BarrierGuard 800. Temporary Steel Safety Barrier NCHRP 350 TL-3 & TL-4. Product and Installation Manual

Size: px
Start display at page:

Download "BarrierGuard 800. Temporary Steel Safety Barrier NCHRP 350 TL-3 & TL-4. Product and Installation Manual"

Transcription

1 Product & Installation Manual : BarrierGuard 800 BarrierGuard 800 Temporary Steel Safety Barrier NCHRP 350 TL-3 & TL-4 Product and Installation Manual Ph or visit July 2013 / Page 1

2 Table of Contents Application Guide Limitations and Warnings System Design Considerations Major Components List Installation Details Ground Conditions & Anchor Specifications Crash Cushions Delineators Installation Tools List Installation Procedure Full Height Terminal Installation Ramped End Terminal Installation Standard Section Installations Intermediate Anchoring Laying BarrierGuard Joining BarrierGuard 800 Sections Drilling for Anchors Maintenance & Repair Removal Special Operations Diagrams of Offset Expansion Joints External Anchor Shoe Connection Inner Anchor Shoe Connection Lifting BarrierGuard Truck Mounted Cranes Using Chains Using Tag Ropes Turning Barrier Over Safety Zones for Loading Loading and Unloading from Trucks Noise Pollution Risk Assessments Unloading and Loading Units Connection of Units Coring/Drilling for Installation of Anchor System Righting Inverted Units/Inverting Units Frequently Asked Questions Installation Check List Appendix A - Technical Drawings Appendix B - Letter of Acceptance Ph or visit July 2013 / Page 2

3 Preface The CSP Pacific BarrierGuard 800 is a temporary barrier system, in conjunction with an approved crash cushion, that is a rapidly deployable safety barrier for use where a vehicle restraint system conforming to NCHRP350 TL-3 or TL-4 is required. As with any roadside safety device, the BarrierGuard 800 must be installed properly to ensure proper performance. Thoroughly review and fully understand the instructions and product limitations before starting the installation. Do not start the installation without the proper plans and tools required. If you require additional information or have questions about the BarrierGuard 800 system please call CSP Pacific on or cspcustomerservice@csppacific.co.nz Introduction BarrierGuard 800 has been extensively tested in accordance with NCHRP 350 and has successfully demonstrated its capability to achieve the containment and performance Levels of Test Level 3 and 4. NCHRP350 TL-3 crash test criteria is an impact with a 2.2 Tonne vehicle at speed of 100kph at an impact angle of 25degrees. NCHRP350 TL-4 crash test criteria is an impact with a 8.0 Tonne vehicle at speed of 80kph at an impact angle of 15degrees and has the same containment energy as a TL-3 impact. BarrierGuard 800 is a deformable vehicle restraint system acting as a continuous beam, anchored to the ground at the end of each run through specially designed terminal sections. It consists of single elements of prefabricated 6.0m long or 3.0m long steel barrier. Two elements are bolted together at the factory providing 12.0m long or 6.0m long sections with male and female QuickLink connectors to facilitate speedy erection on site. Connection is achieved by lining up the barrier and locking the QuickLink connectors together. The permissible length of the system is unlimited as the barrier, which is only anchored at the end of each run, attains its performance characteristics by a combination of torsional rigidity and self-weight. System Application Guide BarrierGuard 800 is a versatile longitudinal steel barrier that has many uses and is quick and easy to install. BarrierGuard 800 is normally made up of two 6m barrier sections that are pre assembled by being bolted together to form a 12m length with the QuickLink linking system at either end. To make the BarrierGuard 800 as versatile as possible there are also sections made up from 2 No. 3m sections to create 6m lengths and a selection of short radius sections to enable installations around tight radii. Ph or visit July 2013 / Page 3

4 BarrierGuard 800 has successfully been tested with a selection of anchoring methods and in various ground conditions making it a versatile system that can be used on many differing surfaces. The barrier system is used as a temporary barrier for road construction sites where it can be used for nearside or offside applications to protect construction sites and construction workforce as a positive form of protection. It can also be used as a positive separation for opposing traffic flows in a contra-flow situation. With the versatile shorter barrier sections and radius sections most vertical and horizontal curve alignments can be accommodated so BarrierGuard 800 is just as useful for the local roads as well as on the State Highway network. Limitations and Warnings The BarrierGuard 800 systems have been designed and tested in accordance to the criteria detailed in the National Cooperative Highway Research Program Report No. 350 (NCHRP 350) for longitudinal barriers, and have been accepted for use by the US Federal Highway Administration (FHWA). For BarrierGuard 800 to perform as tested it must be correctly installed and anchored in accordance with the details contained in this manual. If the installation of the BarrierGuard 800 is not able to be flared as per this manual then there must be an approved NCHRP 350 TL-3 crash cushion connected to the barrier with a clear zone area of 6 x 22.5m adjacent to the crash cushion and behind the barrier that is flat and without hazards. In addition workers, equipment and materials should be a minimum of 6m behind the barrier. Please refer to the drawings in the appendix of this manual. When properly installed and maintained the BarrierGuard 800 allows an impacting vehicle to be stopped in a safe and predictable manner under the NCHRP 350 impact conditions. Vehicle impacts that vary from NCHRP 350 impact conditions described for longitudinal barriers may result in significantly different results than those experienced in testing. Vehicle impact characteristics different than, or in excess of, those encountered in NCHRP 350 testing (weight, speed and angle) may result in a system performance that does not meet the NCHRP 350 evaluation criteria. The adjacent road operating speed must be limited to 100kph for TL-3 performance. The installation should endeavour to minimise the impact angles to 25 degrees (1 lateral:2.14 forward). If the BarrierGuard 800 installation is for TL-4 performance then the operating speed must be limited to 80kph and impact angles minimised to 15 degrees (1 lateral: 3.73 forward). The system should be delineated in accordance with road controlling authority requirements. The BarrierGuard 800 needs to be installed on a firm surface that prevents the system from becoming embedded in the surface over long periods of time. Debris and foreign objects should not be in the clear zone. Ph or visit July 2013 / Page 4

