An Interactive Case Study of a Differing Site Condition. Prepared by: William B. Dobbs MWH

Size: px
Start display at page:

Download "An Interactive Case Study of a Differing Site Condition. Prepared by: William B. Dobbs MWH"

Transcription

1 An Interactive Case Study of a Differing Site Condition Prepared by: William B. Dobbs MWH World Bank FIDIC Seminar Vientiane February /9/2016 1

2 To extract useful lessons from a real world hydroelectric project that did not turn out well Understanding of how things can go wrong on hydroelectric projects Appreciation of how FIDIC terms can help you Balance the risks Deal with disputes Understand the roles 2

3 Personal Introduction Assignment of Roles: Contractor Contractor s Designer Owner Construction Supervision Project overview What could go wrong? Differing site condition: discovery, denial, disbelief diagnosis, denouement Discussion, lessons learned 3

4 Educated in USA Civil Engineering & Social Science Raised in Latin America Worked long term in 13 countries including: Venezuela, Mexico, Bolivia, Egypt, Pakistan, USA Spends time thinking about construction as an ancient form of organized behavior influenced by the following factors: Design Contract Terms Construction Means & Methods, Site Conditions Social and Cultural Context Relationships 4

5 Contractor Is a very experienced and capable dam builder Does not understand engineering design very well Wants to get the job done Concerned about the schedule Contractor s Designer Is very experienced and capable Wants to improve the Basic (Tender) Design Concerned about site conditions, Expects a free hand in design development Feels that Contractor, Owner, Construction Supervision do not understand him Owner Has not build a dam in over a generation Wants his project done Wants to follow the Tender design as much as possible Feels protected by (his lawyers ) aggressive contract terms and conditions Construction Supervision Reviews and approves designs Wants to protect the Employer Is supposed to provide the expertise that the Owner lacks Considers himself an expert in claims denial 5

6 Project Description RCC Dam, 80 meters high 2 each 30 MW Francis Turbines Complex (volcanic) geology Gated spillway Contract terms Non-FIDIC, written by Employer s lawyers Contractor was to Detail Employer s Basic Design Local Law Did not allow the same entity to Design and manage Construction. (FIDIC role of Engineer was illegal.) 6

7 7

8 Contractor was required to detail the Employer s Basic Design. The Basic Designer was absent. Contract Terms were very specific as to type of dam (RCC), height, length, and dam axis location. Contract was written by Employer s Legal Department, and they called it Design-Build. Contractor was required to engage an experienced designer to detail the Basic Design. Geological Risk was (theoretically) the Contractor s. Employer had not built a hydroelectric project in over a generation and lacked experienced staff. Geology was volcanic, complex and seismically active. Local law forbade the design engineer to supervise construction. Bank required him to engage an experienced Construction Manager as Owner s Agent. Cultural factor: Strong mistrust of Contractors. 8

9 Perceptions about risk allocation differ disputes Absence of Tender Designer what is design intent? Rigid Enforcement of Tender Design limited options Separation of Design and Construction Supervision roles confusion as to who owns the design Inexperienced Employer overly reliant on legal department, mistrustful of Contractor s consultants and of his own Construction Supervision Cultural Factors key players from 4 different countries. Mistrust of Contractors Disputes Complex Volcanic Geology surprises 9

10 Note shallow boreholes by the Owner, deeper boreholes by the Contractor Thin clay layer 10

11 Thin Clay Layer 11

12 Original site investigation had shallow boreholes (average < 20 meters, max ~ 50 meters deep). Contractor conducted a more extensive campaign with boreholes exceeding 100 meters depth. Poor rock conditions were observed in right abutment above the clay layer, good conditions beneath it. Good rock throughout the left abutment. New boreholes found an extensive, deep sloping clay layer under the right abutment, sloping towards the river. Slicken-slided surfaces in clay samples indicated the right abutment might be moving. 12

13 13

14 Reference Point on Left Abutment 14

15 Fixed Survey Prisms Fixed Survey Prisms 15

16 16

17 Plot of Displacements Over a 55 day period 17

18

19 19

20 Facing East Facing North Sliding Along Clay Layer 20

21 21

22 Piezometric Head under Right Abutment 22

23 Contractor mobilized independent consultants to get independent opinions. Employer rejected their recommendations because the Contractor had hired the consultants, or reports were not stamped. Employer and Construction Supervision disowned the Basic Design and told the Contractor had to redesign the project, and build it at no extra cost. Contractor proposed to investigate an alternate nearby site. Employer s project representative said that he was not authorized to change the scope of the Contract. Employer s chief executive (appointed by the President of the country) resigned. Contractor was excused from performance and compensated. 23

24 Who was responsible for this situation? Was risk allocated equitably? What could have been done differently? By whom? Owner Construction Supervision Contractor How would the FIDIC Engineer role have helped? Who should own the design on a Hydroelectric Project? How does one deal with laws that forbid the designer from supervising construction? 24

25 Workshop Discussion Role-play a FIDIC Differing Site Conditions Scenario What would you have done? As Contractor As Employer As Engineer What difference would FIDIC have made? 25

26 The Project is King Contract is a tool that helps the project get done by balancing the risks, not to demand financial loss from the Contractor. Contracts cannot eclipse commercial reality. Employers need Contractors. Contractors, to stay in business, need to recover costs. Employers on balance, need to keep contractors profitable. Competitive bidding applies market forces to price a project. Markets assume perfect information. Hydroelectric projects contain hidden risks. Tender information is never perfect. Pricing unquantified risk requires assumptions. Risky projects therefore tend to go to whomever made the most optimistic assumptions about those risks = the party least prepared. Conclusions Risk-averse approaches ( That s their problem ) are not always risk-averse. Know which risks to share. Allocate risks to the party best able to control them. Understand and be confident of the cost estimates. 26

