PUBLIC CONSULTATION AND DISCLOSURE PLAN AZERI, CHIRAG & GUNASHLI (ACG) PHASE 3 PROJECT REV 0
|
|
- Holly McCarthy
- 5 years ago
- Views:
Transcription
1 AZERI, CHIRAG & GUNASHLI (ACG) PHASE 3 PROJECT REV 0 July 2003
2
3 TABLE OF CONTENTS 1. INTRODUCTION PROJECT DESCRIPTION ACG PHASE ACG Contract Area and Field Development The ACG Phase 3 Project Description REQUIREMENTS FOR CONSULTATION & DISCLOSURE Introduction National Requirements for Consultation & Disclosure The EIA Handbook INVENTORY OF STAKEHOLDERS AIOC Stakeholder Identification and Analysis Process ACG Phase 3 Project Stakeholder Inventory Scoping Consultation REVIEW OF PREVIOUS CONSULTATION UNDERTAKEN IN RELATION TO THE PROJECT Introduction Key Issues Identifed from the Review Integration of Project and Operations Activities & Initiatives Resolution of Prior ACG Project Commitments Extension of the Geographical Scope of the Community-based Consultation Stakeholder Fatigue PROGRAMME AND SCHEDULE OF CONSULTATION & DISCLOSURE ACTIVITIES IN RELATION TO ESIA STAGES AND PROJECT IMPLEMENTATION Summary of Types of Methods to be Used Schedule of Consultation Activities & Plan for Integration with ESIA & Project Activities Allocated Budget for the ACG Phase 3 ESIA Consultation Management of Media Publicity Management and Staff Resources Allocated to the Plan Tasks EVALUATION CRITERIA FOR ASSESSING PCDP EFFECTIVENESS...23
4
5 1. INTRODUCTION This document outlines the public consultation and disclosure plan (PCDP) for the ACG Phase 3 project. It has been developed in the context of the ongoing consultation programme for the ACG full field development that commenced prior to the Phase 3 ESIA process and will continue throughout the life of the project. The PCDP defines a technically and culturally appropriate approach to consultation and disclosure for the project. It demonstrates the links between consultation and the project decision-making process and makes the most appropriate use of existing initiatives and communication mechanisms employed by AIOC. The scope of this plan reflects local circumstances, in particular, the previous experience of the stakeholders with respect to oil and gas exploration and production (E&P) activities related to the ACG development and with other international E&P projects. The goals of the PCDP are to ensure that: the project team clearly understands what consultation is and why this is important; the scope of the consultation programme and the roles and responsibilities of project personnel are clearly defined and understood; and stakeholders fully understand the decision-making process and the means by which they can be involved. To this effect the plan sets out to further ensure that: adequate and timely information is provided to project-affected stakeholders; these stakeholders are given sufficient opportunity to voice their opinions and concerns; and these concerns influence project decisions. A number of activities and outputs, against specific timescales and assigned responsibilities, required in order to achieve these goals, are presented in the PCDP. These will form the basis for evaluating the performance and effectiveness of this PCDP. This document is a working document that will need to be updated routinely as information is received and the positions and interests of stakeholders are clarified. This PCDP is linked to key internal AIOC information sources that are of material relevance. These include inter alia: The ACG Phase 3 FEED Team Option Analysis Reports and ENVIID Registers & associated Action Tracking documentation; The Government and Public Relations (GPR) Stakeholder Analysis Database; The GPR Database of articles published in the Media; The GPR Database of Holding Statements; The ESIA Team Database of consultation records (including records for Phases 1, 2 and 3); The Sangachal Terminal Expansion Project (STEP) Database of community based consultation records for Sangachal Village and Umid Settlement; 1
6 Commitments Register and Monitoring Register for the ACG Project (based on Phases 1 and 2 ESIAs); and Community Relations Plan for the Phase 1 ACG project. Together with the activities and outputs proposed in this PCDP these information sources provide an effective basis for a transparent issue identification and management process that is essential for the implementation of the Public Consultation and Disclosure Process. 2
7 2. PROJECT DESCRIPTION ACG PHASE ACG Contract Area and Field Development The Azeri, Chirag and Deep Water Gunashli (ACG) Contract Area has estimated oil reserves in excess of 5.2 billion barrels. It lies in the Azerbaijan sector of the Caspian Sea, approximately 120 km south east of Baku. The Contract Area covers an area of 432 square kilometers in water depths ranging from 100 m to 400 m (Figure 1). Figure 1 The Location of the ACG Contract Area A Production Sharing Agreement (PSA) was signed in 1994 between the State Oil Company of the Azerbaijan Republic (SOCAR) and the Azerbaijan International Operating Company (AIOC), a consortium of foreign oil companies. The Agreement grants the consortium rights to develop and manage the hydrocarbon reserves found in the ACG field. In 1999 BP was appointed operator of AIOC. AIOC is in the process of developing the ACG oil field. Work first began in 1995, culminating in oil production from the Chirag field in 1997 (the Early Oil Project). AIOC is continuing with the development of the Central area of the Azeri field (ACG Phase 1 Project with first oil production is scheduled for late 2004), and the West and East areas of the Azeri field (ACG Phase 2 Project, with first oil production planned for 2006). Both phases of development have been subject to Environmental and Social Impact Assessments (ESIAs) and Environmental Statements have been disclosed locally and internationally. The ACG Phase 1 and the Phase 2 ESIAs are now approved by the Azerbaijan Ministry of Ecology and Natural Resources (MENR). The ACG Phase 3 project completes ACG full field development. It is expected that Phase 3, together with the Early Oil Project and Phases 1 & 2, will achieve plateau production of around 1MMbd by
8 ACG Phase 3 will develop the Deep Water Gunashli field, and will also carry some preinvestment should the option be exercised at a later date to place a development in the West Chirag Field. ACG aims to achieve first oil production by early 2008 (Figure 2) Phase3 8 Early Oil Deep Water Chirag Gunashli /West Chirag 2006 Phase2 West Azeri 2004 Phase1 Central Azeri 2007 Phase 2 East Azeri Figure 2 Development of Azeri, Chirag and Gunashli Oil Field 2.2 The ACG Phase 3 Project Description The Base Case offshore field development concept for the Phase 3 project consists, of a Production, Drilling, Utilities & Quarters (PDUQ) platform, located in Deep Water Gunashli, with a bridge-linked gas export Compression and Water-injection Platform (C&WP). The facilities will be broadly similar to those installed for Phase 1, however, work is currently ongoing to evaluate opportunities to reconfigure and optimize topside design for both platforms. The oil and gas is expected to be exported to shore via new infield flow-lines and the existing pipelines laid as part of the Early Oil Project and Phases 1 and 2 (Figure 3). Sangachal Terminal 2008 Phase 3 DWG 1997 Early Oil Chirag 2006 Phase 2 West Azeri 2005 Phase 1 Central Azeri 2007 Phase 2 East Azeri 2x800mbbl storage tanks?? 24 oil pipeline 2 x 30 oil pipelines +? 28 gas pipeline Figure 3 The Azeri, Chirag and Deep Water Gunashli Full Field Development as conceived at the present time 4
9 Table 1 Onshore the ACG Phase 3 project will include expansion of the existing Sangachal Terminal (Figure 4). The expansion will involve the installation of two additional trains of oil, gas and water separation and stabilization plant, together with associated power and utilities systems and the provision of oil storage and cross connections into the produced water system. Export routes for the oil include the Western Route Pipeline, Northern Route Pipeline, and Baku-Tblisi-Ceyhan Pipeline. A programme of drilling using the mobile drilling rig, the Dada Gorgud, is planned to commence in 2006 and last around a year. Construction of the platforms and terminal expansion will likely begin in If the platforms are constructed within Azerbaijan, some upgrade to existing yards may be required before construction can commence. First oil production is planned for late It is currently anticipated that platform wells will be drilled from 2008 onwards. These will comprise production, and water injection wells and one further cuttings injection well. The Production Sharing Agreement allows AIOC the right to produce oil until 2024, after which time the facilities will be handed to the State Oil Company of the Azerbaijan Republic. The Phase 3 Project has developed a milestone schedule (summarized in Table 1 below) to meet its target first oil date. ACG Phase 3 Project Milestones Description Front End Engineering Design (FEED) start August 2003 Project sanction July 2004 Start fabrication 4Q 2004 Commence pre-drilling wells 2Q 2006 First platform topsides installed 2Q 2007 Second platform topsides installed 4Q 2007 First Production (Oil at Wellhead) 4Q 2007 In order to achieve this schedule AIOC will submit an Environmental Statement for the ACG Phase 3 Project to the Ministry of Ecology and Natural Resources (MENR) in mid Allowing for a 60-day Public Disclosure period and incorporation of MENR and other stakeholder comments, a decision on approval is anticipated in 3Q
10 T ACG Phase 3 ACG and SD Flare Area ACG Phase 2 Azeri ACG Phase 1 Azeri BTC Phase 3 Azeri Azeri 1300 m Shah Deniz SD Power Island EOP Terminal 2080 m Figure 4 The Various Development Phases of the Sangachal Terminal 6
