Iarnród Éireann/Irish Rail Risk Management and Scour Protection Works on Masonry Arches and Piers

Size: px
Start display at page:

Download "Iarnród Éireann/Irish Rail Risk Management and Scour Protection Works on Masonry Arches and Piers"

Transcription

1 Iarnród Éireann/Irish Rail Risk Management and Scour Protection Works on Masonry Arches and Piers Assessment & Maintenance of Masonry Arch Bridges Engineers Ireland 29 th January 2016 Stephen Bateson BSc (Eng) Dip Eng Dip Hy & Geo Eng CEng MIEI Principal Engineer - Structures

2 Background Iarnród Éireann has 5200 bridges in total are termed under-bridges 478 of these span over watercourses. The majority of our structures spanning over water have some form of masonry support in or adjoining the watercourse. This presentation will include both masonry arch structures and structures with masonry piers in/adjoining watercourse that are maintained by IE as part of the Bridge Maintenance Plans over the Network. The characteristics of the bridge assets structures (width, clearance, alignment & position) are set by a track alignment that is in the region 150 years old. The piers may be skew to the river to maintain track alignment. The spans may be short and multiple. The bridges were constructed to the design and requirements of the day.

3 Background Historically the maintenance of the railway infrastructure, including railway bridges has experienced under investment. This has affected the implementation of data capturing and studies as well as physical maintenance works. The present investment level, provided by the MAC (Multi Annual Contract) is still below that required to achieve a steady state level, therefore as the assets get older they require greater funding. Significant works have always been undertaken and a relatively large number have been completed in recent years.

4 Background Examples of Scour Repair Works

5 Background Examples of Scour Repair Works

6 Development of the Maintenance Process From 2005 IÉ has been formally undertaking Underwater Bridge inspections as part of the bridge inspection programme. This was originally based on a limited number of what were deemed high risk or principal structures. In 2009 a scour vulnerability rating was included within the deliverable of a Bridge Scour Inspection (BSI). This programme was widened to include for a full baseline of all bridge structures (span <1.8m). The number of structures inspected was 105. Following organisational change in 2010 the process has evolved into a risk based process to prioritise the maintenance works on scour protection of bridges.

7 Development of the Maintenance Process Comparison with other UIC companies

8 Management Policy These are now managed in accordance with Standard CCE-TMS-415 Flood and Scour Management Standard. The policy of this is to manage the risk posed by hydraulic action on railway infrastructure.

9 Flood & Scour Management Process The process involves Screening Stage Bridge Scour Inspection BSI Initial Assessment Stage Bridge Hydraulic Assessment Detailed Assessment & Design Stage Bridge Scour Countermeasure Stage 2 Assessment Re-assessment Stage Re-inspection

10 Flood & Scour Management Process Scour Inspection BSI -Screening Stage Bridge Scour Inspection Cyclic Inspection 1,3,6 or 10 yrs BHA - Initial Assessment Re- Assessment Counter - measure Design Hydraulic Assessment BSCM BFI Detail Assessment & Design Bridge Scour Countermeasure Design Design to C742 Ciria Manual Bridge Hydraulic Assessment Scour Vulnerability Rating (SVR) Risk Rating generated

11 Bridge Scour Inspection BSI The process involves a BSI Bridge Scour Inspections as the basis for the process. Cyclic Inspection that delivers a factual report of the underwater structure and the river channel. This is undertaken by an external team that tenders the work from a Framework list. This factual report gives details of the condition of the river channel and the structure 1 m above water height of the high water mark. The Inspection survey varies based on the Category of the Structure. Category 1: Inspection of the bridge, through touching and probing of all elements of the bridge to a height of 1m above the highest water level and a riverbed survey to an extent of 60m upstream and 60m downstream of bridge. Category 2: Inspection of the bridge, through touching and probing of all elements of the bridge to a height of 1m above the highest water level and a riverbed survey to an extent of 300m upstream and 60m downstream of bridge. Category 3: Inspection of the bridge, through touching and probing of all elements of the bridge to a height of 1m above the highest water level and a riverbed survey to an extent of 20m upstream and 20m downstream of bridge.

12 Bridge Hydraulic Assessment BHA The Next Step after the BSI cycle involves review of factual reports by Hydrologist for a Hydraulic Assessment. BHA Bridge Hydraulic assessment A Hydrologist undertakes this stage of the process and using the BSI reports a SVR (Scour Vulnerability Rating) is calculated. This SVR is generated from a screening process developed by the US Forestry Service and uses variables from both the structure and the river channel to arrive at a score out of 67. The higher the score the higher the vulnerability to scour. The Hydrologist specifies the return period for the cyclic inspection. 1, 3, 6 or 10 years. For structures considered high risk a shorter return cycle may be advised.

13 Bridge Hydraulic Assessment BHA Risk Level Intervention Required Return Period for BSI Low Risk No Planned Works 6 years Medium Risk Plan works long term 3 years High Risk Plan Works short term < 1 years

14 Bridge Foundation Inspection BFI One of the larger contributors to the SVR score is that of the known depth and characteristic of the foundations. BFI Bridge Foundation Investigation are undertaken. Historically bridge records did not include foundation details, unless by exception, ie UBB 82 Boyne Viaduct. A programme was commenced to use Site Investigation techniques to determine the depth, form and dimensions of foundations. The characteristics of the underlying strata was also determined where possible. These are costly and require careful programming to avoid flooding and planting seasons that effect the accessing of the sites.

15 Bridge Foundation Inspection BFI Investigation involves: Geology Study Field Work coring holes, insitu testing (cobra probe, seismic Refractions, Resistivity Imaging) Determined in this case that there were stone foundations supported by granite bedrock. Position of Rock Core

16 Bridge Foundation Inspection BFI Following reduction in flood levels and inspection of bridge elements, it was possible to allow a reopening of the line within 3 days, due to the knowledge that the bridge piers were founded on Recent Flooding incident in Enniscorthy UBR323. granite bedrock.

17 Bridge Foundation Inspection BFI Flooding at Enniscorthy December 2015

18 Detailed Assessment & Design This stage of Detailed assessment and design involves: Site Inspection/survey. Selection of countermeasure design C742 Manual at Scour Bridges and Other Hydraulic Structures Undertaken hydraulic equations Based on DMRB Advice note on Assessment of Scour at Highway Bridges, Vol 3, Section 4 Part 21 BA 74/06. Q2oo is used as Flood event. Where river gauged, design flow is calculated Where river un-gauged, design flow calculated on catchment area. OPW data. Values used in HEC-Res model to calculate scour depth. Generally a 2 D model. Method statement of proposed works, incl environmental aspects & Fisheries etc. Preparation of a final report to include calculations, construction drawings and method statement.

