APPLICATION OF A RISK-BASED ASSURANCE PROCESS TO A MEGA LNG LIQUEFACTION PROJECT
|
|
- Jordan Smith
- 5 years ago
- Views:
Transcription
1 APPLICATION OF A RISK-BASED ASSURANCE PROCESS TO A MEGA LNG LIQUEFACTION PROJECT John Holding Venture Assurance Manager, OKLNG Free Zone Enterprise 10, Greycoat Place, London SW1P 1SB, UK john.holding@oklng.com Chris Hughes Value & Technical Assurance Manager, OKLNG Free Zone Enterprise 10, Greycoat Place, London SW1P 1SB, UK chris.hughes@oklng.com OVERVIEW LNG is produced by a very capital intensive industrial process. Manufacturers of LNG cannot acquire market share by differentiating it from the product offered by other producers, nor on price. Since LNG is an internationally-traded commodity its price is set by the marketplace based on actual and perceived supply & demand and broader macro-economic considerations. The enabler in this value chain is the LNG Liquefaction Plant which must have effective project management techniques applied throughout the design, engineering and construction implementation phases that will be successful in supplying the LNG at a competitive price on the world market. At OKLNG it was recognized that the project management methodologies that had been applied to other similar projects would need to be extended in the areas of Value Assurance because of the regional challenges and the need to align the perception of risk and uncertainty between the shareholders in order to be able to land an agreement on the commercialization criteria of the project. The Project Team considered it a necessity to create an integrated methodology, defined as the Risk Based Assurance Process, which was needed to be in place to be able to build a liquefaction facility to compete with other Atlantic Basin producers of LNG. This paper examines some novel techniques around Value Assurance and how they are being deployed by OKLNG to compete at a superior level in the present challenging environment. INTRODUCTION 1. Proposition All major capital project investments seek to provide a return to their owners commensurate with the risks associated with the business sector concerned. Established project management practice starts with proper project definition and forward planning followed by careful management of costs, time and resources (CTR) during the execution phase so as to extract maximum economic value from the investment. In addition, today s project management techniques call for the routine application of risk management and value assurance processes in order to reinforce the project s value proposal. This paper takes as a null hypothesis (H o ) that fully effective project management will lead to value maximization whereas our proposed alternative hypothesis (H 1 ) is that without the addition of an appropriate Risk Based Assurance Process maximum value will not be achieved. The case of the OKLNG Liquefaction Project in Nigeria is used to support this contention. It is relevant that many major capital investment projects today are running into $ multi-billions when the engineering contracting industry is overheated and struggling to keep up with orders. Consequently bidders can pick and choose which projects they tender for and what price tag they offer. The result is that record high bids are being tendered and, compounded by high oil & gas prices, we see little sign of - 1 -
2 relaxation soon. With respect to LNG liquefaction projects, currently quoted construction costs per tonne of output have multiplied in the last 10 years even though train sizes, hence economies of scale, have also multiplied yet not as much. We seek to develop our alternative hypothesis against the above background. 2. The OKLNG approach to the challenge of Value Management Competitive advantage is achieved by operators of major LNG projects through the provision of longterm plant reliability, quality of construction, lowest cost of production and customer service. Since project uncertainty can be said to grow in proportion to size, so for a mega project the uncertainties are significant and processes that identify, assess and contribute to the effective understanding and management of these uncertainties are needed. At OKLNG we set out to create a process that integrated the creation of Value with the management of Risk. The key objective was to integrate the steps of Value Creation and Assurance, Risk Identification, Assessment and Management together using a number of standard value management and risk management processes and tools, but ensuring they worked as one integrated process and not as individual functions. At this time the project is in the pre-sanction phase and is looking primarily to create maximum value to all stakeholders. It is within this environment that OKLNG recognized that a process that integrated Risk and Assurance was going to be difficult to achieve but necessary in order to create and retain value from erosion during the life of the project. The theory states that the basic principle of the Value process is to recognize the project objectives, being the shareholder targets related to CAPEX, Schedule, HSSE (Health, Safety, Security and Environment), etc. The resources necessary to achieve these need efficient management to secure these requirements cost effectively. But, the initial challenge in assurance terms is to land on a universal agreement of what each shareholder considers the objective to be and then translate these requirements into absolute measures. Historically, Project Management normally organizes the Value Management and Risk Management functions as two groups not integrated within the portfolio of the same manager. Thus their integration has been largely dependent on the experience of the personnel and the effectiveness of the relationship between the key functions - being our (H o ) condition. In OKLNG we created a common process for these two functions that defined the working terms between them and applied control processes to ensure there was a management compliance regime monitoring the work - the (H 1 ) condition. The challenge to this process is the fact that Value is not an absolute criterion, but a relative one. Perception of risk levels and potential impacts varies between individuals and tolerance towards differing perceived levels of risk exposure varies between each shareholder organization. In theory the assurance steps should be easy: agree Value requirements / criteria, apply internal processes that enable the project team to achieve these objectives etc. So, at any time during project development the dependent variables can be the project objectives and the independent variables are the varying tolerance each shareholder has towards the risks perceived. However, within just a few weeks the dependent and independent can switch round without a trend being observed. The inter-play between Risk and Assurance is critical to maintain the effectiveness of Project Management. Ordinarily without this integration a significant amount of time would be lost as the interfaces between assurance, project management and risk management reacted to the changed requirements. It is for this reason that the full integration of Risk Management with Value Assurance through common systems and governance that the (H 1 ) condition is more likely to contribute to project success. 3. Defining Value Assurance If you refer to Value Assurance codes of practice no absolutely clear definition readily presents itself
