtaining and Securing Project Approvals North of 60: Understanding the Environmental Regulatory Regime by W.K. McNaughton; Summary by Duncan Finley Obtaining and Securing Project Approvals North of 60: Understanding the Environmental Regulatory Regime by W.K. McNaughton; Summary by Duncan Finley 1.0 Introduction The environmental regulatory regime

More information

NOVA SCOTIA ENVIRONMENTAL BILL OF RIGHTS. A Project of the Nova Scotia Environmental Rights Working Group

NOVA SCOTIA ENVIRONMENTAL BILL OF RIGHTS. A Project of the Nova Scotia Environmental Rights Working Group NOVA SCOTIA ENVIRONMENTAL BILL OF RIGHTS A Project of the Nova Scotia Environmental Rights Working Group Table of Contents Preamble 3 PART I Purposes and Guiding Principles of the Act 4 Purposes of the

More information

Site C Dam The Crown s approach to Treaty 8 First Nations consultation SITE C PROJECT BC S PROPOSED PROCESS TO APPROVE SITE C. Legal backgrounder:

Site C Dam The Crown s approach to Treaty 8 First Nations consultation SITE C PROJECT BC S PROPOSED PROCESS TO APPROVE SITE C. Legal backgrounder: Legal backgrounder: Site C Dam The Crown s approach to Treaty 8 First Nations consultation Summary: The Site C Dam project proposal engages the jurisdiction and lawful authority of Treaty 8 First Nations.

More information

A fair, predictable, credible, transparent and efficient Environmental Assessment (EA) process

A fair, predictable, credible, transparent and efficient Environmental Assessment (EA) process Review of Environmental Assessment Processes A fair, predictable, credible, transparent and efficient Environmental Assessment (EA) process Brief submitted to: Expert Panel for Review of Environmental

More information

IMPLEMENTATION OF THE METIS SETTLEMENTS CONSULTATION POLICY

IMPLEMENTATION OF THE METIS SETTLEMENTS CONSULTATION POLICY 1 IMPLEMENTATION OF THE METIS SETTLEMENTS CONSULTATION POLICY BACKGROUND The Government of Alberta s Policy on Consultation with Metis Settlements on Land and Natural Resource Management, 2015 (Policy)

More information

Shell Quest Carbon Capture and Storage Project. Shell Canada Limited

Shell Quest Carbon Capture and Storage Project. Shell Canada Limited SCREENING SCOPING DOCUMENT For the proposed Shell Quest Carbon Capture and Storage Project Shell Canada Limited Prepared by: Canadian Environmental Assessment Agency Natural Resources Canada Fisheries

More information

Nuclear Regulation in Canada

Nuclear Regulation in Canada Nuclear Regulation in Canada The Michael Rinker Director General Directorate of Environmental and Radiation Protection and Assessment Presentation to Mandated Review EA Panel Ottawa, ON September 9, 2016

More information

Licensing Nuclear Power Plants in Canada. Ensuring Safe and Environmentally Acceptable Operations

Licensing Nuclear Power Plants in Canada. Ensuring Safe and Environmentally Acceptable Operations Licensing Nuclear Power Plants in Canada Ensuring Safe and Environmentally Acceptable Operations Nuclear Power the ultimate Energy Source It s been around a long time Nuclear power closer to home Needs

More information

Aligning Environmental Impact Assessment (EIA) with Existing Environmental Regulatory and Management Frameworks to Improve EIA Quality

Aligning Environmental Impact Assessment (EIA) with Existing Environmental Regulatory and Management Frameworks to Improve EIA Quality Aligning Environmental Impact Assessment (EIA) with Existing Environmental Regulatory and Management Frameworks to Improve EIA Quality Celesa L. Horvath 1 and Jeffrey L. Barnes 2 Introduction Canada has

More information

February 15, Mr. Kyle Stanfield Prodigy Gold Incorporated Box 209, 3 Dree Road Dubreuilville, ON P05 1BO

February 15, Mr. Kyle Stanfield Prodigy Gold Incorporated Box 209, 3 Dree Road Dubreuilville, ON P05 1BO Environmental Assessment Canadian Agency Agence canadienne devaluation environnementale Ontario Regional Office Bureau regional de Ontario 55 St. Clair Avenue East, 55, avenue St-Clair est, Room 907 bureau

