This first part of the training will be dedicated to cost analysis. The focus will be put on «how to challenge the cost breakdown given by the

Size: px
Start display at page:

Download "This first part of the training will be dedicated to cost analysis. The focus will be put on «how to challenge the cost breakdown given by the"

Transcription

1 This first part of the training will be dedicated to cost analysis. The focus will be put on «how to challenge the cost breakdown given by the suppliers» or if need be : «how to recreate the cost structure of the supplier». 1

2 As an introduction to the cost analysis part of this module, we are going to review together the various types of cost analysis that a buyer or any person involved on cost issues may be willing to perform according to the 3 phases of a project life cycle : design, development and serial production After this introduction our focus will be primarily on the development phase, as it is there that we need to challenge the cost breakdowns given to the suppliers. 2

3 First of all, we need to gather a global picture of the cost analysis issues by considering the 3 key phases in a project life cycle i.e. -The design phase where the functional specification and the first design options are being defined by the project team -The development phase starting right after the design freeze and where the company is developing the detailed solutions for the selected technical concept. At this point we get the tenders on components and material from the vendors. -The serial production or manufacturing phase where the company assembles the components on a daily basis. Depending on the phase we are in, the cost analysis issues are different : - At the design stage, the issue is to estimate the cost of a sub function or a single component for instance : a wire harness, a motor, a stamped cover, etc.. At this early stage, we do not have yet the full technical definition but only a vague definition of the specification. Therefore we cannot get real offers from vendors. However it is possible to make an analogical cost simulation based on key cost drivers in order to estimate the potential cost. An example of such an analogical cost analysis is shortly described in the next slide. -In the development phase, we should be able to get the cost breakdowns together with the tenders of the vendors. At this point the cost analysis issue will be to check the fairness of the price estimations and thus benchmark the supplier offers. We call this kind of approach an «analytical cost calculation» as it means to analyse every line of the cost breakdown given by the supplier i.e. material, machine, labour, overheads and so on. -Finally in the serial production phase, the issue is again different as we assume that we have chosen the right vendor with the right price. So the issue at this point is mainly to reduce the cost of a component or a function by playing with the technical cost drivers, this is why we perform a cost driver analysis. This last kind of analysis is what we need to do when we perform a productivity workshop with the supplier. 3

4 The first of the 3 approaches is done in the design pahse and is call the analogical approach. The basic principle is to calculate a cost based on -An extrapolation made from historical data available for similar components or parts purchased for previous projects -On a family of parts for which it is possible to identify key factors driving the cost. These cost factors (for axemple : power, volume, standard / non standard, ) are then processed with a linear regression analysis in order to find a coherence with the price paid. The table below shows an illustration for a wire harness connector family. As you can see several cost drivers have been identified such as : yearly volume, number of pins, amp level, water and dust tighness, security level, etc. It may appear that s several cost drivers initially selected have no influence on the price. In such a case, the system is requiring that you try other drivers in order to reach the required level of precision of the model. Once this model is built, it can be used for extrapolating the cost of a new project in the same family (as shown in the example) by indicating the values for each driver. 4

5 At this point it is important to comment upon the pros and the cons of such an analogical approach. On the Pro s, it is Well suitable for sub systems which complexity does not allow to make a full piece by piece analysis The other good point is that it can be updated on a regular base For the Con s there are 2 main limits to this kind of approach : -First its is only based on past information - Secondly it cannot be used to define a target but rather to give an idea of what the market currently offers in terms of price. 5

6 The second approach that a buyer may have to use is called the analytical approach It occurs during the development phase. In this phase of the life cycle, the goal is to challenge the offer of the vendors by analysing each cost item of the breakdown i.e. -The material, components and subcontracted operations which covers all material, components and other subcontracted operations the suppliers requires to manufacture the product -The direct labour cost which covers the cost of the direct people needed to run the machines -The machine cost which basically covers the cost of running equipments directly used during the production i.e.; the machines and their equipments (robots, conveyors,..) -The industrial overheads which covers the cost of the industrial support functions such as : engineering, process engineering, logistics, production planning,.. Etc -The SG&A which stands for sales, general and administration expenses that cover the cost of the company support functions such as sales, general administration, finance and accounting,.. etc -The operating profit which corresponds to the income generated by the vendor from his operational activities. -The packaging and the transport cost which includes the cost of the packaging elements (if any) as well as the transport to reach the customer. The sum of all these cost item gives the price we should pay for this piece or sub assembly. 6

7 In this third and last phase of the project life cycle i.e. the production phase, the cost driver analysis seeks to identify the generating factors of the cost in order to seek cheaper alternatives (during a workshop for instance). There are 2 categories of cost drivers : -The functional drivers which are related to the customer specification (i.e. functionality and performance). For example on a fog lamp for a car : to be able to work under ambient conditions : from -40 C up to + 80 C -The technical drivers which are related to the technical solution (i.e. COMPANY design and/or the supplier organization). For example on the fog lamp : an aluminium casting reflector or manual deburring of the seal aftar demoulding. These 2 solutions are the result of a choice either made by THE COMPANY (for aluminium casted part) or by the supplier (for the manual deburring). They both drive the cost because of their complexity in terms of operational implementation ti i.e. expensive material (aluminium), expensive process (casting or deburring). 7

8 Before we enter into the details of the cost calculation rules, we shall first give a global view of the cost analysis process. 8

9 This cost analysis process is composed of 5 steps. The very first step of the cost analysis process will be to ask the supplier to give us a detailed quotation based on the standard COMPANY format. Please click on the icon on the top right part to access this template on line. This standard and generic template may be completed by some additional breakdown formats, specific to a family of parts. Please click on icon 2 and 3 to access the 2 examples for injection moulding parts and metal stamping. The second step of the cost analysis process will be to challenge the figures with the rules of calculation as well as with benchmark information in order to point out inconsistent figures or mistakes, This comparison will enable us to detect discrepancies between our calculation and that of the supplier. The 3rd step of the process will be to collect more information on the supplier s GENBA. In fact several discrepancies may be related to some specific organizational reasons that we need to understand by going deeper in the analysis. This GENBA information can be obtained using different ways : 1 - Use SQA visits 2 - organize some cooperative productivity workshops 3 - Update the PPAP. This deeper understanding of supplier s GENBA, will help us to sort out the various justifications of the discrepancies : Either : Critical operation requiring more time or resources than initially planned Or : Pure commercial reason indicating some hidden margin. The 4th step will be the recreate the should cost taking into account the criticalities of the GENBA. Finally the fifth step will be to start again to negotiate with the supplier using the simulated should cost. Please click on the icon on the top right part to access this template on line. This standard and generic template may be completed by some additional breakdown formats, specific to a family of parts. Please click on icon 2 and 3 to access the 2 examples for injection moulding parts and metal stamping. 9

