BURIED FLEXIBLE STEEL STRUCTURES. SuperCor

Size: px
Start display at page:

Download "BURIED FLEXIBLE STEEL STRUCTURES. SuperCor"

Transcription

1 BURIED FLEXIBLE STEEL STRUCTURES SuperCor N E W G E N E R A T I O N B R I D G E S

2 Table of contents 1. Introduction 2. Application 3. Production 3.1. Production of corrugated plates 3.2. Corrosion protection 3.3. Bolts, nuts, anchor bolts, base channels 4. Design / construction 4.1. Scope of design 4.2. Design algorithm 4.3. Dimensioning 4.4. Selection of structure cross section 4.5. Cover depth 4.6. Geometry of a structure in longitudinal direction 4.7. Skew angles 4.8. Reinforcing ribs 4.9. Multiple installation Foundation Bedding and backfill End treatment (inlet/outlet) Concrete collar Fittings Durability 5. Installation and construction procedures 5.1. Delivery 5.2. Assembly 5.3. Torque of bolts 5.4. Assembly equipment 5.5. Assembly time 5.6. Deformation during backfilling 5.7. Shape control 6. Relining 7. Tolerances 8. Tests 9. Profiles 10. Case studies page 1 page 3 page 4 page 4 page 6 page 7 page 8 page 8 page 8 page 9 page 9 page 10 page 11 page 12 page 13 page 15 page 16 page 18 page 19 page 20 page 21 page 22 page 24 page 24 page 25 page 26 page 27 page 27 page 28 page 29 page 30 page 31 page 32 page 34 page 45-52

3 1. Introduction SuperCor structures are the new generation of flexible structures made of galvanized corrugated steel plates of a very high stiffness. To take the loads, those structures use interaction with surrounding backfill soil. The load capacity of SuperCor is far higher than traditional structures made of corrugated steel. SuperCor structures are used for building engineering objects above and under roads and railways. Spans can reach 25 m. Structures are simple and easy to assembly. Average assembly time takes a few days in assistance with small crew. The beginning of SuperCor use dates back to the middle of 80 in 20 th century. Nowadays they have been used in many countries all over the world, in Poland used since ViaCon group manufactures SuperCor in Scandinavia and Poland. ViaCon Polska has been producing SuperCor structures since 2008 in Rydzyna, Poland. 1.

4 1. Introduction Typical sequence for construction of SuperCor bridges: - foundations - delivery - assembly - backfilling - finishing works SuperCor structures have many advantages over traditional bridge solutions: - simple design due to fewer details, drawings and calculations database for standard application - easy and fast assembly - possibility to assemble in temperatures below zero - possibility to assemble structures without traffic stop - possibility to assemble of partial or total prefabrication of structures - due to lightweight, corrugated plates can be delivered easily and economically to remote locations - reduction in total time and cost of building a bridge 2.

5 2. Application SuperCor versatile structures are used for roads and railways and industrial applications: - bridges - overpasses - tunnels - culverts - underpasses - pedestrian tunnels - ecological crossings, hangars - shelters - underground storages - belt conveyor protection Furthermore, SuperCor structures can be used for reinforcement and reconstruction of existing structures (bridges, culverts, tunnels, underpasses). 3.

6 3. Production 3.1. Production of corrugated plates We manufacture SuperCor using TQM approach. Our production is certified in accordance to ISO 9001:2008 and ISO 14001:2004. The process of SuperCor production consists of mechanical forming of steel flat plates to the shape of corrugated curved plates which are later hot-dip galvanized. Producing of holes, cutting is done prior to galvanizing. Corrugated plates can be epoxy painted on request. Whole process is located indoor. 4.

7 3. Production Steel used for production of SuperCor conforms to EN or EN Steel grade: S315MC. Yield stress for this steel is min. 315 MPa. [mm] Fig. 1. Cross section of SuperCor plate [mm] Fig. 2. Geometry of a SuperCor plate (total length, i.e. multiple S=406,4 mm) Table 1. Section properties for Supercor plate. Plate thickness [mm] Area [mm 2 /mm] Moment of inertia [mm 4 /mm] Section modulus [mm 3 /mm] 5,5 7,0 6,968 8, , ,45 235,62 297,92 Other plate configurations are available upon request. Selection of plate thickness depends on structure shape, span, depth of cover and live load. Before you specify any of SuperCor structures, please take the opportunity to consult with ViaCon technical representative for advice and assistance on your project. 5.

8 3. Production 3.2. Corrosion protection Hot dip galvanizing is the most durable method of corrosion protection. Galvanized coating is metallurgically- bonded to the steel surface, providing extended service life. In order to extend the durability of SuperCor structures, especially in an aggressive environment, there is a possibility to apply an additional corrosion protection by applying epoxy paint. Corrosion protection of SuperCor structures is made in a production plant and consists of: - hot-dip galvanizing of steel plates and additional fitting elements - epoxy painting galvanized plates (if specified additionally) SuperCor structures are protected by hot galvanizing as a standard, with zinc coating layer according to EN ISO 1461 (table 2). Other thickness of zinc layer is possible on request. Please contact ViaCon representative for advice. Table 2. Zinc layer in acc. to EN ISO 1461 Characteristics Minimal local zinc coating thickness [μm] Requirements acc. to EN ISO 1461 Minimal average zinc coating thickness [μm] Steel plates: 6 mm thick 3 mm up to <6 mm 1,5 mm up to < 3 mm Bolts, nuts, anchor bolts Base channel The protection of structures both by hot-dip galvanizing and epoxy paint creates ViaCoat system conformed to EN ISO Paint coat thickness is controlled by EN ISO Minimum adhesion of the epoxy paint to the zinc base measured by pull - off method shouldn t be less than 4 MPa, and an adjacent test is conducted acc. to the norm PN-EN ISO In order to obtain right adhesion galvanized plates are sweep blast prior to application of paint. In order to obtain the proper protection effect, paint coatings are applied in special conditions i.e. inside of closed halls with controlled temperature, humidity. Keeping a technological regime is crucial for successful performance of the protection system..

9 3. Production 3.3. Bolts, nuts, anchor bolts, base channels SuperCor structures consist of corrugated plates and additional elements. Table 3 lists these elements. Table 3. Parameters of additional elements Type / dimensions Length [mm] Norm Bolts M20 class , 63, 70 EN ISO Nuts M20 - EN ISO Anchor bolts Ø 20 mm 225, 365 EN Base channel 157 x 190 x 38 x 5 mm 3035 EN Corrugated steel plates are joined by bolts M20 (class 8.8 ). The lengths of bolts are related to thickness of connected plates and type of connection. There are two types of bolt heads (Fig. 3): - oval - shaped - cone - shaped All joint elements mentioned above are delivered in marked boxes together with the structure. a) b) Fig. 3. The shape of bolt head: a) oval, b) cone Fig. 4. Connection of ribs to main barrel plates Anchor bolts for concrete collar [mm] [mm] [mm] a) b) Fig. 5. Anchor bolts used to mount structure in foundation (a) and anchor bolts for concrete collar (b) Fig. 6. Base channel used to connect structure to foundation 7.

10 4. Design / construction 4.1. Scope of design Design process includes the following: - design of SuperCor structure (including assembly and backfilling procedure) - design of engineered backfill - design of foundation - design of in and outlet fitting elements SuperCor structures are designed for all road and railway live load classes acc. to Eurocode 1 EN and for national standards as well as for (STANAG 2021) loads Design algorithm The following algorithm should be used when designing of SuperCor structures: - specify the function of a structure bridge (culvert, viaduct, ecological crossing, etc.) - choose the shape (for underpasses, ecological crossings, adjust to box clearance) - determine water flow and light (for culverts and bridges) - choose the type of foundation and specify material - specify the cover depth - determine type of dead and live load (for seismic areas specify seismic zone) - specify the engineered backfill material and its installation procedure - make static calculations as well as specify deformations during construction - select the corrosion protection depending on required durability - choose the assembly procedure (estimate the labor and the cost of assembly) - design of inlet and outlet - design skewed part of a structure 8.

11 4. Design / construction 4.3. Dimensioning SuperCor structures are dimensioned with use of Swedish design method developed by prof. Sundquist and prof. Pettersson. They can also be designed with the use of other methods, approved by producer of the structures, e.g. CHBDC. In complex cases finite element method (FEM) can be used. Contact us for help in static calculations of SuperCor structures Selection of structure cross section In order to select a typical shape of a structure please use tables provides on (pages 34-44). These tables include standard shapes. Other shapes are available on request. A profile of a structure should fit to a clearance box. Allow for tolerances of structure dimensions. Acceptable tolerances are given in chapter

12 4. Design / construction 4.5. Cover depth Definition of the cover depth for road structures: Vertical distance between top of a steel structure main barrel and top of the pavement including the pavement layer. Definition of the cover depth for railway structures: Vertical distance between top of a steel structure main barrel and bottom of railway sleeper. Box structures Depth of cover for box structure should be: 0,45 h c 1,5 [m] Minimum cover depth also depends on the thickness of the pavement layer (G n ) and should not be less than: h c = G n + 0,15 [m] Other shapes For arch, round, elliptical shapes estimated cover depth is calculated using the formula: h c = 0,1 B [m] where B span of the structure [m] Lover cover depth is permissible when appropriate static calculations are conducted. Maximum depth of a cover is always designed individually. For high cover depth load reduction techniques are available. Please contact us for advice. 10.

13 4. Design / construction 4.6. Geometry of a structure in longitudinal direction Bottom length of SuperCor structures should conform to the following formula: Ld=38+n [mm] where n number of full rings alongside length Top length of a structure is determined individually (in and outlets). Ends of SuperCor structures can be vertical or beveled to match the embankment slope (Fig. 7). For beveled ends minimum X-step is 0,18 m. For structures curved in plane use bends to align to designed curvature (Fig. 8) 1:n x x 1 1:n x 2 Fig. 7. End finishes Fig. 8. Supercor bend 11.

14 4. Design / construction 4.7. Skew angles Fig. 9. Skewed structure Minimum permissible angle for skewed ends is 55º. Concrete collars are used for large skews. Steel meshes attached to SuperCor structure can be also used for skewed areas. Please contact us for advice. 12.

15 4. Design / construction 4.8. Reinforcing ribs Reinforcing ribs should be used when flexural capacity of the section is exceeded. Ribs can be used for all shapes of structures. Reinforcing ribs: in cross section (Fig. 10) in haunch and crown on whole perimeter in longitudinal section (Fig. 11) - continuous placed on the whole top length of the structure - spaced at intervals of 762 mm, 1143 mm or 1524 mm In order to get a bigger capacity, space between main barrel and reinforcing ribs can be filled with concrete (EC ribs).the use of EC ribs can be necessary for large span structures. C25/30 concrete is used as filling acc. to EN 206-1:2000. Thanks to such a sulution used for arch structures, bigger cross sectional area is achieved, which leads to decrease of compression stresses in steel wall. For boxes, higher flexural capacity is reached by connecting ribs to the main barrel. Fig. 10. Placement of the ribs in cross section of the structure 13.

