ITER Research Needs. Report by David Campbell Plasma Operation Directorate

Size: px
Start display at page:

Download "ITER Research Needs. Report by David Campbell Plasma Operation Directorate"

Transcription

1 ITER Research Needs Report by David Campbell Plasma Operation Directorate Acknowledgements: Members of PO and CHD directorates, together with many experts in the international fusion community The views and opinions expressed herein do not necessarily reflect those of the ITER Organization. ITPA Coordinating Committee, Cadarache, 12 December 2011 ITER Page 1

2 Synopsis Current status of the ITER Research Plan development Implications of deferrals and recent design decisions Key elements of ITER s Physics R&D needs ITPA contributions to ITER activities Recent ITPA contributions to ITER design and physics basis Preparations for 24 th IAEA Fusion Energy Conference, October 2012 ITPA Coordinating Committee, Cadarache, 12 December 2011 ITER Page 2

3 ITER Research Plan - Status ITPA Coordinating Committee, Cadarache, 12 December 2011 ITER Page 3

4 Boundary Conditions I Phased assembly and commissioning of tokamak, as in the Baseline OPS/ Level-0 Reference Schedule IRP consistent with proposed OPS/ Level-0 Reference Schedule: First Plasma scheduled for late 2020 with minimal in-vessel components target DT operation by end-2027 H&CD systems: H&CD mix of ECRH (20 MW), ICRF (10 15 MW), NBI (33 MW, 870 kev H) installed after Assembly Phase II (P inj ~ 63 MW) 2 nd ICRF antenna and 2 nd HNB installed in pre-nuclear shutdown before deuterium operations phase Diagnostic systems: Construction Phase procurement will focus primarily on in-vessel components principal diagnostic systems required for essential elements of plasma control and protection available (equilibrium control, density control, power exhaust monitoring, DMS etc) this element still under review ITPA Coordinating Committee, Cadarache, 12 December 2011 ITER Page 4

5 Boundary Conditions II Divertor configuration: all-tungsten divertor from First Plasma Central Solenoid: CS3L module to be fabricated from existing CSJA2 conductor, while improved conductor meeting ITER performance requirements developed Tritium Plant: installation and commissioning plan for Tritium Plant follows basic logic developed for Baseline Schedule initial 50:50 DT operation possible in late 2027, with full throughput gradually increasing through subsequent 6-12 operational months Operations scheduling based essentially on RAMI analysis: 2-shift operation during first H/ He campaign 3-shift operation possible for remainder of experimental programme TBM testing programme is constrained by needs of experimental programme towards DT operation ITPA Coordinating Committee, Cadarache, 12 December 2011 ITER Page 5

6 Summary of Operational Implications H&CD capability: reduced headroom for achieving H-mode in non-active phase, but current estimates indicate helium H-mode access remains viable at half-current and field foreseen H-mode and ELM-control testing programme remains possible, subject to results of ongoing physics R&D Diagnostics: Diagnostic installation programme is being adapted to ensure required measurement capability is available as required by experimental programme Central Solenoid: recent calculations indicate that new scenarios can be developed to mitigate possible performance limitations of CS3L module Tungsten divertor: use of tungsten divertor from start of non-active phase will necessitate adaptation of plasma scenarios adequate mitigation measures against transient heat loads will be required ITPA Coordinating Committee, Cadarache, 12 December 2011 ITER Page 6

7 ITER H-mode Power Threshold The latest H-mode threshold power scaling for deuterium plasmas: P thresh = 0.05n 0.72 e B 0.8 T S 0.94 (Y Martin, HMW-2008) The isotope dependence based on JET results in H, D, and DT indicates that P thresh 1/A for hydrogen isotopes Possible helium H-mode access half-field/ half current H-mode development Q=10 Full-field/ full current H-mode development H-mode access path in DT needs 40MW No H-mode access in D for full Q=10 simulation No H-mode access in H at full field Note: margins may be required for (i) core radiation and (ii) access to good confinement (H 98 = 1) ITPA Coordinating Committee, Cadarache, 12 December 2011 ITER Page 7

8 ITER H-mode Threshold - Implications Hydrogen/ Helium Operations: it has long been recognized that achievement of H-mode in hydrogen is at best marginal, requiring essentially full (100%) H&CD power routinely IRP plans call for initial studies of H-modes and ELM control in helium plasmas: ~ 50 MW required for reliable H-mode access at 7.5 MA/ 2.65 T Deuterium Operations: at least 30 MW required for H-mode access at 7.5 MA/ 2.65 T P inj ~ 63 MW might provide just enough headroom for H-mode access at full current and field, but at reduced density Deuterium-Tritium Operations: P inj ~ 50 MW required for access to H-mode at 15 MA/ 5.3 T, but alpha heating power ensures H-mode operation at Q=10 operating point ITPA Coordinating Committee, Cadarache, 12 December 2011 ITER Page 8

9 H&CD Operation Range H&CD access with NB shinethrough protection armour provides considerable flexibility in selecting appropriate operation strategy ITPA Coordinating Committee, Cadarache, 12 December 2011 ITER Page 9

10 ITER Experimental Programme Complete Tokamak Core First Plasma Hydrogen/ Helium Phase Complete Deuterium Phase Complete Plasma Restart Start Torus PumpDown First Plasma Assembly Phase II Plasma Development, H&CD Commissioning, Diagnostics, Control, DMS Commissioning Short Shutdown 15 MA and Disruption Forces, H&CD Commissioning, He H-modes, ELM Mitigation Pre-Nuclear Shutdown Full Heating capability T-Plant Commissioning Hydrogen Commissioning Tritium Introduction ~10% T-throughput D Plasmas, D H-modes D H-mode Studies Trace-T Studies Q=10 Long Pulse Short Pulse Q=10 DT Hybrid DT Non-inductive Scheduled Shutdowns ITPA Coordinating Committee, Cadarache, 12 December 2011 ITER Page 10

11 Operations: 1. Non-Active Phase Hydrogen/ helium operation consists of months of plasma operation over 2 campaigns two-shift operation assumed in Campaign 1 and three-shift operation in Campaign (360) (360) ITPA Coordinating Committee, Cadarache, 12 December 2011 ITER Page 11

12 Non-Active Phase - Deferral Implications Operational Schedule: detailed analysis of effective operational time indicates that it is within 10% of original operational schedule: scheduling of shutdowns and installation; partial utilization of 3 rd shift due to technical constraints etc Experimental Programme: both hydrogen and helium plasmas will be required for efficient commissioning of auxiliary systems (particularly H&CD) all-tungsten divertor may require more cautious experimental approach than originally foreseen to avoid melting, particularly at transients Some planned activities might not be accomplished during this phase, but this may compensate loss of operational time and slower start-up with tungsten divertor: full-power testing of divertor long-pulse commissioning of all H&CD systems - partial loss ITPA Coordinating Committee, Cadarache, 12 December 2011 ITER Page 12

13 Operations: 2. Deuterium Phase Focus is on inductive ELMy H-mode scenario to allow rapid transition to DT operation: new systems commissioned initially with H/ He plasmas Nuclear readiness demonstration for tokamak and auxiliary systems performed Tritium Plant commissioned with tritium in parallel with pre-nuclear shutdown and plasma operation trace tritium experiments precede transition to full DT operation (1100) (880) 5170 ITPA Coordinating Committee, Cadarache, 12 December 2011 ITER Page 13

14 Deuterium Phase - Deferral Implications Operational Schedule: proposed schedule foresees similar operational time in deuterium as previous IRP Experimental Programme: Major additional activity to be incorporated relative to original IRP is the commissioning of the 2 nd ICRF antenna Use of tungsten divertor in non-active phase means commissioning time for tungsten divertor originally foreseen would be saved to maintain early transition to DT operation, emphasis must be given to short pulse operational scenarios ITPA Coordinating Committee, Cadarache, 12 December 2011 ITER Page 14

