Seasonal Assessments and Modeling of Sub-100 kv Elements (Southwest Outage Recommendations 5, 6, 7 and NERC2) May 7, 2014

Size: px
Start display at page:

Download "Seasonal Assessments and Modeling of Sub-100 kv Elements (Southwest Outage Recommendations 5, 6, 7 and NERC2) May 7, 2014"

Transcription

1 Seasonal Assessments and Modeling of Sub-100 kv Elements (Southwest Outage Recommendations 5, 6, 7 and NERC2) May 7, 2014 Background In April 2012, the Federal Energy Regulatory Commission (FERC) and the North American Electric Reliability Corporation (NERC) issued the joint report, Arizona-Southern California Outages on September 8, 2011 (Outage Report). The sequence of events and causes of the Arizona-Southern California outages were illustrated in the Outage Report. The report also presented 27 key findings and recommendations aimed at improving power system reliability. This proposal concentrates on recommendations 5, 6, and 7 of the Outage Report. Recommendation 5: WECC RE should ensure better integration and coordination of the various subregions seasonal studies for the entire WECC system. To ensure a thorough seasonal planning process, at a minimum, WECC RE should require a full contingency analysis of the entire WECC system, using one integrated seasonal study, and should identify and eliminate gaps between subregional studies. Individual [Transmission Operators] TOPs should also conduct a full contingency analysis to identify contingencies outside their own systems that can impact the reliability of the [Bulk Power System] BPS within their system and should share their seasonal studies with TOPs shown to affect or be affected by their contingencies. Recommendation 6: TOPs should expand the focus of their seasonal planning to include external facilities and internal and external sub-100 kv facilities that impact BPS reliability. Recommendation 7: TOPs should expand the cases on which they run their individual planning studies to include multiple base cases, as well as generation maintenance outages and dispatch scenarios during high load shoulder periods. To address the Outage Report recommendations, the Western Electricity Coordinating Council (WECC) issued several recommended NERC activities in the September 28, 2012 report, Response to the Arizona-Southern California Outages on September 8, Approved by the Planning Committee June 11, 2014.

2 The recommended NERC activities which specifically responded to recommendations 5, 6, and 7 of the Outage Report included Sub-100-kV Elements (NERC2). NERC2: To maintain consistency continent-wide, WECC recommends that NERC identify technically-based criteria for identifying which sub-100-kv elements must be modeled in the real-time, next day, seasonal, and near- and long-term horizons. NERC should also identify technically-based criteria for which sub-100-kv elements should be included in the Bulk Electric System. Such criteria must be consistent with any FERC-approved definition of the Bulk Electric System, and should clarify which facilities may be included through any FERC-approved exception process. The System Analysis and Modeling Subcommittee (SAMS) and Modeling Working Group (MWG) were tasked with providing the Planning Committee with guidance on addressing recommendations 5, 6, and 7 of the Outage Report and WECC recommended NERC activity NERC2. SAMS/MWG Assessment Although the Outage Report as written directly addresses WECC TOPs, the issues raised by the recommendations are applicable to all NERC Regions. The recommendations cover the network to be modeled, dispatch scenarios, load levels, outages, base cases, contingencies to be considered, and integrated and coordinated studies. SAMS and MWG believe that Outage Report recommendations 5, 6, and 7, along with WECC recommended NERC activity NERC2, are addressed for all Regions as follows: Outage Report Recommendation 5 (recommendation 5) SAMS and MWG identified the following key components for coordination of seasonal studies in recommendation 5: TOPs should utilize an integrated study model that allows reliability impacts to be identified and coordinated between affected TOPs and RCs; and TOPs should collaborate to identify contingencies outside of their systems which can impact reliability internal to their areas. As established above, SAMS and MWG found that recommendation 5 indicates TOPs should utilize an integrated study model that allows reliability impacts to be identified and coordinated between affected TOPs and RCs. Presently, TOPs establish SOLs (as directed by the Reliability Coordinator) for [their] portion of the Reliability Coordinator Area that are consistent with [their] Reliability Coordinator s SOL methodology, pursuant to FAC-014-2, Requirement R2. To comply with the Reliability Coordinator s SOL methodology, a study model that include[s] at least the entire Reliability Coordinator Area as well as the critical modeling details from other Reliability Coordinator Areas that would impact the Facility or Facilities under study (FAC-011-2, Requirement R3/R3.1), must be used by Seasonal Assessments and Modeling of Sub-100 kv Elements 2

3 TOPs to conduct their seasonal studies. SAMS and MWG believe that the study model described in FAC results in an integrated study model that is coordinated amongst TOPs and RCs. Additionally, proposed standard TOP-002-3, Requirement R2, requires each TOP to plan to operate within each Interconnection Reliability Operating Limit (IROL) and each System Operating Limit (SOL), in accordance with their Operational Planning Analysis 1. Since the SOLs and IROLs determined by the Operational Planning Analysis must be consistent with the Reliability Coordinator s SOL Methodology 2, the use of the FAC integrated study model is required by TOP Therefore, TOP-002-3, which also applies to the operations planning time horizon, also supports the first goal of recommendation 5 to ensure better integration and coordination of the various subregions seasonal studies as required by an interconnection. The second key component of recommendation 5 indicates that TOPs should collaborate to identify contingencies outside of their system which can impact reliability internal to their areas. The existing standard TOP b, Requirement R6, requires TOPs to plan to meet unscheduled changes in system configuration and generation dispatch (at a minimum N-1 Contingency planning) in accordance with NERC, Regional Reliability Organization, subregional, and local reliability requirements. The proposed standard TOP-002-3, Requirement R1 (which would supersede the above standard), states that Each Transmission Operator shall have an Operational Planning Analysis that represents projected System conditions that will allow it to assess whether the planned operations for the next day within its Transmission Operator Area will exceed any of its Facility Ratings or Stability Limits during anticipated normal and Contingency event conditions. Additionally, as a component of the Operational Planning Analysis, TOPs are required to develop a plan to operate within each SOL and IROL that supports reliability internal to its TOP Area (TOP-002-3, Requirement R2). These SOLs and IROLs need to be respected when evaluating normal and Contingency event conditions as part of the Operational Planning Analysis. Contingencies, both internal and external to a TOP Area must be evaluated to fully assess SOLs, IROLs, Facility Ratings, and Stability Limits associated with a TOP s operations. Furthermore, since the above requirements apply to identification of any exceedance of applicable Facility Ratings, Stability Limits, SOLs, and IROLs, the normal and Contingency event conditions to be evaluated should be consistent with the SOL Methodology described in FAC-011-2, Requirement R2. Additionally, FAC-011-2, Requirement R2, requires TOPs to evaluate all normal conditions and single Contingencies, which include, Single line to ground or 3-phase Fault [conditions] (whichever is more severe), with Normal Clearing, on any Faulted 1 Operational Planning Analysis - An analysis of the expected system conditions for the next day s operation. (That analysis may be performed either a day ahead or as much as 12 months ahead.) Expected system conditions include things such as load forecast(s), generation output levels, and known system constraints (transmission facility outages, generator outages, equipment limitations, etc.). Glossary of Terms Used in NERC Reliability Standards, (July 22, 2013) 2 As described above. Seasonal Assessments and Modeling of Sub-100 kv Elements 3