16 4. Design / construction Fig. 11. Placement of the ribs in longitudinal direction of the structure 14.

17 4. Design / construction 4.9. Multiple installation For multiple structure installations, the smallest clear spacing between adjacent structures should be sufficient for the placement and compaction of soil (Fig. 12). The minimum spacing requirement depends upon the shape and size of structures. When the required distance can not be achieved, space between structures should be filled with C10/15 concrete or cement stabilized soil to the level where the distance between structures is not less than 10% of structure span. Please contact us for advice. Fig. 12. Minimum clear spacing for multiple installations 15.

18 4. Design / construction Foundation SuperCor structures with closed shapes (round, elliptical, pipe-arch) are placed on soil bedding as follows: - thickness of soil bedding minimum 60 cm - top portion of the bedding should be shaped to fit to the bottom plates of a structure - particular care should be exercised in compacting soil under haunches - upper 15 cm layer of the bedding should be relatively loose material so that the corrugation can seat in it SuperCor structures with open shapes (arches, boxes) are placed on concrete footings, steel footer pads or a full steel invert. Connection of the structure to the concrete footings is realized by the means of anchor bolts, taking the following into account: - anchor bolts for concrete foundations to be installed in concrete footings prior to delivery of a SuperCor structure - anchor bolts should not stick out from the top of the footing more than 40 mm - placing of anchor bolts should conform to assembly drawing; the allowable tolerance is ±3 mm in longitudinal direction and ±2 mm in the transverse direction - to minimize a risk of mistake, the location of each anchor should always be measured from the starting point (first anchor) - parallel placement of anchor bolts on each footing and perpendicular placement of each pair of anchor bolts for individual rings are of great importance; better accuracy, easier assembly of the structure Fig. 13. Connection of SuperCor structure with concrete footing 16.

19 4. Design / construction SuperCor Wall Base channel Steel footing Fig. 14. Connection of SuperCor structure with steel footer pads of a full steel invert Steel footings must have appropriate erosion control measures. For design of steel footing (width, thickness, depth, erosion control etc.) please contact us for advice

20 4. Design / construction Bedding and backfill Material: - gravel, sand - gravel mix, all - in aggregates and crushed stone can be used as bedding and backfill material - aggregate grain size depends on size of corrugation profile; for 381x140 mm maximum size is 120 mm - aggregate grain size should be mm, ununiformity coefficient is C u >5,0, curvature coefficient 1<C c <3 and permeability k>6 m/24 hours - soil restrictions apply for area adjacent to a structure (please contact us for advice) - the use of cohesive soils, organic soils and soils included permafrost is not acceptable Placing: - backfill material around the structure should be placed in uncompacted layers maximum 300 mm thick and then compacted - the fill should be placed on both sides of the structure at the same time, or alternating from one side of the structure to the other side, to keep it close to the same elevation on both sides of the structure at all times. No more than one layer difference in elevation on each side should be allowed. Each layer must be compacted to the specified density before adding the next - backfill material should be compacted to minimum 95% standard Proctor density in the area of 20 cm next to the structure, 98% standard Proctor density in the remaining area In order to increase load bearing capacity/ soil stiffness of surrounding soil geosynthetic and galvanized steel which can be used. 18.

21 4. Design / construction End treatment (inlet/outlet) End treatment depends on the way the ends of structure are cut. For beveled ends, slopes can be finished by paving with stones blocks, etc. For bevel ends with gabion mattresses, waterproof solutions must be applied. Please contact us for advice. As an alternative to concrete headwalls MSE Walls (for instance ViaWall system) or gabions can be applied

22 4. Design / construction Concrete collar Concrete collar is used: - in order to stiffen inlet and outlet of SuperCor structure with beveled ends - as finishing element used as support of end treatment Concrete collar is applied mostly in following cases: - structures with skew angles to the road axis, when skew angle on outlet and inlet is 65 and span is > 3,5m - structures exceed 6,0 m span - large skews 200 Fig. 15. Example of a concrete collar on inlet and outlet of the structure Contact us for application of steel collars. Formwork for concrete collar 20.

23 4. Design / construction Fittings SuperCor structures can be equipped with additional elements depending on function of the structure e.g.: - lighting boxes - ventilation - shelves for animals - technical holes - others Please contact us for advice

24 4. Design / construction Durability Hot-dip galvanization is a basic anti-corrosion protection of SuperCor structures. Durability of SuperCor structures can extend over 100 years. SuperCor structures are hot-dip galvanized according to EN ISO If necessary, SuperCor structures can be provided with an extra layer of zinc or additional corrosion protection by epoxy coating called ViaCoat. These solutions are applied for aggressive environments. In most cases the extend of corrosion protection by epoxy coating is as follows: - inside and/or outside on the whole area of a structure - at inlet and outlet of the structure (1,5 m inside the structure) - inside up to 0,5 m above mean water level - as a combination of above mentioned Fig. 16. Epoxy coating protection Most common thickness of epoxy paint is 200 μm, however other thicknesses are possible. Please contact us of advice. Following factors have an influence on structure s durability: - aggressiveness of an environment - application of structure - draining solutions - abrasion - installation damages - corrosion protection - plate thickness - quality and frequency maintenance 22.

25 4. Design / construction Procedure of calculating durability of SuperCor structures: - define the function of a structure - define the required durability (lifetime) of a structure - define the aggressiveness of the environment (water, backfill, air) - select the type of a structure - specify the plate thickness based on static calculations (acc. to Sundquist-Petterson method) - specify the corrosion protection (thickness of zinc coating, paint coating, extend of painting, painting procedure) - define annual loss of the protection layers in upper and lower part of a structure - calculate the structure durability by considering corrosion progress over service lifetime - compare calculated durability with the required - adjust the anticorrosion solution and if required repeat the calculations In cases, when the durability of SuperCor structure is not enough, following measures can be taken : - change corrosion protection (thickness of zinc layer, paint coat) - increase the plate thickness - adjust the shape of a structure and section stiffness to allow for more corrosion reserve Durability of the ViaCoat system is higher than sum of durability of the protection layers and can be calculated as: SD=α * (SC+SZ) where: SD total durability of the protection layer [years] SC durability of zinc coat [years] SZ durability of the epoxy coat [years] α synergy factor (from 1,5 to 2,5) for 200 μm thick paint layer α = 1,5; for 400 μm thick paint layer α = 1,

26 5. Installation and construction procedures 5.1. Delivery SuperCor structures are delivered to the building site with following elements: - plates are shipped nested in bundles, complete with wall, bolts and nuts necessary for erection. Each bundle includes plates with the same type and radius. The weight of each package not exceed 3,5 tons - plates are color coded for easy identification, corresponding to the enclosed assembly drawing. - outer plates with cuts (inlet and outlet of the structure) are numbered. - bolts, nuts, anchor bolts, technical drawing, as well as assembly tools (crowbar, bolts feeder, gripper, punch) are delivered in one separate package - the cans of paint are also provided to repair damages - base channel for footing connection can be delivered earlier, when foundation is prepared, in separate package on request. - all elements delivered to the building site are listed on packing list. While unloading, each delivery should be checked in comparison with a packing list. The number of plates should be equal to the amount listed on assembly drawing. Other elements such as: bolts, nuts, anchor bolts, base channels and assembly tools are listed on the assembly list. Unloading can be realized with a crane or an excavator and with use of belts. It s not allowed to use equipment that can damage protective layers. Make sure to adjust the carrying capacity of equipment to weight of bundles. Small damage appeared during transport, loading and unloading could be repaired on the building site, after assembly. There is always repair paint kit delivered with the structure. 24.

27 5. Installation and construction procedures 5.2. Assembly Assembly of SuperCor is quick & easy. It is important to study carefully the assembly drawing and hints before installation. Assembly drawing presents the position of each plate in the structure area and describes the assembly rules. It is necessary to follow the assembly guide step by step. Detailed assembly instructions are delivered with each structure. For profiles with a closed shape, placed on soil foundation, the assembly process starts after preparing the bedding. For profiles with an open shape, placed on concrete foundation, the assembly process starts after making concrete foundation with fixed anchor bolts. Anchor bolts are used to connect base channels, which allows to mount the structure elements. When tightening the bolts during assembly allow for some loose on bolting connection. It will allow for better adjustment of plates. Fully torque will be applied after completion of assembly. The position of nuts (inside or outside) is not important from static point of view. In case when ribs are used, the bolts position should be as in the assembly drawing. Nuts, situated with no access to use wrench machine, should be fully torqued in the first stage

28 5. Installation and construction procedures 5.3. Torque of bolts For connection of corrugated plates in SuperCor structures bolts M20 with nuts are used. Bolts and nuts are color coded for ease in identification and delivered together with steel plates in separate packages. Final torque should be done after whole structure is assembled but before backfilling. Bolts should be tighten progressively and uniformly, starting from the center of the structure towards both ends. During backfilling checks of torque should be done as the actual bolt torque can decrease slightly due to deformation. The recommended torque is: Minimum of 300 Nm, maximum of 360 Nm for structures with spans up to 7,0 m Minimum of 360 Nm, maximum of 450 Nm for structures with spans more than 7,0 m Control of torque. 5% of the whole number of bolts should be checked for torque. Minimum 95% of checked bolts must have required torque and the torque of remaining 5% can not be less than 250 Nm. The measurements are realized with use of dynamometrical key, with a valid calibration certificate. 26.

29 5. Installation and construction procedures 5.4. Assembly equipment - hand wrenches - power wrenches - scaffoldings and ladders - feeders for bolts - belts and ropes - torque wrench - etc Assembly time In good weather conditions, experienced assembly crew (6-8 people) equipped with assembly tools is able to install about 50 corrugated plates per day (within 8 hours) In order to estimate assembly the following data is required: - structure destination - building site conditions - available assembly tools - shape and size of structure - range of ribs - etc. Please contact us for advice

30 5. Installation and construction procedures 5.6. Deformation during backfilling During backfilling SuperCor structure will deform developing soil - structure interaction. The Supercor structure with surrounding soil, constitute soil - steel composite structure with soil being a major load carrying component. Deformations of the structure should be controlled. Please contact us for estimation of deformation of SuperCor structure during backfilling. w - vertical deflection z - cover depth Fig. 17. Example of structure deformation during backfilling (Machelski 2008) 28.

