1 TECHNICAL SPECIAL PROVISION FOR 1001 WATER DISTRIBUTION SYSTEM FINANCIAL PROJECT ID: The official record of this Technical Special Provision is the electronic file signed and sealed under Rule 61G , F.A.C. Prepared by: Reed S. Thursby, P.E. P.E. Number Date: 02/19/2014 Kisinger Campo & Assoc., Corp. 201 N. Franklin Street Suite 400 Tampa, FL Certification of Authorization No.: Pages: of 6-36-
2 SECTION 1001 WATER DISTRIBUTION SYSTEM DESCRIPTION General Requirements: The work specified in this Section consists of the furnishing of all labor and material required for the construction of Water Distribution and Service Line Facilities. This technical special provision is intended to be used in conjunction with the FDOT Specifications. At least two weeks prior to construction the contractor shall notify the Engineer and the appropriate inspectors of the Okeechobee Utility Authority (OUA) and furnish all the required shop drawings, the contractor's name, starting date, projected schedule and other information as required. Any work prior to notifying the above or without a department inspector present may be subject to removal or replacement Materials Materials incorporated in the construction of water distribution facilities under this contract shall comply with this technical special provision. Contractor to coordinate with the OUA prior to the selection and ordering of the water meter and/or backflow prevention device assemblies. Required shop drawings: PVC pipe, valves, backflow preventer, air release valve, meter Ductile Iron Pipe: Ductile iron pipe and fittings (D.I.P.) shall conform to the requirements of AWWA C151/ANSI A21.51, Class 350. Unless otherwise noted on the plans or approved by the Engineer, ductile iron pipe sewers shall have push-on or mechanical joints for underground service. Special joints and restraints shall be used where indicated on the plans Polyvinyl Chloride (PVC) Water Pipe: Pipe sizes of two inches shall meet the requirements of AWWA Schedule 40, class 150. Maximum laying length for all PVC water pipe shall be 20 feet Valves and Valve Boxes: Valves two inches and larger shall open in the same direction. Valves stems shall terminate in two inch square nuts. Contractor shall furnish two suitable keys. The lids of all boxes shall bear the word Water or the Letter W. All valves shall be provided with joints suitable for the pipe to which they are to connect Tapping Sleeves and Valves: Tapping sleeves and valves shall be furnished where required for tapping water mains and installing a branch valve under line pressures. 2 of 6-37-
3 Water Meters and Boxes: Water meters and boxes shall be installed only where specifically required on the plans or elsewhere in this technical special provision. Water meters shall be of the size, type and manufacture as approved by the Engineer in conjunction with the Okeechobee Utility Authority. The meter box shall be of the size necessary to accommodate the water meter and fittings. The meter box shall be cast iron or concrete having a minimum compressive strength of 2500 psi HDPE Pipe: SDR 11, conforming to AWWA C906 DIP size Construction Methods Connections to Existing Mains: Contractor shall make all required connections to existing water mains as approved by the Engineer in conjunction with the Okeechobee Utility Authority Handling and Storing Materials: Water pipe shall be unloaded so as to avoid shock or damage. Handle and store all pipe in such manner as to avoid deformation or other injury thereto. Store pipe and fittings on sills above storm drainage level and place wood stringer between layers of pipe. Place no pipe within pipe of a larger size Pipe Laying: The interior of the pipe shall be clean and joint surfaces brushed and wiped clean and dry when the pipe is lowered into trench. Lower each pipe, fitting and valve into the trench carefully and lay true to line and without objectionable breaks in grade. The depth of cover below finished grade shall not be less than three feet, three feet from any utility pole and eight feet from any parallel utility, and as much deeper as necessary to give proper clearance from other utilities and structures. Where water and sewer pipes cross, water should always cross over the sewer. Where this is not possible, and the sewer crosses over the water pipe, the water pipe shall be sleeved or encased in concrete for a minimum distance of five feet horizontally either side of the centerline of the sewer at the crossing. 3 of 6-38-
4 Sanitary sewers, force mains, and storm sewers should always cross under water mains. Sanitary force mains and storm sewers crossing water mains shall be laid to provide a minimum vertical distance of 18 inches between the invert of the upper pipe and the crown of the lower pipe whenever possible. Where sanitary sewers, force mains and storm sewers must cross a water main with less than 18 inches vertical distance, both the sewer and the water main shall be constructed of ductile iron pipe (DIP) at the crossing (DIP is not required for storm sewers if it is not available in the size proposed). Sufficient lengths of DIP must be used to provide a minimum separation of ten feet between any two joints. All joints on the water main within 20 feet of the crossing must be leak free, and mechanically restrained. A minimum vertical clearance of six inches must be maintained at the crossing. Where there is no alternative to sewer pipes crossing over the water main, the criteria for minimum separation of 18 inches between lines and ten feet between joints shall be required. All crossings shall be arranged so that the sewer pipe joints and the water main pipe joints are equidistant