Jet Grouting Experience at Posey Webster Street Tubes Seismic Retrofit Project

Size: px
Start display at page:

Download "Jet Grouting Experience at Posey Webster Street Tubes Seismic Retrofit Project"

Transcription

1 Jet Grouting Experience at Posey Webster Street Tubes Seismic Retrofit Project Umakant Dash 1, Ph.D., P.E., Thomas S. Lee 2, P.E., G. E., and Randy Anderson 3, P.E. Abstract This paper summarizes the construction experience of a seismic retrofit project for the Posey and Webster Street Tubes near Oakland, California. The Posey and Webster Street Tubes serve as the main tunnels for the California Route SR 722 along the city streets connecting cities of Alameda and Oakland. The retrofit work consisted, among other things, jet grouting and chemical grouting of the soils supporting the tubes. The primary purpose of the grouting work was to strengthen and densify the soils immediately surrounding the tubes to avoid liquefaction of the soils and loss of support for the tubes during major earthquakes with magnitude of M-7.5 or greater. Some of the criteria used for measurement of success of the work consisted of testing the soils after grouting. The tests included density, unconfined compressive strength field permeability tests and visual inspection of the grouted columns. Several construction difficulties were encountered during jet grouting. This paper summarizes materials, equipment, soil and groundwater conditions, grouting operation, rate of production, costs, and time requirements for jet grouting operation at Posey and Webster Street Tube Joint No.1. The paper provides a summary of the experience gained from the jet grouting operation and presents conclusions and recommendations useful for similar applications. Introduction In 1928, the Posey Immersed Tube, designed by the late George Posey, Alameda County engineer, was constructed between the city of Alameda and Oakland by sinking precast tunnel segments in a dredged trench, aligning them accurately and connecting them underwater. The so called trench system, a revolutionary construction method seven decades ago, was used in building the tunnel. It was the first pre-cast reinforced concrete immersed-tunnel with a bituminous coating in the United States and the longest in the world at that time. For 35 years the Posey Tunnel, has served two-way traffic across the Oakland Estuary. During 1962, approximately 30,000 vehicles a day passed through this tunnel. In 1962, the Webster Street Immersed Tube was designed, financed and constructed by the California Department of Transportation. The tunnel was planned to relieve the Posey Tunnel traffic congestion. The trench construction system similar to 1 Transportation Engineer, Caltrans, 801, 12 th Street, Sacramento, CA 2 Senior Professional Associate, Parsons Brinckerhoff Quade & Douglas, Inc., nd Street, Suite 700N, San Francisco, CA 3 Project Manager, Caltrans, 801, 12 th Street, Sacramento, CA

2 Posey Tunnel was also used in building the Webster Street Tube. Figure 1 shows the locations of the two tubes spanning between Oakland and Alameda, California. Figure 2 shows a cross section of the tube with simplified subsurface conditions. Figure 1 Locations of Posey and Webster Street Tubes, Oakland-Alameda, California Figure 2 Simplified Subsurface Conditions of the Tubes The primary seismic retrofit for the two immersed tubes is the ground improvement of the soils immediately surrounding the tubes. The ground improvement work was required to prevent the immersed tubes from floating in the event the backfill soil liquefied during the maximum design M-7.5 earthquake (Lee, el., 2002). The ground improvement work was tested under a demonstration project which was a separate part of the main project. During the Demonstration Project, field and laboratory tests were conducted on the improved soil (Parsons Brinckerhoff, 2001). In addition to ground improvement, the secondary retrofit work was the releasing of tube joints to reduce the high tensile stresses that could rupture or seriously crack the tubes. During construction, many unexpected soil conditions were uncovered. For example, very soft clayey soils to loose sandy soils were encountered at Joint No.1 of the two tubes, each of which was connected to a pile-supported portal building in Alameda,

3 California. In addition, there was a blow out on the ground during excavation of the east cofferdam of Webster Street Joint No. 1, where sand was running into the cofferdam after the soil was excavated to a depth of about 35 feet inside the cofferdam. Concern was raised as to potential subsidence of the tube after Joint No. 1 was completely released or cut loose to allow for insertion of flexible membrane at the joint. This prompted to the need of stabilizing the soft and loose foundation soils by means of jet grouting. Jet Grouting For an immersed tube tunnel to move upward in a liquefied soil mass, the liquid must be able to flow under the tube as it moves up (Figure 3). If this mechanism is prevented, the tube would not float, even if the soil under the tube were to liquefy. Thus was born the isolation principle (Schmidt, et. al, 1998). The space under the tubes can be isolated from the surrounding material by building isolation walls, consisting of material that would not liquefy and that would withstand differential pressure from the liquefied mass. The isolation walls can be sheet piles or any impermeable systems such as jet grouted columns. Due to close proximity to the tubes, jet grout columns were selected to serve as the isolation walls adjacent to the tubes at Joint No. 1 (Figure 4). Two methods of jet grouting were employed as the ground improvement at Joint No.1 of both tubes. The jet grout columns at Joint No.1 of the Webster Street Tube were constructed by means of a single-fluid system using grout as a single fluid to cut and mix the in situ soil to form a jet grout column. Those at Joint No. 1 of the Posey Tube were installed using a double-fluid system using air and grout to construct the jet grout columns. The jet grout columns at Webster Street Tube Joint No. 1 were installed first and then followed by those at the Posey Tube. The reason two different jet grouting systems were used was because of the slow progress of the jet grout operation using a single fluid system, which will be discussed in more details in a subsequent section. Figure 3 Flotation of the Tube under Uplift Pressure (Schmidt, et al., 1998) Webster Street Tube Joint No. 1

4 The isolation walls at Joint No. 1 needed to have a minimum width of 6 feet. With the use of a single-fluid system, the maximum diameter of a jet grout column was found to be 2.5 feet based upon experience at the adjacent cofferdam construction where an impermeable barrier slab was formed at the base of the cofferdam 35 feet below the ground surface. Based on the as-built drawing at Joint No. 1, the tube segment immediately north of the Alameda portal building was founded on a pile-supported tremie concrete platform. However, a 15-ft section between the center of the collar of Joint No. 1 and the tube segment was founded on loose to very loose silty fine sand over a tremie concrete unsupported by any piles. The blowout on the ground surface was believed to have created voids within the loose sand layer immediately beneath the tube. For this reason, two areas, Zone 1 and Zone 2 were developed with different rows of jet grout columns (Figure 5). At Zone 2 area, because of the presence of the pile-supported tremie concrete platform below the tube, the jet grout columns at Zone 2 area were driven 1-ft into the tremie concrete at an average depth of 42 feet. In Zone 1, four rows of jet grout columns were constructed adjacent to the tube (Figure 5). Two of the four rows were vertical columns and the other two were inclined columns at 65 to 75 with the horizontal; all four columns were extended to a depth of 85 to 90 feet (Figure 6). Additionally, four chemical grout holes on each side of the tube in Zone 1 were also constructed. The loose sand immediately below Joint 1 was to be densified by two rows of chemical grout columns constructed inside the tube. As of the time of writing this paper, all jet grout columns were completed and the eight chemical grout holes with pvc pipes were installed in place and were ready for chemical grout injection. Backfill Jet Grout Loose Sand Figure 4 Jet Grout Cut-off Walls (Schematic Diagram) Construction of the jet grout columns was carried out by means of a single fluid system to depths varying from 38 ft to 95 ft below ground surface. This system is the simplest due to the sole dependence of the high velocity grout jet stream to cut, remove, and mix the in situ soil in place. It also gives the smallest diameter grout column ranging from 18 inches to 36 inches. For the same amount of cement injected per volume treated, this system produces the strongest soilcrete (a hybrid of grout and soil). Table 1 below shows the injection parameters of the single fluid system. At least one column spacing was allowed for constructing two adjoining columns. A total of 71 vertical columns and 31 inclined columns were installed. On the average, the contractor constructed the jet grout column at a rate of approximately 90 feet per day. The pace of construction was very slow due to the following reasons:

5 1. The rig did not have a long mast to hold the string of rods up to 90 feet long, which had to be assembled section by section during drilling and broken down section by section during grouting operation; 2. The presence of obstructions slowed down the construction operation; such obstructions were not disclosed in the as-built drawings. Obstructions consisted of tremie concrete, steel bars, wood chips, boulders, bricks, etc; 3. Wearing down of the drilling bit due to extremely hard obstructions slowed down the installation pace; 4. Breakdown of equipment; and 5. The work was done under a force account. There were neither stimuli nor incentives for the contractor to speed up the pace of construction by altering methods of drilling/grouting or changing drilling equipment and tools. Not only was the operation slow, but also construction of the jet grout columns was expensive with the single fluid system method. For example, a column constructed to a depth of 80 feet consumed 24 tons of cement (with withdrawal rate of 10 inches/minute or 29,000 liters of grout (cement:water ratio = 1:1). The spoil return was observed to be very viscous and thick, indicating a substantial volume of grout was wasted. Accordingly, a total of 1,770 tons of cement were used for constructing 104 columns. Instrumentation Program A pair of ground settlement devices were installed over Joint No. 1 to measure movements of the tube during construction of the production columns. The readings were taken daily by the contractor and reported to the field inspector for reference.