11 3. REQUIREMENTS FOR CONSULTATION & DISCLOSURE 3.1 Introduction Communication with organisations, groups and individuals (known collectively as the stakeholders) is an important part of the way that the Azerbaijan International Operating Company (AIOC) conducts its business. Communication with the project stakeholders is an essential component of any environmental and socio-economic assessment (ESIA) process. Through its communication programme for the ACG development AIOC seeks the views of interested or affected stakeholders through engaging them in two-way dialogue. AIOC can then apply the local knowledge learned through this feed back process to the evaluation of alternatives to proposed activities and resolution of and /or avoidance of potential conflicts. Such an approach can assist in developing a cooperative relationship between AIOC and its stakeholders, facilitate stakeholder ownership and acceptability of AIOC s proposals and limit unrealistic expectations. AIOC is committed to active and ongoing communication with all stakeholders regarding the ongoing ACG Full Field Development (FFD) activities and the proposed ACG Phase 3 project activities AIOC is committed to maintaining the same standard of consultation across the ACG FFD development. As such the consultation programme for Phase 3 will be conducted with specific reference to the relevant international finance organization guidelines and standards (i.e. IFC and EBRD) that were applied during earlier phases. In addition the requirements of relevant international conventions (eg. the Espoo and Aarhus Conventions), European Community Directives and national regulations will be applied. The requirements of the relevant international finance organizations, the European Directives and International Conventions of specific relevance for consultation are outlined in the Phase 1 and Phase 2 PCDPs, and have not been reproduced here. 3.2 National Requirements for Consultation & Disclosure The EIA Handbook National requirements for public participation in ESIA are outlined in the Handbook for the Environmental Impact Assessment Process in Azerbaijan 1996, which was developed with the support of the United Nations Development Programme. The EIA Handbook includes definition of the legal requirements for public participation, outlines the opportunities for public to be involved in the process of decision-making, and recommends public information mechanisms. The main regulating environmental body is the Ministry of Environment and Natural Resources (MENR), recently formed from the merger of four state organizations comprising the State Committee for Ecology, State Committee for Hydrometeorology, State Forestry Committee and the Sate Committee for Geology. The MENR is responsible for setting up an expert panel (Environmental Review Expert Group) to review and approve an EIA. 7
12 The EIA Handbook defines public as anyone who is in any way affected by the proposal or has a genuine interest in it. This includes local residents living in the vicinity of the project area, individuals who have their interest in the project, community groups, professional organizations, and industries and enterprises. In some cases, government agencies that participate in the EIA process may also be considered part of the general public. The most important requirement that ensures effective public participation is for AIOC to inform the public about the project at an as early stage of the project as possible. An effective feedback system is required to ensure that the public has not only been consulted but that their opinion will be acknowledged and accounted for. It is the responsibility of the Environmental Review Expert Group to collect and document feedback and provide copies to AIOC. In practice BP/AIOC have taken on this process of consultation and feedback. The EIA Handbook recommends effective ways for the public to be involved in the environmental decision-making. The most effective means of expressing concern, support, or general opinion about the project is by means of written submission. Other recommended means of public participation include discussion forums about particular technical aspects of the project, live television debates and radio discussions. It is pointed out in the EIA Handbook that the most powerful information document is a written submission. In the case of an EIA there are two documents which provide public information. The first document is the Environmental Statement prepared by AIOC, the second document is that produced by the Environmental Review Expert Group. Both documents must be made available to the public. In addition to these project specific documents, the public is also encouraged to draw general environmental information from the State of the Environment Report for Azerbaijan, and other various sources including environmental atlases and the media. Finally, the EIA Handbook stresses the importance of enabling the public to receive the information that they believe they need. 8
13 4. INVENTORY OF STAKEHOLDERS 4.1 AIOC Stakeholder Identification and Analysis Process AIOC already has an established programme of stakeholder consultation in Azerbaijan. The goal of the ACG Phase 3 Project is therefore to build on the work already undertaken. At the time of writing, the AIOC Government and Public Relations (GPR) department, in collaboration with the AIOC HSE department, are progressing a stakeholder identification and analysis process. The key purpose of this process is to bring together the knowledge held by individuals throughout AIOC on both the primary stakeholders (i.e. those directly affected by the project) and the secondary stakeholders (i.e. those not directly affected, but whom may have an influence, interest or expertise to offer). The objective is to classify the stakeholders with respect to their attitude, importance, influence and key area of interest, in order to assist in the process of prioritizing consultation; and to identify both existing and potential opportunities for partnerships and collaboration. It is anticipated that the output from this process will also provide an indication of whether or not and by what means AIOC has previously liaised with specific individuals, organizations and focus groups. The inventory of stakeholders will include those at the local, national and international levels. This GPR led initiative will consolidate the knowledge and lessons learned about AIOC s stakeholders from previous phases of the ACG project, in addition to drawing on external resources such as local NGO directories. The output from this process will form the key linked resource to this section of the PCDP, when available. A second key linked resource to this section of the PCDP is the records on communitybased consultation at the Sangachal Village and Umid Settlement held and managed by the Sangachal Terminal Expansion Project (STEP) Community Liaison Officer. 4.2 ACG Phase 3 Project Stakeholder Inventory Whilst the GPR stakeholder analysis is ongoing, the Phase 3 stakeholder inventory has been based on the inventory built for Phase 1 & 2 (see below), and will be used to develop a database of stakeholders and relevant profile information for each stakeholder Scoping Consultation For the purpose of identifying the key stakeholder groups to be consulted, for the scoping phase of the ACG Phase 3 project ESIA, particular reference was made to the ACG Phase 1 and Phase 2 project consultation summary documents and stakeholder lists. Further clarification was sought through interviews with key AIOC personnel both within the GPR department and within the HSE department, who had previously been involved in the ACG project ESIA consultation process. Additional advice was also sought from the Sangachal Terminal Expansion Project (STEP) HSE team on the appropriate community representatives to consult. Notably, the Scoping consultations focused on community representatives within Umid Settlement and Sangachal Village. However, the potential need to widen the geographical scope of the community-based consultation programme was identified, which will necessarily result in the identification of new project stakeholders (see Section below). Overall, greater emphasis was given to the community based consultation within the scoping 9
14 consultation programme for the ACG Phase 3 project compared to the programmes for the ACG Phase 1 and 2 projects. This was facilitated through the collaboration with the STEP HSE team that enabled the integration of the consultation activities into their ongoing community liaison initiative. The inventory of stakeholders consulted during the ACG Phase 3 ESIA scoping phase, together with the issues raised and method of consultation, will be provided in the ACG Phase 3 Scoping Report. 10
15 5. REVIEW OF PREVIOUS CONSULTATION UNDERTAKEN IN RELATION TO THE PROJECT 5.1 Introduction To date consultation programmes have already been undertaken for previous phases of the ACG Field Development programme including the Early Civils Engingering Work Programme, Early Template Well ESIA, Regional Seismic ESIA, Early Oil and ACG Phases 1 & 2 ESIAs. A detailed review is presented in the Phase 1 PCDP and has not been reproduced here. The lessons learned from these consultations, from a review of the Phase 2 consultation programme, and consultation initiatives since the submission of the Phase 2 ESIA, have been drawn on in the development of the consultation programme for ACG Phase 3 ESIA process. 5.2 Key Issues Identifed from the Review The key issues for the ACG Phase 3 project ESIA consultation programme, identified as a consequence of this review, are presented below Integration of Project and Operations Activities & Initiatives For the ACG Phase 3 project the opportunities for undertaking community based consultations have increased significantly compared to previous phases of the project. This is as a consequence of the establishment of a community liaison programme and social investment/community development programmes for the communities in the immediate vicinity of the Sangachal Terminal site. This has resulted in regular interaction between the ACG project personnel, especially the terminal staff, and the local communites. Further, since there are ongoing project and operational activities running concurrently with the ACG Phase 3 ESIA process, it will be essential to integrate and co-ordinate the ACG Phase 3 ESIA consultation activities and initiatives with those of the other phases of the ACG project. This requirement is further supported through preliminary discussions with the Terminal Manager and the Community Liaison Officer during which they indicated that many local individuals do not distinguish project 'phases' and see only one big project. Thus, given the continuing framework of consultation (on many issues) between the terminal management and local communities it has been decided that the ACG Phase 3 ESIA consultations will be more effective if they were to occur within this framework, with the terminal team assisting with the consultations. This approach should avoid any misunderstandings arising from external unknown individuals, who lack knowledge of the issues and their context, seeking information from consultees alone Resolution of Prior ACG Project Commitments The ACG Phase 3 project is the final phase of the Full Field Development, and as such stakeholders will be looking for this phase to provide a status on the resolution of commitments made during previous phases of the project Extension of the Geographical Scope of the Community-based 11
