INPP Decommissioning Overview Darius Janulevičius
|
|
- Cory Bryan
- 6 years ago
- Views:
Transcription
1 INPP Decommissioning Overview Darius Janulevičius Director General
2 Operation Basics General Information Largest and the most advanced RBMK design (also with later safety upgrading) It was intended to build 4 units Construction of 3 rd unit was suspended in 1989 (about 60% of construction works were accomplished) Plant type Number of units Power per unit Staff in 2014 RBMK (of 4 planned) 1500 MW ~2100 (max 5600 during operat.) Unit 1 Unit 2 Supplied 70-80% of LT national demand Closed at around mid-life No funds accumulated for decommissioning due to early closure of the Plant First operation Dec 1983 Aug 1987 Final Closure Dec 2004 Dec 2009 Power generation 137 TWh 170 TWh Construction Operation Decommissioning X 2
3 INPP Decommissioning Scheme Preparation for decommissioning 1 unit unit Operation PRS Reactors defueled Pools defueled D&D implementation ensuring: safe post-operation ALARA D&D 1 unit unit Post-operation Dismantling & Decontamination 2000 Post-operation as a nuclear facility ensuring: fuel safety containment Post-operation as a waste storage facility ensuring: containment Conventional demolition 203X 3
4 Status of Spent Nuclear Fuel Unit 1: final closure Dec 2004 core fully defueled in 2009; 7175 fuel assemblies in pools. Unit 2: final closure Dec fuel assemblies remain in the core to be removed; Planned defueling starting 2017; 7246 fuel assemblies in pools. Final defueling from SFP
5 Waste Quantities Forecast INPP Stored Operational Waste Fuel => 6000 assemblies Solid Waste => m 3 Bituminized Waste => m 3 Cemented Waste => 4000 m 3 Dismantled in (until July) tons of equipment and structures Fuel Equipment Reactors Decommissioning Waste => assemblies => tons of steel => tons of steel => tons of graphite => tons of fillers Buildings => m 3 concrete => tons of steel 5
6 Key Decommissioning Dates B1 ISFSF construction and commissioning B2/3/4 Solid RW Treatment and Storage Facility construction and commissioning B19-2 Landfill Facility for Short-lived VLL Waste commissioning B25-Near Surface Repository for Low and Interim Level SLRW commissioning (I stage) Unit 2 reactor defueling Unit 1 and 2 Spent Fuel Storage Pools defueling 1 and 2 Reactor R1,2 zones dismantling and 2 Reactors R3 zones dismantling and decontamination Unrestricted release of areas related to Reactor Site Restoration X 6
7 Waste Routes Overview Operational wastes Decommissioning wastes Under construction Waste Retrieval B2 B20 Waste bituminization Waste cementation Operating Operating Operating Under construction Under Design B3/4 SW Processing & Storage Under construction B19-1 Buffer Storage B10 Measurement Facility Tendering shortly B25 B19-2 Free Release Near Surface Repository VLLW Landfill B1 Interim Spent Fuel Storage(s) Operating 7
8 Completed Projects B10 Free Release Measurement Facility Commissioned in August 2010 B19/1 Short-Lived Very Low Level Waste Buffer Storage Facility Commissioned in May
9 New Waste Management Facilities Interim Spent Fuel Storage Facility (B1) Existing INPP spent fuel storage, built in 1999 using GNS casks, lacked capacity for complete defueling due to decommissioning Objective of the Project B1: New ISFSF shall be built as following: To build an Interim SF Storage Facility, to manufacture and install all related equipment The Project is funded by IIDSF, managed by the EBRD To design and manufacture new-type casks with 80% increased capacity for INPP RBMK-1500 type reactor spent fuel, to develop the technologies for its loading and transportation to ISFSF and to install it Results: Spent fuel will be stored in 4,5 m height and 2,6 m diameter r/c casks CONSTOR RBMK-1500/М2, cask with fuel weight 118 t 190 new-type casks will be manufactured Total storage capacity 202 casks Contractor NUKEM Technologies GmbH / GNS Contract signed 5 January 2005 Start of operations (foreseen) 2017 Operational period years 9
10 Interim Spent Fuel Storage Facility (B1) Construction progress The Project is funded by IIDSF, managed by the EBRD 2012/ / / /11 10
11 The Project is funded by IIDSF, managed by the EBRD New Waste Management Facilities Solid Waste Management & Storage Facilities (B2/3/4) Integrated project for managing retrieved operational wastes and dismantling wastes, comprising: Retrieval Facility (B2) Processing Facility (B3) Storage Facility (B4, for long and short lived waste) Objective: To build facility for treatment of solid operational and dismantling radioactive wastes Results: Radioactive wastes will be retreated from the existing interim storages and transported to new treatment facility Wastes will be sorted and treated (resized, incinerated and compacted) Treated wastes will be packed into casks and stored in new treatment facility until the repository facilities will be built Contractor: NUKEM Technologies GmbH Contract signed: 30 November 2005 Start of operations (foreseen):
12 Solid Waste Management & Storage Facilities (B234) Construction progress The Project is funded by IIDSF, managed by the EBRD 2014/ / / /09 Laikinoji panaudoto branduolinio kuro saugykla 12
