1 TERMS OF REFERENCE FOR CONSTRUCTION MANAGEMENT AND INSPECTION FOR THE REPAIRS AND GASPROOFING OF DIGESTER NO.2 AT THE GUELPH WASTEWATER TREATMENT PLANT BACKGROUND The work generally consists of Repairs and Gas proofing, obtaining TSSA approval and commissioning the Digester No.2 at the Guelph Wastewater Treatment Plant (WWTP), in Guelph, Ontario. Tender documents for the Repairs and Gas proofing to the Digester No.2 can be found on the City s website under contract number There is an inspection report prepared after the Digester cleaning was carried out. LOCATION OF THE WORK The Guelph WWTP is located at 530 Wellington Street South, Guelph, Ontario, Canada. GENERAL SCOPE OF WORK: Construction management resident Inspector (CMRI) from Main Consulting Engineering firm and Gas proofing site inspection (GPSI) This will include but not be limited to: Provide part time on-site inspection services for main consultant and full time inspection of Gas proofing inspector. The main Consulting Engineering firm shall have minimum of 3-4 Digester construction projects experience. CMRI, with directly related relevant experience with a minimum of 3-4 years on wastewater treatment projects and 1-2 Digester projects will be necessary Sub contract a 3 rd party independent gas proofing inspection company with minimum of 3-5 years experience in Digester gas proofing projects for Municipalities and able to provide their staff with NACE certification and with a minimum of 2-3 years experience of inspecting gas proofing projects for Municipalities. Qualification and experience details shall be provided with the bid as it will be used for evaluation purposes as-well. Owner will designate CMRI as owners representative when referred to as owner/client/city in the contractor s tender document attached. Maintain written record of site works progress. Maintain a detailed photographic record of site works progress. Provide digital progress photographs of major project milestones complete with title and date on a monthly basis. Arrange to provide by-weekly reports TR1

2 on works. Prepare and implement procedures for timely delivery of documents etc from contractor to client inorder to avoid delays. Establish roles and responsibilities for all stakeholders. Verify that work is carried out to the contract document and contractors proposal. Review and approve shop drawings. Identify deficiencies and prepare list. Perform structural and mechanical inspection and condition assessment before and after the scaffolding has been installed and before and after coating is removed. Prepare and submit list of additional repairs or replacement and recommend works and materials etc that will have to be included as may be necessary. Where change order will be necessary, evaluate the contractor s quotes and recommend to the client if the rates are adequate considering current market rates etc. Review and approve contractor s plan of works, schedule and spills plan. Review contractors hot work permit and confined space entry in comparison to Cities and coordinate with City and Contractor to finalize on the approach for the project. Support and advice owner for the activity related to the project. Co-ordinate and arrange for TSSA approval prior and after works based on TSSA requirements. Review, evaluate and certify contractors progress payment for client approval, where necessary. Consultant shall be responsible for review and approve contractor s proposal for gas proofing and associated works as in the contractor s scope and review the warranty. Check and ensure that all testing, calibration and manufacturers start-up reports, all maintenance information, and all other associated documentation are included in the O&M manual. Provide client with report of deficiencies with cost estimate prior to issuing Substantial Completion Certificate. TIME FOR COMPLETION FOR THE CONTRACT FOR CONTRACTOR The City anticipates that Repairs and Gas proofing of the Digester will take approximately 30 weeks including the gas tightness test. Scope of work for Construction management resident Inspector (CMRI) In order to successfully fulfill the objectives of the assignment, active involvement from the inspector will be required. The role of the CMRI for the consultant team will include but not be limited to: Acting as the main contact person between the consultant firm and the Wastewater treatment plants project manager to ensure timely and accurate communication. Developing and facilitating the meetings with all key stakeholders. ensuring a high quality of work and approving shop drawings as necessary in a timely manner Review the contractors staging area and recommend any reinstatement etc Ensuring the consultant team resources is appropriately utilized and budgets managed during all aspects of the assignment. playing a significant role in presenting information and responding to questions during the progress of works The site inspector shall meet with City Project Manager when necessary but not TR2

3 less than twice per month during all stages of the assignment. Prepare and distribute meeting agendas and all information to be reviewed at the meeting not less than 3 business days prior to the meeting. Prepare and distribute summaries of the meetings not more than 3 working days after the meeting. Develop procedures etc as may be necessary to be able to control/manage the project All other related works as in this document and based on the attached contractor s tender document. Proactive approach to mitigate any possible spills, quantifying for payment to contractor, monitoring hours spent by consultants staff and their subs etc. Co-ordinate staff for inspection in a timely manner and provide reports to client If staff proposed in bid is not available for the project, provide resumes and rates for the new staff for City approval. City reserves the right to approve/disapprove the staff for the project. Witnessing Testing and commissioning Scope of work for Gas proofing site Inspection Company for inspection and testing services (GPSI) Inspection of Gas proofing Surface Preparation and Coating Application Supply all labour, materials, and equipment necessary to carry out the inspection and testing services described below. The general work shall include but not be limited to review and approve contractors proposal/shop drawings for gas proofing, Inspection of gas proofing surface preparation and coating application. Inspect the surface preparation of the concrete substrate for compliance with Specification Section Notify the Contract Administrator s resident inspection staff when all surface preparation has been successfully completed. Witness and inspect the application of the gasproofing coating for compliance with Specification Section Inspect the gasproofing surface preparation and coating application and submit written reports in accordance with Section Inspect the gasproofing coating before the end of the warranty period to evaluate the performance of the work, in accordance with Specification Section The approved gasproofing coating system selected by the contractor includes the following products: Concrete: 1. Surfacer: TBD 2. Primer: TBD TR3

4 3. Topcoat: TBD Field Quality Control.1 General Requirements:.1 All material and equipment furnished, and work done under this Section, shall be subject to inspection by skilled technical representatives to ensure that the surface preparation and coating installation work is executed in a manner that meets the application requirements specified in the Contract..2 Inspector s services will include the following:.1 Verify that coatings and other materials are as specified in the Contract and meet all quality parameters provided by the supplier..2 Verify that surface preparation and application are as specified in the Contract or by the coating manufacturer, whichever has the most stringent requirements. Verify that coverage and coating usage correspond with that specified in the Contract. This will be completed by monitoring the surface area coated and coating consumption..3 Coating Defects: Check coatings for film characteristics or defects that would adversely affect performance or appearance of coating systems..4 Report:.1 Submit weekly written reports describing inspections made and actions taken to correct nonconforming Work..2 Report nonconforming Work not corrected..3 Submit copies of report to the Engineer and the Contractor, at the end of each week..5 General A Quality Assurance Report should be completed by the Contractor for each of the operations. Conditions as noted in this Specification or required by the coating manufacturer shall be monitored and recorded on this quality assurance report. As a minimum it should record the environmental conditions, the identification of Work completed, visual examination results, and coating consumption, and the coverage readings for the Work completed that day. This report shall be made available to the Engineer or the City upon request. TR4

