Construction and Demolition Material Recovery Facility Feasibility Study

Size: px
Start display at page:

Download "Construction and Demolition Material Recovery Facility Feasibility Study"

Transcription

1 FINAL REPORT North Central Texas Council of Governments Construction and Demolition Material Recovery Facility Feasibility Study AUGUST 2007 This study was funded through a solid waste management grant provided by the Texas Commission on Environmental Quality through the North Central Texas Council of Governments. This funding does not necessarily indicate endorsement of the study s findings and recommendations.

2 (This page intentionally left blank)

3 FINAL R. W. BECK C&D MRF Feasibility Study Table of Contents Table of Contents List of Tables List of Figures Section 1 Executive Summary 1.1 Project Overview Waste Characterization Waste Projections Market Analysis Conceptual Design Financial Analysis Sensitivity Analysis Summary and Recommendations Section 2 C&D Waste Characterization 2.1 Overview Material Categories and Classification of Loads Waste Characterization Results Results by Generator Type and Site Type Results by Material Type and Origin Data Comparison Regional Disposal Facility Annualized Data Section 3 Waste Projections 3.1 Introduction Methodology Population and Employment Projections Waste Projections Section 4 Market Analysis of Recoverable Materials 4.1 Overview Material Categories Tier 1 Materials Tier 2 Materials Tier 1 Market Analysis /15/07

4 Table of Contents FINAL Concrete/Cement Soil Scrap Lumber Bricks/ Cinder Blocks Corrugated Cardboard Ferrous Metal Asphalt Wood Packaging Drywall/Gypsum Brush Refuse Other Paper MRF Fine-Particle Residual Summary Tier 2 Materials Materials with Existing Markets Materials with Undeveloped Markets Section 5 C&D MRF Conceptual Design 5.1 Introduction Assumptions Waste Stream Site Personnel Site Infrastructure Operating Hours Building and Site Design General C&D Processing Site Heavy Fraction Processing Site Site Layout Processing Equipment General C&D Processing Heavy Fraction Processing Rolling Stock Personnel Unacceptable Materials Section 6 C&D MRF Financial Analysis 6.1 Introduction Capital Expenditures Financing Assumptions Building and Site Construction Processing Equipment Rolling Stock Capital Reserve Operating Expenses Personnel Equipment O&M ii 8/15/07

5 FINAL Table of Contents Residual Material Disposal Other Operating Expenses Operating Reserve Total Expenses Commodity Revenue Total Net Revenue Sensitivity Analysis Additional Costs for Stand-Alone Facility Other Considerations Sensitivity to Market Conditions Competition for C&D Materials Revenue of Co-located Facility Public-Private Partnerships Conclusion This report has been prepared for the use of the client for the specific purposes identified in the report. The conclusions, observations and recommendations contained herein attributed to R. W. Beck, Inc. (R. W. Beck) constitute the opinions of R. W. Beck. To the extent that statements, information and opinions provided by the client or others have been used in the preparation of this report, R. W. Beck has relied upon the same to be accurate, and for which no assurances are intended and no representations or warranties are made. R. W. Beck makes no certification and gives no assurances except as explicitly set forth in this report. Copyright 2007, R. W. Beck, Inc. All rights reserved. 8/15/07 iii

6 Table of Contents FINAL List of Tables Table 1-1 Waste Composition by Material Type and by City (Annual Tonnage) Table 1-2 Summary of Waste Stream Projection Table 1-3 Tier 1 Materials Table 1-4 Waste Streams by Type of Generator Table 1-5 Total Revenue Requirement Table 1-6 Net Revenue and Required Disposal Fee Table 1-7 Sensitivity Analysis of Required Disposal Fee Table 2-1 Waste Composition by Site Type and Generator Type (Percentage of Weight) Table 2-2 Waste Composition by Material Type (Percentage of Weight) Table 2-3 Waste Composition by City (Percentage of Weight) Table 2-4 Waste Composition by Material Type and by City (Annual Tonnage) Table Year Population Projections Table Year Employment Projections Table 3-3 Growth Drivers for Each Waste Generator Type Table 3-4 Summary of Waste Stream Projection Table 4-1 Tier 1 Materials Table 4-2 Tier 2 Materials Table 4-3 Tier 1 Materials Table 4-4 Materials with Existing Markets Table 5-1 Waste Streams by Type of Generator Table 5-2 Rolling Stock for General C&D Processing Area Table 5-3 Initial Employee Roster Table 6-1 Building and Site Construction Costs Table 6-2 Overall Construction Schedule Table 6-3 Processing Equipment Table 6-4 Rolling Stock Costs Table 6-5 Capital Reserve Table 6-6 Annual Personnel Costs Table 6-7 Annual Rolling Stock O&M Table 6-8 Other Operating Expenses Table 6-9 Total Revenue Requirement Table 6-10 Commodity Recovery and Revenue Table 6-11 Net Revenue and Required Disposal Fee Table 6-12 Sensitivity Analysis of Required Disposal Fee iv 8/15/07

7 FINAL Table of Contents List of Figures Figure 5-1: Overall Site Plan Figure 5-2: Flow Diagram for General C&D Processing Line Figure 5-3: Flow Diagram for Heavy Fraction Processing Line Appendices Appendix A: Annualized Waste Characterization Data Appendix B: Population, Employment, and Waste Projections Appendix C: Conceptual Design Sketches Appendix D: Site and Building Construction Costs 8/15/07 v

8 Table of Contents FINAL (This page intentionally left blank) vi 8/15/07

9 FINAL Section 1 Executive Summary 1.1 Project Overview The North Central Texas Council of Governments (NCTCOG) retained the services of R. W. Beck, Inc. (R. W. Beck) to complete a feasibility study for a material recovery facility (MRF) for processing construction and demolition (C&D) debris. This report summarizes R. W. Beck s analysis and findings regarding the feasibility study. The purpose of this C&D MRF Feasibility Study (Study) is to evaluate whether a C&D MRF could financially compete with other disposal alternatives in the North Central Texas region. To begin the project, R. W. Beck met with the NCTCOG Time To Recycle Subcommittee (Subcommittee) to review the scope of services and determine the location of the visual C&D waste characterization. Once given the notice to process, R. W. Beck completed the following tasks to determine the feasibility of the C&D MRF: Waste Characterization; Waste Projections; Market Analysis; Conceptual Design; and Financial Analysis. 1.2 Waste Characterization Section 2 of this report describes the visual waste characterization work R. W. Beck completed for the Study. One of the key parameters that define a C&D MRF is the amount and type of material that the facility will process. To better understand the C&D waste stream in the North Central Texas region, R. W. Beck conducted two visual C&D waste characterization events at the North Texas Municipal Water District (NTMWD) McKinney Landfill, which currently accepts only C&D debris. The purpose of the visual waste characterization is to estimate the type and quantity of C&D material generated within the wasteshed of the Landfill. R. W. Beck collected information regarding the type of site from which the debris originated (e.g., new construction, demolition) and the type of generator (e.g., residential, commercial). Over the two waste characterization events, R. W. Beck collected data on over 600 loads of C&D debris, totaling over 4,300 tons of material. Table 1-1 summarizes the 10/15/07

10 Section 1 FINAL annual tonnage estimated by R. W. Beck using the annual tonnages provided by NTMWD for each community and the percent composition (by weight) developed by R. W. Beck from the data collected during the waste characterization events. 1 Table 1-1 Waste Composition by Material Type and by City (Annual Tonnage) Category Allen Frisco McKinney Plano Richardson Total Concrete/Masonry 3, , , , , ,640.6 Plastic Metal , , , ,799.0 Paper 2, , , , ,776.4 Wood 2, , , , ,576.1 Glass Other Significant Materials [1] Soil , , , ,738.9 Asphalt , , , ,830.3 Drywall , , , ,959.1 Refuse , ,050.6 Other Materials [1] [2] , ,689.7 Total 13, , , , , ,541.2 [1] R. W. Beck divided the Other category, as described in Section 2.2, into two categories: Other Significant Materials for materials that represented more than one percent of the waste stream and Other Materials for the remaining materials that represented less than one percent of the waste stream. [2] The Other Materials category includes: roofing material, yard waste, carpet, non-wood furniture, tires, ceiling tiles, insulation, and other materials 1.3 Waste Projections For the purposes of this Study, R. W. Beck is assuming the C&D MRF will have a life span of 20 years. As such, it is important to have an understanding of not only the waste processing capability of the facility when it opens, but also over the 20 year span of the facility. Section 3 describes the methodology R. W. Beck used to estimate the 20-year C&D waste stream projections for the wasteshed. 2 R. W. Beck developed the waste projections based on the assumption that changes in C&D debris generation have a high correlation to changes in employment and population. R. W. Beck collected population and employment estimates from NCTCOG Research and Information Services for the waste projections. The projections are published in five-year increments. To enable waste projections for 1 Does not include 1,939 tons hauled to the Landfill by contractors not under contract with one of the five NTMWD member cities. 2 For this analysis, the wasteshed is waste entering the McKinney Landfill from the Cities of Allen, Frisco, McKinney, Plano and Richardson. However, not all C&D waste generated from the cities is disposed at the McKinney Landfill. 1-2 R. W. Beck 10/15/07

11 FINAL Executive Summary each year of the 20 year period, R. W. Beck used straight-line interpolation between the five-year increments to provide projections on an annual basis. Using this data, R. W. Beck developed C&D projections for each of the five NTMWD communities. Table 1-2 summarizes the waste stream projection and Appendix B provides the full C&D waste stream projection. Table 1-2 Summary of Waste Stream Projection Category Avg. Growth Rate Concrete/Masonry 45,641 57,348 72,310 85,566 99, % Plastic ,147 1, % Metal 6,799 8,748 11,438 13,666 15, % Paper 9,776 12,605 16,461 19,484 22, % Wood 18,576 23,437 29,849 35,200 40, % Glass 898 1,224 1,673 1,977 2, % Other Significant Materials [1] Soil 26,739 33,303 41,202 48,609 57, % Asphalt 6,830 8,354 10,136 11,823 13, % Drywall 4,959 6,322 8,232 9,827 11, % Refuse 2,051 2,690 3,557 4,199 4, % Other Materials [1] [2] 3,690 4,731 6,132 7,260 8, % Total 126, , , , , % [3] R. W. Beck divided the Other category, as described in Section 2.2, into two categories: Other Significant Materials for materials that represented more than one percent of the waste stream and Other Materials for the remaining materials that represented less than one percent of the waste stream. [4] The Other Materials category includes: roofing material, yard waste, carpet, non-wood furniture, tires, ceiling tiles, insulation, and other materials 1.4 Market Analysis Revenues generated from the sale of recovered materials help to offset the costs of operating a C&D MRF in two ways: Revenue from the sale of material; and Landfill disposal cost avoidance from material diverted from landfills and/or transfer stations. For these reasons, the feasibility of the MRF depends in part on the ability of the MRF to recover and market incoming materials. Section 4 explores the markets for specific materials that would be processed at the MRF through utilization of waste characterization data and market research. The market analysis is based on the waste characterization discussed in Section 2. 10/15/07 R. W. Beck 1-3

12 Section 1 FINAL In order to focus the resources of this study on the materials with the greatest potential impact to the feasibility of the C&D MRF, R. W. Beck created two categories for analyzing marketability of materials. The categories, Tier 1 and Tier 2, are based on prevalence in the waste stream. All those materials that, individually, represented greater than one percent of the waste stream were categorized as Tier 1 materials. Table 1-3 summarizes the Tier 1 materials. Together, these materials represent almost 93 percent of total waste stream. Table 1-3 Tier 1 Materials Material Tonnage Percent of Total Material Tonnage Percent of Total Concrete/ Cement 36, % Ferrous Metal 6, % Soil 26, % Drywall/ Gypsum 4, % Scrap Lumber 9, % Brush 4, % Bricks/Cinder Blocks 8, % Wood Packaging 3, % Cardboard 7, % Refuse 2, % Asphalt 6, % Other Paper 1, % Total 117, % Section 4 includes a detailed description of each of the Tier 1 materials and provides information regarding the value of these materials in the North Central Texas region. R. W. Beck also included limited discussion of Tier 2 materials. 1.5 Conceptual Design Section 5 summarizes the operational and capital requirements of the conceptual C&D MRF facility. In the design of any facility, there are several options for various aspects of the equipment, site and buildings. The conceptual facility described in Section 5 is one example of a C&D MRF facility based on the waste characterization work, market analysis, and assumptions discussed in this section. While the conceptual design is not intended to be site specific, R. W. Beck did make certain assumptions regarding the site layout that may vary from site to site. While many variations of building, site, and processing equipment are possible, R. W. Beck considered the purpose of the facility was to recover as much C&D material as financially feasible given the market conditions in the North Central Texas region. As such, it was not considered feasible to attempt to recover 100 percent of the recoverable material at the site since some material quantities do not justify the investment in equipment and personnel needed to recover each type of material. Section 5 provides a discussion of the assumptions R. W. Beck made regarding the site. Two of the primary assumptions for the analysis were that the C&D MRF would be: 1-4 R. W. Beck 10/15/07

13 FINAL Executive Summary Operated by a public sector entity; and Co-located with an existing Type 1 MSW landfill. During the visual waste characterization described in Section 2, R. W. Beck observed two primary types of waste flow: General C&D - typical commercial and residential C&D debris; and Heavy Fraction - debris from municipal street departments. The debris from the general commercial and residential loads was similar to typical C&D waste streams (e.g., concrete, wood, drywall). The loads from the municipal street departments primarily consisted of concrete and asphalt, plus and the soil excavated with these materials. The material from municipal street departments represents approximately 43 percent of the waste stream, based on weight. Based on this information, R. W. Beck determined that keeping these two waste stream types separate would result in a more efficient MRF operation. Table 1-4 provides a summary waste projection based on the two waste streams. Table 1-4 Waste Streams by Type of Generator Waste Type Heavy Fraction 55,283 68,042 82,965 97, ,240 General C&D 71,258 91, , , ,042 Total 126, , , , ,282 The remainder of Section 5 provides detailed discussion on the conceptual design of the facility and the resources needed to operate it. The discussion includes: Building and Site Design; Processing Equipment; Rolling Stock; and Personnel. Appendix C contains five conceptual design sketches of the conceptual C&D MRF, including: Overall site plan; Layout of general C&D processing facility; Layout of heavy fraction processing area; Isometric three-dimensional view of the site; and Building elevation views. 10/15/07 R. W. Beck 1-5

14 Section 1 FINAL 1.6 Financial Analysis Section 6 of the report summarizes the capital investment and ongoing operational and maintenance (O&M) costs associated with the C&D MRF. R. W. Beck then determined what disposal fee, or tipping fee, would be required at the MRF to make it financially feasible and then compared that to area landfill tipping fees. R. W. Beck developed estimated budgets for both operating and capital expenses. Table 1-5 summarizes the total requirement for the C&D MRF. Section 6 contains a detailed discussion of each line item of this budget. Table 1-5 Total Revenue Requirement Expense Low High Operating Expenses Personnel $994,000 $1,391,600 Processing Equipment O&M $60,000 $115,000 Rolling Stock O&M $213,000 $337,500 Residual Material Disposal $846,872 $1,058,590 Other Operating Expenses $220,000 $325,000 Operating Reserve $116,694 $161,385 Debt Service Building and Site $544,243 $684,050 Processing Equipment $294,406 $416,477 Rolling Stock $224,768 $297,151 Capital Reserve $141,081 $185,427 Total $3,655,066 $4,972,181 Based on the market analysis in Section 4, R. W. Beck developed an estimate of the total revenue from recovered materials. In order to develop the estimate, R. W. Beck assumed that each material that the Operator targeted for recovery would be recovered at a rate of 75 percent. Table 6-10 in Section 6 provides a detailed account of the revenue estimate. Table 1-6 summarizes the amount of disposal fee revenue needed by the Operator to break even and make the C&D MRF financially feasible. 1-6 R. W. Beck 10/15/07

15 FINAL Executive Summary Table 1-6 Net Revenue and Required Disposal Fee Expense Low Scenarios High Scenarios Best Case Worst Case Total Expenses $3,655,066 $4,972,181 $3,655,066 $4,972,181 Commodity Revenue $1,258,934 $1,812,426 $1,812,426 $1,258,934 Disposal Fee Revenue Requirement [1] $2,396,132 $3,159,754 $1,842,639 $3,713,247 Annual Tonnage 126, , , ,541 Per Ton Disposal Fee $18.94 $24.97 $14.56 $29.34 [1] Disposal Fee Revenue Requirement = Total Expenses Commodity Revenue. This is the amount the MRF must recover through tipping fees in order to break even. Based on the information listed in Table 1-6, R. W. Beck estimates that the Operator would need to charge $19 to $25 per ton to operate a financially viable facility. As comparison, R. W. Beck researched the weighted average tipping fees for landfills in the North Central Texas region who reported their per-ton tipping fees to the Texas Commission on Environmental Quality (TCEQ) in its FY 2006 annual report. R. W. Beck calculated the weighted average tipping fee as $19.93 per ton Sensitivity Analysis R. W. Beck conducted a sensitivity analysis to determine the affect that movements in key variables would have on the required disposal fee of the C&D MRF. Since there are multiple variables that could drive the sensitivity analysis, R. W. Beck assumed the per ton revenue for commodity to be the average of the low and high values from Table R. W. Beck then varied the total expense and material recovery rate to determine the affect on the required disposal fee at the C&D MRF. Table 1-7 contains the results of that analysis. Table 1-7 Sensitivity Analysis of Required Disposal Fee Total Expenses Recovery Rate $3,000,000 $4,000,000 $5,000,000 $6,000,000 65% $13.19 $21.09 $29.00 $ % $12.38 $20.28 $28.19 $ % $11.57 $19.47 $27.38 $ % $10.76 $18.67 $26.57 $ % $9.95 $17.86 $25.76 $ /15/07 R. W. Beck 1-7