13 New Waste Management Facilities Landfill Facility for Short-lived Very Low Level Waste (B19) The Landfill Facility will consist of: The Buffer Storage Facility - a temporary closed building of 0.2 ha area where the systems designed for radiological measurement, transportation and temporary storage of wastes are installed. Capacity of Buffer Storage Facility is 4000 m 3 Disposal Modules - an above ground structure, in which carbon steel 20 feet ISO half-height containers with waste will be closely placed in five layers on the concrete slab. Contract signed 2007 Estimated start of operation (I stage) Buffer Storage Facility (B19-1) in operation 2018 since May
14 The Project is partly funded (Design) by IIDSF, managed by EBRD) New Waste Management Facilities Near Surface Repository (B25) A modular multi-barrier near surface repository for disposal of Low and Intermediate Level Short-lived Radioactive Waste from operation and decommissioning Objective: To design and construct Near Surface Repository for Low and Intermediate Level Short-lived Radioactive Waste Results: Cellular reinforced concrete repository will be build which will consist of several groups of sections designed for final disposal of m 3 of treated radioactive waste packed into concrete containers and cemented radioactive wastes Upon completion of radioactive waste disposal the repository will be closed and its surface will be covered with erosion resistant multilayer engineered protection barriers. After its closure the surveillance of the repository will be carried out for at least 300 years Contract signed: 23 October 2010 Estimated start of operation:
15 Thank you for attention
Current Status of Decommissioning in Lithuania
Current Status of Decommissioning in Lithuania Dr. Gintautas Poškas Researcher Lithuanian Energy Institute Nuclear Engineering Laboratory Nuclear facilities in Lithuania Ignalina NPP (under decommissioning)
More informationIgnalina NPP. Ignalina NPP decommissioning activities are co-financed by European Union
Workshop on Decommissioning of Uranium Contaminated Facilities, Pretoria, SAF 22-26 August 2011 Ignalina Ignalina overview I Decommissioning Strategy What are we going to do? How are we going to do it?
More informationIgnalina NPP. Presentation to Assembly of Contributors December Darius Janulevičius General Director. Decommissioning of Ignalina NPP is
Presentation to Assembly of Contributors December 2017 Ignalina NPP Darius Janulevičius General Director Decommissioning of Ignalina NPP is cofinanced by the European Union activities are co-financed by
More informationIgnalina NPP Decommissioning: Commitment to Achievement
Ignalina NPP Decommissioning: Commitment to Achievement 1 3 About the Ignalina Nuclear Power Plant Vision The enterprise aims to become known as leader and expert in the safe and effective decommissioning
More informationGeneric Aspects for Dismantling Preparation of INPP Reactor Facilities. Aleksej Merežnikov, Ignalina NPP, July 2014
Generic Aspects for Dismantling Preparation of INPP Reactor Facilities Aleksej Merežnikov, Ignalina NPP, July 2014 Agenda INTRODUCTION REGULATORY FRAMEWORK RBMK-1500 FEATURES GENERAL APROACH STATUS AND
More informationNuclear Waste Management Treatment Facility and Spent Fuel Storage at the Ignalina Nuclear Power Plant 9192
Nuclear Waste Management Treatment Facility and Spent Fuel Storage at the Ignalina Nuclear Power Plant 9192 Burkhard Koenning, José Fernández Puga, Johannes Rausch, Ronny Ziehm NUKEM Technologies GmbH
More informationDecommissioning and Radioactive Waste Management in Lithuania
Conference Nuclear Power Safety Regulation Challenges to commemorate the 20 th anniversary of Lithuanian State Nuclear Power Safety Inspectorate (VATESI) Decommissioning and Radioactive Waste Management
More informationIgnalina NPP. Human Resources points of attention for the nuclear decommissioning industry: Ignalina NPP experience
Human Resources points of attention for the nuclear decommissioning industry: Ignalina NPP experience Ignalina NPP Tomas Liukaitis Director of Corporate Affairs & Administration Decommissioning of Ignalina
More informationDecommissioning, Radioactive Waste and Spent Nuclear Fuel Management in Slovakia
Decommissioning, Radioactive Waste and Spent Nuclear Fuel Management in Slovakia Presented by Mr. Vladimir Michal Division for Radiation Safety, NPP Decommissioning and RAW Management GSV, Trnava, 11 October
More informationJoint Convention on the Safety of Spent Fuel and on the Safety of Radioactive Waste Management
Joint Convention on the Safety of Spent Fuel and on the Safety of Radioactive Waste Management Second National Report of Lithuania in accordance with Article 32 of the Convention 2008 Table of contents:
More informationExperience in Safety and Environmental impact assessment to support irradiated graphite decommissioning
Experience in Safety and Environmental impact assessment to support irradiated graphite decommissioning Prof. Povilas POŠKAS Head of Nuclear Engineering Laboratory Technical Meeting Experience of Reactors
More informationCURRENT STATUS ON FAST REACTOR PROGRAM IN KAZAKHSTAN
