Jurgen Franke P. Eng., Director, Engineering & Terminal Development. Review and rationale for changes to Environmental Management Plans
|
|
- Grant Snow
- 6 years ago
- Views:
Transcription
1 Soleil 342 Rosehill Wynd Tsawwassen, BC V4M 3l9 29 April 2015 Fraser Surrey Docks Limited Partnership Elevator Road Surrey, BC, Canada V3V 2R7 Attention: Jurgen Franke P. Eng., Director, Engineering & Terminal Development Re: Review and rationale for changes to Environmental Management Plans Dear Sir: The following document summarizes proposed changes to the preliminary Construction and Operational Environmental Management Plans (CEMP, and OEMP, respectively) for the amended Project as described in the Proposed Permit Amendment to the Direct Transfer Coal Facility Executive Summary prepared by Fraser Surrey Docks (dated march 18, 2015). Some of the proposed changes will reflect reassessment required as a result of the proposed design changes to the Project. It should be noted the original EMPs were prepared as a single document, and the revised CEMP and OEMP will be prepared as two separate documents. Separating the single EMP into two separate documents will necessitate some duplication of text between the two plans (e.g. project description sections). However, it also makes practical sense since some plans or mitigation measures are relevant to both plans, others are only applicable to the operational or construction phase of the project. The original EMP document provides a framework for identifying and managing changes in the scope of the project, and the need to incorporate information from other assessments, and to elaborate on effective mitigation measures, based on best management practices (BMPs) and guidelines applicable at the time of construction. In addition, it is anticipated some sections will be expanded to provide additional information/clarification about roles and responsibilities, and the document could continue to be adapted as contractors are hired, responsibilities defined and construction techniques finalized. In summary, this review provides a number of revisions and changes to the original document and it should be stressed that some of these changes and revisions are part of a normal process of updating and finalizing the CEMP and the OEMP. 1
2 Section Reference 1.0 Introduction Action required Rationale 1.0 Introduction 1.1 Project Description Revisions recommended to update reference to background documents and assessments forming the basis of the EMP. amendments to the project description. No new assessment 1.2 System Components amendments to the project description. No new assessment 2.0 Construction Program 2.0 Construction Program 3.0 Environmental Setting NEW Section Add New section amendments to the project description. No new assessment Section 3.0 to be changed to Section 4.0 Revision to insert a new section describing the environmental setting, and summarizing how construction activities might impact the ecological components. This section will summarize vegetation and wildlife as well as aquatic habitats in the project area. In addition this section will summarize expected impacts to the environment from the project. Conduct field survey to confirm local site conditions relative to revised project design, and reduced footprint impact. 3.0 Construction Environmental Management Plans change to section 4.0 Note: The numbering of all subsequent sections will also be changed from 3 to Surface Water Quality and Sediment Control Plan Revisions required to reflect mitigation measures outlined in the environmental impact assessment (EIA) and/or other background assessments completed for the project. 2
3 3.1.1 Watercourse Adjacent to Elevator road 3.2 Environmental Monitoring Plan 3.3 Hazardous Materials Management and Spill Response Plan (HMMSRP) Move (including sub sections) Information in this section will be moved and incorporated into the new Section 3.0, which will provide an expanded discussion about the environmental setting. Revisions to describe the role and responsibilities of the environmental monitor in more detail and ensure consistency with mitigation measures in other background assessments, primarily the EIA. Revisions in multiple sub-sections of 3.3, to provide more information about management strategies and responsibilities, and to ensure consistency with mitigation measures in other background assessments, primarily the EIA. Where applicable references to other BMPs or guideline documents will also be added, updated or checked. Revisions will also be made to include a new sub-section covering spill prevention and containment as part of the HMMSRP. This does not require any new assessments as the materials contemplated for use in the project remain the same Spill Preparedness Change to subsection 3.4 Move edit and Revisions to move spill preparedness and spill response to a separate management plan/strategy. Revisions will also ensure consistency with mitigation measures in other background assessments, primarily the EIA. Where applicable references to other BMPs or guideline documents will also be added, updated or checked. No new assessments required, the nature of the products and activities have not changed Spill Response Move and edit As described above for Section move to new separate section and revise. 3.4 Soils Management Plan (SMP) Managing Known or Suspect Contaminated Soils Revisions to incorporate additional information and Revisions to incorporate additional information and 3