15 Operations: 3. Deuterium-Tritium Phase 1 Initial DT phase focusses on achievement of Q = 10 scenario at up to 500MW for at least several 10s of seconds emphasis in initial campaign on development of necessary control techniques to allow quasi-stationary production of several 100MW of fusion power at Q~ Achievement of long pulse (several 100s) Q=10 milestone would be pursued in the subsequent DT experimental campaign allocation of time also to development of hybrid and non-inductive scenarios demonstration of Q=5, 3000s likely to require several years of experiments ITPA Coordinating Committee, Cadarache, 12 December 2011 ITER Page 15

16 ITER Research Plan - Summary An initial analysis has been performed of the possible ITER Research Plan towards early DT operation based on planning endorsed by IC-9: no showstoppers have been identified to achieving proposed experimental programme towards short-pulse Q=10 operation in 2028, though there are increased risks to achievement of programme goals on proposed timescale major impact of deferral proposal is associated with (i) reduced H&CD power (63 MW) in non-active phase and (ii) use of tungsten divertor in nonactive phase proposed deferral of diagnostic systems is still to be analyzed in detail to ensure required capabilities are available at required time proposed installation of all-tungsten divertor may necessitate more cautious approach to development of operational scenarios redeveloped plasma scenarios indicate that possible limitations in CS3L module have limited impact on satisfying ITER mission goals any limitations in operational time can be compensated to some extent by deferring elements of long-pulse scenario development until achievement of short pulse (several 10s of seconds) Q=10 ITPA Coordinating Committee, Cadarache, 12 December 2011 ITER Page 16

17 Key elements of ITER s Physics R&D Needs ITPA Coordinating Committee, Cadarache, 12 December 2011 ITER Page 17

18 Key ITER Physics R&D Needs I Key issues for ITER Physics R&D remain: development of integrated operational scenarios with all metallic PFCs in particular, resolution of outstanding issues related to use of tungsten divertor fuel retention with all-metallic walls tritium removal techniques heat fluxes in limiter/ divertor configurations and under stationary/ transient conditions Disruptions/ VDEs: characterization and understanding of rotation of halo current asymmetries following disruptions/ VDEs processes determining current quench time extrapolation to ITER improved quantitative analysis of disruption heat loads improved physics basis for choice of disruption/re mitigation techniques improved understanding of processes influencing confinement and losses of REs improved physics basis for ELM control exploitation of extended RMP coil capabilities to improve specification of requirements for ELM control in ITER studies of potential alternative ELM control techniques ITPA Coordinating Committee, Cadarache, 12 December 2011 ITER Page 18

19 Key ITER Physics R&D Needs II Key issues for ITER Physics R&D remain: experimental validation of ITER plasma scenarios validation of revised current ramp-up scenarios on tungsten divertor development of hybrid/ steady-state scenarios implications for H&CD upgrades extended physics basis for helium H-mode operation understanding of 3-D ripple effects such as produced by TBMs, RMP coils improved diagnosis of hydrogenic retention and dust production Issues highlighted in red are discussed in more detail later in presentation ITPA Coordinating Committee, Cadarache, 12 December 2011 ITER Page 19

20 Divertor and PWI: R&D Needs I The project s decision to give priority to installation of a tungsten divertor from the start of the experimental programme gives added urgency to R&D in this area (IC-9 recommendation delays final implementation of the decision for up to 2 years) demonstration of robust integrated scenarios power load control in longpulse operation over range of scenarios by low-z seeding development of helium plasma scenarios (H-modes, ELM control) impurity generation and core contamination in ELM-controlled regimes effect of divertor target damage on device operability fuel retention with all-metallic walls role of material erosion and migration dust generation Further emphasis is required on model validation activities ITPA Coordinating Committee, Cadarache, 12 December 2011 ITER Page 20

21 Divertor and PWI: R&D Needs II Heat fluxes in limiter/ divertor configurations and under stationary/ transient conditions: development of quantitative description of λ q in limiter plasmas remains critical for first wall design is recent indication that 1/I p is good ordering parameter for λ q in H-mode confirmed? problematic for ITER? characterization of transient heat loads at controlled ELMs and at disruptions/vdes key for estimating PFC lifetime and dust production T. Eich Structured workprogramme of Divertor and SOL TG appears welladapted to addressing and resolving these issues ITPA Coordinating Committee, Cadarache, 12 December 2011 ITER Page 21

22 Stability: R&D Needs I Quantitative characterization of disruption/ VDE parameters and specification of adequate mitigation system for ITER remain critical issues: VDE horizontal forces - improved basis for prediction of ITER loads, including guideline on rotation of asymmetry determination of heat load characteristics at disruptions/ VDEs JET: halo current asymmetry rotates up to 4 revolutions with frequency 100Hz (T Hender) ITPA Coordinating Committee, Cadarache, 12 December 2011 ITER Page 22

23 Design and R&D activity on DMS/ RE mitigation hardware moving forward: Stability: R&D Needs II responsibility allocated to US DA timeschedule under review, but PA signature/ CDR likely in 2013 Key issues: need to finalize species, amount and number of locations (radiation asymmetries important) tests of concepts for RE mitigation most critical issue at present improved understanding of RE production, confinement and losses required Request for allocation of 4 upper port plugs (shown) for DMS and 2 horizontal port plugs for RE mitigation under study ITPA Coordinating Committee, Cadarache, 12 December 2011 ITER Page 23

24 Stability: R&D Needs III Additional high priority issues specification of criteria for tolerable level of low-n resonant and nonresonant error fields at low and high beta - guidance on use of correction coils and in-vessel coils to correct error fields assessment of capability of in-vessel coils to control RWMs in steady-state scenarios Critical issues are being addressed by MHD TG through a series of WGs designed to address ITER key issues on a rapid timescale ITPA Coordinating Committee, Cadarache, 12 December 2011 ITER Page 24

25 Pedestal/ Confinement R&D Needs I Developing effective ELM control and establishing basis for its application in ITER remains the critical issue in this area Recently there has been a rapid expansion of experimental capability in this area: demonstration of ELM suppression with RMPs in AUG, KSTAR improvement of pellet pacemaking experiments in AUG, DIII-D detailed cross-device studies of ELM suppression studies of alternative approaches to ELM suppression continue with some success (eg QH-mode) detailed analysis of issues such as field penetration and impact of RMP coils on heat load distribution are also important contributions ITPA Coordinating Committee, Cadarache, 12 December 2011 ITER Page 25

26 Pedestal/ Confinement R&D Needs II Key priorities in ELM control: coordinated work to improve understanding of ELM suppression with B edge perturbation: DIII-D, AUG, KSTAR, MAST, NSTX, JET revised physics basis for empirical criterion for ITER (n and I coil ) improved understanding of edge power and particle fluxes with ELM control expand ELM control by pellet pacing and determination of effects on confinement and fluxes to PFC during mitigated ELMs quantify requirements for ELM control with schemes which may be useful in lower I p phases of ITER plasma (vertical kicks, edge ECRH) compatibility of plasma fuelling with ELM mitigation/ suppression (particle transport + pellets) access and exit from H ~ 1 H-mode with ELM mitigation further exploration of new methods for ELM control (solid pellets?) analysis of ELMs and ELM control in helium plasmas ITPA Coordinating Committee, Cadarache, 12 December 2011 ITER Page 26

27 Pedestal/ Confinement R&D Needs III Access to H-mode and high confinement in ITER reference H, He, D and DT regimes: more extensive analysis of H-mode characteristics of helium plasmas (ELMs, ELM control) essential for operational planning access to H-mode in current ramp-up phase particularly important to scenario development assessment of additional factors affecting H-mode access (torque, X-point geometry) also necessary studies of plasma performance, ELM behaviour, ELM control in regimes with input power just above H-mode threshold these issues will have a significant impact on planning for ITER operation and development of scenarios for all phases of operation, but are particularly critical in planning for non-active phase of operation likely to affect upgrade plan for heating systems after construction is finished ITPA Coordinating Committee, Cadarache, 12 December 2011 ITER Page 27

