DISTRIBUTION SYSTEM ASSET CONDITION ASSESSMENT UPDATE

Size: px
Start display at page:

Download "DISTRIBUTION SYSTEM ASSET CONDITION ASSESSMENT UPDATE"

Transcription

1 EB-0-0 Exhibit D Page of DISTRIBUTION SYSTEM ASSET CONDITION ASSESSMENT UPDATE 0 EXECUTIVE SUMMARY Background Over the past number of years, THESL has put considerable effort into its Asset Management Program. In 00, a full Asset Condition Assessment ( ACA ) for key distribution assets was conducted by Kinectrics Inc. ( Kinectrics ). Between 00 and 00, THESL took steps to adopt the recommendations prescribed by the 00 ACA and to improve the quality of its asset condition data. Further, THESL developed the Health Index Calculator, an application that evaluates the Health Indices of assets based on current and best available inspection data. 0 In 00, using this Calculator, an ACA was again conducted by THESL. Kinectrics was engaged to audit the progress that THESL had made between 00 and 00, and to compare the results of the 00 and 00 ACA. Between 00 and 00, THESL continued to improve and to adopt the recommendations of the 00 audit. Kinectrics was asked to assess the changes and ACA results between 00 and 00 and produced a report describing the findings, the 00 ACA Audit. THESL continued to focus on the quantity and quality of data available to the ACA and has made further improvements in 0. This schedule shows a comparison of the ACA results between 00 and 0 and describes the changes. Key Achievements Between 00 and 0 Key achievements are highlighted below: Considerable efforts were made to increase the number of installed and inservice assets with sufficient information for condition assessment.

2 EB-0-0 Exhibit D Page of 0 0 Monthly tracking of maintenance program execution to ensure that all assets which were inspected per their maintenance cycle in the previous month had all inspection data recorded so that a health index is able to be calculated for that asset. Processes initiated to catch and reject maintenance records where the inspection data was incomplete, which and would lead to an asset having insufficient data to calculate a Health Index. This will force a crew to go back to that asset and complete the inspection record in its entirety before it can be submitted for completion and approved. A mobile inspection program was started for some of the maintenance inspections. Inspections are recorded on a handheld device instead of paper, which provides the ability to make inspection fields required by the ACA mandatory for completion, thus preventing inspectors from leaving inspection fields blank. More Wood Pole data has been migrated into the Asset Registry (Ellipse). Detailed assessments were conducted to determine which asset classes currently have data available in Ellipse such that dominant factors could be included in the calculation of the Health Index. For asset classes where there is insufficient data to implement the latest recommended Health Index formulations, THESL is in the process of including the new parameters in the maintenance inspection process. The calculator itself, which is now a Business Intelligence ( BI ) report, is enabling employees across the organization to see near real time asset conditions as the data is updated every hours. This facilitates efficiencies in capital projects as engineers can see which assets need to be addressed sooner based on the most current condition information.

3 EB-0-0 Exhibit D Page of 0 0 Comparison of 00 and 0 ACA Methodology Health Index ( HI ) formulation and results from 00 and 0 were compared for the same Asset Categories that were analyzed in the 00 ACA Audit: Stations Power Transformers Station Switchgear Air Blast Circuit Breaker Air Magnetic Circuit Breaker Oil Circuit breaker Oil KSO Circuit Breaker SF Circuit Breaker Vacuum Circuit Breaker Network Transformers Submersible Transformers Vault Transformers Pad-mounted Transformers ATS (Automatic Transfer Switch) Cable Chambers Wood Poles Phase Overhead Gang (Remote) Switches Phase Overhead Gang (Manual) Switches SCADAMATE Pad-mounted Switches Network Vaults Underground Cables (Direct-Buried XLPE) For all asset classes, the 0 assessments were made using the new business rule for capturing data from the last inspection date.

4 EB-0-0 Exhibit D Page of Audit Results This section describes the results of the 0 Audit. Changes in Health Index Formulation There have been no changes between 00 and 0 with respect to Condition Parameters, Weights and Condition Criteria for any of the assets in the ACA. 0 Changes in Asset Category Granularity The assets within each asset category do not represent a homogeneous set of equipment as there are variations in manufacturers, models, types, ratings, installations, environments, etc. All of these factors have impacts on the condition of individual assets and their corresponding Health Index. Changes in Population and Sample Size Table summarizes the changes in population and sample size included in the ACA between 00 and 0. Graphical representations of the data are given on Figure and Figure. 0 With the exception of Direct-Buried ( DB ) XLPE cable, all data used to calculate the population size, sample size and health index distribution comes from Ellipse. This is the enterprise resource planning ( ERP ) system which THESL uses to schedule the maintenance inspections for and record the inspection results of all assets that have regularly scheduled maintenance. The data used to calculate the Health Index for DB XLPE cable was extracted from the THESL GIS system called GEAR. This data was compiled and assessed separately, using the same methodology and formulation as before.

5 EB-0-0 Exhibit D Page of Table : Summary Changes in Population and Sample Size Population Sample Size % % Sample Population Asset Population Sample Sample Size Count Change % Size Size Change % Stations Power Transformers 0.% 0.%.% 0.% Station Switchgear 0.%.0%.%.% Air Blast CB 0.%.%.% Air Magnetic CB -.%.%.%.0% Oil CB.0%.0%.0% -.% Oil KSO CB.%.%.%.0% SF CB.%.%.0% -.% Vacuum CB 0.% 0.% 0.% Network Transformers -.%.0% 0.%.% 0 Submersible Transformers 0.%.%.%.0% Vault Transformers -0.%.%.0%.% Pad-mounted Transformers 00.0%.%.%.0% ATS -.%.%.%.% Cable Chambers 0 0.%.0%.%.% Wood Poles 00.%.%.%.% ф OH Gang (Rem) Switches 0 -.%.%.% 0.% ф OH Gang (Man) Switches.0%.%.0% -.% SCADAMATE Switches.0%.%.%.% Pad-mounted Switches -.%.%.% -.00% 0 Network Vaults 0 -.0%.0%.%.% UG Cable - DB XLPE.%

6 EB-0-0 Exhibit D Page of Changes in Population Network Vaults Padmounted Switches.0%.% SCADAMATE Switches.0% ф OH Gang (Man) Switches.0% ф OH Gang (Rem) Switches.% Wood Poles Cable Chambers.% 0.% ATS.% Padmounted Transformers Vault Transformers Asset Submersible Transformers Network Transformers 0.%.%.0% 0.% Vacuum CB SF CB.%.% Oil KSO CB.% Oil CB.0% Air Magnetic CB.% Air Blast CB Station Switchgear Stations Power Transformers 0.% 0.% 0.% 0% 0% 0% 0% 0% 0% 0% 0% 00% Population Change between 00 and 0 by Percentage Figure : Changes in Population

7 EB-0-0 Exhibit D Page of Changes in Sample Size UG Cable DB XLPE Network Vaults Padmounted Switches SCADAMATE Switches ф OH Gang (Man) Switches ф OH Gang (Rem) Switches Wood Poles Cable Chambers Asset ATS Padmounted Transformers Vault Transformers Submersible Transformers Network Transformers Vacuum CB SF CB Oil KSO CB Oil CB Air Magnetic CB Air Blast CB Station Switchgear Stations Power Transformers.00%.%.%.%.%.%.%.%.%.%.0% 0.%.%.%.%.0%.%.0%.% 0.%.0%.%.0%.0%.% 0.%.%.%.%.0%.%.%.0%.% 0.% 0.%.%.%.%.% 0% 0% 0% 0% 0% 0% 0% 00% 0% Percent Data Availability 0 00 Change between 00 and 0 Figure : Changes in Sample Size

8 EB-0-0 Exhibit D Page of 0 Changes in Population Population sizes have increased for some asset classes due to capital expenditures to improve system reliability. Of particular note are the population increases for padmounted transformers and SCADAMATE switches. Pad-mounted transformers have increased in population slightly due in part to installing pad-mounted transformers instead of submersible transformers in areas prone to flooding. The population of SCADAMATE switches has increased considerably as THESL continues its efforts to automate the distribution system. Automating these three-phase switches enables power system controllers (or automated software) to isolate faulted sections of feeders within minutes of a fault happening. This greatly reduces customer interruption time compared to the use of manual switches that require a crew to be dispatched. Improvement in data quality has led to changes in populations for manually and remotely operated overhead gang switches. Corrections to classification of switch type within Ellipse has led to a decrease in the population of remotely operated units which has translated to an apparent increase in both manually operated switches as well as SCADAMATE switches. 0 A decrease is also seen in the population of pad-mounted switches, as more robust equipment is being used as replacement in the event of equipment failure. For example, air-insulated pad-mounted switches are being replaced with sealed SF insulated type switchgear for improved reliability. Also SCADAMATE switches are being installed to replace legacy manually or remotely operated overhead gang switches as they reach endof-life to improve system reliability. Changes in Sample Size Efforts focusing on quality improvement have resulted in a sample size increase for out of 0 asset classes as outlined in the above tables.