4 3.5 Air Quality Management Plan 3.6 Noise Management Plan Revisions to incorporate additional information and assessments and documents. Incorporate information from other disciplines as available. assessments and documents. Incorporate information from other disciplines as available. 3.7 Pile Driving Plan 3.8 Vegetation and Wildlife Protection Plan Revisions to incorporate differences in environmental impact from design changes near Elevator Road and assessments and documents. Conduct field survey to confirm local site conditions relative to revised project design. Re-evaluate habitat balance, based on reduced footprint impact of new design on local watercourses. 4.0 Operational Environmental Management Plan As noted elsewhere in this document the OEMP is being prepared as a separate document from the CEMP, therefore some of the required revisions will include incorporating or duplicating information for the Introduction section of the CEMP. The actual management plans for various activities will then start in Section 2. In addition, the OEMP will be prepared as a draft document and be finalized following construction. This will allow all design changes required or incorporated during construction to be considered and incorporated into the operational plan as applicable. 1.0 Introduction 1.1 Project Description Revisions recommended to update reference to background documents and assessments forming the basis of the EMP. amendments to the project description, incorporating 4
5 1.2 System Components 4.0 Operational Environmental Management Plans Re-number accordingly as Section Air Quality Management Plan Weather Monitoring amendments to the project description incorporating Revisions to identify and document the current applicable version of any system guiding documents prepared for and in effect at Fraser Surrey Docks. These documents would form the basis of the OEMP and would be complemented by mitigation measures specific to the DTCF project outlined in various background assessments for the project. No new assessments documents, (e.g. FSD Anti Idling Policy). Incorporate documents. Incorporate information from other disciplines as available Dust Monitoring documents. Incorporate information from other disciplines as available Dust Mitigation Measures documents. Incorporate information from other disciplines as available. 4.2 Runoff Management Plan Revisions required to incorporate additional information and ensure consistency with final designs and applicable permits Water Treatment Revisions required to incorporate additional information and ensure consistency with final designs and applicable permits Water Quality Monitoring Revisions required to incorporate additional information and ensure consistency with final designs and applicable permits. 5
6 4.3 Emergency Response Plans assessments and documents, (e.g. FSD Terminal Safety Management System, fire safety plans and emergency procedures). No new assessments Combustion assessments and documents, (e.g. FSD Terminal Safety Management System, fire safety plans and emergency procedures). No new assessments Spill Prevention and Response New Section documents, (e.g. FSD Terminal Safety Management System, fire safety plans and emergency procedures). No new assessments New section proposed to provide information on recommended procedures for site maintenance. Would include reference to FSD safe work procedures (SWPs), product stewardship policy and sustainable procurement policy. 4.4 Lighting Plans 4.5 Noise Management Plans 5.0 References and Information Sources (including sub sections) As described above revisions to incorporate applicable information and ensure consistency with other background assessments and documents. Incorporate Applicable to CEMOP and OEMP Revisions required to update references and ensure accurate citation of background documents, assessments, current BMPs and applicable regulatory guidelines or legislation. Should you have any questions regarding the above described review and rationale for revisions 6
7 please feel free to contact the undersigned at or Peter Frederiksen at Sincerely, Soleil Environmental Consultants Ltd. POLARIS Environmental Consultants Ltd. Tom A. Watson, Ph.D., R.P.Bio. (BC), P. Biol. (AB) Senior Environmental Scientist President Peter Frederiksen, CPESC, DipT Senior Environmental Specialist President 7
Public Comment Period. Consideration to Amend Permit No Direct Transfer Coal Facility May 4 19, 2015 Discussion Guide and Feedback Form
Public Comment Period Consideration to Amend Permit No. 2012 072 Direct Transfer Coal Facility May 4 19, 2015 Discussion Guide and Feedback Form Consideration to Amend Permit No. 2012 072 Direct Transfer
More informationPermitting Decision - Fraser Surrey Docks Direct Coal Transfer Facility
Permitting Decision - Fraser Surrey Docks Direct Coal Transfer Facility August 21, 2014 Presentation overview Overview and corporate governance Coal Mandate and project review process Fraser Surrey Docks
More informationTo develop the new facility, the following site preparation and construction activities are planned.
Project Description To develop the new facility, the following site preparation and construction activities are planned. Site Preparation: Remove existing structures and asphalt within building footprints.
More informationEnvironmental Review Process. Presented by Environment and Natural Resource Unit, Lands and Economic Development, BC Region
Environmental Review Process Presented by Environment and Natural Resource Unit, Lands and Economic Development, BC Region Outline 1. Overview of the Canadian Environmental Assessment Act (CEAA) 2. Indigenous
More informationRound 2 Public Consultation
Round 2 Public Consultation Application to Amend Permit No. 2012 072 Direct Transfer Coal Facility July 17 August 21, 2015 Discussion Guide and Feedback Form Application to Amend Permit No. 2012 072 Direct
More informationENVIRONMENTAL GUIDANCE NOTES: CONSTRUCTION ENVIRONMENTAL MANAGEMENT PLAN (CEMP)
ENVIRONMENTAL GUIDANCE NOTES: CONSTRUCTION ENVIRONMENTAL MANAGEMENT PLAN (CEMP) Disclaimer: The information contained in this communication document is intended solely for the use of guidance cannot be
More informationConsultation Summary Report. Fraser Surrey Docks LP. Application to Amend Permit No Direct Transfer Coal Facility
Fraser Surrey Docks LP Application to Amend Permit No. 2012 072 Direct Transfer Coal Facility Consultation Summary Report Round 2 Public Consultation July 17 August 21, 2015 September 2015 Prepared by:
More informationWhat is the Terms of Reference?