from the point of crossing (pipes centered on the crossing). Where a new pipe conflicts with an existing pipe, the new pipe shall be constructed of DIP and the crossing shall be arranged to meet the requirements above. A minimum ten foot horizontal separation shall be maintained between any type of sewer and water main in parallel installations, whenever possible. In cases where it is not possible to maintain a ten foot horizontal separation, the water main must be laid in a separate trench or an undisturbed earth shelf located on one side of the sewer force main at such an elevation that the bottom of the water main is at least 18 inches above the top of the sewer. Where it is not possible to maintain a vertical distance of 18 inches in parallel installations, the water main shall be constructed of DIP and the sewer or the force main shall be constructed of DIP (if available in The size proposed) with a minimum vertical distance of six inches. The water main should always be above the sewer. Joints on the water main shall be located as far apart as possible from joints on the sewer or force main (staggered joints). DIP shall be class 50 or higher. Adequate protective measures against corrosion shall be used. Any water main within a public right-of-way shall be covered with a magnetic locator per specifications. Under no circumstances drop or dump pipe or appurtenances into the trench. Give all pipes a uniform bearing on the trench bottom. Allow no trench water or dirt to enter the pipe or joint space during laying. Insert a watertight plug in the open end of the piping when pipe laying is not in progress. Cut pipe as necessary to locate fittings and valves in the positions shown on the drawings, cut in and plug openings for branches to be installed later. 4 of 6-39-
5 Cutting Pipe: Cutting of pipe shall be done in a neat and workmanlike manner without damage to the pipe. Unless authorized by the Engineer, cutting shall be done by means of an approved mechanical cutter Fittings and Branch Connections: Install proper fittings at all changes in direction, dead ends, and interconnections of lines Setting Valves: Before setting each valve make sure the interior is clean and test opening and closing. Set valves and stops with stem plumb and at the exact locations shown. Provide a cast iron stop cock holder and a brick laid flat or other similar foot-piece under each curb box. Valve and service boxes shall be plumb, centered over valves, and with tops at finished grade. Tamp trench back fill thoroughly for a distance of three feet on each side of boxes Blocking: Pour lean-mix concrete thrust blocks between the undisturbed trench face and plugged ends, bends and tees to prevent pipe movement at joints. Where the soil is not firm, provide, in lieu of concrete, approved tie rods and collars, painted with coal-tar pitch varnish after placing. This requirement does not apply to galvanized iron pipe with threaded joints Testing and Inspection Hydrostatic Test: Before joints are covered, fill the piping with water, opening outlets as necessary for expelling air. Thereafter, furnish the necessary pump, piping and other apparatus and, under the supervision of the Engineer, the contractor shall perform a pressure test on the water main in accordance with OUA regulations and AWWA standard c600. Said tests shall be certified by the engineer of record and submitted to the OUA for approval. The scheduling, coordination and notification of all parties is the contractor's responsibility. Inspect all joints, and remedy to the satisfaction of the Engineer, all defects so discovered. Continue the tests until all visible leaks have been eliminated from the part of the system under test. Maximum leakage shall not exceed that allowed by the Florida DEP Flushing Mains: Upon completion of the water distribution system, test all valves to insure their opening and flush out the system progressively by opening fire hydrants and building outlets and permitting the flow to continue from each until the water runs clear. During such flushing operation the Engineer may test the flow from hydrants and, before final acceptance of the work, make further tests of hydrant flows to ascertain if the lines are clear. 5 of 6-40-
6 Sterilization of Water Distribution System: As soon as the water distribution system has been flushed out as above specified, it shall be sterilized in accordance with the requirements of the Department of Health and Rehabilitative Services, Division of Health. The Engineer reserves the right to test the water again at any time prior to final acceptance of the work, and if found unsafe bacteriologically, to require the Contractor to rechlorinate the system until the water is proven equal to that supplied by the public system Final Inspection: Upon completion of the water system construction and after obtaining satisfactory test results, the Engineer in conjunction with the Okeechobee Utility Authority shall conduct a final inspection. No tie-in to the public water system is permitted prior to system acceptance and written approval from the OUA Method of Measurement Payment for the work described in this Section shall be made under the appropriate pay items as noted in the proposal and shall include all labor, material, tests, and any other work required to render the job complete and operational Basis of Payment Architectural Water, Sanitary Sewer/Sewage Treatment Lump Sum 6 of 6-41-
SECTION WASTEWATER FORCE MAINS
SECTION 02732 WASTEWATER FORCE MAINS PART - GENERAL 1.01 GENERAL: A. This section includes the general requirements for design and installation of force main systems serving wastewater lift stations. B.