19 Countermeasure Design Selection process This is a basic check list that gives indication of the suitability of the repair chosen for a given location and budget.

20 Case Study 1 UBC 45 Sallins Dublin to Cork Line SVR 51/67 Medium to High Risk River Liffey, near Sallins, Co Kildare. A scour depression upstream side of Central Pier Large blockage on Left span opening. Work done to remove blockage and open channel Install rip rap to central pier Maintenance works to masonry piers and abutments

21

22 Design UBC 45

23 UBC 45 Dublin - Cork Line

24 UBC 45 Dublin - Cork Line Temporary Sandbagging to prepare for installation of rip rap to front of pier.

25 Case Study 2 UBC 289 Dublin to Cork Line SVR 32/67 Medium Risk Undermining of concrete apron in main channel Large Depression downstream of Concrete Apron Erosion along downstream abutment Concrete apron removed and replaced with dished rip rap. Obstruction removed to provide for all 3 channels to be available. Armour provided for river banks

26 Design - UBC 289

27 Design UBC289

28 Rep Rap and rock armour to river banks

29 Completed structure rip rap & armour Dished rip rap apron

30 Case Study 3 UBS 507 Dublin to Sligo Line SVR 37/67 Moderate but other defects present. Undermining of Upstream wingwall. Erosion of channel bed. Repairs to Arch Installation of rip rap and approach Protection armour.

31 Design UBS507

32 Design UBS507

33 UBS 507 Pre- works Dry cell prior to installation of rip rap Excavation works Installation of rip rap in dry cell

34 Case Study 4 UBE147 Limerick to Ennis Line SVR 42/67 - Medium to High Scour Depression along central pier. Further scour occurred and works were programmed. Concrete Apron with Approach Rip Rap installed.

35 UBE 147 Concreting works to span The completed project Finished Rip-Rap

36 Design UBE 147

37

Strategies to Mitigate Scour Critical Structures

Strategies to Mitigate Scour Critical Structures U.S. Department of Transportation Federal Highway Administration Strategies to Mitigate Scour Critical Structures Dan Ghere Hydraulics Engineer (708) 283-3557 dan.ghere@dot.gov Support Material HEC 23,

More information

Appendix 15.3 Hydraulic Assessment of Sewers

Appendix 15.3 Hydraulic Assessment of Sewers Appendix 15.3 Hydraulic Assessment of Sewers Irish Water Arklow Wastewater Treatment Plant Project EIA Report Issue September 2018 Arup \\GLOBAL\EUROPE\DUBLIN\JOBS\247000\247825-00\4. INTERNAL\4-03 DESIGN\4-03-02

More information

South East Route 2011/12 Scour Assessment Programme

South East Route 2011/12 Scour Assessment Programme South East Route 2011/12 Scour Assessment Programme Detailed Scour Assessment Report Bridge: ESK-1209 at 111miles 0968yards June 2012 Network Rail South East Route General Offices Waterloo Station LONDON

More information

Temporary Watercourse Crossing: Fords

Temporary Watercourse Crossing: Fords Temporary Watercourse Crossing: Fords DRAINAGE CONTROL TECHNIQUE Low Gradient Velocity Control Short Term Steep Gradient Channel Lining Medium-Long Term Outlet Control Soil Treatment Permanent [1] [1]

More information

MINNESOTA DEPARTMENT OF TRANSPORTATION BRIDGE SCOUR EVALUATION PROCEDURE FOR MINNESOTA BRIDGES

MINNESOTA DEPARTMENT OF TRANSPORTATION BRIDGE SCOUR EVALUATION PROCEDURE FOR MINNESOTA BRIDGES MINNESOTA DEPARTMENT OF TRANSPORTATION BRIDGE SCOUR EVALUATION PROCEDURE FOR MINNESOTA BRIDGES December 2009 Introduction This document describes the policy of the Minnesota Department of Transportation

More information

Temporary Watercourse Crossing: Culverts

Temporary Watercourse Crossing: Culverts Temporary Watercourse Crossing: Culverts DRAINAGE CONTROL TECHNIQUE Low Gradient Velocity Control Short Term Steep Gradient Channel Lining Medium-Long Term Outlet Control Soil Treatment Permanent Symbol

More information

3.5 Hydrology & Hydraulics

3.5 Hydrology & Hydraulics 3.5 Hydrology & Hydraulics 3.5.1 Purpose The purpose of this section is to provide results from the analysis and assessment of the impact of the proposed Carmichael Rail Alignment (Option 11 Revision 1)

More information

LOCATION AND DESIGN DIVISION

LOCATION AND DESIGN DIVISION VIRGINIA DEPARTMENT OF TRANSPORTATION LOCATION AND DESIGN DIVISION INSTRUCTIONAL AND INFORMATIONAL MEMORANDUM GENERAL SUBJECT: CULVERT DESIGN SPECIFIC SUBJECT: COUNTERSINKING AND LOW FLOW CONSIDERATIONS

More information

Scour Analysis and Countermeasure Design

Scour Analysis and Countermeasure Design Scour Analysis and Countermeasure Design for UNION STREET RAILROAD BRIDGE (Trail Connection Project) Key No. 11085 ODOT, Region 2 Local Agency On-Call ATA 23456 WOC 1 City of Salem, Urban Development HDR

More information

Created by Simpo PDF Creator Pro (unregistered version) Asst.Prof.Dr. Jaafar S. Maatooq

Created by Simpo PDF Creator Pro (unregistered version)  Asst.Prof.Dr. Jaafar S. Maatooq Lect.No.9 2 nd Semester Barrages, Regulators, Dams 1 of 15 In order to harness the water potential of a river optimally, it is necessary to construct two types of hydraulic structures, as shown in Figure

More information

Flood Hazard Assessment Report Falls Gulch, Larimer County, Colorado January 16, 2013

Flood Hazard Assessment Report Falls Gulch, Larimer County, Colorado January 16, 2013 United States Department of Agriculture Natural Resources Conservation Service Denver Federal Center Building 56, Room 2604 P.O. Box 25426 Denver, CO 80225 720-544-2818-OFFICE alton.albin@co.usda.gov Flood