31 5. Installation and construction procedures 5.7. Shape control Structure must be checked periodically during the backfilling procedure to ensure the shape is consistent with the producer s recommendation. Once one full ring of structure is assembled, preliminary shape control should be performed. Shape checks should be carried out both during and after assembly. It is recommended that the producer s representative be present during erection and backfilling of the structure. Control of compaction during construction is the responsibility of the contractor. Please contact us for advise in shape control

32 6. Relining SuperCor structures are also commonly used to repair old bridges where there are no possibilities to build a new one. This method is called relining. Corrugated steel structure is placed inside the existing structure (bridge / culvert / underpass) and space between an old bridge / culvert and new structural plate is filled with concrete C12.5/15. This method allows to strengthen the structures without any traffic stops and eliminates the necessity of remaining the old structure. The control of pouring concrete between existing structure and new steel structure should be done by revision holes. During pouring concrete it is necessary to control deformations of SuperCor. They shouldn t exceed maximum allowed in section No. 7 Tolerances. In a case where so called open shapes will be used for relining there is a need to make concrete footings which could be connected to existing one. Existing footings can be used also but it will require separate analysis or expertise. 30.

33 7. Tolerances Plate dimensions tolerances: - length and width of the plate ±7mm - length and height of the corrugation ±5mm - distance between the holes ±3mm - plate thickness acc. to EN A1 - radius of curvature ±10mm Tolerances of structure geometry (all profiles excl. Boxes): Structure dimensions after torque shouldn t be different than designed with following tolerances: - span +2% - rise ±2% - length ±0.5% Deformation of cross section after backfilling shouldn t exceed 2% of the span measured after assembly. Tolerances of Box structure geometry: Structure dimensions after torque shouldn t be different than designed with following tolerances: - span +2% - rise +2% / -4% - length ±0.5% Deformation of cross section after backfilling shouldn t exceed 1% of the span measured after assembly. Based on experience those deflections are much smaller

34 8. Tests In order to continuously improve design method we cooperate with science centers and research institutes in Europe. Effect of this collaboration is number of research programs including SuperCor structures. SuperCor tests done in Poland: - Nowa Ruda SCA-13, SCA-19 Special, SC-48B and SC-23B. Deformations of steel structure were measured during backfilling (long term test)and under live load (Class A (4x200 kn/axle) acc. to PN-85/S Polanica Zdrój-Szczytna SC-48B and SC-56B. Strain and deflections measurements. Live load test (Class A (4x200 kn/axle) acc. to PN-85/S Pieńsk SC-33B (bridge under railway). Live load test. Strain and deflections measurements Class k+2 acc. to PN-85/S Rydzyna SC-57S. Strain and deflections measurements. Dead load test. - A4 Motoway SCA-33. Strain and deflections measurements. Dead load test. 32.

35 SuperCor abroad tests (selected): - Giman (Sweden) SC-56B. Strain and deflections measurements. - Jarpas (Sweden) SC-35B and SC-60B - Male Zernoseky (Czech Republic) SC-19B - Alberta Stone Mine White Horse Creek (Canada) SC-92SA - Tests of composite effect (barrel+rib) (Canada) Tests mentioned above were done to: - scale and verify the calculation methods - optimize design process - confirm safety of solution especially large span structures 33.

36 9. Profiles SC-R SC-B SC-SA SC-NA SC-OA SC-HA 34.

37 9. Profiles SC-R Type B [mm] H [mm] A [m 2 ] Rc [mm] Total S* SC-66R , SC-68R , SC-70R , SC-72R , SC-74R , SC-76R , SC-78R , SC-80R , SC-82R , SC-84R , SC-86R , SC-88R , SC-90R , SC-94R , SC-98R , SC-102R , SC-106R , SC-110R , SC-114R , SC-118R , SC-122R ,

38 9. Profiles SC-B Type B [mm] H [mm] A [m 2 ] Rt [mm] α [º] Rs [mm] β [º] L [mm] δ [º] Total S* SC-1B , , , ,00 11 SC-2B , , , ,00 13 SC-3B , , , ,31 14 SC-4B , , , ,98 17 SC-5B , , , ,37 13 SC-6B , , , ,68 16 SC-7B , , , ,05 14 SC-8B , , , ,05 18 SC-9B , , , ,74 15 SC-10B , , , ,06 17 SC-11B , , , ,05 20 SC-12B , , , ,42 21 SC-13B , , , ,76 18 SC-14B , , , ,43 20 SC-15B , , , ,53 17 SC-16B , , , ,44 22 SC-17B , , , ,22 18 SC-18B , , , ,80 24 SC-19B , , , ,49 19 SC-20B , , , ,50 21 SC-21B , , , ,50 25 SC-22B , , , ,60 20 SC-23B , , , ,19 22 SC-24B , , , ,20 24 SC-25B , , , ,29 21 SC-26B , , , ,98 22 SC-27B , , , ,97 24 SC-28B , , , ,26 26 SC-29B , , , ,67 23 SC-30B , , , ,67 25 SC-31B , , , ,66 27 SC-32B , , , ,67 29 SC-33B , , , ,38 22 SC-34B , , , ,08 24 SC-35B , , , ,07 26 SC-36B , , , ,09 26 SC-37B , , , ,10 28 SC-38B , , , ,

39 9. Profiles SC-B Type B [mm] H [mm] A [m 2 ] Rt [mm] α [º] Rs [mm] β [º] L [mm] δ [º] Total S* SC-39B , , , ,94 27 SC-40B , , , ,94 29 SC-41B , , , ,95 31 SC-42B , , , ,91 29 SC-43B , , , ,92 31 SC-44B , , , ,92 33 SC-45B , , , ,89 31 SC-46B , , , ,89 33 SC-47B , , , ,89 35 SC-48B , , , ,33 32 SC-49B , , , ,32 34 SC-50B , , , ,32 36 SC-51B , , , ,71 34 SC-52B , , , ,71 36 SC-53B , , , ,60 38 SC-54B , , , ,68 36 SC-55B , , , ,69 38 SC-56B , , , ,68 40 SC-57B , , , ,61 39 SC-58B , , , ,61 41 SC-59B , , , ,28 42 SC-60B , , , ,26 44 SC-61B , , , ,24 44 SC-62B , , , ,25 46 SC-63B , , , ,19 48 SC-64B , , , ,

40 9. Profiles SC-SA Type B [mm] H [mm] A [m 2 ] Rc [mm] α [º] Total S* SC-27SA , SC-28SA , SC-29SA , SC-30SA , SC-31SA , SC-32SA , SC-33SA , SC-34SA , SC-35SA , SC-36SA , SC-37SA , SC-38SA , SC-39SA , SC-40SA , SC-41SA , SC-42SA , SC-43SA , SC-44SA , SC-45SA , SC-46SA , SC-47SA , SC-48SA , SC-49SA , SC-50SA , SC-51SA , SC-52SA , SC-53SA , SC-54SA , SC-55SA , SC-56SA , SC-57SA , SC-58SA , SC-59SA , SC-60SA , SC-61SA , SC-62SA , SC-63SA , SC-64SA ,

41 9. Profiles SC-SA Type B [mm] H [mm] A [m 2 ] Rc [mm] α [º] Total S* SC-65SA , SC-66SA , SC-67SA , SC-68SA , SC-69SA , SC-70SA , SC-71SA , SC-72SA , SC-73SA , SC-74SA , SC-75SA , SC-76SA , SC-77SA , SC-78SA , SC-79SA , SC-80SA , SC-81SA , SC-82SA , SC-83SA , SC-84SA , SC-85SA , SC-86SA , SC-87SA , SC-88SA , SC-89SA , SC-90SA , SC-91SA , SC-92SA , SC-93SA , SC-94SA , SC-95SA , SC-96SA ,

42 9. Profiles SC-NA Type B max [mm] B [mm] H [mm] A [m 2 ] Rt [mm] α [º] Rs [mm] β [º] δ [º] Total S* SC-1NA , , ,29 2,32 30,0 SC-2NA , , ,57 4,04 33,0 SC-3NA , , ,81 6,53 35,0 SC-4NA , , ,68 5,66 36,0 SC-5NA , , ,66 15,64 39,0 SC-6NA , , ,49 4,75 37,0 SC-7NA , , ,54 7,11 39,0 SC-8NA , , ,52 17,09 42,0 SC-9NA , , ,15 6,06 40,0 SC-10NA , , ,71 5,00 41,0 SC-11NA , , ,19 12,78 47,0 SC-12NA , , ,44 7,15 43,0 SC-13NA , , ,71 5,90 44,0 SC-14NA , , ,68 13,79 50,0 SC-15NA , , ,80 4,52 45,0 SC-16NA , , ,03 6,35 47,0 SC-17NA , , ,37 8,79 54,0 SC-18NA , , ,03 8,03 49,0 SC-19NA , , ,42 6,19 50,0 SC-20NA , , ,17 11,56 58,0 SC-21NA , , ,84 7,50 52,0 SC-22NA , , ,65 7,45 52,0 SC-23NA , , ,28 8,88 59,0 SC-24NA , , ,18 9,51 54,0 SC-25NA , , ,33 8,20 55,0 SC-26NA , , ,38 7,57 61,0 SC-27NA , , ,38 6,82 56,0 SC-28NA , , ,65 8,69 58,0 SC-29NA , , ,46 8,30 64,0 SC-30NA , , ,48 7,14 59,0 SC-31NA , , ,51 8,83 61,0 SC-32NA , , ,07 6,68 66,0 SC-33NA , , ,07 7,08 62,0 SC-34NA , , ,83 8,57 64,0 SC-35NA , , ,47 7,00 69,0 SC-36NA , , ,06 6,57 65,0 SC-37NA , , ,44 7,77 67,0 SC-38NA , , ,56 7,43 75,0 40.