28 Pedestal/ Confinement R&D Needs IV Improved physics basis for particle transport in SOL, pedestal and core (in hydrogenic and helium plasmas): a critical issue for establishing the viability of ITER operational scenarios need to develop an improved physics basis for predicting realistic fuelling requirements, core density, impurity content and fusion performance Development of physics basis for momentum transport: prediction of plasma rotation has several implications for confinement properties and mhd stability in ITER operational scenarios can determine tolerance to error fields, use of RMPs, impact of TF ripple particularly 3-D effects Influence of toroidal field ripple on plasma performance: specification of ferromagnetic inserts now complete understanding 3-D ripple effects remains an issue (is ripple or error field/ magnetic braking important?) potential impact on TBM design ITPA Coordinating Committee, Cadarache, 12 December 2011 ITER Page 28

29 Operational Scenarios: R&D Needs I In recent years there has been a significant R&D activity aimed at strengthening the physics basis for the redevelopment of the ITER 15MA baseline scenario There are several outstanding issues which would further improve the predictive capability for this scenario: validation of plasma initiation models validation of transport models for various phases of the scenario, particularly the ramp-up/ ramp-down/ transient phases - quantification of density behaviour is of particular importance characterization of plasma transport with significant electron heating and T e ~ T i re-definition of standard plasma disturbances, particularly L-H and H-L transition experimental simulation and model validation of ITER non-active scenarios ITPA Coordinating Committee, Cadarache, 12 December 2011 ITER Page 29

30 Operational Scenarios: R&D Needs II Recent qualification tests of CS conductor indicate that present samples may only achieve ITER lifetime requirements if Lorentz force (internal stress) is limited to ~70% of reference value To maintain ITER schedule, IC-9 has endorsed decision to proceed with manufacture of CS3L from this conductor while developing improved conductor for other CS modules 15 MA scenario has been reanalyzed with DINA code: - by re-optimizing initial magnetization, loss of flux limited to ~3 Wb - plasma heating during fast current ramp-up allows mission goals to be maintained ( s burn) - experimental validation of revised scenarios, particularly with tungsten divertor, necessary T, s burn Z eff Option 1 P aux : 5=>20MW P aux : 5MW T ramp-up, s DINA: burn duration vs current ramp-up time ITPA Coordinating Committee, Cadarache, 12 December 2011 ITER Page 30

31 Operational Scenarios: R&D Needs III An increased focus on validation of models of plasma control in ITER-relevant scenarios is essential for support of development of Plasma Control System ITER PCS will rely on multi-variable control with limited set of actuators - validated models of control functionality is required to provide an adequate basis for the design of the PCS novel functionality such as heat flux control, burn control etc needs to be addressed The fusion programme is devoting a significant fraction of its resources to the development of advanced scenarios - hybrid and steady-state A systematic approach to validation of simulation codes is required to improve physics basis for extrapolation of these scenarios to ITER, including access conditions optimization of H&CD mix and their use in plasma control is a key issue which will have a significant impact on choice of H&CD upgrades ITPA Coordinating Committee, Cadarache, 12 December 2011 ITER Page 31

32 Energetic Particles: R&D Needs There is a good basis for the calculation of EP losses in presence of TF ripple 3-D effects (eg TBMs, RMPs) need further analysis interaction between EP scattering due to MHD instabilities and TF ripple needs eventually to be addressed recent predictions of significant NBI fast ions in ITER in presence of RMP fields requires further study/ validation Validation of non-linear analysis of AEs to provide improved estimate of EP spatial redistribution and losses Simulation and validation of the generation, confinement and loss processes for (post-disruption) runaway electrons is essential: the potential impact of REs on PFCs in ITER justifies a significant allocation of resources to improve the physics basis for simulation of their behaviour in ITER ITPA Coordinating Committee, Cadarache, 12 December 2011 ITER Page 32

33 Diagnostic: R&D Needs I The Diagnostics TG has identified 6 high priority topics to support the development of ITER s measurement capability: 1. Development of methods of measuring the energy and distribution of alpha particles 2. Assess calibration strategy and calibration sources needed for neutron diagnostics (CLOSED) NEW: Review Measurement Requirements for Plasma Control 3. Determination of life-time of plasma-facing mirrors used in optical systems 4. Development of the measurement requirements for measurements of hot dust, and assessment of techniques for the measurement of hot dust (CLOSED) 5. Assessment of the impacts of wall reflections on diagnostics 6. Assessment of the measurement requirements for plasma initiation and identification of potential gaps in planned measurement techniques These issues reflect major needs supporting procurement activities ITPA Coordinating Committee, Cadarache, 12 December 2011 ITER Page 33

34 Diagnostic: R&D Needs II There are several additional R&D issues which would benefit from ITPA contributions: Gas puff modelling (affects many systems) Effect of gap changes on bolometry performance & bolometer R&D issues Lost alphas as soon as FW is frozen we will need to know localization of alpha losses in the new ITER FW geometry. MHD effects on lost alpha distribution on the FW (where, what energy and pitch angle range) S/N and performance dependence of proposed diagnostics on temperatures, neutron/gamma fluxes, etc. additional ideas on the diagnostic tools for lost alpha measurements Practical tests of erosion monitoring diagnostics for divertor components Interferometric (holographic or speckle interferometry) LIDAR type metrology ITPA Coordinating Committee, Cadarache, 12 December 2011 ITER Page 34

35 ITPA contributions to ITER activities ITPA Coordinating Committee, Cadarache, 12 December 2011 ITER Page 35

36 ITPA Contributions to ITER Design Basis The results of ITPA R&D activities have provided a substantial physics basis for the ITER design over the past decade formalized in Progress in ITER Physics Basis ITPA database activities have been fundamental to establishing guiding physics principles for the tokamak design (eg H-mode threshold, H-mode confinement) - Disruption database has provided crucial input to the ITER Load Specification and Preliminary Safety Report (RPrS - Licensing documentation) Supporting R&D implemented through ITPA made an important contribution to numerous aspects of physics analysis during ITER Design Review Plasma Performance Assessment Heat and Nuclear Load Specifications ITPA Coordinating Committee, Cadarache, 12 December 2011 ITER Page 36

37 ITPA Contributions to STAC Reports ITPA has been active in supporting IO s responses to Council s Charges to specific STAC Charges STAC-8: Plan for ELM Mitigation in ITER STAC-9: H-mode Physics and R&D for ITER STAC-9: Outstanding issues in transient and steady state heat loads to ITER plasma facing components STAC-10: Evaluation of ITER Baseline Scenarios STAC-10: Development of a Disruption Mitigation System for ITER The scope of the ITPA R&D activities has been essential to building a substantial physics case for ITER s approach to resolving key physics issues in these areas ITPA Coordinating Committee, Cadarache, 12 December 2011 ITER Page 37

38 Council Charge to STAC-12 IC-9 has issued a Charge to ITER STAC for the STAC-12 meeting in May 2012 which includes, inter alia, the following request: Assess whether the worldwide research program on carbon- and tungstendivertors, including tritium-retention and transient heat loads, is sufficient for making a timely decision on the ITER divertor, and suggest improvements in the program; The ITER Research Plan will also be revised to reflect in greater detail the implications of deferrals and design decisions: input from the ITPA on key aspects, such as operation with all-metal walls, disruption mitigation, ELM control, H-mode access and plasma scenarios would be invaluable A workprogramme is being drawn up to prepare reports in response to this Charge, with a deadline around end-april 2012: ITPA experts are welcome to contribute to the preparation of these reports ITPA Coordinating Committee, Cadarache, 12 December 2011 ITER Page 38

39 24 th IAEA Fusion Energy Conference 24 th IAEA Fusion Energy Conference will take place in San Diego in October 2012 As at previous conferences, the intention is to organize an ITER session integrating contributions from the IO, ITER DAs and ITPA - an ITER review committee will be established by IO and ITER DAs to review synopses and make recommendations for oral presentations ITPA TGs are welcome to submit papers to the ITER session - ITPA papers submitted to ITER session should be endorsed by TG Chair Formal announcement of conference deadlines is not yet available, but based on previous experience, the deadlines for the ITER system would be (approximately): submission of synopsis to ITER review committee: mid-february 2012 (following all necessary clearance) recommendation by review committee: early-march 2012 submission to conference website: start-april 2012 ITPA Coordinating Committee, Cadarache, 12 December 2011 ITER Page 39