CURRENT STATUS ON FAST REACTOR PROGRAM IN KAZAKHSTAN Presented at the 47 th Annual Meeting of the Technical Working Group on Fast Reactors IAEA, Vienna, 19-23 May, 2014 by S. Andropenkov, National Atomic
More informationOrganizational and Managerial Aspects of Decommissioning after an Accident
Organizational and Managerial Aspects of Decommissioning after an Accident Miroslav Božik, Peter Gerhart JAVYS, Plc. Slovak Republic JAVYS, Plc. International Experts Meeting on Decommissioning and Remediation
More informationInternational Cooperation in the NFC Back End in Ukraine: benefits and challenges Mr. NEZHURA Maxim Head of Analytical Section
International Cooperation in the NFC Back End in Ukraine: benefits and challenges Mr. NEZHURA Maxim Head of Analytical Section Topics to be described 1. Nuclear Power in Ukraine 2. National Policy and
More informationOverview of Zone R3 and Reactor Interim Waste Storage issues
Overview of Zone R3 and Reactor Interim Waste Storage issues SE Ignalina NPP Workshop EXPERIENCE OF REACTORS DISMANTLING October November 2018, Visaginas co-financed by the European Union Content 1 Key
More informationLEGAL AND REGULATORY FRAMEWORK FOR RADIOACTIVE WASTE MANAGEMENT AND DECOMMISSIONING IN SLOVAK REPUBLIC
LEGAL AND REGULATORY FRAMEWORK FOR RADIOACTIVE WASTE MANAGEMENT AND DECOMMISSIONING IN SLOVAK REPUBLIC ABSTRACT /DGLVODY.RQHþQê-DQD%XUFORYi Nuclear Regulatory Authority of the Slovak Republic Trnava Slovak
More informationVUJE experience in NPP decommissioning and radwaste (RAW) treatment
VUJE experience in NPP decommissioning and radwaste (RAW) treatment JRC - Slovakia Conference Bratislava Peter Líška June 10, 2014 www.vuje.sk A1 NPP Decommissioning A1 NPP - CO 2 cooled, HW moderated,
More informationMaria Taranger Foto: Kävlinge Municipality
Maria Taranger Foto: Kävlinge Municipality The icon of nuclear power in Sweden The beginning and the end Type: BWR Capacity: 1800 MWt / 615MWe First connection to the grid: May 15, 1975 / March 21, 1977
More informationSafe disposal of LLW in surface repository
Safe disposal of LLW in surface repository The French case Views from the regulator Loïc Tanguy Autorité de sûreté nucléaire (ASN) February, 3rd 2015 1 General principles about waste management Role of
More informationManagement of Large Waste Volumes of Solid Waste in Ukraine
Management of Large Waste Volumes of Solid Waste in Ukraine Tetiana Kilochytska State Nuclear Regulatory Inspectorate of Ukraine International Expert Meeting on Decommissioning and Remediation after a
More informationRadioactive Waste Management at the NCSR Demokritos - Greece
Radioactive Waste Management at the NCSR Demokritos - Greece Anastasia Savidou Radioactive Materials Management Laboratory Institute of Nuclear & Radiological Sciences & Technology, Energy & Safety, National
More informationJADROVÁ A VYRAĎOVACIA SPOLOČNOSŤ
JADROVÁ A VYRAĎOVACIA SPOLOČNOSŤ 01 JAVYS safely with every step JAVYS THE MISSION Safe, reliable, economically effective and efficient operation and decommissioning of nuclear facilities Safe, reliable,
More informationIgnalina NPP Near Surface Repository Technical project overview
Ignalina NPP Near Surface Repository Technical project overview RAW management scheme at INPP Operational waste Bitumized BITUMINISED RAW storage LRW STORAGE fclt. (B20) Cemented LRW storage facility SRW
More informationIgnalina NPP Closure and Decommissioning. Meeting the Cost
Ignalina NPP Closure and Decommissioning Meeting the Cost March 2011 the decommissioning of the Ignalina Nuclear Power Plant with two 1500 MW RBMK-type reactor units inherited from the former Soviet Union
More informationDecommissioning three main strategies: Immediate dismantling, Safe enclosure (Deferred dismantling), Entombment
: Immediate dismantling, Safe enclosure (Deferred dismantling), Entombment Dr. M Knaack TÜV NORD GmbH, Hamburg / Germany Overwiew Decommissioning when and why? Law, regulations and guidelines Three main
More informationTHE STATE SPECIALIZED ENTERPRISE CHERNOBYL NUCLEAR POWER PLANT
THE STATE SPECIALIZED ENTERPRISE CHERNOBYL NUCLEAR POWER PLANT 1 The State Specialized Enterprise Chernobyl NPP (SSE ChNPP) is the enterprise on power plants units decommissioning and Shelter Object transformation
More informationR3 Optioneering, Concept Design and EIAR Development
ROSATOM STATE CORPORATION COMPANY R3 Optioneering, Concept Design and EIAR Development Visaginas 25.10.2018 Our team Lithuanian partners Other Russian partners, if necessary Our team consists of the following
More informationSelection and evaluation of decontamination and dismantling techniques for the decommissioning of large NPPs components
Dr. Egidijus Babilas - Dr. Boris Brendebach Selection and evaluation of decontamination and dismantling techniques for the decommissioning of large NPPs components Content Motivation Generic selection
More informationChina, Philippines, Serbia, Brazil
GROUP 3 China, Philippines, Serbia, Brazil ASSUMPTIONS Only the reactor building will be decommissioned No fission products from SF fracture Simple technology Wastes go to interim storage Other materials
More informationPlant Life Management in Transition from Operation to Decommissioning of Nuclear Power Plants. National experience, Finland.
