SAFE WORK METHOD STATEMENT

Size: px
Start display at page:

Download "SAFE WORK METHOD STATEMENT"

Transcription

1 SAFE WORK METHOD STATEMENT Principal Contractor: ROBERT LIVINGSTONE Project Address: 123 SYDNEY ROAD SYDNEY NSW 2000 High Risk Work Hazards and Risks Identified Control Measures Persons working at a height of more than 2 metres Demolition of a load-bearing structure (or work related to the physical integrity of the structure) Person could fall; falling objects may strike persons or plant / equipment below Person could be crushed; potential damage to plant and equipment; dusts All persons working at a heights of more than 2 metres are to at all times wear a safety harness Scaffolding is to be erected Safety rails are to be installed [For further reference see Code of Practice Safe Work on Roofs Part 2 Residential Building, 2004 WorkCover NSW] Water is to be applied to the demolished area to minimize dust The demolition area is to be isolated within a secure fence Persons involved in the demolition work are to be licensed and wearing appropriate Personal Protective Equipment 1

2 Work involving the disturbance (or likely disturbance) of asbestos Work involving structural alterations or repairs that require temporary support to prevent collapse Work carried out in or near a confined space Work carried out in or near a shaft or trench with an excavation depth of more than 1.5 metres, or in a tunnel Person could sustain a lung disease The structure could collapse; persons could be crushed; potential damage to plant / equipment Dangerous fumes, excessive noise and lack of adequate lighting could affect persons working in confined spaces Person could be buried, or injured whilst entering or exiting the trench Practice How to Manage and Control Asbestos in the Workplace, WorkCover NSW. The installed temporary support is to be examined and signed off by an engineer, and continually monitored. Where dangerous fumes are present, a ventilation system is to be installed. Work is to be carried out in strict accordance with the Code of Practice Confined Spaces, WorkCover NSW. Check with the appropriate authority for the location of underground services (ie. gas, water, communications, electricity) before any digging takes place Secure a suitable barrier / guardrails is to be erected around any excavation If workers are required to be in a trench 1.5 metres or more deep, the sides of the trench are to be battered at an angle of 45 degrees or shored up with a trench support system. Suitable ladders are to be provided for entry and exit from trenches. Practice Excavation Work, WorkCover NSW. 2

3 Work carried out on or near chemical, fuel or refrigerant lines Work carried out in or near energized electrical installations or services Work carried out in an area that may have a contaminated or flammable atmosphere Work involving tilt-up or pre-cast concrete Work carried out on, in or adjacent to a road, shipping lane or other traffic corridor that is in use by traffic other than pedestrians Person could inhale dangerous fumes, be burned, or injured by an explosion Person could be electrocuted Person could be burned and / or injured in an explosion The structure could collapse; persons could be crushed; potential damage to plant / equipment Persons could be hit by moving vehicles; moving vehicles could be hit by plant, equipment or building products Check with the appropriate authority for the location of underground services (ie. gas, water, communications, electricity) Ensure that all work is supervised The worksite is to be protected by an Earth Leakage Device All work is to be supervised by a licensed electrician All chemicals are to be stored safety and be accompanied by a Material Safety Data Sheet There is to be adequate ventilation in confined working areas Strict no smoking rules are to be applied in the vicinity of such an area Workers are to be required to wear appropriate Personal Protective Equipment, including breathing apparatus The installed temporary support is to be examined and signed off by an engineer, and continually monitored. A traffic management plan is to be prepared and submitted to the local council for approval Workers supervising such work are to be adequately trained 3

4 Work carried out in an area in which there is any movement of powered mobile plant Work carried out in or near water or other liquid that involves the risk of drowning Person could be hit by moving plant Person could drown Practice Moving Plant on Construction Sites, WorkCover NSW. If working near a swimming pool, the water is to be pumped out prior to work commencing In other cases, work is to be supervised SIGNED: Principal Contractor Robert Livingstone Date 1 July 2016 Project Manager * Robert Livingstone Date 1 July 2016 *This person can be a Person Conducting a Business or Undertaking (PCBU), or an officer or authorized agent of the PCBU. 4

5 NOTES: 1. If the entire construction project is valued at $250,000 or more, this Safe Work Method Statement ( SWMS ) will form part of the Principal Contractor s Work Health and Safety Management System. 2. The Principal Contractor is to ensure that: (a) the above control measures are implemented prior to high risk construction work commencing; and (b) that all high risk construction work is carried out in accordance with this SWMS; and (c) that all high risk construction work and the control measures implemented are continually monitored. 3. As part of the obligation for consultation, the Principal Contractor is to regularly consult with workers carrying out the high risk construction work identified in this SWMS in relation to the adequacy of the control measures implemented. 4. The Principal Contractor is to ensure that if high risk construction work is not carried out in accordance with this SWMS, that such work is stopped immediately as soon as it is safe to do so, and resumed only in accordance with this SWMS. 5. Any changes to this SWMS must be documented, and the rules that apply to this SWMS will also apply to the amended SWMS. 6. A copy of this SWMS (and any later changes to it) must be readily accessible to any worker who is carrying out, or who is to carry out, high risk construction work. 7. The Principal Contractor must keep a copy of this SWMS: (a) until the high risk construction work to which it relates is completed; or (b) if a notifiable incident occurs in connection with the high risk construction work to which this SWMS relates, for at least 2 years 5

