Proposal for New Capacity Zone Impact Analysis
|
|
- Oliver Norris
- 6 years ago
- Views:
Transcription
1 Proposal for New Capacity Zone Impact Analysis Tariq N. Niazi Senior Manager, Consumer Interest Liaison New York Independent System Operator Installed Capacity Working Group September 11, 2012 KCC
2 Proposed Agenda Timing of the Impact Analysis Key Assumptions for Consumer Impact Analysis Elements of the Impact Analysis Empirical analysis Next Steps 2
3 Timing of Impact Analysis Since the final boundaries of the New Capacity Zone (NCZ) and other inputs needed for the Impact Analysis, like the Demand Curves and Locational Minimum Installed Capacity Requirements (LCRs) for the NCZ, are not known at this time, we will have to make certain assumptions to conduct the Impact Analysis To address this uncertainty, we will conduct the Impact Analysis for more than one set of assumptions 3
4 Key Assumptions Zonal Boundaries Zonal Nesting Design Demand Curve Slopes External Resources Indicative LCRs 4
5 Zonal Boundaries We will look at two possibilities: A new capacity zone (Locality) that includes Load Zones G, H & I A new capacity zone that includes Load Zones F, G, H & I 5
6 Zonal Nesting Design Since zones J & K are downstate of zones G, H and I and all these zones are east of central east, the new zone might involve a nested design. We will assess the consumer impact of: A new capacity zone including G, H, I & J We will also analyze a combined: F, G, H, I, & J 6
7 Demand Curve Slope The actual demand curves for the NCZ will be determined as part of the reset process. For the Impact Analysis, we will assume the following for all NCZs: A 15% crossing point A 12% crossing point 7
8 Indicative Locational Capacity Requirements (Indicative LCRs) Indicative LCRs for the New Capacity Zone will be identified by the NYISO as part of the process of determining the ICAP Demand Curve for the proposed NCZ. (Actual LCRs for any FERC-accepted NCZ would be determined in early 2014, along with the other LCRs) We will use Indicative LCRs for the conducting the Impact Analysis 8
9 External Resources It will be assumed that capacity resources located in New England will be delivered on the external side of UPNY/SENY interface and not included in the NCZ It will also be assumed that PJM capacity (other than Neptune, VFT or HTP) will be delivered into the upstate region 9
10 Elements of the Impact Analysis Price Impacts: Impact on capacity prices in the new ROS (NYCA minus the NCZ and Zones J and K) after carving out Zones G, H & I or Zones F, G, H & I, to create a G, H, I, and J or F, G, H, I and J New Capacity Zone Capacity prices in the NCZ under different assumptions The price of capacity in Zone J and K Analysis of long-term consumer impact 10
11 Other Impacts to be analyzed Reliability The creation of a NCZ would better reflect reliability needs, as deliverability evaluations would more accurately reflect locational needs. The impact analysis will consider the effect of avoiding the potential for surplus capacity (e.g., in the West) to mask the need for more capacity in Zones F, G, H & I. To evaluate the impact on reliability, the analysis would compare the amount of capacity that cleared in Zones G, H & I or F, G,H & I in the last auction with the indicative LCRs for the NCZ 11
12 Other Impacts, Contd. Environment With the creation of a NCZ, some potential new capacity resources in the new ROS (NYCA minus NCZ and Zones J & K) may no longer have a deliverability constraint These potential new resources, if deliverable, could displace older higher emission units and have a positive environmental impact. 12
13 Other Impacts, Contd. Transparency The creation of a NCZ would lead to more informative capacity market prices both in the new capacity zone and new ROS (NYCA minus NCZ and Zones J & K) 13
14 Empirical Analysis Use data from previous auctions to gain insight into the impact on capacity prices for the new ROS (NYCA minus NCZ and Zones J & K) Estimate how much generation in the West, that could not participate in the capacity market because it was not deemed deliverable to Zones F, G, H or I, will now become deliverable in the new ROS with the creation of the NCZ Examine the generation queue in the West to estimate how much capacity under development and /or construction, that would not have been able to participate in the capacity market because it would have been deemed not deliverable to Zones F, G, H & I, will likely become deliverable in the new ROS with the creation of the NCZ Look at additional capacity, for example HQ that would likely qualify as deliverable in the new ROS Perform a sensitivity analysis of potential exit of capacity in the new ROS,,particularly if capacity yprices fall 14