More information

COAL AND COAL SEAM GAS REGULATION

COAL AND COAL SEAM GAS REGULATION COAL AND COAL SEAM GAS REGULATION The Australian Government protects water resources from the impacts of coal and coal seam gas development through the water trigger provisions of the Environment Protection

More information

Facilitating Implementation of the Canada-Ontario Agreement on Environmental Assessment Cooperation

Facilitating Implementation of the Canada-Ontario Agreement on Environmental Assessment Cooperation Federal/Provincial Environmental Assessment Coordination in Ontario A Guide for Proponents and the Public Facilitating Implementation of the Canada-Ontario Agreement on Environmental Assessment Cooperation

More information

1. The NSC Act now binds the crown (federal and provincial government departments and agencies).

1. The NSC Act now binds the crown (federal and provincial government departments and agencies). THE CONTAMINATED LANDS EVALUATION AND ASSESSMENT NETWORK PROGRAM R.E. Stenson, Canadian Nuclear Safety Commission, P.O. Box 1046, Station B, Ottawa CANADA K1P 5S9 ABSTRACT The (Contaminated Lands Evaluation

More information

Species at Risk Act Policies and Guideline Series

Species at Risk Act Policies and Guideline Series Species at Risk Act Policies and Guideline Series Addressing Species at Risk Act Considerations Under the Canadian Environmental Assessment Act for Species Under the Responsibility of the Minister responsible

More information

Reasons for Ministers Decision

Reasons for Ministers Decision In the matter of the Environmental Assessment Act S.B.C. 2002, c. 43 (Act) and In the matter of an Application for an Environmental Assessment Certificate (Application) by Teck Coal Limited (Proponent)

More information

Comments On "Reforming Environmental Assessment In British Columbia: A Legislation Discussion Paper"

Comments On Reforming Environmental Assessment In British Columbia: A Legislation Discussion Paper Comments On "Reforming Environmental Assessment In British Columbia: A Legislation Discussion Paper" Introduction Since 1974, the West Coast Environmental Law Association (WCELA) has provided legal services

More information

Canadian Northern Economic Development Agency, as represented by the President of the Canadian Northern Economic Development Agency ( CanNor )

Canadian Northern Economic Development Agency, as represented by the President of the Canadian Northern Economic Development Agency ( CanNor ) MEMORANDUM OF UNDERSTANDING DEFINING TERMS AND SCOPE OF COOPERATION BETWEEN FEDERAL DEPARTMENTS, AGENCIES AND THE NORTHERN PROJECTS MANAGEMENT OFFICE FOR COORDINATION OF NORTHERN PROJECTS This Memorandum

More information

2010 EIA Regulations GNR 543 of 18 June 2010, effective 2 August 2010

2010 EIA Regulations GNR 543 of 18 June 2010, effective 2 August 2010 2010 EIA Regulations GNR 543 of 18 June 2010, effective 2 August 2010 CH 1 INTERPRETATION AND PURPOSE OF THESE REGULATIONS S 1 Interpretation; S 2 Purpose of Regulations CH 2 COMPETENT AUTHORITY S3 Who;

More information

TABLE OF CONTENTS. Glossary of Common Environmental Assessment Terms Introduction Environment Assessment Roles and Responsibilities...

TABLE OF CONTENTS. Glossary of Common Environmental Assessment Terms Introduction Environment Assessment Roles and Responsibilities... Disclaimer: This toolkit is intended to assist First Nation communities in understanding the federal, provincial, and/or First Nation environmental assessment regime processes as they relate to energy

More information

CONTACT INFORMATION. Copies of the Cooperation Plan are available from the following offices and web sites.

