SEMOpx Day-ahead Market Products Stage 3 Progress Report. May 2017
|
|
- Nora Barrett
- 6 years ago
- Views:
Transcription
1 SEMOpx Day-ahead Market Products Stage 3 Progress Report May 2017
2 Contents 1 Introduction Purpose of the Document IAT STAGES Scope of IAT Structure of IAT Creation of Test Data by SEMOpx Performing Test Simulations Assessment of Results Stage Overview Goal Assumptions Outcome Stage Overview Goal Assumptions Outcome Stage Overview Goal EirGrid Commercial In Confidence. Page 1
3 8.3 Assumptions Outcome Next Steps Disclaimer EirGrid Commercial In Confidence. Page 2
4 1 Introduction EUPHEMIA is the day-ahead pricing algorithm currently in use throughout Europe to perform day-ahead market coupling. It was developed by the Price Coupling of Regions (PCR) initiative, an organisation of European power exchanges. The use of EUPHEMIA for the day-ahead market in the I-SEM is outlined in the SEM Committee s decision on the high level design (HLD) for the I-SEM (SEM A). In order to include the I-SEM in the day-ahead market (DAM) coupling performed by the PCR, it is necessary for SEMOpx to complete tests with the PCR to show that the impact of adding the new market is acceptable. These tests use a test set of data to represent the SEM, and other data, to simulate a period of test dates and assess the effect of this data on the performance of EUPHEMIA. Following this PCR testing, and appropriate assessment of results, the PCR will confirm the DAM coupling arrangements for I-SEM. However, it will not be possible for the PCR to undertake and conclude its testing until closer to I-SEM go-live. This, understandably, creates a period of uncertainty and an issue of confidence for SEMOpx stakeholders as to whether their requirements will be able to be accommodated in EUPHEMIA. To help mitigate the risk to the delivery of I-SEM of not receiving timely PCR approval, SEMOpx is undertaking some early tests of its own against the current version of EUPHEMIA to gain some insight and understanding prior to the formal PCR testing commencing. In particular, as is explained below, SEMOpx will use this interim testing of its own to assist in setting the parameters 1 for the formal PCR tests. SEMOpx is conscious of the importance of setting the parameters to manage this risk. To aid in the decisions on the final parameter settings, these early tests will look at multiple variations for representing the products 2, including both types and number of products represented. It is also hoped that these tests will provide market participants with the confidence they require about which products will be available to them in the I-SEM, thereby allowing them to progress their own I-SEM implementation projects during what would otherwise be a period of great uncertainty. This document outlines the strategy and progress in mitigating this risk and is updated periodically as further iterations of the SEMOpx tests are performed. Additionally these updates will outline any changes to the strategy which are deemed necessary following analysis of results. 1 The parameters to be used for PCR testing refer to any parameters within EUPHEMIA which will need to be set to represent the I-SEM DAM in EUPHEMIA. Primarily, the IAT is focused on the parameters relating to the products including the maximum number of each product. 2 In this context, the term products refers to the types of order (bid or offer) which may be submitted by a participant to SEMOpx for the DAM. As the I-SEM DAM will use EUPHEMIA, the products available will be based on the suite of products available in EUPHEMIA. EirGrid Commercial In Confidence. Page 3
5 2 Purpose of the Document This document outlines the SEMOpx internal assessments and test (IAT) approach, scope, goals and progress. In this latest release, it has been updated to detail in Section 8 the results of the third stage of testing, adding to the information presented in the previous two releases of the document detailed in Sections 6 and 7. It will be updated further as testing progresses, in order that participants are kept fully abreast of the latest developments. It should be noted that the IAT approach is not designed in any way to forecast or model the I-SEM DAM or any other market segments. While prices, schedules and other data are produced as a result of the IAT, assessment of these values is considered outside of the scope of the IAT and commentary on these results will not be included in this report. While the IAT is intended to inform SEMOpx s decision on the parameters to be used for PCR testing, it will only provide indicative information e.g. the test data is an estimation of the data which may be used in the PCR testing. Furthermore, the IAT does not form part of the PCR testing. The PCR s decision on the coupling arrangements for the I-SEM DAM is subject to their defined testing processes. The IAT is not a substitute for the PCR testing and it does not guarantee any outcome of that testing. In this context, please note the disclaimer in Section 9 of this report. An initial release of the document was published at the end of January 2017, represented as Milestone #61c Publication of report for PCR Change Request against Euphemia V.9.5 in the public Level 2 Milestone Plan for I- SEM. This summarised the outcome of an initial stage of IAT, which was based on an average level of DAM participation. Based upon an assessment of the results of that Stage 1, it was determined that the outcomes were sufficient to proceed to Stage 2 of the IAT, a stress test, where the complexity of the representation of the I-SEM DAM parameters would be expanded. The document was updated on 31 st March 2017 to provide parties with information on the actions SEMOpx took on the back of the results from Stage 2 of the IAT (e.g. any changes to the parameters). The document was further updated on 31 st May 2017 to provide information on Stage 3 of the IAT and further insight into the progress of the testing process. As detailed in later sections, following analysis of the Stage 3 results, SEMOpx are of the view that the current strategy for mitigating the risk associated with the uncertain outcome of PCR testing needs to be revisited. Further to this, the Stage 3 results have indicated challenges in the PCR assessment process beyond the parameters used to represent the I-SEM. Accordingly, this document outlines the issues encountered and the principles SEMOpx feel are appropriate for a revised risk mitigation strategy. 3 IAT STAGES As explained in Section 1 the key priorities of the IAT are to inform the decision on parameters to be entered for the PCR tests and support the decision-making process. Initially, two stages were proposed, namely: EirGrid Commercial In Confidence. Page 4
