PUBLIC PARTICIPATION DOCUMENTS For Holland Board of Public Works Holland, Michigan

Size: px
Start display at page:

Download "PUBLIC PARTICIPATION DOCUMENTS For Holland Board of Public Works Holland, Michigan"

Transcription

1 STATE OF MICHIGAN Rick Snyder, Governor DEPARTMENT OF ENVIRONMENTAL QUALITY AIR QUALITY DIVISION CONSTITUTION HALL 525 WEST ALLEGAN STREET P.O. BOX LANSING, MICHIGAN PUBLIC PARTICIPATION DOCUMENTS For Holland Board of Public Works Holland, Michigan PERMIT APPLICATION NUMBER October 28, 2013

2 Holland Board of Public Works Page 1 Purpose and Summary FACT SHEET October 28, 2013 The Michigan Department of Environmental Quality (MDEQ), Air Quality Division (AQD), is proposing to act on Permit to Install (PTI) application No from Holland Board of Public Works (BPW). The permit application is for a proposed installation and operation of a new Combined Heat and Power (CHP) plant consisting of two natural gas-fired combustion turbine generators (CTGs), two heat recovery steam generators (HRSGs) equipped with natural gas-fired duct burners, one steam generator (STG), two natural gas-fired auxiliary boilers, one natural gasfired fuel heater, one natural gas-fired emergency reciprocating engine, one plume-abated wet mechanical draft cooling tower, one emergency diesel-fueled fire pump, four water and condensate storage tanks, one diesel tank, and one aqueous ammonia storage tank. The proposed project is subject to permitting requirements of the Department s Rules for Air Pollution Control and state and federal Prevention of Significant Deterioration (PSD) regulations. Prior to acting on this application, the AQD is holding a public comment period and a public hearing, if requested in writing, to allow all interested parties the opportunity to comment on the proposed PTI. All relevant information received during the comment period and hearing if held, will be considered by the decision maker prior to taking final action on the application. Background Information Holland BPW was established as a community-owned utility in They provide electricity, snowmelt, fiber broad band, and water and wastewater treatment services to the Holland community. This permit application is for a new combined heat and power plant with two natural gas-fired, combined cycle turbines/heat recovery steam generators and one steam turbine generator for a two-by-one (2x1) configuration. The proposed plant will be installed to provide electric generation, snowmelt services, and potentially hot water district heating. The proposed facility is a new stationary source, located at an existing industrial site. This project covers all equipment at the proposed facility. Proposed Facility The proposed new CHP plant will consist of the following equipment: Two natural gas-fired CTGs, rated at 554 million British thermal units per hour (MMBtu/hr) each, two HRSGs equipped with natural gas-fired duct burners, rated at 93 MMBtu/hr each, and one STG. The proposed 2x1 configuration, comprised of the two CTG/HRSG trains and the STG, will have a total nominal electric generating capacity of approximately 115 megawatts. Two natural gas-fired auxiliary boilers. One rated at 55 MMBtu/hr for station steam requirements, and one rated at 95 MMBtu/hr for a backup for snowmelt and district heating at times in which the combined cycle configuration cannot supply district energy needs. One natural gas-fired fuel heater rated at 3.7 MMBtu/hr to superheat the natural gas fuel. One natural gas-fired emergency reciprocating engine, rated at 1,000 kilowatts (kw), to charge the batteries in the uninterruptible power supply batteries. One plume-abated wet mechanical draft cooling tower with three cells to serve as the heat sink for the station. One emergency diesel-fueled fire pump, rated at 165 horsepower (hp).

3 Holland Board of Public Works Page 2 Six tanks: four water and condensate storage tanks, one diesel tank, and one aqueous ammonia storage tank. The CTG and duct burners will be permitted to operate on natural gas only. The equipment was evaluated with the duct burners continuously firing. The specific make and model for the equipment has not yet been chosen, but Holland BPW has designated that the CTG will be an aeroderivative-type turbine. The review was performed on the emissions profile of the aeroderivative design. The equipment chosen by Holland BPW will be constrained by the permit conditions, should the application be approved. The application is PSD for nitrogen oxides (NOx), carbon monoxide (CO), particulate matter (PM), particulate matter that has an aerodynamic diameter less than or equal to a nominal 10 microns (PM10), particulate matter that has an aerodynamic diameter less than or equal to a nominal 2.5 microns (PM2.5), volatile organic compounds (VOCs), and greenhouse gases (GHGs). Present Air Quality The proposed Holland BPW facility is located in Ottawa County, which is currently in attainment with the National Ambient Air Quality Standards (NAAQS) for nitrogen dioxide (NO 2 ), CO, PM10, PM2.5, ozone, sulfur dioxide (SO 2 ), and lead. There is no NAAQS for GHGs. Pollutant Emissions PSD permitting requirements are triggered if any one regulated pollutant is greater than 100 tons per year (tpy) at a fossil fuel-fired steam electric plant of more than 250 MMBtu/hr heat input. A single CTG alone has a rating of 554 MMBtu/hr, and, as seen in Table 1 below, multiple pollutants exceed 100 tpy. Once PSD permitting requirements are triggered, any regulated pollutant with emissions greater than its PSD significant emission rate, must undergo PSD review. This application is subject to PSD for NOx, CO, PM, PM10, PM2.5, VOCs, and GHGs. The proposed new CHP plant will be a new major stationary source, and, therefore, subject to the PSD Regulations in Part 18 of the Michigan Air Pollution Control Rules and 40 CFR

4 Holland Board of Public Works Page 3 The following table provides the estimated emissions for each regulated pollutant: Table 1: Project Potential Emissions Summary Pollutant Estimated PSD Significant Emissions (tpy) Emission Rate (tpy) Subject to PSD? NOx Yes CO Yes PM Yes PM Yes PM Yes VOCs Yes SO No Lead 7.29E No Fluorides Negligible 3 No Sulfuric Acid Mist Negligible 7 No Hydrogen Sulfide (H 2 S) Negligible 10 No GHGs as CO 2 e* 787,641 75,000 Yes * Carbon dioxide equivalent Key Permit Review Issues The AQD staff evaluated the proposed project to identify all state rules and federal regulations which are, or may be, applicable. The tables in Appendix 1 summarize these rules and regulations. Prevention of Significant Deterioration (PSD) Regulations The project was reviewed under the PSD rules which require Best Available Control Technology (BACT), as summarized in Appendix 2, and an air quality impact analysis for each regulated air pollutant for which the project will result in significant emissions. The pollutants subject to PSD review are NOx, CO, PM, PM10, PM2.5, VOCs, and GHGs. Federal NSPS Regulations New Source Performance Standards (NSPS) were established under Title 40 of the Code of Federal Regulations (40 CFR) Part 60. The CTG/HRSG trains are subject to the NSPS Subpart KKKK for Stationary Combustion Turbines. Auxiliary Boilers A and B are subject to the NSPS Subpart Dc for Small Industrial- Commercial-Institutional Steam Generating Units. The natural gas-fired emergency engine is subject to the NSPS Subpart JJJJ for Stationary Spark Ignition Internal Combustion Engines. The emergency, diesel-fueled fire pump is subject to the NSPS Subpart IIII for Stationary Compression Ignition Internal Combustion Engines.

5 Holland Board of Public Works Page 4 The fuel heater has a heat input capacity of 3.7 MMBtu/hr, which makes it too small to be subject to 40 CFR Part 60 Subpart D, Da, Db, and Dc. The cooling tower is not a regulated piece of equipment by itself under any NSPS. Federal NESHAP Regulations National Emission Standards for Hazardous Air Pollutants (NESHAP) were established under 40 CFR Part 63. A major source under the NESHAP is defined as potential emissions of 10 tpy for a single hazardous air pollutant (HAP) or 25 tpy for all HAPs combined. An area source has potential HAP emissions below the major source values. The total potential HAP emissions from the proposed facility will be less than 10 tpy for any single HAP and less than 25 tpy for all HAPs combined, and therefore the source is considered an area source of HAP emissions. The emergency diesel-fueled fire pump and emergency natural gas-fired engine are subject to 40 CFR Part 63 Subpart ZZZZ for reciprocating internal combustion engines at major or area sources. The only requirement for the engines is to comply with their applicable NSPS. The boilers are not subject to 40 CFR Part 63 Supart JJJJJJ because they are exclusively gas-fired. The facility is an area source and therefore 40 CFR Part 63 Subpart DDDDD (boilers), YYYY (combustion turbines), and Q (industrial cooling towers) do not apply. Rule 224 TBACT Analysis The MDEQ Rules for Air Pollution Control require that new or modified equipment that emits toxic air contaminants (TACs) must utilize the Best Available Control Technology for Toxics (T-BACT), unless the emission unit emits toxic air contaminants that are particulates or VOC and are in compliance with BACT or Lowest Achievable Emission Rate requirements. Per Rule 224(2), the engines and the boilers are excluded from the T-BACT analysis because they are subject to Part 63 NESHAPs ZZZZ and JJJJJJ, respectively. This is consistent with T-BACT for other permits. Other pieces of equipment underwent a top-down BACT analysis for VOC and PM for each emitting piece of equipment to comply with PSD regulations. The only TAC that was not covered through the PSD BACT review was ammonia, which is released during potential ammonia slip from the selective catalytic reduction (SCR) process utilized for NOx control on the CTG/HRSG units. Holland BPW stated that BACT for reduction of ammonia slip is an efficiently designed and managed SCR system, and the AQD concurred with their determination. Rule 225 Toxics Analysis The MDEQ Rules for Air Pollution Control require the ambient air concentration of TACs be compared against health-based screening levels. Holland BPW performed TAC analyses with the allowable emission rates (AER) table and with generic modeling. Most TACs were below their screening level utilizing the AER table, which is considered a conservative approach. Generic modeling takes into account more site specific parameters. The TAC with the highest predicted ambient impact from this project was formaldehyde. The modeled impact was approximately 28 percent of the initial threshold screening level (ITSL). The AQD review found that all TACs show impacts less than the established health-based screening levels and will comply with the requirements of Rule 225.