Safe Work Method Statement

Safe Work Method Statement Safe Work Method Statement 01 WHAT IS A SWMS? A SWMS is a document that sets out the high risk construction work activities to be carried out at a workplace, the hazards arising from these activities and

More information

Safe Work Method Statement (SWMS) for Painting projects

Safe Work Method Statement (SWMS) for Painting projects Safe Work Method Statement (SWMS) for Painting projects This SWMS is a site specific statement that must be prepared before any high risk construction work is commenced. Painting company: Address: Principle

More information

Construction, Demolition & Excavation Works Doc Reference: DoMN-WHSMS 3.14 Version Number: 2.2

Construction, Demolition & Excavation Works Doc Reference: DoMN-WHSMS 3.14 Version Number: 2.2 Purpose This procedure provides guidance to the Diocese of Maitland Newcastle (DoMN), principal contractors and other persons conducting a business or undertaking (PCBU) who commission or carry out construction,

More information

SAFE WORK METHOD STATEMENT

SAFE WORK METHOD STATEMENT COMPANY DETAILS: Company Name Address CLIENT DETAILS: Principal contractor Contact name Phone no. Mobile: Phone no. Mobile: Works manager Contact no.: Project/owner name Work activity Scope of work covered

More information

Safe Work Method Statement

Safe Work Method Statement Safe Work Method Statement Disclaimer: Use of Master Builders Generic Safe Work Method Statements The Master Builders Association of Victoria expressly disclaim all and any liability to any person in respect

More information

UNCONTROLLED IF PRINTED. Issued with the authority of the Chief Commissioner and General Manager of Scouts Australia NSW

UNCONTROLLED IF PRINTED. Issued with the authority of the Chief Commissioner and General Manager of Scouts Australia NSW PROCEDURE Contractor Safety Issued with the authority of the Chief Commissioner and General Manager of Chief Commissioner signature Chief Executive Officer signature Sponsor Head of Risk Document type

More information

WHS Management Plans

WHS Management Plans WHS Management Plans Disclaimer This Guide provides general information about the obligations of persons conducting a business or undertaking and/or persons in control of premises and workers under the

More information

Work Health & Safety Procedure

Work Health & Safety Procedure 1 PURPOSE This procedure explains the process for qualification of Contractors at Port of Newcastle (PON). It outlines the responsibilities for PON Representatives and Contractors. It also provides a system

More information

Appendix 4A - SWMS Description

Appendix 4A - SWMS Description SAFE WORK METHOD STATEMENT (SWMS) Duty holders A person conducting a business or undertaking (PCBU) carrying out any high risk work in connection with a construction project is required to have a detailed

More information

BUILDING A WORLD OF DIFFERENCE. Briefing for Resident Engineers

BUILDING A WORLD OF DIFFERENCE. Briefing for Resident Engineers Introduction to Safe Working in Excavations Briefing for Resident Engineers Planning excavations - considerations Stability of excavations ground conditions People, material and vehicles falling into excavations

More information

OUTLAW AUTOMATION INC. Safety Management System

OUTLAW AUTOMATION INC. Safety Management System Preparation: Safety Mgr Authority: President Issuing Dept: Safety Page: Page 1 of 6 Purpose The purpose of this program is to provide employees general information for working on owner client or other

More information

Duty holders under the OHS Act and OHS Regulations should use the Code together with this legislation.

Duty holders under the OHS Act and OHS Regulations should use the Code together with this legislation. 1 PREFACE This Compliance Code (Code) provides practical guidance for those who have duties or obligations in relation to demolition sites under the Occupational Health and Safety Act 2004 (OHS Act) and

More information

OHS Management of Contractors in Capital Works and Maintenance

OHS Management of Contractors in Capital Works and Maintenance OHS Management of Contractors in Capital Works and Maintenance Physical Resources/Risk, Health and Safety Prepared by: Physical Resources/Risk, Health and Safety Version: 08/04/2008 Contents Page 1. INTRODUCTION...

More information

Compliance code. Demolition. Edition 1. May 2018

Compliance code. Demolition. Edition 1. May 2018 Compliance code Demolition Edition 1 May 2018 Contents Preface 2 Part 1 Introduction 3 Purpose 3 Scope 3 Application 3 What is demolition work? 3 Who has duties? 4 The risk management process 6 Consultation

More information

Date Prepared: Location: Time: Approximate Temperature (degrees F): Weather Conditions: Project Name:

Date Prepared: Location: Time: Approximate Temperature (degrees F): Weather Conditions: Project Name: Appendix C Hazard Assessment and Trench Entry and Authorization Form for regularly scheduled and emergency trenching activities Date Prepared: Location: Time: Approximate Temperature (degrees F): Weather

More information

To Loughborough University Facilities Management (FM) Health and Safety Policy

To Loughborough University Facilities Management (FM) Health and Safety Policy Annex DD To Loughborough University Facilities Management (FM) Health and Safety Policy Work involving excavations Purpose According to the Occupational Safety and Health Administration (OSHA), the fatality

More information

Excavation Safety Program

Excavation Safety Program Excavation Safety Program Excavation, Trenching & Shoring Safety I. Purpose The purpose of this policy is to establish safe operating procedures for any earthwork or underground work that is done on a

More information

HEALTH AND SAFETY (MANAGEMENT IN CONSTRUCTION) (JERSEY) REGULATIONS 2016

HEALTH AND SAFETY (MANAGEMENT IN CONSTRUCTION) (JERSEY) REGULATIONS 2016 Arrangement HEALTH AND SAFETY (MANAGEMENT IN CONSTRUCTION) (JERSEY) REGULATIONS 2016 Arrangement Regulation PART 1 5 INTRODUCTORY 5 1 Interpretation... 5 2 Construction site... 8 3 Construction work...