Plant Life Management in Transition from Operation to Decommissioning of Nuclear Power Plants. National experience, Finland. Jari Tuunanen, 30 Aug.2016 Contents Background Status of decommissioning plans
More informationCONDITIONING OF OPERATIONAL AND DECOMMISSIONING WASTES AT THE KARLSRUHE RESEARCH CENTER
CONDITIONING OF OPERATIONAL AND DECOMMISSIONING WASTES AT THE KARLSRUHE RESEARCH CENTER Iris Hillebrand, Reinhard Pfeiffer, Forschungszentrum Karlsruhe GmbH The Karlsruhe Research Center was founded in
More informationSafety Considerations in the Transition from Operation to Decommissioning of Research Reactors
Safety Considerations in the Transition from Operation to Decommissioning of Research Reactors Research Reactor Safety Section Division of Nuclear Installation Safety - EBP Workshop on the Transition Period
More informationD ECO M M I S S I O N I N G O F KOZ LO D U Y NPP UNITS 1 4 P RO G R E S S & C H A L L E N G E S
State Enterprise Radioactive Waste, Bulgaria D ECO M M I S S I O N I N G O F KOZ LO D U Y NPP UNITS 1 4 P RO G R E S S & C H A L L E N G E S Presented by: Momchil Kazakov Chief Technologist SD Decommissioning
More informationSergej Petrov Head of Dismantling and Decontamination Projects Engineering Support Subdivision
Methods of dismantling and decontamination applied during Ignalina s NPP decommissioning. Dismantling and decontamination technologies for the Ignalina NPP nuclear facilities. Sergej Petrov Head of Dismantling
More informationTREATMENT AND STORAGE OF WASTE FROM THE DECOMMISSIONING OF THE WINDSCALE PILE REACTOR. D H Norton, Project Manager British Nuclear Fuels plc
TREATMENT AND STORAGE OF WASTE FROM THE DECOMMISSIONING OF THE WINDSCALE PILE REACTOR ABSTRACT D H Norton, Project Manager British Nuclear Fuels plc W Botzem Nukem Nuklear A Dale Rolls Royce Nuclear Engineering
More informationDecommissioning of Nuclear Facilities. The Decommissioning Process. Lesson Objectives. Decommissioning. Decontamination. Decommissioning Objective
Lesson Objectives International Atomic Energy Agency Define specific decommissioning terms of Nuclear Facilities The Process Understand the decommissioning process Review the various decommissioning strategies
More informationDECOMMISSIONING LICENSING PROCESS OF NUCLEAR INSTALLATIONS IN SPAIN
DECOMMISSIONING LICENSING PROCESS OF NUCLEAR INSTALLATIONS IN SPAIN Preparation for decommissioning symposium February 16-18, Lyon France Cristina Correa Sáinz ccos@enresa.es 1 TABLE OF CONTENT TABLE OF
More informationSpent Fuel Management in Slovakia
Spent Fuel Management in Slovakia Juraj Václav Nuclear Regulatory Authority of the Slovak Republic International Conference on Management of Spent Fuel from Nuclear Power Reactors 31 May 4June2010 Vienna,
More informationRESULTS OF ACTIVITIES AT ANDREEVA BAY IN 2010 AND PLANS FOR 2011
ПРЕДПРИЯТИЕ ГОСКОРПОРАЦИИ «РОСАТОМ» OF ACTIVITIES AT ANDREEVA BAY IN AND FOR Anatoliy Grigoryev Alexander Shurukhin Oslo, Norway 16-17 February ANDREEVA BAY OF ACTIVITIES IMPLEMENTATION AT ANDREEVA BAY
More informationIPR-R1 TRIGA RESEARCH REACTOR DECOMMISSIONING: PRELIMINARY PLAN
2007 International Nuclear Atlantic Conference - INAC 2007 Santos, SP, Brazil, September 30 to October 5, 2007 ASSOCIAÇÃO BRASILEIRA DE ENERGIA NUCLEAR - ABEN ISBN: 978-85-99141-02-1 IPR-R1 TRIGA RESEARCH
More informationEDF DECOMMISSIONING PROGRAMME - A PREREQUISITE FOR THE ERECTION OF NEW NUCLEAR POWER PLANTS IN FRANCE
EDF DECOMMISSIONING PROGRAMME - A PREREQUISITE FOR THE ERECTION OF NEW NUCLEAR POWER PLANTS IN FRANCE J.-J. Grenouillet Electricité de France Dismantling, Waste management & Environment Engineering Center
More informationAn optimized cask technology for conditioning, transportation and long term interim storage of «End of Life» nuclear waste
An optimized cask technology for conditioning, transportation and long term interim storage of «End of Life» nuclear waste Gilles Clément 17th February 2016 Titre du document ~ February 2016 ~ 1 Waste
More informationZion Project Overview S. Chris Baker VP EH&S
Zion Project Overview S. Chris Baker VP EH&S 1 Agenda Asset Sale Agreement Organization Nuclear Decommissioning Process Overview of Zion Station Decommissioning Schedule Near Term Activities Spent Fuel
More informationClearance, Reuse, Recycle, disposal as VLLW.