CONTACT INFORMATION. Copies of the Cooperation Plan are available from the following offices and web sites. CONTACT INFORMATION The chairs of the boards and agencies responsible for assessing and regulating energy developments in the Northwest Territories have developed a Cooperation Plan describing how, in

More information

REVIEW OF ALTERNATIVES IN DARLINGTON NEW BUILD ENVIRONMENTAL IMPACT STATEMENT

REVIEW OF ALTERNATIVES IN DARLINGTON NEW BUILD ENVIRONMENTAL IMPACT STATEMENT REVIEW OF ALTERNATIVES IN DARLINGTON NEW BUILD ENVIRONMENTAL IMPACT STATEMENT Report to Safe And Green Energy (SAGE) Prepared by the Canadian Environmental Law Association, Theresa A. McClenaghan October

More information

Fisheries and Oceans Canada Species at Risk Act. Directive on the Identification of Critical Habitat for Aquatic Species at Risk

Fisheries and Oceans Canada Species at Risk Act. Directive on the Identification of Critical Habitat for Aquatic Species at Risk Fisheries and Oceans Canada Species at Risk Act Directive on the Identification of Critical Habitat for Aquatic Species at Risk January 2015 Species at Risk Program Programme d espèces en péril To be read

More information

RE: Statutory Review of the Canadian Environmental Assessment Act

RE: Statutory Review of the Canadian Environmental Assessment Act November 21, 2011 Our File: P-5000-540-5450 Marie-France Renaud Procedural Clerk Standing Committee on Environment and Sustainable Development House of Commons Ottawa, ON K1A 0A6 613-992-5023 ENVI@parl.gc.ca

More information

Expert Panel Review of Federal EA Processes British Columbia s Submission

Expert Panel Review of Federal EA Processes British Columbia s Submission Expert Panel Review of Federal EA Processes British Columbia s Submission Environmental Assessment Office and Canadian Environmental Assessment Act 2012 December 20, 2016 2 TABLE OF CONTENTS A. INTRODUCTION...

More information

CABINET DIRECTIVE ON STREAMLINING REGULATION

CABINET DIRECTIVE ON STREAMLINING REGULATION CABINET DIRECTIVE ON STREAMLINING REGULATION Her Majesty the Queen in Right of Canada, 2007 Catalogue No. BT22-110/2007 ISBN 978-0-662-49149-1 Table of Contents Our Commitment to Canadians... 1 1.0 Introduction...

More information

Date: December 13, From: W. Turner. To: Lucia Abellan, Environmental Assessment Officer Canadian Nuclear Safety Commission

Date: December 13, From: W. Turner. To: Lucia Abellan, Environmental Assessment Officer Canadian Nuclear Safety Commission Date: December 13, 2017 From: W. Turner To: Lucia Abellan, Environmental Assessment Officer Canadian Nuclear Safety Commission By email: cnsc.ea-ee.ccsn@canada.ca Subject line: Submission with Respect

More information

Canada. Record of Proceedings, Including Reasons for Decision. Cameco Corp_o_ra_ti_o_n. Proponent

Canada. Record of Proceedings, Including Reasons for Decision. Cameco Corp_o_ra_ti_o_n. Proponent Canadian Nuclear Safety Commission Commission canadienne de sorete nucleaire Record of Proceedings, Including Reasons for Decision Proponent Cameco Corp_o_ra_ti_o_n _ Subject Comprehensive Study Report

More information

Licensing Process for New Uranium Mines and Mills in Canada

Licensing Process for New Uranium Mines and Mills in Canada May 2010 1 Minister of Public Works and Government Services Canada 2010 Catalogue number CC172-40/2010E-PDF ISBN 978-1-100-15866-2 Published by the Canadian Nuclear Safety Commission (CNSC) Catalogue number:

More information

THE RELATIONSHIP BETWEEN ABORIGINAL ENGAGEMENT AND SUSTAINABLE DEVELOPMENT

THE RELATIONSHIP BETWEEN ABORIGINAL ENGAGEMENT AND SUSTAINABLE DEVELOPMENT THE RELATIONSHIP BETWEEN ABORIGINAL ENGAGEMENT AND SUSTAINABLE DEVELOPMENT Recent Developments in the Duty to Consult Mary Hatherly Alderon Aboriginal Relations Manager Newleef 2014 INTRODUCTION 10 years

More information

PROJECT AGREEMENT FOR THE HOWSE PROPERTY IRON MINE IN NEWFOUNDLAND AND LABRADOR

PROJECT AGREEMENT FOR THE HOWSE PROPERTY IRON MINE IN NEWFOUNDLAND AND LABRADOR PREAMBLE PROJECT AGREEMENT FOR THE HOWSE PROPERTY IRON MINE IN NEWFOUNDLAND AND LABRADOR The Canadian Environmental Assessment Agency (CEA Agency) has commenced an environmental assessment (EA) pursuant

