1 Institute of Transporation Engineers (ITE) May 10, 2013

2 The RTD FasTracks Plan 122 miles of new light rail and commuter rail 18 miles of Bus Rapid Transit (BRT) service 31 new park-n-rides; more than 21,000 new spaces Enhanced Bus Network & Transit Hubs (FastConnects) Redevelopment of Denver Union Station

3 FasTracks Update 81 miles of new rail and bus rapid transit currently open, in or under contract West Rail Line Complete and opened on April 26 Denver Union Station 81% complete U.S. 36 BRT construction of express lanes extension underway (Federal Blvd. to 88 th St.) East Rail Line/Gold Line/NW Rail 40% complete I-225 Rail Line construction underway North Metro Line RFP in July

4 FasTracks Update Economic driver for the region West Rail alone added more than $356 M FasTracks has already injected $2.7 billion into the region since Economists estimate that every $1 invested in transit infrastructure translates into $4 injected in the local economy over 20 years.

5 FasTracks Project Delivery Methods Design-build (DB) Design-bid-build (DBB) Design-build-operate-maintain (DBOM) Design-build-finance-operate-maintain (DBFOM) Construction Manager/General Contractor (CMGC)

6 Denver Union Station $480 million project Multimodal hub integrating light rail, commuter rail, Amtrak, buses, taxis, shuttles, bikes and pedestrians Denver Union Station Project Authority oversees development Partners include RTD, Colorado Dept. of Transportation, City and County of Denver, Denver Regional Council of Governments, Master Developer Union Station Alliance is developing historic building into boutique hotel, restaurants and retail stores Transit hub opens in 2014

7 Downtown Denver Circulator Additional transit capacity between Denver Union Station and Civic Center area Service will complement Mall Shuttle Stops are 2-3 blocks apart for faster travel than Mall Shuttle Opening will coincide with opening of Denver Union Station in 2014

8 Eagle P3Project East Line Gold Line Northwest Rail (to south Westminster) Commuter Rail Maintenance Facility Opening in 2016

9 Eagle P3Project RTD pursued concept of P3 in 2007 The Perfect Storm Costs skyrocketed Revenues plummeted First transit P3 of this magnitude in the U.S. RTD retains ownership of assets 34-year contract 6 years design/build 28 years operate/maintain More public entities are turning to P3s to build out their projects

10 I-225 Rail Line 10.5-mile light rail extension Starts at existing Nine Mile Station 8 stations Serving: Aurora City Center Anschutz / Fitzsimons Campus New VA Hospital, which will serve 60,000 military veterans and their families Provides connectivity to East Rail Line at the Peoria Station Opening in 2016

11 US 36 Bus Rapid Transit 18 miles of Bus Rapid Transit (BRT) between downtown Denver and Boulder RTD s BRT Vision o Frequent and reliable service, same or better than light rail or commuter rail o Specialized branded buses o Managed lanes o Permanent BRT stations o Off-vehicle fare collection o Real Time Transit Information o Coordinated effort with stakeholders to establish BRT service standards

12 Northwest Area Mobility Study Develop consensus among RTD, CDOT and corridor stakeholders on cost-effective mobility improvements to serve the Northwest area Analyze Northwest Rail, extending North Metro to Longmont and BRT HNTB will lead study Goal is a list of priorities for improvements and third-party funding options Memorandums of Understanding (MOU) have been signed by all parties agreeing to the process Study begins in May and will be completed in early 2014

13 West Rail Line

14 West Rail Line 12.1 miles of light rail 12 Stations 5,605 parking spaces $707M capital cost Ridership 19, , Opened April 26, 2013

15 Selection Process: CM/GC approach March 2004 West Rail Line RFP released May 23, 2006 RTD s selection committee selected Denver Transit Construction Group (DTCG) June 2006 NTP for Pre-construction Services contract July 2007 Change order for track removal March 2008 Early work and material procurement under LONP June 2008 Guaranteed Maximum Price submitted June 2009 NTP for Construction

16 Procurement Process: Two-Phased Approach (CM/GC) PHASE ONE: Contractor provided professional services like scheduling, planning, and cost estimating in preparation for entering into construction, but not performing construction, although the contract was amended in 2008 to allow for some early construction work. PHASE TWO: Precedent to phase two, DTCG had the first opportunity to negotiate the construction contract. If parties were unable to reach an agreement on guaranteed maximum price, RTD reserved the right to award the contact to another contractor. Construction began. As General Contractor, DTCG manages their work, including their sub-contractors. RTD s role is to provide project management and construction oversight.

17 West Rail Line Schedule 2005 Final Design Begins June 2009 Jan-Feb 2013 March April April 26, 2013 Construction Begins Integrated testing RTD Operations Testing West Rail Line Open to Public

18 Project Elements Rail 12.1 miles 9 double track, 3.1 single track Bridges 10 Light Rail Bridges 3 Street/Highway Bridges 3 pedestrian bridges Bike paths 4.26 miles Walls Retaining Ballast Mechanically Stabilized Earth Soil Nail Crossings 20 at-grade crossings 14 grade separations 10 road closures Tunnels I-70 and Union Boulevard Stations 12 Stations 6 kiss-n-ride 6 with parking 11 new 1 relocated

19 Stations

20 Auraria West and Decatur Federal Stations

21 Knox and Perry Stations

22 Sheridan and Lamar Stations

23 Lakewood Wadsworth and Garrison Stations

24 Oak and Federal Center Stations

25 Red Rocks College and Jeffco Golden Stations

26 Challenges: Stations

27 Station Construction General Aspects: Subsurface conditions in some locations, such as Auraria and Jeffco were not conducive to building structures Coordination between station foundation and utilities Relocations along 13 th Avenue RTD performed potholing and survey of existing utilities Was challenging to service locations along the rail line Construction on streets to locate electrical feeds added cost Double tap fees ROW and Easements

28 Station Construction Lessons Learned What went well: Contractor worked well overcoming various issues Ability to collaborate between Owner and Contractor Lessons Learned What could have been better: City betterments were challenging City provided funding City had their own designer Many existing facilities are substandard Contracts that are split out can cause challenges Coordination and communication (among contractor and subs) Sequencing of work

29 Challenges: Utilities

30 Utilities General Aspects: To determine which utilities were in conflict with the proposed RTD construction, the proposed construction design drawings were reviewed at 30 percent design 60 percent design project started to relocate facilities 90 percent design During design Subsurface Utility Engineering was performed to minimize the impact of utility reconstruction Worked with DEA and utility owners to: Provide a location to relocate facilities Develop a cost estimate for each relocation Determine who was financially responsible for the design and construction costs to relocate utility facilities