4 generator, line, transformer, or shunt device. This contingency analysis also evaluates both internal and external reliability impacts, as TOPs are required to demonstrate [that each TOP Area maintains] transient, dynamic and voltage stability; all Facilities [are planned to] operate within their Facility Ratings and within their thermal, voltage and stability limits; and [that] Cascading or uncontrolled separation shall not occur. Together, the requirements in the above TOP and FAC standards address the second key component of recommendation 5, for TOPs to identify contingencies outside of their system that can impact reliability internal to their areas. Finally, sharing of seasonal studies is covered through the following standard requirements. FAC-014-2, Requirement R5 ensures that SOLs and IROLs are shared amongst Reliability Coordinators (as appropriate), TOPs, Transmission Service Providers, Transmission Planners, and Planning Coordinators. TOP b, Requirement R4 requires each Transmission Operator [to] coordinate (where confidentiality agreements allow) its seasonal planning and operations with neighboring Transmission Operators." MWG and SAMS believe that this requirement facilitates TOP sharing of information such as seasonal studies. In the mapping document for Project Realtime Operations, TOP b, Requirement R4 is proposed for retirement and replaced by TOP-003-2, Requirement R1, which requires TOPs to create specifications for data and information needed to support its Operational Planning Analyses. TOP-003-2, Requirement R5 obligates other TOPs to provide the requested data and information as defined in TOP-003-2, Requirement R1. The above requirements allow TOPs to coordinate seasonal studies and share their seasonal studies with TOPs shown to affect or be affected by their contingencies. As a result the goal of recommendation 5 is met. However, SAMS and MWG recommend that TOPs share the results of their seasonal studies with all affected TOPs and RCs, even if a seasonal study is not requested by an affected TOP/RC, pursuant to proposed standard TOP Outage Report Recommendation 6 (recommendation 6) and NERC2 Recommendation 6 requests that TOPs include 1) external facilities, and 2) internal and external sub- 100 kv facilities that impact BPS reliability in their seasonal planning efforts. Similarly, recommendation NERC2 requests that NERC identify criteria for inclusion of sub-100 kv facilities that should be modeled in real-time, next-day, seasonal, and planning studies. External facilities rated above 100 kv that impact reliability are already included in study models, as explained in the SAMS/MWG proposal for meeting the goals of recommendation 5 above. SAMS and MWG believe that a NERC-wide criteria for which sub-100-kv elements should be modeled and assessed is not appropriate due to regional differences. Therefore, SAMS and MWG recommend that Transmission Planners and Planning Coordinators (Planning Authorities) conduct periodic assessments to identify sub-100 kv facilities either internal or external to their area that impact BES reliability of their system. Any sub-100 kv facilities identified in periodic assessments should be Seasonal Assessments and Modeling of Sub-100 kv Elements 4

5 modeled in long-term planning models, and also be submitted to applicable TOPs and RCs for consideration to be included in their studies. SAMS and MWG believe that this response addresses recommendation 6 and NERC2. Outage Report Recommendation 7 (recommendation 7) Existing standard TOP b, Requirement R5 states that [e]ach Transmission Operator shall plan to meet scheduled system configuration, generation dispatch, interchange scheduling and demand patterns. The requirement covers recommendation 7 from the perspective of base case parameters such as, modeling system configurations, generation dispatch, and load scenarios. However, it does not explicitly mention modeling of dispatch scenarios specific to high load shoulder periods. Proposed standard TOP-002-3, Requirement R1, requires TOPs to conduct an Operational Planning Analysis that considers the following base case parameters that should be used to conduct simulations, which meet the reliability goal of recommendation 7: Transmission and generation outages; Load forecasts(s); and Planned dispatch scenarios (i.e., generation output levels). Although neither the existing standard TOP b nor the proposed standard TOP specifically mention modeling of high load shoulder periods, SAMS and MWG recommend that such scenarios may need to be modeled in order to satisfy these requirements in the standards. As the proposed standard does not specifically mention projected power transfers (interchange scheduling), SAMS and MWG recommend that Regions and TOPs clarify their study procedures, as applicable to incorporate these study parameters. Additionally, SAMS and MWG recommend that base case parameters such as load forecasts incorporating load Mvar/power factor data and reactive resource schedules, should be included in study models consistent with VAR and proposed VAR Conclusions and Recommendations In conclusion SAMS and MWG recommend the current or proposed standards described above, in general address the Outage Report recommendations 5, 6, 7 and NERC2. However, SAMS and MWG recommend that Regions and TOPs develop their own specific guidelines as needed to address the following enhancements: TOPs should share the results of their seasonal studies with all affected TOPs and RCs, pursuant to standard TOP-003-2; SAMS and MWG believe that a NERC-wide criteria for which sub-100-kv elements should be modeled and assessed is not appropriate due to regional differences. Therefore, SAMS and Seasonal Assessments and Modeling of Sub-100 kv Elements 5