5 Safety Statements General Safety All required traffic safety precautions should be complied with. All workers should wear required safety clothing (high visibility vests, steel capped footwear, gloves etc.) Only authorised trained personnel should operate any machinery. Where overhead machinery is used, care must be taken to avoid overhead hazards. Gloves should be worn at all times. System Design Considerations Slopes For the system to perform correctly it should be installed to ground that has a cross slope of no more than 8% or 1:8. On slopes greater than this, approval is required from the road controlling authority. Curbs BarrierGuard 800 can be installed to a surface which is raised by a curb of no more than 100mm high. If the barrier is installed next to the curb you must ensure that the curb is out of the clear zone and does not prevent the barrier deflecting as intended. If there is no option but to install in front, behind or on a curb, approval is required from the road controlling authority. Undulating Ground Conditions Site specific grading may be necessary to ensure that there are no humps or hollows that may significantly alter the impacting vehicles stability or substantially alter the height of the BarrierGuard 800 in relation to the ground. Ph or visit July 2013 / Page 5

6 Soil Conditions BarrierGuard 800 is installed above ground so soil conditions on site are not applicable. However it is recommended that the system is installed on a compacted surface. Underground services Before drilling for the installation of anchors it is important to check the area for any under ground services. Median and Roadside applications BarrierGuard 800 can be used in both roadside and median/bi-directional traffic applications. Anchoring conditions BarrierGuard 800 has been designed and tested to be used utilising several different types of anchoring conditions these include concrete, asphalt and soil, for further details please see page 10 of this manual. Clear Zone When anchored at both ends BarrierGuard 800 requires a clear zone of 1.5m behind to allow the system to perform correctly. When anchored every 12m the deflection is reduced 0.92m. Ph or visit July 2013 / Page 6

7 Major Components List BG800 12m section, male/female QuickLink BG800 6m section, male/female QuickLink BG800 with full height anchor BG800 with a crash cushion end treatment BG800 12m ramped end, male/female QuickLink BG800 6m ramped end, male/female QuickLink or bolted BG800 12m fixed gate post section Ph or visit July 2013 / Page 7

8 BG800 3m mobile hinge section BG800 6m wheeled gate section BG800 6m gate section All M16 Bolts used for connecting sections of Barrier Guard 800 together to be at least Grade 8.8 Ph or visit July 2013 / Page 8

9 Installation Details It is important that before any installation is carried out the correct planning and preparation takes place which includes a site visit. This is necessary to keep to a minimum the time spent on site and that the installation goes quickly and without issue. Things that need to be considered and checked are, any lifting restrictions i.e. low bridges, any underground services in the vicinity of drilling operations, layout and alignment of the barrier including any radii that the barrier may have to go round. It is important to also ensure the correct loading of the BarrierGuard 800, i.e. it is put on to the delivery truck the right way around and the terminal sections are in the correct place on the load. The ground conditions that the barrier is to be installed on and anchored to need to be established to ensure the correct anchoring choice is made and the appropriate anchor shoe is connected to the barrier. Full details of common ground conditions and the available types of anchors and anchor shoes can be found on pages 10 to 12. For use of BarrierGuard 800 on any ground conditions or anchors that are not shown in this drawing please contact CSP Pacific for advice. Standard NCHRP 350 tested BarrierGuard 800 only requires anchoring to the ground at each end of a run, there are integral anchor points beneath an easily removed cover at the extreme end of the specially designed anchor sections. There is a second anchor point at the first bolted joint up stream of the end of the section; these anchors can either be external or internal anchor shoes depending upon site restrictions or preference. Both the anchor shoes and the integral anchor points require 4 x anchor pins/bolts each (8 in total per end anchor section). The Length of Need of BarrierGuard 800 is the total installed length between the two Inner Anchor Shoes. The Beginning of the Length of Need is measured 6m from the approach (upstream) end of the BarrierGuard 800 terminal (at the Inner Anchor Shoe). If an approved, gating (nonredirective) end termination such as an ABSORB 350 crash cushion is connected to the BarrierGuard 800 terminal, then the Beginning of the Length of Need is 6m from the approach (upstream) end of the BarrierGuard 800 terminal (Inner Anchor point). If an approved, nongating (redirective) end termination such as a TAU II crash cushion is connected to the BarrierGuard 800 terminal, then the approach (upstream) end of such system becomes the beginning of the Length of Need. When deciding Length of Need of a system consideration must be given to the proximity of any anchor points to any excavations, if the BarrierGuard 800 is to be used to protect errant vehicles from excavations we recommend that the anchoring takes place beyond any excavation and if any extra anchoring is required it should be single sided away from the excavated face. The minimum recommended installed length of BarrierGuard 800 is 18m between Inner Anchor Shoes i.e. for an installation with no approved crash cushion connected to the end terminal; the minimum total system length including terminals and anchors is 60m. Please refer to the relevant drawings located in Appendix A. Ph or visit July 2013 / Page 9

10 Anchor Foundation Specifications The BarrierGuard 800 system has been designed to attach to concrete or asphalt foundations, or anchored into soil using driven piles. Use the anchorage specified on page 11, depending on the foundation at the specific job sit. 1. Concrete Pad Foundation: Min 150mm reinforced PCC pad or 200mm non reinforced PCC pad 150mm reinforced or 200 non reinforced 2. Asphalt over Subbase Foundation: Min 150mm AC over 150mm compacted DGA subbase 150mm 150mm 3. Asphalt only Foundation: Min 200mm AC 200mm 4. Asphalt over P.C. concrete Foundation: AC over PCC AC PCC 5. Compacted Subbase (DGA) Soil Foundation: Min 200mm compacted PGA subbase or equivalent soil properties Ph or visit July 2013 / Page 10

11 Material Specifications Portland Cement Concrete (PCC) Stone aggregate concrete mix, 28 MPa minimum compressive strength (Sampling per ASTM C31-84 or ASTM C42-84A, testing per ASTM C39-84) Asphaltic Concrete (AC) Compacted Subbase (DGA) AR-4000 A.C. (Per ASTM D3381 '83) 19mm maximum, medium (type A or B) aggregate Sieve Size % Passing 25mm mm mm No No No No mm minimum depth, 95% compaction, class 2 aggregate Sieve Size % Passing 75mm mm No No Ph or visit July 2013 / Page 11

