1 IPMC 2012 PS-24 Successful Path to DCMA EVMS Validation Kevin Fisher Orbital Sciences Corporation , Kevin Fisher on LinkedIn December 11,

2 Learning Objectives Understand the Path that Orbital used to Achieve EVMS Validation from DCMA the First Time Through Determine if Orbital s Methodologies can Benefit your Organization's Validation Project and/or Continuous Improvements Efforts 2

3 Agenda Group Survey Understanding Contract Requirements Self Assessment and Customers Building People System Tools & Architecture Processes & Documentation Demonstrating Validation Review Preparation Validation Review Experience Decisions and Discussions Reflecting DCMA Observations Lessons Learned Questions 3

4 Group Survey Who is Responsible for Performing EVMS in their job? Do you Submit Customer Deliverables (IMS and/or CPR)? Does your Contract Require EVMS Compliance? Does your Company have an Accepted EVMS? Is Anyone in a Company Preparing for a Validation Review? Has Anyone Been on a Team that Supported a Validation Review? Did the Company Get Ready Before the Potential Award? 4

5 Contract Requirement for EVMS DoD Earned Value Management Implementation Guide 5

6 Self-Assessment and Customer Expectations 3 Operating Groups LSG 1998 Advance Agreement SSG Commercial APG Mix of Customers and Requirements Dulles Campus Heritage & Culture 6

7 PMI Conference (Nov08) Best Practices Joint NDIA/DCMA EVM Center Presentation 7

8 DCMA Watch List from PAV 1. PM, CAM ownership, inattention to budgetary responsibilities 2. Work authorization policies and procedures not always followed 3. Budget/data reconciliation issues 4. Lack of integrated management systems 5. Baseline fluctuations and frequent replanning 6. Current period and retroactive changes 7. Improper use of Management Reserve and Undistributed Budget 8. EV techniques not reflecting actual accomplishment 9. Untimely, unrealistic Latest Revised Estimates 10. Not monitoring progress in an integrated way 11. Zero budget work packages and control accounts 12. Lack of vertical and horizontal traceability (critical path) 13. Lack of critical subcontractor integration/oversight 14. Material performance and accounting misalignment 15. Not capturing and using cost and schedule data 16. Poor root cause and predictive variance analysis 17. Not tracking corrective actions to resolution 18. Managerial actions not demonstrated 19. Lack of checks & balances (internal controls) and surveillance 8

9 System Architecture APG System Architecture Alignment 9

10 People -Team Success Executives Program / Control Account Management Business Team Project Lead Program Control Planning / Scheduling Material Control Program Finance Business Systems / Cost Mgmt System Expert Contracts Technical Writing Supply Chain / Subcontract Mgmt Accounting Operations Compliance Consultants / 3 rd Party Reviews Internal Surveillance & Audit DCMA Contract Execution Surveillance Functional Management Prime Contractor / Customer Oversight 10

11 People Training & Support EVMS Training Functional Department Humphrey s Fundamentals Class CAM 15-Module Curriculum Supplemental / Special Topics Training Video-Based Mil-Std WBS Sample Program for Tools / Training New Program Kick-off Meeting Support One-on-One CAM / PMO Mentoring (External Support, Peer-to-Peer) Group Mentoring Sessions / Mock Interview Program CAM-Centric Tools ecam Notebook overlays Standard Directory Structure winsight with Custom Views / Filters EVMS System Description Walk-Down and Storyboards CAM / PMO Interview Guide for Customer EVMS / Baseline Reviews CAM / PMO On-Line Assessments and Certification CAM Transition Process for Knowledge / Execution Transfer Professional Development Planning & Scheduling Professional (PSP)- AACE Earned Value Professional (EVP)- AACE Project Management Professional (PMP)- PMI 11

12 System Tools Architecture Proposal Planning Cost Management Reporting Integrated Cost and Schedule Single point of data entry Data moves between system pairs Commercial Products and Custom Solutions Integrity Checks Any resource can produce incorrect data under the wrong circumstances Checks are scalable and continuously improving Consistency Our standard data flow is the nucleus for many of our processes. Similarity between program baseline, month-end processing, and baseline change processes. 12

13 Processes & Documentation Industry Publications were Primary References as Documentation was Developed - Numerous Documents Released by Government & Industry (DoD, NASA, NDIA.) 13

14 Processes & Documentation Management Control System Description CDM-controlled & Submitted to DCMA / DCAA Supported by Progressively More Detailed Operational Docs Process Guides Application Guides Desktop Instructions Business Operation Directives Templates and Instructional Forms Checklists Presentations Developed for Specific Events Training and Professional Development Integrates With Other Documents / Systems Disclosure Statement Cost Estimating System Operating Group and Corporate Policies ISO Documentation and Processes Audited Results and Processes DCMA / DCAA Customer Internal Surveillance Corporate Internal Audit PwC ISO Industry Representation and Presentations 14

15 The Validation Review Getting Ready and Data Drops 3 rd Party Assessment & Interviews Comprehensive Data Drop DCMA Used Data Miner Data Analysis Responses Cross Reference Checklist System Description Decomposed Mock Interviews for All Participants 15

16 The Validation Review Experience DCMA In-Brief & Exit-Brief DCAA Operates Concurrent Review Company Executive Commitment Statement Executives may be Interviewed on Mgmt Reporting Company In-Briefs Program Brief System Overview Business Systems / Data Flow Data Trace / Storyboard Manager / Functional Pre-Completed Interviews Program Manager Control Account Managers Business Manager Risk Manager Scheduling Material Subcontract Manager Accounting & Indirects VR Report / DRs / Contractor Response 16