43 9. Profiles SC-NA Type B max [mm] B [mm] H [mm] A [m 2 ] Rt [mm] α [º] Rs [mm] β [º] δ [º] Total S* SC-39NA , , ,59 8,79 69,0 SC-40NA , , ,36 8,60 68,0 SC-41NA , , ,23 7,68 77,0 SC-42NA , , ,23 10,53 70,0 SC-43NA , , ,58 8,76 74,0 SC-44NA , , ,55 8,94 82,0 SC-45NA , , ,47 7,79 75,0 SC-46NA , , ,80 9,27 77,0 SC-47NA , , ,80 7,80 84,0 SC-48NA , , ,46 8,09 78,0 SC-49NA , , ,06 6,88 79,0 SC-50NA , , ,57 8,22 87,0 SC-51NA , , ,17 8,19 81,

44 9. Profiles SC-OA Type B max [mm] B [mm] H [mm] A [m 2 ] Rt [mm] α [º] Rs [mm] β [º] δ [º] Total S* SC-1OA , , ,76 2,64 36 SC-2OA , , ,74 13,47 40 SC-3OA , , ,76 3,85 37 SC-4OA , , ,41 12,01 40 SC-5OA , , ,99 3,71 38 SC-6OA , , ,60 12,81 42 SC-7OA , , ,40 5,66 40 SC-8OA , , ,74 18,23 44 SC-9OA , , ,76 2,67 39 SC-10OA , , ,20 9,12 42 SC-11OA , , ,67 15,26 45 SC-12OA , , ,99 2,48 40 SC-13OA , , ,08 11,40 43 SC-14OA , , ,40 16,99 46 SC-15OA , , ,76 6,63 42 SC-16OA , , ,08 12,17 44 SC-17OA , , ,91 17,71 48 SC-18OA , , ,20 6,96 43 SC-19OA , , ,41 15,23 46 SC-20OA , , ,68 19,64 49 SC-21OA , , ,40 6,39 44 SC-22OA , , ,41 16,10 47 SC-23OA , , ,80 18,55 50 SC-24OA , , ,08 11,43 46 SC-25OA , , ,41 15,66 48 SC-26OA , , ,72 13,46 51 SC-27OA , , ,50 10,49 47 SC-28OA , , ,62 19,14 50 SC-29OA , , ,23 15,28 53 SC-30OA , , ,41 14,55 49 SC-31OA , , ,68 16,40 51 SC-32OA , , ,44 17,42 54 SC-33OA , , ,80 11,38 50 SC-34OA , , ,80 15,86 52 SC-35OA , , ,97 19,09 56 SC-36OA , , ,30 10,60 51 SC-37OA , , ,85 14,69 53 SC-38OA , , ,30 16,

45 9. Profiles SC-OA Type B max [mm] B [mm] H [mm] A [m 2 ] Rt [mm] α [º] Rs [mm] β [º] δ [º] Total S* SC-39OA , , ,68 16,15 53 SC-40OA , , ,82 13,95 54 SC-41OA , , ,66 19,02 58 SC-42OA , , ,62 19,94 54 SC-43OA , , ,45 11,12 55 SC-44OA , , ,74 14,01 59 SC-45OA , , ,80 16,21 55 SC-46OA , , ,82 17,00 57 SC-47OA , , ,74 15,80 61 SC-48OA , , ,99 16,17 56 SC-49OA , , ,11 16,50 58 SC-50OA , , ,91 14,55 62 SC-51OA , , ,40 13,68 57 SC-52OA , , ,45 14,51 59 SC-53OA , , ,24 16,64 63 SC-54OA , , ,66 15,85 58 SC-55OA , , ,95 12,67 60 SC-56OA , , ,24 18,96 65 SC-57OA , , ,86 10,67 59 SC-58OA , , ,55 12,15 61 SC-59OA , , ,78 18,

46 9. Profiles SC-HA Type B max [mm] B [mm] H [mm] A [m 2 ] Rt [mm] α [º] Rs [mm] β [º] Rc [mm] γ [º] δ [º] Total S* SC-1HA , , , ,56 9,57 40,0 SC-2HA , , , ,14 10,14 43,0 SC-3HA , , , ,89 10,89 47,0 SC-4HA , , , ,34 11,34 50,0 SC-5HA , , , ,58 10,58 53,0 SC-6HA , , , ,92 10,92 57,0 SC-7HA , , , ,57 10,57 60,0 SC-8HA , , , ,39 10,40 66,0 SC-9HA , , , ,10 11,10 70,0 SC-10HA , , , ,40 12,41 75,0 SC-11HA , , , ,81 11,81 78,0 SC-12HA , , , ,48 12,49 83,0 SC-13HA , , , ,48 12,49 87,0 SC-14HA , , , ,24 10,25 92,0 SC-15HA , , , ,47 10,48 96,0 SC-16HA , , , ,37 10,38 100,0 SC-17HA , , , ,43 10,44 104,0 44.

47 10. Case studies Location: Railway line E20 near Rzepin town (West border of Poland) In 2007 r. over international double truck electrified railway line E20 Section Rzepin - Polish German border two animal overpasses were built. Two SuperCor SCA-35 low profile Arch s set on the concrete foundations were used in two different locations. Basic parameters are following: - span 20,00 m - rise 5,97 m - bottom length 57,988 m - corrugation 381 x 140 mm SuperCor SCA-35 structures were corrosion protected by zinc coat acc. to EN ISO 1461:2000 Assembly was realized parallel by two independent crew and took 19 days only. Structures were assembled using plate by plate method and partially preassembled using one crane/structure and two basket elevators/structure. Arches were backfilled with sand-gravel mix (0-32mm) and compacted to min 98% Acc. to standard Proctor density. Height of cover is 1.5 m. Over each structure geosynthetic (NV geotextile + geomembrane +NV geotextile ambrella were used to protect against rain water leak. On the top of the overpasses antidazzle fences were built with height 2.5 m

48 10. Case studies Location : Highway A2, section Konin Koło In 2006 over highway A2 section Konin Koło two animal overpasses were built. Both overpasses are consist of two corrugated steel arch structures SuperCor SC 57S with span 17,7 m and two MultiPlates structures MP200 G30 with PipeArch profile. There are the biggest structures of these types in Europe. The structures were galvanized acc. to EN ISO 1461:2000 and additionally epoxy painted 200 µm acc. to EN ISO Each Supercor SC-57S structure has the following parameters: - rise 5,461 m - span 17,667 m - bottom length 60 m - corrugation 381 x 140 mm Each MultiPlate G-30 structure has the following parameters: - rise 8,12 m - span 9,36 m - bottom length 76 m - corrugation 200 x 55 mm The structure was designed to carry a live load class E acc. to PN 85/S Assembly of these 4 structures lasted 2 months. Structure was assembled acc. to plate by plate method with the use of two cranes situated on either side of the structure and movable scaffold. 46.

49 10. Case studies Location: Wągrowiec By Pass In 2002 at the crossing of a new by pass of Wągrowiec and existing railway line SuperCor SC 50B box structure was designed. The structure has the following parameters: - rise 3,165 m - span 10,990 m - bottom length 40,386 m - corrugation 381 x 140 mm The structure was designed to carry a live load class A acc. to PN 85/S The structures were galvanized in acc. to EN ISO 1461:2000 In order to ensure the required railway clearance the steel structure was founded on concrete footings 5 m high. The full rings of the structure were first prefabricated and next the rings were installed on the concrete footings. The assembly of the whole structure lasted 2 weeks. At the ends of the structure delicate concrete collars were constructed. The slopes were paved by means of concrete blocks

50 10. Case studies Location: Baczyn close to Sucha Beskidzka In 2001 in Baczyn close to Sucha Beskidzka a bridge was destroyed by the flood. Old bridge was replaced with new corrugated steel structure SuperCor SC-20B. The structure has the following parameters: - rise 1,9 m - span 6,165 m - bottom length 12,192 m - corrugation 381 x 140 mm The structures was galvanized in acc. to EN ISO 1461:2000. The structure were installed on the concrete footings. The assembly of the whole structure lasted 6 days. The cost of steel structure was much less than traditional bridge construction. 48.

51 10. Case studies Location: National Road No. 5 Poznań Wrocław, section Komorniki Głuchowo, Trzebaw In 2003 over National Road No. 5 Poznań Wrocław between Komorniki and Głuchowo in Trzebaw building of animal overpass was started with the use of corrugated steel arch structure SuperCor SC 57S. The steel structure has the following parameters: - rise 5,461 m - span 17,667 m - bottom length 55,626 m - corrugation 381 x 140 mm The structures was galvanized in acc. to EN ISO 1461:2000. The structure was designed to carry a class E live load acc. to PN 85/S Assembling of the structure lasted 11 days and was conducted without stopping the traffic. Structure was assembled acc. to plate by plate method with the use of two cranes situated on either side of the structure and movable scaffold. Steel structure was backfilled with the use of sand gravel mix compacted to Standard Proctor density of minimum 97%. The depth of cover over the steel structure is 1,80 m. Costs of the structure is 70% of costs of the structure built in traditional technology

52 10. Case studies Location: Gniezno bypass Three span bridge was built with use of steel box structures SuperCor in Gniezno in Each of the steel box structure SC-59B has the following parameters: - rise 3,07 m - span 14,075 m - bottom length 23,56 m - corrugation 381 x 140 mm The structure were installed on the pile foundation. SuperCor SC- 59B structures are hot dip galvanized acc. to EN ISO 1461:2000 with zinc layer 85 m and additionally epoxy painted 200 μm acc. to EN ISO The structure were reinforced by steel ribs situated on the whole area. The assembly lasted 3 weeks in assistance with 8 people crew. 50.

53 10. Case studies Location: A4 Motorway section B Wykroty Krzyżowa In 2008 over A4 Motorway on Zgorzelec Krzyżowa section construction of two animal overpasses has started. Each of the overpass consists of two SuperCor SCA-33 arch structures placed on concrete footings. Steel structures have following parameters: - span 19,50 m - rise 5,97 m - bottom length 67,89 m - corrugation profile 380 x 140 mm 51.

54 10. Case studies SCA-33 structures are reinforced by means of additional steel plates. In order to decrease the load on middle footing, helically corrugated steel pipe HelCor Ø2400 mm was used. SuperCor SCA-33 structures are hot dip galvanized acc. to EN ISO 1461 and additionally epoxy painted 200 μm acc. to EN ISO HelCor pipes are hot dip galvanized with zinc coating thickness of 42 μm and have polymer Trenchcoat coating 250 μm thick. Assembly of all 4 structures for two passings lasted 12 weeks. Wooden fences on top of the passings are installed to separate the animal passage from view of moving vehicles. 52.

55 ViaCon Sp. z o.o. ViaCon Sp. z o.o. is a member of ViaCon Group established in Sweden and Norway in At present ViaCon Group operates in a dozen or so European countries and belongs to SAFEROAD Group. Thanks to the support from the entire group and the possibility of using the shared experience, each member company can offer professional technical consulting and top quality products. Business profile of the company: manufacture, design, sale and installation of plastic and steel pipes and flexible structures used for construction and repair of culverts, bridges, overpasses, tunnels, farm accommodation underpasses, wildlife crossings, other engineering structures, and used also as belt conveyor housings, manufacture, design and sale of storm water drainage systems and holding tanks, design, sale and installation of geosynthetics, such as non-woven geotextile fabrics, woven geotextile fabrics, geogrids, geomembranes, and bentonite mats, sale and lease of temporary bridges, sale of gabions, design, manufacture and sale of three retaining structure systems from reinforced soil.