6 MWG recommend that Transmission Planners and Planning Coordinators (Planning Authorities) conduct periodic assessments to identify sub-100 kv facilities either internal or external to their area that impact BES reliability of their system. Any sub-100 kv facilities identified in periodic assessments should be modeled in long-term planning models, and also be submitted to applicable TOPs and RCs for consideration to be included in their studies. Incorporate modeling of scenarios specific to high load shoulder periods relevant to the area under study; Model projected power transfers (interchange scheduling); and Base case parameters such as load forecasts incorporating load Mvar/power factor data and reactive resource schedules, should be included in study models consistent with VAR and proposed VAR Seasonal Assessments and Modeling of Sub-100 kv Elements 6

Mapping of Revised TOP and IRO Reliability Standards to Address 2011 Southwest Outage Report Recommendations

Mapping of Revised TOP and IRO Reliability Standards to Address 2011 Southwest Outage Report Recommendations Mapping of Revised TOP and IRO Reliability Standards to Address 2011 Southwest Outage Report Recommendations The following table provides a mapping of the recommendations applicable to the Reliability

More information

SYSTEM OPERATING LIMITS IN THE PLANNING HORIZON FAC-010 COMPLIANCE

SYSTEM OPERATING LIMITS IN THE PLANNING HORIZON FAC-010 COMPLIANCE SYSTEM OPERATING LIMITS IN THE PLANNING HORIZON FAC-010 COMPLIANCE System Operating Limits (SOLs) in the planning horizon are required to be identified by FAC-010. This guideline describes how Duke Energy

More information

Mapping Document for FAC-010-3

Mapping Document for FAC-010-3 Mapping Document for FAC-010-3 The Project 2015 09 standard drafting team (SDT) is proposing the retirement of the NERC FAC 010 3 Reliability Standard. The SDT further proposes a new paradigm regarding

More information

Table of Contents. To provide a methodology for determining the System Operating Limits (SOL) for the Planning Horizon at the California ISO.

Table of Contents. To provide a methodology for determining the System Operating Limits (SOL) for the Planning Horizon at the California ISO. Table of Contents Purpose... 1 Applicable Reliability Standard(s)... 1 Applicability to California ISO... 1 SOLs and IROLs... 1 Study Methodology... 2 Supporting Information... 6 Responsibilities... 6

More information

Transfer Capability Methodology. for the Near-Term. Transmission Planning Horizon

Transfer Capability Methodology. for the Near-Term. Transmission Planning Horizon Transfer Capability Methodology for the Near-Term Transmission Planning FAC-013-2 Version 2.2 June 30, 2018 Table of Contents 1 PURPOSE... 3 2 DEFINITION... 3 3 APPLICABILITY... 3 4 TRANSFER CAPABILITY

More information

Project System Operating Limits

Project System Operating Limits Project 2015-09 System Operating Limits Technical Conference Background Materials These background materials were prepared by members of the Standard Drafting Team solely for use in conjunction with the

More information

SYSTEM OPERATING LIMITS METHODOLOGY FOR THE OPERATIONS HORIZON

SYSTEM OPERATING LIMITS METHODOLOGY FOR THE OPERATIONS HORIZON SYSTEM OPERATING LIMITS METHODOLOGY FOR THE OPERATIONS HORIZON Rev. 8.1 By Peak Reliability February 24, 2017 PEAK RELIABILITY RELIABILITY COORDINATION 7600 NE 41 st STREET SUITE 201 VANCOUVER WASHINGTON

More information

Standard FAC System Operating Limits Methodology for the Planning Horizon

Standard FAC System Operating Limits Methodology for the Planning Horizon Standard FAC-010-1 System Operating Limits Methodology for the Planning Horizon Standard Development Roadmap This section is maintained by the drafting team during the development of the standard and will

More information

FERC Directives in Order 693 Addressed in IROL Implementation Plan

FERC Directives in Order 693 Addressed in IROL Implementation Plan The following Interconnection Reliability Operating Limit (IROL) standards were under development when the Version 0 project was initiated: IRO-008 Reliability Coordinator Operational Analyses and Real-time

More information

WECC-0111 TOP-007-WECC-1a System Operating Limits Retire or Modify Supporting Narrative and Crosswalk to Retire

WECC-0111 TOP-007-WECC-1a System Operating Limits Retire or Modify Supporting Narrative and Crosswalk to Retire MEMO Date: August 6, 2015 Subject: Retirement of TOP-007-WECC-1a (TOP) System Operating Limits Posting 2 The WECC-0111, TOP-007-WECC-1a, System Operating Limits (TOP) Retire or Modify Drafting Team (DT)

More information

SYSTEM OPERATING LIMITS METHODOLOGY FOR THE OPERATIONS HORIZON. Rev. 1.0

SYSTEM OPERATING LIMITS METHODOLOGY FOR THE OPERATIONS HORIZON. Rev. 1.0 No. RC0610 SYSTEM OPERATING LIMITS METHODOLOGY FOR THE OPERATIONS HORIZON Rev. 1.0 By California Independent System Operator (CAISO RC) No. RC0610 Table of Contents A. Conventions... 5 B. Introduction

More information

July 15 July 31. August First ballot September 1 10, Drafting Team considers comments and makes any revisions indicated

July 15 July 31. August First ballot September 1 10, Drafting Team considers comments and makes any revisions indicated Standard FAC-008-1 Facility Ratings Methodology Standard Development Roadmap This section is maintained by the drafting team during the development of the standard and will be removed when the standard

More information

Methodology for Determining and Communicating System Operating Limits for the Planning Horizon (FAC-010 & -014) Revision Log