5 .6 Visual Examination The cured coating shall be generally smooth and free of sharp protrusions. It should not exhibit any cracking, blisters, off-ratio discolouring, sticky spots, uncovered areas or spots, pigment separation, and other defects due to improper application. Areas with these defects shall be repaired or recoated according to repair procedures as required by the coating manufacturer..7 Film Thickness.3 Work Stages:.1 Thickness determinations using a Type 1 or Type 2 thickness gauge shall be conducted in accordance with the SSPC-PA2 procedure..2 Mark areas where the required DFT has not been reached. These areas are subject to be recoated or repaired according to repair procedures as required by the coating manufacturer..3 Dry film gauges shall be calibrated a minimum of once per day in accordance with SSPC PA2..4 Dry film gauges shall be calibrated in the work area where they are to be used..5 All dry film readings of Type 1 gauges shall be reduced by the average magnetic base reading determined in accordance with SSPC PA2. This value shall be recorded on the Quality Assurance Report..6 Use ultrasound gauges to measure and confirm DFT as per SSPC PA-2..1 Specific inspections are required for each Work stage..2 The minimum number of critical stages requiring inspection is:.1 After abrasive blast cleaning to remove previously applied coating and after grouting voids..2 After application of surfacer and before commencement of coating application..3 During coating application the ambient conditions and wet film thickness readings should be monitored and confirmed to meet the project specifications. TR5

6 .4 Defective Work:.4 After application of coating. After each coating the film thickness should be checked, verified that each individual coat is ready to receive the next coat, and is within the manufacturer s stated recoat window and free of intercoat contamination. Observed imperfections such as pinholes, lack of adhesion, insufficient film thickness should be corrected as this point..5 Post curing: This hold point will verify that the final dry film thickness has been achieved. It will include a visual inspection of the coating for surface defects, and a verification that the coating has completely cured..6 After any repair: If the coating becomes damaged at any point, the coating should be repaired and the repair reinspected..1 The inspector shall be responsible to inform the Contractor where to repair or remove defective Work..2 Any repair Work required to remedy defective Work shall comply with the performance requirements of these Specifications in all respects. In the case of removal, the inspector shall ensure defective Work is replaced by materials conforming to this Specification GENERAL CLAUSES 1. Direction and Supervision Under the general direction of the CMRI, the Gas proofing inspection company shall provide personnel, materials, and equipment to perform the required inspections and tests for the entire construction work defined herein. A qualified professional shall instruct and supervise the testing and inspection personnel and correlate testing activities with design parameters and construction conditions. When required by job conditions, the qualified professional shall make site investigations and submit written reports of findings. Base costs on normal working hours, Monday to Friday 7:30 am to 4:30 pm. Do not include overtime or premium pay in the lump sum or unit price amounts. Matters pertaining to construction of the work will be handled by the CMRI. TR6

7 2. Standards Testing and inspection work shall be performed in accordance with the latest applicable ASTM, ACI, AISC, CSA, NACE, TSSA, or other recognized standard test procedures. 3. Owner s Rights The City of Guelph has the right, at any time, to approve or disapprove any person assigned to perform services. 4. Test Reports Immediately after performing tests or inspections, GPSI shall verbally inform the CMRI of test results and conclusions. A report shall be promptly submitted each week and shall be in a form approved by the City of Guelph and shall contain the following information:.1 Name of the project and its location..2 Name of organization and person(s) doing inspection or test..3 Name of Contractor or Subcontractor performing the work..4 Date the inspection or test was performed..5 Location of the materials tested within the project; i.e. identification of test area locations in relation to structure..6 Source of material inspected or tested; material production and delivery documentation..7 Type of test or inspection performed..8 Referenced Standards; i.e. CSA, ASTM, etc..9 Data collected..10 Name of person(s) writing the report..11 Date the report was written..12 Signatures of data collector(s) and report writer(s). Formats of test and inspection reports are to be submitted to and approved by the City of Guelph before commencing with actual testing and inspection. The test reports shall be sequentially numbered. Submit proposed format for approval. 5. Report Distribution The signed reports shall be submitted by the GPSI to the City of Guelph, the CMRI, within five (5) working days of the inspection or testing. 6. Schedule The anticipated schedule for the inspection and testing services, based on the general contractor s current construction schedule, is shown below. The schedule is TR7

8 approximate only and is subject to change. Digester: November 2013 May 2014 Provide the following for City to Review Proposals Qualification & Experience Evaluation of relevant qualifications and expertise of assigned staff and sub consultant staff members (Details of projects and staff involvement on the project should be provided. Staff should have adequate qualifications and training including confined space entry training) Methodology Should include the understanding and approach to the project and quality assurance and completeness References Provide at least three project references with a similar scope and type Where possible include at least one municipal reference. Describe the nature of the projects including budget, schedule, person resources and scope. The City reserves the right to contact other references than the ones submitted. TR8

SECTION POLYURETHANE MIC COATINGS. A. Furnish and install special coating systems in accordance with the Contract Documents.

SECTION POLYURETHANE MIC COATINGS. A. Furnish and install special coating systems in accordance with the Contract Documents. SECTION 09802 POLYURETHANE MIC COATINGS PART 1 -- GENERAL 1.01 THE REQUIREMENTS A. Furnish and install special coating systems in accordance with the Contract Documents. B. Polyurethane MIC Coating 1.

More information

COATING NEW STRUCTURAL STEEL SIGN SUPPORT STRUCTURES - Item No. Special Provision No. 911S09 November 2006

COATING NEW STRUCTURAL STEEL SIGN SUPPORT STRUCTURES - Item No. Special Provision No. 911S09 November 2006 COATING NEW STRUCTURAL STEEL SIGN SUPPORT STRUCTURES - Item No. Special Provision No. 911S09 November 2006 Amendment to OPSS 911, November 2004 for hot dip galvanizing and subsequent painting, where required,

More information

C. Requirements of this Section relate to customized fabrication and installation procedures, not production of standard products.