6 Stage Description Goal 1 Initial Benchmark Confirm data integrity of dataset and act as a benchmark for Stage 2. SEMOpx will represent an average scenario in this stage. 2 Stress Assessment Act as a stressed test with differing numbers of products represented. This stage will look to adapt the benchmark to investigate other representations of the market parameters. Table 1: IAT Stages Depending on the results of Stage 2, further IAT stages may follow in order for SEMOpx to develop the necessary insights to inform the setting of parameters to be used for PCR testing. That is, the results of testing may inform the recalibration of the parameters, which will necessitate additional testing to understand if the updated values achieve the desired results. This reiteration and refinement will be done subject to the timeframe required to complete PCR testing in line with the I-SEM go-live date. Following completion of IAT Stage 2, it was determined that at least one additional iteration would be required and that others would be allowed for as deemed necessary following review of testing results. The revised IAT stages are listed below. Stage Description Goal 1 Initial Benchmark Confirm data integrity of dataset and act as a benchmark for Stage 2. SEMOpx will represent an average scenario in this stage. 2 Stress Assessment Act as a stress test with differing numbers of products represented. This stage will look to adapt the benchmark to investigate other representations of the market parameters. 3 Revised Limit Assessment Act as a test to assess the effects of a revised set of limits as well as the impact to testing results of this revised set. This will adapt the dataset from Stage 2 to investigate a reduced set of limits. Table 2: Revised IAT Stages EirGrid Commercial In Confidence. Page 5
7 4 Scope of IAT As explained above, the IAT is designed to assess the I-SEM parameters in order to allow for timely identification of any potential issues (e.g. errors in test datasets) such that they may be addressed ahead of PCR testing. This will allow for a test dataset to be prepared in advance of the PCR testing and to inform the decision-making process for arriving at suitable parameters to represent the I-SEM. Assessment of multiple datasets will allow for due diligence to be applied by SEMOpx in arriving at the chosen parameters for the PCR testing and mitigate the risk that the PCR approval process takes longer than expected. 5 Structure of IAT An overview of the key steps of IAT is detailed below. 5.1 Creation of Test Data by SEMOpx For each stage of the IAT, SEMOpx will create a set of data to represent the I-SEM DAM. In order to provide a sufficiently large sample to assess the results, at least two years worth of historical data will be used based on the historical period from 01/05/ /04/2016. This data will include orders (bids and offers) which represent all relevant generator and supplier units in the I-SEM; these orders will be based on historical bid and offer data. It will also include representations of each interconnector based on historical capacity, ramping and loss values. While a dataset is required for each stage, the goal is to arrive at an appropriate dataset (i.e. a dataset which is robust in terms of limits) and then use this dataset in future tests in readiness for PCR testing. As the stages progress, SEMOpx may investigate datasets using different parameters for the purpose of assessing varying approaches. 5.2 Performing Test Simulations Once all data is compiled, tests will be performed. As the IAT is not an official test of the PCR, it will not be possible to replicate fully the conditions of the future PCR testing which will be applicable to the I-SEM DAM. As such, any results must be appropriately caveated and read in this context. 5.3 Assessment of Results Once all of the test data for a testing stage has been run through the process, the test results will be extracted and analysed. The analysis will consider the results and whether changes may be required to parameters for future tests. Whilst it is not possible to release these test results due to PCR confidentiality obligations, these reports will indicate the nature of any actions which SEMOpx is taking based upon the results for example, any changes to the parameters. EirGrid Commercial In Confidence. Page 6
8 6 Stage Overview Stage 1 was completed in late 2016; it was primarily designed to act as an initial benchmark and to prepare the process for stress testing in Stage Goal The goal of Stage 1 was to act as an initial benchmark for further testing. It was conducted over the two year historical and one year forecast periods using a set of data consistent with average participation in the DAM. The purpose of this stage was to assess the average scenario as a benchmark. Furthermore, this stage allowed for completion of the process to highlight and address any issues in the creation or conversion processes (i.e. the process applied to convert SEM data into the required format for testing). This was of benefit as, while the tools used to create data had been used in the I-SEM Trialling of EUPHEMIA 3, the tools used had not been used to create a dataset with as many days as required for the IAT or the PCR testing allowing any issues to be highlighted and addressed before they had an impact on the timing of the PCR testing. 6.3 Assumptions The dataset for Stage 1 testing stage was developed to reflect an average level of DAM participation, based on the following assumptions: All units present in the SEM historical day will be represented Each unit will be represented once only There will be a mix of simple, complex block and linked block orders The number of complex and block orders will represent average expected use of these order types o Each unit represented using a complex order will use one order per day o Block orders will cover a period of 8 hours o Each unit represented using linked block orders will use between 3 and 12 depending on the number of price quantity pairs in their commercial offer data (COD) o Complex and linked block orders will be used for baseload and mid-merit thermal units and pumped storage hydro units Values for wind and load will be taken from the respective ex-ante forecast values Other units will be represented using simple orders 3 EirGrid Commercial In Confidence. Page 7
9 6.4 Outcome Following an assessment of Stage 1 of the IAT by SEMOpx, it was decided that the results were sufficient to proceed to Stage 2 of the IAT, as planned. The priority identified for the first iteration of Stage 2 was to expand on complexity of the representation of the I-SEM DAM parameters. While a range of products was used in Stage 1, this represented an average case. SEMOpx, following assessment of the Stage 1 results, decided to expand the number of orders used for Stage 2. This was primarily aimed at increasing the number of complex and linked block orders for the I-SEM. This was expanded to represent hypothetical maxima of these orders in each test day in line with the goal of Stage 2. In order to be comprehensive, Stage 2 was followed by further testing with different maximum numbers of orders included. 7 Stage Overview Stage 2 of the IAT commenced in quarter ; it was primarily to act as an extension to the initial benchmarking as set out in Stage Goal The goal of Stage 2 was to act as an extension to the testing performed in Stage 1. Representing a significant step change in complexity, Stage 2 of the IAT was conducted using a set of data consistent with a higher level of participation in the DAM than that explored in Stage 1. This higher level of complexity reflected a level of participation in the market reflective of a consistent peak level of participation, as opposed to the average level of Stage 1 of the IAT, as well as reflecting potential market growth in order to assess values to be used as maximum limits on products. Furthermore, the goal was to assess if this higher level of participation identified any specific issues with products not seen in the average volumes assessed in the Stage 1 test. The final outcome of Stage 2 was to arrive at the list of expected SEMOpx products from the list of those marked for investigation during the I-SEM Trialling of EUPHEMIA, namely: Simple orders; Complex orders; Block orders; Linked block orders; and Exclusive Group orders. 7.3 Assumptions The key difference between the data used for Stage 2 and that used for Stage 1 was to expand the number of products used per day in order to assess the values required to provide limits which would offer a high level of EirGrid Commercial In Confidence. Page 8