31 Utilities RTD Relocates and added utilities: Issues relocating all overhead and underground utilities located in the same alignment as the proposed LRT guideway Project located in older section of Lakewood and Denver Building foundations in conflict Utility conduits containing asbestos DTCG was responsible for wet utility relocates with the exception of CMWC water facilities RTD utility team was responsible for the design and construction of existing dry utilities that were in conflict with the proposed LRT construction. All dry utilities were completed by the utility owners: Xcel-Gas Operations, Electric Distribution, Transmission; CenturyLink; Comcast; Level 3; and Zayo

32 Utilities Relocates by utility owners: CenturyLink Had underground ductbank located on 13 th Avenue that consisted of over 30, 2-inch conduits from Quail to Wadsworth and contained asbestos Relocated their facilities out of 13 th Avenue from Independence to Wadsworth into 14 th Avenue Project was able to save CenturyLink facilities from Quail to Independence which saved CenturyLink money and construction time Xcel Energy and Comcast Had an overhead electric facility that ran in the middle of 13 th Avenue from Quail to Harlan with Comcast attached to their power poles Overhead facilities relocates into 10 th and 14 th Avenue

33 Utilities Work Orders by RTD: Included: Relocation of water lines owned by CMWC along 13 th Avenue New fire hydrants in COL, constructed by CMWC Underground communication facilities Overhead electric facilities located in easements Electric transmission towers 348 work orders 295 Dry Utilities

34 Utilities Lessons Learned What went well: Coordination among stakeholders Coordination between DTCG and RTD Communication between parties if there was an issue DTCG would address RTD and vice versa Good production Lessons Learned What could have been better: Relocating utilities began too soon Value engineering drawing integration good in some aspects, but there were aspects that were not taken into account Knowing municipality and the standards ahead of time Need to know municipality s design criteria and what the requirements are for utilities

35 Challenges: Tunnels

36 I-70 and Union Tunnels Excavation Both tunnels were constructed in phases to minimize construction impacts to the public: I-70: Two phases Union: Three phases Importance of stockpile location: Allowed for better onsite coordination Crews were focused on the excavation, not dirt removal Change orders Unforeseen design issues at I-70 Tunnel

37 I-70 and Union Tunnels Conflicts and Resolutions Design: I-70 incorporated precast planks whereas Union Tunnel was a slab-on-grade Union Tunnel design caused another step in the process Rebar cages at Union Tunnel were sinking into subgrade which required DTCG to spend additional time compacting subgrade Coordination included: I-70: Federal Highway Administration (FHWA) and CDOT Union: City of Lakewood and CDOT Coordination involved: Permits and traffic control scheduling around peak traffic times Incident management plan Construction of I-70 Tunnel required the closure of the interstate Union Tunnel utilized lane closures to allow the flow of traffic

38 I-70 and Union Tunnels Lessons Learned What went well: The coordination among parties, prior to construction: Began four to six months in advance Allowed stakeholders to have a positive comfort level Created a partnership Without coordination neither tunnel would have progressed quickly or successfully. The phasing, routing, and shutdown needed full partnership Accelerated bridge construction allows for tunnels and bridges to be constructed in a quick fashion with minimal disruption to the traveling public

39 I-70 and Union Tunnels: Lessons Learned What could ve been better: Contractor should be heavily involved with the physical design of the project, when applicable Design doesn t necessarily take into account the phasing required to build structures Allowing the contractor to assist in the design process, helps to mitigate unforeseen issues during construction Examples: I-70: DTCG was involved and had the ability to offer input since the inception of the tunnel design, phasing, procurement, to actual construction Union: DTCG had no input on tunnel design. To stay on schedule DTCG had to make the design plans fit field conditions

40 Challenges: Track and Subgrade

41 Track Subgrade Construction General aspects: RTD considers track subgrade to be as important to track performance as the rail and ballast Subgrade and maintenance costs are reduced by using an effective exploration and testing program during the design process to include collection and analysis of detailed information Subsoil or foundation for the track subgrade is required to satisfy same basic requirements of a continuous spread foundation Foundation soil should have the strength to support the constructed subgrade Subsurface and surface drainage conditions must be addressed to avoid conditions such as sink holes and springs under the fill

42 Track Subgrade Construction General aspects: Fills, embankments, or select granular fill materials (supplied by off-site commercial sources) Used to raise existing ground surface when required to achieve desired level for track subgrade May serve to elevate the grade above existing or predicted water levels or snow depths, eliminate undesirable topographic variations, and achieve design grades RTD track subgrade 11 feet to both sides of the track centerline Compacted to a minimum density of 95% of the maximum ± 2% of the optimum moisture content Compacted subgrade is sloped at 40:1 toward a track underdrain system

43 Track Subgrade Construction Lessons Learned What went well: Expansive subsoils: Westernmost portion of rail line overlies a bedrock zone consisting of nearly vertically inclined layers of differentially and potentially highly expansive claystone To minimize risk, RTD elected to overexcavate and replace potentially expansive soils with controlled compacted select granular fill materials Artificial fills: Includes soils (clay, silt, sand, gravel) and debris including extensive deposits of trash or landfill type RTD elected to remove and replace artificial fills in whole with an engineered fill

44 Track Subgrade Construction Lessons Learned What could have been better: Minimization of the costs associated with the above unforeseen conditions can be achieved through a comprehensive exploration and testing program during the design process. Prior to project, RTD lowered and redesigned major gas and fiber optic lines, however, smaller feeds weren t necessarily taken into account

45 Challenges: Walls

46 Walls and Embankments Underground/Earth Work: Crews discovered areas with unsuitable material Required geotech analysis provided guidance to ensure wall embankments would not swell or settle Coordination with various stakeholders to ensure phasing plans and haul routes Change Orders/ Value Engineering Wall caissons Geotech allowance Foundation and wall construction

47 Walls and Embankments Lessons Learned What went well: DTCG/RTD performed value engineering (VE) for many walls in an effort to change wall types Approximately 25 walls were VE resulting in change orders (MSE, Cast-in-Place, etc.) VE efforts provided substantial savings to owner and contractor When accessible contractor would slip-form ballast walls rather than form and pour Lessons Learned What could have been better: All utilities need to be relocated or installed before constructing With MSE walls, take into account the utility duct bank, OCS foundations and the MSE straps

48 Challenges: Bridges

49 Bridge Construction Underground/Earth Work: Wet and dry utilities needed to be out of the footprint of bridges Utilities relocations sewer, water, fiber optic lines, etc. Bridges were built, or reconstructed over waterways, creeks, roadways, guideway and channels Special attention to environmental impacts such as waterways and wetlands Proper phasing was required to facilitate construction Material Changes Various bridges were assessed to be changed from steel to concrete

50 Bridge Construction Lessons Learned What went well: Because the construction and reconstruction of bridges were completed in phases there were minimal impacts to the traveling public Allowed various stakeholders to have input on final design elements for betterments to their community Created a sense of community, partnership, and ownership Lessons Learned What could have been better: Some bridge designs didn t fully account for the utility duct banks that were to be constructed on the bridge expansion vaults, conduits, etc.