27 Thank you for your time. 27

Hydro Asia 2016 Training Course on

Hydro Asia 2016 Training Course on Hydro Asia 2016 Training Course on Contracts Management and the Practical Use of FIDIC Conditions of Contract in the Hydropower Construction Industry Supported by Asia Sustainable and Alternative Energy

More information

GEOTECHNICAL ENGINEERING AND DAMS

GEOTECHNICAL ENGINEERING AND DAMS GEOTECHNICAL ENGINEERING AND DAMS Shaping our world A company of OUR EXPERTISE Consultancy for Geotechnical Works in Hydropower and Water Resources Projects General Remarks Geological and geotechnical

More information

Hydropower & Dams Services

Hydropower & Dams Services Hydropower & Dams Services We represent a world-class concentration of hydropower and dam expertise. Since 1920, we have designed hundreds of new hydropower and dams globally, producing clean reliable

More information

Surviving CDM Alasdair N. Beal

Surviving CDM Alasdair N. Beal Surviving CDM 2015 Alasdair N. Beal anbeal@btinternet.com www.anbeal.co.uk If you aren t worried you haven t being paying attention CDM 2015 was supposed to do two things: incorporate domestic projects

More information

DIVERSION CHANNEL OF BELO MONTE HPP

DIVERSION CHANNEL OF BELO MONTE HPP DIVERSION CHANNEL OF BELO MONTE HPP INTRODUCTION The diversion channel of Belo Monte HPP is an important engineering work which required the engagement of several specialties to be able to address all

More information

Replacing Kitec Plumbing in your high rise condominium

Replacing Kitec Plumbing in your high rise condominium Replacing Kitec Plumbing in your high rise condominium A Quick Guide for property managers to help navigate the complex process from start to finish. Prepared by Canadian Design and Construction Inc. (CDC).

More information

Project Owners, especially in the public sector, are. Design-Build and Public-Private Partnerships: Risk Allocation of Subsurface Conditions

Project Owners, especially in the public sector, are. Design-Build and Public-Private Partnerships: Risk Allocation of Subsurface Conditions Design-Build and Public-Private Partnerships: Risk Allocation of Subsurface Conditions By David J. Hatem, Esq. Project Owners, especially in the public sector, are exploring and utilizing alternative project

More information

Estimate d Cost of Constru ction (in Lakh) Cost of Docu ment. (in Rs.)

Estimate d Cost of Constru ction (in Lakh) Cost of Docu ment. (in Rs.) S # A Government of Jammu & Kashmir GOVERNMENT OF JAMMU AND KASHMIR J&K STATE POWER DEVELOPMENT CORPORATION OFFICE OF THE EXECUTIVE ENGINEER CIVIL CONSTRUCTION DIVISION UJH HEP KATHUA. E-mail Id: xenccdujh@gmail.com

More information

Resources in the Amazon

Resources in the Amazon Name Date Resources in the Amazon Using the map, Amazonia: The Human Impact, explore the location of different natural resources in the rain forest. Think about the development that needs to occur to extract

More information

1913 Lausanne, Switzerland

1913 Lausanne, Switzerland FIDIC What is FIDIC? An international federation of consulting engineers, founded in 1913 with its headquarters located in Lausanne, Switzerland, whose objective is to promote the common interests of the

More information

Comparing Suitability of NEC and FIDIC Contracts in Managing Construction Project in Egypt

Comparing Suitability of NEC and FIDIC Contracts in Managing Construction Project in Egypt Comparing Suitability of NEC and FIDIC Contracts in Managing Construction Project in Egypt Noha D. Rasslan B.Sc. in Construction Engineering and Management German University in Cairo Cairo, Egypt Ayman

More information

Construction Cost Consultants and Quantity Surveyors Manitoba Hydro Capital Expenditure Review. January 2018

Construction Cost Consultants and Quantity Surveyors Manitoba Hydro Capital Expenditure Review. January 2018 Construction Cost Consultants and Quantity Surveyors January 2018 Powerhouse Complex July 2017 photograph provided by Manitoba Hydro Contents The Company What is a Quantity Surveyor The Keeyask Hydroelectric

More information

Resources in the Amazon Answer Key

Resources in the Amazon Answer Key Resources in the Amazon Answer Key Using the map, Amazonia: The Human Impact, explore the location of different natural resources in the rain forest. Think about the development that needs to occur to

More information

Recognizing Leadership Blind Spots

Recognizing Leadership Blind Spots Recognizing Leadership Blind Spots And Discovering the Road to Motivating Your Employees dalecarnegie.com Recognizing Leadership Blind Spots and Discovering the Road to Motivating Your Employees Greater

More information

Blue Lake Hydroelectric Project (FERC No. 2230) Expansion Environmental Analysis

Blue Lake Hydroelectric Project (FERC No. 2230) Expansion Environmental Analysis United States Departme nt of Agriculture Forest Service Alaska Region Tongass National Forest (907) 747-6671 Blue Lake Hydroelectric Project (FERC No. 2230) Expansion Environmental Analysis Dear Planning

More information

PHYSICAL PLANT DEPARTMENT MAINTENANCE AND PLANNING DIVISION AUDIT OF ALLEGED CONFLICT OF INTEREST

PHYSICAL PLANT DEPARTMENT MAINTENANCE AND PLANNING DIVISION AUDIT OF ALLEGED CONFLICT OF INTEREST PHYSICAL PLANT DEPARTMENT MAINTENANCE AND PLANNING DIVISION AUDIT OF ALLEGED CONFLICT OF INTEREST THE UNIVERSITY OF NEW MEXICO September 8, 2009 J.E. Gene Gallegos, Chair Carolyn Abeita, Vice Chair James