16 Section 1 FINAL Summary and Recommendations While the analysis conducted as part of this Feasibility Study varies in many respects (e.g., waste stream composition, commodity revenue, reserves) to the original C&D MRF case study R. W. Beck completed for the NCTCOG in 2004, the end result is still very similar. Compared to the disposal fees in the North Central Texas region, the C&D MRF appears to be within the range of financial feasibility. Key components of the financial feasibility include: Co-location of the MRF with another permitted municipal solid waste (MSW) facility, particularly a landfill or transfer station. Find alternative ways to use residual material so that the MRF operator does not have to pay to landfill the residual. Advertise the environmental benefits of the MRF, thereby creating public interest in diverting C&D debris from the landfill. When possible market material to end user to maximize revenue. If quantities are low, the Operator could seek opportunities to cooperatively market materials. Reducing the expenses through efficient operations will help keep the C&D MRF competitive with other C&D disposal or diversion options. The primary operating expenses at a C&D MRF include labor, residual disposal costs, equipment operation and maintenance, and utilities. Controlling the in-bound contamination rate will allow the equipment and labor at the C&D MRF to work more efficiently. If contamination rates are not controlled, the MRF will waste valuable resources separating material that has no value and residual rates will increase. Minimizing residual material that must be disposed of in a landfill will help the MRF reduce expenses. To help avoid the expense associated with landfilling residual material, the MRF operator should find alternative uses for nonrecoverable material. Effectively communicating the importance of disposing of C&D at a MRF is helpful in obtaining support from the consumers and private haulers. 1-8 R. W. Beck 10/15/07

17 FINAL Section 2 C&D Waste Characterization 2.1 Overview One of the key parameters that define a C&D MRF is the amount and type of material the facility will process. To better understand the C&D waste stream in the North Central Texas region, R. W. Beck conducted two visual C&D waste characterization events at the McKinney Landfill (Landfill), which is owned and operated by the NTMWD and which currently accepts only C&D debris. The purpose of the visual waste characterization was to estimate the type and quantity of C&D material generated within the wasteshed of the Landfill. 2.2 Material Categories and Classification of Loads Based on prior planning experience related to C&D debris and expectations on what type of materials were being disposed at the Landfill, R. W. Beck developed a data collection form to collect information on each load characterized at the Landfill. R. W. Beck collected information regarding the type of site from which the debris originated and the type of generator. For the type of site, R. W. Beck used the following classifications: New Construction; Demolition; Renovation; Company Waste; and Other Site Type. The classification Company Waste captured waste from stores (e.g., Home Depot, Wal-Mart, Blockbuster) that have regular roll-off collection, typically compactors. Although not from a construction or demolition site, these loads did not typically contain significant amounts of MSW (refuse). R. W. Beck also categorized loads by the type of generator: Commercial; Residential; City Streets; and Other Generator Type. 10/15/07

18 Section 2 FINAL In this case, Residential refers to construction, demolition and renovation projects for residential homes and not to waste generated by residential households. City Streets refers to the City departments that brought in loads of road construction and demolition materials, and primarily consisted of concrete, asphalt and soil. Other refers to loads that did not fall into one of the other three categories or where the driver was unable to provide the information requested. The material categories included on the form were: Concrete/Masonry: concrete, cement, bricks, cinder blocks, tile, other masonry. Plastic: plastic bottles, buckets, film, polystyrene foam, other plastic. Metal: ferrous metal, non-ferrous metal. Paper: corrugated cardboard, office, paper, newspaper, magazines, phonebooks, other paper. Wood: wood packaging, treated wood, wood furniture, painted wood, brush, scrap lumber. Glass: glass bottles, glass windows, other glass. Other: soil, asphalt, drywall, refuse, roofing, yard waste, carpet, non-wood furniture, tires, ceiling tiles, insulation, other materials. 2.3 Waste Characterization Results This section contains summary-level results for the combined summer and fall waste characterization events. More detailed results are available in Appendix A Results by Generator Type and Site Type As mentioned in Section 2.2.1, R. W. Beck determined the generator type and site type for each load characterized. Table 2-1 summarizes this data, expressed as percentage of weight, based on data from 606 loads (representing 4,313 total tons). Table 2-1 Waste Composition by Site Type and Generator Type (Percentage of Weight) Generator Type Site Type Residential Commercial City Streets Other Generator Total New Construction 2.8% 22.9% 0.4% 0.0% 26.1% Demolition 1.9% 2.6% 46.9% 0.4% 51.9% Renovation 0.8% 5.4% 0.0% 0.0% 6.2% Company Waste 0.0% 13.9% 0.0% 0.1% 14.0% Other Site Type 0.4% 0.4% 0.6% 0.4% 1.8% Total 6.0% 45.2% 47.9% 0.9% 100.0% 2-2 R. W. Beck 10/15/07

19 FINAL C&D Waste Characterization The number for City Streets is largely concentrated under the Demolition site type. Since drivers were often unable to determine the true nature of the road work, R. W. Beck chose to generally classify these loads as Demolition rather than try to determine the true source with limited information Results by Material Type and Origin Table 2-2 presents the percentage of each material, by weight, R. W. Beck estimated during the waste characterization events. Table 2-2 Waste Composition by Material Type (Percentage of Weight) Category Allen Frisco McKinney Plano Richardson Total Concrete/Masonry 1.6% 8.4% 19.3% 2.1% 5.7% 37.0% Plastic 0.0% 0.1% 0.2% 0.1% 0.0% 0.4% Metal 0.4% 1.6% 2.3% 0.8% 0.0% 5.1% Paper 1.0% 1.5% 3.7% 0.8% 0.0% 7.0% Wood 1.1% 2.8% 7.4% 2.0% 0.5% 13.8% Glass 0.2% 0.0% 0.2% 0.1% 0.0% 0.5% Other Significant Materials [1] Soil 0.4% 4.5% 12.3% 0.5% 4.9% 22.6% Asphalt 0.2% 1.0% 3.0% 0.0% 1.6% 5.8% Drywall 0.3% 1.3% 1.1% 0.9% 0.0% 3.7% Refuse 0.3% 0.2% 0.8% 0.1% 0.0% 1.4% Other Materials [1] [2] 0.3% 0.6% 1.4% 0.3% 0.0% 2.7% Total 6.0% 22.1% 51.6% 7.7% 12.7% 100.0% [1] R. W. Beck divided the Other category, as described in Section 2.2, into two categories: Other Significant Materials for materials that represented more than one percent of the waste stream and Other Materials for the remaining materials that represented less than one percent of the waste stream. [2] The Other Materials category includes: roofing material, yard waste, carpet, non-wood furniture, tires, ceiling tiles, insulation, and other materials Observations R. W. Beck made the following general observations regarding the nature of the C&D waste stream coming into the Landfill. The number of City Streets loads hauled to the Landfill was not consistent day to day. Some days there were very few of these loads and some days there were a relatively high number. The number of City Streets loads disposed at the Landfill is dependent on the timing of road work completed by the various cities. Additionally, according to the Landfill staff, some cities stockpile such material since road work is often completed outside of Landfill hours. This material is then hauled to the Landfill once a significant stockpile accumulates. 10/15/07 R. W. Beck 2-3

20 Section 2 FINAL Loads categorized as City Streets contained approximately two-thirds of the concrete and cement accepted at the Landfill and almost 100 percent of the asphalt. However, these loads also contained approximately 90 percent of soil accepted at the site. Clean soil is not captured at the scale house and is taken to a designated area of the Landfill. However, since the soil in the City Streets loads contained significant amount of concrete and asphalt, is was unloaded at the working face area and buried as waste. City Streets loads represented 17 percent of the volume accepted at the Landfill, but 49 percent of the tonnage. This is due to the nature of the materials; concrete, soil and asphalt are some of the heaviest materials per unit of volume accepted at the Landfill. The percentage of loads categorized as Residential New Construction was lower than R. W. Beck anticipated. However, this information was dependent on the collection vehicle drivers. Despite R. W. Beck s efforts to differentiate residential construction project from a commercial construction project, R. W. Beck believes that collection drivers were not always certain of the difference and assumed that waste hauled for a contractor was considered commercial waste Data Comparison R. W. Beck compared the data collected during the two waste characterization events to the data provided by the NTMWD as validation of the data collected in the field. Tons per Load R. W. Beck collected data on 606 loads weighing a total of 4,313 tons, for an average of 7.12 tons per load. In fiscal year (FY) 2005/06, the Landfill accepted a total of 18,196 loads weighing 128,480 tons, for an average of 7.06 tons per load. Tons per Day R. W. Beck collected information at the McKinney Landfill for a total of 8.5 days. Data was collected on 4,313 tons, for an estimated 507 tons per day. By comparison, using 5 day a week operation for 52 week, the data provided by NTMWD indicates approximately 494 tons per day were disposed at the Landfill. Tonnage by City R. W. Beck also compared the tonnage accepted from the NTMWD member communities during the waste characterization events to data provided by NTMWD. R. W. Beck compared the data to both the full FY 2005/06, which ended September 30, 2006, and to the year-to-date (YTD) FY 2006/07 (October 1, 2006 to November 29, 2006). 2-4 R. W. Beck 10/15/07

21 FINAL C&D Waste Characterization Table 2-3 Waste Composition by City (Percentage of Weight) City FY 2005/06 YTD FY 2006/07 R. W. Beck Data Allen 10.4% 6.2% 6.0% Frisco 18.3% 13.3% 22.1% McKinney 53.9% 58.2% 51.6% Plano 9.0% 8.5% 7.7% Richardson 8.4% 13.1% 12.7% Regional Disposal Facility In addition to the data collected at the McKinney Landfill, R. W. Beck also spent two days at the NTMWD 121 Regional Disposal Facility (121 RDF), which includes a Type I MSW landfill. Although the focus of this waste characterization was the McKinney Landfill, R. W. Beck observed loads at the 121 RDF to determine the nature of the C&D debris and type of C&D haulers at that landfill. Since opening the 121 RDF, the McKinney Landfill has accepted only C&D debris and NTMWD has made efforts to divert most C&D generated among its member communities to the McKinney Landfill. R. W. Beck observed that most C&D accepted at the 121 RDF was from small commercial hauling companies, many of which had to unload material manually at the working face. Very few loads were accepted from open-top roll-off containers. The average tons per load was approximately 2.12, versus 7.06 tons per load at the McKinney Landfill. Haulers that have to manually unload waste occupy a tipping area for longer periods of time, and therefore can limit the number of vehicles that can unload at a tipping area during a given period of time. Additionally, since the 121 RDF does not limit waste to C&D debris, loads often contained a higher percentage of non-c&d waste generated from jobsites. R. W. Beck also noted that some of the smaller hauling operations were bringing waste from communities other than the five targeted for the wasteshed (Allen, Frisco, McKinney, Plano, and Richardson). While the 121 RDF does accept some amount of C&D material, R. W. Beck does not believe that type of customers hauling the C&D debris are the target customer for a C&D MRF and therefore data from these haulers was not included in this C&D MRF feasibility analysis. 2.4 Annualized Data Table 2-4 summarizes the annual tonnage estimated by R. W. Beck using the annual tonnages provided by NTMWD for each community and the percent composition (by 10/15/07 R. W. Beck 2-5

22 Section 2 FINAL weight) developed by R. W. Beck from the data collected during the waste characterization events. 1 Table 2-4 Waste Composition by Material Type and by City (Annual Tonnage) Category Allen Frisco McKinney Plano Richardson Total Concrete/Masonry 3, , , , , ,640.6 Plastic Metal , , , ,799.0 Paper 2, , , , ,776.4 Wood 2, , , , ,576.1 Glass Other Significant Materials [1] Soil , , , ,738.9 Asphalt , , , ,830.3 Drywall , , , ,959.1 Refuse , ,050.6 Other Materials [1] [2] , ,689.7 Total 13, , , , , ,541.2 [1] R. W. Beck divided the Other category, as described in Section 2.2, into two categories: Other Significant Materials for materials that represented more than one percent of the waste stream and Other Materials for the remaining materials that represented less than one percent of the waste stream. [2] The Other Materials category includes: roofing material, yard waste, carpet, non-wood furniture, tires, ceiling tiles, insulation, and other materials R. W. Beck will use the data presented in Table 2-4 as the basis for the waste projections (Section 3) and the conceptual design of the C&D MRF (Section 5). 1 Does not include 1,939 tons hauled to the Landfill by contractors not under contract with one of the five NTMWD member cities. 2-6 R. W. Beck 10/15/07

23 FINAL Section 3 Waste Projections 3.1 Introduction Section 2 details the results of the visual waste characterization work R. W. Beck completed as part of this Study and how that information was used to estimate the annual tonnage quantities of the various materials in the C&D waste stream. For the purposes of this Study, R. W. Beck is assuming the C&D MRF will have a life span of 20 years. As such, it is important to have an understanding of not only the waste processing capability of the facility when it opens, but also over the 20 year span of the facility. Section 3 describes the methodology R. W. Beck used to estimate the 20-year C&D waste stream projections for the wasteshed Methodology R. W. Beck initially discussed with NCTCOG using data on past building permit issuances and permit projections to drive the waste projections. R. W. Beck worked with NCTCOG staff and each of the five NTMWD cities in an attempt to collect this building permit data. Since the five cities gather and track this information differently, the data was not consistent enough to enable R. W. Beck to develop waste projections with a singular methodology. R. W. Beck instead used available population and employment projection data to drive the waste projections Population and Employment Projections R. W. Beck collected population and employment estimates from NCTCOG Research and Information Services for the waste projections. The projections are published in five-year increments. To enable waste projections for each year of the 20-year period, R. W. Beck used straight-line interpolation between the five-year increments to provide projections on an annual basis. Table 3-1 summarizes the 20-year population projections. Appendix B contains the full 20-year projection. 1 For this analysis, the wasteshed is waste entering the McKinney Landfill from the Cities of Allen, Frisco, McKinney, Plano and Richardson. However, not all C&D waste generated from the cities is disposed at the McKinney Landfill. 10/15/07

24 Section 3 FINAL Table Year Population Projections City Avg. Growth Rate Allen 79,570 87,391 93,231 95,828 98, % Frisco 87, , , , , % McKinney 88, , , , , % Plano 247, , , , , % Richardson 101, , , , , % Total 604, , , , , % Source: NCTCOG Research and Information Services Table 3-2 summarizes the 20-year employment projections. Appendix B contains the full 20-year projection. Table Year Employment Projections City Avg. Growth Rate Allen 16,264 23,784 34,402 40,743 43, % Frisco 15,080 22,336 34,085 44,557 53, % McKinney 34,766 41,968 50,529 57,970 66, % Plano 126, , , , , % Richardson 112, , , , , % Total 304, , , , , % Source: NCTCOG Research and Information Services 3.3 Waste Projections In order to project the waste stream developed in Section 2, R. W. Beck first designated a growth driver to each of the generator types discussed in Section 2. Table 3-3 summarizes the generator types and growth drivers. Table 3-3 Growth Drivers for Each Waste Generator Type Generator Type Residential Commercial City Streets Other Growth Driver Population Employment Population Population 3-2 R. W. Beck 10/15/07

25 FINAL Waste Projections R. W. Beck then projected the waste stream based on either the population or employment projections from Section For example, the total amount of concrete/cement estimated for the City Allen in 2006 was 2,344 tons (see Appendix A). 2 Of that amount, 1,800 tons was estimated to come from Commercial sites. Since R. W. Beck assumed that the amount of waste generated from Commercial sites would change in correlation with the employment projections, R. W. Beck increased this 1,800 ton amount by the average annual rate of 5.05 percent (see Table 3-2). Therefore, the amount of concrete/cement from Commercial sites in Allen was estimated to be 4,825 tons by the year R. W. Beck used this methodology for each City and each generator type to develop the 20-year C&D waste stream projection. However, instead of the average 20-year growth rate, R. W. Beck calculated the year-to-year waste stream projection based on the year-to-year population or employment growth rate. Table 3-4 summarizes the waste stream projection and Appendix B provides the full C&D waste stream projection. Table 3-4 Summary of Waste Stream Projection Category Avg. Growth Rate Concrete/Masonry 45,641 57,348 72,310 85,566 99, % Plastic ,147 1, % Metal 6,799 8,748 11,438 13,666 15, % Paper 9,776 12,605 16,461 19,484 22, % Wood 18,576 23,437 29,849 35,200 40, % Glass 898 1,224 1,673 1,977 2, % Other Significant Materials [1] Soil 26,739 33,303 41,202 48,609 57, % Asphalt 6,830 8,354 10,136 11,823 13, % Drywall 4,959 6,322 8,232 9,827 11, % Refuse 2,051 2,690 3,557 4,199 4, % Other Materials [1] [2] 3,690 4,731 6,132 7,260 8, % Total 126, , , , , % [1] R. W. Beck divided the Other category, as described in Section 2.2, into two categories: Other Significant Materials for materials that represented more than one percent of the waste stream and Other Materials for the remaining materials that represented less than one percent of the waste stream. [2] The Other Materials category includes: roofing material, yard waste, carpet, non-wood furniture, tires, ceiling tiles, insulation, and other materials The average growth rates in Table 3-4 are greater than the weighted averages from Tables 3-1 and 3-2 since the two communities that contributed the most C&D material, Frisco and McKinney, are also among the fastest growing communities. 2 This amount only includes concrete/cement from the City of the Allen that is hauled to the McKinney Landfill and does not represent the total amount generated in the City. 3 1,800 tons x ( %) 20 = 4,825 tons 10/15/07 R. W. Beck 3-3

26 Section 3 FINAL (This page intentionally left blank) 3-4 R. W. Beck 10/15/07

27 FINAL Section 4 Market Analysis of Recoverable Materials 4.1 Overview Revenues generated from the sale of recovered materials help to offset the costs of operating a C&D MRF in two ways: Revenue from the sale of material; and Landfill disposal cost avoidance from material diverted from landfills and/or transfer stations. For these reasons, the feasibility of the MRF depends in part on the ability of the MRF to recover and market incoming materials. This section explores the markets for specific materials that would be processed at the MRF through utilization of waste characterization data and market research. The market analysis is based on the waste characterization discussed in Section 2. All prices discussed do not include transportation costs. R. W. Beck accounts for transportation costs in Section 6 (budget for the MRF). 4.2 Material Categories In order to focus the resources of this study on the materials with the greatest potential impact to the feasibility of the C&D MRF, R. W. Beck created two categories for analyzing marketability of materials. The categories, Tier 1 and Tier 2, are based on prevalence in the waste stream Tier 1 Materials R. W. Beck defined Tier 1 materials as those that represent one percent or greater of the waste stream, by weight. Table 4-1 contains the list of Tier 1 materials. The Tier 1 designation is weight-based and not an indication of revenue-generating potential. Section 4.3 contains discussion on each of the Tier 1 material. 10/15/07