51 Operations

52 Call-n-Rides Three new Call-n-Rides Belmar Golden Green Mountain Personalized bus service that travels within select RTD service areas. Flex routes during high-traffic hours, as a service to commuters, scheduled stops in designated areas.

53 Operational Info Trains Frequency Every 7.5 minutes in peak Fed Center to Downtown Every 15 minutes Federal Center to Downtown off peak Jeffco to downtown all day First Train at 3:30 4:00 a.m. Last Train at 2:30 a.m. Fares: Zone A Union Station to Sheridan Zone B Lamar to Garrison Zone C Oak to Jeffco Travel in one or two zones = local fare currently $2.25 Travel in three zones = express fare currently $4.00 Travel in four zones = regional fare currently $5.00

54 Fare Info

55 Grand Opening April 26, 2013 On April 26, RTD kicked off a weekend of West Rail Line celebrations with the Grand Opening Ceremony at the Jefferson County Government Center/Golden Station and free West Rail Line rides for the remainder of the day.

56 Grand Opening April 26, 2013

57 QUESTIONS

VE PROPOSAL SUMMARY TABLE

VE PROPOSAL SUMMARY TABLE 3/2/2007 VE SUMMARY TABLE VE DESCRIPTION Potential Environmental Assessment Impacts (Miscellaneous) P01-019 Eliminate the Tennyson pedestrian bridge Item will most likely be included in the $5 million

More information

The RTD FasTracks Plan

The RTD FasTracks Plan PROJECT DELIVERY METHODS Prepared for: PCJPB August 2013 Prepared by: Richard F. Clarke (Assistant General Manager, Capital Programs) The RTD FasTracks Plan 122 miles of new light rail and commuter rail

More information

Why a Public-Private Partnership might be used to deliver passenger rail

Why a Public-Private Partnership might be used to deliver passenger rail INTERCITY PASSENGER RAIL Opportunities & Challenges for Colorado Why a Public-Private Partnership might be used to deliver passenger rail September 16, 2010 Agenda FasTracks Eagle Project Applicability

More information

Phase 2 Exposition Metro Line Project

Phase 2 Exposition Metro Line Project Phase 2 Exposition Metro Line Project Monthly Project Status Report July 2014 TABLE OF CONTENTS PHASE 2 EXPO LINE PROJECT STATUS TABLE OF CONTENTS... 2 Phase 2 Exposition Metro Line Construction Authority

More information

I-225 Rail Line Board Update. Chuck Culig I-225 Rail Line Project Manager Aug. 6, 2013

I-225 Rail Line Board Update. Chuck Culig I-225 Rail Line Project Manager Aug. 6, 2013 I-225 Rail Line Board Update Chuck Culig I-225 Rail Line Project Manager Aug. 6, 2013 I-225 Rail Line 10.5 mile light rail line Starts at Nine Mile Station Eight stations Serves Aurora City Center Serves

More information

DTCG Construct BW 2.1 (WB Sta to. DTCG Construct BW 2.31 (W. Wall B12 Fence. 8th Ave Storm System

DTCG Construct BW 2.1 (WB Sta to. DTCG Construct BW 2.31 (W. Wall B12 Fence. 8th Ave Storm System AREA #2-1253+03 to 1504+72 US 6 to 8TH AVE US 6 BRIDGE - SOUTH SIDE S6thfence 10 Fencing along CDOT ROW 5 19-Apr- A 29-Apr- US6 BRIDGE - 1252+14 to 1259+93 BRIDGE 6thArchLED40 LED Light Procurement 16

More information

Transportation and Utilities

Transportation and Utilities 4 Section 4 Transportation and Utilities 4.0 Introduction Transportation and utility systems are essential to accommodate and support development proposed in the Future Land Use Map. The following pages

More information

North Metro Commuter Rail Line Conception to Implementation

North Metro Commuter Rail Line Conception to Implementation Line Jane Donovan, P.E. North Metro Deputy Project Manager Jacobs Engineering Denver, CO Jennifer Whiteside, P.E. North Metro Structures Lead RTD Denver, CO 18.5 Miles, building 13 Electrified Commuter

More information

Table 2: Recommended Improvement Projects - Northeast Area Transit Evaluation. Plan

Table 2: Recommended Improvement Projects - Northeast Area Transit Evaluation. Plan Table 2: Recommended Improvement Projects - Northeast Area Transit Evaluation Project Location/Type Description Document Source US 85 US 85 interchange/baseline (WCR 2) Single-point diamond interchange

More information

TABLE SUMMARY OF POTENTIAL CONFLICTS WITH MAJOR UTILITIES DUS ACCESS TO 162 ND AVENUE AREA

TABLE SUMMARY OF POTENTIAL CONFLICTS WITH MAJOR UTILITIES DUS ACCESS TO 162 ND AVENUE AREA 3.13 UTILITIES 3.13.1 Introduction to Analysis Impacts to existing utilities by transportation projects have the potential to adversely affect the cost and schedule of a project as well as neighboring

More information

$500M Public Transportation Infrastructure Project with 5 Public/Private Partners, and 9 financing Sources

$500M Public Transportation Infrastructure Project with 5 Public/Private Partners, and 9 financing Sources $500M Public Transportation Infrastructure Project with 5 Public/Private Partners, and 9 financing Sources Regional Transportation District (RTD) City and County of Denver (CCD) Denver Regional Council

More information

Quarterly Progress Report. September 2012

Quarterly Progress Report. September 2012 Quarterly Progress Report September 2012 TABLE OF CONTENTS Project Update... 3 Discipline Summaries... 4 Utility Relocation... 4 Station Construction... 5 Structural Construction... 9 Civil Construction...

More information

Factor Potential Effects Mitigation Measures

Factor Potential Effects Mitigation Measures Natural Environment No impacts of provincial significance to the natural environment are anticipated for the rapid transit project. Other impacts and how they will be mitigated are outlined in the table

More information

Conduct of Construction Plan

Conduct of Construction Plan Conduct of Construction Plan Developed by: DRAFT VERSION Page 2 of 20 TABLE OF CONTENTS 1. PROJECT DESCRIPTION...... 3 2. TRAFFIC & SAFETY CONSIDERATIONS/MAJOR WORK COMPONENTS. 4 A. UTILITY RELOCATIONS.