15 Empirical Analysis, Contd. Use data from previous auctions to gain insight into impact on capacity prices for the NCZ Estimate what capacity prices in Zones G, H & I would have been with the new Capacity Zone by determining how much of Zones G, H & I capacity was offered, how much cleared the auction and compare that with the indicative LCRs for these zones Estimate the possible range of future capacity prices in Zones G, H and I using a combination of data from past auctions and data on new entry and projected peak load Compare the supply in Zone J to the LCR for the combined G, H, I & J capacity zone at various points on the demand curve for both a 12 percent and 15 percent crossing point Repeat the above analyses for a combined F, G, H, I & J capacity zone Make a qualitative assessment of the potential for a new capacity zone to reduce the LCR for Zone J 15
16 Next Steps Conduct the Empirical Analysis Report Back to ICAP Report to BIC Report to MC 16
17 The New York Independent System Operator (NYISO) is a not-for-profit corporation responsible for operating the state s bulk electricity grid, administering New York s competitive wholesale electricity markets, conducting comprehensive long-term planning for the state s electric power system, and advancing the technological infrastructure of the electric system serving the Empire State. 17
Compliance with FERC Order on Technical Conference re: Treatment of Zone K Export Constraints into the G-J Locality
Compliance with FERC Order on Technical Conference re: Treatment of Zone K Export Constraints into the G-J Locality Randy Wyatt Capacity Market Products New York Independent System Operator ICAPWG February
More informationTreatment of Zone K Export Constraints into the G-J Locality : Market Design Concept
Treatment of Zone K Export Constraints into the G-J Locality : Market Design Concept Randy Wyatt Capacity Market Products New York Independent System Operator MIWG/ICAPWG December 18, 2014 NYISO, Rensselaer,
More informationImplementation of New Capacity Zone in Class Year Deliverability Studies
Implementation of New Capacity Zone in Class Year Deliverability Studies Steven Corey Manager, Interconnection Projects New York Independent System Operator ICAP Working Group February 14, 2013 NYISO 2013
More informationLinden VFT Scheduled Line Market Integration Update Initial Tariff Review
Linden VFT Scheduled Line Market Integration Update Initial Tariff Review John Hickey New York Independent System Operator Market Issues Working Group January 28, 2009 1 Linden VFT Scheduled Line Linden
More information2018/2019 NYSRC RELIABILITY RULE A.2 REQUIREMENTS R1, R2, R3 COMPLIANCE SUBMITTAL
2018/2019 NYSRC RELIABILITY RULE A.2 REQUIREMENTS R1, R2, R3 COMPLIANCE SUBMITTAL COVERING THE NEW YORK CONTROL AREA For the 2018 2019 Capability Year Presented to the Reliability Compliance Monitoring
More informationCarbon Charge Proposal Evaluation PREPARED BY: PREPARED FOR: DATE:
Carbon Charge Proposal Evaluation PREPARED BY: PREPARED FOR: DATE: MARC D MONTALVO & MATTHEW LOIACONO IPPTF MEETING AUGUST 20, 2018 Overview Background Work Plan Methodology Input Assumptions Results Questions
More informationCRIS for External-to-ROS Transmission Investment External-to-ROS Deliverability Rights (EDR)
CRIS for External-to-ROS Transmission Investment External-to-ROS Deliverability Rights (EDR) Ethan D. Avallone Senior Market Design Specialist, Energy Market Design Management Committee March 28, 2018
More informationScarcity Pricing. Market Issues Working Group (MIWG) October 25, 2012 Rensselaer, NY
Enhanced Scarcity Pricing Matthew Musto Project Manager Ops and Reliability Products New York Independent System Operator Market Issues Working Group (MIWG) October 25, 2012 Rensselaer, NY Current Process
More informationin the NYISO s Market Administration and Control Area Services Tariff ( Services Tariff ).