Methodology for Determining and Communicating System Operating Limits for the Planning Horizon (FAC-010 & -014) Revision Log Revision Log Page 2 of 13 Revision or Change Number Effective Date Affected Page Numbers Description of Revision/Change 0000 03-26-2011 All Converted TPD document to SPP format 0001 03-26-2012 All Annual

More information

Standards Authorization Request Form

Standards Authorization Request Form Standards Authorization Request Form When completed, please email this form to: sarcomm@nerc.com NERC welcomes suggestions to improve the reliability of the bulk power system through improved reliability

More information

Project Consideration of Commission Directives in Order No. 693

Project Consideration of Commission Directives in Order No. 693 Project 2009-02 Consideration of Commission Directives in Order Order P 905-906 Further, consistent with the NOPR, the Commission directs the ERO to modify IRO-002-1 to require a minimum set of tools that

More information

November 21, 2016 VIA ELECTRONIC FILING

November 21, 2016 VIA ELECTRONIC FILING November 21, 2016 VIA ELECTRONIC FILING David Erickson President and Chief Executive Officer Alberta Electric System Operator 2500, 330-5 Avenue SW Calgary, Alberta T2P 0L4 RE: North American Electric

More information

Mapping Document. Project Phase 2 of System Protection Coordination. Revisions or Retirements to Already Approved Standards

Mapping Document. Project Phase 2 of System Protection Coordination. Revisions or Retirements to Already Approved Standards Mapping Document Project 2007-06.2 Phase 2 of System Protection Coordination Revisions or Retirements to Already Approved Standards This mapping document explains how each of the existing Requirements

More information

Project Revisions to TOP and IRO Reliability Standards Mapping Document Updated December 2014

Project Revisions to TOP and IRO Reliability Standards Mapping Document Updated December 2014 Project 2014-03 Revisions to TOP and IRO Reliability Standards Mapping Document Updated December 2014 This mapping document showing the translation of Requirements in the following currently-enforceable

More information

TOP TOP TOP 003 3

TOP TOP TOP 003 3 TOP 001 3 TOP 002 4 TOP 003 3 September 20, 2016 Fall Workshop Allen Klassen, Westar Mike Hughes, SPP RE Use of Presentation For simplicity, some wording from the standard has been shortened, paraphrased,

More information

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION. NEW HARQUAHALA ) Docket No. RC GENERATING COMPANY, LLC )

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION. NEW HARQUAHALA ) Docket No. RC GENERATING COMPANY, LLC ) UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION NEW HARQUAHALA ) Docket No. RC08-4-002 GENERATING COMPANY, LLC ) COMPLIANCE FILING OF THE NORTH AMERICAN ELECTRIC RELIABILITY CORPORATION

More information

Standard Development Timeline

Standard Development Timeline Standard Development Timeline This section is maintained by the drafting team during the development of the standard and will be removed when the standard is adopted by the NERC Board of Trustees (Board).

More information

NERC Glossary Definitions: System Operating Limit and SOL Exceedance Rationale

NERC Glossary Definitions: System Operating Limit and SOL Exceedance Rationale NERC Glossary Definitions: System Operating Limit and SOL Exceedance Rationale Introduction The standard drafting team ( SDT ) for Project 2015 09 Establish and Communicate System Operating Limits developed

More information

2015 Operational Practices Survey Questions

2015 Operational Practices Survey Questions 2015 Operational Practices Survey Questions This document of survey questions has been provided as a courtesy. It is not the actual survey, which will be completed electronically and only by a designated

More information

AESO System Operating Limits Methodology for the Planning Horizon (R1 FAC-010-AB-2.1)

AESO System Operating Limits Methodology for the Planning Horizon (R1 FAC-010-AB-2.1) (R1 FAC-010-AB-2.1) 1 Purpose This document sets out the System Operating Limits Methodology the Alberta Electric System Operator ( AESO ) uses for any studies conducted on the interconnected electric

More information

Reliability Coordinator Area System Operating Limit Methodology

Reliability Coordinator Area System Operating Limit Methodology Reliability Coordinator Area System Operating Limit Methodology Revision 1.0 MAINTAINED BY SPP Operations Staff PUBLISHED: 10/19/2018 LATEST REVISION: Effective 10/19/2018 Copyright 2018 by Southwest Power

More information

Standard Development Timeline

Standard Development Timeline Standard Development Timeline This section is maintained by the drafting team during the development of the standard and will be removed when the standard is adopted by the NERC Board of Trustees (Board).

More information

Functional Entity Roles and Responsibilities

Functional Entity Roles and Responsibilities Functional Entity Roles and Responsibilities NWPP MC Phase 3 Operations Integration Work Group 9/28/2014 Page 1 of 13 Table of Contents 1. Purpose... 3 2. Roles and Responsibilities of Functional Entities...

More information

Platte River Power Authority. Ten-Year Transmission Plan ( )

Platte River Power Authority. Ten-Year Transmission Plan ( ) Platte River Power Authority Ten-Year Transmission Plan (2015-2024) Prepared by PRPA System Planning December 31, 2014 Table of Contents I. Executive Summary II. III. IV. Scope Assumptions Criteria V.