28 Section 4 FINAL Table 4-1 Tier 1 Materials Material Tonnage Percent of Total Material Tonnage Percent of Total Concrete/ Cement 36, % Ferrous Metal 6, % Soil 26, % Drywall/ Gypsum 4, % Scrap Lumber 9, % Brush 4, % Bricks/Cinder Blocks 8, % Wood Packaging 3, % Cardboard 7, % Refuse 2, % Asphalt 6, % Other Paper 1, % Tier 2 Materials Total 117, % R. W. Beck defined Tier 2 materials as those that, individually, represent less than one percent of the waste stream, by weight. R. W. Beck further categorized Tier 2 materials into two subcategories: those with existing markets and those with undeveloped markets. 1 Table 4-2 summarizes the Tier 2 materials for this Study. Table 4-2 Tier 2 Materials Existing Market Materials Tonnage Percent of Total Undeveloped Market Materials Tonnage Percent of Total Other Masonry % Other Materials 1, % Office Paper % Roofing 1, % Tile % Painted Wood % Yard Waste % Wood Furniture % Non-Ferrous Metal % Other Glass % Other Plastic % Carpet % Buckets % Treated Wood % Glass Bottles % Glass Windows % Newspaper % Ceiling Tiles % Plastic Bottles % Film % Tires % Furniture % Phonebooks % Insulation % Magazines % Polystyrene Foam % Total 3, , The Tier 2 subcategories are based on R. W. Beck s research for this Study, and are not intended to be a definitive list of marketable products in the Region. 4-2 R. W. Beck 10/15/07

29 FINAL Market Analysis of Recoverable Materials Even though Tier 2 materials represent a smaller portion of the waste stream, the Operator may still be able to market the Existing Market materials to the benefit of the MRF operation. For example, non-ferrous metal (in this case, primarily aluminum) only represents 0.3 percent of the waste stream. Yet at $800 to $1,000 per ton, that could translate to $344,480 to $430,600 in revenue. Additionally, some of the paper materials could be mixed and sold as a mixed paper product. Those materials categorized as Tier 2 Undeveloped Market may be re-categorized as Tier 2 Existing Market as the markets for these materials are better developed in the North Central Texas region. 4.3 Tier 1 Market Analysis The following is an analysis of the opportunities to market each of the materials identified within the waste characterization study as having significant volumes Concrete/Cement The primary end-markets for recovered concrete include aggregate for road base, erosion control, and reuse in concrete production. Other uses for recovered concrete include use as drainage medium and as fill. The MRF would have three primary options for the processing of recovered concrete material. The first would be to crush the material on-site and market it to potential users at a price of $4 to $8 per ton. The MRF would store this material on-site for customers to pick up and haul away. R. W. Beck identified city and county streets departments and private road construction companies as the most likely users of this material, as crushed concrete may be used as base material in road construction and maintenance. R. W. Beck spoke with streets departments in several NTMWD member cities that would be interested in purchasing recovered concrete. Another option for the MRF would be to hire a private company to operate mobile crushing equipment at the MRF on an as needed basis. R. W. Beck identified at least one large concrete crushing company within the Metroplex that would be interested in a public/private partnership in which the company provides on-site crushing at the MRF. Under this arrangement, the private company would charge the MRF up to $7 per ton for the crushing of concrete material and the MRF would share in the revenues generated from the sale of this material. 2 The last option is to contract with a private company to process the material. R. W. Beck was able to identify one processor in the Metroplex that will accept unprocessed concrete for free at facilities in Dallas and Carrolton. In discussions with R. W. Beck, a different private concrete processor estimated that they would charge $20 per ton to haul and process the material. 2 This per-ton revenue figure is an estimate provided by the private company, and the actual price would depend on the outcome of contract negotiations. 10/15/07 R. W. Beck 4-3

30 Section 4 FINAL R. W. Beck would recommend that the MRF crush concrete material on-site and market to potential users at a price between $4 and $8 per ton. Based on conversations with city and county streets departments in NTMWD member communities, there is a strong interest in purchasing recycled concrete to use as base material in road construction. Purchasing recycled concrete for this use could represent a significant cost savings to local governments as some governments pay up to $15 per ton for their current road base product Soil Soil recovered at a C&D MRF can be used for erosion control, a drainage medium, as fill, or as daily cover at a landfill. Area soil contractors generally do not pay for soil, but R. W. Beck identified one local soil contractor that would be willing to haul material away from the MRF for free. In addition, the MRF can make this material available on-site to soil contractors, landscapers, or developers. R. W. Beck would recommend that the MRF operator first use the material on-site as daily cover for landfill operations. The secondary use would be to allow soil contractors, landscapers, developers, and other potential users to pick up soil on-site at the MRF for minimal, or no, charge. In the event that demand for soil in the Metroplex increases, the MRF may have the opportunity to sell this product. However, R. W. Beck anticipates that this material will generate minimal revenue Scrap Lumber There are various end-markets for scrap lumber recovered from building construction and demolition. Some recovered scrap lumber is used for boiler fuel. Scrap lumber may also be shredded and used as mulch or alternative daily landfill cover, so long as it has not been treated. 3 Other potential uses for recycled scrap lumber include animal bedding and lumber operations. Wood processing companies may also be able to utilize scrap lumber in the production of engineered wood products, such as fiberboard and plywood. The most viable options for a MRF in the NCTCOG region would be to either process wood scrap into mulch material or contract with a private company for the processing of this material. R. W. Beck was unable to identify any recyclers in the Metroplex that would purchase scrap lumber. However, many would accept scrap lumber for a charge of $2 to $4 per cubic yard. The MRF also has the option to construct an on-site mulching operation for all wood waste and sell mulch product to commercial and residential customers. Processed material could be stored on-site for customers to pick up. Several cities in the Metroplex process wood waste into mulch and market their mulch product. These cities market their single-ground mulch product for a price between $2.50 and $15 per cubic yard, based on the quality of the product. R. W. Beck estimates that the MRF 3 Treated wood was defined as a separate category from other wood waste in the visual waste characterizations performed by R. W. Beck. 4-4 R. W. Beck 10/15/07

31 FINAL Market Analysis of Recoverable Materials could market its mulch product for a price of $2.50 to $7.50 per cubic yard, or $4.54 to $13.63 per ton, 4 and represents the best use of scrap lumber recovered at the MRF Bricks/ Cinder Blocks Bricks and cinder blocks are crushed into various sizes for several uses. Larger particles of crushed material may be sold as landscape rock. Finer grades of crushed brick may be used in the construction of recreational facilities, such as baseball fields, in place of soil. Crushed bricks may also be used in the construction of driveways and private roads or as road stabilizer at landfills or construction sites. R. W. Beck was unable to identify recyclers in the Metroplex who would pay for bricks and/or cinder blocks. However, Metroplex-area crushers report that they would be willing to pick up unprocessed bricks from an area MRF at no charge. R. W. Beck identified one area recycler that would be interested in a public/private partnership in which the company provides on-site crushing at the MRF. Under this arrangement, the private company would charge the MRF a processing fee per ton for the crushing of materials but the MRF would share in the revenues generated from the sale of materials. The MRF may also choose to crush the material on-site. The crushed material could be used on-site as road stabilization for the landfill. The material could also be made available to commercial customers. The MRF would store this material on-site until it is used at the landfill or until customers pick it up. R. W. Beck identified city and county streets departments as the most likely customers of this material, as crushed bricks and cinder blocks may be used in road construction and maintenance. Private contractors may also utilize this material in road and driveway construction. R. W. Beck would recommend that the MRF process bricks and cinder blocks on-site and make crushed material available on-site for use at the landfill or to potential customers. R. W. Beck expects that the MRF will generate minimal revenue from this material, but would avoid disposal cost of the material Corrugated Cardboard The primary market for recovered cardboard is reutilization in cardboard and paperboard (e.g., cereal boxes) packaging. Cardboard separated for recycling at MRFs is either baled directly on-site or sold to a third party facility for processing and sale. The market for old corrugated cardboard (OCC) is well established within the Metroplex. The average monthly price for OCC in 2006 was between $60 and $70 per ton. However, the price of this commodity fluctuates widely, and has recently exceeded $100 per ton in some markets. 4 Mulch is generally sold in cubic yards. However, in order to estimate the revenue that the MRF would generate from the sale of its mulch product, R. W. Beck converted this price range into tons using a volume to weight conversion of 1,100 pounds per cubic yard of mulch. ($2.50 1,100) x 2,000 = $4.54 per ton and ($7.50 1,100) x 2,000 = $13.63 per ton. 10/15/07 R. W. Beck 4-5

32 Section 4 FINAL R. W. Beck would recommend that the MRF bale OCC on-site and market this product to paper mills. Although the price for this commodity varies based on market conditions, R. W. Beck would expect that the MRF will be able to generate a significant amount of revenue from the sale of baled OCC Ferrous Metal Ferrous metals are defined as metals that contain iron (e.g. steel). Recovery of ferrous metals in large scale has been a common practice for many years. These metals are typically marketed to mills and smelting operations. In 2004, nearly 50 percent of the furnace feed bought by the world s steel makers was scrap metal. The market for ferrous metals is well established within the Metroplex. The current market price for scrap ferrous metal is $90 to $130 per ton, depending on the contamination level of the material. However, the price of this commodity fluctuates widely. R. W. Beck identified one area scrap metal company that would be willing to leave roll-off containers at the MRF to be filled with scrap ferrous metal. This company estimated that they would pay the MRF $130 per ton of material picked up. R. W. Beck would recommend that the MRF market its ferrous scrap metal to area scrap metal recyclers. Although the price for this commodity varies based on market conditions, R. W. Beck would expect that the MRF will be able to generate a significant amount of revenue from the sale of this material Asphalt Recovery of asphalt into new hot-mix asphalt has become a standard practice because of cost savings associated with using recovered material. Recovered asphalt may also be used as cold patch 5 for roads, potholes, driveways and parking lots. The MRF has the option to crush recovered asphalt material on-site and market it to commercial and residential customers. The MRF would store this material on-site for customers to pick up. R. W. Beck identified city and county streets departments as the most likely users of this material, as crushed asphalt may be used in road construction and maintenance. Commercial customers may also utilize this material in road, driveway, and parking lot construction and maintenance. The MRF may also opt to contract with a private company for the disposal of asphalt. Area recyclers report a surplus of asphalt currently exists within the Metroplex market. As such, firms are unwilling to pay for recovered asphalt. However, one or more local recyclers may be willing to pick up asphalt from the MRF for recycling at no cost. R. W. Beck would recommend that the MRF crush asphalt on-site and make it available to potential users for minimal, or no, charge or allow it to be picked up by area recyclers for no charge. Depending on changes in market conditions for this material, it is possible that the MRF will be able to generate revenue on this material in the future. However, R. W. Beck expects that this material would initially generate minimal revenue. 5 Cold patch is made of asphalt, aggregate, and a solvent and is used as a temporary patch for potholes. 4-6 R. W. Beck 10/15/07

33 FINAL Market Analysis of Recoverable Materials Wood Packaging Wood packaging primarily consists of recovered wood pallets. This material is processed in the same manner as scrap lumber and is used in similar applications. Refer to sub-section of this section for options regarding wood packaging. R. W. Beck would recommend that the MRF process this material in the same way as scrap lumber Drywall/Gypsum Gypsum drywall is currently viewed as one of the more difficult materials to recycle in the C&D waste stream. There is neither a market for recycled gypsum nor processors of recovered drywall in the Metroplex at this time. However, there are established markets in other areas of the United States, specifically in the Northeast and Northwest. The primary end-markets for recovered gypsum drywall in these areas are Portland cement, new drywall, and agricultural applications. Gypsum is used in the manufacturing of Portland cement and typically represents five to eight percent of the total material inputs. In order for the gypsum to meet factory specifications it must be removed from the paper backing and ground into a fine powder. Participating cement plants report that recycled gypsum performs as well as new gypsum and that the cost savings are significant. Some plants in the northwest United States have committed to using up to 66 percent recycled gypsum in their Portland cement and believe that up to 100 percent recycled content can feasibly be used. Although the market for this material has not yet developed in the North Central Texas region, the presence of several cement plants in the area suggests that there is potential for a market to develop in the future. Recovered gypsum drywall may also be used in the manufacturing of new drywall. However, R.W. Beck was unable to identify any drywall manufacturing plants in or near the North Central Texas region. As such, this application is not a feasible option for recovered drywall sourced in the region. Agricultural applications also hold significant potential for utilizing recovered drywall. Gypsum is commonly used as a soil amendment, as it provides a source of calcium and sulfur to plants. As such, scrap gypsum drywall may also be added to compost. The paper contained in the drywall will biodegrade, however, the gypsum will not biodegrade and will be incorporated into the final compost product. The result will be compost rich in calcium and sulfur, which may provide a benefit to some crops. As the market for recovered gypsum drywall is undeveloped in the North Central Texas region, at the outset of operation, it is likely that the MRF will have to dispose of this material in the landfill. However, the MRF has the option to initiate the development of a potential application by working with local composting operations to create a process for integrating recovered drywall into compost product. 10/15/07 R. W. Beck 4-7

34 Section 4 FINAL Brush The primary end-market for recovered brush is the production of mulch. Mulch can be sold to local area residents or commercial customers for use in landscaping. Mulch may also be used as alternate daily cover at landfills. Please see sub-section of this section for information regarding a mulching operation at the MRF. R. W. Beck would recommend that the MRF process this material in the same way as scrap lumber Refuse By definition, refuse is a contaminant residual of the recycling process that must be landfilled. Hence, no markets for the sale of refuse exist. Disposal costs for refuse within the Metroplex typically ranges from $20 to $30 per ton, with the lower tip fees on the perimeter of the Metroplex. The MRF will be required to dispose of refuse in a landfill Other Paper Other (or mixed) paper separated for recycling at MRFs is either baled directly on site or sold to a third party facility for processing and sale. The primary market for recovered mixed paper is reutilization in paper products. The market for mixed paper is well established within the Metroplex. The market price for mixed paper ranges from $40 to $50 per ton. However, the price of this commodity can fluctuate widely. R. W. Beck would recommend that the MRF bale mixed paper on-site and market it to potential processors. Although the price for this commodity varies based on market conditions, R. W. Beck would expect that the MRF will be able to generate revenue from the sale of baled mixed paper MRF Fine-Particle Residual MRF fine-particle residual has been included within this list because it is likely that significant quantities of this substance will be generated from the processing activities at the MRF. MRF fine-particle residual will contain traces of many materials processed at the C&D MRF, including treated wood. As such, R. W. Beck would recommend further research as to whether regulatory approval would be necessary to use MRF fine-particle residual as alternative daily cover at a landfill or as fill Summary Table 4-3 provides a summary of the revenue estimates for each of the Tier 1 materials. R. W. Beck calculated the revenue estimates based on the recommended course of action for each material. 4-8 R. W. Beck 10/15/07

35 FINAL Market Analysis of Recoverable Materials Table 4-3 Tier 1 Materials Revenue per Ton Material Tonnage Low High Average Market Location Concrete/ Cement 36,019.5 $4.00 $8.00 $6.00 Onsite Soil 26,738.9 $0.00 $0.00 $0.00 Onsite Scrap Lumber 9,393.5 $4.54 $13.63 $9.06 Onsite Bricks/Cinder Blocks 8,283.0 $0.00 $0.00 $0.00 Onsite Cardboard 7,428.6 $60.00 $70.00 $65.00 Hauled to Processor Asphalt 6,830.3 $0.00 $0.00 $0.00 Onsite Ferrous Metal 6,369.0 $90.00 $ $ Hauled to Processor Drywall/ Gypsum 4,959.1 ($25.00) ($30.00) ($27.50) Landfill Brush 4,235.3 $4.54 $13.63 $9.06 Onsite Wood Packaging 3,464.0 $4.54 $13.63 $9.06 Onsite Refuse 2,050.6 ($25.00) ($30.00) ($27.50) Landfill Other Paper 1,700.3 $40.00 $50.00 $45.00 Hauled to Processor 4.4 Tier 2 Materials This section provides an analysis of those materials categorized as Tier 2 materials, or those that individually represent less than one percent of the waste stream in this waste shed Materials with Existing Markets R. W. Beck reviewed the revenue or disposal cost avoidance potential of the Tier 2 materials with existing markets. Since these materials individually represent less than one percent, stockpiling material until marketable quantities are collected is more of an issue than Tier 1 materials. Therefore it may be more feasible for different grades of a material category, paper for example, to be combined and marketed as a mixedgrade material. Additionally, there are certain fixed and variable costs (e.g., sorting personnel) associated with recovering a material. Many of the Tier 2 materials, although recoverable, are present in such small quantities that the cost to recover the material exceeds the revenue and/or cost avoidance associated with the material. Table 4-4 summarizes materials with existing markets. 10/15/07 R. W. Beck 4-9

36 Section 4 FINAL Table 4-4 Materials with Existing Markets Material Tonnage Estimated Revenue per Ton [4] Market Location Mixed Paper [1] $45 Haul to Local Processor Mixed Recyclables $15 Haul to Local Processor Non-Ferrous Metal [2] $900 Haul to Local Processor Mixed Masonry [3] 1,338.1 $0 Onsite Tires 13.1 ($200) [5] Haul to Local Processor Glass bottles 22.8 $0 Haul to Local Processor Yard waste $0 Haul to Local Processor Total 3,278.0 [1] Mixed paper includes: office paper, newspaper, phonebooks, magazines [2] Based on field observations, non-ferrous material was primarily aluminum. Revenue per ton amount shown assumes aluminum. [3] Mixed masonry includes: other masonry, ceramic/porcelain/clay tile [4] Positive numbers indicate positive revenue to the operator. A negative number represents a cost for disposal. [5] Disposal cost for tires is typically not represented in a cost per ton. Rather, disposal cost for tires is usually based on a per tire cost. This estimate is based on $2 per passenger tire with an average weight of 20 pounds per tire. Based on information contained in Sections 5 and 6, R. W. Beck would not anticipate tires, glass bottles, and yard waste to be actively recovered at the MRF Materials with Undeveloped Markets R. W. Beck would anticipate that the materials in Table 4-2 categorized as materials with undeveloped markets would not initially be recovered at the C&D MRF. However, some of these materials may be recovered in the future if the tonnages and available markets make it feasible to recover the material. Some examples include: Roofing; Carpet; Plastic film; and Polystyrene foam. For example, there is a potential market for roofing materials in the future. Asphalt shingles constitute approximately two-thirds of all roofing materials. Scrap shingles are generated by shingle manufacturing facilities (post-industrial) as well as by commercial and residential roof replacements (post-consumer). The largest market for recycled asphalt shingles is the production of hot mix asphalt (HMA), which represents 90 percent of all asphalt produced in the United States R. W. Beck 10/15/07