3 To succeed in making real and objective improvements in value it is necessary to have a basis for defining value that is quantifiable in economic terms e.g. IRR, NPV, PWI. In the case of the OKLNG Project, complicating the challenges still further is the fact that the OKLNG value chain includes the Upstream gas suppliers, the Midstream LNG plant and the Downstream Offtakers. Within the Midstream group are a number of major contractors who are responsible for the Engineering, Procurement, Construction, Commissioning and Start Up. It is in the Midstream that the focus of effort for the Risk Based Assurance Process is concentrated, but Upstream and Downstream play an essential part in creating a technically and commercially viable Midstream project. So, in broad terms, Value Assurance is a process that aims at providing project management and owners with qualitative and quantitative assurance and assistance at critical decision points, through a process of, facilitation, independent challenge and review. Value Assurance is particularly important because LNG development projects are extremely capital intensive and represent long term commitments. The key objectives can therefore be summarized as: Improve time to market Reduce CAPEX and OPEX Identify opportunities for value creation Control project performance Suggest possible improvements Solve technical problems Ensure alignment of effort across the venture Create a dynamic mechanism between Risk Management and Value Assurance that allows the interplay between project objectives and risk tolerance within the venture to be managed effectively across the complete value chain. CONTEXT OF AN LNG PROJECT Relative to other major capital projects in the oil & gas industry LNG facilities can be characterized as follows: Large scale (both in construction effort and in sizes of equipment and tankage) Atlantic and Pacific Basin market-based (predominantly) Substantial and multiple risks: e.g. seasonal and long term product price volatility, gas reserves commitments, political, technical, fiscal, etc. Capital investment costs are from $100 millions into several $ billions High tax take along the value chain Long term project and sales/purchase contract life cycles: typically years. In light of the increasing number of LNG liquefaction projects targeting the same market - and here we are concerned with the Atlantic Basin market - mainly the US Gulf and North East Coasts and Europe - particular importance is attached to the competitive situation; such aspects as reliability of delivery to customers, flexibility in case of changes in shipping nominations, quality of product, relationship with feedstock suppliers, low cost of production - and all on a larger scale than most industries where we, at OKLNG in Nigeria are talking of multiple trains totaling approx. 20 million TPA of LNG output. From a broader perspective there are socio-economic benefits too in the form of job creation, community development, trading opportunities for supplies and services, etc. Spin-offs can include adjacent projects for domestic gas supply, power generation and possibly infrastructure development. Given the above, and our project example, there is also the dimension of its place in the overall gas value chain: Exploration Production Gathering and Pipelining Liquefaction (OKLNG Project) Shipping Receiving and Regasification Gas Marketing
4 Thus for the investors - who usually have an interest in more than one component of the value chain - the maximization of value across the whole value chain is an important consideration, relative to the purely LNG liquefaction component which is usually a buy gas - sell LNG model, and when today it is not acceptable for one part of the value chain to subsidize another. Present LNG trade uses long term (15+ years) gas supply and LNG sales contracts where optimization of storage capacity and shipping terminal facilities represent bottlenecks on capacity and flexibility - both having major capital investments associated with them and both not cheaply or quickly expandable. This consideration stems from the batchwise handling of LNG into ships when compared to the continuous flow of feed supply gas and the continuous, yet daily and seasonably variable, demand for gas in the market place. Integration of the shipping component is largely by a dedicated fleet, purpose-built for the project concerned; relatively little spot LNG shipping capacity is available today, yet trends towards it are emerging. This is to be compared with the crude oil transportation industry where tankers are chartered on a per voyage or short-medium term basis from shipowners who have no financial interests in the crude oil production facilities nor the refineries and who are in the business of chartering vessels at the prevailing market rate per voyage. Needless to say, an alignment of purpose throughout the whole LNG value chain is needed to ensure success in any segment, recognizing the different risks and returns applicable. In saying this, it is often considered that the liquefaction plant is the enabler for the full value chain - so characterized because (1) it is often the most significant investment in the total value chain, (2) its capacity, whilst expandable due to the modular train concept, once set becomes the limiting factor for the economics of the overall value chain (since the LNG business is characterized by economies of scale, and certainly when a green field project is contemplated). IMPLICATIONS FOR MANAGING A COMPLEX MEGA PROJECT TO MAXIMIZE VALUE Of particular importance is the relationship between Project Management Systems (PMS) and Value Management Systems (VMS). The PMS aims at helping the Project Team perform activities within schedule, budget and with the required quality, while the VMS aims at helping the Project Team identify every opportunity for value creation while performing these activities. The performance of Value Management activities improves confidence that one stage is sufficiently complete and that conditions are right for progression to the next decision point. For this reason VMS activities need to be planned in accordance with the Project Schedule. In linking them to the project schedule they should also be linked together. An assurance event may provide input to a subsequent assurance activity. The project development stages are: 1. Evaluation (Gate) 2. Concept Selection (Gate) 3. Concept Definition (Gate) 4. Execution 5. Production Between each stage there is a Decision Gate made up of Technical, Business and HSSE criteria which need to be satisfied before the project can proceed. The Front End Loading (FEL) criteria that need to be complied with are: 1. Have we selected the Best Option from an appropriate range of options? 2. Are plans in place to successfully complete the Definition phase? 3. Are plans in place to fully prepare for the Execution phase? 4. Are all Risks identified and mitigation plans agreed? The objectives of Value Management are to: Establish processes which create and retain value for owners Apply appropriate levels of Assurance during project design & execution Apply high quality Decision Making processes consistently Apply Governance through a Risk & Assurance Committee - 4 -
5 Maintain an integration with the changing levels of risk and potential variations to project objectives, primarily influenced by the parties in the value chain during the pre-sanction phases. The Value Management Functions are: Integration of Project Scope and Objectives Statement (PSOS) Execution Plan Resource Plan Risk & Opportunity Plan Value Assurance Plan Development basis assumptions Decision Making Knowledge Management Value Management Processes Define FEL criteria / categories. The tools and techniques of Value Management are: Value Assurance Methods Value Improving Practices Value Tracking Risk Management Decision Making Knowledge Management and Close Out. Value Assurance Methods provide assurance to shareholders and decision makers and assistance to the project at critical decision points (Gates) through a process of support, independent challenge and review of project activities and deliverables. Value Assurance in its formulation phase brings the team together and reviews the purpose, goals, objectives and constraints of the project. Available information is then shared and reviewed construction issues and driving forces for achieving a successful project with the lowest installed cost and highest profitability are captured. The challenge for any project is to deliver these elements in an integrated way as the project reaches the stage of commercial viability. Value Improving Practices increase project value by applying systematic techniques and methods to reduce design excesses, challenge methods and assumptions. Value Tracking to continuously assess the increase to project value being made by the process. Risk Management minimizes the probability and consequences of adverse events and ensures those risks accepted by the project have been allowed adequate contingency in the budget if they were to occur. Decision Making helps decision makers improve decision quality by offering a methodology that links data structuring, evaluation and agreement. Knowledge Management and Close Out helps the development project team to look back and analyze what went well or badly, learning and extrapolating from the process. To obtain the best possible results, the implementation of Value Management methods should begin early on in the pre-development stages of the project during evaluation and concept selection. They should subsequently be used as a continuous improvement mechanism for ensuring maximum cost effectiveness, functionality and appropriate quality. Value Management is often seen as more of an upstream activity in comparison to Risk Management which is probably true for most projects but not for those with similar value chains to OKLNG and demanding such a large financial investment. For this reason value management needed to be progressed together with Risk Management in a complementary way