6 Figure 5 Layout Plan of Jet Grout Columns at Webster Street Tube Joint No. 1 Zone 2 Zone 1 Figure 6 Cross Section of Jet Grout Columns in Zone 1 Adjacent to the Webster Street Tube Joint No. 1 Table 1 Jet Grout Parameters for Webster Street Tube Joint No.1 Injection Parameter Column Withdrawal Rate Nozzles Water:Cement Ratio Cement Grout Pressure Cement Grout Flow Rate Grout Volume Rotational Speed Parameter Value inches/minute mm 1:1 by weight 6,860 psi (470bars) 78 gal/minute 94 gal/ft rpm

7 Figure 7 Cross Section of Jet Grout Columns in Zone 2 Adjacent to the Webster Street Tube Joint No. 1 Ground Heave Two longitudinal cracks developed at the joint between the Portal Building and the first tube segment next to the Portal Building. A major longitudinal crack opened up as a hair-line crack since the blowout occurred in July 2001, growing bigger with time during

8 grouting operations. The cracks opened and closed during the day possibly due to the fluctuations of the tide and ebb during the day. The total cumulative crack opening was measured to be about 0.75 inches. The crack opening was found to be mainly related to the jet grouting operations which caused ground heave at Joint No. 1. Despite the crack opening at the joint, no cracks of major concern appeared on the ground surface. Posey Tube Joint No. 1 Due to the slow construction pace of the production jet grout columns using a single fluid system, a double fluid system was used for the jet grout columns at Posey Tube Joint No. 1. The double fluid system encapsulates simultaneous injection of high velocity grout within a cone of compressed air, allowing better cutting efficiency of the slurry grout. The system is capable of creating columns at least twice as large as those made by the single fluid system. The increased size of the column was ascribed to: 1. Compressed air acted as a buffer between the jet stream and any ground water present. Therefore, the jet stream could cut at least twice as far in water as compared to when no compressed air was used. 2. Soil cut by the jet is prevented from falling back into the jet stream, thus cutting down on energy lost through the turbulent action of the cut soil. 3. Cut soil was more efficiently removed from the area of cutting by the bubbling action of the compressed air lifting soil debris to the surface. Just like any systems, there are three drawbacks of the double fluid system. The first one is that the soilcrete ( a hybrid of soil and grout) has a high air content, rendering a lower unit weight and strength compared to the single fluid system. Secondly, the addition of compressed air requires pathway, which consists of an inner and outer set of rods with an annulus of about 5 mm. This pathway may become clogged during operation and cannot be used under limited overhead room where the drill rods have to be uncoupled. Thirdly, the amount of air used is much that it could easily lift overlying soils, thus causing substantial ground heave as compared to the single fluid system. Because of a bigger column that could be created, a total of 18 jet grout columns were needed to form the cut off impermeable walls at Posey Tube Joint No. 1, as shown on Figure 7. To minimize uncoupling and re-coupling drilling rods, the drilling rig mast was lengthened to 50 feet. This saved tremendous of time in breaking and assembling the rods during construction. Each jet grout column was drilled to a depth of about 95 feet and jet grouted to the design elevations as shown in Figure 7. Monitoring of the jetting parameters during the performance of jet grouting works was accomplished by means of a real-time instrumentation recorder attached to the drill rig. The jet grouting injection parameters used are presented in Table 2 below. Return flow of the injection was collected via an 8-in plastic pipe to a dumper. Once the injection monitor reached the proposed top of the jet grout column, the high pressure jet was deactivated and the outer casing was removed to the surface.

9 Table 2 Jet Grout Parameters for Posey Tube Joint No.1 Injection Parameter Column Withdrawal Rate Nozzles Water:Cement Ratio Cement Grout Pressure Cement Grout Flow Rate Grout Volume Air Pressure Air Flow Rate Rotational Speed Parameter Value 7.90 in/minute mm 0.8:1 by weight 6,100 psi (420 bars) 76 gal/minute 115 gal/ft 145 psi (10 bars) 60 liter/min 9 rpm Figure 7 Layout of Jet Grout Columns at Posey Tube Joint No. 1 Instrumentation Program An instrumentation program was implemented to monitor the ground heave and the tube differential movement during the jet grouting operation. The program consisted of installing two ground settlement devices over Joint No. 1, 6 settlement points at locations in the vicinity of the production jet grout columns, and 6 tiltmeters installed inside the tube at Joint No. 1. The instrumentation points were monitored daily during construction of the jet grout columns by the contractor and site inspector.

10 Ground Heave A longitudinal crack of 0.1 inch developed at the joint between the Portal Building and the tube segment during construction of the first jet grout column (B-3) at the east side of the Posey tube. This crack grew bigger with time during grouting operations. The cracks appeared to open and close during the day possibly due to the fluctuations of the tide and ebb. The total cumulative crack opening was measured to be about 0.3 inches. The crack opening was found to be mainly related to the jet grouting operations, which caused ground heave at Joint No. 1. In addition to the crack at Joint No. 1, cracks of width up to 0.1 inch were observed on the unpaved ground and pavement outside the jet grouting area. This was believed to be due to a large volume of air pumped into the ground, thereby lifting the overlying soil. No damage of existing utility lines was noted or reported. The ground heave as measured by the settlement points averaged at 0.02 inch. Quality Control Testing A significant factor in the successful application of jet grouting on the project was the incorporation of an adequate quality control (QC) and verification testing program. A well planned and executed program would result in early identification of potential problems and allowed the contractor to make proper modifications to deal with these problems. The QC program was implemented in two phases: 1). Pre-production phase, and 2). Production phase. The Owner, engineer and contractor were involved in implementing these procedures. Webster Street Tube Joint No. 1 Pre-Production QC Work Prior to the production column installation, the Owner had a contract with the contractor to construct a base jet grout slab at the bottom of the two cofferdams at Joint No. 1 using the single fluid system. There was no specific requirement for constructing any test columns for subsequent exposure for their overall structural integrity. Excavation of the cofferdam to its proposed bottom exposed the jet grout columns, which were of diameter about 2.5 feet. Production QC Work A manual check of the injection parameters, e.g., rate of rod withdrawal, grouting pressure, air pressure, cement water ratio, grout volume, was periodically made by the field inspector. This permitted the engineer and the contractor to have a complete quantitative documentation of each column to be constructed in the prescribed manner. The verticality of the hole was checked manually by a level during construction of the jet grout column.

11 Post-Production QC Work The post-production QC work included laboratory strength and unit weight testing of core samples taken from the hardened columns and in situ packer permeability tests performed within the cored columns. In addition, a test pit was excavated to a depth of about 10 feet below ground surface to expose the production jet grout columns. The exposed columns were observed to be composed of a row of at least 6-ft wide continuous, very tight, strong jet grout columns immediately next to the tube. This is in compliance with the design objective. Remediation Work In areas where the QC results showed deviation from the design requirements, remediation works were implemented. Remediation in these cases consisted of chemical grout and cement grout injections into areas depleted of soilcrete. Posey Tube Joint No. 1 Pre-Production QC Work As part of the construction contract, a pre-production test program was implemented prior to installing the production columns using the double-fluid system. The test program consisted of two test columns constructed to a depth of 15 feet below ground surface. The test columns were installed using actual production parameters and equipment, and then exposed for visual inspection to determine the suitability of the jet grout columns and establish the required injection parameters and procedures. Production QC Work The production QC work consisted of real time data collection and monitoring of the entire grouting operation, plus monitoring of the verticality of the jet grouted column. A real time data collection system monitored the mixing, pumping, drilling and grouting works for each completed column. The collected data was downloaded to an on-site mini-computer and condensed into a series of graphs, which plotted the injection parameters in relation to time and depth. This permitted the engineer and the contractor to have a complete quantitative documentation of each column, and allowed verification that each jet grout column was constructed in the prescribed manner. In addition, manual check of the injection parameters, e.g., rate of rod withdrawal, grouting pressure, air pressure was periodically made by the field inspector. The verticality of the hole was checked manually by a level during construction of the jet grout column. Post-Production QC Work As part of the contract, the post-production QC work included laboratory strength and unit weight testing of core samples taken from the hardened columns and in situ packer