37 FINAL Market Analysis of Recoverable Materials According to current TCEQ regulations, only post-industrial shingle scrap may be used in the manufacturing of HMA. Further air emissions tests need to be done in order for TCEQ to authorize the use of post-consumer shingle scrap in HMA. There are no tests being done at this time. Because of these market conditions, there are no active shingle recyclers in the state of Texas. However, R. W. Beck identified several processors that would have the capacity to process shingles if the regulation were expanded to include post-consumer shingle scrap. 10/15/07 R. W. Beck 4-11

38 Section 4 FINAL (This page intentionally left blank) 4-12 R. W. Beck 10/15/07

39 FINAL Section 5 C&D MRF Conceptual Design 5.1 Introduction This section summarizes the operational and capital requirements of the conceptual C&D MRF facility. In the design of any facility, there are several options for various aspects of the equipment, site and buildings. The conceptual facility described in this section is one example of a C&D MRF facility that R. W. Beck developed based on the waste characterization work, market analysis, and assumptions discussed in this section. While the conceptual design is not intended to be site specific, R. W. Beck did make certain assumptions regarding the site layout that may vary from site to site. While many variations of building, site, and processing equipment are possible, R. W. Beck considered the purpose of the facility was to recover as much C&D material as financially feasible given the market conditions in the North Central Texas region. As such, it was not considered feasible to attempt to recover 100 percent of the recoverable material at the site since some material quantities do not justify the investment in equipment and personnel needed to recover each type of material. 5.2 Assumptions Section 5.2 summarizes the assumptions R. W. Beck made regarding the conceptual C&D MRF facility. R. W. Beck used these assumptions as the basis for the site layout, building type and size, and equipment selection. There are two key assumptions regarding the development of the conceptual C&D MRF design: Operated by a public sector entity Co-located with an existing Type 1 MSW landfill As discussed throughout this section, co-location of the MRF with an active MSW landfill has many operational, and thus financial, benefits. The MRF could also be colocated at a MSW transfer station, but the landfill provides the added benefit of low transportation costs for residuals and a potential on-site use of fine particle residual as daily cover. Operation by a public sector entity primarily affects the financial discussion in Section Waste Stream During the visual waste characterization described in Section 2, R. W. Beck observed two primary types of waste flow: 10/15/07

40 Section 5 FINAL General C&D - typical commercial and residential C&D debris Heavy Fraction - debris from municipal street departments The debris from the general commercial and residential loads was similar to typical C&D waste streams (e.g., concrete, wood, drywall). The loads from the municipal street departments primarily consisted of concrete and asphalt, plus and the soil excavated with these materials. The material from municipal street departments represents approximately 43 percent of the waste stream, based on weight. 1 Based on this information, R. W. Beck determined that keeping these two waste stream types separate would result in a more efficient MRF operation. Table 5-1 provides a summary waste projection based on the two waste streams. Table 5-1 Waste Streams by Type of Generator Waste Type Heavy Fraction 55,283 68,042 82,965 97, ,240 General C&D 71,258 91, , , ,042 Total 126, , , , ,282 Material Type and Quantity Sections 2 and 3 provide a detailed description of the type and quantity of materials expected at the site if the facility were constructed in the area of the waste shed. Since the waste type and quantity from any particular waste shed may vary, it is important for any potential MRF operator to evaluate their specific waste shed before developing a C&D MRF. Customer Traffic The flow of general C&D material will be more consistent than the flow of the heavy fraction material since the heavy fraction material is generated primarily through projects conducted by the surrounding streets departments. These road projects occur less consistently than general construction and demolition projects, but generate significant volumes of materials when they do occur Site Personnel Since the MRF would be located at an existing MSW facility, there would not initially be a need to have dedicated scale house attendants or other administrative staff. As tonnage processed at the site increases, additional staff may be added. There would also not be a needed for additional investment in information technology (e.g., scale 1 From Section 2, the waste from streets departments represented 48 percent of actual waste characterized. Once extrapolated to an annual number, the percentage falls to 43 percent since these loads were overrepresented in the waste characterization. 5-2 R. W. Beck 10/15/07

41 FINAL C&D MRF Conceptual Design house software, billing system). The MRF would employ a site supervisor, but overall site management would fall under the responsibility of the landfill management Site Infrastructure By co-locating with an existing site, there will be existing connection points for the necessary utilities needed to operate the MRF. R. W. Beck assumes that rolling stock used at the MRF would be maintained using the existing landfill maintenance facility. R. W. Beck reserved space on the site for an optional administrative office space, but for the purposes of estimating construction costs, R. W. Beck assumed there would be existing administrative offices on site Operating Hours R. W. Beck assumed that the site would accept waste Monday through Friday from 8am to 5pm and Saturday from 8am to noon. However, the C&D MRF would only process material Monday through Friday. Material brought to the site on Saturday would be stockpiled for processing on Monday. By not processing material on Saturday, it will provide dedicated time for routine equipment maintenance and equipment repairs, while reducing labor costs associated with full Saturday operation. If the amount of waste stockpiled on Saturday increases to the point that the tipping floor areas are inadequate or it causes undue strain on Monday operations, the Operator could at that time consider adding partial Saturday operations or limiting acceptance of material on Saturday. 5.3 Building and Site Design This section provides a description of the site and buildings for the C&D MRF. Figure 5-1 provides an illustration of the overall conceptual site plan. See Appendix C for more detailed conceptual drawings of the facility. Figure 5-1: Overall Site Plan 10/15/07 R. W. Beck 5-3

42 Section 5 FINAL Based on the type of waste flow described in Section 5.2.1, R. W. Beck assumed the C&D MRF site would contain two separate processing areas: General C&D Processing Site; and Heavy Fraction Processing Site. Section 5.4 provides a summary of the processing equipment R. W. Beck estimates the facility would require based on the type and quantity of waste generated in the waste stream. Separately processing the heavy fraction (the concrete/cement, asphalt and soil) has several advantages: The heavy fraction would not be subject to manual sorting (via laborers), which would be difficult given the weight of the material. The primary processing line (for general C&D) would receive less wear and tear. The soil from the heavy fraction is relatively clean (free from drywall, plastic and other contaminants), increasing the likelihood it can be used as daily cover or for other uses requiring cleaner soil. Combining it with the general C&D stream would introduce additional material that may reduce the options for reuse of the material. The concrete grinder can generate significant noise and sometimes dust. If necessary this portion of the operation could be located at a different location within the same site. However, for this analysis, R. W. Beck assumed the two processing areas would be located adjacent to one another. The processing line for general C&D would be located within the building and the processing line for the heavy fraction would be located outside, adjacent to the building (See Figure 5-1) General C&D Processing Site The general C&D processing site consists of a pre-engineered metal building. The following list provides a general overview of the general C&D processing area. Appendix C provides detail regarding the layout of equipment within the building. Building size: 175 feet x 300 feet = 52,500 square feet. Reinforced concrete slab. Wear-resistant floor topping on tipping area. Attached restroom/break room facilities. Overhead misting system for dust control. Contains mixed C&D processing line (discussed in Section 5.4.1). Contains baler for baling OCC and other recovered paper. Contains wood grinding machinery for converting wood products to mulch. 5-4 R. W. Beck 10/15/07

43 FINAL C&D MRF Conceptual Design Tipping floor storage is conservatively 450 tons, with additional space available, if needed. Exterior overhang for storage of baled paper materials. Exterior overhang for storage of mulch (ground wood). Customer traffic backs into the building, deposits material onto the tipping area, then pulls forward to exit the building Heavy Fraction Processing Site The heavy fraction processing area is an open-air area surrounded by a concrete wall for acoustic and dust control. The following list provides a general overview of the heavy fraction processing area. Appendix C provides detail regarding the layout of equipment within the area. Site dimensions: 175 feet x 200 feet = 35,000 square feet. Reinforced concrete slab. Wear-resistant floor topping on tipping area. Eight foot concrete wall surrounding area, except entry/exit points and loading area. Contains grinding and screening equipment for processing concrete and asphalt (see Section 5.4.2). Storage bunkers for storage of ground material Site Layout Aside from those facilities that R. W. Beck assumed would be located near/adjacent to the site because of co-location with a MSW landfill, the site is self-contained. Features of the site include: Total site dimensions: 360 feet by 1,000 feet = 360,000 square feet (8.3 acres). Up to two retention ponds for stormwater management. Parking for all employees. Space for optional administrative office building. Below grade loading area, located between C&D processing area and heavy fraction processing area, for loading of recovered material. 5.4 Processing Equipment R. W. Beck had discussions with four suppliers of C&D processing equipment. Each company provided examples of other C&D processing facilities with which they have been involved and provided cost estimates for the processing equipment. The focus of the processing equipment is for the processing of the general C&D waste stream since 10/15/07 R. W. Beck 5-5

44 Section 5 FINAL the material stream is more diverse. The heavy fraction, while a significant portion of the waste stream, only consists of three primary materials and therefore is a less complex processing line General C&D Processing The following process flow diagram (Figure 5-2) describes the processing line for general C&D waste. Figure 5-2: Flow Diagram for General C&D Processing Line 5-6 R. W. Beck 10/15/07

45 FINAL C&D MRF Conceptual Design The following describes each of the main components and the primary function of each. 1. Tipping floor The tipping floor is the area where incoming vehicles deposit loads of C&D material to be processed. 2. Finger screen The vibrating finger screen classifies material by size and separates the incoming waste stream into two categories, an over and under size. The overs are all materials larger than the specified screen size and the unders are all materials smaller than the specified screen size. The size classification typically ranges from six to 12 inches in diameter. For the purposes of this Study, R. W. Beck assumed the screen size would be eight inches, which will divert more material to the overs picking line, where most of the manual labor would be initially focused. 3. Overs picking line The over picking line is a horizontal conveyor that lies on top of a series of storage bunkers. Each bunker is used to capture one type of material (two if a divider is used). There are chutes located along the conveyor that allow material to be dropped to the storage bunkers below. This conveyor is wide enough to accommodate large material sizes. As such, it is difficult for laborers to reach across to the opposite side the conveyor to pick material. Thus laborers stand on each side of the conveyor on the overs picking line. As the mixed stream of material moves down the conveyor, laborers will pull the specified materials and drop them down the appropriate chute to the storage bunkers. The number of materials recovered depends on the number of storage bunkers, the use of bunker dividers, and the number of pick line laborers. In this conceptual design, R. W. Beck included 10 bunkers, not all of which would be used initially. Additionally, the first bunker would be dedicated to the temporary storage of residual screen material. 4. Magnetic separator The magnetic separator automatically pulls ferrous metals from the unders conveyor line before the unders material proceeds to the unders picking line. 5. Fines screen This screen could be in the form of a star screen or a trommel screen. A trommel screen provides fixed screening capacity and provides a more consistent product. A star screener allows for more flexibility since the screen size can be adjusted, but can potentially result in a less consistent screened product. The size of the fines screen typically ranges from 3/8 of an inch to two inches in diameter. To maximize use of this residual screen material daily cover or other potential uses, R. W. Beck would recommend using a 3/8 to ½ inch screen size. 6. Unders picking line Once the unders material passes through the fines screen, it is transported along a horizontal conveyor similar to the overs picking line. However, since the material on this line is smaller in size, the conveyor is more narrow than the overs conveyor and laborers can be located along one side versus both sides. 10/15/07 R. W. Beck 5-7

46 Section 5 FINAL 7. Material storage bunkers The material storage bunkers serve as temporary holding areas for material picked from the overs and unders picking lines. The first bunker would store the residual screen material from the fines screen. 8. Baler The baler is used for baling OCC and other paper products. As needed, the baler could also be used for baling plastics, aluminum beverage containers, etc. However, R. W. Beck does not anticipate the baler would be used for these other materials. This baler would not be capable of baling ferrous or non-ferrous scrap metal. 9. Wood processor The wood processor consists of a wood grinding machine, a magnetic separator to remove ferrous metals (primarily nails from scrap lumber and wood packing), and a conveyor to transport material to temporary storage bunkers located outside of the building. As configured, the general C&D waste processing line is capable of processing approximately 60 to 80 tons per hour. Assuming an average of 70 tons per hour and based on an eight hours per day, five days a week, and 52 weeks per year operation, that translates to 145,600 tons per year. Based on the waste projections in Table 5-1, the general C&D processing line would reach capacity in approximately At 80 tons per hour, the facility could process 166,400 tons annually, which exceeds the estimate for However, initially, the capacity of the MRF should be purposely limited since the facility will not need to operate near its maximum capacity Heavy Fraction Processing Figure 5-3 describes the process flow for the heavy fraction material. 5-8 R. W. Beck 10/15/07

47 FINAL C&D MRF Conceptual Design Figure 5-3: Flow Diagram for Heavy Fraction Processing Line The following describes each of the main components and the primary function of each. 1. Tipping floor The tipping floor is the area where incoming vehicles deposit loads of heavy fraction material to be processed. A laborer will be stationed at this area to manually remove contaminant materials (i.e., anything that is not concrete/cement, asphalt, or soil). To the extent possible, asphalt and concrete will be keep separate on the tipping floor and processed separately. This would be accomplished through a combination of tipping loads in separate areas and physically separating materials using the loader. The need for this activity will be dictated by the market for the end product. 2. Screen for fines The primary purpose of this screen is to separate the soil from the concrete, cement, and asphalt. 3. Crusher The crusher will reduce the size of the heavy fraction material into a more marketable material for reuse. 4. Magnetic separator The magnetic separator automatically pulls ferrous metals from the crushed heavy fraction. R. W. Beck expects most of the ferrous metal to be in the form of rebar imbedded in the concrete. 5. Screen for one-inch material To provide a consistent product, the screen will be sized to allow material one inch in diameter and smaller to pass through. 10/15/07 R. W. Beck 5-9

48 Section 5 FINAL Material over one inch in diameter will be re-circulated to the crusher, via a conveyor, to be further processed for size reduction, if needed. 6. Material storage bunkers Temporary storage of crushed material to be sold onsite or marketed to end users. 5.5 Rolling Stock Table 5-2 summarizes the initial recommended inventory and use of rolling stock at the C&D MRF, including roll-off containers. Table 5-2 Rolling Stock for General C&D Processing Area Type Example Manufacturers Example Models Units Primary Use(s) Large Capacity Loader CAT 966H 2 Managing material at tipping areas, Komatsu WA480-6 moving and loading recovered material Small Capacity Loader CAT Komatsu 908 WA Loading recovered material, managing mulch material Excavator CAT Komatsu M318D PC220LC-8 1 Load general C&D material onto processing line Forklift Hyster S50FT 1 Moving and loading baled material Roll-off Truck Numerous [1] Numerous [1] 2 Transporting recovered material, including residual screen material Roll-off Containers Numerous [1] Numerous [1] 10 Storage and transportation of materials Yard Tractor Numerous [1] Numerous [1] 1 Transporting non-recovered residual to the landfill Transfer Trailer Numerous [1] Numerous [1] 1 Sweeper Waldon Sweepmaster Sweep floors of MRF and heavy fraction areas [1] R. W. Beck only provided specific examples where the size and capacity of the equipment was of more importance. There are many options for these vehicles and as such, R. W. Beck did not include specific examples. Several notes concerning the vehicles listed in Table 5-2: When the excavator is down for maintenance and repair, the large loader can be used to load the general C&D processing line, thus providing a back-up to the excavator. Since R. W. Beck anticipates that some material will be marketed directly from the site, the small loader will be useful for loading pick-up trucks, smaller trailers, and smaller dump trucks as well as moving smaller amounts of material around the site. While the large loader can accomplish these tasks, the small loader will 5-10 R. W. Beck 10/15/07

49 FINAL C&D MRF Conceptual Design be efficient for these tasks. Therefore, R. W. Beck would recommend the Operator maintain a small loader within its inventory. If the yard tractor or transfer trailer is down for maintenance or repair, the Operator could use roll-off container to contain the residual and use the roll-off truck to haul it to the landfill, proving back-up for the transfer vehicle. 5.6 Personnel R. W. Beck developed an initial roster of personnel needed at the site. Table 5-3 summarizes the initial employee roster and provides an indication of where personnel would be used. However, the use of personnel on the site, particularly heavy equipment operators and laborers, will depend on the flow of waste. The site supervisor and/or equipment crew leaders will have responsibility of determining the best use of individuals each day. As the amount of waste accepted at the site increases, the City will be able to add additional laborers to the manual picking lines. Additionally, the Operator would likely need to add a mechanic and dedicated administrative staff. Depending on the capabilities of the existing Operator staff, the City may wish to add a staff person dedicated to sales and marketing of both incoming material and recovered material. Table 5-3 Initial Employee Roster Title General C&D Heavy Fraction Primary Responsibility Site Supervisor Day to day site supervision and management Equipment Crew Leader Serve as both equipment operators and assistant site supervisors Heavy Equipment Operators 3 1 Operate loaders, excavator, transfer vehicle, roll-off truck, forklift Mechanic Maintenance and repair on rolling stock and processing equipment Laborers Manual picking lines 14 0 Manually remove materials from pick lines General Laborers 5 1 Direct traffic around site, keep site clear of debris and litter, direct and assist customers purchasing commodity material Total Unacceptable Materials As a policy, the facility should post a list of materials that are considered unacceptable materials. These materials should be treated as contamination to the incoming waste 10/15/07 R. W. Beck 5-11