6 Value Management coordinates and controls the work flow during each project phase ensuring the criteria for meeting shareholder expectations at the next decision gate are fully understood and that the work effort is project managed to ensure adequate emphasis is placed on the key criteria. Professionally they have developed as separate specialisms without an integrating methodology. Value Management integrates the efforts of the Project Team, contractors and the overall venture with those of shareholders to provide a focus on value throughout the organization. The resulting atmosphere encourages innovation, draws on synergy of people working together and results in a better use of resources in fulfilling the Company s objectives. Value is often considered to be the excess of satisfaction of needs over the resources used in achieving that satisfaction. Each stakeholder has its own needs and a different idea of what constitutes value. Value is therefore not objective but subjective. Achieving good value usually means balancing a series of conflicting parameters in order to reach an optimum position. To assist in overcoming these differences the engagement with shareholders is to enable joint participation at Peer Assist meetings where guidance is sought, Peer Reviews of the work underway and Value Assurance Reviews where the work completed in each phase is verified and accepted. A common aspect of these events is that they need to be performed by or with the participation of members external to the project team, usually drawn from experts, partners or third parties. To obtain the best possible results, the implementation of Value Management methods should begin early on in project development. They should be subsequently used as a continuous improvement mechanism for ensuring maximum cost-effectiveness, functionality and appropriate quality. Regarding the area of conventional Risk Management, the process universally followed on projects is to identify and quantify the important risks - on the basis of their impact and frequency - and then produce mitigation plans that are applied to reduce the risks to the lowest possible levels. On the assumption of a full mitigation (as appropriate to each risk) investment and other commitment decisions can be taken in an informed environment, usually enhanced by the benefits of stochastic modeling techniques. The intersection of Risk Management and Value Assurance can be said to be fully at the centre of Value Management, namely: Value Assurance is applied within the Risk Management process to integrate the areas of uncertainty with the project management work program. In this instance each risk in the risk register is coded to a Value Assurance deliverable, event or decision gate criteria for the end of the present phase and following one. In addition, each risk can be assessed for its residual impact and contingency provision can be made in the budget; the mitigation strategy and the application of the mitigation strategy are done properly and done to a high quality - particularly as the risks and mitigations shift in response to changing circumstances from inside the project and outwith. Risk Management is applied to the Value Assurance process in an oversight capacity to capture risks that surface from Peer Assists, Peer Reviews, Value Assurance Reviews, etc
7 Integrated view of the Risk Based Assurance Process PROCESS PRACTICALITIES 1. Guiding Principles of Value Management (VM) Focus on overall business value rather than just technical solutions Align with best practices in the sector Focus on decision checkpoints not by activity completion Ensure project objectives are communicated to the team and a common understanding is created Provide sufficient flexibility for managing different aspects of the project in terms of complexity, costs and scale of investment. 2. Front End Loading It is also relevant to recognize the application of Front End Loading (FEL) criteria which set out the scope needed, usually from an external perspective, to be completed to pass through each decision gate. These criteria serve to focus on the scope to be completed, clarify responsibilities and also to measure remaining uncertainty as further funding is sought to progress towards greater definition and project sanction. Standard checklists are provided by FEL consultants to facilitate this process and they are often asked to provide an independent project evaluation to support the material used to assess the project s readiness to proceed to the next stage. 3. Apply Good Practice and Control - 7 -
8 The process of developing accurate and consistent engineering design involves the adherence to applicable codes of practice, the integration of design data into system design, and the management of changes that internally occur within the design team as well as those emanating externally from outside the project. This discipline, again, contributes to good Value Management. 4. Value Management Programme (Coordination & Control) It should be prepared early in the evaluation phase and updated at the beginning of each phase. It should use Value Management Policy itself and the Project Scope and Objectives Statement as input to ensure that it reflects the specific objectives and characteristics of the project. It should cover: Roles and Responsibilities Identification of key value drivers Selection of appropriate techniques for carrying out VM (Peer Reviews, Peer Assists, technology selection, Value Engineering etc) Resource / team /timetable /budget Integration of Value Management with project activities Key Performance Indicators (KPIs) and other means for measuring value results Training for project team members Identification of VMS areas (Value Assurance, Risk Management etc) to be applied to the project. 5. Value Management Studies The studies should follow a structured job plan with the following stages: Planning Information Analysis Creative Evaluation Reporting Implementation The performance of Value Management studies improves confidence that one stage is sufficiently complete and that conditions are right for progression to the next stage. For this reason Value Management studies need to be planned in accordance with the Project schedule. 6. Value Assurance Reviews All types of assurance events are performed in the interests of the Project. However, Joint Assurance Reviews (JARs) are principally decision maker driven, while Peer Assists and Peer Reviews are more team oriented. The main purpose of the JAR is assuring shareholders and transferring knowledge to the Project Team. Peer Assists and Peer Reviews on the other hand, are mainly aimed at creating learning opportunities for the Project. Joint Assurance Reviews (JARs) are independent reviews examining all the aspects of a project before accessing a decision gate. JARs take a broad view of the project before a decision gate and provide assurance and assistance both to the project team and to the decision makers. On major projects JARs drive the overall Value Assurance process and are performed at the end of each phase - hence the need for an Assurance Plan which defines the timeline and terms of reference for each JAR and supporting event. 7. Risk Based Assurance Process The conventional project management approach is towards cost control and achievement of engineering, procurement and construction schedules - yet this denies the concept of value contribution. Our fundamental proposition is that value can be engineered in to a project and not - 8 -