C. Requirements of this Section relate to customized fabrication and installation procedures, not production of standard products. SECTION 01400 QUALITY CONTROL SERVICES PART 1 - GENERAL 1.01 RELATED DOCUMENTS A. Drawings and general provisions of Contract, including General and Supplementary Conditions and other Division-1 Specification

More information

SSPC-SP7: Brush-Off Blast Cleaning..1 Minimum surface temperature: 2 C (35 F).2 Maximum surface temperature: 49 C (120 F)

SSPC-SP7: Brush-Off Blast Cleaning..1 Minimum surface temperature: 2 C (35 F).2 Maximum surface temperature: 49 C (120 F) City of Guelph Corporate Building Maintenance Contract: Exhibition Park Arena Open Web Steel Joists and Roof Decking Painting 1 GENERAL 1.1 Section Intent This Section describes products and procedures

More information

SECTION QUALITY REQUIREMENTS

SECTION QUALITY REQUIREMENTS SECTION 014000 - PART 1 - GENERAL 1.1 SUMMARY A. Defines SRP requirements for Contractor Quality Control and Owner Quality Assurance. As an Electric and Water Utility, SRP has many critical facilities.

More information

Rust-Oleum Industrial Brands Specification

Rust-Oleum Industrial Brands Specification Rust-Oleum Industrial Brands Specification Coating Specification for Rust-Oleum Virtual Solutions Coating Solution 23 A solvent based coating system High Performance 4315 High Heat Aluminum For service

More information

MICHIGAN DEPARTMENT OF TRANSPORTATION SPECIAL PROVISION FOR WARRANTY ON CONCRETE SURFACE COATING

MICHIGAN DEPARTMENT OF TRANSPORTATION SPECIAL PROVISION FOR WARRANTY ON CONCRETE SURFACE COATING MICHIGAN DEPARTMENT OF TRANSPORTATION SPECIAL PROVISION FOR WARRANTY ON CONCRETE SURFACE COATING OFS:BDB 1 of 5 APPR:JAB:CER:02-10-17 FHWA:APPR:02-28-17 a. Description. This work consists of furnishing

More information

Rust-Oleum Industrial Brands Specification

Rust-Oleum Industrial Brands Specification Rust-Oleum Industrial Brands Specification Coating Specification for Rust-Oleum Virtual Solutions Coating Solution 2 A solvent based coating system High Performance 9100/9800 System DTM Epoxy Mastic/DTM

More information

QUALITY REQUIREMENTS

QUALITY REQUIREMENTS SECTION 014000 - QUALITY REQUIREMENTS PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division 01 Specification

More information

SECTION CONTRACTOR QUALITY CONTROL

SECTION CONTRACTOR QUALITY CONTROL SECTION 01451 CONTRACTOR QUALITY CONTROL PART 1 GENERAL 1.1 REFERENCES The publications listed below form a part of this specification to the extent referenced. The publications are referred to within

More information

A. The CONTRACTOR shall provide pipe coating, complete and in place, in accordance with the Contract Documents.

A. The CONTRACTOR shall provide pipe coating, complete and in place, in accordance with the Contract Documents. POLYURETHANE COATING ON STEEL PIPE PART 1 -- GENERAL 1.1 THE REQUIREMENT A. The CONTRACTOR shall provide pipe coating, complete and in place, in accordance with the Contract Documents. 1.2 REFERENCE SPECIFICATIONS,

More information

Rust-Oleum Industrial Brands Specification

Rust-Oleum Industrial Brands Specification Rust-Oleum Industrial Brands Specification Coating Specification for Rust-Oleum Virtual Solutions Coating Solution 3 A solvent based coating system High Performance 9300/9800 System Extended Recoat Epoxy

More information

SECTION CORROSION PROTECTION FOR CONCRETE STRUCTURES

SECTION CORROSION PROTECTION FOR CONCRETE STRUCTURES 0590-104217 PART 1 GENERAL 1.01 SCOPE OF WORK SECTION 09850 CORROSION PROTECTION FOR CONCRETE STRUCTURES A. This specification covers work, materials and equipment required for protecting the interior

More information

.4 Submit proof of qualifications and authorization in writing to the Contract Administrator, four (4) weeks prior to commencement of Work.

.4 Submit proof of qualifications and authorization in writing to the Contract Administrator, four (4) weeks prior to commencement of Work. Construction of Roads and Landscaping Page 1 of 8 1. GENERAL 1.1 Work Included.1 Supply and Installation of specialty coatings for the concrete pavement areas adjacent to the south side of the Bulk Chemical

More information

INTERNATIONAL ASSOCIATION OF PLUMBING AND MECHANICAL OFFICIALS UNIFORM EVALUATION SERVICES

INTERNATIONAL ASSOCIATION OF PLUMBING AND MECHANICAL OFFICIALS UNIFORM EVALUATION SERVICES INTERNATIONAL ASSOCIATION OF PLUMBING AND MECHANICAL OFFICIALS UNIFORM EVALUATION SERVICES EVALUATION CRITERIA FOR STRUCTURAL STEEL APPROVED FABRICATOR INSPECTION PROGRAMS 1.0 PURPOSE EC 020-2014 (Adopted

More information

NORTHWESTERN UNIVERSITY PROJECT NAME JOB # ISSUED: 03/29/2017

NORTHWESTERN UNIVERSITY PROJECT NAME JOB # ISSUED: 03/29/2017 SECTION 01 4000 - QUALITY REQUIREMENTS PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division 01 Specification

More information

Specifications. Specifications (Architectual) Metallic System. Metallic System

Specifications. Specifications (Architectual) Metallic System. Metallic System (Architectual) Metallic System Architectual NeverStrip Floor Coatings, 6-15 Mils Master Format Section 096700 Fluid Applied Flooring 1 of 6 NeverStrip Metallic High-Build Decorative Epoxy/Urethane Coating

More information

COATING SPECIFICATION ELASTOMERIC POLYURETHANE PROTECTIVE COATING ON CONCRETE COATING SPECIFICATION: I1 ISSUE: 1 DATE: 12 DECEMBER 2012

COATING SPECIFICATION ELASTOMERIC POLYURETHANE PROTECTIVE COATING ON CONCRETE COATING SPECIFICATION: I1 ISSUE: 1 DATE: 12 DECEMBER 2012 1.0 SCOPE This document summarises the procedure for spray applying Elastomeric Polyurethane protective coatings (e.g. Polybrid, Polyurea ) onto concrete structures. Refer Design Standard, DS 95 (Standard

More information

A. This Section includes administrative and procedural requirements for quality assurance and quality control.

A. This Section includes administrative and procedural requirements for quality assurance and quality control. SECTION 01400 - QUALITY REQUIREMENTS PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division 1 Specification

More information

CITY OF TAMPA ADDENDUM NO. 1. DATE: September 15, Contract 11-C-00001; Wastewater Sewer Rehabilitation by Cured-in-Place Pipe (C.I.P.P.