17 The Long & Winding Road To Acceptance Orbital Followed the 24-Step Process with DCMA / DCAA In Conjunction with External Surveillance on Compliant Programs 4-Years to Our Destination Jan 2008 Kickoff Using Orion Program Jun 2009 Progress Assist Visit / DCAA Initiates Separate Review Mar 2010 Validation Review Canceled due to Orion Termination Jul 2010 F6 Program Termination Dec 2010 VR Notification with Angels as Demonstration Program Angels 6-month Suspension due to Funding / 6-weeks to Resume Apr rd Party Mock Review, DCAA Starts, DCMA Data Drop Jun 2011 Validation Review (2-weeks, 16 Personnel) Jul 2011 Initial Determination Report Received Aug 2011 Initial Determination Response Submitted with DR Actions Nov 2011 Discrepancy Report Actions Accepted Jan 2012 Letter-of-Acceptance / Advance Agreement 17

18 New DCMA Process DCMA is Emphasizing Contractor Preparation as Shown in Compliance Review Instruction Contractor Self- Assessment using DCMA Assessment Tools versus Progress Assist Visit (PAV) mil/39/index.cfm 18

19 Significant Decisions & DCMA Discussion Topics Resource Loaded, Schedule-Driven EVMS Process Requires Enhanced Skill Set within Planning / Scheduling Group Schedule Margin Tasks ACWP at the WP-level / Charge Number Proliferation Subcontractor UB & MR Treatment Consistency Subcontractor BAC and PO Reconciliation by CA MR used to Budget for changes below Contract Threshold Quantifiable Backup Data (QBD) and X/Y Determination Communication Methods Program Addendum, Program Directives & Business Directives Indirect Rate Management, Publication, Thresholds & Variance Analysis Variance Analysis Reports 19

20 DCMA Observations of Orbital Success Demonstrated Upper Management Commitment Attitude was Receptive & Cooperative Resulting in Effective Relationship Quick Responses During VR & Initial Determination Led to Accelerated Closure / Acceptance Modern, Automated Tools with Limited Manual Processes High Level of Data Integrity 20

21 Lessons Learned System Acceptance is a Big Investment Demonstration Program Customer will be Impacted Not a Part-Time Job Staff Properly & Run like a Project Hit Your Deadlines & Make Sure you Pass the 1 st Time Try to have Validation Applicable to All Contract Types (Development & Production) Consultants can be Important to Success but may give Conflicting Guidance Don t let the Debates Continue Pick a Path & Move Forward Prime Contractor Management They are Responsible to Provide Oversight but Don t Let Drive Decisions Supply Chain Flowdowns& Management Suppliers Require Significant Attention Need Experienced, Knowledgeable Personnel on Team Sub Data can Undermine System Validation IBRs & Internal /External Surveillance Needs to be Ready out of the Gate Expect Personnel Turnover in CAM & BusOps Engineers not Generally Receptive Consider Program Control Staff to Bridge Knowledge & System Interface Prepare to Tailor Internal EVMS Reqs for Commercial / FFP programs 21

22 Commit to Continuous Improvement Continuous Improvement and EVMS Maturation are Important Factors in Improving Efficiency, Effectiveness and Competitiveness Performed Repeatable Defined Quantitative Optimized Individual Program Analysis System Surveillance Surveillance Management EVMS Planning Across Programs Program Analysis System Surveillance Surveillance Management Enterprise(corporate/division) Application Program Analysis System Surveillance Quantitative EVMS Enterprise Decision-making with EV Continuous Process Management Innovation 22

23 Questions??? 23

Understanding Requirements for Subcontract EV flow down and Management

Understanding Requirements for Subcontract EV flow down and Management Understanding Requirements for Subcontract EV flow down and Management Introduction The purpose of an Earned Value Management System (EVMS) is to accurately portray the project plan, changes, status, costs,

More information

How to prepare for a DOE EVMS Certification

How to prepare for a DOE EVMS Certification Earned Value Management Practitioners Forum 2018 How to prepare for a DOE EVMS Certification Instructor: Basil A. Soutos, Founder & Principal Company: Samos Advisors LLC (M) 703-409-5941 Email: bsoutos@samosadvisors.com

More information

Surveillance Guide. National Defense Industrial Association Integrated Program Management Division. Revision 3. November 5, 2018

Surveillance Guide. National Defense Industrial Association Integrated Program Management Division. Revision 3. November 5, 2018 National Defense Industrial Association Integrated Program Management Division Surveillance Guide Revision 3 November 5, 2018 National Defense Industrial Association (NDIA) 2101 Wilson Blvd., Suite 700

More information

The Integrated Baseline Review (IBR)

The Integrated Baseline Review (IBR) Page 1 of 10 The Integrated Baseline (IBR) The IBR management review is concerned more with the technical planning aspects and understanding how a contractor manages a project than past reviews that focused

More information

Preparing for the Future: Electronic Data Delivery and the DCMA Automated Surveillance Process

Preparing for the Future: Electronic Data Delivery and the DCMA Automated Surveillance Process Preparing for the Future: Electronic Data Delivery and the DCMA Automated Surveillance Process Dave Scott, BDO USA, dmscott@bdo.com Date: January 18, 2018 Learning Objectives Understand the new DCMA automated

More information

Using your EAC as a GPS 6 Characteristics of a Good EAC. Kim Koster, Senior Director IPM

Using your EAC as a GPS 6 Characteristics of a Good EAC. Kim Koster, Senior Director IPM Using your EAC as a GPS 6 Characteristics of a Good EAC Kim Koster, Senior Director IPM Top Ten Reasons Projects Fail BAD plans and inadequate planning processes Proposal not adequate Lack of scope comprehension