6 Holland Board of Public Works Page 5 Rule 702 VOC Emissions VOC is a PSD pollutant for this project. A top down BACT was performed for all VOC sources and was thoroughly reviewed. VOC BACT will be met and all VOC emission limits in any applicable NSPS will be met. A demonstration of compliance with PSD BACT (summarized in Appendix 2) satisfies the Rule 702 BACT requirement. Criteria Pollutants Modeling Analysis An air quality impact analysis, as required by Rules through , using computer dispersion modeling to predict the ambient air impacts was performed for NOx, CO, PM10, and PM2.5 emissions. NOx refers specifically to nitrogen monoxide and NO 2 with the larger portion being that of NO 2, a highly reactive gas, which is what the United States Environmental Protection Agency (USEPA) established air quality standards for under the CAA. Additionally, Holland BPW was granted a waiver for preconstruction ambient monitoring. Two operating scenarios were utilized in the dispersion modeling for the project and the worst case impact for each criteria pollutant, for each averaging time, was used in comparison to the maximum levels allowed. The two operating scenarios were for baseload operation and startup operation. The two emergency engines have operational restrictions of 500 hours per year each. They were modeled as intermittent sources during the baseload operation and were not included in the startup modeling. The proposed conditions contain these restrictions. The CTG/HRSG units also utilized annualized emission rates for the startup modeling. In the proposed draft there is a condition restricting the total number of startup and shutdown hours. The Significant Impact Level (SIL) analysis considers the potential emission increases from the proposed project for NO 2, CO, PM10, and PM2.5 and compares them to the SIL, as shown in Table 2, below. The impacts of CO for all averaging periods and PM10 on an annual average were determined to all be below their respective SIL. There is no SIL for PM, VOC, or GHGs, and also no NAAQS or PSD Increment. Table 2: Significant Impact Levels (SIL) Pollutant Averaging Period SIL Total Below (ug/m 3 ) Maximum SIL? Impact NO 2 1-Hour No Annual No CO 1-Hour 2, Yes 8-Hour Yes PM10 24-Hour No Annual Yes PM Hour No Annual No

7 Pollutant Holland Board of Public Works Page 6 If the results determine that the modeled ambient air impacts for each pollutant are less than their respective SIL, then no further modeling is required. If the results determine the modeled impacts exceed the SIL, then a facility-wide NAAQS and PSD Increment modeling analysis is required. The NAAQS are intended to protect public health. The analysis added the background impacts to the total facility impact, which includes additional nearby facilities (offsite sources). This summed impact is compared to the NAAQS. There are no NAAQS for PM, VOC, or GHG. Holland BPW was required to do this analysis for all pollutants above their respective SIL: NO 2, 24-hour PM10, and PM2.5. This analysis also included secondary PM2.5 from precursors of NOx and SO 2, therefore the cumulative PM2.5 primary and secondary impacts were examined for comparison with the NAAQS. The results of the NAAQS analysis are below in Table 3. Averaging Period NAAQS (ug/m 3 ) Table 3: NAAQS Analysis Secondary (ug/m 3 ) (ug/m 3 ) Facility + Offisite Sources Maximum Concentration Background Concentration Total Concentration ** (ug/m 3 ) (ug/m 3 ) 1-Hour Yes NO 2 Annual Yes PM10 24-Hour Yes 24-Hour Yes PM2.5* Annual Yes * Includes secondary PM2.5 formation. ** This is the total impact from the facility plus background. Below NAAQS?

8 Holland Board of Public Works Page 7 The PSD increments are intended to allow industrial growth in an area, while ensuring that the area will continue to meet the NAAQS. The analysis compares the total facility impact plus other increment consuming facilities nearby. There are no PSD Increments for CO, PM, VOCs, or GHGs. Holland BPW was required to do PSD Increment modeling for all pollutants above their respective SIL: NO 2 and PM2.5 for all averaging periods, and PM10 on a 24-hour averaging period. This analysis also included secondary PM2.5 from precursors of NOx and SO 2, therefore the cumulative PM2.5 primary and secondary impacts were examined for comparison with the increment. Additionally, there were no increment consuming sources relative to this source. The results of the PSD increment analysis are below in Table 4. Pollutant Averaging Period Table 4: PSD Increment Analysis PSD Facility + Secondary Increme Offisite (ug/m 3 ) nt Sources (ug/m 3 ) Maximum Concentration (ug/m 3 ) Total (ug/m 3 ) NO 2 Annual Yes PM10 24-Hour Yes PM2.5* 24-Hour Yes Annual Yes * Includes secondary PM2.5 formation. Below PSD Increment? While the facility will not directly emit ozone, the facility will emit both NOx and VOC at levels greater than 100 tpy, thus triggering the ozone ambient impact analysis requirements of 40 CFR Ground-level ozone concentrations are the result of photochemical reactions among various chemical species. The chemical species that contribute to ozone formation, referred to as ozone precursors, include NOx and VOC emissions from both anthropogenic (e.g., mobile and stationary sources) and natural sources (e.g., vegetation). The USEPA has not approved an ozone model for single source applications, nor have they provided specific guidance for completing an ambient impact analysis for ozone as it relates to PSD. Therefore, Holland BPW quantified the regional ozone formation impacts from the proposed project using a similar approach to quantifying secondary PM2.5 formation impacts and determined that the highest source impact for ozone would not be significant. Additional Impact Analysis An additional impact analysis is required for major sources or major modifications pursuant to 40 CFR Part 52.21(o) and Rule This analysis is necessary to evaluate the impacts from the proposed project for soils, vegetation, visibility and growth. The proposed project emissions are not anticipated to have a negative impact on soils, vegetation, visibility, and to have no impact on growth once construction is completed.

9 Holland Board of Public Works Page 8 Key Aspects of Draft Permit Conditions The draft permit conditions contain emission limits, material limits, process/operational restrictions, monitoring, recordkeeping, and reporting requirements necessary for an enforceable permit that meets all applicable state and federal requirements. The following is a brief discussion of the key aspects of the draft permit conditions: Emission Limits The draft permit includes emission limits for NOx, CO, PM, PM10, PM2.5, VOC, and GHGs as CO 2 e to make the permit enforceable per the rules, and to protect the air quality standards. Material Limits The draft permit only allows the combustion of pipeline quality natural gas in the CTG, HRSG duct burners, auxiliary boilers, fuel heater, and natural gas-fired engine to assure fuel quality and consistency. Pipeline quality natural gas is required to have a minimum heat input (Btu) content and maximum sulfur content which affects combustion and air emissions. For the same reasons, the draft permit limits the emergency diesel-fueled fire pump fuel to only ultra-low sulfur diesel fuel with the maximum sulfur content of 15 ppm ( percent) by weight. Process/Operational Restrictions The draft permit requires a Malfunction Abatement Plan (MAP) for the CTG/HRSG trains. Holland BPW is required to develop the plan to include a preventative maintenance program and corrective procedures in the event of an equipment malfunction or failure. Also, the draft permit requires a plan that describes how emissions will be minimized during startup and shutdown for both the auxiliary boilers and the CTG/HRSG trains. The plan shall incorporate procedures recommended by the equipment manufacturer as well as incorporate standard industry practices. For the CTG/HRSG trains, startup is defined as the period of time from synchronization to the grid (generator breaker closed) until the combustion turbine reaches steady state operation (i.e. minimum of 50% of the maximum design capacity). Shutdown is defined as that period of time from the initial lowering of the CTG output (i.e. 50% of the maximum design capacity), with the intent to shutdown, until the point at which the combustion process has stopped (generator breaker open). The CTG/HRSG units have a combined limit of 635 hours total of startup and shutdown. The draft permit includes two operating restrictions on the emergency generators. The permittee shall not operate either emergency generator for more than 500 hours each per year on a 12-month rolling time period basis as determined at the end of each calendar month. Additionally, the permittee shall install, maintain, and operate the emergency generators according to the manufacturer s written instructions, or procedures developed by the owner/operator and approved by the engine manufacturer, over the entire life of the engines.

10 Holland Board of Public Works Page 9 Emission Control Device Requirements The draft permit includes emission control device requirements for certain emission units. Emissions are controlled using both low emitting process equipment and add-on emission controls. Control technology is described in detail in the BACT discussion found in Appendix 2, and is summarized in Table 5, below. Table 5: Control Technology Summary Emission Unit Control Technology Pollutant(s) Controlled EUCOOLTWR Mist/drift eliminators Particulates EUNGENGINE Oxidation catalyst CO and VOC EUFUELTANK Conservation vent valves VOC EUCTGHRSG1, Dry low NO x burners NOx EUCTGHRSG2 Selective catalytic reduction EUCTGHRSG1, Oxidation catalyst CO and VOC EUCTGHRSG2 EUAUXBOILERA Dry low NO x burners NOx EUAUXBOILERB Dry low NO x burners, Flue gas recirculation NOx Testing and Monitoring Requirements The draft permit includes emissions testing, monitoring, and recordkeeping requirements for all emission units. Also, the sizes or capacities of the emission units are specified in the permit conditions. Fuel Heater The maximum design heat input capacity for the fuel heater shall not exceed 3.7 MMBtu/hr on a fuel heat input basis. A device to monitor and record the fuel usage rate is required. A record of the fuel usage rate is required. Records on a monthly and 12-month rolling basis of total CO 2 e mass emissions are required. Three Cell Cooling Tower The mist/drift eliminators must be maintained at a vendor-certified maximum drift rate of percent or less. Associated records must be kept. Records of PM10 and PM2.5 emission rate calculations must be kept on a monthly and 12-month rolling basis. Records of any maintenance conducted must be maintained. Emergency Natural Gas-Fired Engine A non-resettable hours meters to track the operating hours is required. The nameplate capacity shall not exceed 1000 kw. A device to monitor and record the fuel usage rate is required. Emissions testing or manufacturer certification documentation is required for NOx, CO, and VOC emission rates. Monthly and 12-month rolling calculations of emissions must be kept. A record of the fuel usage rate is required. Monitor and record the total hours of operation and the hours of operation during non-emergencies on a monthly and12-month rolling time period basis.

11 Holland Board of Public Works Page 10 Emergency Diesel-Fueled Fire Pump A non-resettable hours meters to track the operating hours is required. The nameplate capacity shall not exceed 165 hp. Emissions testing or manufacturer certification documentation is required for NOx, CO, and PM emission rates. Monthly and 12-month rolling calculations of emissions must be kept. The company shall monitor and record the total hours of operation and the hours of operation during non-emergencies on a monthly and12-month rolling time period basis. A record of the fuel usage rate is required. CTG/HRSG Trains The maximum design heat input capacity, on a fuel heat input basis, for each CTG/HRSG train shall not exceed 647 MMBtu/hr. Continuous Emission Monitoring System (CEMS) devices to monitor and record NOx and CO emissions from each CTG/HRSG, along with either oxygen or CO 2, are required. Devices to monitor and record the fuel usage rate are required. The net heat rate for both CTG/HRSGs together shall not exceed 8,361 Btu/kW-hr. A device to monitor and record the gross energy output from each CTG/HRSG is required. Testing for PM, PM10, PM2.5 and VOC emission rates from each CTG/HRSG at maximum routine operating conditions, once every five years, is required. Testing to demonstrate compliance with the net heat rate restriction for the CTG/HRSG trains together once every five years, is required. Records on an hourly and 24-hour rolling average basis of the NOx and CO concentration and mass emissions for each CTG/HRSG are required. Records on a monthly 12-month rolling total basis for CO 2 e mass emissions for each CTG/HRSG are required. Records of the hours for startup and shutdown events are required. Two Auxiliary Boilers The maximum design heat input capacity, on a fuel heat input basis, shall not exceed 55 MMBtu/hr for AUXBOILERA and shall not exceed 95 MMBtu/hr for AUXBOILERB. A device to monitor and record the fuel usage rate is required. Emissions testing is required for NOx, CO, PM, PM10, PM2.5, and VOC emission rates from each boiler at maximum routine operating conditions, once every five years and initial operation. A record of the fuel usage rate is required. Records on a monthly and 12-month rolling basis of total CO 2 e mass emissions are required.