More information

Submission on Bill C-19. Canadian Environmental Assessment Act Amendments NATIONAL ENVIRONMENTAL LAW SECTION CANADIAN BAR ASSOCIATION

Submission on Bill C-19. Canadian Environmental Assessment Act Amendments NATIONAL ENVIRONMENTAL LAW SECTION CANADIAN BAR ASSOCIATION Submission on Bill C-19 Canadian Environmental Assessment Act Amendments NATIONAL ENVIRONMENTAL LAW SECTION CANADIAN BAR ASSOCIATION April 2002 TABLE OF CONTENTS Submission on Bill C-19 Canadian Environmental

More information

Environmental Review Process. Presented by Environment and Natural Resource Unit, Lands and Economic Development, BC Region

Environmental Review Process. Presented by Environment and Natural Resource Unit, Lands and Economic Development, BC Region Environmental Review Process Presented by Environment and Natural Resource Unit, Lands and Economic Development, BC Region Outline 1. Overview of the Canadian Environmental Assessment Act (CEAA) 2. Indigenous

More information

Report for the Environmental Planning and Assessment Caucus, Canadian Environmental Network

Report for the Environmental Planning and Assessment Caucus, Canadian Environmental Network Inter-jurisdictional Coordination of EA: Challenges and opportunities arising from differences among provincial and territorial assessment requirements and processes Report for the Environmental Planning

More information

Operational Policy Statement

Operational Policy Statement Operational Policy Statement Determining Whether a Designated Project is Likely to Cause Significant Adverse Environmental Effects under the Canadian Environmental Assessment Act, 2012 November 2015 i

More information

PROJECT AGREEMENT FOR THE BURNCO AGGREGATE MINE IN BRITISH COLUMBIA

PROJECT AGREEMENT FOR THE BURNCO AGGREGATE MINE IN BRITISH COLUMBIA PROJECT AGREEMENT FOR THE BURNCO AGGREGATE MINE IN BRITISH COLUMBIA PREAMBLE WHEREAS the Government of Canada is committed to improving the efficiency of federal environmental assessment (EA) and regulatory

More information

Licensing and Environmental Assessments of New NPP s

Licensing and Environmental Assessments of New NPP s Licensing and Environmental Assessments of New NPP s PEO/CNS Symposium: Discussing the Viability of a Nuclear Power Plant (NPP) in Renfrew County May 12, 2007 Maury Burton Department Manager, Regulatory

More information

Saskatchewan Mining Association (SMA) 2018 Pre-Budget Submission Tuesday, October 3, 2018

Saskatchewan Mining Association (SMA) 2018 Pre-Budget Submission Tuesday, October 3, 2018 ` Saskatchewan Mining Association (SMA) 2018 Pre-Budget Submission Tuesday, October 3, 2018 Chair, members of the committee, clerk and fellow witnesses: My name is Pam Schwann and I am the President of

More information

PROJECT AGREEMENT FOR THE VICTOR DIAMOND MINE EXTENSION IN ONTARIO

PROJECT AGREEMENT FOR THE VICTOR DIAMOND MINE EXTENSION IN ONTARIO PROJECT AGREEMENT FOR THE VICTOR DIAMOND MINE EXTENSION IN ONTARIO PREAMBLE The Canadian Environmental Assessment Agency (CEA Agency) has commenced an environmental assessment (EA) pursuant to the Canadian

More information

READING GUIDE. Purpose of the Document

READING GUIDE. Purpose of the Document READING GUIDE This Reading Guide has been developed to provide additional context to support your review of the attached document titled Summary of Potential Content for Updated Guidelines for Ontario

More information

There is also some shared jurisdiction on environment issues where there is no clear demarcation.