16 Consultation AZERI, CHIRAG & GUNASHLI FULL FIELD DEVELOPMENT PHASE 3 A need has been identified to extend the geographical scope of the consultation programme beyond the Umid Settlement, Sangachal Village, and Sahil Town, to the wider Garadag region. It is anticipated that this wider geographical area will encompass a higher proportion of the employment and supporting services catchment for the project activities. The potential need to extend the geographical scope of the consultation programme has also been identified for a number of specific options, currently under consideration for the ACG Phase 3 Project, if they were to be selected. In particular, consultations could be required in the vicinity of the ATA Yard if this was selected for undertaking construction / fabrication activities for the ACG Phase 3 project. Further, if the Lokbatan site was selected for disposal of produced water there could be a need to communicate with the stakeholders on this issue. The social baseline assessment will determine the need for any specific consultations. As project decisions had not been made at the time of undertaking the ACG Phase 3 Project scoping consultations as to whether or not the ATA Yard and Lokbatan site would be used a decision was therefore made to postpone associated consultations until such a time as the project position was clarified. However, baseline socio-economic data has recently been collated as part of the ACG Phase 2 project activities that will provide useful input into the identification and analysis of the new stakeholders in the vicinity of the ATA Yard Stakeholder Fatigue Stakeholder fatigue was identified as a potential issue for the ACG Phase 3 project as a consequence of the extensive programme of consultation undertaken for previous phases of the project. To try to overcome this possible 'barrier' to effective consultations, the consultations with a number of stakeholders will focus on a discussion of current socio-economic mitigation measures and community development/social investment programmes. This allows stakeholders to raise concerns and provide feedback and thus help determine their effectiveness and the need for any further intervention 1. 1 This was the approach adopted for the ACG Phase 3 Scoping Consultations where it proved effective, with, in particular, useful comment obtained on current social programmes being run by the STEP (please refer to the ACG Phase 3 Scoping Report). 12
17 6. PROGRAMME AND SCHEDULE OF CONSULTATION & DISCLOSURE ACTIVITIES IN RELATION TO ESIA STAGES AND PROJECT IMPLEMENTATION 6.1 Summary of Types of Methods to be Used A range of consultation methods will be used depending on the aim of the consultation and the type of stakeholders. Below, the methods are described according to the activities involved in the ESIA. Scoping Consultations There are two main types of scoping consultations. First, there will be scoping workshops with three main groups: The Research and Monitoring Group (a body established under the ACG PSA to advise on environmental issues); The Scientific Community; and Non-Governmental Organizations (NGOs). These groups have been consulted by AIOC for the ESIAs for earlier project phases. They are familiar with the overall project concept and its implementation in three separate, but linked phases. The members of these stakeholder categories are all based in Baku or its immediate environs. Also, they are well educated, accustomed to ESIAs and the scoping process, and understand their links to project design and implementation. Consequently, following previous precedent, a workshop approach is proposed. The workshops will be of 1-day duration. They will share a common agenda (see table below). The day begins with presentations on the Phase 3 ESIA process and an account of the key characteristics of the phase 3 development. This is followed by a presentation of environmental monitoring undertaken for earlier ACG Phases and the results to date. All presentations will be supported by a PowerPoint presentation (with hard copies distributed in advance in Azeri or Russian). Following each presentation there will be a question/answer session. After lunch the participants will be divided into working groups to identify key impacts and other concerns for Phase 3 (for academics and NGOs only). The proceedings of the entire day will be recorded and a summary report of the proceedings prepared and used as input to the Scoping Report. The meetings will be conducted in Azeri and Russian with the aid of translators for the benefit of English speaking attendees. Feedback forms will be distributed to provide individuals who had not had the opportunity to raise an issue or who required further clarification to communicate this. Notably, for the meeting for the NGOs a presentation of the ACG social investment / community development programmes will be included as an additional item to the agenda (see Box 1 below). This has been added on the advice of AIOC personnel that a number of the NGOs will have a primarily social rather than environmental focus and would therefore be looking to be provided with information on these programmes. 13
18 Box 1: Agenda for Stakeholder Consultation Workshops - Baku 1. Goals and objectives for the workshop regarding input to scoping process 2. ACG development Phase 3 ESIA process 3. ACG development Phase 3 Project within the context of full field development of Azeri, Chirag fields and deepwater portion of Gunashli Field 4. ACG development Social Investment / Community Development Programmes (NGOs only) 5. General review of key aspects 6. Current and planned initiatives on environmental monitoring 7. Working groups to identify issues of concern for investigation in the ESIA 8. Presentations by working groups to plenary session During previous phases of the ACG project an NGO (based in Baku) that is concerned with protecting the rights of oil workers was identified. It is considered important to consult with a representative of this NGO, especially with regard to employment related and local oil and gas business development related social and economic impacts and issues of concern. This consultation will be based on an interview using a semistructured questionnaire to guide and record the discussion. Second, scoping consultations will be held with key individuals and focus groups from the local communities living in the vicinity of the Sangachal terminal. In previous phases of the ACG project a public meeting approach had been adopted. Whilst this resulted in a significant attendance it is considered that this type of consultation makes it difficult for some groups such as women, teenagers and elders to express their personal views. In particular there is the risk that the views expressed at the meetings will be dominated by one specific group with other groups feeling uncomfortable or unable to express their personal views in the presence of this dominant group. The proposed approach provides for a greater emphasis on a focus group, rather than public meeting approach to community-based consultation. Based on discussions with the STEP team members it is intended that the stakeholders involved in these consultations will comprise those stakeholders and stakeholder groups listed in Box 2 below. Box 2: Local Community Stakeholders 1. Garadagh Executive Power (Lokbatan [headquarters for Garadagh District] and representatives of the Executive Power Committee in Sangachal and Umid) 2. Manager of the Information Centres 3. Councils of Elders (Aksakkals) of Sangachal and Umid 4. Community Development Councils in Sangachal and Umid 5. School Directors (one each from Sangachal and Umid) 6. Women Focus Group 7. Young people Focus Group (ages approximately from 13-19) 14
19 The methods to be used will vary. All interviews will be undertaken using a semistructured questionnaire. The number and type of questions will depend on the stakeholder. Community members (as opposed to those in 'official' positions) will be consulted in an informal 'discussion' style mode focused around a few open questions. Since construction began on the terminal site there have been many interactions between AIOC (particularly terminal management) and local community representatives/individuals. Additionally, AIOC has been implementing a Social Investment / Community Development Programme in the local communities. This Programme is funding a number of projects to assist the local communities. One of these projects is being managed by the international NGO, World Vision. It is considered that the AIOC Sangachal Terminal Community Liaison Officer and / or World Vision should assist with these consultations as discussed in There are some key project decisions still to be made as discussed in for which further scoping consultation could still be required. For example, the ATA yard may be selected for part of the construction / fabrication activities and a site in Lokbatan may be selected for disposal of produced water. It is considered inappropriate to undertake consultations in the vicinity of these localities until AIOC has made these key decisions. Such consultations may create expectations or enhance fears needlessly. However, once the decisions are made consultations can still occur and be incorporated into the ESIA process for Phase 3. Similar methods to those identified for scoping consultations in the communities in the vicinity of the Sangachal terminal will be used for these scoping consultations. The ATA yard is undergoing an upgrade, at present, and a baseline social survey has been carried out for the site that has identified some key stakeholders in the area. The results of this work will be used as a key input to any scoping consultations that may be undertaken as part of the Phase 3 ESIA process. The scoping report will be submitted to the MENR, placed on the BP Projects website, and copies placed in the Information Centres within the local communities. ESIA Preparation It is anticipated that the key element of the consultation process during ESIA preparation will be communication of the progress of outstanding commitments from earlier phases of the ACG project and communication of the decision making process for the ACG Phase 3 facilities design. This will require an underlying robust issues management system that allows for the maintenance of a transparent and auditable trail. Typically, the methods adopted and results of the project decision-making process have been presented within the Environmental Statement and the process disclosed in this way to the interested stakeholders. However, during the ACG Phase 3 Scoping consultations the NGOs, in particular, expressed a strong desire to be involved earlier in the process whilst the decisions were still being made. It would not be practical to involve only certain stakeholder groups in consultations during the ESIA preparation phase of the ESIA process, as this would create a bias in the feedback. Therefore any programme for consultation during this phase would need to be designed to facilitate consultation with all stakeholder groups. It is proposed that written bulletins (holding statements) be prepared on key environmental and social issues of concern to stakeholders, detailing the suggested approach, design, and control measures being considered by the project. These will be 2 At the time of writing the scoping consultations have been completed and the results are contained in the Scoping Report for the ACG Phase 3 ESIA. 15