More information

Dam Safety and Seismicity

Dam Safety and Seismicity Dam Safety and Seismicity January 13, 2014 Fort St. John, BC John Nunn, P.Eng, M.Sc., M.I.C.E Chief Project Engineer Tim Little, P. Eng. Topics 1. The Practice of Dam Safety in BC Hydro 2. Bennett Dam

More information

Gain status in the market

Gain status in the market Gain status in the market RICS Expert Witness Certificate rics.org/expertwitnesscertificate Expert Witness Certificate Founded on the official RICS Professional Guidance, this 12-week blended learning programme

More information

Committee Opinion May 6, 2008 CITY ATTORNEY PROVIDES LEGAL SERVICES TO MULTIPLE CONSTITUENTS WITHIN AN ORGANIZATION.

Committee Opinion May 6, 2008 CITY ATTORNEY PROVIDES LEGAL SERVICES TO MULTIPLE CONSTITUENTS WITHIN AN ORGANIZATION. LEGAL ETHICS OPINION 1836 CONFLICTS OF INTEREST INVOLVED WHEN CITY ATTORNEY PROVIDES LEGAL SERVICES TO MULTIPLE CONSTITUENTS WITHIN AN ORGANIZATION. You have presented hypothetical situations in which

More information

MANAGING UNDERGROUND RISKS: GEOTECHNICAL BASELINE REPORTS

MANAGING UNDERGROUND RISKS: GEOTECHNICAL BASELINE REPORTS MANAGING UNDERGROUND RISKS: GEOTECHNICAL BASELINE REPORTS Randall J. Essex, PE Executive Vice President Tunnels Practice Breakthroughs in Tunneling Short Course September 12-15, 2016 University of Colorado,

More information

Considerations for Indonesia s New Government: Structuring Petroleum-Sector Institutions

Considerations for Indonesia s New Government: Structuring Petroleum-Sector Institutions Briefing October 2014 Considerations for Indonesia s New Government: Structuring Petroleum-Sector Institutions Patrick Heller and Poppy Ismalina Universitas Gadjah Mada As Indonesia s new government seeks

More information

EVERYTHING WE LEARNED ABOUT BUSINESS, WE LEARNED FROM THE HYDRO PROJECT.

EVERYTHING WE LEARNED ABOUT BUSINESS, WE LEARNED FROM THE HYDRO PROJECT. EVERYTHING WE LEARNED ABOUT BUSINESS, WE LEARNED FROM THE HYDRO PROJECT. NORMAN JAEHRLING, CEO PIC MOBERT FIRST NATION NADF ENERGY & FORESTRY FORUM, 2017 MOST EVERYTHING WE LEARNED ABOUT BUSINESS, WE LEARNED

More information

Completion report and next steps. Yemen - Petroleum governance Petroleum Governance Initiative funded Technical Assistance P TAS-TF057534

Completion report and next steps. Yemen - Petroleum governance Petroleum Governance Initiative funded Technical Assistance P TAS-TF057534 Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Completion report and next steps Yemen - Petroleum governance Petroleum Governance Initiative

More information

Enhancing the Climate Resilience of African Infrastructure

Enhancing the Climate Resilience of African Infrastructure Enhancing the Climate Resilience of African Infrastructure THE WATER AND POWER SECTORS: SUMMARY OF FINDINGS FEBRUARY 2015 James Neumann, Principal, Industrial Economics Raffaello Cervigni Lead Environmental

More information

Questions and Answers Contracts and Procurement Process for the Muskrat Falls Project

Questions and Answers Contracts and Procurement Process for the Muskrat Falls Project Questions and Answers Contracts and Procurement Process for the Muskrat Falls Project March 2014 Q1. Can you confirm whether the Asatldi bid was one third less than the next lowest bidder? A1. Nalcor Energy

More information

Contracts and Risk. Building blocks for success. Miami, November 14 th, 2016

Contracts and Risk. Building blocks for success. Miami, November 14 th, 2016 Contracts and Risk Building blocks for success Miami, November 14 th, 2016 Risk, what risk? Heathrow 100% Cost Overrun 6 month delay Channel Tunnel 80% cost overrun Hallandsas 300% Cost overrun 10+ years

More information

Estimation of External Costs Associated with Hydroelectric Projects Having Reservoirs

Estimation of External Costs Associated with Hydroelectric Projects Having Reservoirs Estimation of External Costs Associated with Hydroelectric Projects Having Reservoirs Ghulam Rasul Athar Applied Systems Analysis Group, Pakistan Atomic Energy Commission, P.O. Box 1114, Islamabad, Pakistan

More information

ALTERNATE FORMS OF PROJECT DELIVERY

ALTERNATE FORMS OF PROJECT DELIVERY ALTERNATE FORMS OF PROJECT DELIVERY 1 INTRODUCTION 1.1 BACKGROUND.1 In the building industry today, conventional methods of project delivery are being challenged by Clients, Consultants and Contractors

More information

Middle East Delivering Expertise Since 1978

Middle East Delivering Expertise Since 1978 Middle East Delivering Expertise Since 1978 Global Construction Consultancy ABOUT US We have excelled at providing construction and engineering focused services since 1978. Our Project Management, Programming,

More information

Guidelines for Assessing Seismic Resistance of Important Cultural Properties (Buildings)

Guidelines for Assessing Seismic Resistance of Important Cultural Properties (Buildings) Guidelines for Assessing Seismic Resistance of Important Cultural Properties (Buildings) (Approved by the decision of the Director-General for Cultural Properties Protection Department, Agency for Cultural

More information

SPECIAL COUNCIL AGENDA REPORT

SPECIAL COUNCIL AGENDA REPORT SPECIAL COUNCIL AGENDA REPORT TO: Mayor Murphy and Members of Council MEETING DATE: July 24, 2012 SUBJECT: CAO Recruitment for Township of Muskoka Lakes RECOMMENDATION: That Policy C-CAO-13 a policy respecting

More information

Attendance Attendance refers to the consistency that an employee shows in turning up for work and completing their normal work hours.