Clearance, Reuse, Recycle, disposal as VLLW. A role for all of these options in the optimisation of rad management in decommissioning more work needed on optimisation Claudio Pescatore, OECD NEA Decommissioning
More informationRepublic of Lithuania
Republic of Lithuania Lithuanian National Report on Implementation of Council Directive 2011/70/EURATOM of 19 July 2011 Establishing a Community Framework for the Responsible and Safe Management of Spent
More informationBN-350 REACTOR SPENT FUEL HANDLING
BN-350 REACTOR SPENT FUEL HANDLING Presented by Shaiakhmet Shiganakov Kazakhstan Atomic Energy Committee Technical Meeting, Oskarshamn, Sweden, 26-28 April 2006 1 The Map of Kazakhstan Nuclear Installations
More informationSome Impact of Melting Scrap for the Decommissioning of Nuclear Power Plant Stade
Some Impact of Melting Scrap for the Decommissioning of Nuclear Power Plant Stade Dr. Georg U. Bacmeister. E.ON Kernkraft GmbH, NPP Stade Introduction The German NPP Stade (PWR, 630 MW electric) was shut
More informationRADIOACTIVE WASTE MANAGEMENT PROGRAMMES IN OECD/NEA MEMBER COUNTRIES CZECH REPUBLIC [2013] NATIONAL NUCLEAR ENERGY CONTEXT
RADIOACTIVE WASTE MANAGEMENT PROGRAMMES IN OECD/NEA MEMBER COUNTRIES CZECH REPUBLIC [2013] NATIONAL NUCLEAR ENERGY CONTEXT Utilization of nuclear energy in the Czech Republic started by establishing the
More information3.8 Radioactive Waste Management (RWM) Status in Thailand
3.8 Radioactive Waste Management (RWM) Status in Thailand The "Atom for Peace" program was launched after the end of the World War II. This stimulated the concepts of having an atomic energy research center
More informationManagement of Radioactive Waste The third priority of nuclear industry
Management of Radioactive Waste The third priority of nuclear industry Andras Toth Hungarian Atomic Energy Authority Zoltan Kiss Independent Investment Consultant IAEA TM on Safety Goals Framework for
More informationFIG. 1. Fort St. Vrain Nuclear Generation Station.
Invited Paper XA9848067 FORT ST. VRAIN DECOMMISSIONING PROJECT M. FISHER Public Service Company of Colorado, Denver, Colorado, USA Abstract Public Service Company of Colorado (PSCo), owner of the Fort
More informationRESEARCH REACTOR DECOMMISSIONING PLAN
RESEARCH REACTOR DECOMMISSIONING PLAN Clédola Cássia O. de Tello Pablo Andrade Grossi Brazil Contents General Aspects Ongoing Activities Decommissioning Plan Conclusion 1 TRIGA IPR-R1 REACTOR Four research
More informationRESEARCH REACTOR FRJ-1 (MERLIN) THE CORE STRUCTURES OF THE REACTOR BLOCK ARE DISMANTLED
RESEARCH REACTOR FRJ-1 (MERLIN) THE CORE STRUCTURES OF THE REACTOR BLOCK ARE DISMANTLED B. Stahn, R. Printz, K. Matela, C. Zehbe Forschungszentrum Jülich GmbH 52425 Jülich, Germany J. Pöppinghaus Gesellschaft
More informationWM2012 Conference, February 26 March 1, 2012, Phoenix, Arizona, USA
Modular Design of Processing and Storage Facilities for Small Volumes of Low and Intermediate Level Radioactive Waste including Disused Sealed Sources - 12372 David R. Keene*, Susanta Kumar Samanta** and
More informationStage 3. DETERMINING THE POSSIBILITIES OF DECOMMISSIONING THE REACTOR COMPARTMENTS
PROJECT Preliminary studies for the decommissioning of the reactor compartments of the former Paldiski military nuclear site and for the establishment of a radioactive waste repository Stage 3 DETERMINING
More informationRADIOLOGICAL PROTECTION DURING THE DISMANTLING OF NUCLEAR FACILITIES
Glasgow, 13-18 May 2012 RADIOLOGICAL PROTECTION DURING THE DISMANTLING OF Teresa Ortiz, Oscar González Radiological Protection Technical Unit Spanish National Radioactive Waste Management Company (ENRESA)
More informationSafety Issues in Construction of Facilities for Long-Term Storage of Radioactive Waste at Vector Site
O.Tokarevskyi N.Rybalka Z.Alekseeva S.Kondratiev Safety Issues in Construction of Facilities for Long-Term Storage of Radioactive Waste at Vector Site Vector Site The Vector site is located in the Chernobyl
More informationUNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C SAFETY EVALUATION REPORT
UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555-0001 SAFETY EVALUATION REPORT Docket No. 72-1040 HI-STORM UMAX Canister Storage System Holtec International, Inc. Certificate of Compliance
More informationTHE ROLE OF THE WORLD'S LARGEST INTERIM STORAGE FOR WASTE AND FUEL WITHIN THE DECOM PROJECT OF 6 WWER REACTORS IN GREIFSWALD AND RHEINSBERG (GERMANY)