12 permeability tests performed within the cored columns. At the time of preparing this paper, such work has not been performed. Test Results Webster Street Tube Joint No. 1 A total of eleven (11) unconfined compressive strength tests were conducted on the core samples. The test results exceeded the specified minimum strength of 600 psi. The unconfined compressive strength of the jet-grouted soil ranged from 650 to 9000 psi with an average of 3,040 psi. No relationship between strength and soil type was observed due to the heterogeneous nature of the soil conditions at the site. However, where the in situ soil is of gravelly nature, it appears the strength of the soilcrete became much higher (in excess of 3,000 psi). A total of 6 permeability tests were performed. The permeability ranged from 5 x 10-5 cm/sec to 4 x 10-6 cm/sec. The results of these tests, coupled with the exposure of the production jet grout columns at the site, indicated that the tight overlap of the jet grouted columns is generally effective. Posey Tube Joint No. 1 The field and laboratory testing were not carried out at the time of writing this paper and hence no data can be presented. Evaluation Two different jet grouting systems; single fluid (grout) and double fluid (grout/air) were employed in constructing the cut off walls at Posey and Webster Street Tube Joint No. 1. Both systems achieved the minimum 6-ft width of the cut off walls specified in the contracts. However, jet grout columns using the single fluid system required a lot more rows of columns than the double fluid system to create the specified minimum 6-ft wide cut off wall, as a result of which the associated construction cost with the single fluid system became very expensive. For example, it took approximately 10 weeks to finish the 104 single fluid jet grout columns as compared to 4 weeks for the 18 double fluid jet grout columns. Because of more columns needed to be constructed, it required a lot more grout to construct the cut off wall for the single fluid system than the double fluid system. Construction of the jet grout columns at both tubes encountered a lot of obstructions which were not disclosed from the as-built drawings except the tremie concrete. The obstructions retrieved consisted of wood chips, steel bars, red bricks, steel coils, tremie concrete, etc. These obstructions, coupled with the need of breaking and reassembling strings of rods made the single fluid system a time consuming operation. Subsequent extension of the mast length of the drill rig (to 50 feet) for the double fluid system at the Posey Tube Joint No.1 did increase the production rate, thereby minimizing overall construction costs.

13 Continuous return of jet grout spoil was generally observed during both singlefluid and double-fluid jet grouting. There were a few occasions where grout spoil did not return to the ground surface such as in the first six inclined columns constructed in Zone 1 at the west side of the Webster Street Tube. No such loss of spoil return was subsequently noted at the second rows of jet grout columns in Zone 1 at the Webster Street Tube. It was believed that the grout could have filled the voids at the localized area in Zone 1. Based on the grout-take records, 44,000 liters of grout were pumped in the first inclined hole at A-1, and much less grout was needed for the subsequent inclined columns in Zone 1 of the Webster Street Tube Joint No.1. The grout spoil return became more viscous and thicker during construction of the final two rows of the jet grout columns in Zone 2 at the Webster Street Tube Joint No.1. This suggested that the ground did not take more grout during jet grouting operation in these two last rows. It was then inferred that a water-tight, continuous, cut off wall was in place next to the tube, which was confirmed by subsequent testing and inspection of the jet grout columns. A total of eight cased chemical grout holes were drilled to a depth of about 48 feet at an inclined angle of about 65 degrees in Zone 1 of the Webster Street Tube Joint No. 1. Each of these holes was inserted with a pvc grout tube/tube-a-manchette at the end and each filled with cement grout. The purposed of pumping chemical grout in Zone 1 was to stabilize the localized loose sand immediately below the tube, which could not be stabilized by the jet grout columns. At the time of writing this paper, no chemical grout was pumped into the specified locations. Control of spoil return was handled by two methods. At the Webster Street Tube Joint No.1, the spoil return was contained in a small trench which was led to slurry pit and pumped to a dumpster. The spoil from the jet grouting at the Posey Tube Joint No. 1 was controlled by suing a diverter at the collar of each hole, which was connected to a section of casing installed to a depth of about 20 feet. The spoil was channeled into a pump (with a small container) from the diverter and pumped to a tank. The results of the unconfined compressive strength tests indicated that the strength of the soilcrete is at least 600 psi as is required in the specification. Packer testing conducted in the field showed that the jet grout columns are in general water tight. Good recovery of core runs was obtained in all the four cored holes performed. However, coring through the jet grout column A-1 (an inclined column) west of the Webster Street Tube Joint No. 1 encountered a small void (18 deep) each at depth intervals of feet, and feet. This is believed that the formation of such voids is due to the presence of obstructions at those intervals. In addition, no recovery was obtained from the inclined depth of 86 to the bottom of the column at an inclined depth of 95 feet. A closer look at the geologic profile at Column A-1 indicated that the interface between the overlying Bay Mud and the dense sand is at about El. 70, about 78 feet below, which is the same as the inclined depth of 86. The missing of the jet grout column from that depth downward is believed to be ascribed to washing away of the grout by the artesian pressure at the interface of the Bay Mud and the dense sand.

14 Conclusions A cut off wall consisting of jet grout columns can be constructed along the two sides of Posey and Webster Street Tube Joint No. 1 using either a single or double fluid system. The jet grout wall is in general water tight, but localized leakage at the obstructions should be expected. A jet grout wall of width at least 6-ft could be constructed by a double-fluid system using grout and air to construct the columns as revealed from exposure of the jet grout test columns. For the single fluid system, a jet grout column of up to about 2.5 feet in diameter can be constructed. To create a minimum of 6-ft wide jet grout wall at the Webster Street Tube, multiples of rows were needed for the single fluid system. This resulted in longer construction time and expensive construction costs. Encountering obstructions during construction of jet grout columns would slow down the pace of jet grouting operation. It could not guarantee the overall watertightness of the columns in place. The rate of rod withdrawal during jet grouting is the key parameter to control the size of the jet grout columns. For our project, the withdrawal rate for the double fluid system was 7.9 inches per minute for a minimum 6-ft diameter jet grout column. For the single fluid system, a 2.5-ft diameter jet grout column can be constructed using 10 inches per minute rate of withdrawal of the rod. Construction of large diameter (greater than 6 feet), deep (over 40 ft) jet grout columns should better be done by means of double fluid system rather than the single fluid system from economics point of view. Requirement of a long mast (at least 50 feet) to hold a long string of rods is essential to minimize the need of coupling and uncoupling strings of rod during jet grouting operation. Construction of deep jet grout columns should call for the use of one long string of rods to form the jet grout columns. Ground heave could be a concern for shallow jet grout columns (with less a few feet of overburden over the top of the jet grout column) if double fluid system is used because of the substantial amount of air pumped into the ground, lifting the overlying soil mass. Quality control is a significant factor in the successful application of jet grouting. Multiple phase QC program is recommended. A real-time data collection and monitoring system can be used to control the injection parameters and evaluate the need for any remedial measures. A field trial is essential for each jet grouting project. The pre-production trial assists in evaluating the adequacy of the equipment to be used and selection of the appropriate injection parameters. Pre-qualification of jet grouting contractors is necessary. Detailed prequalification questionnaires should be included in the bidding documents. Close cooperation and partnering between the owner, engineer, and contractors are crucial for the successful implementation of a jet grout project.

15 Acknowledgement The authors are thankful to the California Department of Transportation for the support of publishing this paper. The conclusions of this paper reflect the views of the authors, but do not necessarily reflect official views of the State of California. This paper does not constitute a standard, specification, or regulation. References Lee, T. S., Jackson, T., and Anderson, R. (2002). Innovative Designs of Seismic Retrofitting The Posey & Webster Street Tubes, Oakland/Alameda, California. 3 rd National Seismic Conference, Portland, Oregon, April 30-May 2. Parsons Brinckerhoff Quade & Douglas, Inc. (2001). Technical Report on Demonstration Program, Posey Webster Street Tubes Seismic Retrofit Project, January. Schmidt, B., Hashash, Y., and Stimac, T. (1998). US Immersed Tube Retrofit Tunnel and Tunnelling International Magazine; November

Compaction and Jet Grouting

Compaction and Jet Grouting Compaction and Jet Grouting Alan Ringen, PE Senior Vice President Breakthroughs in Tunneling Short Course August 16, 2017 Grouting Principles Geotechnical Grouting: The injection of pumpable fluid materials

More information

Soil Improvement by Compaction Grouting

Soil Improvement by Compaction Grouting CITY AND COUNTY OF DENVER ENGINEERING DIVISION Wastewater Capital Projects Management Standard Construction Specification 31-3223.12 Soil Improvement by Compaction Grouting Part 1 - General 1.01 Introduction