Attendance Attendance refers to the consistency that an employee shows in turning up for work and completing their normal work hours. Position Title: Evaluation Period: Attendance Attendance refers to the consistency that an employee shows in turning up for work and completing their normal work hours. Employee regularly fails to meet

More information

Careers List Professional Careers in Construction

Careers List Professional Careers in Construction Careers List Professional Careers in Construction Architect Designs buildings, including the preparation of detailed construction drawings and specifications, and advises on their construction. May specialize

More information

SMALL HYDRO BIG CHALLENGES Renewable Energy World Asia 2016 Martin P. Bieri. September 21, 2016

SMALL HYDRO BIG CHALLENGES Renewable Energy World Asia 2016 Martin P. Bieri. September 21, 2016 SMALL HYDRO BIG CHALLENGES Renewable Energy World Asia 2016 Martin P. Bieri September 21, 2016 CONTENT Introduction Potential in Southeast Asia Challenges in Small Hydro Main Design Steps (Bad) Examples

More information

Legal Operations Managers

Legal Operations Managers Legal Operations Managers At the Intersection of Business and the Practice of Law C o p y r i g h t 2 0 1 8 A l t m a n W e i l, I n c. A l l r i g h t s f o r f u r t h e r p u b l i c a t i o n o r r

More information

Management Report RICARDO SAMPLE. Tuesday, June 10, 2003

Management Report RICARDO SAMPLE. Tuesday, June 10, 2003 Management Report RICARDO SAMPLE Tuesday, June 10, 2003 Profiles Antigua Inc. Aflak Building, Friars Hill Road St. John s Antigua (268) 462-5673 www.profilesantigua.com Copyright 1996-2001 Profiles International,

More information

Day 1. WELCOME NOTE AND INTRODUCTION COURSE OVERVIEW Course Outline. Session 1: Introduction and Overview. Introduction and Overview

Day 1. WELCOME NOTE AND INTRODUCTION COURSE OVERVIEW Course Outline. Session 1: Introduction and Overview. Introduction and Overview and the Day 1 WELCOME NOTE AND INTRODUCTION COURSE OVERVIEW Course Outline Session 1: Introduction and Overview Introduction and Overview Advantages of FIDIC Contracts Rules Reasonableness Session 2: Signatories

More information

SAN ANTONIO S PREMIER CIVIL CONTRACTOR

SAN ANTONIO S PREMIER CIVIL CONTRACTOR SAN ANTONIO S PREMIER CIVIL CONTRACTOR SERVING SAN ANTONIO FOR OVER 50 YEARS. Table of Contents Yantis Company..Shaping the San Antonio & South Texas Landscape for over 50 years... 4 What Sets Us Apart...

More information

Mr. Paul Dunlap, California Department of Water Resources

Mr. Paul Dunlap, California Department of Water Resources Memorandum To: From: Mr. Paul Dunlap, California Department of Water Resources Oroville Dam Spillway Incident Independent Forensic Team Date: September 5, 2017 Re: Interim Status Memorandum Introduction

More information

6/15/16. FIDIC ContractingAdvantages and Pitfalls. INTRODUCTON: Who are We? Akin M. Alcitepe Partner, Sedgwick LLP

6/15/16. FIDIC ContractingAdvantages and Pitfalls. INTRODUCTON: Who are We? Akin M. Alcitepe Partner, Sedgwick LLP 6/15/16 FIDIC ContractingAdvantages and Pitfalls AKIN M. ALCITEPE, ESQ. PARTNER WASHINGTON D.C. MEREDITH R PHILIPP, ESQ. ASSOCIATE WASHINGTON D.C. INTRODUCTON: Who are We? Akin M. Alcitepe Partner, Sedgwick

More information

STAFFED OR STUFFED. Creating Resilience Through Your People A PRACTICAL GUIDE FOR ORGANISATIONS

STAFFED OR STUFFED. Creating Resilience Through Your People A PRACTICAL GUIDE FOR ORGANISATIONS STAFFED OR STUFFED Creating Resilience Through Your People A PRACTICAL GUIDE FOR ORGANISATIONS WHY A PEOPLE FIRST APPROACH PAYS DIVIDENDS When disaster strikes, you will need your staff to go the extra

More information

STAFFED OR STUFFED. Creating Resilience Through Your People A PRACTICAL GUIDE FOR ORGANISATIONS

STAFFED OR STUFFED. Creating Resilience Through Your People A PRACTICAL GUIDE FOR ORGANISATIONS STAFFED OR STUFFED Creating Resilience Through Your People A PRACTICAL GUIDE FOR ORGANISATIONS WHY A PEOPLE FIRST APPROACH PAYS DIVIDENDS When disaster strikes, you will need your staff to go the extra

More information

DEAR MS ETHICS * * * * * * * * * * * * * * * * * Should CCIC members be doing police checks on volunteers and others working for them?