More information

Annual report to European Rail Agency from National Investigation Body (Ireland)

Annual report to European Rail Agency from National Investigation Body (Ireland) 2006 Annual report to European Rail Agency from National Investigation Body (Ireland) D. Murton, Chief investigator Rail Incident Investigation Unit (Ireland) 1/1/2006 2006 Annual Report to European Railway

More information

technical memorandum

technical memorandum technical memorandum bridges and other Bridge condition indicator guide TM-4008 March 2014 1.0 Introduction 1.1 The need for bridge indicators In order to maintain and manage a stock of bridges and other

More information

FRST 557 Lecture 7b Cross Drainage Structures: Culverts and Bridges

FRST 557 Lecture 7b Cross Drainage Structures: Culverts and Bridges FRST 557 Lecture 7b Cross Drainage Structures: Culverts and Bridges Lesson Background and Overview: The last lesson introduced the topic of water management relative to forest roads and further explored

More information

Refer to Chapter 3.0 (Description of Development) for a detailed site and development description.

Refer to Chapter 3.0 (Description of Development) for a detailed site and development description. 7. WATER: HYDROGEOLOGY & HYDROLOGY 7.1 Introduction This chapter of the EIAR comprises of an assessment of the likely impact of the proposed development on the surrounding surface water and hydrogeological

More information

CLAY STREET BRIDGE REPLACEMENT

CLAY STREET BRIDGE REPLACEMENT HYDROLOGY /HYDRAULICS REPORT. EL DORADO COUNTY CLAY STREET BRIDGE REPLACEMENT Prepared by: Joseph Domenichelli Domenichelli & Associates 1107 Investment Blvd., Suite 145 El Dorado Hills, California 95762

More information

UNDERWATER BRIDGE INSPECTION REPORT STRUCTURE NO MSAS NO. 119 OVER THE RED LAKE RIVER DISTRICT 2 - POLK COUNTY, CITY OF EAST GRAND FORKS

UNDERWATER BRIDGE INSPECTION REPORT STRUCTURE NO MSAS NO. 119 OVER THE RED LAKE RIVER DISTRICT 2 - POLK COUNTY, CITY OF EAST GRAND FORKS UNDERWATER BRIDGE INSPECTION REPORT STRUCTURE NO. 60019 MSAS NO. 119 OVER THE RED LAKE RIVER DISTRICT 2 - POLK COUNTY, CITY OF EAST GRAND FORKS AUGUST 29, 2012 PREPARED FOR THE MINNESOTA DEPARTMENT OF

More information

UNDERWATER BRIDGE INSPECTION REPORT STRUCTURE NO TRUNK HIGHWAY NO. 3 rd Avenue/Central Avenue OVER THE MISSISSIPPI RIVER

UNDERWATER BRIDGE INSPECTION REPORT STRUCTURE NO TRUNK HIGHWAY NO. 3 rd Avenue/Central Avenue OVER THE MISSISSIPPI RIVER UNDERWATER BRIDGE INSPECTION REPORT STRUCTURE NO. 2440 TRUNK HIGHWAY NO. 3 rd Avenue/Central Avenue OVER THE MISSISSIPPI RIVER DISTRICT M HENNEPIN COUNTY OCTOBER 23, 2008 PREPARED FOR THE MINNESOTA DEPARTMENT

More information

Resilient infrastructure Tools to assess infrastructure performance in the face of coastal erosion and flooding

Resilient infrastructure Tools to assess infrastructure performance in the face of coastal erosion and flooding March 2016 Cathal Mangan Resilient infrastructure Tools to assess infrastructure performance in the face of coastal erosion and flooding Emer Kennedy Susana Lizondo Contents Background & aims Irish Rail

More information

(b) Discuss in brief shaft spillway with neat sketches. Marks 04. OR Q (2) Explain in brief USBR stilling basin. Marks 08

(b) Discuss in brief shaft spillway with neat sketches. Marks 04. OR Q (2) Explain in brief USBR stilling basin. Marks 08 (b) Discuss in brief shaft spillway with neat sketches. Marks 04 OR Q (2) Explain in brief USBR stilling basin. Marks 08 Stilling Basins The basins are usually provided with special appurtenances including

More information

Volume II: Hazard Annex Dam Failure

Volume II: Hazard Annex Dam Failure Volume II: Hazard Annex Dam Failure Causes and Characteristics of Dam Failure Dam Characteristics Dams are impervious structures that block the flow of water in a river or stream, capturing water behind

More information

PLANNING AND DESIGN PARAMETERS BRIDGE STRUCTURES. Engr. Ericson Mammag Feasibility Study Preparation CHARM2 Project

PLANNING AND DESIGN PARAMETERS BRIDGE STRUCTURES. Engr. Ericson Mammag Feasibility Study Preparation CHARM2 Project PLANNING AND DESIGN PARAMETERS BRIDGE STRUCTURES Engr. Ericson Mammag Feasibility Study Preparation CHARM2 Project KEY ELEMENTS IN RURAL INFRA Planning & Design Bridges Potable Communal Small Water Roads

More information

Appendix C: Facility Illustrations

Appendix C: Facility Illustrations Appendix C: Facility Illustrations PORT ELIZABETH EASTERN CAPE CONSULTING ENGINEERS Registration no. 1998/000322/07 Port Elizabeth EASTERN CAPE CONSULTING ENGINEERS Registration no. 1998/000322/07 EASTERN

More information

Unique ID: (from PFRA database) Location: Clonfert, Co. Galway. Stage 1: Desktop Review

Unique ID: (from PFRA database) Location: Clonfert, Co. Galway. Stage 1: Desktop Review Location: Clonfert, Co. Galway Unique ID: 252906 (from PFRA database) Initial OPW Designation APSR AFRR IRR Co-ordinates Easting: 197134 Northing: 221731 River / Catchment / Sub-catchment Un-named minor

More information

Guideline for Bridge Safety Management February 2012

Guideline for Bridge Safety Management February 2012 Guideline for Bridge Safety Management February 2012 Table of Contents Foreword Part A General 0.1 Definitions 0.2 Scope 0.3 Application 0.4 Responsibility Part B Bridge Safety Assurance 1.1 Scope 1.2