12 Holland Board of Public Works Page 11 Federal Regulations Each of the two proposed CTG/HRSG trains will be subject to the NSPS for Stationary Combustion Turbines, 40 CFR Part 60 Subpart KKKK. Also, each auxiliary boiler will be subject to the NSPS for Small Industrial-Commercial-Institutional Steam Generating Units, 40 CFR Part 60 Subpart Dc. The emergency natural gas-fired engine will be subject to the NSPS for Stationary Spark Ignition Internal Combustion Engines, 40 CFR Part 60 Subpart JJJJ. The emergency diesel-fueled fire pump will be subject to the NSPS for Stationary Compression Ignition Internal Combustion Engines, 40 CFR Part 60 Subpart IIII. The draft permit specifies that compliance with certain permit conditions will constitute compliance with the respective NSPS for each emission unit through required emission limits, process/operational restrictions, testing or certification, monitoring/recordkeeping, and reporting. The proposed emergency engines will also be subject to the NESHAP for Stationary Reciprocating Internal Combustion Engines, 40 CFR Part 63 Subpart ZZZZ. Compliance with the requirements of NSPS JJJJ and NSPS IIII constitutes compliance with the NESHAP as the emergency generators subject to the NSPS Subparts JJJJ and IIII have no additional emission limit requirements under the NESHAP. Conclusion Based on the analyses conducted to date, the AQD staff concludes that the proposed project would comply with all applicable state and federal air quality requirements. The AQD staff also concludes that this project, as proposed, would not violate the federal NAAQS or the state and federal PSD increments. Based on these conclusions, the AQD staff has developed draft permit terms and conditions which would ensure that the proposed facility design and operation are enforceable and that sufficient monitoring, recordkeeping, and reporting would be performed by the applicant to determine compliance with these terms and conditions. If the permit application is deemed approvable, the delegated decision maker may determine a need for additional or revised conditions to address issues raised during the public participation process. If you would like additional information about this proposal, please contact Ms. Catherine Asselin, AQD, at

13 Holland Board of Public Works Page 12 State Rule R R R R to R R to R R (2)(b) R R R R and R R to R R R R Appendix 1 STATE AIR REGULATIONS Description of State Air Regulations Requires an Air Use Permit for new or modified equipment that emits, or could emit, an air pollutant or contaminant. However, there are other rules that allow smaller emission sources to be installed without a permit (see Rules through below). Rule also states that the Department can add conditions to a permit to assure the air laws are met. Outlines the permit conditions that are required by the federal Prevention of Significant Deterioration (PSD) Regulations and/or Section 112 of the Clean Air Act. Also, the same types of conditions are added to their permit when a plant is limiting their air emissions to legally avoid these federal requirements. (See the Federal Regulations table for more details on PSD.) New or modified equipment that emits toxic air contaminants must use the Best Available Control Technology for Toxics (T-BACT). The T-BACT review determines what control technology must be applied to the equipment. A T-BACT review considers energy needs, environmental and economic impacts, and other costs. T-BACT may include a change in the raw materials used, the design of the process, or add-on air pollution control equipment. This rule also includes a list of instances where other regulations apply and T-BACT is not required. The ambient air concentration of each toxic air contaminant emitted from the project must not exceed health-based screening levels. Initial Risk Screening Levels (IRSL) apply to cancer-causing effects of air contaminants and Initial Threshold Screening Levels (ITSL) apply to non-cancer effects of air contaminants. These screening levels, designed to protect public health and the environment, are developed by Air Quality Division toxicologists following methods in the rules and U.S. EPA risk assessment guidance. These rules list equipment to processes that have very low emissions and do not need to get an Air Use permit. However, these sources must meet all requirements identified in the specific rule and other rules that apply. Adopts by reference the provisions of 40 CFR to (2002) and 40 CFR to (2002), the federal hazardous air pollutant regulations governing constructed or reconstructed major sources. Limits how air emissions are allowed to look at the end of a stack. The color and intensity of the color of the emissions is called opacity. The particulate emission limits for certain sources are listed. These limits apply to both new and existing equipment. Material collected by air pollution control equipment, such as dust, must be disposed of in a manner, which does not cause more air emissions. Limit the sulfur dioxide emissions from power plants and other fuel burning equipment. Volatile organic compounds (VOCs) are a group of chemicals found in such things as paint solvents, degreasing materials, and gasoline. VOCs contribute to the formation of smog. The rules set VOC limits or work practice standards for existing equipment. The limits are based upon Reasonably Available Control Technology (RACT). RACT is required for all equipment listed in Rules through New equipment that emits VOCs is required to install the Best Available Control Technology (BACT). The technology is reviewed on a case-by-case basis. The VOC limits and/or work practice standards set for a particular piece of new equipment cannot be less restrictive than the Reasonably Available Control Technology limits for existing equipment outlined in Rules through Nitrogen oxide emission limits for larger boilers and stationary internal combustion engines are listed. Prohibits the emission of an air contaminant in quantities that cause injurious effects to human health and welfare, or prevent the comfortable enjoyment of life and property. As an example, a violation may be cited if excessive amounts of odor emissions were found to be preventing residents from enjoying outdoor activities.

14 Holland Board of Public Works Page 13 State Rule R R R R to R R to R Prevention of Significant Deterioration (PSD) Regulations Best Available Control Technology (BACT) R to R and R STATE AIR REGULATIONS Description of State Air Regulations Air pollution control equipment must be installed, maintained, and operated properly. When requested by the Department, a facility must develop and submit a malfunction abatement plan (MAP). This plan is to prevent, detect, and correct malfunctions and equipment failures. A facility is required to notify the Department if a condition arises which causes emissions that exceed the allowable emission rate in a rule and/or permit. Allow the Department to request that a facility test its emissions and to approve the protocol used for these tests. The PSD rules allow the installation and operation of large, new sources and the modification of existing large sources in areas that are meeting the National Ambient Air Quality Standards (NAAQS). The regulations define what is considered a large or significant source, or modification. In order to assure that the area will continue to meet the NAAQS, the permit applicant must demonstrate that it is installing the BACT. By law, BACT must consider the economic, environmental, and energy impacts of each installation on a case-by-case basis. As a result, BACT can be different for similar facilities. In its permit application, the applicant identifies all air pollution control options available, the feasibility of these options, the effectiveness of each option, and why the option proposed represents BACT. As part of its evaluation, the Air Quality Division verifies the applicant s determination and reviews BACT determinations made for similar facilities in Michigan and throughout the nation. Applies to new major stationary sources and major modifications as defined in R These rules contain the permitting requirements for sources located in nonattainment areas that have the potential to emit large amounts of air pollutants. To help the area meet the NAAQS, the applicant must install equipment that achieves the Lowest Achievable Emission Rate (LAER). LAER is the lowest emission rate required by a federal rule, state rule, or by a previously issued construction permit. The applicant must also provide emission offsets, which means the applicant must remove more pollutants from the air than the proposed equipment will emit. This can be done by reducing emissions at other existing facilities. As part of its evaluation, the AQD verifies that no other similar equipment throughout the nation is required to meet a lower emission rate and verifies that proposed emission offsets are permanent and enforceable. Citation Section 109 of the Clean Air Act National Ambient Air Quality Standards (NAAQS) FEDERAL AIR REGULATIONS Description of Federal Air Regulations or Requirements The United States Environmental Protection Agency has set maximum permissible levels for seven pollutants. These NAAQS are designed to protect the public health of everyone, including the most susceptible individuals, children, the elderly, and those with chronic respiratory ailments. The seven pollutants, called the criteria pollutants, are carbon monoxide, lead, nitrogen dioxide, ozone, particulate matter less than 10 microns (PM10), particulate matter less than 2.5 microns (PM2.5), and sulfur dioxide. Portions of Michigan are currently non-attainment for either ozone or PM2.5. Further, in Michigan, State Rules to are used to ensure the public health is protected from other compounds.

15 Holland Board of Public Works Page 14 Citation 40 CFR Prevention of Significant Deterioration (PSD) Regulations Best Available Control Technology (BACT) 40 CFR 60 New Source Performance Standards (NSPS) 40 CFR 63 National Emissions Standards for Hazardous Air Pollutants (NESHAP) Section 112 of the Clean Air Act Maximum Achievable Control Technology (MACT) Section 112g FEDERAL AIR REGULATIONS Description of Federal Air Regulations or Requirements The PSD regulations allow the installation and operation of large, new sources and the modification of existing large sources in areas that are meeting the NAAQS. The regulations define what is considered a large or significant source, or modification. In order to assure that the area will continue to meet the NAAQS, the permit applicant must demonstrate that it is installing BACT. By law, BACT must consider the economic, environmental, and energy impacts of each installation on a case-by-case basis. As a result, BACT can be different for similar facilities. In its permit application, the applicant identifies all air pollution control options available, the feasibility of these options, the effectiveness of each option, and why the option proposed represents BACT. As part of its evaluation, the Air Quality Division verifies the applicant s determination and reviews BACT determinations made for similar facilities in Michigan and throughout the nation. The United States Environmental Protection Agency has set national standards for specific sources of pollutants. These New Source Performance Standards (NSPS) apply to new or modified equipment in a particular industrial category. These NSPS set emission limits or work practice standards for over 60 categories of sources. The United States Environmental Protection Agency has set national standards for specific sources of pollutants. The National Emissions Standards for Hazardous Air Pollutants (NESHAP) (a.k.a. Maximum Achievable Control Technology (MACT) standards) apply to new or modified equipment in a particular industrial category. These NESHAPs set emission limits or work practice standards for over 100 categories of sources. In the Clean Air Act, Congress listed 189 compounds as Hazardous Air Pollutants (HAPS). For facilities which emit, or could emit, HAPS above a certain level, one of the following two requirements must be met: 1) The United States Environmental Protection Agency has established standards for specific types of sources. These Maximum Achievable Control Technology (MACT) standards are based upon the best-demonstrated control technology or practices found in similar sources. 2) For sources where a MACT standard has not been established, the level of control technology required is determined on a case-by-case basis. Notes: An Air Use Permit, sometimes called a Permit to Install, provides permission to emit air contaminants up to certain specified levels. These levels are set by state and federal law, and are set to protect health and welfare. By staying within the levels set by the permit, a facility is operating lawfully, and public health and air quality are protected. The Air Quality Division does not have the authority to regulate noise, local zoning, property values, offsite truck traffic, or lighting. These tables list the most frequently applied state and federal regulations. Not all regulations listed may be applicable in each case. Please refer to the draft permit conditions provided to determine which regulations apply.