NYISO 15-25 2015/2016 ICAP Demand Curve Reset RFP 1.3 RFP Objectives, Scope, and Deliverables The objective of this Request for Proposal is to select a consultant to conduct a study of the parameters,
More informationScarcity Pricing Informational FERC Filing
Scarcity Pricing Informational FERC Filing Dr. Nicole Bouchez Principal Economist, Market Design New York Independent System Operator Market Issues Working Group (MIWG) October 8, 2013 FERC Requirement
More informationLocational Export Capacity Proposal
Locational Export Capacity Proposal Joshua A. Boles ICAP Market Operations New York Independent System Operator jboles@nyiso.com 518-356-6293 Business Issues Committee October 20, 2016 NYISO 2000-2016
More informationGrowing Wind. Final Report of the NYISO 2010 Wind Generation Study. John Adams Principal Electric System Planner New York Independent System Operator
Growing Wind Final Report of the NYISO 2010 Wind Generation Study John Adams Principal Electric System Planner New York Independent System Operator National Wind Coordinating Collaborative Transmission
More informationMilestone Update. Janet Joyce Director, Product and Project Management New York Independent System Operator
2012 Project Plan Schedule Milestone Update Janet Joyce Director, Product and Project Management New York Independent System Operator Budget & Priorities Working Group August 22, 2012 Project Milestone
More informationCarbon Pricing Straw Proposal Overview
Carbon Pricing Straw Proposal Overview Mike DeSocio NYISO IPPTF May 12, 2018, KCC, Rensselaer, NY Agenda Introduction IPPTF Issue Tracks Concept for Carbon Pricing Setting the Gross Social Cost of Carbon
More informationDeliverability Requirements for Capacity Imports
Deliverability Requirements for Capacity Imports Zachary T. Smith Supervisor, ICAP Market Operations ICAPWG October 11, 2017, Rensselaer, NY Minimum deliverability requirements for External Capacity in
More informationAlternative Methods for Determining LCRs
Alternative Methods for Determining LCRs Zachary Stines Associate Market Design Specialist Installed Capacity Working Group June 29, 2017, NYISO Agenda Phase 2: Refining the Methodology Transmission Security
More informationBroader Regional Markets Report
Broader Regional Markets Report Rana Mukerji SENIOR VICE PRESIDENT MARKET STRUCTURES, NYISO Business Issues Committee Meeting February 14, 2018, Rensselear, NY 1 Market-to-Market Coordination-PJM Implement
More informationNYISO MMU EVALUATION OF THE PROPOSED AC PUBLIC POLICY TRANSMISSION PROJECTS
ww2 NYISO MMU EVALUATION OF THE PROPOSED AC PUBLIC POLICY TRANSMISSION PROJECTS By: David B. Patton, Ph.D. Pallas LeeVanSchaick, Ph.D. Raghu Palavadi Naga Market Monitoring Unit for the New York ISO June
More informationBroader Regional Markets Report
Broader Regional Markets Report Rana Mukerji SENIOR VICE PRESIDENT MARKET STRUCTURES, NYISO Business Issues Committee Meeting June 20, 2018, Rensselear, NY 1 Market-to-Market Coordination-PJM Implement
More information/s/ Henry Chao Henry Chao Vice President, System Resource Planning. December 9, 2013
December 9, 2013 10 Krey Boulevard Rensselaer, NY 12144 Re: NYISO 2013 Congestion Assessment and Resource Integration Studies Report Dear NYISO Economic Planning Interested Parties: On November 19, 2013
More informationBroader Regional Markets Report
Broader Regional Markets Report Rana Mukerji SENIOR VICE PRESIDENT MARKET STRUCTURES, NYISO Business Issues Committee Meeting April 11, 2018, Rensselear, NY 1 Market-to-Market Coordination-PJM Implement
More information2017 Project Prioritization & Budgeting Process
2017 Project Prioritization & Budgeting Process Ryan Smith Senior Manager Budget & Priorities Working Group June 24, 2016 Krey Corporate Center 2000-2016 New York Independent System Operator, Inc. All
More informationCarbon Pricing. Overview of the Brattle Report. Nicole Bouchez, PhD Principal Economist Environmental Advisory Council Meeting