10 In order to challenge the cost information given by the supplier or maybe recreate the cost structure, we need to explain now how to perform the calculation of each cost item i.e. the material cost, the direct labour, the machine cost,, the industrial overheads, the SG&A expenses and the profit. 10

11 Let s start first with material cost 11

12 Calculating the cost of the material and the components is the result of the multiplication of 3 factors : the gross weight or the quantity consumed, the cost per Kg or per unit and the percentage of handling cost which covers the cost of buying the material (cash cost), and the inventory carrying cost (insurance, space, depreciation, etc..). For this cost item we must take care of the usual pitfalls : - Always check the gross weight. The initial estimation may come from a theroretical calculation done at an eraly stage of the project. The reality may turn out to be different, and since material may be a significant share of the cost, it is important to check it. It strongly advised to check these weights before performing the cost analysis and without the presence of the supplier. - The cost per kg or per unit may be quite dependant on the ordering quantity. The supplier may have a bad price because is order too little quantities. - The handling cost should stay in the range of 4 to 5%. It may in some specific case exceed 5% but it should then be justified by a low unit value, and or a space constraint. - The recycling of the material must be clearly shown in material cost calculation either it is reprocessed (for example in plactic injection moulding) or sold (aluminium, steel, plastics,.) 12

13 Here is an illustration of the calculation of the cost of material for a plastic injected cover. The key input data for this example are the following : -The type of material is PBT -The material cost / kg is 2.65 /Kg -The handling cost is 4% - The gross weight is 150 g - The net weight is 140 g - The scrap rate is 2% - The maximum authorized share of regrained material is 5 % of piece weight hti.e. 7 g (i.e. 5% of 140g) - The non regrained material is sold at a value of 0.8 / kg The calculation of the material cost is the following : Material loss = the difference between the gross weight and the net weight (10 g) + the scrap (150 g x 2% = 3g) the regrained material (7g) which equals 6 g Thus the material cost is : 0,144 Kg x 2.65 x 1.04 = 0,3969 / piece In this case, the cost of the loss is ( )x = Please note that on purpose, the material loss is not included in the calculation of the material cost. This loss will be added at the very end of the full calculation, after profit and Sg&A in order to avoid considering this loss as an element of the cost breakdown subject to profit margin. 13

14 The second cost item we need to calculate is the labour cost 14

15 Calculating the direct labour cost is obtained by dividing the hourly labour rate by the speed per hour. It is important to have a clear definition of what the hourly rate includes. The hourly labour rate includes wages and salaries social security private pensions so s casualty insurance welfare services (canteens, cultural and recreational activities, ) taxes on labour. It doesn t include any share of indirect labour. For 2006 the benchmarks for hourly labour rates (in / hour) are the following : -France : 22-23, 23 germany : 17-25, Spain : , Japan : 22; Mexico : 2-3, China:1, Korea : 12-13, Portugal : It is also important to note that the speed / hour should be an average production speed for 1 hour and thus should be instant speed multiplied by the OEE. (for instance for an instant speed of 100 parts/ hour with an OEE of 85% the real speed is 85 parts / hour). 15

16 The third item of the cost calculation is the machine cost 16

17 The hourly cost of machines includes only the 5 items of the direct costs of running the equipment i.e. - The depreciation of the investment - The financial interest - The maintenance - The energy cost related to the use of the machine - The cost of the space used by the machine This cost does not include the cost of the support functions such as tool shop or adjusters which are addressed within the cost category called «industrial overheads». Therefore it explains why when we compare the results of our calculation with the supplier s rates (which usually takes the «full machine cost» including overheads) we may find significant differences. 17

18 To perform the calculation of a machine cost, we need 3 different input information : The cost information which includes -The machine cost with its various equipments -The cost of the energy used by the machine ((electricity, gas, etc..) in the country of location - The cost of financing the machine (Interest rate) The technical information which include: - Space occupied by the machine. Usually we consider 4 to 10 times the surface occupied by the machine to account for runways and storage areas. The operational information which includes : - the number of shift the company operates - The number of working days / year. This time can vary a lot according to the industry and the country - the life time of the equipment. The life time can be short for fast moving technologies (3 to 4 years) but rather long (8 to 10 years or more) for stable technologies (stamping, injection moulding). The calculation will consist in calculating the cost of each item over a period of time such as 1hour, 1 year or the whole life time and then divide by the corresponding number of hours. 18

19 A this point it is important to clarify the impact of the efficiency or OEE (overall equipment efficiency) rate in the calculation. The concept of efficiency will be detailed further down in this training module but we can already explain its global purpose. The efficiency indicate the remaining percentage of the time when we exclude all times lost with non efficient work such as : bad quality, failures and breakdowns, reduced speed, set up times and all other down times. In our calculation of the machine hourly cost we do not include the OEE impact. So we assume that the efficient is 100%. The reason is that the efficiency impact will be addressed at the cycle time level when we shall multiply the hourly cost of the machine by the cycle time of the Job done by the supplier. To illustrate this point let us show an example of a stamping machine : -Let s consider an hourly cost of 25 with a speed of 120 shots per minute. This speed was measured during the visit at the supplier. If we assume that the supplier operate with an OEE of 85% then the cost per piece (or shot) can calculated as follow : 25 / 120 x 60 x 85% = 0,00408 / piece (or shot). The efficiency should be related to a specific machine or even sometimes to as specific job and thus it is logical to apply the OEE rate on the cycle time and not on 19

20 The principle is to calculated an hourly cost for each of the 5 cost items i.e : -Depreciation cost -Financial cost -Maintenance cost -Energy cost -And space cost Once all data s have been gathered, we can then sum up these costs in order to get the global hourly cost of the machine. The calculation can be either done with the exact information given by the supplier or based on assumptions of what the normal conditions should be for this kind of activity (stamping, casting,.). 20

21 For depreciation the calculation will be based on set of input data. To illustrate how to proceed we will take the example of 125 tons injection moulding press. In this case the input are the following : - The investment cost including the other equipments (robots, conveyors,..), in this case the daily working time, usually 3 shifts of 8 hours - the yearly working time : usually 220 to 250 days / year, 220 days in the present illustration - the life time of the machine which depends on the speed of obsolescence of the technology. For many industries it is between 7 and 10 years. In the present example we have taken 7 years. Then the calculation of the hourly depreciation cost for the machine is the following : - Number of hours for the whole period : 24 hours / day x 220 days / year x 7 years = hours. - The hourly depreciation cost is : / = 3,25 21