What is the Terms of Reference? Framework for content of the Environmental Assessment Certificate Application Provides the scope of technical studies and consultation processes with the public and First
More information12. Environmental management
12. Environmental management 12.1 Overview This section summarises the framework for managing environmental risks associated with construction, commissioning and operation of the Project. It also includes
More informationJanuary 9, Dear Mike
SNC-Lavalin Inc. 1800 1075 West Georgia Street Vancouver, British Columbia Canada V6E 3C9 Telephone: (604) 662-3555 Facsimile: (604) 662-7688 January 9, 2015 Mr. Mike Hallas Manager, Project Management
More informationShell Quest Carbon Capture and Storage Project. Shell Canada Limited
SCREENING SCOPING DOCUMENT For the proposed Shell Quest Carbon Capture and Storage Project Shell Canada Limited Prepared by: Canadian Environmental Assessment Agency Natural Resources Canada Fisheries
More informationCode of Practice for the Environmental Management of Road Salts
Code of Practice for the Environmental Management of Road Salts PWABC 83 rd Annual Technical Conference Penticton, BC Jim Sheehan for Myra Pagé, Compliance Promotion Scientist September 22, 2015 Code of
More informationPROJECT DESCRIPTION...
ENVIRONMENTAL MANAGEMENT PLAN For Phase 1 Works MARCH 2009 South Fraser Perimeter Road South Fraser Perimeter Road TABLE OF CONTENTS 1 INTRODUCTION... 1 2 PROJECT DESCRIPTION... 2 2.1 PROJECT DELIVERY...
More informationProposed G3 Terminal Vancouver Project Update. Presented to North Shore Waterfront Liaison Committee January 14, 2016
Proposed G3 Terminal Vancouver Project Update Presented to North Shore Waterfront Liaison Committee January 14, 2016 G3 & G3 Terminal Vancouver G3 formed to invest in Canada s grain sector by establishing
More informationFile: Report Date: April 3, 2017 Report Number: Mount Polley Mining Corporation P.O. BOX 12 Likely, BC V0L 1N0
Report Date: April 3, 2017 Report Number: 048281 File:107461 Mount Polley Mining Corporation P.O. BOX 12 Likely, BC V0L 1N0 Dear Mount Polley Mining Corporation, Re: Notice Letter, Pollution Abatement
More informationAugust 27, Jim Crandles Director of Planning Port Metro Vancouver 100 The Pointe, 999 Canada Harbour Place Vancouver, BC V6C 3T4
August 27, 2013 Jim Crandles Director of Planning Port Metro Vancouver 100 The Pointe, 999 Canada Harbour Place Vancouver, BC V6C 3T4 Re: Analysis of Options for Covering Barges Jim We remain confident
More informationAppendix D. Stormwater Pollution Prevention Plan
Appendix D Memorandum AECOM 3292 Production Way, Floor 4 604 444 6400 tel Burnaby, BC, Canada V5A 4R4 604 294 8597 fax www.aecom.com To Joan Liu, Metro Vancouver Page 1 CC Subject Conveyance for the NSWWTP
More informationBHP Potash Export Facility at Fraser Surrey Docks Input Consideration Report Application Review Public Comment Period
40600-CO-RPT-55100 Revision 2 November 8, 2018 Input Consideration Report BHP Potash Export Facility at Fraser Surrey Docks Input Consideration Report Application Review Public Comment Period November
More informationAppendix 4. Soil Management Plan
Appendix 4 Soil Management Plan Soil Management Plan This Soil Management Plan (SMP) has been developed for the Giscome Quarry and Lime Plant Project. The SMP is a living document and will be updated as
More information1. ORIGINAL CONSTRUCTION SEQUENCE PRESENTED IN THE APPROVED EIA REPORT
1. ORIGINAL CONSTRUCTION SEQUENCE PRESENTED IN THE APPROVED EIA REPORT The original construction sequence of the northern landfall reclamation of the Project is illustrated in Figure 3 of the EP-354/2009A
More information^BRITISH COLUMBIA. We are currently involved in a number of initiatives relating to species at risk. I will address your concerns point by point.