More information

JET GROUTING Implenia Spezialtiefbau GmbH

JET GROUTING Implenia Spezialtiefbau GmbH JET GROUTING Implenia Spezialtiefbau GmbH Robert Bosch Straße 25 D-63225 Langen Phone: +49 6103 988 345 Fax: +49 6103 988 277 Email: info.spezialtiefbau@implenia.com www.foundation-engineering.implenia.com

More information

VERTICAL BARRIERS SLURRY TRENCH BARRIERS: excavation equipment. prof. E. Fratalocchi Environmental Geotechnics Waste and polluted sites containment

VERTICAL BARRIERS SLURRY TRENCH BARRIERS: excavation equipment. prof. E. Fratalocchi Environmental Geotechnics Waste and polluted sites containment VERTICAL BARRIERS SLURRY TRENCH BARRIERS: excavation equipment VERTICAL BARRIERS SLURRY TRENCH BARRIERS: excavation equipment rotary drill hydro-mill backhoe Clamshell + Kelly bar VERTICAL BARRIERS SLURRY

More information

ITEM 416 DRILLED SHAFT FOUNDATIONS Materials. All materials shall conform to the requirements of the pertinent items as follows:

ITEM 416 DRILLED SHAFT FOUNDATIONS Materials. All materials shall conform to the requirements of the pertinent items as follows: ITEM 416 DRILLED SHAFT FOUNDATIONS 416.1. Description. This Item shall govern for the construction of foundations consisting of reinforced concrete drilled shafts and/or nonreinforced concrete drilled

More information

Earth Mechanics, Inc. Geotechnical & Earthquake Engineering

Earth Mechanics, Inc. Geotechnical & Earthquake Engineering DATE: August 31, 2000 Earth Mechanics, Inc. Geotechnical & Earthquake Engineering TECHNICAL MEMORANDUM EMI PROJECT NO: 99-136 PREPARED FOR: COPIES: PREPARED BY: Tayfun Saglam / Parsons Brinckerhoff Juan

More information

SPECIAL CONDITIONS FOR HORIZONTAL AUGER BORING (HAB) October, 2006

SPECIAL CONDITIONS FOR HORIZONTAL AUGER BORING (HAB) October, 2006 Michigan Department Of Transportation 3703B (11/06) 1 Materials SPECIAL CONDITIONS FOR HORIZONTAL AUGER BORING (HAB) October, 2006 Page 1 of 5 1.1 Pipe - Pipe used in this method includes an external steel

More information

Grouting Bilfinger Spezialtiefbau GmbH

Grouting Bilfinger Spezialtiefbau GmbH Grouting Bilfinger Spezialtiefbau GmbH Goldsteinstrasse 114 D-60528 Frankfurt Phone: +49 69 6688-345 Fax: +49 69 6688-277 Email: info.spezialtiefbau@bilfinger.com www.foundation-engineering.bilfinger.com

More information

Construction Technology B (CON4313)

Construction Technology B (CON4313) 3 - Basement 1 Quick Revision 1.1 Problems arising from basement construction a. Excavation method. b. Surface and ground water control c. Lateral stability of basement excavation. d. Stability of adjoining

More information

Use of Jet Grouting in Challenging Infrastructure Renewal Situations in Hawaii

Use of Jet Grouting in Challenging Infrastructure Renewal Situations in Hawaii Use of Jet Grouting in Challenging Infrastructure Renewal Situations in Hawaii Reyn Hashiro 1, P.E., M. ASCE, Devin Nakayama 2, P.E. M. ASCE, and James Kwong 3, Ph.D., P.E., M. ASCE 1 Associate, Yogi Kwong

More information

1. All underground utilities under railroad tracks shall be encased in a larger pipe or conduit called the casing pipe.

1. All underground utilities under railroad tracks shall be encased in a larger pipe or conduit called the casing pipe. MTS Jack and Bore Design Criteria Note: For the purposes of this Design Criteria and subsequent Construction Notes, the term Jack and Bore is used generically to refer to a number of trenchless construction

More information

ITEM 481 MONOLITHIC REINFORCED CONCRETE BOX SEWERS

ITEM 481 MONOLITHIC REINFORCED CONCRETE BOX SEWERS AFTER FEBRUARY 1, 2011 ITEM 481 MONOLITHIC REINFORCED CONCRETE BOX SEWERS 481.1 Description. This specification shall govern for the construction of monolithic, reinforced concrete box sewers of the size,

More information

Shoring of Long Beach Main Pump Station utilizing Ground Improvement Methods, Long Beach, CA

Shoring of Long Beach Main Pump Station utilizing Ground Improvement Methods, Long Beach, CA Shoring of Long Beach Main Pump Station utilizing Ground Improvement Methods, Long Beach, CA Gabriel Carvajal, Project Manager, Condon-Johnson & Associates, Inc., 9685 Via Excelencia, Suite 106, San Diego,

More information

Civil Engineering Construction I (CBE5031)

Civil Engineering Construction I (CBE5031) Civil Engineering Construction I (CBE5031) Basement 1 1 Quick Revision 1.1 Problems arising from basement construction a) Excavation method. b) Surface and ground water control c) Lateral stability of

More information

SPECIFICATION FOR JET GROUTING

SPECIFICATION FOR JET GROUTING SPECIFICATION FOR JET GROUTING 1.0 GENERAL The Specialist Contractor shall construct jet grout columns of nominal diameter and spacing as specified in the drawing(s) to the requirements of the Contract.

More information

SECTION BORING AND/OR JACKING PIPE

SECTION BORING AND/OR JACKING PIPE 02910-1 of 6 SECTION 02910 BORING AND/OR JACKING PIPE 02910.01 GENERAL A. Description Boring and/or jacking pipe shall include, but not necessarily be limited to, furnishing and installing carrier pipe

More information

Figure (12.1) Foundation Grouting

Figure (12.1) Foundation Grouting Chapter 12 - Foundation Grouting 12. Foundation Grouting 12.1. Introduction: The construction of structures on weak ground often requires the soil to be improved in order to ensure the safety and the stability

More information

Multi-Institutional Academic Health Science & Research Center Evansville, IN

Multi-Institutional Academic Health Science & Research Center Evansville, IN SECTION 02370 AUGER CAST PILES PART 1 - GENERAL 1.1 SECTION INCLUDES: The work covered by these specifications consists of furnishing all labor, equipment and materials for the installation of auger cast

More information

Case Study. The Challenge. Deep Micropile Installation Under Existing Multistory Building

Case Study. The Challenge. Deep Micropile Installation Under Existing Multistory Building The Challenge The Owners of a former warehouse located in the vibrant tech start-up area south of Market St. in San Francisco made the decision to bring the building up to current earthquake standards

More information

INDEX FOR SPECIFICATIONS FOR JACKING CULVERTS THROUGH EMBANKMENTS SCOPE... 2

INDEX FOR SPECIFICATIONS FOR JACKING CULVERTS THROUGH EMBANKMENTS SCOPE... 2 INDEX FOR SPECIFICATIONS FOR JACKING CULVERTS THROUGH EMBANKMENTS 410. 1 SCOPE... 2 410. 2 DEFINITIONS 2.1 Tunneling and Jacking... 2 2.2 Tunneling... 2 2.3 Jacking... 2 410. 3 MATERIALS 3.1 General...

More information

4.5 GEOTECHNICAL, SUBSURFACE, AND SEISMIC HAZARDS

4.5 GEOTECHNICAL, SUBSURFACE, AND SEISMIC HAZARDS 4.5 GEOTECHNICAL, SUBSURFACE, AND SEISMIC HAZARDS This section discusses the geology, soils, seismicity, hazardous materials, and subsurface obstructions along Flower Street, and evaluates their potential

More information

Jet Grouting for Seepage Control at Lac Des Iles (LDI) Water Management Facility

Jet Grouting for Seepage Control at Lac Des Iles (LDI) Water Management Facility Jet Grouting for Seepage Control at Lac Des Iles (LDI) Water Management Facility Naresh Gurpersaud, P.Eng., M.ASCE, 1 Daniel Lees, P.Eng., 2 and Frank Hu, P.Eng. 3 1 Geo-Foundations Contractors, 302 Main

More information

CONSTRUCTION STANDARDS SECTION CS 3 TRENCH FOUNDATION, BEDDING AND BACKFILL

CONSTRUCTION STANDARDS SECTION CS 3 TRENCH FOUNDATION, BEDDING AND BACKFILL CONSTRUCTION STANDARDS SECTION CS 3 TRENCH FOUNDATION, BEDDING AND BACKFILL CS 3-01 GENERAL: A. The foundation, bedding and backfill for all trenches shall conform with the requirements of the City Standard