16 Holland Board of Public Works Page 15 Appendix 2 Best Available Control Technology Analysis (Michigan Rule and 40 CFR 52.21(j)) A requirement of PSD New Source Review is a Best Available Control Technology (BACT) analysis. The topdown BACT approach per the EPA DRAFT New Source Review Workshop Manual (October 1990) was utilized. The top-down approach considers all available emission reduction options and proceeds in a five-step process as follows: 1. Identify all control technologies; 2. Eliminate technically infeasible options; 3. Rank the remaining control technologies by control effectiveness; 4. Evaluate the most effective controls and document the results; 5. Select BACT (e.g., the most effective option not rejected is BACT). Two (2) Combined Cycle Natural Gas-fired Combustion Turbine Generators (CTG) with Heat Recovery Steam Generators (HRSG) equipped with duct burners for supplemental firing Combined Cycle Combustion Turbine Generators (CTG) The CTG design proposed is an aeroderivative-type turbine. These are smaller units in comparison to the frame-type combustion turbines and have different emission profiles than the frame-type turbines. Typically, the uncontrolled emissions will be higher from an aeroderivate-type turbine. This was taken into account when BACT limits were proposed. The two (2) CTG/HRSG trains are subject to a BACT analysis for the following regulated pollutants: NOx, CO, PM, PM10, PM2.5, VOC, and GHGs (as CO 2 e). The following is a summary of the BACT analysis. BACT for NO x NOx is generated thermally when nitrogen reacts with oxygen in the combustion air in a high temperature environment, and from oxidation of organic nitrogen compounds in the fuel (fuel NO x ). Fuel properties have a significant impact on NO x formation. Pipeline quality natural gas contains free nitrogen, but no fuel bound nitrogen. Holland BPW identified several combustion and post combustion control technologies for the control of NO x emissions from each CTG/HRSG train. The following technologies were identified and evaluated: Combustion and Post Combustion Controls Dry Low-NOx Burners (DLNB) Water or steam injection Selective Catalytic Reduction (SCR) Non-Selective Catalytic Reduction (NSCR) Selective Non-Catalytic Reduction (SNCR) EMx TM (Formerly SCONOx TM ) Xonon Cool Combustion The review of each of these technologies is summarized below. Dry low-nox burners (LNB) are commonly combined with post combustion controls to achieve the lowest NOx emission rates. LNB control fuel and air mixing ratios in the burner of the turbine in order to reduce flame temperature and reduce thermal NOx formation. This technology is considered a technically feasible control alternative and will be the baseline scenario since the proposed turbines will be designed with LNB.

17 Holland Board of Public Works Page 16 Water or steam is injected into the combustion air of the turbine to increase the thermal mass of the combustion flame by dilution. Heat is dissipated and the thermal NOx produced is reduced. Water or steam injection is not compatible with dry low-nox burners, which are considered for this project; however, the technology was carried forward for further evaluation. SCR is a post combustion system that consists of an ammonia injection system and a catalytic reactor. Ammonia is injected into the flue gas where it reacts with NOx in the presence of the catalyst to form molecular nitrogen (N 2 ) and water. This reaction occurs at flue gas temperatures of 400 F to 800 F. The efficiency of the SCR system operation depends on catalyst reactivity, routine replacement of the catalyst, and maintaining a proper ammonia injection rate. This technology is considered a technically feasible control alternative. NSCR is a post combustion system that utilizes a three-way catalytic converter to reduce emissions of NOx, CO, and VOC from the flue gas. No chemical injection is necessary; unburned hydrocarbons are the NOx reducing agent. The reactions occur at flue gas temperatures of 800 F to 1,200 F and minimal oxygen content. This technology can be used in conjunction with an oxidation catalyst for further CO and VOC control. The exhaust gases from the CTG/HRSG trains will be too high in oxygen content for this control technology to be effective. This technology is not considered a technically feasible control alternative. SNCR is a post combustion system that injects ammonia or urea into combustion flue gases to form molecular nitrogen (N 2 ) and water. This reaction occurs at flue gas temperatures of 1,600 F to 2,100 F as the technology does not utilize a catalyst to promote the reaction. The NOx reduction reactions are driven by the thermal decomposition of urea or ammonia and the subsequent chemical reaction reduction of NOx. The technology is less effective at lower levels of uncontrolled NOx. The exhaust gases from the CTG typically range from 800 F to 1,100 F. This technology is not considered a technically feasible control alternative because there is not an appropriate temperature window for ammonia injection and adequate reduction of NOx in the exhaust gases. EMx TM is similar to SCR, except that NOx in the exhaust stream reacts with potassium carbonate (K 2 CO 3 ) to form potassium nitrate (KNO 3 ). This compound is reacted with hydrogen to form gaseous nitrogen (N 2 ), and regenerate the K 2 CO 3. The lower exhaust temperature required for the reactions in the EMx TM to take place is less than that of SCR (300 F verses 600 F to 800 F). The EMx TM system also provides reductions in CO emissions and to a lesser degree, reductions in VOC emissions by oxidation. This technology has not been demonstrated in practice on a larger utility CTG. Therefore, EMx TM is not considered a technically feasible control alternative for this project. Xonon Cool Combustion uses a catalyst instead of a flame in the combustion process, enabling combustion at temperatures below the threshold at which thermal NOx forms. This technology has not been demonstrated in practice on a larger utility CTG. Therefore, Xonon Cool Combustion is not considered a technically feasible control alternative for this project. NSCR, SNCR, EMx TM, and Xonon Cool Combustion were considered not technically feasible for this application. The technically feasible control technologies were ranked by control effectiveness as follows: Control System Expected Effectiveness/Control Efficiency (%) SCR with DLNB SCR with water-steam injection 97 SCR 90 DLNB Water-steam injection 75

18 Holland Board of Public Works Page 17 It is proposed that BACT for NOx is the use of SCR technology and DLNB, together with emission limits at different operating scenarios. It is necessary to include a BACT limit during steady state (normal) operation as well as during startup and shutdown, where combustion is inefficient and emission rates per unit of fuel combusted are significantly elevated compared to normal operation. At low loads, the combustors are not yet operating in lean pre-mix mode which contributes to higher NOx emission rates. During normal operation (loads greater than 50 percent of capacity), BACT is represented by an emission limit of 3 ppmv dry at 15% oxygen based on a 24-hour rolling average and 8.18 pounds per hour based on a 24-hour rolling average for each CTG/HRSG train. During SU/SD operations (loads less than 50 percent of capacity), both CTG/HRSG trains are limited to a total of 635 hours per 12-month rolling time period. BACT is represented by an emission limit of 43.7 pounds per hour during startup and 43.1 pounds per hour during shutdown, both limits are based on an operating hour. All mass emission limits are protective of NAAQS and PSD increment. Compliance with these limits will be monitored using a NOx CEMS and the exhaust gas flow rate. BACT for CO and VOCs CO and VOC emissions result from the incomplete combustion of carbonaceous fuels, such as natural gas. The primary influencing factors for CO and VOC formation are the combustion temperature, turbulence (mixing of fuel and oxygen) and the residence time in the combustion zone. Holland BPW identified combustion and post combustion control technologies for the control of CO and VOC emissions from each CTG/HRSG train. The following technologies were identified for both CO and VOC and were evaluated: Combustion and Post Combustion Controls Oxidation Catalyst Thermal Oxidation NSCR Efficient Combustion NSCR was described above in the NOx BACT discussion. The review of the rest of these technologies is summarized below. Oxidation Catalysts have been applied to combustion turbines and have demonstrated their ability to effectively reduce CO and VOC emissions. They are also commercially available from numerous vendors. A catalyst bed is utilized to oxidize CO and hydrocarbons to CO 2. This reaction can occur over a temperature range of 450 F to 1,200 F. The operating temperature, gas composition, and pressure drop across the catalyst bed are all factors that will affect the efficiency of the oxidation catalyst. This technology is considered a feasible control alternative for this project. Thermal oxidation increases the temperature of the flue gas above the auto-ignition temperature of CO and other hydrocarbons, which is 1,300 F, to induce combustion of flue gas contaminants (CO and VOC). This technology is typically designed for process streams that have high concentrations of VOC. This allows the contaminants to provide a significant portion of the fuel requirements. Relative to the entire exhaust flow, the CTG/HRSG trains will have relatively low concentrations of CO and VOCs. This technology is not considered a technically feasible control alternative for this project. Efficient combustion revolves around operating the equipment properly and must be balanced with the potential increase of NOx emissions that could occur when combustion efficiency is associated with high chamber temperatures. Modern combustion controls are able to reasonably balance this counter-acting relationship.

19 Holland Board of Public Works Page 18 Thermal oxidation and NSCR were considered not technically feasible for this application. The technically feasible control technologies were proposed as BACT and were therefore not ranked. It is proposed that BACT for CO and VOC emissions is oxidation catalyst technology and the use of good combustion control practices together with emission limits. It is necessary to include a BACT limit during steady state (normal) operation and an alternative BACT limit during startup and shutdown, where combustion is inefficient and emission rates per unit of fuel combusted are elevated compared to normal operation. At the very early stages of the startup cycle, the oxidation catalyst is technology limited and it is difficult to accurately measure CO because of specific stack O 2 conditions. During SU/SD events, the add-on oxidation catalyst control technology is not fully functional due to the exhaust gas temperature through the HRSG being less than the temperature necessary for optimal catalyst operation. However, the startup cycle for combustion equipment of this nature requires far less time than other types of combustion processes used to generate electricity. During normal operation (loads greater than 50 percent of capacity), BACT for CO is represented by an emission limit of 4 ppmv dry at 15% oxygen based on a 24-hour rolling average and 5.31 pph based on a 24-hour rolling average for each CTG/HRSG train. During SU/SD operations (loads less than 50 percent of capacity), both CTG/HRSG trains are limited to 635 hours per 12-month rolling time period. BACT, for each CTG/HRSG train, is represented by an emission limit of pph during startup and pph during shutdown, both limits are based on an operating hour. Compliance with the CO limits will be monitored using a CO and diluent CEMS, and the exhaust gas flow rate. For purposes of facilitating emissions measurements during periods of startup and shutdown, the diluent capping procedures of Section of 40 CFR Part 75, Appendix F, may be utilized. During normal operation, BACT for VOC is represented by an emission limit of 4 ppmv dry at 15% oxygen for each CTG/HRSG train. During SU/SD operations, both CTG/HRSG trains are limited to 635 hours per 12- month rolling time period. BACT, for each CTG/HRSG train, is represented by an emission limit of pph during startup and pph during shutdown, both limits are based on an operating hour. Compliance with the VOC limits will be determined through stack testing, and record keeping. Averaging times for the normal operation emission limit will be based on testing protocols. Michigan Air Pollution Control Rule (5) requires that Minimum sample time shall be 60 minutes, which may be continuous or a combination of shorter sampling periods for sources that operate in a cyclic manner. Compliance with the VOC emission limit will be based on a short-term average. BACT for PM, PM10, and PM2.5 Particulate matter emissions from the combustion of natural gas depends on suspended particles in the combustion air, sulfates formed due to sulfur in the fuel, the products of incomplete combustion such as unburned carbon, and metallic oxides from degradation of internal turbine components. PM exists as a solid or liquid at temperatures of approximately 250 F and is considered the filterable or front half of particulate matter. PM10 and PM2.5 each includes both the filterable and condensable fraction of particulate matter and both were evaluated simultaneously. The condensable portion of PM10 and PM2.5 is particulate matter that exists as a solid or liquid at temperatures less than 32 F. It includes substances such as nitrogen compounds and sulfur compounds, which are in a vapor state at high temperatures, acid gases, VOCs, etc., but does not include condensed water vapor. Holland BPW identified several combustion and post combustion control technologies for the control of PM, PM10, and PM2.5 emissions. The following technologies were identified and evaluated:

STATEMENT OF BASIS. For the issuance of Draft Air Permit # 1987-AOP-R4 AFIN:

STATEMENT OF BASIS. For the issuance of Draft Air Permit # 1987-AOP-R4 AFIN: STATEMENT OF BASIS For the issuance of Draft Air Permit # 1987-AOP-R4 1. PERMITTING AUTHORITY: Arkansas Department of Environmental Quality 5301 Northshore Drive North Little Rock, Arkansas 72118-5317

More information

TITLE V OPERATING PERMIT STATEMENT OF BASIS

TITLE V OPERATING PERMIT STATEMENT OF BASIS TITLE V OPERATING PERMIT STATEMENT OF BASIS Facility Name: El Cajon Energy, LLC Title V Application Number: APCD2011-APP-001657 Facility ID: Equipment Address: APCD2009-SITE-06554 222 N. Johnson Ave. Facility

More information

ENGINEERING CALCULATION SHEET AIR RESOURCES DIVISION

ENGINEERING CALCULATION SHEET AIR RESOURCES DIVISION SIC Code: 4911 (Energy Production) DATE: 02/06/2008 Page 1 of 5 DATE APPLICATION RECEIVED: December 14, 2007 (Application # FY07-0259) FACILITY DESCRIPTION Pinetree Power-Tamworth, Inc. (the Permittee)

More information

RELEASE POINT TYPE Enter or select one of the following stack/emission point release orientation: downward

RELEASE POINT TYPE Enter or select one of the following stack/emission point release orientation: downward EMISSION SOURCE (Internal Combustion Engines) Instructions for Form B2-G Form B2-G should be completed for all generators. Make as many copies of the form as necessary. Attach all calculations and assumptions

More information

PSD Background Presentation

PSD Background Presentation PSD Background Presentation May 3 rd 2011 John Holmes 1 Prevention of Significant Deterioration (PSD): Overview Federal preconstruction permitting applies to new major stationary sources and major modifications

More information

Emergency Engine and Turbine Requirements

Emergency Engine and Turbine Requirements 1.0 Purpose and Applicability 1.1 The purpose of these guidelines is to identify the processes and requirements that must be followed to ensure compliance with the Massachusetts Department of Environmental

More information

Oklahoma Department of Environmental Quality Air Quality Division

Oklahoma Department of Environmental Quality Air Quality Division Oklahoma Department of Environmental Quality Air Quality Division BART Application Analysis January 19, 2010 COMPANY: FACILITY: FACILITY LOCATION: TYPE OF OPERATION: Units REVIEWER: AEP- Public Service

More information

STATE OF MINNESOTA MINNESOTA POLLUTION CONTROL AGENCY

STATE OF MINNESOTA MINNESOTA POLLUTION CONTROL AGENCY p-ear2-80b STATE OF MINNESOTA MINNESOTA POLLUTION CONTROL AGENCY IN THE MATTER OF THE DECISION ON THE NEED FOR AN ENVIRONMENTAL IMPACT STATEMENT FOR THE PROPOSED REG ALBERT LEA, LLC PROJECT FREEBORN COUNTY

More information

State of Utah. Department of Environmental Quality DAQE-AN October 26, 2009

State of Utah. Department of Environmental Quality DAQE-AN October 26, 2009 Department of Environmental Quality State of Utah GARY R. HERBERT Governor Amanda Smith Executive Director DIVISION OF AIR QUALITY Cheryl Heying Director GREG BELL Lieutenant Governor DAQE-AN0141510002-09

More information

Excerpt of Thermal Power Guidelines for New Plants

Excerpt of Thermal Power Guidelines for New Plants Excerpt of Thermal Power Guidelines for New Plants The following is an excerpt of the Thermal Power guidelines for New Plants, a complete version of which is found in the Pollution Prevention and Abatement

More information

POTENTIAL TO EMIT LIMITATIONS FOR PART 70 SOURCES. (Adopted 6/15/1995, revised 1/18/2001 and 1/20/2011)

POTENTIAL TO EMIT LIMITATIONS FOR PART 70 SOURCES. (Adopted 6/15/1995, revised 1/18/2001 and 1/20/2011) RULE 370. POTENTIAL TO EMIT LIMITATIONS FOR PART 70 SOURCES. (Adopted 6/15/1995, revised 1/18/2001 and 1/20/2011) A. Applicability 1. General Applicability: This Rule shall apply to any stationary source

More information

TECHNICAL EVALUATION AND PRELIMINARY DETERMINATION. Oleander Power Project, L.P. 190 MW Simple Cycle Gas Turbine

TECHNICAL EVALUATION AND PRELIMINARY DETERMINATION. Oleander Power Project, L.P. 190 MW Simple Cycle Gas Turbine TECHNICAL EVALUATION AND PRELIMINARY DETERMINATION, L.P. 190 MW Simple Cycle Gas Turbine Cocoa, Brevard County DEP File No. 0090180-003-AC () Florida Department of Environmental Protection Division of

More information

FERC PDF (Unofficial) 9/29/2014 4:29:38 PM. Title V Permit Modification Addendum Submitted June 23, 2014

FERC PDF (Unofficial) 9/29/2014 4:29:38 PM. Title V Permit Modification Addendum Submitted June 23, 2014 Title V Permit Modification Addendum Submitted June 23, 2014 REVISED TITLE V PERMIT MODIFICATION APPLICATION Algonquin Gas Transmission, LLC > Stony Point Compressor Station Algonquin Incremental Market

More information

Air Emissions Permitting Considerations for an Integrated Gasification Combined Cycle (IGCC) Unit Potentially Located in the State of Delaware

Air Emissions Permitting Considerations for an Integrated Gasification Combined Cycle (IGCC) Unit Potentially Located in the State of Delaware Air Emissions Permitting Considerations for an Integrated Gasification Combined Cycle (IGCC) Unit Potentially Located in the State of Delaware Center for the Inland Bays Scientific & Technical Advisory

More information

Ambient Air Quality Analysis (Attachment L)

Ambient Air Quality Analysis (Attachment L) Ambient Air Quality Analysis (Attachment L) Killingly Energy Center May 2016 Prepared for: NTE Connecticut, LLC 24 Cathedral Place, Suite 300 Saint Augustine, FL 32084 Prepared by: Tetra Tech, Inc. 2 Lan

More information

PRIMARY OR ALTERNATIVE OPERATING SCENARIO

PRIMARY OR ALTERNATIVE OPERATING SCENARIO EMISSION SOURCE (Fuel Combustion Source) Instructions for Form B2 Form B2 should be completed for all fuel combustion emission sources (e.g., generators, boilers, burn-off ovens, bakeon ovens, bakery ovens,

More information

STATEMENT OF BASIS. NAICS Description: All Other Miscellaneous Chemical Product and Preparation Manufacturing NAICS Code:

STATEMENT OF BASIS. NAICS Description: All Other Miscellaneous Chemical Product and Preparation Manufacturing NAICS Code: STATEMENT OF BASIS For the issuance of Draft Air Permit # 0196-AR-9 1. PERMITTING AUTHORITY: Arkansas Department of Environmental Quality 5301 Northshore Drive North Little Rock, Arkansas 72118-5317 2.

More information

DRAFT AIR EMISSION PERMIT NO Major Amendment IS ISSUED TO. Miller Milling Co LLC

DRAFT AIR EMISSION PERMIT NO Major Amendment IS ISSUED TO. Miller Milling Co LLC DRAFT AIR EMISSION PERMIT NO. 07900006 004 Major Amendment IS ISSUED TO Miller Milling Co LLC Miller Milling Co LLC 100 2nd Avenue Southwest New Prague, Le Sueur County, MN 56071 The emission units, control

More information

CONSTRUCTION PERMIT. DATE ISSUED: January 7, 2015 ISSUED TO: Martin Marietta Materials, Inc.

CONSTRUCTION PERMIT. DATE ISSUED: January 7, 2015 ISSUED TO: Martin Marietta Materials, Inc. COLORADO DEPARTMENT OF PUBLIC HEALTH AND ENVIRONMENT AIR POLLUTION CONTROL DIVISION TELEPHONE: (303) 692-3150 PERMIT NO: CONSTRUCTION PERMIT DATE ISSUED: January 7, 2015 ISSUED TO: 13LR2446 Issuance 1

More information

TruePeak TDLS200. NH 3 Slip Measurement. <Document Number> Copyright Yokogawa Electric Corporation <date/time>

TruePeak TDLS200. NH 3 Slip Measurement. <Document Number> Copyright Yokogawa Electric Corporation <date/time> TruePeak TDLS200 NH 3 Slip Measurement One Background One Two Three Four Gas-Fired Installations The SCR control system must be able to perform in a range of conditions Flue gases from

More information

ADEQ NON-CRITERIA POLLUTANT CONTROL STRATEGY Revised April 2015

ADEQ NON-CRITERIA POLLUTANT CONTROL STRATEGY Revised April 2015 ADEQ NON-CRITERIA POLLUTANT CONTROL STRATEGY Revised April 2015 BACKGROUND Under the federal Clean Air Act, EPA is obligated to establish ambient air quality standards for 6 commonly found criteria pollutants:

More information

Oil and Gas Regulations and TCEQ Lessons Learned

Oil and Gas Regulations and TCEQ Lessons Learned Oil and Gas Regulations and TCEQ Lessons Learned City of Dallas Gas Drilling Task Force Meeting July 26, 2011 Keith Sheedy, P.E. Technical Advisor Chief Engineer s Office Texas Commission on Environmental

More information

BACKGROUND DOCUMENT PROPOSED REVISION TO AP-42 EMISSION FACTORS FOR ESTIMATING PM 2.5 EMISSIONS FROM GAS-FIRED COMBUSTION UNITS