DEAR MS ETHICS * * * * * * * * * * * * * * * * * Should CCIC members be doing police checks on volunteers and others working for them? DEAR MS ETHICS Dear Ms Ethics is a communication vehicle of the CCIC Ethics Review Committee (ERC). It is one means by which they share answers to members' questions about organizational ethical dilemmas

More information

INVITATION OF BID (INTERNATIONAL COMPETITIVE BIDDING)

INVITATION OF BID (INTERNATIONAL COMPETITIVE BIDDING) INVITATION OF BID (INTERNATIONAL COMPETITIVE BIDDING) Bid Title : EPC Bid for Planning, detailed design& engineering, construction/manufacturing of civil, electro-mechanical, hydro- mechanical and switch

More information

GEOTESTA - CONSULTING ENGINEERS

GEOTESTA - CONSULTING ENGINEERS GEOTESTA - CONSULTING ENGINEERS Our aim is to know more about who you are and what you plan to do Geotesta is a specialist Geotechnical Engineering firm established in 2006 with offices in Melbourne and

More information

Contracting Methods and Risk Management

Contracting Methods and Risk Management Contracting Methods and Risk Management In Tunneling and Underground Construction Michael S Schultz Senior Vice President CDM Smith Boston, Massachusetts September 12, 2016 Topics What is a Contract and

More information

2. SCOPE OF WORK Evolution of Plan of Study Hydrology ALASKA ENERGY AUTHORITY AEA ENGINEERING FEASIBILITY REPORT

2. SCOPE OF WORK Evolution of Plan of Study Hydrology ALASKA ENERGY AUTHORITY AEA ENGINEERING FEASIBILITY REPORT 2. SCOPE OF WORK 2.1. Evolution of Plan of Study The purpose of this feasibility study is to define all aspects of the Project in sufficient detail to support the State s decision process regarding project

More information

Lower Mattagami River Project

Lower Mattagami River Project Lower Mattagami River Project 2016 Canadian Consulting Engineering Awards Project summary Ontario Power Generation s (OPG) Lower Mattagami River (LMR) project, its largest hydro project in 40 years, added

More information

A Brief History of Dams in Iraq. The Case of Mosul Dam Presented to Al-Diwan, April 10, 2016 by Mosaid Al-Hussaini, Ph.D, PE

A Brief History of Dams in Iraq. The Case of Mosul Dam Presented to Al-Diwan, April 10, 2016 by Mosaid Al-Hussaini, Ph.D, PE A Brief History of Dams in Iraq The Case of Mosul Dam Presented to Al-Diwan, April 10, 2016 by Mosaid Al-Hussaini, Ph.D, PE Dams in General Definition of a Dam: A dam is a barrier made of soil, concrete

More information

Provided to help candidates understand the format and type of questions for the practitioner examination

Provided to help candidates understand the format and type of questions for the practitioner examination Document Control Information Document Details Document Name: Purpose of Document: Provided to help candidates understand the format and type of questions for the practitioner examination Document Version

More information

Wind Power Variations are exported

Wind Power Variations are exported 1 Wind Power Variations are exported Can we make better use of Danish wind energy? The installation of new wind turbines in Denmark has been seen as an essential step towards meeting the targets in climate

More information

California s Self-Generation Incentive Program: What Is the Consumer Response and Is the CAISO System Peak Load Being Impacted?

California s Self-Generation Incentive Program: What Is the Consumer Response and Is the CAISO System Peak Load Being Impacted? California s Self-Generation Incentive Program: What Is the Consumer Response and Is the CAISO System Peak Load Being Impacted? Patrick Lilly, Itron, Inc./RER Alan Fields, Itron, Inc./RER Brenda Gettig,

More information

Practical Strategies to Make Your Next Project Profitable

Practical Strategies to Make Your Next Project Profitable 55 th Annual TIAC Conference Practical Strategies to Make Your Next Project Profitable Matthew Nicholas Revay and Associates Ltd Toronto August 26, 2017 1 Profit in Construction 2 Profit In Construction»

More information

2010 Dodson Publications, Inc. Page 1 of 6 September 10, :27 AM

2010 Dodson Publications, Inc. Page 1 of 6 September 10, :27 AM Liability The Liability Implications of Pursuing LEED Certification by Jeffrey W. Cavignac, CPCU, ARM, RPLU, CRIS, president & principal, Cavignac & Associates (Editor s Note: Jeff Cavignac, CPCU, ARM,

More information

Effective Relations: Roles of Mayors, Councilmembers, and Appointed Officials

Effective Relations: Roles of Mayors, Councilmembers, and Appointed Officials : Roles of Mayors, Councilmembers, and Appointed Officials One of the most important aspects of effective government is defining, understanding, and accepting the appropriate roles of elected and appointed

More information

Transitioning from Manual Meter Reading/CMR to a Successful AMR Deployment. Ralph Kennedy, Vice President Utility Meter Services, Inc.

Transitioning from Manual Meter Reading/CMR to a Successful AMR Deployment. Ralph Kennedy, Vice President Utility Meter Services, Inc. Transitioning from Manual Meter Reading/CMR to a Successful AMR Deployment Ralph Kennedy, Vice President Utility Meter Services, Inc. Company Overview Asplundh Tree Expert Co. Parent (>28,000 Employees)

More information

Hydropower and Water Resources

Hydropower and Water Resources Hydropower and Water Resources Hydropower and Water Resources The development, planning, design, and construction of hydropower as well as large-scale irrigation schemes and special hydraulic structures

More information

COLD WEATHER AND HIGH ALTITUDE DAM CONSTRUCTION

COLD WEATHER AND HIGH ALTITUDE DAM CONSTRUCTION COLD WEATHER AND HIGH ALTITUDE DAM CONSTRUCTION CASE STUDY TWIN LAKES DAM ENLARGEMENT PROJECTS DANIEL JOHNSON, AECOM DAN HERTEL, ENGINEERING SOLUTIONS TED FELDSHER, AECOM PURPOSE / HISTORY Remove two dams

More information

Template for ToR for Transaction Advisory Services

Template for ToR for Transaction Advisory Services Template for ToR for Transaction Advisory Services Addendum 1 Prepared by Genesis Analytics 4 December 2013 PPP TRANSACTION ADVISOR TERMS OF REFERENCE Terms of reference for transaction advisor services

More information

Buying an Existing Business:

Buying an Existing Business: Buying an Existing Business: Pitfalls & Pointers BILL SEAGRAVES So you re considering buying an existing business. First of all, congratulations! This is a big step, and by many accounts, a smart decision.