9 EB-0-0 Exhibit D Page of Network Vaults and Transformers shows significant increase in sample size, due in part to the lack of completed inspection results at the time when the last audit was completed. Sample sizes increased significantly for ATS, Station Switchgear, Air Magnetic circuit breakers ( CB ) and Vacuum CB. 0 0 Generally, a sample size of ten percent is required to extrapolate ACA results over an entire population. The sample size for Station Switchgear, previously less than ten percent, has increased significantly to over percent. Manual Overhead Switch sample size remains below ten percent and showed a small decrease in sample size while remotely operated switches showed a slight increase in sample size. This can be attributed to improvements made in the identification of switch type via field checks; some switches previously recorded as manual were in fact remotely operated while some that were identified as remotely operated were in fact SCADAMATES. This is also a contributing factor to the large decrease in population size for remotely operated overhead gang switches. In summary, the transition of the ACA to a single uniform report accessible to all applicable groups was a large undertaking and a success. Though it is clear that further revisions of the Health Index Calculator are required to make use of all available inspection data, much time and effort is saved by the BI tool, as opposed to manually operating on Ellipse data in an MS Access database. Health Index Distribution Analysis The changes in Health Index distribution between 00 and 0 are summarized in Table.

10 EB-0-0 Exhibit D Page 0 of Table : Summary of Health Index Distribution Asset Year Very Poor Poor Fair Good Very Good % Sample % Change % Sample % Change % Sample % Change % Sample % Change % Sample % Change Network Transformers %.0%.0%.% -.% 0.% 0.%.0% -0.0% Submersible Transformers 00 0.%.%.0% 0.0% 0.%.% 0 0.0%.%.%.% -.% Vault Transformers 00 0.%.0%.%.% 0.% -0.% 0.% 0 0.%.%.%.% -0.% Padmounted Transformers 00 0.%.%.% 0.%.0% 0 0.%.%.% -.% ATS Cable Chambers Wood Poles 00.%.0%.%.% 0.%.% -.%.% 0 0.%.% 0.% 0.%.0% 00 0.%.%.%.%.% -0.0% -0.0% 0.0%.% 0 0.%.0%.0%.%.0% 00.%.%.%.%.% 0.%.% -.0%.% 0.%.%.%.%.% -.% -.% -.% ф OH Gang (Rem) Switches 00.%.%.% -.% -.0% 0.%.%.%.% ф OH Gang (Man) Switches 00.%.%.% -.00% -.% 0.%.%.%.% 0 SCADAMATE Switches 00.% 0.%.% 0.% -0.%.% 0 0.%.%.%.% -.%

11 EB-0-0 Exhibit D Page of Asset Year Very Poor Poor Fair Good Very Good % Sample % Change % Sample % Change % Sample % Change % Sample % Change % Sample % Change Padmounted Switches 00 0.%.0%.0%.% 0.% -.%.% 0 0.%.%.0%.% -.% Network Vaults 00.0%.0%.0%.0%.0% -0.% -0.% -.0%.% 0.%.% 0.0%.%.% -.% Stations Power Transformers 00.0%.%.%.%.% -.%.0% -.%.0% 0.%.00%.00%.%.%.% Station Switchgear Air Blast CB Air Magnetic CB Oil CB Oil KSO CB SF CB 0 Vacuum CB 00.%.%.%.%.% -.%.0% 0.0%.% 0.%.%.%.% 00.%.% 0.%.%.% -.% -.0% 0.0% 0.%.%.0% 00.%.%.%.%.%.% -.% 0.00%.%.%.00% 00 0.%.0%.%.% -0.0% -0.0% -0.% 0.% 0 0.%.%.%.0% 00.0%.0%.0%.0% -.% 0.% -.0% 0.%.%.00%.% 00.%.% -0.% -.% 0.%.%.% 00 0.%.% 0.% -0.0% -.0% -.% 0 0.%.%.%.%.% -0.% -.% -.%.0%.% UG Cable - DB XLPE 00.00%.00%.00%.00%.% -.0% -.0% -.% 0.%.0%.0%.%.0% -0.0%

12 EB-0-0 Exhibit D Page of The general trend for asset classes listed above is that the number of units in Good and Very Good condition is decreasing, while the number of units in Fair, Poor and Very Poor condition is increasing. This is representative of THESL s ageing infrastructure. UG Cable - DB XLPE Vacuum CB SF CB Oil KSO CB Oil CB Air Magnetic CB Air Blast CB Station Switchgear Stations Power Transformers Network Vaults Padmounted Switches SCADAMATE Switches ф OH Gang (Man) Switches ф OH Gang (Rem) Switches Wood Poles Cable Chambers ATS Padmounted Transformers Vault Transformers Submersible Transformers Network Transformers % 0% 0% 0% 0% 00% 0% 0% 0% 0% 0% 00% Very Poor Poor Fair Good Very Good Figure : Health Index Distribution Change Assets within the Health Index Calculator can be grouped into four main categories, stations assets, network distribution, overhead and underground. Though some asset classes can be found in more than one grouping, for instance cable chambers are found in

13 EB-0-0 Exhibit D Page of the network system and also in underground looped distribution, grouping the assets into these categories will assist with the overall system condition analysis. 0 Stations Assets Critical stations assets which the Health Index Calculator computes health indices for are: Stations Power Transformers Station Switchgear Air Blast Circuit Breaker Air Magnetic Circuit Breaker Oil Circuit breaker Oil KSO Circuit Breaker SF Circuit Breaker Vacuum Circuit Breaker 0 Over the last year the number of power transformers in good and very good condition has increased marginally; however there has been a noteworthy shift in the number of units in fair condition, a decrease of over four percent. As transformers have degraded from fair to poor condition, percent of these transformers are now rated as poor. This brings the total to station power transformers that are now either in very poor or poor condition. Very poor units pose the greatest risk to system reliability as they are the nearest to endof-life. These units need to be scheduled for replacement immediately so that plans can be created to replace these units within the next year. Units currently in poor condition are likely to degrade further into very poor condition; as such replacement for these units should be scheduled as soon as practicable as they will be the next units most likely to fail and cause power outages once the units in very poor condition have been replaced. Despite the large number of units in poor and very poor condition, it is important to note that percent of this asset class or power transformers, are currently in fair condition. An important decision must be made for a long-term plan to either increase

14 EB-0-0 Exhibit D Page of the maintenance work performed on these units to extend their useful life, or have them scheduled for replacement as soon as they have degraded into poor or very poor condition. 0 During the 00 audit, over half of the station switchgear asset class was listed in very poor condition. At that time, there was a lack of infrared scan inspection results to use as part of the HI calculation as recommended by Kinectrics. This data has since been acquired and entered into Ellipse. As a result, the number of units previously listed in very poor condition has been reduced to zero. These advanced inspection techniques and their results have enabled THESL to more accurately identify asset condition. THESL will be continuing to seek out new technologies, where applicable, that can be incorporated into maintenance practices with the benefit of developing a more rigorous Asset Management practice. 0 Despite this apparent improvement in the condition of station switchgears, almost 0 percent of the switchgears are still in poor condition. The replacement of these units is a significant challenge to THESL as switchgear decommissioning and replacement requires load transfers to adjacent feeders and stations which may not have available load capacity. To accommodate this work it is possible that other projects, such as voltage conversion, may be required to alleviate the amount of load that needs to be transferred so that the switchgear may be replaced. Long-term plans for increased maintenance on and/or replacement of the 0 units currently in fair condition must also be considered. Though the units are currently in fair condition, within the next ten years they may pose significant risk to system reliability as they degrade into poor and very poor condition. As can be seen from the asset class descriptions, there are currently six types of circuit breakers in use within THESLs distribution system. Despite the difference between the arc-quenching medium used in each type of breaker, all circuit breakers essentially serve the same purpose. As such analysis of the condition of circuit breakers will group