22 Interest rates are based on the WACC «weighed average cost of capital» which indicates how the company structures the its financial resources. Usually a good assumption is to consider 50% financing by bank loan and 50% by own financial resources. the bank loan interest rates varies from one country to the other but in western Europe a 5% would be a good guess for 2006 the expected return on capital is 15% for own financial resources. For a WACC with 50% bank loans and 50% own financial resources, the interested used for the calculation would be : (50%x 15%) + (50% x 5%) = 10% 22

23 Now that we have the interest rate we can calculate the hourly cost for financial interest The calculation for financial interests is based on 3 input data : -The cost of the machine -The interest rate (resulting from the WACC calculation) -The Number of years of the financial plan. The amount of interest paid during the period is calculated thanks to the formula given here in where : - n is the number of years - K is the amount of the investment - «i» is the financial rate The financial cost / hour is the amount of interest over the period divided by the number of hours of the same period. For the example of the injection press the calculation is the following : Financial interest for 7 years : - 7 x x 10% = ( 1.1) -7 The cost per hour is then : / hours = / hour. 23

24 The yearly cost of maintenance is calculated as a % of the investment cost (1): usually between 2 and 5%. This percentage varies according to the type of technology but also according to the age of the equipment. Please note that for machines such as drilling, grinding, polishing etc... We should consider also a specific additional cost for consumables such as lubricants, small tools, etc This cost can represent up to 5 or 6 / hour in some case and it is not included in the percentage mentioned herein. The input data for the calculation are the following: Value of the equipment or machine when new: Number of hours / year: 5280 % of maintenance cost: 3% Then the hourly cost of maintenance is: 3% x / 5280 hours = / hour 24

25 The calculation of energy cost is based on: -The energy consumption The energy consumption depends on the nominal power and the % of utilization. This % of utilization depends on how the machine operates. For instance a plastic injection press only uses 50% of the nominal power due the specific cycle : injection, cooling, opening of the mould, etc Finally in the calculation we must multiply the nominal power with the % of utilization to get the consumption and then we can multiply this result by the cost of the Kw/h. In the present case, the cost of energy per hour is 35 Kw/h X 50% X 0.06 = 1.05 Please note that the cost of the Kw/h depends on the negotiation capacity of the supplier. 25

26 The cost of space is based on -the space need for running the activity of the machine -The yearly cost of space And The number of working hours / year The total space needed must account for runways and other storage areas: It is usually around 4 to 10 times the space of the machine itself according to the type of parts produced (bulky or not). The yearly cost of the m² depends on the location. It is currently in between 50 to 70 / m² in western countries. In the example taken the input data are the following : - Surface of the machine : 6 m² - Yearly cost of the m² : 50 : - Number of hours per year : 5280 The illustration gives the following calculation : Space allowance : 6 times the surface of the machine or 6 x 8 m² = 48 m² => Hourly cost of space : 48 x 50 / 5280 = / hour 26

27 The principle is to calculated an hourly cost for each of the 5 cost items i.e : -Depreciation cost -Financial cost -Maintenance cost -Energy cost -And space cost To get the global hourly cost of the machine you will have to sum up all the costs that we have gone through on this slide. The calculation can be either done with the exact information given by the supplier or based on assumptions of what the normal conditions should be for this kind of activity (stamping, casting,.). As a results of all the previous calculation, the hourly cost of the machine is the sum of all 5 cost items. In the present case the hourly rate is 6.6. Again it is important to note that this hourly cost does not include any overhead cost nor efficiency impact. 27

28 28

29 29

30 Item n 4 of the cost calculation is the industrial overheads 30

31 The scope of the industrial overheads usually covers all the cost generated by the functions supporting the operational activities i.e. R &D Information technology Production engineering Purchasing Logistics and warehousing Planning, scheduling of production, etc t They do not include sales, general and administration expenses which are a separate cost item. As a general calculation rule we shall consider that OI equals between 25 and 35% of the industrial added value (i.e. machine and labour cost). A regular production plant without high technology nor real R&D should be on the low side of the ratio (25%), whereas other companies providing a high level of engineering skills would on the high side (35%). OI are the first part of the overhead cost of the company, the second part being SG&A. Altogether OI + SG&A are generally equals around 15% to 17% of sales according to the company profile. However comparing these expenses with the sales, may not be very relevant as the ratio might be strongly affected by the value of the material. 31

32 The fifth element that we need to calculate is the Sales general and administration expenses (also called SG&A) 32

33 The scope for sales, general and administration expenses usually covers all the all the cost generated by the business support activity such as : general management sales and marketing finance and accounting Human resources Travel expenses,.. The Calculation rule is quite simple : SG and A usually represent around 5 to 7 % of the piece price. 33

34 Finally we need to calculate the operating profit 34

35 Regarding operating profit, it is important to remember that the operating profit mentioned in the cost breakdown is before income tax. In terms of calculation rule, the profit level depends on the supplier market segment and supplier position. For the «tier 2 suppliers» level of the automotive industry this profit is usually in the area of 4 to 7 % of the piece price. 35

36 Finally we need to account for packaging and transport cost. 36

37 As a general remark : : Packaging cost covers the cost of the lost items needed for the protection of the parts during transport. Very frequently returnable containers are used and do not require any additional protection. If such a protection is needed it should be checked carefully as the minor cost is very often over estimated by suppliers Regarding transport cost, selling conditions are quite often ex work with a milk run system which means that the optimization of transport needs to be addressed at customer level. 37

38 38

39 39

40 At this point we would like to thank you for having spent some time learning this module. We hope you enjoyed it and we would like to remind you to make a hard copy of all the slides so that you can keep track of all the calculation rules and concepts we have been reviewing. We wish you a very good success for the implementation with your suppliers 40

Reading Essentials and Study Guide

Reading Essentials and Study Guide Lesson 3 Cost, Revenue, and Profit Maximization ESSENTIAL QUESTION How do companies determine the most profitable way to operate? Reading HELPDESK Academic Vocabulary generates produces or brings into

More information

YOUR MOST IMPORTANT DECISION!