CITY OF TAMPA ADDENDUM NO. 1. DATE: September 15, Contract 11-C-00001; Wastewater Sewer Rehabilitation by Cured-in-Place Pipe (C.I.P.P. CITY OF TAMPA Pam Iorio, Mayor CONTRACT ADMINISTRATION DEPARTMENT David L. Vaughn, AIA, Director ADDENDUM NO. 1 DATE: September 15, 2010 Contract 11-C-00001; Wastewater Sewer Rehabilitation by Cured-in-Place

More information

ARCHITECTURAL SPECIFICATION

ARCHITECTURAL SPECIFICATION THERMO-SORB ARCHITECTURAL SPECIFICATION PART 1 GENERAL 1.1 SECTION INCLUDES Spray applied, subliming / thin film intumescent, fire resistive coating for interior structural steel framing. Fire resistive

More information

Student Services & Classroom Addition

Student Services & Classroom Addition SECTION 014000 - QUALITY REQUIREMENTS PART 1 - GENERAL 1.1 SUMMARY A. Section includes administrative and procedural requirements for quality assurance and quality control. B. Testing and inspecting services

More information

Rust-Oleum Industrial Brands Specification

Rust-Oleum Industrial Brands Specification Rust-Oleum Industrial Brands Specification Coating Specification for Rust-Oleum Virtual Solutions Coating Solution 44 A solvent based coating system High Performance 7400 System 450 VOC DTM Alkyd Enamel

More information

1/4 Industrial Trowel System

1/4 Industrial Trowel System System Specification 1/4 Industrial Trowel System Revision Date: 6/2015 Printed Date: 6/2015 PART 1 GENERAL 1.01 RELATED DOCUMENTS Drawings and general provisions of contract including General and Special

More information

SQS Supplement C. Galvanizers. MnDOT Supplier Qualification Standard

SQS Supplement C. Galvanizers. MnDOT Supplier Qualification Standard SQS Supplement C MnDOT Supplier Qualification Standard Galvanizers Standard supports the Department's Approved Supplier Program for Structural Metals Suppliers as described in the current Standard Specification

More information

Decorative Quartz Floor Coating System

Decorative Quartz Floor Coating System Decorative Quartz Floor Coating System 1.01 - Work Included 1. Furnish necessary material, labor, and equipment required to prepare designated areas and install a DecoFloor Quartz System 2. Submit three

More information

CITY OF TAMPA ADDENDUM NO. 3. DATE: February 15, 2017

CITY OF TAMPA ADDENDUM NO. 3. DATE: February 15, 2017 CITY OF TAMPA Bob Buckhorn, Mayor CONTRACT ADMINISTRATION DEPARTMENT Michael W. Chucran, Director ADDENDUM NO. 3 DATE: February 15, 2017 Contract 16-C-00027; Ragan Park Restroom Improvements - Rebid Bidders

More information

1993 Specifications CSJ SPECIAL SPECIFICATION ITEM Tunnel Painting

1993 Specifications CSJ SPECIAL SPECIFICATION ITEM Tunnel Painting 1993 Specifications CSJ 8075-18-005 SPECIAL SPECIFICATION ITEM 4514 Tunnel Painting 1. Description. This Item shall govern for the painting of the walls and ceiling of a tunnel. The intent is to provide

More information

Rust-Oleum Industrial Brands Specification

Rust-Oleum Industrial Brands Specification Rust-Oleum Industrial Brands Specification Coating Specification for Rust-Oleum Virtual Solutions Coating Solution 14 A 100% solids epoxy coating system Concrete Saver 6500 System 100% Solids Epoxy For

More information

SECTION QUALITY CONTROL

SECTION QUALITY CONTROL SECTION 01 45 00 QUALITY CONTROL PART 1 - GENERAL 1.1 DESCRIPTION This section specifies requirements for Contractor Quality Control (CQC) for Design-Bid-Build (DBB) or Design-Build (DB) construction projects.

More information

Pigeon Forge, Tennessee City Hall and Thurman Lift Station Coating Rehabilitation. Contract Documents

Pigeon Forge, Tennessee City Hall and Thurman Lift Station Coating Rehabilitation. Contract Documents Pigeon Forge, Tennessee City Hall and Thurman Lift Station Coating Rehabilitation April 21, 2017 Contract Documents Prepared By: Veolia Water North America For the City of Pigeon Forge, Tennessee P.O.

More information

Rust-Oleum Industrial Brands Specification

Rust-Oleum Industrial Brands Specification Rust-Oleum Industrial Brands Specification Coating Specification for Rust-Oleum Virtual Solutions Coating Solution 65 A solvent based coating system High Performance 9100 System 100 VOC DTM Epoxy Mastic

More information

Engine Bay Floors Floor Resurfacing 4000

Engine Bay Floors Floor Resurfacing 4000 Engine Bay Floors Floor Resurfacing 4000 P.O. Box 341 Macungie, PA 18062 610.530.7710 800.573.9198 www.enginebayfloors.com 1.1 SUBMITTALS Flooring Specification SECTION 1 GENERAL A. Product Data: Submit

More information

1/16 Single Broadcast Polymer Flooring System

1/16 Single Broadcast Polymer Flooring System specification 1/16 Single Broadcast Polymer Flooring System Part 1 - GENERAL General Provisions A. Work to be covered by this section, under written specification or by drawing, shall comply with all provisions

More information

1.04 REFERENCES STANDARDS.1 For reference standards tests & results refer to Manufactures Product Data Sheets

1.04 REFERENCES STANDARDS.1 For reference standards tests & results refer to Manufactures Product Data Sheets This specification covers InhibiChem CR-GF-L Chemical-Resistant Glass Flake-Reinforced Steel Tank Lining System. This system consists of a vinyl ester primer, and two troweled coats of glass flake filled

More information

SPECIAL INSPECTION & TESTING AGREEMENT CITY OF NORTON SHORES BUILDING DEPARTMENT Michigan Building Code 2015

SPECIAL INSPECTION & TESTING AGREEMENT CITY OF NORTON SHORES BUILDING DEPARTMENT Michigan Building Code 2015 Project Name: Project Address: SPECIAL INSPECTION & TESTING AGREEMENT CITY OF NORTON SHORES BUILDING DEPARTMENT Michigan Building Code 201 Building Permit No.: PRIOR TO THE ISSUANCE OF THE BUILDING PERMIT:

More information

1/8 DECORATIVE BROADCAST FLOORING SYSTEM

1/8 DECORATIVE BROADCAST FLOORING SYSTEM AIA specification AIA specification AIA Specification 1/8 DECORATIVE BROADCAST FLOORING SYSTEM Part 1 - GENERAL General Provisions A. Work to be covered by this section, under written specification or

