Supplier Harness/ Conductivity Testing Requirements SQR-010. Revision Date: 02 December Approved. Frank Mariot. Supply Chain Quality Manager
|
|
- Charity Antonia Kelly
- 6 years ago
- Views:
Transcription
1 Supplier Harness/ Conductivity Testing Requirements SQR-010 Revision Date: 02 December 2016 Approved Frank Mariot Supply Chain Quality Manager Suppliers may view this document via the Internet at: To obtain a hard copy, please notify Triumph Aerostructures, LLC or Triumph Aerostructures Tulsa, LLC Procurement Representative Supplier Hardness/ Conductivity Requirements Rev E Page 1 of 6
2 REVISION RECORD The latest issue of this manual may be confirmed by viewing the Suppliers web site (address shown on the cover). Revision Date Revision Date Revision Date Rev. A 30 Sep 2003 Rev. B 27 Oct 2010 Rev. C 22 Nov 2010 Rev. D 25 Feb 2014 Rev. E 02 Dec 2016 The following is for Triumph Aerostructures, LLC and Triumph Aerostructures Tulsa, LLC internal use only: The information contained in SQR-010 is controlled by the owner listed in the signature sign-off block and is linked to applicable command media. The owner is responsible for the integrity and maintenance of the SQR. PROPRIETARY RIGHTS Triumph Aerostructures, LLC and Triumph Aerostructures Tulsa, LLC proprietary rights are retained for the information contained herein. The recipient, by acceptance of this document, agrees that neither this document nor the information contained herein, nor any part thereof shall be reproduced or transferred to any other document, used or disclosed to others for any purpose, except as specifically authorized in writing by Triumph Aerostructures, LLC and Triumph Aerostructures Tulsa, LLC. Employees of Triumph Aerostructures, LLC or Triumph Aerostructures Tulsa, LLC may reproduce information contained in this document for internal purposes as necessary. All such copies must be prominently identified as REFERENCE ONLY and/or UNCONTROLLED COPY. Supplier Hardness/ Conductivity Requirements Rev E Page 2 of 6
3 Rev E Summary of Changes Logos information updated Triumph Aerostructures, LLC and Triumph Aerostructures Tulsa, LLC Approvals (Authorizing Signature on File) Frank Mariot -Supply Chain Quality Manager Introduction Section This Document is effective for the following Triumph Aerostructures Companies: Triumph Aerostructures, LLC and Triumph Aerostructures Tulsa, LLC from here on inclusively refer to as Triumph. Supplier Hardness/ Conductivity Requirements Rev E Page 3 of 6
4 TABLE OF CONTENTS Section Title Page Cover sheet 1 Revision Record 2 Summary of Changes 3 Table of Contents Introduction Requirements 5 Table Title Page 1 Temper Validation Sampling Plan 6 Supplier Hardness/ Conductivity Requirements Rev E Page 4 of 6
5 1.0 Introduction This Document is effective for the following Triumph Aerostructures Companies: Triumph Aerostructures, LLC and Triumph Aerostructures Tulsa, LLC from here on inclusively refer to as Triumph. This document specifies the requirements for Hardness/Conductivity testing by Triumph suppliers as identified in the Supplier Quality Assurance Requirements (SQAR) document. The scope of this document applies to all metallic details at the PO line item level and the metallic details that feed into Assemblies. It is not applied at the Assembly level. Affected Suppliers must have hardness and conductivity testing capability for metallic parts or a detailed procedure for purchasing the service. The requirement must be addressed in the supplier's procedures to the extent necessary to ensure compliance, including control of subcontractors if the service is purchased. The supplier is required to flow all of the SQR-010 requirements down to their subtiers. 2.0 Requirements A second temper verification is required for all products regardless of initial or purchased temper condition. This verification (conductivity only) shall be performed post processing in accordance with Table I sampling plan except for steel parts. For steel parts temper verification (hardness only) shall be performed prior to processing in accordance with Table I sampling plan. Note: Prior to processing is defined as completed parts less all surface treatments such as shot peening, chemical process, prime, and paint. Post processing is defined as completed parts including all surface treatments. All nonconforming material must be submitted to Triumph in accordance with SQR Annealed parts/material or parts with thickness less than in. thick and nonstructural detail parts such as fillers, painted, tapered or laminated shims DO NOT require 2nd temper verification. Supplier shall annotate on form CD-4020 or CD- 4020B, if parts/material is in the annealed condition in block 20 (remarks). For suppliers that are not P3 (Delegate Source), record actual results on either CD or CD-4020B as objective evidence. P3 suppliers must annotate results on the packing slip or certifications. The results shall include the customer requirements, actual readings, and quantities tested. Document high and low readings and perform rounding as required by the customer specification. Supplier Hardness/ Conductivity Requirements Rev E Page 5 of 6