10 flexibility in all offered products, while allowing an assessment of the maximum impact on EUPHEMIA performance that I-SEM would have. Development of the dataset for Stage 2 of the IAT was based on the following assumptions: All units present in the SEM historical day will be represented In order to create the number of orders required to represent this higher level of participation, each unit may be represented more than once using different products (e.g. the same unit represented using a complex order and a set of linked block orders) o Units may be represented multiple times using different values in products o Units may be represented multiple times using different products There will be a mix of simple, complex, block and linked block orders The number of complex and block orders will represent a high level of participation in the market, consistent with a significant stress test condition Values for wind and load will be taken from the respective ex-ante forecast values A number of units will be represented using simple orders. 7.4 Outcome Stage 2 did not highlight any specific issues with products. Following an assessment of Stage 2 of the IAT by SEMOpx, it was determined that the results were sufficient to support the products which SEMOpx expected to offer in the DAM, namely: Simple orders; Complex orders; Block orders; Linked block orders; and Exclusive Group orders. However, the results of Stage 2 were not conclusive about the limits appropriate for the SEMOpx exchange. Following assessment of the Stage 2 results, it was decided that: Additional stages of the IAT were required to assess the limits which will be applicable in SEMOpx for golive; and An initial set of limits should be put into the draft SEMOpx rules and operating procedures to ensure the necessary provision is included in the SEMOpx rules and operating procedures before they are finalised in June 2017 (Level 2 Plan Milestone #118); the values of these limits were expected to be updated at a later date following completion of the PCR testing (Level 2 Plan Milestone #61d). 8 Stage Overview Stage 3 of IAT took place in Q2 of It used a less complex dataset than that used in Stage 2 in order to assess the impact of reducing the number of products on the algorithm s performance. EirGrid Commercial In Confidence. Page 9
11 8.2 Goal The two primary goals of IAT Stage 3 were to: assess the impact of a reduced number of products (compared to Stage 2) on the test results; and use this insight to set an initial set of limits (i.e. maximum number of permitted products per day) for inclusion in the draft SEMOpx rules and operating procedures. To do this, the dataset used was a less complex version (i.e. a set of data using fewer total products per day) of the dataset used in Stage 2. This allowed SEMOpx to assess the impact of the reduced complexity on whether this could provide a sufficient level of confidence in the limits represented by the dataset for inclusion in the draft SEMOpx rules and operating procedures. 8.3 Assumptions Development of the dataset for Stage 3 was based on the following assumptions: The total number of orders would be less than in Stage 2 but more than in Stage 1; Other assumptions used will be consistent with Stage 2; and Testing conditions of Stage 2 will be replicated such that the only change is the number of products being reduced. The purpose of the dataset was to assess the impact to performance from a range of levels of complexity across the three stages in order to gain confidence in an appropriate set of product limits. 8.4 Outcome The Stage 3 results did not provide SEMOpx with sufficient confidence that the limits represented by the datasets in Stage 3 would pass the PCR testing. Accordingly, SEMOpx does not feel that these limit values are appropriate for inclusion in the SEMOpx rules and operating procedures as an initial set of limit values. As an initial set of limits will not be included at this time, the SEMOpx rules and operating procedures will initially mark all product limits as to be determined. As originally planned, the product limit values will be finalised following the PCR testing and the SEMOpx rules and operating procedures will allow for such updates. Furthermore, Stage 3 has highlighted underlying challenges in the PCR assessment process, beyond the parameters being used to represent the I-SEM. Following assessment of the Stage 3 results by SEMOpx, SEMOpx believes that further stages of IAT are highly unlikely to mitigate the risks associated with the PCR assessment process without tackling these underlying challenges. SEMOpx are now of the view that the current strategy for mitigating the risk associated with the uncertain outcome of PCR assessment process needs to be revisited. EirGrid Commercial In Confidence. Page 10
12 This revised strategy will need to: Address the challenges being faced in the PCR assessment process; Take account of the time constraints relating to market readiness for I-SEM go-live by providing participants with the necessary certainty they need when they need it; Take a multi-lateral approach to explore all avenues (e.g. SEMOpx representation on the NEMO Committee) available to resolve the issue including avenues available through co-operation with its service providers and the RAs; and Provide the best available solution for I-SEM go-live. The SEMOpx preferred solution remains an approach using the range of products outlined in section 7.4; however, it will be necessary for SEMOpx to assess both a reduced range of products and the numbers of each product. The purpose of this assessment is to find an appropriate balance between: Ensuring exchange members have a sufficient range of products to provide a functional day-ahead market for I-SEM go-live; and Ensuring that SEMOpx has a high degree of confidence that this range of products will receive PCR approval. 9 Next Steps SEMOpx will work to develop a revised strategy for progressing the SEMOpx DAM products. This will be aimed at developing the best approach to provide confidence in the SEMOpx products ahead of I-SEM go-live. This strategy will be communicated to market stakeholders through the appropriate I-SEM participant engagement forums (e.g. PMG meetings, stakeholder meetings etc.). This strategy will comprise of four key components: 1. Governance Process: SEMOpx will develop a strategy that appropriately escalates the issue of PCR change request assessment to the appropriate European governance committees including, inter alia, the PCR Committee and the NEMO Committee; 2. DAM Product Set for Go-live: SEMOpx will further investigate the appropriate product range for go-live and strategy for developing that range of products over time. SEMOpx will engage with the RAs and other stakeholders, as appropriate, in this process; 3. SEMOpx Rules and Operating Procedures: SEMOpx will continue to develop the SEMOpx rules and operating procedures on the basis that product limits will be determined at a later point following further investigation. SEMOpx will present the SEMOpx rules to the RAs for approval as scheduled, with limit values marked as to be determined ; and 4. Level 2 Milestones: SEMOpx will work with the RAs to introduce appropriate new milestones into the Level 2 Milestone Plan to provide visibility for all interested parties of the timings for upcoming activities and deliverables. These additional milestones will be progressed through the standard change control process. EirGrid Commercial In Confidence. Page 11