More information

Rust-Oleum Industrial Brands Specification

Rust-Oleum Industrial Brands Specification Rust-Oleum Industrial Brands Specification Coating Specification for Rust-Oleum Virtual Solutions Coating Solution 70 A solvent based coating system Concrete Saver 6200 System Fast-Cure Epoxy Floor Coating

More information

Concrete and H2S Gas in Wet Wells and Tanks. James Orr - Project Manager NACE Inspector - Dixon Engineering

Concrete and H2S Gas in Wet Wells and Tanks. James Orr - Project Manager NACE Inspector - Dixon Engineering Concrete and H2S Gas in Wet Wells and Tanks James Orr - Project Manager NACE Inspector - Dixon Engineering What can H2S Gas do to Concrete????????? Ho Chunk WWTP Influent Wet Well Recoating Project Influent

More information

INSPECTION SYSTEM REQUIREMENTS

INSPECTION SYSTEM REQUIREMENTS MILITARY SPECIFICATIONS MIL-I-45208A INSPECTION SYSTEM REQUIREMENTS This specification has been approved by the Department of Defense and is mandatory for use by all Agencies. 1. SCOPE 1.1 Scope. This

More information

Protective Industrial Polymers - USA Manufacturer s Specification February 11, 2015

Protective Industrial Polymers - USA Manufacturer s Specification February 11, 2015 This specification covers InhibiChem SR-GF-L Enhanced Chemical and Solvent-Resistant Glass-Flake Reinforced Steel Tank Lining System. This system consists of a vinyl ester primer, and two troweled coats

More information

BROADCAST KITCHEN FLOORING SYSTEM

BROADCAST KITCHEN FLOORING SYSTEM AIA specification AIA specification AIA Specification Part 1 - GENERAL BROADCAST KITCHEN FLOORING SYSTEM General Provisions A. Work to be covered by this section, under written specification or by drawing,

More information

ACCREDITATION OF BOILER AND PRESSURE VESSEL REPAIR OR ALTERATION ORGANIZATIONS

ACCREDITATION OF BOILER AND PRESSURE VESSEL REPAIR OR ALTERATION ORGANIZATIONS ACCREDITATION OF BOILER AND PRESSURE VESSEL REPAIR OR ALTERATION ORGANIZATIONS TSSA GUIDE FOR SURVEY TEAMS The Technical Standards and Safety Authority Boilers and Pressure Vessels Safety Division 3300

More information

Capital Projects Group Mechanical Work Commissioning Specification

Capital Projects Group Mechanical Work Commissioning Specification Capital Projects Group Mechanical Work Commissioning Specification Specification 20 05 40 Revision 0 Date: August 2018 Mechanical Work Commissioning Specification Specification 20 05 40 Publication Date:

More information

DECOFLAKE DECORATIVE FLOORING SYSTEM

DECOFLAKE DECORATIVE FLOORING SYSTEM AIA Specification DECOFLAKE DECORATIVE FLOORING SYSTEM Part 1 - GENERAL General Provisions A. Work to be covered by this section, under written specification or by drawing, shall comply with all provisions

More information

CONSTRUCTION SPECIFICATION FOR CRACK REPAIR - CONCRETE

CONSTRUCTION SPECIFICATION FOR CRACK REPAIR - CONCRETE ONTARIO PROVINCIAL STANDARD SPECIFICATION METRIC OPSS 932 MARCH 1998 CONSTRUCTION SPECIFICATION FOR CRACK REPAIR - CONCRETE 932.01 SCOPE 932.02 REFERENCES 932.03 DEFINITIONS TABLE OF CONTENTS 932.04 SUBMISSION

More information

APPLICATION OF CHEMICAL RESISTANT PROTECTIVE COATING ON CONCRETE BUNDS IN WATER AND WASTEWATER TREATMENT PLANTS

APPLICATION OF CHEMICAL RESISTANT PROTECTIVE COATING ON CONCRETE BUNDS IN WATER AND WASTEWATER TREATMENT PLANTS APPLICATION OF CHEMICAL RESISTANT PROTECTIVE COATING ON CONCRETE BUNDS IN WATER AND WASTEWATER TREATMENT PLANTS SPECIFICATION: CR5 ISSUE: 2 DATE: AUGUST 2018 1.0 SCOPE This document summarises the procedure

More information

Food Service FDA Title 21 CFR

Food Service FDA Title 21 CFR 1.0 Scope 1.1 This recommendation covers the requirements for the surface preparation, application of primers and finish coats of resin linings to the interior surfaces of carbon/stainless steel vessels.

More information

Rust-Oleum Industrial Brands Specification

Rust-Oleum Industrial Brands Specification Rust-Oleum Industrial Brands Specification Coating Specification for Rust-Oleum Virtual Solutions Coating Solution 22 A solvent based coating system Concrete Saver AS5400Anti-Slip High One-Step Epoxy System

More information

PROLINE MID-TEMPERATURE VINYL ESTER LINING INSTALLATION GUIDE ProLine 4865T with optional 4822S Gel Coat Food Service FDA Title 21 CFR 175.

PROLINE MID-TEMPERATURE VINYL ESTER LINING INSTALLATION GUIDE ProLine 4865T with optional 4822S Gel Coat Food Service FDA Title 21 CFR 175. 1.0 Scope 1.1 This recommendation covers the requirements for the surface preparation, application of primers and finish coats of resin linings to the interior surfaces of carbon/stainless steel vessels.

More information

DECOCOLOR FLOORING SYSTEM

DECOCOLOR FLOORING SYSTEM AIA Specification DECOCOLOR FLOORING SYSTEM Part 1 - GENERAL General Provisions A. Work to be covered by this section, under written specification or by drawing, shall comply with all provisions of the

More information

Rust-Oleum Industrial Brands Specification

Rust-Oleum Industrial Brands Specification Rust-Oleum Industrial Brands Specification Coating Specification for Rust-Oleum Virtual Solutions Coating Solution 19 A 100% solids epoxy coating system Concrete Saver AS6500 System Anti-Slip 100% Solids

More information

NFCA 400 Field Quality Assurance Procedure for Application of Mastic and Thin-Film Intumescent Fire Resistive Coatings

NFCA 400 Field Quality Assurance Procedure for Application of Mastic and Thin-Film Intumescent Fire Resistive Coatings NFCA 400 Field Quality Assurance Procedure for Application of Mastic and Thin-Film Intumescent Fire Resistive Coatings 1 Scope The application of mastic and thin-film intumescent fire resistive coatings

More information

Rust-Oleum Industrial Brands Specification

Rust-Oleum Industrial Brands Specification Rust-Oleum Industrial Brands Specification Coating Specification for Rust-Oleum Virtual Solutions Coating Solution 20 A solvent based coating system Concrete Saver Anti-Slip High Performance Epoxy AS9100