20 distributed to key project personnel and representatives of organizations or groups who are then charged with the responsibility for further disseminating the information and collating feedback. For example within the local communities either the Community Liaison officer or the head of the local Executive Power or the Community Development Committees could be charged with the responsibility for the Sangachal Village and Umid Settlement. Representatives of the academics and the R&MG could be nominated for these groups, and an organization that provides capacity building support to local NGOs could be used to co-ordinate the communication and collation of feedback from the NGOs. Draft ESIA report Once the environmental statement is completed it will be available for comment. It will be issued in Azeri, Russian and English and placed on the BP project website 3. Copies, containing an Executive Summary, will be placed in locations with easy public access such as schools, libraries, Community Information Centres, the Human Development Centre, BP Villa Petrolea reception, Executive Power offices, and the new Environmental Information Centre within the Ministry of Ecology and Natural Resources. Notification will be given through newspaper advertisements and posters, and written comments requested within the formal 60 day consultation period. A public meeting will be held in Baku. This public meeting will be announced in the media and information will be posted in prominent public places. The meeting will begin with a presentation outlining the project, the ESIA process followed, and the key findings/recommendations of the ESIA Report. This will be followed by a question and answer session. The public meeting will be held in the evening rather than during the day to allow those that are working to attend. The public meeting will be supplemented by a series of community-based focus group round table discussions. The groups involved will include those consulted during the scoping phase and any additional focus groups identified during the course of the EISA preparation process. Finally an open day is proposed, to be held at a venue or venues yet to be determined, at which information will be provided on the project, Phase 3 project personnel would be available to answer questions and members of the public will be able to voice opinions and concerns with regards to the project. All questions asked and issues raised will be documented. It is suggested that the open day be run as a table session, with each table designated for discussion of a different key issue. The themes will be determined nearer the time when the ESIA team is clear on the areas they feel should be the focus of consultation with respect to the community interests. It is recommended that consideration be given to ensuring that the form and content of the day be conducive for all members of the community to attend (e.g women members of the project team will be present in order to encourage women to attend). Interpreters will also be available
21 All comments will be collated and analyzed and entered into a reporting template format that provides for AIOC to summarize its response to comments. It is proposed that a similar format is used to that used in the Supplementary Lenders Information Package prepared for Phase 1 (available on the BP projects website 4 ). Once completed this template can then be incorporated into the final ESIA report. Final ESIA Report Copies, in English, Russian and Azeri, of the ESIA Report will be placed in the public domain and announced? as per the draft ESIA Report. Post-ESIA Project Consultations Considerable attention has been given in the PCDPs of the earlier phases to the type and nature of post-esia consultations (especially the Phase 1 PCDP). Since terminal construction began a community relations programme has been initiated and appears to be working well. It is realized that there is an existing framework and that it should only be altered for a very good reason. The Complaints Procedure detailed in the Phase 1 PCDP will be adopted also for Phase 3. Phase 3 is about to begin and will be followed directly by an operational period of many years. It is therefore considered appropriate at this time to consider how community consultations should be structured to best meet the needs of the project operators and the local communities. At present, the programme of community consultations being led by the STEP team is strongly linked to the Social Investment /Community Development programme and it would appear that currently the consultation effort is focused on these programme issues, and thus on the Sangachal Village and Umid Settlement Communities. The construction Environmental Management System is now better developed and understood, allowing a proactive approach to the management of issues such as noise, traffic movement, and other potential community nuisances. It is expected that project environmental and social aspects (as identified within the Environmental Management System aspects register), and their associated control and mitigation measures, will be subject to regular review and analysis using performance data. Analysis of the data collated through the Complaints Procedure can form part of this performance data, and feedback can be provided to the communities on performance (eg. results of noise monitoring). Consultation Under the Espoo Convention Azerbaijan is a signatory to the Convention on Environmental Impact Assessment in a Transboundary Context (the Espoo Convention). This requires the Azerbaijan Government to provide initial notification to countries that may be subject to transboundary environmental impacts as a result of a development within Azerbaijan. An offshore oil development carries with it the small risk of a major oil spill. Such a scenario has been modelled for the ACG Phase 1 and Phase 2 developments and the results indicate that should such a spill occur, there is the potential for transboundary impacts. It is currently assumed that the Phase 3 development carries a similar risk. For this reason AIOC has forwarded to the Azerbaijan Ministry of Ecology and Natural Resources the ESIA scoping report for Phase 3, for onward delivery to the Caspian littoral states. The littoral states are required to respond to the Ministry indicating whether they wish to participate in the ESIA process. Should the Ministry receive confirmation from any of the littoral states that they wish to participate, this PCDP will be updated to reflect the planned consultation with those states. This document will
22 then also be circulated to the littoral states wishing to participate. 6.2 Schedule of Consultation Activities & Plan for Integration with ESIA & Project Activities It is not possible to provide a precise plan for consultation activities and their integration with the ESIA and project activities for two main reasons: The ACG Phase 3 development is still at the 'concept' stage with key decisions on project options still to be made (expected by August, 2003); and The ESIA has not yet been tendered so its timescale is not yet known precisely. Therefore, the schedule of consultations and linkages to the ESIA and project activities are presented with indicative timings. Once timings are known the PCDP will be amended accordingly to ensure it is current with ESIA/project activities. The indicative consultation schedule is shown in Table 2. Table 2: Consultation Plan and links to ESIA and Project Activities Consultation activities 1. Three workshops with stakeholders in Baku April Consultation meetings in Sangachal and Umid with community stakeholders (listed in section 6.1) May Interviews with representatives of Garadagh Executive Power and Manager of the Information Centres May 2003 Consultations and interviews with stakeholders as necessary Holding statements ESIA/Project Activities Scoping and preparation of Terms of Reference (ToR) for the ESIA (April - July 2003) The results of the scoping meetings will be summarized in a Scoping Report. The results will form the basis for the ToR. Also, issues raised may be used to assist decision-making by AIOC in the continuing design work for Phase 3. Implementation of ESIA and preparation of draft ESIA Report (August June 2004 During ESIA work there may be a need to obtain additional baseline data on socioeconomic and other characteristics. Also, there may be a need to refine impact prediction work to make it more focused and relevant. In such a situation 'follow on' consultations with stakeholders and/or consultations de novo with other stakeholders may be required to assist the ESIA. Also, if stakeholders request meetings to discuss the ESIA progress and preliminary results then meetings may be held at the discretion of AIOC. 18
23 1. Announcements in press and local notices in public places of details regarding the consultation process and period allowed for commenting. 2. Draft ESIA Report posted on the website. 3. Copies of Executive Summary available at key locations with good public access (in Azeri and Russian). 4. Copies of draft ESIA Report available at key locations with good public access (in Azeri and Russian). 5. Workshops held with Baku-based stakeholders (identical to those consulted during Scoping consultations). 6. A public meeting held in Baku. 7. Focus group consultation and open day 1. Final ESIA Report posted on the website. 2. Copies of final ESIA Report available at key locations with good public access (in Azeri and Russian). A programme of consultations is already in place from Phase 1. This will continue throughout Phase 3 and into the operational phase of the project. The Environmental Management System will be used to assess the performance against mitigation and control measures, and consultation will feed into measurement of performance. Draft ESIA Report (Environmental Statement) June - August 2004 (based on 60 day period for comments to be received by AIOC) Comments will be collated and analyzed using a standard reporting template. AIOC responses will be recorded in this template. The completed template with an account of consultations undertaken will be included as a section in the final ESIA Report. The comments received may lead to changes in the draft ESIA Report and, thus, determine to some extent the contents of the final ESIA report. Also, they may lead to changes in proposed project design and implementation actions. In line with the need for feedback to consultees, the summary of comments received and AIOC responses will be issued as soon as possible after completion of the 60-day consultation period. Final ESIA Report (Environmental Statement) August 2004 Post ESIA Report (Environmental Statement) Project Consultations Quarter et seq. Phase 3 construction actions will begin, followed by the operational phase. Regular, systematic and structured consultations between the terminal management and local stakeholders will play an important role in assisting implementation of effective impact management. Impact management is likely to involve amendments to operational practices and their timing. An evaluation report of PCDP effectiveness will be prepared and reported to a senior manager (see Section 6.5 below) and used to assist future ESIA consultation activities 6.3 Allocated Budget for the ACG Phase 3 ESIA Consultation The total allocated budget for the ACG Phase 3 ESIA Consultation process will be required to encompass five key components: media management activities to be undertaken and/or co-ordinated by the AIOC 19