9 merely identified and captured, but steps deliberately taken to add value to improve overall economic performance alongside cost and schedule imperatives. The following sections enumerate the OKLNG Risk Based Assurance Process model. THE OKLNG CHALLENGE The key attributes of the project are: Build an LNG Liquefaction plant, marine loading facility and offsites, utilities and infrastructure at an undeveloped green field site in Nigeria Process gas and produce LNG at a rate of approx. 20 million TPA for export, including byproducts production and sale Implement a fit-for-purpose world class facility using equipment and systems with wellproven reliable performance, all at a competitive unit cost. Implications for Venture Management follow: To consolidate a business case which has the following structure: 1. Business Proposal 2. Project Scope and Objectives Statement (PSOS) 3. Project Development Plan 4. Project Execution Plan 5. Operations Strategy Plan 6. Procurement Strategy Plan 7. Project Organization Plan 8. Gas Supply and Offtake Plan 9. Risk Register 10. Risk Management Plan 11. Value Management Plan 12. HSSE Plan 13. Joint Assurance report 14. Concept Definition Phase Report To focus the engineering mind it is necessary to address the following: - 9 -
10 Setting the Business Goals (Pre-event) Setting the Business Goals is a communication process that identifies the shareholders requirements and expectations associated with business opportunity / problems and ultimately translate them into project goals, ranked according to their relative importance to the business strategy. This puts the shareholders of the business in alignment with the project team who can deliver the business results. Value Improving Practices Value Improving Practices (VIPs) is an area of the VMS describing processes and activities that should result in improved project outcomes (e.g. cost, operability, schedule, reliability, safety, etc). They are a systematic approach to obtaining optimum value for money, for example, by reducing non-critical scope items, increasing reliability or simplifying processes. VIPs are distinct, focused activities that are generally applied during the design stages of a project. They should be incorporated into the overall planning of design activities. Value Improving Practices comprise: 1. Technology Evaluation 2. Process simplification 3. Energy optimization 4. Waste Minimization and Management 5. Availability / Reliability / Operability 6. Design to Capacity 7. Maintainability 8. Constructability 9. Process Reliability Modeling 10. Codes & Standards 11. Predictive Maintenance 12. Value Engineering 13. Benchmarking. And the Process Steps to achieve the above comprise: Information gathering Creative review Analysis of requirements and the potential options Development of the recommended proposal Present / Report the findings Implementation of the agreed recommendations. Now, in the evolution of the OKLNG project, value enhancing opportunities have arisen during the Front End Engineering and Design (FEED) Phase which challenges the project to: Reduce capital expenditures and improve economics Identify high cost areas and potential significant reduction of the investment and contribution to the Project rate of return Identify and evaluate Value Improvement Practices. Specific opportunities under evaluation are: Reliability optimization - Variable Cost performance - Fixed Cost Performance CAPEX reductions - Reduce scope & specs - Implement design efficiency - Identify risk allocation and scope shifts Decrease rate of expenditure
11 - Cost effective procurement & sub-contracting schedule Increase Revenue stream - Increase LNG Train capacity - Optimize overall process performance. RISK BASED ASSURANCE PROCESS Risk Management Given that Risk Management is the systematic process of identifying, analyzing and managing risks in order to maximize Project value the process can be considered as the formalization of commonly - used Project Management practices and should be carried out routinely within the Development Project s life cycle. Through the correct assessment and quantification of risk the appropriate mitigation strategy can be applied from the Transfer, Take, Terminate or Treat array. The key steps in this management process are: Identify and quantify the risks Increase knowledge about the risks Identify ownership Define and agree mitigation strategy Manage and monitor the mitigation process Be alert for changing circumstances and assumptions. Project Value can be destroyed by unmitigated risk impact and the process should address this possible consequence in the context of probabilistic analysis of the Schedule, Estimate and Project Economics. Integration of Risk and Value It is often considered that Risk and Value should be linked in the early stages only, however, Value Assurance covers the facets of Value Creation and Value Retention in the fight against the intensification of Risk and the erosion of Value. It should be recognized that Value Creation drops quickly away at Sanction and the battle is then on to retain the value that has been generated. OKLNG realized from past projects that the management of Value and Risk needed to be better integrated and responsible to a governing body to ensure the integration of the disciplines. A Risk and Assurance Committee was therefore formed of the Senior Management Team plus discipline professionals. A basket of criteria that met shareholders requirements was needed and we also identified the criteria that shareholders would likely need to achieve FID (Final Investment Decision), being the start of the Execution phase. For these criteria we assessed the barriers to achieving them and included the potential risk barriers in the Risk Register. The OKLNG Risk Based Assurance Process Recapping; the requirements of a Risk Based Assurance Process are: Create Value Assurance that supports the requirements of the Venture s governance model Integrate the Risk Management, Value Assurance, Venture & Technical Assurance Processes (which includes Quality Assurance) Ensure the expectations of shareholders, the Board and the Senior Management Team are understood, communicated and duly achieved Establish a governance structure: in OKLNG, the Risk and Assurance Committee Enable the project to achieve the overall objectives in a safe, reliable and cost effective way. The continuous cycle that is followed has the following steps: 1. Establish the Assurance Framework and programme aligned to the Project Schedule 2. Progress the project definition - Venture & Technical 3. Monitor the environment around and within the project definition 4. Capture risks and develop opportunities
12 5. Report to the Risk & Assurance Committee (Risk Report + Assurance Report) 6. Revisit the Value Assurance process for alignment to increase / decrease the degree of Risk and Assurance work. To put the Risk Based Assurance Process into operation: 1. Establish the Audit Plan Project-wide (H o ) 2. Establish Governance - here the Risk and Assurance Committee (H 1 ) 3. Implement Risk Process Project-wide (H o ) 4. Produce and issue the Assurance Plan appropriate to the present Phase of the Project (H o ) 5. Set up Terms of Reference for Expert Committees (H 1 ) 6. Monitor the Value Improving Practices Processes at engineering contractors offices (H 1 ) 7. Integrate the above processes with the contractors (H 1 ). Current Structure of the Risk Based Assurance Process: - Processes being applied are: 1. Risk Management 2. Key Decisions (Decision Analysis / Decision Quality) 3. Knowledge Management 4. Benchmarking 5. Governance - all subject to Peer Review & Peer Assist to frame the appropriate processes. - Scope of Assurance Area is: 1. Joint Assurance Reviews (JARs) 2. Peer Assists 3. Peer Reviews 4. Expert Committees 5. Sponsor Audits 6. Internal Audits 7. VIP exercises - all applied to the processes within the Venture s overall business context. - Controls: 1. Assurance Plan (Scope of the Assurance Area) 2. Audit Plan (for OKLNG & Contractors) 3. Document Matrix (Project Management Procedures) 4. Policies & Procedures 5. Risk Register. - Compliance: 1. Risk and Assurance Committee (formed from the Senior Management Team) 2. Shareholders Audit Committee. Operationalizing the above To get a sense of how the above processes and procedures work in practice, discrete activities have to be managed jointly, for example: Integration of Risk Management and Assurance Integrated Action Tracking applied for OKLNG Benchmarking of other project risks Integration of engineering contractors into the Value Assurance Process Implementation of Best Practices and Lessons Learned from other sources Quantitative Risk Analysis - input to contingency plans OKLNG compliance with external Risk Management exigencies (e.g. Sarbanes-Oxley)