6 Table 1 TEMPER VALIDATION SAMPLING PLAN C=0 95% Reliability Lot size up to 10 All 11 to to to to and up 14 Supplier Hardness/ Conductivity Requirements Rev E Page 6 of 6
Quality Assurance Acceptance Sampling Requirements for Suppliers SQR 009. Revision Date: 02 December Approved. Frank Mariot
Quality Assurance Acceptance Sampling Requirements for Suppliers SQR 009 Revision Date: 02 December 2016 Approved Frank Mariot Supply Chain Quality Manager Suppliers may view this document via the Internet
More informationSupplier Advanced Quality Practices SQR 002. Revision Date: 18 July Approved David Copeland, Manager Supply Chain Quality
SQR 002 Revision Date: 18 July 2014 Approved David Copeland, Manager Supply Chain Quality Suppliers may view this document via the Internet at: http://www.voughtaircraft.com/suppliers/quality/quadocs/sqr-002.pdf
More informationNONCONFORMANCE REFERENCE HANDBOOK FOR SUPPLIERS SQR-003. Revision Date: 22 November Approved David Copeland, Manager Supply Chain Quality
NONCONFORMANCE REFERENCE HANDBOOK FOR SUPPLIERS SQR-003 Revision Date: 22 November 2010 Approved David Copeland, Manager Supply Chain Quality Suppliers may view this document via the Internet at: http://www.voughtaircraft.com/suppliers/
More informationTERMS AND CONDITIONS MATRIX
Revision/Date: ORIGINAL /February 28, 2010 Approved Dorith Hakim Chief Procurement Officer Suppliers may view this document via the Internet at: http://www.voughtaircraft.com/suppliers/contract/tcmatrix.htm
More informationSupplier Quality Requirements for Control and Use of Digital Product Definition SQR-004 REVISION DATE: 22 NOVEMBER 2010
Supplier Quality Requirements for Control and SQR-004 REVISION DATE: 22 NOVEMBER 2010 Approved David Copeland, Manager Supply Chain Quality Suppliers may view this document via the Internet at: http://www.voughtaircraft.com/suppliers/
More informationSupplier Quality Assurance Requirements Manual
12716 EAST PINE STREET TULSA, OK 74116 Supplier Quality Assurance Requirements Manual Approved: Bobby Gravison Quality Assurance Manager Accurus Tulsa Machining & Manufacturing 1 Record of Revisions Revision
More informationSatellite Aerospace, Inc. TERMS & CONDITIONS Page 1 of 6
TERMS & CONDITIONS Page 1 of 6 1.0 PURPOSE 1.1 Satellite Aerospace, Inc. Quality Requirements to Subtier Sources. 2.0 SCOPE 2.1 This document applies to all purchasing and sales personnel responsible for
More informationQuality Procedure QP-843 Information for External Providers
Page 1 of 12 Quality Procedure Approval On File John Morrissey, Management Representative On File John Morrissey, President PROPRIETARY RIGHTS Superior Jig, Inc. proprietary rights are retained for the
More informationHAMILTON SUNDSTRAND (BOEING) DROP SHIP CERTIFICATION OF CONFORMANCE REQUIREMENTS FOR SUPPLIERS
Alice Chamberland DATE: 2014/03/20 ENGINEERING RECORDS: A CHAMBERLAND THIS DOCUMENT IS THE PROPERTY OF UTC AEROSPACE SYSTEMS YOU MAY NOT POSSESS, USE, COPY OR DISCLOSE THIS DOCUMENT OR ANY INFORMATION
More informationLT Industries SQFR 101
Page 1 of 5 LT Industries SQFR 101 Supplier Quality Flow down Requirements 1.0 GENERAL REQUIREMENTS: The supplier must flow down these requirements from LTI to their sub tier suppliers whenever those sub
More informationElectro-Miniatures Corp. 68 West Commercial Ave. Moonachie New Jersey Phone: Fax:
Electro-Miniatures Corp. 68 West Commercial Ave. Moonachie New Jersey 07074 Phone: 201-460-0510 Fax: 201-935-8153 1. PURPOSE GENERAL SUPPLIER REQUIREMENTS CLAUSE This general requirement describes the
More informationHelical Products Company
Q01 GENERAL REQUIREMENTS 1. Supplier Responsibilities 1.1. Delivery Certification By delivering products or services on the Contract, the Supplier certifies that such products or services are in compliance
More informationReport number A0436 PRODUCT REQUIREMENTS FOR SELLERS OF BOEING DESIGNED DETAIL PARTS AND NON-FUNCTIONAL MINOR ASSEMBLIES
Report number A0436 PRODUCT REQUIREMENTS FOR SELLERS OF BOEING DESIGNED DETAIL PARTS AND NON-FUNCTIONAL MINOR ASSEMBLIES Revision date 14 DEC 2007 Revision letter T Issue date 30 APRIL 1970 Contract number
More informationSupplier Quality Requirements
Page 1 of 5 SQR-01 Quality Management Systems AS9100 Suppliers: The supplier will at a minimum maintain and implement a documented quality management system, available in the English language, which is
More informationThis guide is applicable to River Protection Project - Waste Treatment Plant (RPP-WTP) project suppliers and is intended for supplier use only.