13 10 Disclaimer The Information is provided as is and no representation or warranty of any kind, express or implied, is made in relation to the Information and all such representations or warranties, express or implied, in relation to the Information are hereby excluded to the fullest extent permitted by law. No responsibility, liability or duty of care to you or to any other person in respect of the Information is accepted, and any reliance you or any other person places on the Information is therefore strictly at your own or their own risk. In no event will liability be accepted for any loss or damage including, without limitation, indirect or consequential loss or damage, arising out of or in connection with the use of the Information. By using or relying on the Information, you automatically consent to the terms and conditions of this disclaimer. In the event that the Information is provided by you, in whole or in part, to a third party for whatever reason you shall ensure that this disclaimer is included with the Information and brought to the attention of the third party. Copyright Notice All rights reserved. The entire publication is subject to the laws of copyright. This publication may not be reproduced or transmitted in any form or by means, electronic or manual, including photocopying without the prior written permission of EirGrid plc. EirGrid Plc 2017 The Oval, 160 Shelbourne Road, Ballsbridge, Dublin 4. Ireland. EirGrid Commercial In Confidence. Page 12
SEMOpx Day-ahead Market Products Stage 2 Progress Report. March 2017
SEMOpx Day-ahead Market Products Stage 2 Progress Report March 2017 Contents 1 Introduction... 2 2 Purpose of the Document... 3 3 IAT STAGES... 4 4 Scope of IAT... 4 5 Structure of IAT... 5 5.1 Creation
More informationI-SEM Trialing of EUPHEMIA: Initial Phase Results Overview. I-SEM EUPHEMIA Working Group 16 th April 2015
I-SEM Trialing of EUPHEMIA: Initial Phase Results Overview I-SEM EUPHEMIA Working Group 16 th April 2015 EUPHEMIA Workshop Agenda Background of EUPHEMIA algorithm Overview of background and goal of EUPHEMIA
More informationI-SEM Trialling of EUPHEMIA: Trial Plan
I-SEM Trialling of EUPHEMIA: Trial Plan 11 March 2015 CONTENTS 1 Introduction... 2 2 Final Plan... 3 2.1 Initial Phase... 3 2.2 Communication of Initial Phase Results... 3 2.3 Commercial Phase... 4 2.3.1
More informationI-SEM Business Liaison Group NEMO. 09 November2017
I-SEM Business Liaison Group NEMO 09 November2017 1 Agenda Update on NEMO Implementation Project TSO Counter trading Market Trial 2 Agenda Update on NEMO Implementation Project TSO Counter trading Market
More informationQuick Guide to the I-SEM
Quick Guide to the I-SEM 1 Contents 1 BACKGROUND... 3 2 THE NEW MARKET THE I-SEM... 6 3 HOW I-SEM WORKS... 7 4 IMPACT ON CONSUMERS... 9 5 I-SEM KEY BENEFITS... 10 Glossary of Key Terms... 11 2 1 BACKGROUND
More informationSection 3 Firm Access Quantities and Associated Transmission Reinforcements
GATE 3 FREQUENTLY ASKED QUESTIONS Latest Update May 2013 Section 3 Firm Access Quantities and Associated Transmission Reinforcements 1. What does the term Firm Access Quantity or FAQ mean? 2. I own or
More informationLFC Block Operational Agreement Ireland and Northern Ireland
LFC Block Operational Agreement Ireland and Northern Ireland For Publication; 05/10/2018 Notice This document, provided by EirGrid and SONI, is the draft for stakeholder consultation of the proposal for
More informationUPGRADE CONSIDERATIONS Appian Platform
UPGRADE CONSIDERATIONS Appian Platform ArchiTECH Solutions LLC 7700 Leesburg Pike #204 www.architechsolutions.com 703-972-9155 atsdelivery@architechsolutions.com TABLE OF CONTENTS Introduction... 3 Upgrade
More informationRegulatory Approach to Maintaining Local Security of Supply in Electricity
An Coimisiún um Rialáil Fóntas Commission for Regulation of Utilities Regulatory Approach to Maintaining Local Security of Supply in Electricity Information Paper Reference: CRU17346 Date Published: 18/12/2017
More informationGRID Implementation Plan SEA Screening Statement
GRID Implementation Plan 2017-2022 SEA Screening Statement 27 July 2016 GRID Implementation Plan 2017-2021 Project No: 32106700 Document Title: Document No.: Revision: 1 SEA Screening Statement 32106700_01_1
More informationI-SEM Testing Tariff High Level Options Consultation
I-SEM Testing Tariff High Level Options Consultation 02 June 2017 Version 1.0 EXECUTIVE SUMMARY Testing Tariffs are currently applied to Units Under Test (UUT) in the Single Electricity Market (SEM) on
More informationAlberta Capacity Market
Alberta Capacity Market Comprehensive Market Design (CMD 1) Design Proposal Document Section 1: Overview of the Alberta Capacity Market Prepared by: Alberta Electric System Operator Date: January 26, 2018
More informationConsultation report for the Channel CC Methodology proposal
Consultation report for the Channel CC Methodology proposal September 15 th, 2017 Disclaimer This assessment of stakeholders comments is submitted by all TSOs of the Channel Region to all NRAs of the Channel
More informationBusiness Process. BP_SO_12.1 Unit Testing
Business Process BP_SO_12.1 Unit Testing EirGrid and SONI support the provision of information to the marketplace by publishing operational data, processes, methodologies and reports. This information
More informationI-SEM Programme Project Office Programme Change Control Procedure
Project Office Programme Change Control Procedure Version: 1.1 FINAL Date: 8 March 2017 Document Control Production Authors Responsibility Date Jim McAllister I-SEM PMO 01/07/2015 Helen Mounsey I-SEM PMO
More informationGE/GN8640. Risk Evaluation and Assessment. Guidance on Planning an Application of the Common Safety Method on. Rail Industry Guidance Note
GN Published by: Block 2 Angel Square 1 Torrens Street London EC1V 1NY Copyright 2014 Rail Safety and Standards Board Limited GE/GN8640 Method on Risk Evaluation and Assessment Issue One; June 2014 Rail
More informationTomorrow s Energy Scenarios 2017 Summary Booklet
Tomorrow s Energy Scenarios 2017 Summary Booklet Planning our Energy Future EirGrid Tomorrow s Energy Scenarios Summary Booklet Planning our Energy Future Page 1 Introducing scenario planning At EirGrid,
More informationDirected Contracts Implementation
Integrated Single Electricity Market (I-SEM) Directed Contracts Implementation Decision Paper SEM-17-081 15 th November 2017 Table of Contents Acronyms... 3 1. Introduction... 4 1.1 Background... 4 2.