Scientific Status of ITER

Scientific Status of ITER Scientific Status of ITER D J Campbell ITER Organization, Cadarache Acknowledgements: Many colleagues in the ITER IO, ITER Members and ITPA Page 1 Summary of Presentation What are the main changes resulting

More information

The ITER Research Plan

The ITER Research Plan The ITER Research Plan D.J. Campbell ITER Organization, Route de Vinon sur Verdon, 13115 St Paul lez Durance, France Acknowledgements: Many colleagues in the ITER Organization, ITPA and the international

More information

ITER R&D Needs, Challenges, and the Way Forward

ITER R&D Needs, Challenges, and the Way Forward ITER R&D Needs, Challenges, and the Way Forward Bernard Bigot Director General ITER Organization, Cadarache, France Fusion Power Co-ordinating Committee Mtg, IO Headquarters, 24 Jan 2018 1 Context of ITER

More information

EX/9-1 Progress in Preparing Scenarios for ITER Operation

EX/9-1 Progress in Preparing Scenarios for ITER Operation EX/9-1 Progress in Preparing Scenarios for ITER Operation George Sips (JET-EFDA, UK) G. Giruzzi, S. Ide, C. Kessel, T. Luce, J. Snipes, J. Stober For the IOS-TG of the ITPA FEC 2014, St Petersburg, Russia

More information

Plasma Scenarios and Control

Plasma Scenarios and Control Plasma Scenarios and Control R. J. Hawryluk Presented at the SECOND IAEA DEMO PROGRAMME WORKSHOP December 19, 2013 What is the Difference in the Scenario and Control Requirements Between ITER and DEMO?

More information

Critical Physics Issues for Tokamak Power Plants

Critical Physics Issues for Tokamak Power Plants Critical Physics Issues for Tokamak Power Plants D J Campbell 1, F De Marco 2, G Giruzzi 3, G T Hoang 3, L D Horton 4, G Janeschitz 5, J Johner 3, K Lackner 4, D C McDonald 6, D Maisonnier 1, G Pereverzev

More information

Perspectives on Burning Plasma Research

Perspectives on Burning Plasma Research Perspectives on Burning Plasma Research Charles M. Greenfield, Director Amanda E. Hubbard, Deputy Director US Burning Plasma Organization National Academies Burning Plasma Committee June 5, 2017 This work

More information

ITER Research Needs and Possible DIII-D Contributions

ITER Research Needs and Possible DIII-D Contributions ITER Research Needs and Possible DIII-D Contributions Alberto Loarte Plasma Operation Directorate Acknowledgements: Members of POP and CHD directorates, together with many experts in the international

More information

ITER contributions to closing DEMO physics gaps

ITER contributions to closing DEMO physics gaps ITER contributions to closing DEMO physics gaps SD Pinches, DJ Campbell, Y Gribov, GTA Huijsmans, S-H Kim, M Lehnen, A Loarte, JA Snipes, G de Temmerman Science & Operations Department, ITER Organization

More information

Competed ITER Task Agreements (ITAs, for information and expression of interest)

Competed ITER Task Agreements (ITAs, for information and expression of interest) Competed ITER Task Agreements (ITAs, for information and expression of interest) ONGOING CALLS Ref F4E-CITA-002: "Evaluation of edge MHD stability and uncontrolled ELM energy losses for ITER H-mode plasmas

More information

A Pilot Plant as the Next Step toward an MFE Demo, )

A Pilot Plant as the Next Step toward an MFE Demo, ) A Pilot Plant as the Next Step toward an MFE Demo, ) George H. NEILSON, David A. GATES, Charles E. KESSEL, Jonathan E. MENARD, Stewart C. PRAGER, Steven D. SCOTT, James R. WILSON and Michael C. ZARNSTORFF

More information

Overview of future Plasma Wall Interaction (PWI) work

Overview of future Plasma Wall Interaction (PWI) work 1 Overview of future Plasma Wall Interaction (PWI) work J. Likonen VTT,, Finland Contributions from: M. Groth (Aalto), A. Hakola (VTT), K. Nordlund (UH) The Annual Finnish Fusion Seminar Annual Fusion

More information

Magnetic Confinement Fusion: Progress and Recent Developments

Magnetic Confinement Fusion: Progress and Recent Developments Magnetic Confinement Fusion: Progress and Recent Developments Howard Wilson, Dept Physics, University of York, Heslington, York YO10 5DD With thanks to A Field, K Gibson and A Kirk howard.wilson@york.ac.uk

More information

THE UNITED STATES MUST MAINTAIN A WORLD-CLASS DOMESTIC TOKAMAK PROGRAM TO SUPPORT BURNING PLASMA SCIENCE DEVELOPMENT

THE UNITED STATES MUST MAINTAIN A WORLD-CLASS DOMESTIC TOKAMAK PROGRAM TO SUPPORT BURNING PLASMA SCIENCE DEVELOPMENT THE UNITED STATES MUST MAINTAIN A WORLD-CLASS DOMESTIC TOKAMAK PROGRAM TO SUPPORT BURNING PLASMA SCIENCE DEVELOPMENT C.M. Greenfield, 1, 2 D.N. Hill, 1 M.R. Wade 1 1 General Atomics, General Atomics, San

More information

GA A26763 CONFINEMENT AND PEDESTAL CHARACTERISTICS IN H-MODE WITH ECH HEATING

GA A26763 CONFINEMENT AND PEDESTAL CHARACTERISTICS IN H-MODE WITH ECH HEATING GA A26763 CONFINEMENT AND PEDESTAL CHARACTERISTICS by R. PRATER, J.S. degrassie, P. GOHIL, T.H. OSBORNE, E.J. DOYLE, and L. ZENG MAY 2010 DISCLAIMER This report was prepared as an account of work sponsored

More information

Disruptions in ITER: Major Catastrophe or Minor Annoyance? Sarah Angelini April 21, 2011

Disruptions in ITER: Major Catastrophe or Minor Annoyance? Sarah Angelini April 21, 2011 Disruptions in ITER: Major Catastrophe or Minor Annoyance? Sarah Angelini April 21, 2011 Disruptions Types of Disruptions Time Scales from the IDDB Thermal Quench Current Quench DINA Simulation Results

More information

Non-linear MHD modelling of pellet injection for ELM control in ITER. Technical Specifications

Non-linear MHD modelling of pellet injection for ELM control in ITER. Technical Specifications Non-linear MHD modelling of pellet injection for ELM control in ITER Technical Specifications Table of Contents 1 PURPOSE 3 2 SCOPE 3 3 DEFINITIONS 5 4 REFERENCES 5 5 ESTIMATED DURATION 5 6 WORK DESCRIPTION

More information

Fusion Nuclear Science Facility (FNSF) low Q mission range & prerequisites options in associated research program for discussion and feedback

Fusion Nuclear Science Facility (FNSF) low Q mission range & prerequisites options in associated research program for discussion and feedback Fusion Nuclear Science Facility (FNSF) low Q mission range & prerequisites options in associated research program for discussion and feedback Normal Plasma Aspect Ratio Embodiment: Fusion Development Facility

More information

NOT EVERY HYBRID BECOMES A PRIUS: THE CASE AGAINST THE FUSION-FISSION HYBRID CONCEPT

NOT EVERY HYBRID BECOMES A PRIUS: THE CASE AGAINST THE FUSION-FISSION HYBRID CONCEPT NOT EVERY HYBRID BECOMES A PRIUS: THE CASE AGAINST THE FUSION-FISSION HYBRID CONCEPT IAP 2010 DON STEINER PROFESSOR EMERITUS,RPI JANUARY 22, 2010 IN 1997 TOYOTA INTRODUCED ITS HYBRID CAR CALLED THE PRIUS

More information

Magnetohydrodynamics (MHD) III

Magnetohydrodynamics (MHD) III Magnetohydrodynamics (MHD) III Yong-Su Na National Fusion Research Center POSTECH, Korea, 8-10 May, 2006 Review II 1. What is Stability? 2. MHD Instability Interchange Mode Flux Tube Instabilities 3. Formulation

More information

4 JET Studies. 4 JET Studies 4.1 INTRODUCTION

4 JET Studies. 4 JET Studies 4.1 INTRODUCTION 4.1 INTRODUCTION JET has been in shutdown for the whole of the year to install the ITER-Like Wall (ILW) and to complete the major neutral beam enhancement and a suite of diagnostic changes and improvements.