1.0 Objective 2.0 Scope Provide guidance to those suppliers preparing and submitting quality verification documents to Bechtel National Inc. (BNI), when required by a Bechtel National Inc. (BNI) Purchase
More informationForm Fit & Function Engineering, LLC 350 Seminole Drive Spartanburg, SC Supplementary Quality Assurance Clauses
Supplementary Quality Assurance Clauses The Supplementary Quality Assurance Clauses specified on the face of the attached Purchase Order are listed below. Your compliance with these requirements is necessary
More informationSUPPLIER QUALITY REQUIREMENTS
PURPOSE This procedure defines the policy for the use of suppliers in the purchasing of products and services that affect product conformity. Purchased goods shall meet the requirements of our purchase
More informationSUPPLIER QUALITY ASSURANCE REQUIREMENTS (SQAR)
SUPPLIER QUALITY ASSURANCE REQUIREMENTS (SQAR) Revision Date: 31 AUG 2016 Approved Mark Nejtek, Manager Supply Chain Quality Suppliers may view this document via the Internet at https://www.triumphsupplysource.com/suppliers/pageview.php?menuitemid=51
More informationSatellite Aerospace, Inc. TERMS & CONDITIONS Page 1 of 5
TERMS & CONDITIONS Page 1 of 5 1.0 PURPOSE 1.1 Quality Requirements to Subtier Sources. 2.0 SCOPE 2.1 This document applies to all purchasing and sales personnel responsible for the flow down of Quality
More informationQUALITY ASSURANCE TERMS & CONDITIONS FOR PROCUREMENT Rev E
Sections 1.0 through 5.0 apply to all suppliers doing business with RSI. Sections 6.0 through 8.0 apply to those suppliers providing materials and products for Aerospace and Defense applications. Acceptance
More informationSupplier Requirements Manual
ABACO-EQP-001 REV A Supplier Requirements Manual (European Edition) : Approved By Department Signatory Martin Edwards Quality A 13 TH Sep 2017 Martin Edwards Peter Rhodes Purchasing A 13 TH Sep 2017 Peter
More informationThese requirements apply to all suppliers:
Page 1 of 5 These requirements apply to all suppliers: A. Right of Entry Tri Models, Tri Model s customer and their customers or applicable regulatory agencies shall have right of access to all facilities,
More informationPPI/TZ Standard Quality Requirements for Suppliers -SQRS-
PPI/TZ Standard Quality Requirements for Suppliers -SQRS- AS9100, ISO 13485 and ISO 9001 Revision: March 19, 2014 For questions concerning Standard Quality Requirements for Supplier (SQRS), please contact
More informationSQR Supplier Quality Requirements TRANSLINE TECHNOLOGY, INC. (TTI) SQRs SUPPLIER QUALITY REQUIREMENTS
TRANSLINE TECHNOLOGY, INC. (TTI) 1106 S Technology Circle Anaheim, CA 92805 Telephone: (714) 533-8300 FAX: (714) 533-8791 www.translinetech.com SQRs SUPPLIER QUALITY REQUIREMENTS Revision B 03/18 When
More informationHILLPRO LLC PURCHASE ORDER TERMS AND CONDITIONS
HILLPRO LLC PURCHASE ORDER TERMS AND CONDITIONS This document defines purchase order requirements that may apply to your purchase order. Please refer to your purchase order for specific requirements that
More information2. GENERAL REQUIREMENTS
1. PURPOSE AND SCOPE 1.1 This document defines the Supplier Quality Requirements to be met by suppliers in the performance of the purchase order issued by Sagetech to ensure that externally provided processes,
More informationQUALITY TERMS & CONDITIONS FOR PROCUREMENT Rev A