12 Types of Anchor Anchor connecting to BarrierGuard 800 Flat top pin: 30mm Embedment depth: 400mm Hole size: 32mm x 450mm deep Can be used on foundation conditions types 1, 2, 3, 4 Flag top pin 30mm Embedment depth 400mm Hole size: 32mm x 450mm DEEP Can be used on foundation conditions types 1, 2, 3, 4 NOT TO BE USED EXTERNALLY OF TRAFFIC FACE 210mm galvanised threaded bar assembled with a M24 galv washer and M24 nut use with suitable chemical resin anchor. 150mm embedment. Can be used on foundation conditions type 1 only M24 x 460mm galvanised threaded bar assembled with a M24 galv washer and M24 nut use with suitable chemical resin anchor. 400mm embedment. Can be used on foundation conditions type 1, 2, 3, 4 M24 Mechanical anchor with effective embedment depth of 150mm. Can be used on foundation conditions type 1 only Special Special External Anchor Shoe Assembly Can be used with: 1" X 200mm Threaded bar 1" X 460mm Threaded bar M24 Mech anchor Flat top pins Flag top pins (non traffic face) Single Intermediate Anchor Can be used with: 1" X 200mm Threaded bar 1" X 460mmThreaded bar M24 Mech anchor Flat top pins Flag top pins (non traffic face) Double Intermediate Anchor Can be used with: 1" X 200mm Threaded bar 1" X 460mm Threaded bar M24 Mech anchor Flat top pins Flag top pins (non traffic face) External Anchor Shoe Assembly Can be used with: 1" X 200mm Threaded bar 1" X 460mm Threaded bar M24 Mech anchor Flat top pins Flag top pins (non traffic face) Subbase anchor pile Intermediate Subbase Anchor Can be used with Subbase anchor pile Special Subbase anchor pile 140mm Embedment depth of 800mm Can be used on foundation conditions type 5 MUST BE DRIVEN Ph or visit July 2013 / Page 12

13 Crash Cushions When choosing a suitable crash cushion for use with BarrierGuard 800 special consideration must be given to opting for a Gating (non re-directive) Crash Cushion or a Non-Gating (redirective) Crash Cushion. A Non-Gating Crash Cushion is one that has been tested to withstand a side impact from an errant vehicle and a Gating system is one that has not been tested for this impact angle. If opting for a Gating Crash Cushion then consideration must be given to allow for a safe run out area behind the system. If it is not possible to locate the terminal ends outside the Clear Zone, then an approved end termination (such as a crash cushion) can be fitted to the BarrierGuard 800. Any crash cushion will have its own anchoring specifications and assembly instructions. Any connection between BarrierGuard 800 and the approved end termination will be designed and supplied by either CSP Pacific or the approved end termination supplier. Approved end terminations that are currently available with designed connections are: i ii ABSORB refer to the CSP Pacific ABSORB 350 Product & Installation manual for number of units required. TAU II - refer to the CSP Pacific TAU II Product & Installation manual for further information. Please note that i is Gating (non re-directive)and ii is Non-Gating (re-directive). The performance of the selected crash cushion and the BarrierGuard 800 could be greatly affected if the barrier is positioned next to a curb or other fixed object, The barrier should be positioned so that all fixed objects are outside of the barriers Clear Zone for the speed and containment level. Delineators Depending on location, delineation may be required as per the Road Controlling Authority Guidelines. For further details consult MoTSaM, Part 2: Section 5 or contact CSP Pacific on or cspcustomerservice@csppacific.co.nz Ph or visit July 2013 / Page 13

14 Installation Tools List Lifting Device: Lifting Chains: Must have suitable lifting capacity and reach to lift, manoeuvre and install BarrierGuard 800 (e.g. Truck mounted crane such as a HIAB). It is also recommended that these cranes are remote control for ease of use A two leg assembly with a 2500kg lifting capacity, each chain is 2m long c/w a hook and locking clasp, and shortening clutch. This is suitable for lifting 12m sections of barrier and 6m sections made up from 2 x 3m sections only A two leg set with a 2500kg lifting capacity, each chain needs to be 3m long c/w hook and locking clasp, and shortening clutch. These chains are for lifting 6m lengths of barrier that are half of the 12m sections Tag rope: Drilling Equipment: Rope with spring loaded karabiner clip. The Rope length needs to be 1.5 times the lifting height of the barrier Either an electric hammer drill c/w 32mm drill bit or an Air driven Rock Drill c/w 33mm rock drill tool. To speed up installation consideration should be given to having 2 drilling machines available Also a Diamond Core drill suitable for cutting a 32mm hole up to 300mm deep in case of reinforcement bar when drilling in concrete Generator: Extension Leads: For use with the hammer drills, and or Diamond Core drill. Should be capable of a high enough output to drive two hammer drills at the same time as a minimum For generator above 10m Tape Measure Road Marking Paint and Chalk 2 x 1.8m Crow Bar/Wrecking Bar 8mm Allen Key 10mm Allen Key Magnetic BarrierGuard 800 T Bar socket and suitable handle Wooden Packers: Timbers: Approx 520mm x 300mm x 19mm, wooden ply wood packers. These are used to support barrier over uneven surfaces Two blocks approx 200mm x 200mm x 300mm. Approx 75mm x 75mm timber bearers Ph or visit July 2013 / Page 14

15 Small Impact Gun: Compressor: Extension Pipes: Spanners/Wrenches: C/w suitable sockets. 24mm impact socket as a minimum For the Rock Drills and Impact Gun. Should be capable of driving two rock drills at once For compressor above Combination spanners to include as a minimum 2 No each of the following 13mm, 24mm, 30mm, 32mm & 36mm 13mm and 19mm Drive Socket sets Torque Wrench (S): Torque Wrench (L): Suitable for torques up to 150 Nm. C/W suitable 24mm socket Suitable for torques up to 300 Nm. C/W suitable 32mm socket Podger (Round Pry Bar) Sledge Hammer Measuring Wheel Cranked Crow Bar: Useful for removing tight pins Ph or visit July 2013 / Page 15