Carbon Pricing Overview of the Brattle Report Nicole Bouchez, PhD Principal Economist Environmental Advisory Council Meeting November 3, 2017, Albany Capital Center, Albany, NY COPYRIGHT NYISO 2017. ALL
More informationConsumer Impact Analysis: Transmission Constraint Pricing
Consumer Impact Analysis: Transmission Constraint Pricing Tariq N. Niazi Senior Manager, Consumer Interest Liaison New York Independent System Operator Market Issues Working Group January 31, 2017 NYISO
More informationNYISO Management Response to FTI Consulting Report Evaluation of the New York Capacity Market
NYISO Management Response to FTI Consulting Report Evaluation of the New York Capacity Market March 2013 Evaluation of the New York Capacity Market Introduction In an effort to evaluate and, where appropriate,
More informationEthan D. Avallone Senior Market Design Specialist, Energy Market Design ICAPWG/TPAS February 21, 2018 Rensselaer, NY
Performance Assurance Management Response to Analysis Group s Capacity Resource Performance in NYISO Markets: An Assessment of Wholesale Market Options Ethan D. Avallone Senior Market Design Specialist,
More informationProposed ICAP Manual Revisions Regarding Deliverability Requirements for Capacity Imports from PJM
Proposed ICAP Manual Revisions Regarding Deliverability Requirements for Capacity Imports from PJM Zachary T. Smith Manager, Capacity Market Design Business Issues Committee January 17, 2018, Rensselaer,
More informationMarket Impact Assessment: Preliminary DAM Results Overview
Market Impact Assessment: Preliminary DAM Results Overview Nicole Bouchez, Ph.D. Michael Swider Market Issues Working Group April 24, 2017, Rensselaer NY Agenda Overview of the Integrating Public Policy
More informationBroader Regional Markets Report
Broader Regional Markets Report Rana Mukerji SENIOR VICE PRESIDENT MARKET STRUCTURES, NYISO Business Issues Committee Meeting August 13, 2018, Rensselear, NY 1 Market-to-Market Coordination-PJM Implement
More informationOutlook for the New York wholesale power market and analysis of the drivers of transmission congestion within the New York Markets
Outlook for the New York wholesale power market and analysis of the drivers of transmission congestion within the New York Markets July 1st, 2015 Prepared for Hudson Valley Smart Energy Coalition by Julia
More informationCompetitive Entry Exemption: New Proposal
Competitive Entry Exemption: New Proposal Dr. Nicole Bouchez Principal Economist, Market Design New York Independent System Operator Installed Capacity Working Group December 10, 2013 KCC 2013 New York
More information2018 Project Schedule Milestone Update
2018 Schedule Milestone Update Robb Pike Director, & Product Management Budget and Priorities Working Group January 31 st, 2018 Krey Corporate Center Milestone and Definitions COPYRIGHT NYISO 2017. ALL
More information2019 Project Prioritization and Budgeting Process
2019 Project Prioritization and Budgeting Process Brian Hurysz Manager, Market Products Budget and Priorities Working Group May 10, 2018, Krey Corporate Center Agenda Project Prioritization Process Project
More information2013 Congestion Assessment and Resource Integration Study
Style Definition: Footnote: Font: (Default) Arial 2013 Congestion Assessment and Resource Integration Study Comprehensive System Planning Process CARIS Phase 1 DRAFT August 27September 9, 2013 NYISO System
More informationConcepts for Behind-the- Meter Net Generation
Concepts for Behind-the- Meter Net Generation Pradip Ganesan Donna Pratt New York Independent System Operator Joint Meeting of Installed Capacity, Market Issues and Price Responsive Load Working Groups
More informationBroader Regional Markets Report
Broader Regional Markets Report Rana Mukerji SENIOR VICE PRESIDENT MARKET STRUCTURES, NYISO Business Issues Committee Meeting December 12, 2018, Rensselaer, NY 1 Market-to-Market Coordination-PJM Implement
More informationBroader Regional Markets Report
Broader Regional Markets Report Rana Mukerji SENIOR VICE PRESIDENT MARKET STRUCTURES, NYISO Business Issues Committee Meeting January 16, 2019, Rensselaer, NY 1 Market-to-Market Coordination-PJM Implement