More information

Special Provision No. 911F06 October 2000

Special Provision No. 911F06 October 2000 COATING EXISTING STRUCTURAL STEEL - Item No. Special Provision No. 911F06 October 2000 References, Definitions, Pre-Tender Trials, Elimination of Pre-Start Material Sample, Material Requirements, Operational

More information

SECTION LITHIUM BASED MOISTURE VAPOR CONTROL CURE SYSTEM AND FINISHING

SECTION LITHIUM BASED MOISTURE VAPOR CONTROL CURE SYSTEM AND FINISHING SECTION 033960 LITHIUM BASED MOISTURE VAPOR CONTROL CURE SYSTEM AND FINISHING PART 1 GENERAL 1.1 SECTION INCLUDES A. Work includes labor, materials, appliances, tools, equipment, facilities, transportation,

More information

SECTION GENERAL REQUIREMENTS PART 1 - GENERAL I 1 GENERAL REQUIRMENTS

SECTION GENERAL REQUIREMENTS PART 1 - GENERAL I 1 GENERAL REQUIRMENTS SECTION 01 00 00 GENERAL REQUIREMENTS PART 1 - GENERAL 1.1 SECTION INCLUDES A. Summary of Work: 1. General 2. Contract. B. Contract Considerations: 1. Schedule of values. 2. Applications for payment. 3.

More information

May 8, 2017 ADDENDUM #1. IFB Resin Floor System For Highway Department Central District Building

May 8, 2017 ADDENDUM #1. IFB Resin Floor System For Highway Department Central District Building May 8, 2017 ADDENDUM #1 IFB 17-082 Resin Floor System For Highway Department Central District Building Addendum #1 is being issued to offer an alternate resin flooring system. 096700 FLUID-APPLIED FLOORING

More information

ZONE 7 WATER AGENCY CWS 5 TURNOUT REPLACEMENT PROJECT # ADDENDUM NO. 3 April 02, 2019

ZONE 7 WATER AGENCY CWS 5 TURNOUT REPLACEMENT PROJECT # ADDENDUM NO. 3 April 02, 2019 ZONE 7 WATER AGENCY CWS 5 TURNOUT REPLACEMENT PROJECT # 275-18 ADDENDUM NO. 3 April 02, 2019 This Addendum No. 3 ( Addendum ) is dated the date set forth above and modifies certain Bidding Documents issued

More information

GUIDE SPECIFICATION SECTION 07576

GUIDE SPECIFICATION SECTION 07576 GUIDE SPECIFICATION SECTION 07576 TRAFFIC DECK MEMBRANE SYSTEM NOTE TO ARCHITECTS & ENGINEERS: The Oak Ridge traffic membrane system provides for applied high build, durable and waterproof membrane consisting

More information

Rust-Oleum Industrial Brands Specification

Rust-Oleum Industrial Brands Specification Rust-Oleum Industrial Brands Specification Coating Specification for Rust-Oleum Virtual Solutions Coating Solution 40 A water based coating system Sierra Performance S40 Water Based Epoxy Floor Coating

More information

SECTION RESINOUS FLOORING

SECTION RESINOUS FLOORING SECTION 09705 PART I - GENERAL 1.01 DESCRIPTION A. Scope: Work of this Section includes all materials and installation necessary to provide resinous flooring system with integral cove base and top finish

More information

DRAFT ITEM GP-100 ITEM GP-100 CONTRACTOR QUALITY CONTROL PROGRAM 1.1 GENERAL

DRAFT ITEM GP-100 ITEM GP-100 CONTRACTOR QUALITY CONTROL PROGRAM 1.1 GENERAL 1.1 GENERAL When the specification requires a Contractor Quality Control Program, the Contractor shall establish, provide, and maintain an effective Quality Control Program that details the methods and

More information

COATING SPECIFICATION INORGANIC ZINC SILICATE, EPOXY PRIMER MIST-COAT, TWO PACK ACRYLIC TOP COAT ON STEEL OR CAST IRON

COATING SPECIFICATION INORGANIC ZINC SILICATE, EPOXY PRIMER MIST-COAT, TWO PACK ACRYLIC TOP COAT ON STEEL OR CAST IRON 1.0 SCOPE This document summarises the procedure for the application of Inorganic Zinc Silicate (IZS), Epoxy Primer Mist Coat coat followed by two pack Acrylic on Steel or Cast Iron structures. Refer Design

More information

FACILITIES MANAGEMENT

FACILITIES MANAGEMENT FACILITIES MANAGEMENT Design & Construction January 18, 2017 Re: Request for Proposals- Third Party Testing and Special Inspections for Concrete, Applied Fire-Proofing, and High Performance Coatings 0691801

More information

DURASHIELD 110 &

DURASHIELD 110 & DURASHIELD 110 & 110-61 EFFECTIVE: 3/01/19 I. Scope A. This specification defines application requirements of DuraShield 110/110-61 plural-component, 100% solids, 1:1 volumetric mix ratio polyurethane

More information

Refining Corrosion Technologist NACE-RCT-001

Refining Corrosion Technologist NACE-RCT-001 Refining Corrosion Technologist NACE-RCT-001 NACE Coating Inspector Level 1 Written Exam Exam Preparation Guide October 2017 Exam Preparation Guide May 2017 1 Table of Contents Introduction... 3 Target

More information

SECTION CERAMIC EPOXY LINING DUCTILE IRON PIPE AND FITTINGS

SECTION CERAMIC EPOXY LINING DUCTILE IRON PIPE AND FITTINGS SECTION 02500 CERAMIC EPOXY LINING DUCTILE IRON PIPE AND FITTINGS (As provided by Tnemec Company, Inc.) GENERAL 1.1 SUMMARY 1. This Section includes surface preparation and shop application of Series 431

More information

COATING SPECIFICATION HIGH BUILD CERAMIC FILLED EPOXY COATING ON NEW AND EXISTING PUMPS COATING SPECIFICATION: F3 ISSUE: 1 DATE: 12 DECEMBER 2012

COATING SPECIFICATION HIGH BUILD CERAMIC FILLED EPOXY COATING ON NEW AND EXISTING PUMPS COATING SPECIFICATION: F3 ISSUE: 1 DATE: 12 DECEMBER 2012 1.0 SCOPE This document summarises the procedure for the application of using 2 pack High Build Ceramic Filled Epoxy coating. Refer Design Standard, DS 95 (Standard for the Selection, Preparation, Application,

More information

Broadcast Parking Garage System

Broadcast Parking Garage System AIA Specification Part 1 General Broadcast Parking Garage System 1.01 Work Included A. All work to be provided in this section shall include material, labor, and equipment necessary to furnish the complete