^BRITISH COLUMBIA 2 1Q ls P ^ 7 2003 VANCOUVER Reference: 73748 Jeremy McCall President Federation of BC Naturalists 425-1367 West Broadway Ave Vancouver BC V6H 4A9 Dear Mr. McCall: a ' Thank you for your
More informationWestridge Marine Terminal Environmental Protection Plan
Westridge Marine Terminal Environmental Protection Plan 1 Westridge Marine Terminal Environmental Protection Plan: Overview What The Environmental Protection Plan (EPP) communicates environmental procedures
More informationEnvironmental Assessment Approval. Sydney Harbour Access Channel Deepening and Sydport Container Terminal
Approval Approval Date: April 28, 2009 Sydney Harbour Access Channel Deepening and Sydport Container Terminal Laurentian Energy Corporation, Proponent Cape Breton Regional Municipality, Nova Scotia The
More informationDESCRIPTION OF THE PROJECT CHANGE
Stantec Consulting Ltd. 70 Southgate Drive, Unit 1 Guelph, Ontario N1G 4P5 September 19, 2012 Stantec File: 160960584 Ministry of the Environment Environmental Approvals Access & Service Integration Branch
More informationGUIDE TO THE DEVELOPMENT OF A MINING AND RECLAMATION PLAN IN NEW BRUNSWICK
PROVINCE OF NEW BRUNSWICK DEPARTMENT OF ENERGY AND RESOURCE DEVELOPMENT Minerals and Petroleum Development Branch GUIDE TO THE DEVELOPMENT OF A MINING AND RECLAMATION PLAN IN NEW BRUNSWICK Guide to the
More informationConstruction Environmental Management Plan (CEMP) for Potash Overland Conveyor
Construction Environmental Management Plan (CEMP) for Potash Overland Conveyor Stephanie Jay K2 Environmental Engineer The Mosaic Company Esterhazy, Saskatchewan, S0A 0X0 Matt Tyree Operations Manager
More informationSouth Landfill Annual Cover Rate Screening Criteria Checklist
South Landfill Annual Cover Rate Screening Criteria Checklist The following checklist is taken from the Guide to Environmental Assessments for Waste Management Projects, Part B Environmental Screening
More informationProject & Environmental Review. Guidelines Demolition. May 2016
Project & Environmental Review Guidelines Demolition May 2016 TABLE OF CONTENTS 1. Introduction... 3 2. Objectives... 3 3. Applicability and Building Permits... 3 4. Guidelines for Preparing a Project
More informationPage 1 of 5. FrontCounterBC Kamloops 441 Columbia Street Kamloops, BC V2C 2T3
FrontCounterBC Kamloops 441 Columbia Street Kamloops, BC V2C 2T3 Date: August 13, 2014 Investigation Plan: General Commercial (Solar Energy) Application for Investigative Licence Site name: Brenda Mine
More informationVANCOUVER FRASER PORT AUTHORITY Project and Environmental Review Project Report COPY
Project and Environmental Review Report Warehouse Development (Phase 3) Prepared for: Greg Yeomans Director, Planning & Development Date: October 5, 2015 Prepared by: Andrew Taylor, Senior Planner Page
More informationWe did. Have you tested your environmental unit lately? Jeff Blanchard, Spectra Energy Sheri Gilmour, Stantec Consulting Ltd.
REMTECH 2016 FAIRMONT BANFF SPRINGS OCTOBER 12-14, 2016 Have you tested your environmental unit lately? We did. Jeff Blanchard, Spectra Energy Sheri Gilmour, Stantec Consulting Ltd. RemTech 2016 October
More informationGolf Course and Recreational Facilities Best Management Guidelines. Regional Official Plan Guidelines
Golf Course and Recreational Facilities Best Management Guidelines Regional Official Plan Guidelines Halton Region Official Plan Guidelines The Regional Official Plan (ROP) is Halton s guiding document
More informationAlberta Transportation The City of Edmonton The City of Calgary
Alberta Transportation The City of Edmonton The City of Calgary PUBLISHING INFORMATION TITLE: PREPARED BY: DOCUMENT HOLDER: Environmental Construction Operations (ECO) Plan Framework Instructions for
More informationKiewit Ledcor TMEP Partnership KLTP Temporary Construction Staging, Parking & Barge Loading COPY
PER No.: 17-122 Tenant: Project: Project Location: VFPA SID No.: VANCOUVER FRASER PORT AUTHORITY PROJECT AND ENVIRONMENTAL REVIEW PROJECT PERMIT Kiewit Ledcor TMEP Partnership KLTP Temporary Construction
More informationShort-term (Construction) Impacts and Potential Mitigation
4 Short-term (Construction) Impacts and Potential Mitigation CHAPTER 4. SHORT-TERM (CONSTRUCTION) IMPACTS AND POTENTIAL MITIGATION This chapter describes short-term (construction) impacts that could result
More informationFactor Potential Effects Mitigation Measures
Natural Environment No impacts of provincial significance to the natural environment are anticipated for the rapid transit project. Other impacts and how they will be mitigated are outlined in the table
More informationProject & Environmental Review. Guidelines Construction Environmental Management Plan (CEMP) Vancouver Fraser Port Authority
Project & Environmental Review Guidelines Construction Environmental Management Plan (CEMP) Vancouver Fraser Port Authority July 2015 TABLE OF CONTENTS 1. Overview... 3 2. Introduction... 3 3. Principles/Objectives...