50 Section 5 FINAL stream and amounts of these materials that appear in the waste stream should be monitored. The Operator could impose penalties for repetitive occurrences of excessive contamination. The following list provides an example of materials that might be listed as unacceptable. Refuse Furniture Batteries Household Hazardous Waste Hazardous Waste Asbestos Liquids Contaminated Soils 5-12 R. W. Beck 10/15/07

51 FINAL Section 6 C&D MRF Financial Analysis 6.1 Introduction This section of the report summarizes the capital investment and ongoing O&M costs associated with the C&D MRF. R. W. Beck then determined what disposal fee, or tipping fee, would be required at the MRF to make it financially feasible and then compared that to area landfill tipping fees. 6.2 Capital Expenditures Financing Assumptions R. W. Beck made several assumptions regarding the financing of the MRF s capital assets. Type of funding - R. W. Beck assumed all purchases would be made with public sector debt. Therefore, the annual budget includes debt service for capital expenditures. Cost of capital R. W. Beck assumed an average cost of capital (i.e., interest rate on debt) of 5.5 percent. Term Since the assumed life of the MRF is 20 years, R. W. Beck assumed all site and building costs would be financed over a 20 year period. R. W. Beck assumed a useful life, and therefore financing period, for processing equipment of 10 years and useful life of rolling stock of seven years. Taxes R. W. Beck realizes that some materials and/or services may be exempt if the Operator is a public sector entity. However, to keep the estimate conservative, R. W. Beck assumed a sales tax of 8.25 percent would apply Building and Site Construction R. W. Beck developed cost estimates for the building and site construction. Table 6-1 provides a brief summary of the cost estimates and Appendix D contains a more detailed estimate. 10/15/07

52 Section 6 FINAL Table 6-1 Building and Site Construction Costs Description Low High Permitting, Design, and Construction Administration $880,200 $1,398,000 Site Work $1,064,306 $1,277,167 C&D MRF Building $3,484,530 $4,181,436 Heavy Fraction Processing Area $579,200 $695,040 Subtotal $6,008,236 $7,551,643 Sales Tax $495,679 $623,011 Total $6,503,915 $8,174,654 Annual Debt Service $544,243 $684,050 Design and Construction Schedule Table 6-2 provides a high-level summary of a typical timeline to design, permit and build a facility similar to the C&D MRF described in this Study. However, through efficient management of the design and construction process, R. W. Beck would expect there to be opportunities to compress the schedule. Table 6-2 Overall Construction Schedule Activity Design and Permitting Bidding Construction Total Duration Duration 9 to 12 months 2 months 10 to 12 months 21 to 26 months Processing Equipment Based on conversations with four equipment manufacturers that provide equipment for C&D MRF operations, R. W. Beck developed the cost estimates listed in Table 6-3. Section 5.4 contains the detail regarding the components of each processing line. 6-2 R. W. Beck 10/15/07

53 FINAL C&D MRF Financial Analysis Table 6-3 Processing Equipment Description Low High C&D Processing Line $1,500,000 $2,000,000 Heavy Fraction Processing Line $300,000 $500,000 Wood Grinder $150,000 $250,000 Baler $100,000 $150,000 Subtotal $2,050,000 $2,900,000 Sales Tax $169,125 $239,250 Total $2,219,125 $3,139,250 Annual Debt Service $294,406 $416, Rolling Stock Table 6-4 provides an estimate of the cost for rolling stock needed at the site. As mentioned in Section 6.2.1, R. W. Beck assumed a useful life for all rolling stock of seven years. Table 6-4 Rolling Stock Costs Unit Cost Total Cost Title Low High Number Low High Large Capacity Loader $300,000 $400,000 2 $600,000 $800,000 Small Capacity Loader $70,000 $100,000 1 $70,000 $100,000 Excavator $150,000 $200,000 1 $150,000 $200,000 Forklift $20,000 $30,000 1 $20,000 $30,000 Roll-off Truck $80,000 $95,000 2 $160,000 $190, CY Roll-off Containers $2,000 $4, $20,000 $40,000 Yard Tractor $75,000 $85,000 1 $75,000 $85,000 Transfer Trailer $55,000 $75,000 1 $55,000 $75,000 Sweeper $30,000 $40,000 1 $30,000 $40,000 Subtotal $1,180,000 $1,560,000 Sales Tax $97,350 $128,700 Total $1,277,350 $1,688,700 Annual Debt Service $224,768 $297,151 10/15/07 R. W. Beck 6-3

54 Section 6 FINAL Capital Reserve A capital reserve fund is typically a required term for issuing revenue-based debt. In many cases, revenue bonds will require that the payee have an amount equal to one year of principal and interest payments. Depending on the entity seeking the debt, this requirement may or may not be necessary. However, R. W. Beck would recommend having a capital reserve in place. Based on the estimated annual debt service payments, R. W. Beck would recommend a capital reserve amount of $1,063,418 to $1,397, The primary methods for funding the capital reserve fund are (1) debt, (2) a fee added to the disposal rate, and (3) excess revenue. At this time, R. W. Beck assumes the Operator would fund the entire amount with debt and finance it over a period of 10 years. Table 6-5 Capital Reserve Description Low High Total capital reserve $1,063,418 $1,397,678 Finance term (years) Debt service from capital reserve $141,081 $185,427 Requirements from bond issuers may differ from the assumptions made by R. W. Beck and could therefore change the amount of the capital reserve and the manner in which it is funded. 6.3 Operating Expenses Section 6.3 summarizes the estimated annual operating expense of the C&D MRF, based on the personnel and resources used at the site Personnel Using the information from Section 5.6, R. W. Beck developed the following cost estimate for employee salaries and benefits. 1 This amount represents the annual debt service for site and building construction, processing equipment, and rolling stock. 6-4 R. W. Beck 10/15/07

55 FINAL C&D MRF Financial Analysis Table 6-6 Annual Personnel Costs Salary Total Salary Title Low High Number Low High Site Supervisor $45,000 $55,000 1 $45,000 $55,000 Equipment Crew Leader $40,000 $50,000 2 $80,000 $100,000 Heavy Equipment Operators $35,000 $45,000 4 $140,000 $180,000 Mechanic $35,000 $45,000 1 $35,000 $45,000 Laborers Manual picking lines $20,000 $30, $280,000 $420,000 Spotters/General Laborers $20,000 $30,000 6 $120,000 $180,000 Salary Total $700,000 $980,000 Benefits (35%) $245,000 $343,000 Overtime (7%) $49,000 $68,600 Total Salary and Benefits $994,000 $1,391, Equipment O&M Rolling Stock Table 6-7 provides estimates of the annual O&M costs for the rolling stock, including roll-off containers. O&M includes repair, routine maintenance, and fuel. Table 6-7 Annual Rolling Stock O&M Total O&M Title Low High Number Low High Large Capacity Loader $55,000 $85,000 2 $110,000 $170,000 Small Capacity Loader $15,000 $25,000 1 $15,000 $25,000 Excavator $25,000 $35,000 1 $25,000 $35,000 Forklift $2,500 $7,500 1 $2,500 $7,500 Roll-off Truck $20,000 $30,000 2 $40,000 $60, CY Roll-off Containers $200 $ $2,000 $5,000 Yard Tractor $15,000 $25,000 1 $15,000 $25,000 Transfer Trailer $1,000 $2,500 1 $1,000 $2,500 Sweeper $2,500 $7,500 1 $2,500 $7,500 Total Rolling Stock O&M $213,000 $337,500 10/15/07 R. W. Beck 6-5

56 Section 6 FINAL Processing Equipment Operations and maintenance of the processing equipment will vary by component and depend on the type of material accepted at the site over a period of time. For example, the conveyors and magnetic separators are typically less prone to needing repair than machinery with more complex moving parts, such as the finger screens. R. W. Beck estimates that annual O&M will range from 3 to 4 percent of the purchase price of the equipment. Based on the pre-tax purchase price of the equipment (see Section 6.2.3), R. W. Beck estimates annual O&M cost for the processing equipment (general C&D and heavy fraction) will be approximately $60,000 to $115,000 per year. R. W. Beck would expect this cost to be at the lower end of the range when the equipment is new and increase over time. This cost does not include the electricity needed to power the processing equipment, which is taken into account under utilities in Section Residual Material Disposal As discussed further in the revenue section (Section 6.5), R. W. Beck estimated that 42,343.6 tons of material accepted at the C&D MRF would be disposed as residual. Based on tipping fees of $20 to $25, the total disposal cost of residual in the first year would be $846,872 to $1,058,590. In practice, some of the residual tonnage will be in the form of residual screen material or other material that the Operator may be able to divert, thus reducing the amount of disposal expense for residual material Other Operating Expenses Table 6-8 contains estimates of additional operating expenses that need to be accounted for in the operation of a C&D MRF. Table 6-8 Other Operating Expenses Description Low High Utilities $80,000 $120,000 Supplies $5,000 $10,000 Training $35,000 $50,000 Building and site maintenance $10,000 $20,000 Professional Services $75,000 $100,000 Miscellaneous $15,000 $25,000 Total $220,000 $325, Operating Reserve The purpose of the operations and maintenance reserve fund would be to financially prepare the Operator for any unbudgeted expenses that may occur in the future and fluctuations in revenue due to commodity markets. R. W. Beck would recommend a 6-6 R. W. Beck 10/15/07

57 FINAL C&D MRF Financial Analysis fund based on three months of the O&M portion of the annual budget (total budget minus capital expenses). This amount would equal $2,333,873 to $3,227,691, based on the low and high scenarios. In order to minimize the rate impact of building this reserve, R. W. Beck would recommend accumulating the O&M reserve over a five year period. Therefore over a five year period, the Operator would need to fund $116,694 to $161,385 annually. 6.4 Total Expenses Table 6-9 summarizes the expense information from Sections 6.2 and 6.3. The Operator needs to generate this amount of revenue, from either the sale of commodities or tipping fees, to make the C&D MRF a financially feasible option. Table 6-9 Total Revenue Requirement Expense Low High Operating Expenses Personnel $994,000 $1,391,600 Processing Equipment O&M $60,000 $115,000 Rolling Stock O&M $213,000 $337,500 Residual Material Disposal $846,872 $1,058,590 Other Operating Expenses $220,000 $325,000 Operating Reserve $116,694 $161,385 Debt Service Building and Site $544,243 $684,050 Processing Equipment $294,406 $416,477 Rolling Stock $224,768 $297,151 Capital Reserve $141,081 $185,427 Total $3,655,066 $4,972, Commodity Revenue Based on the market analysis in Section 4, R. W. Beck developed an estimate of the total revenue from recovered materials. In order to develop the estimate, R. W. Beck assumed that each material that the Operator targeted for recovery would be recovered at a rate of 75 percent. 10/15/07 R. W. Beck 6-7

58 Section 6 FINAL Table 6-10 Commodity Recovery and Revenue Tonnage Revenue per Ton Total Revenue Material Total Revenue [1] Residual [2] Low High Low High Concrete/ Cement 36, , ,004.9 $4.00 $8.00 $108,058 $216,117 Soil 26, , ,684.7 $0.00 $0.00 $0 $0 Scrap Lumber 9, , ,348.4 $4.54 $13.63 $31,985 $96,025 Bricks/Cinder Blocks 8, , ,070.8 $0.00 $0.00 $0 $0 Corrugated Cardboard 7, , ,857.1 $60.00 $70.00 $334,286 $390,000 Asphalt 6, , ,707.6 $0.00 $0.00 $0 $0 Ferrous Metal 6, , ,592.2 $90.00 $ $429,905 $620,974 Brush 4, , ,058.8 $4.54 $13.63 $14,421 $43,295 Wood Packaging 3, , $4.54 $13.63 $11,795 $35,410 Other Paper 1, , $40.00 $50.00 $51,009 $63,761 Other Masonry $0.00 $0.00 $0 $0 Office Paper $40.00 $50.00 $18,775 $23,469 Non-Ferrous Metal $ $1, $258,047 $322,559 Newspaper $40.00 $50.00 $566 $707 Phonebooks $40.00 $50.00 $87 $109 Magazines $40.00 $50.00 $0 $0 Total 112, , ,065.9 $1,258,934 $1,812,426 [1] Based on an average recovery rate of 75 percent, this amount of tonnage would have the potential to generate revenue for the MRF. [2] Based on an average recovery rate of 75 percent, this amount of material would pass through the MRF and be disposed at the landfill. Additionally, the following materials would not be targeted for recovery, at least until the tonnage increases or better markets develop: Drywall/ Gypsum Refuse Other Materials Roofing Tile Painted Wood Wood Furniture Other Glass Carpet Yard Waste Treated Wood Glass Windows Other Plastic Ceiling Tiles Film Furniture Insulation Buckets Polystyrene foam Glass Bottles Plastic Bottles Tires These materials represent a total of 14,277.8 tons based on the waste characterization from Section 2. Combined with the residual tonnage of 28,065.9 from Table 6-10, total residual tonnage is 42, This represents approximately one-third of the total incoming waste stream. It is R. W. Beck s opinion that proper management of 6-8 R. W. Beck 10/15/07

59 FINAL C&D MRF Financial Analysis incoming materials and efficient recovery of targeted materials will result in an overall reduction in the residual rate over time. 6.6 Total Net Revenue Table 6-11 summarizes the amount of disposal fee revenue needed by the Operator to break even and make the C&D MRF financially feasible. Table 6-11 Net Revenue and Required Disposal Fee Expense Low Scenarios High Scenarios Best Case Worst Case Total Expenses $3,655,066 $4,972,181 $3,655,066 $4,972,181 Commodity Revenue $1,258,934 $1,812,426 $1,812,426 $1,258,934 Disposal Fee Revenue Requirement [1] $2,396,132 $3,159,754 $1,842,639 $3,713,247 Annual Tonnage 126, , , ,541 Per Ton Disposal Fee $18.94 $24.97 $14.56 $29.34 [1] Disposal Fee Revenue Requirement = Total Expenses Commodity Revenue. This is the amount the MRF must recover through tipping fees in order to break even. Based on the information listed in Table 6-11, R. W. Beck estimates that the Operator would need to charge $19 to $25 per ton to operate a financially viable facility. As comparison, R. W. Beck researched the weighted average tipping fees for landfills in the North Central Texas region who reported their per-ton tipping fees to the TCEQ for the FY 2006 annual report. R. W. Beck calculated the weighted average tipping fee as $19.93 per ton Sensitivity Analysis R. W. Beck conducted a sensitivity analysis to determine the affect that movements in key variables would have on the required disposal fee of the C&D MRF. Since there are multiple variables that could drive the sensitivity analysis, R. W. Beck assumed the per ton revenue for commodity to be the average of the low and high values from Table R. W. Beck then varied the total expense and material recovery rate to determine the affect on the required disposal fee at the C&D MRF. Table 6-12 contains the results of that analysis. The assumed recovery rate in Section 6.5 was 75 percent. 10/15/07 R. W. Beck 6-9

60 Section 6 FINAL Table 6-12 Sensitivity Analysis of Required Disposal Fee Total Expenses Recovery Rate $3,000,000 $4,000,000 $5,000,000 $6,000,000 65% $13.19 $21.09 $29.00 $ % $12.38 $20.28 $28.19 $ % $11.57 $19.47 $27.38 $ % $10.76 $18.67 $26.57 $ % $9.95 $17.86 $25.76 $ Additional Costs for Stand-Alone Facility Throughout Sections 5 and 6, R. W. Beck s analysis assumed that the C&D MRF facility would be co-located with an active MSW facility, specifically a MSW landfill. If the Operator were to develop the C&D MRF as a stand-alone facility, there are several additional costs and/or issues to consider, including but not limited to: Additional permitting costs (building a facility within the boundaries of an existing TCEQ permitted MSW site is typically easier to permit or register); Scale house with scales, scale house attendants and software; Maintenance facility; Additional mechanics; Possibly a dedicated site manager (to whom the site supervisor would report); and Increase in site size for scale house, maintenance facility, and administrative facilities. 6.8 Other Considerations If a public entity with an existing landfill were to build a C&D MRF, there are some additional considerations the Operator should take into account in the planning process Sensitivity to Market Conditions This analysis was based on the value of commodities in the North Central Texas region at the time of this study. As with other market-driven commodities, the price the Operator receives for recovered material will vary based on supply and demand, as well as other factors, over the life span of the C&D MRF. Therefore, the viability of the MRF is tied to factors that have an amount of risk associated with them. Employing risk management strategies, such as establishing contracts for both 6-10 R. W. Beck 10/15/07

61 FINAL C&D MRF Financial Analysis incoming material and recovered material, will help reduce this risk. However, even contracts for recoverable material often adjust based on direction of the market for the materials Competition for C&D Materials Some of the materials in the waste stream are valuable commodities and thus efforts to recover these materials will likely increase with time. For example, during the waste characterization, only trace amounts of copper were found in the waste stream. Since the price of copper has risen dramatically, it is efficiently recovered from most construction and demolition projects. As demand for materials such as ferrous and non-ferrous metals, OCC, and concrete increase in the North Central Texas region, there will be increased competition among those Operators looking to recover the material, thus putting downward pressure on disposal fees. In addition to competition for the material as a commodity, the C&D MRF would also compete against other MSW landfills, and specifically landfills that accept only C&D waste. Having some contractual or legal control (e.g., city ordinances or other flow control 2 measures) of the waste stream will help reduce the risk associated this competition Revenue of Co-located Facility Based on the waste characterization work, R. W. Beck assumed that approximately 126,541 tons of material would be accepted at the facility in the first year of operation. Based on the FY 2005 data from the TCEQ, this represents 1.4 percent of the total MSW tonnage disposed in landfills and 8.4 percent of C&D material disposed in landfills. Since the 126,541 tons is a part of the overall waste stream generated in the region, acceptance of this material at the MRF means that another facility will see a drop in tonnage. This reduction in tonnage could be from a combination of sources, including the co-located landfill or competitive MSW facilities in the region. If all the tonnage were to be transitioned from the co-located landfill to the C&D MRF, then the total cost of operating both the landfill and MRF could potentially increase compared to the total cost of operating the landfill alone, with the same amount of incoming tonnage. This would result in an overall higher cost per ton for disposal and processing. However, if a significant portion of this tonnage from customers that previously hauled the materials to another site, this affect on the colocated landfill would be minimized. If the tonnage accepted at the co-located landfill decreases, there would be decreases in certain costs that would help offset the potential negative financial impacts discussed in the previous paragraph. These cost decreases would primarily be related to extending the life of the landfill. Cell development costs would be amortized over a longer period of time and financial assurance reserve fund contributions would be 2 A recent Supreme Court ruling, in the case of United Haulers Association v. Oneida-Herkimer Solid Waste Management Authority, provides local governments increased control of waste within their jurisdiction. 10/15/07 R. W. Beck 6-11