More information

Facilities Planning and Construction (FP&C)

Facilities Planning and Construction (FP&C) Appendix 8.4a Facilities Planning and Construction (FP&C) UAA FP&C Quality Assessment Checklist (A) Project: PM: Project ID: Updated:

More information

SECTION INTUMESCENT MASTIC FIREPROOFING

SECTION INTUMESCENT MASTIC FIREPROOFING PART 1 GENERAL 1.01 SUMMARY SECTION 07 81 23 - INTUMESCENT MASTIC FIREPROOFING A. Section Includes: 1. Intumescent Mastic Fireproofing for Application to Exposed Steel 2. Protection of Adjacent Surfaces

More information

SUPPLY AND INSTALLATION OF TURBINES AND GENERATORS CONTRACT SCHEDULE 8 QUALITY MANAGEMENT TABLE OF CONTENTS

SUPPLY AND INSTALLATION OF TURBINES AND GENERATORS CONTRACT SCHEDULE 8 QUALITY MANAGEMENT TABLE OF CONTENTS SUPPLY AND INSTALLATION OF TURBINES AND GENERATORS CONTRACT SCHEDULE 8 QUALITY MANAGEMENT TABLE OF CONTENTS 1 INTERPRETATION... 1 1.1 Definitions... 1 2 QUALITY MANAGEMENT SYSTEM... 2 2.1 Quality Management

More information

SECTION RESINOUS FLOORING or SECTION QUARTZ FLOORING

SECTION RESINOUS FLOORING or SECTION QUARTZ FLOORING SECTION 09 67 23 RESINOUS FLOORING or SECTION 09 67 26 QUARTZ FLOORING PART 1 - GENERAL 1.1 SUMMARY (Specification writer shall add, delete or amend, as deemed necessary) A. Provide all labor, materials,

More information

ACCREDITATION OF MANUFACTURERS OF BOILERS & PRESURE VESSELS

ACCREDITATION OF MANUFACTURERS OF BOILERS & PRESURE VESSELS ACCREDITATION OF MANUFACTURERS OF BOILERS & PRESURE VESSELS [Not applicable to ASME Sec. IV, Cast Iron and Aluminum Boilers, ASME Sec. VIII Div 1, UG-90 (c) (2) and Graphite Vessels, ASME Sec. VIII, Div.

More information

SECTION STRUCTURAL STEEL

SECTION STRUCTURAL STEEL PART 1 GENERAL 1.01 SCOPE OF WORK A. The Contractor shall furnish and install all materials, labor, equipment and incidentals required to provide structural steel shown on the Contract Drawings and as

More information

Ontario ENGINEERING STANDARD SPECIFICATION 1/7 REV. SPECIALTY ENGINEERING MATERIALS ENGINEERING QA CLARABELLE MILL NI-HARD TYPE 1 LINERS

Ontario ENGINEERING STANDARD SPECIFICATION 1/7 REV. SPECIALTY ENGINEERING MATERIALS ENGINEERING QA CLARABELLE MILL NI-HARD TYPE 1 LINERS 1/7 Rev Description Approved by Reviewed by Issue Date YYYY/MM/DD 1 Document format and number changed. Previous number QA - 015 PB 011/1/4 PB 011/1/4 01/04/19 SPEC Reviewed 016 Regional Approvals removed,

More information

SECTION CONTRACTOR QUALITY CONTROL

SECTION CONTRACTOR QUALITY CONTROL SECTION 01 40 00 PART 1 - GENERAL 1.1 SUMMARY A. This section covers the establishment and operation of the Contractor s Quality Control (CQC) system as specified by the General Conditions of the Contract.

More information

TNEMEC ELEVATED TEMERATURE VINYL ESTER LINING INSTALLATION GUIDE ProPolymer Series 1402, 1422 and 1432 Direct Food Contact FDA Title 21 CFR 175.

TNEMEC ELEVATED TEMERATURE VINYL ESTER LINING INSTALLATION GUIDE ProPolymer Series 1402, 1422 and 1432 Direct Food Contact FDA Title 21 CFR 175. 1.0 Scope 1.1 This recommendation covers the requirements for the surface preparation and the application of primers and finish coat linings for the interior surfaces of carbon/stainless steel vessels

More information

DURASHIELD JARS APPLICATION SPECIFICATION SHEET FIELD-APPLIED JOINT & REPAIR SYSTEM (JARS) EFFECTIVE: 6/2/15

DURASHIELD JARS APPLICATION SPECIFICATION SHEET FIELD-APPLIED JOINT & REPAIR SYSTEM (JARS) EFFECTIVE: 6/2/15 DURASHIELD 310-61 JARS FIELD-APPLIED JOINT & REPAIR SYSTEM (JARS) I. Scope A. This specification defines application requirements of DuraShield 310-61 Joint and Repair System (JARS) plural-component 100%

More information

Note: This specification was written for Clarabelle Mill's flotation cells but may have other applications.

Note: This specification was written for Clarabelle Mill's flotation cells but may have other applications. 017/03/3 1/7 1.0 PURPOSE This specification describes the minimum application and performance requirements for a field-applied, elastomer spray coating either polyurethane or polyurea type. Note: This

More information

Trident Precision Manufacturing

Trident Precision Manufacturing Trident Precision Manufacturing QASQC Rev. A 6/7/06 Title: Supplier Quality Clauses Author: April V. Lusk Director of Quality General Suppliers are responsible for compliance to all stated Quality Clauses

More information

TECHNICAL REQUIREMENTS AND SPECIFICATIONS. PROTECTIVE COATING OF STEEL (As Provided by Raven Lining Systems) FOREWORD

TECHNICAL REQUIREMENTS AND SPECIFICATIONS. PROTECTIVE COATING OF STEEL (As Provided by Raven Lining Systems) FOREWORD TECHNICAL REQUIREMENTS AND SPECIFICATIONS PROTECTIVE COATING OF STEEL (As Provided by Raven Lining Systems) FOREWORD This specification covers work, materials and equipment required for protecting and/or

More information

I. Development, Submittal, and Acceptance of a Quality Management System

I. Development, Submittal, and Acceptance of a Quality Management System I. Development, Submittal, and Acceptance of a Quality Management System 1. Scope Under the Contract, quality assurance and quality control management are the responsibility of the Contractor. The Contractor

More information

DURASHIELD 210 &

DURASHIELD 210 & DURASHIELD 210 & 210-61 I. Scope A. This specification defines application requirements of DuraShield 210 & DuraShield 210-61 plural-component 100% solids, 2:1 volumetric mix ratio polyurethane to steel