24 Government and Public Relations (GPR) Department; issues management and stakeholder analysis activities to be undertaken through the collaboration of the AIOC GPR and HSE Departments; activities to be undertaken and /or co-ordinated by the individuals within the AIOC HSE Department responsible for management of the ACG Phase 3 ESIA process; community liaison activities to be undertaken and / or co-ordinated by the STEP team on behalf of the ACG Phase 3 ESIA project team; and activities to be undertaken and / or co-ordinated by the successful external consultant contracted to undertake the ESIA and prepare the associated Environmental Statement on behalf of AIOC. As a consequence of the later bullet point, the total allocated budget for the ESIA Consultation process will need to be determined following technical and commercial review of the Tender Documents received in response to the Invitation to Tender for the ACG Phase 3 ESIA. It is anticipated that, as far as practical, the execution of the consultation programme for ACG Phase 3 ESIA will be co-ordinated with existing and planned activities and initiatives for other phases of the ACG project. As such the allocated budget for the programme may be shared. 6.4 Management of Media Publicity Management of Media Publicity is the primary responsibility of the Government and Public Relations (GPR) department within AIOC. The GPR department has provided the following support to previous ESIA Consultation processes for the ACG project and it is anticipated that this same support will be available for the ACG Phase 3 project: Preparation of Holding Statements for key issues, in collaboration with the HSE department; Preparation of Question and Answer Sheets on key issues; Preparation of fact sheet handouts for use at public meetings; Preparation and dissemination of Press Releases; and Management of media enquiries. Requirements for support for management of media publicity for the ACG Phase 3 EISA consultation process will need to be discussed with the GPR department so that they can be integrated in the (HSE) External Communication Plan. 6.5 Management and Staff Resources Allocated to the Plan Tasks Within AIOC the responsible senior manager for the ACG Phase 3 Project is the Phase 3 Project Manager. His primary responsibility is to ensure that the ESIA decision on approval is delivered without impeding the project schedule. The Phase 3 Environmental Manager reports to the Phase 3 Project Manager and has overall responsibility for the entire ESIA process for Phase 3. This includes the adequacy of the ESIA process, the quality of the documentation and the effective implementation of the PCDP. In particular, she will ensure that the report of the evaluation of the Phase 3 PCDP is circulated to appropriate AIOC staff and that the lessons learnt are incorporated into future ESIA consultation activities. 20
25 She will be responsible for overseeing the implementation of the PCDP and will be supported by other HSE and GPR staff, as required, with respect to the day-to-day management of PCDP implementation. In particular, she will ensure that the activities outlined in Table 2 above are implemented effectively and on schedule. She will ensure, finally, that the effectiveness of the PCDP is evaluated. Figure 5 below presents a flow diagram showing the interfaces between the ACG Phase 3 ESIA Team and the other departments providing support to the public consultation and disclosure process. 21
26 Figure 5 AZERI, CHIRAG & GUNASHLI FULL FIELD DEVELOPMENT PHASE 3 Sangachal Terminal Expansion Project Community Liaison Environmental & Social Advisor Manager of Human Development Centre Manager of Information Centres World Vision Management Resources for ACG Phase 3 Public Consultation & Disclosure Process ACG Phase 3 Project Manager ACG Phase 3 ESIA Manager HSE Department (incl. Phase 1 & 2 HSE Managers) Government & Public Relations Deparment Management of Media Publicity and Stakeholder Analysis 22
27 7. EVALUATION CRITERIA FOR ASSESSING PCDP EFFECTIVENESS The PCDP will be evaluated against the goals set out in the Introduction. These goals are to ensure that; adequate and timely information is provided to project-affected stakeholders; these stakeholders are given sufficient opportunity to voice their opinions and concerns; and these concerns influence the ESIA process and project decisions. In addition, there are a number of activities to be implemented and outputs to be produced accompanied by time 'milestones'. The evaluation will be based on extent to which the activities and outputs have been undertaken according to the plan and within the specified time limits. In addition, the extent to which the goals have been achieved will be assessed, partly, depending on the extent to which the activities and outputs have taken place effectively. AIOC will undertake the evaluation. A brief Terms of Reference will be written to guide the evaluation. The evaluation will require interviews with AIOC staff and selected stakeholders and an examination of written records and materials pertinent to the implementation of the PCDP. The evaluation results will be presented in Table 3. This table will also provide a format for undertaking the evaluation. 23
Chapter 1 Introduction
Chapter 1 Introduction TABLE OF CONTENTS 1 INTRODUCTION... 1-1 1.1 General... 1-1 1.2 Background to the WREP... 1-1 1.3 Rationale for WREP-SR Project... 1-2 1.4 WREP Operator: GPC and BP Relationship...
More informationINTRODUCTION. List of Figures. List of Tables
3 Introduction...3-1 3.1 The SCP Owner Group... 3-1 3.2 Project Rationale... 3-2 3.3 Project Alternatives... 3-3 3.4 Project Description... 3-4 3.5 Scope of this ESIA... 3-5 3.5.1 Geographical extent...
More informationENVIRONMENTAL AND SOCIO-ECONOMIC IMPACT ASSESSMENT
ENVIRONMENTAL AND SOCIO-ECONOMIC IMPACT ASSESSMENT AZERI, CHIRAG & GUNASHLI (ACG) PHASE 3 PROJECT DRAFT June 2003 TABLE OF CONTENTS 1. INTRODUCTION...1 1.1 ACG PSA...1 1.2 ACG Contract Area and Field
More informationAppendix C1 Public Consultation and Disclosure Plan
Appendix C1 Public Consultation and Disclosure Plan TABLE OF CONTENTS 1 PUBLIC CONSULTATION AND DISCLOSURE PLAN (PCDP)... 1 2 STAKEHOLDER ENGAGEMENT... 1 3 PUBLIC DISCLOSURE AND DISTRIBUTION OF DOCUMENTS...
More informationJune 2018 Template for ESS10: Stakeholder Engagement and Information Disclosure Stakeholder Engagement Plan and Stakeholder Engagement Framework
This template provides guidance for the Borrower on specific aspects of the application of the Environmental and Social Standards (ESSs), which form part of the World Bank s 2016 Environmental and Social
More informationModule 5: Project Evaluation in
Module 5: Project Evaluation in IUCN 5-1 Module 5: Project Evaluation in IUCN 5-2 Module 5: Project Evaluation in IUCN Table of contents 1. THE ROLE OF PROJECT EVALUATION IN IUCN... 6 1.1. THE PURPOSE
More information9 ENVIRONMENTAL MANAGEMENT PLAN 9.1 OVERVIEW AND SCOPE Introduction
9 ENVIRONMENTAL MANAGEMENT PLAN 9.1 OVERVIEW AND SCOPE 9.1.1 Introduction This chapter is the provisional Environmental Management Plan (EMP) for the Jubilee Phase 1 Development project. The elements of
More informationSocio-Economic Baseline Data Gathering
FINAL REPORT ACG Phase 1 Technical Appendix 13 Socio-Economic Baseline Data Gathering BP EXPLORATION (CASPIAN SEA) LTD BAKU, AZERBAIJAN URS Dames & Moore Nizami 86, Apt. 7 Baku, Azerbaijan Tel: (99412)
More information5 ENVIRONMENTAL AND SOCIAL TRAINING ACTIVITIES
5 5 ENVIRONMENTAL AND SOCIAL TRAINING ACTIVITIES 5.1 PROJECT WIDE APPROACH Training continues to take place at many levels of the Project, to ensure all employees are effective in their job and are able
More informationCritical infrastructure aspects of energy security: Azerbaijan and regional context
Critical infrastructure aspects of energy security: Azerbaijan and regional context Bakhtiyar Aslanbayli Professor of Security and Energy Policy Baku State University, AZERBAIJAN Keywords: Azerbaijan,
More informationLEGAL AID BOARD BOARD EVALUATION FINAL REPORT
LEGAL AID BOARD BOARD EVALUATION FINAL REPORT May 2018 Governance Advisory Services Ireland Limited, 32 Leeson Street Lower, Dublin 2, Ireland. Telephone: +353 (0)1 639 2928, Email: info@governanceireland.ie,
More informationNATIONAL INSTITUTE FOR HEALTH AND CARE EXCELLENCE. Health and Social Care Directorate. Indicator Process Guide. Published December 2017
NATIONAL INSTITUTE FOR HEALTH AND CARE EXCELLENCE Health and Social Care Directorate Indicator Process Guide Published December 2017 Please note that this is an interim factual update to the NICE Indicator
More informationFor personal use only
PALADIN ENERGY LTD ACN 061 681 098 CORPORATE GOVERNANCE STATEMENT 2018 The Board of Directors of Paladin Energy Ltd (Paladin) and the entities it controlled (Consolidated Entity or Group) is responsible
More informationPALADIN ENERGY LTD ACN CORPORATE GOVERNANCE STATEMENT 2018
CORPORATE GOVERNANCE STATEMENT 2018 The Board of Directors of Paladin Energy Ltd (Paladin) and the entities it controlled (Consolidated Entity or Group) is responsible for the corporate governance of the
More informationAudit Committee Self Assessment
Audit Committee Institute United Kingdom Audit Committee Self Assessment The audit committee should regularly assess its own effectiveness and the adequacy of its terms of reference, work plans, forums
More informationQuick Guide to Neighbourhood Plans. Locality Neighbourhood Plans Quick Guide 1
www.locality.org.uk Locality Quick Guide 1 2 5 11 Contents Introduction Producing a Neighbourhood Plan Bringing the Plan into Legal Force Introduction Since April 2012, local communities have been able
More informationMALIN CORPORATION PLC CORPORATE GOVERNANCE GUIDELINES. Adopted on 3 March 2015 and Amended on 26 May 2015
MALIN CORPORATION PLC CORPORATE GOVERNANCE GUIDELINES Adopted on 3 March 2015 and Amended on 26 May 2015 The following Corporate Governance Guidelines (the "Guidelines") and Schedule of Matters reserved
More informationBASICS OF ENVIRONMENTAL AND SOCIAL IMPACT ASSESSMENT (ESIA)
BASICS OF ENVIRONMENTAL AND SOCIAL IMPACT ASSESSMENT (ESIA) HSE specialists, environmental engineers, design engineers, project managers and senior project managers involved in conceptual design, Front-End
More informationTerms of Reference for the Audit and Risk Committee (the Committee )
Terms of Reference for the Audit and Risk Committee (the Committee ) Amended and approved by the Board on 12 April 2016 Table of Contents 1. Background... 1 2. The Committee s Duties... 1 3. Composition...