56 MP200 pl ok_folder-srodek2.qxd :00 Strona 13 PECOR OPTIMA HelCor HelCor PA MultiPlate MP200 SuperCor Acrow 700XS - temporary bridges Woven and non-woven geotextiles Geogrids Gabions HelCor TC holding tanks HelCor wells PECOR OPTIMA M wells ViaWall A retaining walls ViaWall B retaining walls Pecor Quattro sewage system ViaBlock retaining walls Our goal is to improve products and to cooperate closely with customers, scientific and research centres, public administration and suppliers. ViaCon Sp. z o.o. ul. Przemysłowa Rydzyna, Poland phone: fax: office@viacon.pl That s why our motto is: Let s Create a Better Future Together

SuperCor A NEW GENERATION OF BRIDGES

SuperCor A NEW GENERATION OF BRIDGES SuperCor A NEW GENERATION OF BRIDGES SuperCor versatile structures are used for roads and railways and industrial applications as well as for reinforcement and reconstruction of existing structures such

More information

BURIED FLEXIBLE STEEL STRUCTURES. MultiPlate MP200 MULTIPURPOSE TECHNOLOGY

BURIED FLEXIBLE STEEL STRUCTURES. MultiPlate MP200 MULTIPURPOSE TECHNOLOGY BURIED FLEXIBLE STEEL STRUCTURES MultiPlate MP200 MULTIPURPOSE TECHNOLOGY MP200 pl ok_folder-srodek2.qxd 2012-10-08 14:59 Strona 3 1. Introduction Soil-steel interaction means that a flexible steel structures

More information

ROAD TO SUCCESS A2 MOTORWAY ŚWIECKO NOWY TOMYŚL

ROAD TO SUCCESS A2 MOTORWAY ŚWIECKO NOWY TOMYŚL ROAD TO SUCCESS A2 MOTORWAY ŚWIECKO NOWY TOMYŚL Map of the Świecko - Nowy Tomyśl section 2. A2 motorway The A2 motorway runs latitudinally through central areas of Poland. It is one of the most strategic

More information

RETAINING WALL SYSTEM. ViaWall. ViaWall A. ViaWall B. ViaBlock

RETAINING WALL SYSTEM. ViaWall. ViaWall A. ViaWall B. ViaBlock RETAINING WALL SYSTEM ViaWall ViaWall A ViaWall B ViaBlock Table of contents Introduction page 1 ViaWall type A Elements of the system 1. Reinforced concrete panel 2. Reinforcing meshes 3. U-bolts Additional

More information

ITEM 461 STRUCTURAL PLATE STRUCTURES. Galvanized steel plates shall conform to AASHTO M167 and aluminum plates shall conform to AASHTO M219.

ITEM 461 STRUCTURAL PLATE STRUCTURES. Galvanized steel plates shall conform to AASHTO M167 and aluminum plates shall conform to AASHTO M219. ITEM 461 STRUCTURAL PLATE STRUCTURES 461.1. Description. This Item shall govern for the furnishing and installing of structural plate pipes, pipe arches, arches, underpasses, box culverts and special shapes

More information

Horizontal Ellipse. Contact LSBC for additional sizes. Buried Ellipse for Pedestrian Traffic. Elliptical Stream Crossing

Horizontal Ellipse. Contact LSBC for additional sizes. Buried Ellipse for Pedestrian Traffic. Elliptical Stream Crossing Horizontal Ellipse By eliminating the need for concrete footings this shape can often provide the lowest overall installed cost of any long span structure. If a natural stream bottom is desired the invert

More information

HELICALLY CORRUGATED STEEL PIPES. HelCor & HelCor PA

HELICALLY CORRUGATED STEEL PIPES. HelCor & HelCor PA HELICALLY CORRUGATED STEEL PIPES HelCor & HelCor PA Table of Contents 1. Applications 2. Steel 3. Plate thickness and corrugation types 4. Production 5. Section lengths and coupling bands 6. Geometric

More information

Design & Detail Installation Manual. LongSpan Bridge and Culvert Construction System

Design & Detail Installation Manual. LongSpan Bridge and Culvert Construction System Design & Detail Installation Manual LongSpan Bridge and Culvert Construction System Table of Contents 1.0 Long Span Installation... 2 2.0 Long Span Conceptual Details... 3 3.0 Footing Options... 6 4.0

More information

The Right Solution for Any Job.

The Right Solution for Any Job. bigrbridge.com The Right Solution for Any Job. When it comes to infrastructure projects, Big R Bridge is the design specialist with a proven reputation for consistently delivering the right solutions,

More information

MULTI-PLATE VERSATILE BRIDGE AND CULVERT PRODUCT MADE OF CURVED CORRUGATED STEEL PLATES ECONOMICAL DURABLE EASY TO INSTALL ARMTEC.

MULTI-PLATE VERSATILE BRIDGE AND CULVERT PRODUCT MADE OF CURVED CORRUGATED STEEL PLATES ECONOMICAL DURABLE EASY TO INSTALL ARMTEC. DRAINAGE SOLUTIONS SINCE 1908 MULTI-PLATE VERSATILE BRIDGE AND CULVERT PRODUCT MADE OF CURVED CORRUGATED STEEL PLATES ECONOMICAL DURABLE EASY TO INSTALL ARMTEC.COM MULTI-PLATE MULTI-PLATE HAS A PROVEN

More information

APPENDIX B ABC STRUCTURES DESIGN GUIDE

APPENDIX B ABC STRUCTURES DESIGN GUIDE APPENDIX B ABC STRUCTURES DESIGN GUIDE The Cohos Evamy Partners TABLE OF CONTENTS Page No. DISCLAIMER... I 1. STRUCTURAL DESIGN GUIDELINES... 1 2. GENERAL REQUIREMENTS (FIGURE B.2, STEP 1)... 1 3. GENERAL

More information

MULTI-PLATE PRODUCT GUIDE

MULTI-PLATE PRODUCT GUIDE ARMTEC.COM DRAINAGE SOLUTIONS AND WATER TREATMENT / MULTI-PLATE MULTI-PLATE PRODUCT GUIDE VERSATILE AND ECONOMICAL PIPE AND BRIDGE PRODUCT MADE OF CURVED, CORRUGATED GALVANIZED STEEL PLATES Variety of

More information

B U I L D I N V A L U E W I T H S U P E R C O R S T R U C T U R A L S T E E L P L A T E.

B U I L D I N V A L U E W I T H S U P E R C O R S T R U C T U R A L S T E E L P L A T E. B U I L D I N V A L U E W I T H S U P E R C O R S T R U C T U R A L S T E E L P L A T E. ail.ca Structural Plate 4We ve been Sound adding Walls Systems value 23 to Related some Products of the 28 world

More information

STRUCTURE IN BIG SKEW GLADSAXE CASE DENMARK 1

STRUCTURE IN BIG SKEW GLADSAXE CASE DENMARK 1 ARCHIWUM INSTYTUTU INŻYNIERII LĄDOWEJ Nr 23 ARCHIVES OF INSTITUTE OF CIVIL ENGINEERING 2017 STRUCTURE IN BIG SKEW GLADSAXE CASE DENMARK 1 Piotr TOMALA*, Rene VEGERBY-HANSEN** *) MSc. Eng., ViaCon Polska

More information

ARMTEC.COM. Bridge Materials / Strength Variety of Shapes Durability Low Shipping Cost

ARMTEC.COM. Bridge Materials / Strength Variety of Shapes Durability Low Shipping Cost ARMTEC.COM Bridge Materials / TECHNICAL GUIDE DEEP CORRUGATED STRUCTURAL PLATE PROVIDES AN ECONOMICAL AND DURABLE SOLUTION FOR A BROAD RANGE OF BRIDGE, CULVERT AND TUNNEL APPLICATIONS Strength Variety

More information

Installation Manual. ArchCast Bridge. 3-Sided Precast Concrete Bridge Structure

Installation Manual. ArchCast Bridge. 3-Sided Precast Concrete Bridge Structure ArchCast Bridge 3-Sided Precast Concrete Bridge Structure Installation Manual Salem Location: 749 West Commercial Ave. Salem, IL 62881 (618) 548-1190 countymaterials.com Email: info@countymaterials.com

More information

Innovation Flows From Here

Innovation Flows From Here Innovation Flows From Here Superior Structural Strength and Value CANADA CULVERT has compiled years of research to manufacture an advanced, structurally superior corrugated steel pipe that will take on

More information

ENGINEERED SOLUTIONS. Aluminum Structural Plate

ENGINEERED SOLUTIONS. Aluminum Structural Plate ENGINEERED SOLUTIONS Aluminum Structural Plate 1 Aluminum Structural Plate Time-Tested & Durable Engineers, officials and contractors know that proper construction materials play an important part in designing

More information

ARMOR-BLOCK. Installation guide. Installation Manual: ARMOR-BLOCK Retaining Wall System. Cap Block. Exposed void for planting.

ARMOR-BLOCK. Installation guide. Installation Manual: ARMOR-BLOCK Retaining Wall System. Cap Block. Exposed void for planting. ARMOR-BLOCK Installation guide Cap Block Exposed void for planting In situ soil Engineered backfill Compacted and prepared base Setback Lip Ph 0800 655 00 or visit www.csppacific.co.nz 19 February 08 /

More information

October BC MoTI

October BC MoTI 7.1 SCOPE... 2 7.5 STRUCTURAL DESIGN... 3 7.5.2 Load factors... 3 7.5.5 Seismic requirements... 4 7.5.5.4 Seismic design of concrete structures... 4 7.6 SOIL-METAL STRUCTURES... 4 7.6.2 Structural materials...

More information

STANDARD SPECIFICATION FOR CRIBLOCK CONCRETE CRIBWALL

STANDARD SPECIFICATION FOR CRIBLOCK CONCRETE CRIBWALL STANDARD SPECIFICATION FOR CRIBLOCK CONCRETE CRIBWALL 1. SCOPE 2. DESIGN 3. MATERIALS 4. CONSTRUCTION 5. METHOD OF MEASUREMENT AND PAYMENT SCOPE This Specification sets out requirements for the design,

More information

Product Manual: Multiplate 100+ Multiplate 100+ Product Manual. Ph or visit

Product Manual: Multiplate 100+ Multiplate 100+ Product Manual. Ph or visit Product Manual: Multiplate 100+ Multiplate 100+ Product Manual Ph 0800 655 200 or visit www.csppacific.co.nz July 2018 / Page 1 Product Manual: Multiplate 100+ Table of Contents Introduction......... 3

More information

TUNNEL LINER PLATE INTRODUCTION GENERAL APPLICATIONS CHAPTER 11

TUNNEL LINER PLATE INTRODUCTION GENERAL APPLICATIONS CHAPTER 11 CHAPTER 11 INTRODUCTION The open-trench method of placing underground conduits is commonly used on new construction of culverts, sewers and underpasses. Interference with traffic, as well as inconvenience

More information

VOLUME 2 TECHNICAL SPECIFICATIONS BID NO PROJECT MANUAL FOR BONDS RANCH ROAD WIDENING PROJECT BIDS DUE JULY 9, :00 P.M.