More information

COATING SPECIFICATION ANTI-GRAFFITI COATING ON OLD AND NEW CONCRETE STRUCTURES COATING SPECIFICATION: J2 ISSUE: 1 DATE: 12 DECEMBER 2012

COATING SPECIFICATION ANTI-GRAFFITI COATING ON OLD AND NEW CONCRETE STRUCTURES COATING SPECIFICATION: J2 ISSUE: 1 DATE: 12 DECEMBER 2012 : J2 ISSUE: 1 DATE: 12 DECEMBER 2012 1.0 SCOPE This document summarises the coating procedure to protect external surfaces of concrete structures by application of one coat of epoxy concrete sealer followed

More information

1.07 SUPPLEMENTS PRODUCTS (NOT USED) EXECUTION (NOT USED) END OF SECTION

1.07 SUPPLEMENTS PRODUCTS (NOT USED) EXECUTION (NOT USED) END OF SECTION 1.07 SUPPLEMENTS d. Complete using typewriter or electronic printing. 3. Include detailed lubrication instructions and diagrams showing points to be greased or oiled; recommend type, grade, and temperature

More information

TECHNICAL SPECIFICATION FOR CURED-IN-PLACE MANHOLE REHABILITATION LINER SYSTEM

TECHNICAL SPECIFICATION FOR CURED-IN-PLACE MANHOLE REHABILITATION LINER SYSTEM TECHNICAL SPECIFICATION FOR CURED-IN-PLACE SYSTEM PART 1 GENERAL 1.01 SCOPE OF WORK Furnish all materials, labor, equipment, tools and required incidentals for providing and installing a resin impregnated

More information

CONSTRUCTION SPECIFICATION FOR COATING STRUCTURAL STEEL SYSTEMS

CONSTRUCTION SPECIFICATION FOR COATING STRUCTURAL STEEL SYSTEMS ONTARIO PROVINCIAL STANDARD SPECIFICATION METRIC OPSS 911 APRIL 2010 CONSTRUCTION SPECIFICATION FOR COATING STRUCTURAL STEEL SYSTEMS TABLE OF CONTENTS 911.01 SCOPE 911.02 REFERENCES 911.03 DEFINITIONS

More information

COATING SPECIFICATION ZINC RICH EPOXY PRIMER, EPOXY MASTIC COATING ON STEEL OR CAST IRON COATING SPECIFICATION: C3 ISSUE:2 DATE: OCTOBER 2016

COATING SPECIFICATION ZINC RICH EPOXY PRIMER, EPOXY MASTIC COATING ON STEEL OR CAST IRON COATING SPECIFICATION: C3 ISSUE:2 DATE: OCTOBER 2016 1.0 SCOPE This document summarises the procedure for the application of 2 pack Zinc Rich Epoxy primer over-coated with 2 pack Epoxy mastic. Refer Design Standard, DS 95 (Standard for the Selection, Preparation,

More information

Special Provision No. 199S53 January 2018

Special Provision No. 199S53 January 2018 PERFORMANCE REQUIREMENT - QUALITY PROCESSES Special Provision No. 199S53 January 2018 1.0 SCOPE This Special Provision describes the performance requirements for quality processes, assessment of conformance

More information

WINTER SAND TENDER Friday September 7, 2018 at 1:10 p.m.

WINTER SAND TENDER Friday September 7, 2018 at 1:10 p.m. WINTER SAND TENDER 003-2018 Tender Number PW 003-2018 Sealed Tenders will be received by: Corporation of the Township of Strong 28 Municipal Lane, PO Box 1120 Sundridge, Ontario P0A 1Z0 Tender Closing

More information

Special Provision No. 911S07 October Coating the Ends of New Steel Girders with the Epoxy-Zinc/Epoxy/Polyurethane System

Special Provision No. 911S07 October Coating the Ends of New Steel Girders with the Epoxy-Zinc/Epoxy/Polyurethane System COATING NEW STRUCTURAL STEEL - Item No. Special Provision No. 911S07 October 2000 Coating the Ends of New Steel Girders with the Epoxy-Zinc/Epoxy/Polyurethane System 911.02 REFERENCES Section 911.02 of

More information

Table of Contents. Project Agreement Schedule 14

Table of Contents. Project Agreement Schedule 14 Table of Contents PART 1 DEFINITIONS... 3 PART 2 INTEGRATED MANAGEMENT SYSTEM REQUIREMENTS... 6 2.1. Introduction... 6 2.2. Overview... 6 2.2.1 Management System Requirements... 7 2.2.2 Certification...

More information

STRUCTURAL STEEL FRAMING

STRUCTURAL STEEL FRAMING SECTION 05 12 00 - STRUCTURAL STEEL FRAMING PART 1 - GENERAL 1.1 SUMMARY A. Section includes 1. Structural steel framing 2. Structural steel framing required for support and framing of rooftop mechanical

More information

Tnemec Fluid Applied Thermal Break Long Form Specification

Tnemec Fluid Applied Thermal Break Long Form Specification PART 1 GENERAL 1.01 DESCRIPTION Tnemec Fluid Applied Thermal Break Long Form Specification A. This specification covers labor, materials, equipment, and application necessary for, and incidental to, the

More information

Chambers Creek, WA Pierce County WWTP Digester #1

Chambers Creek, WA Pierce County WWTP Digester #1 Manufacturer Raven Lining Systems 13105 E. 61st Street, Suite A Broken Arrow, OK 74012 (918) 615-0020 Location: Chambers Creek WWTP Pierce County, WA, 80 Diameter Sewage Digester Contractor(s): Long Painting

More information

Elastocoat Protective Coatings APPLICATION GUIDE

Elastocoat Protective Coatings APPLICATION GUIDE Elastocoat Protective Coatings DESCRIPTION Elastocoat polyurea and polyurethane coatings are two-component, 100% solids elastomer systems. The coatings systems are designed for processing through plural

More information

SECTION High Performance Coatings Field Applied Acrylic Urethanes (Solid Color, Pearl and Metallic Finishes)

SECTION High Performance Coatings Field Applied Acrylic Urethanes (Solid Color, Pearl and Metallic Finishes) - 1 - SECTION 099600 High Performance Coatings Field Applied Acrylic Urethanes (Solid Color, Pearl and Metallic Finishes) PART 1 GENERAL 1.1 SECTION INCLUDES A. Systems for field applied acrylic urethane

More information

Earthworks QA/QC Plan Sample

Earthworks QA/QC Plan Sample Earthworks QA/QC Plan Sample Selected pages (not a complete plan) Part 1: Project Specific Quality Plan Part 2: Quality Manual Part 3: Submittal Forms Part 4: Inspection Checklist Forms Contact: FirstTimeQuality

More information