Sections 1 through 5 apply to all suppliers doing business with RSI. Sections 6 through 9 apply to those suppliers providing materials and products for Aerospace and Defense applications. Acceptance of
More informationQuality Management System
Quality Management System 6.1 Quality Q-Codes () 6.1 Quality Q-Codes Quality Clauses The following quality control clauses apply when specifically noted on the Gear Technology purchase order: Q1- Material
More informationAltech Machining, Inc. Terms and Conditions
11000 Woodside Avenue North Phone: (619) 448-3392 Santee, CA 92071 Fax: (619) 448-6854 info@altechmachining.net Altech Machining, Inc. Terms and Conditions The terms and conditions listed in this document
More informationPurchase Order Quality Terms and Conditions
Section I: General Quality Assurance Requirements Applicable To All Purchase/Subcontract Orders; A. Quality System The Supplier s Quality System shall comply with ISO 9001:2008. All sample inspection must
More informationVendor / Sub-Contractor General Terms & Conditions
Vendor / Sub-Contractor General Terms & Conditions 1. The goods or services are to be delivered to our works or depots as ordered. They must be delivered in good order and condition and exactly in accordance
More informationSupplier Quality Requirements
1 Surveillance and Auditing 1.1 The Supplier s Quality System is subject to initial and annual audits/surveys and acceptance by Texas Almet, its customers, and government regulatory agencies (e.g. The
More informationQUALITY REQUIREMENTS FOR SUPPLIERS
NMB-Minebea UK Ltd Phone: +44 (0)1522 500 933 Doddington Road, Lincoln, Fax: +44 (0)1522 500 975 Lincolnshire LN6 3RA United Kingdom URL: http://www.minebea.co.jp QUALITY REQUIREMENTS FOR SUPPLIERS LNQA0500
More information(A.2) DURING PERFORMANCE OF THIS ORDER, YOUR QUALITY CONTROL SYSTEMS AND MANUFACTURING PROCESS ARE SUBJECT TO REVIEW, VERIFICATION,
(A) GENERAL: (A.1) GENERAL ELECTRIC (GE) IS THE END USER. (A.2) DURING PERFORMANCE OF THIS ORDER, YOUR QUALITY CONTROL SYSTEMS AND MANUFACTURING PROCESS ARE SUBJECT TO REVIEW, VERIFICATION, ANALYSIS, AND
More informationOrbital ATK Alliant Techsystems Defense Electronic Systems Special Mission Aircraft Fort Worth
QUALITY ASSURANCE PROVISIONS FOR PURCHASE ORDER This document includes all Quality Assurance Provisions and definition available for inclusion on purchase orders and subcontracts issued by, Inc.,,, referenced
More informationSTANDARD QUALITY REQUIREMENTS FOR SUPPLIERS F05-QP008 Rev A Dated 08/12/2010
For questions concerning Standard Quality Requirements for Suppliers (F05-QP008), please contact your APC buyer. 1. SCOPE This document establishes requirements for supplier s quality control systems.
More information104 OUTSIDE SERVICES - U.S. GOVERNMENT (DESIGN AUTHORITY IS P&W): (A) GENERAL: (A.1) THE U.S. GOVERNMENT IS THE END USER.
(A) GENERAL: (A.1) THE U.S. GOVERNMENT IS THE END USER. (A.2) DURING PERFORMANCE OF THIS ORDER, YOUR QUALITY CONTROL SYSTEMS AND MANUFACTURING PROCESS ARE SUBJECT TO REVIEW, VERIFICATION, ANALYSIS, AND
More informationNAV 06 MATERIAL CONTROL
MATERIAL CONTROL 1. Is traceability maintained from the material to the material certification test report and other required Objective Quality Evidence (OQE)? 2. Does the contractor have written procedures
More information002 Supplier Quality System Compliance with Rocker Quality System for Suppliers is required for this Purchase Order.