More information

Safe Management of Structures

Safe Management of Structures Safe Management of Structures Synopsis This document mandates the requirements for managing the structural integrity of structures so that they do not present an unacceptable risk to safety as a result

More information

APPLICATION FORM AF-50: CONSENT UNDER SECTION 50, ARTERIAL DRAINAGE ACT, 1945

APPLICATION FORM AF-50: CONSENT UNDER SECTION 50, ARTERIAL DRAINAGE ACT, 1945 APPLICATION FORM AF-50: CONSENT UNDER SECTION 50, ARTERIAL DRAINAGE ACT, 1945 APPLICATION DETAILS Name of Applicant: Company / authority: Address: Tel: Fax: Email: Date of Application: Client (if appropriate):

More information

State of New Jersey NEW JERSEY DEPARTMENT OF TRANSPORTATION 1035 PARKWAY AVENUE P.O. Box 600 TRENTON, NEW JERSEY

State of New Jersey NEW JERSEY DEPARTMENT OF TRANSPORTATION 1035 PARKWAY AVENUE P.O. Box 600 TRENTON, NEW JERSEY State of New Jersey NEW JERSEY DEPARTMENT OF TRANSPORTATION 1035 PARKWAY AVENUE P.O. Box 600 TRENTON, NEW JERSEY 08625-0600 BRIDGE RE-EVALUATION SURVEY REPORT STRUCTURE NO. 3XXX-XXX ROUTE I-287 SB OVER

More information

Rumsey Bridge Project

Rumsey Bridge Project Prepared for Rumsey Town Hall July 21, 2014 Public Information Meeting Firm Introduction Quincy Engineering since 1992 We specialize in: Bridge design Roadway design Construction management Our key clients

More information

Welcome to your weekly update on the latest situation on the county s bridges and roads following the floods

Welcome to your weekly update on the latest situation on the county s bridges and roads following the floods 26 February 2016 Welcome to your weekly update on the latest situation on the county s bridges and roads following the floods 2015-16. Whilst we will make every effort to make this as comprehensive as

More information

Good Practice Guide. Technical Guidance: Flood risk activity exemptions Date Published: April GPG 221 Document Owner: Flood Risk Strategy

Good Practice Guide. Technical Guidance: Flood risk activity exemptions Date Published: April GPG 221 Document Owner: Flood Risk Strategy Good Practice Guide Technical Guidance: Flood risk activity exemptions Date Published: April 2016 GPG 221 Document Owner: Flood Risk Strategy Page 1 of 41 Version History: Document Date Summary of Changes

More information

UPRR criteria for sizing waterway openings under bridges and through culverts are as follows:

UPRR criteria for sizing waterway openings under bridges and through culverts are as follows: UNION PACIFIC RAILROAD SCOPE OF HYDROLOGIC/HYDRAULIC DESIGN ENGINEERING AND PERMITTING SERVICES FOR SIZING WATERWAY OPENINGS AT NEW AND REPLACEMENT STRICTURES These flood passage criteria were developed

More information

Experimental Study on the Skewed Integral Bridge by Using Crushed Concrete Geobags as Scour Protection (ICSE6-276)

Experimental Study on the Skewed Integral Bridge by Using Crushed Concrete Geobags as Scour Protection (ICSE6-276) Experimental Study on the Skewed Integral Bridge by Using Crushed Concrete Geobags as Scour Protection (ICSE6-276) Engineering applications Bridge Scour Authors: Shatirah Akib Afshin Jahangirzadeh Lim

More information

MISENER DAM. Site Number LYNN STREET, PORT DOVER km N of Highway 6

MISENER DAM. Site Number LYNN STREET, PORT DOVER km N of Highway 6 NORFOLK COUNTY MISENER DAM Site Number 980501 LYNN STREET, PORT DOVER 0.65 km N of Highway 6 Ontario Structure Inspection Manual - Inspection Form Site Number: 980501 Inventory Structure Name Misener Dam

More information

Temporary Stream Crossing

Temporary Stream Crossing Categories EC Erosion Control SE Sediment Control TC Tracking Control WE Wind Erosion Control Non-Stormwater NS Management Control Waste Management and WM Materials Pollution Control Legend: Primary Objective

More information

8 Geology, Hydrology & Hydrogeology

8 Geology, Hydrology & Hydrogeology Inverneill Wind Farm Scoping Report Page 42 8 Geology, Hydrology & Hydrogeology 8.1 Introduction The EIA will consider the potential issues arising from the construction, operation and decommissioning

More information

Temporary Stream Crossing

Temporary Stream Crossing Temporary Stream Crossing NS-4 Objectives EC Erosion Control SE Sediment Control TR Tracking Control WE Wind Erosion Control Non-Stormwater NS Management Control Waste Management and WM Materials Pollution

More information

APPLICATION FORM AF-50: CONSENT UNDER SECTION 50, ARTERIAL DRAINAGE ACT, 1945

APPLICATION FORM AF-50: CONSENT UNDER SECTION 50, ARTERIAL DRAINAGE ACT, 1945 APPLICATION FORM AF-50: CONSENT UNDER SECTION 50, ARTERIAL DRAINAGE ACT, 1945 APPLICATION DETAILS Name of Applicant: Company / authority: Address: Date of Application: Client (if appropriate): BRIDGE DETAILS

More information

BRIDGE INSPECTION REPORT

BRIDGE INSPECTION REPORT NC DEPARTMENT OF TRANSPORTATION ATTENTION DIVISION OF HIGHWAYS BRIDGE MANAGEMENT UNIT BRIDGE INSPECTION REPORT INSPECTION TYPE: Routine Inspection COUNTY IREDELL BRIDGE NUMBER 480596 INSPECTION CYCLE 2

More information

Guidance for Retrofitting Vehicle Restraint Systems on the Single Carriageway National Road Network

Guidance for Retrofitting Vehicle Restraint Systems on the Single Carriageway National Road Network Guidance for Retrofitting Vehicle Restraint Systems on the Single Carriageway National Road Network February 2017 TRANSPORT INFRASTRUCTURE IRELAND (TII) PUBLICATIONS About TII Transport Infrastructure

More information

Management of geotechnical risks for some tunnels in the Wellington Region

Management of geotechnical risks for some tunnels in the Wellington Region Proc. 18 th NZGS Geotechnical Symposium on Soil-Structure Interaction. Ed. CY Chin, Auckland Management of geotechnical risks for some tunnels in the Wellington Region David Stewart Opus International

More information

ICSE Risk based methodology applied to bridge scour analysis and implementation on the national road network

ICSE Risk based methodology applied to bridge scour analysis and implementation on the national road network ICSE 6 00086 Risk based methodology applied to bridge scour and implementation on the national road network Sabine STAAL: CETE Méditerranée, Department of Risks Water and Construction (Aix en Provence,

More information

ILLINOIS URBAN MANUAL PRACTICE STANDARD TEMPORARY STREAM CROSSING (no.) CODE 975. Source: Hey and Associates, Inc.