More information

Excavation work. Code of Practice PN11577 Excavation work Code of Practice 2013 Page 1 of 43

Excavation work. Code of Practice PN11577 Excavation work Code of Practice 2013 Page 1 of 43 Excavation work Code of Practice 2013 PN11577 Excavation work Code of Practice 2013 Page 1 of 43 This Queensland code of practice has been approved by the Attorney-General and Minister for Justice and

More information

Rockhampton Office Brisbane Office Tarong Site. Barron Gorge Hydro PS Kareeya Hydro PS Mica Creek PS

Rockhampton Office Brisbane Office Tarong Site. Barron Gorge Hydro PS Kareeya Hydro PS Mica Creek PS Business Procedure Excavation and Penetration Document Number OHS-PROC-126 This document applies to the following sites: All Sites Rockhampton Office Brisbane Office Tarong Site Barron Gorge Hydro PS Kareeya

More information

HEALTH AND SAFETY (MANAGEMENT IN CONSTRUCTION) (JERSEY) REGULATIONS 2016

HEALTH AND SAFETY (MANAGEMENT IN CONSTRUCTION) (JERSEY) REGULATIONS 2016 HEALTH AND SAFETY (MANAGEMENT IN CONSTRUCTION) (JERSEY) REGULATIONS 2016 Revised Edition Showing the law as at 1 January 2017 This is a revised edition of the law Health and Safety (Management in Construction)

More information

Safe Work Method Statement. 14/4/16 Approved by (Snr Management Rep):

Safe Work Method Statement. 14/4/16 Approved by (Snr Management Rep): ABN 39 137 318 873 Unit 2, 36 Lidco St Arndell Park NSW 2148 QAC swms2 Phone: 1300 121 544 Fax 1300 078 877 Safe Work Method Statement SWMS No: 1 Revision Date: 14/4/16 Approved by (Snr Management Rep):

More information

Work involving excavations

Work involving excavations Annex DD To Loughborough University Facilities Management (FM) Health and Safety Policy Work involving excavations All persons who carry out or work in excavations have a duty to :- Comply with the Safety

More information

Contractor Induction Manual

Contractor Induction Manual Contractor Induction Manual Contractor Management September, 2014 Authored by: OHS Services Version 1.1 Contractor Induction Manual Table of Contents 1. INTRODUCTION... 2 2. CONTRACTOR MANAGEMENT INFORMATION...

More information

A GUIDE TO WORKING SAFELY AROUND VECTOR S ELECTRICITY, GAS AND COMMUNICATIONS NETWORKS.

A GUIDE TO WORKING SAFELY AROUND VECTOR S ELECTRICITY, GAS AND COMMUNICATIONS NETWORKS. A GUIDE TO WORKING SAFELY AROUND VECTOR S ELECTRICITY, GAS AND COMMUNICATIONS NETWORKS. Date of issue 27/01/2017 Date of next review 29/01/2018 Page 1 V4 18/07/2018 CONTENTS CONTENTS... 2 WORKING SAFELY...

More information

Contractor Induction Manual

Contractor Induction Manual Contractor Induction Manual Contractor Management December, 2014 Authored by: OHS Services Version 2 Contractor Induction Manual Table of Contents 1. INTRODUCTION... 2 2. CONTRACTOR MANAGEMENT INFORMATION...

More information

Who is responsible for construction safety? Presented by WorkSafe Victoria and Master Builders Association Victoria

Who is responsible for construction safety? Presented by WorkSafe Victoria and Master Builders Association Victoria Who is responsible for construction safety? Presented by WorkSafe Victoria and Master Builders Association Victoria Work Safe Week 2013 For the respect of others please ensure your mobile phone is switched

More information

Excavation General Awareness Safety Training Presentation Red Willow Production Co.

Excavation General Awareness Safety Training Presentation Red Willow Production Co. Excavation General Awareness Safety Training Presentation Red Willow Production Co. Learning Objectives Understand the purpose of our Excavation SOP - to protect employees and contractors when working

More information

To establish the Panama Canal Authority (ACP) occupational safety requirements for excavations.

To establish the Panama Canal Authority (ACP) occupational safety requirements for excavations. 1.0 PURPOSE To establish the Panama Canal Authority (ACP) occupational safety requirements for excavations. 2.0 BACKGROUND Excavation activities are highly dangerous and thus require adequate planning

More information

ESSENTIAL STANDARD no.1. Excavations

ESSENTIAL STANDARD no.1. Excavations ESSENTIAL STANDARD no.1 Excavations KEY MESSAGES Ensure that public safety and the safety of those doing the work is the number one priority. Plan to use the best/correct method. For example, where space

More information

Marshall Municipal Utilities EXCAVATIONS AND TRENCHING Effective August 1, 2011 Revised August 17, 2017