More information

IMPORTANCE OF RELIABLE GEOTECHNICAL INVESTIGATION FOR SAFE AND ECONOMICAL FOUNDATION DESIGN OF CIVIL STRUCTURES

IMPORTANCE OF RELIABLE GEOTECHNICAL INVESTIGATION FOR SAFE AND ECONOMICAL FOUNDATION DESIGN OF CIVIL STRUCTURES IGC 2009, Guntur, INDIA Importance of Reliable Geotechnical Investigation for Safe and Economical Foundation Design of Civil Structures IMPORTANCE OF RELIABLE GEOTECHNICAL INVESTIGATION FOR SAFE AND ECONOMICAL

More information

STAY CLEAR, STAY SAFE

STAY CLEAR, STAY SAFE STAY CLEAR, STAY SAFE What you need to know about safety around dams, hydroelectric stations and surrounding waterways. Yukon Energy STAY CLEAR, STAY SAFE Yukon Energy is the company that makes most of

More information

WORKING WITH BC HYDRO GENERATION 10 YEAR CAPITAL PLAN

WORKING WITH BC HYDRO GENERATION 10 YEAR CAPITAL PLAN WORKING WITH BC HYDRO GENERATION 10 YEAR CAPITAL PLAN The main purpose of this document is to provide our suppliers insight into the upcoming Capital Plan at BC Hydro s dams and generating facilities.

More information

PPPs in the transport sector Anthony Pearce

PPPs in the transport sector Anthony Pearce PPPs in the transport sector Anthony Pearce Honorary Director General Who is doing PPPs? Why do PPPs? How to do PPPs Agenda 2007 transport projects 90 projects, involving investment commitments of US$25.4

More information

CD based Bid Management Training from Biz Guru Ltd The Missing Piece from the Bidding Process

CD based Bid Management Training from Biz Guru Ltd The Missing Piece from the Bidding Process CD based Bid Management Training from Biz Guru Ltd The Missing Piece from the Bidding Process Page 1 of 14 Biz Guru Ltd Taking you from Wish to Win! Key Benefits From Attending These Training Courses v

More information

İSPİR DAM AND HEPP (HYDROELECTRİC POWER PLANT) PROJECT

İSPİR DAM AND HEPP (HYDROELECTRİC POWER PLANT) PROJECT İSPİR DAM AND HEPP (HYDROELECTRİC POWER PLANT) PROJECT Brief Profile of the Project İspir Dam, the second dam of Upper Çoruh Watershed is planned to build on the downstream of Laleli Dam. The Project is

More information

William Cundiff. From: Sent: To: Cc: Subject: Attachments: Bill, Steve, Bob,

William Cundiff. From: Sent: To: Cc: Subject: Attachments: Bill, Steve, Bob, William Cundiff From: Sent: To: Cc: Subject: Attachments: neexpansion@aol.com Tuesday, September 28, 2010 12:10 PM wcundiff@douglasma.org szisk@douglasma.org; pbrown@brown-brown-pc.com; info@americanprowind.com;

More information

Water Resources. Associate Prof. Ahmed Moustafa Moussa Lecture -1 Lecture 4

Water Resources. Associate Prof. Ahmed Moustafa Moussa Lecture -1 Lecture 4 Water Resources By Associate Prof. Ahmed Moustafa Moussa Lecture -1 Lecture 4 High Aswan Dam Project 1. Location The High Aswan Dam (HAD) location was determined to fit the topographical features of the

More information

RETURN TO WORK Strategies for supporting the supervisor when mental health is a factor in the employee s return to work

RETURN TO WORK Strategies for supporting the supervisor when mental health is a factor in the employee s return to work ABSTRACT: Factors and strategies to help occupational health nurses assist in supporting the supervisor for return-to-work cases where the returning employee has experienced mental health issues. RETURN

More information

Diagnostic Report on Transparency, Citizen Participation and Accountability (TPA) in Supreme Audit Institutions (SAIs) of Latin America

Diagnostic Report on Transparency, Citizen Participation and Accountability (TPA) in Supreme Audit Institutions (SAIs) of Latin America Diagnostic Report on Transparency, Citizen Participation and Accountability (TPA) in Supreme Audit Institutions (SAIs) of Latin America TRANSPARENCY CITIZEN PARTICIPATION ACCOUNTABILITY The TPA Initiative

More information

Applied / Partially. Explanation / Compensating Practices. Not Applied. Chapter Principle Principle Description

Applied / Partially. Explanation / Compensating Practices. Not Applied. Chapter Principle Principle Description / Partially Chapter Principle Principle Description / Not IoDSA GAI Score Chapter 1 Principle 1.1 The Board provides effective leadership based on ethical foundation Chapter 1 Principle 1.2 The Board ensures

More information

Software Development Effort Estimation: Why it fails and how to improve it

Software Development Effort Estimation: Why it fails and how to improve it Software Development Effort Estimation: Why it fails and how to improve it Steria, June 2012 Magne Jørgensen Simula Research Laboratory & University of Oslo" About me! Scientific researcher at Simula Research

More information

What Makes a Good Employee? Human Resources Assignment

What Makes a Good Employee? Human Resources Assignment What Makes a Good Employee? Human Resources Assignment What Makes a Good Employee? You can find the answer to this question by reading the following true stories about employees who developed certain characteristics

More information

Techno-Economic Assessment Study Rogun HPP. Phase II Considerations. Riparian Consultations

Techno-Economic Assessment Study Rogun HPP. Phase II Considerations. Riparian Consultations Techno-Economic Assessment Study Rogun HPP Phase II Considerations Riparian Consultations July 2014 Engineering and Dam Safety Panel of Experts Presenters: R.Gill (Chair), L.Spasic-Gril, Prof. Dr. E. Todini

More information

Headquarters. Registered office. Via F.lli Ceirano, Cuneo (Cn) - Italia. Corso Dante, Cuneo (Cn) - Italia.