BACKGROUND DOCUMENT PROPOSED REVISION TO AP-42 EMISSION FACTORS FOR ESTIMATING PM 2.5 EMISSIONS FROM GAS-FIRED COMBUSTION UNITS BACKGROUND DOCUMENT PROPOSED REVISION TO AP-42 EMISSION FACTORS FOR ESTIMATING PM 2.5 EMISSIONS FROM GAS-FIRED COMBUSTION UNITS Submitted by: Karin Ritter American Petroleum Institute 1220 L Street NW

More information

DRAFT PROPOSED PERMIT. San Diego County Air Pollution Control District Old Grove Rd San Diego, CA (858)

DRAFT PROPOSED PERMIT. San Diego County Air Pollution Control District Old Grove Rd San Diego, CA (858) DRAFT PROPOSED PERMIT San Diego County Air Pollution Control District 10124 Old Grove Rd San Diego, CA 92131-1649 (858) 586-2600 TITLE V OPERATING PERMIT 960392 Issued To: Applied Energy North Island,

More information

State of New Hampshire Department of Environmental Services Air Resources Division. Temporary Permit

State of New Hampshire Department of Environmental Services Air Resources Division. Temporary Permit State of New Hampshire Department of Environmental Services Air Resources Division Temporary Permit Permit No: FP-T-0152 Date Issued: July 18, 2007 Administrative Permit Amendment: June 11, 2008 This certifies

More information

PUBLIC PARTICIPATION DOCUMENTS For United States Steel Corporation Ecorse, Wayne County SRN: A7809

PUBLIC PARTICIPATION DOCUMENTS For United States Steel Corporation Ecorse, Wayne County SRN: A7809 STATE OF MICHIGAN Rick Snyder, Governor DEPARTMENT OF ENVIRONMENTAL QUALITY AIR QUALITY DIVISION CONSTITUTION HALL 525 WEST ALLEGAN STREET P.O. BOX 30260 LANSING, MICHIGAN 48909-7760 www.michigan.gov/air

More information

Criteria Pollutants. Sulfur Dioxide (SO 2 ) Nitrogen Oxides (NOx)

Criteria Pollutants. Sulfur Dioxide (SO 2 ) Nitrogen Oxides (NOx) 1) Sulfur dioxide 2) Nitrogen oxides 3) Carbon monoxide 4) Ozone 5) Particulates 6) Lead Criteria Pollutants Sulfur Dioxide (SO 2 ) SO 2 is a colorless gas that is formed from the combustion of sulfur-containing

More information

Air Permitting for Major Sources/Title V (Part 2)

Air Permitting for Major Sources/Title V (Part 2) Air Permitting for Major Sources/Title V (Part 2) Bob Hodanbosi Bob.hodanbosi@epa.state.oh.us Mike Hopkins Mike.hopkins@epa.state.oh.us Introduction Who, what, where, why of Title V permitting How can

More information

NEW JERSEY STATE DEPARTMENT OF ENVIRONMENTAL PROTECTION NEW JERSEY ADMINISTRATIVE CODE TITLE 7 CHAPTER 27 SUBCHAPTER 10. Sulfur in Solid Fuels

NEW JERSEY STATE DEPARTMENT OF ENVIRONMENTAL PROTECTION NEW JERSEY ADMINISTRATIVE CODE TITLE 7 CHAPTER 27 SUBCHAPTER 10. Sulfur in Solid Fuels NEW JERSEY STATE DEPARTMENT OF ENVIRONMENTAL PROTECTION NEW JERSEY ADMINISTRATIVE CODE TITLE 7 CHAPTER 27 SUBCHAPTER 10 Sulfur in Solid Fuels TABLE OF CONTENTS Section Page REGULATORY HISTORY... 2 7:27-10.1

More information

47.0 GOOD ENGINEERING PRACTICE STACK HEIGHT

47.0 GOOD ENGINEERING PRACTICE STACK HEIGHT 47.0 GOOD ENGINEERING PRACTICE STACK HEIGHT 47.1 General Provisions A. This section provides that the degree of emission limitation required of any source for control of any air pollutant must not be affected

More information

GASP comments regarding Air Quality Plan Approval C - Tenaska Pennsylvania Partners, LLC Westmoreland Generating Station

GASP comments regarding Air Quality Plan Approval C - Tenaska Pennsylvania Partners, LLC Westmoreland Generating Station Via Email February 23, 2015 Pennsylvania Dept. of Environmental Protection Air Quality Program 400 Waterfront Drive Pittsburgh, PA, 15222 asandy@pa.gov GASP comments regarding Air Quality Plan Approval

More information

YOLO-SOLANO AIR QUALITY MANAGEMENT DISTRICT 1947 Galileo Court, Suite 103; Davis, CA Phone (530) ; Fax (530)

YOLO-SOLANO AIR QUALITY MANAGEMENT DISTRICT 1947 Galileo Court, Suite 103; Davis, CA Phone (530) ; Fax (530) YOLO-SOLANO AIR QUALITY MANAGEMENT DISTRICT 1947 Galileo Court, Suite 103; Davis, CA 95618 Phone (530)757-3650; Fax (530)757-3670 AUTHORITY TO CONSTRUCT (ATC) APPLICATION A separate application must be

More information

New Source Review Reform: What Lies Ahead

New Source Review Reform: What Lies Ahead New Source Review Reform: What Lies Ahead Presented at: Flexible Packaging Association 2004 Environmental Summit January 23, 2004 Ken Weiss, P.E. DEE, Director, Air Quality Services ERM ken.weiss@erm.com

More information

Clean Air Act History

Clean Air Act History Clean Air Act Compliance Clean Air Act Compliance Clean Air Act History 1940s serious smog in LA, CA and Donora, PA raised concerns about air quality. 1955, Air Pollution Control Act was the 1st national

More information

6.1 INTRODUCTION 6.2 REGULATORY FRAMEWORK NATIONAL AMBIENT AIR QUALITY STANDARDS COMPLIANCE STATUS TRANSPORTATION CONFORMITY

6.1 INTRODUCTION 6.2 REGULATORY FRAMEWORK NATIONAL AMBIENT AIR QUALITY STANDARDS COMPLIANCE STATUS TRANSPORTATION CONFORMITY Chapter 6 Air Quality 6.1 INTRODUCTION This chapter presents a project-level analysis of the potential for air quality impacts that could result from mobile and stationary sources of air emissions generated

More information

Minor Source BAT Programs

Minor Source BAT Programs Minor Source BAT Programs Ali Mirzakhalili, P.E. Director DE Division of Air Quality NACAA JOINT PERMITTING AND ENFORCEMENT WORKSHOP December 9 11, 2014 Major Source Thresholds Pollutant Nonattainment

More information

CHAPTER 6: AIR EMISSIONS

CHAPTER 6: AIR EMISSIONS This chapter summarizes federal air emissions regulations for petroleum storage tanks and bulk gasoline terminals. Federal and state permitting requirements are summarized, as well as other general state

More information

Statement of Basis for Frederickson Power LP (Frederickson)

Statement of Basis for Frederickson Power LP (Frederickson) Frederickson Power LP (Frederickson) I. PURPOSE OF THIS STATEMENT OF BASIS This document summarizes the legal and factual bases for the air operating permit conditions for Frederickson Power LP at Frederickson

More information

Controlling NOx and other Engine Emissions

Controlling NOx and other Engine Emissions Controlling NOx and other Engine Emissions Extensive Emissions Control Experience in Stationary Diesel and Natural Gas Engines Distributed Power Generation Cogeneration Plants (CHP) Gas Compression & Transmission

More information

BOILER/HEATER < 5 MMBTU BACT Size: Small Emitter BACT (PTE < 10 lb/day) BOILER. BACT Determination Information

BOILER/HEATER < 5 MMBTU BACT Size: Small Emitter BACT (PTE < 10 lb/day) BOILER. BACT Determination Information DRAFT SMAQMD CLEARINGHOUSE CATEGORY: BOILER/HEATER < 5 MMBTU Size: Small Emitter (PTE < 10 lb/day) BOILER Determination Number: 136 Determination Date: 1/25/2017 Equipment Information Permit Number: N/A

More information

New Source Review (NSR) Program Review Questionnaire May 14, 2003

New Source Review (NSR) Program Review Questionnaire May 14, 2003 New Source Review (NSR) Program Review Questionnaire May 14, 2003 Note: This questionnaire does not address implementation of changes made to the major NSR rules in EPA s rulemaking on December 31, 2002.

More information

Whiting Business Unit

Whiting Business Unit Whiting Business Unit ENVIRONMENTAL STATEMENT FOR YEAR 2015 (Review of Y2014 performance) Introduction Recognizing the complex nature of petroleum refining operations and to ensure that we meet our stated

More information

Regulation I Rule 104 Prohibitions

Regulation I Rule 104 Prohibitions Regulation I Rule 104 Prohibitions The content of this Rule was first adopted as part of Regulation I in 1982. The current version was adopted by the Governing Board via Resolution 2015-9 on. TABLE OF

More information

DEPARTMENT OF ENVIRONMENTAL PROTECTION BUREAU OF AIR QUALITY

DEPARTMENT OF ENVIRONMENTAL PROTECTION BUREAU OF AIR QUALITY DEPARTMENT OF ENVIRONMENTAL PROTECTION BUREAU OF AIR QUALITY DOCUMENT NUMBER: 275-2101-007 TITLE: EFFECTIVE DATE: AUTHORITY: POLICY: PURPOSE: APPLICABILITY: Best Available Technology and Other Permitting

More information

EXAMPLE: TEST PLAN FOR SOLVENT BASED PRINTING & COATING PROCESS SOURCES

EXAMPLE: TEST PLAN FOR SOLVENT BASED PRINTING & COATING PROCESS SOURCES EXAMPLE: TEST PLAN FOR SOLVENT BASED PRINTING & COATING PROCESS SOURCES Proposed test date(s): (Test plan postmark or e-mail date triggers 30 day notification period) PART I. GENERAL INFORMATION 1. Name

More information

Single-Source Impacts on Secondary PM 2.5 Formation A Case Study

Single-Source Impacts on Secondary PM 2.5 Formation A Case Study Single-Source Impacts on Secondary PM 2.5 Formation A Case Study Midwest Environmental Compliance Conference Joe Stolle, PE, Senior Environmental Engineer Wendy Vit, PE, Senior Environmental Engineer May

More information

Post Combustion CO 2 Capture Scale Up Study

Post Combustion CO 2 Capture Scale Up Study Post Combustion CO 2 Capture Scale Up Study Prachi Singh and Mike Haines International Greenhouse Gas R&D programme 6 th International Conference on Clean Coal Technologies (CCT 2013) 12-16 th May 2013