Marshall Municipal Utilities EXCAVATIONS AND TRENCHING Effective August 1, 2011 Revised August 17, 2017 Marshall Municipal Utilities EXCAVATIONS AND TRENCHING Effective August 1, 2011 Revised August 17, 2017 POLICY This policy applies to all open excavations and trenches; including those excavations and

More information

CONTRACTOR WHS SYSTEM STANDARD RISK MANAGEMENT EXTERNAL USE ONLY

CONTRACTOR WHS SYSTEM STANDARD RISK MANAGEMENT EXTERNAL USE ONLY CONTRACTOR WHS SYSTEM STANDARD RISK MANAGEMENT EXTERNAL USE ONLY Principles in the Optus Contractor WHS management process CONTRACTOR MANAGEMENT STAGES PRINCIPLES THIS STANDARD REQUISITION Requisition

More information

FATAL AND SEVERE RISKS CONTROLS STANDARD

FATAL AND SEVERE RISKS CONTROLS STANDARD FATAL SEVERE RISKS STARD CONTENTS Contents FSR 1 Temporary works, excavations and underground and overhead services 5 FSR 2 Plant and Equipment 6 FSR 3 Cranes and Lifting 7 FSR 4 Working at Heights 8 FSR

More information

Prevention of falls in general construction

Prevention of falls in general construction Compliance code Prevention of falls in general construction Edition 1 October 2018 Contents Preface 2 Part 1 Introduction 3 Purpose 3 Scope 3 Application 4 Who has duties? 4 The risk management process

More information

CONSULTING OFFICE OF MORRIS S. FARKAS PROFESSIONAL SAFETY ENGINEER

CONSULTING OFFICE OF MORRIS S. FARKAS PROFESSIONAL SAFETY ENGINEER CONSULTING OFFICE OF MORRIS S. FARKAS PROFESSIONAL SAFETY ENGINEER EDUCATION 3835 East Thousand Oaks Boulevard, #365 Westlake Village, California 91362 Telephone: (805) 494-0444 Facsimile: (805) 494-0441

More information

Contractors Code of Practice

Contractors Code of Practice Estates and Facilities Department of the University of Bradford In partnership with ICT Services Contractors Code of Practice Issue Date Comments 1 st Draft 2 nd Draft Issued 19/5/2010 Distributed as per

More information

PRO Ground Disturbance

PRO Ground Disturbance MS&L Procedure PRO-4.5-0001-1-03 Ground Disturbance Version: 3 Authorised by: Tom Angliss & Owen Quake Authorisation Date: 21/11/2017 This document has been approved for release and changed as per the

More information

Risk Control at United Fire Group

Risk Control at United Fire Group INTRODUCTION work can be a very hazardous exposure to employees and other contractors on construction job sites. is one of the most hazardous construction operations. The most feared hazard is excavation

More information

Contractors Safety Code of Practice

Contractors Safety Code of Practice Document Control Revision No. Date Document Reviewed 8 October 2017 Publication on Web Site November 2017 Date of next Review October 2019 or following any changes Summary of main changes Change in format

More information

The Corporation of The City of London

The Corporation of The City of London The Corporation of The City of London Legislative Health and Safety Requirements The following is a health and safety guide for those providing a tender to assist in determining legislative health and

More information

SAFE DESIGN AUSTRALIA

SAFE DESIGN AUSTRALIA SAFE DESIGN REPORT PROJECT DETAILS PROJECT NAME PROJECT ADDRESS 0 Missenden Road, Camperdown PROJECT REFERENCE SCR 86 DESIGNER True North Architects CLIENT St Johns College PREPARED B Rebekah Colman DATE

More information

OSH LEGISLATION LAW AND REGULATION TO CONSTRUCTION SAFETY LAW AND REGULATION TO CONSTRUCTION SAFETY 20/2/2013

OSH LEGISLATION LAW AND REGULATION TO CONSTRUCTION SAFETY LAW AND REGULATION TO CONSTRUCTION SAFETY 20/2/2013 LAW AND REGULATION TO CONSTRUCTION SAFETY Sr Dr. Mohd Saidin Misnan UNIVERSITI TEKNOLOGI MALAYSIA 81310 UTM Skudai, Johor, Malaysia LAW AND REGULATION TO CONSTRUCTION SAFETY OSH LEGISLATION 1 To enable

More information

SAFE WORK METHOD STATEMENT (SWMS)

SAFE WORK METHOD STATEMENT (SWMS) ABN: 12 345 678 910 ACN: 123 456 789 Address: Your Company Address PH: Your Company Phone E: Your Company Email Web: Your Company Website PROJECT DETAILS: Project: SAFE WORK METHOD STATEMENT (SWMS) Area:

More information

Contents. Before you begin. Introduction: Installing trench support 1. Element 1: Planning and preparing 3

Contents. Before you begin. Introduction: Installing trench support 1. Element 1: Planning and preparing 3 Contents Contents Before you begin v Introduction: Installing trench support 1 Element 1: Planning and preparing 3 Section 1.1 Accessing, interpreting and applying compliance documentation 4 to the work

More information

Health Safety, & Environment

Health Safety, & Environment GROUP SAFETY HEALTH AND ENVIRONMENT MANUAL R.G. Carter Construction Ltd Integrated Management System Section 7 Health Safety, & Environment Issue Manual No. Holders Name: Issue Date: GROUP HEALTH AND SAFETY