More information

Implementation Plan Project Operations Personnel Training

Implementation Plan Project Operations Personnel Training Implementation Plan Project 2010-01 Operations Personnel Training Implementation Plan for PER-005-2 Operations Personnel Training Approvals Required PER-005-2 Operations Personnel Training Prerequisite

More information

Implementation Plan IRO Reliability Coordination Current Day Operations

Implementation Plan IRO Reliability Coordination Current Day Operations Implementation Plan IRO-005-4 Reliability Coordination Current Day Operations Approvals Required IRO-005-4 Reliability Coordination Current Day Operations Prerequisite Approvals None Revisions to Glossary

More information

RELIABILITY PLAN for the SERC Southeastern Subregion Reliability Coordinator July 14, 2016

RELIABILITY PLAN for the SERC Southeastern Subregion Reliability Coordinator July 14, 2016 Agenda Item 3.b.i ORS Meeting September 7-8, 2016 RELIABILITY PLAN for the SERC Southeastern Subregion Reliability Coordinator July 14, 2016 Introduction The Southern Company Services is the Southeastern

More information

Updated October 2, 2014 TITLE: System Operator Transmission - Senior DEPARTMENT: System Operations

Updated October 2, 2014 TITLE: System Operator Transmission - Senior DEPARTMENT: System Operations Updated October 2, 2014 System Operator Transmission - Senior interconnected system. Maintains the Western Electricity Coordinating Council (WECC) Coordinated Outage System (COS), documents standardized

More information

Implementation Plan for IRO Reliability Coordination Facilities Prerequisite Approvals Adoption of IRO-001-2, IRO-010-0, COM-001-2

Implementation Plan for IRO Reliability Coordination Facilities Prerequisite Approvals Adoption of IRO-001-2, IRO-010-0, COM-001-2 Prerequisite Approvals Adoption of IRO-001-2, IRO-010-0, COM-001-2 Conforming Changes to Requirements in s None Coordination with revisions proposed in other standards projects The IROL SDT proposes retiring

More information

Standard Development Timeline

Standard Development Timeline Standard Development Timeline This section is maintained by the drafting team during the development of the standard and will be removed when the standard is adopted by the NERC Board of Trustees (Board).

More information

Planning Coordinator and/or Transmission Planner TRANSMISSION SYSTEM PLANNING GUIDELINES

Planning Coordinator and/or Transmission Planner TRANSMISSION SYSTEM PLANNING GUIDELINES Planning Coordinator and/or Transmission Planner TRANSMISSION SYSTEM PLANNING GUIDELINES Effective Date: September 11, 2017 Revision History Date Version Description June 6, 1998 0.0 Initial LGEE document

More information

SOL Methodology Revision Kick-off

SOL Methodology Revision Kick-off SOL Methodology Revision Kick-off Welcome - the webinar will begin shortly All participants will be muted during the webinar Peak will unmute phones at the end to take questions Peak will be recording

More information

Project Single Points of Failure TPL-001 Cost Effectiveness

Project Single Points of Failure TPL-001 Cost Effectiveness Project 2015-10 Single Points of Failure TPL-001 Cost Effectiveness Known Outages FERC Order No. 786 FERC Order No. 786 Paragraph 40 directs a change to address the concern that the six month threshold

More information

Review of Data Change Management Processes for RTCA and Planning Models (Recommendation 16) March, 2017

Review of Data Change Management Processes for RTCA and Planning Models (Recommendation 16) March, 2017 Review of Data Change Management Processes for RTCA and Planning Models (Recommendation 16) March, 2017 Background In April 2012, the Federal Energy Regulatory Commission (FERC) and the North American

More information

POTOMAC ELECTRIC POWER COMPANY

POTOMAC ELECTRIC POWER COMPANY POTOMAC ELECTRIC POWER COMPANY FERC Form 715 (Part 4) - Transmission Planning Study Guidelines Transmission Reliability Guidelines 1. General Overview The reliability guidelines used to plan the transmission

More information

Load Shed Philosophy

Load Shed Philosophy APPLICABILITY: Reliability Coordinator I. Background While time limits exist for mitigation of the exceedance of certain types of system operating limits, events can occur quickly necessitating a responsive

More information

September 12, 2016 VIA ELECTRONIC FILING

September 12, 2016 VIA ELECTRONIC FILING !! September 12, 2016 VIA ELECTRONIC FILING Kirsten Walli, Board Secretary Ontario Energy Board P.O Box 2319 2300 Yonge Street Toronto, Ontario, Canada M4P 1E4 Re: North American Electric Reliability Corporation

More information

Standard TPL-002-0b System Performance Following Loss of a Single BES Element

Standard TPL-002-0b System Performance Following Loss of a Single BES Element A. Introduction 1. Title: System Performance Following Loss of a Single Bulk Electric System Element (Category B) 2. Number: TPL-002-0b 3. Purpose: System simulations and associated assessments are needed

More information

Security Guideline for the Electricity Sector: Identifying Critical Assets

Security Guideline for the Electricity Sector: Identifying Critical Assets Note: The guideline was developed for CIP-002-1 but is also applicable to CIP- 002-2 and CIP-002-3. Security Guideline for the Electricity Sector: Identifying Critical Assets Disclaimer: This supporting

More information

Standard MH-TPL Transmission System Planning Performance Requirements

Standard MH-TPL Transmission System Planning Performance Requirements A. Introduction 1. Title: Transmission System Planning Performance Requirements 2. Number: MH-TPL-001-4 3. Purpose: Establish Transmission system planning performance requirements within the planning horizon

More information

Remedial Action Scheme (RAS) Modeling Value Proposition

Remedial Action Scheme (RAS) Modeling Value Proposition Remedial Action Scheme (RAS) Modeling Value Proposition Modeling SPS and Relay Ad-hoc Task Force of the Technical Studies Subcommittee and WECC Staff Western Electricity Coordinating Council May 2, 2014

More information

Standard Development Timeline

Standard Development Timeline Standard Development Timeline This section is maintained by the drafting team during the development of the standard and will be removed when the standard is adopted by the NERC Board of Trustees (Board).