THE ROLE OF THE WORLD'S LARGEST INTERIM STORAGE FOR WASTE AND FUEL WITHIN THE DECOM PROJECT OF 6 WWER REACTORS IN GREIFSWALD AND RHEINSBERG (GERMANY) Hartmann, Burkhard Leushacke, Dieter F. Dr Energiewerke
More informationRelease and demolition of buildings and concrete structures on the Greifswald site
Release and demolition of buildings and concrete structures on the Greifswald site Ronald Zimmer Eberhard Thurow Energiewerke Nord GmbH (December 2010) Page 1 Content 1. Strategy and boundary conditions
More informationPreparation for Future Defuelling and Decommissioning Works on EDF Energy s UK Fleet of Advanced Gas Cooled Reactors
PREDEC 2016: February 16-18, Lyon, France Preparation for Future Defuelling and Decommissioning Works on EDF Energy s UK Fleet of Advanced Gas Cooled Reactors John BRYERS, Simon ASHMEAD EDF Energy Generation
More informationBest practices for preparing vessel internals segmentation projects
Best practices for preparing vessel internals segmentation projects Joseph BOUCAU a*, Per SEGERUD b, Moisés SANCHEZ c a Westinghouse Electric Company, 43 rue de l Industrie, 1400 Nivelles, Belgium b Westinghouse
More informationComparison of estimated and actual decommissioning cost of José Cabrera NPP
Comparison of estimated and actual decommissioning cost of José Cabrera NPP International Conference on the Financing of Decommissioning Stockholm, 20-21 September 2016 Emilio García, Jorge Borque, Adolfo
More informationDECOMMISSIONING EXPERIENCE IN SPAIN. Manuel Rodríguez Silva
DECOMMISSIONING EXPERIENCE IN SPAIN Manuel Rodríguez Silva ISPRA, July 2011 Strategy: The Spanish Scenario Decommissioning responsibility Enresa RW Management Plan Financial aspects Enresa s Fund Final
More informationUnrestricted Release of Buildings and Site of NPP Versuchsatomkraftwerk Kahl - VAK
Unrestricted Release of Buildings and Site of NPP Versuchsatomkraftwerk Kahl - VAK Ingolf Auler, NIS Gerald Rudolph, NIS Walter Hackel, VAK IAEA Training Course on Release of Sites and Building Structures,
More informationStatus of Decommissioning Preparation for Kori #1
Status of Decommissioning Preparation for Kori #1 http://www.khnp.co.kr December 6, 2017 KHNP Overview (1/2) AA (S&P), Aa2 (Moody s) KHNP Overview (2/2) Power Plants Operational status in Korea 24 22,529
More informationDecommissioning plans for TVO's new reactors. Pekka Viitanen TVO
Decommissioning plans for TVO's new reactors Pekka Viitanen TVO Abstract In new NPP projects in Finland decommissioning has gained increasingly visible role already in licensing phase. E.g. for OL1 and
More informationJoint Convention on the Safety of Spent Fuel Management and on the Safety of Radioactive Waste Management
Joint Convention on the Safety of Spent Fuel Management and on the Safety of Radioactive Waste Management 5th as referred to in Article 32 of the Convention Sixth Review Meeting of Contracting Parties
More informationPRR-1 Decommissioning: Preparing for Dismantling and Decontamination. R2D2 Project Meeting, Manila, Philippines September
PRR-1 Decommissioning: Preparing for Dismantling and Decontamination R2D2 Project Meeting, Manila, Philippines 15-19 September 2008 1 Presented by Leonardo S. Leopando Philippine Nuclear Research Institute
More informationDecommissioning a Magnox Power Station
Slide 1 Decommissioning a Magnox Power Station Neutron Users Club 6 October 2005 H Madog Jones Trawsfynydd Decommissioning Site Slide 2 Trawsfynydd Power Station Role of the Nuclear Decommissioning Authority
More informationSaulius Piksrys Community ATGAJA CEE Bankwatch Network
NGO s cooperation with authorities to ensure social responsibility while shutting down Ignalina NPP Saulius Piksrys Community ATGAJA CEE Bankwatch Network CURRENT SITUATION IN ENERGY SECTOR No primary
More informationRadioactive Waste and Spent Fuel Management activities in the IAEA
Radioactive Waste and Spent Fuel Management activities in the Gérard Bruno Radioactive Waste and Spent Fuel Management Unit Department of Nuclear Safety and Security International Atomic Energy Agency
More informationRADIOACTIVE WASTE MANAGEMENT PROGRAMMES IN OECD/NEA MEMBER COUNTRIES SLOVENIA [2013] NATIONAL NUCLEAR ENERGY CONTEXT
RADIOACTIVE WASTE MANAGEMENT PROGRAMMES IN OECD/NEA MEMBER COUNTRIES SLOVENIA [2013] NATIONAL NUCLEAR ENERGY CONTEXT Production of nuclear energy plays a significant role in the national electricity supply.