ILLINOIS URBAN MANUAL PRACTICE STANDARD TEMPORARY STREAM CROSSING (no.) CODE 975. Source: Hey and Associates, Inc. ILLINOIS URBAN MANUAL PRACTICE STANDARD TEMPORARY STREAM CROSSING (no.) CODE 975 Source: Hey and Associates, Inc. DEFINITION A bridge or culvert crossing installed across a stream or watercourse for short-term

More information

10(a) Bridge and culvert design information

10(a) Bridge and culvert design information 10(a) Bridge and culvert design information The following information is required to accompany resource consent applications for bridges or culverts on waterways. Please answer all questions if possible.

More information

LYNNVILLE ROAD BRIDGE. Site Number D00027 LYNNVILLE ROAD, CONCESSION 11, WINDHAM. 2.3km W of Highway 24

LYNNVILLE ROAD BRIDGE. Site Number D00027 LYNNVILLE ROAD, CONCESSION 11, WINDHAM. 2.3km W of Highway 24 LYNNVILLE ROAD BRIDGE Site Number LYNNVILLE ROAD, CONCESSION 11, WINDHAM 2.3km W of Highway 24 Ontario Structure Inspection Manual - Inspection Form Site Number: Inventory Structure Name Lynnville Road

More information

Horizontal Ellipse. Contact LSBC for additional sizes. Buried Ellipse for Pedestrian Traffic. Elliptical Stream Crossing

Horizontal Ellipse. Contact LSBC for additional sizes. Buried Ellipse for Pedestrian Traffic. Elliptical Stream Crossing Horizontal Ellipse By eliminating the need for concrete footings this shape can often provide the lowest overall installed cost of any long span structure. If a natural stream bottom is desired the invert

More information

Kicking Horse Cantilever Structure. Bruce Hamersley, P.Eng., Klohn Crippen Berger Ltd. Keith Mitchell, P.Eng., Klohn Crippen Berger Ltd.

Kicking Horse Cantilever Structure. Bruce Hamersley, P.Eng., Klohn Crippen Berger Ltd. Keith Mitchell, P.Eng., Klohn Crippen Berger Ltd. Kicking Horse Cantilever Structure Bruce Hamersley, P.Eng., Klohn Crippen Berger Ltd. Keith Mitchell, P.Eng., Klohn Crippen Berger Ltd. Brian Borton, P. Eng., Klohn Crippen Berger Ltd. Paper prepared for

More information

UNDERWATER BRIDGE INSPECTION REPORT STRUCTURE NO CR 958 OVER A STREAM ST. LOUIS COUNTY

UNDERWATER BRIDGE INSPECTION REPORT STRUCTURE NO CR 958 OVER A STREAM ST. LOUIS COUNTY UNDERWATER BRIDGE INSPECTION REPORT STRUCTURE NO. 88631 CR 958 OVER A STREAM ST. LOUIS COUNTY SEPTEMBER 18, 2012 PREPARED FOR THE MINNESOTA DEPARTMENT OF TRANSPORTATION BY COLLINS ENGINEERS, INC. JOB NO.

More information

Parish Flood List. Issue/Impact (Jan 16) Cause Short Term Actions (by Feb 16) (by Feb 16) Continue using now has 20k tons of

Parish Flood List. Issue/Impact (Jan 16) Cause Short Term Actions (by Feb 16) (by Feb 16) Continue using now has 20k tons of 74 Next 75 Number 39 Glenridding A592 between Highways & Glenridding Patterdale and Patterdale Lake overspill onto the Volume of water in road leading to road the lake closure for 2 days Debris cleared

More information

Water Quality Planning: no deterioration and the Water Framework Directive

Water Quality Planning: no deterioration and the Water Framework Directive Water Quality Planning: no deterioration and the Water Framework Directive Operational instruction 50_12 Issued 16/02/2012 What s this document about? This document explains how the no deterioration requirements

More information

TITLE: Bridge Inspection and Evaluation Procedure

TITLE: Bridge Inspection and Evaluation Procedure TITLE: Bridge Inspection and Evaluation Procedure 1. EFFECTIVE DATE: (date to be added later) 2. CANCELLATION: This procedure supersedes the previous version of the Real Property Branch Bridge Inspection

More information

SPECIFICATIONS FOR STRUCTURAL EXCAVATION

SPECIFICATIONS FOR STRUCTURAL EXCAVATION SPECIFICATIONS FOR STRUCTURAL EXCAVATION 1.0 DESCRIPTION The Work shall consist of:.1 Excavation and removal of material for the placement of foundations, substructure units, approach slabs, transition

More information

OKLAHOMA DEPARTMENT OF TRANSPORTATION SECTION 404 PRE-CONSTRUCTION NOTIFICATION FORM FOR STATE PROJECTS

OKLAHOMA DEPARTMENT OF TRANSPORTATION SECTION 404 PRE-CONSTRUCTION NOTIFICATION FORM FOR STATE PROJECTS OKLAHOMA DEPARTMENT OF TRANSPORTATION SECTION 404 PRE-CONSTRUCTION NOTIFICATION FORM FOR STATE PROJECTS DATE: Project No.: J/P: Facility: County: Description: Let Date: Division: Programmed Construction

More information

Unique ID: (from PFRA database) Location: Newport, Co. Tipperary. Stage 1: Desktop Review

Unique ID: (from PFRA database) Location: Newport, Co. Tipperary. Stage 1: Desktop Review Location: Newport, Co. Tipperary Unique ID: 240433 (from PFRA database) Initial OPW Designation APSR AFRR IRR Co-ordinates Easting: 172620 Northing: 162375 River / Catchment / Sub-catchment Newport/Mulcair

More information

Initial OPW Designation APSR AFRR IRR Co-ordinates Easting: Northing: PFRA database comments (in italics):