More informationBroader Regional Markets Report
Broader Regional Markets Report Rana Mukerji SENIOR VICE PRESIDENT MARKET STRUCTURES, NYISO Business Issues Committee Meeting November 14, 2018, Rensselaer, NY 1 Market-to-Market Coordination-PJM Implement
More information2014 Project Schedule Milestone Update
2014 Project Schedule Milestone Update Ryan Smith Senior Manager, Enterprise Product & Project Management New York Independent System Operator Budget and Priorities Working Group May 05, 2013 Krey Corporate
More information2011 Congestion Assessment and Resource Integration Study
2011 Congestion Assessment and Resource Integration Study Comprehensive System Planning Process CARIS Phase 1 Final Report March 20, 2012 NYISO System Resources and Planning staff can be reached at 518-356-6000
More information2014 Project Schedule Milestone Update
2014 Project Schedule Milestone Update Ryan Smith Senior Manager, Enterprise Product & Project Management New York Independent System Operator Budget and Priorities Working Group November 21, 2014 Krey
More informationNYISO 2015/2016 ICAP Demand Curve Reset
NYISO 2015/2016 ICAP Demand Curve Reset Business Issues Committee March 17, 2016 BOSTON CHICAGO DALLAS DENVER LOS ANGELES MENLO PARK MONTREAL NEW YORK SAN FRANCISCO WASHINGTON Today s Presentation Provide
More informationLess than 20 MW Constraint Reliability Margin Values
Less than 20 MW Constraint Reliability Margin Values David Edelson Manager Operations Performance and Analysis Management Committee August 29, 2018 Rensselear, NY Background NYISO s tariff currently requires
More informationNumerical Example of Net Short Threshold for Self Supply Exemption
Numerical Example of Net Short Threshold for Self Supply Exemption Julia Popova, PhD Economist, ICAP Market Mitigation New York Independent System Operator ICAP WG April 06, 2016 Krey Blvd, Rensselaer,
More informationICA Demand Curve Development:
ICA Demand Curve Development: Proposed Approach for Ontario PRESENTED TO Market Renewal Incremental Capacity Auction Stakeholder Group PRESENTED BY Kathleen Spees Johannes Pfeifenberger Yingxia Yang John
More informationCon Ed/PSEG Wheel Replacement Protocol - Update
Con Ed/PSEG Wheel Replacement Protocol - Update David Edelson Manager Operations Performance and Analysis MIWG April 24, 2017, KCC Agenda FERC Filing Status. Market Changes on May 1, 2017. Market-to-Market
More information2013 Project Schedule Milestone Summary
2013 Project Schedule Milestone Summary Janet Joyce Director, Product & Project Management New York Independent System Operator Budget and Priorities Working Group February 13, 2014 Krey Corporate Center
More informationEvaluation of the New York Capacity Market
Evaluation of the New York Capacity Market Prepared by Scott M. Harvey William W. Hogan Susan L. Pope March 5, 2013 i Executive Summary There are no critical flaws in the design of the New York ISO capacity
More informationSecuring 100+kV Transmission Facilities in the Market Model Market Design Complete Presentation
Securing 100+kV Transmission Facilities in the Market Model Market Design Complete Presentation Shaun Johnson DIRECTOR MARKET MITIGATION & ANALYSIS, NYISO Business Issues Committee September 12, 2018 Rensselear,
More informationCarbon Pricing Import/Export Transaction Examples
Carbon Pricing Import/Export Transaction Examples Ethan D. Avallone SENIOR MARKET DESIGN SPECIALIST ENERGY MARKET DESIGN Market Issues Working Group (MIWG) January 15, 2019Rensselaer NY Agenda Purpose
More informationConcepts for Aggregation Participation In Demand Side Ancillary Service Program (DSASP)
Concepts for Aggregation Participation In Demand Side Ancillary Service Program (DSASP) Donna Pratt Manager, Demand Response Products Demand Response Products New York Independent System Operator Market
More informationBroader Regional Markets Report
Broader Regional Markets Report Rana Mukerji SENIOR VICE PRESIDENT MARKET STRUCTURES, NYISO Business Issues Committee Meeting February 13, 2019, Rensselaer, NY 1 Market-to-Market Coordination-PJM Implement