YOUR MOST IMPORTANT DECISION! YOUR MOST IMPORTANT DECISION! Let me ask you a question. Do you think increasing your sales would be a good thing? If I told you that your price was too low, would you still think increasing sales would

More information

Managerial Accounting Prof. Dr. Varadraj Bapat School of Management Indian Institute of Technology, Bombay

Managerial Accounting Prof. Dr. Varadraj Bapat School of Management Indian Institute of Technology, Bombay Managerial Accounting Prof. Dr. Varadraj Bapat School of Management Indian Institute of Technology, Bombay Module - 9 Lecture - 20 Accounting for Costs Dear students, in our last session we have started

More information

Understanding and Using Cost Breakdowns. Professional courses to optimize your buying team s performance

Understanding and Using Cost Breakdowns. Professional courses to optimize your buying team s performance Understanding and Using Cost Breakdowns Professional courses to optimize your buying team s performance 1 Introductions All APD Personnel Main Presenter Jeoff Burris Producer Jon Homrich 2 Making Purchasing

More information

ACTIVITY BASED COSTING

ACTIVITY BASED COSTING CHAPTER 5 ACTIVITY BASED COSTING LEARNING OUTCOMES r Discuss problem of traditional costing system. r Discuss usefulness of Activity Based Costing(ABC). r Discuss Cost Allocation under ABC. r Discuss Different

More information

Savings Gap Closure. October 2012

Savings Gap Closure. October 2012 Savings Gap Closure October 2012 Executive Summary A well structured plan of attack will help ensure year end targets are met. Identification A systematic approach will ensure savings opportunities are

More information

Fill-in-the-Blank Equations. Exercises

Fill-in-the-Blank Equations. Exercises Chapter 15 (1) Introduction to Managerial Accounting Study Guide Solutions 1. Merchandise available for sale 2. Cost of merchandise sold Fill-in-the-Blank Equations 3. Cost of goods manufactured during

More information

Exemplar for Internal Achievement Standard. Accounting Level 3

Exemplar for Internal Achievement Standard. Accounting Level 3 Exemplar for Internal Achievement Standard Accounting Level 3 This exemplar supports assessment against: Achievement Standard 91409 Demonstrate understanding of a job cost subsystem for an entity An annotated

More information

CHAPTER ONE: OVEVIEW OF MANAGERIAL ACCOUNTING

CHAPTER ONE: OVEVIEW OF MANAGERIAL ACCOUNTING CHAPTER ONE: OVEVIEW OF MANAGERIAL ACCOUNTING The Basic Objectives of Accounting Basic objective of accounting is to provide stakeholders with useful information about a business enterprise in order to

More information

Waste minimisation in plastics processing

Waste minimisation in plastics processing Waste minimisation in plastics processing TANGRAM TECHNOLOGY Waste minimisation in plastics processing Practical worksheets for industry Waste Worksheets CONTENTS Part 1 - The business reasons...3 Part

More information

Calculation Schema. Setting up the calculation schema in beas. Beas Tutorial. Boyum Solutions IT A/S

Calculation Schema. Setting up the calculation schema in beas. Beas Tutorial. Boyum Solutions IT A/S Calculation Schema Setting up the calculation schema in beas Boyum Solutions IT A/S Beas Tutorial TABLE OF CONTENTS 1. INTRODUCTION... 3 2. PROCESS... 3 2.1. Master Data Tab... 5 2.2. Overhead Costs Tab...

More information

YOUR MOST IMPORTANT DECISION!

YOUR MOST IMPORTANT DECISION! YOUR MOST IMPORTANT DECISION! Let me ask you a question. Do you think increasing your sales would be a good thing? If I told you that your price was too low, would you still think increasing sales would

More information

A job costing tool for construction company X. Ansa Huikko

A job costing tool for construction company X. Ansa Huikko A job costing tool for construction company X Ansa Huikko 2 March 2015 Abstract 2.3.2015 Author Ansa Huikko Degree programme Bachelor of Business Administration Report/thesis title A Job Costing Tool for

More information

Costing & Pricing Your Products. An introduction

Costing & Pricing Your Products. An introduction Costing & Pricing Your Products An introduction Contents 01 - Costing and Pricing: An introduction... 4 02 Costs - the basics... 6 What are Costs... 6 Types of Costs... 8 03 Costing Your Products... 11

More information

The Examiner's Answers Specimen Paper. Performance Management

The Examiner's Answers Specimen Paper. Performance Management The Examiner's Answers Specimen Paper P2 - SECTION A Answer to Question One The Value Chain is the concept that there is a sequence of business factors by which value is added to an organisation s products

More information

Hilton Chapter14 Adobe Connect CHAPTER 14: DECISION MAKING, RELEVANT COSTS & BENEFITS. The decision process consists of the six steps that follow.

Hilton Chapter14 Adobe Connect CHAPTER 14: DECISION MAKING, RELEVANT COSTS & BENEFITS. The decision process consists of the six steps that follow. 1 Hilton Chapter14 Adobe Connect CHAPTER 14: DECISION MAKING, RELEVANT COSTS & BENEFITS Chapter 14 concerns decision making. In one sense, the entire book leads to this chapter. THE DECISION-MAKING PROCESS

More information

Unleash Hidden Profits: Make Your Supply Chain Work for You

Unleash Hidden Profits: Make Your Supply Chain Work for You Unleash Hidden Profits: Make Your Supply Chain Work for You Objective Learn how you can Reduce Working Capital Improve Cash Flow Increase Profits by improving how you manage your materials and supply chain

More information

Managerial Accounting Prof. Dr. Varadraj Bapat Department of School of Management Indian Institute of Technology, Bombay

Managerial Accounting Prof. Dr. Varadraj Bapat Department of School of Management Indian Institute of Technology, Bombay Managerial Accounting Prof. Dr. Varadraj Bapat Department of School of Management Indian Institute of Technology, Bombay Lecture - 32 Standard Costing, Mix, Yield, Sales and Fixed Overhead Variances The

More information

Quoting & Estimating. Introduction (Seminar 5)

Quoting & Estimating. Introduction (Seminar 5) Quoting & Estimating Introduction (Seminar 5) Quoting and Estimating is a key operational activity required to get the ManuDyn system fully operational. The reason for this is that in order to quote you

More information

Financing FoodDistribution in the 1970 s

Financing FoodDistribution in the 1970 s Financing FoodDistribution in the 1970 s Consumers Cooperative f$od70 s Methods of raising necessary capital for a retail consumers cooperative Robert Morrow, President Greenbelt Consumer Services, Inc.

More information

COST OF GOODS MANUFACTURED & SOLD STATEMENT

COST OF GOODS MANUFACTURED & SOLD STATEMENT COST OF GOODS MANUFACTURED & SOLD STATEMENT In order to understand the financial and cost statement of a concern we should clear about the procedure adopted by trading concern and manufacturing concern

More information

Managerial Accounting Prof. Dr. Vardaraj Bapat School of Management Indian Institute of Technology, Bombay

Managerial Accounting Prof. Dr. Vardaraj Bapat School of Management Indian Institute of Technology, Bombay Managerial Accounting Prof Dr Vardaraj Bapat School of Management Indian Institute of Technology, Bombay Module - 11 Lecture - 25 Activity Based Costing and Management Today, we will continue our discussion

More information

GLOBALIZATION IN MANUFACTURING INDUSTRIES

GLOBALIZATION IN MANUFACTURING INDUSTRIES GLOBALIZATION IN MANUFACTURING INDUSTRIES ISSUE 2 GLOBALIZING THE MANUFACTURING FOOTPRINT Globalization of the manufacturing footprint has been an imperative for manufacturing firms for a long time. However,