62 Section 6 FINAL reduced since the operator would have more time to contribute to the fund. Additionally, the siting and permitting of a new landfill can be an expensive process and extending the life of the landfill would defer these expenses Public-Private Partnerships Public-private partnerships may be an option for the development of a C&D MRF in North Central Texas region. Typically, such partnerships would utilize the financing advantages of the public sector entity (i.e., lower cost of capital) and the operational expertise of the private sector. Additionally, a private sector operator may also operate a C&D collection operation, which could provide a source of incoming C&D debris for the MRF. 6.9 Conclusion While the analysis conducted as part of this Feasibility Study varies in many respects (e.g., waste stream composition, commodity revenue, reserves) to the original C&D MRF case study R. W. Beck completed for the NCTCOG in 2004, the end result is still very similar. Compared to the disposal fees in the North Central Texas region, the C&D MRF appears to be within the range of financial feasibility. Key components of the financial feasibility include: Co-location of the MRF with another permitted MSW facility, particularly a landfill or transfer station. Find alternative ways to use residual material so that the MRF operator does not have to pay to landfill the residual. Advertise the environmental benefits of the MRF, thereby creating public interest in diverting C&D debris from the landfill. When possible, market materials to end users to maximize revenue. If quantities are low, the Operator could seek opportunities to cooperatively market materials. Reducing the expenses through efficient operations will help keep the C&D MRF competitive with other C&D disposal or diversion options. The primary operating expenses at a C&D MRF include labor, residual disposal costs, equipment operation and maintenance, and utilities. Controlling the in-bound contamination rate will allow the equipment and labor at the C&D MRF to work more efficiently. If contamination rates are not controlled, the MRF will waste valuable resources separating material that has no value and residual rates will increase. Minimizing residual material that must be disposed of in a landfill will help the MRF reduce expenses. To help avoid the expense associated with landfilling residual material, the MRF operator should find alternative uses for nonrecoverable material. Effectively communicating the importance of disposing of C&D at a MRF is helpful in obtaining support from the consumers and private haulers R. W. Beck 10/15/07

63 Appendix A Annualized Waste Characterization Data

64 (This page intentionally left blank)

65 Appendix A - Detail Waste Composition Data Concrete/ Cement Bricks/Cinder Blocks Other Masonry Plastic Bottles Buckets Film Styrofoam Other Plastic Ferrous Metal Non-Ferrous Metal Corrugated Cardboard Office Paper Newspaper Magazines Phonebooks Other Paper Wood Packaging Tile Volume Allen Frisco McKinney , Plano Richardson Total 1, , , Tonnage Allen Frisco McKinney Plano Richardson Total 1, Allen Tonnage FY 05/06 Tonnage 13,165.3 Percent Composition 17.8% 6.5% 2.4% 0.0% 0.0% 0.2% 0.3% 0.1% 0.2% 6.8% 0.3% 13.3% 1.4% 0.0% 0.0% 0.0% 1.5% 4.8% 0.2% FY 05/06 Composition 2, , Frisco Tonnage FY 05/06 Tonnage 23,172.8 Percent Composition 25.8% 9.5% 0.9% 1.7% 0.0% 0.1% 0.1% 0.0% 0.2% 7.0% 0.1% 5.9% 0.0% 0.0% 0.0% 0.0% 0.9% 3.0% 0.2% FY 05/06 Composition 5, , , , McKinney Tonnage FY 05/06 Tonnage 68,148.7 Percent Composition 30.7% 6.3% 0.1% 0.3% 0.0% 0.0% 0.1% 0.0% 0.2% 4.1% 0.3% 4.8% 0.6% 0.0% 0.0% 0.0% 1.8% 2.5% 0.2% FY 05/06 Composition 20, , , , , , Plano Tonnage FY 05/06 Tonnage 11,436.0 Percent Composition 17.6% 8.4% 0.3% 0.8% 0.0% 0.2% 0.2% 0.0% 0.3% 9.3% 1.0% 9.0% 0.1% 0.1% 0.0% 0.0% 0.9% 4.1% 1.2% FY 05/06 Composition 2, , , Richardson Tonnage FY 05/06 Tonnage 10,618.5 Percent Composition 44.9% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% FY 05/06 Composition 4, Total Tonnage 36, , , , , , Treated Wood Page 1 of 2

66 Appendix A - Detail Waste Composition Data Volume Allen Frisco McKinney Plano Richardson Total Tonnage Allen Frisco McKinney Plano Richardson Total Allen Tonnage FY 05/06 Tonnage Percent Composition FY 05/06 Composition Frisco Tonnage FY 05/06 Tonnage Percent Composition FY 05/06 Composition McKinney Tonnage FY 05/06 Tonnage Percent Composition FY 05/06 Composition Plano Tonnage FY 05/06 Tonnage Percent Composition FY 05/06 Composition Richardson Tonnage FY 05/06 Tonnage Percent Composition FY 05/06 Composition Total Tonnage Wood Furniture Painted Wood Brush Scrap Lumber Glass Bottles Glass Windows Other Glass Drywall/ Gypsum Roofing Carpet Yard Waste Furniture Tires Asphalt Refuse Ceiling Tiles Dirt Insulation Other Materials , , , , , , , , , , % 0.4% 0.9% 10.0% 0.0% 1.0% 2.9% 5.7% 0.0% 2.1% 0.2% 0.0% 0.0% 4.2% 5.2% 0.2% 7.0% 0.1% 2.4% 100.0% , , % 0.2% 1.6% 7.4% 0.0% 0.1% 0.1% 6.0% 0.4% 0.3% 0.3% 0.1% 0.0% 4.5% 0.9% 0.4% 20.6% 0.2% 1.1% 100.0% , , , , , % 0.6% 4.8% 6.2% 0.0% 0.1% 0.2% 2.1% 1.2% 0.1% 0.4% 0.1% 0.0% 5.7% 1.5% 0.1% 23.8% 0.1% 0.7% 100.0% , , , , , , , % 1.0% 0.9% 19.0% 0.0% 0.7% 0.0% 12.3% 1.7% 0.8% 0.5% 0.0% 0.0% 0.0% 1.1% 0.2% 6.8% 0.1% 1.0% 100.0% , , , % 0.0% 3.9% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 12.7% 0.0% 0.0% 38.4% 0.0% 0.1% 100.0% , , , , , , , , , , , ,541.2 Total Page 2 of 2

67 Appendix B Population, Employment, and Waste Projections

68 (This page intentionally left blank)

69 Appendix B - Population, Employment, and Waste Projections Allen Population 77,947 79,570 81,193 82,816 84,439 86,062 87,391 88,719 90,048 91,376 92,705 93,231 93,757 94,282 Employment 14,958 16,264 17,570 18,875 20,181 21,487 23,784 26,081 28,377 30,674 32,971 34,402 35,833 37,263 Frisco Population 80,969 87,320 93, , , , , , , , , , , ,050 Employment 13,867 15,080 16,293 17,506 18,719 19,932 22,336 24,740 27,143 29,547 31,951 34,085 36,219 38,352 McKinney Population 83,678 88,116 92,554 96, , , , , , , , , , ,504 Employment 33,410 34,766 36,122 37,477 38,833 40,189 41,968 43,747 45,525 47,304 49,083 50,529 51,975 53,420 Plano Population 245, , , , , , , , , , , , , ,882 Employment 124, , , , , , , , , , , , , ,392 Richardson Population 101, , , , , , , , , , , , , ,654 Employment 110, , , , , , , , , , , , , ,324 Page 1 of 2

70 Appendix B - Population, Employment, and Waste Projections Allen Population Employment Frisco Population Employment McKinney Population Employment Plano Population Employment Richardson Population Employment ,808 95,334 95,828 96,322 96,815 97,309 97,803 98,109 38,694 40,125 40,743 41,360 41,978 42,595 43,213 43, , , , , , , , ,941 40,486 42,620 44,557 46,495 48,432 50,370 52,307 53, , , , , , , , ,494 54,866 56,312 57,970 59,628 61,287 62,945 64,603 66, , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , ,619 Page 2 of 2

71 Appendix B - Population, Employment, and Waste Projections C&D Waste Projections (values in tons) Concrete/Cement 36,019 37,651 39,282 40,913 42,544 44,779 47,014 49,249 51,484 53,719 55,608 57,497 59,386 61,274 63,163 65,387 67,611 69,835 72,059 74,283 76,033 Bricks/Cinder Blocks 8,283 8,718 9,153 9,588 10,022 10,724 11,425 12,127 12,828 13,529 14,107 14,684 15,261 15,838 16,415 16,974 17,533 18,091 18,650 19,209 19,694 Tile ,031 1,110 1,189 1,248 1,306 1,364 1,423 1,481 1,521 1,561 1,602 1,642 1,682 1,711 Other Masonry ,049 1,126 1,204 1,281 1,348 1,416 1,484 1,551 1,619 1,684 1,749 1,814 1,879 1,944 1,995 Plastic Bottles Buckets Film Polystyrene Foam Other Plastic Ferrous Metal 6,369 6,699 7,029 7,359 7,689 8,225 8,760 9,296 9,831 10,367 10,799 11,232 11,664 12,097 12,529 12,930 13,331 13,731 14,132 14,533 14,875 Non-Ferrous Metal Corrugated Cardboard 7,429 7,821 8,213 8,606 8,998 9,636 10,273 10,911 11,549 12,186 12,676 13,165 13,655 14,144 14,634 15,054 15,474 15,894 16,314 16,734 17,106 Office Paper ,030 1,065 1,099 1,133 1,168 1,196 1,223 1,251 1,279 1,307 1,336 Newspaper Magazines Phonebooks Other Paper 1,700 1,780 1,861 1,941 2,021 2,143 2,265 2,387 2,509 2,631 2,727 2,824 2,920 3,016 3,112 3,204 3,296 3,387 3,479 3,571 3,663 Wood Packaging 3,464 3,644 3,824 4,004 4,184 4,473 4,763 5,053 5,343 5,633 5,860 6,087 6,315 6,542 6,770 6,974 7,178 7,383 7,587 7,791 7,975 Treated Wood Wood Furniture ,012 1,057 1,102 1,148 1,193 1,239 1,272 1,305 1,339 1,372 1,406 1,432 Painted Wood ,011 1,040 1,070 1,100 1,130 1,160 1,190 1,221 Brush 4,235 4,420 4,605 4,789 4,974 5,222 5,471 5,719 5,968 6,216 6,425 6,633 6,842 7,050 7,259 7,519 7,780 8,041 8,302 8,562 8,784 Scrap Lumber 9,394 9,836 10,278 10,721 11,163 11,843 12,522 13,202 13,882 14,561 15,105 15,649 16,193 16,737 17,281 17,808 18,335 18,863 19,390 19,917 20,368 Glass Bottles Glass Windows Other Glass ,027 1,069 1,111 1,153 1,196 1,238 1,262 1,286 1,310 1,334 1,358 1,378 Drywall/Gypsum 4,959 5,201 5,443 5,684 5,926 6,322 6,719 7,116 7,512 7,909 8,232 8,555 8,878 9,201 9,524 9,827 10,129 10,432 10,734 11,036 11,284 Roofing 1,111 1,153 1,195 1,237 1,279 1,334 1,389 1,444 1,500 1,555 1,601 1,647 1,693 1,739 1,786 1,838 1,890 1,942 1,994 2,046 2,103 Carpet ,036 1,073 1,097 1,121 1,145 1,169 1,193 1,211 Yard Waste ,015 1,041 Furniture Tires Asphalt 6,830 7,120 7,409 7,698 7,987 8,354 8,720 9,086 9,452 9,818 10,136 10,454 10,772 11,089 11,407 11,823 12,239 12,655 13,070 13,486 13,789 Refuse 2,051 2,165 2,279 2,393 2,507 2,690 2,874 3,057 3,240 3,424 3,557 3,691 3,825 3,959 4,093 4,199 4,306 4,413 4,519 4,626 4,722 Ceiling Tiles Dirt 26,739 27,974 29,210 30,445 31,681 33,303 34,925 36,548 38,170 39,792 41,202 42,611 44,020 45,430 46,839 48,609 50,378 52,148 53,918 55,687 57,004 Insulation Other Materials 1,186 1,253 1,320 1,387 1,455 1,564 1,673 1,783 1,892 2,002 2,086 2,169 2,253 2,337 2,421 2,492 2,563 2,634 2,705 2,776 2,836 Total 126, , , , , , , , , , , , , , , , , , , , ,282

72 (This page intentionally left blank)

73 Appendix C Conceptual Design Sketches

74 (This page intentionally left blank)

75 SITE BOUNDARY INCOMING TRAFFIC C&D MATERIAL PROCESSING BELOW GRADE LOADING HEAVY FRACTION PROCESSING AREA RETENTION POND 360 AREA RETENTION POND 4 OUTGOING TRAFFIC Legend: 1 OPTIONAL SUPPORT BUILDING 2 BALE STORAGE 3 MULCH STORAGE 4 LOADING RAMP FOR BALES 5 RESTROOM / BREAK ROOM PERSONNEL DOOR OVERHEAD ROLLUP DOOR OVERALL SITE PLAN CONCEPTUAL DESIGN Scale Feet North Central Texas Council of Governments C & D Material Recovery Facility Feasibility Study

76 BELOW GRADE LOADING AREA Legend: 1 PROCESS EQUIPMENT BALE STORAGE 3 MULCH STORAGE LOADING RAMP FOR BALES RESTROOM / BREAK ROOM FERROUS SCRAP BALER TEMPORARY STORAGE SPACE 4 9 INCOMING MATERIAL STORAGE 10 RESIDUAL WOOD GRINDING AREA MAGNETIC SEPARATOR PERSONNEL DOOR OVERHEAD ROLLUP DOOR C&D MATERIAL PROCESSING CONCEPTUAL DESIGN North Central Texas Council of Governments C & D Material Recovery Facility Feasibility Study Scale Feet

77 BELOW GRADE LOADING AREA Legend: 1 STORAGE BUNKERS 2 CRUSHED MATERIAL 3 INCOMING HEAVY MATERIAL 4 MAGNETIC SEPARATOR 5 SCREEN 6 FERROUS SCRAP 7 RECIRCULATION CONVEYOR 8 CRUSHER 9 10 FEED CONVEYOR & SCREEN RESIDUAL SCREEN MATERIAL HEAVY FRACTION PROCESSING AREA CONCEPTUAL DESIGN North Central Texas Council of Governments C & D Material Recovery Facility Feasibility Study Scale Feet

78 ISO VIEW CONCEPTUAL DESIGN North Central Texas Council of Governments C & D Material Recovery Facility Feasibility Study

79 VIEW A-A CONCEPTUAL DESIGN Scale Feet VIEW B-B CONCEPTUAL DESIGN Scale Feet North Central Texas Council of Governments C & D Material Recovery Facility Feasibility Study

Economic Impact of Recycling in Alabama and Opportunities for Growth. Alabama Department of Environmental Management. Land Division Solid Waste Branch

Economic Impact of Recycling in Alabama and Opportunities for Growth. Alabama Department of Environmental Management. Land Division Solid Waste Branch Economic Impact of Recycling in Alabama and Opportunities for Growth Alabama Department of Environmental Management Land Division Solid Waste Branch June 2012 Alabama Department of Environmental Management

More information

CONSTRUCTION WASTE MANAGEMENT PLAN

CONSTRUCTION WASTE MANAGEMENT PLAN CONSTRUCTION WASTE MANAGEMENT PLAN Project: Construction Manager: Location: Prepared by: PREMIER FACILITY MANAGEMENT (PFM) Date: I. OBJECTIVES The objectives of this plan are to: 1. Recycle, reuse or salvage

More information

Consulting Services in Support of Resource Recovery Planning and Implementation

Consulting Services in Support of Resource Recovery Planning and Implementation FINAL REPORT MAY 2014 CITY OF DALLAS SANITATION SERVICES Consulting Services in Support of Resource Recovery Planning and Implementation Consulting Services in Support of Resource Recovery Planning and

More information

CITY OF FONTANA COMMUNITY DEVELOPMENT DEPARTMENT Building and Safety Division Construction Waste Management Plan (CWMP) (Provide During Plan Review)

CITY OF FONTANA COMMUNITY DEVELOPMENT DEPARTMENT Building and Safety Division Construction Waste Management Plan (CWMP) (Provide During Plan Review) CITY OF FONTANA COMMUNITY DEVELOPMENT DEPARTMENT Building and Safety Division Construction Waste Management Plan (CWMP) (Provide During Plan Review) Building permit applicants must prepare a Construction

More information

Fauquier County Department of Environmental Services

Fauquier County Department of Environmental Services Fauquier County Department of Environmental Services W. Nathaniel Townley Commodity Coordinator Former Chairman VRA C&D Committee Building Contractor Phone : 540-347-6811 Mobile : 540-631-4321 Fax : 540-341-7129

More information

Appendix M-2 Example Specification Language for Construction Waste Management

Appendix M-2 Example Specification Language for Construction Waste Management The State of Minnesota Sustainable Building Guidelines Version 2.1 Appendix M-2 Example Specification Language for Construction Waste Management The following pages show example language that may be of

More information

Tompkins County Solid Waste Management Plan Executive Summary

Tompkins County Solid Waste Management Plan Executive Summary Tompkins County Solid Waste Management Plan Executive Summary Tompkins County has prepared a comprehensive, twenty-year Solid Waste Management Plan to comply with the requirements of the Solid Waste Management

More information

C & D Processing & Shingle Recycling

C & D Processing & Shingle Recycling C & D Processing & Shingle Recycling SWMCB Pre Demo Workshop March 31, 2017 Ben Wetzell Waste Services Manager 1967 Corvair Landfill Established 1985 (Louisville Landfill 1965), 120 Acre Site Subtitle