More information

Long term renovation inside KSTAR vacuum vessel toward steady state operation

Long term renovation inside KSTAR vacuum vessel toward steady state operation IAEA SSO Long term renovation inside KSTAR vacuum vessel toward steady state operation Jong-Gu Kwak, S.W. Jung, S.G. Kim, J.H. Kim, D.R. Lee K-DEMO On behalf of KSTAR team NFRI, Korea KSTAR ITER Near term(~2021)

More information

Key results and future directions of the JET fusion research programme

Key results and future directions of the JET fusion research programme Key results and future directions of the JET fusion research programme Karl Krieger on behalf of the JET contributors This work has been carried out within the framework of the EUROfusion Consortium and

More information

Strategic Approach 1 (SA-1): Use present physics and technology basis for DEMO.

Strategic Approach 1 (SA-1): Use present physics and technology basis for DEMO. Strategic Approach 1 (SA-1): Use present physics and technology basis for DEMO. Steve Zinkle, David Newman, Wayne Solomon, Francesca Turco, SA-1 co-chairs 1. Brief description of the strategic approach

More information

Disruption Science Issues and Opportunities for a Burning Plasma Science Experiment

Disruption Science Issues and Opportunities for a Burning Plasma Science Experiment Disruption Science Issues and Opportunities for a Burning Plasma Science Experiment Prepared and presented by: John Wesley General Atomics San Diego, California With recent disruption science results and

More information

Overview of ASDEX Upgrade results

Overview of ASDEX Upgrade results Overview of ASDEX Upgrade results Arne Kallenbach on behalf of the ASDEX Upgrade team and the EUROfusion MST1 team* Max-Planck-Institute for Plasma Physics D-85748 Garching *see appendix of H. Meyer et

More information

Technical Specification

Technical Specification IDM UID PVHYAE VERSION CREATED ON / VERSION / STATUS 03 Sep 2014 / 1.0 / Approved EXTERNAL REFERENCE Technical Specification Physics-based transport modelling of main species particle and energy transport

More information

Progress report for the MHD Physics Working Group (P3) Ted Strait and Chris Hegna July 12, 2002

Progress report for the MHD Physics Working Group (P3) Ted Strait and Chris Hegna July 12, 2002 Progress report for the MHD Physics Working Group (P3) Ted Strait and Chris Hegna July 12, 2002 Broad questions for the MHD working group What limitations will MHD instabilities impose on the ability of

More information

High-Radiation and High-Density Experiments in JT-60U

High-Radiation and High-Density Experiments in JT-60U High-Radiation and High-Density Experiments in JT-6U H. Kubo, S. Sakurai, N. Asakura, S. Konoshima, H. Tamai, S. Higashijima, A. Sakasai, H. Takenaga, K. Itami, K. Shimizu, T. Fujita, Y. Kamada, Y. Koide,

More information

Taming the Plasma Material Interface Workshop. Internal Components Panel

Taming the Plasma Material Interface Workshop. Internal Components Panel Taming the Plasma Material Interface Workshop Internal Components Panel Presented by Richard W. Callis UCLA Outline What is an Internal Component (IC) What-Who is the IC Panel What is it to do? How is

More information

PPP&T Power Exhaust Studies

PPP&T Power Exhaust Studies PPP&T Power Exhaust Studies Leena Aho-Mantila VTT Technical Research Centre of Finland Visiting researcher at the Max-Planck- Institut für Plasmaphysik (IPP), Garching, Germany Euratom-TEKES Annual Seminar

More information

Overview of EUROfusion PEX strategy, DTTs role and summary of assessment reports

Overview of EUROfusion PEX strategy, DTTs role and summary of assessment reports Overview of EUROfusion PEX strategy, DTTs role and summary of assessment reports DC. McDonald, T. Donné, X. Litaudon, M. Reinhart, M. Turnyanskiy, D. Borba Steps in Plasma Exhaust strategy 1. European

More information

INTERNAL TRANSPORT BARRIER THRUST

INTERNAL TRANSPORT BARRIER THRUST INTERNAL TRANSPORT BARRIER THRUST by C.M. Greenfield Presented to Program Advisory Committee Meeting January, 3 /TST/wj THE GOAL OF THRUST 7 IS TO ESTABLISH CONTROL OVER THE INTERNAL TRANSPORT BARRIER

More information

A U.S. STRATEGIC PLAN FOR TIMELY FUSION ENERGY DEVELOPMENT

A U.S. STRATEGIC PLAN FOR TIMELY FUSION ENERGY DEVELOPMENT A U.S. STRATEGIC PLAN FOR TIMELY FUSION ENERGY DEVELOPMENT M.R. Wade * General Atomics, San Diego, CA, USA WHITE PAPER Prepared for Committee on a Strategic Plan for US Burning Plasma Research US National

More information

EAST(HT-7U ) Physics and Experimental Plan

EAST(HT-7U ) Physics and Experimental Plan EAST(HT-7U ) Physics and Experimental Plan EAST team, presented by Jiangang Li Institute of Plasma Physics, CAS 1 st EAST IAC meeting Hefei, Oct.10-11 The mission of EAST To explore the methods to achieve

More information

Development Scenario of Tokamak Reactor for Early Demonstration of Electric Power Generation

Development Scenario of Tokamak Reactor for Early Demonstration of Electric Power Generation Development Scenario of Tokamak Reactor for Early Demonstration of Electric Power Generation US/Japan Workshop on Power Plant Studies and Related Advanced Technologies With EU Participation 24-25 January

More information

ARIES Issues and R&D Needs Technology Readiness for Fusion Energy

ARIES Issues and R&D Needs Technology Readiness for Fusion Energy page 1 of 16 ARIES Issues and R&D Needs Technology Readiness for Fusion Energy M. S. Tillack ARIES Project Meeting 28 May 2008 page 2 of 16 The goal of the TWG s is to translate advisory committee recommendations

More information

Operation of DIII-D National Fusion Facility and Related Research Cooperative Agreement DE-FC02-04ER54698 (GA Project 30200)

Operation of DIII-D National Fusion Facility and Related Research Cooperative Agreement DE-FC02-04ER54698 (GA Project 30200) May 10, 2010 Dr. Mark Foster U. S. Department of Energy Office of Science General Atomics Site/Bldg. 7 Rm. 119 3550 General Atomics Ct. San Diego, CA 92121 Reference: Operation of DIII-D National Fusion

More information

EU considerations on Design and Qualification of Plasma Facing Components for ITER

EU considerations on Design and Qualification of Plasma Facing Components for ITER EU considerations on Design and Qualification of Plasma Facing Components for ITER Patrick Lorenzetto, F4E Barcelona with inputs from B. Riccardi (F4E), V. Barabash and M. Merola (ITER IO) on Readiness

More information

SCIENCE. Briefing for National Academy of Sciences Board on Physics and Astronomy

SCIENCE. Briefing for National Academy of Sciences Board on Physics and Astronomy OFFICE OF SCIENCE Briefing for National Academy of Sciences Board on Physics and Astronomy Presented by: Dr. Stephen Eckstrand Acting Director Office of Fusion Energy Sciences Office of Science, U.S. Department

More information

DEMO Concept Development and Assessment of Relevant Technologies

DEMO Concept Development and Assessment of Relevant Technologies 1 FIP/3-4Rb DEMO Concept Development and Assessment of Relevant Technologies Y. Sakamoto, K. Tobita, H. Utoh, N. Asakura, Y. Someya, K. Hoshino, M. Nakamura, S. Tokunaga and the DEMO Design Team Japan