Initial OPW Designation APSR AFRR IRR Co-ordinates Easting: Northing: PFRA database comments (in italics): Location: Aughinish CHP and ESB Sub Station Co. Limerick Unique ID: 240366 (from PFRA database) Initial OPW Designation APSR AFRR IRR Co-ordinates Easting: 129250 Northing: 153000 River / Catchment / Sub-catchment

More information

Types of cross drainage works

Types of cross drainage works Definition: A cross drainage work is a structure carrying the discharge from a natural stream across a canal intercepting the stream. Canal comes across obstructions like rivers, natural drains and other

More information

Prestwick and Ayr (Potentially Vulnerable Area 12/09) Local Plan District Ayrshire Local authority South Ayrshire Council Main catchment Doonfoot to M

Prestwick and Ayr (Potentially Vulnerable Area 12/09) Local Plan District Ayrshire Local authority South Ayrshire Council Main catchment Doonfoot to M Prestwick and Ayr (Potentially Vulnerable Area 12/09) Local Plan District Ayrshire Local authority South Ayrshire Council Main catchment Doonfoot to Monkton coastal Summary of flooding impacts At risk

More information

Ontario Structure Inspection Manual Inspection Form Structure Number: 12

Ontario Structure Inspection Manual Inspection Form Structure Number: 12 Inventory Data: Structure Name Gailbraith Road Bridge 1 Main Hwy/Road # On Under Crossing Navig. Water Non-Navig. Water Rail Type: Road Ped. Other Hwy/Road Name Structure Location Latitude Owner(s) Galbraith

More information

OFFICE OF STRUCTURES MANUAL ON HYDROLOGIC AND HYDRAULIC DESIGN CHAPTER 11 EVALUATING SCOUR AT BRIDGES

OFFICE OF STRUCTURES MANUAL ON HYDROLOGIC AND HYDRAULIC DESIGN CHAPTER 11 EVALUATING SCOUR AT BRIDGES OFFICE OF STRUCTURES MANUAL ON HYDROLOGIC AND HYDRAULIC DESIGN CHAPTER 11 EVALUATING SCOUR AT BRIDGES APRIL 2011 Table of Contents 11.1 Introduction... 4 11.1 General......4 11.2 Qualifications of Personnel......4

More information

Riprap must be placed uniformly and carefully to eliminate any weak area where erosion can get a start.

Riprap must be placed uniformly and carefully to eliminate any weak area where erosion can get a start. 10.1 Riprap - General Riprap is a protective layer of material used to protect earth slopes and channels from the effects of erosion by runoff or scour by stream flow. Riprap can be a hand placed layer

More information

UNDERWATER BRIDGE INSPECTION REPORT DISTRICT 4 - WILKIN COUNTY

UNDERWATER BRIDGE INSPECTION REPORT DISTRICT 4 - WILKIN COUNTY UNDERWATER BRIDGE INSPECTION REPORT STRUCTURE NO. 84505 CSAH NO. 14 OVER THE OTTER TAIL RIVER DISTRICT 4 - WILKIN COUNTY PREPARED FOR THE MINNESOTA DEPARTMENT OF TRANSPORTATION BY COLLINS ENGINEERS, INC.

More information

Retaining Wall Replacement along Theodore Fremd Avenue at Blind Brook

Retaining Wall Replacement along Theodore Fremd Avenue at Blind Brook Retaining Wall Replacement along Theodore Fremd Avenue at Blind Brook City of Rye Westchester County City Council Public Meeting Presentation September 16, 2009 Presentation Outline Project Overview Existing

More information

Introduction.» Demolition Concepts» Concept Design» Final Design» Construction» Health Monitoring

Introduction.» Demolition Concepts» Concept Design» Final Design» Construction» Health Monitoring Location of Project Introduction» Demolition Concepts» Concept Design» Final Design» Construction» Health Monitoring Existing Bridge» Built in 1928» 255-foot Open Spandrel Concrete Arch Bridge» 24-foot

More information

Chapter 11 Culverts and Bridges

Chapter 11 Culverts and Bridges Chapter 11 Culverts and Bridges Contents 1.0 Introduction... 1 2.0 General Design... 1 2.1 Design Criteria... 1 2.2 Design Flows... 1 2.3 Permitting and Regulations... 1 2.4 Aesthetics and Safety... 2

More information

RECOMMENDED PROCEDURES FOR RAILWAY CULVERT INSPECTION

RECOMMENDED PROCEDURES FOR RAILWAY CULVERT INSPECTION RECOMMENDED PROCEDURES FOR RAILWAY CULVERT INSPECTION By: Robert J. Frascella, P.E.; Chairman, AREMA Committee 1, Sub-committee-4 Culverts; Senior Project Manager Railroads; Jacobs Civil Inc. and James

More information

Rehabilitation of West Main Street Culvert and Shirley Street Bridge. Town of Ayer. November 22, 2016

Rehabilitation of West Main Street Culvert and Shirley Street Bridge. Town of Ayer. November 22, 2016 Rehabilitation of West Main Street Culvert and Shirley Street Bridge Town of Ayer November 22, 2016 Agenda Outline Introductions Project Goals and Objectives Existing Conditions Review Design Considerations

More information

Module 3. Irrigation Engineering Principles. Version 2 CE IIT, Kharagpur

Module 3. Irrigation Engineering Principles. Version 2 CE IIT, Kharagpur Module 3 Irrigation Engineering Principles Lesson 8 Conveyance Structures for Canal Flows Instructional objectives On completion of this lesson, the student shall learn the following: 1. The need for structures

More information

OFFICE OF STRUCTURES MANUAL ON HYDROLOGIC AND HYDRAULIC DESIGN CHAPTER 11 EVALUATING SCOUR AT BRIDGES

OFFICE OF STRUCTURES MANUAL ON HYDROLOGIC AND HYDRAULIC DESIGN CHAPTER 11 EVALUATING SCOUR AT BRIDGES OFFICE OF STRUCTURES MANUAL ON HYDROLOGIC AND HYDRAULIC DESIGN CHAPTER 11 EVALUATING SCOUR AT BRIDGES May 26, 2015 Preface ABSCOUR 10 is the current version of the scour evaluation program used by the