More information

SECTION 39 - MANHOLES TABLE OF CONTENTS 39-1 GENERAL PRECAST CONCRETE MANHOLES

SECTION 39 - MANHOLES TABLE OF CONTENTS 39-1 GENERAL PRECAST CONCRETE MANHOLES Section SECTION 39 - MANHOLES TABLE OF CONTENTS 39-1 GENERAL... 39-1 39-2 PRECAST CONCRETE MANHOLES... 39-1 39-2.01 Precast Concrete Storm Drain Manholes... 39-1 39-3 SADDLE MANHOLES... 39-2 39-3.01 Saddle

More information

Overburden Effect on the Axial Resistance of Instrumented CFA Piles. Knoxville, TN 37922, ph ,

Overburden Effect on the Axial Resistance of Instrumented CFA Piles. Knoxville, TN 37922, ph , 703 Overburden Effect on the Axial Resistance of Instrumented CFA Piles Timothy C. Siegel 1, M. ASCE, P.E., G.E., D.GE and Peter Faust 2 1 Principal Engineer, Dan Brown and Associates, PC, 1808 Northshore

More information

Ingenuity Offers a Solution to an Anomaly in a Bridge Support

Ingenuity Offers a Solution to an Anomaly in a Bridge Support Ingenuity Offers a Solution to an Anomaly in a Bridge Support CSDA Contractor Member Part of the Most Expensive Public Works Project in California History Walkway to the congested work platform. San Francisco

More information

SECTION WATERTIGHTNESS TEST FOR PLANT TANKAGE STRUCTURES

SECTION WATERTIGHTNESS TEST FOR PLANT TANKAGE STRUCTURES SECTION 01 48 00 - WATERTIGHTNESS TEST FOR PLANT TANKAGE STRUCTURES PART 1 - GENERAL 1.1 SCOPE OF WORK A. Furnish all labor, materials and incidentals required and perform tightness testing of water-containing

More information

Stabilization of Running Granular Soils in TBM Alignment with Sodium Silicate Grout

Stabilization of Running Granular Soils in TBM Alignment with Sodium Silicate Grout Stabilization of Running Granular Soils in TBM Alignment with Sodium Silicate Grout Brendan P. Harkins 1, E.I.T.; Dominic M. Parmantier 2, M. ASCE, P.E. 1 Project Engineer, Condon-Johnson & Associates,

More information

SECTION XXXXX AGGREGATE PIERS PART 1 - GENERAL

SECTION XXXXX AGGREGATE PIERS PART 1 - GENERAL SECTION XXXXX AGGREGATE PIERS PART 1 - GENERAL 1.1 RELATED DOCUMENTS: Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division 00 and Division

More information

SECTION 39 - MANHOLES TABLE OF CONTENTS

SECTION 39 - MANHOLES TABLE OF CONTENTS Section SECTION 39 - MANHOLES TABLE OF CONTENTS Page 39-1 GENERAL... 39.1 39-2 CONCRETE MANHOLES... 39.1 39-2.01 NOT USED... 39.1 39-2.02 Concrete Storm Drain Manholes... 39.1 39-3 SADDLE SEWER MANHOLES...

More information

STANDARD SPECIFICATION FOR MICROPILE CONSTRUCTION

STANDARD SPECIFICATION FOR MICROPILE CONSTRUCTION Section 67.0 Knoxville, Tennessee March 2013 1. Description STANDARD SPECIFICATION FOR MICROPILE CONSTRUCTION a) This work shall consist of constructing micropiles as shown on the Contract plans in accordance

More information

ITEM 432 TUNNEL CONSTRUCTION

ITEM 432 TUNNEL CONSTRUCTION AFTER MARCH 1, 2012 ITEM 432 TUNNEL CONSTRUCTION 432.1 Description. This Item shall govern for tunnel lines under railroads, state highways, and concrete paved streets or other obstructions indicated.

More information

Drilling of grout holes will be measured for payment on the basis of the linear feet of holes actually drilled.

Drilling of grout holes will be measured for payment on the basis of the linear feet of holes actually drilled. I - Measurement and payment Mobilization and Demobilization: Payment will be made for costs for assembling all plant and equipment at the site preparatory to initiating the work and for removing it there

More information

#47 CASE STUDY INSTALLATION OF A SOIL-BENTONITE CUTOFF WALL THROUGH AN ABANDONED COAL MINE (GROVE CITY, PA)

#47 CASE STUDY INSTALLATION OF A SOIL-BENTONITE CUTOFF WALL THROUGH AN ABANDONED COAL MINE (GROVE CITY, PA) #47 CASE STUDY INSTALLATION OF A SOIL-BENTONITE CUTOFF WALL THROUGH AN ABANDONED COAL MINE (GROVE CITY, PA) by Michael J. Carey Michael J. Fisher Steven R. Day Presented at: International Containment Technology

More information

SHAFT CONSTRUCTION SECANT PILE

SHAFT CONSTRUCTION SECANT PILE by Rob jameson and eric lindquist feature story SECANT PILE SHAFT CONSTRUCTION Modern Tools and Techniques Allow Excavation to Depths Previously Considered Infeasible By Rob Jameson and Eric Lindquist

More information

DIAPHRAGM WALLS, CUT-OFF WALLS AND SLURRY WALLS

DIAPHRAGM WALLS, CUT-OFF WALLS AND SLURRY WALLS DIAPHRAGM WALLS, CUT-OFF WALLS AND SLURRY WALLS Implenia Spezialtiefbau GmbH Robert Bosch Straße 25 D-63225 Langen Phone: +49 6103 988 345 Fax: +49 6103 988 277 Email: info.spezialtiefbau@implenia.com

More information

Lesson 7 & 8 Construction Inspection/ Quality Control (QA/QC) Load Testing. Learning Outcomes. Quality Assurance and Quality Control (QA/QC)

Lesson 7 & 8 Construction Inspection/ Quality Control (QA/QC) Load Testing. Learning Outcomes. Quality Assurance and Quality Control (QA/QC) Lesson 7 & 8 Construction Inspection/ Quality Control (QA/QC) Load Testing schnabel-eng.com Learning Outcomes Identify proper approaches to inspect, monitor and document construction and testing of micropile

More information

Jet Grout Soilcrete Stabilization Version 2006

Jet Grout Soilcrete Stabilization Version 2006 Version 2006 GUIDE TECHNICAL SPECIFICATIONS JET GROUTING SOIlCRETE STABILIZATION (This technical specification is to be used to guide the writer in the contract requirements for Soilcrete Stabilization

More information

Brochure E. The Soilcrete Jet Grouting Process

Brochure E. The Soilcrete Jet Grouting Process Brochure 67-03 E The Soilcrete Jet Grouting Process Contents History...3 Soilcrete Jet Grouting Process... 4 Process Variations... 6 Construction Forms... 7 Construction Sequences... 8 Stabilisation...

More information

Jet Grouting to Increase Lateral Resistance of Pile Group in Soft Clay

Jet Grouting to Increase Lateral Resistance of Pile Group in Soft Clay GROUND MODIFICATION, PROBLEM SOILS, AND GEO-SUPPORT 265 Jet Grouting to Increase Lateral Resistance of Pile Group in Soft Clay Kyle M. Rollins 1, Matthew E. Adsero 2, and Dan A. Brown 3 1 Prof. Civil &

More information

Wastewater Capital Projects Management Standard Construction Specification

Wastewater Capital Projects Management Standard Construction Specification CITY AND COUNTY OF DENVER ENGINEERING DIVISION Wastewater Capital Projects Management Standard Construction Specification 7.4 PERMEATION GROUTING 7.4.1 Definitions 7.4.1.1 Geotechnical Data Report (GDR)

More information

Ground Improvement. Cutter Soil Mixing Multi-Axis Soil Mixing Deep Soil Mixing Jet Grouting Vibro Systems Specialized Geotechnical Grouting

Ground Improvement. Cutter Soil Mixing Multi-Axis Soil Mixing Deep Soil Mixing Jet Grouting Vibro Systems Specialized Geotechnical Grouting Ground Improvement Cutter Soil Mixing Multi-Axis Soil Mixing Deep Soil Mixing Jet Grouting Vibro Systems Specialized Geotechnical Grouting www.malcolmdrilling.com Cutter Soil Mixing Multi-Axis Soil Mixing

More information

Misan University - College of Engineering Civil Engineering Department

Misan University - College of Engineering Civil Engineering Department CHAPTER 2 Soil and Excavations Soil investigation including two phases: surface investigation and subsurface investigation Surface investigation involves making a preliminary judgment about the site s