More information

2004 FEASIBILITY STUDY UPDATE

2004 FEASIBILITY STUDY UPDATE Austin-San Antonio Intermunicipal Commuter Rail District 2004 FEASIBILITY STUDY UPDATE December 2004 EXECUTIVE SUMMARY INTRODUCTION Almost 3 million people in Central Texas, living and working between

More information

Phase 2 Exposition Metro Line Project

Phase 2 Exposition Metro Line Project Phase 2 Exposition Metro Line Project Monthly Project Status Report April 2013 TABLE OF CONTENTS PHASE 2 EXPO LINE PROJECT STATUS TABLE OF CONTENTS... 2 Phase 2 Exposition Metro Line Construction Authority

More information

Exposition Light Rail Transit Project

Exposition Light Rail Transit Project Exposition Light Rail Transit Project Downtown & Mid-Corridor Project Status Update Meeting Holman United Methodist Church Thursday, July 23, 2009 Phase 1 Project Description 8.6 mile corridor from Downtown

More information

DENVER UNION STATION $500M TRANSPORTATION INFRASTRUCTURE FINANCING

DENVER UNION STATION $500M TRANSPORTATION INFRASTRUCTURE FINANCING DENVER UNION STATION $500M TRANSPORTATION INFRASTRUCTURE FINANCING 2001 2002 4 2005 6 2007 2008 RTD ACQUIRES DUS MASTER PLANNING DEVELOPER SELECTION DESIGN REFINEMENT PRELIMINARY ENG. August 2001 RTD acquires

More information

Design/Build. How Utilities Are Handled. Gus Kretschmer Michael Baker Engineering

Design/Build. How Utilities Are Handled. Gus Kretschmer Michael Baker Engineering Design/Build How Utilities Are Handled Gus Kretschmer Michael Baker Engineering US 601 Union County, NC NCDOT Union County, NC US 601 $53.8 Million Construction Costs Widening of 11 Miles of two lane roadway

More information

Category: 11 Best Building Project GC ($70M) Contractor: Saunders Construction. Project Name: 16 Chestnut Office Tower, Denver, Colorado

Category: 11 Best Building Project GC ($70M) Contractor: Saunders Construction. Project Name: 16 Chestnut Office Tower, Denver, Colorado Category: 11 Best Building Project GC ($70M) Contractor: Saunders Construction Project Name: 16 Chestnut Office Tower, Denver, Colorado Denver is growing up. So many cranes have been visible for so long

More information

Innovative Improvement Driven Foundation for Denver s Transit Expansion Program

Innovative Improvement Driven Foundation for Denver s Transit Expansion Program Innovative Improvement Driven Foundation for Denver s Transit Expansion Program Timothy Stokes, PE Delcan Corp. Denver, CO INTRODUCTION The Denver Regional Transportation District (RTD) has embraced managerial

More information

West Corridor Quarterly Progress Report. March 2011

West Corridor Quarterly Progress Report. March 2011 West Corridor Quarterly Progress Report TABLE OF CONTENTS Project Update... 3 Discipline Summaries... 4 Utility Relocation... 4 Station Construction... 5 Structural Construction... 8 Civil Construction...

More information

Review of Plans and Specs from a Constructability Perspective

Review of Plans and Specs from a Constructability Perspective Review of Plans and Specs from a Constructability Perspective The Executive Regional Manager and the Project Manager, with approval of the Director of Project Management, may request the Constructability

More information

Final Report APRIL 21, 2004

Final Report APRIL 21, 2004 REVIEW OF THE RTD FASTRACKS PLAN Final Report APRIL 21, 2004 This page intentionally left blank REVIEW OF THE RTD FASTRACKS PLAN Final Report Denver Regional Council of Governments 4500 Cherry Creek South

More information

Los Angeles Westside Purple Line Extension Project Challenges and Lessons Learned

Los Angeles Westside Purple Line Extension Project Challenges and Lessons Learned Los Angeles Westside Purple Line Extension Project Challenges and Lessons Learned Ashok Kothari, P.E. WSP USA, Sr. Vice President Los Angeles, California Michael McKenna, P.E. LACMTA Executive Officer,

More information

Phase 2 Exposition Metro Line Project

Phase 2 Exposition Metro Line Project Phase 2 Exposition Metro Line Project Monthly Project Status Report December 2013 TABLE OF CONTENTS PHASE 2 EXPO LINE PROJECT STATUS TABLE OF CONTENTS... 2 Phase 2 Exposition Metro Line Construction Authority

More information

The Future of Transit in Colorado

The Future of Transit in Colorado Note: Will be adding photos to slides before finalizing The Future of Transit in Colorado CDOT Division of Transit and Rail Speakers: David Krutsinger, AICP Manager, Rail and Special Projects Tracey MacDonald

More information

3.0 AFFECTED ENVIRONMENT, IMPACT EVALUATION, AND MITIGATION MEASURES

3.0 AFFECTED ENVIRONMENT, IMPACT EVALUATION, AND MITIGATION MEASURES TABLE OF CONTENTS Page 3.0 AFFECTED ENVIRONMENT, IMPACT EVALUATION, AND MITIGATION MEASURES ------------------------------------------------------------------------------------------------ 3-1 3.1 Land

More information

IT TAKES A VILLAGE AND MULTIPLE SOURCES OF REVENUE: A CASE STUDY OF THE DENVER UNION STATION REDEVELOPMENT PROJECT

IT TAKES A VILLAGE AND MULTIPLE SOURCES OF REVENUE: A CASE STUDY OF THE DENVER UNION STATION REDEVELOPMENT PROJECT IT TAKES A VILLAGE AND MULTIPLE SOURCES OF REVENUE: A CASE STUDY OF THE DENVER UNION STATION REDEVELOPMENT PROJECT CATHERINE C. GALE, ESQ. EMMA R. KEYSER, ESQ. BROWNSTEIN HYATT FARBER SCHRECK, LLP I. Introduction

More information

Phase 2 Exposition Metro Line Project

Phase 2 Exposition Metro Line Project Phase 2 Exposition Metro Line Project Monthly Project Status Report November 2013 TABLE OF CONTENTS PHASE 2 EXPO LINE PROJECT STATUS TABLE OF CONTENTS... 2 Phase 2 Exposition Metro Line Construction Authority