VOLUME 2 TECHNICAL SPECIFICATIONS BID NO PROJECT MANUAL FOR BONDS RANCH ROAD WIDENING PROJECT BIDS DUE JULY 9, :00 P.M. Vendor Name: JACK BEACHAM, C.P.M., A.P.P. PURCHASING AGENT TARRANT COUNTY PURCHASING DEPARTMENT ROB COX, C.P.M., A.P.P. ASSISTANT PURCHASING AGENT VOLUME 2 TECHNICAL SPECIFICATIONS BID NO. 2015-161 PROJECT

More information

SECTION 303 CULVERTS

SECTION 303 CULVERTS 303.01 Scope - This section covers the construction of pipe culverts. 303.01.01 Definitions for the purposes of this section, the following general terms are defined as follows: a) Backfilling means the

More information

BRIDGE-PLATE DEEP CORRUGATED STRUCTURAL PLATE FOR BRIDGE, CULVERT AND TUNNEL APPLICATIONS STRONG DURABLE ECONOMICAL ARMTEC.COM

BRIDGE-PLATE DEEP CORRUGATED STRUCTURAL PLATE FOR BRIDGE, CULVERT AND TUNNEL APPLICATIONS STRONG DURABLE ECONOMICAL ARMTEC.COM DRAINAGE SOLUTIONS SINCE 1908 BRIDGE-PLATE DEEP CORRUGATED STRUCTURAL PLATE FOR BRIDGE, CULVERT AND TUNNEL APPLICATIONS STRONG DURABLE ECONOMICAL ARMTEC.COM BRIDGE-PLATE Bridge-Plate is one of the strongest

More information

DETENTION, RETENTION AND RECHARGE STRUCTURES

DETENTION, RETENTION AND RECHARGE STRUCTURES DETENTION, RETENTION AND RECHARGE STRUCTURES Introduction Foundation, trenchwall, bedding and backfill considerations for multiple barrel detention systems are not unlike those for conventional CSP installations.

More information

CHAPTER 16 - GANTRIES

CHAPTER 16 - GANTRIES CHAPTER 16 - GANTRIES DS Temple 16.1 SCOPE This section covers the inspection of Sign Gantries as specified in the applicable chapter of the Specifications. It also covers the special attention which must

More information

SPECIFICATION FOR REINFORCED SOIL WALL

SPECIFICATION FOR REINFORCED SOIL WALL SPECIFICATION FOR REINFORCED SOIL WALL 1.0 EXTENT OF WORK The work shall consist of Reinforced Soil walls built in accordance with this specification and in conformity with the lines, levels and details

More information

SPECIAL SPECIFICATION 4653 Polypropylene Pipe

SPECIAL SPECIFICATION 4653 Polypropylene Pipe 2004 Specifications CSJ 2158-01-013, Etc. SPECIAL SPECIFICATION 4653 Polypropylene Pipe 1. Description. Furnish and install polypropylene pipe for constructing polypropylene pipe culverts or polypropylene

More information

SPECIAL SPECIFICATION 4425 Thermoplastic Pipe

SPECIAL SPECIFICATION 4425 Thermoplastic Pipe 2004 Specifications CSJ 0264-07-028 SPECIAL SPECIFICATION 4425 Thermoplastic Pipe 1. Description. Furnish and install thermoplastic pipe for constructing thermoplastic pipe culverts or thermoplastic storm

More information

SECTION MECHANICALLY STABILIZED EARTH RETAINING WALLS

SECTION MECHANICALLY STABILIZED EARTH RETAINING WALLS SECTION 13100 MECHANICALLY STABILIZED EARTH RETAINING WALLS PART 1 -- GENERAL 1.01 THE REQUIREMENT A. Includes all labor, material, equipment, testing and submittals required to design and complete construction

More information

SECTION A-A NTS. Figure 4.1 Alternative Flow Dispersal Trench NOTES:

SECTION A-A NTS. Figure 4.1 Alternative Flow Dispersal Trench NOTES: Figure 4.1 Alternative Flow Dispersal Trench NOTES: galvanized bolts 2" x 12" pressure treated grade board 2" x 2" notches 18" O.C. *20% max 12" min. 36" max 1' - 6" min *20% max 4" x 4" support post clean

More information

INDEX FOR SPECIFICATIONS FOR REMOVING CULVERTS AND PLACING CULVERTS SCOPE... 1

INDEX FOR SPECIFICATIONS FOR REMOVING CULVERTS AND PLACING CULVERTS SCOPE... 1 March 2002 No. 400 INDEX FOR SPECIFICATIONS FOR REMOVING CULVERTS AND PLACING CULVERTS 400. 1 SCOPE... 1 400. 2 REMOVING CULVERTS AND TIMBER STRUCTURES 2.1 Concrete and Metal Pipe Culverts... 1 2.2 Structural

More information

STRUCTURAL ANALYSIS. PSDS s.r.o. IČ: TRABANTSKÁ 673/18, PRAHA 9. for building permit. March 2012 NUMBER OF PAGES 15

STRUCTURAL ANALYSIS. PSDS s.r.o. IČ: TRABANTSKÁ 673/18, PRAHA 9. for building permit. March 2012 NUMBER OF PAGES 15 2012 CONSTRUCTION DEGREE for building permit STRUCTURAL ANALYSIS March 2012 PERSON RESPONSIBLE Ing. Jiří Surovec NUMBER OF PAGES 15 PSDS s.r.o. IČ: 280 980 64 www.psds.cz TRABANTSKÁ 673/18, 190 15 PRAHA

More information

GEOGRID CONNECTION DETAIL OLYMPIA RADIUS UNIT

GEOGRID CONNECTION DETAIL OLYMPIA RADIUS UNIT PLACE TWO STANDARD CONNECTORS IN EACH UNIT AS SHOWN (VERTICAL ORIENTATION) INSERT TWO CONNECTORS PER HORIZONTALLY ORIENTED BLOCK; INSERT ONE CONNECTOR PER VERTICALLY ORIENTED BLOCK SHIM BETWEEN BLOCK COURSES

More information

ITEM D-701 PIPE FOR STORM DRAINS AND CULVERTS

ITEM D-701 PIPE FOR STORM DRAINS AND CULVERTS ITEM D-701 PIPE FOR STORM DRAINS AND CULVERTS 701-1 DESCRIPTION 701-1.1 This item shall consist of the construction of pipe culverts, and storm drains, removal of existing storm pipes, connections to existing

More information

PIPE CULVERTS. Construct pipe culverts, beveled ends, pipe aprons, and associated appurtenances.

PIPE CULVERTS. Construct pipe culverts, beveled ends, pipe aprons, and associated appurtenances. PIPE CULVERTS PART 1 - GENERAL 1.01 SECTION INCLUDES A. Pipe Culverts B. Pipe Aprons and Beveled Ends C. Footings for Concrete Pipe Aprons D. Pipe Apron Guards 1.02 DESCRIPTION OF WORK Construct pipe culverts,

More information

TECHNICAL MANUAL. HPKM Column Shoe Reliable Bolted Column Connections. Version: PEIKKO GROUP ACI-M 01/2017 Designed according to ACI 318M-11

TECHNICAL MANUAL. HPKM Column Shoe Reliable Bolted Column Connections. Version: PEIKKO GROUP ACI-M 01/2017 Designed according to ACI 318M-11 TECHNICAL MANUAL Column Shoe Reliable Bolted Column Connections Version: PEIKKO GROUP -M 01/2017 Designed according to 318M-11 Column Shoe For bolted column connections Full-Scale tested & approved connection

More information

MICHIGAN DEPARTMENT OF TRANSPORTATION SPECIAL PROVISION FOR LOW-TENSION CABLE BARRIER. OPR:CT 1 of 5 APPR:JAR:DBP: FHWA:APPR:

MICHIGAN DEPARTMENT OF TRANSPORTATION SPECIAL PROVISION FOR LOW-TENSION CABLE BARRIER. OPR:CT 1 of 5 APPR:JAR:DBP: FHWA:APPR: MICHIGAN DEPARTMENT OF TRANSPORTATION SPECIAL PROVISION FOR LOW-TENSION CABLE BARRIER OPR:CT 1 of 5 APPR:JAR:DBP:09-07-11 FHWA:APPR:09-07-11 a. Description. This work consists of furnishing and installing

More information

Technical Data Sheet NEC/GRAN/95:01

Technical Data Sheet NEC/GRAN/95:01 Technical Data Sheet NEC/GRAN/95:01 Installation Guidance Notes Granular Surround Note : These guidance notes refer only to the installation of Granular surround underground tanks. These guidance notes

More information

FEATURES & BENEFITS OF ARMTEC TUNNEL LINER PLATE

FEATURES & BENEFITS OF ARMTEC TUNNEL LINER PLATE TUNNEL LINER PLATE FEATURES & BENEFITS OF ARMTEC TUNNEL LINER PLATE SAFE ECONOMICAL VERSATILE SIMPLE EASY TO HANDLE READILY AVAILABLE All underground work can be undertaken from within the assembled shell.

More information

Special Provision No. 421F01 April 2006

Special Provision No. 421F01 April 2006 RIGID PIPE CULVERTS Item No. FLEXIBLE PIPE CULVERTS Item No. CSP ARCH CULVERTS Item No. STRUCTURAL PLATE CSP Item No. CORRUGATED STEEL PIPE EXTENSIONS Item No. ROCK EXCAVATION FOR CULVERTS Item No. CLAY

More information

ENGINEERED SOLUTIONS. Contech Bridge Plank

ENGINEERED SOLUTIONS. Contech Bridge Plank ENGINEERED SOLUTIONS Contech Bridge Plank Contech Bridge Plank for Rehabilitation Make unsound bridges safe with Contech Bridge Plank Every state is faced with the problem of replacing old bridges. In

More information

TECHNICAL MANUAL. HPKM Column Shoe. Reliable Bolted Column Connections

TECHNICAL MANUAL. HPKM Column Shoe. Reliable Bolted Column Connections TECHNICAL MANUAL Column Shoe Reliable Bolted Column Connections Version: PEIKKO GROUP 05/2014 Column Shoe For bolted column connections System benefits The stiff ness of Peikko s column connection is verifi

More information

GABIONS PVC Coated. Product Standard Specifications Installation Instructions Method of Measurement and Payment. Update: May 1999

GABIONS PVC Coated. Product Standard Specifications Installation Instructions Method of Measurement and Payment. Update: May 1999 PSS-GBPVC.doc - Page 1 GABIONS PVC Coated Product Standard Specifications Installation Instructions Method of Measurement and Payment Update: May 1999 ENVIRONMENTAL SOLUTIONS PSS-GBPVC.doc - Page 2 FOREWORD

More information

Structural Plate Products Solving Site Problems

Structural Plate Products Solving Site Problems Structural Plate Products Solving Site Problems BURIED STRUCTURES ABOUT LANE As a full-line manufacturer of corrugated metal and plastic drainage products, Lane Enterprises, Inc. operates a number of plants

More information

TECHNICAL MANUAL. PEC Column Shoe. Heavy-duty Bolted Column Connections

TECHNICAL MANUAL. PEC Column Shoe. Heavy-duty Bolted Column Connections TECHNICAL MANUAL PEC Column Shoe Heavy-duty Bolted Column Connections Version: PEIKKO GROUP 09/2018 PEC Column Shoe For bolted column connections Advanced casting process with the help of standard accessories