More information

REVISION: MANUFACTURING 12 SEPTEMBER 2013

REVISION: MANUFACTURING 12 SEPTEMBER 2013 REVISION: MANUFACTURING 12 SEPTEMBER 2013 Lesson Description In this lesson we: Revise ledger accounts and the production cost statement Key Concepts Ledger Accounts for Manufacturing Differences between

More information

B292 Revision Part 2 EX (6)

B292 Revision Part 2 EX (6) EX (6) B292 Revision Part 2 My Tablet Inc. specializes in Tablets. The results of the company's operations during 2013 are given in the following table. All units produced during the year were sold. (Ignore

More information

Cost Accounting. Multiple Choice Questions:

Cost Accounting. Multiple Choice Questions: Multiple Choice Questions: 1- The Value Chain a- Involves external companies as well as internal activities. b- Is the sequence of business functions in which customer usefulness is added to products or

More information

VDL Systems. Part of VDL Group

VDL Systems. Part of VDL Group VDL Systems Part of VDL Group VDL Groep n International industrial enterprise n HQ in Eindhoven, the Netherlands n Family-owned company n 88 companies in 19 countries (70% export) n 1,200,000 m 2 production

More information

COST AND MANAGEMENT ACCOUNTING

COST AND MANAGEMENT ACCOUNTING EXECUTIVE PROGRAMME COST AND MANAGEMENT ACCOUNTING SAMPLE TEST PAPER (This test paper is for practice and self study only and not to be sent to the institute) Time allowed: 3 hours Maximum marks : 100

More information

Cost Behavior. Material Cost: Direct material: 1. seen in the final product 2. economic/visible to trace Indirect Material:

Cost Behavior. Material Cost: Direct material: 1. seen in the final product 2. economic/visible to trace Indirect Material: 1 Chapter 2 Introduction to Cost Terms and Purposes Cost A cost is the value of economic resources (e.g., money) sacrificed or used up to achieve a particular objective (e.g., produce a product or perform

More information

INTRODUCTION. Professional Accounting Supplementary School (PASS) Page 1

INTRODUCTION. Professional Accounting Supplementary School (PASS) Page 1 INTRODUCTION Under the new CPA certification program, management accounting has become very important on the CFE and it will therefore be critical for students to have a strong grounding in this area.

More information

1/2018. Operation Manual. How to calculate a plastic part

1/2018. Operation Manual. How to calculate a plastic part 1/2018 Operation Manual How to calculate a plastic part How to Calculate a Plastic Part Step 1: Connecting to a Database... 2 Step 2: Adjust Project Specifications... 3 Step 3: Take over Project Specifications...

More information

CPA Evaluation Core 2 Module Page 1

CPA Evaluation Core 2 Module Page 1 CPA Evaluation Core 2 Module Page 1 Overview The Core 1 and 2 examinations are a mix of objective format and case questions. The maximum length for an individual case will be 60 minutes. The Core cases

More information

The Getting Gross: Make More Gross Margin. Workbook

The Getting Gross: Make More Gross Margin. Workbook The Getting Gross: Make More Gross Margin Workbook Getting Gross: How to Make More Gross Margin There are lots of areas of the financials that deserve our attention including revenue, equipment, salaries,

More information

target and lifecycle 01 technical taken by conventional costing. accounting so it is worth first looking at the approach

target and lifecycle 01 technical taken by conventional costing. accounting so it is worth first looking at the approach 01 technical target and lifecycle RELEVANT to ACCA QUAlification paper F5 Target costing and lifecycle costing can be regarded as relatively modern advances in management accounting so it is worth first

More information

HIGH-PERFORMANCE MACHINING CENTER ROI: HOW TO DETERMINE A MACHINE S TRUE VALUE

HIGH-PERFORMANCE MACHINING CENTER ROI: HOW TO DETERMINE A MACHINE S TRUE VALUE HIGH-PERFORMANCE MACHINING CENTER ROI: HOW TO DETERMINE A MACHINE S TRUE VALUE AUTHOR BIO TOM CLARK VICE PRESIDENT, MAKINO INC. Tom Clark is vice president of engineering and operations at Makino (Mason,

More information

DECISION MAKING. Key Terms and Concepts to Know

DECISION MAKING. Key Terms and Concepts to Know DECISION MAKING Key Terms and Concepts to Know Relevance: Relevant costs and benefits are those that differ among alternatives Total approach vs. differential approach and why relevant costs must be isolated.

More information

CPA Mock Evaluation Management Accounting Module (Core 2) Page 1

CPA Mock Evaluation Management Accounting Module (Core 2) Page 1 CPA Mock Evaluation Management Accounting Module (Core 2) Page 1 Overview The Core 1 and 2 examinations are a mix of objective format and case questions. The maximum length for an individual case will

More information

Back to Basics TOC: Throughput Accounting

Back to Basics TOC: Throughput Accounting Back to Basics TOC: Throughput Accounting Presented by: Dr. Lisa Lang and Beau S. Ganas Date: March 17, 2018 2018 TOCICO. All Rights Reserved. Cost Accounting History Cost Accounting: The Number One Enemy

More information

Copyright holder is licensing this under the Creative Commons License, Attribution 3.0.

Copyright holder is licensing this under the Creative Commons License, Attribution 3.0. 2010 by Scott Richards of Beyond the Numbers Copyright holder is licensing this under the Creative Commons License, Attribution 3.0. http://creativecommons.org/licenses/by/3.0/us/ This is a free e-book

More information

Management Accounting 2 nd Year Examination

Management Accounting 2 nd Year Examination Management Accounting 2 nd Year Examination May 2017 Solutions, Examiners Comments & Marking Scheme NOTES TO USERS ABOUT THESE SOLUTIONS The solutions in this document are published by Accounting Technicians

More information

CONTROL. Chapter 3-7. Cost of Quality Institute of Industrial Engineers 3-7-1

CONTROL. Chapter 3-7. Cost of Quality Institute of Industrial Engineers 3-7-1 Chapter 3-7 Cost of Quality 2011 Institute of Industrial Engineers 3-7-1 Cost of Quality Topics Introduction Understanding Quality Cost Categories and Models Hidden Costs Benefits of a Cost of Quality

More information

Costs classification,

Costs classification, Theme No. 5: Costs classification, functions (models), analysis Department of Economics and Management UCT PRAGUE 1 Department of Economics and Management E-mail: jiri.klecka@vscht.cz 2 As an introduction

More information

An accounting perspective: Business insight

An accounting perspective: Business insight An accounting perspective: Business insight Engineers for automobile companies in the United States believe that Japanese manufacturers can build cars for considerably less than their US counterparts.