More informationCONNECTION A Newsletter for Market Participants
FOURTH QUARTER 2010 New York ISO CONNECTION A Newsletter for Market Participants Sufficient Electricity Supply Forecast for Winter 2010-2011 Winter can pose many challenges in the Empire State, but a sufficient
More informationTRC Solutions. Cost and Feasibility Analysis of a Third Converter Station for the Champlain Hudson Power Express Project
TRC Solutions Cost and Feasibility Analysis of a Third Converter Station for the Champlain Hudson Power Express Project October 2013 Table of Contents: I. Executive Summary II. Cost Estimate and Physical
More informationNew York s Evolving Electric Grid
POWER TRENDS New York s Evolving Electric Grid 2017 Power Trends 2017 1 THE NEW YORK INDEPENDENT SYSTEM OPERATOR (NYISO) is a not- for-profit corporation responsible for operating the state s bulk electricity
More informationMarket Design Concepts to Prepare for Significant Renewable Generation
Market Design Concepts to Prepare for Significant Renewable Generation Flexible Ramping Product Ethan D. Avallone SENIOR MARKET DESIGN SPECIALIST ENERGY MARKET DESIGN Market Issues Working Group April
More informationPrice Formation Education 4: Shortage Pricing and Operating Reserve Demand Curve
Price Formation Education 4: Shortage Pricing and Operating Reserve Demand Curve Patricio Rocha Garrido Lisa Morelli Laura Walter Disclaimer This is not a committee meeting. This session is for educational
More information2007 Project Plan Schedule Milestone Update. Budgets & Priority Working Group February 6, 2007
2007 Project Plan Schedule Milestone Update Budgets & Priority Working Group February 6, 2007 1 Agenda Project Schedule Milestone Review / Update Review of Other Active Projects Project Backlog Review
More informationSolar Integration Study
Solar Integration Study Timothy Duffy Manager, Economic Planning Electric and System Planning Working Group June 7, 2016 2000-2016 New York Independent System Operator, Inc. All Rights Reserved. Key Takeaways
More informationPricing Carbon into NYISO s Wholesale Energy Market
Pricing Carbon into NYISO s Wholesale Energy Market Study Overview and Summary of Findings P R E S E N T E D T O NYISO Business Issues Committee P R E P A R E D B Y Sam Newell Roger Lueken Tony Lee S e
More information2020/2021 RPM Base Residual Auction Planning Period Parameters
Introduction The planning parameters for the 2020/2021 RPM Base Residual Auction (BRA) that is to be conducted in May of 2017 were posted on the PJM RPM website on February 1, 2017. This document describes
More informationWho should calculate the UCAP. Eligibility WG September 12, 2017
Who should calculate the UCAP Eligibility WG September 12, 2017 Overview The following materials provide an examination of the question: Who should be responsible for calculating the UCAP for qualified
More informationUpdate on Northeast Seams Issues. February 20, 2008 NYISO Business Issues Committee Meeting
Update on Northeast Seams Issues February 20, 2008 NYISO Business Issues Committee Meeting Status of Seams Projects Current Deliverables Project 1. Intra-Hour Transaction Scheduling NYISO and ISO-NE have
More informationImpacts from Peak Load Reductions in Markets and Long-Range Planning
JUNE 21, 2016 BOSTON, MA Impacts from Peak Load Reductions in Markets and Long-Range Planning MA Energy Efficiency Advisory Council Eric Winkler, Ph.D. TECHNICAL MANAGER, SYSTEM PLANNING Overview of Presentation
More informationNYISO s Integrating Public Policy Project
NYISO s Integrating Public Policy Project Phase 2: Study Description and Assumption Review Dr. Nicole Bouchez & Mike Swider MIWG Krey Blvd, Rensselaer February 16, 2017 2000-2017 New York Independent System
More informationDesign Criteria for Energy Market Prices
Design Criteria for Energy Market Prices Energy Price Formation Senior Task Force February 15, 2018 Catherine Tyler Market Pricing Principles A market is a set of interactions between buyers and sellers.