Rocker Industries Supplier Quality Assurance Requirements When any of the following SQAR codes appear on a Purchase Order, the supplier must comply with the requirement. If the supplier has questions or
More information(A.2) DURING PERFORMANCE OF THIS ORDER, YOUR QUALITY CONTROL SYSTEMS AND MANUFACTURING PROCESS ARE SUBJECT TO REVIEW, VERIFICATION,
(A) GENERAL: (A.1) PRATT & WHITNEY (P&W) IS THE END USER. (A.2) DURING PERFORMANCE OF THIS ORDER, YOUR QUALITY CONTROL SYSTEMS AND MANUFACTURING PROCESS ARE SUBJECT TO REVIEW, VERIFICATION, ANALYSIS, AND
More informationQUALITY CLAUSE CODES
14201 Myerlake Circle 5307 Luce Avenue, Bldg 243E Clearwater, FL 33760 McClellan, CA 95652 P (727) 539-8585 F (727) 539-0316 THESE ARE IN ADDITION TO THOSE SET FORTH IN ANY DOCUMENT THAT IS PART OF THE
More informationQUALITY PROCEDURES MANUAL 8.4 PROCUREMENT OF EXTERNALLY PROVIDED GOODS AND SERVICES
M. Sullivan & Son Limited Last Saved Date: 2015-12-10 QUALITY PROCEDURES MANUAL 8.4 PROCUREMENT OF EXTERNALLY PROVIDED GOODS AND SERVICES M. Sullivan & Son Limited Proprietary TABLE OF CONTENTS Section
More informationPURCHASING QUALITY CLAUSES
Page 1 of 5 These requirements apply to all suppliers A. Right of Entry Tri Models, Tri Model s customer and their customers or applicable regulatory agencies shall have right of access to all facilities,
More informationQuality Notes. PCX Aerostructures, LLC Supplier Quality Assurance Requirements - Quality Clauses Revision 14 - January 02, 2015
Quality Notes PCX Aerostructures, LLC Supplier Quality Assurance Requirements - Quality Clauses Revision 14 - January 02, 2015 1.All special processes required by the Purchase Order must be performed by
More informationReplaces: Not applicable.
Page 1/12 SCOPE - defines the quality requirements for purchasing materials, parts and services that may affect product quality of Airborne items. does not include requirements for design and development
More informationSUPPLIER QUALITY CLAUSES
SUPPLIER QUALITY SYSTEM REQUIREMENTS Q1 Quality System The supplier must have a documented and third party accredited system (as applicable) in accordance with the current revision of one or more of the
More informationQuality Assurance Manual
McGarvin Engineering Inc. 35 Maple St. Lowell Ma. 01852 ph. 978-454-2741 fx. 978-459-7999 Quality Assurance Manual 1 Table of Contents Section Element 1.0 Scope and Policy 2.0 Organization 3.0 Quality
More informationSTRAN Technologies Quality Notes
SQN-01 SQN-02 SQN-03 SQN-04 SQN-05 SQN-06 TEST DATA- Test Data is required for all fiber optic cable supplied on this purchase order. An OTDR trace of every optical channel of the fiber optic cable is
More informationTASK REQUIREMENTS. Supplier Quality Requirements
This document is applicable only to suppliers of Production Items as defined below and their subtier suppliers. Non-Production Item suppliers are not subject to this document. This document specifies the
More informationSupplier Quality Requirements
1 of 7 NOTE: YELLOW HI-LITE INDICATES CHANGE FROM THE PREVIOUS REVISION GENERAL REQUIREMENTS (Applies to all orders issued from GMW referencing this document) QR-01 Quality Management Systems AS9100 Suppliers:
More informationPURCHASING QUALITY CLAUSES
PURCHASING QUALITY CLAUSES AS9120:2016, Clause 8.4 AvAir, Inc. Chandler, AZ Revision C Approvals Purchasing Quality Clauses Refer to the Documented Information Register. Revision History Listed below are
More information1.0 Purpose. 2.0 General notes 3.0 QUALITY SYSTEM REQUIREMENTS. Approved by: G. Stugart Prepared by: Schelert
1.0 Purpose This document defines PECO-Astronics (PECO) purchased material flow-down requirements. Additional specifications may also apply and will be documented on the purchase order; all requirements
More informationSupplier Quality Assurance Requirements (SQAR)
Supplier Quality Assurance Requirements (SQAR) Revision B, Date: 6/9/17 Approved (signature on file) Helen Byrnes Director, Quality Assurance Page 1 of 11 Revision Record The current and applicable issue
More informationDocument Type: Main Process: Revision Level: Page: POLICY QUALITY ASSURANCE 3 1 of 6 Process Owner Title:
POLICY QUALITY ASSURANCE 3 1 of 6 Process Owner A. SCOPE This document contains requirements for conducting business with Tri Star Metals, LLC and its customers. It is applicable to suppliers that provide
More informationSupplier Requirements Manual Revision Date:
ABACO-EQP-001 REV B : Approved By Department Signatory Martin Edwards Quality A 13 TH Sep 2017 Martin Edwards Peter Rhodes Purchasing A 13 TH Sep 2017 Peter Rhodes Kelvin Greaves SQE A 13 TH Sep 2017 Kelvin
More informationEIT, LLC Quality Assurance Provisions
EIT, LLC Quality Assurance Provisions The Following QAPs (Quality Assurance Provisions) are applicable to all EIT, LLC externally provided processes, products and services. (Latest revision changes are
More informationEIT, LLC Quality Assurance Provisions
EIT, LLC Quality Assurance Provisions The Following QAPs (Quality Assurance Provisions) are applicable to all EIT, LLC externally provided processes, products and services. (Latest revision changes are
More informationProcedure Documentation
Title: Supplier Quality Requirements (SQR) Page: Page 1 of 14 Record of Revision Revision No. Summary of Revision Revised by Date of Issuance/Revision Section Revised/Added/Deleted 0 J Meiser 05/28/13
More informationSupplier Quality Requirements (SQR)
Supplier Quality Requirements (SQR) General Warmelin Precision Products, LLC (WPP) may refuse to accept materials and services delivered under a Purchase Order (PO) if the Seller fails to comply with the
More informationCopyright JnF Specialties, LLC. All rights reserved worldwide.