More information***************************************************************************************************************
02732 SANITARY FORCE MAIN *************************************************************************************************************** SPECIFIER: CSI MasterFormat 2004 number 33 34 00. ***************************************************************************************************************
More informationSECTION POLYVINYL CHLORIDE (PVC) WATERLINE
SECTION 02632 POLYVINYL CHLORIDE (PVC) WATERLINE PART 1 - GENERAL 1.01 SCOPE OF WORK A. Furnish all labor, materials, equipment, and incidentals required, and install polyvinyl chloride (PVC) waterline,
More informationSECTION C1 DUCTILE IRON PIPE AND FITTINGS GENERAL
SECTION C1 DUCTILE IRON PIPE AND FITTINGS GENERAL This section covers the furnishing and installation of ductile iron water pipe, fittings, thrust restraint and pipe disinfection. Ductile Iron Pipe MATERIALS
More informationSECTION WATER DISTRIBUTION SYSTEM
Conditions of Use/ Responsibility of Data Montgomery County Public Schools Facilities Guide DIVISION 2 - SITE WORK These guideline specifications are to be used by the A/E as a base document in the development
More information1. B16.1 Cast Iron Pipe Flanges and Flanged Fittings, Class C 111 Rubber Gasket Joints for Ductile Iron Pressure Pipe and Fittings
SECTION 33 34 00 SANITARY FORCE MAIN PART 1 GENERAL 1.1 SCOPE OF WORK A. This section specifies the requirements for furnishing and installing sanitary force main and appurtenances. The pipe shall be of
More informationSECTION MEASUREMENT AND PAYMENT
SECTION 01026 PART 1 GENERAL 1.1 SECTION INCLUDES A. Explanation and Definitions B. Measurement C. Payment D. Schedule of Values E. Application for Payment 1.2 EXPLANATION AND DEFINITIONS A. The following
More informationSUB WATER DEPARTMENT STANDARD CONSTRUCTION SPECIFICATIONS TABLE OF CONTENTS SECTION POLYETHYLENE PRESSURE PIPE
SUB WATER DEPARTMENT STANDARD CONSTRUCTION SPECIFICATIONS TABLE OF CONTENTS SECTION 33 11 13.24 POLYETHYLENE PRESSURE PIPE PART 1 GENERAL... 2 1.1 Description... 2 1.2 Reference Specification... 2 1.3
More informationSan Antonio Water System Standard Specifications for Construction ITEM NO. 812 WATER MAIN INSTALLATION
ITEM NO. 812 WATER MAIN INSTALLATION 812.1 DESCRIPTION: This item shall consist of water main installation in accordance with these specifications and as directed by the Engineer. 812.2 MATERIALS: The
More informationSan Antonio Water System Standard Specifications for Construction ITEM NO. 813 WATER SERVICE FOR FIRELINES
ITEM NO. 813 WATER SERVICE FOR FIRELINES 813.1 DESCRIPTION: This item shall consist of water service for fire line installations in accordance with these specifications and as directed by the Engineer.
More informationSECTION WASTEWATER FORCE MAINS
SECTION 02732 WASTEWATER FORCE MAINS PART 1 GENERAL 1.01 GENERAL: A. This section includes the general requirements for design and installation of force main systems serving wastewater lift stations. B.
More informationSECTION FIRE HYDRANTS
SECTION 02080 FIRE HYDRANTS PART 1 - GENERAL 1.01 DESCRIPTION A. Work Specified The work specified shall include all labor, material, equipment, tools, services and incidentals necessary to furnish and
More informationSECTION WATER DISTRIBUTION
SECTION 33 10 00 WATER DISTRIBUTION PART 1 GENERAL 1.01 SUMMARY 1.02 CODES A. Section Includes: 1. Underground water service piping, watermains and appurtenances. A. All work shall comply with the most
More informationCITY OF FARGO SPECIFICATIONS SEWER AND WATER SERVICE CONNECTIONS
SEWER AND WATER SERVICE CONNECTIONS PART 1 DESCRIPTION OF WORK The work to be done under this section of the Specifications and the accompanying plans consists of the furnishing of all labor, material,
More informationNOTICE OF INTENT TO USE THE GENERAL PERMIT FOR CONSTRUCTION OF WATER MAIN EXTENSIONS FOR PWSs
NOTICE OF INTENT TO USE THE GENERAL PERMIT FOR CONSTRUCTION OF WATER MAIN INSTRUCTIONS: This notice shall be completed and submitted by persons proposing to construct projects permitted under the "General
More informationSECTION PUBLIC WATER SERVICE CONNECTIONS
SECTION 33 14 14 PUBLIC WATER SERVICE CONNECTIONS PART 1 GENERAL 1.1 SUMMARY A. Section Includes: 1. Pipe and fittings for water service connections to small commercial, light industrial, and residential
More informationSan Antonio Water System Standard Specifications for Construction ITEM NO. 812 WATER MAIN INSTALLATION
ITEM NO. 812 WATER MAIN INSTALLATION 812.1 DESCRIPTION: This item shall consist of water main installation in accordance with these specifications and as directed by the Inspector. 812.2 SUBMITTALS: Contractor
More informationA. Gravity-Flow, Nonpressure, Drainage-Piping Pressure Rating: 10-foot head of water (30 kpa).
SECTION 221313 - FACILITY SANITARY SEWERS PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 01 Specification
More informationPROJECT TITLE PROJECT NO: CONTRACT TITLE GRANT NO: UNIVERSITY OF CALIFORNIA, DAVIS CITY, CALIFORNIA
The following standard specification is intended to be edited according to the specifics of the project. Brackets [ ] and areas shaded in gray [e.g. format] indicate requirements that are optional depending
More informationSECTION WATER UTILITIES
SECTION 33 10 00 PART 1 - GENERAL 1.1 DESCRIPTION: Underground water distribution system complete, ready for operation, including all appurtenant structures, and connections to both new building service
More informationCity of Middletown WATER & SEWER DEPARTMENT 82 Berlin Street Middletown, CT TEL: (860) FAX: (860)
City of Middletown WATER & SEWER DEPARTMENT 82 Berlin Street Middletown, CT 06457 TEL: (860) 638-3500 FAX: (860) 343-8091 GENERAL REQUIREMENTS WATER MAIN AND SERVICE INSTALLATION JANUARY 2017 WATER MAINS:
More informationTABLE OF CONTENTS PART III MINIMUM DESIGN STANDARDS Section 115 WATER DISTRIBUTION SYSTEM GENERAL SIZING LINES 115.