More information

NSP/007/002 Guidance on Substation Design: Design Risk Assessment

NSP/007/002 Guidance on Substation Design: Design Risk Assessment Version:- 2.0 Date of Issue:- January 2018 Page 1 of 19 NSP/007/002 Guidance on Substation Design: Design Risk Assessment 1. Purpose The Construction (Design and Management) Regulations ( CDM ) and the

More information

PROPERTY SERVICES OPERATING PROCEDURE

PROPERTY SERVICES OPERATING PROCEDURE This is a internal document and is only applicable to the internal operations of the RMIT. OPERATING PROCEDURE INTENT The Permit to Work (PTW) procedure is a formal written system used to control certain

More information

FATAL AND SEVERE RISKS CONTROLS STANDARD. August 2018

FATAL AND SEVERE RISKS CONTROLS STANDARD. August 2018 FATAL SEVERE RISKS STARD August 2018 CONTENTS Contents FSR 1 Excavations, Underground and Overhead Services 5 FSR 2 Plant and Equipment 6 FSR 3 Cranes and Lifting 7 FSR 4 Working at Heights 8 FSR 5 Scaffolding

More information

CONSTRUCTION SITES (SAFETY) (AMENDMENT) REGULATION 2003

CONSTRUCTION SITES (SAFETY) (AMENDMENT) REGULATION 2003 L. S. NO. 2 TO GAZETTE NO. 48/2003 L.N. 258 of 2003 B2475 L.N. 258 of 2003 CONSTRUCTION SITES (SAFETY) (AMENDMENT) REGULATION 2003 CONTENTS Section Page 1. Interpretation... B2479 2. Restriction on employment

More information

SAMPLE PAGES. Construction Safety and Health Program. [Company name]

SAMPLE PAGES. Construction Safety and Health Program. [Company name] The safety and health of our employees is our top priority. Everyone goes home safe and healthy every day. Construction Safety and Health Program [Company name] [Date Authorized] [Version} 0 Contents Mission

More information

Excavation &Trenching

Excavation &Trenching Excavation &Trenching The Hazards of Excavation and Trenching and How to Control Them Whitman College Department of Environmental Health & Safety and the Washington State Department of Labor & Industries

More information

29 CFR 1926 Construction Subpart P

29 CFR 1926 Construction Subpart P Industry code # 1781 Water Well Drilling Special trade contractors primarily engaged in water well drilling. (Establishments primarily engaged in drilling oil or gas field water intake wells on a contract

More information

Construction Method Statement

Construction Method Statement Construction Method Statement Introduction. The project involves the construction of the new Apartment Extra Car Home for Grwp Cynefin in Pothmadog, Gwynedd, Wales. The programme and construction methodology

More information

EXCAVATION PROCEDURE

EXCAVATION PROCEDURE TABLE OF CONTENTS 1 PREFACE... 3 2 OBJECTIVE... 3 3 SCOPE... 3 4 RELATED DOCUMENTS... 3 5 PURPOSE... 3 6 PPA EXCAVATION PERMIT FORM... 4 6.1 THE EXCAVATION PERMIT FORM.... 4 6.2 WHERE TO OBTAIN THE EXCAVATION

More information

Work Health and Safety Regulations for Western Australia Discussion Paper

Work Health and Safety Regulations for Western Australia Discussion Paper Australian Industry Group Work Health and Safety Regulations for Western Australia Discussion Paper Submission to WorkSafe Western Australia AUGUST 2016 WORK HEALTH AND SAFETY REGULATIONS FOR WESTERN AUSTRALIA

More information

Construction Safety Guidelines -31 Demolition DEM MO OLITION Rev 00 December 2013 Page 1 of 14

Construction Safety Guidelines -31 Demolition DEM MO OLITION Rev 00 December 2013 Page 1 of 14 Construction Safety Guidelines -31 Demolition DEMOLITION Page 1 of 14 Table of Contents 1. 2. 3. Purpose Scope Procedure 3. 1 General 3.2 Demolition Survey 3.33 Preferred methods of Demolition work 3.4

More information

Excavations and Penetrations

Excavations and Penetrations A printed or saved copy is an UNCONTROLLED copy. Check that it is the latest available version before use. Title: Number: EXCAVATIONS AND PENETRATIONS CSBP-GM-11-036-04 Version Number: 17.0.0 Date Revised:

More information

1. PURPOSE 2. SCOPE 3. APPLICATIONS AND INTERPRETATION. This document is to be read and understood in conjunction with the following, inter alia:

1. PURPOSE 2. SCOPE 3. APPLICATIONS AND INTERPRETATION. This document is to be read and understood in conjunction with the following, inter alia: HEALTH & SAFETY SPECIFICATIONS FOR RENOVATION OF EXISTING BUILDINGS AND CONSTRUCTION OF NEW INFRASTRUCTURE IN THE NZG (PRETORIA AND MOKOPANE) AND THOHOYANDOU BOTANICAL GARDEN 1. PURPOSE The objective of

More information

All employees who perform work which requires the removal of material that exceeds a depth of 1.2 meters (4 feet).

All employees who perform work which requires the removal of material that exceeds a depth of 1.2 meters (4 feet). POLICY NO.: 12.4.6 EFFECTIVE DATE: January 26, 2004 PAGE: 1 OF 6 POLICY STATEMENT: Working in a trench can be hazardous. This policy, in combination with the Trenching, Shoring, and Excavating Program,

More information

Duty holders under the OHS Act and OHS Regulations should use the Code together with this legislation.