More information

STRENGTH CONSEQUENCE MINIMIZATION OF DIGGING OFF BURIED GAS PIPELINE AT ISOLATION COAT RENOVATION REALIZED DURING OPERATION

STRENGTH CONSEQUENCE MINIMIZATION OF DIGGING OFF BURIED GAS PIPELINE AT ISOLATION COAT RENOVATION REALIZED DURING OPERATION STRENGTH CONSEQUENCE MINIMIZATION OF DIGGING OFF BURIED GAS PIPELINE AT ISOLATION COAT RENOVATION REALIZED DURING OPERATION Assoc. Prof. MSc. Roland JANČO, PhD. Institute of Applied Mechanics and Mechatronics,

More information

COLUMN SHOES HPKM, PPKM, PEC

COLUMN SHOES HPKM, PPKM, PEC COLUMN SHOES HPKM, PPKM, PEC Version 9/2007 (Update 7/2009) Replaces brochure /2006 HPKM, PPKM, PEC -column shoes Benefits of Peikko -column joints Saves time, costs and materials Easy and fast adjustments

More information

SECTION STORM DRAINAGE

SECTION STORM DRAINAGE SECTION 02720 STORM DRAINAGE PART 1 - GENERAL 1.01 WORK INCLUDED A. Trenching and other excavation. B. Ground water control. C. Pipe bedding. D. Installation of storm drains and appurtenances. E. Installation

More information

SOLVING SITE PROBLEMS WITH LANE STRUCTURAL PLATE PRODUCTS

SOLVING SITE PROBLEMS WITH LANE STRUCTURAL PLATE PRODUCTS SOLVING SITE PROBLEMS WITH LANE STRUCTURAL PLATE PRODUCTS ABOUT LANE ABOUT LANE Lane Enterprises specializes in partnering with cusmers from consultation installation provide highly engineered products

More information

Efficient Buried Bridge Solutions

Efficient Buried Bridge Solutions Efficient Buried Bridge Solutions E C O N O M I C A L A L T E R N A T I V E S F O R A W I D E V A R I E T Y O F A P P L I C A T I O N S bigrbridge.com About Big R Bridge America s go-to partner in Buried

More information

TEST AND ANALYSIS OF A SHORT-SPAN RAILWAY BRIDGE

TEST AND ANALYSIS OF A SHORT-SPAN RAILWAY BRIDGE Proceedings of the 6th International Conference on Mechanics and Materials in Design, Editors: J.F. Silva Gomes & S.A. Meguid, P.Delgada/Azores, 26-30 July 2015 PAPER REF: 5756 TEST AND ANALYSIS OF A SHORT-SPAN

More information

CAPRICORN MUNICIPAL DEVELOPMENT GUIDELINES PRECAST BOX CULVERTS CONSTRUCTION SPECIFICATION

CAPRICORN MUNICIPAL DEVELOPMENT GUIDELINES PRECAST BOX CULVERTS CONSTRUCTION SPECIFICATION CAPRICORN MUNICIPAL DEVELOPMENT GUIDELINES C222 CONSTRUCTION SPECIFICATION CAPRICORN MUNICIPAL DEVELOPMENT GUIDELINES C222 ISSUE: NO:3 July 2018 TABLE OF CONTENTS CLAUSE CONTENTS PAGE GENERAL... 2 C222.01

More information

Super Cor. Strong Durable Versatile

Super Cor. Strong Durable Versatile ail.ca Super Cor We Support You. Atlantic Industries Limited (AIL) has built a solid reputation delivering professional support and innovative, high-quality, corrugated metal products around the world.

More information

CHAPTER 11: WALLS.

CHAPTER 11: WALLS. CHAPTER 11: WALLS MODULAR BLOCK WALL (DRY CAST) Rather than being pre-approved as systems, the components of Modular block walls (dry cast) are pre-approved separately. The approved MBW components are

More information

CONSTRUCTION SPECIFICATION FOR PIPE CULVERT INSTALLATION IN OPEN CUT

CONSTRUCTION SPECIFICATION FOR PIPE CULVERT INSTALLATION IN OPEN CUT ONTARIO PROVINCIAL STANDARD SPECIFICATION METRIC OPSS 421 NOVEMBER 2012 CONSTRUCTION SPECIFICATION FOR PIPE CULVERT INSTALLATION IN OPEN CUT TABLE OF CONTENTS 421.01 SCOPE 421.02 REFERENCES 421.03 DEFINITIONS

More information

THE BEBO SYSTEM. World s Best for Overfilled Arches. For Precasters, Bridge Suppliers, General Contractors, Road/Rail Authorities and Consultants

THE BEBO SYSTEM. World s Best for Overfilled Arches. For Precasters, Bridge Suppliers, General Contractors, Road/Rail Authorities and Consultants THE BEBO SYSTEM World s Best for Overfilled Arches For Precasters, Bridge Suppliers, General Contractors, Road/Rail Authorities and Consultants AREAS OF APPLICATION Overpasses Bridges Spans of 3.6 m to

More information

Solving Roadway Stream Crossings w/structural Plate Products

Solving Roadway Stream Crossings w/structural Plate Products Solving Roadway Stream Crossings w/structural Plate Products 2012 Dirt & Gravel Road Workshop Treasure Lake, Dubois PA Presenter Joseph Kisic, LANE Enterprises, Inc. Solving Roadway Stream Crossings w/structural

More information

The system: it supports 3 load classes (A15, B125, C250) in compliance with Standard EN 1433

The system: it supports 3 load classes (A15, B125, C250) in compliance with Standard EN 1433 The system: it supports 3 load classes (A15, B125, C250) in compliance with Standard EN 1433 it is made up of a channel - entirely made from HD-PE - which needs no strengthening frame it has a wide usable

More information

Tasman Retaining Wall System

Tasman Retaining Wall System Tasman Retaining Wall System The Tasman Retaining Wall System incorporates purpose made corners and capping units to provide classical reconstructed stone retaining walls for any landscape situation. From

More information

ROAD COMMISSION FOR OAKLAND COUNTY. SPECIAL PROVISION FOR GABION WALL RCOC/DESIGN: AB Page 1 of 8 RCOC12SP706F 10/28/2013

ROAD COMMISSION FOR OAKLAND COUNTY. SPECIAL PROVISION FOR GABION WALL RCOC/DESIGN: AB Page 1 of 8 RCOC12SP706F 10/28/2013 ROAD COMMISSION FOR OAKLAND COUNTY SPECIAL PROVISION FOR GABION WALL RCOC/DESIGN: AB Page 1 of 8 RCOC12SP706F a. Description This work shall be done in accordance with Section 205 and 206 of the 2012 Michigan

More information

Metal Detention/Retention Products

Metal Detention/Retention Products Metal Detention/Retention Products Optimizer CMP DETENTION SYSTEMS Corrugated Metal Pipe CMP Detention Systems CONTECH CMP detention systems store stormwater runoff exceeding a site s allowable discharge

More information

Handling and Installation Instructions

Handling and Installation Instructions Handling and Installation Instructions SUPERTANK Water Reclamation Solutions, LLC Unloading and Handling NOTE: It is the responsibility of the installer to follow OSHA safety guidelines during the installation,

More information

ULTRA FLO STEEL PIPE PRODUCT GUIDE

ULTRA FLO STEEL PIPE PRODUCT GUIDE DRAINAGE SOLUTIONS SINCE 1908 ULTRA FLO STEEL PIPE PRODUCT GUIDE LARGE-DIAMETER STORM SEWER PIPE DELIVERS SUPERIOR HYDRAULIC PERFORMANCE FAST INSTALLATION DURABLE NESTABLE PIECES VALUE EFFICIENT HYDRAULICS

More information

Underground Exhaust System

Underground Exhaust System Operation and Maintenance Manual Underground Exhaust MONOXIVENT - SOURCE CAPTURE SYSTEMS - info@ Oct. - 2015 Underground Duct Construction Standards 1. Dig trench depth to allow for minimum distance from

More information

Field and Laboratory Performance of FRP Bridge Panels

Field and Laboratory Performance of FRP Bridge Panels Field and Laboratory Performance of FRP Bridge s D. Stone, A. Nanni, & J. Myers University of Missouri Rolla, Rolla, Missouri, USA ABSTRACT: The objective of this research project is to examine the use

More information

CONSTRUCTION SPECIFICATION FOR INSTALLATION OF ELECTRICAL CHAMBERS

CONSTRUCTION SPECIFICATION FOR INSTALLATION OF ELECTRICAL CHAMBERS ONTARIO PROVINCIAL STANDARD SPECIFICATION OPSS.PROV 602 NOVEMBER 2017 CONSTRUCTION SPECIFICATION FOR INSTALLATION OF ELECTRICAL CHAMBERS TABLE OF CONTENTS 602.01 SCOPE 602.02 REFERENCES 602.03 DEFINITIONS

More information

WATER AND DRAINAGE. Drainage Around Walls Water Applications Drainage Structures Water and Drainage Q & A

WATER AND DRAINAGE. Drainage Around Walls Water Applications Drainage Structures Water and Drainage Q & A WATER AND DRAINAGE Drainage Around Walls Water Applications Drainage Structures Water and Drainage Q & A H CONSTRUCTION H-1 W A T E R A N D D R A I N A G E DRAINAGE AROUND WALLS Poor drainage is a leading

More information

SECTION PLATE CONNECTED WOOD TRUSSES

SECTION PLATE CONNECTED WOOD TRUSSES SECTION 06173 PLATE CONNECTED WOOD TRUSSES PART 1 GENERAL 1.01 SUMMARY A. Section Includes: 1. Shop fabricated wood trusses for roof and floor framing. 2. Bridging, bracing, and anchorage. B. Related Sections:

More information

BIN-WALL BRIDGE ABUTMENTS PRODUCT GUIDE

BIN-WALL BRIDGE ABUTMENTS PRODUCT GUIDE _ ARMTEC.COM BRIDGE MATERIALS / BIN-WALL BRIDGE ABUTMENTS BIN-WALL BRIDGE ABUTMENTS PRODUCT GUIDE LIGHTWEIGHT, GALVANIZED STEEL BIN-WALL BRIDGE ABUTMENTS SUPPORTS BRIDGE SUPER-STRUCTURES AND TRAFFIC LOADINGS

More information

Redi Rock Specification and Installation Manual

Redi Rock Specification and Installation Manual Redi Rock Specification and Installation Manual 1.0 General Scope This Specification covers the Design, Materials and Installation of Redi Rock modular block Retaining and Freestanding Wall systems as

More information

CONSTRUCTION SPECIFICATION FOR PIPE CULVERT INSTALLATION IN OPEN CUT

CONSTRUCTION SPECIFICATION FOR PIPE CULVERT INSTALLATION IN OPEN CUT ONTARIO PROVINCIAL STANDARD SPECIFICATION METRIC OPSS 421 NOVEMBER 2007 CONSTRUCTION SPECIFICATION FOR PIPE CULVERT INSTALLATION IN OPEN CUT TABLE OF CONTENTS 421.01 SCOPE 421.02 REFERENCES 421.03 DEFINITIONS

More information

Item 460 Corrugated Metal Pipe

Item 460 Corrugated Metal Pipe Item 460 Corrugated Metal Pipe 1. DESCRIPTION 2. MATERIALS Furnish and install corrugated metal pipes, materials for constructing corrugated metal pipe culverts, or corrugated metal storm drain mains,

More information

CONSTRUCTION SPECIFICATION FOR THE INSTALLATION OF ELECTRICAL CHAMBER

CONSTRUCTION SPECIFICATION FOR THE INSTALLATION OF ELECTRICAL CHAMBER ONTARIO PROVINCIAL STANDARD SPECIFICATION METRIC OPSS 602 MARCH 1993 CONSTRUCTION SPECIFICATION FOR THE INSTALLATION OF ELECTRICAL CHAMBER 602.01 SCOPE 602.02 REFERENCES 602.05 MATERIALS TABLE OF CONTENTS

More information

Bolt-A-Bin. We Support You. We Support You.