More informationConsultation on DS3 System Services Contracts for Interim Arrangements. DS3 System Services Implementation Project
Consultation on DS3 System Services Contracts for Interim Arrangements DS3 System Services Implementation Project 21 April 2016 Disclaimer EirGrid as the Transmission System Operator (TSO) for Ireland,
More informationTemplate for ToR for Transaction Advisory Services
Template for ToR for Transaction Advisory Services Addendum 1 Prepared by Genesis Analytics 4 December 2013 PPP TRANSACTION ADVISOR TERMS OF REFERENCE Terms of reference for transaction advisor services
More informationWEM Demand Forecasting Methodology. October Issues Paper
WEM Demand Forecasting Methodology October 2018 Issues Paper Important notice PURPOSE The purpose of this publication is to consult on the proposed scenarios, data sources and methodologies for forecasting
More information1. How can Ofgem ensure that sharper Cash Out incentives from the Significant Code Review:
1. How can Ofgem ensure that sharper Cash Out incentives from the Significant Code Review: encourage generators and suppliers to balance their own positions before gate closure, thus reducing the call
More informationNational Electricity Market Demand Forecasting Methodology. November Issues Paper
National Electricity Market Demand Forecasting Methodology November 2018 Issues Paper Important notice PURPOSE The publication of this Issues Paper commences AEMO s consultation on the effectiveness of
More informationGrid Code Review Panel Intermittent Generation Strategy Paper Date Raised: 18 July 2012 GCRP Ref: pp12/34 A Panel Paper by Steven Lam National Grid
Grid Code Review Panel Intermittent Generation Strategy Paper Date Raised: 18 July 2012 GCRP Ref: pp12/34 A Panel Paper by Steven Lam National Grid Summary The purpose of this paper is to describe the
More informationInitial Enrolment Project Feasibility Draft Report Consultation Document
Initial Enrolment Project Feasibility Draft Report Consultation Document Date issued: 11/11/2016 Consultation closes: 20/01//2017 Classification: DCC Public Contents 1 Executive Summary... 4 2 Introduction...
More informationChapter 3: The Scheduling & Chapter 4: The Scheduling and Dispatch Process
Chapter 3: The Scheduling & Chapter 4: The Scheduling and Dispatch Process 1 Foreword Our scheduling and dispatch process incorporates a range of activities associated with managing the close to real-time
More informationEY s submission to AEMO s 2019 Planning and Forecasting Consultation
EY s submission to AEMO s 2019 Planning and Forecasting Consultation Australian Energy Market Operator 20 March 2019 Release Notice Ernst & Young has prepared this submission for the benefit those using
More informationIntra-Day Trading Project. Market Participant Technical Overview. Conference call number: , pin: 79592
Intra-Day Trading Project Market Participant Technical Overview 3 rd August 2011, 10.30 am 13:00 pm Conference call number: 00353 1 6647777, pin: 79592 Welcome Welcome to this information session on the
More informationWaypoints Sequence Extension API
Waypoints Sequence Extension API Release Notes Version 2.0.0 Waypoints Sequence Extension API Release Notes 2 Contents Contents Legal Notices...3 Document Information... 4 Overview...5 Known Issues...
More informationworking with partnerships
A practical guide to: working with partnerships Practical step-by-step building blocks for establishing an effective partnership in the not-for-profit sector N 2 (squared) Consulting with Nottingham Council
More informationDS3 System Services Project Plan Detailed Design and Implementation Phase
DS3 System Services Project Plan Detailed Design and Implementation Phase Dated: 20/5/2015 Executive Summary The System Services work stream within the DS3 Programme relates to the procurement of services
More informationREPORT ON CONSULTATION ON DRAFT TRANSMISSION DEVELOPMENT PLAN
REPORT ON CONSULTATION ON DRAFT TRANSMISSION DEVELOPMENT PLAN 2016-2026 Table of Contents Abbreviations... 3 Glossary... 4 Introduction... 5 Description of Consultation Process... 5 Purpose of the Transmission
More informationWIND AND SOLAR FARMS TESTING REQUIREMENTS FOR CONTINGENCY FCAS REGISTRATION
WIND AND SOLAR FARMS TESTING REQUIREMENTS FOR CONTINGENCY FCAS REGISTRATION PREPARED BY: AEMO Operations Department Systems Performance & Commercial VERSION: 1.0 EFFECTIVE DATE: 5 October 2018 STATUS:
More informationWhat is the Carbon Price Support supporting?
2016 Aurora Energy Research Limited. All rights reserved. What is the Carbon Price Support supporting? An assessment of the impact of CPS removal post 2025 August 2016 Executive summary The intention to
More informationWEM OPERATIONAL CONTINGENCIES VERSION 3.0
WEM OPERATIONAL CONTINGENCIES VERSION 3.0 Published: November 2015 IMPORTANT NOTICE Purpose AEMO has prepared this document to provide information about AEMO s contingency procedures to deal with Market
More informationMarch Contents. Shrinkage Incentive Methodology Statement Review. UK Gas Transmission
March 2016 Contents ef Shrinkage Incentive Methodology Statement Review UK Gas Transmission 6 Contents 1 Executive Summary... 3 2 Background... 5 2.1 Introduction... 5 2.2 Overview of NTS Shrinkage...