More informationKELLY SCHERR, P.ENG., MBA, FEC MANAGING DIRECTOR - ENVIRONMENTAL & ENGINEERING SERVICES & CITY ENGINEER RECOMMENDATION
1 TO: FROM: SUBJECT CHAIR AND MEMBERS CIVIC WORKS COMMITTEE MEETING ON JULY 17, 2017 KELLY SCHERR, P.ENG., MBA, FEC MANAGING DIRECTOR - ENVIRONMENTAL & ENGINEERING SERVICES & CITY ENGINEER APPOINTMENT
More informationAPPENDIX C and 2009 Contractor Environmental Management Plans
APPENDIX C 2008 and 2009 Contractor Environmental Management Plans ENVIRONMENTAL MANAGEMENT PLAN For Terminal Finishing Works Deltaport Container Terminal Berth 3 Expansion Delta, British Columbia Prepared
More informationWESTRIDGE MARINE TERMINAL UPGRADE AND EXPANSION PROJECT APPLICATION TO VANCOUVER FRASER PORT AUTHORITY
WESTRIDGE MARINE TERMINAL IN WATER EXCAVATION REPORT WESTRIDGE MARINE TERMINAL UPGRADE AND EXPANSION PROJECT APPLICATION TO VANCOUVER FRASER PORT AUTHORITY Trans Mountain Pipeline ULC Kinder Morgan Canada
More informationPrepared for: Millennium EMS Solutions Ltd. Prepared by: Pisces Environmental Consulting Services Ltd. Red Deer, AB
TURBIDITY MONITORING AND FISH CAPTURE AND RELEASE OPERATIONS FOR THE DX CULVERT SOLIDS REMOVAL PROJECT ON APETOWUN CREEK LOCATED IN NE 23-53-24W5M, NORTHEAST OF HINTON, ALBERTA Prepared for: Prepared by:
More informationTechnical Guidance Document for Environmental Audit Reports
Technical Guidance Document for Environmental Audit Reports EAD-EQ-PCE-TG-10 Signature on Original Environment Quality Sector * Corporate Management Representative Secretary General Originated By Reviewed
More informationLNG Canada submitted a formal update as per Condition 11.2 of the CEAA Decision Statement on June 30, 2017:
LNG Canada Development Inc. Shell Centre 32 nd Floor 400 4 th Avenue SW PO Box 100, Station M Calgary AB T2P 2H5 Canada Submitted electronically to: compliance.conformite@ceaa-acee.gc.ca July 4, 2018 Canadian
More informationA Guide to Project Review
A Guide to Project Review Updated March 2015 Vancouver Fraser Port Authority, doing business as Port Metro Vancouver, has prepared this guide to assist tenants, terminal operators, consulting firms and
More informationSustainable Development
Sustainable Development June 2009 Sustainable Development Vision, commitment and leadership, built on integrity and social conscience. President & CEO John C.S. Lau Husky Energy Inc. Sustainability Definitions
More informationAssessment of Landfill Footprint Alternatives West Carleton Environmental Centre. Option #4 Impact on Agriculture
Assessment of Landfill Footprint Alternatives Figure 422 99 Option #4 Impact on Agriculture The net effects with respect to continued service to customers, the optimized site life/ capacity is 65 million
More informationBackground Information & Mitigation Guidelines MANURE STORAGE IMPROVEMENTS and MORTALITY MANAGEMENT
Background Information & Mitigation Guidelines MANURE STORAGE IMPROVEMENTS and MORTALITY MANAGEMENT I. BACKGROUND FOR MANURE STORAGE AND HANDLING SYSTEMS Supplementary Information Form on sizing and safety
More informationWelcome. About the Proponent. About the Proposed Project. The Proposed Project is now in the Regulatory Review period of the schedule.
Welcome Thank you for attending this Open House for the British Columbia Environmental Assessment Office (EAO) Pre-Application Public Comment Period. The B.C. Ministry of Transportation and Infrastructure
More informationBC Timber Sales ENVIRONMENTAL MANAGEMENT SYSTEM
Functional Area Potential Impacts Impacts Rationalization (assessment of each impact as it relates to the environmental aspect) HARVESTING & SILVICULTURE Construction/rehabilita tion of trails within harvest
More informationAppendix 8. Petroleum Hydrocarbon Products, Ammonium Nitrate and Explosives Management Plan
Appendix 8 Petroleum Hydrocarbon Products, Ammonium Nitrate and Explosives Management Plan Petroleum Hydrocarbon Products, Ammonium Nitrate, and Explosives Management Plan This Petroleum Hydrocarbon Products,
More informationGolf Course and Recreational Facilities Best Management Guidelines
Golf Course and Recreational Facilities Best Management Guidelines JUNE 2012 Legislative & Planning Services Sustainable Communities. Economic Opportunities. Transparent Government Prepared with the assistance
More informationAbbot Point Stormwater Return Dam (EPBC 2010/5561) Operation Annual Compliance Report, January 2016
Abbot Point Stormwater Return Dam (EPBC 2010/5561) Operation Annual Compliance Report, 2015 22 January 2016 Table of Contents 1. Introduction... 4 1.1. The purpose of this Document... 4 1.2. Project Background...