16 Installation Procedure When planning the job it is essential that the following points are established and agreed with the client: The required performance level of the BarrierGuard 800 relevant to the operating speed environment; The start, finish and alignment of the BarrierGuard 800; Any additional anchorages required (e.g. to reduce deflection at a specific hazard that cannot be relocated away from the safety zone) and their locations; Any curvature of the BarrierGuard 800 in both the horizontal and vertical planes; The type of road surface and the method of anchorage; Any expansion joints are identified; In the case of concrete pavements, if reinforcement is encountered when drilling that this can be drilled through; The method of reinstatement of drilled holes when the BarrierGuard 800 is removed; There are no underground services, waterproof membranes etc. which could be damaged by drilling; There are no overhead cables that could be contacted by the lifting operation; and There is adequate working room and safety zone. Prior to loading in preparation for the job, the orientation of the BarrierGuard 800 must be determined and the truck loaded with all barriers facing the correct way and as the barriers are loaded a visual check on there condition must be carried out, if in doubt of the suitability of a damaged barrier do not use until checked by a competent person. Installation is normally started from the end of the BarrierGuard 800 and laid in the direction of traffic flow. Sometimes when a long length of BarrierGuard 800 is to be installed and site conditions allow, the installation can commence at any point along the length of the run, using a section of BarrierGuard 800 with two male ends as the first unit to be placed and subsequent standard sections laid outwards in both directions from this section simultaneously, this double male quick link section can easily be identified by applying a paint mark to the top external face of the barrier. BarrierGuard 800 is always secured at its end by a Ramped End terminal or transitioned to an approved end termination (such as a Crash Cushion). Details of Crash Cushion transitions are available from CSP Pacific. Ph or visit July 2013 / Page 16

17 Full Height Terminal Installation For External Anchor Shoe Applications: 1. Lower the terminal into the correct position as agreed with the client. 2. Drill through the External Anchor Shoe (DO NOT ANCHOR AT THIS TIME) anchor to the ground after completely connecting first standard section to the terminal section (see Standard Sections Installation section), use the appropriate method of anchoring as agreed with the client prior to installation (see Drilling for Anchors section). 3. Go directly to point 7 from the following (For Inner Anchor Shoe Applications section). For Inner Anchor Shoe Applications: 1. Mark out the location of the first Inner Anchor Shoe on the centre line of the barrier run 6m in from the start of the terminal section. 2. Centralise the Inner Anchor Shoe over this mark. 3. Drill through the Inner Anchor Shoe and fasten using the appropriate method as agreed with the client prior to installation (see Drilling for Anchors section). 4. Lower a male Full Height Terminal over the Inner Anchor Shoe so that the horizontal bars of the frame at the 6m joint are located inside the Inner Anchor Shoe frame. DO NOT LOCK THE BARRIER TO THE INNER ANCHOR SHOE AT THIS TIME. Completely connect the initial standard section to the terminal section first (see Standard Sections Installation section). 5. Reach through the access hatch and place shims between the horizontal bars of the frame and the Inner Anchor Shoe to take up any clearance. Ph or visit July 2013 / Page 17

18 6. Slide the Horizontal Locking Pin through the holes in the Inner Anchor Shoe, secure with retaining clips and replace the cover over the access hatch. 7. Remove the 8 No. bolts (3 along each side and 2 on the end) from the end cap section of the barrier and lift off the terminal cover (approx 30kgs). 8. Drill through the Anchor Plate and fasten using the appropriate method as agreed with the client prior to installation (see Drilling for Anchors section). Replace and secure cover. The anchorage at the departure end of the run uses a similar method to the approach end but with a female Full Height Terminal. The Inner Anchor Shoe position can either be determined by measuring 6 metres from the end of the outer skin of the last section of barrier already installed, or by temporarily placing the Full Height Terminal section in position and marking the joint line. For External Anchor Shoe applications, fixing is done with the terminal in place as with the approach end. Ramped End Terminal Installation CAUTION: THE USE OF A RAMPED END TERMINAL AT ANY EXPOSED LOCATION MUST ONLY BE USED IN SPEED LIMIT ZONES WITH A POSTED SPEED 50 KM/H OR LESS This is an identical operation to the Full Height Terminal Installation except the anchored end terminates in a ramp down to ground level as opposed to at full height. Follow the same procedure as for the Full Height Terminal Installation up to and including point number 6, then: 1. Remove the cover at the terminal end of the Full Height Terminal, drill through the Anchor Plate and fasten using the appropriate method as agreed with the client prior to installation (see Drilling for Anchors section). Replace cover. 2. Drill through the Anchor Plate and fasten using the appropriate method as agreed with the client prior to installation (see Drilling for Anchors section). Replace cover. The anchorage at the departure end of the run uses a similar method to the approach end but with a female ramped terminal end. The Inner Anchor Shoe position can either be determined by measuring 6 metres from the end of the outer skin of the last section of barrier already installed, or by temporarily placing the end terminal section in position and marking the joint line. For External Anchor Shoe applications, fixing is done with the terminal in place as with the approach end. Ph or visit July 2013 / Page 18

19 Standard Section Installation All sections must be physically bolted together through the top QuickLink plates using the double lock assembly shown in these photographs. These assemblies are pre-installed on the BarrierGuard 800 and the connected sections are simply bolted together by attaching the nut into the magnetic socket of the T Bar, lowering it through the hole located in the roof of the BarrierGuard 800 and placing it over the bolt thread. The T Bar can then be used to tighten the connection. At the beginning and end of each run of barrier each terminal section and the adjacent standard length of BarrierGuard 800 must also be bolted through the bottom QuickLink plate with an additional lock assembly. This applies to both the approach and departure end. This procedure is performed in the following way. If using the External Anchor Shoe. After placing the terminal section on the ground the next operation is to connect the next section of BarrierGuard 800 to it using the QuickLink and then secure the upper QuickLink plates as described above. These two sections are then lifted sufficiently so that wooden blocks no less than 200mm x 200mm in section and spanning the full width of the BarrierGuard 800 can be placed either side of the joint, and the BarrierGuard 800 lowered onto the blocks. The lower QuickLink plates are then secured by placing nut over the preinstalled nyloc nut and bolt assembly and tightening it. The BarrierGuard 800 can then be lifted, the wooden blocks removed and the barrier then placed on to the ground. Once this procedure has been carried out and the BarrierGuard 800 is placed in the correct position on the ground, the drilling of the anchor holes can be carried out (see Full Height Terminal Installation section) If using the Inner Anchor Shoe Carry out the procedures described above to secure both the upper and lower QuickLink plates of the QuickLink joint between the terminal section and the next standard section. After completing the above procedures lower the BarrierGuard 800 back onto the Inner anchor shoe and then anchor with the Horizontal Locking Pin (see Inner Anchor Shoe Applications section). This procedure must be carried out before the end of the terminal is fixed to the surface, before the External anchor is fixed or before the terminal section is locked to the Inner Anchor Shoe. Ph or visit July 2013 / Page 19