More information

Northeast Recycling Council

Northeast Recycling Council Presented at: Northeast Recycling Council October 2008 Presented By: Greg Wirsen CMRA Northeast Chapter Director www.gseenv.com 1 This Presentation What is the CMRA and what do we do? C&D Commodities Individual

More information

Oconee County Solid Waste

Oconee County Solid Waste C&D DEBRIS GUIDEBOOK Oconee County Solid Waste Roughly 80% of a home builder s waste stream is recyclable, and contractors are partially liable for waste generated at jobsites. Date: 07/01/04 Waste Generation

More information

Contribution of the Recycling Industry to the Local Economy. What Input-Output Models Show

Contribution of the Recycling Industry to the Local Economy. What Input-Output Models Show Contribution of the Recycling Industry to the Local Economy What Input-Output Models Show Carolina Recycling Association Annual Conference April 3, 2014 1 Jobs Associated with Recycling Industries Establishments

More information

2015 Demolition, Land-clearing, and Construction Waste Composition Monitoring Program

2015 Demolition, Land-clearing, and Construction Waste Composition Monitoring Program 2015 Demolition, Land-clearing, and Construction Waste Composition Monitoring Program PRESENTED TO Metro Vancouver JANUARY 11, 2016 ISSUED FOR USE FILE: SWM.SWOP03008-01 Tetra Tech EBA Inc. Suite 1000

More information

H 7033 SUBSTITUTE A AS AMENDED ======== LC003107/SUB A ======== S T A T E O F R H O D E I S L A N D

H 7033 SUBSTITUTE A AS AMENDED ======== LC003107/SUB A ======== S T A T E O F R H O D E I S L A N D 01 -- H 0 SUBSTITUTE A AS AMENDED LC00/SUB A S T A T E O F R H O D E I S L A N D IN GENERAL ASSEMBLY JANUARY SESSION, A.D. 01 A N A C T RELATING TO HEALTH AND SAFETY -- FOOD RESIDUALS RECYCLING Introduced

More information

Construction and Demolition Material Recycling Program

Construction and Demolition Material Recycling Program Construction and Demolition Material Recycling Program WMAC Meeting June 26, 2012 Purpose As part of the Waste Management Advisory Committee s (WMAC) defined role and associated task/project document:

More information

City of Tustin Construction and Demolition Debris Recycling Requirements

City of Tustin Construction and Demolition Debris Recycling Requirements City of Tustin Construction and Demolition Debris Recycling Requirements The California Green Building Standards Code requires project applicants to recycle or divert from landfills at least 65% of the

More information

Developing a Zero Waste Implementation Plan, Montgomery County, MD MRN/SWANA-MidAtlantic Annual Conference Maryland Recycling Network

Developing a Zero Waste Implementation Plan, Montgomery County, MD MRN/SWANA-MidAtlantic Annual Conference Maryland Recycling Network Developing a Zero Waste Implementation Plan, Montgomery County, MD 2014 MRN/SWANA-MidAtlantic Annual Conference Maryland Recycling Network Bill Davidson, DSWS, June 19, 2014 Key Thoughts Eye on the Ball

More information

APPENDIX B CONSTRUCTION WASTE MANAGEMENT SAMPLE SPECIFICATION

APPENDIX B CONSTRUCTION WASTE MANAGEMENT SAMPLE SPECIFICATION APPENDIX B CONSTRUCTION WASTE MANAGEMENT SAMPLE SPECIFICATION The following appendix includes information and standard drawings that are diagrammatic and are used only to convey intent. Construction Waste

More information

DUKE UNIVERSITY CONSTRUCTION & DESIGN STANDARDS

DUKE UNIVERSITY CONSTRUCTION & DESIGN STANDARDS 1 01 74 00 Cleaning and Waste Management 1. Introduction The University, Durham County, and North Carolina are committed to reducing waste and the use of landfills. Waste reduction and recycling practices

More information

Construction / Demolition (C&D) Recycling Program

Construction / Demolition (C&D) Recycling Program Construction / Demolition (C&D) Recycling Program The State of California requires that all cities in the State divert at least 65% of its waste materials from landfills (AB 939). The City of Stockton

More information

SWANA RECYCLING TECHNICAL ASSISTANCE STUDY PROPOSED BRADFORD COUNTY FIBER PROCESSING FACILTITY

SWANA RECYCLING TECHNICAL ASSISTANCE STUDY PROPOSED BRADFORD COUNTY FIBER PROCESSING FACILTITY SWANA RECYCLING TECHNICAL ASSISTANCE STUDY PROPOSED BRADFORD COUNTY FIBER PROCESSING FACILTITY Prepared for: NORTHERN TIER SOLID WASTE AUTHORITY WEST BURLINGTON TOWNSHIP, BRADFORD COUNTY, PENNSYLVANIA

More information

SECTION CONSTRUCTION WASTE MANAGEMENT. A. Section includes administrative and procedural requirements for Construction Waste Management.

SECTION CONSTRUCTION WASTE MANAGEMENT. A. Section includes administrative and procedural requirements for Construction Waste Management. SECTION 01 35 63 CONSTRUCTION WASTE MANAGEMENT PART 1 - GENERAL 1.1 SUMMARY A. Section includes administrative and procedural requirements for Construction Waste Management. 1.2 DEFINITIONS A. Construction

More information

Arizona Department of Environmental Quality Annual Waste Reduction and Recycling Questionnaire

Arizona Department of Environmental Quality Annual Waste Reduction and Recycling Questionnaire Arizona Department of Environmental Quality Annual Waste Reduction and Recycling Questionnaire Fiscal Year 2000: July 1, 1999 to June 30, 2000 Jurisdiction: This questionnaire contains the following five

More information

MICHIGAN WOOD WASTE A CIRCULAR ECONOMY OPPORTUNITY!

MICHIGAN WOOD WASTE A CIRCULAR ECONOMY OPPORTUNITY! MICHIGAN WOOD WASTE A CIRCULAR ECONOMY OPPORTUNITY! Michigan Forest Bioeconomy Conference February 1-2, 2017 Norman Christopher MSW (Municipal Solid Waste) Food Waste Household and Commercial Waste Packaging

More information

2016/2017 MATERIALS MANAGEMENT CALL FOR PROJECTS PROJECT SUMMARY SLIDE

2016/2017 MATERIALS MANAGEMENT CALL FOR PROJECTS PROJECT SUMMARY SLIDE APPLICANT: City of Denton Solid Waste & Recycling GRANT ADMINISTRATOR: Nicholas Vincent KEY PARTNERS: 2016/2017 MATERIALS MANAGEMENT CALL FOR PROJECTS PROJECT SUMMARY SLIDE PROJECT TITLE: Purchase Slow

More information

Construction and Demolition (C&D) Waste Management Plan Program Requirements

Construction and Demolition (C&D) Waste Management Plan Program Requirements Construction and Demolition (C&D) Waste Management Plan Program Requirements The State of California requires that all cities in the State divert at least 65% of its waste materials from landfills (AB

More information

City of Asheboro. Solid Waste Management Plan. July1, 2010 June 30, 2020

City of Asheboro. Solid Waste Management Plan. July1, 2010 June 30, 2020 City of Asheboro Solid Waste Management Plan July1, 2010 June 30, 2020 INTRODUCTION This plan, which is being submitted, to the Solid Waste Section of the N.C. Department of Environment and Natural Resources,

More information

Quarterly Performance Measurement Report

Quarterly Performance Measurement Report Quarterly Performance Measurement Report Department: Solid Waste and Recycling Services Division: Solid Waste and Recycling Services/Mandatory Collections Section: Municipal Services To provide for the

More information

REPORT TO THE CHIEF ADMINISTRATIVE OFFICER FROM THE PUBLIC WORKS AND UTILITIES DEPARTMENT PROPOSED LANDFILL TIPPING FEE INCREASES

REPORT TO THE CHIEF ADMINISTRATIVE OFFICER FROM THE PUBLIC WORKS AND UTILITIES DEPARTMENT PROPOSED LANDFILL TIPPING FEE INCREASES July 24, 2014 REPORT TO THE CHIEF ADMINISTRATIVE OFFICER FROM THE PUBLIC WORKS AND UTILITIES DEPARTMENT ON PROPOSED LANDFILL TIPPING FEE INCREASES PURPOSE To seek Council's approval to increase tipping

More information

Resource Recovery Planning and Implementation - On the road to Zero Waste

Resource Recovery Planning and Implementation - On the road to Zero Waste Memorandum DATE 6 June 2014 CITY OF DALLAS TO SUBJECT The Honorable Members of the Transportation and Trinity River Project Committee: Vonciel Jones Hill (Chair), Lee Kleinman (Vice Chair), Deputy Mayor

More information

Construction & Demolition Recycling Program Building Contractor s Resource Guide & FAQ s (Revised December 2016)

Construction & Demolition Recycling Program Building Contractor s Resource Guide & FAQ s (Revised December 2016) Construction & Demolition Recycling Program Building Contractor s Resource Guide & FAQ s (Revised December 2016) Table of Contents Frequently Asked Questions 3 List of Organizations & Agencies....7 List

More information

SWANA RECYCLING TECHNICAL ASSISTANCE STUDY SPRINGETTSBURY EVALUATION OF COMMERCIAL RECYCLING PROGRAM AND ALTERNATIVES

SWANA RECYCLING TECHNICAL ASSISTANCE STUDY SPRINGETTSBURY EVALUATION OF COMMERCIAL RECYCLING PROGRAM AND ALTERNATIVES SWANA RECYCLING TECHNICAL ASSISTANCE STUDY SPRINGETTSBURY EVALUATION OF COMMERCIAL RECYCLING PROGRAM AND ALTERNATIVES Prepared for: SPRINGETTSBURY TOWNSHIP, YORK COUNTY, PENNSYLVANIA Prepared by: GANNETT

More information

CITY OF CHICAGO DEPARTMENT OF ENVIRONMENT. CONSTRUCTION or DEMOLITION SITE WASTE RECYCLING RULES AND REGULATIONS

CITY OF CHICAGO DEPARTMENT OF ENVIRONMENT. CONSTRUCTION or DEMOLITION SITE WASTE RECYCLING RULES AND REGULATIONS CITY OF CHICAGO DEPARTMENT OF ENVIRONMENT CONSTRUCTION or DEMOLITION SITE WASTE RECYCLING RULES AND REGULATIONS W hereas, pursuant to Chapters 11-4 and 2-30 of the Municipal Code of Chicago (the Code ),

More information

City of Brisbane Construction and Demolition Debris Recycling and Waste Reduction Plan

City of Brisbane Construction and Demolition Debris Recycling and Waste Reduction Plan City of Brisbane Construction and Demolition Debris Recycling and Waste Reduction Plan This form is to be completed for all demolition, remodel, re-roofing and new construction projects covered by Ordinance

More information

I. INTRODUCTION. Solid waste has been classified into the following categories:

I. INTRODUCTION. Solid waste has been classified into the following categories: I. INTRODUCTION Proper solid waste and hazardous waste management are essential for adequate protection of the County s natural resources and the public health, safety, and welfare. The potential environmental

More information

Construction & Demolition (C&D) Materials Management in the Northeast in 2013 December 7, 2017

Construction & Demolition (C&D) Materials Management in the Northeast in 2013 December 7, 2017 Construction & Demolition (C&D) Materials Management in the Northeast in 2013 December 7, 2017 Prepared by the NEWMOA C&D Materials Management Workgroup State environmental agencies in the Northeast have

More information

WASTE AUDIT AND INVENTORY

WASTE AUDIT AND INVENTORY California State University East Bay WASTE AUDIT AND INVENTORY FINAL REPORT Prepared by Cascadia Consulting Group, Inc. December 17, 2015 EXECUTIVE SUMMARY California State University East Bay (CSU EB)

More information

Table 11: Active C&D Debris Facilities in Florida (November 1998) DISTRICT C&D Disposal Land Clearing Debris Disposal

Table 11: Active C&D Debris Facilities in Florida (November 1998) DISTRICT C&D Disposal Land Clearing Debris Disposal Landfill Disposal Overview In 1980, Florida had approximately 500 open dumps. During this time period, it was a common practice to either burn or use one of these open dumps in order to alleviate the solid

More information

Regional Waste Management/Material Recovery Facility Study Report

Regional Waste Management/Material Recovery Facility Study Report Regional Waste Management/Material Recovery Facility Study Report PRESENTED TO MD of Foothills No. 31 Town of Black Diamond Town of High River Town of Nanton Town of Okotoks Town of Turner Valley MARCH

More information

PLANNING ELEMENTS NC LOCAL GOVERNMENT 10 YEAR SOLID WASTE MANAGEMENT PLAN Check appropriate element PLANNING YEARS 2012 through 2022

PLANNING ELEMENTS NC LOCAL GOVERNMENT 10 YEAR SOLID WASTE MANAGEMENT PLAN Check appropriate element PLANNING YEARS 2012 through 2022 Residential continuing to use education process through literature. Also, landfill staff refers to available resources, such as NC DEAO. Several municipalities offer tips in their quarterly newsletters

More information

Construction Waste Minimization and Reuse Management

Construction Waste Minimization and Reuse Management Construction Waste Minimization and Reuse Management Mr.M.KalilurRahman 1, Mr.S.S.Janagan 2 1 Student M.E., (CE&M), Gnanamani College of Engineering, Namakkal-637018, Tamilnadu, India 2 Assistant Prof,

More information

SHELBY COUNTY COMMISSION SOLID WASTE MANAGEMENT PLAN ADOPTED BY THE SHELBY COUNTY COMMISSION

SHELBY COUNTY COMMISSION SOLID WASTE MANAGEMENT PLAN ADOPTED BY THE SHELBY COUNTY COMMISSION SHELBY COUNTY COMMISSION SOLID WASTE MANAGEMENT PLAN ADOPTED BY THE SHELBY COUNTY COMMISSION 04-13-2015 Table of Contents 1.0 County Statistics. 2 2.0 Solid Waste Generation 5 2.1 Projected Future Waste

More information

Recover Your Resources. Reduce, Reuse, and Recycle Construction and Demolition Materials at Land Revitalization Projects

Recover Your Resources. Reduce, Reuse, and Recycle Construction and Demolition Materials at Land Revitalization Projects Recover Your Resources Reduce, Reuse, and Recycle Construction and Demolition Materials at Land Revitalization Projects What s in Your Dumpster? Don t waste your resources Sustainable reuse of brownfield

More information

MATERIALS AND RESOURCES

MATERIALS AND RESOURCES MATERIALS AND RESOURCES MR- P1: STORAGE AND COLLECTION OF RECYCLABLES To reduce the waste that is generated by building occupants and hauled to and disposed of in landfills. PREREQUISITE REQUIREMENTS Provide

More information

A. IEMA ten day notification for demolition provisions as necessary. C. IEPA Uncontaminated Soil Certification LPC 663

A. IEMA ten day notification for demolition provisions as necessary. C. IEPA Uncontaminated Soil Certification LPC 663 August 2013, Rev 00 01 7419 Construction Waste Management PART 1. GENERAL 1.01 Requirements Include: A. Each Contractor provide: 1. Participation in Construction Waste Management plan, including separation

More information

Construction & Demolition Waste Management Plan Resource Guide for Contractors

Construction & Demolition Waste Management Plan Resource Guide for Contractors Construction & Demolition Waste Management Plan Resource Guide for Contractors Environmental Utilities Solid Waste Division 2005 Hilltop Circle Roseville, California 95747 916-774-5780 916-774-5798 fax

More information

Lane Wasteshed 2010 Recovery Plan Update

Lane Wasteshed 2010 Recovery Plan Update Lane Wasteshed 2010 Recovery Plan Update January 16, 2013 To: Mr. Craig C. Filip Solid Waste Reduction Analyst Oregon Department of Environmental Quality filip.craig@deq.state.or.us Submitted by: Sarah

More information

INFORMATION SHEET. To demolish the entire building to the foundation will require a demolition permit (Form 6).