Duty holders under the OHS Act and OHS Regulations should use the Code together with this legislation. 0 PREFACE This Compliance Code (Code) provides practical guidance for those who have duties or obligations in relation to demolition sites under the Occupational Health and Safety Act 2004 (OHS Act) and

More information

Excavation and Trenching

Excavation and Trenching Excavation and Trenching Excavation and trenching are among the most hazardous construction operations. The Occupational Safety and Health Administration s (OSHA) Excavation standards, 29 Code of Federal

More information

Occupational Health and Safety Regulation 2001

Occupational Health and Safety Regulation 2001 New South Wales Occupational Health and Safety Regulation 2001 under the Occupational Health and Safety Act 2000 Her Excellency the Governor, with the advice of the Executive Council, has made the following

More information

Section Safety Section Cleanup. None Required

Section Safety Section Cleanup. None Required January 2000 Page 1 of 6 PART 1 GENERAL 1.01 OTHER CONTRACT DOCUMENTS 1.02 DESCRIPTION OF WORK 1.03 RELATED SECTIONS PART 2 PRODUCTS The General Conditions of the Contract, General Requirements, and Supplemental

More information

Jobsite Specifications The A standard provides jobsite specifications for each of the following hazards:

Jobsite Specifications The A standard provides jobsite specifications for each of the following hazards: Overview of American National Standard A10.34-2001 Protection of the Public on or Adjacent to Construction Sites American National Standard for Construction and Demolition Operations The A10.34-2001 standard

More information

Trenching. 29 CFR Excavation Requirements. - Controls the trenching and excavation requirements for construction (excluding tunnels)

Trenching. 29 CFR Excavation Requirements. - Controls the trenching and excavation requirements for construction (excluding tunnels) 29 CFR 1926.651 Excavation Requirements - Controls the trenching and excavation requirements for construction (excluding tunnels) - Provides requirements for employee entrance, working environment, and

More information

Owners List of Known Workplace Hazards CONTRACT TITLE LIBRARY SQUARE ELEVATORS #10-#11 MODERNIZATION (OCT20/16)

Owners List of Known Workplace Hazards CONTRACT TITLE LIBRARY SQUARE ELEVATORS #10-#11 MODERNIZATION (OCT20/16) Owners List of Known Workplace Hazards CONTRACT TITLE LIBRARY SQUARE ELEVATORS #10-#11 MODERNIZATION (OCT20/16) PROJECT MANAGER (CITY EMPLOYEE) MORRIS PONTELLINI CONTRACT NAME & # (IF KWN) Purpose This

More information

SAFE WORK METHOD STATEMENT Part 1. Date:

SAFE WORK METHOD STATEMENT Part 1. Date: SAFE WORK METHOD STATEMENT Part 1 Company Details: Company Name: Raven Scaffolds Pty Ltd ABN:17 158 846 550 Contact Name, Position and Phone number: Justin Ericson, Manager, 0412 141 906 Address: 4/80

More information

Asbestos in Grounds, Asbestos Management Plan, Sydney Secondary College Balmain Campus, Balmain, NSW 2041

Asbestos in Grounds, Asbestos Management Plan, Sydney Secondary College Balmain Campus, Balmain, NSW 2041 Asbestos in Grounds, Asbestos Management Plan, Sydney Secondary College Balmain Campus, Balmain, NSW 2041 March 2014 NSW Public Works Parsons Brinckerhoff Australia Pty Limited ABN 80 078 004 798 Level

More information

SCHEDULE 8 CITY PRE-CONTRACT HAZARD ASSESSMENT FORM

SCHEDULE 8 CITY PRE-CONTRACT HAZARD ASSESSMENT FORM SCHEDULE 8 CITY PRE-CONTRACT HAZARD ASSESSMENT FORM Contract Title: INVITATION TO TENDER NO. PS20161432 WATERLESS TOILET BUILDINGS AT FRASERVIEW AND MCCLEERY (City employee) John Ross Contract Name and

More information

ESSENTIAL SAFETY RESOURCES

ESSENTIAL SAFETY RESOURCES ESSENTIAL SAFETY RESOURCES GS-3043 TRENCHING / SHORING / EXCAVATION PROGRAM Originator: Safety Advisor s Signature: Type Name Approval: HSE Manager s Signature: Type Name Approval: Operations Manager s

More information

A handbook for the construction regulations Working safely in the housing construction industry

A handbook for the construction regulations Working safely in the housing construction industry A handbook for the construction regulations Working safely in the housing construction industry February 2008 Edition No. 1 Contents Introduction 1 Application of the Regulations 2 What is construction

More information

Emergency Contact Numbers: Police, Fire, Ambulance 000 SES Vic Roads EPA Vic 1300 EPA VIC ( ) Safe Work Method Statement

Emergency Contact Numbers: Police, Fire, Ambulance 000 SES Vic Roads EPA Vic 1300 EPA VIC ( ) Safe Work Method Statement Safe Work Method Statement Emergency Contact Numbers: Police, Fire, Ambulance 000 SES 132 500 Vic Roads 13 11 70 EPA Vic 1300 EPA VIC (1300 372 842) WMS No: Task/Activity Grader Operation SPH Job No: Date