20 For the departure end, the procedure is similar to that of the approach end. Install the departure terminal in the usual fashion, but do not drill and fix the External Anchor, lock the terminal to the Inner Anchor Shoe or fix the end of the terminal to the surface. Once the system is connected and the top QuickLinks bolted together, lift the BarrierGuard 800 and place the two wooden blocks either side of the joint. Lower the BarrierGuard 800 onto these blocks and connect the lower QuickLink plates as with the approach end. Once the securing of the upper and lower plates of the QuickLink has been completed then either fix the External Anchor to the ground or lock the terminal to the Inner Anchor Shoe and then fix the end of the terminal as detailed in Ramped End Terminal Installation. Intermediate Anchoring Additional anchorage along the length of the installed BarrierGuard 800 may be specified. A requirement of the NZTA BarrierGuard 800 acceptance is that the maximum spacing between anchor points is 72m. This may be waived in special circumstances subject to an application in writing to the National Manager Traffic & Safety. It is recommended that continuous lengths of standard working width BarrierGuard 800 that exceed 480m (i.e. 40 standard 12m sections) have an intermediate anchoring at intervals not exceeding 480m. There are 2 different types of intermediate anchors for use with BarrierGuard 800 one that is connected at the QuickLink Joint and the second which is attached to the barrier at the bolted joint. To fit the Intermediate Anchor at the QuickLink joint, lower the barrier to the ground with the male end supported on a block at least 300mm high. Bolt the anchor plate to the barrier using the two tubes located inside the barrier on the lower QuickLink plate on the male end. Use M24 x 120 grade 8.8 bolts with nuts and a washer, the nuts and washers must be located inside the barrier. The bolts should be tightened to a torque of approximately 90Nm, i.e. normal spanner tight. Ph or visit July 2013 / Page 20

21 To fit an Intermediate Anchor at the bolted joint the BarrierGuard 800 must be inverted (see section on Lifting Barrier). Once the inverted BarrierGuard has been turned over and made safe the 2 No. small barrier joint plates need to be removed and swapped with the intermediate anchor small lower joint plates using the existing M16 fasteners. Then the L plate needs to be bolted to the two protruding plates using 4 No. M24 x 50mm bolts, nuts and washers, and on to this L plate the intermediate anchor can be fixed. Once either of the intermediate anchors have been fixed to the BarrierGuard 800, position the barrier in the usual way. After installation, drill through the intermediate anchor using the holes as templates and secure by the specified method (asphalt pins, mechanical anchor bolts or resin anchors according to pavement surface). Laying BarrierGuard 800 The barrier should be unloaded from the truck as detailed in the section Lifting BarrierGuard 800. If a truck mounted crane with remote operation is used, a minimum of a three man team is required. These operatives should carry out the following operations: One person is in charge of all movements and all directions should be given by that person only. This operative will usually operate the crane, guide the BarrierGuard 800 QuickLinks into place, and unhook the chains from the barrier. The second member of the team guides the barrier with a tag rope while it is being lifted down from the load. The third member of the team hooks the chains onto the barrier on the load. Before any lifting takes place this person must be in a safe and secure position. Joining BarrierGuard 800 Sections Caution: Keep hands and feet clear when connecting barrier units together. The BarrierGuard 800 should be suspended from the crane with the female end approximately 100mm lower than the male end. The female end is then lowered over the male end of the BarrierGuard 800 already in place and the QuickLinks connected leaving all faces of the BarrierGuard 800 flush with each other. The Maximum Allowable Tolerance at the joints is the female section should be no more than 10mm above the male end. Ph or visit July 2013 / Page 21

22 If this cannot be achieved, first check along the length of BarrierGuard 800 for alignment and adjust for horizontal alignment if necessary. If the ground is uneven and the male end is low, lift the male end of the installed BarrierGuard 800 and place plywood packers under the foot at the male end. If the BarrierGuard 800 still won t sit flush, unhook the leg of the chain nearest the joint being made, bring the other chain leg vertical and lift and lower on this leg. The last option is to lift the last installed section of BarrierGuard 800, place a timber bearer under the male end and lower the BarrierGuard 800 onto this timber bearer. Then lower the next section of BarrierGuard into place and connect. Once the connection is made and the joint flush, (within 10mm) raise the penultimate section and remove the timber bearer. If these methods do not work the barrier may be damaged and should not be used. Where the barrier needs to curve in the horizontal or vertical planes, a limited amount of adjustment can be achieved at the bolted joint (see section on Curved Barrier). To achieve this, remove the cover by the bolted joint and slacken all the bolts. This can be best done using an impact wrench. If this is not available use a ring spanner. The loosening process can be helped by hitting the domed head of the bolts with a large, copper mallet while pulling on the spanner. Re-tighten the bolts. Drilling for Anchors Hole Sizes Holes for securing BarrierGuard 800 are drilled 32mm diameter for the asphalt pins and mechanical anchor bolts and 34mm diameter for resin anchors. Using Hammer Drill Drilling Asphalt There are several connection systems, check when preparing equipment that the drill bit fits the drill. Normally take two of each size of drill bit required. Before inserting the drill bit into the drill chuck, wipe clean the mating part and, if a SDS drill, grease with a small quantity of grease. Drill bits wear. When blunt it is not worth re-sharpening them as they will also have worn on the diameter and will produce an undersize hole. Drilling through asphalt in flexible pavement may be slower than drilling concrete. There is an increased risk of the drill dust jamming the drill bit so regularly lift the drill out of the hole when drilling. On deep holes, start with a short drill bit for maximum drilling speed and change to a longer drill bit when necessary. Drill through the steel plate to a depth of 500mm below the top face of the plate. This depth is correct for both steel pins and resin anchors. Do not drill deeper (bridge decks or special surfacings may require different depths of hole). Ph or visit July 2013 / Page 22