More information

Title V. Model General Permit Template SERIES 1 FLARES. Template # SJV-FL-1-1

Title V. Model General Permit Template SERIES 1 FLARES. Template # SJV-FL-1-1 Title V Model General Permit Template SERIES 1 FLARES Template # SJV-FL-1-1 nonassisted, air-assisted, or steam-assisted elevated open flares actual emissions less than 20 tons VOC per year used to comply

More information

Greenhouse Gas Regulation (new Federal)

Greenhouse Gas Regulation (new Federal) Mercury & Air Toxics (MATS) Interstate Transport (CAIR/CSAPR) Regional Haze/Visibility Portland Cement NESHAP Greenhouse Gas Regulation (new Federal) Mercury & Air Toxics (MATS) Finalized December 2011

More information

Limiting Potential to Emit (PTE) in New Source Review (NSR) Permitting

Limiting Potential to Emit (PTE) in New Source Review (NSR) Permitting EPA Mid-Atlantic Air Protection, available at http://www.epa.gov/reg3artd/permitting/limitptemmo.htm (last visited April 8, 2014) Limiting Potential to Emit (PTE) in New Source Review (NSR) Permitting

More information

BART DETERMINATION REPORT AMERICAN ELECTRIC POWER COMANCHE POWER STATION UNITS 1 AND 2

BART DETERMINATION REPORT AMERICAN ELECTRIC POWER COMANCHE POWER STATION UNITS 1 AND 2 BART DETERMINATION REPORT AMERICAN ELECTRIC POWER COMANCHE POWER STATION UNITS 1 AND 2 Prepared by: N.N. Dharmarajan Vern Choquette Principal Consultant Eugene Chen, PE Senior Consultant Jeremy Townley

More information

11/10/2014 Oklahoma s SIP Submittal Infrastructure Checklist 2010 Primary Sulfur Dioxide (SO 2 ) NAAQS Update 1

11/10/2014 Oklahoma s SIP Submittal Infrastructure Checklist 2010 Primary Sulfur Dioxide (SO 2 ) NAAQS Update 1 Oklahoma s State Implementation Plan (SIP) Submittal Infrastructure Checklist CAA 110(a)(2)(A)-(M) Requirements in the Current SIP or Pending SIP Revisions Updated for the 2010 Primary Sulfur Dioxide (SO

More information

6NYCRR Part 212 Process Operations

6NYCRR Part 212 Process Operations 1 6NYCRR Part 212 Process Operations The Evaluation of Public Health & Environmental Impacts Permitting Sources of Air Pollution From Process Operations Air & Waste Management Association Meeting Niagara

More information

Prevention of Significant Deterioration Permit Application Canal Unit 3

Prevention of Significant Deterioration Permit Application Canal Unit 3 Prevention of Significant Deterioration Permit Application Canal Unit 3 Canal Generating Station Sandwich, MA Updated through Supplement No. 2 November 2016 Prepared for: NRG Canal 3 Development LLC 9

More information

AIR PERMITS FORM 805 APPLICATION

AIR PERMITS FORM 805 APPLICATION PERMIT FORMS PURSUANT TO REGULATIONS FOR THE CONTROL AND ABATEMENT OF AIR POLLUTION COMMONWEALTH OF VIRGINIA DEPARTMENT OF ENVIRONMENTAL QUALITY AIR PERMITS FORM 805 APPLICATION FEDERAL OPERATING PERMIT

More information

AIR EMISSION PERMIT NO IS ISSUED TO. Van Hoven Company, Inc.

AIR EMISSION PERMIT NO IS ISSUED TO. Van Hoven Company, Inc. AIR EMISSION PERMIT NO. 03700070-001 IS ISSUED TO Van Hoven Company, Inc. VAN HOVEN COMPANY, INC. 505 Hardman Avenue South South Saint Paul, Dakota County, Minnesota 55075-2413 The emission units, control

More information

Topsoe s Emission Management Solution--DeNOx

Topsoe s Emission Management Solution--DeNOx Topsoe s Emission Management Solution--DeNOx Presented by : 1 SACHIN PANWAR Table of Content Haldor Topsoe in Brief Topsoe Solution Range Topsoe Environmental solution. Catalytic Filtration technology

More information

Potential to Emit Fact Sheet: What is Potential to Emit (PTE)?

Potential to Emit Fact Sheet: What is Potential to Emit (PTE)? Potential to Emit Fact Sheet: What is Potential to Emit (PTE)? PTE is defined as the maximum capacity of a stationary source to emit any air pollutant under its physical and operational design. Thus, your

More information

Integrated CHP Using Ultra-Low-NOx Supplemental Firing

Integrated CHP Using Ultra-Low-NOx Supplemental Firing Integrated CHP Using Ultra-Low-NOx Supplemental Firing David Cygan and Derek Wissmiller, Gas Technology Institute Gearoid Foley, Integrated CHP Systems Corporation ABSTRACT The objective of the work presented

More information

NO2, SO2, PM2.5, Oh my!?! Information Session EPA R/S/L Modelers Workshop May 10, 2010

NO2, SO2, PM2.5, Oh my!?! Information Session EPA R/S/L Modelers Workshop May 10, 2010 NO2, SO2, PM2.5, Oh my!?! Information Session EPA R/S/L Modelers Workshop May 10, 2010 Purpose & Outline Provide background and updates on permit modeling processes and technical aspects related to new

More information

ENGINEERING ANALYSIS

ENGINEERING ANALYSIS FACILITY HISTORY ENGINEERING ANALYSIS Sklar Exploration Company, LLC (Sklar) operates Oil & Gas Production Area No. 6 (Area 6) under SMOP Nos. 502-003-X00 and 502-003-X002 in northern Escambia County,

More information

ARE Fall 2005 Lecture Slides - Clean Air Act - Part 2 (October 12, 2005)

ARE Fall 2005 Lecture Slides - Clean Air Act - Part 2 (October 12, 2005) ARE309 Fall 2005 Class 8 (October 12) Clean Air Act Part 2 Reading Assignments: Salzman & Thompson, Chapter 4 (pages 85-102) Case: American Trucking Tonight Reading Assignment Quiz #8 (Hand In) Guest:

More information

Complying with 1-Hour NO2 NAAQS

Complying with 1-Hour NO2 NAAQS Complying with 1-Hour NO2 NAAQS SESHA Hill Country Chapter November 16, 2010 Brett Jay Davis, PE Zephyr Environmental Corporation bdavis@zephyrenv.com, 512 879-6628 Presentation Outline 1. NO2 NAAQS What

More information

APPENDIX A TECHNICAL SUPPLEMENTS

APPENDIX A TECHNICAL SUPPLEMENTS APPENDIX A TECHNICAL SUPPLEMENTS Disclaimer The Emissions Assessment Section (EAS) has developed technical supplements for several common emission sources. The supplements are intended to help you accurately

More information

ENERGY EFFICIENCY AND EMISSION REDUCTION OF TPM, PM 2.5, AND SO 2 FROM NATURAL GAS AND FUEL OIL FIRED BOILER EXHAUSTS

ENERGY EFFICIENCY AND EMISSION REDUCTION OF TPM, PM 2.5, AND SO 2 FROM NATURAL GAS AND FUEL OIL FIRED BOILER EXHAUSTS ENERGY EFFICIENCY AND EMISSION REDUCTION OF TPM, PM 2.5, AND SO 2 FROM NATURAL GAS AND FUEL OIL FIRED BOILER EXHAUSTS Robert W. Triebe, M.A.Sc., P.Eng. CTO, Thermal Energy International Inc. Robert A.

More information

Note: The definition of "photochemically reactive material" is based upon OAC rule (C)(5).

Note: The definition of photochemically reactive material is based upon OAC rule (C)(5). ADDITIONAL TERMS AND CONDITIONS 1. VISIBLE EMISSION LIMIT Visible particulate emissions from any stack shall not exceed 20 per cent opacity, as a 6-minute average, except for a period of 6 consecutive

More information

Technical Support Document

Technical Support Document Bureau of Air Quality Technical Support Document General Plan Approval and General Operating Permit for Unconventional Natural Gas Well Site Operations and Remote Pigging Stations (BAQ- GPA/GP-5A) and

More information

STATEMENT OF BASIS. For the issuance ofdraft Air Permit # 1140-AOP-R4 AFIN: PERMITTING AUTHORITY:

STATEMENT OF BASIS. For the issuance ofdraft Air Permit # 1140-AOP-R4 AFIN: PERMITTING AUTHORITY: STATEMENT OF BASIS For the issuance ofdraft Air Permit # 1140-AOP-R4 1. PERMITTING AUTHORITY: Arkansas Department ofenvironmental Quality 5301 Northshore Drive North Little Rock, Arkansas 72118-5317 2.

More information

ALTERNATIVE EMISSIONS REDUCTION PLANS AND AUTHORIZATIONS

ALTERNATIVE EMISSIONS REDUCTION PLANS AND AUTHORIZATIONS SUBCHAPTER 11. ALTERNATIVE EMISSIONS REDUCTION PLANS AND AUTHORIZATIONS Section 252:100-11-1. Purpose 252:100-11-2. Definitions 252:100-11-3. Applicability 252:100-11-4. Application for alternative emissions

More information

Advances in NOx Compliance Testing with Portable Electrochemical Analyzers

Advances in NOx Compliance Testing with Portable Electrochemical Analyzers Advances in NOx Compliance Testing with Portable Electrochemical Analyzers LADCO Workshop: Emission Control and Measurement Technology for Industrial Sources March 24-25, 2009 Craig McKim, Emission Division

More information

COMMONWEALTH OF VIRGINIA STATE AIR POLLUTION CONTROL BOARD REGULATIONS FOR THE CONTROL AND ABATEMENT OF AIR POLLUTION

COMMONWEALTH OF VIRGINIA STATE AIR POLLUTION CONTROL BOARD REGULATIONS FOR THE CONTROL AND ABATEMENT OF AIR POLLUTION COMMONWEALTH OF VIRGINIA STATE AIR POLLUTION CONTROL BOARD REGULATIONS FOR THE CONTROL AND ABATEMENT OF AIR POLLUTION 9VAC5 CHAPTER 30. AMBIENT AIR QUALITY STANDARDS. 9VAC5-30-10. General. 9VAC5-30-15.