There is also some shared jurisdiction on environment issues where there is no clear demarcation. The Canadian Energy Landscape Electricity Planning Comments delivered by Ric Cameron, NERC Canadian Affairs Representative at the Planning Committee meeting, Toronto, Ontario June 7, 2011; these comments

More information

Hydrology and Watershed Management

Hydrology and Watershed Management Hydrology and Watershed Management The summaries and their associated interpretations contained in this document are for general information only, not legal advice. To interpret or apply the law, you must

More information

TOWERBIRCH EXPANSION PROJECT

TOWERBIRCH EXPANSION PROJECT TOWERBIRCH EXPANSION PROJECT FEDERAL/PROVINCIAL CONSULTATION AND ACCOMMODATION REPORT Proposed by: NOVA Gas Transmission Ltd. Prepared by: Major Projects Management Office British Columbia Environmental

More information

Recommendations relating to the Canadian Environmental Assessment Act 2012

Recommendations relating to the Canadian Environmental Assessment Act 2012 Review of federal environmental assessment processes: Recommendations relating to the Canadian Environmental Assessment Act 2012 Presented by the James Bay Advisory Committee on the Environment to the

More information

Ontario Power Generation Questions and Answers

Ontario Power Generation Questions and Answers Ontario Power Generation Questions and Answers Natural Disasters Could a similar earthquake or tsunami happen in Ontario? No. Ontario s reactors are at two sites on Lake Ontario and one site on Lake Huron

More information

TRANSPORTATION AND ENVIRONMENTAL SERVICES Rapid Transit Initiative

TRANSPORTATION AND ENVIRONMENTAL SERVICES Rapid Transit Initiative REGION OF WATERLOO TRANSPORTATION AND ENVIRONMENTAL SERVICES Rapid Transit Initiative TO: Chair Jim Wideman and Members of the Planning and Works Committee DATE: FILE CODE: D10-20/RT SUBJECT: PROPOSED

More information

NORTH SLAVE MÉTIS ALLIANCE

NORTH SLAVE MÉTIS ALLIANCE NORTH SLAVE MÉTIS ALLIANCE PO Box 2301 Yellowknife, NT X1A 2P7 CLOSING STATEMENT: GIANT MINE REMEDIATION PROJECT (EA0809-001) Submitted by the North Slave Métis Alliance To the Mackenzie Valley Environmental

More information

...,... \ u1" . tj.. ' ~i... . '\,,.., \ \ ~~\ i I '. ~-' ' '' f l 4',... 'lfll 6 \l ;, 0 ") \ LUI '"

...,... \ u1 . tj.. ' ~i... . '\,,.., \ \ ~~\ i I '. ~-' ' '' f l 4',... 'lfll 6 \l ;, 0 ) \ LUI ' March 29, 2016 N K37 -CO R R-00531-02537....,.... \ u1". tj.. ' ~i... ~~\ i I '. ~-' ' '' f l 4',..... 'lfll 6 \l ;, 0 ") \ LUI '". '\,,.., \ \. 1'l ' L "?9 CNSC ~ Bruce Power CCSN II 111 11111111111111111111

More information

CANADIAN NUCLEAR SAFETY COMMISSION

CANADIAN NUCLEAR SAFETY COMMISSION CANADIAN NUCLEAR SAFETY COMMISSION nuclearsafety.gc.ca Marc Leblanc Commission Secretary e-doc 5531125 Presentation to l Union des municipalités du Québec May 16, 2018 Gatineau, QC The Canadian Nuclear

More information

Environmental Assessment, Reclamation and Exploration

Environmental Assessment, Reclamation and Exploration Environmental Assessment, Reclamation and Exploration The summaries and their associated interpretations contained in this document are for general information only, not legal advice. To interpret or apply

More information

PROJECT AGREEMENT FOR THE TRANS MOUNTAIN PIPELINE EXPANSION PROJECT IN ALBERTA AND BRITISH COLUMBIA

PROJECT AGREEMENT FOR THE TRANS MOUNTAIN PIPELINE EXPANSION PROJECT IN ALBERTA AND BRITISH COLUMBIA PROJECT AGREEMENT FOR THE TRANS MOUNTAIN PIPELINE EXPANSION PROJECT IN ALBERTA AND BRITISH COLUMBIA PREAMBLE The National Energy Board (NEB) has commenced a review pursuant to the Canadian Environmental

More information

Access to Information

Access to Information Access to Information Ottawa, 7 January 2016 The Honourable Scott Brison Treasury Board of Canada Secretariat President's Office 90 Elgin Street Ottawa, Ontario K1A 0R5 Dear Mr. Brison, The Canadian Historical