15 EB-0-0 Exhibit D Page of 0 together all types from this point forward. Combining the condition data of all types, 0 units are currently in poor condition and two are in very poor condition. Plans for replacement of the units in very poor condition should be started immediately as these units pose the greatest risk to system reliability of all circuit breakers in the ACA. Plans for the replacement of the 0 units currently in poor condition should be developed as soon as practicable as it is possible that these units may degrade further, into very poor condition, over the next three years. Replacement of 0 poor condition units presents the same challenges as the replacement of station switchgear in that surrounding feeders may not have the load capacity to absorb load transfers to accommodate the breaker replacement. Other developmental work, such as new feeder construction or voltage conversion, may need to first take place. Special attention should be given to the larger volume of circuit breakers (,0 units) currently in fair condition. These breakers will likely degrade into poor and very poor condition, over the next ten years. Long-term plans must be developed to ensure these units are either maintained to delay degradation or replaced after they move to poor and very poor condition. Given the significantly large number of units to eventually replace and the current system load capacity limits, gradually phasing out the units in the worst condition over time may be the only option, short of new station construction. 0 Network Assets Critical network assets which the Health Index Calculator computes health indices for are: Network Vaults Cable Chambers Network Transformers ATS

16 EB-0-0 Exhibit D Page of 0 Since the 00 audit, the number of vaults in poor and very poor condition has shown little change. Of all in-service network vaults, are currently in very poor condition while are in poor condition. Structural repair of these vaults poses a significant challenge in that many are located under main streets in the downtown core. Work to maintain the structural integrity of these vaults may create traffic and pedestrian obstacles and delays. Consequently, THESL may be limited to only working on a specific number of vaults per year to keep the traffic disruptions to an acceptable level. Given that, development of long term plans to repair the vaults currently in fair condition is critical as they continue to deteriorate to poor and very poor condition over the next decade. The shifting of over two percent of vaults from very good to good condition over the past year is also an indicator that some vaults which only last year were in very good condition, are already starting to deteriorate. 0 Over the last year, there has also been a significant shift of Network Transformers from good to fair condition. In total, of these transformers are currently in fair condition. Replacement of these units requires very detailed planning as their replacement may need to happen in conjunction with network vault rebuilds or cable replacement. During this time a network may be running under contingency for extended amounts of time while the improvement work is executed. This may require that other projects designed to increase the load capacity or contingency capability of the network be executed before actual transformer replacements. However, as the condition of these units deteriorates, plans should be made to maximize economies of scale in the replacement of other network components, in addition to the select transformers. The ATS grouping has continued to see asset condition degradation to the point where over percent of the asset class is now in poor or very poor condition. This amounts to eight units in very poor condition and in poor condition. Given the extremely high impact of failure of network electrical components, the units in very poor condition

17 EB-0-0 Exhibit D Page of 0 should be replaced within the next year as the probability for failure is high. The units in poor condition should be scheduled for replacement as soon as practicable, given the high impact that a failure could create. The shifting of condition for this asset class to poor and very poor has resulted in a reduction of the number of units in fair condition; this now stands at eight. Long-term plans should be developed to phase out these units over the next number of years as they degrade to poor and very poor condition. Given the obsolescence of these components due to their age, it may be beneficial to replace some of the units in conjunction with other network projects such as vault rebuilds or transformer replacements. This will help to gain efficiencies in terms of project planning, scheduling and coordination between groups within and external to THESL. Overhead Assets The Health Index Calculator computes health indices for the following critical overhead assets: Wood Poles Phase Overhead Gang (Rem.) Switches Phase Overhead Gang (Man.) Switches SCADAMATE 0 After continuing the migration of wood pole inspection data to Ellipse so that health index scores can be calculated, a slight decrease can be seen in the percentage of population in fair condition. This reduction of units in fair condition actually shifted to an increase in the percentage of population in poor and very poor condition. Currently over percent of the population of wood poles are either in poor or very poor condition. Though this percentage may seem small, one must take into account the fact that the population itself is very large at 0,0 wood poles. This brings the number of poles in very poor condition to, and the number of poles in poor condition to,. In addition to these poles, almost 0 percent of the population is listed as fair condition

18 EB-0-0 Exhibit D Page of amounting to, poles. The replacement of, poles over the next three years together with developing long-term plans to replace over,000 poles over the next ten years presents a significant challenge for THESL. In addition to all other civil work being completed by THESL, such as cable duct bank, pad and vault installations, pole replacements will create an extremely large volume of permits that will need to be acquired before construction can begin. This has the potential to limit THESL s ability to maximize efficiencies that can be gained by the replacement of all poles close to end-oflife that are along the same street as opposed to spot replacement of only the poles in the worst conditions. 0 0 Though pole condition itself is a major factor in the decision to replace a pole, other factors such as the condition or obsolescence of attachments, or other work required in the area, may also be taken into account. For example, it may not make sense to rehabilitate a single pole that still has porcelain insulators and is near its end-of-life to accommodate a new tree-proof conductor when it is on a street where all other poles are at end-of-life. The risks of failing to replace that pole along with all the others may be much greater than the potential savings from deferring its replacement to a later date. In this example, the outage that could result from the failure of that pole would negate all of the effort expended to replace the other end-of-life poles as the customers would still experience a power interruption. Overhead ganged switches, both manual and remotely operated, are used within the distribution system to isolate faulted sections of the feeder. They are connected to the trunk of the feeder and actuate all three phases simultaneously to either isolate or restore power to a section of the trunk. Given the potential impact to thousands of customers in the event of a switch malfunction, routine maintenance and testing of these switches is performed to ensure seamless operation, if and when required in the future. Currently none of these switches are in poor or very poor condition; however, nearly percent of

19 EB-0-0 Exhibit D Page of 0 0 all manually and remotely operated overhead gang switches are in fair condition. This amounts to units which are likely to degrade into poor and very poor condition over the next ten years. Given the reliability impact of a switch failure, long-term plans should be made to phase out these switches as they degrade into poor and very poor condition. If these long-term plans incorporate replacing these end-of-life switches with automated ones capable of inclusion in feeder automation, great improvements to overall system reliability may be achieved. SCADAMATE switches differ from remotely operated overhead gang switches in that they have the capability to be included in automatic restoration schemes; this is commonly referred to as feeder automation. Feeder automation allows for teams of switches to automatically isolate faulted sections of the system and maximize the load restored within one minute of a fault occurring. These switches have great potential for improving system reliability and as such are a critical component for the modernization of the grid. Currently there are two switches in poor condition which should be replaced as soon as practicable and ten switches in fair condition which may degrade into poor and very poor condition over the next ten years. Overall percent of SCADAMATE switches are either in good or very good condition. Given the reliability improvement potential of these switches, efforts should be made to ensure the continued good health of this asset class. Underground Assets Critical underground assets which the Health Index Calculator computes health indices for are: Vault Transformers Pad-mounted Transformers Submersible Transformers Pad-mounted Switches

20 EB-0-0 Exhibit D Page 0 of Cable Chambers Underground Cables (Direct-Buried XLPE) 0 The vault transformers asset class has seen a slight shift from very good to good, and from fair to poor condition over the last year. Currently there are vault transformers listed in poor condition. These should be replaced as soon as practicable as they are likely to degrade to very poor condition over the next three years. Though the percentage of this asset class in fair condition is only slightly over percent, due to the large population this amounts to,0 vault transformers which may degrade to poor and very poor condition over the next ten years. Replacement of these transformers will be a challenge to THESL as these transformers are often the only source of power for the buildings in which they are located. Long duration outages will need to be scheduled on a customer by customer basis over the next ten years to address all units currently in fair condition. For some customers who operate on a / basis, alternative solutions to power outages may need to be found, such as supplying temporary backup generators to maintain power while the vault transformers are being replaced. Having to supply and fuel a generator for the customer will increase the overall cost of the transformer replacement. 0 The vast majority of pad-mounted transformers are in good or very good condition; however over the last year there has been a significant shift from very good to good condition and a slight increase was also seen in the percentage of units in fair condition. There are currently units in fair condition which need to have long term plans in place for replacement over the next ten years as they degrade to poor and very poor condition. Despite the large volume of new submersible transformers being installed in the system, dramatic shifts are still taking place from very good to good condition. There is currently only one unit listed in poor condition and 0 units in fair condition. The standardization