More information

Module 9: Balanced Scorecard

Module 9: Balanced Scorecard file:///f /Courses/2009-10/CGALU/MA2/06course/01mod/m09intro.htm Module 9: Balanced Scorecard Overview Module 9 ties all previous modules together into a method for facilitating decision-making and performance

More information

QuoteCAM. Fast & Accurate Quoting for Machined Parts

QuoteCAM. Fast & Accurate Quoting for Machined Parts Fast & Accurate Quoting for Machined Parts Engineering is a business No business can survive without making a profit. This is quite a simple process for many types of business but in engineering, and especially

More information

Institute of Certified Management Accountants of Sri Lanka Operational Level November 2018 Examination. Management Accounting (MA / OL 1-201)

Institute of Certified Management Accountants of Sri Lanka Operational Level November 2018 Examination. Management Accounting (MA / OL 1-201) Copyright Reserved Serial No Institute of Certified Management Accountants of Sri Lanka Operational Level November 2018 Examination Examination Date : 17 th November 2018 Number of Pages : 06 Examination

More information

CONTRACTOR COST ACCOUNTING

CONTRACTOR COST ACCOUNTING CONTRACTOR COST ACCOUNTING PURPOSE AND SCOPE This teaching note explains certain key concepts of cost or managerial accounting, describes the types of cost accounting systems, and how the systems are used

More information

COSTING COSTING NAME:

COSTING COSTING NAME: NAME: COSTING This Costing Workshop is aimed at employees in the clothing and textile value chain involved in the costing process as well as those who make decisions that influence product costs. Contents

More information

THE PROFESSIONALS ACADEMY OF COMMERCE Mock Exam, Summer-2015 Management Accounting (Solution)

THE PROFESSIONALS ACADEMY OF COMMERCE Mock Exam, Summer-2015 Management Accounting (Solution) THE PROFESSIONALS ACADEMY OF COMMERCE Mock Exam, Summer-2015 Management Accounting (Solution) Answer to Q-1 Minimum price for making 500 units of AK 100 Materials: Rs. X (500 units 4kg) Rs.8 16,000 Y (500

More information

P2 Performance Management

P2 Performance Management DO NOT OPEN THIS QUESTION PAPER UNTIL YOU ARE TOLD TO DO SO Performance Pillar P2 Performance Management 20 November 2013 Wednesday Afternoon Session Instructions to candidates You are allowed three hours

More information

Introduction to Technical Cost Modeling Concepts and Illustrations

Introduction to Technical Cost Modeling Concepts and Illustrations Introduction to Technical Cost Modeling Concepts and Illustrations Why Is Cost Important? A measure of resource consumption How much is required to do (e.g., produce) something? Resources themselves are

More information

B. Com (Hons.) III Semester Paper Title: Cost Accounting Paper Code: AS-2620

B. Com (Hons.) III Semester Paper Title: Cost Accounting Paper Code: AS-2620 B. Com (Hons.) III Semester Paper Title: Cost Accounting Paper Code: AS-26 * Prepared by: Nilmani Tripathi, Assistant Professor, Department of Commerce, GGV Answer 1. Short answer question 1. Eight example

More information

Maintenance, Reliability, Operations, Production, and working together to create the greatest Total Profit Added

Maintenance, Reliability, Operations, Production, and working together to create the greatest Total Profit Added BEARING AND RELIABILITY CONFERENCE AND EXHIBITION 2017 Maintenance, Reliability, Operations, Production, and working together to create the greatest Total Profit Added Procurement Todd Snelgrove, Vice

More information

Profit Is Everybody s Business

Profit Is Everybody s Business Profit Is Everybody s Business A Member Service From How to Drive Higher Profits, Provide Better Salaries and Fringes, Smile More, and Have Your Work be Really Meaningful Presented by Dr. Albert D Bates

More information

Percent decrease for common items based on reduction in crude from $110 per bbl.

Percent decrease for common items based on reduction in crude from $110 per bbl. February 2015 Sourcing in a Declining Market Category Sourcing Guide Resin Price Decline. Many industrial resins have seen dramatic price reductions due to the decrease in crude oil and natural gas feedstocks.

More information

LOYOLA COLLEGE (AUTONOMOUS), CHENNAI

LOYOLA COLLEGE (AUTONOMOUS), CHENNAI LOYOLA COLLEGE (AUTONOMOUS), CHENNAI 600 034 B.Com. DEGREE EXAMINATION CORPORATE SECRETARYSHIP FOURTH SEMESTER APRIL 2016 BC 4504/BC 5501 COST ACCOUNTING Date: 22-04-2016 Dept. No. Max. : 100 Marks Time:

More information

No. 8: Avoid Wild Pitches with Overhead Allocation BY MIKE ODE

No. 8: Avoid Wild Pitches with Overhead Allocation BY MIKE ODE No. 8: Avoid Wild Pitches with Overhead Allocation BY MIKE ODE No. 8: Avoid Wild Pitches with Overhead Allocation Editor's Note: This is the eighth article in the series, "Software Feature Line-Up," by

More information

What we are expecting from this presentation:

What we are expecting from this presentation: What we are expecting from this presentation: A We want to inform you on the most important highlights from this topic D We exhort you to share with us a constructive feedback for further improvements

More information

BENCHMARKING WASTE IN PLASTICS PROCESSING

BENCHMARKING WASTE IN PLASTICS PROCESSING ENVIRONMENTAL TECHNOLOGY BEST PRACTICE PROGRAMME BENCHMARKING WASTE IN PLASTICS PROCESSING Polymer purchase, utilities and packaging are significant costs for any plastics business. Most companies are

More information

Required If the Bath Department is dropped, what will be the effect on the operating income of the company as a whole?

Required If the Bath Department is dropped, what will be the effect on the operating income of the company as a whole? In Class #12.1 Dropping or Retaining a Segment Required If the Bath Department is dropped, what will be the effect on the operating income of the company as a whole? Contribution margin lost if the Bath

More information

Case study Dealing with overheads

Case study Dealing with overheads Case study Dealing with overheads This is the solution to the case study found at the end of: Chapter 7 Costing (a) Overhead apportionment Basis Total Cutting and turning Assembly and finishing Factory

More information

10-1. Learning Objective. Identify relevant and irrelevant costs and benefits in a decision.