Manufacturing Plant Quality Manual (Mo/Yr) Revisions Rev: Letter E.O. Number - Description Date Used On Contract#: Your Company Name Prepared By: Your Dept: Your Dept: POLICIES AND PROCEDURES Your Dept:
More information2.2. The Seller shall be responsible for achieving and maintaining a quality performance level of either:
2.0. Supplier Quality Performance: 2.1. When requested by Boeing, Seller agrees to work with Boeing to develop and implement processes designed at improving Seller s quality performance. Process will include
More informationOrbel Corporation Quality Assurance Provisions (QAP) for Suppliers
A. PURPOSE To define the Orbel quality assurance provisions for inventory materials received from strategic suppliers. This document is intended for use by Orbel strategic suppliers to aid in the quality
More informationMeggitt Oregon Purchase Order Quality Notes
QP-1 QP-2 QP-3 QP-4 QP-5 QP-6 QP-7 QP-8 Inspection System: Supplier shall maintain an inspection system that complies with ISO 9001; AS9100; Meggitt Supplier Quality Requirements Document - MPRC-10, or
More informationPP Quality Assurance Procurement Clauses for Suppliers
PP 360.3 Quality Assurance Procurement Clauses for Suppliers Version No: 7 Created By: Approved By: Erik Keim on 01/29/2019 at 10:44 PM Eric Deffarges on 02/05/2019 at 09:17 AM Valid From: 06/12/2017 Strictly
More information(A.2) DURING PERFORMANCE OF THIS ORDER, YOUR QUALITY CONTROL SYSTEMS AND MANUFACTURING PROCESS ARE SUBJECT TO REVIEW, VERIFICATION,
(A) GENERAL: (A.1) GENERAL ELECTRIC (GE) IS THE END USER. (A.2) DURING PERFORMANCE OF THIS ORDER, YOUR QUALITY CONTROL SYSTEMS AND MANUFACTURING PROCESS ARE SUBJECT TO REVIEW, VERIFICATION, ANALYSIS, AND
More informationPrinted versions may not be the latest. Suppliers shall utilize the latest version which can be found on our website at
6707 Hardeson Rd Everett, WA 98203-7101 USA 425-405-3500 FAX: 425-405-3599 Printed versions may not be the latest. Suppliers shall utilize the latest version which can be found on our website at www.umbragroup.it.
More informationCounterfeit Control Plan for Electrical, Electronic and Electromechanical Parts
Your Logo Counterfeit Control Plan for Electrical, Electronic and Electromechanical Parts Origination Date: XXXX Document Identifier: Date: Project: Document Status: Counterfeit Control Plan for Electrical,
More informationEIT, LLC Quality Assurance Provisions
EIT, LLC Quality Assurance Provisions The Following QAPs (Quality Assurance Provisions) are applicable to all EIT, LLC external providers. External providers are organizations or individuals who provide
More informationCounterfeit Material Prevention I. PURPOSE
I. PURPOSE REV. A Page 1 of 3 The purpose of this procedure is to document the necessary avoidance, detection, mitigation, and disposition process to prevent the purchase and/or use of counterfeit material.