More informationDecember 2014 John Dalton
ISO-New England Forward Capacity Auction #9 Summary Price Forecast December 2014 John Dalton 978-369-2465 jdalton@poweradvisoryllc.com ISO-New England s upcoming Forward Capacity Auction prices are likely
More informationGreening the Grid. Challenges & Opportunities. Tom Rumsey. Transition to a Green Economy
Greening the Grid Challenges & Opportunities Tom Rumsey Vice President External Affairs New York Independent System Operator Transition to a Green Economy Newburgh, NY November 20, 2013 Topics About the
More informationNEW YORK CITY S ROADMAP TO 80 X 50. July 18, 2017
NEW YORK CITY S ROADMAP TO 80 X 50 July 18, 2017 1 Sources and Magnitude of NYC s GHG Emissions Sources and Magnitude of NYC s GHG Emissions in 2015 Inventory of New York City Greenhouse Gas Emissions
More information2017/2018 RPM Base Residual Auction Planning Period Parameters
Introduction The RPM Base Residual Auction (BRA) for the 2017/2018 Delivery Year is scheduled to be conducted in May of 2014. This document describes the 2017/2018 BRA planning period parameters and also
More informationIncorporating Energy Efficiency in Long Term
Incorporating Energy Efficiency in Long Term System Planning Arthur Maniaci Supervisor, Load Forecasting & Energy Efficiency New York Independent System Operator Northeast Energy Efficiency Partnerships
More informationPlan Summary. Budget and Priorities Working Group February 15, 2013 Krey Corporate Center
2012 Project Plan Summary Janet Joyce Director, Product & Project Management New York Independent System Operator Budget and Priorities Working Group February 15, 2013 Krey Corporate Center 2013 New York
More information2018 DRAFT Annual Incentive Goals
2018 DRAFT Annual Incentive Goals Emilie Nelson VP MARKET OPERATIONS, NYISO Budget & Priorities Working Group November 2, 2017. Krey Corporate Center, Rensselaer, NY. Agenda Background Objectives Structural
More informationAppendices. New York Control Area Installed Capacity Requirement. December 2, For the Period May 2017 To April 2018
Appendices New York Control Area Installed Capacity Requirement For the Period May 2017 To April 2018 December 2, 2016 New York State Reliability Council, LLC Installed Capacity Subcommittee NYSRC: NYCA
More informationNYISO Markets. New York s Marketplace for Wholesale Electricity
NYISO Markets New York s Marketplace for Wholesale Electricity Why Markets? Markets Support Reliability Competitive wholesale electricity markets preserve system reliability with pricing signals that attract
More informationWholesale Markets for the Grid of the Future Whitney Lesnicki Manager, Energy Market Design DRAFT FOR DISCUSSION PURPOSES ONLY
Master Plan Wholesale Markets for the Grid of the Future Whitney Lesnicki Manager, Energy Market Design Market Issues Working Group May 15, 2018, Rensselaer NY Agenda Background Strategic Themes Proposed
More informationConstraint Specific Transmission Shortage Pricing. Study Approach
Constraint Specific Transmission Shortage Pricing Study Approach Jennifer Boyle Energy Market Design MIWG April 10, 2018, Krey Corporate Center Today s Agenda Project Plan/Deliverables Scope of Study Proposed
More informationCoordination with PJM
Market-to-Market Coordination with PJM Mike DeSocio Market Product Specialist New York Independent System Operator MIWG October 27, 2011 Rensselaer, New York Agenda M2M and NYISO Markets Examples Tariff
More informationImplementation Update: Coordinated Transaction Scheduling (CTS) Enhancements
Implementation Update: Coordinated Transaction Scheduling (CTS) Enhancements Christopher Brown New York Independent System Operator Market Issues Working Group September 29, 2014 Rensselaer, NY 2014 New
More informationThe Part A Application of NextEra Energy Transmission New York, Inc.
10 Krey Boulevard Rensselaer, NY 12144 November 6, 2015 Hon. Kathleen H. Burgess Secretary to the Commission New York State Public Service Commission Agency Building 3, 19th Floor Albany, NY 12223-1350
More informationEmergency Assistance Model
Emergency Assistance Model Status Report John Adams NYSRC Consultant April 5, 2017 ICS Meeting First Draft 3/23/2017 3/23/2017 April 5, 2017 ICS Meeting 1 Activities Since 3/1/2017 Meeting Finalized EA
More information2007 NYSRC RELIABILITY COMPLIANCE PROGRAM
2007 RELIABILITY PROGRAM MEASUREMENT DESCRIPTION DOC. OF Resource Adequacy A-M2 A-R2,3 Establishing LSE ICAP requirements A 4/1/07 3/8/07 3/8/07 FC A-M3 A-R2,3 Certifying LSE ICAP obligations are met*
More informationMaster Plan Wholesale Markets for the Grid of the Future. A Report by the New York Independent System Operator
Master Plan Wholesale s for the of the Future A Report by the New York Independent System Operator June 2018 Table of Contents INTRODUCTION... 4... 5... 5... 6 Capacity s... 6 STRATEGIC MARKET DESIGN CONCEPTS
More informationPSE&G/ConEd Wheel Modeling
PSE&G/ConEd Wheel Modeling Stan Williams Director, Compliance & Settlements MC Webinar June 27, 2016 Overview of PSE&G-ConEd 600/400 Contract PJM NYISO Wheel Overview 1,000 MW from NYISO to PJM at the
More informationComprehensive Shortage Pricing
Comprehensive Shortage Pricing Mike DeSocio Manager, Energy Market Design New York Independent System Operator Management Committee December 17, 2014 Krey Corporate Center 2014 New York Independent System
More informationDonna Pratt Manager, Demand Response Products New York Independent System Operator
Incremental ACL for SCRs Donna Pratt Manager, Demand Response Products New York Independent System Operator Joint Price Responsive Load and Installed Capacity Working Groups September 11, 2012 2011 New
More informationISO/RTO Metrics Initiative
ISO/RTO Metrics Initiative Mary McGarvey Vice President & Chief Financial Officer New York Independent System Operator Management Committee NYISO Krey Corporate Center January 20, 2010 Government Accountability
More informationCarbon Pricing Straw Proposal. A Report Prepared for the Integrating Public Policy Task Force. April 30, 2018 DRAFT FOR DISCUSSION PURPOSES ONLY
Carbon Pricing Straw Proposal A Report Prepared for the Integrating Public Policy Task Force April 30, 2018 DRAFT FOR DISCUSSION PURPOSES ONLY Table of Contents INTRODUCTION... 3 CONCEPT FOR CARBON PRICING...
