Appendix U Draft exceedence response plans

Size: px
Start display at page:

Download "Appendix U Draft exceedence response plans"

Transcription

1 Appendix U Draft exceedence response plans

2 Draft Exceedence Response Plans Rev [0] [April 202]

3 Stage Groundwater Monitoring Bore Aquifer Testing Revision B March 202 TABLE OF CONTENTS.0 EXCEEDENCE RESPONSE PLANS 2.0 RESPONSE PLAN I THRESHOLD VALUES FOR SURFACE WATER QUALITY AND WATER ENVIRONMENTAL VALUES ARE EXCEEDED 2.2 Exceedence Response Plan Phase 2.3 Exceedence Response Plan Phase Exceedence Response Plan Phase RESPONSE PLAN IIA THRESHOLD VALUES FOR AQUIFER DRAWDOWN ARE EXCEEDED 3. Introduction 3.2 Threshold Groundwater Monitoring Program 3.3 Classification of Monitoring Installations 3.4 Exceedence Response Plan Phase Management Process 3.4. Early Warning Monitoring Bore Exceedence Threshold Monitoring Bore Exceedence without Early Warning Monitoring Bore Exceedence Threshold Monitoring Bore Exceedence with previous Early Warning Monitoring Bore Exceedence 4.0 PART IIB THRESHOLD VALUES FOR AQUIFER DRAWDOWN AT GROUNDWATER PRODUCING BORES ARE EXCEEDED 5.0 PART IIC THRESHOLD VALUES FOR GROUNDWATER CONTAMINATION ARE EXCEEDED 5. Introduction 5.2 Threshold Development 5.3 Exceedence Response Plan Phase Management Process 5.3 Exceedence Response Plan Phase 2 Management Process 5.4 Exceedence Response Plan Phase 3 Management Process 6.0 PART III SUBSIDENCE OR SURFACE DEFORMATION OCCURS WHICH IMPACTS ON SURFACE OR GROUNDWATER HYDROLOGY 6. Introduction 6.. Ground Motion Over Time 6..2 Types of Deformation Event 6..3 Ground Motion Monitoring and Management Plan 6..4 General Ground Motion Data Review Process 6.2. Exceedence Response Plan - Phase Exceedence Response Plan - Phase Exceedence Response Plan Phase 3 Management Process 2 of 25

4 Stage Groundwater Monitoring Bore Aquifer Testing Revision B March EXCEEDENCE RESPONSE PLANS This document contains draft exceedence response plans that include mechanisms to avoid, minimise and manage the risks of adverse impacts and response actions and timeframes if: Threshold values for surface water quality and water environmental values specified in the Stage 2 WMMP are exceeded Threshold values specified in the Stage 2 WMMP for aquifer drawdown or groundwater contamination are exceeded Subsidence or surface deformation occurs which impacts on surface or groundwater hydrology These response plans have been developed in accordance with the requirements of Condition 52d i of Approval Referral EPBC QGC uses an adaptive management framework in relation to the management of threshold exceedences. Response Plan I will also be used for planned discharges of treated CSG water from the Woleebee Creek WTP at Glebe Weir on the Dawson River. QGC will develop an REMP for the Dawson River in parallel with EA and BUA conditions. Response Plan IIA has been developed as part of a collaborative effort with the other three major CSG operators in the southern Bowen and Surat Basins.The plan is a draft and will be subject to further monitoring data and QWC modelling results becoming available. Response Plan IIB Aquifer Drawdown is yet to be developed and is subject to the final release of the QWC UWIR. Response Plan IIB Groundwater Contamination and III Subsidence are also in draft. A separate response plan for unforeseen emergency discharges has been developed and is part of the Procedure Site Emergency Response Kenya presented at Appendix S of the Stage 2 WMMP. 5 of 25

5 Stage Groundwater Monitoring Bore Aquifer Testing Revision B March RESPONSE PLAN I THRESHOLD VALUES FOR SURFACE WATER QUALITY AND WATER ENVIRONMENTAL VALUES ARE EXCEEDED 2. Introduction QGC has in place an REMP which monitors surface water quality for the approved temporary discharge of treated CSG water to Wieambilla Creek and in association with SunWater the discharge of treated CSG water to Chinchilla Weir. Where monitoring results from release points at Wieambilla Creek and Chinchilla Weir indicate an exceedence of the investigation and reporting trigger limit for any of the toxicants specified in Tables T- and T-2, a phased Critical Review Process built within a risk assessment framework is to be carried out. This will be aimed at quantifying the risks posed by that toxicant to the aquatic environments, or organisms found in and around the receiving waters at the release point. The Critical Review process is outlined at Figure T-. Table T-: Release Limits: EA PEN for discharge to Wieambilla Creek Release Point Physiochemical Parameters Release Limits Limit Type Monitoring Frequency Sampling Point RP Electrical ConductivityµScm) 300 Maximum Daily during release S RP ph ph unit) Range Daily during release S RP Dissolved Oxygen mgl) 4 Minimum Daily during release S2 RP Temperature ºC) 26 Maximum Daily during release S2 RP Suspended Solids mgl) 45 Maximum Monthly during release S RP Calcium mgl) 2-3 Range Weekly during release S RP Chloride mgl) 42 Maximum Weekly during release S RP Fluoride mgl) Maximum Weekly during release S RP Magnesium mgl) 2-0 Range Weekly during release S RP Sodium mgl) 75 Maximum Weekly during release S RP Sulphate mgl) 4.6 Maximum Weekly during release S RP Chlorophyll-aµgL) NA NA Monitor in REMP As per QGC REMP RP Hardness mgl) 72 Maximum Weekly during release S RP Alkalinity mgl) 7.5 Minimum Weekly during release S RP SAR 4 Maximum Weekly during release S RP Ammonia mgl) 0.9 Maximum Weekly during release S 6 of 25

6 Stage Groundwater Monitoring Bore Aquifer Testing Revision B March 202 Table T-2: Release Limits: BUA ENBU02708 Discharge of treated water to Chinchilla Weir Characteristic of Resource Quality Limit Limit Type Monitoring Frequency Electrical Conductivity µscm) 500 Maximum Continuous ph ph unit) Range Continuous Total Suspended Solids mgl) 75 Maximum Monthly Calcium mgl) 6 Minimum Weekly Chloride mgl) 35 Maximum Weekly Fluoride mgl) 0.5 Maximum Weekly Magnesium mgl) 4.5 Minimum Weekly Sodium mgl) 95 Maximum Weekly Sulphate mgl) 8.8 Maximum Weekly Total Dissolved Solids mgl) 320 Maximum Weekly Alkalinity mgl) 20 Minimum Weekly SAR 6 Maximum Weekly Boron mgl).0 Maximum weekly in situ, continuous or field monitoring 2.2 Exceedence Response Plan Phase Following initial advice to the Minister, within 0 days of the exceedence, a Phase Desktop Review and written report will be prepared and submitted to SEWPaC within 60 days of the exceedence and address the following: Verification of the exceedence from results of a re-analysis of the sample exceedence and a resampling at the relevant discharge location; Changes in processes natural or anthropogenic) or source water quality in and around the sample area that may have contributed to the exceedence; Likelihood of continued exceedences without further action, considering the sources and pathways identified; Management options to avoid future exceedences; Any additional monitoring required to confirm the significance and duration of the exceedence; Any changes recorded by the Receiving Environment Monitoring Program; and Statement about potential effects on the receiving environment and the need for toxicity assessment. Phase 2 is enacted where the conclusions of the Desktop Review identify an unacceptable risk of an adverse or significant effect on the receiving environment, andor SEWPaC concludes from the report that further investigation is required. 7 of 25

7 Stage Groundwater Monitoring Bore Aquifer Testing Revision B March 202 Figure T-: Surface Water QualityEV Risk Assessment Process 8 of 25

8 Stage Groundwater Monitoring Bore Aquifer Testing Revision B March Exceedence Response Plan Phase 2 Under Phase 2 of the Critical Review Process, an Ecotoxicological Risk Assessment ERA) will be conducted to quantify the risk posed by each and all toxicants that exceed the investigation and reporting trigger limit. This ERA process must follow the hierarchical approach as detailed in the Australian and New Zealand Environment and Conservation Council s Australian Water Quality Guidelines for Fresh and Marine Water Quality, December 2000 ANZECC 2000). Where there is insufficient pre-existing data to accurately quantify or estimate the risk posed by a particular chemical to aquatic organisms, there may be a requirement, at SEWPaC s discretion, to perform a: Toxicological Bioassay TB), designed to demonstrate that a specific toxicant found exceeding the Investigation and Reporting Trigger Limit does not exhibit acute toxicological effects in appropriate test specimens) when exposed to concentrations consistent with those observed in monitoring data for no less than hours, andor Direct Toxicity Assessment DTA), designed to demonstrate that the toxicants in the discharge water as a whole) do not exhibit acute toxicological effects in appropriate test specimens) when exposed to concentrations observed in monitoring data for no less than hours Where a TB or DTA is required, the bioassays are to: be performed on organisms belonging to five taxa from four taxonomical groups as per ANZECC 2000, and be approved by the administering authority. be conducted on discharge water that is a representation of normal plant operations. demonstrate that there is no observable effect in any of the TB or DTA test organisms after 24 hours, and if an observable effect is recorded; then an Incident Management Program IMP) comes into effect; and the outcome of the IMP will be that there is no observable adverse affect in any of the test organisms after an identical or equivalent) TB or DTA is repeated. A written report on the results, or progress of the ERA, must be submitted to the administering authority within 60 days of completion of the TB or DTA. Phase 3 is enacted where the conclusions of the Phase 2 study identify an unacceptable risk of an adverse or significant effect on the receiving environment andor SEWPaC concludes from the report that further investigation is required. 2.4 Exceedence Response Plan Phase 3 As noted, Phase 2 is a tailored program aimed at understanding the impact of the exceedence. Phase 3 is considered a mitigation phase where all investigative options and assessments have been completed. Measures that may be considered during this phase include: The development and implementation of a long-term incident management process Modifications to plant or infrastructure Review of the beneficial reuse practices currently in place. 9 of 25

9 Stage Groundwater Monitoring Bore Aquifer Testing Revision B March RESPONSE PLAN IIA THRESHOLD VALUES FOR AQUIFER DRAWDOWN ARE EXCEEDED 3. Introduction QGC has in place a Groundwater Monitoring Program which is intended to monitor groundwater level and quality at a network of monitoring bores on QGC leases and between QGC leases and MNES springs. Through this monitoring network, water level responses for each aquifer of interest can be monitored for drawdown if any). Threshold values for this aquifer drawdown exist for geological strata that: are hydraulically connected or potentially connected to MNES springs are strata from which groundwater is extracted for domestic use, stock watering, irrigation, industrial usage or town water supply. Under its Australian Government EPBC approval conditions, QGC has responsibility for surveying and monitoring of spring clusters at Scott s Creek, Dawson River 8 and Cockatoo Creek. Responsibility is shared with Origin at Dawson River 8Cockatoo Creek spring complexes and Origin and Santos at Scott s Creek springs. It is intended that this unified approach to MNES monitoring will enable a more robust standardised monitoring program to be implemented. Benefits of this collaborative approach among proponents include minimising the footprint in terms of intrusive drilling and a minimum but adequate number of monitoring locations being established. For the purpose of this plan, QGC assumes sole or shared responsibility for the following spring monitoring bores. Table T Early warning and threshold monitoring bores Bores Function Indicative Location QCLNG Tenure Aquifer monitored Spring Complex Monitored Spring Management Responsibilty Cassio GW, GW2 Early Warning 30 km south of Taroom Cassio block Hutton, Precipice Dawson River 8Cockatoo Creek QGC CHAR 583 GW, GW2 Threshold Monitoring 0 km south of Taroom Off tenure Hutton, Precipice Dawson River 8Cockatoo Creek QGC Charlie GW, GW2 Early Warning 40 km northwest of Wandoan Charlie block Hutton, Precipice Scott s Creek QGC Charlotte GW, GW2 Threshold Monitoring 60 km northwest of Wandoan Charlotte block Hutton, Precipice Scott s Creek QGC Indicative monitoring bore locations are shown at Figure T-2. All proposed CSG company monitoring bores in the vicinity of MNES springs are shown at Figure T-3. 0 of 25

10 Stage Groundwater Monitoring Bore Aquifer Testing Revision B March 202 Figure T-2 QGC monitoring bores #)) 2:6 2:,,-.0) > 2:4,;8=6 2:4,;8=, #)) Stage 2 QGC groundwater monitoring bores and VWPs Towns Roads Watercourses Springs for QGC survey Other springs VWP well conversions WCM and shallow aquifers) Pressure monitoring VWPs) # # Shallow formations Deep formations 564 2:6 2:, 0:> 4-: 0-5>, 2>9>8 39>,; 24>>,< 23, 23, # 23< 23) 23>; ; 237 0B>7 # <4=,54= 0. 6:7;.6 4@>6 >:=>:774 Water quality and water level monitoring Condamine Alluvium Mooga Gubberamunda Westbourne Springbok Walloons Eurumbah Hutton Precipice QCLNG EIS Area QGC Field QCLNG PL QCLNG ATP 5=,46:=; 5, 56 9, 96 9) 98 5> , ; 3..<?5@4= ) 5.4>, 3..>) #8 00#, #, # # # 00#6 #6 #) 00#>,8,, 6 ) #,, # 2A>,) 344 <?.9>,, Kilometers Scale :,000,000 A3) # -., of 25

11 Groundwater Project QCLNG Stage Groundwater Monitoring Bore Aquifer Testing Revision B March 202 Figure T-3 CSG company monitoring bores for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antos Precipice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antos Hutton 8-3J8ECN?G?NC APLNG Precipice 6>A><B84@K F>E8@RK E2).K@:.5.LL25)M..0NH.)2.05.)M990L25N)9209G)9II##5).OAM.I2#)9202L <: =:?@ABCDCEF 2GE?HIFJ8# 6>A><B84@K 4KG8EAPCND?AHQ3R> 4KG8EAPCND?AHQ3R> )M990L25N)920M2IH02).5.I9.H20)M..P#)L9.IHI2#)920O 8-3JODDAH APLNG Hutton?@ABCDCEF?@ABCDCEF : : 2KHDAFAHZCHD?AHK@3KF [3 3 0, AKLFMKDCENAOEFCFJ3 )CHCBCHDFJ4 2GE?HIFJ8# AKLFMKDCENAOEFCFJ3 )CHCBCHDFJ4 >: 2Q ;QST:M::: U=V 2Q ;QST:M::: U=V E2).K@:.5.LL25)M..0NH.)2.05.)M990L25N)9209G)9II##5).OAM.I2#)9202L )M990L25N)920M2IH02).5.I9.H20)M..P#)L9.IHI2#)920O Scale :680,000 A3) 8-3W2KHDAFJ8ECN?G?NC APLNGSantos Precipice 2KHDAFAHZCHD?AHK@3KF 2KHDAFAHZCHD?AHK@3KF 6>A@K :>W:RW<:;< =>FE<K 2Q 4Y;R>S:Y:; ;QST:M::: U=V 4KG8EAPCND?AHQ3R> 8@QE<K 48@>A@6C-K 5 )3 =>FE<K 2GE?HIFJ8# 6>A@K :>W:RW<:;< 4Y;R>S:Y:; 6>A><B84@K 03 =>FA-F@K Z> DXCE 4S@4T@6C-K AKLFMKDCENAOEFCFJ3 8@QE<K 48@>A@6C-K 5 )3 )CHCBCHDFJ4 3 F>E8@RK Z> DXCE 03 =>FA-F@K 4S@4T@6C-K - [3 2KHDAF 2 of W2KHDAFJODDAH QPLNGSantos Hutton [3 :>W:RW<:;< =>FE<K 4Y;R>S:Y:; 6>A@K 8-3J8ECN?G?NC 2KHDAFJODDAH 48@>A@6C-K 5 )3 8@QE<K 2KHDAFJ8ECN?G?NC 2KHDAFJODDAH 03 =>FA-F@K Z> DXCE 4S@4T@6C-K A.0.N.0)S2IH.5 2KHDAFJ8ECN?G?NC F>E8@RK 8-3 =?@ QGC Precipice [3J8ECN?G?NC 2KHDAF ) ) ) 2KHDAF Kilometres ) ) APLNG W2KHDAFJODDAH [3J8ECN?G?NC - 2KHDAF Santos 8-3W2KHDAFJ8ECN?G?NC 8-3W2KHDAFJODDAH [3 QGC 8-3JODDAH 8-3W2KHDAFJ8ECN?G?NC D>E6<>E 2KHDAFAHZCHD?AHK@3KF Santos Conventional Gas 8-3J8ECN?G?NC 8-3JODDAH A.0.N.0)S2IH.5 QGC Hutton [3JODDAH [3JODDAH KE@]KEH?HI4AH?DAE?HI5AECF ARROW 0 KE@]KEH?HI4AH?DAE?HI5AECF ) )E?IICE4AH?DAE?HI5AECF - - ) Monitoring Bores Trigger Early Warning Monitoring Bores ?FDCL2GE?HIJ4AH?DAE?HIHADC\O?ECLOHLCE6# 42#) # Monitoring Wells [3J8ECN?G?NC [3JODDAH 5 ) 8-3W2KHDAFJ8ECN?G?NC 2GE?HI4AH?DAE?HI8EAIEKBBCJ[3 Springs56Impact Mitigation Santos 2GE?HIF#BGKND4?D?IKD?AHJ2KHDAF A.0.N.0)S2IH.5 2GE?HIF#BGKND4?D?IKD?AHJ JODDAH # 85?FDCL2GE?HIJ4AH?DAE?HIHADC\O?ECLOHLCE6# 2GE?HI4AH?DAE?HI8EAIEKBBCJ[3 Spring Monitoring Programme QGC 8-3J8ECN?G?NC 5=209)2590JD.II -3 # 85?FDCL2GE?HIJ4AH?DAE?HIHADC\O?ECLOHLCE6# EPBC Listed Spring Monitoring not required 5 6 under UWIR 2KHDAFJODDAH )E?IICE4AH?DAE?HI5AECF ) - =209)2590JD.II 2KHDAFJ8ECN?G?NC )E?IICE4AH?DAE?HI5AECF KE@]KEH?HI4AH?DAE?HI5AECF Tenement Holder 5 FGH 5 3, ) 2GE?HIF#BGKND4?D?IKD?AHJ2KHDAF Springs Impact Mitigation APLNG ) # ), ) 6JB44B =209)2590JD.II G590J?NG#)=0J.N.0))5).J [3JODDAH Springs Impact Management Strategy # G590J?NG#)=0J.N.0))5).J 25#.K65L)B0H.5J520HD).5?NG#)8.G25) [3J8ECN?G?NC Source: Draft Underground Water Impact Report42#) #2)CHCBCHD5AOHLKE]<:_B5O``CE,6 L2).QH:.5.RR25)?..0SO.)2.05.)?990R25S)9 )?990R25S)920?2@O02).5.@9.O20 -JHKB 4KPAEKDCENAOEFCF 4KPAEAKLF )E?IICE4AH?DAE?HI5AECF #2)CHCBCHD5AOHLKE]<:_B5O``CE 4KPAEKDCENAOEFCF KE@]KEH?HI4AH?DAE?HI5AECF #2)CHCBCHD5AOHLKE]<:_B5O``CE ) A>8<<= 2GE?HIF#BGKND4?D?IKD?AHJ8-3 25#.K65L)B0H.5J520HD).5?NG#)8.G25) 8-3W2KHDAFJODDAH # Watercourses Major EIS Tenement Boundary 20 km Buffer =209)2590JD.II. #. # #) ). Town City )A^HW?D] 85?FDCL2GE?HIJ4AH?DAE?HIHADC\O?ECLOHLCE6# # )A^HW?D] Major Roads 4KPAEAKLF # 2GE?HI4AH?DAE?HI8EAIEKBBCJ[ :.5; 6 # 4KPAEKDCENAOEFCF G590J?NG#)=0J.N.0))5).J F52G2.H@5ID5090J G590J?NG#)=0J.N.0))5).J 25#.K65L)B0H.5J520HD).5?NG#)8.G25) F52G2.H@5ID5090J 0HA59JJ.5=209)2590J 25#.K65L)B0H.5J520HD).5?NG#)8.G25) 2GE?HIF#BGKND4?D?IKD?AHJ8-3 0HA59JJ.5=209)2590J C25. Proposed early warning and trigger monitoring bores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``CE, ) ). 2. # # # # ).- 56 ) # KPAEKDCENAOEFCF 3, - 4KPAEAKLF ) ) 5 4 8EFB )A^HW?D] <: 4KG8EAPCND?AHQ3R> 6BIBEJ84HQ ),. ) 2 # ) F52G2.H@5ID5090J 0HA59JJ.5=209)2590J C25. #, 3) )) ;:?@ABCDCEF # # 6 F52G2.H@5ID5090J 0HA59JJ.5=209)2590J C25. 2 # : 50

12 Stage Groundwater Monitoring Bore Aquifer Testing Revision B March Threshold Groundwater Monitoring Program For each spring cluster, it is proposed that groundwater level monitoring be undertaken at two locations. The first will be close to the area of CSG water extraction at or in the vicinity of tenement boundaries while the second will be located closer to the springs and nominally 20 km from tenement boundaries. The relative locations of monitoring bores, herein referred to as early warning monitoring installations and trigger monitoring installations, respectively, are shown in Figure T-4. This strategy recognises that: near-field responses may provide an early warning of potential far-field effects; it may take many years for far-field responses due to CSG water extraction activities to be observed; this especially applies to groundwater quality changes, and it may be difficult to detect far-field drawdown responses due to CSG activities which may potentially be very slight and less than natural or anthropogenic-induced fluctuations. 3.3 Classification of Monitoring Installations Monitoring installations have been split into two classifications: Early warning monitoring installations providing secondary data in support of observations made at threshold monitoring installations. At these locations, groundwater level changes are expected to be more pronounced in terms of the amplitude of response to CSG water extraction compared with trigger monitoring installations. Trigger monitoring installations monitoring groundwater levels and groundwater quality data in target aquifers in accordance with regulatory requirements. This will enable the accurate comparison of such data against threshold values for which management activities will be initiated in response to threshold exceedences. Observations made at early warning monitoring installations will have a trigger drawdown established, based on a modelled drawdown of 90 of the Cumulative Impact Model drawdown at the monitoring bore location. The drawdown value selected will be subject to the Queensland Water Commission s QWC) nominated percentile exceedence probable maximum drawdown. 3 of 25

13 Stage Groundwater Monitoring Bore Aquifer Testing Revision B March 202 Figure T-4. Cross section showing the relative positions of early warning and threshold monitoring locations in relation to CSG extraction and EPBC springs. 3.4 Exceedence Response Plan Phase Management Process Where monitoring results in the monitoring installations exceed threshold limits, a phased Critical Review Process built within a risk assessment framework will quantify the risks posed by the drawdown exceedence. The Critical Review Process is outlined at Figure T-5. QGC defines an exceedence as: Groundwater levels measured in a monitoring bore that are greater than a trigger value for a continuous period of three months. The response plan can be triggered by two events: when 90 of the estimated drawdown maximum allowable groundwater level threshold value) from the QWC Regional Groundwater Model occurs in an early warning monitoring bore; When a 0.2 m drawdown excluding natural and anthropogenic non CSG) variations) is observed in the trigger monitoring bore The Phase plan process will depend on whether either event has triggered the exceedence 4 of 25

14 Stage Groundwater Monitoring Bore Aquifer Testing Revision B March of 25

15 Stage Groundwater Monitoring Bore Aquifer Testing Revision B March Early Warning Monitoring Bore Exceedence Where 90 of the estimated drawdown from the QWC s Regional Groundwater Model occurs in an early warning monitoring bore,, initial advice to QGC management and SEWPaC will occur within 0 days of QGC becoming aware of the exceedence. A Phase Desktop Review and written report must be prepared and submitted to SEWPAC within 60 days of the initial advice and address the following: Verification of the exceedence from results of a manual standing water level measurement at the monitoring bore; Assessment and verification of groundwater level trend type using the approved trend assessment procedure; Identification of potential causes that may have contributed to the exceedence; Likelihood of continued exceedences without further action; Management options to avoid future exceedences; Any additional monitoring required to confirm the significance and duration of the exceedence Advice on the need for additional cumulative regional modelling or any recommended changes to the Groundwater Monitoring Plan; and Statement about potential drawdowns at trigger monitoring bores or effects on MNES andor non-csg groundwater users and the need for further assessment at springs. Recommendations for any Phase 2 work would be identified in the Phase report. No mitigation works would be expected to be proposed Trigger Monitoring Bore Exceedence without Early Warning Monitoring Bore Exceedence In this case, initial advice to QGC management and SEWPaC of an exceedence within 0 days of QGC becoming aware of the exceedence. A Phase Desktop Review and written report must be prepared and submitted to SEWPAC within 60 days of the first such exceedence and address the following: Verification of the exceedence from the results of a manual standing water level measurement at the monitoring bore; Assessment and verification of groundwater level trend type using the approved trend assessment procedure; Identification of potential causes that may have contributed to the exceedence; Likelihood of continued exceedences Recommended actions Recommendations for any Phase 2 work would be identified in the Phase report. No mitigation works would be expected to be proposed. For any subsequent exceedence where there has been no early warning monitoring bore exceedence, SEWPAC will be advised within 28 days of QGC becoming aware of the exceedence. 6 of 25

16 Stage Groundwater Monitoring Bore Aquifer Testing Revision B March Threshold Monitoring Bore Exceedence with previous Early Warning Monitoring Bore Exceedence In this case, initial advice would be provided to QGC management and to SEWPAC of an exceedence within 0 days of QGC becoming aware of the exceedence. The Phase Desktop Review and written report in this instance must be prepared and submitted to SEWPAC within 60 days of the exceedence and address the following: Verification of the exceedence from the results of a manual standing water level measurement at the monitoring bore; Assesment and verification of groundwater level trend type using the approved trend assessment procedure; Identification of potential causes that may have contributed to the exceedence; Assessment of likelihood of continued exceedences by additional groundwater modelling to better predict impacts) without further action; Outline management options to avoid future exceedences; Any additional monitoring required to confirm the significance and duration of the exceedence Any changes recorded by the Groundwater Monitoring Plan; and Statement about potential effects on MNES andor non-csg groundwater users and the need for further assessment at springs. Recommendations for any Phase 2 work would be identified in the Phase report. This could involve the installation of monitoring bores close to springs and further groundwater modelling. Mitigation works could also be proposed. 4.0 PART IIB THRESHOLD VALUES FOR AQUIFER DRAWDOWN AT GROUNDWATER PRODUCING BORES ARE EXCEEDED This response plan will be developed following the release of the QWC s Underground Water Impact Report. The plan will however incorporate the following steps; Incident report to QGC management and DERM within 0 days Initiation of Response Plan Investigation of likely drawdown causes. This will include a review of data; ascertain the sourcescauses of the exceedence Negotiations to rectify the drawdown and make good with the water user. 7 of 25

17 Stage Groundwater Monitoring Bore Aquifer Testing Revision B March PART IIC THRESHOLD VALUES FOR GROUNDWATER CONTAMINATION ARE EXCEEDED 5. Introduction QGC interprets this requirement as relating to the need to have a response plan in place in the unlikely event there are changes in groundwater quality due to inter-aquifer leakage. Accordingly, the response plan is designed to address threshold value exceedences by indicator parameters ph, total dissolved salts, bicarbonate, chloride) for the following locationsactivities: monitored water quality at springs; regional groundwater monitoring bores; Groundwater threshold values will be highly dependent on the location within the formation where groundwater is monitored. Groundwater threshold values will be developed in three stages; Stage Regional specific default groundwater quality threshold values will be developed based on existing groundwater quality information. Timing April 203. Stage 2 Initial site specific monitoring bore groundwater threshold values will be developed based on a minimum of three baseline analyses for bores constructed in 20202, where the resultant threshold values are consistent with the regional default groundwater threshold values or judged appropriate based on hydrochemical model development. Timing April 203. Stage 3 Final monitoring bore specific groundwater threshold values will be developed based on a minimum of three baseline analyses for bores constructed in 203, where the resultant threshold values are consistent with the regional default groundwater threshold values or judged appropriate based on hydrochemical model development. Timing end October Threshold Development Groundwater thresholds will be developed for key indicator parameters such as ph, TDS, bicarbonate and chloride by December 203. Note that this approach is consistent with the site specific adaptive management process which QGC will to develop across all operations. The current proposed investigation threshold is a 25 change in values from reading toreading for EC, bicarbonate and chloride and a change of.5 ph units from the upper baseline value. 8 of 25

18 Stage Groundwater Monitoring Bore Aquifer Testing Revision B March Exceedence Response Plan Phase Management Process Where trigger thresholds have been exceeded QGC management and SEWPaC will be advised within 0 days of QGC becoming aware of the exceedence. Subsequently a Phase Desktop Review and written report must be prepared and submitted to SEWPAC within 90 days of the exceedence being identified and address the following: Verification of the change in concentration causing an exceedence. This would at least involve re sampling and analysis of the location of interest; Review and assessment of the processes that may have contributed to the change; Likelihood of continued threshold exceedences without further action; Management options to avoid future exceedences; Any additional monitoring required to confirm the significance and duration of the exceedence; Any other changes recorded by the relevant monitoring program; and Statement about potential effects on the receiving environment and the need for further investigationassessment. Statement about potential effects on MNES andor non-csg groundwater users and the need for further assessment at springs. Recommendations for any Phase 2 work would be identified in the Phase report. 5.4 Exceedence Response Plan Phase 2 Management Process Phase 2 is enacted where the conclusions of the Desktop Review and the additional monitoring works defined above identify an unacceptable risk of an adverse or significant effect on the receiving environment, stakeholder, andor SEWPaC concludes from the report that further investigation is required. The current proposed Phase 2 process involves conducting a full risk assessment and the development of a conceptual model where sources, pathways and receptors are formally identified and assessed. In some instances the aquifers of interest are at some considerable depth with minimal connection to receptors. So while a threshold may have been exceeded the risk of the exceedence to receptors of concern could be minimal. A conceptual model and risk based approach defines the relationships between these three elements, which needs to be correctly defined before any mitigation or management plans are developed. 9 of 25

19 Stage Groundwater Monitoring Bore Aquifer Testing Revision B March 202 This conceptual model and risk assessment process would typically involve: Spatial definition of the area where the groundwater thresholds have been exceeded; Assessment of the geological hydrogeological conditions in that area and within the lithologies identified. Also review any pressure or water level data at this time to determine any changes in hydraulic conditions; A review of the geochemical conditions and an assessment of reactions that may be occurring that may be the cause of the change in water quality; Assessment of how and at the rate at which the inter aquifer leakage may be occurring via mass balanceflux assessments); Definition of the groundwater users in and around the area, their location relative to the area where the threshold exceedence occurred. Consideration will also be given to what this water is used for stock, irrigation etc); Development of a conceptual model for the area where all the study areas defined above are drawn together; Completion of a risk assessment based on these findings; Statement about potential effects on the receiving environment and the need for further investigationassessment; Statement about potential effects on MNES andor non-csg groundwater users and the need for further assessment at springs. Should this threshold exceedence be found to be a function of slowly evolving changes in aquifer water quality over time then QGC propose to adopt an adaptive management approach to the threshold. In such a case the derivation of the threshold would be revisited and a new threshold would be derived that more accurately allows for this naturally evolving system. 5.4 Exceedence Response Plan Phase 3 Management Process This could involve installation of monitorng bores close to springs and further groundwater modelling. This process is presented in the attached flow chart at Figure T-6 20 of 25

20 2 of 25 Groundwater Project QCLNG Stage Groundwater Monitoring Bore Aquifer Testing Revision B March 202

21 Stage Groundwater Monitoring Bore Aquifer Testing Revision B March PART III SUBSIDENCE OR SURFACE DEFORMATION OCCURS WHICH IMPACTS ON SURFACE OR GROUNDWATER HYDROLOGY 6. Introduction Currently QGC is in a data collection phase with regard to ground motion. The derivation of area specific triggers in relation to ground motion will be completed once the baseline program is complete and the adjoining programs have also been advanced in support of this process. However the absence of trigger values does not preclude the development of a response plan should the trigger values being derived be exceeded in the future. 6.. Ground Motion Over Time Should ground motion occur this motion is predicted to advance at a very slow rate over long time periods. This is due to the depths that the CSG process is occurring at, the competency of the rock the abstraction is occurring from as well as the competency of the overlying material. Settlement rates are estimated to be in the order of m for the WCMs for the lifetime of the project, with movement in the Springbok unit that overlays the WCMs estimated at less than 5 mm. These longer timeframes have been considered in the development of this response plan Types of Deformation Event While ground motion is expected to be very limited and occur over long timeframes QGC has tentatively identified the following deformation events that may require a risk management and a formal response: Movement in and around MNES or areas identified as a sensitive receptor; Movement in and around existing surface infrastructure; Defined cracking cracks in roads etc); General ground motion Ground Motion Monitoring and Management Plan In order to monitor and assess potential deformation relating to ground motion QGC are developing a ground motion monitoring and management plan General Ground Motion Data Review Process As detailed in the ground motion monitoring and management plan ground motion data will be reviewed every three years with a formal report generated every five years. There will be no reviews possible outside this period as satellite data compilation occurs over bi yearly periods. 6.2 Exceedence Response Plan Golder Associates, of 25

22 Stage Groundwater Monitoring Bore Aquifer Testing Revision B March Exceedence Response Plan - Phase Should a ground motion event be recorded during the data review process, either via the radar satellite program or physical observation, the following response process has been developed. A Desktop Review and written report will prepared and submitted to SEWPAC within a nominated number of days of the exceedence and address the following: QGC will advise SEWPaC within 0 days of unexpected ground motion being detected. QGC will undertake a Phase investigation which will include: o o o o o Ground motion data review including all historical records; Assess any changes to natural surface environments occurring independently of CSG activities increased erosion due to vegetation loss, changes in drainage or rainfall patterns etc) or changes in anthropogenic factors in the areas of interest; Report to SEWPaC in the area of interest Included in this report will be a statement about potential effects on the receiving environment and the need for further investigationassessment Statement about potential effects on MNES andor non-csg groundwater users and the need for further assessment at springs Recommendations for any Phase 2 work would be identified in the Phase report Exceedence Response Plan - Phase 2 Phase 2 is enacted where the conclusions of the Desktop Review identify an unacceptable risk of an adverse or significant effect on the receiving environment, stakeholder, andor SEWPaC concludes from the report that further investigation is required. The timeframe for Phase 2 depends on the specific exceedence, but considering the timeframes involved with the monitoring and measurement of ground motion response in this phase is expected to be six months at a minimum. QGC propose for Phase 2 to consist of the following in relation to ground motion:. Notify ecological and environmental teams of the motion. Commission ecological hydrological studies to assess the impact of this motion as necessary; Review current field survey plan and commission new field survey plans to include the area of interest as required; Once ecologicalhydrological impact studies are available submit to SEWPaC with a update; Examine the potential use of corner reflectors or an increase in radar satellite coverage. Statement about potential effects on the receiving environment and the need for further investigationassessment; Statement about potential effects on MNES andor non-csg groundwater users and the need for further assessment at springs. The studies referred to above are proposed to consist of: 23 of 25

23 Stage Groundwater Monitoring Bore Aquifer Testing Revision B March 202 Surface waterhydrologicecologic assessment of all surface waterways within the suspected deformation area. Through this process sensitive surface water bodies and waterways will be identified and quantified. Once these have been identified these features will be surveyed in detail by survey field teams. Assessment of all road bridges and major intersections within the suspected deformation area and ensure accurate surveys for these features are completed. Any surface cracks or deformation of the road surface will also be recorded. Assessment of any major man made structures that exist within the suspected deformation area such as large barns, grain silos etc). These structures will also be surveyed in detail and any defects or surface deformations noted. Once these assessments are completed QGC will catalogue those features according to environmental and community risk and then implement an ongoing detailed satellite and ground truthing monitoring program for these locations. Should Phase 2 yield inconclusive findings then it is intended to revisit the meothodologies utilised for the investigation, review their suitability in light of the findings and potentially engage in a revised study schedule andor aquifer assessment programs. QGC will inform the Minister via letter of the revsision to the investigation process and a revised monitoring schedule as necessary. Should this threshold exceedence be found to be a fuction of slowly evolving changes in ground surface elevations over time then QGC propose to adopt an adaptive management approach to the threshold. In such a case the derivation of the threshold would be reassessed and a new threshold derived Exceedence Response Plan Phase 3 Management Process Phase 3 is enacted where the conclusions of the Phase 2 investigation and the additional monitoring works defined above continue to identify an unacceptable risk of an adverse or significant effect on the receiving environment, andor SEWPaC concludes from the report that further investigationmonitoring is required. Measures that may be considered during this phase could include: The development and implementation of a long term incident management process; A modification of radar and field survey programs to enable more regular reporting for the area of interest; Numerical groundwater head modelling and ground motion estimation; Review potential modifications to water abstraction within aquifers and the area of interest to assess ground response; The continuation of field survey, ecological and hydrological assessment programs until the ground motion in the area of interest stabilises. Investigation of ground stabilisation solutions; Potential repair or relocation of any impacted infrastructure. This process is presented in the attached flow chart at Figure T of 25

24 Stage Groundwater Monitoring Bore Aquifer Testing Revision B March 202 Figure T-7 Ground Motion Exceedence Response Action Process 25 of 25

12.0. Exceedance thresholds and determining response actions

12.0. Exceedance thresholds and determining response actions 12.0 Exceedance thresholds and determining response actions 144 12.0 Exceedance thresholds and determining response actions 12.1 Introduction QGC has systematically quantified and now is implementing monitoring

More information

8.0. Springs monitoring and management the Joint Industry Plan

8.0. Springs monitoring and management the Joint Industry Plan 8.0 Springs monitoring and management the Joint Industry Plan 131 132 8.0 Springs monitoring and management the Joint Industry Plan # Department Condition Description Completion date Status Pre-Dec 2012

More information

Arrow Energy EIS GROUNDWATER IMPACT ASSESSMENT. April 2012

Arrow Energy EIS GROUNDWATER IMPACT ASSESSMENT. April 2012 Arrow Energy SURAT GAS PROJECT EIS GROUNDWATER IMPACT ASSESSMENT Jeroen van Dillewijn April 2012 FIRST A REFRESHER... Groundwater occurs in pores and fractures in rock and soil. Aquifers are layers that

More information

1.0. Stage 2 CSG water monitoring and management plan

1.0. Stage 2 CSG water monitoring and management plan 1.0 Stage 2 CSG water monitoring and management plan 2 1.0 Stage 2 CSG water monitoring and management plan 1.1 Introduction Coal seam gas has been produced in Queensland for more than 10 years and accounts

More information

Appendix K DERM database preliminary assessment

Appendix K DERM database preliminary assessment Appendix K DERM database preliminary assessment FILE NOTE SUBJECT: DERM GROUNDWATER MONITORING DATABASE ANALYSIS AUTHOR: NICOLE CARUSO DATE: MARCH 2012 PROJECT: GROUNDWATER Introduction QGC aims to undertake

More information

Santos Gas Field Development Project (GFD Project)

Santos Gas Field Development Project (GFD Project) Santos Gas Field Development Project (GFD Project) EPBC Approval No. 2012 / 6615 Annual Environmental Return 2017 Santos Ltd l 2017 GFD Project AER (2012/6615) l February 2018 Page 1 of 17 Introduction

More information

Stage 3 CSG water monitoring and management plan 1.0

Stage 3 CSG water monitoring and management plan 1.0 1.0 Stage 3 CSG water monitoring and management plan 1 2 1.0 Stage 3 CSG water monitoring and management plan 1.1 INTRODUCTION Coal seam gas has been produced in Queensland for more than 10 years and accounts

More information

QGC STAGE 3 WATER MONITORING MANAGEMENT PLAN 2015 ANNUAL REPORT

QGC STAGE 3 WATER MONITORING MANAGEMENT PLAN 2015 ANNUAL REPORT QGC STAGE 3 WATER MONITORING MANAGEMENT PLAN 2015 ANNUAL REPORT QGC 2015 Page 1 of 32 Scope and application In accordance with condition 49 (i) of its EPBC Approval and Stage 3 WMMP, QGC is required to

More information

COAL SEAM GAS WATER AND SALT MANAGEMENT STRATEGY

COAL SEAM GAS WATER AND SALT MANAGEMENT STRATEGY COAL SEAM GAS WATER AND SALT MANAGEMENT STRATEGY COAL SEAM GAS WATER AND SALT MANAGEMENT STRATEGY TABLE OF CONTENTS 1. INTRODUCTION... 2 1.1 Purpose... 2 1.2 Objectives... 2 2. ARROW OPERATIONAL AREAS...

More information

Community Information Session Surat Basin

Community Information Session Surat Basin Community Consultation June 2010 Community Information Session Surat Basin May 2011 1 INTRODUCTION OF PRESENTERS Tony Knight, Vice President, Exploration St John Herbert, Groundwater Modelling Coordinator

More information

Arrow Energy. Surat operational update. July 2016

Arrow Energy. Surat operational update. July 2016 Surat operational July 2016 Why we are here today Provide an to the community on Arrow s operational activities over the past 24 months Approval stages for the Surat Gas Project Upcoming survey activities

More information

11.0. Re-injection and repressurisation options

11.0. Re-injection and repressurisation options 11.0 Re-injection and repressurisation options 126 11.0 Re-injection and repressurisation options Condition 49c 11.1 Introduction Coal seam gas extraction cogenerates significant groundwater volumes which

More information

Advice to decision maker on coal mining project

Advice to decision maker on coal mining project . Advice to decision maker on coal mining project IESC 2015-063: West Muswellbrook Project New Development Requesting agency The New South Wales Mining and Petroleum Gateway Panel Date of request 27 January

More information

Appendix X.6 Queensland Government CSG Water Management Policy

Appendix X.6 Queensland Government CSG Water Management Policy Appendix X.6 Queensland Government CSG Water Management Policy Coal Seam Gas Water Management Policy June 2010 Tomorrow s Queensland: strong, green, smart, healthy and fair Purpose The purpose of this

More information

Appendix J: IESC Advice and Response Checklist

Appendix J: IESC Advice and Response Checklist Appendix J: IESC Advice and Response Checklist Description of the Proposal Description of the Proposal Groundwater Context and Conceptualisation A regional overview of the proposed Project area including

More information

CTSCo s Surat Basin Carbon Capture and Storage Project

CTSCo s Surat Basin Carbon Capture and Storage Project CTSCo s Surat Basin Carbon Capture and Storage Project The Surat Basin Carbon Capture and Storage Project aims to determine the viability of industrial-scale carbon capture and storage in the Surat Basin.

More information

15.0. Brine and salt management

15.0. Brine and salt management 15.0 Brine and salt management 257 258 15.0 Brine and salt management # Department Condition Description Completion date Status Pre-Dec 2012 Post-Dec 2012 48 Confirmation that salt regulated waste facility

More information

Arrow Energy. Surat development update. December 2017

Arrow Energy. Surat development update. December 2017 Surat development update December 2017 Why we are here today Arrow has agreed one of the largest gas supply deals on Australia s east coast: - 27-year deal between Arrow and QCLNG to commercialise the

More information

Holcim (Australia) Pty Limited. Lynwood Quarry Groundwater Monitoring Program Revision 2

Holcim (Australia) Pty Limited. Lynwood Quarry Groundwater Monitoring Program Revision 2 Holcim (Australia) Pty Limited Lynwood Quarry Groundwater Monitoring Program Revision 2 June 2011 Lynwood Quarry Groundwater Monitoring Program Revision 2 Prepared by on behalf of Holcim (Australia) Pty

More information

4.0. Surat QCLNG bore baseline program status

4.0. Surat QCLNG bore baseline program status 4.0 Surat QCLNG bore baseline program status 50 4.0 Surat QCLNG bore baseline program status 4.1 Summary of Plan Submitted and Approved by DEHP In accordance with the Water Act 2000 requirements (Section

More information

Arrow Update. Arrow Research. Groundwater monitoring and modelling. Demonstrations at Theten. Arrow Update. Domestic gas expansion activities

Arrow Update. Arrow Research. Groundwater monitoring and modelling. Demonstrations at Theten. Arrow Update. Domestic gas expansion activities Arrow appreciates the importance of groundwater for agricultural and domestic use, and the concern of potential impacts of coal seam gas development on water quality and supply. Groundwater monitoring

More information

Australia Pacific LNG Upstream Phase 1

Australia Pacific LNG Upstream Phase 1 Australia Pacific LNG Upstream Phase 1 Stage 1 CSG Water Monitoring and Management Plan Rev Date Details By Check Eng/QA App A 09-08-11 Issued for Review RM AM 0 18-08-11 Issued for Use RM AM KJ 1 01-02-12

More information

(No. of pages excluding this page = 10)

(No. of pages excluding this page = 10) SPECIALIST CONSULTANT STUDIES 3-65 BIG ISLAND MINING PTY LTD (No. of pages excluding this page = 10) Ltd BIG ISLAND MINING PTY LTD 3-66 SPECIALIST CONSULTANT STUDIES This page has intentionally been left

More information

ARROW ENERGY UPDATE COMMUNITY INFORMATION SESSIONS SEPTEMBER 2018

ARROW ENERGY UPDATE COMMUNITY INFORMATION SESSIONS SEPTEMBER 2018 ARROW ENERGY UPDATE COMMUNITY INFORMATION SESSIONS SEPTEMBER 2018 Arrow Energy update Community information session 4-5 September 2018 Introduction In September 2018, Arrow Energy (Arrow) held a series

More information

Appendix L Preliminary trend analysis methodology report

Appendix L Preliminary trend analysis methodology report Appendix L Preliminary trend analysis methodology report Methodology for groundwater level trend analysis Rev 0 April 2012 Uncontrolled when printed GROUNDWATER PROJECT Table of Contents 1.0 GROUNDWATER

More information

PROPOSALS FOR A GROUNDWATER CLASSIFICATION SYSTEM AND ITS APPLICATION IN REGULATION. Final Report (SR1 2007)

PROPOSALS FOR A GROUNDWATER CLASSIFICATION SYSTEM AND ITS APPLICATION IN REGULATION. Final Report (SR1 2007) UK Technical Advisory Group on the Water Framework Directive PROPOSALS FOR A GROUNDWATER CLASSIFICATION SYSTEM AND ITS APPLICATION IN REGULATION Final Report (SR1 2007) October 2007 Contents INTRODUCTION...

More information

14.0. Ensuring responsible CSG water management and beneficial use

14.0. Ensuring responsible CSG water management and beneficial use 14.0 Ensuring responsible CSG water management and beneficial use 194 14.0 Ensuring responsible CSG water management and beneficial use 14.1 Introduction QGC appreciates that careful management of water

More information

The following potential environmental receptors and impacts form the basis of TRCA s review under Ontario Regulation 166/06 and the Fisheries Act:

The following potential environmental receptors and impacts form the basis of TRCA s review under Ontario Regulation 166/06 and the Fisheries Act: TRCA Technical Guidelines for the Development of Environmental Management Plans for Dewatering September 2013 Rationale: The Technical Guidelines for the Development of Environmental Management Plans for

More information

COAL AND COAL SEAM GAS REGULATION

COAL AND COAL SEAM GAS REGULATION COAL AND COAL SEAM GAS REGULATION The Australian Government protects water resources from the impacts of coal and coal seam gas development through the water trigger provisions of the Environment Protection

More information

The following potential environmental receptors and impacts form the basis of TRCA s review under Ontario Regulation 166/06 and the Fisheries Act:

The following potential environmental receptors and impacts form the basis of TRCA s review under Ontario Regulation 166/06 and the Fisheries Act: Interim TRCA Technical Guidelines for the Development of Environmental Management Plans for Dewatering September 2013 Rationale: The Technical Guidelines for the Development of Environmental Management

More information

Appendix I Stage 1 groundwater monitoring bore pumping tests

Appendix I Stage 1 groundwater monitoring bore pumping tests Appendix I Stage 1 groundwater monitoring bore pumping tests Aquifer Testing Report Stage 1 Groundwater Monitoring Wells Rev [B] [March 212] Uncontrolled when printed GROUNDWATER PROJECT Groundwater Project

More information

Spring Gully North-West and North-East Project Preliminary Documentation. Appendix 2: Cross Reference with Request for Information

Spring Gully North-West and North-East Project Preliminary Documentation. Appendix 2: Cross Reference with Request for Information Spring Gully North-West and North-East Project Appendix 2: Cross Reference with Request for Information Spring Gully North-West and North-East Project Table 1 provides a cross reference of the request

More information

SEMI-QUANTITATIVE RISK ASSESSMENT FOR SMALL CLOSED LANDFILLS

SEMI-QUANTITATIVE RISK ASSESSMENT FOR SMALL CLOSED LANDFILLS SEMI-QUANTITATIVE RISK ASSESSMENT FOR SMALL CLOSED LANDFILLS Abstract Phil Lindsay (email: plindsay@golder.co.nz) Golder Associates Ltd Level 1, 79 Cambridge Terrace Christchurch Margaret Leonard Current

More information

Release Notice. Document Conventions. Document Custodian

Release Notice. Document Conventions. Document Custodian Release Notice This document is available through the Australia Pacific LNG (APLNG) Upstream Project controlled document system TeamBinder. The responsibility for ensuring that printed copies remain valid

More information

Groundwater and Surface Water Overview of the Lochend Area, Alberta

Groundwater and Surface Water Overview of the Lochend Area, Alberta Groundwater and Surface Water Overview of the Lochend Area, Alberta The Lochend Industry Producers Group (LIPG) conducted a hydrogeological / hydrological study in the Lochend operating field. The objectives

More information

PROTECTING WATER RESOURCES

PROTECTING WATER RESOURCES PROTECTING WATER RESOURCES WATER AT A GLANCE OUR PURPOSE Appropriately manage our impacts on water resources and ensure water security for our business and other water users. Laws and regulations Water

More information

Western Surat Gas Project Water Monitoring and Management Plan

Western Surat Gas Project Water Monitoring and Management Plan Western Surat Gas Project Water Monitoring and Management Plan Document Number: SENEX-WSGP-EN-PLN-011 Revision: 1 Position Name (tick one column only) Signature Date Approve Review Environment Manager

More information

8 Geology, Hydrology & Hydrogeology

8 Geology, Hydrology & Hydrogeology Inverneill Wind Farm Scoping Report Page 42 8 Geology, Hydrology & Hydrogeology 8.1 Introduction The EIA will consider the potential issues arising from the construction, operation and decommissioning

More information

Background. Much of the CA is directly underlain by the Walloon Coal Measures (WCM) which are the target of proposed coalbed methane (CBM) development

Background. Much of the CA is directly underlain by the Walloon Coal Measures (WCM) which are the target of proposed coalbed methane (CBM) development WaterTech 2016 Banff, Canada April 8, 2016 A Multi-Disciplinary Assessment of Hydrogeological Connectivity between Coal Measures and an Overlying Water Supply Aquifer, and Potential Impacts of Coalbed

More information

E30. Contaminated land

E30. Contaminated land E30. Contaminated land E30.1. Background This section addresses the effects of the discharge of contaminants from contaminated land or land containing elevated levels of contaminants into air, or into

More information

GROUND WATER. Practice Note # water. sensitive. urban. design \ \ \ \ \ \ \ \ \ \ \ \ \ \ \ \ \ \ \ \ \ \ \ \ \ \ \ \

GROUND WATER. Practice Note # water. sensitive. urban. design \ \ \ \ \ \ \ \ \ \ \ \ \ \ \ \ \ \ \ \ \ \ \ \ \ \ \ \ 2013 water. sensitive. urban. design \ \ \ \ \ \ \ \ \ \ \ \ \ \ \ \ \ \ \ \ \ \ \ \ \ \ \ \ Practice Note #8 GROUND Water Smart design is the effective planning, design and building of homes, subdivisions,

More information

Water Management in Queensland Coal Seam Gas. John Walsh, PhD CETCO Energy Services

Water Management in Queensland Coal Seam Gas. John Walsh, PhD CETCO Energy Services Water Management in Queensland Coal Seam Gas John Walsh, PhD CETCO Energy Services Background: Water Management in the Coal Seam Gas industry in Queensland is a complex and expensive undertaking Huge pipeline

More information

ATTACHMENT 5 AQUIFER INTERFERENCE POLICY AND WATER LICENSING ADDENDUM

ATTACHMENT 5 AQUIFER INTERFERENCE POLICY AND WATER LICENSING ADDENDUM ATTACHMENT 5 AQUIFER INTERFERENCE POLICY AND WATER LICENSING ADDENDUM COWAL GOLD MINE EXTENSION MODIFICATION TABLE OF CONTENTS A5 AQUIFER INTERFERENCE POLICY CONSIDERATIONS AND WATER LICENSING ADDENDUM

More information

Consultation Regulatory Impact Statement

Consultation Regulatory Impact Statement Consultation Regulatory Impact Statement Post Implementation Review of the Industry Levy to fund the petroleum and gas water functions of the Office of Groundwater Impact Assessment December 2016 This

More information

Spring Gully Water Treatment Facility Water Quality Discharge Annual Report

Spring Gully Water Treatment Facility Water Quality Discharge Annual Report Public Report Q-8220-15-RP-005 Spring Gully Water Treatment Facility Water Quality Discharge Annual Report Version: Rev 0 Released: 15/12/2011 Document Owner: Manager Land, Stakeholder and Environment

More information

27 Land and groundwater contamination

27 Land and groundwater contamination 27 Land and groundwater contamination Overview This Chapter assesses the potential effects of the proposed Expressway on identified areas of contaminated land with the Project area. The contamination assessment

More information

Coal Seam Gas: Context, Issues and (some) Solutions

Coal Seam Gas: Context, Issues and (some) Solutions Vision: To become the World Leader in CSG Education and Research Coal Seam Gas: Context, Issues and (some) Solutions Prof Chris Moran Director Sustainable Minerals Institute Interim Director Centre for

More information

Mid-Loddon Groundwater Management Area Local Management Rules

Mid-Loddon Groundwater Management Area Local Management Rules Mid-Loddon Groundwater Management Area Local Management Rules Annual Report For year ending 30 June 2015 Document History and Distribution Version (s) Version Date Author(s) Notes Draft 1 11 Sep 2015 A

More information

Environmental Impact Statement Surat Gas Project

Environmental Impact Statement Surat Gas Project 2. PROJECT APPROVALS This chapter details the principal approvals required by Arrow to construct, operate and decommission the including the role that the environmental impact statement (EIS) plays within

More information

2. Project Justification and Feasible Alternatives

2. Project Justification and Feasible Alternatives 2. Project Justification and Feasible Alternatives 2.1 Project Justification Energy intensive industries associated with the coal and gas sectors in the Surat region continue to drive electricity demand

More information

2017 Annual Compliance and Water Quality Monitoring Report Stormwater Return Dam (2010/5561)

2017 Annual Compliance and Water Quality Monitoring Report Stormwater Return Dam (2010/5561) 2017 Annual Compliance and Water Quality Monitoring Stormwater Return Dam (2010/5561) Table of Contents Introduction... 3 Monitoring Results... 3 Compliance Condition Checklist... 4 Document Information...

More information

Terms of Reference (TOR): Preparation Guide for Water and Wastewater Work Studies- EPB 389

Terms of Reference (TOR): Preparation Guide for Water and Wastewater Work Studies- EPB 389 Terms of Reference (TOR): Preparation Guide for Water and Wastewater Work Studies- EPB 389 Use of this guide is voluntary and at the risk of the user. This document provides a short introduction to a Terms

More information

Information Requirements Table for Liquid Waste

Information Requirements Table for Liquid Waste Applicant Summary Tracking # Authorization # Applicant / Facility Name Ministry of Environment Prepared by: Title Date The Information Requirements Table (IRT) for Liquid Waste is a tool used by Ministry

More information

CSG GROUNDWATER FIELD DAY [WORKBOOK]

CSG GROUNDWATER FIELD DAY [WORKBOOK] CSG GROUNDWATER FIELD DAY [WORKBOOK] Agenda Time Speaker Topic 9am Daniel Phipps CSG Project Officer AgForce Projects TAROOM 17 JUNE Introduction CSG activities across Queensland Make good framework Landholder

More information

in brief corrs Policy What it means for developments in april 2012

in brief corrs Policy What it means for developments in   april 2012 corrs in brief april 2012 Delivery of the Strategic Regional Land Use Policy What it means for developments in regional areas The NSW Government has recently released a number of draft plans, policies

More information

Monitoring Program Groundwater

Monitoring Program Groundwater Procedure Document No. 2791 Document Title Monitoring Program Groundwater Area HSE Issue Date 23 August 2017 Major Process Environment Sub Process Checking Authoriser Jacqui McGill Asset President Version

More information

Monitoring Program Groundwater

Monitoring Program Groundwater Procedure Document No. 2791 Document Title Area Shared Services Issue Date 27 July 2018 Major Process Environment Sub Process Environment Authoriser Jacqui McGill Asset President Version Number 16 TABLE

More information

Appendix B: Proposed trigger levels for groundwater quality and Response to Breach of Trigger Levels

Appendix B: Proposed trigger levels for groundwater quality and Response to Breach of Trigger Levels Appendix B: Proposed trigger levels for groundwater quality and Response to Breach of Trigger Levels Trigger levels Miners Road and Selwyn McLeans Island Suite 1 - All wells ph field measurement

More information

11 HYDROLOGY, HYDROGEOLOGY AND DRAINAGE

11 HYDROLOGY, HYDROGEOLOGY AND DRAINAGE 11 HYDROLOGY, HYDROGEOLOGY AND DRAINAGE 11.1 introduction 11.1.1 The objective of this section and the statements presented is to assess the existing hydrological and hydrogeological conditions to understand

More information

ARROW ENERGY SURAT GAS PROJECT. April 30 May 10

ARROW ENERGY SURAT GAS PROJECT. April 30 May 10 SURAT GAS PROJECT April 30 May 10 SURAT GAS PROJECT TODAY S AGENDA Welcome and introductions Arrow Energy update Field Development update Surat Gas Project Environmental Impact Statement (EIS) overview

More information

Groundwater Monitoring Requirements of the CCR Rule What s Next?

Groundwater Monitoring Requirements of the CCR Rule What s Next? 2017 World of Coal Ash (WOCA) Conference in Lexington, KY - May 9-11, 2017 http://www.flyash.info/ Groundwater Monitoring Requirements of the CCR Rule What s Next? Thomas A. Mann, PE SynTerra Corporation,

More information

Environmental Performance Report Guideline EPB 453

Environmental Performance Report Guideline EPB 453 Environmental Performance Report Guideline September 2013 EPB 453 Ministry of Environment TABLE OF CONTENTS 1 DEFINITIONS 3 2 INTRODUCTION 5 2.1 Purpose 5 2.2 Legislation 5 2.2.1 Environmental Assessment

More information

Wellsite Salt Remediation: Subsoil Salinity Tool vs. Site- Specific Salt Risk Assessment? Erik J. Martin, Ph.D., DABT

Wellsite Salt Remediation: Subsoil Salinity Tool vs. Site- Specific Salt Risk Assessment? Erik J. Martin, Ph.D., DABT Wellsite Salt Remediation: Subsoil Salinity Tool vs. Site- Specific Salt Risk Assessment? Erik J. Martin, Ph.D., DABT October 2011 Co-Authors David Alberti, M.Sc., P.Geol. Stantec David.Alberti@stantec.com

More information

REVIEW OF DEEP WAIRAU AQUIFER - GROUNDWATER CHEMISTRY ASPECTS. July 2008

REVIEW OF DEEP WAIRAU AQUIFER - GROUNDWATER CHEMISTRY ASPECTS. July 2008 REVIEW OF DEEP WAIRAU AQUIFER - GROUNDWATER CHEMISTRY ASPECTS July 2008 Client Report CSC0806 REVIEW OF DEEP WAIRAU AQUIFER - GROUNDWATER CHEMISTRY ASPECTS for the Marlborough District Council by Murray

More information

Bowen Gas Project. EIS Community Information Sessions. June Arrow s Moranbah Compression Station Bowen Basin

Bowen Gas Project. EIS Community Information Sessions. June Arrow s Moranbah Compression Station Bowen Basin Bowen Gas Project EIS Community Information Sessions June 2012 Arrow s Moranbah Compression Station Bowen Basin TODAY S AGENDA Arrow Energy Overview Arrow Energy Activities Bowen Gas Project Environmental

More information

UK Technical Advisory Group on the Water Framework Directive

UK Technical Advisory Group on the Water Framework Directive UK Technical Advisory Group on the Water Framework Directive Paper 11b(i) Groundwater Chemical Classification for the purposes of the Water Framework Directive and the Groundwater Daughter Directive. This

More information

Released by EHP under the

Released by EHP under the Tara Air Emission Data Collation Response to the Queensland Health Action Plan Report drafted by the Department of Environment and Heritage Protection Page 15-185 File B Page 1 of 18 Contents 1. Introduction...

More information

E31. Hazardous substances

E31. Hazardous substances E31. Hazardous substances E31.1. Background Hazardous substances include substances defined in the Hazardous Substances and New Organisms Act 1996 and substances with radioactive properties or high biological

More information

ATTACHMENT 2. Aquifer Interference Policy Considerations and Water Licensing COWAL GOLD OPERATIONS MINE LIFE MODIFICATION

ATTACHMENT 2. Aquifer Interference Policy Considerations and Water Licensing COWAL GOLD OPERATIONS MINE LIFE MODIFICATION ATTACHMENT 2 Aquifer Interference Policy Considerations and Water Licensing COWAL GOLD OPERATIONS MINE LIFE MODIFICATION Environmental Assessment 2016 TABLE OF CONTENTS A2 AQUIFER INTERFERENCE POLICY CONSIDERATIONS

More information

Appendix C: 2014 Monitoring Results and Interpretation

Appendix C: 2014 Monitoring Results and Interpretation Appendix C: 2014 Monitoring Results and Interpretation Quarterly monitoring of the pressure in artesian bores and water level in sub-artesian bores was undertaken in 2014 in accordance with the interim

More information

To construct or alter a bore

To construct or alter a bore Resource Consent Application Form 9A To construct or alter a bore For office use only Consent o Job o Important notes for the applicant You must complete this application form 9A and Resource Consent Application

More information

9.1 Introduction. 9.2 Issues

9.1 Introduction. 9.2 Issues 9 Groundwater 9.1 Introduction Groundwater is the water that occupies or moves through openings, cavities or spaces in geological formations under the ground. It is an important resource to many of Otago

More information

2. Assessing the potential risk to Groundwater

2. Assessing the potential risk to Groundwater Page no: 1 of 11 1. Introduction 1.1 This document provides guidance on the protection of the water environment from cemetery developments. It is for developers and local authorities intending to expand

More information

Bauxite Hills Project. Supplementary Report to the. Metro Mining. Section 3 Introduction. Environmental Impact Statement

Bauxite Hills Project. Supplementary Report to the. Metro Mining. Section 3 Introduction. Environmental Impact Statement Metro Mining Bauxite Hills Project Supplementary Report to the Environmental Impact Statement Section 3 Introduction 3 Introduction This section refers to submission comments relating to Chapter 1 Introduction

More information

Coal Seam Gas Water Management

Coal Seam Gas Water Management Coal Seam Gas Water Management Response to 2012 Draft Policy 30 November 2012 AgForce Queensland Industrial Union of Employers ABN 21 241 679 171 First Floor, 183 North Quay, Brisbane, Qld, 4000 PO Box

More information

CHAPTER 12 WATER VALUES AND QUALITY GULF ALUMINA LTD SKARDON RIVER BAUXITE PROJECT

CHAPTER 12 WATER VALUES AND QUALITY GULF ALUMINA LTD SKARDON RIVER BAUXITE PROJECT CHAPTER 12 WATER VALUES AND QUALITY GULF ALUMINA LTD SKARDON RIVER BAUXITE PROJECT TABLE OF CONTENTS 12.1 Introduction... 12-1 12.2 Environmental Objectives and Performance Outcomes... 12-1 12.2.1 Environmental

More information

1 Introduction 1-1. Project Need and Objectives

1 Introduction 1-1. Project Need and Objectives Introduction 1 CONTENTS 1 Introduction 1-1 1.1 1.1 Introduction Introduction 1-1 1-1 1.2 1.2 Project Overview Project Overview 1-1 1-1 1.3 1.3 Project Site Project Site 1-1 1-1 1.4 1.4 The Proponent The

More information

Contaminated Land Management

Contaminated Land Management Contaminated Land Management Helen Jones WSP Speaker Introduction Helen Jones WSP 2 Technical Executive in Contaminated Land Management at WSP. BSc Hon degree in Engineering Geology 22 years experience

More information

Wallerberdina Station site

Wallerberdina Station site JULY 2018 Wallerberdina Station site study Site characterisation studies at Wallerberdina Station completed Located around 30 kilometres north-west of Hawker is Wallerberdina Station, one of three sites

More information

Scope of Decree. Designation of water bodies

Scope of Decree. Designation of water bodies Ministry for Environmental Protection and Water (KvVM) Decree 30/2004. (XII. 30.) on rules for investigation of groundwaters Authorised by the provisions set forth in clause m), paragraph (8), Article

More information

Certainty in uncertainty: navigating environmental impact assessment regulatory processes

Certainty in uncertainty: navigating environmental impact assessment regulatory processes Certainty in uncertainty: navigating environmental impact assessment regulatory processes Geraldine Squires Principal Impact Assessment Manager, CEnvP IA Specialist, GHD Pty Ltd There is increased pressure

More information

Water Resources on PEI: an overview and brief discussion of challenges

Water Resources on PEI: an overview and brief discussion of challenges Water Resources on PEI: an overview and brief discussion of challenges Components: Components and links Atmospheric water Surface water (including glacial water) Groundwater Links: Precipitation (atm(

More information

A Risk to Groundwater from Coal Seam Gas Extraction in the Surat Basin

A Risk to Groundwater from Coal Seam Gas Extraction in the Surat Basin A Risk to Groundwater from Coal Seam Gas Extraction in the Surat Basin Bridle, A. 1 and Harris, C. 2 1 Talbingo Dalby, Qld 4405, Email: rabridle1@bigpond.com 2 Bungara Ironpot, Qld 4610, Email: caroline.harris1@bigpond.com

More information

Schedule 9 Water Quality Classification Standards and Criteria

Schedule 9 Water Quality Classification Standards and Criteria Schedule 9 Water Quality Classification Standards and Criteria The Water Quality Classification Standards and Criteria in Schedule 9 will be used to assess discharges to water that are discretionary activities

More information

Mid-Loddon Groundwater Management Area Local Management Rules. Annual Report

Mid-Loddon Groundwater Management Area Local Management Rules. Annual Report Mid-Loddon Groundwater Management Area Local Management Rules Annual Report June 2014 Document History and Distribution Version(s) Version Date Author(s) Notes v1 24 Jul 2014 B Knowles Document Creation

More information

WATER MANAGEMENT PLAN (WMP)

WATER MANAGEMENT PLAN (WMP) Established 1907 WATER MANAGEMENT PLAN (WMP) APPROVED BY MSC DATE: OCTOBER 2018 Version Date Section Modified 1 February 2005 All 2 December 2010 All Reason for Modification Original Management Plan 5

More information

Management Plan. Groundwater

Management Plan. Groundwater Management Plan Groundwater Risk Statement: High This document will be reviewed on a two yearly basis, unless a process change occurs earlier than this period. THIS DOCUMENT IS UNCONTROLLED WHEN PRINTED

More information

Fortescue Metals Group Ltd. Peer review and model appraisal. Hydrogeological Assessment for the. Cloudbreak Water Management Scheme

Fortescue Metals Group Ltd. Peer review and model appraisal. Hydrogeological Assessment for the. Cloudbreak Water Management Scheme Fortescue Metals Group Ltd Peer review and model appraisal Hydrogeological Assessment for the Cloudbreak Water Management Scheme 14 th October 2010 HydroConcept Pty Ltd ABN: 42 143 302 201 PO Box 4231,

More information

WATER MANAGEMENT PLAN (WMP)

WATER MANAGEMENT PLAN (WMP) Established 1907 WATER MANAGEMENT PLAN (WMP) APPROVED BY MSC DATE: MARCH 2018 Version Date Section Modified 1 February 2005 All 2 December 2010 All Reason for Modification Original Management Plan 5 Yearly

More information

Greymouth Petroleum Limited Deep Well Injection Monitoring Programme Annual Report Technical Report

Greymouth Petroleum Limited Deep Well Injection Monitoring Programme Annual Report Technical Report Greymouth Petroleum Limited Deep Well Injection Monitoring Programme Annual Report 2016-2017 Technical Report 2017-22 Taranaki Regional Council ISSN: 1178-1467 (Online) Private Bag 713 Document: 1855942

More information

6 IMPACT ASSESSMENT METHOD

6 IMPACT ASSESSMENT METHOD 6 IMPACT ASSESSMENT METHOD ENTER HERE BACK TO CONTENTS 6 Impact Assessment Method This chapter outlines the methods employed within the EIS specialist technical studies to undertake an assessment of potential

More information

FREQUENTLY ASKED QUESTIONS (FAQS)

FREQUENTLY ASKED QUESTIONS (FAQS) About the Project FREQUENTLY ASKED QUESTIONS (FAQS) Q. Why are you doing this project here? A. In 2012 CTSCo was awarded a Greenhouse Gas Storage Tenement (GHG) at EPQ7 by the Queensland Government for

More information

ASHTON LONGWALL 103 MID PANEL REPORT

ASHTON LONGWALL 103 MID PANEL REPORT Ashton Longwall 13 ASHTON LONGWALL 13 MID PANEL REPORT 1 INTRODUCTION This report has been prepared by Ashton Coal Operations Pty Ltd (ACOL) with the assistance of an independent groundwater consultant,

More information

Abbot Point Stormwater Return Dam (EPBC 2010/5561) Operation Annual Compliance Report, January 2016

Abbot Point Stormwater Return Dam (EPBC 2010/5561) Operation Annual Compliance Report, January 2016 Abbot Point Stormwater Return Dam (EPBC 2010/5561) Operation Annual Compliance Report, 2015 22 January 2016 Table of Contents 1. Introduction... 4 1.1. The purpose of this Document... 4 1.2. Project Background...

More information

ENVIRONMENTAL APPROVALS

ENVIRONMENTAL APPROVALS SOUTH AUSTRALIAN MINING ACT (1971) ENVIRONMENTAL APPROVALS Prominent Hill Copper Gold Mine, 2011 Erik Lock Principal i Mining i Assessment Officer DMITRE Outline Honeymoon Uranium Mine, 2011 Regulatory

More information

Australia Pacific LNG submission to the Senate Rural Affairs and Transport Committee: Inquiry into the management of the Murray-Darling Basin impact

Australia Pacific LNG submission to the Senate Rural Affairs and Transport Committee: Inquiry into the management of the Murray-Darling Basin impact Australia Pacific LNG submission to the Senate Rural Affairs and Transport Committee: Inquiry into the management of the Murray-Darling Basin impact on mining of coal seam gas Submitted 6 September 2011

More information

Katunga Water Supply Protection Area Management Plan (Groundwater)

Katunga Water Supply Protection Area Management Plan (Groundwater) Katunga Water Supply Protection Area Management Plan (Groundwater) ANNUAL REPORT FOR YEAR ENDING JUNE 9 GMW Docs #759 Foreword This report is submitted to the Minister for Water, the Goulburn Broken Catchment

More information

Final Terms of Reference for the Arrow Bowen Pipeline Project Environmental Impact Statement (EIS)

Final Terms of Reference for the Arrow Bowen Pipeline Project Environmental Impact Statement (EIS) Final Terms of Reference for the Arrow Bowen Pipeline Project Environmental Impact Statement (EIS) Contents Background... 4 Glossary of terms...5 1. Introduction... 5 1.1 Project proponent...5 1.2 Project

More information

Landscapes & Industries

Landscapes & Industries K N O W L E D G E Landscapes & Industries Groundwater Flow Systems Framework ESSENTIAL TOOLS FOR PLANNING SALINITY MANAGEMENT Summary Report Glen Walker, Mat Gilfedder, Ray Evans, Phil Dyson & Mirko Stauffacher

More information