More information

RECENT DEVELOPMENTS IN NUCLEAR WASTE MANAGEMENT IN CANADA

RECENT DEVELOPMENTS IN NUCLEAR WASTE MANAGEMENT IN CANADA RECENT DEVELOPMENTS IN NUCLEAR WASTE MANAGEMENT IN CANADA Frank King Manager, Long-term Waste Management Technology Nuclear Waste Management Division Ontario Hydro, Canada ABSTRACT This paper provides

More information

Environmental Assessment Office SERVICE PLAN 2004/ /07

Environmental Assessment Office SERVICE PLAN 2004/ /07 Environmental Assessment Office SERVICE PLAN 2004/05 2006/07 National Library of Canada Cataloguing in Publication Data British Columbia.. Service Plan. 2002/2003/2004/2005/2006/2007 Annual. Also available

More information

POLICY PAPER #4. TO: UBCM Members. FROM: UBCM Executive. DATE: September 5, 2007

POLICY PAPER #4. TO: UBCM Members. FROM: UBCM Executive. DATE: September 5, 2007 TO: UBCM Members FROM: UBCM Executive DATE: September 5, 2007 POLICY PAPER #4 RE: LOCAL GOVERNMENTS AND THE TRADE, INVESTMENT AND LABOUR MOBILITY AGREEMENT (TILMA) 2007 CONVENTION 1. Introduction The purpose

More information

An Overview of Canada s Environmental Assessment Regime

An Overview of Canada s Environmental Assessment Regime Volume 7, Issue 5, December 2015 An Overview of Canada s Environmental Assessment Regime As the Liberal government takes up the reins in Ottawa, it has signalled a shift in its approach to energy, environment

More information

Fisheries Protection Program: an overview. WaterTech 2016, April 6-8, 2016, Banff

Fisheries Protection Program: an overview. WaterTech 2016, April 6-8, 2016, Banff Fisheries Protection Program: an overview WaterTech 2016, April 6-8, 2016, Banff 1 Amendments to the Fisheries Act All amendments have been in effect as of November 25, 2013 Focus the Act s regulatory

More information

available in multiple formats Environmental Self-Assessment Handbook for Rail Infrastructure Projects

available in multiple formats Environmental Self-Assessment Handbook for Rail Infrastructure Projects available in multiple formats Environmental Self-Assessment Handbook for Rail Infrastructure Projects This document and other Canadian Transportation Agency publications are available on our Web site at

More information

National Centre for First Nations Governance CONSULTATION FACT SHEET 2

National Centre for First Nations Governance CONSULTATION FACT SHEET 2 National Centre for First Nations Governance CONSULTATION FACT SHEET 2 CONSULTATION PROCEDURES/STEPS DEFINITION: Consultation procedures refer to the series of steps that need to be taken to accomplish

More information

Federal Requirements for Waterpower Development Environmental Assessment Processes in Ontario - PRACTITIONER S GUIDE -

Federal Requirements for Waterpower Development Environmental Assessment Processes in Ontario - PRACTITIONER S GUIDE - Federal Requirements for Waterpower Development Environmental Assessment Processes in Ontario - PRACTITIONER S GUIDE - Version 2.0 2010 MacKay Generating Station on the MontrealRiver. Photo Courtesy of

More information

Department of Environment and Conservation. NEIA newleef 2013 October 10, 2013

Department of Environment and Conservation. NEIA newleef 2013 October 10, 2013 Department of Environment and Conservation NEIA newleef 2013 October 10, 2013 1 The Environmental Assessment Process in Newfoundland & Labrador 2 Overview Purpose of EA in Newfoundland & Labrador EA Goals

More information

February 24, Re: Bill 135, Energy Statute Law Amendment Act, 2015 Standing Committee on General Government. A. Overview

February 24, Re: Bill 135, Energy Statute Law Amendment Act, 2015 Standing Committee on General Government. A. Overview February 24, 2016 Re: Bill 135, Energy Statute Law Amendment Act, 2015 Standing Committee on General Government A. Overview Thank you for the opportunity to provide these comments on Bill 135, Energy Statute

More information

Legal Backgrounder Bill 2: Responsible Energy Development Act

Legal Backgrounder Bill 2: Responsible Energy Development Act Legal Backgrounder Bill 2: Responsible Energy Development Act Overview Bill 2, the Responsible Energy Development Act (REDA), is scheduled to come into force in June 2013. REDA proposes significant changes

More information

ONE WINDOW COORDINATION PROCESS for Mineral Development Projects in Ontario

ONE WINDOW COORDINATION PROCESS for Mineral Development Projects in Ontario ONE WINDOW COORDINATION PROCESS for Mineral Development Projects in Ontario Page 1 of 30 Table of Contents 1. INTRODUCTION AND PURPOSE... 3 Introduction... 3 Interpretation... 3 Definitions... 4 Objectives...