More information

SECTION XXXXX STONE COLUMNS PART 1 - GENERAL

SECTION XXXXX STONE COLUMNS PART 1 - GENERAL SECTION XXXXX STONE COLUMNS PART 1 - GENERAL 1.1 RELATED DOCUMENTS: Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division 00 and Division 01

More information

STANDARD SPECIFICATION Section Auger-Grout Injected Piles Civil Engineering Group Revised: August, 2000

STANDARD SPECIFICATION Section Auger-Grout Injected Piles Civil Engineering Group Revised: August, 2000 DIVISION 2: SITE WORK SECTION 02320 AUGER-GROUT INJECTED PILES STANDARD SPECIFICATION PART 1 GENERAL 1.0 DESCRIPTION OF WORK This work shall include all excavation, concrete, equipment and accessories

More information

SECTION 920 SANITARY AND STORM SEWER MANHOLES

SECTION 920 SANITARY AND STORM SEWER MANHOLES SECTION 920 SANITARY AND STORM SEWER MANHOLES 920.1 GENERAL This section contains items which are relative to the installation of sanitary and storm sewer manholes. 920.2 REFERENCES 920.2.1 ASTM C 43 C

More information

SECTION DRILLED CONCRETE PIERS AND SHAFTS

SECTION DRILLED CONCRETE PIERS AND SHAFTS SECTION 31 63 29 PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 01 Specification Sections, apply

More information

June i TABLE OF CONTENTS

June i TABLE OF CONTENTS June 2005 - i - 05-526 TABLE OF CONTENTS SECTION PAGE 1.0 INTRODUCTION... 1 1.1 Purpose of the Investigation... 1 1.2 Description of the Project and Scope of Work... 1 1.3 Site Geology... 1 1.4 Site Description

More information

mtec REPORT OF GEOTECHNICAL EXPLORATION FTFA Construct Bin Wall at HERD Eglin AFB, Florida

mtec REPORT OF GEOTECHNICAL EXPLORATION FTFA Construct Bin Wall at HERD Eglin AFB, Florida mtec REPORT OF GEOTECHNICAL EXPLORATION FTFA 14-3001 - Construct Bin Wall at HERD Eglin AFB, Florida MTEC Project Number 2014-101 November 10, 2014 Revised: January 5, 2015 Prepared For: Peterson Engineering,

More information

SECTION UTILITY POLYETHYLENE CONTAINMENT PIPE SYSTEMS

SECTION UTILITY POLYETHYLENE CONTAINMENT PIPE SYSTEMS SECTION 02670 UTILITY POLYETHYLENE CONTAINMENT PIPE SYSTEMS PART 1 - GENERAL 1.01 WORK INCLUDED A. Trenching and other excavation. B. Ground water control. C. Pipe bedding. D. Installation of containment

More information

APPENDIX F GEOTECHNICAL INVESTIGATION UPDATE CITY OF SANTA CRUZ D RAFT EIR L A B AHIA H OTEL JANUARY 2014

APPENDIX F GEOTECHNICAL INVESTIGATION UPDATE CITY OF SANTA CRUZ D RAFT EIR L A B AHIA H OTEL JANUARY 2014 GEOTECHNICAL INVESTIGATION UPDATE. CITY OF SANTA CRUZ D RAFT EIR L A B AHIA H OTEL JANUARY 2014 October 5, 2013 Project No. SCR-0720 SANTA CRUZ SEASIDE COMPANY Craig French 911 Center Street, Suite B Santa

More information

Minimum Guidelines for the Design and Use of Underpins When Performing Foundation Stabilization and/or Supplementation UP-08

Minimum Guidelines for the Design and Use of Underpins When Performing Foundation Stabilization and/or Supplementation UP-08 Minimum Guidelines for the Design and Use of Underpins When Performing Foundation Stabilization and/or Supplementation UP-08 Table of Contents 1. Title 2. Designation 3. List of Figures 4. Scope 5. Referenced

More information

Wastewater Capital Projects Management Standard Construction Specification

Wastewater Capital Projects Management Standard Construction Specification CITY AND COUNTY OF DENVER ENGINEERING DIVISION Wastewater Capital Projects Management Standard Construction Specification 10.1 PRECAST CONCRETE PIPE 10.1.1 General This section covers material requirements,

More information

ITEM D-701 PIPE FOR STORM DRAINS AND CULVERTS

ITEM D-701 PIPE FOR STORM DRAINS AND CULVERTS ITEM D-701 PIPE FOR STORM DRAINS AND CULVERTS 701-1 DESCRIPTION 701-1.1 This item shall consist of the construction of pipe culverts, and storm drains, removal of existing storm pipes, connections to existing

More information

Risk Management of the Restoration of Shanghai Metro Line 4

Risk Management of the Restoration of Shanghai Metro Line 4 ISGSR2007 First International Symposium on Geotechnical Safety & Risk Oct. 18~19, 2007 Shanghai Tongji University, China Risk Management of the Restoration of Shanghai Metro Line 4 X. P. Yu, W. J. Zhu

More information

Steven Dapp, Ph.D., P.E. Steven Dapp, Ph.D., P.E. Dan Brown and Associates

Steven Dapp, Ph.D., P.E. Steven Dapp, Ph.D., P.E. Dan Brown and Associates LA Transportation Conference: 10 Jan 2011 Drilled Shaft Foundations For Two Mississippi River Bridges in Louisiana Dan Brown and Associates Projects John James Audubon Bridge, St. Francisville New Construction

More information

Ground Improvement Techniques

Ground Improvement Techniques GRD Journals Global Research and Development Journal for Engineering Recent Advances in Civil Engineering for Global Sustainability March 2016 e-issn: 2455-5703 Ground Improvement Techniques 1 Nimisha

More information

Learning Outcomes. Background Definitions. Lesson 2 & 3. Definitions, Background, Classification, Applications and Costs

Learning Outcomes. Background Definitions. Lesson 2 & 3. Definitions, Background, Classification, Applications and Costs Lesson 2 & 3 Definitions, Background, Classification, Applications and Costs schnabel-eng.com Learning Outcomes Define a micropile Describe the characteristics, advantages and limitations of micropiles

More information

Ground Improvement Prof. G. L. Sivakumar Babu Department of Civil Engineering Indian Institute of Science, Bangalore

Ground Improvement Prof. G. L. Sivakumar Babu Department of Civil Engineering Indian Institute of Science, Bangalore Ground Improvement Prof. G. L. Sivakumar Babu Department of Civil Engineering Indian Institute of Science, Bangalore Module No. # 07 Lecture No. # 22 Micropiles (Refer Slide Time: 00:30) So, we would be

More information

Slurry Trench / Diaphragm Walls

Slurry Trench / Diaphragm Walls UNIVERSITY OF WASHINGTON DEPARTMENT OF CONSTRUCTION MANAGEMENT CM 420 TEMPORARY STRUCTURES Winter Quarter 2007 Professor Kamran M. Nemati Temporary Structures Slurry Trench / Diaphragm Walls CM 420 TEMPORARY

More information

INSTALLATION GUIDE PLEASE READ ENTIRE INSTRUCTION MANUAL BEFORE PROCEEDING!

INSTALLATION GUIDE PLEASE READ ENTIRE INSTRUCTION MANUAL BEFORE PROCEEDING! DURA - TRENCH INSTALLATION GUIDE This guide is intended to aide in the installation of Dura-Trench systems. There are many different applications and situations for the use of this product and the installation

More information

SPECIAL CONDITIONS FOR PIPE JACKING (PJ) October, 2006

SPECIAL CONDITIONS FOR PIPE JACKING (PJ) October, 2006 Michigan Department Of Transportation 3703C (11/06) 1 Materials 1.1 Pipe SPECIAL CONDITIONS FOR PIPE JACKING (PJ) October, 2006 Page 1 of 5 The type of pipe used for the pipe jacking method shall be capable

More information

SECTION / ENGINEERED AGGREGATE PIERS (SOIL REINFORCEMENT AND FOUNDATION SYSTEM)

SECTION / ENGINEERED AGGREGATE PIERS (SOIL REINFORCEMENT AND FOUNDATION SYSTEM) PART 1 GENERAL 1.01 WORK INCLUDED SECTION 02360 / 31 34 30.13 ENGINEERED AGGREGATE PIERS (SOIL REINFORCEMENT AND FOUNDATION SYSTEM) A. Provide all equipment, material, labor and supervision to design and

More information

GEOTECHNICAL INVESTIGATION PROPOSED OUTFALL LOCATION CITY OF MORGAN S POINT DRAINAGE HARRIS COUNTY, TEXAS REPORT NO

GEOTECHNICAL INVESTIGATION PROPOSED OUTFALL LOCATION CITY OF MORGAN S POINT DRAINAGE HARRIS COUNTY, TEXAS REPORT NO GEOTECHNICAL INVESTIGATION PROPOSED OUTFALL LOCATION CITY OF MORGAN S POINT DRAINAGE HARRIS COUNTY, TEXAS REPORT NO. 1140198001 Reported to: SIRRUS ENGINEERS, INC. Houston, Texas Submitted by: GEOTEST

More information

Table of Contents 18.1 GENERAL Overview Responsibilities References

Table of Contents 18.1 GENERAL Overview Responsibilities References Table of Contents Section Page 18.1 GENERAL... 18.1-1 18.1.1 Overview... 18.1-1 18.1.2 Responsibilities... 18.1-1 18.1.3 References... 18.1-2 18.2 MISCELLANEOUS FOUNDATION DESIGNS... 18.2-1 18.2.1 Buildings...

