ANALYSIS OF SDG&E S PROPOSAL TO DE-RATE LINE 1600 AND CONSTRUCT LINE 3602

Size: px
Start display at page:

Download "ANALYSIS OF SDG&E S PROPOSAL TO DE-RATE LINE 1600 AND CONSTRUCT LINE 3602"

Transcription

1 ANALYSIS OF SDG&E S PROPOSAL TO DE-RATE LINE 00 AND CONSTRUCT LINE 0 Prepared testimony of Margaret C Felts M.C. Felts Co. Elk Grove California, USA on behalf of Utility Consumers Action Network California Public Utilities Commission Application -0-0 April, 0

2 A.-0-0 Table of Contents Page I. Introduction II. Prudent management of gas supply for safe operations demands the ability to re-route the supply of gas without delay during daily operations to meet peak demand, during emergencies and for routine maintenance.... III. Prudent engineering requires good long term planning to insure pipeline safety and a reliable supply for operations.... IV. Line 00 should be taken out of service because SDG&E/SCG cannot prove that it is safe to operate, even at 0 MAOP.. V. Taking Line 00 out of service requires additional new infrastructure.. VI. It is not reasonable to rely on Line 00 to supply the entire San Diego region... VII. Installing Line 0 is a prudent solution to maintain a safe pipeline system to deliver a reliable supply of gas to the San Diego region... VIII. Conclusion..

3 A I. Introduction The purpose of my testimony on behalf of UCAN is to provide my analysis of San Diego Gas and Electric/SoCalGas (SDG&E/SCG ) proposals to de-rate Line 00 to distribution service and to replace it with a new inch diameter transmission Line 0. Initially, UCAN and I were very skeptical of SDG&E/SCG's proposal, especially given the cost to the ratepayers. However, after an examination of SDG&E/SCG's evidence, a review of all the data responses to the intervenors, the Office of Ratepayer Advocates (ORA) and the Commission's Safety and Enforcement Division (SED), Energy Division (ED) questions, as well as independent research, we became convinced that SDG&E/SCG's proposal deserves support. We arrived at this conclusion in light of Line 00 safety issues and the resiliency and reliability issues associated with having only Line 00 to serve the region should Line 00 be de-rated or taken out of service. Based on technical information provided by SDG&E/SCG, I conclude that Line 00 should be removed from service as soon as practicable and find the proposal to construct Line 0 to be a reasonable and prudent engineering solution for the San Diego region. My testimony will set out the basic engineering principles and technical information I used to arrive at these conclusions. 0 II. Prudent management of gas supply for safe operations demands the ability to re-route the supply of gas without delay during daily operations to meet peak demand during emergencies and for routine maintenance. In the oil & gas industry, products are moved through ships, barges, trucks and rail cars, storage tanks and pipelines. There is hour, days per week, vigilance and operators are constantly balancing volume, flow and pressure in the pipelines as products are moved from fixed volume vessels (batches) to constantly flowing pipelines. It is not an easy task to balance inventory levels, pipeline flows, and pressures, while industrial, commercial, and consumer demands constantly fluctuate. In

4 A California, the ISO s constant shifting of demand for electricity from source to source, adds another layer of complexity for the gas provider because Electric Generator (EG) demand fluctuates from day to day, and even within hours. Sound engineering requires design for flexibility in gas pipeline operations -- at minimum to include loops or redundant lines so that adequate gas supplies are always readily available. There cannot be a delay in acquiring gas because a gas supply system cannot be allowed to drop below minimum operating pressures. To maintain gas pressure, it is necessary to match the flow of gas into the pipeline system to the outgoing gas demand by users. While curtailment of interruptible supplies helps slow demand to preserve pipeline gas pressure, SDG&E/SCG cannot curtail core consumer demand because it is not feasible to go out and close the valves to homes. In an extreme case when gas supply suddenly decreases, such as when a pipeline fails unexpectedly, a redundant supply that can be routed to core consumers immediately is essential. In that respect, the pipeline system currently supplying the San Diego region is defective because SDG&E/SCG currently lack the redundancy to maintain a sufficient supply at all times to the San Diego gas users. In the past, SCG&E/SCG/Sempra anticipated that LNG from Energia Costa Azul (ECA) and/or gas transported across northern Mexico to Otay Mesa might supplement the San Diego region. Due to changing dynamics of the supply and demand for gas in Mexico, and the current prices of LNG, neither of those options exists today as practical and affordable sources of gas. Those facilities are also in a foreign Prepared Direct Testimony of S. Ali Yari, February, 0, p. (Attachment D) A significant loss of pressure requires a massive effort to turn off every user valve, to purge systems for safety, followed by another massive effort to put gas back into the system, turn gas back on, light pilot lights and restart the system. This is an expensive and inherently unsafe operation and not one that should ever be considered a part of normal operations. Supplemental Testimony of SDG&E and SCG, February, 0, p. referencing D at, and Atch A, Gas Capacity Planning and Demand Forecast Semi-Annual Report, October, 0 p. Current Status, Plans, and Constraints Related to Expansion of Natural Gas-Fired Power Plants, Pipelines and Bulk Electric Transmission in the California/Mexico Border Region, California Energy Commission, August 00 CEC , pp. - (Attachment E) Direct Testimony of Paul Borkovich, February, 0, Sec. III (Attachment F) and Response to Energy Division DR (Response CEA-A.) (Attachment C) and Response to UCAN DR Q (Attachment B)

5 A country and fall outside of the Commission s regulatory authority, making reliance on them risky. III. Prudent engineering requires good long term planning to insure pipeline safety and a reliable supply for operations. There are two basic engineering principles taught in engineering schools and industry that apply to the current situation. First, design for 0 years. Second, past performance cannot be used to predict future performance. The planning horizon for pipeline replacement is typically 0 years. In engineering, the typical design horizon for pipeline infrastructure is 0 years, therefore a reasonable planning horizon for the Line 0 project, including the forecast for natural gas supply and demand, should be at least 0 years. One only has to look at histories within pipeline companies to see this principle at work. In fact, the idea of building Line 0 is not one that evolved from the Pipeline Safety Enhancement Plan (PSEP) proceedings. In, SDG&E had already planned Line 0 construction. Line 00 would have been years old in. If it took years to complete the project, Line 0 would have been installed when Line 00 was 0 years old. While the routes contemplated were slightly different than the current proposed route, the point is that engineers at SDG&E and SCG were planning ahead to provide new pipeline capacity. That project was ultimately shelved, except for the small section along Pomerado Road in Poway. 0 Citing to SDG&E s long-term gas resource plan, SDG&E/SCG say that the new pipeline was planned to meet increasing Response to TURN DR Q, Note that the SDG&E Transmission pipeline book life (used for depreciation calculations) is years. While this is an accounting parameter, it is also suggests the anticipated life of the facility. (Attachment C) R.-0-0, February 0 Prepared Direct Testimony of Neil Navin, March, 0, p. (Attachment G) Response to UCAN DR Q and UCAN DR Q (Attachment B) 0 Prepared Direct Testimony of N. Navin, March, 0, p. (Attachment G)

6 A gas demand, and to interconnect to the existing Line0 crosstie in Escondido, which would improve system reliability and increase flow. In 00 SDG&E/SCG were still planning to install a transmission line (Line 0) with year completion. Project # (0 0 MMcfd option) described in Table - is the most likely project to be constructed on the SDG&E system to meet increasing demand. The total length of this pipeline would be miles, extending to the existing -inch Pipeline 000 in Santee. Essentially, this pipeline would complete a loop between the Rainbow Compressor station and the southern extreme of the SDG&E service territory. SDG&E personnel confirmed this project is ideal to significantly improve system reliability, especially in time of emergencies or when other transmission lines are in need of maintenance. The lead-time for this project is estimated at three to four years, with the southern portion being the most problematic since it goes through federal government property and various sensitive environmental zones.... By 00 this project would have been completed and Line 00 would have been years old and Line 00 would have been years old. While the short project descriptions do not state the planned replacement of Line 00, given gas demand forecasts at the time, installation of a transmission line would have allowed the de-rating of Line 00 to a distribution line, or to be taken out of service, if necessary. In the current Application, SDG&E/SCG now propose to install Line 0 with year completion. By the time Line 0 is completed in 0, Line 00 will be years old and Line 00 will be years old, well beyond the design lives of both lines. As 0 approaches, ensuring the integrity of Line 00 will require increased vigilance, inspections, maintenance and repairs. Fortunately, Line 0 ( ) planned capacity will provide complete redundancy in times when Line 00 will be shut down. Response to UCAN DR Q (Attachment B) San Diego Regional Energy Infrastructure Study, SAIC, December 0, 00, p. - (Attachment H) Prepared Direct Testimony of N. Navin, March, 0, p. (Attachment G)

7 A.-0-0 As another example of long term planning in the industry, in PG&E initiated a 0 year forward-looking plan called the Gas Pipeline Replacement Plan, stating 0 0 The steel transmission lines proposed for replacement are to years old and were originally installed in open spaces, often in narrow rights-of-way in areas which have since been highly developed. Many of these pipelines are now in confined areas with reduced ground cover. They need to be replaced with modern pipe to enable PG&E to continue to provide safe and reliable service. In addition, the three pipelines supplying San Francisco from Milpitas were built between and. They will be replaced... Line, constructed in, was one of those three pipelines to be replaced. Ultimately, PG&E did not replace L as planned and it subsequently failed catastrophically in San Bruno on September, 00. The NTSB reported that the Line weld failed catastrophically at psig, below the MAOP of 00 psig. Past performance cannot be used to predict future performance. There may be a tendency to assume that since a pipeline has not leaked or failed in the past, it will not do so in the future. This logic is faulty, like assuming your shoes will last forever because they have served you well for the past years, or the roof on your house will last forever because it has not leaked for the past years, or Line would not explode because it had operated for years without incident. Prudent Engineers do not wait for a pipeline to fail to plan the replacement pipeline using the latest design information and technology. Pipelines, just like all infrastructure, are subject to damage over time for a number of reasons. A 0 year time frame for planning the replacement of pipelines necessarily assumes the pipeline will not fail by the time it is replaced at 0 years, therefore one would assume that it has not suffered too many, if any, problems Revised Report and Testimony of Margaret Felts, I.-0-0, March, 0, p. (Attachment I) NTSB Accident Report, August 0, 0, titled PG&E Natural Gas transmission Pipeline Rupture and Fire, San Bruno, CA, September, 00, pp. and (Attachment J) The northern stretch of Line, which passed through San Bruno was installed in. Supplemental Testimony of SDG&E and SCG, Atch C, Michael Rosenfeld, Review of Risk Factors for Line 00, February 0, 0, p.0, Figure, Summary of Probability of Failure Scores.

8 A.-0-0 for those first 0 years. While there are engineering formulas used to calculate the remaining life of a pipeline, reliance on these predictions has yet to be proven as a safe planning tool for an entire pipeline system. As SDG&E/SCG witness Rosenfeld states, there is much that is unknowable about the line [00], including the ability of girth welds to withstand loadings from natural events, and features in the longitudinal seams. Risk is proportional to what is unknown, at least in part. Line 00 is a system that was built and buried underground in. Line 00 was built and buried just years later, in 0. There is much that is unknown about any pipeline that is buried underground and the longer they are in place and subject to unknown loadings, the higher the number of unknowns, along with risk. Therefore, past performance of Lines 00 and 00 cannot be used to predict the future performance of Lines 00 and 00. IV. Line 00 should be taken out of service because SDG&E/SCG cannot prove that it is safe to operate, even at 0 MAOP. The Post Assessment of Line 00 reveals the alarming unknown and unknowable condition of the line. SDG&E performed a series of pipeline examinations utilizing different detection technologies, including Direct Examination (DE) of pipeline pieces where an In-line Inspection (ILI) showed anomalies. 0 SDG&E reported anomalies in five categories: crack-like, deformation, longitudinal seam, manufacturing and metal loss (which overlaps some of the other categories). DE involves physically excavating down to the pipe to perform additional inspections from the outside of the Typically, remaining life calculations measure the impact of corrosion, i.e. how much metal thickness is left and how long it will survive before failure. Supplemental Testimony of SDG&E and SCG, Atch C, Michael Rosenfeld, Review of Risk Factors for Line 00, February 0, 0, p. 0 Post Assessment Report for the 0-0 In-line Inspection of SDG&E Pipeline 00, Pipeline Integrity Transmission Integrity & Analysis, February, 0, p. (Attachment K) Ibid,

9 A.-0-0 pipe. In a instances, a section of pipe was removed for internal inspection and lab analyses. When SDG&E performed DE, it discovered numerous anomalies in longitudinal seams that had not been detected with the ILI equipment. SDG&E concludes that 0 [t]he discovery of undetected longitudinal seam anomalies during direct examinations suggests that additional flaws that are unknown to SDG&E may remain on Pipeline 00. During the investigation,, anomalies were detected using ILI. Of those, were selected for DE. Direct examination of the locations revealed longitudinal seam flaws that were not reported (not detected) by the ILI vendor as anomalies. The lengths and depths of the undetected flaws are reported on Table. These flaws Ibid, Ibid, Ibid,, note: Anomalies include Crack-like, fractures such as hook cracks, lack of fusion, cold welds; deformation, such as dents, buckles, ripple or wrinkle, metal loss or a stress riser; Longitudinal seam manufacturing anomaly such as lack of penetration, lack of fusion, and misalignment; manufacturing, such as metal loss, mid-wall, inclusion or lamination that cannot be sized; and metal loss, which is any pipe anomaly in which metal has been removed, usually corrosion, but gouging, manufacturing defects or mechanical damage can also cause metal loss. See descriptions on p. of the Post Assessment Report. (Attachment K) Ibid, Ibid, and Ibid, Table, p. -

10 A.-0-0 were found in EFW and ERW Long Seam types and were not insignificant given that most of them were repaired by pipe replacement or bands around the pipe. The remaining anomalies that were found during ILI were not inspected using DE. 0 If undetected flaws were detected in the locations sampled, then / yields an average of undetected flaws per anomaly location. By simple multiplication, that leaves potentially, undetected flaws, remaining in Line 00 in unknown locations. The total detected and undetected flaws in Line 00 Electric Resistance Weld (ERW) pipe materials and a similar material called electric-flash-welded (EFW) pipe first appeared in the 0s. Both processes involved making line pipe by cold forming previously hotrolled plates or strips into round cans and joining the longitudinal edges of the cans by a combination of localized electrical resistance heating and mechanical pressure. The heat-softened edges were forced together extruding excess material to the outside and inside of the newly formed pipe. The excess material was immediately trimmed away leaving smooth surfaces or at most a small protrusion along the bondline. Prior to, all ERW materials and EFW pipe were made by means of DC or low frequency AC current (up to 0 Hz) using low-carbon steels made in open hearth or electric arc furnaces and cast into ingots. The DC or low-frequency AC currents used for resistance heating required intimate contact between the rolling electrodes and the skelp (i.e., the plate or strip used to form the cans). Dirt, grease, scale, or other oxide films on the skelp could, and often did, cause enough interference to prevent adequate heating at the bondline interface. Momentary reductions or loss of current could result in isolated or repeated areas of nonbonding called cold welds as well as other imperfections. Lack of fusion due to insufficient heat and pressure is the principal defect, although hook cracks can also form due to realignment of non metallic inclusions at the weld interface. A hook crack or upturned fiber imperfection is defined in API Bulletin TL as, Metal separations resulting from imperfections at the edge of the plate or skelp, parallel to the surface, which turn toward the inside diameter or outside diameter pipe surface when the edges are upset during welding. The precursors for hook cracks are non- metallic inclusions, primarily manganese sulfide stringers. These flattened, nonmetallic inclusions are formed during hot rolling of plate or skelp. In general, they reduce the ductile toughness of the steel even in their normal position (i.e., layers interspersed between the rolling elongated grain structure of the steel). In this position, they can cause poor through-thickness properties that inherently reduce ductile fracture tearing resistance but not necessarily the yield or tensile strength of the material. Near an ERW bondline, however, these weak layers become reoriented such that they are subjected to tensile hoop stress when the pipe is pressurized. The layers may be of sufficient extent or so closely associated that the resulting planes of weakness separate, forming J-shaped (i.e., hook) cracks that curve from being parallel to the plate surfaces near mid-wall to being nearly parallel to the ERW bondline at the OD or ID surface. These cracks can be up to 0 percent of the wall thickness in depth and up to several inches in length. Source: Non-Destructive Evaluation of Low-frequency Electric Resistance Welded (ERW) Pipe Utilizing Ultrasonic In-Line Inspection Technology, 00,Rick MEADE, Tuboscope Pipeline Services, Houston, TX Ibid, note: In the same report, See Table, page, where None Required appears under Repair Method for some metal loss anomalies. None of the flaws listed on Table are annotated as requiring no repair. 0,-=,, x =, 0

11 A.-0-0 longitudinal seams that have not yet been directly examined or repaired could be as high as,. While SDG&E/SCG have no information about any of these potential, flaws, a 0 study of pipe failures informs the risk associated with operating Line 00, with all of these flaws, as proposed, at 0 psig, which would be less than a hoop stress of 0% Specified Minimum Yield Strength (SMYS): there can exist situations in which a pipeline operating at low or moderate hoop stress can fail in a rupture mode, namely: (a) where a defect is both long and deep even where the material is ductile, or (b) where a defect is not so large but the material toughness is extremely low. Five of nine risk categories to Line 00 cannot be mitigated by lowering the MAOP and de-rating the line. In testimony SDG&E witness Mr. Rosenfeld identifies and compares risk categories in a summary graph: outside forces, mechanical damage, incorrect operations, equipment failure, external corrosion, manufacturing ruptures, manufacturing leaks, stress-corrosion cracking and internal corrosion. The last risks in the list will be reduced, but not eliminated, by de-rating Line 00. There will be no change to the other risk categories by de-rating. Based on my expertise and experience, I agree with Mr. Rosenfeld s analysis and conclusions. One of these risk categories that cannot be diminished by de-rating is mechanical damage. Theoretically, mechanical damage is immediately repaired when it occurs. But, if the damage is not reported, it remains in the pipe until it is discovered or the pipe fails. During ILI inspection, dents were identified in Line 00 that had not previously been reported when they occurred, likely caused by rd parties (Construction, +,=, Study of Pipelines that Ruptured while Operating at a Hoop Stress Below 0% SMYS, Michael Rosenfeld and Robert Fassett, Pipeline Pigging and Integrity Management Conference, February -, 0. p. (Attachment L) Supplemental Testimony of SDG&E and SCG, Atch C, Michael Rosenfeld, Review of Risk Factors for Line 00, February 0, 0, p.0, Figure, Summary of Probability of Failure Scores.

12 A.-0-0 equipment digging near the pipeline.) These are potential pipeline explosions avoided only because excavators did not completely breach the pipeline. However, the dents remained in the pipeline unreported, representing damage that might later lead to pipeline failure. 0 0 Mechanical damage results from the pipe being struck by excavating equipment. The damage is in the form of a scrape or gouge, often with a shallow indentation. Mechanical damage, if severe, may result in immediate failure of the pipe. More often, the pipe initially withstands the damage which may then cause a failure weeks, months, or even ears after the damage occurred. In fact, mechanical damage is one of the most frequent causes of pipeline failure. There is currently no completely reliable method for assessing the severity of mechanical damage. If it is discovered on a pipeline, it is usually considered to be injurious and requiring immediate repair. Mr. Rosenfeld observes that the susceptibility of a pipeline to mechanical damage failure has been observed to be significantly greater for older vintage pipelines. The INGAA pipeline age study found that natural gas pipelines installed prior to 0 were. times more likely to experience a failure due to being hit by a third-party excavator than pipelines installed after 000, and. times more likely to rupture due to latent (previous) damage. In the end, no amount of inspections or repairs, or de-rating for that matter, can mitigate the 0. thickness of the pipe, which makes Line 00 subject to more mechanical damage than newer, thicker pipe. 0 According to Mr. Rosenfeld, during Post Assessment Report for the 0-0 In-line Inspection of SDG&E Pipeline 00, Pipeline Integrity Transmission Integrity & Analysis, February, 0, p. (Attachment K) Supplemental Testimony of SDG&E and SCG, Atch C, Michael Rosenfeld, Review of Risk Factors for Line 00, February 0, 0, pp.- Ibid, Ibid The Role of Pipeline Age in Pipeline Safety, The INGAA Foundation, Inc., November, 0, p., Table (Attachment M) 0 Supplemental Testimony of SDG&E and SCG, Atch C, Michael Rosenfeld, Review of Risk Factors for Line 00, February 0, 0, Table, Vulnerability of Line 00 and Line 0 to Excavator Damage, showing that % of excavators are large enough to breach LINE 00, p.

13 A alone there were requests to excavate within 0 ft. of Line 00. This risk cannot be understated. Another risk category that cannot be mitigated by de-rating Line 00 is incorrect operation that can lead to fatigue crack growth, which affects how the metal and welds in the pipeline hold up over time. Incorrect operations would include operating beyond MAOP either purposely or during an unplanned event. It could also include operating in a cyclical pressure range that leads to long term damage from stresses that exceed the pipeline design. Although regulations anticipate that pipeline companies will retain operating pressure records for the life of the pipeline, SDG&E/SCG did not retain operating pressure records. Therefore, it is not possible to analyze actual operating conditions for the life of Line 00. Kiefner and Associates, Mr. Rosenfeld s employer, performed an analysis to determine the susceptibility of fatigue crack growth in Line 00 due to pressure cycles acting on a defect such as a hook crack. Using basic lab calculations applied to specific lab data, the shortest predicted time to failure was years. There is a tendency to rely on this type of calculation for assurance of safety. However, Mr. Rosenfeld points out the fallacies in that prediction: 0 0 While those results would appear to put concerns for hook cracks to rest, there are some residual concerns that cannot be easily addressed. One is that the estimates of time to failure relied on operating pressure dated from 0 and 0 and assumed the pipeline had always operated similarly. Early in its history the pipeline may have operated differently and in a manner that could be more severe from the fatigue standpoint. Secondly, a study of the causes of failures in ERW and flash welded seams performed for the Pipeline Hazardous Material Safety Administration (PHMSA) found that commonly used ductile fracture initiation models gave unsatisfactory (i.e. overestimated) predictions of the failure stress levels of hook crack defects. There was essentially no correlation between predicted and actual failure stress levels... Finally, multiple hook cracks may be present in parallel or aligned and in close proximity to each other. Recent research gives Ibid, Table, p. Ibid, Ibid,

14 A evidence that individual hook cracks can interact with other adjacent hook cracks so as to lead to failure in less time than would be expected with a single hook crack. The most adverse combination is hook cracks occurring on the same side of the seam bondline but with one hook crack on the inside and the other on the outside pipe surfaces. Another type of manufacturing defect (rupture) that may not be mitigated by derating Line 00 is Selective Seam Weld Corrosion (SSWC), which is linked to sulfur content in the pipe because susceptibility to SSWC is enhanced by high sulfur content in the steel. The sulfur content of Line 00 is 0 times higher than modern pipe. According to Rosenfeld, 0 The combination of SSWC and low toughness in the seam bondline, may create a serious defect that is more likely to cause a rupture than coincident corrosion in the body of the pipe, or cause a rupture at low hoop stress. Conventional corrosion evaluation methods such as ASME BG cannot be reliably used to evaluate SSWC if the flaw cannot be accurately sized or if the seam can exhibit low-toughness behavior. SDG&E has so far not reported the occurrence of SSWC on Line 00, however the line should be regarded as susceptible based on its chemistry and seam type. With the potential for low seam toughness at the operating temperature, the occurrence of selective corrosion in Line 00 could pose an integrity concern. A failure in Line 00 would result in a rupture rather than a leak. Line 00 is constructed from A.O. Smith Corporation (AOS) flash welded pipe. Although many small sections of the pipeline have been replaced over time, % of the line segments is still the original pipe that was installed in. Although the industry thought the controlling factors of SMYS and wall thickness were sufficient design parameters for a pipeline, subsequent gas pipeline ruptures in two pipelines resulted in cracks that Ibid, - Ibid, Ibid Ibid Ibid, Post Assessment Report for the 0-0 In-line Inspection of SDG&E Pipeline 00, Pipeline Integrity Transmission Integrity & Analysis, February, 0, p. (Attachment K)

15 A.-0-0 opened along the pipelines for distances of. miles and miles, caused the industry to reconsider design for fracture control. 0 Fracture control would limit the extent of the failure therefore confining a rupture to a short piece of the pipe, rather than miles of pipe. The pipe installed in Line 00 was not manufactured with fracture control in mind because the concept was not known at that time. Therefore, a rupture that is initiated in one flaw could result in a pipe splitting open for a long distance, possibly miles, exposing a large number of people and multiple properties to the effects of an explosion and subsequent gas releases and fires. Rosenfeld explains fracture control as it relates specifically to Line 00, ultimately concluding: 0 The implication of these inherent properties of Line 00 is that in the event of a failure, particularly in the seam but potentially even in the pipe body, a failure would result in a rupture and propagating brittle fracture, rather than a leak. For the reasons discussed in this section the prudent action to promote safety and reliability of the SDG&E/SCG pipeline system serving the San Diego service territory would be to take Line 00 out of service as soon as practicable. 0 V. Taking Line 00 out of service requires additional new infrastructure. SDG&E/SCG did not consider the option of taking Line 00 out of service in the Preliminary Environmental Assessment (PEA), therefore, any additional costs of connecting the proposed L-0 to the distribution systems currently served by Line 00 were not provided in the Application. When asked about the cost, SDG&E/SCG s response was: Customers currently supplied by Line 00 are in SDG&E s service territory and SDG&E has an obligation to provide service. If Line 00 0 Supplemental Testimony of SDG&E and SCG, Atch C, Michael Rosenfeld, Review of Risk Factors for Line 00, February 0, 0, p. Ibid, Ibid,

16 A were hypothetically removed from service, no customer would be stranded without service as SDG&E would modify its gas system to maintain service ahead of the hypothetical abandonment. The geographic areas that would be impacted are communities located in eastern San Diego County between the Riverside County Line and the Marine Corps Air Station Miramar, including, but not limited to, Valley Center, Escondido, portions of San Diego and Poway. Two EG plants are directly served from Line 00 and would be impacted by a hypothetical abandonment of Line 00; however, one EG is served from a segment of Line 00 beyond the scope of the Proposed Project. While not served directly by Line 00, EG plants in the Escondido area would also be impacted. Replacing Line 00 in-kind is not a feasible alternative due to right of way (ROW) issues which drive up the costs. The current condition of Line 00, as described above, dictates that the existing line be permanently taken out of service as soon as practicable. There simply is not a feasible repair option other than replacing the line. Replacement in-kind, as considered in the PEA alternatives, turns out to be far more costly and disruptive to consumers than building a new pipeline along another route. Line 00 was constructed in. At the time, a 0 foot right of way seemed adequate since the cities had not developed around the pipeline. In assessing the option for replacing Line 00 in-kind in the future, SDG&E/SCG describe the current right of way issues: 0... Regardless of which of the alternatives within the existing alignment is considered, construction or installation of new pipe that utilizes the existing Line 00 ROW would require acquisition of additional temporary ROW to establish a safe work area during construction and provide enough room for equipment to maneuver. Generally, a minimum width of 0 to 0 feet of temporary workspace is required to install a -inch natural gas pipeline; however, the width can increase to up to 00 feet in areas with side slopes, bedrock, sandy soils, and/or topsoil salvage requirements. Response to UCAN DR Q.a. (Attachment B) Response to UCAN DR Q.b. (Attachment B) Proponent s Environmental Assessment for the Pipeline Safety & Reliability Project, Volume II, Application -0-0, September 0, (PEA) Chapter, p.-, E-page /

17 A Adequate space for new construction does not exist along the Line 00 centerline because the area surrounding the existing approximately 0-foot-wide ROW has been heavily developed in many locations since the line was originally constructed in. Approximately 00 parcels would be affected in order to obtain the minimum amount of temporary workspace required during construction, including public, private, commercial, and residential properties. Of the parcels anticipated to be affected, approximately homes and other structures would be permanently displaced or acquired due to impacts to primary structures. Further, acquiring the additional ROW would affect 0 public and governmental agencies, including local municipal agencies, municipalities, and state agencies. Approximately commercial buildings, seven apartment buildings, and possibly two commercial pools may require total acquisitions for the additional ROW needed. Ranch and ranchette properties along the existing route would also be affected. The total partial acquisition cost is estimated to run as high as $. million and total costs for ROW acquisition are estimated to be over $0,000,000. However, the actual costs associated with acquiring the additional ROW would be even higher, as this estimate does not include costs such as those associated with the interruption of business activities or acquisitions through eminent domain, which could result in substantial legal fees. Furthermore, because the estimate is based on the minimum ROW width, additional businesses and residences would likely be displaced when site-specific workspace needs are determined during the design phase. In an additional note, consider that SDG&E/SCG s statement also reflects the current proximity of Line 00 to existing buildings, highlighting the risks of major property damage and loss of life in the event of a pipeline explosion. 0 VI. It is not reasonable to rely on Line 00 to supply the entire San Diego region. Line 00 is an aging pipeline that lacks capacity to supply forecasted demand without curtailment. From an engineering perspective, it is prudent to recognize that Ibid, note: The cost estimate to acquire ROW to construct line 00 was modified from $ to $ million to $0 million in the Proponent s March 0 Environmental Assessment Supplement, Appendix A: PEA Corrections and Modifications, p.

18 A Line 00, by itself, cannot supply peak daily demand in the San Diego region, let alone supply a higher than normal level of connected load and peak loads associated with renewable resources going off line after dark, that could be called upon. During routine operations, Line 00 supplies 0 percent of SDG&E s capacity (0 MMcfd) and Line 00 supplies 0% ( MMcfd at psig when operated with Line 00), for a total of MMcfd with both lines operating. By taking Line 00 out of service, the remaining maximum capacity would be 0 MMcfd. While it may appear that Line 00 alone could supply all demand based on demand figures provided in the 0 California Gas Report which shows the highest demand at MMcfd in the year 0, this report is misleading because it is based on annualized forecast demand data for a -in- cold temperature year and dry hydro year condition, 0 a figure that is far from representing actual demand on a real time basis. SDG&E s October 0 Gas Capacity Planning and Demand Forecast Semi- Annual Report developed from the same data as the California Gas Report, shows the highest demand forecast of 0 MMcfd in the year 00 for in 0 year cold day demand. SDG&E/SCG state that Table of the Report provides daily demand forecast data under a different set of temperature conditions, namely the -in- year peak day and -in-0 year cold day mandated design standards. At a capacity of 0 MMcfd/Line 00 would fall short of meeting the -in-0 year cold day demand. Still, this Report is also based on daily average data and gas pipeline systems are not operated based on average demand. Pipelines must be operated to supply peak demand in real time. Supplemental Testimony of SDG&E and SCG, February, 0, p., l.-, and Atch A, Gas Capacity Planning and Demand Forecast Semi-Annual Report, October, 0 p. Prepared Direct Testimony of S. Ali Yari, February, 0 (Attachment A) Supplemental Testimony of SDG&E and SCG, February, 0, p., including foonotes, and Prepared Direct Testimony of David M. Bisi, February, 0, p. (Attachment O) 0 0 California Gas Report, p. (Attachment Q) and Response to UCAN DR Q (Attachment B) Supplemental Testimony of SDG&E and SCG, February, 0, Atch A, Gas Capacity Planning and Demand Forecast Semi-Annual Report, October, 0 p. Response to UCAN DR Q (Attachment B)

19 A.-0-0 As stated in the Prepared Direct Testimony of David Bisi, 0 0 although connected load is not the standard that should be used to design capacity on the system it is a useful indicator of the potential for EG demand that may quickly be dispatched and that may not otherwise be captured under long-term demand forecasting. This potential has already been demonstrated, as the historical maximum SDG&E demand of MMcfd exceeds the SDG&E system capacity of 0 MMcfd. At any point in time during a day s operation, gas demand may peak well above the recorded average. The gas operator must be prepared to supply sufficient gas to meet that peak demand and sustain operating pressures in the pipeline system. In 0, SCG points out that recent requests for service to new natural gas power plants have included quick-start technology, with 0-00% demand in 0 minutes and 0-0% demand in minutes and 0-00% in minute. This demand causes a sudden and rapid pipeline pressure loss, up to 0 psig drop in extreme situations. It is in these situations that SDG&E/SCG must have extra gas immediately available in the pipeline system. In addition, any condition, such as inspecting, testing or repairing Line 00, or an emergency, would result in loss of supply, thus possible curtailments. Loss of Line 00 entirely without an immediate alternate supply source would result in a loss of gas to San Diego until additional supplies could be scheduled through Otay Mesa. Even then, those supplies would be limited to SDG&E s maximum capacity of 00 MMcfd, which would be insufficient at some times, leading to curtailments. Therefore, it is unreasonable to assume Line 00 alone can provide a safe and reliable supply of gas to the San Diego area currently served by Lines 00 and 00. In the future, if Line 00 is retired, a new 0 line will have insufficient capacity to serve Prepared Direct Testimony of David M. Bisi, February, 0, p., l. - (Attachment O) Response to ORA DR 0 Q (Attachment C) Overview of Southern California Gas / San Diego Gas & Electric System Design & Operations, Beth Musich, July, 0 (Attachment P) Supplemental Testimony of SDG&E and SCG, February, 0, p. L.0-

20 A.-0-0 the entire area during peak periods if Line 00 is out of service. I agree with Mr. Bisi when he notes: 0 0 Only a inch or larger diameter pipeline will also provide redundancy for the Moreno Compressor Station, serve an SDG&E demand of 0 MMcfd in the event of an outage of Line 00, and improve SDG&E s capability to meet rapid changes in customer demand. VII. Installing Line 0 is a prudent solution to maintain a safe pipeline system to deliver a reliable supply of gas to the San Diego region. Line 0 would be a new pipeline designed and built to current code that will provide at least another 0 years of safe, reliable service. While Line 0 is envisioned to supplement Line 00 capacity for peak demand and rapid demand increase periods, at it will have sufficient capacity to supply entire region without curtailments when Line 00 is out of service. Total capacity will increase to 0 MMcfd in winter operating season with an MAOP of 0 psig. Line 0 will provide instant access to an alternative supply of gas in emergencies and will allow flexibility in operating to supply day-to-day demand, creating a safe and reliable operating environment. Options to operate more connected load would be possible because additional gas could be delivered to the region. Given the number of undetected anomalies found recently on direct examination of Line 00, one might expect that there are additional, unknown anomalies in Line 00 that were not identified in the recent ILI inspections of that line. With Line 0 in place, SDG&E/SCG will be able to take Line 00 out of service for inspections and maintenance, which will ensure the line is safe to operate and may extend the life of the pipeline. Similarly, the redundancy will also allow ongoing inspections and maintenance of Line 0. When it is time to take Line 00 out of service, the Prepared Direct Testimony of David M. Bisi, February, 0, p., l. - (Attachment O) Response to Energy Division DR (CEA G.0) (Attachment C) Response to UCAN DR Q a. (Attachment B) 0

21 A.-0-0 alternative Line 0, a year younger pipeline, will already be in place that has sufficient capacity to serve the region until the pipeline system is once again re- configured to provide continued flexibility. 0 0 VIII. Conclusion Applying basic engineering principles, it is prudent to design a gas pipeline system in a manner that allows flexibility and redundancy so an adequate supply of gas can be provided to the region at all times, including during peak demand periods, routine maintenance and emergencies. I think a 0 year planning horizon for Line 0 is reasonable, and relying on the past performance of Line 00, or the existing system as a whole, is unreasonable because past performance does not predict future performance for infrastructure. After review of SDG&E/SCG s data for inspections of Line 00, it is evident that there are sufficient known defects and even more unknowns about the physical condition of the line to raise safety concerns regarding continued use of the line, even under reduced pressure. SDG&E/SCG do not know how many flaws lie undetected in Line 00, but the most recent inspection report suggests the number is in the thousands. Line 00 is made of thin walled pipe (. inches thick) compared to current standards, making the pipe more susceptible to rupture by construction equipment, a pipe characteristic that will not change if the line is de-rated. SDG&E/SCG s own expert has concerns about existing hook cracks, selective seam weld corrosion, and the lack of fracture control in Line 00. Finally, no record of how Line 00 was operated from until 0 exists, leaving it unknown whether any of the defects in the line are a result of, or influenced by, fatigue. In consideration of all of the evidence, it is my opinion that Line 00 should be removed from service as soon as practicable because the physical condition of the line makes it risky to continue operation, even at 0 psig. I agree with SDG&E/SCG that replacing Line 00 in kind is not a feasible alternative due to costly right of way issues. And, I also acknowledge that taking Line

22 A out of service will require some additional investment in infrastructure to connect distribution areas currently served via Line 00 to alternate supply lines. In conclusion, in addition to taking Line 00 out of service as soon as practicable, it is my opinion that Line 0 ( ) should be built. The combined capacity of Lines 00 and 0 will provide sorely needed operational flexibility, making the system safer to operate and providing adequate capacity to ensure uninterrupted service into the future. And, from an operational perspective, a new Line 0 will provide sufficient capacity to supply the region when Line 00 is taken out of service.

TABLE OF CONTENTS LIST OF FIGURES LIST OF ATTACHMENTS

TABLE OF CONTENTS LIST OF FIGURES LIST OF ATTACHMENTS TABLE OF CONTENTS 2.0 TRANSMISSION SYSTEM OVERVIEW... 2-1 2.1 PROPOSED PROJECT OBJECTIVES... 2-2 2.2 SAFETY, RELIABILITY AND RESILIENCY, AND OPERATIONAL FLEXIBILITY AND CAPACITY... 2-5 2.2.0 Pipeline Safety...

More information

Gas Transmission MAOP Verification Integrity Verification Process Oklahoma CC Pipeline Safety Conference

Gas Transmission MAOP Verification Integrity Verification Process Oklahoma CC Pipeline Safety Conference Gas Transmission MAOP Verification Integrity Verification Process Oklahoma CC Pipeline Safety Conference U.S. DOT / PHMSA Steve Nanney November 19, 2014 1 Integrity Verification Process Drivers Overview

More information

SAN DIEGO GAS & ELECTRIC COMPANY SOUTHERN CALIFORNIA GAS COMPANY PIPELINE SAFETY & RELIABILITY PROJECT (PSRP) (A ) (DATA REQUEST ORA-68)

SAN DIEGO GAS & ELECTRIC COMPANY SOUTHERN CALIFORNIA GAS COMPANY PIPELINE SAFETY & RELIABILITY PROJECT (PSRP) (A ) (DATA REQUEST ORA-68) PRELIMINARY STATEMENT 1. These responses and objections are made without prejudice to, and are not a waiver of, SDG&E and SoCalGas right to rely on other facts or documents in these proceedings. 2. By

More information

PRELIMINARY STATEMENT

PRELIMINARY STATEMENT PRELIMINARY STATEMENT 1. These responses and objections are made without prejudice to, and are not a waiver of, SDG&E and SoCalGas right to rely on other facts or documents in these proceedings. 2. By

More information

Advances In ILI Allow Assessing Unpiggable Pipelines. By Lisa Barkdull and Ian Smith, Quest Integrity Group, Houston

Advances In ILI Allow Assessing Unpiggable Pipelines. By Lisa Barkdull and Ian Smith, Quest Integrity Group, Houston As seen in Pipeline & Gas Journal, August 2011 edition Advances In ILI Allow Assessing Unpiggable Pipelines By Lisa Barkdull and Ian Smith, Quest Integrity Group, Houston Advances in in-line inspection

More information

PREPARED DIRECT TESTIMONY OF DOUGLAS M. SCHNEIDER ON BEHALF OF SAN DIEGO GAS & ELECTRIC COMPANY AND SOUTHERN CALIFORNIA GAS COMPANY

PREPARED DIRECT TESTIMONY OF DOUGLAS M. SCHNEIDER ON BEHALF OF SAN DIEGO GAS & ELECTRIC COMPANY AND SOUTHERN CALIFORNIA GAS COMPANY Application No: A.1-0-01 Exhibit No.: Witness: D. Schneider In The Matter of the Application of San Diego Gas & Electric Company (U 0 G) and Southern California Gas Company (U 0 G) for a Certificate of

More information

Hazardous Liquid Pipeline Integrity Verification Process (HL IVP) Overview

Hazardous Liquid Pipeline Integrity Verification Process (HL IVP) Overview Hazardous Liquid Pipeline Integrity Verification Process (HL IVP) Overview Industry (API/AOPL) Briefing November 18, 2014 1 HL IVP What is HL IVP Where would HL IVP be applicable Drivers - GT Statutory

More information

Delmont Line 27 Incident Update

Delmont Line 27 Incident Update Pennsylvania Public Utility Commission Delmont Line 27 Incident Update July 21, 2016 Agenda Introductions Penn-Jersey system overview Incident and preliminary cause Texas Eastern actions and commitments

More information

COMPOSITES - CASE STUDIES OF PIPELINE REPAIR APPLICATIONS. By Andrew J. Patrick, Clock Spring Company, L.P., Huntingdon, UK

COMPOSITES - CASE STUDIES OF PIPELINE REPAIR APPLICATIONS. By Andrew J. Patrick, Clock Spring Company, L.P., Huntingdon, UK COMPOSITES - CASE STUDIES OF PIPELINE REPAIR APPLICATIONS By Andrew J. Patrick, Clock Spring Company, L.P., Huntingdon, UK ABSTRACT Composite repairs have been utilised within the transmission pipeline

More information

National Academy of Sciences

National Academy of Sciences National Academy of Sciences Transportation Research Board Study of Pipeline Transportation of Diluted Bitumen PHMSA Regulatory Authority and Keystone XL Pipeline October 23, 2012-1 - Topics for Briefing

More information

This study is concerned with mechanical damage experienced by steel pipes transporting gas and liquids for energy-related applications.

This study is concerned with mechanical damage experienced by steel pipes transporting gas and liquids for energy-related applications. MECHANICAL DAMAGE (1) Preamble This study is concerned with mechanical damage experienced by steel pipes transporting gas and liquids for energy-related applications. (2) Definition In the context of the

More information

Managing Cracks. Crack Management. Tom Bubenik DNV GL

Managing Cracks. Crack Management. Tom Bubenik DNV GL Managing Cracks Tom Bubenik DNV GL 1 SAFER, SMARTER, GREENER Crack Management Cracks are a growing concern for PHMSA and pipeline operators. Managing cracks is high on PHMSA s list as it considers potential

More information

Gas Transmission NPRM. David Johnson November 10, 2016

Gas Transmission NPRM. David Johnson November 10, 2016 Gas Transmission NPRM David Johnson November 10, 2016 Friday the 13 th came 5 days early! 2 A few statistical facts As published in the FR: 136 pages like this 103 pages of intro & preamble 33 pages of

More information

SAN DIEGO GAS & ELECTRIC COMPANY SOUTHERN CALIFORNIA GAS COMPANY

SAN DIEGO GAS & ELECTRIC COMPANY SOUTHERN CALIFORNIA GAS COMPANY PRELIMINARY STATEMENT 1. These responses and objections are made without prejudice to, and are not a waiver of, SDG&E and SoCalGas right to rely on other facts or documents in these proceedings. 2. By

More information

TAKING STOCK: Opportunities and Challenges in California s Natural Gas Distribution System

TAKING STOCK: Opportunities and Challenges in California s Natural Gas Distribution System TAKING STOCK: Opportunities and Challenges in California s Natural Gas Distribution System INTRODUCTION California natural gas distribution pipeline system is a network of more than 150,000 miles of pipe

More information

SDG&E JOINT TESTIMONY OF MICHAEL A. BERMEL AND BETH MUSICH (GAS TRANSMISSION CAPITAL) October 6, 2017

SDG&E JOINT TESTIMONY OF MICHAEL A. BERMEL AND BETH MUSICH (GAS TRANSMISSION CAPITAL) October 6, 2017 Company: San Diego Gas & Electric Company (U 0 M) Proceeding: 01 General Rate Case Application: A.1-- Exhibit: SDG&E-0 SDG&E JOINT TESTIMONY OF MICHAEL A. BERMEL AND BETH MUSICH (GAS TRANSMISSION CAPITAL)

More information

Public Workshop on Integrity Verification Process (IVP)

Public Workshop on Integrity Verification Process (IVP) Public Workshop on Integrity Verification Process (IVP) Arlington, Virginia 8/7/2013 Presenting on behalf of INGAA Dwayne Burton Kinder Morgan INGAA s Integrity Management Continuous Improvement (IMCI)

More information

The Added Value of In-Line Inspection to Hydrostatic Testing Programs

The Added Value of In-Line Inspection to Hydrostatic Testing Programs The Added Value of In-Line Inspection to Hydrostatic Testing Programs René Irani Business Development Director, Pipeline Resources, Middle East & Africa The Complementary Benefits of Using Both: Hydro-test

More information

) ) ) ) ) ) ) ) DIRECT TESTIMONY OF DAVID M. BISI SAN DIEGO GAS & ELECTRIC COMPANY AND SOUTHERN CALIFORNIA GAS COMPANY

) ) ) ) ) ) ) ) DIRECT TESTIMONY OF DAVID M. BISI SAN DIEGO GAS & ELECTRIC COMPANY AND SOUTHERN CALIFORNIA GAS COMPANY Application No: A.1-1-xxx Exhibit No.: Witness: David M. Bisi Application of Southern California Gas Company (U 0 G) and San Diego Gas & Electric Company (U 0 G) For Authority To Recover North-South Project

More information

ILI: An Improvement Over Pressure Testing for Pipeline Integrity Management

ILI: An Improvement Over Pressure Testing for Pipeline Integrity Management Bruce L. Paskett, PE Dr. Pete Riccardella June, 2018 ILI: An Improvement Over Pressure Testing for Pipeline Integrity Management Gas MegaRule MAOP Verification Requirements - Advantages from Using ILI

More information

) ) SUPPLEMENTAL DIRECT TESTIMONY OF DAVID BISI SAN DIEGO GAS & ELECTRIC COMPANY AND SOUTHERN CALIFORNIA GAS COMPANY

) ) SUPPLEMENTAL DIRECT TESTIMONY OF DAVID BISI SAN DIEGO GAS & ELECTRIC COMPANY AND SOUTHERN CALIFORNIA GAS COMPANY Application No: A. 11-11-00 Exhibit No.: Witness: David Bisi ) In the Matter of the Application of San Diego Gas & ) Electric Company (U 90 G) and Southern California ) Gas Company (U 90 G) for Authority

More information

PHMSA Update: Aging Infrastructure and Integrity Verification Process

PHMSA Update: Aging Infrastructure and Integrity Verification Process PHMSA Update: Aging Infrastructure and Integrity Verification Process NAPCA Workshop August 15, 2013 Houston, Texas Safety Administration (PHMSA) Steve Nanney 1 PHMSA Safety Update - Topics Performance

More information

From the desk of G. A. Aaker, Jr., PE.

From the desk of G. A. Aaker, Jr., PE. SAMPLE CALCULATIONS TO DETERMINE THE REQUIRED MINIMUM WALL THICKNESS PER DOT 192 / ASME B31.8 FOR GAS TRANSMISSION AND DISTRIBUTION PIPING SYSTEMS 192.103 GENERAL Pipe must be designed with sufficient

More information

Engineering Critical Assessment of Vintage Girth Welds

Engineering Critical Assessment of Vintage Girth Welds Engineering Critical Assessment of Vintage Girth Welds Fan Zhang PhD, Jing Ma PhD, Mark Van Auker Michael Rosenfeld PE Kiefner and Associates, Inc. Thien-An Nguyen Pacific Gas and Electric Company AGA

More information

) ) ) ) ) ) ) ) SUPPLEMENTAL DIRECT TESTIMONY OF DAVID BUCZKOWSKI SAN DIEGO GAS & ELECTRIC COMPANY AND SOUTHERN CALIFORNIA GAS COMPANY

) ) ) ) ) ) ) ) SUPPLEMENTAL DIRECT TESTIMONY OF DAVID BUCZKOWSKI SAN DIEGO GAS & ELECTRIC COMPANY AND SOUTHERN CALIFORNIA GAS COMPANY Application No: Exhibit No.: Witness: A.1-1-01 David Buczkowski Application of Southern California Gas Company (U 0 G and San Diego Gas & Electric Company (U 0 G For Authority To Recover North-South Project

More information

IPC PRESSURE CYCLING MONITORING HELPS ENSURE THE INTEGRITY OF ENERGY PIPELINES. Peter Song Enbridge Pipelines Inc. Edmonton, Alberta, Canada

IPC PRESSURE CYCLING MONITORING HELPS ENSURE THE INTEGRITY OF ENERGY PIPELINES. Peter Song Enbridge Pipelines Inc. Edmonton, Alberta, Canada Proceedings of the ASME 8 th International Pipeline Conference IPC2010 September 27 October 1, 2010, Calgary, Canada IPC2010-31394 PRESSURE CYCLING MONITORING HELPS ENSURE THE INTEGRITY OF ENERGY PIPELINES

More information

Regulatory Agenda and Notices RSPA / OPS

Regulatory Agenda and Notices RSPA / OPS Regulatory Agenda and Notices RSPA / OPS Download the Regulations http://www.tsi.dot.gov Click on Pipeline Safety (Valve Setting), Publications & Follow Links Advisory Bulletins Advisory Bulletins http://ops.dot.gov

More information

CHAPTER 1 PREPARED DIRECT TESTIMONY OF RICK PHILLIPS PHASE 2 PIPELINE SAFETY ENHANCEMENT PLAN BEFORE THE PUBLIC UTILITIES COMMISSION

CHAPTER 1 PREPARED DIRECT TESTIMONY OF RICK PHILLIPS PHASE 2 PIPELINE SAFETY ENHANCEMENT PLAN BEFORE THE PUBLIC UTILITIES COMMISSION Application No: A.1-0- Exhibit No.: Date: June 1, 01 Witness: Rick Phillips Application of Southern California Gas Company (U 0 G) and San Diego Gas & Electric Company (U 0 G) to Proceed With Phase of

More information

INGAA Foundation, Inc. Construction Safety and Construction QA/QC Workshop Houston, Texas. PHMSA Update on Construction and Inspection March 21, 2012

INGAA Foundation, Inc. Construction Safety and Construction QA/QC Workshop Houston, Texas. PHMSA Update on Construction and Inspection March 21, 2012 INGAA Foundation, Inc. Construction Safety and Construction QA/QC Workshop Houston, Texas PHMSA Update on Construction and Inspection March 21, 2012 Alan Mayberry - 1 - Today s Agenda Updates on the past

More information

Pipeline Safety Update

Pipeline Safety Update Pipeline Safety Update NAPCA Workshop August 16, 2012 Houston, Texas Safety Administration (PHMSA) Steve Nanney - 1 - PHMSA Safety Update - Topics PHMSA Overview Perspective on Past Performance Agency

More information

BEFORE THE PIPELINE AND HAZARDOUS MATERIALS SAFETY ADMINISTRATION UNITED STATES DEPARTMENT OF TRANSPORTATION WASHINGTON, D.C.

BEFORE THE PIPELINE AND HAZARDOUS MATERIALS SAFETY ADMINISTRATION UNITED STATES DEPARTMENT OF TRANSPORTATION WASHINGTON, D.C. BEFORE THE PIPELINE AND HAZARDOUS MATERIALS SAFETY ADMINISTRATION UNITED STATES DEPARTMENT OF TRANSPORTATION WASHINGTON, D.C. Pipeline Safety: Public Workshop on the Integrity Verification Process Docket

More information

) ) ) ) ) ) ) ) UPDATED DIRECT TESTIMONY OF DAVID M. BISI SAN DIEGO GAS & ELECTRIC COMPANY AND SOUTHERN CALIFORNIA GAS COMPANY

) ) ) ) ) ) ) ) UPDATED DIRECT TESTIMONY OF DAVID M. BISI SAN DIEGO GAS & ELECTRIC COMPANY AND SOUTHERN CALIFORNIA GAS COMPANY Application No: A.1-1-01xxx Exhibit No.: Witness: David M. Bisi Application of Southern California Gas Company (U 0 G) and San Diego Gas & Electric Company (U 0 G) For Authority To Recover North-South

More information

HALL AND ASSOCIATES High Pressure Natural Gas Pipeline Accidents and Safety Factors November 19, 2018

HALL AND ASSOCIATES High Pressure Natural Gas Pipeline Accidents and Safety Factors November 19, 2018 HALL AND ASSOCIATES High Pressure Natural Gas Pipeline Accidents and Safety Factors November 19, 2018 Jim Hall, Former Chairman, NTSB Bob Chipkevich, former Director of Pipeline Investigations, NTSB Executive

More information

NAME 345 Welding Technology Lecture 09 SAW, ESW & Resistance Welding

NAME 345 Welding Technology Lecture 09 SAW, ESW & Resistance Welding NAME 345 Welding Technology Lecture 09 Md. Habibur Rahman Lecturer Department of Naval Architecture & Marine Engineering Bangladesh University of Engineering & Technology Dhaka-1000, Bangladesh Submerged

More information

NAPCA Workshop August 19, 2010 Houston, Texas Kenneth Y. Lee Office of Pipeline Safety

NAPCA Workshop August 19, 2010 Houston, Texas Kenneth Y. Lee Office of Pipeline Safety Pipeline Construction Challenges NAPCA Workshop August 19, 2010 Houston, Texas Kenneth Y. Lee Office of Pipeline Safety PHMSA Mission To ensure the operation of the Nation s pipeline transportation system

More information

FLORIDA PUBLIC SERVICE COMMISSION

FLORIDA PUBLIC SERVICE COMMISSION FLORIDA PUBLIC SERVICE COMMISSION NATURAL GAS PIPELINE ANNUAL SAFETY REPORT 2017 DIVISION OF ENGINEERING Table of Contents Figures and Tables... iii Gas Safety Background... 1 Transmission Integrity Management

More information

NATIONAL ENERGY BOARD PIPELINE PERFORMANCE MEASURES REPORTING GUIDANCE

NATIONAL ENERGY BOARD PIPELINE PERFORMANCE MEASURES REPORTING GUIDANCE NATIONAL ENERGY BOARD PIPELINE PERFORMANCE MEASURES REPORTING GUIDANCE Amended November 2014 PIPELINE PERFORMANCE MEASURES - OVERVIEW Introduction The National Energy Board (Board) took action in March

More information

9 Conclusion. 9.1 Introduction

9 Conclusion. 9.1 Introduction 9 Conclusion 9.1 Introduction This final chapter presents a synthesis of the evaluation criteria leading to conclusions and recommendations. Also included is a summary of the current status of the Tappan

More information

REPORT NO , REV. 1

REPORT NO , REV. 1 METALLURGICAL INVESTIGATION OF A FRACTURED SECTION OF THE 20" O.D. PIPELINE AT MILEPOST 314.77 IN THE CONWAY TO CORSICANA SEGMENT OF THE PEGASUS CRUDE OIL PIPELINE REPORT NO. 64961, REV. 1 Prepared for

More information

Seismic Upgrade of Pipes Across the Hayward Fault

Seismic Upgrade of Pipes Across the Hayward Fault Seismic Upgrade of Pipes Across the Hayward Fault by John Eidinger 1 ABSTRACT This paper provides the status of all water pipelines crossing the Hayward fault, and a few other utilities such as sewers,

More information

BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA ) ) ) ) ) ) )

BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA ) ) ) ) ) ) ) BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA Order Instituting Rulemaking on the Commission s Own Motion to Adopt New Safety and Reliability Regulations for Natural Gas Transmission

More information

Annual Natural Gas Pipeline Safety Report

Annual Natural Gas Pipeline Safety Report Annual Natural Gas Pipeline Safety Report 2009 Florida Public Service Commission Division of Service, Safety and Consumer Assistance Annual Natural Gas Pipeline Safety Report 2009 At the March 5, 1984,

More information

EQT MIDSTREAM DESIGN AND CONSTRUCTION MANUAL DESIGN STANDARD WELDING AND JOINING 3.4 HOT TAP AND BRANCH CONNECTIONS Total Pages: 13

EQT MIDSTREAM DESIGN AND CONSTRUCTION MANUAL DESIGN STANDARD WELDING AND JOINING 3.4 HOT TAP AND BRANCH CONNECTIONS Total Pages: 13 Table of Contents Scope... 845 References... 845 Governmental... 845 EQT Midstream Publications... 845 Industry Standards... 846 Computer Programs... 846 1 Manufactured Branch Connections... 846 1.1 Extruded

More information

Pipeline Safety: Plastic Pipe

Pipeline Safety: Plastic Pipe U.S. Department of Transportation Pipeline and Hazardous Materials Safety Administration Pipeline Safety: Plastic Pipe Draft Environmental Assessment Docket No. PHMSA-2014-0098 May 1, 2015 Prepared for:

More information

CONTENTS. Foreword... Committee Roster Introduction Summary of Changes

CONTENTS. Foreword... Committee Roster Introduction Summary of Changes CONTENTS Foreword.............................................................................. Committee Roster Introduction Summary of Changes General Provisions and Definitions 801 General... 1 802

More information

REINFORCING LARGE DIAMETER ELBOWS USING COMPOSITE MATERIALS SUBJECTED TO EXTREME BENDING AND INTERNAL PRESSURE LOADING

REINFORCING LARGE DIAMETER ELBOWS USING COMPOSITE MATERIALS SUBJECTED TO EXTREME BENDING AND INTERNAL PRESSURE LOADING Proceedings of the 2016 11th International Pipeline Conference IPC2016 September 26-30, 2016, Calgary, Alberta, Canada IPC2016-64311 REINFORCING LARGE DIAMETER ELBOWS USING COMPOSITE MATERIALS SUBJECTED

More information

Silicon Valley Mid-Summer Emergency: Santa Clara Addresses Peak-Demand Repair of 96-inch Pipeline Mike Larsen Anna Pridmore, PhD, PE

Silicon Valley Mid-Summer Emergency: Santa Clara Addresses Peak-Demand Repair of 96-inch Pipeline Mike Larsen Anna Pridmore, PhD, PE Silicon Valley Mid-Summer Emergency: Santa Clara Addresses Peak-Demand Repair of 96-inch Pipeline Mike Larsen Anna Pridmore, PhD, PE BACKGROUND Santa Clara Valley Water District: Primary Water Source for

More information

PART TWO. Pipeline Integrity Evaluation and Engineering Assessment

PART TWO. Pipeline Integrity Evaluation and Engineering Assessment PART TWO Pipeline Integrity Evaluation and Engineering Assessment This page intentionally left blank CHAPTER ONE Introduction Contents Pipeline integrity management 136 High consequence area analysis 138

More information

SUMMARY OF TRANSMISSION INTEGRITY MANAGEMENT PROGRAM

SUMMARY OF TRANSMISSION INTEGRITY MANAGEMENT PROGRAM Page 1 of 6 SUMMARY OF TRANSMISSION INTEGRITY MANAGEMENT PROGRAM Program Overview: The Company s Transmission Integrity Management Program ( TIMP ) was established to comply with federal TIMP regulations

More information

GN01 DEAERATOR CRACKING

GN01 DEAERATOR CRACKING GN01 DEAERATOR CRACKING 1 SCOPE 1.1 This note summarises the results of surveys and investigations of Australian and overseas incidents with deaerators and associated water storage vessels, and makes recommendations

More information

SAN DIEGO GAS & ELECTRIC COMPANY SOUTHERN CALIFORNIA GAS COMPANY

SAN DIEGO GAS & ELECTRIC COMPANY SOUTHERN CALIFORNIA GAS COMPANY PRELIMINARY STATEMENT 1. These responses and objections are made without prejudice to, and are not a waiver of, SDG&E and SoCalGas right to rely on other facts or documents in these proceedings. 2. By

More information

Innovations in the Integrity Management of Seam Welds in Cyclic Service

Innovations in the Integrity Management of Seam Welds in Cyclic Service Presented at the PPIM Conference, Houston, February 11-12, 2015 Innovations in the Integrity Management of Seam Welds in Cyclic Service Ted L. Anderson Ian Smith Quest Integrity Group 1965 57 th Court

More information

THE CASE AGAINST CASINGS

THE CASE AGAINST CASINGS THE CASE AGAINST CASINGS Prior to 1993, the AREA Manual recommended that all pipelines carrying flammable gas and flammable liquids under the track to be encased in a larger steel pipe. This casing requirement

More information

PROLONG THE INTEGRITY OF HIGH ENERGY PIPING SYSTEMS: UNIT SPECIFIC STRATEGIC PLANNING

PROLONG THE INTEGRITY OF HIGH ENERGY PIPING SYSTEMS: UNIT SPECIFIC STRATEGIC PLANNING 2013 Thielsch Engineering, Inc. Pamela Smoske, Executive Director of Development and Operations; 4-SYTE Systems PROLONG THE INTEGRITY OF HIGH ENERGY PIPING SYSTEMS: UNIT SPECIFIC STRATEGIC PLANNING High-energy

More information

The Safety Board supported PHMSA s rulemaking in this area and closed the 1987 safety recommendations as acceptable action.

The Safety Board supported PHMSA s rulemaking in this area and closed the 1987 safety recommendations as acceptable action. Testimony of Bob Chipkevich, Director Office of Railroad, Pipeline and Hazardous Materials Investigations National Transportation Safety Board Before the Subcommittee on Highways, Transit and Pipelines

More information

Pipeline Integrity. QuestIntegrity.com CHALLENGE CONVENTION

Pipeline Integrity. QuestIntegrity.com CHALLENGE CONVENTION Pipeline Integrity Solutions Pipeline Integrity Management Services (PIMS) InVista Ultrasonic In-Line Inspection Technology Engineering Assessment and Consulting QuestIntegrity.com CHALLENGE CONVENTION

More information

PIPELINE INTEGRITY SOLUTIONS

PIPELINE INTEGRITY SOLUTIONS PIPELINE INTEGRITY SOLUTIONS Pipeline Integrity Management Services (PIMS) InVista Ultrasonic In-Line Inspection Technology Engineering Assessment and Consulting QuestIntegrity.com CHALLENGE CONVENTION

More information

American Petroleum Institute th St, NW Suite L St, NW Washington, DC Washington, DC December 1, 2017

American Petroleum Institute th St, NW Suite L St, NW Washington, DC Washington, DC December 1, 2017 David Murk Andrew Black Pipeline Manager, President & CEO Midstream & Industry Operations Association of Oil Pipe Lines American Petroleum Institute 900 17 th St, NW Suite 600 1220 L St, NW Washington,

More information

Catasrophic Failure of Aging Underground Pipelines Is Inevitable Under Certain Corrosion Conditions

Catasrophic Failure of Aging Underground Pipelines Is Inevitable Under Certain Corrosion Conditions Catasrophic Failure of Aging Underground Pipelines Is Inevitable Under Certain Corrosion Conditions M.ZEE,PHD FELLOW OF NACE, FELLOW OFASM Zee@exova.com (412)952-9441 NACE CERTIFIED CORROSION/ MATERIALS

More information

3. CLASSIFICATION AND IMPLICATIONS OF DAMAGE

3. CLASSIFICATION AND IMPLICATIONS OF DAMAGE 3. CLASSIFICATION AND IMPLICATIONS OF DAMAGE 3.1 Summary of Earthquake Damage There are no modifications to the Guidelines or Commentary of Section 3.1 at this time. 3.2 Damage Types There are no modifications

More information

Gas Transmission and Distribution Piping Systems

Gas Transmission and Distribution Piping Systems ASME B31.8-2007 (Revision of ASME B31.8-2003) Gas Transmission and Distribution Piping Systems ASME Code for Pressure Piping, B31 AN AMERICAN NATIONAL STANDARD Three Park Avenue New York, NY 10016 CONTENTS

More information

Half Pipe Sleeve Half Sole Repair Sleeve Pre-Stressed Metallic Sleeve. Manufacturers of : RELIABLE PIPES & TUBES LTD.

Half Pipe Sleeve Half Sole Repair Sleeve Pre-Stressed Metallic Sleeve. Manufacturers of : RELIABLE PIPES & TUBES LTD. OHSAS 18001:2007 CERTIFIED Manufacturers of : Half Pipe Sleeve Half Sole Repair Sleeve Pre-Stressed Metallic Sleeve General Half Repair pipe Sleeves are designed to avoid a costly shut down. Existing lines

More information

The following questions are in reference to SoCalGas/SDG&E s Line 2000-C Hydrotest Project presented in A for reasonableness review.

The following questions are in reference to SoCalGas/SDG&E s Line 2000-C Hydrotest Project presented in A for reasonableness review. QUESTION 01: Please provide the detailed chain of events leading to identifying the wrinkle bend on Test Section 7. RESPONSE 01: SoCalGas and SDG&E construe Test Section 7 to mean Test Break 7. With this

More information

Pipeline Records - - Lessons Learned. The Changing Industry Landscape and Transmission Records Implications NGA Operations Conference April 3, 2012

Pipeline Records - - Lessons Learned. The Changing Industry Landscape and Transmission Records Implications NGA Operations Conference April 3, 2012 Pipeline Records - - Lessons Learned The Changing Industry Landscape and Transmission Records Implications NGA Operations Conference April 3, 2012 Who Are We? CHA Consulting, Inc. CHA is a highly diversified,

More information

PART I PERFORMANCE OF MATERIALS IN SERVICE. Materials and Process Selection for Engineering Design: Mahmoud Farag

PART I PERFORMANCE OF MATERIALS IN SERVICE. Materials and Process Selection for Engineering Design: Mahmoud Farag PART I PERFORMANCE OF MATERIALS IN SERVICE 1 Performance of Materials in Service I Part I discusses the different types of failure and how to prevent, or at least delay, such failures by selecting appropriate

More information

BONDING, POTTING, WELDING

BONDING, POTTING, WELDING 40-60 Delaware St. BONDING, POTTING, WELDING Part No. PR303 - INDEX- : 5/17/05 This Quality Standard applies unless otherwise specified by drawing or specification. PAGE 1 : INDEX PAGE 2 : DEFINITIONS

More information

PHMSA Update Significant Accidents Review

PHMSA Update Significant Accidents Review PHMSA Update Significant Accidents Review 2015 RRC/PHMSA Training and Qualification Conference Thursday, September 17, 2015 11:15 11:45 AM - 1 - What We Regulate Pipeline Miles by System Types end of CY

More information

APPLYING ULTRASOUND FOR IN-LINE INSPECTION: FACTS AND ISSUES. By Dr. Michael Beller, NDT Systems & Services AG, Stutensee, Germany

APPLYING ULTRASOUND FOR IN-LINE INSPECTION: FACTS AND ISSUES. By Dr. Michael Beller, NDT Systems & Services AG, Stutensee, Germany APPLYING ULTRASOUND FOR IN-LINE INSPECTION: FACTS AND ISSUES Abstract By Dr. Michael Beller, NDT Systems & Services AG, Stutensee, Germany 1. In-Line Inspection Today the use of in-line inspection tools

More information

REINFORCING FIELD FABRICATED BRANCH CONNECTIONS USING COMPOSITE MATERIALS

REINFORCING FIELD FABRICATED BRANCH CONNECTIONS USING COMPOSITE MATERIALS Proceedings of IPC2006 6th International Pipeline Conference September 25-29, 2006, Calgary, Alberta, Canada IPC2006-10483 REINFORCING FIELD FABRICATED BRANCH CONNECTIONS USING COMPOSITE MATERIALS Chris

More information

ASSET INTEGRITY Project Case Studies

ASSET INTEGRITY Project Case Studies Project Case Studies Development of Corrosion Under Insulation (CUI) Protocol and Inspection Procedure Multi-National Natural Gas Pipeline Operator Texas Contacts Background A large multi-national energy

More information

Correlating Aldyl A and Century PE Pipe Rate Process Method Projections With Actual Field Performance

Correlating Aldyl A and Century PE Pipe Rate Process Method Projections With Actual Field Performance Correlating Aldyl A and Century PE Pipe Rate Process Method Projections With Actual Field Performance Dr. Gene Palermo Consulting for: Jana Laboratories Aurora, Ontario, Canada Abstract The recent Department

More information

NATIONAL ENERGY BOARD ONSHORE PIPELINE REGULATIONS

NATIONAL ENERGY BOARD ONSHORE PIPELINE REGULATIONS PDF Version [Printer-friendly - ideal for printing entire document] NATIONAL ENERGY BOARD ONSHORE PIPELINE REGULATIONS Published by Quickscribe Services Ltd. Updated To: [includes Federal Regulation SOR/2016-134

More information

NAME 345 Welding Technology Lecture 03 (Welding Joint Design)

NAME 345 Welding Technology Lecture 03 (Welding Joint Design) NAME 345 Welding Technology Lecture 03 (Welding Joint Design) Md. Habibur Rahman Lecturer Department of Naval Architecture & Marine Engineering Bangladesh University of Engineering & Technology Dhaka-1000,

More information

PHMSA Rule Update. David Johnson November 14, 2018

PHMSA Rule Update. David Johnson November 14, 2018 PHMSA Rule Update David Johnson November 14, 2018 PHMSA Active Rulemakings Gas Transmission (Mega Rule) now 3 parts o o o MAOP, Assessment requirements Repair criteria, IM improvements, CP, MOC Gas gathering

More information

Structural design criteria

Structural design criteria chapter three Structural design criteria Contents 3.1 Modes of failure... 3.2 Theories of failure... 3.3 Theories of failure used in ASME Boiler and Pressure Vessel Code... 3.4 Allowable stress limits

More information

Gas Transmission and Distribution Piping Systems

Gas Transmission and Distribution Piping Systems ASME B31.8-2010 (Revision of ASME B31.8-2007) Gas Transmission and Distribution Piping Systems ASME Code for Pressure Piping, B31 A N A M E R I C A N N A T I O N A L S T A N D A R D ASME B31.8-2010 (Revision

More information

Asset Integrity Management Damage mechanisms. in South American pipelines

Asset Integrity Management   Damage mechanisms. in South American pipelines Asset Integrity Management www.giemdp.com.ar Damage mechanisms in South American pipelines Damage mechanisms in South American pipelines GIE experiences José Luis Otegui, Ph.D Damage mechanisms in South

More information

Module 4 Design for Assembly

Module 4 Design for Assembly Module 4 Design for Assembly Lecture 2 Design for Welding-I Instructional Objective By the end of this lecture, the student will learn: (a) how a weld joint should be designed to improve the joint performance,

More information

PREPARED REBUTTAL TESTIMONY OF DAVID M. BISI SOUTHERN CALIFORNIA GAS COMPANYAND SAN DIEGO GAS & ELECTRIC COMPANY

PREPARED REBUTTAL TESTIMONY OF DAVID M. BISI SOUTHERN CALIFORNIA GAS COMPANYAND SAN DIEGO GAS & ELECTRIC COMPANY Application No: A.1-0-01 Exhibit No.: Witness: David M. Bisi Application of Southern California Gas Company (U 0 G) and San Diego Gas & Electric Company (U 0 G) for Low Operational Flow Order and Emergency

More information

FILED :59 PM

FILED :59 PM BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA FILED 4-21-16 04:59 PM Application of San Diego Gas & Electric Company (U902G) and Southern California Gas Company (U904G) for a Certificate

More information

Weld Imperfections and Preventive Measures

Weld Imperfections and Preventive Measures FOURTH EDITION Weld Imperfections and Preventive Measures Published by FOURTH EDITION Weld Imperfections and Preventive Measures Kita-Shinagawa, Shinagawa-Ku, Tokyo, 141-8688 Japan Published by KOBE STEEL,

More information

Gas Transmission and Distribution Piping Systems

Gas Transmission and Distribution Piping Systems ASME B31.8-2014 (Revision of ASME B31.8-2012) Gas Transmission and Distribution Piping Systems ASME Code for Pressure Piping, B31 AN INTERNATIONAL PIPING CODE ASME B31.8-2014 (Revision of ASME B31.8-2012)

More information

For almost 20 years, composite

For almost 20 years, composite As seen in the issue of Assessing the state of composite repair systems With improved innovations and technology, the pipeline industry will benefit from the continued development of composite materials.

More information

In-Line Inspection Data Interpretation Appalachian Underground Corrosion Short Course (AUCSC)

In-Line Inspection Data Interpretation Appalachian Underground Corrosion Short Course (AUCSC) In-Line Inspection Data Interpretation 2018 Appalachian Underground Corrosion Short Course (AUCSC) By Terry Shamblin and W. K. Bill Deaton, P.E. May 15 th, 2018 For Consideration Discussion Question Does

More information

Oil and Gas Pipeline Design, Maintenance and Repair

Oil and Gas Pipeline Design, Maintenance and Repair Oil and Gas Pipeline Design, Maintenance and Repair Dr. Abdel-Alim Hashem El-Sayed Professor of Petroleum Engineering Mining, Petroleum & Metallurgical Eng. Dept. Faculty of Engineering Cairo University

More information

Composite Repairs Past, Present, and Future Composite Repair Users Group Quarterly Meeting (Houston, Texas) Wednesday, December 11, 2013

Composite Repairs Past, Present, and Future Composite Repair Users Group Quarterly Meeting (Houston, Texas) Wednesday, December 11, 2013 Composite Repairs Past, Present, and Future Composite Repair Users Group Quarterly Meeting (Houston, Texas) Wednesday, December 11, 2013 Presentation by Chris Alexander Today s Presentation State of the

More information

RECENT CHANGES IN CODE REQUIREMENTS FOR REPAIR OF IN-SERVICE PIPELINES BY WELDING. William A. Bruce Materials Section, Edison Welding Institute

RECENT CHANGES IN CODE REQUIREMENTS FOR REPAIR OF IN-SERVICE PIPELINES BY WELDING. William A. Bruce Materials Section, Edison Welding Institute IPC2000-215 RECENT CHANGES IN CODE REQUIREMENTS FOR REPAIR OF IN-SERVICE PIPELINES BY WELDING William A. Bruce Materials Section, Edison Welding Institute ABSTRACT The API code requirements for repair

More information

Pipeline Safety Compliance

Pipeline Safety Compliance Wyoming Pipeline Authority Public Meeting Casper, Wyoming February 17, 2009 Presenter: John Beets - Principle GIS Technologist, Kansas City Operations Objectives: Who is the regulator? Brief review of

More information

ASTM Standards for Pipe & Fittings

ASTM Standards for Pipe & Fittings for Pipe & Fittings There are many International Standards for stainless and carbon steel pipes and fittings. The list below is a basic overview of some of these. For more in-depth details of these Standards

More information

Advanced Calculation Methods to Improve Pipeline Integrity Management

Advanced Calculation Methods to Improve Pipeline Integrity Management Advanced Calculation Methods to Improve Pipeline Integrity Management Daniel Ersoy, R&D Executive Director Gas Technology Institute Outline of Presentation 1. Acknowledgements 2. Background 3. Hydro-testing

More information

High Energy Piping Inspection Program for Power Generation and Process Industries. For Regulatory Compliance, Safety, and System Longevity

High Energy Piping Inspection Program for Power Generation and Process Industries. For Regulatory Compliance, Safety, and System Longevity High Energy Piping Inspection Program for Power Generation and Process Industries For Regulatory Compliance, Safety, and System Longevity EAPC Industrial Services offers an inspection plan for assessment

More information

Another component of the depth of cover maintenance program will be regular in-water surveys of crossings with elevated scour potential.

Another component of the depth of cover maintenance program will be regular in-water surveys of crossings with elevated scour potential. CA PDF Page 1 of 16 2.0 PIPELINE CONDITION ASSESSMENT To demonstrate that the pipe for conversion from natural gas to oil service will be suitable for the intended service, an EA was completed to assess

More information

Subpart E Welding of Steel in Pipelines

Subpart E Welding of Steel in Pipelines Subpart E Welding of Steel in Pipelines 192.221 Scope This subpart prescribes minimum requirements for welding steel materials in pipelines. This subpart does not apply to welding that occurs during the

More information

DOUBLE WALLED PIPING SYSTEMS

DOUBLE WALLED PIPING SYSTEMS DOUBLE WALLED PIPING SYSTEMS The design and construction of a double wall pipe is more complex than a single wall pipe because of the additional pipe, associated welds and tie in procedures. There are

More information

Module 3 Selection of Manufacturing Processes. IIT Bombay

Module 3 Selection of Manufacturing Processes. IIT Bombay Module 3 Selection of Manufacturing Processes Lecture 3 Design for Bulk Deformation Processes Instructional objectives By the end of this lecture, the students are expected to learn the working principle

More information

CHAPTER II DIRECT TESTIMONY OF RONN GONZALEZ ON BEHALF OF SOUTHERN CALIFORNIA GAS COMPANY AND SAN DIEGO GAS & ELECTRIC COMPANY

CHAPTER II DIRECT TESTIMONY OF RONN GONZALEZ ON BEHALF OF SOUTHERN CALIFORNIA GAS COMPANY AND SAN DIEGO GAS & ELECTRIC COMPANY Application No.: A.-0-0XXX Exhibit No: Witness: R. Gonzalez Application of Southern California Gas Company (U 0 G) and San Diego Gas & Electric Company (U 0 G) for (A) Approval of the Forecasted Revenue

More information

Standard Specification for Seamless Cold-Drawn Carbon Steel Feedwater Heater Tubes 1

Standard Specification for Seamless Cold-Drawn Carbon Steel Feedwater Heater Tubes 1 Designation: A 556/A 556M 96 (Reapproved 2005) www.tubingchina.com Standard Specification for Seamless Cold-Drawn Carbon Steel Feedwater Heater Tubes 1 This standard is issued under the fixed designation

More information

CFC-SEU DATA REQUEST-005 SOCALGAS- SDG&E 2019 GRC A /8 SEU RESPONSE DATE RECEIVED: FEBRUARY 14, 2018 DATE RESPONDED: MARCH 1, 2018

CFC-SEU DATA REQUEST-005 SOCALGAS- SDG&E 2019 GRC A /8 SEU RESPONSE DATE RECEIVED: FEBRUARY 14, 2018 DATE RESPONDED: MARCH 1, 2018 Exhibit Reference: SDG&E-33, SCG -15 SDG&E Witness: Gentes, Phillips Subject: Define critical customer, RAMP, RSE s 1. SDGE-33, page RCG-3, describes the Capital Planning Process: "The capital requirements

More information

) ) ) ) ) ) ) ) UPDATED SUPPLEMENTAL DIRECT TESTIMONY OF DAVID BUCZKOWSKI SAN DIEGO GAS & ELECTRIC COMPANY AND SOUTHERN CALIFORNIA GAS COMPANY

) ) ) ) ) ) ) ) UPDATED SUPPLEMENTAL DIRECT TESTIMONY OF DAVID BUCZKOWSKI SAN DIEGO GAS & ELECTRIC COMPANY AND SOUTHERN CALIFORNIA GAS COMPANY Application No: Exhibit No.: Witness: A.1-1-01 David Buczkowski Application of Southern California Gas Company (U 0 G and San Diego Gas & Electric Company (U 0 G For Authority To Recover North-South Project

More information