Bolt-A-Bin.   We Support You. We Support You. www.ail.ca Bolt-A-Bin We Support You. We Support You. Our Commitment Atlantic Industries Limited (AIL) has built a solid reputation by providing professional support and innovative, high quality corrugated

More information

Draft. Not Yet Approved SECTION 10.1 GENERAL SCOPE DEFINITIONS

Draft. Not Yet Approved SECTION 10.1 GENERAL SCOPE DEFINITIONS SECTION 10.1 GENERAL 10.1.1 SCOPE This part of the Manual covers the structural design and installation of reinforced concrete pipe for railway culverts. Pipe geometry may be circular, arch, or elliptical.

More information

MagnumStone Specifications Gravity

MagnumStone Specifications Gravity MagnumStone Specifications Gravity SPECIFICATION FOR MAGNUMSTONE GRAVITY MECHANICALLY STABILIZED EARTH SYSTEM PART 1: GENERAL.01Description The work consists of supplying and installing all aspects of

More information

Basic types of bridge decks

Basic types of bridge decks Bridge Deck Slab 1 Introduction 2 Bridge deck provide the riding surface for traffic, support & transfer live loads to the main load carrying member such as girder on a bridge superstructure. Selection

More information

Bridge articulation No. 1.04

Bridge articulation No. 1.04 Bridge articulation Scope This Guidance Note gives advice on the selection of the articulation arrangements, the choice of bearing types and dispositions of bearings, for bridges where relative movement

More information

SECTION 39 - MANHOLES TABLE OF CONTENTS

SECTION 39 - MANHOLES TABLE OF CONTENTS Section SECTION 39 - MANHOLES TABLE OF CONTENTS Page 39-1 GENERAL... 39.1 39-2 CONCRETE MANHOLES... 39.1 39-2.01 NOT USED... 39.1 39-2.02 Concrete Storm Drain Manholes... 39.1 39-3 SADDLE SEWER MANHOLES...

More information

Uwall UNIVERSAL CONSTRUCTION MANUAL

Uwall UNIVERSAL CONSTRUCTION MANUAL Uwall UNIVERSAL Retaining Wall System CONSTRUCTION MANUAL TM President s Letter CSI is a leader in its industry supplying precast infrastructure products throughout New England and beyond since 1972, developing

More information

BIRSTA 1P N2 WORKING DESCRIPTION INSTALLATION, REPAIRS AND MAINTENANCE. Doc. No.: Birsta 1P N2 - Rev. 0

BIRSTA 1P N2 WORKING DESCRIPTION INSTALLATION, REPAIRS AND MAINTENANCE. Doc. No.: Birsta 1P N2 - Rev. 0 BIRSTA 1P N2 WORKING DESCRIPTION INSTALLATION, REPAIRS AND MAINTENANCE Doc. No.: Birsta 1P N2 - Rev. 0 Working Description Prepared by: Fredrik Sangö Doc. no.: Birsta 1P N2 Introduction/data: Birsta 1P

More information

WESTERN UNDERGROUND COMMITTEE GUIDE 3.6 (3.6/02/0588)

WESTERN UNDERGROUND COMMITTEE GUIDE 3.6 (3.6/02/0588) WESTERN UNDERGROUND COMMITTEE GUIDE 3.6 (3.6/02/0588) NONCONCRETE ENCLOSURES NOTE: This "Guide" summarizes the opinions, recommendations, and practices of the Western Underground Committee members and

More information

DEPARTMENT OF TRANSPORTATION STATE OF GEORGIA SPECIAL PROVISION. Section 550 Storm Drain Pipe, Pipe-Arch Culverts, and Side Drain Pipe

DEPARTMENT OF TRANSPORTATION STATE OF GEORGIA SPECIAL PROVISION. Section 550 Storm Drain Pipe, Pipe-Arch Culverts, and Side Drain Pipe Revised: October 25, 2007 Revised: June 11, 2010 DEPARTMENT OF TRANSPORTATION STATE OF GEORGIA SPECIAL PROVISION Section 550 Storm Drain Pipe, Pipe-Arch Culverts, and Side Drain Pipe Delete Section 550

More information

A. Product Data: For surface pathways, wireways and fittings, floor boxes, hinged-cover enclosures, and cabinets.

A. Product Data: For surface pathways, wireways and fittings, floor boxes, hinged-cover enclosures, and cabinets. ALLIANT ENERGY CENTER PAVILIONS Project No. 2013 027 SECTION 27 05 28 - PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions

More information

Save time. Save money. Specify a fast, economical Vist-A-Wall MSE. fast and easy to install. They adapt well to curves, angles and

Save time. Save money. Specify a fast, economical Vist-A-Wall MSE. fast and easy to install. They adapt well to curves, angles and bigrbridge.com Save time. Save money. Specify a fast, economical Vist-A-Wall MSE Structural Wall System for your next engineered embankment project. These historically-proven, cost-effective systems have

More information

h Installation Manual

h Installation Manual h Installation Manual 1 General Information The installation of HOBAS GRP Pipes is subject to applicable standards and guidelines such as EN 1610 and ISO/ TS 10465-1. Correct installation always requires

More information

ULTRACOR 1-ST REALIZATION IN EUROPE, DESIGN, ERECTION, TESTING 1

ULTRACOR 1-ST REALIZATION IN EUROPE, DESIGN, ERECTION, TESTING 1 ARCHIWUM INSTYTUTU INŻYNIERII LĄDOWEJ Nr 23 ARCHIVES OF INSTITUTE OF CIVIL ENGINEERING 2017 ULTRACOR 1-ST REALIZATION IN EUROPE, DESIGN, ERECTION, TESTING 1 Czesław MACHELSKI*, Piotr TOMALA**, Bartłomiej

More information

SECTION 552 HELICAL ANCHORS AND HELICAL PILES

SECTION 552 HELICAL ANCHORS AND HELICAL PILES SECTION 552 HELICAL ANCHORS AND HELICAL PILES DESCRIPTION 552.01 This work pertains to furnishing and installing helical anchors and helical piles shown in the Contract in accordance with the Drawings

More information

Water Channeling System

Water Channeling System Water Channeling System BUILDING S FLOORING ROOFING PASSIVE FIRE PROTECTION www.laydex.ie Allied Industrial Estate Kylemore Rd Dublin 10 sales@laydex.ie MufleSystem Benefits EASY TO CONNECT STACKABLE EASY

More information

SECTION MECHANICALLY STABILIZED EARTH 1.01 SUMMARY

SECTION MECHANICALLY STABILIZED EARTH 1.01 SUMMARY SECTION 028300 PART 1 GENERAL 1.01 SUMMARY A. Section includes Basis of Design Mechanically Stabilized Earth System: SierraScape Mechanically Stabilized Earth (MSE) retaining wall system having high density

More information

Rehabilitation of the Ramalho Ortigão Viaduct

Rehabilitation of the Ramalho Ortigão Viaduct Rehabilitation of the Ramalho Ortigão Viaduct Edited by Kelly M. Page The Ramalho Ortigão Viaduct is an overpass carrying a high volume of traffic. The viaduct goes over one of the main Lisbon, Portugal,

More information

FLAT. The system: it supports 3 load classes (A15, B125, C250) in compliance with Standard EN 1433

FLAT. The system: it supports 3 load classes (A15, B125, C250) in compliance with Standard EN 1433 The system: it supports 3 load classes (A15, B125, C250) in compliance with Standard EN 1433 it is made up of a channel - entirely made from HD-PE - which needs no strengthening frame it has a wide usable

More information

MANDATORY SUPPLEMENTAL SPECIFICATIONS FOR CONTRACTOR QUALITY CONTROL Contractor Quality Control - is replaced with the following:

MANDATORY SUPPLEMENTAL SPECIFICATIONS FOR CONTRACTOR QUALITY CONTROL Contractor Quality Control - is replaced with the following: MANDATORY SUPPLEMENTAL SPECIFICATIONS FOR CONTRACTOR QUALITY CONTROL EFFECTIVE DATE: OCTOBER 14, 2011 200.07 Contractor Quality Control - is replaced with the following: (a) (b) (c) Scope: These requirements

More information

STEEL DECK INSTITUTE Industry Standard Terms & Definitions

STEEL DECK INSTITUTE Industry Standard Terms & Definitions s Industry Standard Terms & Definitions November 2016 Industry Standard Terms & Definitions A specialized set of jargon to describe common terms used by manufacturers and other professionals associated

More information

Tasman Retaining Wall System

Tasman Retaining Wall System Tasman Retaining Wall System The Tasman Retaining Wall System incorporates purpose made corners and capping units to provide classical reconstructed stone retaining walls for any landscape situation. From

More information

Industry Standard Terms & Definitions Of The Steel Deck Institute

Industry Standard Terms & Definitions Of The Steel Deck Institute Industry Standard Terms & Definitions Of The Steel Deck Institute A specialized set of jargon to describe common terms used by manufacturers and other professionals associated with the usage of Steel Deck

More information

SPECIFICATIONS FOR PRECAST MODULAR BLOCK RETAINING WALL SYSTEM (revised 5/8/7)

SPECIFICATIONS FOR PRECAST MODULAR BLOCK RETAINING WALL SYSTEM (revised 5/8/7) Page 1 of 7 STONE STRONG SYSTEMS SPECIFICATIONS FOR PRECAST MODULAR BLOCK RETAINING WALL SYSTEM (revised 5/8/7) PART 1: GENERAL 1.01 Description A. Work includes furnishing and installing precast modular

More information