Headquarters. Registered office. Via F.lli Ceirano, Cuneo (Cn) - Italia. Corso Dante, Cuneo (Cn) - Italia. Foto - archivio E++ Headquarters Via F.lli Ceirano, 9 12100 Cuneo (Cn) - Italia Registered office Corso Dante, 10 12100 Cuneo (Cn) - Italia info@eplusplus.net Ph. +39 0171 413963 Fax +39 0171 414981 1

More information

Fifth Conference of the Latin America and the Caribbean Monitoring and Evaluation Network

Fifth Conference of the Latin America and the Caribbean Monitoring and Evaluation Network United States M&E Trends: Using Performance Information to Improve Results Fifth Conference of the Latin America and the Caribbean Monitoring and Evaluation Network John R. Pfeiffer U.S. Office of Management

More information

TTI Personal Talent Skills Inventory Sales Management version

TTI Personal Talent Skills Inventory Sales Management version TTI Personal Talent Skills Inventory Sales Management version John Demonstration File Opportunity for Talent 4-19-2006 Copyright 2004-2006. Target Training International, Ltd. and Dr. D. Mefford. INTRODUCTION

More information

Economics: Introduction

Economics: Introduction Economics: Introduction Study notes for the Introduction To Economics (section 1) and introduction to Miceconomics (section 2) By Nils Österberg for nilsnotes On HL paper two there are usually three out

More information

INNOVATION CLEAN IN FOCUS. Tesera Systems Inc. THIS ISSUE FEATURING

INNOVATION CLEAN IN FOCUS. Tesera Systems Inc. THIS ISSUE FEATURING CLEAN INNOVATION THIS ISSUE FEATURING Tesera Systems Inc. IN FOCUS A special publication prepared by CETAC-WEST with support from NRC-IRAP and the Government of Alberta 2 Delivering excellence by solving

More information

NATIONAL CAPITAL DISTRICT COMMISSION Office of the Governor Hon. Powes Parkop, MP P.O. Box 7270, Boroko. NCD CITY OF PORT MORESBY

NATIONAL CAPITAL DISTRICT COMMISSION Office of the Governor Hon. Powes Parkop, MP P.O. Box 7270, Boroko. NCD CITY OF PORT MORESBY NATIONAL CAPITAL DISTRICT COMMISSION Office of the Governor Hon. Powes Parkop, MP P.O. Box 7270, Boroko. NCD CITY OF PORT MORESBY Telephone : : : Facsimile : 3251091/3251092 City Hall 3240500 Tengdui Depot

More information

SANRAL DELIVERING TOWARDS ECONOMIC GROWTH IN SOUTH AFRICA. Presenter : Zandile Nene Project Manager : Design & Construction SANRAL : Eastern Region

SANRAL DELIVERING TOWARDS ECONOMIC GROWTH IN SOUTH AFRICA. Presenter : Zandile Nene Project Manager : Design & Construction SANRAL : Eastern Region SANRAL DELIVERING TOWARDS ECONOMIC GROWTH IN SOUTH AFRICA Presenter : Zandile Nene Project Manager : Design & Construction SANRAL : Eastern Region CONTENTS 1. SANRAL background 2. SANRAL current network

More information

Oversight of the Private Infrastructure Development Group

Oversight of the Private Infrastructure Development Group Report by the Comptroller and Auditor General Department for International Development Oversight of the Private Infrastructure Development Group HC 265 SESSION 2014-15 4 JULY 2014 4 Key facts Oversight

More information

Analysis of the application of the

Analysis of the application of the King III Report 1. Ethical leadership and corporate citizenship 1.1 The board should provide effective leadership based on an ethical foundation 1.2 The board should ensure that the company is and is seen

More information

The Orion Pre-Employment Assessment Program

The Orion Pre-Employment Assessment Program The Orion Pre-Employment Assessment Program The Role of Orion Assessments Identify critical workplace attitudes and behaviors rarely revealed in other prehire processes or interviews Provide assessment

More information

Analysis of the application of the 75 corporate governance principles as recommended in the King III report

Analysis of the application of the 75 corporate governance principles as recommended in the King III report King III report 1. Ethical leadership and corporate citizenship 1.1 The board should provide effective leadership based on an ethical foundation. 1.2 The board should ensure that the company is and is

More information

DEPARTMENT OF PUBLIC WORKS MANAGEMENT MANUAL ADOPTED BY THE BOARD OF PUBLIC WORKS, CITY OF LOS ANGELES BACKGROUND

DEPARTMENT OF PUBLIC WORKS MANAGEMENT MANUAL ADOPTED BY THE BOARD OF PUBLIC WORKS, CITY OF LOS ANGELES BACKGROUND DEPARTMENT OF PUBLIC WORKS MANAGEMENT MANUAL Personnel Directive Subject: LEAVES OF ABSENCE PERSONAL AND TO ACCEPT OUTSIDE EMPLOYMENT ADOPTED BY THE BOARD OF PUBLIC WORKS, CITY OF LOS ANGELES June 20,