More information

Earned Value Management Training Program Course Brochure and Competency Matrix

Earned Value Management Training Program Course Brochure and Competency Matrix Earned Value Management Training Program Course Brochure and Competency Matrix INDEX: 1. Company Introduction 2. Training Program Description 3. Training Delivery Options 4. Course Syllabus 5. Program

More information

How DCMA data driven metrics may be used for continuous EVMS process improvement

How DCMA data driven metrics may be used for continuous EVMS process improvement BDO INDUSTRY SPECIALTY SERVICES GROUP Program Optimization and Project Controls Solutions How DCMA data driven metrics may be used for continuous EVMS process improvement Dave Scott, dmscott@bdo.com dmscott@bdo.com

More information

01/16/2019 Ellen Barber Lunch n Learn Integrated Baseline Review

01/16/2019 Ellen Barber Lunch n Learn Integrated Baseline Review 01/16/2019 Ellen Barber ellen.barber@dau.mil Lunch n Learn Integrated Baseline Review Agenda Who are we? BLUF: What is an Integrated Baseline Review IBR Objectives Who must do an IBR? Current guidance

More information

Program managers (PMs)

Program managers (PMs) BEST PRACTICES Integrating Systems Engineering with Earned Value Management Program managers (PMs) expect their supplier s earned value management system (EVMS) to accurately report the program s integrated

More information

QUICK START GUIDE. SQF Implementation. for.

QUICK START GUIDE. SQF Implementation. for. QUICK START GUIDE for SQF Implementation www.22000-tools.com CONTENTS WHAT IS SQF? BENEFITS OF SQF SQF LEVELS SQF MODULES IMPLEMENTING SQF AND PREPARING FOR CERTIFICATION ASSIGN YOUR PEOPLE RESOURCES

More information

Business Value and Customer Benefits Derived from High Maturity

Business Value and Customer Benefits Derived from High Maturity CMMI sm Technology Conference and User Group November 2002 Business Value and Customer Benefits Derived from High Maturity Alan Pflugrad Northrop Grumman Information Technology Defense Enterprise Solutions

More information

Integrated Baseline Review (IBR) Guide

Integrated Baseline Review (IBR) Guide National Defense Industrial Association Program Management Systems Committee Integrated Baseline Review (IBR) Guide Revision 1 September 1, 2010 National Defense Industrial Association (NDIA) 2111 Wilson

More information

CMMI Project Management Refresher Training

CMMI Project Management Refresher Training CMMI Project Management Refresher Training Classifica(on 2: Foxhole Technology Employees Only RMD 032 Project Management Refresher Training Course September 21, 2017 Version 1.0 The Process Approach The

More information

Quantitative Prediction and Improvement of Program Execution A New Paradigm

Quantitative Prediction and Improvement of Program Execution A New Paradigm Quantitative Prediction and Improvement of Program Execution A New Paradigm Dr. Shawn Rahmani Boeing Defense, Space/Security Huntington Beach, California NDIA 16 th Annual SE Conference October, 2013 See

More information

Acquisition Reform: Integrate Technical Performance with Earned Value Management

Acquisition Reform: Integrate Technical Performance with Earned Value Management Acquisition Reform: Integrate Technical Performance with Earned Value Management Paul Solomon, PMP Performance-Based Earned Value www.pb-ev.com paul.solomon@pb-ev.com NDIA Systems Engineering Conference

More information

EDWARDS PERFORMANCE SOLUTIONS

EDWARDS PERFORMANCE SOLUTIONS REVISED: J 5523920 PORTFOLIO MANAGEMENT SIZE STANDARD: $7.0M Edwards Project Solution ( ) provides portfolio management services through building enterprise project management solutions and providing portfolio

More information

Preparing for a Successful EVMS Certification

Preparing for a Successful EVMS Certification WRPS-48898-FP Revision 0 Preparing for a Successful EVMS Certification Prepared for the U.S. Department of Energy Assistant Secretary for Environmental Management Contractor for the U.S. Department of

More information

GAO Best Practices Guides

GAO Best Practices Guides GAO Best Practices Guides Karen Richey 2017 EVMP Forum August 24 th & 25 th 1 Learning Objectives Become familiar with various GAO best practices guides used to develop audit findings Introduction to Cost

More information

Performance-Based Earned Value

Performance-Based Earned Value Performance-Based Earned Value NDIA Systems Engineering Conference San Diego, CA October 25, 2006 Paul J. Solomon, PMP Performance-Based Earned Value Paul.Solomon@PB-EV.com 1 Agenda DoD Policy and Guidance,

More information

Contractors Purchasing System Review

Contractors Purchasing System Review Contractors Purchasing System Review Jeffery A. White, C.P.M. February 2016 Our Mission Statement With constant and ever changing challenges in a procurement environment, J.A. White & Associates, Inc.

More information

Contractor Business Systems Earned Value Management, Material Management and Accounting, and Property Management

Contractor Business Systems Earned Value Management, Material Management and Accounting, and Property Management McKenna Government Contracts, continuing excellence in Dentons Contractor Business Systems Earned Value Management, Material Management and Accounting, and Property Management Michael McGuinn, Dentons

More information

Delivering End-to-End Supply Chain Excellence

Delivering End-to-End Supply Chain Excellence Delivering End-to-End Supply Chain Excellence -The DCMA Perspective- Ms. Marie A. Greening Director, Operations and Aeronautical Systems Divisions 19 March 2009 DCMA Mission We provide Contract Administration

More information

Agility in DoD Acquisition

Agility in DoD Acquisition Agility in DoD Acquisition Gordon M. Kranz gmkranz@eipm-llc.com gordon.kranz@agileforgovernment.com 1 Agenda Framework Agile Guidance Agile EVM in the DoD Measuring for Sustained Success 2 Government Digital