More information

The EU Plasma Wall Interaction Task Force : Recent Achievements and Plans

The EU Plasma Wall Interaction Task Force : Recent Achievements and Plans The EU Plasma Wall Interaction Task Force : Recent Achievements and Plans R. Zagórski PWI Responsible Officer EFDA CSU Garching Special thanks to: E. Tsitrone (CEA) and R.Neu (IPP) and EU TF on PWI R.Zagórski:

More information

Integrated Scenarios: Advanced Regimes

Integrated Scenarios: Advanced Regimes Integrated Scenarios: Advanced Regimes Program Advisory Committee Meeting February 6-8, 2008 MIT PSFC Presented by A. Hubbard, for the Advanced Scenarios thrust group Outline Scope and niche of Advanced

More information

COREDIV modelling of JET ILW discharges with different impurity seeding: nitrogen, neon, argon and krypton*

COREDIV modelling of JET ILW discharges with different impurity seeding: nitrogen, neon, argon and krypton* NUKLEONIKA 17;(1): 7 doi: 1./nuka-17-1 ORIGINAL PAPER 17 Irena Ivanova-Stanik et al. This is an open access article distributed under the Creative Commons Attribution -NonCommercial-NoDerivatives. License

More information

EU DEMO Design Point Studies

EU DEMO Design Point Studies EU DEMO Design Point Studies R. Kemp 1, D. J. Ward 1, G. Federici 2, R. Wenninger 2,3 and J. Morris 1 1 CCFE, Culham Science Centre, Oxfordshire OX14 3DB, United Kingdom 2 EFDA PPPT, Boltzmannstr.2, Garching

More information

Integrated Scenarios: Advanced Regimes

Integrated Scenarios: Advanced Regimes Integrated Scenarios: Advanced Regimes Program Advisory Committee meeting February 4-6, 2009 MIT PSFC Presented by A. Hubbard, for the Advanced Scenarios thrust group Outline Introduction: Scope and niche

More information

ITER Vacuum Vessel Status and Procurement

ITER Vacuum Vessel Status and Procurement ITER Vacuum Vessel Status and Procurement IBF, Nice 11 December 2007 Presented by K. Ioki Tokamak Department, ITER Organization 1 VV design Design Review Activities VV Procurement Contents Main Vessel

More information

GA A25839 HIGH PERFORMANCE PLASMA OPERATION ON DIII-D DURING EXTENDED PERIODS WITHOUT BORONIZATION

GA A25839 HIGH PERFORMANCE PLASMA OPERATION ON DIII-D DURING EXTENDED PERIODS WITHOUT BORONIZATION GA A25839 HIGH PERFORMANCE PLASMA OPERATION ON DIII-D DURING EXTENDED PERIODS WITHOUT BORONIZATION by W.P. WEST, M. GROTH, A.W. HYATT, G.L. JACKSON, M.R. WADE, C.M. GREENFIELD, and P.A. POLITZER JULY 2007

More information

R&D required to place a test module on FNF (how does it compare to ITER TBM?) R&D required for base blanket

R&D required to place a test module on FNF (how does it compare to ITER TBM?) R&D required for base blanket Testing Strategy, Implications for R&D and Design What are the preferred blankets options for testing on FNF and what are the implications for R&D? Comparison of strategies for testing space allocation

More information

Taming Plasma-Materials Interface for Steady-State Fusion

Taming Plasma-Materials Interface for Steady-State Fusion Taming Plasma-Materials Interface for Steady-State Fusion by H.Y. Guo, with H. Wang, J.G. Watkins, A.L. Moser, J. Boedo, L. Casali, B. Covele, B. Grierson, M. Groth, D.N. Hill, A.W. Hyatt, L.L. Lao, A.W.

More information

Prospects for a next-step ST

Prospects for a next-step ST Prospects for a next-step ST Jon Menard (PPPL) with contributions from: Ray Fonck (UW Madison) Stan Kaye (PPPL) Dick Majeski (PPPL) Masa Ono (PPPL) Steve Sabbagh (Columbia U.) October 24, 2009 Comprehensive

More information

Development and Application of System Analysis Program for Parameters Optimization and Economic Assessment of Fusion Reactor (SYSCODE)

Development and Application of System Analysis Program for Parameters Optimization and Economic Assessment of Fusion Reactor (SYSCODE) Development and Application of System Analysis Program for Parameters Optimization and Economic Assessment of Fusion Reactor (SYSCODE) Presented By Dehong Chen Contributed by FDS Team Key Laboratory of

More information

Shattered Pellet Injection as the Primary Disruption Mitigation Technique for ITER

Shattered Pellet Injection as the Primary Disruption Mitigation Technique for ITER 1 EX/9-2 Shattered Pellet Injection as the Primary Disruption Mitigation Technique for ITER D. Shiraki 1, N. Commaux 1, L.R. Baylor 1, N.W. Eidietis 2, E.M. Hollmann 3, V.A. Izzo 3, C.J. Lasnier 4, R.A.

More information

Plasma-Facing Material Development Strategy in ITER

Plasma-Facing Material Development Strategy in ITER Plasma-Facing Material Development Strategy in ITER Michiya Shimada, Richard Pitts, Alberto Loarte, Alexei Polevoi, Vladimir Mukhovatov, Andrei Kukushkin, Masayoshi Sugihara, David Campbell and Valery

More information

ITER Organization. Françoise Flament. Head of Procurement Arrangements & Contracts Division. Journée ITER/CEA 01/12/2010. Page 1

ITER Organization. Françoise Flament. Head of Procurement Arrangements & Contracts Division. Journée ITER/CEA 01/12/2010. Page 1 ITER Organization Françoise Flament Head of Procurement Arrangements & Contracts Division Page 1 1. Overview of the IO Procurement System 2. Business Opportunities 3. IO Procurement Processes and Procedures

More information

c O N F - y r-elm HEAT FLUX IN THE ITER DIVERTOR

c O N F - y r-elm HEAT FLUX IN THE ITER DIVERTOR GAmA22899 c O N F - y 60 6 7 r-elm HEAT FLUX IN THE ITER DIVERTOR by AUG 1 OSTI A.W. LEONARD A. HERMANN K. ITAMI J. LINGERTAT A. LOARTE T.H. OSBORNE W. SUTTROP the ITER DIVERTOR MODELING and DATABASE EXPERT

More information

THE ARIES-I TOKAMAK REACTOR STUDY

THE ARIES-I TOKAMAK REACTOR STUDY THE ARIES-I TOKAMAK REACTOR STUDY Farrokh Najmabadi, Robert W. Conn, and The ARIES Team 16th SOFT London, September 3-7, 1990 ARIES Is a Community-Wide Study U. W. UCLA ANL U. IL. FEDC ORNL RPI ARIES GA

More information

High-density operation with pellets on ASDEX Upgrade - and its impact on the DEMO design

High-density operation with pellets on ASDEX Upgrade - and its impact on the DEMO design 78. DPG-Frühjahrstagung AMOP 17. 21. March 2014, Berlin High-density operation with pellets on ASDEX Upgrade - and its impact on the DEMO design M. Bernert, L. Casali, R. Fischer, O. Kardaun, G. Kocsis,

More information

The Status of the ITER Design. N. Holtkamp

The Status of the ITER Design. N. Holtkamp The Status of the ITER Design N. Holtkamp For the ITER Organization, Domestic Agencies and ITER Collaborators ITER Organization, CS 90 046, 13067 Saint Paul lez Durance, France email contact of the author:

More information

Disruption mitigation with high-pressure noble gas injection

Disruption mitigation with high-pressure noble gas injection Disruption mitigation with high-pressure noble gas injection D. G. Whyte*, University of California San Diego T.C. Jernigan, Oak Ridge National Laboratory D.A. Humphreys, A.W. Hyatt, T.E. Evans, P.B. Parks,

More information

Simulation of Power Exhaust in Edge and Divertor of the SlimCS Tokamak Demo Reactor