More informationCustomer Specific Requirements. Last Update 23July2015
Customer Specific Requirements Last Update 23July2015 A17 A. In performing the obligations of this Agreement, both Parties will comply with United States export control and sanctions laws, regulations,
More informationSTRAN Technologies Quality Notes
STRAN Technologies Quality Notes SQN-01 SQN-02 SQN-03 SQN-04 TEST DATA Test Data is required for all fiber optic cable supplied on this purchase order. An OTDR trace of every optical channel of the fiber
More informationControlled By: QA Mgr. / Gen. Mgr. Effective Date: 3/31/2014 FORM-70
Controlled By: QA Mgr. / Gen. Mgr. Effective Date: 3/31/2014 FORM-70 RUSSTECH PURCHASE ORDER CLAUSES RPOC 1000 EARLY DELIVERY OK "Time is of the essence for performance under this Purchase Order. Seller
More informationSUPPLIER QUALITY ASSURANCE REQUIREMENTS (SQAR)
SUPPLIER QUALITY ASSURANCE REQUIREMENTS (SQAR) Revision Date: 11 JULY 2014 Approved David Copeland, Manager Supply Chain Quality Suppliers may view this document via the Internet at https://www.triumphsupplysource.com/suppliers/pageview.php?menuitemid=51
More informationSECURE COMMUNICATION SYSTEMS INC. (Secure) QUALITY CLAUSES
SECURE COMMUNICATION SYSTEMS INC. (Secure) QUALITY CLAUSES These quality clauses, when referenced on a Secure s Purchase Order, are considered contractual requirements, in addition to any Purchase Order
More informationSUPPLIER QUALITY ASSURANCE REQUIREMENTS (SQAR)
SUPPLIER QUALITY ASSURANCE REQUIREMENTS (SQAR) Revision Date: 04 OCT 2012 Approved David Copeland, Manager Supply Chain Quality Suppliers may view this document via the Internet at http://www.voughtaircraft.com/suppliers/quality/qualitysqar.htm
More informationDocument Rev: 18 State: RELEASED see Smarteam for approval authorities TASK REQUIREMENTS. Supplier Quality Requirements
Document 0000000000000045 Rev: State: RELEASED see Smarteam for approval authorities This document is applicable only to suppliers of Production Items as defined below and their sub-tier suppliers. Non-
More informationGE - Aviation, Services Supplier Quality Specification
GE - Aviation, Services Supplier Quality Specification Printed Copies Will Not Be Kept Up To Date NUMBER: S-485 Part II Revision: 04 ISSUE DATE: 08 Feb 2012 Title: QUALITY SYSTEM STANDARD FOR DISTRIBUTORS
More informationSupplier Quality Requirements
1 of 7 NOTE: YELLOW HI-LITE INDICATES CHANGE FROM THE PREVIOUS REVISION GENERAL REQUIREMENTS (Applies to all orders issued from GMW referencing this document) QR-01 Quality Management Systems AS9100 Suppliers:
More informationSELLER QUALITY REQUIREMENTS QCS-001 PROCESSING SOURCES
Page 1 SELLER QUALITY REQUIREMENTS QCS-001 PROCESSING SOURCES Notice: A hard copy of this document may not be the document currently in effect. The current version is always the version on the Lockheed
More informationSupplier Nonconformance Notification and Waiver Procedure
DOC NUMER: 1 of 11 Supplier Nonconformance Notification and Waiver Procedure Created y Checked y Checked y Approvals Name Title Date Signature Tamara Crismundo Jesus Villegas Denis eaulieu Sr. Quality
More informationSupplier Nonconformance Requirements (SQR-002) Revision C 18 December 2018
Supplier Nonconformance Requirements () Revision C 18 December 2018 Approved by: ALATUS Aerosystems Supplier Quality Assurance Jeff Harmon Supplier Quality Manager Supplier may view this document on the
More informationType : Quality Procedure: Q - 023CLR Titre / Title: Flow Down of Additional Requirements Revised Date: May
SUPPLIER S MATRIX General Quality Requirements for Supplier: When Code is called out on PO, the following requirements apply: A. The supplier is responsible for meeting all requirements of specifications,
More informationPurchase Order and Quality Clauses
Purchase Order Clauses P01) DELIVERY PAPERWORK - shipments are to include all material traceability, packing sheets, certifications and test reports when the shipment arrives on our dock. Tech Manufacturing
More informationQuality System Supplier Rating
This document may not be disclosed or reproduced in whole or in part without prior written permission from a representative of the Company with the authority to grant such permission. Tips: Double click
More information10. MCI Sales Order Procedure SOP
1.0 PURPOSE 1.1 To define the process and procedure for processing customer Purchase Orders 2.0 RESPONSIBILITY 2.1 The CSE s are responsible for managing this process. 2.2 The Order Entry Manager administers