13 Trend Analysis of Project Risks through Assurance Activities and the recognition of residual impacts on the Venture s economic viability. It is useful to recognize the different levels of Technical and Venture Assurance as determined by the intervention situation: Level 1: Project structure / continuous Improvement Level 2: Performance improvement methods Level 3: Independent expert support Level 4: Engagement of shareholders - Expert Committees. And the intervention levels of Decision Making: Level 1: Shareholder decisions Level 2: Project / Venture decisions (Board) Level 3: Group decisions (General Managers) Level 4: Contractor decisions. With regards to the Decision-Making Process three phases were followed: 1. Structuring Phase to: 1.1 Identify or clarify the problem or opportunity 1.2 Assess the business situation 1.3 Create alternatives 1.4 Develop a decision model. 2. Evaluation Phase to: 2.1 Discover what is important 2.2 Quantify the risk and return 2.3 Determine value of new information. 3. Agreement Phase to: 3.1 Decide on course of action 3.2 Allocate appropriate resources 3.3 Implement course of action. Finally, our Risk Based Assurance Process acknowledges that the capture of Lessons Learned & formal Close Out procedures are not only associated with quality processes but provide a useful forensic attribute should this be required under the governance remit. In this regard, we are seeking to: ensure that each project takes maximum advantage of all lessons learned onto other projects, such as expansion projects, gather all learning the Project Team has accumulated during the project, and from past projects of a similar nature, so as to leverage learning and facilitate quality accreditation. CONCLUSIONS Recognizing: Different perceptions and attitudes towards Risk and Value between shareholders as well as amongst the management team, hence the challenge of aligning and prioritizing project objectives for all stakeholders The diligence necessary to successfully and simultaneously implement a Risk and an Assurance process to be able to understand, communicate and manage the value proposition represented by the project opportunity That comparison to other projects will inevitably occur such that clarity of derivation and justification of actions will need to be documented
14 - we propose that a Risk Based Assurance Process is not only appropriate but that it is superior in terms of ultimately maximizing value. With the above review and argumentation we suggest rejection of H 0 in favor of H 1, thereby hypothesizing that the addition of an appropriate Risk Based Assurance Process is necessary, in addition to effective project management, in order to achieve maximum value from a given project
DECISIONS BETWEEN RISK AND UNCERTAINTY EXPERIENCES FROM MAJOR LNG PROJECTS
DECISIONS BETWEEN RISK AND UNCERTAINTY EXPERIENCES FROM MAJOR LNG PROJECTS 32 nd IAEE International Conference June 21-24, 2009 San Francisco, Ca. John Holding, OKLNG FZE (London, UK) Dieter Beike, Independent
More informationThinking about tomorrow: capital efficiency
Thinking about tomorrow: capital efficiency in the GCC One billion Dollars. Seven billion Dollars. Ten billion, 30 billion, 100 billion, 130 billion Dollars! These numbers reflect neither the GDP of any
More informationLNG Experience. Owner & Investor Project Management
LNG Experience Owner & Investor Project Management Project Management (Operator / Investor) Most mega projects fail to meet FID Cost & Schedule Contracting Strategies are not meeting the challenges Regulatory
More informationTransaction Advisory Services. Operational Transaction Services. Working with you to make your transaction a success
Transaction Advisory Services Operational Transaction Services Working with you to make your transaction a success Operational Transaction Services Canada offers substantial growth opportunities for both
More informationSoftware Project & Risk Management Courses Offered by The Westfall Team
Software Project & Risk Management is a 5-day course designed to provide a knowledge base and practical skills for anyone interested in implementing or improving Software Project and Risk Management techniques
More informationGuidance on portfolio, programme and project management
Guidance on portfolio, programme and project management The Standard for Infrastructure Procurement and Delivery Management (SIPDM) defines the following two generic terms: Portfolio: collection of projects
More informationCAPITAL INVESTMENT SYSTEMS MAKING THE RIGHT INVESTMENT DECISIONS
INTRODUCTION CAPITAL INVESTMENT SYSTEMS MAKING THE RIGHT INVESTMENT DECISIONS Neil Cusworth Managing Director Enthalpy Pty Ltd Investment decisions to develop or acquire new capital assets should be made
More informationAchieving Organisational Goals. Accomplishing Strategic Initiatives. Implementation of Organisational Objectives. Stakeholder Management
Achieving Organisational Goals Accomplishing Strategic Initiatives Implementation of Organisational Objectives High Quality Training Courses presented by Internationally Recognised Expert Speakers Stakeholder
More informationTHE STANDARD FOR PROGRAM MANAGEMENT
THE STANDARD FOR PROGRAM MANAGEMENT COURSE STRUCTURE INTRODUCTION Module 1 PROGRAM MANAGEMENT PERFORMANCE DOMAINS Module 2 PROGRAM STRATEGY ALIGNMENT Module 3 PROGRAM BENEFITS MANAGEMENT Module 4 COURSE
More informationSYNOPSIS OF THE 2017 NATIONAL GAS POLICY
SYNOPSIS OF THE 2017 NATIONAL GAS POLICY Introduction On Wednesday, June 28, 2017, the Federal Executive Council (FEC) at its monthly meeting approved the National Gas Policy, 2017 ( NGP ). The NGP, which
More informationMicrosoft REJ Framework: Step by Step
Microsoft REJ Framework: Step by Step Quantifying the Business Value of Information Technology (IT) Investments Abstract IT managers today face challenges of delivering products to markets faster, making
More informationGleim CIA Review Updates to Part Edition, 1st Printing June 2018
Page 1 of 15 Gleim CIA Review Updates to Part 1 2018 Edition, 1st Printing June 2018 Study Unit 3 Control Frameworks and Fraud Pages 66 through 69 and 76 through 77, Subunit 3.2: In accordance with the
More informationBusiness Case for Value Realization During Implementation Delivering Projects on Time, on Budget, and on Value
SAP Thought Leadership Value Realization Business Case for Value Realization During Implementation Delivering Projects on Time, on Budget, and on Value The Business Transformation Services group of SAP
More informationAUSTRALIAN ENGINEERING COMPETENCY STANDARDS STAGE 2 - EXPERIENCED PROFESSIONAL ENGINEER IN LEADERSHIP AND MANAGEMENT
AUSTRALIAN ENGINEERING COMPETENCY STANDARDS STAGE 2 - EXPERIENCED IN LEADERSHIP AND MANAGEMENT The Stage 2 Competency Standards are the profession's expression of the knowledge and skill base, engineering
More informationImproving project delivery in oil and gas: managing the megaprojects
Improving project delivery in oil and gas: managing the megaprojects The oil and gas sector is increasingly dominated by megaprojects, typically characterized by their complexity and highly technical nature,
More informationHOW AN INDUSTRIAL BASELINE SURVEY CAN INFORM LONG-TERM STRATEGIC PLANNING AND FACILITATE CREATION OF SUSTAINABLE ECONOMIC LINKAGES
HOW AN INDUSTRIAL BASELINE SURVEY CAN INFORM LONG-TERM STRATEGIC PLANNING AND FACILITATE CREATION OF SUSTAINABLE ECONOMIC LINKAGES Framework Step: STEP 2 - Build an empirical basis to inform decision-making
More informationAsset Management Policy
Asset Management Policy January 2018 Introduction Our Asset Management Policy was last published in 2014. It is being updated to reflect our commitment to regularly review and improve all of our Asset
More informationProject Management Session 6.2. Project Initiation Phase Integration Management
Project Management Session 6.2 Project Initiation Phase Integration Management 1 Project Phases & Knowledge Areas 1. Integration 2. Scope Management 3. Time Management 4. Cost Management 5. Quality Management
More informationAML model risk management and validation
AML model risk management and validation Who we are EY s Anti-Money Laundering (AML) and Regulatory Compliance Technology practice is a global team of client-serving, financial services professionals.