Simulation of Power Exhaust in Edge and Divertor of the SlimCS Tokamak Demo Reactor J. Plasma Fusion Res. SERIES, Vol. 9 (2010) Simulation of Power Exhaust in Edge and Divertor of the SlimCS Tokamak Demo Reactor Nobuyuki ASAKURA, Katsuhiro SHIMIZU, Hisato KAWASHIMA, Kenji TOBITA and Tomonori

More information

ITER Fuelling System Design and Challenges Gas and Pellet Injection and Disruption Mitigation

ITER Fuelling System Design and Challenges Gas and Pellet Injection and Disruption Mitigation ITER Fuelling System Design and Challenges Gas and Pellet Injection and Disruption Mitigation ITR/P1-28 S. Maruyama 1, Y. Yang 1, R.A. Pitts 1, M. Sugihara 1, S. Putvinski 1, S. Carpentier-Chouchana 1,

More information

Recent Results and Plans for the Advanced Tokamak Program

Recent Results and Plans for the Advanced Tokamak Program Recent Results and Plans for the Advanced Tokamak Program Program Advisory Committee Review February 6-7, 2002 MIT PSFC Presented by A. Hubbard Outline Overview Results from 2001and plans for 2002 - Internal

More information

Conceptual design of a demonstration reactor for electric power generation

Conceptual design of a demonstration reactor for electric power generation 1 FT/P7-4 Conceptual design of a demonstration reactor for electric power generation Y. Asaoka 1), R. Hiwatari 1), K. Okano 1), Y. Ogawa 2), H. Ise 3), Y. Nomoto 3), T. Kuroda 3), S. Mori 3), K. Shinya

More information

The Tokamak Concept. Magnetic confinement. The Tokamak concept

The Tokamak Concept. Magnetic confinement. The Tokamak concept Major radius Minor radius The Tokamak Concept ITER is based on the tokamak concept. A tokamak is a device able to produce and confine a large volume of high temperature plasma -a mixture of electrons and

More information

Research Thrust to Address Major Measurement Gaps

Research Thrust to Address Major Measurement Gaps Research Thrust to Address Major Measurement Gaps RENEW Workshop Presentation Theme: Plasma Material Interface Subpanel on Internal Components Presented by Tony Peebles, UCLA Physics & Astronomy Department:

More information

GA A FUSION TECHNOLOGY FACILITY KEY ATTRIBUTES AND INTERFACES TO TECHNOLOGY AND MATERIALS by C.P.C. WONG

GA A FUSION TECHNOLOGY FACILITY KEY ATTRIBUTES AND INTERFACES TO TECHNOLOGY AND MATERIALS by C.P.C. WONG GA A27273 FUSION TECHNOLOGY FACILITY KEY ATTRIBUTES AND INTERFACES TO TECHNOLOGY AND MATERIALS by C.P.C. WONG MARCH 2012 DISCLAIMER This report was prepared as an account of work sponsored by an agency

More information

Integrated System Level Simulation and Analysis of DEMO with Apros. Sami Kiviluoto

Integrated System Level Simulation and Analysis of DEMO with Apros. Sami Kiviluoto Integrated System Level Simulation and Analysis of DEMO with Apros Sami Kiviluoto 3.11.2016 DEMO modelling project Fortum joined FinnFusion consortium in the fall 2015 EUROfusion WPPMI project (Plant Level

More information

Assessment and comparison of pulsed and steady-state tokamak power plants

Assessment and comparison of pulsed and steady-state tokamak power plants Assessment and comparison of pulsed and steady-state tokamak power plants Farrokh Najmabadi UC San Diego 21 st International Toki Conference, 28 Novemeber-1 December 2011 Toki, Japan Choice between steady-state

More information

Overview of ARIES ACT-1 Study

Overview of ARIES ACT-1 Study Overview of ARIES ACT-1 Study Farrokh Najmabadi Professor of Electrical & Computer Engineering Director, Center for Energy Research UC San Diego and the ARIES Team Japan-US Workshop on Fusion Power Plants

More information

SUMMARY ITER FINAL DESIGN REPORT

SUMMARY ITER FINAL DESIGN REPORT ITER EDA DOCUMENTATION SERIES NO. 22 International Thermonuclear Experimental Reactor (ITER) Engineering Design Activities (EDA) SUMMARY of the ITER FINAL DESIGN REPORT July 2001 INTERNATIONAL ATOMIC ENERGY

More information

5 th INTERNATIONAL CONFERENCE ON THE FRONTIERS OF PLASMA PHYSICS AND TECHNOLOGY April 21, 2011, Singapore

5 th INTERNATIONAL CONFERENCE ON THE FRONTIERS OF PLASMA PHYSICS AND TECHNOLOGY April 21, 2011, Singapore 5 th INTERNATIONAL CONFERENCE ON THE FRONTIERS OF PLASMA PHYSICS AND TECHNOLOGY April 21, 2011, Singapore Outline Early history the underpinnings in Basic Studies Tokamak program Aditya and SST-1 - Some

More information

TOKAMAK ARCHITECTURE FOR PRACTICAL REMOTE MAINTENANCE

TOKAMAK ARCHITECTURE FOR PRACTICAL REMOTE MAINTENANCE TOKAMAK ARCHITECTURE FOR PRACTICAL REMOTE MAINTENANCE ERIC VILLEDIEU IAEA WORKSHOP DAEJEON KOREA 2018, 7 TH 10 TH OF MAY ISFNT-12 14-18 September 2O15 PAGE 1 CONTENT o o Problematic CFETR exercice Tokamak

More information

Fusion Power Plants. 52 Energia, ambiente e innovazione 4/2017 QUADRO INTERNAZIONALE_

Fusion Power Plants. 52 Energia, ambiente e innovazione 4/2017 QUADRO INTERNAZIONALE_ QUADRO INTERNAZIONALE_ Fusion Power Plants Developing fusion energy as a new source of energy represents a considerable challenge. The European Union, together with all ITER Parties, is currently engaged

More information

Critical Physics Issues for Tokamak Power Plants

Critical Physics Issues for Tokamak Power Plants Critical Physics Issues for Tokamak Power Plants D J Campbell 1, F De Marco 2, G Giruzzi 3, G T Hoang 3, L D Horton 4, G Janeschitz 5, J Johner 3, K Lackner 4, D C McDonald 6, D Maisonnier 1, G Pereverzev

More information

AT Task Force Summary. Amanda Hubbard C-Mod Ideas Forum 2005 Dec 2-6, 2004

AT Task Force Summary. Amanda Hubbard C-Mod Ideas Forum 2005 Dec 2-6, 2004 AT Task Force Summary Amanda Hubbard C-Mod Ideas Forum 2005 Dec 2-6, 2004 Main goals of the AT physics program (from 5-yr plan 2003) 1. Demonstrate and model current profile control using LH and ICRF waves,

More information

Arcing in DIII-D as a Source of PFC

Arcing in DIII-D as a Source of PFC Arcing in DIII-D as a Source of PFC Erosion and Dust Production D.L. Rudakov K.R. Umstadter R.P. Doerner S.I. Krasheninnikov University of California, San Diego W.R. Wampler Sandia National Laboratories

More information

Gas Jet Disruption Mitigation Studies on Alcator C-MOD

Gas Jet Disruption Mitigation Studies on Alcator C-MOD Gas Jet Disruption Mitigation Studies on Alcator C-MOD R. Granetz 1, D. Whyte 2, V. Izzo 1, T. Biewer 1, M. Reinke 1, J. Terry 1, A. Bader 1, M. Bakhtiari 2, T. Jernigan 3, G. Wurden 4 1 MIT Plasma Science

More information

Pellet Fueling, ELM pacing, and Disruption Mitigation Technology Development for ITER

Pellet Fueling, ELM pacing, and Disruption Mitigation Technology Development for ITER 1 IT/P6-19 Pellet Fueling, ELM pacing, and Disruption Mitigation Technology Development for ITER L.R. Baylor 1, S.K. Combs 1, C.R. Foust 1, T.C. Jernigan 1, S. J. Meitner 1, P.B. Parks 2, J.B. Caughman