TABLE OF CONTENTS PART III MINIMUM DESIGN STANDARDS Section 115 WATER DISTRIBUTION SYSTEM SECTION TITLE PAGE 115.1 GENERAL 115.1 115.2 SIZING LINES 115.1 115.3 DISTRIBUTION SYSTEM 115.2 115.3.1 Layout
More informationSECTION HIGH DENSITY POLYETHYLENE PIPE AND FITTINGS (PRESSURE PIPE)
SECTION 02623 HIGH DENSITY POLYETHYLENE PIPE AND FITTINGS (PRESSURE PIPE) PART 1 - GENERAL 1.1 SCOPE OF WORK A. Furnish all labor, materials, equipment and incidentals required and install high density
More informationSANITARY SEWERS. B. Construct or relocate building sanitary sewer services, stubs, and connections.
SANITARY SEWERS PART 1 - GENERAL 1.01 SECTION INCLUDES A. Sanitary Sewer Gravity Mains B. Sanitary Sewer Force Mains C. Sanitary Sewer Services 1.02 DESCRIPTION OF WORK A. Construct sanitary sewer gravity
More informationWastewater Capital Projects Management Standard Construction Specification. 9.0 Pipe Testing, Inspection and Acceptance
CITY AND COUNTY OF DENVER ENGINEERING DIVISION Wastewater Capital Projects Management Standard Construction Specification 9.0 Pipe Testing, Inspection and Acceptance 9.1 General In addition to any other
More informationSECTION GRAVITY WASTEWATER LINES
SECTION GRAVITY WASTEWATER LINES 1. DESCRIPTION This specification shall govern all work required for furnishing, handling and installing gravity wastewater lines required to complete the project. 2. MATERIALS
More informationIce Rink Renovation & New Clubhouse
SECTION 331213 - WATER SERVICE CONNECTIONS PART 1 GENERAL 1.1 SUMMARY A. Section Includes: 1. Pipe and fittings for domestic water service connections to buildings. 2. Corporation stop assembly. 3. Curb
More informationCHINO VALLEY FIRE DISTRICT FIRE PROTECTION STANDARD
CHINO VALLEY FIRE DISTRICT FIRE PROTECTION STANDARD SPECIFICATIONS Establishing Minimum Standards for as Related To Fire Protection STANDARD # 103 REVISED 04/01/19 PAGES 7 SCOPE: These specifications shall
More informationSECTION 2100 WATER MAIN
SECTION 2100 WATER MAIN WATER MAIN PART 1 GENERAL 1.01 Section Summary A. This section includes product and installation requirements for water main pipe, gate valves, hydrants, fittings, and miscellaneous
More informationVALLECITOS WATER DISTRICT SECTION POLYVINYL CHLORIDE (PVC) PRESSURE PIPE
PART 1 - GENERAL 1.1 DESCRIPTION A. This section designates the requirements for the manufacture and installation of polyvinyl chloride, abbreviated PVC, pressure pipe. 1.2 RELATED WORK SPECIFIED ELSEWHERE
More informationSECTION POLYVINYL CHLORIDE (PVC) PRESSURE PIPE
SECTION 02622 POLYVINYL CHLORIDE (PVC) PRESSURE PIPE PART 1 - GENERAL 1.1 SCOPE A. The work covered by this section includes furnishing all labor, equipment, and materials required to install and test
More informationSECTION PIPE INSTALLATION
SECTION 02232 PIPE INSTALLATION A. General The pipe shall be Ductile Iron pipe with Tyton push-on joints and cement lined as described and manufactured in accordance with ANSI/AWWA C151/A21.51. Gaskets
More informationChapter 248 WATER DEPARTMENT
Chapter 248 WATER DEPARTMENT [HISTORY: Adopted by the Town of Lee as Appendix D, Part II, Section III, of the 1971 Code. Amendments noted where applicable.] Plumbing See Ch. 154. Water See Ch. 195. Public
More informationT a b l e o f C o n t e n t s
C i t y o f G l a d s t o n e P u b l i c W o r k s D e s i g n S t a n d a r d s T a b l e o f C o n t e n t s SECTION THREE SANITARY SEWER REQUIREMENTS... 1 3.0000 SANITARY SEWERS... 1 3.0010 General
More informationSection V WATER DISTRIBUTION SYSTEM DESIGN GUIDELINES
Section V WATER DISTRIBUTION SYSTEM DESIGN GUIDELINES A. GENERAL 1. The following water system design guidelines are based on Federal, State and local health requirements and the Hilton Head No. 1 Public
More informationCHAPTER 5 WATER SYSTEM DESIGN STANDARDS
CHAPTER 5 WATER SYSTEM DESIGN STANDARDS TABLE OF CONTENTS CHAPTER 5 WATER SYSTEM DESIGN STANDARDS 5.00 Objective Page 1 5.01 Additional Referenced Standards Page 1 5.02 Special Design Problems Page 2 5.03
More informationSECTION WATER SERVICE CONNECTIONS
SECTION 33 12 13 WATER SERVICE CONNECTIONS PART 1 GENERAL 1.1 SUMMARY A. Section Includes: 1. Pipe and fittings for domestic water service connections to buildings. 2. Corporation stop assembly. 3. Curb
More information2. A preconstruction meeting with the TWA s staff is required prior to initiating construction.