More information

Managing Project Portfolio. Contents are subject to change. For the latest updates visit

Managing Project Portfolio. Contents are subject to change. For the latest updates visit Managing Project Portfolio Page 1 of 7 Why Attend The overall aim of this course is to provide participants with a generic and practical methodology to build and manage a balanced project portfolio. The

More information

Leading KPIs of Positive Financial Performance. Presented by: Hugh Shaw, Ventera Corporation Bill Riviere, Unanet

Leading KPIs of Positive Financial Performance. Presented by: Hugh Shaw, Ventera Corporation Bill Riviere, Unanet Leading KPIs of Positive Financial Performance Presented by: Hugh Shaw, Ventera Corporation Bill Riviere, Unanet Introduction Hugh Shaw (Ventera Corporation) Bill Riviere (Unanet) 2 KPI Introduction Monitoring

More information

Achieving Benefits in Project and in Program Management Guidelines for Success. Here Is What We Will Cover

Achieving Benefits in Project and in Program Management Guidelines for Success. Here Is What We Will Cover Achieving Benefits in Project and in Program Management Guidelines for Success Dr. Ginger Levin, PMP, PgMP Certified OPM3 Professional A Member of PMI s Registered Consultant Program linkedin.com/in/gingerlevin

More information

EVMax Feature List. Configuration, Setting Up Core Data ProjStream 1

EVMax Feature List. Configuration, Setting Up Core Data ProjStream 1 EVMax List Configuration, Setting Up Core Data Set up an unlimited number of user defined fields to support project unique data views and reporting requirements Import from anywhere using MS Excel Establish

More information

STUDENT GUIDE. CON 170 Fundamentals of Cost & Price Analysis. Unit 5, Lesson 1 Cost Analysis Process, Players, and Business Systems

STUDENT GUIDE. CON 170 Fundamentals of Cost & Price Analysis. Unit 5, Lesson 1 Cost Analysis Process, Players, and Business Systems STUDENT GUIDE CON 170 Fundamentals of Cost & Price Analysis Unit 5, Lesson 1 Cost Analysis Process, Players, and Business Systems January 2017 CON170, Unit 5 Lesson 1 Cost Analysis Process and Players

More information

Performance Assessments and Root Cause Analyses

Performance Assessments and Root Cause Analyses APPROVED FOR PUBLIC RELEASE DISTRIBUTION UNLIMITED: 15-S-1951, 15 JUL 2015. 0 Performance Assessments and Root Cause Analyses August 13, 2015 Mr. Gary Bliss Director, PARCA gary.r.bliss.civ@mail.mil 571-256-0646

More information

Integrated Baseline Review (IBR) Refocusing on Achievability August 24, 2017

Integrated Baseline Review (IBR) Refocusing on Achievability August 24, 2017 Integrated Baseline Review (IBR) Refocusing on Achievability August 24, 2017 1 What is an IBR? The Review A Government program manager led review to ensure the Contractor's baseline plan has: Adequate

More information

DLA Enterprise Supplier Conference and Exhibition

DLA Enterprise Supplier Conference and Exhibition DLA Enterprise Supplier Conference and Exhibition June 29, 2011 Patrick Fitzgerald Director, Defense Contract Audit Agency The views expressed in this presentation are DCAA's views and not necessarily

More information

Achieving Business Analysis Excellence

Achieving Business Analysis Excellence RG Perspective Achieving Business Analysis Excellence Turning Business Analysts into Key Contributors by Building a Center of Excellence 11 Canal Center Plaza Alexandria, VA 22314 HQ 703-548-7006 Fax 703-684-5189

More information

Cost Estimation and Earned

Cost Estimation and Earned Cost Estimation and Earned Value Integration Presented to 2013 ICEAA EVM Track New Orleans, LA NRO Acquisition Environment The National Reconnaissance Office (NRO) is the national program to meet the U.S.

More information

The last four phrases should be sound familiar to any of you practicing agile software development.

The last four phrases should be sound familiar to any of you practicing agile software development. Thank you for having me this morning. You ve heard many speakers address way of developing software using agile development methods. That is not the topic of this briefing. I m going to introduce a parallel

More information

Contractor Estimating Systems: System Adequacy Standards and Key Compliance Issues

Contractor Estimating Systems: System Adequacy Standards and Key Compliance Issues McKenna Government Contracts, continuing excellence in Dentons Contractor Estimating Systems: System Adequacy Standards and Key Compliance Issues Joe Martinez, Esq. Dentons US LLP Michael Steen, CPA Redstone

More information

Tailoring Earned Value Management

Tailoring Earned Value Management cost work schedule Tailoring Earned Value Management General Guidelines Eleanor Haupt ASC/FMCE Wright-Patterson AFB OH REPORT DOCUMENTATION PAGE Form Approved OMB No. 0704-0188 Public reporting burder

More information

Software Project & Risk Management Courses Offered by The Westfall Team

Software Project & Risk Management Courses Offered by The Westfall Team Software Project & Risk Management is a 5-day course designed to provide a knowledge base and practical skills for anyone interested in implementing or improving Software Project and Risk Management techniques

More information

PMP Exam Prep Coaching Program

PMP Exam Prep Coaching Program PMP Exam Prep Coaching Program 1 Charter Direct and Manage Work Monitor and Control Work Perform Integrated Change Control Close or Phase 2 Vinai Prakash, PMCHAMP.COM 1 Defines how the project is executed,

More information

PART THREE: Work Plan and IV&V Methodology (RFP 5.3.3)