More information

Exhibit A. Reliability Standards Proposed for Approval

Exhibit A. Reliability Standards Proposed for Approval Exhibit A Reliability Standards Proposed for Approval Proposed New Standard IRO-006-5 Standard IRO-006-5 Reliability Coordination Transmission Loading Relief A. Introduction 1. Title: Reliability Coordination

More information

Standard TPL System Performance Following Extreme BES Events

Standard TPL System Performance Following Extreme BES Events A. Introduction 1. Title: System Performance Following Extreme Events Resulting in the Loss of Two or More Bulk Electric System Elements (Category D) 2. Number: TPL-004-1 3. Purpose: System simulations

More information

Standard IRO a Reliability Coordination Current Day Operations

Standard IRO a Reliability Coordination Current Day Operations A. Introduction 1. Title: Reliability Coordination Current Day Operations 2. Number: IRO-005-3.1a 3. Purpose: must be continuously aware of conditions within its Reliability Coordinator Area and include

More information

Appendix 5B Statement of Compliance Registry Criteria Revision 5.2 Effective: October 15, 2015

Appendix 5B Statement of Compliance Registry Criteria Revision 5.2 Effective: October 15, 2015 Appendix 5B Statement of Compliance Registry Criteria Revision 5.2 Effective: October 15, 2015 Statement of Compliance Registry Criteria (Revision 5.2) Summary This document describes how the North American

More information

Periodic Review Recommendation FAC System Operating Limits Methodology for the Operations Horizon

Periodic Review Recommendation FAC System Operating Limits Methodology for the Operations Horizon Periodic Review Recommendation FAC-011-3 - System Operating Limits Methodology for the Operations Horizon Introduction NERC is required to conduct a periodic review of each NERC Reliability Standard at

More information

Western Interconnection Seasonal Operations Planning Coordination Process Rev. 3.0

Western Interconnection Seasonal Operations Planning Coordination Process Rev. 3.0 Western Interconnection Seasonal Operations Planning Rev. 3.0 Issued March 26, 2019 Effective May 1, 2019 PEAK RELIABILITY RELIABILITY COORDINATION 7600 NE 41 st STREET SUITE 201 VANCOUVER WASHINGTON 98662-6772

More information

ASSOCIATED NERC STANDARD(S): TPL (referred to as TPL-001 in this document) IMPLEMENTATION: In effect when approved.

ASSOCIATED NERC STANDARD(S): TPL (referred to as TPL-001 in this document) IMPLEMENTATION: In effect when approved. ASSOCIATED NERC STANDARD(S): TPL-001-4 (referred to as TPL-001 in this document) IMPLEMENTATION: In effect when approved. Phase in of individual TPL-001 requirements will be based on the effective dates

More information

Standard TPL-003-0b System Performance Following Loss of Two or More BES Elements

Standard TPL-003-0b System Performance Following Loss of Two or More BES Elements A. Introduction 1. Title: System Performance Following Loss of Two or More Bulk Electric System (Category C) 2. Number: TPL-003-0b 3. Purpose: System simulations and associated assessments are needed periodically

More information

Standard TPL Transmission System Planning Performance Requirements

Standard TPL Transmission System Planning Performance Requirements A. Introduction 1. Title: Transmission System Planning Performance Requirements 2. Number: TPL-001-4 3. Purpose: Establish Transmission system planning performance requirements within the planning horizon

More information

Project : Generator Requirements at the Transmission Interface Background Resource Document

Project : Generator Requirements at the Transmission Interface Background Resource Document Project 2010-07: Generator Requirements at the Transmission Interface Background Resource Document Introduction The integrated grid consists of many parts such as power plants, Transmission, and Facilities

More information

Standard TPL-003-0b System Performance Following Loss of Two or More BES Elements

Standard TPL-003-0b System Performance Following Loss of Two or More BES Elements Page 220 of 257 A. Introduction 1. Title: System Performance Following Loss of Two or More Bulk Electric System (Category C) 2. Number: TPL-003-0b 3. Purpose: System simulations and associated assessments

More information

Standard Development Timeline

Standard Development Timeline Standard TPL-001-4 Transmission System Planning Performance Requirements Standard Development Timeline This section is maintained by the drafting team during the development of the standard and will be

More information

Proposed Revisions to the Applicability of NERC Reliability Standards NERC Standards Applicability to Dispersed Generation Resources

Proposed Revisions to the Applicability of NERC Reliability Standards NERC Standards Applicability to Dispersed Generation Resources Draft White Paper Proposed Revisions to the Applicability of NERC Reliability Standards NERC Standards Applicability to Dispersed Generation Resources Project 2014-01 Standards Applicability for Dispersed

More information

February 15, 2013 VIA ELECTRONIC FILING

February 15, 2013 VIA ELECTRONIC FILING February 15, 2013 VIA ELECTRONIC FILING Ms. Kimberly D. Bose Secretary Federal Energy Regulatory Commission 888 First Street, NE Washington, D.C. 20426 Re: Supplemental Information to NERC Compliance Filing

More information

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION NORTH AMERICAN ) Docket No. RR07-11- ELECTRIC RELIABILITY CORPORATION ) ) COMPLIANCE FILING OF THE NORTH AMERICAN ELECTRIC RELIABILITY

More information

Periodic Review Recommendation FAC System Operating Limits Methodology for the Planning Horizon

Periodic Review Recommendation FAC System Operating Limits Methodology for the Planning Horizon Periodic Review Recommendation FAC-010-3 - System Operating Limits Methodology for the Planning Horizon Introduction NERC is required to conduct a periodic review of each NERC Reliability Standard at least

More information

Proposed Revisions to the Applicability of NERC Reliability Standards NERC Standards Applicability to Dispersed Generation Resources

Proposed Revisions to the Applicability of NERC Reliability Standards NERC Standards Applicability to Dispersed Generation Resources Draft White Paper Proposed Revisions to the Applicability of NERC Reliability Standards NERC Standards Applicability to Dispersed Generation Resources Project 2014-01 Standards Applicability for Dispersed

More information

Periodic Review Recommendation FAC System Operating Limits Methodology for the Operations Horizon

Periodic Review Recommendation FAC System Operating Limits Methodology for the Operations Horizon Periodic Review Recommendation FAC-011-3 - System Operating Limits Methodology for the Operations Horizon Introduction NERC is required to conduct a periodic review of each NERC Reliability Standard at

More information

Standard TPL-003-0a1a System Performance Following Loss of Two or More BES Elements