General: 1. Construct utilities in accordance to TWA approved plans and shop drawings. Any deviation from the approved plans shall be approved by the DEVELOPER S ENGINEER and TWA 2. A preconstruction meeting
More informationSECTION SANITARY SEWER SYSTEM
SECTION 02731 SANITARY SEWER SYSTEM PART 1 GENERAL 1.01 SUMMARY A. Section Includes: Sanitary sewer system including necessary accessories indicated on drawings and specified in this section. Contractor
More information1.1 SECTION INCLUDES.1 Materials and installation for water mains, hydrants, valves, valve boxes, and valve chambers, including service connections.
Issued 2005/06/01 Section 02511 Water Mains Page 1 of 10 PART 1 GENERAL 1.1 SECTION INCLUDES.1 Materials and installation for water mains, hydrants, valves, valve boxes, and valve chambers, including service
More information1. Required Minimum Flow:
SECTION 6 6. 6.01 General The City of Castle Rock Water System Minimum Standards and Specifications are minimum base level performance, design, and construction standards used to maintain uniformity of
More informationSECTION FACILITY SANITARY SEWERS
SECTION 22 13 13 FACILITY SANITARY SEWERS PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 01 Specification
More informationCITY OF WARRENVILLE STANDARD SPECIFICATIONS WATER MAIN, SANITARY SEWER AND STORM SEWER
CITY OF WARRENVILLE STANDARD SPECIFICATIONS WATER MAIN, SANITARY SEWER AND STORM SEWER WATER MAIN 1. All open cut water main shall be polyvinyl chloride plastic (PVC) pressure pipe per AWWA specification
More informationUniversity of Central Florida Main Campus. Domestic Water. Service and Meter Installations Requirements. Issued January 26 th, 2017.
University of Central Florida Main Campus Domestic Water Service and Meter Installations Requirements Issued January 26 th, 2017 1 P a g e Table of Contents 1. GENERAL INFORMATION... 3 2. DEFINITIONS...
More informationAPPENDIX B STANDARD CONSTRUCTION DRAWING NOTES
APPENDIX B STANDARD CONSTRUCTION DRAWING NOTES B-1 General Notes: SACWSD Standard Construction Drawing Notes 1. No work shall begin on any water or wastewater construction project until the construction
More informationSan Antonio Water System Standard Specifications for Construction ITEM NO. 848 SANITARY SEWERS
ITEM NO. 848 SANITARY SEWERS 848.1 DESCRIPTION: This item shall govern the furnishing, installation and jointing of sanitary sewer pipe of the size and type specified by the project's plans and specifications.
More informationCITY OF FARGO SPECIFICATION SANITARY SEWER
SECTION 1200 SECTION 1200 CITY OF FARGO SPECIFICATION SANITARY SEWER PART 1 DESCRIPTION OF WORK (revised March, 2007) The work to be done under these Specifications and the accompanying drawings consist
More informationDONALA WATER AND SANITATION DISTRICT
Revised September, 2018 DONALA WATER AND SANITATION DISTRICT To All Builders/Developers/ Vacant Lot Owners: Enclosed is a copy of the policies and procedures for the Donala Water and Sanitation District
More informationSECTION 5 INSTALLATION OF DUCTILE IRON AND PVC PIPE, VALVES, FITTINGS, FIRE HYDRANTS, AND APPURTENANCES
SECTION 5 INSTALLATION OF DUCTILE IRON AND PVC PIPE, VALVES, FITTINGS, FIRE HYDRANTS, AND APPURTENANCES 5-01 GENERAL Unless specified differently on the plans or as supplemented herein, installation of
More informationCITY OF PANAMA CITY BEACH Utilities Administration & Engineering Offices 116 South Arnold Road Panama City Beach, FL 32413
Page: 1 of 5 CITY OF PANAMA CITY BEACH Utilities Administration & Engineering Offices 116 South Arnold Road Panama City Beach, FL 32413 COMMERCIAL/RESIDENTIAL UTILITY PLAN COMPLETENESS CHECK LIST Updated
More informationTECHNICAL SPECIFICATIONS WATER MAINS & MATERIALS
WATER MAINS & MATERIALS Scope of Work Work to be performed under this contract shall consist of furnishing and installing, complete and ready for service, the water mains with various appurtenances as
More informationSANITARY SEWERS. B. Construct or relocate building sanitary sewer services, stubs, and connections.