More information

Frequently Asked Questions About OPG s Deep Geologic Repository for Low and Intermediate-level Nuclear Waste

Frequently Asked Questions About OPG s Deep Geologic Repository for Low and Intermediate-level Nuclear Waste NEED FOR A DGR Frequently Asked Questions About OPG s Deep Geologic Repository for Low and Intermediate-level Nuclear Waste Q. Where is the low and intermediate level waste managed now? A. Low and intermediate

More information

Consultation Protocol of the Mikisew Cree First Nation

Consultation Protocol of the Mikisew Cree First Nation November 24, 2009 In our every deliberation we must consider the impact of our decisions on the next seven generations - author unknown Consultation Protocol of the Mikisew Cree First Nation ( the Protocol

More information

CCME. Canadian Council of Ministers of the Environment. Le Conseil canadien des ministres de l environnement

CCME. Canadian Council of Ministers of the Environment. Le Conseil canadien des ministres de l environnement Canadian Council of Ministers of the Environment CCME Le Conseil canadien des ministres de l environnement A CANADA-WIDE ACCORD ON ENVIRONMENTAL HARMONIZATION VISION Governments working in partnership

More information

Commonwealth Lands and Activities of the Commonwealth and Commonwealth Agencies

Commonwealth Lands and Activities of the Commonwealth and Commonwealth Agencies Commonwealth Lands and Activities of the Commonwealth and Commonwealth Agencies 1. INTRODUCTION The Commonwealth Environment Protection and Biodiversity Conservation Act 1999 (the EPBC Act ) came into

More information

PROJECT AGREEMENT FOR THE MAGINO GOLD MINE IN ONTARIO

PROJECT AGREEMENT FOR THE MAGINO GOLD MINE IN ONTARIO PROJECT AGREEMENT FOR THE MAGINO GOLD MINE IN ONTARIO PREAMBLE The Canadian Environmental Assessment ( ) has commenced an environmental assessment (EA) pursuant to the Canadian Environmental Assessment

More information

PROPOSED TERMS OF REFERENCE OF EXPERT PANEL REVIEW OF CANADIAN ENVIRONMENTAL ASSESSMENT ACT, 2012

PROPOSED TERMS OF REFERENCE OF EXPERT PANEL REVIEW OF CANADIAN ENVIRONMENTAL ASSESSMENT ACT, 2012 July 19, 2016 BY EMAIL Review of Environmental Assessment Processes Canadian Environmental Assessment Agency 160 Elgin Street, 22 nd Floor Ottawa, Ontario K1A 0H3 RE: PROPOSED TERMS OF REFERENCE OF EXPERT

More information

Model for Harmonized Provincial Environmental and Sustainability Assessment

Model for Harmonized Provincial Environmental and Sustainability Assessment Model for Harmonized Provincial Environmental and Sustainability Assessment Prepared By Brenda Heelan Powell Staff Counsel Environmental Law Centre (Alberta) Library and Archives Canada Cataloguing in

More information

Outline of the presentation

Outline of the presentation Socio-economic considerations in environmental decision-making in India Asha Rajvanshi ar@wii.gov.in Head, EIA Cell Wildlife Institute of India, Dehradun Outline of the presentation Historical perspective

More information

CEF. Cumulative Effects Framework. Interim Policy. for the Natural Resource Sector. October Cumulative Effects Framework

CEF. Cumulative Effects Framework. Interim Policy. for the Natural Resource Sector. October Cumulative Effects Framework CEF Cumulative Effects Framework Cumulative Effects Framework Interim Policy for the Natural Resource Sector October 2016 Policy Approval The Cumulative Effects Framework Interim Policy is approved for

More information

By Fax: (416) and

By Fax: (416) and Rodney Northey Direct 416-369-6666 rodney.northey@gowlings.com File No. T1001328 By Fax: (416) 952-1573 and Email: CEAA.LogisticsHub-PoleLogistique.ACEE@ceaa-acee.gc.ca Canadian Environmental Assessment