More information

Integrated Scenarios: Advanced Regimes

Integrated Scenarios: Advanced Regimes Integrated Scenarios: Advanced Regimes Program Advisory Committee meeting January 27-29, 2010 MIT PSFC Presented by A. Hubbard, for the Advanced Scenarios thrust group v7 1/28/10 Outline Introduction:

More information

Reflections on Fusion Chamber Technology and SiC/SiC Applications Mohamed Abdou UCLA

Reflections on Fusion Chamber Technology and SiC/SiC Applications Mohamed Abdou UCLA Reflections on Fusion Chamber Technology and SiC/SiC Applications Mohamed Abdou UCLA Presented at CREST Conference, Kyoto, Japan, May 21, 2002 The Region Immediately Surrounding the Plasma Divertor / First

More information

WHITE PAPER: Machine Learning Application to Fusion Energy Predictive Disruption Studies. William Tang

WHITE PAPER: Machine Learning Application to Fusion Energy Predictive Disruption Studies. William Tang WHITE PAPER: Machine Learning Application to Fusion Energy Predictive Disruption Studies William Tang (wtang@princeton.edu) Princeton University Dept. of Astrophysical Sciences, Plasma Physics Section,

More information

Development of Advanced Operation Scenarios in Weak Magnetic-Shear Regime on JT-60U

Development of Advanced Operation Scenarios in Weak Magnetic-Shear Regime on JT-60U EX/1-4Rc Development of Advanced Operation Scenarios in Weak Magnetic-Shear Regime on JT-60U T. Suzuki 1), N. Oyama 1), A. Isayama 1), Y. Sakamoto 1), T. Fujita 1), S. Ide 1), Y. Kamada 1), O. Naito 1),

More information

The Development Path for Magnetic Fusion Energy

The Development Path for Magnetic Fusion Energy The Development Path for Magnetic Fusion Energy Rob Goldston Princeton Plasma Physics Laboratory Global Climate and Energy Project Workshop on Fusion Energy May 1, 2006 Fusion is an Attractive Long-term

More information

EX/7-3Ra. Disruption Control on FTU and ASDEX Upgrade with ECRH

EX/7-3Ra. Disruption Control on FTU and ASDEX Upgrade with ECRH 1 Disruption Control on FTU and ASDEX Upgrade with ECRH B. Esposito 1), G. Granucci 2), S. Nowak 2), J.R. Martin-Solis 3), L. Gabellieri 1), P. Smeulders 1), M. Maraschek 4), G. Pautasso 4), J. Stober

More information

Status and Plans for APEX Task A Plasma/Liquid-Wall Interactions

Status and Plans for APEX Task A Plasma/Liquid-Wall Interactions Status and Plans for APEX Task A Plasma/Liquid-Wall Interactions T.D. * with J. Brooks, T. Evans, A. Hassanein, & M. Rensink* APEX Fall Meeting PPPL Nov. 4, 2002 Work performed under auspices of US DOE;

More information

Prof. Robert Goldston, Princeton University

Prof. Robert Goldston, Princeton University Prof. Robert Goldston, Princeton University Director, DOE Princeton Plasma Physics Laboratory Congressional Research and Development Caucus December 7, 2005 Fusion is an Attractive Long-term Form of Nuclear

More information

Fusion Nuclear Science. Required Fusion Nuclear Environment

Fusion Nuclear Science. Required Fusion Nuclear Environment Fusion Nuclear Science Research Thrust & the Required Fusion Nuclear Environment Martin Peng, Tom Burgess, John Canik, Mike Cole, Steffi Diem, Yutai Katoh, Kofi Korsah, Brad Patton, Aaron Sontag, John

More information

Fueling Technology for Disruption & VDE Mitigation

Fueling Technology for Disruption & VDE Mitigation Fueling Technology for Disruption & VDE Mitigation ORNL Fueling Group [Gouge, Foster, Fisher, Jernigan, Baylor, et al.] Oak Ridge National Laboratory Burning Plasma Workshop May 1-3, 2001 MJG/PWF/NAU,

More information

Safety Classification of Mechanical Components for Fusion Application

Safety Classification of Mechanical Components for Fusion Application Safety Classification of Mechanical Components for Fusion Application 13 rd International Symposium on Fusion Nuclear Technology 25-29 September 2017, Kyoto, Japan Oral Session 1-2: Nuclear System Design

More information

Science/Fusion Energy Sciences

Science/Fusion Energy Sciences Fusion Energy Sciences Overview The mission of the Fusion Energy Sciences (FES) program is to expand the fundamental understanding of matter at very high temperatures and densities and to build the scientific

More information

Runaway Electron Transport & Disruption Mitigation Optimization on Alcator C-Mod

Runaway Electron Transport & Disruption Mitigation Optimization on Alcator C-Mod Runaway Electron Transport & Disruption Mitigation Optimization on Alcator C-Mod D.G. Whyte 1, R. Granetz 1, V. Izzo 2, M. Reinke 1, G. Olynyk 1 & Alcator C-Mod team 1 MIT Plasma Science & Fusion Center

More information

TOROIDAL REACTOR DESIGNS AS A FUNCTION OF ASPECT RATIO

TOROIDAL REACTOR DESIGNS AS A FUNCTION OF ASPECT RATIO TOROIDAL REACTOR DESIGNS AS A FUNCTION OF ASPECT RATIO C.P.C. Wong, J.C. Wesley, R.D. Stambaugh, E.T. Cheng General Atomics, San Diego, California TSI Research Inc., Solana Beach, California e-mail contact

More information

IT/P1-20 Beryllium containing plasma interactions with ITER materials

IT/P1-20 Beryllium containing plasma interactions with ITER materials IT/P1-2 Beryllium containing plasma interactions with ITER materials R.P. Doerner 1), M. Baldwin 1), G. Federici 2), J. Hanna 1), A. Loarte 2), D. Nishijima 1), R. Pugno 3), J. Roth 3), K. Schmid 3), G.

More information

Plasma Fueling and Implications for FIRE, ITER, ARIES

Plasma Fueling and Implications for FIRE, ITER, ARIES Plasma Fueling and Implications for FIRE, ITER, ARIES M. J. Gouge Oak Ridge National Laboratory March 6, 2001 MJG:TTM, 3/01 1 Outline Fueling system functions Fueling program scope ITER and FIRE fueling

More information

We can describe a simple power balance for a fusion power plant in steady state with the following definitions,

We can describe a simple power balance for a fusion power plant in steady state with the following definitions, Producing Electricity in a Fusion Nuclear Science Facility or Similar C. E. Kessel, PPPL 1. Introduction The ultimate goal of fusion plasma and fusion nuclear science is the construction and operation

More information

Advanced Study of a Tokamak Transmutation System

Advanced Study of a Tokamak Transmutation System Abstract Advanced Study of a Tokamak Transmutation System L. J. Qiu, Y. C. Wu, B. Wu, X.P. Liu, Y.P. Chen, W.N. Xu, Q.Y. Huang Institute of Plasma Physics, Chinese Academy of Sciences P.O. Box 1126, Hefei,

More information

Fueling Requirements for Steady State Spherical Torus Operation

Fueling Requirements for Steady State Spherical Torus Operation Supported by Fueling Requirements for Steady State Spherical Torus Operation Roger Raman, Thomas R. Jarboe, + Henry W. Kugel University of Washington, Seattle + Princeton Plasma Physics Laboratory Joint

More information

Operation of the helium cooled DEMO fusion power plant and related safety aspects

Operation of the helium cooled DEMO fusion power plant and related safety aspects Operation of the helium cooled DEMO fusion power plant and related safety aspects 1 st IAEA workshop on Challenges for coolants in fast spectrum system: Chemistry and materials, Vienna, July, 5-7 2017

More information

MAST Upgrade Research Plan June MAST-U_Research_Plan_v3.0

MAST Upgrade Research Plan June MAST-U_Research_Plan_v3.0 MAST Upgrade Research Plan June 2015 1 1 INTRODUCTION AND BASIC INFORMATION ABOUT MAST UPGRADE The MAST Upgrade programme has three main objectives that are central to the drive towards commercial fusion

More information