More informationSkeena Sawmills Ltd SFI Certification Audit
Skeena Sawmills Ltd. 2017 SFI Certification Audit From September 27-29 an audit team from KPMG Performance Registrar Inc. (KPMG PRI) carried out an SFI registration audit of Skeena Sawmills Ltd. woodlands
More informationTsawwassen Eelgrass Project
Vancouver Fraser Port Authority Habitat Enhancement Program Tsawwassen Eelgrass Project Public consultation March 20 to April 7, 2017 Discussion guide and feedback form Feedback form inside. Please submit
More informationWelcome! Contact Information
Welcome! Thank you for taking the time to participate in this information session for G3 Terminal Vancouver (G3), an export grain terminal to be built at Lynnterm West Gate in the City of North Vancouver
More informationProject & Environmental Review. Construction Environmental
Project & Environmental Review Guidelines Construction Environmental Management Plan (CEMP) April 2018 TABLE OF CONTENTS 1. Overview... 4 2. Introduction... 4 3. Principles/Objectives... 4 4. Applicability...
More informationCox's Construction Ltd. P.O.Box 157 Lawn A0E-2E0 Tel: (709) Fax: (709)
Cox's Construction Ltd. P.O.Box 157 Lawn A0E-2E0 Tel: (709) 873-2301 Fax: (709) 873 2567 Cells: (709) 873-7731/873-7730/ 697-0861 September 23, 2016 Government of Newfoundland and Labrador Department of
More informationPENDER HARBOUR DOCK MANAGEMENT PLAN
PENDER HARBOUR DOCK MANAGEMENT PLAN 1.0 INTENT OF DOCK MANAGEMENT PLAN The Pender Harbour Dock Management Plan (the DMP) is an instrument of policy that provides guidance in relation to docks authorized
More informationJuly 30, Gordon Edwards Executive Director Alberta Water Council Street, 1400 South Petroleum Plaza Edmonton AB T5K 2G8
July 30, 2008 Gordon Edwards Executive Director Alberta Water Council 9915-108 Street, 1400 South Petroleum Plaza Edmonton AB T5K 2G8 Dear Mr. Edwards: Re: CAPP Position on Wetland Policy and Implementation
More informationProposed Maplewood Marine Restoration Project Discussion guide and feedback form
Vancouver Fraser Port Authority Habitat Enhancement Program Proposed Maplewood Marine Restoration Project Discussion guide and feedback form Public consultation September 24 October 12, 2018 Feedback form
More informationProject Component, Impact Concern, and TK Recommendations that Informed Snap Lake Mine Designs
Table 1 Project Component, Impact Concern, and TK Recommendations that Informed Snap Lake Mine Designs Project Component Impact Concern TK Recommendation Included in Snap Lake Design Not Included in Snap
More informationPhysical Works Terms of Reference
Physical Works Terms of Reference Williston Targeted Debris Management GMSWORKS #22 Order/Clause: Schedule A 3 (c ) and 5 (a) November 26, 2008 1.0 Introduction Terms of Reference for the Peace Water Use
More informationSustainability. April 4, 2018 Marcia Smith, Senior Vice President, Sustainability and External Affairs
Sustainability April 4, 2018 Marcia Smith, Senior Vice President, Sustainability and External Affairs Forward Looking Information Both these slides and the accompanying oral presentation contain certain
More informationMINISTRY OF TRANSPORTATION. Environmental Reference for Contract Preparation
MINISTRY OF TRANSPORTATION Version: February 2007 MINISTRY OF TRANSPORTATION Part of the Environmental Standards and Practices ISSUED BY: PROVINCIAL AND ENVIRONMENTAL PLANNING OFFICE MINISTRY OF TRANSPORTATION
More informationReview of the Fisheries Act 23 DECEMBER 2016 PREPARED BY: THE CANADIAN ENERGY PIPELINE ASSOCIATION
Review of the Fisheries Act 23 DECEMBER 2016 PREPARED BY: THE CANADIAN ENERGY PIPELINE ASSOCIATION 1 Contents Introduction 3 Delegation to the NEB 3 Assessments and regulatory guidance 4 Provincial requirements
More informationApplication for Paragraph 35(2)(b) Fisheries Act Authorization for Workforce Accommodation Centre Revision 1, November 2015
Application for Paragraph 35(2)(b) Fisheries Act Authorization for Workforce Accommodation Centre The copyright of this document is vested in LNG Canada Development Inc. All rights reserved. 8. FISH HABITAT
More information1. Description of and Rationale for Proposed Change
Suite 500, 4342 Queen Street Niagara Falls, Ontario, Canada L2E 7J7 Tel. 905 374 5200 Fax: 905 374 1157 www.hatch.ca Nick Colella 2 St. Clair Avenue West Floor 12A Toronto, ON M4V 1L5 Dear Mr. Colella:
More informationAppendix M. Criteria, Measures and Indicators for Effects Assessment
Appendix M Criteria, Measures and Indicators for Effects Assessment Appendix M. Criteria, Measures and Indicators for Effects Assessment Objective 1: Naturalization Changes to Aquatic Habitat Disruption,
More informationSantoy 8 Satellite Mine at the Seabee Gold Mine. Technical Review Comments. on the. Environmental Impact Statement.