More information

Programmatic Implementation of ABC: Module 3 Innovative Contracting and ABC

Programmatic Implementation of ABC: Module 3 Innovative Contracting and ABC Programmatic Implementation of ABC: Module 3 Innovative Contracting and ABC 2 Presentation Outline Construction Manager/General Contractor (CM/GC) and ABC CM/GC Project Highlights Hartford Bridge Replacement

More information

Project Budget and Schedule Status Report

Project Budget and Schedule Status Report Item 52 Transit Program Project Budget and Schedule Status Report Construction Committee June 19, 2014 & Schedule Performance Summary Chart Slide # Project Performance Schedule Performance Comments 3 Crenshaw/LAX

More information

Project Budget and Schedule Status

Project Budget and Schedule Status Item 47 Program Management Project Budget and Schedule Status Transit Project Delivery Transit Project Delivery Construction Committee January 16, 2014 & Schedule Performance Summary Chart Project Performance

More information

Strategies to keep people and goods moving in and through Seattle

Strategies to keep people and goods moving in and through Seattle Strategies to keep people and goods moving in and through Seattle Period of Maximum Constraint and the Permanent Viaduct Closure 2018-2024 West Seattle Transportation Coalition September 27, 2018 Department

More information

Green Line Extension EOT. Project Location. Project Purpose. Environmental Impact Report Public Scoping Session

Green Line Extension EOT. Project Location. Project Purpose. Environmental Impact Report Public Scoping Session Green Line Extension Environmental Impact Report Public Scoping Session Somerville High School October 16, 2006 Project Location Green Line Extension Project Purpose Implement enhancements to transit services

More information

Constructability Guidelines

Constructability Guidelines Constructability Guidelines The Constructability Guidelines offer a list of items that should be considered by Constructability function personnel during the Concept Development Phase through the Final

More information

Cleveland Opportunity Corridor Project Section 3. Subcontractor Informational Meeting August 12, 2016

Cleveland Opportunity Corridor Project Section 3. Subcontractor Informational Meeting August 12, 2016 Cleveland Opportunity Corridor Project Section 3 Subcontractor Informational Meeting August 12, 2016 Agenda Welcome and Opening Remarks Project Overview Prequalifications & Work Types Procurement Overview

More information

City of Brandon Division 2 Standard Construction Specifications Section January 2007(Revision 1) Page 1 of 8 ROADWAY EXCAVATION AND GRADING

City of Brandon Division 2 Standard Construction Specifications Section January 2007(Revision 1) Page 1 of 8 ROADWAY EXCAVATION AND GRADING January 2007(Revision 1) Page 1 of 8 PART 1 GENERAL 1.01 OTHER CONTRACT DOCUMENTS 1.02 DESCRIPTION OF WORK 1.03 RELATED WORK 1.04 CLASSIFICATION OF THE WORK 1.05 QUALITY ASSURANCE PART 2 PRODUCTS 2.01

More information

Phase 2 Exposition Metro Line Project

Phase 2 Exposition Metro Line Project Phase 2 Exposition Metro Line Project Monthly Project Status Report November 2014 TABLE OF CONTENTS PHASE 2 EXPO LINE PROJECT STATUS TABLE OF CONTENTS... 2 Phase 2 Exposition Metro Line Construction Authority

More information

Project Budget and Schedule Status

Project Budget and Schedule Status Item Program Management Project Budget and Schedule Status Transit Project Delivery Transit Project Delivery Construction Committee February 20, 2014 & Schedule Performance Summary Chart Slide # Project

More information

2007 Annual Report to DRCOG on FasTracks. December 2007

2007 Annual Report to DRCOG on FasTracks. December 2007 December 2007 TABLE OF CONTENTS Section Page No. Executive Summary... Project Definition and Scope... Plan and Corridor Costs... 5 Revenue Projections... 5 Implementation Schedule...7 Level of Bus Service...

More information

A Systems Engineering Approach to Enhance and Support the Acceptance Process for RTD FasTracks Projects

A Systems Engineering Approach to Enhance and Support the Acceptance Process for RTD FasTracks Projects A Systems Engineering Approach to Enhance and Support the Acceptance Process for RTD FasTracks Projects Timothy Stokes, PE Parsons Corp. Denver, CO OVERVIEW Project closeout is often the most neglected

More information

Lessons Learned Meeting Notes

Lessons Learned Meeting Notes EXTERNAL MEMORANDUM Lessons Learned Meeting Notes Distribution Date: April 24, 2017 Date of Meeting: April 19, 2017 Project: Sacramento Wash Crossing at Oatman Highway TRACS No. T0021 01D Federal Project

More information

E. CONSTRUCTION PROCEDURES

E. CONSTRUCTION PROCEDURES E. CONSTRUCTION PROCEDURES The Project facilities would be constructed in accordance with established electric utility practices, best management practices, final engineering plans, CL&P s specifications

More information

FEDERAL HIGHWAY ADMINISTRATION RECORD OF DECISION FOR THE LYNNWOOD LINK EXTENSION

FEDERAL HIGHWAY ADMINISTRATION RECORD OF DECISION FOR THE LYNNWOOD LINK EXTENSION FEDERAL HIGHWAY ADMINISTRATION RECORD OF DECISION FOR THE LYNNWOOD LINK EXTENSION AUGUST 2015 Table of Contents 1 Decision... 1 1.1 Project Description... 2 1.2 Basis for the FHWA Decision... 7 1.2.1

More information

MILTON-MADISON BRIDGE REPLACEMENT

MILTON-MADISON BRIDGE REPLACEMENT MILTON-MADISON BRIDGE REPLACEMENT Andy Barber P.E. Kevin Hetrick P.E. 1 Presentation Overview KYTC lead Environmental Study TIGER Grant INDOT lead Design Build solution Bridge Sliding Project Status Questions

More information

APPENDIX A - PLANS AND POLICY REVIEW FEBRUARY 2017

APPENDIX A - PLANS AND POLICY REVIEW FEBRUARY 2017 APPENDIX A - PLANS AND POLICY REVIEW FEBRUARY 2017 DENVERMOVES Transit Denver Moves: Transit APPENDIX A PLANS AND POLICY REVIEW 2035 Metro Vision Regional Transportation Plan (MVRTP) (2011) 2040 Fiscally

More information

SPECIAL PROVISION Detours, Barricades, Warning Signs, Sequence of Work, etc.