Standard TPL-003-0a1a System Performance Following Loss of Two or More BES Elements Standard Development Roadmap This section is maintained by the drafting team during the development of the standard and will be removed when the standard becomes effective. Development Steps Completed:

More information

MOD-001-1a Available Transfer Capability Implementation Document

MOD-001-1a Available Transfer Capability Implementation Document Available Transfer Capability Implementation Document For NERC MOD-001-2a Page 1 of 18 1.0 Purpose The California Independent System Operator Corporation (ISO), as a Transmission Service Provider 1 and

More information

Standards de planification du NERC

Standards de planification du NERC Demande R-3498-2002 Standards de planification du NERC PREUVE EN CHEF DE TRANSÉNERGIE Original : 2002-11-27 HQT-4, Document 2 (en liasse) NERC PLANNING STANDARDS North American Electric Reliability Council

More information

TRANSMISSION PLANNING ASSESSMENT METHODOLOGY AND CRITERIA

TRANSMISSION PLANNING ASSESSMENT METHODOLOGY AND CRITERIA TRANSMISSION PLANNING ASSESSMENT METHODOLOGY AND CRITERIA For Compliance with NERC Reliability Standard: TPL-001-4 1/10/2017 Version: 4.2 Table of Contents 1 Revision and Approval History... 2 1.1 Revision

More information

California Independent System Operator Corporation Fifth Replacement Tariff

California Independent System Operator Corporation Fifth Replacement Tariff Table of Contents Method to Assess Available Transfer Capability... 2 L.1 Description of Terms... 2 L.1.1 Available Transfer Capability (ATC)... 2 L.1.2 Total Transfer Capability (TTC)... 2 L.1.3 Existing

More information

California Independent System Operator Corporation Fifth Replacement Tariff

California Independent System Operator Corporation Fifth Replacement Tariff Table of Contents Method to Assess Available Transfer Capability... 2 L.1 Description of Terms... 2 L.1.1 Available Transfer Capability (ATC)... 2 L.1.2 Total Transfer Capability (TTC)... 2 L.1.3 Existing

More information

Performance Standards Issues. Donald Lamontagne Principal Engineer Arizona Public Service

Performance Standards Issues. Donald Lamontagne Principal Engineer Arizona Public Service Performance Standards Issues Donald Lamontagne Principal Engineer Arizona Public Service Free Template from www.brainybetty.com 2 Regulatory Entities FERC Energy Policy Act of 2005 NERC Designated Electric

More information

Post SAR July day Formal Comment Period with Parallel Ballot July 2013

Post SAR July day Formal Comment Period with Parallel Ballot July 2013 Standard Development Timeline This section is maintained by the drafting team during the development of the standard and will be removed when the standard becomes effective. Development Steps Completed

More information

MOD Steady-State and Dynamic System Model Validation

MOD Steady-State and Dynamic System Model Validation MOD-033-1 Steady-State and Dynamic System Model Validation A. Introduction 1. Title: Steady-State and Dynamic System Model Validation 2. Number: MOD-033-1 3. Purpose: To establish consistent validation

More information

Northwest Power Pool Processes

Northwest Power Pool Processes Northwest Power Pool Processes Background The Northwest Power Pool membership (NWPP) was founded in 1941 to promote efficient production of electrical energy. The NWPP is the geographic area encompassed

More information

Standard Development Timeline

Standard Development Timeline Standard Development Timeline This section is maintained by the drafting team during the development of the standard and will be removed when the standard is adopted by the NERC Board of Trustees (Board).

More information

Standard Authorization Request Form

Standard Authorization Request Form Standard Authorization Request Form Title of Proposed Standard Glossary of Terms change System Operator definition (Project 2010-16 Definition of System Operator) Request Date October 5, 2010 SC Approval

More information

NERC Standards Report, Status and Timetable for Addressing Regulatory Directives, and Periodic Review of Reliability Standards Docket No.

NERC Standards Report, Status and Timetable for Addressing Regulatory Directives, and Periodic Review of Reliability Standards Docket No. March 31, 2016 Ms. Kimberly D. Bose Secretary Federal Energy Regulatory Commission 888 First Street, NE Washington, D.C. 20426 Re: NERC Standards Report, Status and Timetable for Addressing Regulatory

More information

IROL Framework Assessment Report

IROL Framework Assessment Report IROL Framework Assessment Report NERC Methods for Establishing IROLs Task Force (MEITF) September 2018 NERC Report Title Report Date I Table of Contents Preface... iii Executive Summary... iv Key Findings

More information

Standard IRO Reliability Coordination Monitoring and Analysis

Standard IRO Reliability Coordination Monitoring and Analysis Standard Development Timeline This section is maintained by the drafting team during the development of the standard and will be removed when the standard becomes effective. Development Steps Completed

More information

Standards Authorization Request Form

Standards Authorization Request Form When completed, email this form to: sarcomm@nerc.net NERC welcomes suggestions for improving the reliability of the Bulk-Power System through improved Reliability Standards. Please use this form to submit

More information

Standard TPL-004-0a System Performance Following Extreme BES Events

Standard TPL-004-0a System Performance Following Extreme BES Events A. Introduction 1. Title: System Performance Following Extreme Events Resulting in the Loss of Two or More Bulk Electric System Elements (Category D) 2. Number: TPL-004-0a 3. Purpose: System simulations

More information

Glossary of Terms Used in Reliability Standards. Preliminary Draft Version 0 Reliability Standards September 1, 2004

Glossary of Terms Used in Reliability Standards. Preliminary Draft Version 0 Reliability Standards September 1, 2004 Glossary of Terms Used in Standards Preliminary Draft Version 0 Standards September 1, 2004 Source References (Noted in draft only will not be part of final glossary) Functional Model () Glossary (GL)

More information

Standard TPL System Performance Under Normal Conditions

Standard TPL System Performance Under Normal Conditions Standard TPL-001-0.1 System Performance Under rmal Conditions Standard Development Roadmap This section is maintained by the drafting team during the development of the standard and will be removed when