More informationPressure Control Supplier Quality Requirements Coating & Plating Services SQ-03 Rev: 1.1
Approved By: Jerry Longmire Vice President - Quality Jim Harris Quality Leader - NAM Document Revision Chart The following chart lists the revisions made to this document tracked by version. Use this to
More informationPurchase Order Quality Clause SCC20 Revision E, Effective 1/20/2015
Clause A - Quality System Requirements All references to the term Government in any of the documents referenced below shall be replaced with the term Curtiss-Wright and/or the Government. All references
More informationGARDNER AEROSPACE SUPPLIER QUALITY REQUIREMENTS MANUAL
GARDNER AEROSPACE SUPPLIER QUALITY REQUIREMENTS MANUAL Issue Number: 2 Issue Date: 12/8/15 1 of 19 Contents Revision Summary... 4 1.0 Introduction... 5 2.0 Supplier Quality System Requirements... 6 3.0
More informationPurchase Order Quality Clauses These quality clauses are in addition to the Standard Ameriflex Inc.Terms & Conditions
Purchase Order Quality Clauses These quality clauses are in addition to the Standard Ameriflex Inc.Terms & Conditions Quality Requirements 1-9 are Mandatory on all Purchase Orders for products or services
More informationFLYSHEET 100 Rev. 14 QUALITY SYSTEM REQUIREMENTS
FLYSHEET 100 Rev. 14 QUALITY SYSTEM REQUIREMENTS In addition to the applicable Quality System Code incorporated in this contract, Seller shall comply with the requirements of Section 2.0, titled Additional
More informationQuality Honeycomb Supplier Quality Requirements
1 Surveillance and Auditing 1.1 The Supplier s Quality System is subject to initial and annual audits/surveys and acceptance by, its customers, and government regulatory agencies (e.g. The Department of
More informationD. All distributors shall be reviewed and approved as per company procedure.
PROCEDURE Number: QM-251 Purchase Order (QAP) Quality Assurance Provisions Department: Quality Assurance Revision: 5 Publish Date: 2015-11-18 Prepared by: Quality Manager Authorised by: Director of Operations
More information(A.2) DURING PERFORMANCE OF THIS ORDER, YOUR QUALITY CONTROL SYSTEMS AND MANUFACTURING PROCESS ARE SUBJECT TO REVIEW, VERIFICATION,
(A) GENERAL: (A.1) PRATT & WHITNEY IS THE END USER. (A.2) DURING PERFORMANCE OF THIS ORDER, YOUR QUALITY CONTROL SYSTEMS AND MANUFACTURING PROCESS ARE SUBJECT TO REVIEW, VERIFICATION, ANALYSIS, AND APPROVAL
More informationDefinitions contained in the above mentioned document and industry regulations are applicable herein.
Quality Specification TEC-1021 21May12 Rev E Global Quality Management System Supplement for Various International Nuclear Quality Assurance Criteria, Regulations, and Requirements 1. SCOPE 1.1. Content
More informationPROCUREMENT QUALITY REQUIREMENTS
PROCUREMENT QUALITY REQUIREMENTS S-TEC Corporation One S-Tec Way Mineral Wells, TX 76067 940-325-9406 The supplier including manufacturers and distributors shall follow S-TEC Procurement Quality Requirements
More informationPROCUREMENT QUALITY REQUIREMENTS
PROCUREMENT QUALITY REQUIREMENTS S-TEC Corporation One S-Tec Way Mineral Wells, TX 76067 940-325-9406 The supplier shall follow S-TEC Procurement Quality Requirements (PQRs) during the fabrication of all
More informationGE Oil & Gas Quality Management System Sourcing Guidelines for FPQ/PLQ inspection ARSB-O&G-004 Rev: 2.0
Approved By: Type name or written signature Giovanni Cecchi TMS Quality Leader Livio Loschiavo Global Supply Chain & Global Operations QMS Leader Michele Serpi TMS Leader (Not required if controlled by
More informationSupplier Quality Clauses
Page: 1 of 9 Supplier 425 Strempel St. Seguin, TX 78155 Page: 2 of 9 1.0 PURPOSE 1.1 The purpose of this this Quality Clause Document is to specify requirements by which Quality/Production activities shall
More informationQUALITY MANUAL REVISION CONTROL LOG. Number Rev Rev Date SS Description of Change By Chk App
Superecedes: QPOL-1001.24 Section: REVISION CONTRO LOG REVISION CONTROL LOG Number Rev Rev Date SS Description of Change By Chk App QPOL-0001 18 02-JAN-12 A Review & Update Quality Manual JD CN JD QPOL-0001
More informationPlasma Ruggedized Solutions
Quality Clauses Q1 through Q9E apply to ALL Purchase Orders. Quality Clauses Q10 through Q20 apply when referenced in the text of the purchase order. Q1: Quality Management System The supplier shall maintain