SPECIAL PROVISION Detours, Barricades, Warning Signs, Sequence of Work, etc. 2004 Specifications CSJ 0299-04-049, Etc. SPECIAL PROVISION 000---979 Detours, Barricades, Warning Signs, Sequence of Work, etc. 1. Description of Project. A. General. This project provides for the construction

More information

Chapter 3: Permit Procedures and Requirements

Chapter 3: Permit Procedures and Requirements Chapter 1: General Provisions 1 1 Short Title 1 2 Jurisdiction 1 3 Amendments and Revisions 1 4 Enforcement Responsibility 1 5 Review Process 1 6 Prior Approval 1 7 Relationship to Other Standards 1 8

More information

Dulles Corridor Metrorail Project Phase 1 & Phase 2 Updates

Dulles Corridor Metrorail Project Phase 1 & Phase 2 Updates Dulles Corridor Metrorail Project Phase 1 & Phase 2 Updates June 30, 2017 Charles W. Stark Executive Project Director Phase 2 Station Tour 2 Phase 1 Phase 1 Cost Summary Quarter Expenditures (Feb, Mar,

More information

TRANSPORTATION RELATIONSHIP TO OTHER ELEMENTS OF THE PLAN AND COUNTY REGULATIONS VISION FOR TRANSPORTATION PLANNING ROAD NETWORK SECTION 7

TRANSPORTATION RELATIONSHIP TO OTHER ELEMENTS OF THE PLAN AND COUNTY REGULATIONS VISION FOR TRANSPORTATION PLANNING ROAD NETWORK SECTION 7 TRANSPORTATION Like many growing western counties, Douglas County focuses on one of the most integral elements in land-use planning: transportation. The primary purpose of a transportation network is to

More information

WELCOME EAST LINK OVERLAKE MASTER PLANNED DEVELOPMENT

WELCOME EAST LINK OVERLAKE MASTER PLANNED DEVELOPMENT WELCOME The purpose of tonight s meeting is to: Educate the Overlake community about why Sound Transit is applying for a Master Planned Development Permit to build East Link within the City of Redmond

More information

SH 7 BRT Concept Evaluation: Modeling: Ridership and Ridership Evaluation: Travel Time Evaluation: Station Usage:...

SH 7 BRT Concept Evaluation: Modeling: Ridership and Ridership Evaluation: Travel Time Evaluation: Station Usage:... FINAL REPORT 2018 Prepared for: BOULDER COUNTY in association with: HDR Rocky Mountain Transit & Urban Planning EPS Logan Simpson Design Felsburg Holt & Ulliveg 1 Contents A Corridor Vision of Local Livability

More information

1560 Broadway, Suite 700, Denver, CO phone

1560 Broadway, Suite 700, Denver, CO phone RESOLUTION NO. 1 SERIES OF 2006 REVISED TRANSIT ORIENTED DEVELOPMENT POLICY Whereas, the Board of Directors has determined that transit oriented development (TOD) can enhance the value and effectiveness

More information

Life Cycle Cost Analysis

Life Cycle Cost Analysis Life Cycle Cost Analysis Washington Street Widening 144 th Avenue to 148 th Avenue City of Thornton Deborah Turner, PE Overview Project Location What is Life Cycle Cost Analysis? Project Background 7 Steps

More information

CM/GC Contracting Lessons Learned from Portland and San Francisco

CM/GC Contracting Lessons Learned from Portland and San Francisco CM/GC Contracting Lessons Learned from Portland and San Francisco Lance Erz, TriMet Robin M Reitzes, SF City Attorney s Office American Public Transportation Association Legal Affairs Seminar February

More information

CHAPTER 6: CUMULATIVE IMPACTS

CHAPTER 6: CUMULATIVE IMPACTS CHAPTER 6: CUMULATIVE IMPACTS A cumulative impacts analysis considers all aspects of the environment affected by project alternatives in the context of other past, present, and reasonably foreseeable future

More information

Phase 2 Exposition Metro Line Project

Phase 2 Exposition Metro Line Project Phase 2 Exposition Metro Line Project Monthly Project Status Report February through April 2012 TABLE OF CONTENTS PHASE 2 EXPO LINE PROJECT STATUS TABLE OF CONTENTS... 2 Phase 2 Exposition Metro Line Construction

More information

ALAMEDA CORRIDOR EAST San Gabriel Valley

ALAMEDA CORRIDOR EAST San Gabriel Valley ALAMEDA CORRIDOR EAST San Gabriel Valley San Pedro Bay ports: 40% of nation s imports; 30% of exports. ACE Trade Corridor: 21% of waterborne containers entering/exiting the U.S. 81 trains/day (2009) 141

More information

Transit Service Guidelines

Transit Service Guidelines G R E AT E R VA N CO U V E R T R A N S P O RTAT I O N A U T H O R I T Y Transit Service Guidelines PUBLIC SUMMARY REPORT JUNE 2004 Greater Vancouver Transportation Authority TRANSIT SERVICE GUIDELINES

More information

Design-Build and Design-Bid-Build

Design-Build and Design-Bid-Build Design-Build and Design-Bid-Build Comparison of Overall Cost and Time Question: How does the total cost and time to deliver a $55,000,000 and 814 day design-build project compare to using design-bid-build

More information

GULF COAST RAIL DISTRICT VISION FOR REGIONAL RAIL

GULF COAST RAIL DISTRICT VISION FOR REGIONAL RAIL GULF COAST RAIL DISTRICT VISION FOR REGIONAL RAIL OCTOBER 2014 Cover photographs courtesy of Top left - Mike Bates TABLE OF CONTENTS MISSION... 1 INTRODUCTION... 1 VISION STATEMENT... 1 BACKGROUND... 2

More information

Gold Line Environmental Impact Statement (EIS)

Gold Line Environmental Impact Statement (EIS) Gold Line Environmental Impact Statement (EIS) Workshop No. 3 Level 3, Detailed Evaluation February 5 and 7, 2007 1 Agenda Introduction Railroad (RR) Negotiations Update What is the Project? Mission of

More information

Category: Contractor: Project Name:

Category: Contractor: Project Name: Category: 10 Best Building Project General Contractor ($40-$70 Million) Contractor: PCL Construction Services, Inc., Ashley Watson, Marketing, amwatson@pcl.com Project Name: RTD Commuter Rail Maintenance

More information

Overview of City of Dallas and DART Interlocal Agreements

Overview of City of Dallas and DART Interlocal Agreements Overview of City of Dallas and DART Interlocal Agreements Council Transportation and Environment Committee Prepared by Transportation Programs Public Works and Transportation March 24, 2008 Purpose of

More information

Quality of Life Study High Level Measures

Quality of Life Study High Level Measures 2008 Quality of Life Study High Level Measures December 2009 TABLE OF CONTENTS INTRODUCTION i 1. Purpose of the Study i 2. Study Scope ii 3. Study Measures v 4. 2008 Findings vi HIGH LEVEL MEASURES 1 1.

More information

What is the Transportation Policy Plan (TPP)?