More information

SAN JOAQUIN VALLEY UNIFIED AIR POLLUTION CONTROL DISTRICT FINAL DRAFT STAFF REPORT PROPOSED AMENDMENTS TO RULE 2020 (EXEMPTIONS) November 18, 2014

SAN JOAQUIN VALLEY UNIFIED AIR POLLUTION CONTROL DISTRICT FINAL DRAFT STAFF REPORT PROPOSED AMENDMENTS TO RULE 2020 (EXEMPTIONS) November 18, 2014 SAN JOAQUIN VALLEY UNIFIED AIR POLLUTION CONTROL DISTRICT FINAL DRAFT STAFF REPORT PROPOSED AMENDMENTS TO RULE 2020 (EXEMPTIONS) November 18, 2014 Prepared by: Jim Swaney, Permit Services Manager Reviewed

More information

AIR EMISSION PERMIT NO IS ISSUED TO

AIR EMISSION PERMIT NO IS ISSUED TO AIR EMISSION PERMIT NO. 06100001-011 IS ISSUED TO Blandin Paper Company/Minnesota Power Rapids Energy Center/Minnesota Power 115 1st Street Southwest Grand Rapids, Itasca County, MN 55744 The emission

More information

IA-01 Insignificant Activities Required to be Listed

IA-01 Insignificant Activities Required to be Listed IA-01 Insignificant Activities Required to be Listed Air Quality Permit Program Doc Type: Permit Application Instructions on Page 2 1a) AQ Facility ID No.: 1b) AQ File No.: 2) Facility Name: 3) Check and

More information

AIR DISPERSION MODELING

AIR DISPERSION MODELING Click to edit Master title style AIR DISPERSION MODELING Use of AERMOD for NAAQS Area Designations and State Implementation Plan Submittals SPEAKER Stewart McCollam DATE February 10, 2016 USE OF AERMOD

More information

Comments on Draft Permit #12-POY-079. FTS International Proppants, LLC. Acadia, Trempealeau, Wisconsin. March 15, 2013

Comments on Draft Permit #12-POY-079. FTS International Proppants, LLC. Acadia, Trempealeau, Wisconsin. March 15, 2013 Comments on Draft Permit #12-POY-079 FTS International Proppants, LLC Acadia, Trempealeau, Wisconsin March 15, 2013 FTS International Proppants, LLC has applied for an air pollution control construction

More information

CAPCOA Air Toxic Hot Spots Program

CAPCOA Air Toxic Hot Spots Program CAPCOA Air Toxic Hot Spots Program Facility Prioritization Guidelines Prepared by: California Air Pollution Control Officers Association (CAPCOA) Air Toxics and Risk Managers Committee (TARMAC) August

More information

Major Air Pollutants

Major Air Pollutants Major Air Pollutants 1 Particulate Matter Particulate refers to all substances that are not gases. It can be suspended droplets / solid particles / mixture of two. Size: 100 µm to 0.1 µm and less. Particulates

More information

ABB Measurement & Analytics Monitoring cement plant stack emissions using FTIR

ABB Measurement & Analytics Monitoring cement plant stack emissions using FTIR White paper WP/ANALYTICAL/002 EN ABB Measurement & Analytics Monitoring cement plant stack emissions using FTIR ABB FTIR CEMS analyzer successfully monitors cement plant stack emissions in extensive field

More information

FACILITY PROFILE. New Brunswick Power Corporation for the Belledune Thermal Generating Station

FACILITY PROFILE. New Brunswick Power Corporation for the Belledune Thermal Generating Station FACILITY PROFILE New Brunswick Power Corporation for the Belledune Thermal Generating Station Prepared by: Industrial Processes Section, Impact Management Branch Department of Environment and Local Government

More information

ALLEGHENY COUNTY HEALTH DEPARTMENT AIR QUALITY PROGRAM

ALLEGHENY COUNTY HEALTH DEPARTMENT AIR QUALITY PROGRAM Universal Stainless TVOP Technical Support Document Page 1 Appendix ALLEGHENY COUNTY HEALTH DEPARTMENT AIR QUALITY PROGRAM May 26, 2017 SUBJECT: Review of Application Title V Operating Permit Renewal Universal

More information

Clean Air Act. Compliance

Clean Air Act. Compliance Clean Air Act Compliance Learning Objectives Understand the basic history and structure of the Clean Air Act Recognize the types of projects that do and do not trigger CAA compliance, and when to hire

More information

natcom burner solutions Advanced burner technology for stringent emissions requirements

natcom burner solutions Advanced burner technology for stringent emissions requirements natcom burner solutions Advanced burner technology for stringent emissions requirements The benchmark of the industry Our Technological Edge HyperMix TM technology for ultra-low NOx and CO with compact

More information

MEMORANDUM June 30, Phillip Fielder, P.E., Permits and Engineering Group Manager

MEMORANDUM June 30, Phillip Fielder, P.E., Permits and Engineering Group Manager DRAFT OKLAHOMA DEPARTMENT OF ENVIRONMENTAL QUALITY AIR QUALITY DIVISION MEMORANDUM June 30, 2011 TO: THROUGH: THROUGH: THROUGH: FROM: SUBJECT: Phillip Fielder, P.E., Permits and Engineering Group Manager

More information

MEMORANDUM December 9, Phillip Fielder, P.E., Permits and Engineering Group Manager, Air Quality Division

MEMORANDUM December 9, Phillip Fielder, P.E., Permits and Engineering Group Manager, Air Quality Division OKLAHOMA DEPARTMENT OF ENVIRONMENTAL QUALITY AIR QUALITY DIVISION DRAFT MEMORANDUM December 9, 2008 TO: THROUGH: THROUGH: THROUGH: FROM: SUBJECT: Phillip Fielder, P.E., Permits and Engineering Group Manager,

More information

Emission Challenges in Cement Making due to alternative Fuels

Emission Challenges in Cement Making due to alternative Fuels Emission Challenges in Cement Making due to alternative Fuels March 2017 / Carl-Henrik Persson Yara Environmental Technologies AB carl-henrik.persson@yara.com Presentation Contents Yara s start in environmental

More information

MINNESOTA POLLUTION CONTROL AGENCY RMAD and Industrial Divisions Environment & Energy Section; Air Quality Permits Section

MINNESOTA POLLUTION CONTROL AGENCY RMAD and Industrial Divisions Environment & Energy Section; Air Quality Permits Section 001 p-bp15-01-02a 002 003 004 005 MINNESOTA POLLUTION CONTROL AGENCY RMAD and Industrial Divisions Environment & Energy Section; Air Quality Permits Section The University of Minnesota Twin Cities Combined

More information

POLLUTION FROM MOTOR VEHICLES

POLLUTION FROM MOTOR VEHICLES POLLUTION FROM MOTOR VEHICLES Urgency of development of environment-friendly, cleaner system for road transport: A. Introduction: Pollution from motor vehicle is the single largest source of air pollution

More information

FACT SHEET. Whelan Energy Center 4520 East South Street Hastings, Nebraska March 26, 2004

FACT SHEET. Whelan Energy Center 4520 East South Street Hastings, Nebraska March 26, 2004 FACT SHEET Whelan Energy Center 4520 East South Street Hastings, Nebraska 68901 March 26, 2004 DESCRIPTION OF THE FACILITY OR ACTIVITY: Hastings Utilities (HU) currently operates the Whelan Energy Center

More information

Current Topics In Air Quality

Current Topics In Air Quality 76 th KSPE Annual Convention Current Topics In Air Quality Sean Alteri, Assistant Director Division for Air Quality Department for Environmental Protection Energy and Environment Cabinet Current Topics

More information

Potential to Emit. Calculating your PTE Jenifer Dixon Public Affairs and Outreach

Potential to Emit. Calculating your PTE Jenifer Dixon Public Affairs and Outreach Potential to Emit Calculating your PTE Jenifer Dixon dixonj2@michigan.gov Public Affairs and Outreach Topics of Discussion Introduction to Potential to Emit When to Calculate Potential to Emit How to Calculate

More information

Catalytic air pollution control systems for the removal of volatile organic compounds (VOCs)

Catalytic air pollution control systems for the removal of volatile organic compounds (VOCs) Catalytic air pollution control systems for the removal of volatile organic compounds (VOCs) Bietigheim-, 02.08.2010 Catalytic methods to treat hazardous air pollutants are experiencing a comeback. In

More information

Commercial and Industrial Solid Waste Incinerator (CISWI) Rules Final Reconsidered Rules Requirements Summary

Commercial and Industrial Solid Waste Incinerator (CISWI) Rules Final Reconsidered Rules Requirements Summary Commercial and Industrial Solid Waste Incinerator (CISWI) Rules Reconsidered Rules Requirements Summary Federal Regulations: 40 C 60 Subpart CCCC NSPS for new/reconstructed/modified CISWI 40 C 60 Subpart

More information

A PENNSYLVANIA FRAMEWORK OF ACTIONS FOR METHANE REDUCTIONS FROM THE OIL AND GAS SECTOR

A PENNSYLVANIA FRAMEWORK OF ACTIONS FOR METHANE REDUCTIONS FROM THE OIL AND GAS SECTOR A PENNSYLVANIA FRAMEWORK OF ACTIONS FOR METHANE REDUCTIONS FROM THE OIL AND GAS SECTOR INTRODUCTION Methane (CH4) has been identified by the U.S. Environmental Protection Agency (EPA) as the second most

More information

Implementation Issues for the PM 2.5 National Ambient Air Quality Standards PM 2.5 NAAQS

Implementation Issues for the PM 2.5 National Ambient Air Quality Standards PM 2.5 NAAQS Implementation Issues for the PM 2.5 National Ambient Air Quality Standards Update for MARAMA CEMS Webinar October 6, 2011 Rich Damberg US EPA Office of Air Quality Planning and Standards 1 PM 2.5 NAAQS

More information

The Role of Combined Heat and Power (CHP) in Virginia s Energy Future

The Role of Combined Heat and Power (CHP) in Virginia s Energy Future The Role of Combined Heat and Power (CHP) in Virginia s Energy Future Prepared for: Workshop on Combined Heat and Power Development in Virginia, Alexandria, VA Prepared by: M. Willingham and M. Pipattanasomporn

More information

Catalog of CHP Technologies

Catalog of CHP Technologies Catalog of CH Technologies Introduction to CH Technologies Introduction ueled by electric industry deregulation, environmental concerns, unease over energy security, and a host of other factors, interest

More information

SWCAA 400. General Regulations for Air Pollution Sources

SWCAA 400. General Regulations for Air Pollution Sources General Regulations for Air Pollution Sources Effective: June 18, 2017 CR-101 Filed with Code Reviser: WSR 16-23-073 November 15, 2017 Preproposal Published: WSR 16-23 December 7, 2016 CR-102 Filed with

More information

Presented to. November 6, 2002

Presented to. November 6, 2002 Comments of the Plumbers and Steamfitters Union, Local 166 Concerning a Proposed PSD Major Modification Permit for Iron Dynamics, Inc., Butler, IN & Request for Public Hearing Presented to Indiana Department

More information

AIR QUALITY MANAGEMENT DISTRICT

AIR QUALITY MANAGEMENT DISTRICT 777 12th Street, 3rd Floor SACRAMENTO METROPOLITAN Sacramento, CA 95814 AIR QUALITY MANAGEMENT DISTRICT AUTHORITY TO CONSTRUCT EVALUATION APPLICATION NO.: REVIEW STARTING DATE: 01/13/17 ISSUING ENGINEER:

More information