21 EB-0-0 Exhibit D Page of and reliability improvement programs to replace non-switchable transformers with standard switchable ones is helping to keep the number of units in poor and very poor condition at a minimum; however, despite this, submersible transformers continue to be a contributing factor to underground reliability issues. Efforts will be made to improve the inspection process and asset health calculation so that the ACA more truly reflects the reliability performance of this asset class. Notwithstanding these actions, long-term plans are still needed over the next ten years to replace the units currently in fair condition as they degrade to poor and very poor condition. 0 0 A significant number of pad-mounted switches have shifted from very good to good condition over the last year. There has also been a large shift from fair to good condition, due in part to the increase in maintenance activities on this asset, such as more frequent infra-red inspections as well as more frequent cleanings. Despite these improved maintenance practices, some units have shifted from fair to poor condition. Currently there are five units in poor condition that need to be replaced as soon as practicable. Padmounted switches are connected to the trunk of underground feeders and serve the same purpose as overhead gang switches do for overhead feeders; they isolate and restore power to sections of the feeder by operating all three phases simultaneously. Isolation of these pad-mounted switches can be very time consuming as they may feed multiple distribution sub-loops. Careful planning of switching order and feeder contingency operation is required before replacement can take place. A particular challenge for THESL will be in addressing the units currently in fair condition. Long-term plans for phasing out these units as they degrade over the next ten years are required. Cable chambers, typically located near roadways, may cause significant traffic disruption during their repair or replacement. Currently there are units listed in very poor condition and in poor condition. These units must be addressed in the very near future. In addition, the cable chambers currently in fair condition are a significant

22 EB-0-0 Exhibit D Page of part of the total population. Similar to network vaults, long-term plans must be in place to address these cable chambers as they deteriorate into poor and very poor condition over the next decade. 0 Direct-buried XLPE cable has seen very significant deterioration into the very poor category over the last year. Almost 0 percent (kilometres) of direct-buried XLPE cable is rated as very poor. Despite the fact that significant capital has been invested to remove this direct-buried cable from the system, the number of faults in 00 from primary cables and splices remains the same as it was in 00. At this point, less than seven percent of direct-buried cable in the system is in very good or good condition, while over percent of these cables are in fair, poor or very poor condition. Essentially, all direct-buried cable will need to be replaced within the system over the next ten years with over half of that cable currently at the highest risk of failure and therefore having the highest probability of negatively impacting reliability. Without replacement, reliability impacts will continue to increase as the remaining direct-buried cable in the system deteriorates. 0 Conclusions THESL s Asset Management Program has improved between 00 and 0 in the following ways: Efforts have been made to consolidate asset information as Wood Pole data continue to be migrated into Ellipse. All Health Index calculations are now computed by a single tool which is accessible to everyone in the organization. This not only improves the ACA itself, but the degree to which it is utilized by THESL as an organization in planning asset renewal and replacement.

23 EB-0-0 Exhibit D Page of By focusing on last inspection data, the Health Index Calculator is helping to drive improvements in overall data quality by identifying assets with incomplete inspection records within hours of data entry. Over half of the asset categories showed an increase in the number of assets that had sufficient data to calculate a Health Index. Efforts are underway to implement newer formulations of the Health Index for certain asset classes as recommended by Kinectrics.

DISTRIBUTION SYSTEM SYSTEM CHALLENGES

DISTRIBUTION SYSTEM SYSTEM CHALLENGES EB-0-0 Exhibit D Page of 0 0 0 DISTRIBUTION SYSTEM SYSTEM CHALLENGES INTRODUCTION The electrical distribution system owned and operated by Toronto Hydro-Electric System Limited ( THESL ) is comprised of

More information

Analysis of distribution system reliability and outage rates

Analysis of distribution system reliability and outage rates Reclosers Technical Data TD280026EN Supersedes pril 2003 (R280-90-7) COOPER POWER SERIES nalysis of distribution system reliability and outage rates Recloser Technical Data TD280026EN nalysis of distribution

More information

DOWNTOWN UNDERGROUND NETWORK SECONDARY SERVICES GUIDELINES

DOWNTOWN UNDERGROUND NETWORK SECONDARY SERVICES GUIDELINES Guidelines effective March 5, 2007 NES is committed to providing safe, reliable electric service at a reasonable price for all of our customers. These guidelines offer direction for activities relating

More information

Withlacoochee River Electric Cooperative, Inc. P.O. Box 278 Dade City, FL Billy E. Brown, Executive V.P.

Withlacoochee River Electric Cooperative, Inc. P.O. Box 278 Dade City, FL Billy E. Brown, Executive V.P. Wednesday, February 25, 2015 PSC 25 6.0343 Municipal Electric Utility and Rural Electric Cooperative Reporting Requirements Withlacoochee River Electric Cooperative, Inc. P.O. Box 278 Dade City, FL 33526-0278

More information

Transmission Owner Asset Management

Transmission Owner Asset Management Transmission Owner Asset Management Pieces of Asset Management New customers, load growth, repairs, maintenance, operational issues, etc. All the pieces make up the asset management plan for repair or

More information

GRU Storm Hardening Report to the Florida Public Service Commission Pursuant to Rule , F.A.C. Calendar Year 2014

GRU Storm Hardening Report to the Florida Public Service Commission Pursuant to Rule , F.A.C. Calendar Year 2014 1) Introduction GRU Storm Hardening Report to the Florida Public Service Commission Pursuant to Rule 25-6.0343, F.A.C. Calendar Year 2014 a) Gainesville Regional Utilities (GRU) b) 4747 N. Main Street

More information

ELECTRIC INFRASTRUCTURE RELIABILITY PERFORMANCE INDICATORS

ELECTRIC INFRASTRUCTURE RELIABILITY PERFORMANCE INDICATORS Page of 8 ELECTRIC INFRASTRUCTURE RELIABILITY PERFORMANCE INDICATORS 7 8 9 0 FIVE-YEAR HISTORICAL RELIABILITY PERFORMANCE General THESL tracks reliability performance indicators System Average Interruption

More information

Kissimmee Utility Authority Storm Hardening Report to the Florida Public Service Commission Pursuant to Rule , F.A.C. Calendar Year 2006

Kissimmee Utility Authority Storm Hardening Report to the Florida Public Service Commission Pursuant to Rule , F.A.C. Calendar Year 2006 Kissimmee Utility Authority Storm Hardening Report to the Florida Public Service Commission Pursuant to Rule 25-6.0343, F.A.C. Calendar Year 2006 1) Introduction This report is filed in response to the

More information

Basic Reliability Analysis of Electrical Power Systems

Basic Reliability Analysis of Electrical Power Systems Basic Reliability Analysis of Electrical Power Systems Course No: E03-020 Credit: 3 PDH Velimir Lackovic, Char. Eng. Continuing Education and Development, Inc. 9 Greyridge Farm Court Stony Point, NY 10980

More information

POTOMAC ELECTRIC POWER COMPANY

POTOMAC ELECTRIC POWER COMPANY POTOMAC ELECTRIC POWER COMPANY FERC Form 715 (Part 4) - Transmission Planning Study Guidelines Transmission Reliability Guidelines 1. General Overview The reliability guidelines used to plan the transmission

More information

Smart Distribution Applications and Technologies - Program 124

Smart Distribution Applications and Technologies - Program 124 Smart Distribution Applications and Technologies - Program 124 Program Description Program Overview New technologies will be critical to future smart grid operation. These technologies will include advanced

More information

Medium Voltage Service Maintenance and refurbishment

Medium Voltage Service Maintenance and refurbishment Medium Voltage Service Maintenance and refurbishment 2 Service maintenance and refurbishment Brochure Table of contents Maintenance strategies - Concepts...4 Preventative maintenance/testing...6 Preventative

More information

NEEDS ASSESSMENT REPORT

NEEDS ASSESSMENT REPORT Hydro One Networks Inc. 483 Bay Street Toronto, Ontario M5G 2P5 NEEDS ASSESSMENT REPORT Toronto Region Date: October 18, 2017 Prepared by: Toronto Region Study Team Disclaimer This Needs Assessment Report

More information

GV 001 Equipment Bases and Enclosures General Information

GV 001 Equipment Bases and Enclosures General Information Eq u ip me n tba s e s a n d En c lo s u re s Ge n e ra lin fo rma tio n E n g in e e r :R.An th o n GV0 0 1 Ap p r o v e r :Jo s h u a Jo n e s Ap r 1 7 2 0 Ap r1 7 GV 001 Equipment Bases and Enclosures

More information

PLANNING GUIDE FOR SINGLE CUSTOMER SUBSTATIONS SERVED FROM TRANSMISSION LINES

PLANNING GUIDE FOR SINGLE CUSTOMER SUBSTATIONS SERVED FROM TRANSMISSION LINES Prepared by: NIB/EOB PLANNING GUIDE FOR SINGLE CUSTOMER SUBSTATIONS SERVED FROM TRANSMISSION LINES 05503 Department: Electric T&D Section: T&D Engineering and Technical Support Approved by: G.O. Duru (GOD)

More information

Long Beach July 2015 Secondary Network Outages RCE. Summary and Report

Long Beach July 2015 Secondary Network Outages RCE. Summary and Report Long Beach July 2015 Secondary Network Outages RCE Summary and Report 1 P age Table of Contents Background... 3 Root Cause... 5 Chronology... 7 Immediate, Interim, and Corrective Actions... 12 Exhibit

More information

Contact Voltage at Toronto Hydro

Contact Voltage at Toronto Hydro Contact Voltage at Toronto Hydro Detection, Mitigation, Prevention Presented by: Ben La Pianta, P.Eng., MBA Vice President Distribution Grid Management 2009 Jodie Lane National Conference Stray Voltage

More information

Alvin.Xu, ABB Xiamen Switchgear Co,Ltd, Green & Energy saving concept of ABB MV apparatus For a better tomorrow.