More informationThe EFQM 2013 Model Changes. Implications for Organizations
1-June-13 The EFQM 2013 Model Changes Implications for Organizations by Sunil Thawani EFQM reviews the EFQM Excellence model every three years to ensure it continues to reflect reality and relevance to
More informationGet Better Business Results
Get Better Business Results From the Four Stages of Your Customer Lifecycle Stage 4 Retain How to Retain Your Profitable Customers A white paper from Build in Retention and Profitability at Each Stage
More informationGet Better Business Results
Get Better Business Results From the Four Stages of Your Customer Lifecycle Stage 4 Retain How to Retain Your Profitable Customers A white paper from Build in Retention and Profitability at Each Stage
More informationUNIVERSITY OF CAMBRIDGE INFORMATION SERVICES COMMITTEE PROJECT AND PROGRAMME GOVERNANCE: DOCUMENTATION GUIDE: STAGE GATES
UNIVERSITY OF CAMBRIDGE INFORMATION SERVICES COMMITTEE PROJECT AND PROGRAMME GOVERNANCE: DOCUMENTATION GUIDE: STAGE GATES Document Status: Approving Body: Last Update: Author: Approved Information Services
More informationThe Communications Audit NEVER MORE RELEVANT, NEVER MORE VALUABLE:
WHITE PAPER The Communications Audit NEVER MORE RELEVANT, NEVER MORE VALUABLE: VALUE PROPOSITION OBJECTIVES METHODOLOGY BY GARY DOLZALL CHIEF COMMUNICATIONS OFFICER I. INTRODUCTION: THE VALUE PROPOSITION
More informationIntroduction. The Assessment consists of:
ESG / Sustainability Governance Assessment: A Roadmap to Build a Sustainable Board By Coro Strandberg President, Strandberg Consulting www.corostrandberg.com November 2018 Introduction This is a tool for
More informationQuality Management System Guidance. ISO 9001:2015 Clause-by-clause Interpretation
Quality Management System Guidance ISO 9001:2015 Clause-by-clause Interpretation Table of Contents 1 INTRODUCTION... 4 1.1 IMPLEMENTATION & DEVELOPMENT... 5 1.2 MANAGING THE CHANGE... 5 1.3 TOP MANAGEMENT
More informationINTRODUCTION TO QUALITY ASSURANCE
INTRODUCTION TO QUALITY ASSURANCE Basic Quality Terminology No more definitions...please! Page 1 Quality is the degree to which a specific product conforms to a design or specification H.L. Gilmore Product
More informationAgenda. Enterprise Risk Management Defined. The Intersection of Enterprise-wide Risk Management (ERM) and Business Continuity Management (BCM)
The Intersection of Enterprise-wide Risk (ERM) and Business Continuity (BCM) Marc Dominus 2005 Protiviti Inc. EOE Agenda Terminology and Process Introductions ERM Process Overview BCM Process Overview
More informationStrategic Gaming. An Introduction to its Application in Oil & Gas and Energy
Strategic Gaming An Introduction to its Application in Oil & Gas and Energy Contents About Dragonfly Game Theory and Strategic Gaming Strategic Gaming Applications 2 Background 3 Our work has spanned the
More informationAUSTRALIAN ENGINEERING COMPETENCY STANDARDS STAGE 2 - EXPERIENCED PROFESSIONAL ENGINEER
AUSTRALIAN ENGINEERING COMPETENCY STANDARDS STAGE 2 - EXPERIENCED The Stage 2 Competency Standards are the profession's expression of the knowledge and skill base, engineering application abilities, and
More informationProcess Plant Design: The High Cost of Slow Decisions Using Risk Analysis Software to Confidently Speed the Design Process
Process Plant Design: The High Cost of Slow Decisions Using Risk Analysis Software to Confidently Speed the Design Process Paul Donnelly Industry Marketing Director, Engineering & Construction, Aspen Technology,
More informationStrategic procurement in capital expenditure the use of program management & delivery
Strategic procurement in capital expenditure the use of program management & delivery Project Scope Changes Changing Client Needs Environment of Uncertainty Diverse Stakeholder Interests Community Involvement
More informationImplementing Benefits Realization at Farm Credit Canada. Jacob van der Merwe Project Portfolio Manager November 8, 2011
Implementing Benefits Realization at Farm Credit Canada Jacob van der Merwe Project Portfolio Manager November 8, 2011 Learning Objectives Learn how FCC developed its Benefits Realization methodology and
More informationForeword. We would like to thank the dedicated organisations who participated in this work. On behalf of the Get It Right Initiative
A Guide to Improving Value by Reducing Design Error Synopsis 13 key recommendations July 2018 Foreword Members of the Get It Right Initiative, from across all disciplines, have collaborated to create this
More informationISACA Systems Implementation Assurance February 2009
ISACA Pressures Today Pressure to increase realization of value from IT spending Pressure to deliver on IT projects at a time when resources/budgets are constrained Pressure from risk of technology-based
More informationENGINEERS AUSTRALIA ACCREDITATION BOARD ACCREDITATION MANAGEMENT SYSTEM EDUCATION PROGRAMS AT THE LEVEL OF PROFESSIONAL ENGINEER
ENGINEERS AUSTRALIA ACCREDITATION BOARD ACCREDITATION MANAGEMENT SYSTEM EDUCATION PROGRAMS AT THE LEVEL OF PROFESSIONAL ENGINEER Document No. Title P05PE Australian Engineering Stage 1 Competency Standards
More informationEnter Foreign Markets with Advantage
Enter Foreign Markets with Advantage Introduction This note considers the challenges and opportunities for businesses when entering Foreign Markets. I use the term Foreign Market to describe any market
More informationResponding to RFPs. Slide 1 Responding to RFIs and RFPs Welcome this module on responding to RFIs and RFPs.
Slide 1 Responding to RFIs and RFPs Welcome this module on responding to RFIs and RFPs. Slide 2 In this module Companies today are spending more time planning and conducting a comprehensive screening process
More informationGuidelines for the Development of a Policy for Managing Unsolicited Proposals in Infrastructure Projects
Draft Document Shared for Consultation Purposes Only Not for Redistribution Guidelines for the Development of a Policy for Managing Unsolicited Proposals in Infrastructure Projects March 2017 Draft Document
More informationEnergy Services. Your one-stop-shop solutions provider
Energy Services Your one-stop-shop solutions provider We are Uniper We are a leading international energy company with operations in more than 40 countries and 12,600 employees. We combine a balanced portfolio
More informationProject Management Auditing Guide
Project Management Auditing Guide Index Page 1.0 Objective 4 2.0 Risks 4 3.0 Safeguards and Controls 3.1.Project Characteristics 4 3.2.Quality in Project Management Process 4 3.3.Strategic Processes 5
More informationTAMING COMPLEXITY ON MAJOR RAIL PROJECTS WITH A COLLABORATIVE SYSTEMS ENGINEERING APPROACH
TAMING COMPLEXITY ON MAJOR RAIL PROJECTS WITH A COLLABORATIVE SYSTEMS ENGINEERING APPROACH Chris Rolison CEO, Comply Serve Limited The Collaborative Systems Engineering Approach Collaboration A system
More informationCreating a Sustainable PMO for Achieving Effective Business Results By Dennis L. Bolles, PMP DLB Associates, LLC
Introduction Strategic and tactical planning are actions that the executive and senior management of an enterprise can take to assure the successful implementation of a sustainable PMO. Many enterprises
More informationBURNING BRIGHTER, BURNING GREENER. Accenture capabilities for global gas and LNG organizations
BURNING BRIGHTER, BURNING GREENER Accenture capabilities for global gas and LNG organizations PILLARS OF SUCCESS Although LNG companies may follow different paths to profitable growth, there are common
More informationThe Sector Skills Council for the Financial Services Industry. National Occupational Standards. Risk Management for the Financial Sector
The Sector Skills Council for the Financial Services Industry National Occupational Standards Risk Management for the Financial Sector Final version approved April 2009 IMPORTANT NOTES These National Occupational
More informationGuidance on project management
BSI Standards Publication NO COPYING WITHOUT BSI PERMISSION EXCEPT AS PERMITTED BY COPYRIGHT LAW raising standards worldwide Guidance on project management BRITISH STANDARD National foreword This British
More informationRisk Management in the 21 st Century Ameren Business Risk Management
Management in the 21 st Century Ameren Business Management Charles A. Bremer V.P. Ameren Service Center/Information Technology Ameren Services Co. November, 2007 Ameren s History 2 Ameren Today Electric
More information239 Purchasing V4 Current
239 Purchasing V4 Current 1 PURPOSE This policy provides a best practice approach to purchasing for the City of Busselton (the City ). It also ensures compliance with the Local Government Act 1995 ( the
More informationTHE VALUE OF STRATEGIC SOURCING FOR PROCUREMENT PROFESSIONALS
THE VALUE OF STRATEGIC SOURCING FOR PROCUREMENT PROFESSIONALS UNDERSTANDING STRATEGIC SOURCING Maximizing value while minimizing cost is a business imperative across every discipline within organizations.