More information

RCR-35 Reliability Coordinator Reliability Plan for the SaskPower Subregion of the Midwest Reliability Organization

RCR-35 Reliability Coordinator Reliability Plan for the SaskPower Subregion of the Midwest Reliability Organization RCR-35 Reliability Coordinator Reliability Plan for the SaskPower Subregion of the Midwest Reliability Organization - 1 - Introduction The North American Electric Reliability Council (NERC) requires every

More information

Black Hills Power, Inc Basin Electric Power Cooperative Powder River Energy Corporation

Black Hills Power, Inc Basin Electric Power Cooperative Powder River Energy Corporation Black Hills Power, Inc Basin Electric Power Cooperative Powder River Energy Corporation Transmission System Planning Methodology, Criteria and Process Business Practice December 07, 2007 Table of Contents

More information

Transmission Loading Relief Eastern Interconnection

Transmission Loading Relief Eastern Interconnection Transmission Loading Relief Eastern Interconnection Purpose: This standard defines procedures for curtailment and reloading of Interchange Transactions to relieve overloads on transmission facilities modeled

More information

PER Operations Personnel Training

PER Operations Personnel Training A. Introduction 1. Title: Operations Personnel Training 2. Number: PER-005-2 3. Purpose: To ensure that personnel performing or supporting Real-time operations on the Bulk Electric System are trained using

More information

Standards Authorization Request Form

Standards Authorization Request Form Standards Authorization Request Form When completed, email this form to: Howard.Gugel@nerc.netValerie.Agnew@nerc.net For questions about this form or for assistance in completing the form, call Howard

More information

Standards Authorization Request Form

Standards Authorization Request Form When completed, please email this form to: sarcomm@nerc.com NERC welcomes suggestions to improve the reliability of the bulk power system through improved reliability standards. Please use this form to

More information

Standard IRO Reliability Coordinator Data Specification and Collection

Standard IRO Reliability Coordinator Data Specification and Collection A. Introduction 1. Title: Reliability Coordinator Data Specification and Collection 2. Number: IRO-010-2 3. Purpose: To prevent instability, uncontrolled separation, or Cascading outages that adversely

More information

Standard IRO Reliability Coordination Monitoring and Analysis

Standard IRO Reliability Coordination Monitoring and Analysis A. Introduction 1. Title: Reliability Coordination Monitoring and Analysis 2. Number: IRO-002-4 3. Purpose: Provide System Operators with the capabilities necessary to monitor and analyze data needed to

More information

Reading, Understanding, and Following NERC Standards

Reading, Understanding, and Following NERC Standards Reading, Understanding, and Following NERC Standards September 15, 2011 Greg Sorenson, PE Senior Compliance Engineer gsorenson.re@spp.org 501.688.1713 Outline Philosophy behind standards Reading standards

More information

Rochelle Municipal Utilities TRANSMISSION PLANNING CRITERIA. March 21, 2017

Rochelle Municipal Utilities TRANSMISSION PLANNING CRITERIA. March 21, 2017 Rochelle Municipal Utilities TRANSMISSION PLANNING CRITERIA March 21, 2017 Contents 1 Background...3 2 National and Regional Criteria and Guides...4 2.1 2.1 NERC Transmission Planning Standards...4 2.2

More information

Standard IRO Reliability Coordinator Data Specification and Collection

Standard IRO Reliability Coordinator Data Specification and Collection A. Introduction 1. Title: Reliability Coordinator Data Specification and Collection 2. Number: IRO 010 2 3. Purpose: To prevent instability, uncontrolled separation, or Cascading outages that adversely

More information

Appendix 5B. Statement of Compliance Registry Criteria

Appendix 5B. Statement of Compliance Registry Criteria Appendix 5B Statement of Compliance Registry Criteria Revision 5.1 Effective: July 1, 2014 (as noted below) The highlighted terms Bulk Electric System and Load in this document will become effective as

More information

Operating Procedure PURPOSE... 2

Operating Procedure PURPOSE... 2 No. 3100 Table of Contents PURPOSE... 2 1. RESPONSIBILITIES... 2 2. SCOPE/APPLICABILITY... 3 2.1. Background... 3 2.2. Scope/ Applicability... 3 3. PROCEDURE DETAIL... 4 3.1. Acceptable System Performance

More information

APPENDIX B PLANNING FRAMEWORK. This Appendix B describes the process to be used by the Midwest ISO in planning

APPENDIX B PLANNING FRAMEWORK. This Appendix B describes the process to be used by the Midwest ISO in planning FERC Electric Tariff, First Revised Rate Schedule No. 1 Original Sheet No. 103 I. Overview. PLANNING FRAMEWORK This Appendix B describes the process to be used by the in planning the Transmission System.

More information

Western Electricity Coordinating Council WECC Glossary of Terms and Naming Conventions Updated: December 6, 2016

Western Electricity Coordinating Council WECC Glossary of Terms and Naming Conventions Updated: December 6, 2016 Table of Contents Western Electricity Coordinating Council WECC Glossary of Terms and Naming Conventions Updated: December 6, 2016 Overview/Glossary Characteristics... 2 Terms Developed Using the WECC

More information

Risk-Based Registration Technical Justification. August 26, 2014

Risk-Based Registration Technical Justification. August 26, 2014 Risk-Based Registration Technical Justification August 26, 2014 Table of Contents Preface and NERC Mission... iv Executive Summary... v Introduction...1 Background...1 Functional Entities Considered...1

More information

Standard IRO Reliability Coordination Monitoring and Analysis

Standard IRO Reliability Coordination Monitoring and Analysis Page 349 of 577 A. Introduction 1. Title: Reliability Coordination Monitoring and Analysis 2. Number: IRO-002-4 3. Purpose: Provide System Operators with the capabilities necessary to monitor and analyze

More information