More informationTERMS OF REFERENCE. Independent Evaluation of the ILO Action Plan for Gender Equality
TERMS OF REFERENCE Independent Evaluation of the ILO Action Plan for Gender Equality 2010-15 1 Introduction The results-based ILO Action Plan for Gender Equality 2010-15 (the Action Plan) aims to operationalize
More informationEngagement Performance 49% Independence and Ethical Requirements 40% Human Resources 31% Monitoring 28%
International Forum of Independent Audit Regulators Report on 2016 Survey of Inspection Findings March 2017 1 Highlights In 2016, IFIAR conducted the fifth annual survey ( Survey ) of its Members findings
More informationEstablishing a Multi-Stakeholder Group and National Secretariat
Construction Sector Transparency Initiative October 2013 / V1 Guidance Note: 4 Establishing a Multi-Stakeholder Group and National Secretariat Introduction An essential feature of CoST is the multi-stakeholder
More informationIbstock plc. (the Company) Audit Committee - Terms of Reference
Ibstock plc (the Company) Audit Committee - Terms of Reference 1. PURPOSE 1.1 The role of the Audit Committee (the Committee) is to: monitor the integrity of the financial statements and related announcements
More informationCHARTER OF THE BOARD OF DIRECTORS
SUN LIFE FINANCIAL INC. CHARTER OF THE BOARD OF DIRECTORS This Charter sets out: 1. The duties and responsibilities of the Board of Directors (the Board ); 2. The position description for Directors; 3.
More informationTECHNICAL GOVERNANCE REVIEW RESPONSE TO FINAL REPORT
Australia s independent, not-for-profit, developer of Australian Standards TECHNICAL GOVERNANCE REVIEW RESPONSE TO FINAL REPORT April 2018 Page 2 Background Each year, Standards Australia hosts open forums
More informationChiyoda Corporation Corporate Governance Policy (Revised on June 23, 2016)
[Translation] Chiyoda Corporation Corporate Governance Policy (Revised on June 23, 2016) This policy sets forth the basic views and basic guideline of Chiyoda Corporation (hereinafter the Company ) with
More informationStakeholder engagement: demonstrating compliance with international standards
IAIA18 Conference Proceedings Environmental Justice in Societies in Transition 38 th Annual Conference of the International Association for Impact Assessment 16-19 May 2018 Durban Intl. Convention Center
More informationHalma plc Terms of Reference Audit Committee Approved 18 January 2018
Reference to the Committee shall mean the Audit Committee. Reference to the Board shall mean the Board of Directors. 1. Membership 1.1. The Committee shall comprise at least three members and, where possible,
More informationONE WINDOW COORDINATION PROCESS for Mineral Development Projects in Ontario
ONE WINDOW COORDINATION PROCESS for Mineral Development Projects in Ontario Page 1 of 30 Table of Contents 1. INTRODUCTION AND PURPOSE... 3 Introduction... 3 Interpretation... 3 Definitions... 4 Objectives...
More informationMNC WIRELESS BERHAD ( T)
MNC WIRELESS BERHAD (635884-T) BOARD CHARTER 1. Introduction The Board of Directors ( Board ) of MNC Wireless Berhad ( MNC or the Company ) is responsible for overseeing the Company s management and ensuring
More informationRAVEN RUSSIA LIMITED CORPORATE GOVERNANCE. Terms of reference of the Audit Committee
RAVEN RUSSIA LIMITED CORPORATE GOVERNANCE Terms of reference of the Audit Committee TERMS OF REFERENCE OF THE AUDIT COMMITTEE 1 MEMBERSHIP 1.1 The board of directors of the company (the Board ) has resolved
More informationRHI MAGNESITA N.V. (the Company )
RHI MAGNESITA N.V. (the Company ) Terms of Reference: Audit and Compliance Committee as adopted by the Board of the Company on 12 October 2017 References to the Committee shall mean the Audit and Compliance
More informationSUBPROGRAMME EVALUATION: SUSTAINABLE DEVELOPMENT POLICIES DIVISION
EXECUTIVE SUMMARY SUBPROGRAMME EVALUATION: SUSTAINABLE DEVELOPMENT POLICIES DIVISION Period: January 2014 - December 2017 Nadia BECHRAOUI EXECUTIVE SUMMARY This is the Final Evaluation Report of the United
More informationCLINICAL & PROFESSIONAL SUPERVISION POLICY (replacing 033/Workforce)
CLINICAL & PROFESSIONAL SUPERVISION POLICY (replacing 033/Workforce) POLICY NUMBER 051/Workforce POLICY VERSION 1 RATIFYING COMMITTEE HR Policy Review Group DATE RATIFIED December 2010 NEXT REVIEW DATE
More informationAgenda Item 7: Strategic Transport Forum Revised Terms of Reference
Strategic Transport Forum 15 th December 2017 englandseconomicheartland@b uckscc.gov.uk Agenda Item 7: Strategic Transport Forum Revised Terms of Reference Recommendation: It is recommended that the Forum:
More informationOffice of the Ombudsman and the. Office of the Information Commissioner OFFICIAL LANGUAGES ACT, 2003
Office of the Ombudsman and the Office of the Information Commissioner OFFICIAL LANGUAGES ACT, 2003 Language Scheme 2016-2019 Chapter 1... 3 1.1 Introduction and Background... 3 1.2 Guidelines for preparation
More informationPEACE IV PROGRAMME ( ) European Territorial Cooperation Programme United Kingdom-Ireland (Ireland - Northern Ireland) EVALUATION PLAN
PEACE IV PROGRAMME (2014-2020) European Territorial Cooperation Programme United Kingdom-Ireland (Ireland - Northern Ireland) EVALUATION PLAN 23 NOVEMBER 2016 CONTENTS 1. INTRODUCTION 2. OVERVIEW OF PLANNED
More informationVACANCY ANNOUNCEMENT Ref: Issued on: 16 August 2017 DUTY STATION: NOD Re-advertise. CLOSING DATE: 26 August 2017
United Nations Human Settlements Programme P.O. Box 30030, Nairobi 00100, KENYA Tel: +254-20 7623120, Fax: +254-20 7624266/7 infohabitat@unhabitat.org, www.unhabitat.org VACANCY ANNOUNCEMENT Ref: 2017-07-02
More informationChapter 22: Environmental and Social Management
Chapter 22: Environmental and Social Management URS-EIA-REP-204635 Table of Contents 22 Environmental and Social Management... 22-1 22.1 Introduction... 22-1 22.2 Environmental and Social Commitments...
More informationNorth Sea Offshore Authorities Forum
North Sea Offshore Authorities Forum REPORT OF THE RESULTS OF THE 2001 / 2002 THEME AUDIT PROGRAMME State Supervision of M ines NSOAF Multi National Theme Audit 2001 / 2002 Composite Report 1. Introduction
More informationThe following are matters specifically reserved for the Board:-
To establish and review training programme and succession planning to the Board and all candidates appointed to senior management positions are of sufficient calibre; To approve the change of corporate
More informationRelated manuals Health & Safety Part 1 Section 1; H&S Part 1 Section 2; H&S Part 1 Section 3 ; Part 2 Section 1; Corporate Services Part 5 Section 1
H&S01_05_V4 - Page No.1 summary Health and Safety Audit & Review document control Responsible Author Sig for Sig for RB Issue Date Review Date Director CFO/CE ACFO B Hoad July 2013 July 2015 Related documents
More informationG4 DEVELOPMENT. Document 2 of 12 Statistics: Quantitative Online Feedback. Second G4 Public Comment Period: Submissions.