INFORMATION SHEET. To demolish the entire building to the foundation will require a demolition permit (Form 6). City and County of San Francisco Department of Building Inspection Edwin M. Lee, Mayor Tom C. Hui, S.E., C.B.O., Director INFORMATION SHEET NO. 5-04 DATE CATEGORY SUBJECT : June 22, 2015 Structural Demolition

More information

mendi ing th t e S ource Separation Ordinance

mendi ing th t e S ource Separation Ordinance Amending the Source Separation Ordinance In Mecklenburg County January 22, 2013 This is a business recycling law, which was adopted by the Board of County Commissioners and all seven municipalities, requiring

More information

2013 Statewide Waste Characterization

2013 Statewide Waste Characterization Final Report 2013 Statewide Waste Characterization Minnesota Pollution Control Agency December 2013 2013 Statewide Waste Characterization prepared for Minnesota Pollution Control Agency St. Paul, Minnesota

More information

Establishing a Green Deconstruction Project. Presenter: Barry J. Franz, PE, BCEE, PG, CP (119) Environmental Director

Establishing a Green Deconstruction Project. Presenter: Barry J. Franz, PE, BCEE, PG, CP (119) Environmental Director Establishing a Green Deconstruction Project Presenter: Barry J. Franz, PE, BCEE, PG, CP (119) Environmental Director Objectives of Presentation Define green deconstruction. Provide background for green

More information

Sustainable Alternatives to Building Demolition

Sustainable Alternatives to Building Demolition Sustainable Alternatives to Building Demolition 2005 States Solid Waste Conference Phoenix, AZ It s Not Just Garbage Anymore Tom Napier Construction Engineering Research Laboratory Champaign, IL WHAT CAUSES

More information

CURRENT STATE OF CONSTRUCTION WASTE IN THE CITY OF CAPE TOWN. A VAN VUUREN / 16 September 2014

CURRENT STATE OF CONSTRUCTION WASTE IN THE CITY OF CAPE TOWN. A VAN VUUREN / 16 September 2014 CURRENT STATE OF CONSTRUCTION WASTE IN THE CITY OF CAPE TOWN A VAN VUUREN / 16 September 2014 THE CAPE TOWN WE LOVE OTHER IMAGES OF OUR CITY ILLEGAL DUMPING IS A REALITY During 2013: There were more than

More information

IWRC. Member Survey Report 1 PROCESSING ~ Making Recycling Work. September 1990 REMANUFACTURING. Waste Recyclers Council

IWRC. Member Survey Report 1 PROCESSING ~ Making Recycling Work. September 1990 REMANUFACTURING. Waste Recyclers Council - IWRC Waste Recyclers Council Member Survey Report 1 PROCESSING ~ REMANUFACTURING Making Recycling Work September 1990 9 Million Tons of Material Handled by WRC In 1989 In 1989, members of the Waste

More information

Construction Wood Debris Recycling Pilot Project Report. Natural Resources Department December 2000

Construction Wood Debris Recycling Pilot Project Report. Natural Resources Department December 2000 Construction Wood Debris Recycling Pilot Project Report Natural Resources Department December 2000 TABLE OF CONTENTS I. EXECUTIVE SUMMARY...1 II. PROJECT BACKGROUND...1 III. PILOT PROJECT DESIGN...2 IMAGE

More information

CT Department of Environmental Protection. Getting SMART Waste Management to Reduce Disposal & Increase Recycling

CT Department of Environmental Protection. Getting SMART Waste Management to Reduce Disposal & Increase Recycling CT Department of Environmental Protection Getting SMART Waste Management to Reduce Disposal & Increase Recycling Resource Conservation Challenge Workshop March 25, 2009 Municipal Unit Based Pricing Programs

More information

CASE. Recycling capacity in Chicagoland gets a significant boost from Lakeshore Recycling Systems Heartland material recovery facility

CASE. Recycling capacity in Chicagoland gets a significant boost from Lakeshore Recycling Systems Heartland material recovery facility CASE Recycling capacity in Chicagoland gets a significant boost from Lakeshore Recycling Systems Heartland material recovery facility SUMMARY BORROWER LAKESHORE RECYCLING SYSTEMS (IL) PORTFOLIO AREA SORTATION

More information

Evaluation of Enhanced Residential Waste and Recyclables Collection and Processing for New Castle County

Evaluation of Enhanced Residential Waste and Recyclables Collection and Processing for New Castle County Evaluation of Enhanced Residential Waste and Recyclables Collection and Processing for New Castle County FINAL REPORT OCTOBER 15, 2003 Presented to Delaware Recycling Public Advisory Council Prepared by:

More information

CONTAINER REDEMPTION SYSTEM OPTIMIZATION STUDY

CONTAINER REDEMPTION SYSTEM OPTIMIZATION STUDY January 14 th, 2014 CONTAINER REDEMPTION SYSTEM OPTIMIZATION STUDY Commissioned by the Glass Packaging Institute with the engagement from other stakeholders in the beverage container recycling industry

More information

Recycle Clark County LLC. Prepared By: Michael Snoddy, SC Kevin Dewey, MBA, PMP

Recycle Clark County LLC. Prepared By: Michael Snoddy, SC Kevin Dewey, MBA, PMP 2013-2014 Recycle Clark County LLC. Prepared By: Michael Snoddy, SC Kevin Dewey, MBA, PMP 1 2013-2014 Contents Recycle Clark County is a solid waste transfer station.... 3 Why do waste haulers prefer Recycle

More information

CONSTRUCTION AND DEMOLITION PERMIT APPLICATION PACKAGE

CONSTRUCTION AND DEMOLITION PERMIT APPLICATION PACKAGE CONSTRUCTION AND DEMOLITION PERMIT APPLICATION PACKAGE CITY OF RANCHO SANTA MARGARITA 22112 El Paseo Rancho Santa Margarita, CA 92688 (949) 635-1800 x 6506 Revised July 2017 Construction and Demolition

More information

Summary of Key Results

Summary of Key Results Attachment 1 Summary of Key Results The 2016 Waste Characterization Study involved an extensive year-long process that produced a precise estimate of waste quantity and waste composition. Methods used

More information

ATTACHMENT N LEED PROJECT PROCEDURES

ATTACHMENT N LEED PROJECT PROCEDURES ATTACHMENT N LEED PROJECT PROCEDURES 1. All subcontractors, sub-subcontractors and suppliers at all tiers are to include the following items in their trade scope of work: a. Submit data and documentation

More information

Integrating Deconstruction and Recycling Into the Demolition Process in Buffalo, NY

Integrating Deconstruction and Recycling Into the Demolition Process in Buffalo, NY Cornell University ILR School DigitalCommons@ILR Buffalo Commons Centers, Institutes, Programs 2007 Integrating Deconstruction and Recycling Into the Demolition Process in Buffalo, NY Tara Stahl Follow

More information

Source Reduction, Recycling, Composting, and Disposal Information and Worksheets

Source Reduction, Recycling, Composting, and Disposal Information and Worksheets Source Reduction, Recycling, Composting, and Disposal Information and Worksheets These pages contain helpful background information and instructions. You are encouraged to read through them and complete

More information

6.20 UTILITIES SOLID WASTE

6.20 UTILITIES SOLID WASTE 6.20 UTILITIES SOLID WASTE 6.20.1 OVERVIEW AND SUMMARY Solid waste generated by the proposed project would be disposed primarily at the Toland Road Landfill. Prior to disposal, recyclable materials would

More information

DECONSTRUCTION OPPORTUNITIES FOR SALVAGE, REUSE & RECYCLING. Northeast Recycling Council Inc. Spring Conference EPA Region III, March 2006.

DECONSTRUCTION OPPORTUNITIES FOR SALVAGE, REUSE & RECYCLING. Northeast Recycling Council Inc. Spring Conference EPA Region III, March 2006. DECONSTRUCTION OPPORTUNITIES FOR SALVAGE, REUSE & RECYCLING Northeast Recycling Council Inc. Spring Conference EPA Region III, March 2006 Tom Napier Construction Engineering Research Laboratory Champaign,

More information

TABLE OF CONTENTS. 1.1 General Background Waste Diversion Waste Disposal WASTE COLLECTION AND DISPOSAL...

TABLE OF CONTENTS. 1.1 General Background Waste Diversion Waste Disposal WASTE COLLECTION AND DISPOSAL... Draft Environmental Assessment Terms of Reference Supplementary Document Waste Management System Summary TABLE OF CONTENTS 1. INTRODUCTION...1 1.1 General...1 1.2 Background...1 1.3 Waste Diversion...1

More information

Sanitation Services Bulk and Brush Program - Update. Quality of Life & Environment Committee November 14, 2016

Sanitation Services Bulk and Brush Program - Update. Quality of Life & Environment Committee November 14, 2016 Sanitation Services Bulk and Brush Program - Update Quality of Life & Environment Committee November 14, 2016 Briefing Overview Provide a recap of the current collection program Provide information related

More information

Fairfield County General Health District Comprehensive Solid Waste Regulations

Fairfield County General Health District Comprehensive Solid Waste Regulations Fairfield County General Health District Comprehensive Solid Waste Regulations Adopted August 10, 2016. FAIRFIELD COUNTY DISTRICT BOARD OF HEALTH COMPREHENSIVE SOLID WASTE REGULATIONS DEFINITIONS... 1-4

More information

CITY OF ALISO VIEJO CONSTRUCTION AND DEMOLITION DOCUMENTATION

CITY OF ALISO VIEJO CONSTRUCTION AND DEMOLITION DOCUMENTATION CITY OF ALISO VIEJO CONSTRUCTION AND DEMOLITION DOCUMENTATION This document includes the following: Section I: Construction and Demolition Recycling Requirements... Page 1 Section II: Compliance Form..Page

More information

Recycling Markets and Opportunities for Local Government Recycling Program Expansion

Recycling Markets and Opportunities for Local Government Recycling Program Expansion Recycling Markets and Opportunities for Local Government Recycling Program Expansion Overview It is commonly argued that there are limits to recycling because of lack of markets or weakness in markets.

More information

GRC 20 th Annual Conference

GRC 20 th Annual Conference Salvaging Recycling, New Developments in Construction and Demolition Materials Andy Lake CSI NDA CMRA Recycling Infrastructure Process Specialist ABP Technology Armstrong World Industries GRC 20 th Annual

More information

BOMA BEST Sustainable Buildings 3.0 Waste Auditing Requirements

BOMA BEST Sustainable Buildings 3.0 Waste Auditing Requirements BOMA BEST Sustainable Buildings 3.0 Waste Auditing Requirements This document provides the requirements for completing an audit compliant with the BEST Practice. For a more comprehensive description of

More information

C&D/wood debris management trends

C&D/wood debris management trends C&D/wood debris management trends by Peter Yost P romising C&D debris recovery results are beginning in the residential sector As the field of construction and demolition debris management develops, new

More information

Jim Penor, Solid Waste Coordinator Stuart Ashton, Solid Waste Assistant Michele Elfers, Program Manager

Jim Penor, Solid Waste Coordinator Stuart Ashton, Solid Waste Assistant Michele Elfers, Program Manager The RecycleWorks program develops and implements Recycling, Household Hazardous Waste, Junk Vehicle and Organics Management programs for the City and Borough of Juneau to protect the health and safety

More information

MEMORANDUM. Introduction. Enabling Legislation

MEMORANDUM. Introduction. Enabling Legislation To: Jan McHargue, Winston-Salem/Forsyth County Utility Commission From: Abby M. Goldsmith, R. W. Beck, An SAIC Company Subject: Solid Waste Management Authorities Date: Introduction Currently, the Winston-Salem/Forsyth

More information

Town of The Blue Mountains Waste Diversion Plan

Town of The Blue Mountains Waste Diversion Plan Report on Waste Diversion Plan Completed by: Adam McMullin Environmental Initiatives Coordinator October 2012 This Project has been delivered with the assistance of Waste Diversion Ontario s Continuous

More information

ARCHITECTURE/ ENGINEERING

ARCHITECTURE/ ENGINEERING S ARCHITECTURE/ ENGINEERING NOVEMBER 25, 2013 CITY OF EL CENTRO COUNCIL CHAMBERS ADA RENOVATION ADDENDUM #02 All documents referenced in this addendum are available in electronic format at ftp site listed

More information

Builder Agreement. Access to build in Mountainside Village constitutes agreement to abide by the following:

Builder Agreement. Access to build in Mountainside Village constitutes agreement to abide by the following: Builder Agreement Access to build in Mountainside Village constitutes agreement to abide by the following: 1. It shall be the responsibility of each builder in Mountainside Village ( Builder ) that the

More information

RESIDENTIAL WASTE DIVERSION STRATEGY November 30, 2015

RESIDENTIAL WASTE DIVERSION STRATEGY November 30, 2015 RESIDENTIAL WASTE DIVERSION STRATEGY November 30, 2015 Waste & Recycling Services Table of Contents WHY DO WE NEED A STRATEGY?...2 WHAT ARE WE WASTING?...4 WHAT ARE WE DIVERTING?...5 WHAT COULD WE DO

More information

Quarterly Performance Measurement Report

Quarterly Performance Measurement Report Quarterly Performance Measurement Report Department: Solid Waste and Recycling Services Division: Solid Waste and Recycling Services/Mandatory Collections Section: Municipal Services To provide for the

More information

Recycling and Waste Minimization Case Studies

Recycling and Waste Minimization Case Studies PREPARED FOR: HOUSTON-GALVESTON AREA COUNCIL Recycling and Waste Minimization Case Studies Report February 2008 This study was funded through a solid waste management grant provided by the Texas Commission

More information

City of South San Francisco Construction and Demolition Waste Management Plan Information for the Applicants

City of South San Francisco Construction and Demolition Waste Management Plan Information for the Applicants City of South San Francisco Construction and Demolition Waste Management Plan Information for the Applicants General The City of South San Francisco is mandated by the State of California to divert 65

More information

Zack Hansen and Judy Hunter Ramsey/Washington Counties Resource Recovery Board Joint Staff Committee

Zack Hansen and Judy Hunter Ramsey/Washington Counties Resource Recovery Board Joint Staff Committee Memorandum Foth Infrastructure & Environment, LLC Eagle Point II 8550 Hudson Blvd. North, Suite 105 Lake Elmo, MN 55042 (651) 288-8550 Fax: (651) 288-8551 www.foth.com April 18, 2014 TO: CC: FR: RE: Zack

More information

Opportunities for the Woodwaste Resource By Bob Falk

Opportunities for the Woodwaste Resource By Bob Falk Opportunities for the Woodwaste Resource By Bob Falk For most of us, the word recycling conjures up visions of curbside programs focused on collecting glass bottles, aluminum cans, plastic jugs, and old

More information

Lincoln County. Solid Waste Management Plan

Lincoln County. Solid Waste Management Plan Lincoln County Solid Waste Management Plan 3 Year Update Plan Effective July 1, 2012 June 30, 2022 For Lincoln County City of Lincolnton Revised June 28, 2012 Table of Contents Sections Page Section 1

More information

Mecklenburg County Solid Waste Management Plan Public Meeting Tuesday, April 17 th

Mecklenburg County Solid Waste Management Plan Public Meeting Tuesday, April 17 th Mecklenburg County Solid Waste Management Plan 2012 Public Meeting Tuesday, April 17 th Why do we Plan? A requirement of the North Carolina Solid Waste Management Act of 1996 (NCGS 130A 309.09A) County

More information

Considerations for a Statewide Container Recycling Refund Program. cmconsultinginc.com

Considerations for a Statewide Container Recycling Refund Program. cmconsultinginc.com Considerations for a Statewide Container Recycling Refund Program cmconsultinginc.com In business since 1998, Ontario, Canada What we do: Environmental research and report writing Stewardship program planning

More information

5.1 Description of the County

5.1 Description of the County Section 5 ELBERT COUNTY 5.1 Description of the County 5.1.1 Background Elbert County is located on the eastern edge of the planning area, on the border of South Carolina. The County covers approximately

More information

5-Year Audit Program Assessment Revised Final Report

5-Year Audit Program Assessment Revised Final Report Alameda County Source Reduction and Recycling Board 5-Year Audit Program Assessment Revised Final Report HF&H Consultants, LLC Kies Strategies Skumatz Economic Research Associates Environmental Planning

More information

ECONOMIC FACTS AND PERFORMANCE

ECONOMIC FACTS AND PERFORMANCE RECYCLING ECONOMIC FACTS AND PERFORMANCE JAMES J. BINDER AND PATRICK J. CALPIN Alternative Resources, Inc. Concord, Massachusetts ABSTRACT As the recycling ethic takes hold at the state and municipal level,

More information

Materials Management Methodology Draft Agreements

Materials Management Methodology Draft Agreements Materials Management Methodology Draft Agreements Developed by a Committee of CO, MT, ND, SD, UT, and WY State offices and Recycling Association representatives. 8/19/2011 1 Origin of Materials Management

More information

DESCRIPTION OF RECYCLING AND REUSE BUSINESS CATEGORIES

DESCRIPTION OF RECYCLING AND REUSE BUSINESS CATEGORIES APPENDIX A DESCRIPTION OF RECYCLING AND REUSE BUSINESS CATEGORIES Table A-1 provides detailed descriptions of 45 recycling and reuse business categories, grouped into 5 industry segments. The table is

More information

ANNE ARUNDEL COUNTY Waste Management Services SWANA PRESENTATION

ANNE ARUNDEL COUNTY Waste Management Services SWANA PRESENTATION ANNE ARUNDEL COUNTY Waste Management Services SWANA PRESENTATION By: Linda K. Currier, Solid Waste Operations Administrator 1 Waste Management Services Operation 1 large, active landfill 2 smaller closed

More information

A SYSTEM FOR ESTIMATING RESIDENTIAL CONSTRUCTION AND DEMOLITION DEBRIS

A SYSTEM FOR ESTIMATING RESIDENTIAL CONSTRUCTION AND DEMOLITION DEBRIS A SYSTEM FOR ESTIMATING RESIDENTIAL CONSTRUCTION AND DEMOLITION DEBRIS Authors: Ali Touran, James Wang, Christoforos Christoforou, Nasiru Dantata (Northeastern University, Boston, Massachusetts) ABSTRACT

More information

COMPLETE ONLY ONE OF THE RECYCLING REPORT FORMS! HOW TO DECIDE WHICH REPORT TO SUBMIT:

COMPLETE ONLY ONE OF THE RECYCLING REPORT FORMS! HOW TO DECIDE WHICH REPORT TO SUBMIT: Annual Recycling Report Instructions for Forms FM-11, FM-12 or FM-13 COMPLETE ONLY ONE OF THE RECYCLING REPT FMS! HOW TO DECIDE WHICH REPT TO SUBMIT: Act 101 Compliance Report for Commercial, Municipal

More information

Casar. Please submit this form to by September 1, Mailing Address:PO Box 1014 City: Shelby Zip: 28151

Casar. Please submit this form to by September 1, Mailing Address:PO Box 1014 City: Shelby Zip: 28151 Local Government Required - Enter Your Local Government Casar State of North Carolina Department of Environment and Natural Resources Division of Waste Management & Division of Environmental Assistance

More information

SOLID WASTE MANAGEMENT FACILITIES STUDY Town of New London, New Hampshire

SOLID WASTE MANAGEMENT FACILITIES STUDY Town of New London, New Hampshire SOLID WASTE MANAGEMENT FACILITIES STUDY Town of New London, New Hampshire Prepared for New London Department of Public Works File No. 4220.00 November 2017 TABLE OF CONTENTS 1.0 BACKGROUND AND PURPOSE...

More information

Strategy for Sustainable Solid Waste Management. Mid-America Regional Council (MARC) Solid Waste Management District Kansas City, Missouri

Strategy for Sustainable Solid Waste Management. Mid-America Regional Council (MARC) Solid Waste Management District Kansas City, Missouri Strategy for Sustainable Solid Waste Management prepared for Mid-America Regional Council (MARC) Solid Waste Management District Kansas City, Missouri March 2009 Project No. 48739 prepared by Burns & McDonnell

More information

Strategy for Sustainable Solid Waste Management. Mid-America Regional Council (MARC) Solid Waste Management District Kansas City, Missouri

Strategy for Sustainable Solid Waste Management. Mid-America Regional Council (MARC) Solid Waste Management District Kansas City, Missouri Strategy for Sustainable Solid Waste Management prepared for Mid-America Regional Council (MARC) Solid Waste Management District Kansas City, Missouri March 2009 Project No. 48739 prepared by Burns & McDonnell

More information