Alvin.Xu, ABB Xiamen Switchgear Co,Ltd, Green & Energy saving concept of ABB MV apparatus For a better tomorrow. Alvin.Xu, ABB Xiamen Switchgear Co,Ltd, 2014-11 Green & Energy saving concept of ABB MV apparatus For a better tomorrow Slide 1 VD4 vacuum circuit-breaker in China Inheritance and innovation Y1992 Y2003

More information

2014 Reliability Plan. Annual Planning Report

2014 Reliability Plan. Annual Planning Report Annual Planning Report 2 Annual Planning Report Executive Summary Hydro Ottawa s reliability performance in 2013 did not meet our expected targets. Interruption categories such as defective equipment and

More information

Grid Solutions. ASSET PERFORMANCE MANAGEMENT for Electrical Substations

Grid Solutions. ASSET PERFORMANCE MANAGEMENT for Electrical Substations Grid Solutions ASSET PERFORMANCE MANAGEMENT for Electrical Substations Electrical equipment is a critical component of an asset portfolio. Beyond its financial value, it plays an even greater role in overall

More information

DOMESTIC ELECTRICAL INSTALLATION PERIODIC INSPECTION REPORT (FOR A SINGLE DWELLING) B ADDRESS AND DETAILS OF THE INSTALLATION Address: SPECIMEN

DOMESTIC ELECTRICAL INSTALLATION PERIODIC INSPECTION REPORT (FOR A SINGLE DWELLING) B ADDRESS AND DETAILS OF THE INSTALLATION Address: SPECIMEN A DETAILS OF THE CLIENT Client / Address: C PURPOSE OF THE REPORT Purpose for which this report is required: E PARTICULARS OF THE CONTRACTOR Trading Title: Address: DOMESTIC ELECTRICAL INSTALLATION PERIODIC

More information

Reference report Oil & Gas

Reference report Oil & Gas Distributed generator management with WinCC OA The system integrator DMC, Inc., works extensively with a manufacturer of heat and power cogeneration systems used in a wide variety of industries from oil

More information

Detailed Requirements Document (DRD) Rail Engineering Advanced Technician Level 4 Electrification Knowledge & Skills Content

Detailed Requirements Document (DRD) Rail Engineering Advanced Technician Level 4 Electrification Knowledge & Skills Content Detailed Requirements Document (DRD) Rail Engineering Advanced Technician Level 4 Electrification Knowledge & Skills Content Purpose The purpose of this Detailed Requirements Document (DRD) is to provide

More information

Smart Grid Demonstrations Cost and Benefit Analysis Methodology

Smart Grid Demonstrations Cost and Benefit Analysis Methodology Presentation Identifier (Title or Location), Month 00, 2008 Cost and Benefit Analysis Framework: Update EPRI Smart Grid Advisory Meeting October 14, 2009 Albuquerque, New Mexico Steve Bossart Director,

More information

PAPUC Proposed Inspection and Maintenance Standards FirstEnergy s Comments

PAPUC Proposed Inspection and Maintenance Standards FirstEnergy s Comments PAPUC Proposed Inspection and Maintenance Standards FirstEnergy s Comments Good morning. My name is Eric Dickson, and I would like to thank the Commission and its staff for giving FirstEnergy an opportunity

More information

Leaside to Main Infrastructure Refurbishment Project Strengthening the transmission system in your neighbourhood

Leaside to Main Infrastructure Refurbishment Project Strengthening the transmission system in your neighbourhood Leaside to Main Infrastructure Refurbishment Project Strengthening the transmission system in your neighbourhood Purpose of this Public Information Centre Provide you with an update on Hydro One s infrastructure

More information

Partnering for reliable distribution

Partnering for reliable distribution Published by and copyright 013: Siemens AG Infrastructure & Cities Sector Smart Grid Division Humboldtstr. 59 90459 Nuremberg, Germany Further information is available from our Customer Support Center

More information

Product-related services for switchgear, transformers, and cables

Product-related services for switchgear, transformers, and cables Product-related services for switchgear, transformers, and cables Making the most of your T&D assets Asset Services/Product-related services Switchgear Services Transformer Services Cable and Line Services

More information

Asset Risk Assessment Through Advanced Analytics. Cop yri g h t 2014 OSIso f t, LLC.

Asset Risk Assessment Through Advanced Analytics. Cop yri g h t 2014 OSIso f t, LLC. Asset Risk Assessment Through Advanced Analytics Presented by Richard Wernsing Contacts Public Service Electric & Gas Richard Wernsing Cell: 973-303-889 Email: Richard.wernsing@pseg.com OSIsoft Kevin Walsh

More information

What new capabilities

What new capabilities White Paper Emerging Trends in Analytics What new capabilities mean for distribution grid management Kent Hedrick Director of Grid Management Solutions at Landis+Gyr Future. Ready. SM July 2014 Analytics

More information

ICM Project. Externally Initiated Plant Relocations and Expansions. Waterfront Toronto. Toronto Hydro Electric System Limited (THESL)

ICM Project. Externally Initiated Plant Relocations and Expansions. Waterfront Toronto. Toronto Hydro Electric System Limited (THESL) ( pages) ICM Project Waterfront Go Transit / Metrolinx Minsitry of Transportiation / City of (THESL) I EXECUTIVE SUMMARY. Project Description 0 Construction by governmental and other agencies within the

More information

6. SECONDARY SERVICES (under 600 volts) 6.1 AVAILABILITY For the electrical characteristics of available secondary services see Section 3.4.

6. SECONDARY SERVICES (under 600 volts) 6.1 AVAILABILITY For the electrical characteristics of available secondary services see Section 3.4. 6. SECONDARY SERVICES (under 600 volts) 6.1 AVAILABILITY For the electrical characteristics of available secondary services see Section 3.4. 6.2 OVERHEAD SERVICES Wiring of any premises for connection

More information

Asset Management and Maintenance in Transmission and Distribution Networks

Asset Management and Maintenance in Transmission and Distribution Networks Asset and Maintenance in Transmission and Distribution Networks S. Surender Reddy Department of Railroad and Electrical System Engineering, Woosong University 171 Dongdaejeon-ro, Jayang-dong, Dong-gu,

More information

Optimal network topology and reliability indices to be used in the design of power distribution networks in oil and gas plants *

Optimal network topology and reliability indices to be used in the design of power distribution networks in oil and gas plants * Optimal network topology and reliability indices to be used in the design of power distribution networks in oil and gas plants * R Naidoo and EJ Manning University of Pretoria, Pretoria, South Africa ABSTRACT:

More information

Electrical Networks Principles and Performance

Electrical Networks Principles and Performance Engineering Standard Electrical Networks Electrical Networks Principles and Performance Version: 1 Issued: January 2015 Owner: Chief Engineer Approved By: Paul O Halloran Chief Engineer PRINTOUT MAY NOT

More information

School of Electrical Engineering and Computer Science. Expansion: Analysis, and Formulation. Washington State University

School of Electrical Engineering and Computer Science. Expansion: Analysis, and Formulation. Washington State University Distributed Generation Expansion: Analysis, Directions, Modeling, and Formulation Kevin Tomsovic Kevin Tomsovic Washington State University Importance of Distribution Systems Reliability under competition

More information

Pepco s Reliability Enhancement Model Using Predictive Reliability to Plan Investment in Electrical Infrastructure