More informationEVALUATION FRAMEWORK 2017
EVALUATION FRAMEWORK 2017 Contents Introduction 1 1. Background 2 2. Role and Overview of AMPC 4 3. Evaluation Framework 6 4. Strategic Alignment 12 5. Key Performance Information 14 6. Dissemination of
More informationInnovate 2 Succeed Invitation to Tender External Evaluator - June 2017
1. Introduction: Innovate 2 Succeed Invitation to Tender External Evaluator - June 2017 1.1 Invitation to Tender This is an invitation to submit a tender to provide services ( Services ) to meet the requirements,
More informationEuropean Commission DG Energy Unit B2: Wholesale markets, electricity & gas Office: DM24, 6th floor Rue De Mot 24 B 1049 Brussels/Belgium
European Commission DG Energy Unit B2: Wholesale markets, electricity & gas Office: DM24, 6th floor Rue De Mot 24 B 1049 Brussels/Belgium 6th February 2013 European Commission public consultation on generation
More informationSAMPLE. Not for training purposes. Assessor Guide. TAEASS502 Design and develop assessment tools. 2 nd Edition 2017
TAEASS502 Design and develop assessment tools 2 nd Edition 2017 Part of a suite of support materials for the TAE Training and Education Training Package Acknowledgement Innovation and Business Industry
More informationFlexibility and the outlook for the GB power market
Aurora Energy Research Limited. All rights reserved. Flexibility and the outlook for the GB power market Presentation to Demand Responsive, 11 May 217 Dr. Benjamin Irons, Director, Aurora Energy Research
More informationSystem Management Action. Flagging Methodology Statement. Version Date: [05 th November 2009]
System Management Action Flagging Methodology Statement Version Date: [05 th November 2009] System Management Action Flagging Methodology Statement 1 Version Control Date Version No. Notes 20.3.01 1.0
More informationIdentification Selection Definition Execution. Schedule.
SCHEDULE DEVELOPMENT Schedule development is the identification, definition and sequencing of activities that are required to be performed for successful completion of the project scope. Identification
More informationISO INTERNATIONAL STANDARD. Risk management Principles and guidelines. Management du risque Principes et lignes directrices
INTERNATIONAL STANDARD ISO 31000 First edition 2009-11-15 Risk management Principles and guidelines Management du risque Principes et lignes directrices http://mahdi.hashemitabar.com Reference number ISO
More informationTomorrow s Energy Scenarios 2017
Tomorrow s Energy Scenarios 2017 Planning our Energy Future EirGrid Tomorrow s Energy Scenarios Report Planning our Energy Future Page 1 Disclaimer EirGrid has followed accepted industry practice in the
More informationRecommended Values for I-SEM Scheduling and Dispatch Parameters
Recommended Values for I-SEM Scheduling and Dispatch Parameters Report to the Regulatory Authorities Version 1.0 10/05/2017 2017 EirGrid plc. Contents 1. SEM Committee Policy and Trading & Settlement Code
More informationResponse ELECTRICITY MARKET DESIGN AND THE GREEN AGENDA
Response ELECTRICITY MARKET DESIGN AND THE GREEN AGENDA Andreas EHRENMANN June 2018 Disclaimer: The opinions expresed in the presentation are those of the author alone and might not reflect the views of
More informationSemi-Scheduled Generation Dispatch Self-Forecast - Assessment Procedure Consultation. December Final Determination
Semi-Scheduled Generation Dispatch Self-Forecast - Assessment Procedure Consultation December 2018 Final Determination Important notice PURPOSE On 13 November 2018, AEMO invited written submissions on
More informationCapture full potential of the service business. Christian Venderby, Group SVP and Head of Service
Capture full potential of the service business Christian Venderby, Group SVP and Head of Service Aarhus, 12 June 2014 Disclaimer and cautionary statement This presentation contains forward-looking statements
More informationLines of Communication. Our New Approach to Consultation - Have Your Say
Lines of Communication Our New Approach to Consultation - Have Your Say Who are EirGrid - and what do we do? What is this guide for? EirGrid is responsible for a safe, secure and reliable supply of electricity:
More information2018 CMMI Institute 1
2018 CMMI Institute 1 Copyright 2018 CMMI Institute THIS CMMI INSTITUTE MATERIAL IS FURNISHED ON AN AS-IS BASIS. TO THE MAXIMUM EXTENT ALLOWED BY LAW, THE CMMI INSTITUTE SPECIFICALLY DISCLAIMS ALL WARRANTIES,
More informationBriefing on How Resource Adequacy Works in ISO s Current Balancing Authority Area
Briefing on How Resource Adequacy Works in ISO s Current Balancing Authority Area Regional Resource Adequacy Meeting December 16, 2015 Salt Lake City, Utah Keith Johnson Manager, Infrastructure Policy
More informationBusiness Requirements Specification
Business Requirements Specification Flexible Resource Adequacy Criteria and Must- Offer Obligation Revision History Date Version Description 5/30/2013 1.0 Creation of Document 7/21/2013 1.1 Deletion of
More informationSummary of analyst presentation 24 July Dialight plc. Half year results 2017
Dialight plc Half year results 2017 Summary of analysts presentation by: Michael Sutsko, Chief Executive Fariyal Khanbabi, Chief Financial Officer Page 1 Positioned for long-term sustainable growth Michael
More informationI-SEM Milestones. November 2017
I-SEM Milestones November 2017 1 1.1 Milestone Descriptions Includes update since the approval of JCR 170 Ref Milestone & Description RA / TSO Baseline Date 1 2 3 4 5 6 7a 7b 7c Start Balancing Market
More informationRoles and Responsibilities
Growth Deal Programme Roles and Responsibilities Appendix 17 The Programme Management Office A dedicated PMO has been established within Black Country Consortium Ltd to support all aspects of Black Country
More informationChapter 2: Inputs. Chapter 3: Inputs
Chapter 2: Inputs Chapter 3: Inputs 1 Foreword (1/2) This section describes the data inputs to the scheduling and dispatch process including the source of the data and how it is used. There are thousands
More informationREGISTERED CANDIDATE AUDITOR (RCA) TECHNICAL COMPETENCE REQUIREMENTS
REGISTERED CANDIDATE AUDITOR (RCA) TECHNICAL COMPETENCE REQUIREMENTS 1. Context After completion of the recognised training contract, a period of specialisation is required, appropriate to the level required
More informationMarket Trial Working Group I-SEM Project
Market Trial Working Group I-SEM Project Dublin, 31 August 2017 1 Overview of the Session Meeting Details Meeting Purpose Chair Secretariat I-SEM Market Trial Working Group Mark Needham Louise Dalton Amy
More informationSmart Metering Implementation Programme
Smart Metering Implementation Programme Consultation on Smart Metering Rollout Strategy DCC response 19 th May 2015 DCC PUBLIC Page 1 of 14 1 Executive Summary 1.1 Introduction and background 1. DCC provides
More informationJULY 2015 INITIATIVES PLAN FOR REGULATED TRANSMISSION SERVICES
JULY 2015 INITIATIVES PLAN FOR REGULATED TRANSMISSION SERVICES TABLE OF CONTENTS 1. INTRODUCTION... 3 1.1 Services Covered by the Initiatives Plan... 3 1.2 Activities Covered by the Initiatives Plan...