More informationLevel 5 NVQ Diploma in Management and Leadership Complete
Learner Achievement Portfolio Level 5 NVQ Diploma in Management and Leadership Complete Qualification Accreditation Number: 601/3550/5 Version AIQ004461 Active IQ wishes to emphasise that whilst every
More informationRequirements Analysis and Design Definition. Chapter Study Group Learning Materials
Requirements Analysis and Design Definition Chapter Study Group Learning Materials 2015, International Institute of Business Analysis (IIBA ). Permission is granted to IIBA Chapters to use and modify this
More informationCSR / Sustainability Governance and Management Assessment By Coro Strandberg President, Strandberg Consulting
Introduction CSR / Sustainability Governance and Management Assessment By Coro Strandberg President, Strandberg Consulting www.corostrandberg.com November 2015 Companies which adopt CSR or sustainability
More informationInternational Diploma in Project Management. (Level 4) Course Structure & Contents
Brentwood Open Learning College (Level 4) Page 1 Unit 1 Overview of Project Management The unit 1 covers the following topics: What is A Project? What is Project Management? Project Constraints Tools and
More information4/26. Analytics Strategy
1/26 Qlik Advisory As a part of Qlik Consulting, Qlik Advisory works with Customers to assist in shaping strategic elements related to analytics to ensure adoption and success throughout their analytics
More informationDeveloping a successful governance strategy. By Muhammad Iqbal Hanafri, S.Pi., M.Kom. IT GOVERNANCE STMIK BINA SARANA GLOBAL
Developing a successful governance strategy By Muhammad Iqbal Hanafri, S.Pi., M.Kom. IT GOVERNANCE STMIK BINA SARANA GLOBAL it governance By NATIONAL COMPUTING CENTRE The effective use of information technology
More informationCMMI V2.0 MODEL AT-A-GLANCE. Including the following views: Development Services Supplier Management. CMMI V2.0 outline BOOKLET FOR print.
CMMI V.0 MODEL AT-A-GLANCE Including the following views: Development Services Supplier Management CMMI V.0 outline BOOKLET FOR print.indd CMMI V.0 An Integrated Product Suite Designed to meet the challenges
More informationSignificant Service Contracts Framework
1 Significant Service Contracts Framework The Significant Service Contracts Framework is delivered by New Zealand Government Procurement (NZGP). NZGP delivers on the Ministry of Business Innovation and
More informationProject Management Knowledge Areas SECTION III
Project Management Knowledge Areas SECTION III 1 Project Integration Management CHAPTER 4 2 The Key to Overall Project Success: Good Project Integration Management Project managers must coordinate all
More informationRealizing the UN Global Compact Advanced 2017
Realizing the UN Global Compact Advanced 2017 Vestas Communication on Progress consists of the Annual Report 2017 combined with additional information about Vestas sustainability initiatives at vestas.com.
More informationStrategy Analysis. Chapter Study Group Learning Materials
Chapter Study Group Learning Materials 2015, International Institute of Business Analysis (IIBA ). Permission is granted to IIBA Chapters to use and modify this content to support chapter activities. All
More informationReview of Operations and Activities: Listing Rule Guidance Note 10. Introduction. Issued: March 2003
: Listing Rule 4.10.17 Issued: March 2003 Key topics 1. Review of operations and activities guide 2. Assistance in preparing disclosures accompanying financial statements 3. Recommendations 4. Risk management
More informationBasel Committee on Banking Supervision. Stress testing principles
Basel Committee on Banking Supervision Stress testing principles October 2018 This publication is available on the BIS website (www.bis.org). Bank for International Settlements 2018. All rights reserved.
More informationSTRATEGIC GROWTH AND INNOVATION
STRATEGIC GROWTH AND INNOVATION Building Growth and Business Value Rapidly Through Execution DOMESTIC MARKETS EXPANSION PROGRAM (DMEP) Presented by: Roy Luebke Business Growth Consultant We are the U.S.
More information2. Ofqual level 6 descriptors
Learning Outcomes and Assessment Criteria The learning outcomes and assessment criteria for the Chartered Manager Degree Apprenticeship have been based upon the following: 1. DfEdefinition - level 6 descriptor
More informationDeveloping and Implementing Floating <Title of Presentation>
17 th INTERNATIONAL CONFERENCE & EXHIBITION ON LIQUEFIED NATURAL GAS (LNG 17) 17 th INTERNATIONAL CONFERENCE & EXHIBITION ON LIQUEFIED NATURAL GAS (LNG 17) Developing and Implementing Floating Regasification
More informationVOLUNTARY CODE OF CONDUCT IN RELATION TO EXECUTIVE REMUNERATION CONSULTING IN THE UNITED KINGDOM
VOLUNTARY CODE OF CONDUCT IN RELATION TO EXECUTIVE REMUNERATION CONSULTING IN THE UNITED KINGDOM (December 2015) Preamble Executive remuneration consultants are business advisers who provide a valuable
More informationIdentification Selection Definition Execution. Schedule.
SCHEDULE DEVELOPMENT Schedule development is the identification, definition and sequencing of activities that are required to be performed for successful completion of the project scope. Identification
More information4. Organic documents. Please provide an English translation of the company s charter, by-laws and other organic documents.
Commitment to Good Corporate Governance 1. Ownership structure. Please provide a chart setting out the important shareholdings, holding companies, affiliates and subsidiaries of the company. If the company
More informationMBA Curriculum Program Schedule
MBA Curriculum Program Schedule Click on Course Title to see Course Description Accounting ACCT 600 1 st Semester Finance FIN 620 Leadership & Ethics BUAD 625 Information Technology & Supply Chain INSS
More informationOnline PM Courses. Guide to the Project Business Case. Why and How to Create a Robust Project Business Case
Online PM Courses Guide to the Project Business Case Why and How to Create a Robust Project Business Case Table of Contents 1. Introduction 2. About The Author 3. Great Big Guide to the Project Business
More informationGuidance Note: Corporate Governance - Audit Committee. January Ce document est aussi disponible en français.