10-1. Learning Objective. Identify relevant and irrelevant costs and benefits in a decision. 10-1 Learning Objective Identify relevant and irrelevant costs and benefits in a decision. 10-2 Relevant Costs and Benefits A relevant cost is a cost that differs between alternatives. A relevant benefit

More information

Test Bank For Cost Accounting A Managerial Emphasis Fifth Canadian 5th Edition By Horngren Foster Datar And Gowing

Test Bank For Cost Accounting A Managerial Emphasis Fifth Canadian 5th Edition By Horngren Foster Datar And Gowing Test Bank For Cost Accounting A Managerial Emphasis Fifth Canadian 5th Edition By Horngren Foster Datar And Gowing Link full download: https://digitalcontentmarket.org/download/test-bank-for-cost-accounting-amanagerial-emphasis-fifth-canadian-5th-edition-by-horngren-foster-datar-andgowing/

More information

ton as co low volume at lower cost

ton as co low volume at lower cost ton as co low volume at lower cost ton as co High Mix Wide mix of mechanical parts & mechatronic assemblies from a high mix of materials and processes. Low Volume Production series of 1-20 pieces are our

More information

ACCTG 221 / ABC Costing

ACCTG 221 / ABC Costing ACCTG 221 / ABC Costing ACTIVITY BASED COSTING SYSTEMS First identifies activities in an organization and then assigns the cost of each activity to products and services based on actual consumption The

More information

INSERT BLACK & WHITE PICTURE. Purchasing Input Perfect Storm February 2016

INSERT BLACK & WHITE PICTURE. Purchasing Input Perfect Storm February 2016 INSERT BLACK & WHITE PICTURE Purchasing Input Perfect Storm February 2016 Dec-14 Jan-15 Feb-15 Mar-15 Apr-15 May-15 Jun-15 Jul-15 Aug-15 Sep-15 Oct-15 Nov-15 Dec-15 Jan-16 Feb-16 Dec-14 Jan-15 Feb-15 Mar-15

More information

10 The Circular Flow and Gross Domestic Product. How economists use aggregate measures to track the performance of the economy

10 The Circular Flow and Gross Domestic Product. How economists use aggregate measures to track the performance of the economy Printed Page 102 [Notes/Highlighting] 10 The Circular Flow and Gross Domestic Product How economists use aggregate measures to track the performance of the economy The circular flow diagram of the economy

More information

CHAPTER 8 LEARNING OBJECTIVES

CHAPTER 8 LEARNING OBJECTIVES CHAPTER 8 LEARNING OBJECTIVES 1. COMPUTE A TARGET COST WHEN THE MARKET DETERMINES A PRODUCT PRICE. 2. COMPUTE A TARGET SELLING PRICE USING COST- PLUS PRICING. 3. USE TIME-AND-MATERIAL PRICING TO DETERMINE

More information

Module III. Total Cost Analysis for TCO

Module III. Total Cost Analysis for TCO Module III Total Cost Analysis for TCO Behavioral & Data Based Negotiation Techniques Always Negotiate With Data Don t believe everything you read about negotiations Negotiations are no longer about psychological

More information

LCA in decision making

LCA in decision making LCA in decision making 1 (13) LCA in decision making An idea document CHAINET LCA in decision making 2 (13) Content 1 INTRODUCTION 2 EXAMPLE OF AN INDUSTRIAL DEVELOPMENT PROCESS 2.1 General about the industrial

More information

Managerial Accounting and Cost Concepts

Managerial Accounting and Cost Concepts Managerial Accounting and Cost Concepts Chapter 2 PowerPoint Authors: Susan Coomer Galbreath, Ph.D., CPA Charles W. Caldwell, D.B.A., CMA Jon A. Booker, Ph.D., CPA, CIA Cynthia J. Rooney, Ph.D., CPA Copyright

More information

Integrating suppliers with your online store

Integrating suppliers with your online store Integrating suppliers with your online store You've figured out your market, planned on how you'll build and run your store and what your business model is. You've registered your business and you are

More information

Multiple Choice Questions

Multiple Choice Questions Multiple Choice Questions 1. A cost not relevant to deciding whether to purchase a new machine is: a) The cost of the new machine b) Lower maintenance costs for the new machine c) The cost of the old machine

More information

COST SHEET. Samir K Mahajan

COST SHEET. Samir K Mahajan COST SHEET Samir K Mahajan COMPONENTS OF TOTAL COST Prime cost: It is the aggregate of direct material cost, direct labour cost and direct expenses. Prime cost or Direct cost = Direct materials + Direct

More information

Advanced Engineering Projects Management

Advanced Engineering Projects Management Advanced Engineering Projects Management Dr. Nabil I El Sawalhi Assistant Professor of Construction Management AEPM L8 1 Preparing For the Detailed Estimate Listing Quantities Tender Cost Direct Project

More information

How Can Entrepreneurs Control Costs? Council for Economic Education, New York, NY Entrepreneurship in the U.S. Economy, Lesson 20

How Can Entrepreneurs Control Costs? Council for Economic Education, New York, NY Entrepreneurship in the U.S. Economy, Lesson 20 How Can Entrepreneurs Control Costs? Council for Economic Education, New York, NY Entrepreneurship in the U.S. Economy, Lesson 20 Lesson Description DESCRIPTION In this lesson students will learn that

More information

Post(s): S7 Grade Syllabus Total No. of Questions Junior Engineer (Mechanical)

Post(s): S7 Grade Syllabus Total No. of Questions Junior Engineer (Mechanical) Syllabus for Computer Based Test The paper will consist of 100 questions in 2 parts. Part 1: Knowledge of the subject/discipline Part-2: General Aptitude test (viz. General Knowledge, Logical Reasoning,

More information

User Manual: Stocker, Feeder Retained Ownership Profit Projection

User Manual: Stocker, Feeder Retained Ownership Profit Projection User Manual: Stocker, Feeder Retained Ownership Profit Projection You can t predict but you can prepare. Cattle retained ownership is a margin business where added revenue must be greater than added cost

More information

Assignment #2 IE 2303/AME 2303 Spring 2012 Introduction to Manufacturing. Example Answers

Assignment #2 IE 2303/AME 2303 Spring 2012 Introduction to Manufacturing. Example Answers Assignment #2 IE 2303/AME 2303 Spring 2012 Introduction to Manufacturing Example Answers 1. Short Response 2 to 3 sentences each (10 pts.) Explain in your own words the challenges/opportunities for U.S.