PART THREE: Work Plan and IV&V Methodology (RFP 5.3.3) PART THREE: Work Plan and IV&V Methodology (RFP 5.3.3) 3.1 IV&V Methodology and Work Plan 3.1.1 NTT DATA IV&V Framework We believe that successful IV&V is more than just verification that the processes

More information

Government Contract Controls: Going Beyond Business Systems

Government Contract Controls: Going Beyond Business Systems Government Contract Controls: Going Beyond Business Systems Breakout Session A03 Sajeev Malaveetil, Partner, Ernst & Young LLP Andy Artz, Senior Manager, Ernst & Young LLP Karl Fultz, Manager, Ernst &

More information

PMP TRAINING COURSE CONTENT

PMP TRAINING COURSE CONTENT PMP TRAINING COURSE CONTENT SECTION1: INTRODUCTION PMI, PMP AND PMBOK What is PMI, PMP, and PMBOK? What do I get out of PMP? How do I get certified? Exam qualifications and PM experience Guidelines to

More information

SPE4AX-15-D-9412 Clause Number Clause Date Clause Title

SPE4AX-15-D-9412 Clause Number Clause Date Clause Title SPE4AX-15-D-9412 Clause Number Clause Date Clause Title 52.215-2 (OCT 2010) Audit and Records-Negotiation 252.211-7003 (DEC 2013) ITEM UNIQUE IDENTIFICATION AND VALUATION 252.211-7006 (SEP 2011) PASSIVE

More information

How to Prepare a DCAA Compliant Cost or Price Proposal. Bag Lunch Webinar November 17, 2016

How to Prepare a DCAA Compliant Cost or Price Proposal. Bag Lunch Webinar November 17, 2016 How to Prepare a DCAA Compliant Cost or Price Proposal Bag Lunch Webinar November 17, 2016 Presenter: Paul H. Calabrese Rubino & Company, CPAs & Consultants Senior Manager Tel: 301 214 4137 pcalabrese@rubino.com

More information

QUICK START GUIDE. for FSSC Implementation. Copyright 2016 Vinca, LLC.

QUICK START GUIDE. for FSSC Implementation.  Copyright 2016 Vinca, LLC. QUICK START GUIDE for FSSC 22000 Implementation www.22000-tools.com Copyright 2016 Vinca, LLC. CONTENTS WHAT IS FSSC 22000? BENEFITS OF FSSC22000 IMPLEMENTING FSSC 22000 AND PREPARING FOR CERTIFICATION

More information

DEPARTMENT OF THE ARMY COMPLETE STATEMENT MIKE FERGUSON CHIEF, COST AND TECHNICAL BRANCH/ENGINEERING DIVISION

DEPARTMENT OF THE ARMY COMPLETE STATEMENT MIKE FERGUSON CHIEF, COST AND TECHNICAL BRANCH/ENGINEERING DIVISION DEPARTMENT OF THE ARMY COMPLETE STATEMENT OF MIKE FERGUSON CHIEF, COST AND TECHNICAL BRANCH/ENGINEERING DIVISION U.S. ARMY CORPS OF ENGINEERS, HUNTINGTON DISTRICT BEFORE THE COMMITTEE ON APPROPRIATIONS

More information

Value of Failure! Students Course! Module 4: Preventing Failure!

Value of Failure! Students Course! Module 4: Preventing Failure! Value of Failure Students Course Content 1. Project Management 2. Basics of risk management Project: The black box of project management Project Idea Project Management Completion / Operation Project management

More information

1.0 PART THREE: Work Plan and IV&V Methodology

1.0 PART THREE: Work Plan and IV&V Methodology 1.0 PART THREE: Work Plan and IV&V Methodology 1.1 Multi-Faceted IV&V Methodology Large, complex projects demand attentive and experienced IV&V and project management support to meet expectations. Monitoring

More information

Risk Mitigated SCAMPI SM Process

Risk Mitigated SCAMPI SM Process Risk Mitigated SCAMPI SM Process Gary Natwick, Debra Perry Harris Corporation November 19, 2008 NDIA CMMI Conference - 1 Providing Value To Our Customers Communications and information networks Aviation

More information

IBR Considerations for Agile Projects with EVM

IBR Considerations for Agile Projects with EVM IBR Considerations for Agile Projects with EVM Zachary Coates Matthew Strain February 19 th, 2015 2015 General Dynamics. All rights reserved. 1 Outline Roadmap for where we re headed Introductions and

More information

PART THREE - WORK PLAN AND IV&V METHODOLOGY WORK PLAN. FL IT IV&V Work Plan

PART THREE - WORK PLAN AND IV&V METHODOLOGY WORK PLAN. FL IT IV&V Work Plan WORK PLAN FL IT IV&V Work Plan PART THREE - WORK PLAN AND IV&V METHODOLOGY ID Task Name Duration 1 FL IT IV&V Project Work Plan 261 days 2 DDI / SI Contract Award 0 days 3 Project Initiation and Planning

More information

Roger D. Duke Vice President -Contracts & Procurement. September 21, 2016

Roger D. Duke Vice President -Contracts & Procurement. September 21, 2016 MINDING THE GAPS BETWEEN THE PRIME CONTRACT AND SUBCONTRACT(S) Roger D. Duke Vice President -Contracts & Procurement September 21, 2016 The 1 concepts expressed herein are solely my own and do not necessarily

More information

CSU Project Management Certificate Program

CSU Project Management Certificate Program CSU Project Management Certificate Program Project Quality Management Instructor: Ric Rothschild, PMP Contact Info: ric.rothschild@comcast.net 303-664-1117 1 Project Quality Management Agenda Introduction

More information

The 10-day Project Professional MBA (Project Management Professional)