What is the Transportation Policy Plan (TPP)? Summary What is the Transportation Policy Plan (TPP)? The region s long range transportation plan Includes all modes of transportation: highways, transit, airports, freight, biking, pedestrians Meets the

More information

ATTACHMENT 3. Background:

ATTACHMENT 3. Background: Colorado Tolling Enterprise (CTE) or High Performance Transportation Enterprise Additional Information Requirements for Amendment Submittals for the DRCOG Fiscally Constrained RTP Adopted by DRCOG Board

More information

Exposition Light Rail Transit Project

Exposition Light Rail Transit Project Exposition Light Rail Transit Project Downtown Corridor USC Galen Center November 13, 2007 Project Summary 8.6 mile corridor from 7th/Metro to Culver City 1.3 miles shared with Metro Blue Line 10 stations,

More information

CROWS LANDING CORRIDOR PLAN

CROWS LANDING CORRIDOR PLAN ATTACHMENT 1: SCOPE OF WORK CROWS LANDING CORRIDOR PLAN INTRODUCTION: StanCOG proposes the Crows Landing Corridor Plan (Plan), which is needed to determine the feasibility of inter-jurisdictional transportation

More information

COUNTY ENGINEERS ASSOCIATION OF MARYLAND SPRING 2016 CONFERENCE. Conference Center at the Maritime Institute Anne Arundel County, Maryland

COUNTY ENGINEERS ASSOCIATION OF MARYLAND SPRING 2016 CONFERENCE. Conference Center at the Maritime Institute Anne Arundel County, Maryland COUNTY ENGINEERS ASSOCIATION OF MARYLAND SPRING 2016 CONFERENCE Conference Center at the Maritime Institute Anne Arundel County, Maryland Thursday, April 28, 2016 Two bridges in Two Months - Accelerated

More information

CONSTRUCTION SPECIFICATION FOR EXCAVATING AND BACKFILLING - STRUCTURES

CONSTRUCTION SPECIFICATION FOR EXCAVATING AND BACKFILLING - STRUCTURES ONTARIO PROVINCIAL STANDARD SPECIFICATION METRIC OPSS 902 DECEMBER 1983 CONSTRUCTION SPECIFICATION FOR EXCAVATING AND BACKFILLING - STRUCTURES 902.01 SCOPE 902.02 REFERENCES 902.03 DEFINITIONS TABLE OF

More information

SECTION SITE GRADING. Part 1 - General Work Included Related Requirements Reference Standards...

SECTION SITE GRADING. Part 1 - General Work Included Related Requirements Reference Standards... SECTION 02210 - SITE GRADING CONTENTS: Part 1 - General... 1 1.01 Work Included... 1 1.02 Related Requirements... 1 1.03 Reference Standards... 1 1.04 Quality Assurance... 1 1.05 Measurement and Payment...

More information

Date: January 28, TriMet Contract Review Board. Daniel W. Blocher, P.E.

Date: January 28, TriMet Contract Review Board. Daniel W. Blocher, P.E. Date: January 28, 2015 To: From: Subject: TriMet Contract Review Board Daniel W. Blocher, P.E. Evaluation of Public Improvement Project Not Contracted By Low Bidding West Segment of the Portland Milwaukie

More information

Northern Intermodal Transit Facility WHAT IS AN INTERMODAL TRANSIT FACILITY?

Northern Intermodal Transit Facility WHAT IS AN INTERMODAL TRANSIT FACILITY? WHAT IS AN INTERMODAL TRANSIT FACILITY? An intermodal transit facility gathers many modes of transportation together and is strategically located to increase destination alternatives. Intermodal facilities

More information

I-25 South Gap Project

I-25 South Gap Project I-25 South Gap Project Monument to Castle Rock I-25 Gap Coalition Meeting April 26, 2018 EA Schedule/Key Dates EA Release April 27, 2018 EA Comment Period = 30 days, ends May 28, 2018 Media Briefing April

More information

S-09: Auburn Station Access Improvements

S-09: Auburn Station Access Improvements Project Number S-09 Subarea South King Primary Mode Commuter Rail Facility Type Infrastructure Improvements Length Version Number ST Board Workshop Date Last Modified 11-25-2015 PROJECT AREA AND REPRESENTATIVE

More information

STATEMENT QUALIFICATIONS FOR UTILITY SERVICES

STATEMENT QUALIFICATIONS FOR UTILITY SERVICES STATEMENT OF QUALIFICATIONS FOR UTILITY SERVICES Included in this Statement of Qualifications... Introducing Ourselves Key Personnel Joel R. Colwell, P.E. Ramon A. Herrera, P.E. Terry L. McDaniel, P.E.

More information

10. PROJECT DEVELOPMENT, LEADERSHIP, AND OVERSIGHT GUIDELINES

10. PROJECT DEVELOPMENT, LEADERSHIP, AND OVERSIGHT GUIDELINES 10. PROJECT DEVELOPMENT, LEADERSHIP, AND OVERSIGHT GUIDELINES It is important to note that the Transitway Guidelines are not intended to be prescriptive, but rather to provide a consistent basis for planning,

More information

Priorities are for AG comment at today's meeting. Four time frames proposed for implementation

Priorities are for AG comment at today's meeting. Four time frames proposed for implementation Prioritization Overview Priorities are for AG comment at today's meeting Four time frames proposed for implementation Prioritization Overview Some editing of Principles to read as implementation versus

More information

Construction Project Briefing. November 19, 2014

Construction Project Briefing. November 19, 2014 Construction Project Briefing November 19, 2014 Today s Presentation Traction Power Farwell/Armitage/Hill Substations Kimball/Princeton/State Substations O Hare Blue Line Station Improvements (Damen, Western,

More information

Chapter 1: Overview. page 1. Figure 2-1: Road congestion is expected to continue to grow

Chapter 1: Overview. page 1. Figure 2-1: Road congestion is expected to continue to grow Chapter 1: Overview Figure 2-1: Road congestion is expected to continue to grow The region s mobility so fundamental to its economic vitality and quality of life is challenged by mounting congestion, rising

More information

3.11 HAZARDOUS MATERIALS

3.11 HAZARDOUS MATERIALS 3.11 HAZARDOUS MATERIALS 3.11.1 Introduction to Analysis This section provides information regarding known contaminated sites and general areas of potentially contaminated properties along the proposed

More information

Regional Connector Transit Corridor Project Draft Environmental Impact Statement/ Draft Environmental Impact Report

Regional Connector Transit Corridor Project Draft Environmental Impact Statement/ Draft Environmental Impact Report Los Angeles County Metropolitan Transportation Authority Regional Connector Transit Corridor Project Draft Environmental Impact Statement/ Draft Environmental Impact Report Public Scoping Meeting 1 Agenda!