Guidance Note: Corporate Governance - Audit Committee January 2018 Ce document est aussi disponible en français. Applicability The Guidance Note: Corporate Governance Audit Committee (the Guidance Note
More informationBalanced Scorecard: linking strategic planning to measurement and communication Gulcin Cribb and Chris Hogan Bond University, Australia
Balanced Scorecard: linking strategic planning to measurement and communication Gulcin Cribb and Chris Hogan Bond University, Australia Abstract This paper discusses issues and strategies in implementing
More information9001:2015, ISO 14001:2015 & ISO
Quality management input comprises the standard requirements from ISO 9001:2015 which are deployed by our organization to achieve customer satisfaction through process control. Environmental input comprises
More informationDriving Success Across the Enterprise with Enterprise Project & Portfolio Management (EPPM) Guy Barlow Director, Industry Strategy
Driving Success Across the Enterprise with Enterprise Project & Portfolio Management (EPPM) Guy Barlow Director, Industry Strategy Chile s Unprecedented Opportunity In 2020 Chile will produce 8.5 million
More informationBotswana Power Corporation (BPC)
Botswana Power Corporation (BPC) Operations Job Specification Position: Template: Technical Services: Senior Engineer (Telecommunications) Business Unit: Print Date: 25 Oct 2017 Page 1 of 8 Position Particulars
More informationModels in Engineering Glossary
Models in Engineering Glossary Anchoring bias is the tendency to use an initial piece of information to make subsequent judgments. Once an anchor is set, there is a bias toward interpreting other information
More informationEngaging the private sector in NBS uptake and implementation: Opportunities and challenges
Factsheet 2 Private businesses lack awareness of market opportunities and appropriate business models for deploying naturebased solutions. GREEN MARKET OPPORTUNITIES AND BUSINESS POLICIES FOR URBAN NATURE-BASED
More information2015 THROUGH RESULTS INTEGRATED THINKING THE BENEFITS OF INTEGRATED REPORTING <IR>
IFAC CREATING GLOBAL VALUE SMP FOR SURVEY: SMEs 2015 THROUGH RESULTS INTEGRATED THINKING THE BENEFITS OF INTEGRATED REPORTING Exposure Drafts, Consultation Papers, and other IFAC publications are
More informationPROJECT MANAGEMENT METHODOLOGY
Put your logo here Put your organization name here Project Management Methodology Rev. 3.0, 4/15/2008 PROJECT MANAGEMENT METHODOLOGY Your organization logo here Your organization name
More informationTurning Enterprise Asset Management into Real Earnings Per Share
Reliability Consulting White Paper November 2018 Turning Enterprise Asset Management into Real Earnings Per Share By Robert DiStefano and Scott McWilliams Table of Contents The Situation... 3 The Challenges...
More informationThe World Bank Oil, Gas, and Mining Policy Division. Study on NOCs and Value Creation. ESW Concept Note
Project Nr. PI09169 The World Bank Oil, Gas, and Mining Policy Division Study on NOCs and Value Creation. ESW Concept Note 1. Introduction National Oil Companies (NOCs) control approximately 90 percent
More informationNOGDAWINDAMIN FAMILY AND COMMUNITY SERVICES
This dictionary describes the following six functional competencies and four enabling competencies that support the differentiated territory for professional accountants in strategic management accounting:
More informationA PRACTICAL GUIDE TO: S.M.A.R.T.E.R. SUPPLIER MANAGEMENT. [ T y p e t h e c o m p a n y a d d r e s s ]
A PRACTICAL GUIDE TO: S.M.A.R.T.E.R. SUPPLIER MANAGEMENT Entire contents 2009 Procurementtoolkit.com. All rights reserved. Page 1 EVALUATION REPORT HISTORY Document Location This document becomes uncontrollable
More informationControl of Documented Information. Integrated Management System Guidance
Control of Documented Information Integrated Management System Guidance ISO 9001:2015, ISO 14001:2015 & OHSAS 18001:2007 Table of Contents Integrated Management System Guidance 1 INTRODUCTION... 4 1.1
More informationProject Management Professional (PMP) Examination Content Outline
Project Management Professional (PMP) Examination Content Outline Project Management Institute Project Management Professional (PMP) Examination Content Outline April 2015 Published by: Project Management
More informationAn Overview of the AWS Cloud Adoption Framework
An Overview of the AWS Cloud Adoption Framework Version 2 February 2017 2017, Amazon Web Services, Inc. or its affiliates. All rights reserved. Notices This document is provided for informational purposes
More information4 The balanced scorecard
SUPPLEMENT TO THE APRIL 2009 EDITION Three topics that appeared in the 2007 syllabus have been removed from the revised syllabus examinable from November 2009. If you have the April 2009 edition of the
More informationThe four steps to Service Management Exellence. White Paper.
The four steps to Service Management Exellence White Paper Table of Contents Executive Summary Introduction Stage One: The Primary Role of Service Management Stage Two: The Operational Role of Service
More informationSTATEMENT ON RISK MANAGEMENT AND INTERNAL CONTROL
STATEMENT ON RISK MANAGEMENT AND INTERNAL CONTROL Pursuant to the Main Market Listing Requirements of Bursa Malaysia Securities Berhad ( Bursa Malaysia ) ( Listing Requirements ), Practice Note 9 issued
More informationSPE Seminar on Introduction to E&P Projects, 17 November 2016, London
SPE Seminar on Introduction to E&P Projects, 17 November 2016, London Managing E&P Projects by Prabhat Garga, Senior Advisor, Upstream Advisors Ltd. T: +44 (0)203 617 7020 E: info@upstream-advisors.com
More informationProtect what is valuable
Protect what is valuable Deal Advisory / Global We can help you achieve successful Sell Side transactions. Supporting growth through active portfolio management and successful divestments. / 1 Your vision.
More information2018 European Payment Processing Platform Customer Value Leadership Award
2018 European Payment Processing Platform Customer Value Leadership Award 2018 Contents Background and Company Performance... 3 Industry Challenges... 3 Customer Impact and Business Impact... 4 Conclusion...
More informationMastio & Company s. Midstream Services Customer Value & Loyalty Benchmarking Study. Metrics to Manage the Midstream Customer Experience
Mastio & Company s Midstream Services Customer Value & Loyalty Benchmarking Study 6 th Edition 2018 Metrics to Manage the Midstream Customer Experience Tel: (001) 816-364-6200 Fax: (001) 816-364-3606 www.mastio.com
More informationPPP Contract Management
PPP Eddie Hannah Infrastructure and Projects Authority March 2017 Agenda 1. What is? 2. Stages of (Project Whole Life) 3. Managing Performance Tools Available (Paymech, Change Control) 4. Lessons Learned
More informationTIPS PREPARING AN EVALUATION STATEMENT OF WORK ABOUT TIPS
NUMBER 3 2 ND EDITION, 2010 PERFORMANCE MONITORING & EVALUATION TIPS PREPARING AN EVALUATION STATEMENT OF WORK ABOUT TIPS These TIPS provide practical advice and suggestions to USAID managers on issues
More informationCorporate Activity Scope3 Scorecard Criteria (Ver.1)
Corporate Activity Scope3 Scorecard Criteria (Ver.1) January 12, 2011 Deloitte Tohmatsu Evaluation and Certification Organization Co., Ltd. Contents A. Introduction... 2 B. About the Scope3 Scorecard...
More informationCapturing synergies to deliver deal value
November 2012 Capturing synergies to deliver deal value A publication from PwC's Deals M&A Integration practice At a glance Value realized from an acquisition depends on how well the newly combined company
More informationImplementation Tips for Revenue Recognition Standards. June 20, 2017
Implementation Tips for Revenue Recognition Standards June 20, 2017 Agenda Overview Journey to implement the new standard The challenge ahead Page 1 Overview Where are we now? Since the new standard was
More informationThis charter defines the purpose, authority and responsibility of News Corporation s (the Company ) Corporate Audit Department.
CORPORATE AUDIT DEPARTMENT CHARTER PURPOSE This charter defines the purpose, authority and responsibility of News Corporation s (the Company ) Corporate Audit Department. The Institute of Internal Auditors
More informationSponsor/CRO Partnership Optimization
Insight Brief Sponsor/CRO Partnership Optimization Developing a CRO Governance Model Geoff Garabedian, Vice President and Managing Director, Consulting at Quintiles Josh Samon, Principal Life Sciences
More information