More information

SECTION STORM DRAINAGE

SECTION STORM DRAINAGE SECTION 02720 STORM DRAINAGE PART 1 - GENERAL 1.01 WORK INCLUDED A. Trenching and other excavation. B. Ground water control. C. Pipe bedding. D. Installation of storm drains and appurtenances. E. Installation

More information

Lesson 4. Construction Techniques and Materials. Learning Outcomes. Basic Construction

Lesson 4. Construction Techniques and Materials. Learning Outcomes. Basic Construction Lesson 4 Construction Techniques and Materials schnabel-eng.com Learning Outcomes Describe sequence of construction for a micropile Identify materials used to construct a micropile Describe principle function

More information

Lantz-Boggio Architects, P.C LBA Project No

Lantz-Boggio Architects, P.C LBA Project No SECTION 313430- PART 1 GENERAL 1.1 WORK INCLUDED A. Provide all equipment, material, labor and supervision to design and install Engineered Aggregate Piers for the soil reinforcement. Design shall rely

More information

Forensics by Freezing

Forensics by Freezing Forensics by Freezing Joseph A. Sopko, Ph.D., P.E., M.ASCE Moretrench American Corporation, 100 Stickle Avenue, Rockaway, NJ 07866, e-mail: jasopko@moretrench.com ABSTRACT Subsurface conditions in water

More information

King County Uses Trenchless Methods to Construct a Large Siphon Under Seattle s Ship Canal

King County Uses Trenchless Methods to Construct a Large Siphon Under Seattle s Ship Canal North American Society for Trenchless Technology (NASTT) NASTT s 2013 No-Dig Show Sacramento, California March 3-7, 2013 TA-T1-03 King County Uses Trenchless Methods to Construct a Large Siphon Under Seattle

More information

TRENCHLESS CONSTRUCTION (BORING, JACKING, AND TUNNELING)

TRENCHLESS CONSTRUCTION (BORING, JACKING, AND TUNNELING) PART 1 - GENERAL TRENCHLESS CONSTRUCTION (BORING, JACKING, AND TUNNELING) 1.01 SECTION INCLUDES A. Trenchless Installation of Carrier Pipe with Casing Pipe B. Trenchless Installation of Carrier Pipe without

More information

ASSESSMENT AND MITIGATION OF LIQUEFACTION RISK FOR EXISTING BUILDING FOUNDATION

ASSESSMENT AND MITIGATION OF LIQUEFACTION RISK FOR EXISTING BUILDING FOUNDATION ASSESSMENT AND MITIGATION OF LIQUEFACTION RISK FOR EXISTING BUILDING FOUNDATION Rolando P. Orense 1, Yukio Morita 2 and Masanori Ide 3 ABSTRACT This paper outlines the mitigation measures performed to

More information

Pump Station Excavation

Pump Station Excavation Pump Station Excavation SPONSORED BY THE KIEWIT CORPORATION A capstone project for the The Department of Civil & Environmental Engineering in The Ira A. Fulton College of Engineering and Technology Brigham

More information

CONSTRUCTION SPECIFICATION FOR PRECAST REINFORCED CONCRETE BOX CULVERTS AND BOX SEWERS IN OPEN CUT

CONSTRUCTION SPECIFICATION FOR PRECAST REINFORCED CONCRETE BOX CULVERTS AND BOX SEWERS IN OPEN CUT ONTARIO PROVINCIAL STANDARD SPECIFICATION METRIC OPSS 422 APRIL 2004 CONSTRUCTION SPECIFICATION FOR PRECAST REINFORCED CONCRETE BOX CULVERTS AND BOX SEWERS IN OPEN CUT TABLE OF CONTENTS 422.01 SCOPE 422.02

More information

ALMEDA TUNNEL PAST, PRESENT AND FUTURE

ALMEDA TUNNEL PAST, PRESENT AND FUTURE ALMEDA TUNNEL PAST, PRESENT AND FUTURE Ravi Kaleyatodi, P.E., CPM Senior Assistant Director, City of Houston Ravi.kaleyatodi@cityofhouston.net Paul C. Wallick, P.E., Senior Project Manager Patricia Frayre,

More information

Geotechnical Investigation Long Timber Brewing Building Highway 99 and Kelly Street Monroe, Oregon TABLE OF CONTENTS

Geotechnical Investigation Long Timber Brewing Building Highway 99 and Kelly Street Monroe, Oregon TABLE OF CONTENTS Highway 99 and Kelly Street TABLE OF CONTENTS PROJECT INFORMATION... 1 FIELD EXPLORATION... 1 SITE CONDITIONS... 2 Surface Conditions:... 2 Subsurface Conditions:... 2 FILL.... 2 Topsoil.... 2 Clay Alluvium....

More information

or (800)

or (800) WWW.CELL-CRETE.COM or (800) 669-0433 CALIFORNIA (Lic #243404), OREGON, WASHINGTON, NEVADA, UTAH, IDAHO, MONTANA, ARIZONA, HAWAII, ALASKA, WESTERN CANADA Re: Cellular Concrete as Engineered Fill I m pleased

More information

CUTTER SOIL MIXED WALL SHORING AND SEEPAGE CUT OFF OFFICE BUILDING NEAR WATERFRONT

CUTTER SOIL MIXED WALL SHORING AND SEEPAGE CUT OFF OFFICE BUILDING NEAR WATERFRONT CUTTER SOIL MIXED WALL SHORING AND SEEPAGE CUT OFF OFFICE BUILDING NEAR WATERFRONT By John Kvinsland Malcolm Drilling Company, Kent, Washington Bob Plum ASCE, P.E., Principal Kleinfelder Consultants, Seattle

More information

REQUIREMENTS FOR SERVICES UNDER THE RAILWAY CORRIDOR (NON-QR SERVICES)

REQUIREMENTS FOR SERVICES UNDER THE RAILWAY CORRIDOR (NON-QR SERVICES) SYSTEMS AND CAPABILITY TECHNICAL REQUIREMENT NO: MCE-SR-16 ISSUE: Initial DATE: 14-10-2009 PAGE: 1 of 19 REQUIREMENTS FOR SERVICES UNDER THE RAILWAY CORRIDOR (NON-QR SERVICES) ISSUE DATE DESCRIPTION /

More information

ITEM 431 PNEUMATICALLY PLACED CONCRETE. All material shall conform to the pertinent requirements of the following items:

ITEM 431 PNEUMATICALLY PLACED CONCRETE. All material shall conform to the pertinent requirements of the following items: ITEM 431 PNEUMATICALLY PLACED CONCRETE 431.1. Description. This Item shall govern for furnishing and placing of "Pneumatically Placed Concrete" for encasement of designated structural steel members, the

More information

Case Histories. Cap and Compaction Grouting for Sinkhole Remediation R.M. Bivens, P.E. Rembco Geotechnical Contractors, Inc.

Case Histories. Cap and Compaction Grouting for Sinkhole Remediation R.M. Bivens, P.E. Rembco Geotechnical Contractors, Inc. Case Histories Cap and Compaction Grouting for Sinkhole Remediation R.M. Bivens, P.E. Rembco Geotechnical Contractors, Inc. Cap Grouting Capping the top of the rock surface with grout to provide a barrier

More information

MEMORANDUM. TO: STUART OLSON DOMINION CONSTRUCTION LTD. DATE: JANUARY 31, 14 ATTENTION: MR. Dave Bauder, Construction Manager KENNY K. C.KO, P.ENG.