The 10-day Project Professional MBA (Project Management Professional) HR CERTIFICATION INSTITUTE ISO 9001:2015 Certified ISO 29990:2010 Certified ISO 29990 05-FEB-18 The 10-day Project Professional MBA (Project Management Professional) 04-15 Mar 2018, Dubai 27 Aug - 07 Sep

More information

Organizational Alignment for Contracting/Subcontracting:

Organizational Alignment for Contracting/Subcontracting: Breakout Session #: G17 Organizational Alignment for Contracting/Subcontracting: Optimizing Performance and Managing Performance Risk Presented by: The Subcontract Management Institute (ScMI ) Date: Wednesday,

More information

Understanding the DCAA Audit Process and How to Prepare for Success

Understanding the DCAA Audit Process and How to Prepare for Success Understanding the DCAA Audit Process and How to Prepare for Success Breakout Session #: C11 Presented by: Beverly Arviso, CPA, Fellow, CPCM, CFCM Date: July 22, 2013 Time: 4:00-5:15 DCAA s Mission Compliance

More information

Quantitative Prediction and Improvement of Program Execution

Quantitative Prediction and Improvement of Program Execution Quantitative Prediction and Improvement of Program Execution Dr. Shawn Rahmani Boeing Defense, Space/Security Huntington Beach, California The 26th Annual IEEE Software Technology Conference March-April

More information

Efficient Research Project Management It s all in Managing Change!

Efficient Research Project Management It s all in Managing Change! Efficient Research Project Management It s all in Managing Change! Denise Turso M.Ed., M.S., CSEP Penn State Project Management Conference November 5, 2015 Content Definition Need Purpose Project Stakeholders

More information

INTEGRATED PROGRAM & PROJECT MANAGEMENT A STRATEGIC APPROACH

INTEGRATED PROGRAM & PROJECT MANAGEMENT A STRATEGIC APPROACH http://pmsymposium.umd.edu/pm2017/ INTEGRATED PROGRAM & PROJECT MANAGEMENT A STRATEGIC APPROACH Gordon M. Kranz, President, Enlightened Integrated Program Management 2017 Project Management Symposium Agenda

More information

Glossary. BoM Bill of material. CAPM Certified Associate in Project Management. CCB Change Control Board

Glossary. BoM Bill of material. CAPM Certified Associate in Project Management. CCB Change Control Board Glossary Note: All the project management standards following DIN 69901-5:2009 follow the project management glossary from the Projekt Magazin (Angermeier, Georg; URL: https://www.projektmagazin.de/glossar/).

More information

CMMI-SVC V1.3 CMMI for Services Version 1.3 Quick Reference Guide

CMMI-SVC V1.3 CMMI for Services Version 1.3 Quick Reference Guide processlabs CMMI-SVC V1.3 CMMI for Services Version 1.3 Quick Reference Guide CMMI-SVC V1.3 Process Areas Alphabetically by Process Area Acronym processlabs CAM - Capacity and Availability Management...

More information

Earned Value Management Practitioners Symposium. EVM Center of Excellence

Earned Value Management Practitioners Symposium. EVM Center of Excellence Earned Value Management Practitioners Symposium Pamela J. Walter Pamela J. Walter EVM Center of Excellence Assumptions Case study of Leidos Agile/EVMS programs Program 1 Program 2 Challenges/Perceived

More information

Case study: Developing effective risk management in a global mining group

Case study: Developing effective risk management in a global mining group Creating value from uncertainty Broadleaf Capital International Pty Ltd ABN 24 054 021 117 www.broadleaf.com.au Case study: Developing effective risk management in a global mining group Broadleaf helped

More information

Enabling SDBOR s Goals

Enabling SDBOR s Goals Enabling SDBOR s Goals Standardization, Optimization, Modernization Cindy Martini, Director Strategic Solutions Sue Stern, VP Operations ATTACHMENT I 5 Agenda 1 SDBOR Project Goals 2 Proposed Approach

More information

Lessons Learned in Seamless Integration of CMMI, TSP, and PSP Why All Three Are Needed. CMMI Technology Conference November 14, 2007

Lessons Learned in Seamless Integration of CMMI, TSP, and PSP Why All Three Are Needed. CMMI Technology Conference November 14, 2007 Lessons Learned in Seamless Integration of CMMI, TSP, and PSP Why All Three Are Needed CMMI Technology Conference November 14, 2007 Winner IEEE Software Process Achievement Award http://www.sei.cmu.edu/managing/ieee-award/ieee.award.html

More information

IMPROVING RESOURCE CAPACITY THROUGH TIMESHEET MANAGEMENT. Generate project resource capacity without hiring by using best timesheet business practices

IMPROVING RESOURCE CAPACITY THROUGH TIMESHEET MANAGEMENT. Generate project resource capacity without hiring by using best timesheet business practices IMPROVING RESOURCE CAPACITY THROUGH TIMESHEET MANAGEMENT Generate project resource capacity without hiring by using best timesheet business practices By: Chris Vandersluis President, HMS Software chris.vandersluis@hms.ca

More information

DFARS Business Systems Compliance. March 11, 2015

DFARS Business Systems Compliance. March 11, 2015 DFARS Business Systems Compliance March 11, 2015 Speakers Steven Tremblay Ernst & Young Executive Director Government Contract Services Jack Gay Ernst & Young Senior Manager Government Contract Services

More information

WORK PLAN AND IV&V METHODOLOGY Information Technology - Independent Verification and Validation RFP No IVV-B

WORK PLAN AND IV&V METHODOLOGY Information Technology - Independent Verification and Validation RFP No IVV-B 1. Work Plan & IV&V Methodology 1.1 Compass Solutions IV&V Approach The Compass Solutions Independent Verification and Validation approach is based on the Enterprise Performance Life Cycle (EPLC) framework

More information

Rational Software White Paper TP 174

Rational Software White Paper TP 174 Reaching CMM Levels 2 and 3 with the Rational Unified Process Rational Software White Paper TP 174 Table of Contents Abstract... 1 Introduction... 1 Level 2, Repeatable... 2 Requirements Management...