More informationStandards Management
Standards Management Publication and Change Management Policy Version: 1.1 Final Date: 03/07/2017 Distribution: Industry DISCLAIMER Origo Services Limited believes it has employed personnel using reasonable
More informationJune 2017 DISCLAIMER
Channel TSOs proposal of common capacity calculation methodology for the day-ahead and intraday market timeframe in accordance with Article 20 of Commission Regulation (EU) 2015/1222 of 24 July 2015 establishing
More informationLow-Level Design Validation and Testing
Low-Level Design Validation and Testing Service Description Document November 2009 Contents 1. Introduction... 2 2. Eligibility and Prerequisites... 2 3. Service Features and Deliverables... 2 4. Customer
More informationEWEA Response to the European Wind Integration Study (EWIS) Report Main Conclusions in a Nutshell
EWEA Response to the European Wind Integration Study (EWIS) Report Main Conclusions in a Nutshell A consortium of Transmission System Operators (TSOs) carried out the European Wind Integration Study (EWIS)
More informationConsultation on DS3 System Services Market Ruleset. DS3 System Services Implementation Project
Consultation on DS3 System Services Market Ruleset DS3 System Services Implementation Project 15 March 2018 Disclaimer EirGrid as the Transmission System Operator (TSO) for Ireland, and SONI as the TSO
More informationXXXXX. Bremner Trio Small Hydro Project. Interconnection Facilities Study and Project Plan
XXXXX Bremner Trio Small Hydro Project Interconnection Facilities Study and Project Plan June 25, 2011 British Columbia Hydro and Power Authority British Columbia Hydro and Power Authority 2011. All rights
More information11/02/2016. The Scheduling & Dispatch Process in I-SEM - Design Interpretation
11/02/2016 The Scheduling & Dispatch Process in I-SEM - Design Interpretation Release Date Version No. Summary of Changes 11/02/2016 1.0 Design Interpretation document published for discussion at Market
More informationAll NEMOs proposal for the price coupling algorithm and for the continuous trading matching algorithm, also incorporating TSO and NEMO proposals for
All NEMOs proposal for the price coupling algorithm and for the continuous trading matching algorithm, also incorporating TSO and NEMO proposals for a common set of requirements, in accordance with Article
More informationTomorrow s Energy Scenarios 2017 Locations Consultation
Tomorrow s Energy Scenarios 2017 Locations Consultation Planning our Energy Future EirGrid Tomorrow s Energy Scenario 2017 Locations Consultation Planning our Energy Future Page 1 Disclaimer EirGrid has
More informationManagement of Shared Information Systems
To be superseded by GERT8054 Iss 2 published on Railway 03/09/2011 Group Standard Management of Shared Information Systems Synopsis This document defines the requirements for managing shared information
More informationResponses to: ACER public consultation on the influence of existing bidding zones on electricity markets
Responses to: ACER public consultation on the influence of existing bidding zones on electricity markets 30 September EUROPEX Rue Montoyer 31 Bte 9 BE-1000 Brussels T. : +32 2 512 34 10 E.: secretariat@europex.org
More informationConsultation on DS3 System Services Scalar Design
Consultation on DS3 System Services Scalar Design DS3 System Services Implementation Project 11 March 2015 Disclaimer EirGrid as the Transmission System Operator (TSO) for Ireland, and SONI as the TSO
More informationMonitoring the impact of onshore wind farms on birds - January 2009
Guidance te Monitoring the impact of onshore wind farms on birds - January 2009 Introduction 1. As the number of wind farms constructed in Scotland increases the need to understand the impact that these
More informationAUDIT GUIDELINES: ELECTRICITY, GAS AND WATER LICENSING: AUDIT TEMPLATE FOR SMALLER ORGANISATIONS
AUDIT GUIDELINES: ELECTRICITY, GAS AND WATER LICENSING: AUDIT TEMPLATE FOR SMALLER ORGANISATIONS This document is available from the Economic Regulation Authority website www.era.wa.gov.au. For further
More informationSOUTH AUSTRALIA VICTORIA (HEYWOOD) INTERCONNECTOR UPGRADE
26 October 2012 Hugo Klingenberg Senior Manager Network Development Electranet Pty Ltd consultation@electranet.com.au Ashley Lloyd Senior Manager Victorian Planning Australian Energy Market Operator planning@aemo.com.au
More informationOracle Value Chain Planning Demantra Demand Management
Oracle Value Chain Planning Demantra Demand Management Is your company trying to be more demand driven? Do you need to increase your forecast accuracy or quickly converge on a consensus forecast to drive
More informationRequest for Proposal Energy Efficiency (Conservation) Potential Assessment and Modeling Software Tool
Energy Efficiency (Conservation) Potential Assessment and Modeling Software Tool Issued: April 27, 2018 Responses Due: June 8, 2018 Contact: Lori Blattner, Manager Energy Efficiency & Regulatory Process
More informationof your sustainability strategy
of your sustainability strategy Carbon Trust Advisory 140bn 48% The market for low-carbon goods and services is set to grow by 5 billion a year to 140 billion by 2015 in the UK 1 The average internal rate
More informationStorage as a Transmission Asset Stakeholder Comment Template
Storage as a Transmission Asset Stakeholder Comment Template Submitted by Company Date Submitted Fernando E. Cornejo fernando.cornejo@sce.com Southern California Edison November 6, 2018 Please use this
More informationRISK STATEMENT & ASSURANCE PLAN. Statement of risks, strengths and weaknesses and draft assurance plans for 2015/16. For consultation.