G4 DEVELOPMENT Document 2 of 12 Statistics: Quantitative Online Feedback February 2013 INTRODUCTION ABOUT THE SUBMISSIONS DOCUMENTS In 2010 GRI began the development of the fourth generation of its Sustainability
More informationALTISOURCE PORTFOLIO SOLUTIONS S.A. CORPORATE GOVERNANCE GUIDELINES
ALTISOURCE PORTFOLIO SOLUTIONS S.A. CORPORATE GOVERNANCE GUIDELINES The following were adopted by the Board of Directors (the Board ) of Altisource Portfolio Solutions S.A. (the Company ) at its meeting
More informationWelsh Language Commissioner Standards Investigation
Welsh Language Commissioner Standards Investigation 1. General 1.1. Full name of the organization: The Health and Care Professions Council (HCPC) 1.2. Type of organization: Health and Care Regulator 1.3.
More informationWORKPLACE MEDIATION. March 2013
WORKPLACE MEDIATION March 2013 V1 Jan2010; updated May 2011 STAF'446 - Workplace Mediation Policy March 2013-1 Contents 1. INTRODUCTION 3 2. POLICY AIMS 3 3. WHAT IS WORKPLACE MEDIATION? 3 4. GENERAL PRINCIPLES
More informationTerms of Reference - Audit Committee
1. Membership 1.1 The committee shall comprise at least three members. Members of the committee shall be appointed by the board, on the recommendation of the nomination committee in consultation with the
More informationAzeri, Chirag & Gunashli Full Field Development Phase 3 Environmental & Socio-economic Impact Assessment
Azeri, Chirag & Gunashli Full Field Development Phase 3 Environmental & Socio-economic Impact Assessment Final Report APPENDIX 11 ACG FFD Phase 3 & Shah Deniz Air Dispersion Modelling ACG PHASE 3 Offshore
More informationRISK MANAGEMENT STRATEGY
Agenda Item No: 15 RISK MANAGEMENT STRATEGY PURPOSE: The Risk Management Strategy has been updated to reflect the revised approach to the Corporate Risk Register and Board Assurance Framework and to reflect
More informationIAESB Strategy and Work Plan
International Accounting Education Standards Board April 2010 IAESB 2010 2012 Strategy and Work Plan International Accounting Education Standards Board International Federation of Accountants 545 Fifth
More informationMemorandum of understanding between the Competition and Markets Authority and NHS Improvement
1 April 2016 Memorandum of understanding between the Competition and Markets Authority and NHS Improvement Contents Page Foreword... 2 Summary points of the MoU... 3 Memorandum of understanding between
More informationBoosting Decent Employment for Africa s Youth. Request for Concept Notes
Boosting Decent Employment for Africa s Youth Request for Concept Notes Submission deadline: October 8, 2018 i Table of Contents 1. About the partner organizations... 1 2. Background and rationale... 2
More informationSyvash Wind Farm Environmental and Social Action Plan (ESAP)
General Environmental, Social Governance (ESG) management 1. Ensure Compliance with National legislation and attain all relevant National Permits, including EIA permit for the Project and associated infrastructure
More informationInvitation to Tender RGT Evaluation Framework Agreement, 2016 to 2019
Invitation to Tender RGT Evaluation Framework Agreement, 2016 to 2019 26th May 2016 1. Purpose of this Invitation to Tender (ITT) 1.1. This invitation to tender is for appointment to a three-year framework
More informationB&M EUROPEAN VALUE RETAIL S.A. TERMS OF REFERENCE OF THE AUDIT AND RISK COMMITTEE
B&M EUROPEAN VALUE RETAIL S.A. TERMS OF REFERENCE OF THE AUDIT AND RISK COMMITTEE These terms of reference have been approved by the board of directors (the "Board") of B&M European Value Retail S.A. (the
More informationSECTOR ASSESSMENT (SUMMARY): ENERGY 1
Country Partnership Strategy: Azerbaijan, 2014 2018 SECTOR ASSESSMENT (SUMMARY): ENERGY 1 Sector Road Map A. Sector Performance, Problems, and Opportunities 1. Azerbaijan is rich in energy resources. The
More informationThe aim of the public participation process undertaken as part of this Scoping phase is to:
SECTION 5: PUBLIC PARTICIPATION PROCESS 5.1 PUBLIC PARTICIPATION PROCESS Public participation is an integral aspect of any EIA process and should aim to meaningfully engage stakeholders at all levels throughout
More informationTHE LAIKIPIA COUNTY PUBLIC PARTICIPATION BILL, 2014 ARRANGEMENT OF CLAUSES PART I PRELIMINARY
1 THE LAIKIPIA COUNTY PUBLIC PARTICIPATION BILL, 2014 ARRANGEMENT OF CLAUSES Clause PART I PRELIMINARY 1-Short title. 2- Interpretation. 3-Purpose of the Act. 4- Principles of public participation. PART
More informationThe Gym Group plc. (the Company ) Audit and Risk Committee - Terms of Reference. Adopted by the board on 14 October 2015 (conditional on Admission)
The Gym Group plc (the Company ) Audit and Risk Committee - Terms of Reference Adopted by the board on 14 October 2015 (conditional on Admission) 1. BACKGROUND The board of directors of the Company (the
More informationBig Local evaluation plan
Big Local evaluation plan By Jayne Humm, programme manager, July 2015 This paper sets out the evaluation plan for the Big Local programme building on the research and evaluation conducted thus far on the
More informationAudit Committee - Terms of Reference
1 Membership 1.1 Members of the Committee shall be appointed by the Board, on the recommendation of the Nomination Committee in consultation with the Chairman of the Audit Committee. The Committee shall
More informationNZAID Evaluation Policy Statement
NZAID Evaluation Policy Statement Contents Introduction 1 Scope..1 Definition of evaluation.1 Purpose of evaluative activities in NZAID.1 NZAID s commitment to learning from evaluative activity..2 Location
More informationAppendix 4 Communications and Stakeholder Engagement Strategy
Appendix 4 Communications and Stakeholder Engagement Strategy Table of Contents 1. Introduction... 2 1.1. Objectives of Engagement... 3 1.2. Strategic Approach... 3 2. Stakeholder Identification... 3 2.1.
More informationTERMS OF REFERENCE 1. BACKGROUND ECCSA. Demand Study for the Ethiopian Chamber of Commerce and Sectoral Associations (ECCSA) 1.1 Assignment background
ECCSA TERMS OF REFERENCE Sida Demand Study for the Ethiopian Chamber of Commerce and Sectoral Associations (ECCSA) July and August 2016 1. BACKGROUND 1.1 Assignment background The Ethiopian Chamber of
More informationMilestones & Benchmarks
2014 Center for Communities That Care, University of Washington Phase 1: Get Started 1.1 Organize the community to begin the Communities That Care Process. Designate a single point of contact to act as
More informationIntroduction. Project outline
ES1 ES1.1 Introduction Project outline The Azerbaijan International Operating Company (AIOC), operated by BP is planning to begin development of Phase 1 of the Azeri Chirag and Deep Water Gunashli (ACG)
More informationAudit, Risk and Compliance Committee Terms of Reference. Atlas Mara Limited. (The "COMPANY") Amendments approved by the Board on 22 March 2016
Audit, Risk and Compliance Committee Terms of Reference Atlas Mara Limited (The "COMPANY") Amendments approved by the Board on 22 March 2016 1. OVERVIEW 1.1 The primary objective of the committee is to
More informationOrganisational Change Policy
Organisational Change Policy 1 Organisational Change Policy Policy ref no: HR022 Author (inc job Rob Osment, HR Business Partner title) Date Approved 17 May 2016 Approved by Quality and Governance Committee
More informationCorporate Governance Guidelines
Corporate Governance Guidelines Chapter 1. General Provisions Article 1. Purpose These guidelines set out the basic policy, framework and operating policy of the corporate governance of Fuji Heavy Industries
More informationIAASB Main Agenda (December 2016) Agenda Item
Agenda Item 9-A ENHANCING AUDIT QUALITY: PROJECT PROPOSAL FOR THE REVISION OF THE IAASB S INTERNATIONAL STANDARDS RELATING TO QUALITY CONTROL AND GROUP AUDITS This document was developed and approved by
More informationPROCEDURE FOR MANAGING WORKFORCE CHANGE
PROCEDURE FOR MANAGING WORKFORCE CHANGE Issued by Department of Human Resources Updated: 06 March 2012 CONTENTS Page Section 1: Introduction 2 Section 2: Scope of the Procedure 2 Section 3: Consultation
More informationWelsh Language Scheme
Welsh Language Scheme 28 May 2009 www.wao.gov.uk This Scheme was approved by the Welsh Language Board under Section 14 of the Welsh Language Act 1993. It came into effect on 28 May 2009. Rachel Moss Head
More informationCOMMUNITY AND STAKEHOLDER ENGAGEMENT PLAN APPENDIX ENVIRONMENTAL IMPACT STATEMENT
COMMUNITY AND STAKEHOLDER ENGAGEMENT PLAN APPENDIX J ENVIRONMENTAL IMPACT STATEMENT Boral Gold Coast Quarry: Community and Stakeholder Engagement Plan (EIS advertising phase and beyond) APRIL 2013 TABLE
More informationRegional Animal Welfare Strategy for Asia, the Far East and Oceania: Draft Implementation Plan. Prepared by the RAWS Implementation Working Group
Regional Animal Welfare Strategy for Asia, the Far East and Oceania: Draft Implementation Plan Prepared by the RAWS Implementation Working Group November 2008 Contents Acronyms and abbreviations... 3 Introduction...