More information

PROJECT MANAGEMENT OVERVIEW

PROJECT MANAGEMENT OVERVIEW Chapter One PROJECT MANAGEMENT OVERVIEW Project management itself is not a new concept. It has been practiced for hundreds, even thousands of years. Any large undertaking requires a set of objectives,

More information

Practice Symposia Project Planning Track

Practice Symposia Project Planning Track Practice Symposia Project Planning Track Coordinator: Dale Gillam PS-13 The Art of Planning Joshua Garvey, ClearPlan PS-14 Walk the Flight Line - Finding Risk and Opportunities Kellie Cloud, Booz Allen

More information

Chapter One PROJECT MANAGEMENT OVERVIEW

Chapter One PROJECT MANAGEMENT OVERVIEW Chapter One PROJECT MANAGEMENT OVERVIEW Project management itself is not a new concept. It has been practiced for hundreds, even thousands of years. Any large undertaking requires a set of objectives,

More information

Project Management Training Brochure

Project Management Training Brochure Project Management Training Brochure We develop project management training sessions by integrating our 40 years of combined practitioner experience with the most current project management knowledgebase

More information

Capital project planning, design, delivery and operation process review City of Nanaimo November 20, 2017

Capital project planning, design, delivery and operation process review City of Nanaimo November 20, 2017 Capital project planning, design, delivery and operation process review City of Nanaimo November 20, 2017 Background Deloitte s Scope Conduct a review of the City s project planning, design, delivery and

More information

PROJECT AND PORTFOLIO MANAGEMENT PPM.RAMBOLL.COM

PROJECT AND PORTFOLIO MANAGEMENT PPM.RAMBOLL.COM PROJECT AND PORTFOLIO MANAGEMENT PPM.RAMBOLL.COM WORLD CLASS PROJECT AND PORTFOLIO MANAGEMENT All we do serves the same overall purpose: To help you succeed. We support your projects with best in class

More information

One team, one voice delivering global acquisition insight that matters. DCMA Update. Presented By: Bill Weisler. Date February

One team, one voice delivering global acquisition insight that matters. DCMA Update. Presented By: Bill Weisler. Date February One team, one voice delivering global acquisition insight that matters. DCMA Update Presented By: Bill Weisler Date February 7 2019 Agenda New EVMS Center Director, Deputy Director New Process 3.1 Changes

More information

Certificate in Advanced Project Management. Contents are subject to change. For the latest updates visit

Certificate in Advanced Project Management. Contents are subject to change. For the latest updates visit Certificate in Advanced Project Management Page 1 of 7 Why Attend The overall aim of this course is to provide participants with the knowledge and skills needed to perform in-depth analysis for a project

More information

The ASC 606 clock is ticking It may be time for brute force

The ASC 606 clock is ticking It may be time for brute force The ASC 606 clock is ticking It may be time for brute force By the time you read this, ASC 606 will be two minutes closer to a reality (see sidebar: ASC 606 in brief). The clock is ticking down toward

More information

Subcontract Management Regulatory Compliance - The Most Current Trends and Issues

Subcontract Management Regulatory Compliance - The Most Current Trends and Issues Subcontract Management Regulatory Compliance - The Most Current Trends and Issues Breakout Session #: B16 Presented by: Jeffery A. White, C.P.M. Date: July 22, 2013 Time: 2:30 3:45 Subcontract Compliance

More information

OUSD(A&T) Initiatives Update. Wayne Abba 8th Annual International Cost Schedule Performance Management Conference

OUSD(A&T) Initiatives Update. Wayne Abba 8th Annual International Cost Schedule Performance Management Conference OUSD(A&T) Initiatives Update Wayne Abba 8th Annual International Cost Schedule Performance Management Conference October 27, 1996 REPORT DOCUMENTATION PAGE Form Approved OMB No. 0704-0188 Public reporting

More information

REQUIREMENTS DOCUMENTATION

REQUIREMENTS DOCUMENTATION REQUIREMENTS DOCUMENTATION Project Title: Date Prepared: Stakeholder Requirement Category Priority Acceptance Criteria REQUIREMENTS DOCUMENTATION Project Title: Date Prepared: Stakeholder Requirement Category

More information

A Contracting Officer s Guide To Getting Stronger Contractors

A Contracting Officer s Guide To Getting Stronger Contractors A Contracting Officer s Guide To Getting Stronger Contractors Breakout Session # B12 Jeff Shen, VP & GM, Red Team Consulting Date: Monday, July 28, 2014 Time: 2:30pm-3:45pm Introductions Red Team Federal

More information

Projects: Stray Rescue

Projects: Stray Rescue Projects: Stray Rescue James Page, Jr., PMP, U. S. Postal Service Ninoska Clarkin, Edward Jones Lynn Pias, Monsanto Jim Bostick, PMP, CSC Barbara Strang, PMP Just the facts by two independent research

More information

PMAG's Program Startup Assistance

PMAG's Program Startup Assistance SMC/PI Program Management and Integration Program Management Assistance Group (PMAG) PMAG's Program Startup Assistance 5/6/2009 Col Mun Kwon Director, PMAG 1 Agenda Introduction What is PMAG Background,

More information

Measuring EV in an Agile World - How to Make it Work!