More information

SAFE WORK METHOD STATEMENT (Shaded sections to be filled in by Relevant Person)

SAFE WORK METHOD STATEMENT (Shaded sections to be filled in by Relevant Person) WORK ACTIVITY: Working Around Mobile Plant HIGH RISK COMPONENT: SWMS No. 04 SITE/PROJECT: PROJECT ID: Prepared for: Prepared by: Jet Excavators & Trucks ABN: 67 504 656 7 Prepared by: Michelle Falevaai

More information

Health & Safety Plan DEMOLITION WORKS: No 2 Substation

Health & Safety Plan DEMOLITION WORKS: No 2 Substation DEMOLITION WORKS: No 2 Substation Revision History Revision Date Section Detail of Amendment By r3a 09/10/14 First Issue JH 17 October 2014 Page 2 Revision 4 Contents 1. Description of Project 1.1. Introduction

More information

"CAUGHT-IN/BETWEEN HAZARDS IN CONSTRUCTION ENVIRONMENTS"

CAUGHT-IN/BETWEEN HAZARDS IN CONSTRUCTION ENVIRONMENTS PRESENTER'S GUIDE "CAUGHT-IN/BETWEEN HAZARDS IN CONSTRUCTION ENVIRONMENTS" Part of the "CONSTRUCTION SAFETY KIT" Series Quality Safety and Health Products, for Today...and Tomorrow OUTLINE OF MAJOR PROGRAM

More information

REFURBISHMENT DEMOLITION

REFURBISHMENT DEMOLITION CONTRACTOR WHS HAZARD STANDARD REFURBISHMENT DEMOLITION EXTERNAL USE ONLY Principles in the Optus Contractor WHS management process CONTRACTOR MANAGEMENT STAGES PRINCIPLES THIS STANDARD REQUISITION Requisition

More information

RISK ASSESSMENT SHEET

RISK ASSESSMENT SHEET Task Generic install telecoms equipment Assessment date 3rd October 2017 Location Various Review date 2nd October 2018 Number of staff at work Various Signature 1 Selected locations Works carried out during

More information

HSE Priorities for Construction Designers April 2007

HSE Priorities for Construction Designers April 2007 HSE CONSTRUCTION DIVISION PRIORITY RISKS 2004 ONWARDS Safety Priorities Work at height Reducing falls from height through: elimination by design; appropriate selection and use of equipment avoidance or

More information

Management Plan: Hazardous Materials Removal & Demolition

Management Plan: Hazardous Materials Removal & Demolition Management Plan: Hazardous Materials Removal & Demolition Kingswood School (Upper Site), Corby 1.0 Introduction 1.1 Background Lambert Smith Hampton has been instructed by Northamptonshire County Council

More information

OPTUS SUPPLIER WORK HEALTH & SAFETY POLICY

OPTUS SUPPLIER WORK HEALTH & SAFETY POLICY OPTUS SUPPLIER WORK HEALTH & SAFETY POLICY 1. Introduction 1.1 SCOPE & PURPOSE This policy (which includes this document and the work health and safety standards, policies, procedures and safety control

More information

ETELÄ KARJALAN JÄTEHUOLTO OY DRY DIGESTION FACILITY AND BIOGAS UPGRADING AND FILLING STATION DESIGN AND TURN KEY CONTRACT

ETELÄ KARJALAN JÄTEHUOLTO OY DRY DIGESTION FACILITY AND BIOGAS UPGRADING AND FILLING STATION DESIGN AND TURN KEY CONTRACT ETELÄ KARJALAN JÄTEHUOLTO OY DRY DIGESTION FACILITY AND BIOGAS UPGRADING AND FILLING STATION DESIGN AND TURN KEY CONTRACT SAFETY DOCUMENT, SAFETY REGULATIONS AND CODE OF PRACTICE 25.05.2018 Contents 1

More information

Ground Disturbance or Surface Penetration

Ground Disturbance or Surface Penetration PURPOSE To define the minimum requirements for managing the health and safety risks associated with ground disturbance or surface penetration activities. Where: Ground disturbance involves digging, excavation,

More information

Construction Safety Education Forum. 6 March Scaffolding. Dimitri Barlas, State Coordinator Construction Work Health and Safety Division DRAFT

Construction Safety Education Forum. 6 March Scaffolding. Dimitri Barlas, State Coordinator Construction Work Health and Safety Division DRAFT Construction Safety Education Forum 6 March 2013 Scaffolding Dimitri Barlas, State Coordinator Construction Work Health and Safety Division DRAFT SRWSD in confidence 1 Presentation Outline Introduction

More information

Trenching and Shoring Safety in Construction Environments. Leaders Guide and Quiz

Trenching and Shoring Safety in Construction Environments. Leaders Guide and Quiz Trenching and Shoring Safety in Construction Environments Leaders Guide and Quiz 4843 INTRODUCTION TO THE PROGRAM Structure and Organization Information in this program is presented in a definite order

More information

Client Duties. Co-operate with the project supervisor and supply necessary information

Client Duties. Co-operate with the project supervisor and supply necessary information Summary of Key Duties under the Procurement, Design and Site Management Requirements of the Safety Health and Welfare at Work (Construction) Regulations, 2006 This leaflet sets out the key duties of clients,