SANITARY SEWERS PART 1 - GENERAL 1.01 SECTION INCLUDES A. Sanitary Sewer Gravity Mains B. Sanitary Sewer Force Mains C. Sanitary Sewer Services 1.02 DESCRIPTION OF WORK A. Construct sanitary sewer gravity
More information4A General Information A. Concept... 1 B. Conditions... 1
Design Manual Chapter 4 - Water Mains Table of Contents TOC Table of Contents Chapter 4 - Water Mains 4A General Information 4A-1---------------------------------General Information A. Concept....... 1
More informationARTICLE 26 UTILITY LINE INSTALLATION REQUIREMENTS
UTILITY LINE INSTALLATION REQUIREMENTS Index 26.01 JACK AND BORE OPERATIONS 26.02 PRESSURE PIPE RESTRAINT 26.03 PRESSURE CONNECTION BACK TO TABLE OF CONTENTS Section 26.01 JACK AND BORE OPERATIONS 26.01.01
More informationSECTION SANITARY SEWERAGE PART 1 GENERAL 1.01 RELATED DOCUMENTS
SECTION 02530 - SANITARY SEWERAGE PART 1 GENERAL 1.01 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 1 Specification Sections,
More informationThis section includes materials and installation of ductile-iron pipe and fittings for potable and recycled water systems.
NORTH MARIN WATER DISTRICT STANDARD SPECIFICATIONS SECTION 15056 DUCTILE-IRON PIPE AND FITTINGS PART 1 GENERAL 1.01 DESCRIPTION This section includes materials and installation of ductile-iron pipe and
More informationSECTION LAYING AND JOINTING BURIED PIPELINES
SECTION 02650 LINES PART 1 GENERAL 1.1 SUMMARY A. Section Includes: Installation of all underground pipelines. Provide pipeline materials, coatings and linings as specified and pipe of the types, sizes
More informationGENERAL INFORMATION AND REQUIREMENTS
GENERAL INFORMATION AND REQUIREMENTS 1.0 BOARD S STANDARD SPECIFICATIONS: Copies of these Standard Specifications for Water Mains, Sanitary Sewers and Sewage Pumping Stations may be purchased from the
More informationCONSTRUCTION OF WATER SYSTEMS 1.0 PIPING
CONSTRUCTION OF WATER SYSTEMS 1.0 PIPING 1.1 HANDLING Pipe, fittings and accessories shall be handled with care and shall not be dropped or bumped against pipe or appurtenances already or against any other
More informationPART 5 WATER SYSTEMS
PART 5 WATER SYSTEMS Abbreviations and Symbols Plan 501 Abbreviations and symbols for water... 205 Concrete Boxes and Hardware 502 27" Frame and cover... 207 503 38" Frame and cover... 209 505 Concrete
More informationPART II. - SPECIFICATIONS AND DESIGN STANDARDS TO CITY OF HEWITT, TEXAS SUBDIVISION ORDINANCE FOR PUBLIC WORKS CONSTRUCTION [TEXT]
PART II. - SPECIFICATIONS AND DESIGN STANDARDS TO CITY OF HEWITT, TEXAS SUBDIVISION ORDINANCE FOR PUBLIC WORKS CONSTRUCTION [TEXT] A. - General. B. - Streets. C. - Stormwater drainage system. D. - Water
More informationSECTION SANITARY SEWER SYSTEM
SECTION 02530 SANITARY SEWER SYSTEM PART 1 - GENERAL 1.1 SUMMARY A. Section includes sanitary sewer system piping for collection of wastewater. B. Related Sections include but are not limited to: 1. Division
More informationDETAILED WATER MAIN SPECIFICATONS INDEX. Sec. No. Items Page Nos.
INDEX Sec. No. Items Page Nos. 1. Ductile Iron Pipe............... DWM 2 thru DWM 5 2. Reinforced Concrete Water Main............... DWM 5 thru DWM 6 3. Hydrants............... DWM 7 4. Gate Valves and
More informationSECTION 8 SEPARATION OF LINES
SECTION 8 SEPARATION OF LINES 8.01 INDEX 8.01 INDEX 8.02 PURPOSE 8.03 DEFINITIONS 8.04 SEWER SEPARATION 8.05 NON-POTABLE SEPARATION 8.06 REFERENCES 8.02 PURPOSE This section states the requirements and
More informationSECTION STORM SEWER COLLECTION SYSTEM
SECTION 02722 STORM SEWER COLLECTION SYSTEM PART 1 GENERAL 1.01 SUMMARY A. This section addresses the installation of storm sewer collection mains and includes the acceptable products, materials, and construction
More informationSUPPLEMENTAL SPECIFICATIONS TO STANDARD SPECIFICATIONS FOR WATER MAIN AND SERVICE LINE INSTALLATION NO. 2611
Revised October 10, 2014 SUPPLEMENTAL SPECIFICATIONS TO STANDARD SPECIFICATIONS FOR WATER MAIN AND SERVICE LINE INSTALLATION NO. 2611 Water Main and Service Line Installation shall be in accordance with
More informationSECTION REUSE WATER DISTRIBUTION SYSTEMS
SECTION 02661 REUSE WATER DISTRIBUTION SYSTEMS PART 1 GENERAL 1.01 SCOPE OF WORK A. WORK covered by this Section consists of furnishing and installing reuse water distribution pipes and appurtenances,
More informationDIVISION II TECHNICAL SPECIFICATIONS SECTION S-003 SANITARY SEWER FORCE MAIN SYSTEM
DIVISION II TECHNICAL SPECIFICATIONS SECTION S-003 SANITARY SEWER FORCE MAIN SYSTEM TABLE OF CONTENTS: I. DESCRIPTION:... 2 II. COORDINATION:... 2 III. CONSTRUCTION LAYOUT:... 3 IV. MATERIALS:... 3 V.