23 Drilling Concrete Drill with the Hammer Drill on high speed. It is not necessary to push down on the drill, the weight of the drill is sufficient. If the drill has ATC it needs to be only lightly held. Remove the drill from the hole frequently to clear the dust. Drill to a depth of 240mm below the surface of the plate being drilled through. Use tape on the drill bit or a depth stop. Do not drill deeper than necessary. If reinforcing bar is found in the concrete, stop using the hammer drill and drill through the bar with a diamond core drill (see following section Using a wet diamond core drill). Using a Wet Diamond Core Drill The diamond core drill is generally used just to cut through reinforcing bar found when hammer drilling concrete. The system used consists of a drill incorporating a slip clutch, a connection between the drill and the core bit incorporating a swivelling water connector, the diamond core bit and a pump up water bottle and hose. Always carry a spare core bit. To use, pump up the water bottle and adjust the feed tap until there is a steady trickle from the drill. Start the drill on high speed and carefully feed the drill bit down the hole. Drill with light pressure but hold the drill tightly as the bit may jam. Progress will be slow through the reinforcing bar. As soon as the drill starts to cut faster, you are back in concrete. Withdraw the core drill, check to see if the rebar has come out inside the core drill. If not, drill down the hole for a few seconds with the hammer drill and then fish out the cut rebar with a magnet on the end of a rod. Carry on drilling with the hammer drill. Maintenance and Repair With years of use around the world and through rigorous testing BarrierGuard 800 sections have proved to be very robust and extremely hard wearing. That said however we do advise and recommend some very basic maintenance schedules detailed below. The BarrierGuard 800 sections should be thoroughly inspected prior to dispatch to the job site, during this inspection checks should be made that all the fasteners are present, there is no sign of damage to the QuickLinks, no excessive penetrating rust, no tears in the barrier wall that have left a sharp edge or could create a snag point, the gap between the two sections of barrier at the bolted joint does not exceed 15mm, and that there is no creases or dents in the barrier that could prevent it connecting together during the installation. If any of the above faults are detected then the damaged section or sections of barrier should marked and put to one side for further assessments to take place and repairs made before the section of BarrierGuard 800 is used again. As BarrierGuard 800 is predominantly used for road work situations it is very easy to check the condition of the installed barrier as there is usually personnel driving through the site, and also as the barrier is usually only installed for medium or short term it can be regularly inspected as it is returned to storage and again inspected as it is dispatched to the next job site. However, for more remote site installations a 12 monthly drive by inspection is recommended, consideration should be given to making these inspections more frequent if the site has a history of regular impacts. Ph or visit July 2013 / Page 23

24 The drive by inspection is usually achievable by driving fairly slowly along the length of the installed barrier, depending on the location and site conditions then this may require additional safety systems put in place for example traffic management. During this inspection checks should be made for any damage to the barrier sections such as tears to the barrier skin that could cause a snag point, also a visual check that the anchor pin is in and also inspect for any signs of impacts along the barrier run. If there is a tear that could potentially create a snag issue then the relevant section of barrier needs replacing as soon as possible. There are three levels to the signs of impacts, firstly a glancing blow this usually just leaves a black or paint mark on the barrier wall, this type of impact usually requires no further inspection or action, secondly the more heavy impact could cause the barrier to be pushed out of alignment, the barrier can normally be put back into position fairly easily by using a long pry bar to move the barrier back in to position, the third is the extreme impact where the barrier has been impacted by a force way in excess of a design impact, signs of this would be large deflection of the barrier (over 1m), significant deformation of the BarrierGuard 800 profile and potentially tears in the barrier wall. If there are signs of an extreme impact then a more thorough inspection should be carried out as soon as possible. The barrier sections will need to be replaced in the installation and the damaged sections taken away for further analysis, if they are severely deformed or torn, the gap between the barrier sections at the bolted joint are in excess of 15mm or if there are any signs of deformation of the pegs of the QuickLink. If the sections to be replaced are with in a short distance from the end (or beginning) of the barrier run then it is generally much quicker and easier to remove sections from the end working towards the damaged sections. If the sections to be removed are a long way from an end then the barrier installation will need to be split at one of the bolted joints. This is done simply by gaining access to the nuts through the inspection hatch and removing the fasteners and plates at the joint, this will then enable the barrier run to be lifted section by section from this split joint. (It is advisable to split the bolted joint down stream of the damaged area or ahead of the damaged area). Any fasteners that need replacing because of loss or damage must to the correct specification and performance; the bolts must have an 8.8 strength classification and be the correct type of fastener for the application. Although tears and deep scratches normally do not affect the performance of the barrier system it should be remembered that this may introduce corrosion to the barrier units, so the application of a protective coat of zinc rich paint maybe necessary locally in the area of the damage. Do not use any sections of barrier that show signs of significant thinning of the barrier skin caused by corrosion. For any further information or advice on levels or extent of damage please contact CSP Pacific on or cspcustomerservice@csppacific.co.nz Ph or visit July 2013 / Page 24