More information

PROJECT AGREEMENT FOR THE SHELBURNE BASIN VENTURE EXPLORATION DRILLING PROJECT IN NOVA SCOTIA

PROJECT AGREEMENT FOR THE SHELBURNE BASIN VENTURE EXPLORATION DRILLING PROJECT IN NOVA SCOTIA PROJECT AGREEMENT FOR THE SHELBURNE BASIN VENTURE EXPLORATION DRILLING PROJECT IN NOVA SCOTIA PREAMBLE The Canadian Environmental Assessment ( ) has commenced an environmental assessment (EA) pursuant

More information

Nuisance Claims May Now Be Easier to Prove St. Lawrence Cement Inc. v. Barrette, 2008 SCC 64

Nuisance Claims May Now Be Easier to Prove St. Lawrence Cement Inc. v. Barrette, 2008 SCC 64 Environmental Law Centre News Brief Vol. 23 No. 4, 2008 Page 1 Vol. 23 No. 4, 2008 Page 1 ISSN 1712-6843 Nuisance Claims May Now Be Easier to Prove St. Lawrence Cement Inc. v. Barrette, 2008 SCC 64 By

More information

March Protected area boundary adjustments fall within one of three categories:

March Protected area boundary adjustments fall within one of three categories: PROVINCIAL PROTECTED AREA BOUNDARY ADJUSTMENT POLICY, PROCESS AND GUIDELINES March 2010 1. BACKGROUND: Provincial protected areas 1 are set aside to provide a wide range of opportunities that support tourism

More information

Environmental Regulation & Mine Permitting in Ontario

Environmental Regulation & Mine Permitting in Ontario Environmental Regulation & Mine Permitting in Ontario A Presentation to the Ad Hoc Committee on Mining Lake Superior Work Group Mark O Brien, Mineral Development Consultant MNDMF, Thunder Bay Agenda Regulatory

More information

5 MAY, 2017 PREPARED BY: CANADIAN ENERGY PIPELINE ASSOCIATION

5 MAY, 2017 PREPARED BY: CANADIAN ENERGY PIPELINE ASSOCIATION Response to the Expert Panel Review of Environmental Assessment Processes Final Report, Building Common Ground: A new Vision for Impact Assessment in Canada 5 MAY, 2017 PREPARED BY: CANADIAN ENERGY PIPELINE

More information

Province - Department of Municipal and Provincial Affairs Nunatsiavut Government. Activities Responsibility Timing

Province - Department of Municipal and Provincial Affairs Nunatsiavut Government. Activities Responsibility Timing SUBJECT: Consultation on land use laws Activity Sheet: 10-1 OBLIGATION: PARTIES: Consult on land use policy or development regulation in Labrador Inuit Settlement Area (LISA) outside Labrador Inuit Lands

More information

GNWT BOARD FORUM PRESENTATION NOVEMBER 27/28, 2013

GNWT BOARD FORUM PRESENTATION NOVEMBER 27/28, 2013 1 GNWT BOARD FORUM PRESENTATION NOVEMBER 27/28, 2013 Introductions and Overview Shaleen Woodward, Assistant Deputy Minister, Devolution Implementation Planning Martin Goldney, Deputy Minister, Department

More information

Environmental Assessment Law for a Healthy, Secure and Sustainable Canada A Checklist for Strong Environmental Laws February 2012

Environmental Assessment Law for a Healthy, Secure and Sustainable Canada A Checklist for Strong Environmental Laws February 2012 Environmental Assessment Law for a Healthy, Secure and Sustainable Canada A Checklist for Strong Environmental Laws February 2012 Canadians want strong environmental laws, and they deserve an environmental

More information

DFO - Fisheries Protection Program and Environmental Consultants Workshop. Holiday Inn St. John s NL March 16, 2016

DFO - Fisheries Protection Program and Environmental Consultants Workshop. Holiday Inn St. John s NL March 16, 2016 DFO - Fisheries Protection Program and Environmental Consultants Workshop Holiday Inn St. John s NL March 16, 2016 Overview Overview Fisheries Act and Fisheries Protection Program Review of Proposed Work

More information