More information

FACILITIES MANAGEMENT CONTRACTOR SAFETY PROGRAM

FACILITIES MANAGEMENT CONTRACTOR SAFETY PROGRAM FACILITIES MANAGEMENT CONTRACTOR SAFETY PROGRAM Document History Version Date Comments 0.1 Sept 1, 2015 Initial Draft 0.2 Sept 30, 2015 Internal Review 0.3 Jan 25, 2016 External Review 0.4 March 21, 2016

More information

Asbestos Management Policy

Asbestos Management Policy ECM Document Set ID Number: 3428289 Revision Date: August 2016 July 2016 20 th July 2016 Risk Principal Approval Date: 20 th July 2016 Manager Works 20 th July 2016 Manager Building and Property Review

More information

!!! Sample Written Program For Your Company!!! Excavation Safety. 29 CFR 1926, Subpart P !!!!! Provided By:

!!! Sample Written Program For Your Company!!! Excavation Safety. 29 CFR 1926, Subpart P !!!!! Provided By: Sample Written Program For Your Company Excavation Safety Provided By: 29 CFR 1926, Subpart P P. O. Box 2136 Slidell, LA 70458 Phone: 985-781-1444 Fax: 985-718-4957 Email: info@se-safety.com 29 CFR 1926,

More information

Prevention of falls in housing construction

Prevention of falls in housing construction Compliance code Prevention of falls in housing construction Edition 1 October 2018 Contents Preface 2 Part 1 Introduction 3 Purpose 3 Scope 3 Application 4 Who has duties? 4 The risk management process

More information

Union County Vocational - Technical Schools Scotch Plains, New Jersey

Union County Vocational - Technical Schools Scotch Plains, New Jersey SECTION 024116 - STRUCTURE DEMOLITION PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 01 Specification

More information

Permit Requirements: Building Codes: The City of Clanton has adopted the following codes which are enforced by the Building Department:

Permit Requirements: Building Codes: The City of Clanton has adopted the following codes which are enforced by the Building Department: Permit Requirements: Any owner, authorized agent, or contractor who desires to construct, enlarge, alter, repair, move, demolish, or change the occupancy of a building or structure, or to erect, install,

More information

8 GROSVENOR GARDENS, LONDON NW11 0HG METHOD STATEMENT AND RISK ASSESSMENTS

8 GROSVENOR GARDENS, LONDON NW11 0HG METHOD STATEMENT AND RISK ASSESSMENTS 20 March 2006 Planning and Project Management Services 32 Sneath Avenue, London NW11 9AH Telephone (020) 8458 4519 Fax (020) 8209 1255 e-mail alvin@ppms.fsnet.co.uk 8 GROSVENOR GARDENS, LONDON NW11 0HG

More information

ABN: ADDRESS: 103 Copperfield St GEEBUNG, QLD 4034

ABN: ADDRESS: 103 Copperfield St GEEBUNG, QLD 4034 Page: 1 of 6 Page: 2 of 6 WORK HEALTH SAFETY (WHS) PACK 1 This is the larger pack is best suited to those undertaking structural landscaping, landscape construction and landscape maintenance. It includes

More information

Property and Public Protection Plan

Property and Public Protection Plan Property and Public Protection Plan OTTO CONSTRUCTION PROPERTY AND PUBLIC PROTECTION PLAN Otto Construction s pre-planning of construction activities includes procedures to protect the general public and

More information

Training Standard Draft Only

Training Standard Draft Only Title Duration Purpose/ Scope Occupational Relevance Health and Safety in Construction (Site Manager) Minimum 5 days of 6 learning hours per day Purpose: The purpose of training delivered against this

More information

CONTRACTORS CODE OF PRACTICE

CONTRACTORS CODE OF PRACTICE CONTRACTORS CODE OF PRACTICE HEALTH & SAFETY UNIT SUMMER 2007 CONTENTS 1 INTRODUCTION...4 2 APPLICATION...5 3 AIM...5 4 BEFORE COMMENCING WORK...5 5 CO-ORDINATION MEETINGS...5 6 RISK ASSESSMENT...6 7 TRAINING...6

More information

OSHA New Confined Space Rule

OSHA New Confined Space Rule OSHA New Confined Space Rule OSHA CLAIMS NEW CONFINED SPACE RULE WILL PREVENT 780 INJURIES A YEAR The Occupational Safety and Health Administration issued a final rule to increase protections for construction

More information

CONSTRUCTION WORK. Code of Practice JULY 2012

CONSTRUCTION WORK. Code of Practice JULY 2012 CONSTRUCTION WORK Code of Practice JULY 2012 Safe Work Australia is an Australian Government statutory agency established in 2009. Safe Work Australia consists of representatives of the Commonwealth, state

More information

Procedure. Work Health and Safety Contractor Management. Document number: PRO Rev no. Description Process Owner Approved for issue

Procedure. Work Health and Safety Contractor Management. Document number: PRO Rev no. Description Process Owner Approved for issue Procedure Work Health and Safety Contractor Management Document number: PRO-00808 This document is the property of Seqwater. It must not be copied or reproduced in any way whatsoever without the authority

More information

Worksite Safety Update Promoting safety in road construction

Worksite Safety Update Promoting safety in road construction Worksite Safety Update Promoting safety in road construction No 114 December 2011 In this Edition: Mobile Plant Safety Challenges for 2012 Page 1 Truck Mounted Attenuators Recent Developments Page 2 Traffic

More information