MEMORANDUM. TO: STUART OLSON DOMINION CONSTRUCTION LTD. DATE: JANUARY 31, 14 ATTENTION: MR. Dave Bauder, Construction Manager KENNY K. C.KO, P.ENG. MEMORANDUM Levelton Consultants Ltd. 150-12791 Clarke Place Richmond, BC V6V 2H9 Canada Tel: 604 278-1411 Fax: 604 278-1042 E-Mail: rhillaby@levelton.com Web Site: www.levelton.com TO: STUART OLSON DOMINION

More information

Construction Specification for Utility Adjustments

Construction Specification for Utility Adjustments Engineering & Construction Services Division Standard Specifications for Road Works TS 4.50 September 2017 for Utility Adjustments Table of Contents TS 4.50.01 SCOPE... 2 TS 4.50.02 REFERENCES... 2 TS

More information

STANDARD SPECIFICATIONS SECTION BORING AND JACKING. A. Section includes requirements for boring and jacking casing pipe.

STANDARD SPECIFICATIONS SECTION BORING AND JACKING. A. Section includes requirements for boring and jacking casing pipe. STANDARD SPECIFICATIONS SECTION 02445 BORING AND JACKING PART 1 GENERAL 1.1 DESCRIPTION A. Section includes requirements for boring and jacking casing pipe. 1.2 DEFINITIONS A. Carrier Pipe: Sewer or water

More information

SECTION CS-2. TRENCH EXCAVATION CONSTRUCTION STANDARDS

SECTION CS-2. TRENCH EXCAVATION CONSTRUCTION STANDARDS SECTION CS-2. TRENCH EXCAVATION CONSTRUCTION STANDARDS CS-2-01. GENERAL: Trench excavation shall conform with the City Standard Specifications. In general a trench is defined as an excavation in which

More information

Proceedings of the 10 th Australia New Zealand Conference on Geo-Mechanics, Common Ground Brisbane Australia, October 2007

Proceedings of the 10 th Australia New Zealand Conference on Geo-Mechanics, Common Ground Brisbane Australia, October 2007 Page 1 of 6 Proceedings of the 10 th Australia New Zealand Conference on Geo-Mechanics, Common Ground Brisbane Australia, October 2007 Vertical groundwater barriers for contaminated site reclamation Christopher

More information

Earthquake Reinforcement Using Jet Grouting for a Factory in Operation

Earthquake Reinforcement Using Jet Grouting for a Factory in Operation 6 th International Conference on Earthquake Geotechnical Engineering 1-4 November 2015 Christchurch, New Zealand Earthquake Reinforcement Using Jet Grouting for a Factory in Operation J. Kawamura 1 ABSTRACT

More information

BASEMENT CONSTRUCTION PREPARED BY PN NOOR AISYAH ASYIKIN

BASEMENT CONSTRUCTION PREPARED BY PN NOOR AISYAH ASYIKIN BASEMENT CONSTRUCTION PREPARED BY PN NOOR AISYAH ASYIKIN BASEMENT CONSTRUCTION 01 content 1.DEFINITION 2. CONSTRUCTION CONSIDERATION 3. DESIGN REQUIREMENT 4.METHOD OF CONSTRUCTION a. Open Cut Construction

More information

SLURRY WALLS FOR SEEPAGE CUTOFF IN LEVEE APPLICATIONS RECENT EXPERIENCE AND CONSTRUCTION CHALLENGES IN THE NORTHERN CENTRAL VALLEY OF CALIFORNIA

SLURRY WALLS FOR SEEPAGE CUTOFF IN LEVEE APPLICATIONS RECENT EXPERIENCE AND CONSTRUCTION CHALLENGES IN THE NORTHERN CENTRAL VALLEY OF CALIFORNIA SLURRY WALLS FOR SEEPAGE CUTOFF IN LEVEE APPLICATIONS RECENT EXPERIENCE AND CONSTRUCTION CHALLENGES IN THE NORTHERN CENTRAL VALLEY OF CALIFORNIA Deep Foundation Institute Slurry Wall Committee July 22,

More information

7. Draw an equipment set up for the production of a beam by post tensioning. 10. What are the common concrete structures which are produced by

7. Draw an equipment set up for the production of a beam by post tensioning. 10. What are the common concrete structures which are produced by Construction Technology B (CON4313) Self Assessment Questions: Chapter 1 Prestressed Concrete 1. How does the prestressing of steel tendons in prestressed concrete offer a higher loading capacity than

More information

MODIFIED DRY MIXING (MDM) A NEW POSSIBILITY IN DEEP MIXING

MODIFIED DRY MIXING (MDM) A NEW POSSIBILITY IN DEEP MIXING MODIFIED DRY MIXING (MDM) A NEW POSSIBILITY IN DEEP MIXING J. Gunther, G. Holm, G. Westberg, H. Eriksson ABSTRACT A Modified Dry Mixing (MDM) method has been developed. By an innovative modification to

More information

PLEASE READ ENTIRE INSTRUCTION MANUAL BEFORE PROCEEDING!

PLEASE READ ENTIRE INSTRUCTION MANUAL BEFORE PROCEEDING! INSTALLATION GUIDE This guide is intended to aide in the installation of Dura-Trench systems. There are many different applications and situations for the use of this product and the installation procedures

More information

Application of Vibro Techniques for Infrastructure Projects in India

Application of Vibro Techniques for Infrastructure Projects in India Application of Vibro Techniques for Infrastructure Projects in India Rainer Wegner Contract Manager, Keller Grundbau GmbH, Germany Dr. V.R. Raju Director, Keller Ground Engineering India Pvt Ltd, India

More information

SPECIAL SPECIFICATION 5787 Manhole Rehabilitation

SPECIAL SPECIFICATION 5787 Manhole Rehabilitation 2004 Specifications CSJ 1062-04-047 SPECIAL SPECIFICATION 5787 Manhole Rehabilitation 1. Description. Repair, rehabilitate, or replace deteriorated, leaking, or structurally unsound existing sanitary sewer

More information

EVALUATION REPORT. PFC-5551 Reissued April 1, Filing Category: DESIGN Steel (038)

EVALUATION REPORT. PFC-5551 Reissued April 1, Filing Category: DESIGN Steel (038) ICBO Evaluation Service, Inc. 5360 WORKMAN MILL ROAD WHITTIER, CALIFORNIA 90601-2299 A subsidiary corporation of the International Conference of Building Officials EVALUATION REPORT Copyright 2001 ICBO

More information

SEISMIC RETROFIT OF AN UNDERGROUND RESERVOIR. Robert Small 1, Rob Jameson 2

SEISMIC RETROFIT OF AN UNDERGROUND RESERVOIR. Robert Small 1, Rob Jameson 2 ABSTRACT SEISMIC RETROFIT OF AN UNDERGROUND RESERVOIR Robert Small 1, Rob Jameson 2 Seismic Upgrade of the University Mound Reservoir North Basin included 542 micropiles with 1335 KN (300 kip) design capacity

More information

An Introduction to Keller in the UK COLCRETE EURODRILL GETEC PHI GROUP. Piling and Ground Improvement. Grouting, Soil Nails and Anchors

An Introduction to Keller in the UK COLCRETE EURODRILL GETEC PHI GROUP. Piling and Ground Improvement. Grouting, Soil Nails and Anchors An Introduction to Keller in the UK Piling and Ground Improvement Grouting, Soil Nails and Anchors Retaining Walls Equipment Manufacture Monitoring and Instrumentation PHI GROUP GETEC COLCRETE EURODRILL

More information

The work required for this project includes, but is not limited to, the following items, not listed in order of execution.

The work required for this project includes, but is not limited to, the following items, not listed in order of execution. ESTIMATE OF QUANTITIES SPECIFICATIONS Construction Specifications: South Dakota Standard Specifications for Roads and Bridges, 2004 Edition and Required Provisions, Supplemental Specifications and/or Special

More information

SECTION 44 SHOTCRETE, CAST CONCRETE CHANNEL LINING, AND GROUTED COBBLE TABLE OF CONTENTS

SECTION 44 SHOTCRETE, CAST CONCRETE CHANNEL LINING, AND GROUTED COBBLE TABLE OF CONTENTS SECTION 44 SHOTCRETE, CAST CONCRETE CHANNEL LINING, AND GROUTED COBBLE TABLE OF CONTENTS Section Page 44-1 SHOTCRETE... 44.1 44-1.01 Description... 44.1 44-1.02 Materials... 44.1 44-1.03 Proportions...

More information

Case Study: Cement-Bentonite Pre-Trenching and Cutter Soil Mixing (CSM) for Temporary Shoring and Groundwater Cutoff

Case Study: Cement-Bentonite Pre-Trenching and Cutter Soil Mixing (CSM) for Temporary Shoring and Groundwater Cutoff Case Study: Cement-Bentonite Pre-Trenching and Cutter Soil Mixing (CSM) for Temporary Shoring and Groundwater Cutoff Dominic M. Parmantier 1, M. ASCE, P.E; Rowland F P Stow 2, P.Eng.; R. John Byrne 3,

More information