25 Removal This is a reversal of the installation procedure. Bolts can be unscrewed but will be tight for the full length of the thread due to the cone nut being squeezed onto the bolt. Do not tap the bolt down as it will release the cone from the sleeve and the cone will turn with the bolt and not unscrew. If the cone comes loose from the sleeve, crowbar the bolt upwards and retighten the bolt before attempting to unscrew the bolt. After removing the barrier/anchor, remove the anchor bolt sleeves which project from the concrete. Resin anchors unscrew easily. Cut off the plastic tubes which project from the concrete. Asphalt pins can normally be loosened by tapping sideways with a hammer and pulled out of the hole. Alternatively, a pin removal tool may be fabricated that allows the flag top to be levered to aid removal. See adjacent photograph and photograph below for details. Tight pins in the terminal end and inner anchor shoe can be attached to the crane using a ring and shackle. Apply a small amount of lift and rotate the pin by using a large adjustable spanner on the "flag" part of the pin. Driven pins used for securing intermediate anchors are best withdrawn by lifting the barrier with a 3 tonne strap passed under the barrier next to the anchorage. To separate the barrier sections, lift with the chain legs at equal length. This will tend to lift the connected end first. If the section of barrier being removed lifts the next section, place a 50mm high block under the foot of the section being removed next to the joint to be separated and lower the barrier. It will then separate. Ph or visit July 2013 / Page 25

26 Special Operations Curved Barrier In many cases, the barrier may have to follow a curve. There are a number of options depending on the curve. These are described below followed by a table of curvatures that can be achieved and methods of estimating the curvature. 1. Movement at the QuickLink - this allows slight curvature usually sufficient for horizontal curves on motorways and dual carriageways. 2. Slackening the bolts in the standard joint in the middle of a 12m section and retightening after "bending". 3. Replacing the standard joining plates at the bolted joint in the barrier with slotted plates designed to allow up to a 5 bend in the barrier. Where these plates are fitted the bolts need to be slackened slightly to set required angle and then all bolts of the joint where the plates are installed must be re-tightened. 4. Using shorter barrier lengths. If methods 3 and 4 are used with 12m barrier sections, a 10º bend can be achieved in 12m. If, however, the 6m (2x3m) barriers are used then effectively the radius is halved. Ph or visit July 2013 / Page 26

27 Diagrams of Offset: Offset Ends to Barrier It is sometimes required that the ends of the barrier are angled away from the traffic flow. This can be achieved by utilising the movement in the QuickLinks to curve the BarrierGuard 800 layout to create a flare away from the traffic lane. Ph or visit July 2013 / Page 27

28 BarrierGuard Gate Installation A BarrierGuard 800 Gate can be installed in a length of BarrierGuard 800 at any predetermined and pre-planned point along its length within 24m of the start point and end point. To install a BarrierGuard 800 Gate, a 12 m Female QuickMount Fixed Gate Post is introduced into the run by connecting it to the previous section using the standard QuickMount connector. To this section a 3m Mobile Gate section is connected using the two gate hinge pins. The pre determined number of 6m Wheeled Gate sections are attached to the 3m Gate Section using a standard bolted joint to make the gate 9m short of its required length. A standard 6m Gate section is joined to the last 6m Wheeled Section and a 3m Mobile Gate section bolted to the other end of it. This second 3m Gate Post section is connected to a second 12m Male QuickMount Fixed Gate post using two further hinge pins. The normal barrier installation using the QuickMounts can then resume from this departure end Fixed Gate post (See Diagram). At each end of the BarrierGuard 800 Gate an External Anchor shoe will be attached to the Fixed Gate post and will require anchoring (see For External Anchor Shoe Applications section). In addition, at the QuickMount joints immediately before and after the gate, an intermediate anchor will be required (see Intermediate Anchoring section). BarrierGuard T-Top is also required to be added to the top of the barrier for the BarrierGuard 800 Gate installation. This T- Top is a standard 6m T-Top section and attached in the conventional way along the length of the gate and for a gate installation only, at least 12m before and after the anchor point of the Fixed Gate Post except at the hinge point where a special removable section is used. Expansion Joints Expansion joints are not required on long runs of barrier on normal carriageways. Where expansion joints exist in the road surface, such as at the edges of a bridge deck, these should be mirrored in the BarrierGuard 800. If the barrier is anchored either side of a bridge i.e. not on the bridge structure but into the ground either side of the structure then there is no need for expansion joints in the BarrierGuard 800. Expansion within the system is catered for by replacing the standard coupling plates found in the connection between two 6m elements with special plates which have elongated slots enabling movement of the system under temperature fluctuations. These units should be preinstalled and correctly located and identified on the load for speed of installation. If this is not possible however, this process can be performed on site. For sites where the expansion of the ground that the BarrierGuard 800 is to be anchored to is a concern there is a special section of BarrierGuard 800 called a Variable Length Section which could be used. The barrier expansion joint has a movement of 100mm. Where the road surface expansion joint movement is expected to exceed this amount additional expansion joints can be used on adjacent sections. Expansion joints could allow extra deflection of the barrier when hit. This can be prevented by securing the barrier either side of the expansion joint with intermediate anchors. Adjust the gap between the barrier sections at the expansion joint before installation to reflect the situation - cold day large gap hot, sunny day small gap. Torque the nuts to 100 Nm. Ph or visit July 2013 / Page 28

29 External Anchor Shoe Connection The External Anchor Shoe can be preinstalled into the BarrierGuard 800 or anchored to the ground and then BarrierGuard 800 placed on top of it and connected in the same way as the Internal anchor shoe (see Inner Anchor Shoe section). Any excess longitudinal slack in the anchorage is taken up by hanging the required number of shims from the steel retaining pin. Ph or visit July 2013 / Page 29

30 Inner Anchor Shoe Connection The Inner Anchor Shoe is connected to the BarrierGuard 800 by first opening the inspection hatch located on the side of the unit. Any excess longitudinal slack in the anchorage is taken up by inserting the required number of shims. The steel retaining pin is then pushed through the two guide holes on the Inner Anchor Shoe and held in place with a spring clip. The inspection hatch is then replaced. Ph or visit July 2013 / Page 30