More information

ACTIVITY BASED COSTING PERFORMANCE MEASUREMNENT ABC. Benchmarking

ACTIVITY BASED COSTING PERFORMANCE MEASUREMNENT ABC. Benchmarking PERFORMANCE MEASUREMNENT Benchmarking Measuring and benchmarking supply chain performance is a vital first step in any reengineering programme. Understanding the differences between value adding time and

More information

22 ways to get the most out of OEE and lean manufacturing disciplines

22 ways to get the most out of OEE and lean manufacturing disciplines automation technology & consulting 22 ways to get the most out of OEE and lean manufacturing disciplines Overall equipment effectiveness (OEE) and lean manufacturing have won many converts. These two disciplines

More information

Institute of Certified Management Accountants of Sri Lanka. Managerial Level May 2013 Examination. Integrative Management Accounting (IMA/ ML 1-301)

Institute of Certified Management Accountants of Sri Lanka. Managerial Level May 2013 Examination. Integrative Management Accounting (IMA/ ML 1-301) Copyright Reserved Serial No Managerial Level May 2013 Examination Examination Date : 5 th May 2013 Number of Pages : 05 Examination Time: 9.30 a:m. 12.30 p:m. Number of Questions: 05 Instructions to candidates:

More information

P2 Performance Management

P2 Performance Management Performance Pillar P2 Performance Management Examiner s Answers SECTION A Answer to Question One (a) Flexed Actual Budget Output (batches) 50 50 Variance Direct labour hours 68 91 93 65 24 74 adverse Direct

More information

PM B Task 5 Name : Page 1 Matr.-Nr. : PM II Task 1, 20 Points

PM B Task 5 Name : Page 1 Matr.-Nr. : PM II Task 1, 20 Points PM B Task 5 Name : Page 1 Matr.-Nr. : PM II Task 1, 20 Points After finishing your studies you start as an assistant to the management board of a medium-sized company that produces interior trims for the

More information

Get a clearer view of your business

Get a clearer view of your business Get a clearer view of your business Essential Tips for Every Business Owner START HERE Small businesses - we salute you Canada s small and medium businesses account for 95% of all net job creation.¹ That

More information

CBI Product Factsheet for Rubber and Metal Parts for Vehicles in Eastern Europe

CBI Product Factsheet for Rubber and Metal Parts for Vehicles in Eastern Europe CBI Product Factsheet for Rubber and Metal Parts for Vehicles in Eastern Europe Practical market insights for your product Eastern European demand for rubbertometal bonded automotive parts is increasing

More information

COST CONCEPTS IN DECISION MAKING

COST CONCEPTS IN DECISION MAKING CHAPTER 2 COST CONCEPTS IN DECISION MAKING BASIC CONCEPTS & FORMULAE Basic Concepts 1. Relevant cost in decision making process: Costs which are relevant for a particular business option, which are not

More information

Gatsby s Accounting System and Policies Designed by Regina Rexrode Copyright - Armond Dalton

Gatsby s Accounting System and Policies Designed by Regina Rexrode Copyright - Armond Dalton Gatsby s Accounting System and Policies a Images used on the front cover and throughout this book were obtained under license from Shutterstock.com 2017, by Armond Dalton Publishers, Inc. All rights reserved.

More information

Manage Your Own Company Business Game LIUC Cattaneo University

Manage Your Own Company Business Game LIUC Cattaneo University Manage Your Own Company Business Game LIUC Cattaneo University Player s Guide Initiative promoted by the University Carlo Cattaneo - LIUC in collaboration with the Regional School Office for Lombardy Versione

More information

Costing of Service Sector

Costing of Service Sector 6 Costing of Service Sector LEARNING OBJECTIVES After finishing this chapter, you will be able to understand and appreciate the peculiarities involved in the costing of service sector. Through this chapter

More information

CESIM SIMFIRM Introduction. Simulation for general business management

CESIM SIMFIRM Introduction. Simulation for general business management CESIM SIMFIRM Introduction Simulation for general business management What is Cesim SimFirm? Cesim SimFirm is an online business simulation game that develops students understanding of the complexity of

More information

10 Things In-House Counsel Need to Understand About Business Alan K. Tse, General Counsel, LG Electronics MobileComm USA Karen Wishart, Executive VP

10 Things In-House Counsel Need to Understand About Business Alan K. Tse, General Counsel, LG Electronics MobileComm USA Karen Wishart, Executive VP 10 Things In-House Counsel Need to Understand About Business Alan K. Tse, General Counsel, LG Electronics MobileComm USA Karen Wishart, Executive VP and Chief Legal Officer, TV One Marti Wronski, VP and

More information

2017 Accounting. Higher. Finalised Marking Instructions

2017 Accounting. Higher. Finalised Marking Instructions National Qualifications 2017 2017 Accounting Higher Finalised Marking Instructions Scottish Qualifications Authority 2017 The information in this publication may be reproduced to support SQA qualifications

More information

Simulation for strategy and international business. Introduction. Ver 2.11

Simulation for strategy and international business. Introduction.   Ver 2.11 Cesim Global Challenge Simulation for strategy and international business Introduction Ver 2.11 What is Cesim Global Challenge? Cesim Global Challenge is an on-line business simulation game that develops

More information

Cost Analysis and Estimating for Engineering and Management

Cost Analysis and Estimating for Engineering and Management Cost Analysis and Estimating for Engineering and Management Chapter 8 Product Estimating Ch 8-1 Overview Processes for Determining Price Bottom Up and Top Down Using Productive Hour Costs Learning in Product

More information

A Guide to Costing and Pricing a Product or Service

A Guide to Costing and Pricing a Product or Service A Guide to Costing and Pricing a Product or Service Business Information Factsheet BIF054 December 2016 Introduction Setting the right price for a new product or service can be one of the hardest tasks

More information

COST SHEET. Samir K Mahajan

COST SHEET. Samir K Mahajan COST SHEET Samir K Mahajan COMPONENTS OF TOTAL COST Prime cost or Direct cost : It is the aggregate of direct material cost, direct labour cost and direct expenses. i.e. Prime cost or Direct cost = Direct

More information

Managerial Economics Prof. Trupti Mishra S.J.M School of Management Indian Institute of Technology, Bombay. Lecture - 23 Theory of Cost (Contd )

Managerial Economics Prof. Trupti Mishra S.J.M School of Management Indian Institute of Technology, Bombay. Lecture - 23 Theory of Cost (Contd ) Managerial Economics Prof. Trupti Mishra S.J.M School of Management Indian Institute of Technology, Bombay Lecture - 23 Theory of Cost (Contd ) In today s session we will continue our discussion on the

More information

ASSIGNMENT SOLUTIONS GUIDE ( ) E.C.O.-10

ASSIGNMENT SOLUTIONS GUIDE ( ) E.C.O.-10 1 ASSIGMET SOLUTIOS GUIDE (2016-2017) E.C.O.-10 Elements of Costing Disclaimer/Special ote: These are just the sample of the Answers/Solutions to some of the Questions given in the Assignments. These Sample

More information

Case Study. Cosma International improves systems through collaboration with Solarsoft. Customer Spotlight.

Case Study. Cosma International improves systems through collaboration with Solarsoft.  Customer Spotlight. Case Study Cosma International improves systems through collaboration with Solarsoft Customer Spotlight Victor Manufacturing (Cosma) Tier-1 supplier of automotive assemblies A division of Magna International

More information