More information

Post-earthquake response plans for State Highways in the Wellington Region

Post-earthquake response plans for State Highways in the Wellington Region Post-earthquake response plans for State Highways in the Wellington Region P. Brabhaharan & J. Hobman Opus International Consultants, Wellington D. Robertson New Zealand Transport Agency, Wellington 2015

More information

Filter Tube Barriers (Instream)

Filter Tube Barriers (Instream) Filter Tube Barriers (Instream) INSTREAM PRACTICES Flow Control No Channel Flow Dry Channels Erosion Control Low Channel Flows Shallow Water Sediment Control High Channel Flows Deep Water Symbol Photo

More information

Bridge Planning Updates. Bridge Planning Practitioners Workshop April 2012

Bridge Planning Updates. Bridge Planning Practitioners Workshop April 2012 Bridge Planning Updates Bridge Planning Practitioners Workshop April 2012 Bridge Website Bridge Website Bridge Website Bridge Website BPG 11 Stormwater Management at Rural Bridges Released July 2010 Documents

More information

NORWICH ROAD BRIDGE. Site Number D00016 NORWICH ROAD, DELHI. 1.0 km N of King Street Delhi

NORWICH ROAD BRIDGE. Site Number D00016 NORWICH ROAD, DELHI. 1.0 km N of King Street Delhi NORWICH ROAD BRIDGE Site Number NORWICH ROAD, DELHI 1.0 km N of King Street Delhi Ontario Structure Inspection Manual - Inspection Form Site Number: Inventory Structure Name Norwich Road Bridge On Crossing

More information

Scour risk assessment at river crossings

Scour risk assessment at river crossings Scour risk assessment at river crossings Marta Roca 1 and Richard Whitehouse 2 1 HR Wallingford, Howbery Park, Wallingford, OX10 8BA, UK, m.roca@hrwallingford.com 2 HR Wallingford, Howbery Park, Wallingford,

More information

introduction Introduction to Bridge and Tunnel Engineering Characteristics of ideal bridge Ideal location Factors affecting bridge type Classification

introduction Introduction to Bridge and Tunnel Engineering Characteristics of ideal bridge Ideal location Factors affecting bridge type Classification 1 introduction Introduction to Bridge and Tunnel Engineering A structure constructed over an obstacle to provide the passage Road bridge movement of traffic See NRS 2045 Cross drainage structure span greater

More information

421 - PIPE CULVERTS - OPSS 421 INDEX

421 - PIPE CULVERTS - OPSS 421 INDEX 421 - PIPE CULVERTS - OPSS 421 INDEX 421.1 GENERAL 421.1.1 Environmental Concerns 421.1.2 Pipe Culvert Materials 421.1.3 Pipe Diameter 421.1.4 Corrugated Steel Pipe Extensions 421.1.5 Bedding 421.1.6 Embedment

More information

SCOUR AT COMPLEX BRIDGE STRUCTURES THE BENEFITS OF TWO-DIMENSIONAL HYDRAULIC MODELLING IN THE ESTIMATION OF SCOUR DEPTHS

SCOUR AT COMPLEX BRIDGE STRUCTURES THE BENEFITS OF TWO-DIMENSIONAL HYDRAULIC MODELLING IN THE ESTIMATION OF SCOUR DEPTHS SCOUR AT COMPLEX BRIDGE STRUCTURES THE BENEFITS OF TWO-DIMENSIONAL HYDRAULIC MODELLING IN THE ESTIMATION OF SCOUR DEPTHS M Burgess 1, C Moore 1 1 Arup, Sydney, NSW Abstract Assessing scour potential at

More information

Interesting Solutions for a Culvert Rehabilitation Project in a Sensitive Urban Watershed

Interesting Solutions for a Culvert Rehabilitation Project in a Sensitive Urban Watershed Interesting Solutions for a Culvert Rehabilitation Project in a Sensitive Urban Watershed Jason Stahl, P. Eng., Project Engineer, Amec Foster Wheeler David Sinke, P. Eng., Principal, Transportation Engineering,

More information

Minersville, Ohio Riverbank Stabilization

Minersville, Ohio Riverbank Stabilization Minersville, Ohio Riverbank Stabilization A Case History Lisa Gatens, E.I. Seth Lyle, P.E. U.S. Army Corps of Engineers Huntington District Geotechnical Branch Huntington, West Virginia Presentation Outline

More information

DEVELOPMENT OF THE BRIDGE MANAGEMENT SYSTEM UNDER THE PROJECT BRIDGE SMS

DEVELOPMENT OF THE BRIDGE MANAGEMENT SYSTEM UNDER THE PROJECT BRIDGE SMS An overview of Key Performance Indicators across Europe and Overseas The main findings from WG1 and other contributions from WG2 and WG3 DEVELOPMENT OF THE BRIDGE MANAGEMENT SYSTEM UNDER THE PROJECT BRIDGE

More information

Following the November 2009 flood event Galway County Council and the OPW have been working together on the Ballinasloe flooding situation.

Following the November 2009 flood event Galway County Council and the OPW have been working together on the Ballinasloe flooding situation. Derrymullan, Ballinasloe Flood Defence Wall, Report October 2011 Following the November 2009 flood event Galway County Council and the OPW have been working together on the Ballinasloe flooding situation.

More information

Design Concept of the facilities to. space. Kamoto Minoru Chief Researcher

Design Concept of the facilities to. space. Kamoto Minoru Chief Researcher Design Concept of the facilities to manage river or to occupy the River space Kamoto Minoru Chief Researcher ICHARM/PWRI 1 Contents Names of the river Dike, inspection passage, super levee Revetment, gabion,

More information

SCHEDULE OF EMPLOYERS REQUIREMENTS

SCHEDULE OF EMPLOYERS REQUIREMENTS SCHEDULE 3 SCHEDULE OF EMPLOYERS REQUIREMENTS 1) BACKGROUND 1.1 UNOPS Introduction: UNOPS plays a critical role in providing management services for our life-saving peacebuilding, humanitarian and development

More information

Surface Water Management Procedure Environment

Surface Water Management Procedure Environment 1 Purpose and Scope This procedure specifies the operational environmental requirements that relate to surface water management at the Roy Hill Project. This procedure applies to all personnel involved

More information

The Chief Estimator Software. Item Cost Summary Bridge & Overpass Projects

The Chief Estimator Software. Item Cost Summary Bridge & Overpass Projects The Chief Estimator Software Item Cost Summary Bridge & Overpass Projects Elevated Transit Guideways Precast Girder Elevated Guideway 10 Abutment Excavation & Backfill 1,500.00 m3 222 10,368 8,634 1,309

More information

Transactions on Ecology and the Environment vol 19, 1998 WIT Press, ISSN

Transactions on Ecology and the Environment vol 19, 1998 WIT Press,   ISSN Water surface profiles and scour analysis for a river reach with multiple bridge proposals C.C. Nuthmann & C.C. Chang Sverdrup Civil, Inc., Two Center Plaza, Boston, Massachusetts, USA, 02108 Email: nuthmacc@sverdrup.