Environmental Impact Assessment Technical Review Comments on the Environmental Impact Statement as submitted by Claude Resources Inc. Saskatchewan Ministry of Environment December, 2009 1. INTRODUCTION
More information5 SCOPE OF THE ENVIRONMENTAL IMPACT ASSESSMENT. The scope of the EIA falls under three broad categories:
5 SCOPE OF THE ENVIRONMENTAL IMPACT ASSESSMENT 5.1 INTRODUCTION The scope of the EIA falls under three broad categories: technical scope; spatial scope; and temporal scope. The scoping process for the
More informationNote: This is a draft document and does not represent a position or decision by government. Part 2: Policy for Cumulative Effects Management
Cumulative CEF DRAFT Effects Policy (April, 2016) Framework Part 2: Policy for Cumulative Effects Management Preamble This is a draft natural resource sector policy being shared for the purpose of gaining
More informationEnvironmental Impact Assessment (EIA)
Environmental Impact Assessment (EIA) as a tool for sustainable mining Cheryl E. Wasserman Associate Director for Policy Analysis Office of Federal Activities Office of Enforcement and Compliance Assurance
More informationChapter 4 Cumulative Effects
Chapter 4 This chapter reevaluates the likely level of cumulative effects to which the Elliott Bay Seawall Project could contribute, given the proposed changes to the project, and determines whether these
More informationGISCOME QUARRY AND LIME PLANT PROJECT
GISCOME QUARRY AND LIME PLANT PROJECT ASSESSMENT REPORT With respect to: the Application by Graymont Western Canada Inc. for an Environmental Assessment Certificate pursuant to the Environmental Assessment
More informationCargill. North Vancouver Grain Terminal Power System Upgrade
Cargill North Vancouver Grain Terminal Power System Upgrade Project Overview Construction of new 69kV/12.47kV indoor substation c/w environmental safeguards Construction of one new power distribution center
More informationRE: Modifications to Suncor Energy Adelaide Wind Project Location
Ministry of Natural Resources Ministère des Richesses naturelles Renewable Energy Operations Team 300 Water Street Peterborough, Ontario K9J 8M5 October 23, 2012 Suncor Energy Products Inc. 150 6th Avenue
More informationBHP Potash Export Facility at Fraser Surrey Docks Input Consideration Report Preliminary Public Comment Period January 2018
40600-CO-RPT-55027 Revision A January 15, 2018 Input Consideration Report Preliminary Public Comment Period This Input Consideration Report presents the findings from the Preliminary Public Comment Period
More informationAppendix H. Construction Environmental Management Plan (CEMP)
Appendix H Construction Environmental Management Plan (CEMP) Giscome Quarry and Lime Plant Giscome, BC Construction Environmental Management Plan PGL File: 2184-10.01 Rev. 1.0 July 2016 Table of Contents
More informationTechnical Guidance Document for Operational Environmental Management Plan (OEMP)
Technical Guidance Document for Operational Environmental Management Plan (OEMP) EAD-EQ-PCE-TG-06 Signature on Original Environment Quality Sector * Corporate Management Representative Secretary General
More informationTSLEIL-WAUTUTH NATION
TSLEIL-WAUTUTH NATION People of the Inlet lisa Walls Regional Director, Pacific and Yukon Region Canadian Environmental Assessment Agency PO Box 10114 701 West Georgia St, Suite 410 Vancouver, BC V7V 1C6
More informationBACKGROUND INFORMATION DOCUMENT:
BACKGROUND INFORMATION DOCUMENT: APPLICATION FOR A MINING RIGHT MMAKAU COAL (PTY) LTD SCHURVEKOP 227 IS, BETHAL, MPUMALANGA 1. INTRODUCTION Mmakau Coal (Pty) Ltd intends to submit an application for a
More informationSan Francisco Water Power Sewer Operator of the Hetch Hetchy Regional Water System
San Francisco Water Power Sewer Operator of the Hetch Hetchy Regional Water System Bureau of Environmental Management 1145 Market Street, Suite 500 San Francisco, CA 94103 T 415.934.5700 F 415.934.5750
More informationSummary of proposed amendment to the Class EA for MNRF Resource Stewardship and Facility Development Projects
Summary of proposed amendment to the Class EA for MNRF Resource Stewardship and Facility Development Projects Background: MNRF is requesting amendments to the Class EA for MNRF Resource Stewardship and
More informationCOPY. Land Use Plan to be amended. Port Water proposed.
PER No.: 15-167 Applicant: Project: Project Location: VFPA SID No.: Land Use Designation: Category of Review: VANCOUVER FRASER PORT AUTHORITY PROJECT AND ENVIRONMENTAL REVIEW PROJECT PERMIT Vancouver Fraser
More informationClient File No.: November 1, Dallas Mowat Target Products Ltd Bradner Road Abbotsford B.C. V4X 1H3. Dear Mr.