Pepco s Reliability Enhancement Model Using Predictive Reliability to Plan Investment in Electrical Infrastructure 1 Pepco s Reliability Enhancement Model Using Predictive Reliability to Plan Investment in Electrical Infrastructure General Meeting of the IEEE Power Engineering Society Panel Discussion Predictive Reliability

More information

Secondary Electrical Maintenance Service. Scope of Work

Secondary Electrical Maintenance Service. Scope of Work Secondary Electrical Maintenance Service Scope of Work Reviewed By: Approved By: Version 3.0 Date 080907 Author K.Vandenbussche 1 Background The Integrated Service Provider s program will provide superior

More information

Survey and Summary of Best Practices for Distribution Reliability Improvement. December 8, p.m. EST

Survey and Summary of Best Practices for Distribution Reliability Improvement. December 8, p.m. EST Survey and Summary of Best Practices for Distribution Reliability Improvement December 8, 2016 2 3 p.m. EST Webinar Overview Moderator: Speaker: Michele Suddleson DEED Program Director American Public

More information

EFFECTIVE DATE: November 1, 2011, unless a later date is cited at the end of a section. [ NMAC - Rp,

EFFECTIVE DATE: November 1, 2011, unless a later date is cited at the end of a section. [ NMAC - Rp, TITLE 14 CHAPTER 10 PART 4 HOUSING AND CONSTRUCTION ELECTRICAL CODES 2011 NEW MEXICO ELECTRICAL CODE 14.10.4.1 ISSUING AGENCY: The Construction Industries Division of the Regulation and Licensing Department.

More information

DUQUESNE LIGHT COMPANY TRANSMISSION PLANNING CRITERIA

DUQUESNE LIGHT COMPANY TRANSMISSION PLANNING CRITERIA DUQUESNE LIGHT COMPANY TRANSMISSION PLANNING CRITERIA Transmission Planning Criteria Updated: March Compiled: September 2007 Compiled from: s Comprehensive Transmission Reliability Plan, July 2005 s Strategic

More information

Same As Client Address SPECIMEN. operational limitations. of the inspection and. agreed with):

Same As Client Address SPECIMEN. operational limitations. of the inspection and. agreed with): DOMESTIC ELECTRICAL INSTALLATION CONDITION REPORT Issued in accordance with British Standard BS 7671 - Requirements for Electrical Installations Certificate Reference: DEICR000021652 1 DETAILS OF THE CLIENT

More information

AMI information. for improved outage management

AMI information. for improved outage management Utilities the way we see it AMI information for improved outage management The information contained in this document is proprietary. 2013 Capgemini. All rights reserved. Rightshore is a trademark belonging

More information

ATTACHMENT 13 NORTHEAST-POCONO RELIABILITY PROJECT PPL DESIGN CRITERIA AND SAFETY PRACTICES

ATTACHMENT 13 NORTHEAST-POCONO RELIABILITY PROJECT PPL DESIGN CRITERIA AND SAFETY PRACTICES ATTACHMENT 13 NORTHEAST-POCONO RELIABILITY PROJECT PPL DESIGN CRITERIA AND SAFETY PRACTICES The National Electrical Safety Code (NESC) is a set of rules to safeguard people during the installation, operation,

More information

Circuit Breaker Asset Management Using Intelligent Electronic Device (IED)- Based Health Monitoring

Circuit Breaker Asset Management Using Intelligent Electronic Device (IED)- Based Health Monitoring 21, rue d Artois, F-75008 PARIS CIGRE US National Committee http : //www.cigre.org 2014 Grid of the Future Symposium Circuit Breaker Asset Management Using Intelligent Electronic Device (IED)- Based Health

More information

E(Orlando, Florida, U.S.), knocking

E(Orlando, Florida, U.S.), knocking Fleet Tracking Enables Efficient Crew Dispatch Progress Energy Florida integrates OMS, AVL to create mobile outage management system. By Claude Pitts, Progress Energy Florida arlier this year, a violent

More information

CHILLED WATER PRODUCTION SUB-ELEMENT

CHILLED WATER PRODUCTION SUB-ELEMENT CHILLED WATER PRODUCTION SUB-ELEMENT The University of Central Florida employs three chilled water production plants combined with a three million gallon thermal energy storage tank to augment the chilled

More information

DATE: September 8, 2014 REPORT NO. PW Chair and Members Committee of the Whole Operations and Administration

DATE: September 8, 2014 REPORT NO. PW Chair and Members Committee of the Whole Operations and Administration PUBLIC WORKS COMMISSION DATE: September 8, 2014 REPORT NO. PW2014-047 TO: FROM: Chair and Members Committee of the Whole Operations and Administration Geoff Rae, MBA, P.Eng. General Manager, Public Works

More information

20 Ways to Save Time & Money Implementing Contracting Cost Tracking Software

20 Ways to Save Time & Money Implementing Contracting Cost Tracking Software 20 Ways to Save Time & Money Implementing Contracting Cost Tracking Software Introduction: Companies can save a considerable amount of time and money by implementing Contractor Cost Tracking Software when

More information

SERVICE ENTRANCES. OPPD S Electrical Service Designer (ESD) shall designate the Point Of Entrance.

SERVICE ENTRANCES. OPPD S Electrical Service Designer (ESD) shall designate the Point Of Entrance. SERVICE ENTRANCES 3.01 POINT OF ENTRANCE General Service The customer, or the customer s electrician, should provide OPPD with a site plan, load schedule, and voltage requirements when requesting service.

More information

4. GENERAL REQUIREMENTS

4. GENERAL REQUIREMENTS 4. GENERAL REQUIREMENTS 4.1 APPLICATION FOR SERVICE Application for service must be made to, and accepted by, the Company before service will be furnished. At the time of application, the Customer shall

More information

The Canadian Electrical Code (Saskatchewan Amendments) Regulations, 1999

The Canadian Electrical Code (Saskatchewan Amendments) Regulations, 1999 CANADIAN ELECTRICAL CODE 1 The Canadian Electrical Code (Saskatchewan Amendments) Regulations, 1999 Repealed by Chapter E-6.3 Reg 8 (effective June 24, 2003). Formerly Chapter E-6.3 Reg 6 (effective March

More information

Electric Service Handbook

Electric Service Handbook Electric Service Handbook Revised August 2017 Contact Information Telephone (253): Electrical Inspection Office 502-8277 7:30 am - 4:30 pm Electrical Inspectors Area Map on Website 7:30 am - 8:30 am Automated

More information

ENMAX POWER CORPORATION. Requirements for Distribution Wires Access

ENMAX POWER CORPORATION. Requirements for Distribution Wires Access ENMAX POWER CORPORATION Requirements for Distribution Wires Access December 7, 2016 Table of Contents Foreword 4 Section One: Making an Application for New Services, Upgrades or Changes 6 1. New Connections

More information

Reliable and economical power supply for industrial plants

Reliable and economical power supply for industrial plants Infrastructure & Cities Sector Background Information Low and Medium Voltage Division Erlangen, Germany, March 2013 Hannover Messe 2013, Hall 9, Stand D35 Reliable and economical power supply for industrial

More information

An Oracle White Paper October Four Ways Enterprise Project Portfolio Management Can Increase ROI in Asset- Intensive Process Industries

An Oracle White Paper October Four Ways Enterprise Project Portfolio Management Can Increase ROI in Asset- Intensive Process Industries An Oracle White Paper October 2009 Four Ways Enterprise Project Portfolio Management Can Increase ROI in Asset- Intensive Process Industries Executive Overview Asset-intensive companies like those in the

More information

Electric T&D Bulletin

Electric T&D Bulletin UTILITY OPERATIONS Bulletin Number: 2007-09A FOR IMMEDIATE RELEASE Date: 08-01-07 Title: Check all appropriate boxes Electric T&D Bulletin Underground Residential & Commercial Construction SAFETY ALERT

More information

Service plans enhance the benefits of preventive maintenance programs

Service plans enhance the benefits of preventive maintenance programs Service plans enhance the benefits of preventive maintenance programs White Paper Document 1910DB1612 by Charles Alvis Executive summary Companies are continually being tasked by management to increase

More information

TS 801 ELECTRICAL WORK - GENERAL TABLE OF CONTENTS

TS 801 ELECTRICAL WORK - GENERAL TABLE OF CONTENTS TORONTO TRANSPORTATION January 2012 TS 801 ELECTRICAL WORK - GENERAL TABLE OF CONTENTS 1. DRAWINGS TTD 801.001 ELECTRICAL ABBREVIATIONS AND SYMBOLS TTD 801.005 ELECTRICAL LEGEND I TTD 801.006 ELECTRICAL

More information

Distribution Information Exchange Code

Distribution Information Exchange Code Distribution Information Exchange Code Version 5.1 Approved September 2007 Comments to this document can be forwarded to: The RSA Grid Code Secretariat Attention: Mr. Bernard Magoro Eskom, Transmission

More information

The Narragansett Electric Company d/b/a National Grid. and Clear River Energy LLC. (Burrillville Interconnection Project) RIPUC Dkt. No.