RISK STATEMENT & ASSURANCE PLAN Statement of risks, strengths and weaknesses and draft assurance plans for 2015/16. For consultation. November 2015 About this document Severn Trent Water is one of the
More informationLMEshield. Frequently Asked Questions
May 2017 LMEshield LMEshield is the LME s central electronic register providing global off-warrant commodity receipting. The system supports and enables lending by addressing uncertainties surrounding
More informationProduct Roadmap. Restoration
Product Roadmap Restoration May 2018 This page is only needed for interactive version Product Roadmap 01 Foreword Today we are publishing a roadmap of actions to shape the future of system restoration.
More informationEn.Trading 017 Seminar
Independent Bulgarian Energy Exchange En.Trading 017 Seminar Market Coupling and further developments on the Bulgarian PX Regional markets status Readiness for market integration, set-up and perspectives.
More informationWHITE PAPER JUNE Running a Successful Global Payroll Implementation
WHITE PAPER JUNE 2017 Running a Successful Global Payroll Implementation CONTENTS Management Summary 3 Transition from procurement to implementation 5 Preparation 6 Project Management 8 Change Management
More informationTrusted KYC Data Sharing Framework Implementation
July 2017 Trusted KYC Data Sharing Framework Implementation Supporting Document Contents Preface... 3 1 Objective of this Document... 4 2 Evolving Benefits Provided by the Data Sharing Environment... 5
More informationProject Charter. A. General Information
A. General Information Project Title: Brief Project Description: Prepared By: Date: Version: B. Project Objective: Explain the specific objectives of the project. For example: What value does this project
More informationBalancing Market Principles Statement A Guide to Scheduling and Dispatch under the Revised Single Electricity Market Arrangements
Balancing Market Principles Statement A Guide to Scheduling and Dispatch under the Revised Single Electricity Market Arrangements CONSULTATION VERSION 7 April 2017 IMPORTANT INFORMATION This Balancing
More informationNEM EVENT - DIRECTION TO SOUTH AUSTRALIA GENERATOR - 9 FEBRUARY 2017
NEM EVENT - DIRECTION TO SOUTH AUSTRALIA GENERATOR - 9 FEBRUARY 2017 Published: July 2017 IMPORTANT NOTICE Purpose AEMO has prepared this report in accordance with clause 3.13.6A(a) of the National Electricity
More informationElectric Ireland response to CER/15/272 Proposed Decisions on Empowering & Protecting Customers
Smart Metering Programme Office Commission for Energy Regulation, The Exchange, Belgard Square North, Tallaght, Dublin 24. 22 nd January 2016 response to CER/15/272 Proposed Decisions on Empowering & Protecting
More informationwww.adaptaconsulting.co.uk Adapta Consulting is a CFG Corporate Subscriber Published by Adapta Consulting First published 2013 Copyright Adapta Consulting All rights reserved No part of this book may be
More informationE2/67. Green Evaluation City of Gothenburg. Transaction Overview. Green Evaluation Overview. Overall Score. Transaction Transparency.
Green Evaluation City of Gothenburg Transaction Overview On June 15, 2016 the City of Gothenburg, Sweden issued Swedish krona (SEK) 1 billion of green bonds due June 15, 2022 to fund a number of eligible
More informationTomorrow s Energy Scenarios 2017 Locations
Tomorrow s Energy Scenarios 2017 Locations Planning our Energy Future EirGrid Tomorrow s Energy Scenario 2017 Locations Planning our Energy Future Page a Disclaimer EirGrid has followed accepted industry
More informationDelivering Business Results Today by Using Tomorrow s Field Optimisation Engine
INSTR COVE 1. 2. 3. 4. 5. Delivering Business Results Today by Using Tomorrow s Field Optimisation Engine S t G C C L u INSTR IMAG 1. 2. 3. C G T o 4. T t Kai Eberspaecher / Antony Wauchope October 2017
More informationGIB Offshore Wind Fund
January 017 Executive summary The Sustainable Finance Team of the Green Investment Bank plc ( GIB ), acting on behalf of GIB Financial Services (GIB FS), has assessed the Green Impact of the Projects which
More informationTG 16 SOUTH AUSTRALIAN WATER CORPORATION
TG 16 SOUTH AUSTRALIAN WATER CORPORATION TECHNICAL GUIDELINE Checklist: Detail Design of Major Wastewater Collection Infrastructure Issued by: Principle Engineer Water & Wastewater s Issue Date: 10 January
More informationENERGY PORTFOLIO MAN AGEMENT. Hydro and pump storage modelling in ABB Ability PROMOD Benchmark report
ENERGY PORTFOLIO MAN AGEMENT Hydro and pump storage modelling in ABB Ability PROMOD Benchmark report TABLE OF CONTENTS Table of Contents 1 ABSTRACT... 1 2 INTRODUCTION... 1 2.1 Hydro Modelling... 1 2.2
More informationProposal for a common set of requirements used for the continuous trading matching algorithm
Proposal for a common set of requirements used for the continuous trading matching algorithm 13 November 2017 1. Background 1. This document is a common proposal developed by all Transmission System Operators
More informationSystem Management Action Flagging Methodology Statement
System Management Action Flagging Methodology Statement Effective Date: 01 April 20172018 Version Number: 910.0 Published in accordance with Standard Condition C16 of National Grid Electricity Transmission
More informationORACLE HYPERION PLANNING
ORACLE HYPERION PLANNING KEY FEATURES AND BENEFITS KEY FEATURES: Multi-dimensional / multi user planning with a powerful business rules engine Flexible workflow and plan management capabilities Comprehensive
More information