More informationThe EnBW Strategyfor Decommissioningand DismantlingofNuclearPower Plants»
The EnBW Strategyfor Decommissioningand DismantlingofNuclearPower Plants» 40 th MPA-Seminar Stuttgart, 6 th & 7 th October2014 Peter Daiß, EnBW Kernkraft GmbH Content 1. Introduction and Company Profile
More informationRADIOACTIVE GRAPHITE MANAGEMENT AT UK MAGNOX NUCLEAR POWER STATIONS. G. HOLT British Nuclear Fuels plc, Berkeley, United Kingdom 1.
RADIOACTIVE GRAPHITE MANAGEMENT AT UK MAGNOX NUCLEAR POWER STATIONS G. HOLT British Nuclear Fuels plc, Berkeley, United Kingdom Abstract. The UK nuclear power industry is predominantly based on gas-cooled,
More informationRadiation Protection during Decommissioning of Nuclear Facilities Experiences and Challenges
Radiation Protection during Decommissioning of Nuclear Facilities Experiences and Challenges IRPA Glasgow 13 th International Congress of the International Radiation Protection Association 13 18 May 2012
More informationRAW management, decontamination techniques and methods used at SSE ChNPP
RAW management, decontamination techniques and methods used at SSE ChNPP RAW management at ChNPP Interim storage High-level waste (HLW) Low- and intermediatelevel waste (LILW) Below exemption level LLW
More informationRADIOACTIVE WASTE AND MANAGEMENT PROGRAMMES IN OECD/NEA MEMBER COUNTRIES SWEDEN [2010] NATIONAL NUCLEAR ENERGY CONTEXT
RADIOACTIVE WASTE AND MANAGEMENT PROGRAMMES IN OECD/NEA MEMBER COUNTRIES SWEDEN [2010] NATIONAL NUCLEAR ENERGY CONTEXT Commercial utilisation of nuclear power in Sweden started in 1972 and as of 2010 ten
More informationDECOMMISSIONING OF NUCLEAR FACILITIES IN UKRAINE
DECOMMISSIONING OF NUCLEAR FACILITIES IN UKRAINE Tatiana Kilochytska State Nuclear Regulatory Committee of Ukraine Annual Forum for Regulators and Operators in the Field of Decommissioning International
More informationImplementing Waste Led Decommissioning in Practice - Experiences from a Research Facility
Implementing Waste Led Decommissioning in Practice - Experiences from a Research Facility 2017-02-07 Per Lidar and Karin Strid, Studsvik Magnus Hörling, MAX IV Laboratory, Lund University Arne Larsson,
More informationINTRODUCTION. Note: The following is based on The Principles of Radioactive Waste Management [1].
INTRODUCTION The Principles of Radioactive Waste Management Note: The following is based on The Principles of Radioactive Waste Management [1]. Since the beginning of the twentieth century, research and
More informationDecommissioning Planning for Nuclear Units at the Oskarshamn Site
PREDEC 2016: Decommissioning Planning for Nuclear Units at the Oskarshamn Site, February 16-18, Lyon, France Decommissioning Planning for Nuclear Units at the Oskarshamn Site Thom RANNEMALM a, Jörgen ERIKSSON
More informationDevelopments in Disposal at the LLWR
Developments in Disposal at the LLWR IAEA International Workshop on the Safe Disposal of Low Level Radioactive Waste, Paris Date: February 2015 Dr Richard Cummings Head of Science and Engineering Presentation
More informationWASTE MANAGEMENT STRATEGY. French Experience in Legacy Waste Management. 1 st International Forum on the Decommissioning of the Fukushima Daiichi NPS
1 st International Forum on the Decommissioning of the Fukushima Daiichi NPS 10-11 th April, 2016 - Japan WASTE MANAGEMENT STRATEGY French Experience in Legacy Waste Management Chantal Mergui CEA / Nuclear
More informationThis document is the property of and contains Proprietary Information owned by Westinghouse Electric Company LLC and/or its subcontractors and
This document is the property of and contains Proprietary Information owned by Westinghouse Electric Company LLC and/or its subcontractors and suppliers. It is transmitted to you in confidence and trust,
More informationNuclear Aircraft Carrier Inactivation Approach for Waste Management and Exposure Reduction 14201
Nuclear Aircraft Carrier Inactivation Approach for Waste Management and Exposure Reduction 14201 ABSTRACT Irin P. Hall, Kimberly Grubb and Ashley Williams Newport News Shipbuilding Since 2007, Newport