More informationCarbon Pricing Straw Proposal. A Report Prepared for the Integrating Public Policy Task Force. April 30, 2018 DRAFT FOR DISCUSSION PURPOSES ONLY
Carbon Pricing Straw Proposal A Report Prepared for the Integrating Public Policy Task Force April 30, 2018 DRAFT FOR DISCUSSION PURPOSES ONLY Table of Contents INTRODUCTION... 3 CONCEPT FOR CARBON PRICING...
More information2018/2019 RPM Base Residual Auction Planning Period Parameters
Introduction The planning parameters for the 2018/2019 RPM Base Residual Auction (BRA) that is to be conducted in May of 2015 were posted on the PJM RPM website on January 30, 2015. Two versions of the
More informationIssue Track 5: Customer Impacts
Issue Track 5: Customer Impacts Proposed Methodology for Modeling and Analysis Tim Duffy, Manager Economic Planning, NYISO IPPTF April 23, 2018, KCC, Rensselaer COPYRIGHT NYISO 2018. ALL RIGHTS RESERVED
More informationAnalysis of the 2020/2021 RPM Base Residual Auction
Analysis of the 2020/2021 RPM Base Residual Auction The Independent Market Monitor for PJM November 17, 2017 Monitoring Analytics 2017 www.monitoringanalytics.com Introduction This report, prepared by
More informationSeth G. Parker Direct Testimony on the New England Clean Power Link on behalf of Champlain VT, LLC Exhibit 9. Technical Report
Seth G. Parker Direct Testimony on the New England Clean Power Link on behalf of Champlain VT, LLC Exhibit 9. Technical Report 100 SUMMER STREET, SUITE 3200 BOSTON, MASSACHUSETTS 02110 TEL 617-531-2818
More informationPJM Organization and Markets. Saudi Delegation Columbus Ohio May 22, 2012
PJM Organization and Markets Saudi Delegation Columbus Ohio May 22, 2012 Agenda Introduction & Governance Energy Markets LMP FTRs/ARRs Two Settlement Virtual Bids Ancillary Capacity - Reliability Pricing
More informationCongestion Assessment and Resource Integration Studies. A Report by the New York Independent System Operator
Congestion Assessment and Resource Integration Studies A Report by the New York Independent System Operator April 2018 2017 Congestion Assessment and Resource Integration Study Comprehensive System Planning
More informationSmall Generator Interconnection Procedures
Small Generator Interconnection Procedures Thinh Nguyen Senior Manager, Interconnection Projects ICAP WG/MIWG/PRLWG September 28, 2018 Topics Determining the Applicable Interconnection Process for ERIS
More informationSustaining & Enhancing Reliability in NY
Sustaining & Enhancing Reliability in NY Stephen G. Whitley President & CEO New York Independent System Operator Northeast Power Coordinating Council General Meeting December 1, 2010 Albany, NY Topics
More informationQuarterly Report on the New York ISO Electricity Markets Second Quarter 2015
Quarterly Report on the New York ISO Electricity Markets Second Quarter 2015 David B. Patton, Ph.D. Pallas LeeVanSchaick, Ph.D. Jie Chen, Ph.D. Potomac Economics Market Monitoring Unit August 2015 This
More information