More information7. Allowable Fittings.
7. Allowable Fittings. a. General Requirements. 1) The fittings listed in this section are generally the allowable fittings for the design of DIP and PVC pipe. For steel pipe and fittings, see Part One,
More informationCopper-Type K soft Drawn 40, 50 HDPE 100 and larger
1.0 GENERAL 1.1 Scope 1.1.1 The work covered by this section involves the installation of water and sewer service connections and all other associated work. 1.2 Authorization 1.2.1 Do not install service
More informationSECTION VII WATER. Concrete anchor and thrust blocks shall be provided at all discontinuities in accordance with Standard Details G-7.1 and G-7.2.
SECTION VII WATER VII-1. DESIGN GUIDELINES Water pipelines and appurtenant structures within the jurisdiction of the City of Paso Robles shall be constructed in accordance with plans prepared by a Professional
More informationCHAPTER 8 WATER SUPPLY SYSTEM
CHAPTER 8 WATER SUPPLY SYSTEM 8-1 INTRODUCTION These improvement standards shall govern the engineering design of all domestic water systems intended for operation and maintenance by the County of Sutter
More informationF. Provide at least 2 feet of vertical separation between a water line and any utility or stormdrain crossing it.
Section 3 F. Provide at least 2 feet of vertical separation between a water line and any utility or stormdrain crossing it. 3.8 Highway Crossings The design engineer shall, prior to the design of any highway
More informationWASTEWATER SYSTEM STANDARDS
8.1 SCOPE Wastewater pipelines and appurtenances shall be provided as shown on the plans and as specified herein. Clearing, grubbing, trench excavation and backfill, pipe material, valves, cutting and
More informationSECTION DUCTILE IRON FITTINGS. A. This section includes materials, installation, and testing of ductile iron fittings 48 inches and smaller.
PART 1 - GENERAL 1.1 DESCRIPTION A. This section includes materials, installation, and testing of ductile iron fittings 48 inches and smaller. 1.2 RELATED WORK SPECIFIED ELSEWHERE A. Section 01300 Record
More informationTABLE OF CONTENTS
DIVISION 33: SEWER AND SEPTIC SYSTEMS 33 3633 UTILITY SEPTIC TANK DRAINAGE FIELD TABLE OF CONTENTS 33 0000-1 SECTION 33 3633-- UTILITY SEPTIC TANK DRAINAGE FIELD PART 1 - GENERAL 1.1 SUMMARY A. Includes
More information1. Will have water lines designed by a North Carolina Registered Professional Engineer.
03/07/16 DEVELOPER/OWNER RESPONSIBILITES 1. Will have water lines designed by a North Carolina Registered Professional Engineer. 2. Will have the water line installed by a North Carolina Licensed Utility
More informationUTILITIES CHECKLIST CITY OF CHESAPEAKE DEPARTMENT OF PUBLIC WORKS SUBDIVISION NAME: A/C & TAX MAP PARCEL NOS (13 DIGITS) DEVELOPER:
UTILITIES CHECKLIST CITY OF CHESAPEAKE DEPARTMENT OF PUBLIC WORKS SUBDIVISION NAME: A/C & TAX MAP PARCEL NOS (13 DIGITS) DEVELOPER: REVIEWING ENGINEER: WATERSHED (INCLUDE SUBSCRIPT) I. PRELIMINARY ITEMS
More informationStainless Steel Aeration Equipment Specification
Section 15 Stainless Steel Aeration Equipment Specification Part 1 - General 1.01 Description A. Scope of Work 1. Furnish, install and test aeration system including air mains, drop pipes, valves, expansion
More informationSECTION 400 SANITARY SEWER SYSTEM
SECTION 400 SANITARY SEWER SYSTEM Section Title Page 401 General................................... 25 402 Materials.................................. 25 403 Design Requirements........................
More informationSECTION FACILITY STORM DRAINAGE PIPING
SECTION 221413 FACILITY STORM DRAINAGE PIPING PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 01 Specification
More informationUBC OKANAGAN UBC Technical Guidelines Section Edition Water Utilities Page 1 of 11
Page 1 of 11 1.0 GENERAL 1.1 This Section refers to those portions of work related to supply and installation of geothermal mains, valves and valve boxes, fittings, service connections and related appurtenances.
More informationSEWER SYSTEM DESIGN GUIDELINES
SEWER SYSTEM DESIGN GUIDELINES PART 1 GENERAL 1.1 GENERAL GUIDELINES A. The following sewer system design guidelines are based on Federal, State and Local health requirements, and the Berkeley County Water
More informationSECTION I. (Sub-Section 3) Water Systems Design Standards. 3.1 General Plans Preparation 3-1
SECTION I (Sub-Section 3) Water Systems Design Standards Article Page 3.1 General 3-1 3.2 Plans Preparation 3-1 3.3 Design and Construction Standards 3-1 thru 3-2 3.4 Protection of Water Supply 3-4 3.5
More informationPIPE AND FITTINGS. Submit product information sheet for joint restraint system to be used.