More informationПРЕДПРИЯТИЕ ГОСКОРПОРАЦИИ «РОСАТОМ» STATE CORPORATION "ROSATOM GROUP OF COMPANIES
ПРЕДПРИЯТИЕ ГОСКОРПОРАЦИИ «РОСАТОМ» STATE CORPORATION "ROSATOM GROUP OF COMPANIES Development Program of Cask Technologies for Management of Spent Fuel Assemblies from Russian NPPs as Means of Harmonization
More informationStorage and disposal of radioactive waste in Italy
8 th edition of the International Summer School on Nuclear Decommissioning and Waste Management Storage and disposal of radioactive waste in Italy ANGELO PARATORE Sogin Deputy Director TRINO 15 th September
More informationRemediation of Chernobyl NPP Site. Vladimir Kholosha Valeriy Seyda Ukraine Vienna, January, 2013, IAEA
Remediation of Chernobyl NPP Site Vladimir Kholosha Valeriy Seyda Ukraine Vienna, 28-31 January, 2013, IAEA Chernobyl NPP. Construction Start 2 Commissioning Development of installed ChNPP capacities:
More informationWM 2010 Conference, March 7-11, 2010 Phoenix, AZ
Optimized Planning of the Disposal of radioactive Waste Packages exceeding the German Waste Acceptance Criteria Limits for Fissile Material Content and for Heat Generation - 10450 Peter Brennecke, Stefan
More informationPRESENT STATUS OF LEGAL & REGULATORY FRAMEWORK AND DECOMMISSIONING PLANNING FOR DNRR. Prepared by NUCLEAR RESEARCH INSTITUTE, VAEC.
TECHNICAL MEETING ON THE RESEARCH REACTOR DECOMMISSIONING DEMONSTRATION PROJECT: CHARACTERIZATION SURVEY PHILIPPINES, 3 7 DECEMBER 2007 PRESENT STATUS OF LEGAL & REGULATORY FRAMEWORK AND DECOMMISSIONING
More informationDecommissioning Studies for the Oskarshamn and Forsmark Nuclear Power Plants in Sweden
Decommissioning Studies for the Oskarshamn and Forsmark Nuclear Power Plants in Sweden Niklas Bergh, Gunnar Hedin, Mathias Edelborg, Jan Nordin Westinghouse Electric Sweden AB, Västerås, Sweden Fredrik
More informationCOMMUNICATION ABOUT RADIOACTIVE WASTE MANAGEMENT
COMMUNICATION ABOUT RADIOACTIVE WASTE MANAGEMENT IAEA Technical Meeting on Stakeholder Involvement and Public Information 13-16 June 2017 Rūta Jarašūnienė Public Relations Officer Radioactive waste management
More informationSpent Fuel and Spent Fuel Storage Facilities at Fukushima Daiichi
Spent Fuel and Spent Fuel Storage Facilities at Fukushima Daiichi The National Academies Lessons Learned from the Fukushima Nuclear Accident for Improving Safety and Security of U.S. Nuclear Plants: Phase
More informationDecommissioning Group Ketut Kamajaya
Decommissioning Group Ketut Kamajaya Contents of presentation Briefly history of Bandung TRIGA reactor Location of the facility Decommissioning options Characterization of System, Structure and Component
More informationIAEA CLASSIFICATION OF RADIOACTIVE WASTE
IAEA CLASSIFICATION OF RADIOACTIVE WASTE GERARD BRUNO Workshop on Clearance of Decommissioning Waste 6 9 November 2012, Bangkok, Thailand Outline Overview of radioactive waste arising Waste management
More informationAnd leading the way in decommissioning is Trawsfynydd. By Simon Parsons
The Trawsfynydd station in the magnificent setting of the Snowdonia National Park in Wales. Handling Legacy Waste Streams at Trawsfynydd The establishment of the U.K. Nuclear Decommissioning Authority
More informationDRAFT IMPLEMENTING DECREE. of 2016
1. ------IND- 2016 0202 CZ- EN- ------ 20160523 --- --- PROJET II. DRAFT IMPLEMENTING DECREE of 2016 on the requirements for the safe management of radioactive waste and on the decommissioning of nuclear
More informationSpanish Management Issues in Radioactive and Nuclear Waste Materials Dr. Amparo González Espartero
Spanish Management Issues in Radioactive and Nuclear Waste Materials Dr. Amparo González Espartero Senior Researcher Head of CIEMAT Quality Management CYTED- Energy Area Technical Secretary of Spanish
More informationRevised Mid-and-Long-Term Roadmap towards the Decommissioning of TEPCO s Fukushima Daiichi NPP Units 1-4
Revised Mid-and-Long-Term Roadmap towards the Decommissioning of TEPCO s Fukushima Daiichi NPP Units 1-4 Tatsuya Shinkawa Director, Nuclear Accident Response Office, Agency for Natural Resources and Energy,
More information