The Narragansett Electric Company d/b/a National Grid. and Clear River Energy LLC. (Burrillville Interconnection Project) RIPUC Dkt. No. d/b/a National Grid and Clear River Energy LLC (Burrillville Interconnection Project) RIPUC Dkt. No. Testimony of David J. Beron, P.E., P.M.P. November, 0 0-v R.I.P.U.C. Dkt. No. 0 0 INTRODUCTION Q. Please

More information

DA concept for higherquality. supplies. 24 ABB Review 4/1996

DA concept for higherquality. supplies. 24 ABB Review 4/1996 DA concept for higherquality power supplies Low power network losses and an uninterrupted supply of electricity are no longer enough to satisfy today s consumers, who take a highquality power supply for

More information

SECTION 16496A MTS MANUAL TRANSFER SWITCH (MANUAL CONTROL ONLY) Note to Spec Writer: { } Denotes EATON Feature reference number

SECTION 16496A MTS MANUAL TRANSFER SWITCH (MANUAL CONTROL ONLY) Note to Spec Writer: { } Denotes EATON Feature reference number MTS MANUAL TRANSFER SWITCH (MANUAL CONTROL ONLY) Note to Spec Writer: { } Denotes EATON Feature reference number PART 1 GENERAL 01 02 03 04 SCOPE Furnish and install Manual Transfer Switches (MTS) and

More information

PSS E. High-Performance Transmission Planning Application for the Power Industry. Answers for energy.

PSS E. High-Performance Transmission Planning Application for the Power Industry. Answers for energy. PSS E High-Performance Transmission Planning Application for the Power Industry Answers for energy. PSS E architecture power flow, short circuit and dynamic simulation Siemens Power Technologies International

More information

TEMPORARY GRID RECONFIGURATIONS NET BENEFIT TEST METHODOLOGY

TEMPORARY GRID RECONFIGURATIONS NET BENEFIT TEST METHODOLOGY TEMPORARY GRID RECONFIGURATIONS NET BENEFIT TEST METHODOLOGY 1 1. Summary When one part of the grid is facing security of supply risk where local generation in one region of the grid is not enough for

More information

CONSTRUCTION SPECIFICATION FOR INSTALLATION OF CABLE

CONSTRUCTION SPECIFICATION FOR INSTALLATION OF CABLE ONTARIO PROVINCIAL STANDARD SPECIFICATION OPSS.PROV 604 NOVEMBER 2017 CONSTRUCTION SPECIFICATION FOR INSTALLATION OF CABLE TABLE OF CONTENTS 604.01 SCOPE 604.02 REFERENCES 604.03 DEFINITIONS - Not Used

More information

Contact Clark Public Utilities Construction Services department at (360) to initiate a request for service.

Contact Clark Public Utilities Construction Services department at (360) to initiate a request for service. CHAPTER3 Clark Public Utilities Commercial Electric Service Handbook Commercial Underground Services Preparing for the installation The following checklist will assist in preparing a project for the installation

More information

SERVICES DEPUTY CITY MANAGER I ADMINISTRATIVE SERVICES PUBLIC WORKS ClOY ENGINEER DIRECTOR DIRECTOR PROJECT & CONSTRUCTION ENGINEERING

SERVICES DEPUTY CITY MANAGER I ADMINISTRATIVE SERVICES PUBLIC WORKS ClOY ENGINEER DIRECTOR DIRECTOR PROJECT & CONSTRUCTION ENGINEERING Operation and Maintenance This section summarizes key operation and maintenance aspects of the City's sewer system. Included in this section is a description of the wastewater system personnel, instrumentation

More information

Performance of Buried High Voltage Power Cables due to Earthquake Loads

Performance of Buried High Voltage Power Cables due to Earthquake Loads Performance of Buried High Voltage Power Cables due to Earthquake Loads John M. EIDINGER 1, Leon KEMPNER 2 1 G&E Engineering Systems Inc., Olympic Valley, California eidinger@geengineeringsystems.com 2

More information

General Symbols, Ducts and Cables

General Symbols, Ducts and Cables DIVISION 2000 - ABBREVIATIONS 2009 11 2000.001 0 Abbreviations, General 2009 11 2011.101 0 General Symbols, Ducts and Cables 2009 11 2011.201 0 General Symbols, Maintenance Holes, Junction Boxes, Pads,

More information

Gas-insulated medium-voltage switchgear. for marine and offshore applications. Answers for energy.

Gas-insulated medium-voltage switchgear. for marine and offshore applications. Answers for energy. Gas-insulated medium-voltage switchgear for marine and offshore applications Answers for energy. 8DH10 switchgear up to 24 kv, up to 20 ka, up to 1,250 A up to 17.5 kv, up to 25 ka, up to 1,250 A Full

More information

POWER QUALITY IN REGULATION OF DISTRIBUTION COMPANIES A FINNISH CASE

POWER QUALITY IN REGULATION OF DISTRIBUTION COMPANIES A FINNISH CASE POWER QUALITY IN REGULATION OF DISTRIBUTION COMPANIES A FINNISH CASE Markku KINNUNEN Energy Market Authority Finland markku.kinnunen@emvi.fi Ritva HIRVONEN Energy Market Authority - Finland ritva.hirvonen@emvi.fi

More information

ELECTRICAL INSPECTION BULLETIN (Effective )

ELECTRICAL INSPECTION BULLETIN (Effective ) ELECTRICAL INSPECTION BULLETIN (Effective 2009-02-01) Rule 36-000 Customer Owned High Voltage Installations With the increase in customer own high voltage equipment there appears to be confusion over which

More information

Gas-insulated medium-voltage switchgear. for wind parks. Answers for energy.

Gas-insulated medium-voltage switchgear. for wind parks. Answers for energy. Gas-insulated medium-voltage switchgear for wind parks Answers for energy. Switchgear for wind turbines: 8DH10 up to 24 kv, up to 20 ka, up to 1,250 A up to 17.5 kv, up to 25 ka, up to 1,250 A Best performance

More information

DECISION SUPPORT FOR LIFE TIME MANAGEMENT OF HV INFRASTRUCTURES

DECISION SUPPORT FOR LIFE TIME MANAGEMENT OF HV INFRASTRUCTURES DECISION SUPPORT FOR LIFE TIME MANAGEMENT OF HV INFRASTRUCTURES E.Gulski (1), J.J.Smit (1), B. Quak (1), E.R.S.Groot (2) (1) Delft University of Technology, (2) KSANDR The Netherlands e.gulski@ewi.tudelft.nl

More information

Business Plan: Drinking Water Supply

Business Plan: Drinking Water Supply Business Plan: Drinking Water Supply How does this service contribute to the results identified in the City of London Strategic Plan? A Sustainable Infrastructure Compliance with all regulatory requirements

More information

Ameren Illinois Electric Quality Assurance Program Keith Lowry Superintendent, Electric Quality Assurance

Ameren Illinois Electric Quality Assurance Program Keith Lowry Superintendent, Electric Quality Assurance Ameren Illinois Electric Quality Assurance Program Keith Lowry Superintendent, Electric Quality Assurance May 15, 2015 Development of Quality Assurance Process Illinois Commerce Commission Reliability

More information

Conventional Damage Assessment. Lockheed Martin ARIES Damage Assessment. Right Crew Size Right Materials

Conventional Damage Assessment. Lockheed Martin ARIES Damage Assessment. Right Crew Size Right Materials LOCKHEED MARTIN ARIES AUTOMATED RAPID INFRASTRUCTURE EVALUATION SYSTEM Conventional Damage Assessment Lockheed Martin ARIES Damage Assessment Slow Response Time Impassable Roads Fast Accurate Evaluation

More information

SurvalentONE Outage Management System

SurvalentONE Outage Management System SurvalentONE Outage Management System Efficiently & Effectively Manage Outages to Reduce Downtime SurvalentONE ADMS The SurvalentONE ADMS platform is a fully integrated SCADA, OMS, and DMS solution that

More information

Standard of Practice - Campus Electrical Distribution System

Standard of Practice - Campus Electrical Distribution System A26.3 Standard of Practice - Campus Electrical Distribution System NOTE: Significant revisions or additions to the previous standards are highlighted in italics. GENERAL Designers shall verify that all

More information

Title: YALE OFFICE OF FACILITIES PROCEDURE MANUAL Chapter: 01 - Yale Design Standard Division: Electrical Standards

Title: YALE OFFICE OF FACILITIES PROCEDURE MANUAL Chapter: 01 - Yale Design Standard Division: Electrical Standards Change History Date Description of Change Pages / Sections Modified Change Approver Initials 6/15/16 Updated division section from 16124 to 2605 - mgl44 13, removed references to other section 10/17/14

More information

Seven-Year Electric Service Reliability Statistics Summary

Seven-Year Electric Service Reliability Statistics Summary Oregon Investor-owned Utilities Seven-Year Electric Service Reliability Statistics Summary 2010-2016 June 2017 Report available at http://www.puc.state.or.us (Click on Safety, then click on Reports ) Information

More information

Advantage Services. Driving outcomes through value-based services.