Measuring EV in an Agile World - How to Make it Work! Measuring EV in an Agile World - How to Make it Work! Laura Bier, Agile Track Chair Dave Scott, EVMP Chair 2017 EVMP Forum August 24 th & 25 th 1 Learning Objectives Gain an understanding of a lean approach

More information

DoD PARCA EVM. EVM Policy Initiatives. Mr. John McGregor PARCA Director for EVM. NDIA IPMD April 27, 2017

DoD PARCA EVM. EVM Policy Initiatives. Mr. John McGregor PARCA Director for EVM. NDIA IPMD April 27, 2017 1 NDIA IPMD April 27, 2017 DoD PARCA EVM EVM Policy Initiatives Mr. John McGregor PARCA Director for EVM A Few Words 2 3 1. EVM-CR Industry Role 2. DoDI 5000.02 3. IPMR 4. EVMSIG 5. MIL-STD-881C OUSD AT&L

More information

PMI - Minnesota August 14, Oh no - PMO. Presented by: Michael Vinje - PMP.

PMI - Minnesota August 14, Oh no - PMO. Presented by: Michael Vinje - PMP. PMI - Minnesota August 14, 2007 Oh no - PMO Presented by: Michael Vinje - PMP 1 mvinje@trissential.com 2005 All Rights Reserved. Agenda Presentation Objective PMO Background & Survey What The Experts Said

More information

Process for Managing Service Transition Efficiently. By Ravinder Singh Zandu

Process for Managing Service Transition Efficiently. By Ravinder Singh Zandu Process for Managing Service Transition Efficiently By Ravinder Singh Zandu Project Pain points Typical budget over-runs 30%; 1 in 6 projects going more than 50 % over budget;10 out of 29 projects on the

More information

M3 Playbook Guidance. 1.1 Establish Initial Customer PMO and Processes. Human Resources (HR)/Staffing Plan

M3 Playbook Guidance. 1.1 Establish Initial Customer PMO and Processes. Human Resources (HR)/Staffing Plan M3 Playbook Guidance Phase 1: Readiness This guidance is intended for use by organizations to confirm and validate that their plans are comprehensive and have adequate level of detail for proper migration

More information

PMP. Processexam.com. PMI Project Management Professional. Exam Summary Syllabus Questions

PMP. Processexam.com. PMI Project Management Professional. Exam Summary Syllabus Questions PMP PMI Project Management Professional Processexam.com Exam Summary Syllabus Questions Table of Contents Keys to success in PMP Exam on PMI Project Management Professional... 2 PMI PMP Certification Details:...

More information

MORS Introduction to Cost Estimation (Part I)

MORS Introduction to Cost Estimation (Part I) MORS Introduction to Cost Estimation (Part I) Mr. Huu M. Hoang Slide 1 Disclosure Form Slide 2 Module Three Module #(s) Items covered Presenter Start Stop One (1) Overview and Background (1) Define Estimate

More information

Integration Knowledge Area

Integration Knowledge Area Integration Knowledge Area Develop Project Charter Project statement of work Expert judgment Project charter Business case Contract (if third party project) EEF: government/industry standards, organizational

More information

itech AG provides experienced personnel and knowledgeable leadership that have implemented controls on complex programs and projects.

itech AG provides experienced personnel and knowledgeable leadership that have implemented controls on complex programs and projects. itech AG PROGRAM CONTROLS Our Program Controls services provide our clients with meaningful insight into their programs which give them the necessary data they need to make proactive and informed decisions.

More information

Energy Future Holdings (EFH)

Energy Future Holdings (EFH) Energy Future Holdings (EFH) Inclusion of Data Analytics into the Internal Audit Lifecycle June 3, 2015 Starting Place Baseline Questions Pertaining to the utilization of data analytics in the internal

More information

Ninth Edition. Rita Mulcahy, PMP, etai. Rita Mulcahy s. Inside this book:

Ninth Edition. Rita Mulcahy, PMP, etai. Rita Mulcahy s. Inside this book: Rita s Course in a Book for Passing the Project Management Professional (PMP) Exam Rita Mulcahy s Ninth Edition Inside this book: Tricks of the Trade What you really need to know to pass the exam Straightforward

More information

Download the document titled DOD for information regarding key program documentation and reports.

Download the document titled DOD for information regarding key program documentation and reports. Page 1 of 12 Program Execution Summary EVM data from the Contract Performance Report (CPR) is often required in the documentation of service program reviews. For example, the Selected Acquisition Report

More information

Initiation Group Process. Planning Group Process

Initiation Group Process. Planning Group Process Initiation Group Process Develop Project Charter Project statement of work Expert judgment Project charter Business case Contract (if third party project) EEF: government/industry standards, organizational

More information

DON T GET LEFT IN THE COLD!...

DON T GET LEFT IN THE COLD!... B U I L D Y O U R S E L F A DON T GET LEFT IN THE COLD!... B R I G H T E R, M O R E P R O S P E R O U S F U T U R E! WITH OUR FREE TASTER COURSES IN: Engineering, Construction, Plumbing and Electrical.

More information

Washington Metropolitan Area District Office

Washington Metropolitan Area District Office Presentation by: Anthony Ruiz Assistant District Director/8(a) Business Development for the National Defense Industrial Association 11 th National Small Business Conference September 10, 2014 Part I: The

More information

Workshop: Advanced Cost Management Techniques Using Cobra

Workshop: Advanced Cost Management Techniques Using Cobra Workshop: Advanced Cost Management Techniques Using Cobra Jessica Coral, BDO 2017 EVMP Forum August 24 th & 25 th 1 BDO Industry Specialty Services Program Optimization and Project Controls Solutions BDO

More information