4'4,1ati' oi:w IOW Conservation and Water Stewardship Climate Change and Environmental Protection Division Environmental Approvals Branch 123 Main Street, Suite 160, Winnipeg, Manitoba R3C 1A5 T 204 945-8321
More informationRe: Roberts Bank Terminal 2 Project Response to Comments on Environmental Impact Statement Completeness. Dear Chief James Thomas and Councillors:
October 13, 2015 Chief James Thomas and Councillors Halalt First Nation 7973 Chemainus Road Chemainus BC V0R 1K5 By Email: Re: Roberts Bank Terminal 2 Project Response to Comments on Environmental Impact
More informationSubstation Developments Environmental Guidelines Checklist for Applicants
Substation Developments Environmental Guidelines Checklist for Applicants Effective date: February 1, 2016 These guidelines are intended to be used in conjunction with the flowchart in Figure 1 which conceptually
More informationSpectra Energy Midstream Canada Partner Corporation 2016 Application for Approval to Reactivate the Pesh Creek Pipeline and Pesh Creek Loop
APPLICATION Spectra Energy Midstream Canada Partner Corporation 2016 Application for Approval to Reactivate the Pesh Creek Pipeline and Pesh Creek Loop Spectra Energy Midstream Canada Partner Corporation,
More informationDraft Amendment Application Report, Agni Steels SA February 2011 Executive Summary EXECUTIVE SUMMARY
EXECUTIVE SUMMARY PROJECT BACKGROUND AND DESCRIPTION On the 16 February 2009, Agni Steels SA (Pty) Ltd (formerly Afro Asia Steels), was issued an Environmental Authorisation for the construction and operation
More informationCOPY PROJECT AND ENVIRONMENTAL REVIEW REPORT PER NO NEPTUNE BULK TERMINALS (CANADA) LTD. DUST SUPPRESSION UPGRADE
PROJECT AND ENVIRONMENTAL REVIEW REPORT PER NO. 16-072 NEPTUNE BULK TERMINALS (CANADA) LTD. DUST SUPPRESSION UPGRADE Prepared for: Director, Planning & Development May 15, 2017 VANCOUVER FRASER PORT AUTHORITY
More informationGrassy Mountain Coal Project Environmental Impact Assessment Project Summary Table
Grassy Mountain Coal Project Environmental Impact Assessment Project Summary Table Benga Mining Limited 233 20 Avenue PO Box 660 Blairmore, Alberta, T0K 0E0 Phone: + 403 73 60 Business: 470 93 Riversdale
More informationE1184 v1. 6. Environmental Management Plan (EMP)
Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized 6. Environmental Management Plan (EMP) This EMP reviews the potential negative impacts
More informationPrepared for: Millennium EMS Solutions Ltd. Prepared by: Pisces Environmental Consulting Services Ltd. Red Deer, AB
TURBIDITY MONITORING AND FISH CAPTURE AND RELEASE OPERATIONS FOR FISH BARRIER REMOVAL, CHANNEL RESTORATION, AND BANK ARMOURING PROJECTS ON APETOWUN CREEK LOCATED IN NE 23-53-24 W5M AND SW 25-53-24 W5M,
More informationSemCAMS Area Project Description
REGULATORY The Redwillow Pipeline Project involves crossing a provincial boundary, and therefore, approval for it will require the preparation of an application to the NEB. plans to proceed with the regulatory
More informationBMA Broadmeadow Mine - EHP EA amendment application (Pre-lodgement meeting) Wednesday 22 April, 2015
BMA Broadmeadow Mine - EHP EA amendment application (Pre-lodgement meeting) Wednesday 22 April, 2015 Broadmeadow Mine 2 BRM Subsidence Management Plan SMP Purpose SMP is the document that outlines the
More informationAPPENDIX A ENVIRONMENTAL MANAGEMENT PLAN - CONSTRUCTION
APPENDIX A ENVIRONMENTAL MANAGEMENT PLAN - CONSTRUCTION ENVIRONMENTAL MANAGEMENT PLAN FOR THE CONSTRUCTION OF THE TRENTS GENERATING STATION AND ASSOCIATED FACILITIES Submitted to: The Barbados Light &
More informationAbout the Proposed Project
About the Proposed Project The proposed facility will be used to ship bulk grain products including wheat, barley, oil seeds, pulses and other specialty grains. The throughput for this proposed Project
More informationTable of Contents. List of Tables. 11. Advantages and Disadvantages
Table of Contents 11. Advantages and Disadvantages... 11-1 page List of Tables... 11-1 11. Advantages and Disadvantages The overall advantages and disadvantages of the DMNP are articulated, summarized
More informationLNG Canada Development Inc.
LNG Canada Development Inc. Shell Centre 32 nd Floor 400 4 th Avenue SW PO Box 100, Station M Calgary AB T2P 2H5 Canada Submitted electronically to: compliance.conformite@ceaa-acee.gc.ca April 20, 2016
More informationCanada. Record of Proceedings, Including Reasons for Decision. Cameco Corp_o_ra_ti_o_n. Proponent
Canadian Nuclear Safety Commission Commission canadienne de sorete nucleaire Record of Proceedings, Including Reasons for Decision Proponent Cameco Corp_o_ra_ti_o_n _ Subject Comprehensive Study Report
More information