More information

Overview of Construction Activities

Overview of Construction Activities Chapter 5.0 Overview of Construction Activities This chapter describes, to the extent feasible, how construction of the Preferred Alternative might be undertaken and summarizes the measures that have been

More information

Expo Light Rail Line. Expo Line Community Meeting Quarterly Phase 2 Construction and Design Update October 2012

Expo Light Rail Line. Expo Line Community Meeting Quarterly Phase 2 Construction and Design Update October 2012 Expo Line Community Meeting Quarterly Phase 2 Construction and Design Update October 2012 Meeting Agenda Phase 2 Design Update Meeting Meeting Purpose and Format Final Design Update Expo Bikeway Update

More information

Midtown Corridor Alternatives Analysis. Technical Advisory Committee Meeting November 15, 2012

Midtown Corridor Alternatives Analysis. Technical Advisory Committee Meeting November 15, 2012 Midtown Corridor Alternatives Analysis Technical Advisory Committee Meeting November 15, 2012 Today s Agenda Introductions Roles and Responsibilities Alternatives Analysis Process Overview Outreach Overview

More information

Plessis Road Twinning and Grade Separation at CN Redditt Subdivision: Design Challenges and Innovative Solutions

Plessis Road Twinning and Grade Separation at CN Redditt Subdivision: Design Challenges and Innovative Solutions Plessis Road Twinning and Grade Separation at CN Redditt Subdivision: Design Challenges and Innovative Solutions Tanya D. Worms, P.Eng. M.Sc., Project Manager, M.D. Steele Construction Ltd. Paper prepared

More information

Construction Specification for General Excavation

Construction Specification for General Excavation Engineering & Construction Services Division Standard Specifications for Road Works TS 2.10 September 2018 for General Excavation Table of Contents TS 2.10.01 SCOPE... 2 TS 2.10.02 REFERENCES... 2 TS 2.10.03

More information

ACTIVE TRANSPORTATION ADVISORY COMMITTEE. Memphis MPO March 30, 2015

ACTIVE TRANSPORTATION ADVISORY COMMITTEE. Memphis MPO March 30, 2015 ACTIVE TRANSPORTATION ADVISORY COMMITTEE Memphis MPO March 30, 2015 Agenda Welcome & Introductions Announcements and Briefings Livability 2040: Regional Transportation Plan Congestion Management Process

More information

DDI s Can Move More Than Cars. Alex Ariniello. Presentation for the ITE Western District Annual Meeting. July, 2016 in Albuquerque, New Mexico

DDI s Can Move More Than Cars. Alex Ariniello. Presentation for the ITE Western District Annual Meeting. July, 2016 in Albuquerque, New Mexico DDI s Can Move More Than Cars Alex Ariniello Presentation for the ITE Western District Annual Meeting July, 2016 in Albuquerque, New Mexico In January, 2016, a Diverging Diamond Interchange (DDI) opened

More information

Gateway Corridor Transitway

Gateway Corridor Transitway Locally Preferred Alternative Summary Gateway Corridor Transitway 1 Metropolitan Council, Nov. 12, 2014 Gateway Corridor Transitway Proposed highcapacity transit improvement connecting east metro suburbs

More information

Stormwater Management Utility Annual Report

Stormwater Management Utility Annual Report Stormwater Management Utility 2012 Annual Report March 2013 The Stormwater Management Utility provides services and improvements throughout the City including: Maintenance of existing drainage facilities

More information

The Policies section will also provide guidance and short range policies in order to accomplish the goals and objectives.

The Policies section will also provide guidance and short range policies in order to accomplish the goals and objectives. 4 Goals & Objectives INTRODUCTION The 2015-2040 MTP preserves and promotes the quality of life and economic prosperity of the MAB by providing a transportation system consistent with the regional goals.

More information

SOUTHEAST FLORIDA REGIONAL COMPACT CLIMATE CHANGE. Sustainable Communities & Transportation Planning

SOUTHEAST FLORIDA REGIONAL COMPACT CLIMATE CHANGE. Sustainable Communities & Transportation Planning SOUTHEAST FLORIDA REGIONAL COMPACT CLIMATE CHANGE Draft Regional Climate Action Plan Sustainable Communities & Transportation Planning SP-1 Develop criteria in collaboration with municipal and county planning

More information

Chapter 9: Vision Plan. Chapter 9. Vision Plan. Lake Loveland. Image 179 Credit: City of Loveland

Chapter 9: Vision Plan. Chapter 9. Vision Plan. Lake Loveland. Image 179 Credit: City of Loveland Chapter 9 Vision Plan Lake Loveland. Image 179 Credit: City of Loveland Chapter 9: Vision Plan A. Regionally Significant Corridor and Regional Bike Corridor Visions Corridor visioning seeks to develop

More information

For immediate questions, please contact Dr. Florine P. Raitano, Coalition Director and Project Manager for this project.

For immediate questions, please contact Dr. Florine P. Raitano, Coalition Director and Project Manager for this project. October 17, 2007 Dear : The I-70 Coalition is pleased to announce the release of the long awaited Request for Proposal for the I-70 Corridor Transit Planning Project. Attached you will find a copy of the

More information

Construction Requirements for Installation of Utilities in the Public Right-of-way of McPherson County, Kansas October 2011

Construction Requirements for Installation of Utilities in the Public Right-of-way of McPherson County, Kansas October 2011 Construction Requirements for Installation of Utilities in the Public Right-of-way of McPherson County, Kansas October 2011 General Provisions and Specifications - These provisions and specifications shall

More information

DESIGN AND CONSTRUCTION OF DERRY ROAD AND CANADIAN NATIONAL RAIL GRADE SEPARATION

DESIGN AND CONSTRUCTION OF DERRY ROAD AND CANADIAN NATIONAL RAIL GRADE SEPARATION DESIGN AND CONSTRUCTION OF DERRY ROAD AND CANADIAN NATIONAL RAIL GRADE SEPARATION Vireak Hinh, P.Eng. R.V. Anderson Associates Ltd., Toronto, Canada Jennifer Trimble Region of Halton, Oakville, Canada

More information

Environmental Analysis, Chapter 4 Consequences, and Mitigation

Environmental Analysis, Chapter 4 Consequences, and Mitigation Environmental Analysis, Chapter 4 Table 4.17-3. Summary of Adverse Environmental Justice Impacts Topic No Build TSM At-Grade Emphasis LRT Underground Emphasis LRT Locally Preferred Alternative Transit

More information