Advantage Services. Driving outcomes through value-based services. Advantage Services Driving outcomes through value-based services www.usa.siemens.com/service How do I juggle repairs, compliance issues, and budget constraints while keeping everyone happy? We work hard.

More information

SECTION AUTOMATIC TRANSFER SWITCH

SECTION AUTOMATIC TRANSFER SWITCH SECTION 26 36 23 AUTOMATIC TRANSFER SWITCH PART 1: GENERAL 1.01 SCOPE A. Furnish all labor, materials, equipment and appurtenances, install and test electrically operated, automatic transfer switch (ATS)

More information

PREPARING FOR & RESPONDING TO EXTREME WEATHER & EXTENDED OUTAGES

PREPARING FOR & RESPONDING TO EXTREME WEATHER & EXTENDED OUTAGES 2013 PREPARING FOR & RESPONDING TO EXTREME WEATHER & EXTENDED OUTAGES Forward-Looking Statement Readers are cautioned that statements contained in this presentation about our and our subsidiaries' future

More information

Digital Asset Management: Optimizing the Asset Life-cycle with new generation of tools. Filip Kowalski, SAP CEE

Digital Asset Management: Optimizing the Asset Life-cycle with new generation of tools. Filip Kowalski, SAP CEE Digital Asset Management: Optimizing the Asset Life-cycle with new generation of tools Filip Kowalski, SAP CEE #NP#_JZBta4MwEID/iuTTxmyrLhr1m1Vr fwnnuszbyjdmi3u4d SqsUPrfd+ngCJ d7nssduak6rv4 VTW3a IB+Zhg

More information

CHANGE REQUEST for FY BUDGET REQUEST CYCLE

CHANGE REQUEST for FY BUDGET REQUEST CYCLE CHANGE REQUEST for FY 2010-11 BUDGET REQUEST CYCLE Department: Colorado Department of Public Safety Priority Number: 1 Change Request Title: Computer-Aided Dispatch, Records Management System, and Mobile

More information

There are many technologies available for

There are many technologies available for Engineering Technologies for Pipeline Asset Management Bryon L. Livingston, Ahmad Habibian, and Dan Kugler There are many technologies available for managing the condition of underground infrastructure,

More information

Jemena Electricity Networks (Vic) Ltd

Jemena Electricity Networks (Vic) Ltd Jemena Electricity Networks (Vic) Ltd 2016-20 Electricity Distribution Price Review Regulatory Proposal User-requested services explanatory statement Public 30 April 2015 TABLE OF CONTENTS TABLE OF CONTENTS

More information

and Certified Services Chris Forland, Operations Consultant Scott Grunwald, Turnaround Business Manager Miranda Pilrose, Marketing Manager

and Certified Services Chris Forland, Operations Consultant Scott Grunwald, Turnaround Business Manager Miranda Pilrose, Marketing Manager Parts, People, Process: The Winning Formula for Emerson Turnarounds and Certified Services Chris Forland, Operations Consultant Scott Grunwald, Turnaround Business Manager Miranda Pilrose, Marketing Manager

More information

(Condensed from National Electric Code)

(Condensed from National Electric Code) WIRING, SPECIFICATIONS, INSPECTION, AND METER INSTALLATION PROCEDURES FOR RESIDENTIAL CUSTOMERS SERVED BY SOUTHWEST ARKANSAS ELECTRIC COOPERATIVE CORPORATION Effective April 1, 1974 Revised February 3,

More information

ELECTRICAL SAFETY INSPECTION REPORT

ELECTRICAL SAFETY INSPECTION REPORT ELECTRICAL SAFETY INSPECTION REPORT ADVANCE WORLD LIMITED Lalkha Shair Char, Fatullah, Narayanganj, Dhaka, Bangladesh Factory List: 1.. Inspected by: Sherub Tenzin & Md. Moin Hasan Report Generated by:

More information

A Best Practice for the Implementation of a Pavement Management System For Small and Medium Airports

A Best Practice for the Implementation of a Pavement Management System For Small and Medium Airports A Best Practice for the Implementation of a Pavement Management System For Small and Medium Airports Architectural & Engineering Services Civil Engineering Directorate Airport Engineering ATR-045 Real

More information

Procedure UE PR Access to the United Energy Electricity Network. Document UE PR 0001

Procedure UE PR Access to the United Energy Electricity Network. Document UE PR 0001 Access to the United Energy Electricity Network Document UE PR 0001 Procedure UE PR 0001 This procedure outlines the requirements for access to work on or near the UE electricity network for the performance

More information

Index January 23, 2015 MANITOBA HYDRO 2015/16 & 2016/17 GENERAL RATE APPLICATION

Index January 23, 2015 MANITOBA HYDRO 2015/16 & 2016/17 GENERAL RATE APPLICATION 0 0 Tab Index MANITOBA HYDRO 0/ & 0/ GENERAL RATE APPLICATION CAPITAL EXPENDITURE FORECAST INDEX.0 Overview.... Capital Expenditure Forecast.... Electric Operations Capital Expenditure Forecast (CEF)....

More information

MESP TECHNICAL SPECIFICATION FOR ELECTRIC CABLE 400mm 2 ALUMINIUM CONDUCTOR 1.9kV XLPE INSULATED WITH METALLIC SCREEN

MESP TECHNICAL SPECIFICATION FOR ELECTRIC CABLE 400mm 2 ALUMINIUM CONDUCTOR 1.9kV XLPE INSULATED WITH METALLIC SCREEN Engineering Specification Electrical Networks TECHNICAL SPECIFICATION FOR ELECTRIC CABLE 400mm 2 ALUMINIUM CONDUCTOR 1.9kV XLPE INSULATED Version: 1 Issued: March 2014 Owner: Electrical Networks Asset

More information

DIVISION MEDIUM VOLTAGE VAULT DESIGN Contents MEDIUM VOLTAGE VAULT DESIGN... 2 DIVISION LIST OF FIGURES...

DIVISION MEDIUM VOLTAGE VAULT DESIGN Contents MEDIUM VOLTAGE VAULT DESIGN... 2 DIVISION LIST OF FIGURES... DIVISION 13 00 60 - MEDIUM VOLTAGE VAULT DESIGN Contents 13 00 60 - MEDIUM VOLTAGE VAULT DESIGN... 2 DIVISION 13 00 60 LIST OF FIGURES... 6 13 00 60 - MEDIUM VOLTAGE VAULT DESIGN 1. General Requirements

More information

Technical Requirements for Distributed Generation Connection

Technical Requirements for Distributed Generation Connection Technical Requirements for Distributed Generation Connection Distributed Generation Connection Requirements SECTION 1: INTRODUCTION 1.1 General Purpose This document defines the requirements for connecting

More information

Draft. 1. For grade crossing warning devices, see Manual Part Recommended Guidelines for Grade Crossing Warning Devices.

Draft. 1. For grade crossing warning devices, see Manual Part Recommended Guidelines for Grade Crossing Warning Devices. 2017 Part 3.1.10 Recommended Functional/Operating Guidelines for Interconnection Between Highway Traffic Signals or Other Traffic Control Devices and Grade Crossing Warning Systems Reaffirmed 2017 Revised

More information

New trends in Process Automation for the cement industry

New trends in Process Automation for the cement industry New trends in Process Automation for the cement industry Author: E. Vinod Kumar, ABB Ltd., Bangalore, India 1. Abstract: Process Automation is an important component of modern cement production. The versatility

More information