31 Lifting BarrierGuard 800 Each standard 12m section of BarrierGuard 800 weighs 1080kg. If using the normal method of installation with a truck mounted crane (HIAB) then the safe working load of the crane must be in excess of 1.08 tonnes at a reach of 8m to enable 12m units to be safely offloaded, loaded and installed on site. BarrierGuard 800 is lifted with two leg chains attached to the lifting points on the top of the barrier. Each individual piece of BarrierGuard 800 has two lifting points and when these pieces are bolted together to make up a normal section of BarrierGuard 800 there are four possible lifting points along its length. (BarrierGuard 800 has identical lifting points on the underside to facilitate lifting inverted sections). If the barrier to be lifted has a bolted joint in its length (I.E. a section made from two pieces) then using the standard chains, the barrier must be lifted from the lifting points closest to and either side of this bolted joint. If the length of barrier is a piece without a joint in the middle (I.E. an individual piece) then the longer chains are required as the lifting points are at either end of the piece. Truck Mounted Cranes It is essential that the operators of such equipment are fully trained and are aware of the regulations related to lifting and lifting equipment. These brief notes are not intended to replace or supplement any training course that the crane operator should attend. However, they give an erector an indication of the factors that have to be considered by the authorised crane operator. Ph or visit July 2013 / Page 31

32 Before using the lifting equipment some of the things that it can be recommended the operators should check are: The safe working load of the equipment That there are no defects with the equipment That there are no overhead cables That the vehicle is stabilised That the vehicle is on reasonably level ground Before lifting the load it is recommended the operator should: Check the safe working load of any slings or chains Establish the weight of the load Check that the area to receive the load is clear Ensure that the load will not swing out of control Ensure that the load is balanced When lifting the load it is recommended the operator should: NOT swing the load over any other workers NOT allow others to walk under a suspended load NOT allow the load to swing out of control NOT swing the jib or load over a live traffic lane NOT exceed the safe working load After lifting the load the operator should: Stow the crane in such a way that it cannot move during the transit. Using Chains All fabric slings and metal chains must be checked before use to ensure: That they are undamaged; and The load imposed is within their capacity The recommended chains to use are two leg sets each leg 2 metres long, each with a shortening clutch to allow tilting the barrier if required. They are rated at 2 tonnes per pair provided that the angle between the legs does not exceed 90 or 2 tonnes per leg if one leg is used with the chain vertical. It is recommended that before using the chains: Check the number on the chain against the test certificate and check that the test certificate is current. Ph or visit July 2013 / Page 32

33 Check the chain for damage - look at the links for distortion and nicks. Look at the hooks - not bent open, not twisted, latches working; Check the chain lengths for the lift being carried out, and shorten one leg if necessary to adjust the slope of the barrier. Shortening one chain will raise the end with the short chain. Check the chain is properly seated in the shortening clutch. If hook type shortening clutches are used the chain goes across the hook into the slot formed by the hook. The point of the hook does not go into the chain link! Check chains are not twisted before hooking on. When hooking on to the barrier, make sure the hook is around the bar that runs across the slot. NEVER HOOK ONTO THE SHEET STEEL DIRECTLY. Make sure the hooks face outwards, i.e. the open side of the hook nearest the end of the barrier. Avoid overloading chains. This is particularly easy to do by snatching the chains, as when turning the barrier over. A chain which has been overloaded can break at any time. Inspection cannot detect imminent failure. A chain break can kill. Report any chain that has been overloaded - it must be replaced. When loading barrier on to trailers generally use the chains at equal length. This will give the barrier a slight slope down to the male end. Terminal end sections are heavier at the terminal end. Shorten one chain by about six links and attach the shortened chain to the terminal. Barrier where the central joint has been angled to follow a curve will not lift level with a two leg chain. Where the angle is more than 1-2 it is advisable to use 2 two leg chains on the crane hook. One two leg chain will need to have 3 metre legs, both with shortening clutches. The other two leg chains will need to have 6 metre legs, both legs with shortening clutches. Both chains need to be rated at least 1.4 tonnes at to vertical. Hook the 3 metre chains to the lifting points nearest the bolted joint and use the 6 metre legs for the outer lifting points. Adjust chain length for even lifting but keep the angle to the vertical of the outer chains less than 60. Ph or visit July 2013 / Page 33

34 Using Tag Ropes Use tag ropes to control the position of the barrier being lifted. They should not be too long, 8 metres is adequate for a load 3 sections high. They should be attached to the lifting eyes towards the ends of the barrier sections,. A light pull for a limited period is all that is needed to control the barrier; any more will give the barrier momentum which has then to be stopped. Do not wrap the rope around your hand or fingers and avoid treading on or over the rope. Keep at least 3 metres from the barrier as slight adjustments with the crane can cause a pendulum effect along the barrier. Never get between the length of the barrier and a solid object. A swinging barrier carries energy and can crush. Turning the Barrier Over In order to stack the barrier or work on the fastenings inside the barrier it is occasionally necessary to invert the barrier. Do not turn the barrier over by pulling it sideways with the crane. This can cause damage to the crane and chains which could cause an accident due to failure during subsequent lifting operations. The following method can be used but note that the chain hooks are subject to side load when using this method. Always, therefore, use hooks that are well overrated (typically 2 tonnes per hook) and use of the conventional type, not the type where the chain attaches to the extended latching bar. Inverting BarrierGuard 800 Lower the barrier onto a wooden block so that the barrier settles on the block near the centre of the barrier clear of cross members and with only one side of the barrier supported by the block. Continue lowering the barrier until it lies on its side. Transfer the chains from the lifting eyes on the top of the barrier to the lifting eyes on the bottom of the barrier and lift the inverted barrier. CAUTION - WHEN THE BARRIER IS SET DOWN INVERTED IT IS UNSTABLE AND MAY FALL OVER CAUSING INJURY. Ph or visit July 2013 / Page 34

35 Righting Inverted BarrierGuard 800 Lower the barrier onto a timber wedge with approximately a one in three slope. The barrier will settle on its side. Transfer the lifting chains from the bottom of the barrier to the top of the barrier and lift in the normal way. CAUTION - WHEN INVERTING AND RIGHTING BARRIERS THE BARRIERS MAY KICK SIDEWAYS, ALWAYS KEEP AWAY FROM THE BARRIER - Control by the use of tag ropes. Safety Zones for offloading and loading The swinging load must be controlled with correctly fixed tag ropes. The loads must not be allowed to swing over or into live traffic lanes. Suitable safety zones will need to be considered as part of the planning process. The decision regarding these zones will need to take into account the lengths of the units being delivered. