Acknowledgements... ACK-1

Size: px
Start display at page:

Download "Acknowledgements... ACK-1"

Transcription

1

2 Table of Contents Acknowledgements... ACK-1 1 Executive Summary Introduction Results Conclusions and Recommendations Conclusions Program Recommendations Introduction Background Purpose General Approach SGIP System Data Avoided Cost Data Metered Performance Data Utility Tariff Data Data from Secondary Sources Other Assumptions Variation from the Standard Practice Manual Report Organization Cost and Benefit Components Equipment Purchase and Maintenance Equipment Purchase Equipment Maintenance Equipment Salvage Value Electricity Production and Savings TMY 8760-Hour Electricity Production and Savings (kwh) Electricity Retail Value Electric Utility Avoided Costs Natural Gas Consumption and Savings TMY 8760-Hour Natural Gas Consumption and Savings Natural Gas Avoided Costs Natural Gas Retail Value SGIP Administration and Incentives General Financial Assumptions Societal Test Introduction Variations from the SPM Table of Contents i

3 4.3 Societal Benefits External Environmental Benefits Summary of Societal Benefits Societal Costs External Environmental Costs Summary of Societal Costs Societal Test Results Participant Test Introduction Variations from the SPM Participant Benefits Tax Credits Depreciation Benefits Other Incentives Summary of Participant Benefits Participant Costs Summary of Participant Costs Participant Test Results Nonparticipant Test Introduction Variations from the SPM Nonparticipant Benefits Summary of Non-participant Benefits Non-participant Costs Summary of Non-participant Costs Non-participant Test Results Appendix A DG System Performance Modeling Description... A-1 A.1 Introduction...A-1 A.2 PV System Performance...A-1 A.3 Natural Gas Cogeneration System Performance...A-3 Appendix B Utility Avoided Cost Forecasts... B-1 B.1 Introduction...B-1 B.2 Electric Avoided Costs...B-1 B.3 Natural Gas Avoided Costs...B-6 Appendix C Retail Price Forecasts... C-1 C.1 Introduction... C-1 C.2 Electricity... C-1 C.3 Natural Gas... C-2 Appendix D Framework Equations... D-1 D.1 Introduction... D-1 ii Table of Contents

4 D.2 Societal Test... D-1 Summary of Societal Benefits... D-1 Summary of Societal Costs... D-3 D.3 Participant Test... D-4 Summary of Participant Benefits... D-4 Summary of Participant Costs... D-6 D.4 Nonparticipant Test... D-7 Summary of Electric Ratepayer Nonparticipant Benefits... D-7 Summary of Gas Ratepayer Nonparticipant Benefits... D-8 Summary of Electric Ratepayer Nonparticipant Costs... D-9 Summary of Gas Ratepayer Costs... D-9 Appendix E Detailed Results and Benefits and Cost Component Tables...E-1 E.1 Introduction...E-1 E.2 Societal Test Results and Components...E-1 E.3 Participant Test Results and Components...E-4 E.4 Non-Participant Test Results and Components...E-7 Appendix F Total Resource Cost Test...F-1 F.1 Introduction...F-1 F.2 TRC Benefits...F-1 Tax Credit Benefits...F-1 Summary of TRC Benefits...F-2 F.3 TRC Costs...F-2 Summary of TRC Costs...F-2 F.4 Total Resource Cost Test Results...F-3 List of Tables Table 1-1: Cost and Benefit Components for Each Test Table 1-2: Program Benefit-Cost Ratio Results Table 3-1: SGIP DG System Costs Table 3-2: New Chiller Costs Table 3-3: Variable Maintenance Costs (Cents/kWh) Table 3-4: Fixed Maintenance Costs Table 3-5: Cogeneration and Biogas System Capacity Factor Scenarios Table 3-6: Electric Tariffs Table 3-7: Cogeneration System Nonbypassable Electric Charges (Cents/kWh) Table 3-8: Incentives Paid and Reserved Table 3-9: Discount Rates Assumed in the Analysis Table 4-1: Small Gas Boiler Environmental Externalities (2004) Table 4-2: Cogeneration System Environmental Externalities (2004) Table 4-3: Societal Test Base Case Net Benefits Results Summary (Net present value, millions 2004 $) Table 4-4: Societal Test Breakdown of Base Case Benefits (Net present value, millions 2004 $) Table of Contents iii

5 Table 4-5: Societal Test Breakdown of Base Case NPV Costs (millions 2004 $) Table 4-6: Comparison of Base and Optimistic Cases Table 4-7: Societal Test - Benefits Results (Optimistic Case) Table 4-8: Societal Test Benefit-Cost Ratio Results Table 5-1: State Tax Credit Provisions PV Table 5-2: Federal Tax Credit Provisions PV Table 5-3: Federal First-Year Bonus Depreciation Provisions PV and Cogeneration Table 5-4: Federal Five-Year Depreciation Provisions Table 5-5: Participant Test Base Case Net Benefits Results (Net present value, millions 2004 $) Table 5-6: Participant Test Breakdown of Base Case Benefits (Net present value, millions 2004 $) Table 5-7: Participant Test Breakdown of Base Case Costs (Net present value, millions 2004 $) Table 5-8: Participant Test Optimistic Case Net Benefits Results Benefits (Net present value, millions 2004 $) Table 5-9: Participant Test Benefit-Cost Ratio Results Table 6-1: SGIP Cost Summary by Ratepayer Group Table 6-2: Nonparticipant Test Net Benefits All Ratepayers (Base Case) Table 6-3: Nonparticipant Test Net Benefits Electric Ratepayers (Base Case) Table 6-4: Nonparticipant Test Net Benefits Gas Ratepayers (Base Case) Table 6-5: Nonparticipant Test Net Benefits All Ratepayers (Optimistic) Table 6-6: Nonparticipant Test Net Benefits Electric Ratepayers (Optimistic Case) Table 6-7: Nonparticipant Test Net Benefits Gas Ratepayers (Optimistic Case) Table 6-8: Nonparticipant Test Breakdown of Base Case Benefits (Net present value, millions 2004 $) Table 6-9: Nonparticipant Test Breakdown of Base Case Costs (millions 2004 $) Table 6-10: Nonparticipant Test Benefit-Cost Ratio Results (Base Case) Table 6-11: Nonparticipant Test Benefit-Cost Ratio Results (Optimistic Case) Table A-1: Basis of Season Assignments...A-2 Table A-2: General Form of PV Performance Models...A-2 Table A-3: Cogeneration System Performance Scenarios...A-5 Table B-1: 2006 Annual Average Electric Avoided Cost by Utility Market and CO 2 Components (Cents/kWh, nominal)...b-1 iv Table of Contents

6 Table B-2: 2006 Annual Average Electric Avoided Cost by Utility and Climate Zone T&D Component (Cents/kWh, nominal)...b-3 Table B-3: Natural Gas Transportation Marginal Costs for B-6 Table C-1: Electrical Tariffs Assumed Rates for C-1 Table C-2: Electric Retail Rate Escalation Factors... C-2 Table E-1: Societal Test - Base Case with T&D - Summary of Benefits and Cost Components ($/kw)...e-2 Table E-2: Summary of Societal Benefits and Cost Results (Base Case)...E-3 Table E-3: Summary of Societal Benefits and Cost Results (Optimistic Case)...E-3 Table E-4: Summary of Benefit/Cost Ratios for Societal Test...E-4 Table E-5: Participant Test Base Case- Summary of Benefits and Cost Components ($/kw)...e-5 Table E-6: Summary of Participant Benefits and Cost Results (Base Case)...E-6 Table E-7: Summary of Participant Benefits and Cost Results (Optimistic Case)...E-6 Table E-8: Summary of Benefit/Cost Ratios for Participant Test...E-6 Table E-9: Non-Participant Test Base Case Summary of Benefits and Cost Components ($/kw)...e-8 Table E-10: Summary of Non-Participant Benefits and Cost Results (Base Case)...E-9 Table E-11: Summary of Non-Participant Benefits and Cost Results (Optimistic Case)...E-10 Table E-12: Summary of Benefit/Cost Ratios for Non-Participant Test...E-10 Table F-1: TRC Test Base Case Net Benefits Results Summary (Net present value, millions 2004 $)...F-3 Table F-2: TRC Test Breakdown of Base Case Benefits (Net present value, millions 2004 $)...F-4 Table F-3: TRC Test Breakdown of Base Case NPV Costs (millions 2004 $)...F-4 Table F-4: Comparison of Base and Optimistic Cases...F-5 Table F-5: TRC Test Benefits Results (Optimistic Case)...F-5 Table F-6: TRC Test Benefit-Cost Ratio Results...F-6 List of Figures Figure 1-1: Societal and Participant Test Benefit-Cost Ratios Sensitivity Analysis Figure 3-1: Summary of Electric Retail Rate Projections Figure 3-2: Summary of Electric Energy Avoided Cost Projections Figure 3-3: Annual Average Natural Gas Avoided Cost from Society s Perspective by Year Figure 4-1: Relationship Between Costs and Benefits in Societal Test Table of Contents v

7 Figure 4-2: Summary of Energy Services and Avoided External Environmental Costs - Conventional Energy Services Delivery Model Figure 4-3: Summary of Energy Services and External Environmental Costs - DG Energy Services Delivery Model Figure 5-1: Relationship Between Participant Test Benefits and Costs Figure 6-1: Relationship Between Benefits and Costs in Non- Participant Test Figure A-1: Level 3/3-N/3-R On-Line MW and Average Capacity Factor (2004)...A-3 Figure A-2: Natural Gas Cogeneration System Base Case Capacity Factors...A-4 Figure B-1: Climate Zones Map...B-2 Figure B-2: 2006 Annual Average Electric Avoided Cost by Season and Hour of Day Market Component (Cents/kWh)...B-3 Figure B-3: 2006 Annual Average Electric Avoided Cost by Season and Hour of Day CO 2 Component (Cents/kWh)...B-4 Figure B-4: 2006 Annual Average Electric Avoided Cost by Season and Hour of Day T&D Component (Cents/kWh)...B-5 Figure B-5: Annual Average Electric Avoided Cost by Year (Cents/kWh)...B-5 Figure B-6: Natural Gas Avoided Cost Commodity + Transportation - Month-to-Month Variability for B-7 vi Table of Contents

8 ACKNOWLEDGEMENTS Itron would like to acknowledge the following individuals and organizations for their help and cooperation in the development of this report: Lisa Paulo and Valerie Beck of the California Public Utilities Commission, who provided valuable insight and direction on a number of fronts, SDREO, SCE, PG&E and SoCalGas Program Administrators for consistently providing the required project application information and for coordinating the transfer of available electric net generator output data that supported this analysis, Host customers and Third-Party applicants that agreed to provide SGIP project operations and energy output data that supported this analysis, Brown Vence & Associates (BVA) and Environmental Systems, Inc. (ESI), who were instrumental in developing and installing thermal energy and net generator output monitoring systems providing data that supported this analysis, Energy and Environmental Economics, Inc. (E 3 ), whose avoided cost projections are a seminal foundation for the cost effectiveness evaluation, Fred Sebold, who created the framework making the report possible, Kurt Scheuermann, the primary author of this report, whose devotion and dedication formed the basis of this report, Questions and comments on the report should be directed to George Simons at Itron (george.simons@itron.com) Acknowledgement ACK-1

9 1 Executive Summary 1.1 Introduction This report summarizes the findings of the first cost-effectiveness evaluation of the California Self-Generation Incentive Program (SGIP). The SGIP is a statewide 1 program developed by the California Public Utilities Commission (CPUC) to provide incentives for the installation of certain renewable and clean distributed generation (DG) technologies serving all or a portion of a facility s electric needs. DG technologies involved in the SGIP include photovoltaic (PV) systems, reciprocating internal combustion (IC) engines, microturbines (MT), fuel cells, and wind turbines. The purpose of this study is to assess the cost-effectiveness of the program at the 2004 program year stage of implementation. It should be recognized that the cost-effectiveness results in this study are based on SGIP-specific projects and incentive structures. As such, the results may not be reflective of the current performance or costs of DG technologies or those employed in other settings. Similarly, care should be taken in trying to gauge the performance or cost-effectiveness of DG technologies in general from these results. Cost-effectiveness is assessed based on a recently developed cost-effectiveness analysis framework report 2 using metered project performance information from the Program Year 2004 Impacts Report. In accordance with that framework, cost-effectiveness is evaluated from three perspectives: Participants (project owners within the SGIP), Nonparticipants (ratepayers), and Society as a whole. The Participant Test evaluates the benefits and costs of the SGIP from the perspective of participants. From this perspective, the participant s costs of owning and operating the SGIP 1 Available in the service territories of Pacific Gas & Electric, Southern California Edison, Southern California Gas Company, and San Diego Gas & Electric. 2 Itron, Inc., Self-Generation Incentive Program: Framework for Assessing the Cost-Effectiveness of the Self- Generation Incentive Program, prepared for the California Public Utilities Commission, March Executive Summary 1-1

10 system are compared against the retail energy costs that would have been incurred by the participant had they continued to obtain all of their electricity from a utility company. The Nonparticipant Test evaluates the costs and benefits of the SGIP from the perspective of utility customers that did not participate in the SGIP. This test is sometimes called the Ratepayer Impact Measure (RIM) Test because its principal objective is to measure what happens to customer bills or rates due to changes in utility revenues and operating costs caused by the program. The Societal Test evaluates the costs and benefits of the SGIP from the perspective of all members of society. This test is a variant of the total resource cost (TRC) Test typically used by the CPUC in evaluating demand-side management programs. The TRC Test assesses program cost-effectiveness from the combined perspective of all utility customers (participants and nonparticipants). 3 Typically, only a TRC test or a Societal test is conducted to examine this type of cost-effectiveness perspective. However, a TRC test is included as Appendix F to the report to provide additional information to the societal perspective. It is important to note that results of any cost-effectiveness evaluation are directly related to the underlying analysis framework. In this case, the SGIP-specific framework was meant to be implemented in the near term to conduct an initial assessment of the program s costeffectiveness. A number of issues, including classification and valuation of benefits and costs within the different tests, have surrounded discussion of the framework. However, the framework development and implementation schedule did not permit the opportunity to reach consensus and closure on some of these issues. Consequently, findings and conclusions made in this report could change significantly with modifications in the framework and should be viewed in that context. A number of benefit and cost components are used in conducting cost-effectiveness tests. Section 3 describes how the components used in the evaluation are calculated. Sections 4 through 6 provide more detailed discussion of what components are used in each of the tests. The Commission issued interim ruling R adopting general policies and principles for cost-benefit methods for evaluating DG facilities. 4 Among the adopted policies and principles were the following: 3 The Societal Test differs from the TRC in that the Societal Test ignores tax credits, considers externalities that impact society as a whole, and makes use of a societal discount rate that is usually lower than the private discount rate employed in the TRC test. 4 California Public Utilities Commission, Interim Opinion Adopting Cost-Benefit methodology for Distributed Generation, R , September 6, Executive Summary

11 DG projects should be analyzed using a societal test, a non-participant test and a participant test, The avoided costs presented by E 3 and adopted in D for energy efficiency projects should be applied to DG projects, with some modifications, until the Commission has adopted avoided costs for DG facilities in that proceeding, The impacts of DG projects on market prices should be included as a benefit in the societal model, All relevant environmental benefits should be included in the cost-benefit models, whether or not their impacts result from regulation or compliance with state or federal laws, Tax incentives, standby charge exemptions, and Self-Generation Incentive Program (SGIP) incentives should be considered benefits to DG projects in the participant tests and costs in non-participant tests, and The value of DG projects in terms of market transformation should be considered in R The framework and treatment of benefits and costs in this evaluation are consistent with the interim ruling with the following exceptions: Environmental benefits included in the evaluation were limited to CO 2 and NOx (e.g., excluded environmental benefits that could be accrued from reduced waste disposal), and Did not include market transformation impacts. Table 1-1 on the following page shows how the various benefit and cost components are allocated in the three tests of this cost-effectiveness evaluation. Executive Summary 1-3

12 Table 1-1: Cost and Benefit Components for Each Test Test Costs Benefits Societal External environmental costs from operating SGIP facilities Avoided grid generation costs (avoided electricity costs) System installed costs (Includes: emission controls, interconnection, and emission offsets) Avoided T&D capital deferral costs System O&M costs SGIP administration costs DG fuel costs Reliability net benefits Reduced line losses External environmental benefits CO2 (only for grid generated electricity) Participant System removal less salvage value System installed costs (Includes: emission controls, interconnection, and emission offsets) System O&M costs DG fuel costs Nonbypassable Charges NOx and CO2 for avoided natural gas (from host site boilers) Market Price (elasticity) Impacts Avoided host site natural gas fuel costs (from waste heat recovery) Reduced electricity bills (deferred retail rate electricity) Host site natural gas fuel costs (from waste heat recovery) Incentives from SGIP & other programs Tax credits Depreciation benefits 1-4 Executive Summary

13 Table 1-1: Cost and Benefit Components for Each Test (continued) Test Costs Benefits Nonparticipant Electricity ratepayer costs SGIP costs Decreased sale of electricity to participants Reduced electric T&D revenue Electricity ratepayer benefits Avoided grid generation costs Avoided T&D capital deferral costs, and reduced line losses Reliability net benefits Gas ratepayer costs SGIP costs Decreased revenues from transportation of fuel for boilers Increased utility cost of transportation of fuel for natural gas-fired SGIP systems Price (elasticity) benefits Gas ratepayer benefits Increased revenues from transportation of fuel for natural gas-fired SGIP systems Decreased cost of transportation of fuel for host-site boilers Due to the nature and scope of a statewide cost-effectiveness assessment, certain items have not been considered. Among the items not covered by this cost-effectiveness evaluation are market transformation impacts, energy security benefits, effects of increased power quality, and site-by-site assessments of costs attributable to the program. Including these items in future analyses could significantly alter the results. 1.2 Results Results of the preliminary SGIP cost-effectiveness evaluation are summarized in Table 1-2. These results indicate that the SGIP, as a portfolio of projects, is cost-effective from the participant perspective, but cost-effectiveness declines significantly when viewed from the nonparticipant, TRC, or societal perspectives. Within technology classes, cogeneration systems maintain a higher benefit-to-cost ratio than do PV systems in the Nonparticipant, TRC, and Societal tests. This gap is narrowed in the Participant test. Moreover, IC cogeneration systems maintain a relatively high benefit-to-cost ratio across all perspectives. The highest benefit-to-cost ratio (1.58) estimate is calculated for biogas systems viewed from the participant perspective. These results are not unexpected in light of the emerging status of most of the SGIP technologies, with their associated high capital costs. As technologies mature, installed capital costs are likely to decrease and therefore drive up benefit-to-cost ratios. For example, Executive Summary 1-5

14 system average costs for PV systems installed in the SGIP for the 2004 reporting year are significantly higher than current PV system costs in other settings. Similarly, viewed from a portfolio perspective, growth of SGIP-incentivized distributed generation systems may continue to add benefits to the electricity system overall, including greater potential for deferred T&D and increased ability to meet localized and system peak demand. Consequently, it may be useful to view these early cost-effectiveness results of the SGIP as a starting point from which parties can begin to shape the future direction of the program. Table 1-2: Program Benefit-Cost Ratio Results 5 Perspective/Test (Base Case) Technology Society TRC Nonparticipants Participants PV Biogas Cogeneration (all) IC Engine Microturbine Total (Wtd.Avg.) Results in Table 1-2 can be viewed as comprising a base case. In particular, the results exclude possible net benefits related to electric system transmission and distribution (T&D) cost savings. The rationale for this exclusion in the base case is discussed in the SGIP Cost- Effectiveness Framework Report. 6 In addition, the results reflect maintenance costs and performance factors that are based on available metered operating performance during their early years and therefore these parameters may be considered conservative. For this reason an Optimistic case was developed for each technology that includes the T&D benefits, as well as other more favorable assumptions about system performance and maintenance costs. The base case (lower bound) and optimistic case (upper bound) benefit-cost ratios for the societal and participant perspectives are illustrated in box plot format in Figure 1-1. Several important observations can be made in reviewing the bracketed results. First, the benefit-cost ratio for the portfolio of SGIP projects increases by over 33 percent under the Optimistic case, suggesting that performance and cost factors considered under the Optimistic case may provide benefits across the range of SGIP technologies. Second, biogas 5 The framework considers only three tests: societal, non-participant and participant. A TRC test is included here only to provide additional information and perspective. 6 It should be noted that contradictory provisions in part exclude T&D benefits from accruing to SGIP DG projects. In D , one of the conditions DG systems must meet to provide T&D benefits is the requirement that the DG system be accompanied by contractual physical assurances. However, in D , DG projects that have contracts to provide distribution support are ineligible to receive SGIP incentives. 1-6 Executive Summary

15 systems have the most significant changes in value from Base to Optimistic cases and are the only technology for which Optimistic case benefit-cost ratio estimates exceed one from the societal perspective. These high and wide benefit-cost ratio ranges for biogas systems may be due to relatively high capacity factors, captive renewable fuel supplies (which eliminates their need to purchase fuel, and, more importantly, avoids volatility in fuel prices experienced with natural gas), and a relatively modest increase in installed system costs over natural gas-fueled systems. Lastly, natural gas microturbines are the only technology for which the switch from Base to Optimistic assumptions results in participant test results moving from less than one to greater than one. This increase in benefit-cost ratio for microturbines is largely due to assumptions in the Optimistic case that decreased maintenance costs will occur with maturing of the technology, as identified in Appendix A. Figure 1-1: Societal and Participant Test Benefit-Cost Ratios Sensitivity Analysis Benefit-Cost Ratio Biogas Nat. Gas Systems IC Engine Total Nat. Gas Microturbine PV Biogas Systems Nat. Gas IC Engine Nat. Gas Microturbine Total PV Societal Test Participant Test The principal question motivating this evaluation can be simply stated as: Is the SGIP costeffective? The simplest answer to that question is: For this present group of operational projects, not during the 2004 timeframe because the benefit-cost ratios from the societal and nonparticipant perspectives for the group as a whole are substantially less than one. However, lifecycle economic analyses particularly from the societal perspective are not Executive Summary 1-7

16 simple. Important elements of complexity that must inform interpretation of these results include: Certain societal benefits were not included because they were too difficult to quantify. These benefits include demonstration and market inducement effects, energy security benefits, and, for PV systems, power quality benefits (e.g., the ability of PV inverter systems to reduce disturbances in voltage and frequency). For certain participants, cogeneration provides increased electrical power reliability, which can be an important electric customer benefit for some industries that was not included in the analysis. Several key factors limit the accuracy of quantitative results, as well as qualitative conclusions that can be drawn at this time. These limiting factors include: For cogeneration systems, availability of metered overall system performance data particularly useful recovered heat data is limited to a relatively small sample of operational systems. SGIP systems typically have a 20-year facility economic life, however; necessarily in all cases less than two years operating experience was available upon which to base estimates of life-cycle economic performance. There appears to be a trend toward incorporating heat recovery chillers into cogeneration systems, which may lead to increased average heat recovery rates and improved system economics. The natural gas prices faced by cogeneration system owners during periods of the analysis period were quite high and variable, causing an unusual spread between electricity rates and gas prices. This is especially important in that volatility in natural gas prices is not necessarily reflected in electricity prices (i.e., most cogeneration facilities purchasing natural gas have market-based contracts that require them to pay (e.g., see ) higher natural gas prices which are not being reflected in electricity retail rates). SGIP systems that do not purchase or displace natural gas (e.g., PV, biogas, and wind systems), but receive value based on avoided electricity generation costs are affected to a similar, but lesser degree by this spread. There is a high degree of uncertainty regarding future retail electricity and natural gas prices. The electricity price projection used in this analysis is much lower than the historic trend for the past 20 years. Moreover, it is important to recognize that the current results represent only a snapshot in time. Given the substantive changes likely to occur with future SGIP systems (e.g., increased efficiency of microturbines, better air pollution control for IC engines, and lower costs of PV system components), the level of program cost-effectiveness may change significantly. 1-8 Executive Summary

17 1.3 Conclusions and Recommendations Conclusions Notwithstanding the limitations of this analysis noted above, several conclusions about the program s cost-effectiveness can be drawn based on this initial assessment: 1. The SGIP appears to be cost-effective with respect to participants, but there is a noticeable drop in cost-effectiveness for the nonparticipants or society as a whole. 2. Biogas systems have among the highest benefit-to-cost ratios in the Participant, TRC, and Societal tests. 3. Cogeneration and biogas systems generally have higher benefit-to-cost ratios than PV systems from a societal perspective. 4. Within cogeneration systems, IC engine-based systems are more cost-effective than microturbine systems. 5. If electric system T&D benefits are included, and several other favorable scenario assumptions are made, the cost-effectiveness of the SGIP is markedly improved. However, the cost-effectiveness of the program is still doubtful from the nonparticipant and societal test standpoint when viewed at the 2004 year stage in the program s development. 6. Major uncertainties with regard to future energy prices and long-term system performance make an absolute definitive cost-effectiveness determination impossible at this time. Program Recommendations In light of the cost-effectiveness results to date, the CPUC s Energy Division and other program stakeholders should consider the potential costs and benefits that could result from the following targeted analyses: Investigate the relationship between climate zone and cost-effectiveness of the program and the various SGIP technologies. In particular, determine whether the SGIP is more cost-effective in hot inland areas, where there may be increased distribution system daily peak load and annual demand growth. Similarly, determine and identify what differences exist between the cost-effectiveness of SGIP technologies in these areas, and how significant increases in different technologies (e.g., PV or other renewable-fueled systems) may impact the Program s cost-effectiveness. Examine the relationship between those geographical areas where local electricity transfer congestion poses a problem and assess the cost effectiveness of using various SGIP technologies in those areas of T&D congestion. Sensitivity analyses Executive Summary 1-9

18 could indicate future impacts of deploying additional SGIP within these congested areas and assess the cost-effectiveness under the different framework tests. Conduct sensitivity analyses to assess the impacts of improved performance or reduced capital and/or operating costs on the cost-effectiveness of the SGIP and its eligible technologies. Among the components that could be considered are improved heat recovery rates for chillers on cogeneration technologies; PV battery backup and DC output circuits that allow continued operation of such items as lighting or computers in commercial businesses; variations in natural gas prices, adoption of new air pollution control equipment on IC cogeneration projects; and the incorporation of selected new technologies to the program. Discrepancies between natural gas prices and realized electricity prices mask a precise assessment of the cost-effectiveness of the SGIP and program-deployed generation technologies. Future cost-effectiveness evaluations should employ electricity price projections (or sensitivity analyses) that allow for a more marketdynamic response. The Energy Division should investigate the discrepancies between the reduction in PV component costs that have been occurring over the past twenty years, the lack of PV system price reductions through the first four years of the SGIP, and explore available pathways to address these apparent discrepancies Executive Summary

19 2 Introduction The California Self-Generation Incentive Program (SGIP) is a statewide 1 program developed by the California Public Utilities Commission (CPUC) to provide incentives for the installation of certain renewable and clean distributed generation technologies serving all or a portion of a facility s electric needs. This preliminary SGIP cost-effectiveness evaluation is the latest report in the ongoing assessment of the SGIP. Prior program evaluation activities addressed system performance characteristics (i.e., impact evaluation), and effectiveness of program implementation processes (i.e., process evaluation). The first step of the preliminary cost-effectiveness evaluation was to develop a SGIP-specific analysis framework. 2 The framework outlines how the most important cost and benefit elements of the analysis will be treated. The framework proposes to assess program costeffectiveness from the perspectives of three key stakeholders: Society; SGIP Participants, and Nonparticipants (or Ratepayers). This report utilizes this analytic methodology to assess SGIP cost-effectiveness. 2.1 Background Assembly Bill 970 (Ducheny, 2000), signed into law on September 6, 2000, required the CPUC to initiate certain load control and distributed generation program activities. The SGIP was adopted by the CPUC on March 21, 2001 under Decision D Since July 2001, the SGIP has been available to provide financial incentives for installation of new qualifying electric generation equipment that can meet all or a portion of the electric needs of an eligible customer s facility. The SGIP is available to electric and/or gas customers of Southern California Edison, Pacific Gas and Electric, Southern California Gas Company, and 1 Available in the service territories of Pacific Gas & Electric, Southern California Edison, Southern California Gas Company, and San Diego Gas & Electric. 2 Itron, Inc., Self-Generation Incentive Program: Framework for Assessing the Cost-Effectiveness of the Self- Generation Incentive Program, prepared for the California Public Utilities Commission, March Introduction 2-1

20 San Diego Gas and Electric. The SGIP was authorized an annual statewide allocation of $125 million for program years 2001 through Assembly Bill 1685, signed into effect on October 12, 2003, extended the SGIP through December 31, The SGIP was designed utilizing information available in 2001 regarding likely distributed generation (DG) costs and expected benefits. Since then, cost and operational data collected from SGIP projects in real-time provide an opportunity to assess actual program costs and benefits, and to recommend refinements to program design and evaluation techniques. The cost-effectiveness framework developed by Itron is the result of a number of CPUC decisions, rulings, and hearings. In Decision , the CPUC directed the Energy Division to retain a consultant to study and develop recommendations concerning costeffectiveness assumptions used to evaluate energy efficiency, demand response, or distributed generation projects and programs. A subsequent decision, D , refined the scope of work to update the avoided costs and externality adders presently used to evaluate energy efficiency programs. These avoided costs and externality adders constitute some, but not all, of the required inputs to the Standard Practice Manual 3 (SPM) costeffectiveness tests. Energy and Environmental Economics, Inc. (E 3 ) prepared and submitted a report to the CPUC in January 2004 addressing avoided costs and externality adders. The E 3 report was finalized on October 25, In R , the CPUC expressed its intention to develop an overall DG cost-benefit methodology. The CPUC directed that such an approach would, to the extent possible, consider other cost-effectiveness tests, such as those described in the E 3 report, the SPM, and input assumptions from the E 3 report. In addition, the August 6, 2004 Assigned Commissioner's Scoping Memo directed parties to propose cost-benefit methodologies in testimony due in October The SGIP-specific cost-effectiveness framework developed by Itron is based largely on the SPM, the E 3 report approach, E 3 findings relative to avoided costs and externalities, and testimony provided by parties relative to distributed generation cost-effectiveness evaluation. Itron made this framework publicly available in March The framework was distributed to the interested parties for comment. 4 3 California Standard Practice Manual: Economic Analysis of Demand-Side Programs and Projects, Governor s Office of Planning and Research, July On September 6, 2005, the CPUC issued interim ruling R Both the framework and the treatment of costs and benefits within this evaluation are consistent with the adopted policies and principles with few exceptions. 2-2 Introduction

21 2.2 Purpose This report provides the first cost-effectiveness assessment of the SGIP. The findings in this report are intended to: Establish an updated cost-effectiveness reference point based on information that was not available at the time the SGIP was originally conceived and designed (e.g., updated forecasts of avoided costs and retail electricity rates, actual selfgeneration system installed and operating costs), Assess the influence of certain parameters (e.g., self-generation system capacity factor) on the estimate of program cost-effectiveness; and Illuminate the economic market drivers of DG from the perspective of SGIP participants. 2.3 General Approach The March 2005 framework report served as the overall guide for this Preliminary Cost- Effectiveness Evaluation analysis. Due to the preliminary nature of this analysis, its scope is largely focused on assessment of solar photovoltaic (PV) systems and cogeneration systems fueled by natural gas. These technologies account for 95% of the operational SGIP system capacity as of the end of 2004, and 98% of the incentives (distributed or reserved) corresponding to these projects. Information for biogas-fueled systems has been included, but is limited to a relatively small number of systems. The principal data elements identified in the framework are summarized briefly below. Detailed discussion of these data elements and their use in the preliminary cost-effectiveness analysis is included in subsequent sections of this report. SGIP System Data Data obtained through program applications and site inspections include system type, system size, technology type, fuel type, eligible system installed cost, SGIP incentive magnitude, and startup date. Avoided Cost Data When program participants generate their own power, their utility companies avoid costs that would otherwise have been incurred to procure and deliver that electric power using conventional means. The avoided electric cost values for each electric utility vary from hour to hour during the year and are a function of many factors. Substitution of self-generation in place of conventional central station generation technologies also results in changes in air pollutant emission rates, which may have economic consequences. Avoided electric and Introduction 2-3

22 environmental cost forecasts and associated models developed by E 3 5 and approved by the CPUC in D are used to calculate avoided electricity generation benefits and avoided external environmental benefits in this assessment for the Nonparticipant and Societal tests. Metered Performance Data The principal source of information on the performance of the DG systems subsidized by the SGIP is the data archive compiled by Itron in conjunction with its on-going SGIP monitoring program and data collection for the recently filed Fourth-Year Program Impact Report. Metered data for a sample of operational projects were available. The metered data include electric net generator output, fuel consumption, and useful recovered thermal energy (heat). In some instances (e.g., electricity and heat), data are provided on an hourly basis throughout the year. Fuel data are more typically collected on a monthly basis. Utility Tariff Data Forecasts of retail prices for both gas and electricity rely on current tariffs as a starting point. Retail electric prices were escalated based on revenue requirement forecasts developed by the utilities. Retail gas rates were used to value both purchased generator input fuel and avoided purchases of natural gas resulting from recovered waste heat. Data from Secondary Sources While key DG system-eligible initial costs and first-year performance information is available at the site-specific level, the life-cycle basis of this analysis requires incorporation of additional cost and performance data from secondary sources. For example, cogeneration system prime movers require a major overhaul periodically, and some PV power inverters may require replacement while PV module power output is expected to degrade slowly. Values assumed for these types of data elements are based on secondary sources. Other Assumptions Influential assumptions are embedded in many of the data elements identified above. Other assumptions having a direct bearing on the cost-effectiveness evaluation results include those related to such factors as inflation rates, debt service (loan) interest rates, private and social discount rates, and treatment of tax rates, credits, and depreciation. 5 Energy and Environmental Economics, Inc., Methodology and Forecast of Long Term Avoided Costs for the Evaluation of California Energy Efficiency Programs, prepared for the California Public Utilities Commission, October 25, Available at Introduction

23 2.4 Variation from the Standard Practice Manual The Standard Practice Manual was originally developed in February of 1983 to provide official guidelines for evaluating the cost-effectiveness of conservation and load management programs from a variety of perspectives. Perspectives in the 1983 SPM included participants, nonparticipants, all ratepayers, society, and the utility. The SPM was revised in Primary changes between the 1983 and 1987 SPM included: renaming of the Nonparticipant Test to the Ratepayer Impact Test (RIM), renaming of the All Ratepayer Test to the Total Resource Cost (TRC) Test, and treatment of the Societal Test as a variant of the TRC. The SPM was again revised in 2001 to reflect cumulative changes in the natural gas and electric industries. Among the changes made in the 2001 SPM include renaming of the Utility Test to the Program Administrator Test, definition of self-generation as a type of demand-side management, and expanded description of externalities in the Societal Test. In developing an SGIP-specific framework, Itron started with the concepts in the 2001 SPM and tailored them to the specific needs and aspects of self-generation technologies and systems. In general, this involved identifying the specific benefits and costs to be incorporated into each of the tests in order to apply them to selfgeneration. Itron considered a broad range of sources in developing the SGIP-specific framework including: Economic studies of distributed energy resources, with specific emphasis on the assessment of distributed generation options, the SPM, and cost-benefit analysis Public comments to the CPUC and the California Energy Commission on the assessment of DG technologies and market development programs The E 3 avoided cost study As a result of this approach, the SGIP-specific framework differs from the SPM in containing more detail than the tests in the SPM and in being tailored to the needs of evaluating distributed generation programs. An overview of each test, a description of the cost and benefit components used in the test, and how it differs from the SPM is contained in each of the following sections. Appendix D provides a listing of framework equations used for each test. Appendix E provides a listing of the cost and benefit components used by Itron for each SGIP technology under each of the test perspectives. Introduction 2-5

24 2.5 Report Organization An Executive Summary, which provides a high-level overview of the key objectives and findings of this preliminary cost-effectiveness evaluation, is presented in Section 1 of this report. The remainder of the report has been organized as described below: Section 3 describes the data and assumptions used to estimate the effects of the SGIP on the component variables used in the three test perspectives. Section 4 presents the cost-effectiveness results with respect to the Societal Test. Section 5 presents the cost-effectiveness results with respect to the Participant Test. Section 6 presents the cost-effectiveness results with respect to the Nonparticipant Test. Appendix A contains additional detail regarding the modeling of PV, biogas, and cogeneration system performance for the typical meteorological year. Appendix B contains details of the utility avoided cost forecasts. Appendix C contains detailed retail energy price forecasts. Appendix D contains details of the framework methodology. Appendix E contains detailed results for individual benefit and cost elements. Appendix F presents the cost-effectiveness results with respect to the Total Resource Cost Test. 2-6 Introduction

25 3 Cost and Benefit Components This section describes how the components used to evaluate SGIP cost-effectiveness are calculated. Program cost-effectiveness is evaluated from three perspectives. Many components of the economic cost and benefit analyses are common to more than one perspective. Thus, to avoid repetition, the component cost-benefit data, methods, and assumptions are described in this section. The applicability of these cost-benefit components is explained in Sections 4 to 6, in which the costs and benefits are summarized for each of the three primary perspectives (society, SGIP participants and nonparticipants). Appendix F contains an explanation of a fourth test; the Total Resource Cost (TRC) Test. 1. The discussion of the cost-benefit components is organized as follows: Equipment Purchase and Maintenance Electricity Production and Savings Natural Gas Consumption and Savings SGIP Administration and Incentives General Financial Assumptions 3.1 Equipment Purchase and Maintenance Equipment Purchase SGIP project costs are provided by program applicants through the program application process. This project cost information is available in aggregate in Itron s 2004 Program Impact Report. 2 These costs include the cost of generation equipment and pollution control equipment (where applicable). Reported SGIP DG system costs are summarized by technology type in Table 3-1. These totals include the costs for design, installation, and manufacturers warranty in addition to hardware costs. Note that capital costs for SGIP systems may reflect the effect of incentive levels. 1 The TRC Test looks at the combined participants plus nonparticipants perspective. 2 Itron, Inc., CPUC Self-Generation Incentive Program Fourth-Year Impact Report, prepared for Southern California Edison and the Self Generation Incentive Program Working Group, April 15, 2005 Cost and Benefit Components 3-1

26 Table 3-1: SGIP DG System Costs SGIP DG System Cost Technology Total (MW) Avg. ($/W) Total ($ MM) PV 31.0 $8.30 $257.2 Biogas 3.2 $2.81 $9.1 Cogeneration 68.8 $2.07 $142.7 Microturbine 6.4 $2.69 $17.1 Engine 62.5 $2.01 $125.6 Total $3.97 $409.0 The equipment purchase price data summarized in Table 3-1 are based on equipment and systems eligible for SGIP incentives. In developing the SGIP-specific framework, Itron used a net-to-gross ratio for allocating costs and benefits attributable to the program. The net-togross ration represents the percentage of distributed generation technology that would not have been installed in the absence of the program. Itron assumed that for PV and cogeneration systems, 100% of the benefits can be attributed to the program. In some instances, distributed generation technology components were purchased and installed by project applicants even though the components were not eligible for SGIP incentives. Examples include new waste heat recovery absorption/adsorption chillers; battery backup with DC connection for some PV systems; and improved reactors for biogas systems. There are a significantly large number of new waste heat recovery chiller systems being installed, and relatively few installations of PV systems with battery backup and biogas systems with improved biogas reactors within the program. As a result, Itron made a simplifying assumption to consider only the additional costs and benefits associated with waste heat recovery chillers in the evaluation of SGIP cost-effectiveness. The net impact of this assumption was an improvement in cost-effectiveness of those cogeneration systems employing new waste heat recovery chillers. The benefits of the newly installed heat recovery chillers were estimated based on the assumption that they were installed in lieu of new standard-efficiency electric chillers. Substitution of heat recovery chiller capacity for electric chiller capacity yields electricity savings that are discussed in a later section of this chapter. These electricity savings correspond to a cost adder for the heat recovery chiller. Chiller purchase price estimates obtained from independent sources are summarized in Table 3-2. The additional cost adder of new heat recovery chillers installed in lieu of new electric chillers is estimated equal to $350 per Ton of chilling ton of chilling is equivalent to 12,000 Btu per hour of cooling 3-2 Cost and Benefit Components

27 Table 3-2: New Chiller Costs Technology Assumed Cost ($/Ton) Electric chiller $350 Heat recovery chiller $700 Equipment Maintenance DG systems must be maintained if they are to continue operating reliably and efficiently throughout their life. Maintenance activities generally are of either the variable or the fixed variety. Examples of variable maintenance include engine tune-up and PV module washing. Fixed maintenance items, such as PV system inverter replacement and microturbine prime mover replacement, occur much less frequently but may involve considerable expense. Estimates of variable maintenance costs used in the preliminary cost-effectiveness evaluation analysis are summarized in Table 3-3. The Base Case variable maintenance costs were developed from interviews with SGIP participants. Some owners of PV systems did not wash their PV modules, some utilized their own staff to wash PV modules periodically, and some hired outside firms to periodically wash the PV modules. The value indicated for PV module washing costs represents a weighted average based on the interviews. In the case of engines and microturbines the interview respondents reported the expectation that maintenance costs would be lower in the future. To help gauge the influence of uncertainty on estimates of SGIP cost-effectiveness, information from secondary sources was used to estimate Optimistic Case variable maintenance costs for microturbines and engines. 4 In the case of engines, scheduled overhauls are included in the variable maintenance cost. Table 3-3: Variable Maintenance Costs (Cents/kWh) Technology Base Case Optimistic Case PV Microturbine Engine Assumed fixed maintenance events and estimated costs are presented in Table 3-4. All of the SGIP systems are assumed to have economic lives of 20 years. In the case of PV, inverters are assumed to require replacement half way through their economic life. The equipment life 4 Gas-Fired Distributed Energy Resource Technology Characterizations, joint project of the Gas Research Institute (GRI) and the National Renewable Energy Laboratory (NREL), October Cost and Benefit Components 3-3

28 assumed for microturbines is 10 years, which explains the replacement event occurring half way through the cogeneration system economic life. Table 3-4: Fixed Maintenance Costs Cost (% of Initial DG System Cost) Technology Maintenance Event Frequency Base Optimistic PV Inverter replacement 10 years 20% 10% Microturbine Microturbine replacement 10 years 60% 30% Equipment Salvage Value While the economic life of SGIP PV systems is assumed to be 20 years, the PV modules are assumed to retain some economic value at the end of the system economic life. In the preliminary cost-effectiveness evaluation the salvage value of PV modules is assumed equal to 10% (in real terms) of the initial PV system cost. 3.2 Electricity Production and Savings All SGIP DG systems produce electricity for use by the host facility. In some cases the waste heat from cogeneration systems is used to substitute for site energy needs that would otherwise be met using electricity. Electrical usage displaced in this manner is valued at the retail price or the avoided cost of electricity, depending on the test perspective. Valuation of electricity production and savings (i.e., displacement) entails two steps. First, available metered data are used to estimate electricity production and savings (kwh) for each hour of a typical meteorological year (TMY). Next, information about retail prices and utility avoided costs is used to calculate estimates of the economic value corresponding to the hourly kwh values. TMY 8760-Hour Electricity Production and Savings (kwh) Available metered data are used to estimate electricity production and savings (kwh) for each hour of a typical meteorological year (TMY). These TMY data sets were produced for each year of each SGIP system s economic life. Use of metered data to develop TMY data sets for PV systems and cogeneration systems is summarized below. PV Systems The power output of PV systems depends on the weather. Weather occurring during any particular period of time may deviate from the long-run average (i.e., climate). To ensure that PV system performance information included in the lifecycle cost-effectiveness analysis 3-4 Cost and Benefit Components

29 is representative of climate the available metered power output data collected from SGIP PV systems were adjusted using TMY data. This weather normalization adjustment process also yielded PV system performance information that was used to estimate power output of SGIP PV systems for which no metered power output data were available. The analysis accounted for effects of PV system orientation, location, and size. Details of the PV system power output analytic methodology are contained in Appendix A. Cogeneration and Biogas Systems The power output of cogeneration and biogas systems depends on many factors. To ensure that power output performance information included in the lifecycle cost-effectiveness analysis is representative of long-run average performance expectations it was necessary to adjust the available metered data collected from SGIP systems. The adjustments accounted for two factors. The first factor adjusts capacity factor due to the uncommonly high natural gas prices occurring during the fourth quarter of This capacity factor adjustment was applied only to natural gas cogeneration systems, and is described in Appendix A (see page A-3). The second factor adjusts for the likelihood that system performance will improve as owners and vendors gain operating experience. This adjustment applies both to natural gas cogeneration systems and biogas systems. 6 The net impact of these adjustments was an improvement in cogeneration and biogas system cost-effectiveness. The fairly short observation period provides a less than ideal basis for projecting power output performance of monitored systems 20 years into the future. Projected performance of the unmonitored systems is subject to even greater uncertainty. Simply projecting the first year capacity factors into the future may underestimate lifecycle averages because system commissioning and optimization may take a year or longer. To help gauge the influence of uncertainty on estimates of SGIP cost-effectiveness an alternative set of cogeneration system performance data was developed from the available metered data. For each system the three months exhibiting the best performance were identified and used to calculate average capacity factors and heat recovery rates that were subsequently assumed for all other months. Weighted average results are summarized in Table Due to high natural gas prices, a number of SGIP cogeneration facilities would not operate their systems during non-peak conditions or when they could not use the electricity on-site. As such, this reduced the capacity factor below the technical rating. 6 Capacity factors for natural gas cogeneration and biogas systems employed in the SGIP are significantly below the 70% plus capacity factors typically observed for these technologies. Interviews with SGIP applicants indicated that lack of experience with microturbine and biogas engine technologies resulted to some degree of reduced capacity factor. As a result, a capacity factor adjustment took this learning curve into account. This adjustment was not made to PV or wind systems as the intermittent nature of the resource was believed to have a substantially greater impact on capacity factor. Cost and Benefit Components 3-5

30 Table 3-5: Cogeneration and Biogas System Capacity Factor Scenarios Technology Type Base Case Optimistic Case Biogas 40% 43% Natural Gas Microturbine 53% 55% Natural Gas Engine 47% 49% Details of the cogeneration and biogas system power output modeling methodology are contained in Appendix A. Electricity Retail Value The retail value of the electricity generated by SGIP-sponsored facilities is the product of the amount of generation produced by program-supported facilities and the unit-value of that generation. Despite the relatively short duration of data collection (usually less than one year), the electric net generator output (ENGO) data for the sampled projects contain sufficient detail to permit accurate evaluation of the retail value of the electricity based on time of day. This is important because the value of electricity is based not only on the quantity of energy but also the time period in which it is used. Utility rate structures for medium to large commercial and industrial facility are based on the time period in which the usage occurs because it is more expensive to provide electricity during peak demand periods. Both the utility-billed energy charges (cost per kwh) and demand charges (cost per kw) are based on time of use. Electric tariffs used as the basis for this cost-effectiveness evaluation are listed in Table Table 3-6: Electric Tariffs Utility PG&E SCE SDG&E Electric Tariff E-19: Medium General Demand-Metered Time-of-Use Service TOU-8: Time-of-Use General Service Large AL-TOU-DER: General Service Time Metered Distributed Energy Resources Calculation of retail value of electricity generated by SGIP cogeneration systems includes effects of certain nonbypassable charges applied to departing loads. The Public Purpose Programs Charge (PPPC) and the Nuclear Decommissioning Charge (NDC) apply to all cogeneration systems; the DWR Bond Charge (DWR-BC) applies only to cogeneration 7 These rates apply to facilities that have a demand of 500kW or more. Some of the SGIP sites have lower demand capacities. However, these three rates provide a reasonable first approximation. Retail electric rates for smaller capacity sites would be somewhat higher than the tariffs selected. 3-6 Cost and Benefit Components

31 systems larger than 1 MW in size. To estimate the charges in future years these values were escalated using the assumed general rate of inflation. Nonbypassable charges affecting cogeneration systems are presented in Table 3-7 in nominal dollars. Table 3-7: Cogeneration System Nonbypassable Electric Charges (Cents/kWh) Electric Utility Tariff Public Purpose Programs Charge (PPPC) Nuclear Decommissioning Charge (NDC) DWR Bond Charge* (DWR-BC) PG&E E SCG TOU SDG&E AL-TOU-DER *DWR-BC applies to systems larger than 1 MW. Computing the retail value of energy saved by DG is straightforward using the ENGO data. Estimating the demand charge saving is more difficult without access to the revenue meter data for the entire site demand and without detailed knowledge of the planned facility operation. To get around this problem, it was assumed that the DG equipment would be used during the peak demand or partial peak demand periods. By identifying the monthly minima for these periods, the demand charges saving could be estimated. The revenue requirement forecasts submitted by the electric utilities to the CEC in connection with the 2005 Integrated Energy Policy Report (IEPR) proceeding were used as the basis for projecting future retail electricity prices. The revenue requirement forecasts were transformed into escalation factors that were then applied to the January 2004 rates corresponding to the tariffs listed in Table 3-6. Because the utilities revenue requirement forecasts only extend through 2016 the remaining years were assumed to have zero additional escalation in real terms. Results of the electric retail rate projection are depicted graphically in Figure 3-1. In real terms the rates of PG&E and SDG&E are projected to remain relatively unchanged through the study period, while those of SCE are expected to increase by approximately 20%. Electric rate escalation factors in Figure 3-1 are expressed in nominal dollars and therefore include effects of the 2% general inflation rate assumption. Details of the electric retail rate analysis are included as Appendix C. Cost and Benefit Components 3-7

32 Figure 3-1: Summary of Electric Retail Rate Projections Electric Rate Escalation Factor (Nominal $) SDGE PGE SCE Electric Utility Avoided Costs When DG systems produce electricity or yield electricity displacement the electric utility avoids having to provide power it would otherwise have had to deliver. The avoided cost of electricity refers to the value of this power. As with the retail value, avoided cost has both energy and a demand component. Both components are included in the E 3 Avoided Cost Model. The hourly avoided generation cost data were combined with estimated hourly generation profiles in the preliminary cost-effectiveness evaluation analysis. The E 3 model computes avoided costs by year and hour of year for each of the three SGIP electric utilities. For each hour a marginal generator type and vintage is assumed based on load factors and on the mix of generation equipment likely to be used at that time. Off-peak hours are typically served by efficient, clean, base-loaded generation units. During peak hours less efficient and more polluting units are also brought into service. The E 3 model includes both the energy costs and the T&D (transmission and distribution) costs for each hour for years 2006 through The T&D costs are used only for the hours when the utility is at or close to its peak capacity. As such, these costs are very sensitive to the time of generation and are highly variable. Avoided Generation Costs The E 3 avoided generation cost forecasts are used to value the energy benefits of SGIP systems. The avoided costs reflect the hourly marginal costs of utility generation. They thus also reflect the value to society and to utility ratepayers corresponding to reduced electricity demand resulting from operation of SGIP systems. In addition to cost elements such as fuel 3-8 Cost and Benefit Components

33 and pollution management costs 8, the energy component of avoided costs from E 3 s model also includes several additional factors discussed in the Framework Report. These factors include: reliability net benefits, reduced line losses, and price effects. Each of these factors is discussed briefly below. Reliability Net Benefits. In the E 3 model, reliability net benefits are defined as the cost of providing ancillary services for a given load. As noted in the Framework Report, these effects are reflected in E 3 s Electricity Avoided Cost model as a 0.3 cents per kwh adder to the energy component of avoided costs. Thus they are included in the present analysis wherever avoided electricity costs are calculated. Reliability effects on the grid, as noted in the Framework report, are counted in a limited sense. Reduced Line Losses. Line losses are eliminated for locally consumed on-site generation. This benefit of DG is accounted for in the E 3 generation avoided costs. Price Effects. By reducing electricity demand for all ratepayers, it can be argued that the SGIP program produces positive price externalities by lowering the price elasticity for electricity. But as noted in Section of the Framework Report this would only be true if the electricity system were not in long-run equilibrium. The E 3 analysis assumes that the system is in log-run equilibrium starting in Prior to that time, a small (0.3%) adder is included in avoided costs. After that time, the adder is zero. These effects were included in the framework s proposed analytic methodology and they are included in the preliminary cost-effectiveness evaluation analysis. The electric energy avoided cost data are summarized at a very high level in Figure 3-2, which illustrates the trend for costs in a similar format as was used for electricity prices in Figure 3-1. The avoided cost data for each year shown in Figure 3-2 represent means of all of the hourly values for all climate zones, electric utilities, and zones. As such, they provide a very general indication of the projected trend for electric energy avoided costs. On the right-hand axis the mean avoided costs are expressed in units of cents/kwh (2004 $). During the period 2004 through 2023 the per-kwh avoided costs are projected to increase by approximately 70%. The discrepancy between projected avoided costs and projected retail rates pinpoints a problem that surfaced in operation of natural gas-fired cogeneration facilities. In particular, volatility in natural gas prices is not realized in retail rates. Consequently, SGIP cogeneration facilities faced with unusually high natural gas prices in the fourth quarter of 2004 elected to shut down their facilities during non-peak hours as they 8 Generation of electricity using conventional means results in creation of certain gaseous and particulate pollutants that must be managed. Principal means of management include ownership and operation of air pollution control systems, and purchase of air pollutant emissions offsets on the open market. Cost and Benefit Components 3-9

34 were unable to recoup the prices paid for natural gas in the lower electricity retail rate savings. Figure 3-2: Summary of Electric Energy Avoided Cost Projections Ratio of Costs (Year y to 2004) Mean Cost (Cents/kWh) Avoided Transmission and Distribution Costs E 3 provides forecasts of avoided T&D costs by utility, climate zone, division, voltage level, hour, and forecast year. These costs are meant to be discounted savings from deferrals of T&D investments. Due to information availability constraints there is some question as to the applicability of the E 3 T&D avoided cost data to the evaluation of the SGIP. 9 In light of this the framework includes this parameter as a benefit of the program, but sets these benefits equal to zero for purposes of calculating primary estimates of SGIP cost-effectiveness. However, to provide potentially useful information to the regulatory process results are also calculated for a scenario that includes the E 3 T&D avoided costs in the estimation of T&D benefits. Other Factors Possible economic impacts (e.g., employment, income, tax revenues), national security impacts, and power quality impacts of DG were discussed in the Framework Report. However, these factors were not included in the framework s proposed analytic methodology and they are not included in the preliminary cost-effectiveness evaluation analysis. 9 Moreover, as D precludes SGIP projects from entering into contracts for distribution services, Itron has assumed that these benefits are set to zero in the cost-effectiveness evaluation Cost and Benefit Components

35 3.3 Natural Gas Consumption and Savings The volume of natural gas affected by the program consists of both the fuel used for cogeneration and the volume of gas saved as a result of utilization of useful recovered heat. As with electricity, natural gas is valued both in terms of it retail value and the costs avoided/incurred by the gas utility or society as a consequence of changes in overall gas delivery. These cost elements are used in the cost-effectiveness tests as appropriate for each test perspective. TMY 8760-Hour Natural Gas Consumption and Savings Natural gas consumption of microturbines and engines is a function of power output and electrical conversion efficiency. Modeling of cogeneration system power output was discussed above in Section 3.2. In most cases where power output data were available metered natural gas consumption data collected by utility companies were also available. In cases where metered natural gas consumption data were not available the gas usage was estimated using typical electrical conversion rates indicated by the available metered data. Estimates of natural gas savings resulting from utilization of recovered heat were calculated based on available metered heat recovery rates. The quantity of metered heat recovery data remains small however. In cases where metered heat recovery data were not available the heat recovery rate was estimated using typical heat recovery rates indicated by the available metered data. In most cases heat recovered from cogeneration systems reduced fuel consumption of natural gas boilers. An assumed boiler efficiency of 75% was assumed to translate heat recovery rates into natural gas savings estimates. Natural Gas Avoided Costs Total natural gas costs comprise a commodity component and a T&D component. 10 The basis of natural gas avoided costs depends on the test perspective. For this study all natural gas is assumed to be purchased under non-core tariffs. Under these tariffs the customer buys the commodity component of natural gas from some source other than the gas utility company. From the utility company s perspective, and thus from the perspective of its ratepayers, natural gas avoided costs are limited to the transportation component of natural gas costs. From society s perspective, natural gas avoided costs include both the commodity and transportation components. 10 The workbook also treats an environmental component for NOx and CO2, however in our analysis we are treating this component outside of the E 3 workbook because we need to treat a variety of technologies not included among the end uses included in the E 3 workbook. Cost and Benefit Components 3-11

36 Estimated values of the transportation component of natural gas avoided costs are based on a simplifying assumption. Specifically, the costs faced by natural gas utility companies to transport fuel used in SGIP systems are assumed to be equal to the marginal costs faced by natural gas utility companies to transport fuel to their commercial core customers. Gas transportation marginal costs for commercial core customers were obtained from E 3. These costs are assumed to escalate at the general rate of inflation (2%). The variability exhibited by total natural gas avoided cost values across years is summarized in Figure 3-3. Data currently available from E 3 extend from 2006 onward, whereas for purposes of this cost-effectiveness analysis 2004 is assumed to be the first year of SGIP system operation. In this analysis the nominal 2006 data were also used for 2004 and Figure 3-3: Annual Average Natural Gas Avoided Cost from Society s Perspective by Year 9 8 Avg. Avoided Cost ($/MMBtu, nominal) PG&E SoCalGas&SDG&E Natural Gas Retail Value Price forecasts for natural gas purchased by electricity generators are included in the E 3 electricity avoided cost model. These same price forecasts are applicable to SGIP cogeneration systems. Details of the application of the price forecasts are included as Appendix C In preparing this report, it became apparent that discrepancies between natural gas prices and retail rate electricity were negatively impacting natural gas-fired SGIP facilities. Differences between the magnitude of natural gas price forecasts and projected electricity retail rates suggest future discrepancies could occur with similar negative impacts. See Appendix A for additional discussion on the relationship between natural gas prices and the SGIP natural gas-fired cogeneration capacity factors Cost and Benefit Components

37 3.4 SGIP Administration and Incentives The program s implementation and evaluation costs are included in the cost-effectiveness analysis. Implementation costs comprise two components: incentives and administration. Incentives corresponding to the SGIP systems included in this preliminary cost-effectiveness evaluation are summarized in Table 3-8. Table 3-8: Incentives Paid and Reserved Incentives Paid/Reserved Technology Total (MW) Avg. ($/W) Total ($ MM) PV 29.6 $3.4 $101.2 Biogas 3.2 $0.78 $2.5 Cogeneration 42.2 $0.58 $24.6 Microturbine 37.1 $0.56 $20.9 Engine 5.1 $0.72 $3.7 Total 71.8 $1.75 $125.8 Expenditures for program administration cover such factors as salaries and facilities, and costs incurred by program administrators to hire subcontractors involved with program design and implementation (e.g., engineering firms performing field work and providing engineering review services). Program administrators report these costs to the CPUC on a regular basis. Through the end of 2004 the total of these costs for the four program administrators totaled $9.4 million. Program evaluation costs include those incurred by program administrators individually to hire electric meter installation subcontractors, and those incurred jointly to cover the costs of the principal program evaluation subcontractor. Through the end of 2004 the total of these costs for the four program administrators totaled $3.1 million. The simplest treatment of total program administration and evaluation costs ($12.5 million) would be to allocate the total across all active and complete projects based on project size. This approach results in an estimate of per-kw program administration cost equal to $47.75/kW. Cogeneration projects require engineering review of waste heat utilization worksheets, and the metering for cogeneration projects costs more than the metering for PV projects. On the other hand, the average size of PV projects (138 kw) is smaller than the average size of cogeneration projects (481 kw), and some costs (e.g., creating and maintaining files, driving to a site to verify system installation) are relatively independent of project size. Given these considerations, the possible benefits of more rigorous allocation analysis were deemed inconsequential and the $47.75/kW result was used in the analysis. Cost and Benefit Components 3-13

38 3.5 General Financial Assumptions For simplicity several assumptions are made regarding the timing of the system installation and the financial arrangements. The systems are assumed to be paid for and installed in year zero. In year 1 the system is assumed to be fully operational and to receive the incentive payment. Federal and state tax credits are assumed to be received in year one. 12 For Participant Test purposes, after-tax costs and benefits are assumed to be the relevant measure. For this purpose it was assumed that the marginal tax rate for participant system owners is 34% federal and 8% state, for an effective marginal tax rate of 39.3%. The assumption regarding general inflation rates, cost escalation rates, social and private discount rates and loan rates are all assumed to be interrelated. An inflation rate equal to 2% is assumed. Assuming this inflation and a real social discount rate of 3% yields a nominal social discount rate of 5.1%. 13 The real discount rate applicable to the other three perspectives is assumed to be 6% in real terms. Discount rates assumed for the analysis are summarized in Table 3-9. Table 3-9: Discount Rates Assumed in the Analysis Test Discount Rate (%, nominal) Societal Test 5.1% Total Resource Cost Test 8.1% Participant Test 8.1% Nonparticipant Test 8.1% The loan term for financed equipment is limited to the typical expected life of the generating source. The capital cost of equipment is assumed to be financed by a loan that covers the entire capital cost less incentive payments. O&M costs for SGIP projects are assumed to escalate at the general inflation rate. It is assumed that the costs of major non-routine maintenance events (such as replacement of PV inverters after 10 years) are expensed 14 in the year they occur. 12 In effect, the system owner carries the capital costs offset by the incentive and the tax credits during year zero. 13 The nominal discount rate is calculated as (1+inflation rate) x (1+real discount rate) This implies that the equipment owner has sufficient profits to offset these expenses. If this were not the case, the deduction would be carried forward into future years Cost and Benefit Components

39 4 Societal Test 4.1 Introduction The societal test evaluates the costs and benefits of the SGIP from the perspective of all members of society. The reason for adopting a Societal perspective is that it is consistent with the Commission s desire to use this type of methodology to assess resource options, one of which (DG) is promoted through the SGIP. A distinguishing characteristic of the societal test is its inclusion of economic impacts of air pollutant emissions that are not tied directly to the delivery or purchase of energy. Environmental externalities covered by this analysis include oxides of nitrogen (NOx) and carbon dioxide (CO 2 ). The societal test also includes consideration of adders for reliability, marginal transmission and distribution effects and other social externalities. Section 4.2 discusses differences between the Standard Practice Manual and the SGIP-framework relative to the societal test. Section 4.3 discusses the components and methods used to evaluate societal benefits. Societal cost variables and measurement methods are presented in Section 4.4. The last section provides a summary of SGIP cost-effectiveness evaluation results from the perspective of all members of society. 4.2 Variations from the SPM The Itron framework report details the reasoning behind, and the development of, an SGIPspecific societal test, and contains more detailed discussion of the components. In general, the societal test is a variant of the CPUC s Total Resource Cost (TRC) Test. The perspective of the Societal Test differs from that of the standard TRC in three ways: The Societal Test ignores tax credits, which are benefits to participants but costs to other taxpayers, The Societal Test considers a series of externalities, which affect society as a whole, and The Societal Test makes use of a societal discount rate, which is generally lower than the private discount rate employed in the TRC test. Figure 4-1 shows the general relationship between benefits and costs for an SGIP cogeneration facility from the societal perspective. Societal Test 4-1

40 Figure 4-1: Relationship Between Costs and Benefits in Societal Test SGIP Facility Fuel Input Waste Heat Recovery* Non-Electrical Waste Heat Recovery Electrical Benefits Electricity from utility generator Costs Avoided natural gas from on-site boiler Avoided electricity from on-site electrical chiller Avoided T&D Reduced line losses Increased reliability Price benefits Avoided electricity generation* Avoided CO 2 damage Fuel costs (as appropriate) Equipment purchase & installation Operating & maintenance External environmental costs (beyond control equipment costs) Program administration * For SGIP facilities using waste heat recovery to run absorption/adsorption chillers, environmental benefits are rolled into avoided electricity generation benefits. For SGIP facilities using waste heat recovery for non-electrical purposes and which displaces natural gas use from on-site boilers, environmental benefits are calculated using avoided natural gas environmental adders from E3 4.3 Societal Benefits The benefit components included in the societal test are listed below. Several of these benefits also apply to one or more of the other tests. To avoid repetition in these cases discussion of the evaluation data, assumptions, and analysis pertaining to these common benefits is included in Section 3 of this report. Avoided generation costs (see Section 3.2) Avoided/deferred transmission and distribution capital costs (see Section 3.2) Reliability net benefits (see Section 3.2) Reduced line losses (see Section 3.2) External environmental benefits (see discussion below) Price effects (see Section 3.2) Waste heat use benefits of combined heat and power applications (see Section 3.3). Only the external environmental benefits are discussed in detail in this section. Methods used to treat the remaining benefit categories were discussed previously and can be found in Section 3.2 and Section Societal Test

41 External Environmental Benefits External environmental benefits refer to reductions in pollution-related costs that are excluded from transactions between utility companies and utility customers. 1 Operation of SGIP systems results in decreased use of conventional fuels and energy technologies to deliver heating, cooling, and electric end-use 2 energy services. These energy services, the conventional fuels and technologies, and resulting external environmental costs are depicted graphically in Figure 4-2 and Figure Avoidance of external environmental costs attributable to operation of SGIP systems represents an economic benefit from the perspective of society. Figure 4-2: Summary of Energy Services and Avoided External Environmental Costs - Conventional Energy Services Delivery Model Natural Gas Other Fuels NG Boiler THE GRID Electric Chiller CO2 (External Cost) NOx (External Cost) NG Heating Services CO2 (External Cost) Electric end use services Cooling services Avoided External Environmental Costs The Grid. All SGIP systems produce electricity that would otherwise have been provided by an electric utility company through the grid. When reliance on the grid is reduced, the air pollution emissions associated with grid generation are also reduced. To the extent that the reduced emissions are not internalized by the marketplace, these impacts should be valued and included in a societal test. This has been a fairly standard practice in California for the assessment of energy efficiency options. However, utility generation units are typically required to provide emission offsets for residual emissions of some pollutants. To the extent that the costs of generation reflect the costs of these offsets, these costs are internalized by the market and need not be considered separately as an additional benefit. Such offsets are currently required for NOx, and PM-10 1 External costs stand in contrast to internal environmental costs that are accounted for in costs incurred by conventional generators and prices paid for grid-supplied power. Internal environmental costs are included in the market component of E 3 s avoided electric cost model, as described in Section Including electric resistance heating applications. 3 PM-10 is not shown as an emission from natural gas boilers. The E 3 avoided cost model for natural gas consumption end uses excludes PM-10 as a significant pollutant because the levels of PM-10 emissions are so low that they would be inconsequential to the overall consumption emission analysis. PM-10 was treated identically in this cost-effectiveness analysis (including when the natural gas consumption end use was a microturbine or internal combustion engine). Societal Test 4-3

42 emissions, but not for CO 2. As a result, the framework report specifies inclusion of environmental externalities for only emissions of carbon dioxide associated with grid generated electricity. The E 3 model estimates the marginal economic impacts of carbon dioxide emissions. These estimates are used in the societal test cost-effectiveness evaluation to value CO 2 reduction benefits. The E 3 economic value of this environmental externality ranges from $8.00 per ton of reduced CO 2 in 2004 to $20 per ton of reduced CO 2 in As indicated in the E 3 report, the dollar per-mwh values for reduced CO 2 vary from hour to hour with changing characteristics of the marginal generation unit. 4 Avoided External Environmental Costs Natural Gas Boilers (at Host Sites). Many SGIP participants installing cogeneration systems use recovered heat to provide onsite heating services that would otherwise have been provided by a natural gas boiler. By utilizing waste heat the air pollution that would have been emitted by natural gas boilers is avoided. The societal costs associated with these emissions are not accounted for in the price of natural gas; they are external costs and therefore are accounted for separately in the costeffectiveness evaluation. The E 3 avoided cost gas model is used to estimate the economic benefits from these avoided emissions. As with grid emissions, these estimates are based on avoided emission impacts that remain after required control devices were taken into account. The E 3 model considered emissions from three size classes of natural gas boilers: residential units (generally less than 30,000 Btu per hour); small commercial boilers less than 100 million Btu per hour; and large industrial boilers greater than 100 million Btu per hour in rating. Using a heat rate of 14,000 Btu/kwhr for a typical SGIP generation unit provides an upper limit electricity generating capacity of 7 MW. As most SGIP facilities are sized below 7 MW, the cost effectiveness analysis used the values for small commercial natural gas fired boilers (<100 MMBtuh) with uncontrolled emissions out of the E 3 model. The CO 2 and NO x emissions rates for such a boiler were estimated by E 3 in their Avoided Gas Cost Model 5, as were the avoided costs per unit of pollutant weight. The avoided environmental externalities resulting from decreased use of gas boilers are summarized in Table 4-1 on a per-million Btu (MMBtu) basis (higher heating value input). Note that for SGIP facilities that use waste heat recovery absorption/adsorption chillers, environmental benefits resulting from displaced electricity are captured in the avoided electricity generation calculations. 4 For example,e 3 notes that CO 2 values ranged from approximately $3/MWhr to $8/MWhr depending on heat rate 5 The E 3 avoided cost model for natural gas consumption end uses excludes PM-10 as a significant pollutant because the levels of PM-10 emissions are so low that they would be inconsequential to the overall consumption emission analysis. PM-10 was treated identically in this cost-effectiveness analysis (including when the natural gas consumption end use was a microturbine or internal combustion engine). 4-4 Societal Test

43 Table 4-1: Small Gas Boiler Environmental Externalities ( ) Pollutant Emission Rate (Pound/MMBtu) Unit Value ($/lb) Value ($/MMBtu) NO x CO Summary of Societal Benefits The societal benefits of the program (SocietalBenefits) are specified as the sum of societal benefits associated with individual technologies (SocietalBenefits i ): (1) ( + ) SocietalBenefits = N NTG i = 1 i AvoidedElectricCosts WasteHeatBenefits where AvoidedElectricCostsi represents avoided electric costs associated with technology i, WasteHeatBenefitsi reflects total waste heat benefits associated with technology i, and NTG i is a net-to-gross ratio assumed for the technology in question. This net-to-gross ratio reflects the fraction of benefits that are actually attributable to the program, and is defined as the percentage of distributed generation of the technology in question that would not have been installed in the absence of the SGIP. For the preliminary cost-effectiveness evaluation NTG i is assumed equal to one for both PV and cogeneration systems. i i 4.4 Societal Costs The cost components used in the societal test are listed below. Several of these costs also apply to one or more of the other tests. To avoid repetition in these cases discussion of the evaluation data, assumptions, and analysis pertaining to these common costs is included in Section 3 of this report. External environmental costs from cogeneration system operations (see discussion below). System purchase, operation, and maintenance costs (see Section 3.1) SGIP Program Administration costs (see Section 3.4) Only the external environmental costs are discussed in detail in this section. Methods used to treat the remaining cost categories were discussed previously and can be found in Section 3.1 and Section Table 4-1 presents avoided emissions values for 2004 only. These values, as estimated in the E 3 avoided cost gas model, increase over the period of analysis. Societal Test 4-5

44 External Environmental Costs Increased external environmental costs corresponding to operation of SGIP systems tends to offset the above-described benefits resulting from decreased reliance on the conventional energy services delivery model. These external environmental costs are depicted graphically in Figure The economic impacts of these emissions are not accounted for in the price of natural gas; they are external costs and therefore are accounted for separately in the costeffectiveness evaluation for the societal perspective. Only SGIP systems that do not consume conventional fuels, such as PV or wind systems, do not incur these external environmental costs. Figure 4-3: Summary of Energy Services and External Environmental Costs - DG Energy Services Delivery Model CO2 (External Cost) NOx (External Cost) Natural Gas Solar Energy DG Heat Recovery Chiller Electric end use services NG Heating services Cooling services Section 4.3 includes a discussion of the use of the E 3 Natural Gas Avoided Cost model to estimate the economic benefit attributable to reducing natural gas boiler use. A similar approach was used to estimate external environmental costs attributable to DG equipment operation. The emission factors assumed for cogeneration systems are presented in Table 4-2. The emission rate values were obtained from manufacturers specifications, California Air Resources Board distributed generation certification emissions standards (NOx), and a study of distributed generation completed by the National Renewable Energy Laboratory (CO 2 ). 8 Depending on the technology and the timing of delivery of energy services, cogeneration systems could create external environmental costs exceeding the air pollution control cost savings resulting from avoided grid generation. 7 This general model encompasses PV systems and cogeneration systems. When applied to PV systems, natural gas input is zero, air pollutant emissions are zero, and only electric end use services apply. 8 DER Benefits Studies: Final Report. National Renewable Energy Laboratory (NREL), June, Societal Test

45 Table 4-2: Cogeneration System Environmental Externalities (2004) Unit-Electricity Emission Rate (Pound/MWh) Unit-Electricity Value ($/MWh) Unit-Weight Value Pollutant MT ICE ($/lb) MT ICE NO x CO The forecast values of the cost of air pollutants from the E 3 model were combined with estimates of DG air pollutant emissions characteristics to estimate the environmental cost incurred by society as a result of increased use of SGIP DG systems. Summary of Societal Costs In summary, societal costs include installed equipment costs (InstCost), operating and maintenance costs (OMCost), external environmental costs (EnvCost), and program administrative costs (AdminCost). The present value of societal costs is given by: N (2) SocietalCo sts = NTG ( InstCosti + OMCosti + EnvCosti ) + AdminCosti i i = 1 Note that costs associated with participant activity are multiplied by the net-to-gross ratio to account for the fact that some of these costs could have been incurred in the absence of the program. For the preliminary cost-effectiveness evaluation NTG i is assumed equal to one for all projects. Program administrative costs are all attributable to the program and are thus not multiplied by NTG. Both installation costs and program administration costs are assumed to be incurred in the year of the program; O&M costs and external environmental costs occur over the lifetime of the DG, and the societal discount rate is used to discount annual results back to present values. 4.5 Societal Test Results Two figures of merit are used to summarize results of the societal test: net societal benefits and the benefit-cost ratio. The net societal benefits of the SGIP are calculated as the difference between societal benefits and societal costs: (12) Net Societal Benefits = SocietalBenefits - SocietalCosts As indicated in Section 1, both a Base Case and Optimistic Case were developed for each of the tests. The Optimistic Case includes T&D benefits as well as other favorable assumptions Societal Test 4-7

46 about system performance and maintenance costs. Societal Test net benefits results of the cost-effectiveness evaluation for the Base Case are presented in Table 4-3. These results are based upon the available information from the operational projects under the SGIP as of December 31, This is the same reference point used for the program s PY2004 Impact Evaluation Report. Table 4-3: Societal Test Base Case Net Benefits Results Summary (Net present value, millions 2004 $) NPV Benefits ($million) NPV Costs Net NPV Benefits ($million) Technology No T&D T&D ($million) No T&D T&D PV $62 $75 $227 ($165) ($152) Biogas $11 $11 $14 ($4) ($3) Cogeneration (all) $402 $431 $558 ($156) ($127) IC Engine $362 $389 $485 ($123) ($96) Microturbine $40 $42 $73 ($33) ($31) Total $475 $517 $800 ($325) ($283) A breakdown of Base Case net present value benefits is presented in Table 4-4. Table 4-4: Societal Test Breakdown of Base Case Benefits (Net present value, millions 2004 $) Element PV Biogas ICN MTN Avoided Electricity Costs $46 $7 $269 $27 Avoided T&D Costs $12 $1 $27 $2 Avoided Electricity CO2 Costs $5 $1 $28 $3 Waste Heat Benefits NOx $0 $0 $0 $0 Waste Heat Benefits CO2 $0 $0 $6 $1 Avoided (Host Site) Fuel Costs $0 $3 $59 $9 Salvage Value of Equipment $11 $0 $0 $0 Total (Excl. T&D) $62 $11 $362 $40 Total (Incl. T&D) $75 $11 $389 $42 A breakdown of Base Case net present value costs is presented in Table 4-5. Fuel costs for PV are zero, and initial system costs account for 86% of total costs. The periodic maintenance cost represents replacement of inverters mid-way through the life of the system. For the cogeneration technologies initial system costs account for less than 30% of total costs, while fuel is the largest cost element. 4-8 Societal Test

47 Table 4-5: Societal Test Breakdown of Base Case NPV Costs (millions 2004 $) Element PV Biogas ICN MTN System costs $195 $9 $119 $15 Maintenance Costs - Annual $2 $4 $73 $11 Maintenance Costs - Periodic $29 $2 $0 $7 DG NOx Costs $0 $0 $0 $0 DG CO2 Costs $0 $0 $24 $3 DG Fuel Costs $0 $0 $267 $37 Program Administration $1 $0 $3 $0 Total $227 $14 $485 $73 The influence of T&D benefits on societal test results is indicated in Table 4-3 and Table 4-4. Including T&D benefits increases total net present value benefits of the evaluated group of projects by a total of 9% ($36 million). The influence of several other key factors was examined by calculating societal test results for an alternative, optimistic case. Characteristics differentiating the base and optimistic cases are presented in Table 4-6. Table 4-6: Comparison of Base and Optimistic Cases 9 Technology Factor Base Case PV Biogas ICN MTN Cogeneration Heat Recovery Annual O&M (Cents/kWh) Periodic O&M (% of System Cost) Annual O&M (Cents/kWh) Capacity Factor (%, Weighted Avg.) Annual O&M (Cents/kWh) Capacity Factor (%, Weighted Avg.) Annual O&M (Cents/kWh) Periodic O&M (% of System Cost) Capacity Factor (%, Weighted Avg.) Heat Recovery Rate (MBtu/kWh, Avg.) Optimistic Case % 10% % 43% % 49% % 30% 47% 55% Capacity factors are not provided for PV in table 4-5 as there was no change assumed for PV capacity factor between the base and optimistic case. Societal Test 4-9

48 Societal Test net benefits results of the cost-effectiveness evaluation for the Optimistic Case are presented in Table 4-7. For cogeneration systems the higher capacity factors increase costs for fuel purchases as well as benefits (e.g., electric energy production). Table 4-7: Societal Test - Benefits Results (Optimistic Case) NPV Benefits ($million) NPV Costs Net NPV Benefits ($million) Technology No T&D T&D ($million) No T&D T&D PV $62 $75 $222 ($159) ($147) Biogas $13 $14 $12 $1 $2 Cogeneration (all) $471 $502 $538 ($67) ($36) IC Engine $424 $453 $474 ($50) ($21) Microturbine $47 $50 $64 ($17) ($15) Total $547 $591 $771 ($225) ($180) The societal benefit-cost ratio is calculated as: (3) Societal Benefit-Cost Ratio = SocietalBenefits SocietalCosts Benefit-cost ratio results of the cost-effectiveness evaluation from the perspective of society are presented in Table 4-8. For all cogeneration systems, when excluding T&D benefits the optimistic cost and performance assumptions result in an 18% increase in benefit-cost ratio. The addition of T&D benefits increases the benefit-cost ratio result of PV by 25% and of cogeneration by 5%. The difference is attributable to the fact that PV system energy production occurs exclusively during daylight hours when T&D benefits occur. Table 4-8: Societal Test Benefit-Cost Ratio Results Base Case Optimistic Case Technology No T&D T&D No T&D T&D PV Biogas Cogeneration (all) IC Engine Microturbine Total (Wtd. Avg.) Additional discussion of the cost and benefit components, their overall impact on net present value of benefits, and the benefit-cost ratios is contained in Appendix E Societal Test

49 5 Participant Test 5.1 Introduction The participant test evaluates the benefits and costs of the SGIP from the perspective of participants. From this perspective, the participant s costs of owning and operating the SGIP system are compared against the retail energy costs that would have been incurred by the participant had they continued to obtain all of their electricity from a utility company. A distinguishing characteristic of the participant test is its inclusion of the tax credit and depreciation effects. In this section, discussions of participant-perspective benefits and costs are followed by a summary of analytic methodologies pertaining specifically to the participant test. This section concludes with a summary of cost-effectiveness evaluation results from the perspective of specific groups of SGIP participants and all program participants. 5.2 Variations from the SPM There are no discernable differences from the framework approach to the participant test and that used in the SPM. Within the SPM, the participant test is the measure of the quantifiable benefits and costs to the customer due to participation in the program. Benefits in the SPM and the framework participant test both include reduction in the customer s utility bill, any incentive paid by the utility or third party, and any received federal, state or local tax credits. Similarly, costs in the SPM and framework participant test include all out-of-pocket expenses incurred as a result of participating in the program, plus any increases in the customer s utility bill. These costs include the cost of any equipment or materials purchased, including sales tax and installation; any on-going operation and maintenance costs; any removal costs (minus the salvage value of the equipment); and the value of the customer s time in implementation of the system. Participant Test 5-1

50 Figure 5-1 shows the general relationship between benefits and costs for an SGIP cogeneration facility from the participant perspective. Figure 5-1: Relationship Between Participant Test Benefits and Costs Costs SGIP Facility Benefits Waste Heat Recovery* Non-Electrical Waste Heat Recovery Electrical Difference in electricity demand & consumption Electricity from utility generator Net differences: Lower cost of electricity Avoided natural gas from on-site boiler Avoided electricity from on-site electrical chiller Combined heat and power benefits* Other benefits: Fuel costs (as appropriate) Equipment purchase & installation (net of SGIP Incentive) Operating & maintenance External environmental costs (beyond required control equipment costs) Tax credits Other incentives Depreciation benefits * For SGIP facilities using waste heat recovery to run absorption/adsorption chillers, environmental benefits are rolled into avoided electricity generation benefits. For SGIP facilities using waste heat recovery for non-electrical purposes and which displaces natural gas use from on-site boilers, environmental benefits are calculated using avoided natural gas environmental adders from E Participant Benefits The benefits included in the Participant Test are listed below. In many cases these benefits also apply to one or more of the other tests as well. In these instances the discussion of the evaluation data, assumptions, and analysis is included in Section 3 of this report. To avoid repetition these discussions are not repeated here. Lower cost of electricity (see Section 3.2) Combined heat and power (see Section 3.3) Other incentives (see discussion below) Tax credits (see discussion below) Depreciation benefits (see discussion below) 5-2 Participant Test

51 Other incentives, tax credits, and depreciation benefits are discussed in detail in this section, because these benefits are applicable only to the Participant Test. Treatment of the remaining benefit categories is discussed in Section 3.2 and Section 3.3. Tax Credits State and federal tax regulations include provisions for tax credits and production incentives to offset the cost of qualifying SGIP systems. Tax credits affect project economics in a manner similar to that exhibited by the SGIP rebates. Tax credits are calculated as a percentage of system cost, and the system owner is able to reduce its tax liability by an amount equal to the tax credit. Tax credits were examined only for PV system projects. 1 Key elements of tax credit regulations include provisions governing rates and bases. Key elements of applicable state tax credit regulations are summarized in Table The state tax credit rate depends on the tax year. For purposes of estimating SGIP cost-effectiveness, the date when the PV system entered normal operations was used as the basis for assigning a tax year. Table 5-1: State Tax Credit Provisions PV Element Description Rate (%) Varies depending on tax year: a) : 15.0% b) : 7.5% Basis ($) Applies only to first 200 kw of PV system capacity Tax credit rate is applied to the lesser of a) $4.50/Watt, or b) Cost of system after deducting value of municipal, state (e.g., SGIP), or federal incentives Key elements of applicable federal tax credit regulations are summarized in Table The federal tax credit is not subject to a maximum PV system size limit. Another possible federal tax credit is the recently enacted Renewable Electricity Production Tax Credit. This credit applies to PV, wind, and renewable-fueled cogeneration systems. It provides a 1.9 cent per 1 State and federal tax credits were examined only for PV systems as there were no qualifying tax credits for non-renewable cogeneration facilities and there were too few wind and biogas facilities in the SGIP for these impacts to have much effect on cost effectiveness. 2 Provisions of the state tax credit are outlined in California Franchise Tax Board (FTB) Form 3508, Solar or Wind Energy System Credit. 3 Provisions of the federal tax credit are outlined in Internal Revenue Service (IRS) Form 3468, Investment Credit. Participant Test 5-3

52 kwh production tax credit. However, producers who take advantage of this credit cannot claim the larger 10% Federal tax credit. Therefore, it is not assumed to influence the economics of SGIP systems. 4 Table 5-2: Federal Tax Credit Provisions PV Element Rate (%) : 10% Description Basis ($) Applies only to first 200 kw of PV system capacity Tax credit rate is applied to the lesser of a) $4.50/Watt, or b) Cost of system after deducting value of municipal, state (e.g., SGIP), or federal incentives Depreciation Benefits Depreciation benefits apply both to SGIP PV and cogeneration systems. Whereas tax credits reduce tax liability directly, depreciation allowances do so indirectly. Taxable net income (i.e., profit) is reduced by a depreciation allowance prior to determination of tax liability. The economic benefit of depreciation is thus calculated as the product of the depreciation allowance and the applicable marginal tax rate. Depreciation benefits are realized at both the state and federal levels. In the case of the latter, two types of depreciation benefits exist: additional first-year bonus depreciation, and the applicable five-year depreciation schedule for the qualified equipment. Key elements of applicable federal bonus depreciation provisions are summarized in Table The federal bonus depreciation rate depends on the date when the system entered service. For purposes of estimating SGIP cost-effectiveness the date when the SGIP system entered normal operations was used as the basis for assigning a bonus depreciation rate. The basis is reduced by 50% of the value of applicable federal tax credits, but is not reduced by the value of applicable state tax credits. 4 University of North Carolina DSIRE database: rentpageid=1 5 Provisions of the federal tax credit are outlined in Internal Revenue Service (IRS) Form 3468, Investment Credit. 5-4 Participant Test

53 Table 5-3: Federal First-Year Bonus Depreciation Provisions PV and Cogeneration Rate (%) Basis ($) Element Description Varies depending on tax year: a) Sep. 10, 2001 May 4, 2003: 30% b) May 5, 2003 Dec. 31, 2004: 50% Cost of system after deducting value of municipal and state incentives, and after deducting 50% of value of federal tax credit. Key elements of applicable federal five-year depreciation regulations are summarized in Table Table 5-4: Federal Five-Year Depreciation Provisions Element Rate (%) Basis ($) Description Year 1: 20.00% Year 2: 32.00% Year 3: 19.20% Year 4: 11.52% Year 5: 11.52% Year 6: 5.76% Cost of system after deducting value of municipal and state incentives, and after deducting 50% of value of federal tax credit, and after deducting value of one-time bonus depreciation allowance. Other Incentives In some instances SGIP projects received financial support from programs other than the SGIP. The program having the largest influence on the SGIP cost-effectiveness evaluation is the PV incentive program sponsored by the Los Angeles Department of Water and Power (LADWP). Support from LADWP had a significant impact on the cost-effectiveness of SGIP PV projects from the participant perspective. SGIP program administrators compiled and provided data on financial support from other sources for purposes of evaluating SGIP cost-effectiveness. Summary of Participant Benefits To recognize variations in participant benefits across technologies, the analysis is conducted at the technology level, and then aggregated to the program level. 6 Provisions of the federal tax credit are outlined in Internal Revenue Service (IRS) Form 3468, Investment Credit. Participant Test 5-5

54 That is, program-level participant benefits (ParticpantBenefits) are expressed as: (1) N Participan tbenefits = Re delecbills + ValDispFuels + Inc + IncO + TC i i i i i i = 1 where Inci represents SGIP incentives, IncOi reflects other incentives, and TCi indicates tax credits and depreciation benefits. Reductions in electric bills are computed as the sum of reductions in energy charges (RedEnChg) and reductions in demand charges (RedDemChg). These reductions take into account the specific treatments of net metering under the SGIP, which differ across DG technologies. Note that these reductions are net of any possible charges associated with the use of DG (e.g., non-bypassable charges for cogeneration systems). 5.4 Participant Costs The benefits included in the framework for the Participant Test are listed below. In many cases these costs also apply to one or more of the other tests. In these instances the discussion of the evaluation data, assumptions, and analysis is included in Section 3. To avoid repetition these discussions are not repeated here. System purchase, operation, and maintenance costs (see Section 3.1) The cost elements pertaining to the participant test were discussed in Section 3. Summary of Participant Costs Participant costs are expressed as: (9) ParticipantCosts = N ( InstCost i i = 1 + OMCosts ) i where InstCosti is the installed cost of equipment and offsets and OMCostsi reflects O&M costs. Installed costs are assumed to be incurred in the first period, and incentives are assumed to be paid in that period as well. O&M costs are recognized to occur over time, and their present values are calculated. 5.5 Participant Test Results Two figures of merit are used to summarize results of the participant test: net participant benefits and benefit-cost ratio. 5-6 Participant Test

55 The net participant benefits of the SGIP are calculated as the difference between participant benefits and participant costs: (15) Net Participant Benefits = ParticipantBenefits - ParticipantCosts Net benefits results of the cost-effectiveness evaluation from the perspective of participants are presented in Table Table 5-5: Participant Test Base Case Net Benefits Results (Net present value, millions 2004 $) Technology Benefits ($million) Costs ($million) Net Benefits ($million) PV $86 $97 ($11) Biogas $12 $8 $5 Cogeneration $290 $277 $13 ICE $261 $241 $20 MT $29 $36 ($7) Total $389 $38 $7 A breakdown of Base Case net present value benefits is presented in Table 5-6. Table 5-6: Participant Test Breakdown of Base Case Benefits (Net present value, millions 2004 $) Element PV Biogas ICN MTN Avoided Electricity Costs $28 $9 $203 $21 Tax Credits $19 $0 $0 $0 Tax Depreciation Benefits $35 $2 $31 $4 Avoided Fuel Costs $0 $1 $28 $4 Salvage $4 $0 $0 $0 Total $86 $12 $261 $29 A breakdown of Base Case net present value costs is presented in Table 5-7. Fuel costs for PV and biogas are zero. The periodic maintenance cost represents replacement of inverters mid-way through the life of the system. For the cogeneration technologies, initial system costs account for approximately 30% of total costs, while fuel is the largest cost element. Participant Test 5-7

56 Table 5-7: Participant Test Breakdown of Base Case Costs (Net present value, millions 2004 $) Element PV Biogas ICN MTN Net System costs (less Incentives) $82 $5 $67 $9 Maintenance Costs - Annual $1 $2 $34 $5 Maintenance Costs - Periodic $14 $1 $0 $3 Nonbypassable Charges $0 $0 $13 $1 DG Fuel Costs $0 $0 $127 $18 Total $97 $8 $241 $36 Participant Test net benefits results of the cost-effectiveness evaluation for the Optimistic Case are presented in Table 5-8. Table 5-8: Participant Test Optimistic Case Net Benefits Results Benefits (Net present value, millions 2004 $) Technology Benefits ($million) Costs ($million) Net Benefits ($million) PV $86 $97 ($11) Biogas $14 $7 $7 Cogeneration $326 $272 $55 ICE $294 $240 $54 MT $32 $32 $1 Total $427 $376 $51 The Participant Test benefit-cost ratio is calculated as: (13) Participant Benefit-Cost Ratio = ParticipantBenefits ParticipantCosts 5-8 Participant Test

57 Benefit-cost ratio results of the cost-effectiveness evaluation from the perspective of SGIP participants are presented in Table 5-9. Table 5-9: Participant Test Benefit-Cost Ratio Results Technology Base Case Optimistic Case PV Biogas Cogeneration (all) IC Engines Microturbines Total (Wtd. Avg.) Additional discussion of the cost and benefit components, their overall impact on net present value of benefits, and the benefit-cost ratios is contained in Appendix E. Participant Test 5-9

58 6 Nonparticipant Test 6.1 Introduction The non-participant test evaluates the costs and benefits of the SGIP from the perspective of utility customers that did not participate in the SGIP. This test is sometimes called the ratepayer impact measure (RIM) test because its principal objective is to measure what happens to customer bills or rates due to changes in utility revenues and operating costs caused by the program. Costs can be conceptualized as reductions in electricity revenues from participants, which would ultimately shift the burden for rate recovery to nonparticipants, plus program costs that would have to be covered through rates. In general, rates will go down if the change in revenues of the program is greater than the change in utility costs. Both gas and electric utilities provided support through the SGIP. Consequently, a distinguishing characteristic of the SGIP non-participant test is that it identifies and quantifies the extent to which customers of gas utilities provide financial support for installation of SGIP systems that have only electric impacts. 1 In this section discussions of non-participant costs and benefits costs are followed by a summary of analytic methodologies pertaining specifically to the non-participant test. This section concludes with a summary of cost-effectiveness evaluation results from the perspective of utility customers that did not participate in the SGIP. Unlike the other tests discussed above in Sections 4 and 5, non-participant tests are conducted first separately for gas and electricity utility customers, then on an overall gas and electric utility ratepayer basis. 6.2 Variations from the SPM There are no significant differences from the framework approach to the non-participant test and that used in the SPM. Under the SPM and the framework, calculated benefits are the savings from avoided supply costs. These avoided costs include reduction in transmission, distribution, generation and capacity costs for those periods when load is reduced and the increase in revenues for any periods in which load is increased. Both reductions in supply 1 This is relevant in that the non-participant test is intended to identify costs borne by ratepayers and ultimately the reasonableness of those costs. Consequently, identifying electricity benefits borne by gas ratepayers is significant in isolating out costs that might otherwise not have been borne by those ratepayers. Nonparticipant Test 6-1

59 costs and revenue increases are calculated using net energy savings. Costs for the nonparticipant test in both the SPM and the framework are the program costs incurred by the utility and any other entities incurring costs involved in creating and administering the program; incentives paid to participants; decreased revenues for any period in which load has been decreased and increased supply costs for periods when load has been increased. Figure 6-1 shows the general relationship between benefits and costs for an SGIP cogeneration facility from the non-participant perspective. Figure 6-1: Relationship Between Benefits and Costs in Non-Participant Test Natural Gas Impact Costs/Benefits Fuel Delivery Net Differences: Increased revenue from transportation of fuel (natural gas) Decreased costs for transportation of fuel for on-site boilers SGIP Facility Waste Heat Waste Heat Recovery Recovery Non-Electrical Electrical Avoided natural Avoided electricity gas from on-site from on-site boiler electrical chiller Electricity Impact Costs/Benefits Difference in electricity demand & consumption Electricity from utility generator Net Differences: Avoided electricity costs Avoided T&D costs Net reliability benefits Reduced line losses Price effects SGIP Program Costs: Incentives Program Administration 6.3 Nonparticipant Benefits The benefits included for the non-participant test are listed below. In many cases these benefits also apply to one or more of the other tests as well. In these instances the discussion of the evaluation data, assumptions, and analysis is included in Section 3 of this report. To avoid repetition these discussions are not repeated here. Benefits to Non-participant Electric Utility Ratepayers: Avoided generation costs (see Section 3.2) Avoided transmission and distribution capital costs (see Section 3.2) Reliability net benefits (see Section 3.2) 6-2 Nonparticipant Test

60 Reduced line losses (see Section 3.2) Price effects (see Section 3.2) Benefits to Non-participant Gas Utility Ratepayers: Increased revenue from transportation of fuel for gas-fired SGIP systems (see Section 3.3) Decreased costs for transportation of fuel for boilers (see Section 3.3) Summary of Non-participant Benefits The overall benefits accruing to electric ratepayers include the reductions in system costs associated with the replacement of conventional generation with DG. As with the other tests discussed above, electric ratepayer benefits are derived at the technology level, and then aggregated to the program level. That is: (1) ElecRatePBen = N NTG AvNPEleCosts i i i = 1 where NTGi is the net-to-gross ratio associated with technology i and AvNPEleCostsi is gross avoided costs from the electric ratepayer perspective. Note that the net-to-gross ratio is required by the SPM for use in ratepayer tests. From the perspective of gas customers, benefits (call these GasNPBenefits) consist of avoided fuel transportation costs associated with the use of waste heat by CHP projects (WasteHeatBenefits), plus increased revenues from the transportation of natural gas for gasfired DG (IncrGasRev). These benefits are computed at the technology level and then summed to the program level, as given by: N (8) GasNPBenef its = NTG ( WasteHeatBenefits + IncrGas Rev ) i i i i = 1 Note that the use of the Net-to-Gross Ratio limits benefits to those that are attributable to the program. Waste heat benefits for each technology are estimated for the lifetime of the technology and discounted back to the present period using a discount rate equal to 8.1%. 6.4 Non-participant Costs The costs included in the framework for the non-participant test are listed below. In many cases these costs also apply to one or more of the other tests as well. In these instances the Nonparticipant Test 6-3

61 discussion of the evaluation data, assumptions, and analysis is included in Section 3 of this report. To avoid repetition these discussions are not repeated here. Costs to Non-participant Electric Utility Ratepayers: SGIP Program costs (see discussion below) Decreased revenue from sale of electricity to participants (see Section 3.2) Costs to Non-participant Gas Utility Ratepayers SGIP Program costs (see discussion below) Decreased revenue from transportation of fuel for boilers (see Section 3.3) Increased utility costs for transportation of fuel for gas-fired SGIP systems (see Section 3.3) Summary of Non-participant Costs Electric ratepayer costs (ElecRatePCosts) include foregone revenues from sales of electricity (RedElecBillsi), 2 interconnection costs not covered by participant payments, plus electric program incentive and administration costs paid by electric customers. Electric ratepayer costs are expressed as: (5) ElecRatePCosts = ( NTGi RedElecBillsi + IntCostsi + IncCostEi ) + AdminCostE where IncCostEi indicates electric incentives provided to technology i, AdminCostE depicts administration costs funded by electric ratepayers, and IntCostsi includes any utility interconnection costs not paid for by participants. The calculation of electric bill reductions (RedElecBillsi) was discussed in Section 3. SGIP incentive and administration costs allocated to the operational projects included in the analysis are summarized in Table 6-1. In the case of SGIP projects administered by PG&E and SDREO both gas ratepayers and electric ratepayers fund the program. PG&E gas ratepayers pay 13.7% of PG&E s share 3 of program costs, while SDG&E gas ratepayer pay 21% of program costs. 4 SoCalGas and SCE are single-fuel utility companies. 2 Again, these estimated bill reductions take into account the specific treatment of net metering for qualifying technologies. 3 Public Utilities Commission of the State of California: Advice Letter 2329-G/2140-E (Pacific Gas and Electric Company ID U 39 M). July 11, Public Utilities Commission of the State of California: Advice Letter 1363-E-B, March 8, Nonparticipant Test

62 Table 6-1: SGIP Cost Summary by Ratepayer Group SGIP Incentives ($ MM) Gas Ratepayers Electric Ratepayers Total Incentives $36.29 $ $ Administration $1.78 $2.44 $4.22 Total $38.07 $ $ Non-participant Test Results Two figures of merit are used to summarize results of the non-participant test: net nonparticipant benefits and benefit-cost ratio. The net non-participant benefits of the SGIP are calculated as the difference between nonparticipant benefits and non-participant costs: (12) Net Nonparticipant Benefits = NonparticipantBenefits - NonparticipantCosts Net benefits results of the cost-effectiveness evaluation from the perspective of nonparticipants are presented in Table 6-2 to Table 6-7. Results for the Base Case are presented in the first three of these tables. Table 6-2: Nonparticipant Test Net Benefits All Ratepayers (Base Case) Benefits ($million) Costs Net Benefits ($million) Technology No T&D T&D ($million) No T&D T&D PV $36 $45 $144 ($108) ($99) Biogas $5.7 $6.2 $17 ($12) ($11) Cogeneration $253 $275 $448 ($196) ($173) ICE $229 $249 $405 ($176) ($155) MT $24 $26 $44 ($20) ($18) Total $294 $327 $610 ($315) ($283) Table 6-2 provides estimates of the benefits, costs and net benefits to all ratepayers (electric and natural gas) from implementation of the SGIP under base case conditions. However, these same benefits can be broken out by ratepayer type to show how electricity versus natural gas ratepayers are impacted by the SGIP. Table 6-3 shows the impacts of the SGIP on only electricity ratepayers. Table 6-4 shows the impacts of the SGIP on only natural gas ratepayers. Nonparticipant Test 6-5

63 Table 6-3: Nonparticipant Test Net Benefits Electric Ratepayers (Base Case) Benefits ($million) Costs Net Benefits ($million) Technology No T&D T&D ($million) No T&D T&D PV $36 $45 $130 ($94) ($85) Biogas $5 $6 $17 ($12) ($11) Cogeneration $230 $252 $391 ($161) ($138) ICE $209 $229 $354 ($145) ($125) MT $21 $23 $37 ($16) ($14) Total $271 $304 $538 ($267) ($234) Table 6-4: Nonparticipant Test Net Benefits Gas Ratepayers (Base Case) Benefits ($million) Costs Net Benefits ($million) Technology No T&D T&D ($million) No T&D T&D PV $0 $0 $14 ($14) ($14) Biogas $0 $0 $0 $0 $0 Cogeneration $23 $23 $58 ($35) ($35) ICE $20 $20 $51 ($31) ($31) MT $3 $3 $7 ($4) ($4) Total $23 $23 $72 ($49) ($49) Non-participant Test net benefits results of the cost-effectiveness evaluation for the Optimistic Case are presented in Table 6-5 to Table 6-7. Table 6-3 and Table 6-4 show impacts of the SGIP to electricity and natural gas ratepayers under base case conditions. Table 6-5 shows the impact to all ratepayers under the optimistic case. Table 6-6 and Table 6-7 show the impacts under the optimistic case conditions separately for the electricity and natural gas ratepayers, respectively. In general, as discussed in Section 3 of this report, the optimistic case conditions involve higher capacity factors and lower O&M costs for cogeneration and biogas systems. 6-6 Nonparticipant Test

64 Table 6-5: Nonparticipant Test Net Benefits All Ratepayers (Optimistic) Benefits ($million) Costs Net Benefits ($million) Technology No T&D T&D ($million) No T&D T&D PV $36 $45 $144 ($108) ($99) Biogas $6 $7 $18 ($12) ($12) Cogeneration $275 $299 $480 ($204) ($181) ICE $249 $271 $434 ($184) ($162) MT $26 $28 $46 ($20) ($18) Total $317 $351 $642 ($325) ($291) Table 6-6: Nonparticipant Test Net Benefits Electric Ratepayers (Optimistic Case) Benefits ($million) Costs Net Benefits ($million) Technology No T&D T&D ($million) No T&D T&D PV $36 $45 $130 ($94) ($85) Biogas $6 $6 $18 ($12) ($12) Cogeneration $247 $271 $418 ($171) ($148) ICE $225 $246 $380 ($155) ($133) MT $22 $24 $39 ($16) ($14) Total $288 $322 $566 ($278) ($244) Table 6-7: Nonparticipant Test Net Benefits Gas Ratepayers (Optimistic Case) Benefits ($million) Costs Net Benefits ($million) Technology No T&D T&D ($million) No T&D T&D PV $0 $0 $14 ($14) ($14) Biogas $1 $1 $0 $0 $0 Cogeneration $28 $28 $61 ($33) ($33) ICE $25 $25 $54 ($29) ($29) MT $3 $3 $7 ($4) ($4) Total $29 $29 $76 ($47) ($47) Nonparticipant Test 6-7

65 A breakdown of Base Case net present value benefits is presented in Table 6-8. Table 6-8: Nonparticipant Test Breakdown of Base Case Benefits (Net present value, millions 2004 $) Element PV Biogas ICN MTN Avoided Electricity Costs $35.9 $5.3 $208.9 $21.2 Avoided T&D Costs $9.5 $0.5 $20.6 $1.8 Increased Gas Revenues $0.0 $0.0 $12.8 $1.6 Avoided Gas Costs (host site) $0.0 $0.4 $7.0 $1.1 Total (Excl. T&D) $35.9 $5.7 $228.7 $23.9 Total (Incl. T&D) $45.4 $6.2 $249.3 $25.7 A breakdown of Base Case net present value costs is presented in Table 6-9. Fuel costs for PV are zero, and initial system costs account for 86% of total costs. The periodic maintenance cost represents replacement of inverters mid-way through the life of the system. For the cogeneration technologies initial system costs account for less than 30% of total costs, while fuel is the largest cost element. Table 6-9: Nonparticipant Test Breakdown of Base Case Costs (millions 2004 $) Element PV Biogas ICN MTN Reduced Electric Utility Sales $46.5 $14.5 $334.0 $34.1 Increased Gas Utility Costs $0.0 $0.0 $31.0 $4.8 Decreased Gas Utility Revenue $0.0 $0.1 $2.7 $0.4 Incentives $96.3 $2.5 $34.1 $4.2 Program Administration $1.2 $0.2 $2.9 $0.3 Total $144.0 $17.2 $404.7 $43.7 The Non-participant Test benefit-cost ratio is calculated as: (13) Non-participant Benefit-Cost Ratio = NonparticipantBenefits NonparticipantCosts Benefit-cost ratio results of the cost-effectiveness evaluation from the perspective of SGIP non-participants are presented in Table 6-10 and Table Nonparticipant Test

66 Table 6-10: Nonparticipant Test Benefit-Cost Ratio Results (Base Case) All Ratepayers Electric Ratepayers Technology No T&D T&D No T&D T&D Gas Ratepayers PV Biogas Cogeneration ICE MT Total Table 6-11: Nonparticipant Test Benefit-Cost Ratio Results (Optimistic Case) All Ratepayers Electric Ratepayers Technology No T&D T&D No T&D T&D Gas Ratepayers PV Biogas Cogeneration ICE MT Total Additional discussion of the cost and benefit components, their overall impact on net present value of benefits, and the benefit-cost ratios is contained in Appendix E. Nonparticipant Test 6-9

67 Appendix A DG System Performance Modeling Description A.1 Introduction Metered data collected from a sample of operational PV and cogeneration systems were used to create 8,760-hour performance data sets intended to represent expectations regarding longrun average performance. Whereas the monitored data collected during 2003 and 2004 were used directly to calculate summary statistics reported in the impact evaluation reports, these data were subject to several modifications prior to use in the cost-effectiveness evaluation analysis. The methods used to translate monitored performance data collected from PV and cogeneration systems into typical-performance data sets used in the lifecycle costeffectiveness evaluation are described below. A.2 PV System Performance Metered power output data collected from 2002 to 2004 were combined with observed weather data to develop relationships between weather and PV system power output. The observed weather parameter of principal interest is plane of array solar radiation (POASOLRAD); however, only global horizontal solar radiation data were readily available. For tilted PV systems the ratio of POASOLRAD to global horizontal solar radiation is a function of PV system configuration, hour of year, and cloud cover. A solar radiation model was used to estimate POASOLRAD values coincident with each metered power output data point. The result of the solar radiation modeling described above is a large table containing pairs of POASOLRAD values and their corresponding PV system power output. The tables for each PV system were separated into groups based on season, hour of day, and POASOLRAD level. Table A-1 indicates the three months that are assigned to each season. DG System Performance Modeling Description A-1

68 Table A-1: Basis of Season Assignments Season Spring Summer Fall Winter Months March, April, May June, July, August September, October, November December, January, February The general form of the PV performance modeling is illustrated in Table A-2. These are actual data for one of the SGIP PV systems for the summer season of 2004 for the hour from noon to 1 P.M. (PDT). There are 90 PV system power output values, one for each day during this three-month period. Table A-2: General Form of PV Performance Models (A) SOLRAD (W/sq.m.) (B) System Power Output (kw power output per kw of PV system size) , 0.67, , 0.67, 0.67, 0.67, 0.67, 0.63, 0.63, 0.67, 0.63, 0.67, 0.63, 0.63, 0.63, , 0.77, 0.73, 0.73, 0.70, 0.70, 0.73, 0.67, 0.70, 0.70, 0.70, 0.70, 0.70, 0.67, 0.70, 0.70, 0.67, , 0.77, 0.73, 0.73, 0.77, 0.77, 0.80, 0.77, 0.77, 0.80, 0.77, 0.77, 0.77, 0.73, 0.77, 0.73, 0.73, 0.73, 0.73, 0.73, 0.77, 0.73, 0.73, 0.77, 0.73, 0.77, 0.73, 0.77, 0.73, 0.73, 0.70, 0.73, 0.70, 0.73, 0.73, 0.67, 0.70, 0.70, , 0.73, 0.77, 0.73, 0.77, 0.80, 0.77, 0.73, 0.70, 0.73, 0.77, 0.77, 0.73, 0.73, 0.70, 0.67 The next step in the analysis entailed estimation of POASOLRAD for each hour of an average year representative of long-run average climate, as expressed by data for a typical meteorological year (TMY). Existing 8760-hour TMY weather data sets for 12 climate zones in California served as the starting point. An 8760-hour TMY weather data set was then created for each of the operational PV systems based on facility location. Next, the orientation of each PV system was used to translate global horizontal solar radiation into estimates of the corresponding POASOLRAD. Finally, a PV system power output value was randomly selected (from Column B in Table A-2) based on POASOLRAD value. The methodology described above was used to estimate hourly PV system power output during year one of the analysis. PV system power output for future years was estimated based on the assumption of a 0.5%/yr PV system power output degradation. This factor roughly corresponds to degradation rates embedded in PV module warranties. A-2 DG System Performance Modeling Description

69 A.3 Natural Gas Cogeneration System Performance The power output of cogeneration systems depends on many factors, including facility operating schedules and the price of natural gas. The power generation characteristics of the sample of metered SGIP cogeneration systems during 2004 were summarized in the annual impact evaluation report. Monthly weighted-average capacity factors are summarized in Figure A-1 along with the monthly project on-line capacity trend. Figure A-1: Level 3/3-N/3-R On-Line MW and Average Capacity Factor (2004) To ensure that cogeneration system performance included in the lifecycle cost-effectiveness analysis was representative of future SGIP distributed generation systems, it was necessary to adjust the available metered power generation data collected during 2004 from SGIP cogeneration systems. Interviews conducted with cogeneration system owners in early 2005 indicated that the drop-in weighted average capacity factor late in the year was due in part to abnormally high natural gas prices in Q (i.e., facilities opted not to run cogeneration systems when natural gas prices exceeded electricity savings). A situation where natural gas prices are not reflected in electricity prices is not expected to repeat every year. Consequently, Q metered power output data were excluded from the normalization analysis in cases where a substantial difference was observed between Q3 and Q4 projectspecific capacity factor. Results of this adjustment are presented in Figure A-2, which reflects the upward adjustment of capacity factors during the fourth quarter as compared to those based on raw metered data and summarized in Figure A-1. DG System Performance Modeling Description A-3

70 Metered power output data were available for approximately 40% of the total cogeneration system capacity on-line during These available metered data were used to calculate hourly ratios considered to be more representative of actual power output per unit of rebated system capacity. For periods where no metered data were available for an operational cogeneration system, estimates of power output were calculated as the product of these hourly ratios and the rebated capacity of the unmetered cogeneration system. Figure A-2: Natural Gas Cogeneration System Base Case Capacity Factors 60% Weighted Avg. Capacity Factor (%) 50% 40% 30% 20% 10% 0% Month of 2004 Capacity Factor In addition to the value of electricity produced directly by SGIP facilities, it is necessary to consider the value of electricity savings from the substitution of recovered waste heat for uses that would otherwise require electricity. Typically, these uses involve substitution of an absorption chiller (using waste heat) for an electrical chiller. Less common applications include the use of recovered heat for applications otherwise requiring electrical resistance heating. The basis for estimates of electric savings attributable to absorption chillers is described in the following equation: Chiller Electric Savings sdh kwh = cold [ HEAT ] MBtu [ COP ] [ EFF ] sdh hot HRAC MBtu MBtu Where: Chiller = Electric savings for system s on day d during hour h Electric Units: kwh hot elec kwh 1 Ton Hr Ton Hr 12 MBtu cold A-4 DG System Performance Modeling Description

71 Savings sdh HEAT sdh COP HRAC EFF elec = Recovered heat delivered to the absorption chiller for system s on day d during hour h Units: Thousands of Btu (i.e., MBtu) Source: Metered data = Efficiency of heat recovery absorption chiller. Value: 0.6 Units: MBtu cold /MBtu hot Basis: Assumed = Efficiency of new standard-efficiency electric chiller Value: 0.6 Units: kwh/ton Hr Basis: Assumed The relatively short observation period in this preliminary cost-effectiveness assessment provides a far from ideal basis for projecting power output and heat recovery performance of monitored systems 20 years into the future. Projected performance of the unmonitored systems is subject to even greater uncertainty. Many projects have recently resolved (or are still in the process of resolving) system start-up and shakedown problems; in these instances the currently available metered data may underestimate future performance. As noted in the Fourth-Year Impact Assessment, many cogeneration interview respondents anticipated that their projects would have higher capacity factors in the future. There are other instances of cogeneration system abandonment; it is possible that cogeneration systems observed to be operational in 2004 could be abandoned in the future or experience extended periods of down time due to mechanical or electrical component or system failure. To help gauge the influence of this uncertainty on estimates of SGIP cost-effectiveness an alternative set of ENGO and Recovered Heat data was developed from the available metered data. First, monthly capacity factors (%) and heat recovery rates (MBtu/kWh) were calculated for each project where monitored data were available. The three months exhibiting the highest average capacity factor were identified and used to calculate average capacity factors and heat recovery rates that were subsequently assumed for all other months. Results of this analysis are summarized in Table A-3. On a capacity-weighted average basis the Optimistic Case annual capacity factor is 15% higher than the Base Case. The Optimistic Case annual Heat Recovery is 19% higher than the Base Case. Table A-3: Cogeneration System Performance Scenarios Season Base Case Optimistic Case Capacity Factor (%) 47% 54% Heat Recovery (MBtu/kWh) DG System Performance Modeling Description A-5

72 Appendix B Utility Avoided Cost Forecasts B.1 Introduction Utility avoided cost data forecasts play a critical role in the cost-effectiveness evaluation. Electric and gas avoided cost data prepared by Energy and Environmental Economics, Inc. (E 3 ) were obtained and incorporated into the analysis. The avoided cost data exhibit considerable variability. The data and their variability are summarized below. B.2 Electric Avoided Costs Electric avoided cost data developed by E 3 were used for purposes of evaluating costeffectiveness from the societal and nonparticipant (i.e., ratepayer) perspectives: Filename: Download location: cpucavoided26.xls The workbook s Export Output to File function was used to generate files containing electric avoided cost data for PG&E, SCE, and SDG&E. During the export process the secondary voltage level was selected. Resulting data files include nominal values for three avoided cost components: market (i.e., commodity/generation), environmental (i.e., CO 2 ), and transmission and distribution (T&D). An assumed inflation rate of 2% is embedded in the nominal data. Hourly electric avoided cost data exhibit considerable variability. Variability exhibited by the market and CO 2 components across utility companies is summarized for 2006 in Table B-1. Table B-1: 2006 Annual Average Electric Avoided Cost by Utility Market and CO 2 Components (Cents/kWh, nominal) Component PG&E SCE SDG&E Market CO Utility Avoided Cost Forecasts B-1

73 The T&D values vary depending on climate zone/region. 1 A climate zone map is presented in Figure B-1. Figure B-1: Climate Zones Map Variability exhibited by the T&D component of electric avoided costs across utilities and climate zones for 2006 is summarized in Table B-2. 1 The strong relationship between climate zone and T&D cost variation is explained by E3 as the influence of time dependent value of the avoided cost and that temperature alone can in fact be tied directly to hourly T&D allocation factors. B-2 Utility Avoided Cost Forecasts

1 EXECUTIVE SUMMARY. Executive Summary 1-1

1 EXECUTIVE SUMMARY. Executive Summary 1-1 1 EXECUTIVE SUMMARY Distributed generation and storage technologies are playing an increasing role in the electricity system. As more distributed generation and storage systems improve their cost effectiveness

More information

CPUC Self-Generation Incentive Program Fifth Year Impact Evaluation Final Report

CPUC Self-Generation Incentive Program Fifth Year Impact Evaluation Final Report CPUC Self-Generation Incentive Program Fifth Year Impact Evaluation Final Report Submitted to: PG&E and The Self-Generation Incentive Program Working Group Prepared by: Itron, Inc. 601 Officers Row Vancouver,

More information

Self-Generation Incentive Program

Self-Generation Incentive Program Self-Generation Incentive Program Framework for Assessing the Cost-Effectiveness of the Self-Generation Incentive Program Submitted to: Ms. Valerie Beck California Public Utilities Commission Energy Division

More information

SGIPce 2014: Looking Under the Hood. January 13, 2016 George Simons Tom Mayer Jean Shelton, PhD Itron

SGIPce 2014: Looking Under the Hood. January 13, 2016 George Simons Tom Mayer Jean Shelton, PhD Itron SGIPce 2014: Looking Under the Hood January 13, 2016 George Simons Tom Mayer Jean Shelton, PhD Itron TOPICS FOR TODAY S WEBINAR» Introductions» Overview of SGIPce 2014 model Goals and objectives Inputs

More information

California s Self-Generation Incentive Program: What Is the Consumer Response and Is the CAISO System Peak Load Being Impacted?

California s Self-Generation Incentive Program: What Is the Consumer Response and Is the CAISO System Peak Load Being Impacted? California s Self-Generation Incentive Program: What Is the Consumer Response and Is the CAISO System Peak Load Being Impacted? Patrick Lilly, Itron, Inc./RER Alan Fields, Itron, Inc./RER Brenda Gettig,

More information

Self-Generation Incentive Program Semi-Annual Renewable Fuel Use Report No. 12 for the Six-Month Period Ending June 30, 2008

Self-Generation Incentive Program Semi-Annual Renewable Fuel Use Report No. 12 for the Six-Month Period Ending June 30, 2008 Self-Generation Incentive Program Semi-Annual Renewable Fuel Use Report No. 12 for the Six-Month Period Ending June 30, 2008 1. Summary The purpose of this report is to provide the Energy Division of the

More information

Self-Generation Incentive Program Semi-Annual Renewable Fuel Use Report No. 15 for the Six-Month Period Ending December 31, 2009

Self-Generation Incentive Program Semi-Annual Renewable Fuel Use Report No. 15 for the Six-Month Period Ending December 31, 2009 Self-Generation Incentive Program Semi-Annual Renewable Fuel Use Report No. 15 for the Six-Month Period Ending December 31, 2009 1. Overview Report Purpose This report complies with Decision 02-09-051

More information

Self-Generation Incentive Program Semi-Annual Renewable Fuel Use Report No. 9 For the Six-Month Period Ending December 31, 2006

Self-Generation Incentive Program Semi-Annual Renewable Fuel Use Report No. 9 For the Six-Month Period Ending December 31, 2006 1. Purpose of this Report Self-Generation Incentive Program Semi-Annual Renewable Fuel Use Report No. 9 For the Six-Month Period Ending December 31, 2006 The purpose of this report is to provide the Energy

More information

PREPARED FOR: ARIZONA PUBLIC SERVICE Updated Solar PV Value Report

PREPARED FOR: ARIZONA PUBLIC SERVICE Updated Solar PV Value Report PREPARED FOR: ARIZONA PUBLIC SERVICE 2013 Updated Solar PV Value Report MAY 2013 2013 Updated Solar PV Value Report Arizona Public Service May 10, 2013 This report has been prepared for the use of the

More information

Modeling Distributed Generation Adoption Using Electric Rate Feedback Loops

Modeling Distributed Generation Adoption Using Electric Rate Feedback Loops Overview Modeling Distributed Generation Adoption Using Electric Rate Feedback Loops Mark Chew (Principal, Distributed Generation - m5ci@pge.com), Matt Heling, Colin Kerrigan, Dié (Sarah) Jin, Abigail

More information

Part 1 Introduction and Overview

Part 1 Introduction and Overview Part 1 Introduction and Overview A. Applicability: This Application for Customer Generation Cost Responsibility Surcharge (CRS) Tariff Exemptions (Application) is for the purpose of requesting an exemption

More information

Solar Photovoltaic Volumetric Incentive Program 2015 Report to the Legislative Assembly

Solar Photovoltaic Volumetric Incentive Program 2015 Report to the Legislative Assembly Solar Photovoltaic Volumetric Incentive Program 2015 Report to the Legislative Assembly Prepared by: Oregon Public Utility Commission January 1, 2015 Table of Contents Executive Summary... 2 Background...

More information

PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA ENERGY DIVISION

PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA ENERGY DIVISION October 10, 2011 Advice No. 22 (California Center for Sustainable Energy) Advice No. 3245-G/3923-E (Pacific Gas and Electric Company U 39 M) Advice No. 2637-E (Southern California Edison Company U 338-E)

More information

Actual Performance of CHP DG Systems Installed for Industrial Applications in California

Actual Performance of CHP DG Systems Installed for Industrial Applications in California Actual Performance of CHP DG Systems Installed for Industrial Applications in California Kurt Scheuermann, George Simons, Amber Buhl, Myles O'Kelly, and Heidi Ochsner, Itron, Inc. ABSTRACT Combined heat

More information

CPUC Self-Generation Incentive Program Ninth-Year Impact Evaluation Final Report (Excluding Appendices)

CPUC Self-Generation Incentive Program Ninth-Year Impact Evaluation Final Report (Excluding Appendices) CPUC Self-Generation Incentive Program Ninth-Year Impact Evaluation Final Report (Excluding Appendices) Submitted to: PG&E and The Self-Generation Incentive Program Working Group Prepared by: Itron, Inc.

More information

Locational Net Benefits Analysis Working Group Long Term Refinement Topics Scoping Document Prepared for the ICA Working Group by More Than Smart

Locational Net Benefits Analysis Working Group Long Term Refinement Topics Scoping Document Prepared for the ICA Working Group by More Than Smart Locational Net Benefits Analysis Working Group Long Term Refinement Topics Scoping Document Prepared for the ICA Working Group by More Than Smart Background: A June 7, 2017 Assigned Commissioner Ruling

More information

2009 Power Smart Plan

2009 Power Smart Plan 2009 Power Smart Plan July 2009 *Manitoba Hydro is a licensee of the Official Mark Executive Summary The 2009 Power Smart Plan forecasts Manitoba Hydro s costs and savings to the benchmark year of 2024/25

More information

An Economic Assessment of the Benefits of Storage in South Africa. by Jeremy Hargreaves, Energy & Environmental Economics

An Economic Assessment of the Benefits of Storage in South Africa. by Jeremy Hargreaves, Energy & Environmental Economics An Economic Assessment of the Benefits of Storage in South Africa by Jeremy Hargreaves, Energy & Environmental Economics USTDA/IDC Storage Assessment IDC commissioned the South Africa Energy Storage Technology

More information

California s Approach to Designing a Net Energy Metering (NEM) Tariff. Sara Kamins California Public Utilities Commission June 18, 2014

California s Approach to Designing a Net Energy Metering (NEM) Tariff. Sara Kamins California Public Utilities Commission June 18, 2014 California s Approach to Designing a Net Energy Metering (NEM) Tariff 1 Sara Kamins California Public Utilities Commission June 18, 2014 2 California Presentation topics California s energy market and

More information

CHAPTER 6 - Load Forecast & Resource Plan

CHAPTER 6 - Load Forecast & Resource Plan CHAPTER 6 - Load Forecast & Resource Plan Introduction This Chapter describes the electric resource portfolio that may be acquired to meet the energy requirements of MBCP customers. The following overarching

More information

From: Keith Casey, Vice President, Market and Infrastructure Development

From: Keith Casey, Vice President, Market and Infrastructure Development California Independent System Operator Corporation Memorandum To: ISO Board of Governors From: Keith Casey, Vice President, Market and Infrastructure Development Date: August 18, 2011 Re: Briefing on Renewable

More information

2012 SGIP Impact Evaluation and Program Outlook

2012 SGIP Impact Evaluation and Program Outlook 2012 SGIP Impact Evaluation and Program Outlook Submitted to: PG&E and The SGIP Working Group Prepared by: 330 Madson Pl Davis, CA 95618 Feb 2014 TABLE OF CONTENTS TABLE OF CONTENTS... i LIST OF FIGURES...

More information

Calculating a Dependable Solar. Generation Curve for. SCE s Preferred Resources Pilot

Calculating a Dependable Solar. Generation Curve for. SCE s Preferred Resources Pilot S o u t h e r n C a l i f o r n i a E d i s o n P a g e 1 Calculating a Dependable Solar Generation Curve for SCE s Preferred Resources Pilot October 2017 S o u t h e r n C a l i f o r n i a E d i s o

More information

What s New 2009 Self-Generation Incentive Program

What s New 2009 Self-Generation Incentive Program What s New 2009 Self-Generation Incentive Program The 2009 Self-Generation Incentive Program (SGIP) handbook includes significant changes resulting from recent CPUC decisions. 1. An additional incentive

More information

Proposal Concerning Modifications to LIPA s Tariff for Electric Service

Proposal Concerning Modifications to LIPA s Tariff for Electric Service Proposal Concerning Modifications to LIPA s Tariff for Electric Service Requested Action: The Long Island Power Authority ( LIPA ) staff proposes revisions to the LIPA Tariff for Electric Service to authorize

More information

The Value of Distributed Photovoltaics to Austin Energy and the City of Austin

The Value of Distributed Photovoltaics to Austin Energy and the City of Austin The Value of Distributed Photovoltaics to Austin Energy and the City of Austin Electric Utility Commission Resource Management Commission June 26, 2006 Dr. Thomas E. Hoff 1 Clean Power Research Team Members

More information

Economics of Distributed Resources

Economics of Distributed Resources ELG4126- Sustainable Electrical Power Systems- DGD Economics of Distributed Resources Maryam Parsa DGD 06- March 07, 2013 Winter 2013 Outline COMBINED HEAT AND POWER (CHP) Energy-efficiency Measures of

More information

Renewable Electricity Procurement in California

Renewable Electricity Procurement in California Renewable Electricity Procurement in California June 25, 2012 Yuliya Shmidt Division of Ratepayer Advocates, California Public Utilities Commission National Association of Regulatory Utility Commissioners

More information

ENABLING EMBEDDED GENERATION

ENABLING EMBEDDED GENERATION APRIL 2014 ENABLING EMBEDDED GENERATION Turning Australian electricity on its head WHAT IS EMBEDDED GENERATION? Energy supply systems around the world are being transformed by embedded (or distributed)

More information

City of Solana Beach

City of Solana Beach City of Solana Beach City of Solana Beach Peer Review of Community Choice Aggregation Study April 6, 2017 Prepared by: 570 Kirkland Way, Suite 100 Kirkland, Washington 98033 A registered professional engineering

More information

AEP Ohio. Combined Heat and Power (CHP) May 24 th, 2017 Steve Giles Vice President Alternative Energy Hull & Associates, Inc.

AEP Ohio. Combined Heat and Power (CHP) May 24 th, 2017 Steve Giles Vice President Alternative Energy Hull & Associates, Inc. AEP Ohio Combined Heat and Power (CHP) May 24 th, 2017 Steve Giles Vice President Alternative Energy Hull & Associates, Inc. OUR MARKET AREAS Shale Oil & Gas Waste Management PROJECT DEVELOPMENT AND ASSET

More information

Self Generation Incentive Program (SGIP) Jason Legner Sr. Program Manager

Self Generation Incentive Program (SGIP) Jason Legner Sr. Program Manager 1 Self Generation Incentive Program (SGIP) Jason Legner Sr. Program Manager SGIP History Self Generation Incentive Program (SGIP) Statewide - California Public Utilities Commission (CPUC) incentive program

More information

West Monroe Partners April 2017

West Monroe Partners April 2017 West Monroe Partners April 2017 Executive Summary Background and Objectives Market and Regulatory Structure Stakeholder Overview Modeling Approach Impact Categories and Quantification Methods Scenarios

More information

PACIFICORP: PRIVATE GENERATION RESOURCE ASSESSMENT FOR LONG TERM PLANNING

PACIFICORP: PRIVATE GENERATION RESOURCE ASSESSMENT FOR LONG TERM PLANNING PACIFICORP: PRIVATE GENERATION RESOURCE ASSESSMENT FOR LONG TERM PLANNING AUGUST 30, 2018 1 DISCLAIMER Notice Regarding Presentation This presentation was prepared by Navigant Consulting, Inc. (Navigant)

More information

VALUING ROOFTOP SOLAR

VALUING ROOFTOP SOLAR INTRODUCTION NET ENERGY METERING VALUING ROOFTOP SOLAR ALTERNATIVES TO NEM 1 INTRODUCTION TURN DISTRIBUTED GENERATION 2 TURN A Consumer Advocacy Organization Fighting for Small Ratepayers since 1973 Founded

More information

SENATE, No STATE OF NEW JERSEY

SENATE, No STATE OF NEW JERSEY SENATE BUDGET AND APPROPRIATIONS COMMITTEE STATEMENT TO SENATE, No. 2314 STATE OF NEW JERSEY DATED: APRIL 5, 2018 The Senate Budget and Appropriations Committee reports favorably Senate Bill No. 2314.

More information

CAISO Generator Deliverability Assessment Methodology. On-Peak Deliverability Assessment Methodology (for Resource Adequacy Purposes)

CAISO Generator Deliverability Assessment Methodology. On-Peak Deliverability Assessment Methodology (for Resource Adequacy Purposes) Background On-Peak Deliverability Assessment Methodology (for Resource Adequacy Purposes) The CAISO s deliverability study methodology for resource adequacy purposes was discussed extensively in the CPUC

More information

Understanding Early Retirement of Combined Heat and Power (CHP) Systems: Going Beyond First Year Impacts Evaluations

Understanding Early Retirement of Combined Heat and Power (CHP) Systems: Going Beyond First Year Impacts Evaluations Understanding Early Retirement of Combined Heat and Power (CHP) Systems: Going Beyond First Year Impacts Evaluations ABSTRACT William Marin, Itron Inc. Myles O Kelly, Itron Inc. Kurt Scheuermann, Itron

More information

Cost-benefit Analysis of the New Jersey Clean Energy Program Energy Efficiency Programs

Cost-benefit Analysis of the New Jersey Clean Energy Program Energy Efficiency Programs Cost-benefit Analysis of the New Jersey Clean Energy Program Energy Efficiency Programs January 9, 2008 Table of Contents I. Summary...3 II. Methodology...4 III. Cost-Benefit Analysis Assumptions...6 IV.

More information

The Gambia National Forum on Renewable Energy Regulation: Policy Incentives and Enabling an Environment for Renewable Energy

The Gambia National Forum on Renewable Energy Regulation: Policy Incentives and Enabling an Environment for Renewable Energy The Gambia National Forum on Renewable Energy Regulation: Policy Incentives and Enabling an Environment for Renewable Energy Melicia Charles California Public Utilities Commission January 31, 2012 www.cpuc.ca.gov/puc/energy/distgen/

More information

Joint Workshop on Multiple-Use Applications and Station Power for Energy Storage CPUC Rulemaking and CAISO ESDER 2 Stakeholder Initiative

Joint Workshop on Multiple-Use Applications and Station Power for Energy Storage CPUC Rulemaking and CAISO ESDER 2 Stakeholder Initiative Joint Workshop on Multiple-Use Applications and Station Power for Energy Storage CPUC Rulemaking 15-03-011 and CAISO ESDER 2 Stakeholder Initiative Issue Paper May 2-3, 2016 April 14, 2016 Table of Contents

More information

Energy & Emissions Strategic Plan. Executive Summary. Encina Wastewater Authority. April Prepared for

Energy & Emissions Strategic Plan. Executive Summary. Encina Wastewater Authority. April Prepared for Energy & Emissions Strategic Plan Executive Summary April 2011 Prepared for Encina Wastewater Authority Executive Summary Section 1: Introduction The Encina Wastewater Authority (EWA) is a Joint Powers

More information

DISTRIBUTED GENERATION POTENTIAL STUDY FOR PENNSYLVANIA

DISTRIBUTED GENERATION POTENTIAL STUDY FOR PENNSYLVANIA ITC DISTRIBUTED GENERATION POTENTIAL STUDY FOR PENNSYLVANIA Prepared for: PENNSYLVANIA PUBLIC UTILITY COMMISSION Final Report March 2015 Prepared by: Statewide Evaluation Team Intentionally Left Blank

More information

Methodology for calculating subsidies to renewables

Methodology for calculating subsidies to renewables 1 Introduction Each of the World Energy Outlook scenarios envisages growth in the use of renewable energy sources over the Outlook period. World Energy Outlook 2012 includes estimates of the subsidies

More information

Costs and Benefits of Combined Heat and Power

Costs and Benefits of Combined Heat and Power Costs and Benefits of Combined Heat and Power June 19, 2013 Draft v.2 With minor modifications to the presentation made to the NJ CHP/FC Working Group on 19 June 2013 (marked in red) Center for Energy,

More information

Energy Trust Electric and Gas Avoided Cost Update for Oregon for 2018 Measure and Program Planning

Energy Trust Electric and Gas Avoided Cost Update for Oregon for 2018 Measure and Program Planning Energy Trust Electric and Gas Avoided Cost Update for Oregon for 2018 Measure and Program Planning August 8, 2017 Energy Trust s estimates of future electric and gas avoided costs are critical assumptions

More information

Distributed Generation in the Ontario Regulatory Context

Distributed Generation in the Ontario Regulatory Context Distributed Generation in the Ontario Regulatory Context Distributed Generation and the Future of Ontario 's Electricity Grid October 27, 2008 James C. Sidlofsky Partner, Borden Ladner Gervais LLP Chair,

More information

Amended Supplemental Testimony of Southern California Edison Company Regarding Forecast GHG Reductions and Cost Savings Resulting from Default TOU

Amended Supplemental Testimony of Southern California Edison Company Regarding Forecast GHG Reductions and Cost Savings Resulting from Default TOU Application No.: Exhibit No.: Witnesses: 1-1-0 et al. SCE-0-A Y. Liang (U -E) Amended Supplemental Testimony of Southern California Edison Company Regarding Forecast GHG Reductions and Cost Savings Resulting

More information

Waste Heat and Carbon Emissions Reduction

Waste Heat and Carbon Emissions Reduction Waste Heat and Carbon Emissions Reduction This Act is based on California law. Under California law, the State Energy Resources Conservation and Development Commission (Energy Commission) is charged with

More information

Viewpoint. Renewable portfolio standards and cost-effective energy efficiency investment

Viewpoint. Renewable portfolio standards and cost-effective energy efficiency investment Viewpoint Renewable portfolio standards and cost-effective energy efficiency investment A. Mahone a, C.K. Woo a,b*, J. Williams a, I. Horowitz c a Energy and Environmental Economics, Inc., 101 Montgomery

More information

California Development of DG Standby Rates and Exit Fees

California Development of DG Standby Rates and Exit Fees California Development of DG Standby Rates and Exit Fees Midwest CHP Initiative Distributed Generation Tariff Workshop St. Paul, Minnesota Scott Tomashefsky California Energy Commission May 14, 2003 California

More information

SCE-01. Exhibit No.: Witness: 338-E) Edison. Before the. November 1, 2012

SCE-01. Exhibit No.: Witness: 338-E) Edison. Before the. November 1, 2012 Application No.: Exhibit No.: Witness: A.1-0-001 SCE-01 Russelll Garwacki (U -E) Revised Rebuttal Testimony of Southern California Edison Company (U -E) Regarding Pacific Gas and Electric Compan y s Application

More information

An Overview of Eligible SGIP Technologies. March 10, 2010

An Overview of Eligible SGIP Technologies. March 10, 2010 An Overview of Eligible SGIP Technologies March 10, 2010 Outline SGIP Requirements for Fuel Cells and Fuel Cell Performance SGIP Requirements Wind Turbines and Wind Turbines Performance Advance Energy

More information

The Impacts of the Green Communities Act on the Massachusetts Economy:

The Impacts of the Green Communities Act on the Massachusetts Economy: The Impacts of the Green Communities Act on the Massachusetts Economy: A Review of the First Six Years of the Act s Implementation Paul J. Hibbard Susan F. Tierney Pavel G. Darling Analysis Group, Inc.

More information

BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA

BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA Order Instituting Rulemaking to Oversee ) the Resource Adequacy Program, Consider ) Program Refinements, and Establish Annual ) Rulemaking

More information

Independent Assessment of Conservation and Energy Efficiency Potential for Connecticut and the Southwest Connecticut Region FINAL REPORT June 2004

Independent Assessment of Conservation and Energy Efficiency Potential for Connecticut and the Southwest Connecticut Region FINAL REPORT June 2004 Table of Contents 1.0 EXECUTIVE SUMMARY...1 1.1 Study Scope...1 1.2 Key Findings...2 1.3 Future Program Investment Scenarios...6 1.4 Present Value of Savings and Costs (in millions of 2003 $)...6 1.5 Definition

More information

Distributed PV the road California is already on. PIELC Bill Powers, P.E., Powers Engineering March 5, 2011

Distributed PV the road California is already on. PIELC Bill Powers, P.E., Powers Engineering March 5, 2011 Distributed PV the road California is already on PIELC Bill Powers, P.E., Powers Engineering March 5, 2011 1 John Geesman, Energy Commissioner, 2007 source: California Energy Circuit, State Sees DG Providing

More information

A TOOL TO MARKET CUSTOMER-SITED SMALL WIND SYSTEMS

A TOOL TO MARKET CUSTOMER-SITED SMALL WIND SYSTEMS A TOOL TO MARKET CUSTOMER-SITED SMALL WIND SYSTEMS Tony Jimenez, Ray George, Trudy Forsyth National Renewable Energy Laboratory 1617 Cole Blvd./3811 Golden, CO 80401 USA Thomas E. Hoff Clean Power Research

More information

BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA CLEAN COALITION COMMENTS ON INTERIM STAFF REPORT AND ENERGY STORAGE WORKSHOPS

BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA CLEAN COALITION COMMENTS ON INTERIM STAFF REPORT AND ENERGY STORAGE WORKSHOPS BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA Order Instituting Rulemaking Pursuant to Assembly Bill 2514 to Consider the Adoption of Procurement Targets for Viable and Cost-Effective

More information

SB 843 (WOLK) Community Based Renewable Energy Self Generation Program. Utility & Policy Maker Frequently Asked Questions

SB 843 (WOLK) Community Based Renewable Energy Self Generation Program. Utility & Policy Maker Frequently Asked Questions SB 843 (WOLK) Community Based Renewable Energy Self Generation Program Utility & Policy Maker Frequently Asked Questions What problem is SB 843 addressing? Access to renewable energy. The bill allows for

More information

Economic Analysis of Large Stationary Fuel Cell Value in California

Economic Analysis of Large Stationary Fuel Cell Value in California Economic Analysis of Large Stationary Fuel Cell Value in California ICEPAG 2009 February 10, 2009 Newport Beach, California Lori Smith Schell, Ph.D. February 10, 2009 1 Economic Analysis Can Inform Policy

More information

Net Energy Metering (NEM) Strategy Recommendations a. NEM Export Adder

Net Energy Metering (NEM) Strategy Recommendations a. NEM Export Adder February 7, 2018 East Bay Community Energy 1111 Broadway, 3rd Floor Oakland, CA 94607 Via Email Submission to LDBPcomments@ebce.org Re: Comments on East Bay Community Energy s Draft Local Development Business

More information

Laura Genao Director of Regulatory Affairs Southern California Edison May 18, 2012

Laura Genao Director of Regulatory Affairs Southern California Edison May 18, 2012 Laura Genao Director of Regulatory Affairs Southern California Edison May 18, 2012 1 Overview of SCE One of the nation s largest electric utilities Nearly 14 million residents in service territory and

More information

Distributed Generation

Distributed Generation Distributed Generation November 2014 November 6, 2014 1 Forward-Looking Statements Leading the Way in Electricity SM Statements contained in this presentation about future performance, including, without

More information

PREPARED DIRECT TESTIMONY OF JEFF HUANG SAN DIEGO GAS & ELECTRIC COMPANY AND SOUTHERN CALIFORNIA GAS COMPANY

PREPARED DIRECT TESTIMONY OF JEFF HUANG SAN DIEGO GAS & ELECTRIC COMPANY AND SOUTHERN CALIFORNIA GAS COMPANY Application No: A.1-0- Exhibit No.: Witness: Jeff Huang Application of Southern California Gas Company (U 0 G) and San Diego Gas & Electric Company (U 0 G) for Authority to Revise their Natural Gas Rates

More information

Distribution System Planning. Introduction and Overview Chris Villarreal <Month> <Day>, 2017

Distribution System Planning. Introduction and Overview Chris Villarreal <Month> <Day>, 2017 Distribution System Planning Introduction and Overview Chris Villarreal , 2017 1 Solar and wind costs declining Source: GTM Research and Wood Mackenzie 2 Source: Lazard s Levelized Cost of

More information

MEMORANDUM DATE: OCTOBER 4, 2006 APPROVAL OF ULTRA-CLEAN LOCAL DISTRIBUTED GENERATION INCENTIVE PROGRAM GUIDELINES

MEMORANDUM DATE: OCTOBER 4, 2006 APPROVAL OF ULTRA-CLEAN LOCAL DISTRIBUTED GENERATION INCENTIVE PROGRAM GUIDELINES MEMORANDUM TO: FROM: UTILITIES ADVISORY COMMISSION UTILITIES DEPARTMENT DATE: OCTOBER 4, 2006 TITLE: APPROVAL OF ULTRA-CLEAN LOCAL DISTRIBUTED GENERATION INCENTIVE PROGRAM GUIDELINES REQUEST Staff requests

More information

Distributed Generation Certified Professional (DGCP) Study Guide & Sample Questions

Distributed Generation Certified Professional (DGCP) Study Guide & Sample Questions Distributed Generation Certified Professional (DGCP) Study Guide & Sample Questions The following is a list of the subjects for DGCP examination. Each subject covers a number of topics. Following the list

More information

Making the Case for Energy Efficiency Policy Support: Results from the EPA / DOE Energy Efficiency Benefits Calculator

Making the Case for Energy Efficiency Policy Support: Results from the EPA / DOE Energy Efficiency Benefits Calculator Making the Case for Energy Efficiency Policy Support: Results from the EPA / DOE Energy Efficiency Benefits Calculator Snuller Price, Energy and Environmental Economics, Inc. Katrina Pielli and Stacy Angel,

More information

SOLAR VALUATION & COST/BENEFIT ANALYSES

SOLAR VALUATION & COST/BENEFIT ANALYSES SOLAR VALUATION & COST/BENEFIT ANALYSES Workshop for Utah Municipal Utilities Presented by: Jim Lazar and John Shenot Regulatory Assistance Project May 11, 2017 ROOFTOP SOLAR WORKSHOPS FOR UTAH MUNICIPAL

More information

DEMAND-SIDE MANAGEMENT MARKET POTENTIAL STUDY. Final Report. Volume 5: Distributed Generation Analysis. Prepared for: Ameren Missouri

DEMAND-SIDE MANAGEMENT MARKET POTENTIAL STUDY. Final Report. Volume 5: Distributed Generation Analysis. Prepared for: Ameren Missouri DEMAND-SIDE MANAGEMENT MARKET POTENTIAL STUDY Volume 5: Distributed Generation Analysis Final Report EnerNOC Utility Solutions Consulting 500 Ygnacio Valley Road Suite 450 Walnut Creek, CA 94596 925.482.2000

More information

CHAPTER 3: RESOURCE STRATEGY

CHAPTER 3: RESOURCE STRATEGY Seventh Northwest Conservation and Electric Power Plan CHAPTER 3: RESOURCE STRATEGY Contents Key Findings... 3 A Resource Strategy for the Region... 3 Summary... 3 Scenario Analysis The Basis of the Resource

More information

Phase 2 of 2015 General Rate Case Revenue Allocation Proposals

Phase 2 of 2015 General Rate Case Revenue Allocation Proposals Application No.: Exhibit No.: Witnesses: A.1-0-XXX SCE-0 R. Pardo R. Thomas (U -E) Phase of 01 General Rate Case Revenue Allocation Proposals Before the Public Utilities Commission of the State of California

More information

MAXIMUM ACHIEVABLE POTENTIAL FOR GAS DSM IN UTAH FINAL REPORT JUNE Table of Contents

MAXIMUM ACHIEVABLE POTENTIAL FOR GAS DSM IN UTAH FINAL REPORT JUNE Table of Contents Table of Contents 1.0 EXECUTIVE SUMMARY UTAH GAS DSM POTENTIAL...1 1.1 Types of Savings Potential Analyzed...1 1.2 Key Findings...2 1.3 Future Program Investment Scenarios...5 1.4 Present Value of Savings

More information

Phase 2 of 2018 General Rate Case Revenue Allocation Proposals

Phase 2 of 2018 General Rate Case Revenue Allocation Proposals Application No.: Exhibit No.: Witnesses: A.1-0-XXX SCE-0 R. Pardo R. Thomas (U -E) Phase of 01 General Rate Case Revenue Allocation Proposals Before the Public Utilities Commission of the State of California

More information

11. Stakeholder Process

11. Stakeholder Process Ameren Missouri Highlights Ameren Missouri conducts an inclusive stakeholder process to solicit feedback on its assumptions and analysis methods. Ameren Missouri hosted a stakeholder meeting in February

More information

The Superior Value of Distribution-interconnected Generation

The Superior Value of Distribution-interconnected Generation The Superior Value of Distribution-interconnected Generation Summary: The cost of delivering energy from the point it is interconnected to the grid to the point that it is consumed by a customer can be

More information

PV Valuation Methodology

PV Valuation Methodology PV Valuation Methodology Recommendations for Regulated Utilities in Michigan February 23, 2016 Prepared for: Midwest Renewable Energy Association Prepared by: Ben Norris, Clean Power Research Legal Notice

More information

PASADENA WATER AND POWER MEMORANDUM. August 9, 2016

PASADENA WATER AND POWER MEMORANDUM. August 9, 2016 PASADENA WATER AND POWER MEMORANDUM August 9, 2016 To: Environmental Advisory Committee From: Gurcharan Bawa Interim General Manager Subject: Pasadena Solar Program Updates This report is for information

More information

Calculation of Demand Curve Parameters

Calculation of Demand Curve Parameters Calculation of Demand Curve Parameters Rationale 4.1 Resource adequacy standard 4.1.1 The resource adequacy standard announced by the Government of Alberta prescribes a minimum level of reliability as

More information

CPUC Self-Generation Incentive Program. Optimizing Dispatch and Location of Distributed Generation

CPUC Self-Generation Incentive Program. Optimizing Dispatch and Location of Distributed Generation CPUC Self-Generation Incentive Program Optimizing Dispatch and Location of Distributed Generation Submitted to: PG&E and The Self-Generation Incentive Program Working Group Prepared by: Itron, Inc. 60

More information

BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA

BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA Order Instituting Rulemaking to Develop a Successor to Existing Net Energy Metering Tariffs Pursuant to Public Utilities Code Section 2827.1,

More information

Revised Overview of PV Inputs, Data Sources, and Potential Study Results

Revised Overview of PV Inputs, Data Sources, and Potential Study Results Date: September 28, 2012 To: From: Re: PacifiCorp Revised Overview of PV Inputs, Data Sources, and Potential Study Results Introduction, under contract to PacifiCorp, has calculated the predicted technical

More information

Recommendations for Reforming Energy Efficiency Cost-Effectiveness Screening in the United States

Recommendations for Reforming Energy Efficiency Cost-Effectiveness Screening in the United States Recommendations for Reforming Energy Efficiency Cost-Effectiveness Screening in the United States Using the Resource Value Framework to Identify Those Efficiency Programs That Are in the Public Interest

More information

Data responses are posted at

Data responses are posted at Benefit-Cost Analyses Docket 4780 Second Set of Data Requests From the Division of Public Utilities to National Grid January 8, 2018 2-1. Please provide a qualitative description for each of the ways that

More information

Real Options Application Portfolio:

Real Options Application Portfolio: Real Options Application Portfolio: Sizing a Pulverized Combustion Boiler Power Plant and Determining When to Add Carbon Capture Technology to the Plant December 10, 2005 ESD.71 Professor deneufville Konstantinos

More information

2014 Self-Generation Incentive Program HANDBOOK

2014 Self-Generation Incentive Program HANDBOOK Self-Generation Incentive Program 2014 Self-Generation Incentive Program HANDBOOK Provides financial incentives for installing clean, efficient, on-site distributed generation January 1, 2014 V.1 What

More information

STATE OF VERMONT PUBLIC UTILITY COMMISSION

STATE OF VERMONT PUBLIC UTILITY COMMISSION STATE OF VERMONT PUBLIC UTILITY COMMISSION Case No. --INV Investigation into the petition of Green Mountain Power Corporation's tariff filing requesting an overall rate increase in the amount of.%, to

More information

BEFORE THE PUBLIC UTILITY COMMISSION OF OREGON. In February of 2015, the Oregon Public Utility Commission (OPUC) opened Docket No.

BEFORE THE PUBLIC UTILITY COMMISSION OF OREGON. In February of 2015, the Oregon Public Utility Commission (OPUC) opened Docket No. BEFORE THE PUBLIC UTILITY COMMISSION OF OREGON UM 1716 In the Matter of ) ) OREGON PUBLIC UTILITY COMMISSION ) PORTLAND GENERAL ELECTRIC S COMMENTS ON STAFF SCOPING DOCUMENT Investigation to Determine

More information

Demystifying Rooftop Solar

Demystifying Rooftop Solar Demystifying Rooftop Solar Week 4 : Economics OLLI at Illinois Study Group Fall 2017 1:30 pm Tuesdays Blue Room Proposed Session Outline 1. Overview of solar power in general. How PV works with demos.

More information

Feed-in Tariffs in Oregon and Vermont

Feed-in Tariffs in Oregon and Vermont Feed-in Tariffs in Oregon and Vermont Lisa Schwartz NARUC Energy Resources and the Environment Committee July 19, 2010 The Regulatory Assistance Project China EU India United States About the Regulatory

More information

Outline. Introduction to Wisconsin. Barriers to Generating Electricity from. Incentives and Regulations Intended to

Outline. Introduction to Wisconsin. Barriers to Generating Electricity from. Incentives and Regulations Intended to Experience of the United States in the Application of Incentives and Regulations for the Supply of Renewable Energy Chairperson Eric J. Callisto Public Service Commission of Wisconsin 20 May 2010 Outline

More information

SELF-GENERATION INCENTIVE PROGRAM

SELF-GENERATION INCENTIVE PROGRAM SELF-GENERATION INCENTIVE PROGRAM RETENTION STUDY M&E COMMITTEE REVIEW DRAFT SELF-GENERATION INCENTIVE PROGRAM RETENTION STUDY Submitted To: PG&E M&E Project Manager Betsy Wilkins and M&E Committee of

More information

Survey of Modeling Capabilities and Needs for the Stationary Energy Storage Industry

Survey of Modeling Capabilities and Needs for the Stationary Energy Storage Industry Survey of Modeling Capabilities and Needs for the Stationary Energy Storage Industry Prepared for: Energy Storage Association 1155 15th Street, NW Suite 500 Washington, DC 20005 202.293.0537 energystorage.org

More information

2013 Self-Generation Incentive Program HANDBOOK

2013 Self-Generation Incentive Program HANDBOOK Self-Generation Incentive Program 2013 Self-Generation Incentive Program HANDBOOK Provides financial incentives for installing clean, efficient, on-site distributed generation February 1, 2013 V.1 What

More information

BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA (NOT CONSOLIDATED) And Related Matters. Application Application

BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA (NOT CONSOLIDATED) And Related Matters. Application Application BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA Order Instituting Rulemaking Regarding Policies, Procedures and Rules for Development of Distribution Resources Plans Pursuant to Public

More information

TREASURE COAST REGIONAL PLANNING COUNCIL M E M O R A N D U M. To: Council Members AGENDA ITEM 8

TREASURE COAST REGIONAL PLANNING COUNCIL M E M O R A N D U M. To: Council Members AGENDA ITEM 8 TREASURE COAST REGIONAL PLANNING COUNCIL M E M O R A N D U M To: Council Members AGENDA ITEM 8 From: Date: Subject: Staff February 20, 2009 Council Meeting Report on Florida Renewable Energy Potential

More information

Recommendations on the TPP policy and economic assessment by TPP topic

Recommendations on the TPP policy and economic assessment by TPP topic Public Advocates Office California Public Utilities Commission 505 Van Ness Avenue San Francisco, California 94102 Tel: 415-703-1584 www.publicadvocates.cpuc.ca.gov COMMENTS OF THE PUBLIC ADVOCATES OFFICE

More information