PIPE AND FITTINGS PART 1 - GENERAL 1.01 SECTION INCLUDES A. Pipe B. Fittings C. Special Fittings D. Pipeline Accessories 1.02 DESCRIPTION OF WORK Construct water mains and building service pipes. 1.03
More informationUnderground Piping for Private Hydrants & Sprinkler Supply Line
City of Brea Brea Fire Department Fire Prevention 1 Civic Center Circle Phone: (714) 990-7655 Underground Piping for Private Hydrants & Sprinkler Supply Line PURPOSE The provision of adequate water supplies
More informationTCC/SHORE TRANSIT BUS MAINTENANCE FACILITY - PHASE II
SECTION 221313 - FACILITY SANITARY SEWERS PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 01 Specification
More informationSECTION STORM DRAINAGE
SECTION 02720 STORM DRAINAGE PART 1 - GENERAL 1.01 WORK INCLUDED A. Trenching and other excavation. B. Ground water control. C. Pipe bedding. D. Installation of storm drains and appurtenances. E. Installation
More informationTECHNICAL SPECIFICATION
TECHNICAL SPECIFICATION ITEM 02514 MANHOLES 1.0 GENERAL 1.1 SCOPE This section provides for construction of sewer manholes complete in place, including the furnishing and adjusting to grade of an existing
More informationSECTION WATER DISTRIBUTION SYSTEMS
SECTION 02660 WATER DISTRIBUTION SYSTEMS PART 1 GENERAL 1.01 SCOPE OF WORK A. WORK covered by this Section consists of furnishing and installing water distribution pipes and appurtenances, including, but
More informationCITY OF LA MARQUE, TEXAS CHAPTER 3 WATER SYSTEM DESIGN CRITERIA
CITY OF LA MARQUE, TEXAS CHAPTER 3 WATER SYSTEM DESIGN CRITERIA CHAPTER 3 WATER SYSTEM DESIGN 3.1 WATER SYSTEM DESIGN GENERAL 3.1.1 Criteria for the design of water service and water distribution lines
More informationEASTSIDE UTILITY DISTRICT
EASTSIDE UTILITY DISTRICT WATER LINE INSTALLATION SPECIFICATIONS AUGUST 2008 UPDATED 11-2016 These specifications provide guidance on the acceptable materials and their installation for developments inside
More informationSECTION VI SANITARY SEWERS
SECTION VI SANITARY SEWERS VI-1. DESIGN GUIDELINES Sewer collection lines and appurtenant structures within the jurisdiction of City of Paso Robles shall be constructed in accordance with plans prepared
More informationSECTION 39 - MANHOLES TABLE OF CONTENTS 39-1 GENERAL PRECAST CONCRETE MANHOLES
Section SECTION 39 - MANHOLES TABLE OF CONTENTS 39-1 GENERAL... 39-1 39-2 PRECAST CONCRETE MANHOLES... 39-1 39-2.01 Precast Concrete Storm Drain Manholes... 39-1 39-3 SADDLE MANHOLES... 39-2 39-3.01 Saddle
More informationSECTION STORM DRAINAGE SYSTEM Excavating, Backfilling, and Compaction for Utilities Cast-in-place Concrete.
SECTION 02720 STORM DRAINAGE SYSTEM PART 1 GENERAL 1.01 SUMMARY A. Related Sections: 1. 02221 - Excavating, Backfilling, and Compaction for Utilities. 2. 03300 - Cast-in-place Concrete. 1.02 REFERENCES
More informationYAKIMA COUNTY, WASHINGTON. Special Provisions For Water Main Construction
YAKIMA COUNTY, WASHINGTON Special Provisions For Water Main Construction The 2014 Standard Specifications for Road, Bridge, and Municipal Construction as prepared by the Washington State Department of
More informationUNIFORM DESIGN AND CONSTRUCTION STANDARDS FOR EXTENDING WATER DISTRIBUTION SYSTEMS SECTION 2 DESIGN STANDARDS
UNIFORM DESIGN AND CONSTRUCTION STANDARDS FOR EXTENDING WATER DISTRIBUTION SYSTEMS SECTION 2 DESIGN STANDARDS DESIGN STANDARDS SECTION 2 INDEX ITEM DESCRIPTION 2.00 GENERAL STATEMENT 2.01 WATER DISTRIBUTION
More informationCONSTRUCTION OF WATER SYSTEMS 1.0 PIPING
CONSTRUCTION OF WATER SYSTEMS 1.0 PIPING 1.1 HANDLING Pipe, fittings and accessories shall be handled with care and shall not be dropped or bumped against pipe or appurtenances already or against any other
More information120 WATER DISTRIBUTION SYSTEMS
120 WATER DISTRIBUTION SYSTEMS 120.01 GENERAL 120.01.01 All public water main extensions shall by designed by a Design Professional and shall be approved by the Public Water Supply Section of NCDEQ/DEH.
More informationCHAPTER 4 - CULINARY WATER
CHAPTER 4 - CULINARY WATER 4.1 GENERAL This Division covers furnishing and installing pressure pipe to the lines and grades shown on the drawings and/or established in the field, and all flushing, testing,
More information