More informationPHILLIPS 66 CORPORATE GOVERNANCE GUIDELINES. (As Amended and Restated July 11, 2018)
PHILLIPS 66 CORPORATE GOVERNANCE GUIDELINES (As Amended and Restated July 11, 2018) The Board of Directors (the Board ) of Phillips 66 (the Company ) has adopted these corporate governance guidelines (the
More informationorganisational change, redundancy, sickness Medical & Dental Whitley Handbook; and
Human Resources Redeployment Policy Document Control Summary Status: Replacement. Replaces: Redeployment Policy H/BLU/r&s/02 Version: v2.0 Date: May 2015 Author/Owner/Title: Sarah Guy - Operational HRODE
More informationJD SPORTS FASHION PLC (THE "COMPANY") AUDIT COMMITTEE TERMS OF REFERENCE
JD SPORTS FASHION PLC (THE "COMPANY") AUDIT COMMITTEE TERMS OF REFERENCE 1 CONSTITUTION 1.1 The committee has been established by resolution of the board of directors of the Company (the "Board") and is
More information4. Organic documents. Please provide an English translation of the company s charter, by-laws and other organic documents.
Commitment to Good Corporate Governance 1. Ownership structure. Please provide a chart setting out the important shareholdings, holding companies, affiliates and subsidiaries of the company. If the company
More informationA project supported by the European Union s INTERREG VA Programme, managed by the Special EU Programmes Body.
A project supported by the European Union s INTERREG VA Programme, managed by the Special EU Programmes Body. MACE (Breaking the Cycle) Children s Services Project Co-operation and Working Together (CAWT)
More informationTERMS OF REFERENCE. Evaluation of the Independent Science and Partnership Council (ISPC) May Background Rationale and Context
TERMS OF REFERENCE Evaluation of the Independent Science and Partnership Council (ISPC) May 2017 1. Background 1.1. Rationale and Context The Independent Science and Partnership Council (ISPC) is an independent
More informationTERMS OF REFERENCE FOR THE REVIEW OF WIPO S TECHNICAL ASSISTANCE ACTIVITIES IN THE AREA OF COOPERATION FOR DEVELOPMENT prepared by the Secretariat
E CDIP/4/8/REV/TOR ORIGINAL: ENGLISH DATE: OCTOBER 20, 2010 TERMS OF REFERENCE FOR THE REVIEW OF WIPO S TECHNICAL ASSISTANCE ACTIVITIES IN THE AREA OF COOPERATION FOR DEVELOPMENT prepared by the Secretariat
More informationBOARD OF DIRECTORS CHARTER
BOARD OF DIRECTORS CHARTER Title: Board of directors charter Document No.001 Effective Date: 7 November 2017 Next Review Date: November 2020 Approved by the Chairman and board of directors TABLE OF CONTENTS
More informationEU Presentation Enhancing existing means of participation. In session Workshop Bonn, 8 June 2011
EU Presentation Enhancing existing means of participation In session Workshop Bonn, 8 June 2011 1. EU s policies and practices on Public Participation RIO UNCED 1992 also for EU the key reference: Rio
More informationBOARD OF DIRECTORS TERMS OF REFERENCE OF SUB-COMMITTEES
BOARD OF DIRECTORS TERMS OF REFERENCE OF SUB-COMMITTEES January 2011 Page 1 of 19 AUDIT, RISK AND ASSURANCE COMMITTEE TERMS OF REFERENCE STRUCTURE AND RELATIONSHIPS 1. CONSTITUTION The Audit, Risk & Assurance
More informationImplementation Guides
Implementation Guides Implementation Guides assist internal auditors in applying the Definition of Internal Auditing, the Code of Ethics, and the Standards and promoting good practices. Implementation
More informationVolex plc (the "Company") Audit Committee. Terms of Reference
Volex plc (the "Company") Audit Committee Terms of Reference 1. Overview The Audit Committee has been established by resolution of the Board of Directors of the Company (the "Board"). 2. Membership 2.1
More information2.2. Attendance: Others may be invited by the Chair to attend all or part of any meeting (but they will not be entitled to vote).
Audit Committee Terms of Reference Effective Date Approved by Audit Committee on 15 March 2016 Approved by Governing Council on 20 May 2016 1. Purpose 1.1. The main purpose of the Audit Committee is to
More informationRubbish or Resource? Public Consultation
West of England Waste Management & Planning Strategy Rubbish or Resource? Public Consultation Phase 1 Summer 2006 25th September 2006 Report no: 1 West of England Waste Management & Planning Strategy Rubbish
More informationGrievance Procedure. for Support, Research, Teaching & Scholarship and Casual Staff
Grievance Procedure for Support, Research, Teaching & Scholarship and Casual Staff 1 Contents Grievance Procedure... 1 1) Aims of Procedure... 2 2) Scope... 2 3) Confidentiality... 3 4) Definition of terminology...
More informationHOW AN INDUSTRIAL BASELINE SURVEY CAN INFORM LONG-TERM STRATEGIC PLANNING AND FACILITATE CREATION OF SUSTAINABLE ECONOMIC LINKAGES
HOW AN INDUSTRIAL BASELINE SURVEY CAN INFORM LONG-TERM STRATEGIC PLANNING AND FACILITATE CREATION OF SUSTAINABLE ECONOMIC LINKAGES Framework Step: STEP 2 - Build an empirical basis to inform decision-making
More informationThe Charity Commission for Northern Ireland. Public Authority Statutory Equality and Good Relations Duties Annual Progress Report
The Charity Commission for Northern Ireland Public Authority Statutory Equality and Good Relations Duties Annual Progress Report 2015-16 Contact: Aubrey McCrory Section 75 of the NI Act 1998 and Equality
More informationIntegration Joint Board 13 September 2018 Locality Planning Forum Review
Subject: Purpose: Recommendation: Integration Joint Board 13 September 2018 Locality Planning Forum Review Informs IJB of the outcome of the Locality Planning Forum review with key stakeholders. Approve
More informationBoard Recruitment Policy
83/85 Dougrie Road, Castlemilk Glasgow, G45-9NS 0141-634-6473 2017 Board Recruitment Policy AS WITH ALL OF THE ASSOCIATION S POLICIES, THIS GUIDE IN FULL AND IN PART IS AVAILABLE IN SUMMARY, ON TAPE, IN
More informationInternal Audit report
Financial Conduct Authority Internal Audit report A review of the design and effectiveness of the FCA s external communications strategy Findings identified Major 0 Moderate 3 Minor 1 October 2014 1 1
More informationRecognizing that pollution of the Caspian Sea by oil and by oil pollution incidents of the sea threatens the marine environment,
PROTOCOL CONCERNING REGIONAL PREPAREDNESS, RESPONSE AND CO-OPERATION IN COMBATING OIL POLLUTION INCIDENTS TO THE FRAMEWORK CONVENTION ON THE PROTECTION OF THE MARINE ENVIRONMENT OF THE CASPIAN SEA Preamble
More informationTown of Bowden Province of Alberta Policy Document ( ) PUBLIC PARTICIPATION POLICY
Page 1 of 8 Town of Bowden Box 338, 2101 20 th Ave Bowden, Alberta, T0M 0K0 _ Town of Bowden Province of Alberta Policy Document (1900-02) PUBLIC PARTICIPATION POLICY 1 STATUTORY REQUIREMENT a The Town
More informationEUROPEAN BANK FOR RECONSTRUCTION AND DEVELOPMENT
EUROPEAN BANK FOR RECONSTRUCTION AND DEVELOPMENT PROJECT COMPLAINT MECHANISM COMPLIANCE REVIEW MONITORING REPORT II PARAVANI HYDROPOWER PROJECT, REQUEST NUMBER: 2012/01 March 2015 1 1 The report is prepared
More informationAZERI, CHIRAG and deepwater GUNASHLI (ACG) FULL FIELD DEVELOPMENT PROJECT (FFD) Phase 1
AZERI, CHIRAG and deepwater GUNASHLI (ACG) FULL FIELD DEVELOPMENT PROJECT (FFD) Phase 1 FRAME WORK DOCUMENT FOR THE PREVENTION AND RESPONSE TO OIL SPILLS ACG Phase 1 Framework Oil Spill Response Plan -
More information