More information

St James Weir Assessment Report

St James Weir Assessment Report Assessment Report Document: R10 Version: 2 South West Fish Passes Environment Agency 28 May 2013 Assessment Report South West Fish Passes Environment Agency 28 May 2013 Halcrow Group Limited Ash House,

More information

HEAD STREET BRIDGE (SIMCOE)

HEAD STREET BRIDGE (SIMCOE) NORFOLK COUNTY HEAD STREET BRIDGE (SIMCOE) Site Number 000009 HEAD STREET, SIMCOE 0.3km S of Windham Street Ontario Structure Inspection Manual - Inspection Form Site Number: 000009 Inventory Structure

More information

Request for Proposal Design-Build Reconstruction of Bridge No. 15 and Bridge No. 17

Request for Proposal Design-Build Reconstruction of Bridge No. 15 and Bridge No. 17 374028 6 th Line, Amaranth ON L9W 0M6 Phone: 519-941-1007 Fax: 519-941-1802 Email: info@amaranth.ca Request for Proposal 1-2017 Design-Build Reconstruction of Bridge No. 15 and Bridge No. 17 Description

More information

DECOU ROAD BRIDGE. Municipal Structure Inspection Form NORFOLK COUNTY. Site Number DECOU ROAD, SIMCOE. 1.Okm E of Willow Drive

DECOU ROAD BRIDGE. Municipal Structure Inspection Form NORFOLK COUNTY. Site Number DECOU ROAD, SIMCOE. 1.Okm E of Willow Drive NORFOLK COUNTY DECOU ROAD BRIDGE Site Number 000003 DECOU ROAD, SIMCOE 1.Okm E of Willow Drive Ontario Structure Inspection Manual - Inspection Form Site Number: 000003 Inventory Data: Structure Name Decou

More information

National Roads Authority

National Roads Authority Project nr 2008-1/049 Belfast: 22-23 June 2009 Presentation to Trans-national Workshop NRA: Maintenance and repair of bridges Albert Daly National Roads Authority, IRELAND Investing in our common future

More information

Response to a Bridge Strike over the Railway

Response to a Bridge Strike over the Railway Response to a Bridge Strike over the Railway A Protocol for Highway and Road Managers, Police and Bridge Owners NR/GPG/CIV/007 Note This protocol has been produced for the benefit of Network Rail staff

More information

Modular Sediment Barriers (Instream)

Modular Sediment Barriers (Instream) Modular Sediment Barriers (Instream) INSTREAM PRACTICES Flow Control No Channel Flow Dry Channels Erosion Control Low Channel Flows Shallow Water Sediment Control High Channel Flows Deep Water Symbol Photo

More information

Term Project GIS in Water Resources C E 394 K. Oscar Galvis (odg252) Fall 2016

Term Project GIS in Water Resources C E 394 K. Oscar Galvis (odg252) Fall 2016 Term Project GIS in Water Resources C E 394 K Oscar Galvis (odg252) Fall 2016 Estimation of the Economic s of IH 35 Bridge Deterioration Due to Floods in Onion Creek Introduction to the problem Bridges

More information

GEOMETRIC DESIGN STANDARDS FOR LOCAL 3R PROJECTS

GEOMETRIC DESIGN STANDARDS FOR LOCAL 3R PROJECTS Local Assistance Procedures Manual EXHIBIT 11-A Geometric Design Standards for Local 3R Projects EXHIBIT 11-A GEOMETRIC DESIGN STANDARDS FOR LOCAL 3R PROJECTS GEOMETRIC DESIGN STANDARDS FOR LOCAL 3R PROJECTS

More information

EAST ¼ LINE BRIDGE, CONCESSION 2

EAST ¼ LINE BRIDGE, CONCESSION 2 NORFOLK COUNTY EAST ¼ LINE BRIDGE, CONCESSION 2 Site Number 010055 VILLA NOVA ROAD, TOWNSEND 1.13 km S of County Road 20 Ontario Structure Inspection Manual - Inspection Form Site Number: 010055 Inventory

More information

Technical Standard for the Design of Forest Entrances from Public Roads

Technical Standard for the Design of Forest Entrances from Public Roads Technical Standard for the Design of Forest Entrances from Public Roads Contents Acknowledgements... 3 1) Introduction... 4 2) Forest Entrances from National Primary and National Secondary Routes... 5

More information

Forest Service AOP Policy and Program. John R. Kattell, P.E. Northern Region Structures Engineer

Forest Service AOP Policy and Program. John R. Kattell, P.E. Northern Region Structures Engineer Forest Service AOP Policy and Program John R. Kattell, P.E. Northern Region Structures Engineer AOP Policy and Program In years past: Aquatic passage to be considered where important and economically feasible.

More information

Appendix 6 Weir Assessments

Appendix 6 Weir Assessments Appendix 6 Weir Assessments Second edition, September 2013 1. Introduction This section of work assesses the connectivity of the River Teme with respect to fish passage. A number of barriers have been

More information

1 layer of untreated timber running planks, 254 mm x 89 mm.

1 layer of untreated timber running planks, 254 mm x 89 mm. BRIDGE INSPECTION BRIDGE NO./NAME N2-103: Kootenay By-Pass (9.50 km) Inspection Date: September 23 rd, 2012 Inspected By: M. Hanson, R. Veitch Year Built: 1982 Number of Spans: 4 Span Lengths: Spans 1

More information

GENERAL NOTES ENGINEERS OVERSIGHT 1. ALL ELEVATIONS, DIMENSIONS, ALIGNMENTS AND ORIENTATION OF ALL ELEMENTS SHOWN IN THE PLANS MUST BE APPROVED BY THE ENGINEER OR ENGINEER'S REPRESENTATIVE ( REP ENGINEER

More information