More information

Update Ituango Hydrolectric Project. June 6 th, 2018

Update Ituango Hydrolectric Project. June 6 th, 2018 Update Ituango Hydrolectric Project June 6 th, 2018 Location of Main Civil Works and Contingency GEOLOGICAL CONTINGENCY ZONE DEPOSIT ZONE LANDSLIDE ENTRY PORTAL DIVERSION TUNNELS LANDSLIDE SPILLWAY Capacity

More information

personal injury, employment law, and general civil litigation.

personal injury, employment law, and general civil litigation. personal injury, employment law, and general civil litigation. Micah Longo, a highly respected South Florida injury and civil trial lawyer, decided to partner with White Shark Media because he was not

More information

Dominion Virginia Power and Clean Power Plan Costs: A brief review of the Dominion s 2015 Integrated Resource Plan compliance cost estimates

Dominion Virginia Power and Clean Power Plan Costs: A brief review of the Dominion s 2015 Integrated Resource Plan compliance cost estimates Dominion Virginia Power and Clean Power Plan Costs: A brief review of the Dominion s 2015 Integrated Resource Plan compliance cost estimates by William Shobe Center for Economic and Policy Studies and

More information

Appendix A: Outline of Construction Management Functions /Roles for each phase of the project (source: Construction Management Association of America)

Appendix A: Outline of Construction Management Functions /Roles for each phase of the project (source: Construction Management Association of America) Appendix A: Outline of Construction Management Functions /Roles for each phase of the project (source: Construction Management Association of America) 108 Appendix B: Questionnaire 109 CONSTRUCTION MANAGEMENT

More information

The Environment and Oberlin: An Update

The Environment and Oberlin: An Update The Environment and Oberlin: An Update Page 4 In 1995, President Nancy Dye authorized planning to construct a 10,000-square-foot, $2.5 million environmental studies center that would be a model of ecological

More information

STATIC ALTERNATING CYCLIC HORIZONTAL LOAD TESTS ON DRIVEN

STATIC ALTERNATING CYCLIC HORIZONTAL LOAD TESTS ON DRIVEN STATIC ALTERNATING CYCLIC HORIZONTAL LOAD TESTS ON DRIVEN STEEL PIPE PILES OF FOUNDATIONS FOR HIGHWAY BRIDGES Kouichi TOMISAWA, Civil Engineering Research Institute of Hokkaido, Japan Satoshi NISHIMOTO,

More information

Analysis of the application of the 75 corporate governance principles as recommended in the King III Report

Analysis of the application of the 75 corporate governance principles as recommended in the King III Report the King III Report 1. Ethical leadership and corporate citizenship 1.1 The board should provide effective leadership based on an ethical foundation. 1.2 The board should ensure that the company is and

More information

The FIDIC accredited Advanced Module 1A training in Russian in Almaty (Kazakhstan): The Practical Use of FIDIC Conditions of Contract

The FIDIC accredited Advanced Module 1A training in Russian in Almaty (Kazakhstan): The Practical Use of FIDIC Conditions of Contract The FIDIC accredited Advanced Module 1A training in Russian in Almaty (Kazakhstan): The Practical Use of FIDIC Conditions of Contract 88 Important Issues 26 April, 2018-08:30 to 27 April, 2018-17:00 Type:

More information

Grupo Unidos por el Canal. Design & Construction 3rd Set of Panama Canal Locks A Contractors Perspective

Grupo Unidos por el Canal. Design & Construction 3rd Set of Panama Canal Locks A Contractors Perspective Grupo Unidos por el Canal Design & Construction 3rd Set of Panama Canal Locks A Contractors Perspective PIANC London 28 th October 2013 Michael Fitzsimons 1 2012 turnover Euro 2.1 billion What we do Jan

More information

Inspire. Educate. Unite.

Inspire. Educate. Unite. Cogent Project Management 12 May 2017 Mission + Purpose Cogence (Latin) To drive together or Thinking that is well organized The purpose of the Alliance is to bring Owners and Developers, Architects and

More information

Ingula Pumped Storage Scheme: Project Management Case Study

Ingula Pumped Storage Scheme: Project Management Case Study Ingula Pumped Storage Scheme: Project Management Case Study Colin Logan Project Manager Gibb Engineering & Science South Africa BRAAMHOEK CONSULTANTS JOINT VENTURE Definition of Project Management Planning,

More information

TECHNICAL SPECIFICATIONS OF LAYING OF UNDER GROUND POWER CABLE FOR TRANSMISSION LINE

TECHNICAL SPECIFICATIONS OF LAYING OF UNDER GROUND POWER CABLE FOR TRANSMISSION LINE GUJARAT ENERGY TRANSMISSION CORPORATION LTD. Sardar Patel Vidyut Bhavan, Race Course, Vadodara: 390 007 TECHNICAL SPECIFICATIONS OF LAYING OF UNDER GROUND POWER CABLE FOR TRANSMISSION LINE GETCO/E/TS LUC058/R1

More information

sector Anthony Pearce Honorary Director General

sector Anthony Pearce Honorary Director General PPPs in the transport t sector Anthony Pearce Honorary Director General Who is doing PPPs? Why do PPPs? How to do PPPs Agenda 2007 transport projects 90 projects, involving investment commitments of US$25.4

More information

Top 10 Areas for Productivity Improvement on Alberta Mega Oil Sands Construction Projects

Top 10 Areas for Productivity Improvement on Alberta Mega Oil Sands Construction Projects Top 10 Areas for Productivity Improvement on Alberta Mega Oil Sands Construction Projects George F. Jergeas PhD, PEng Professor of Project Management, University of Calgary October 24, 2012: BREAKOUT:

More information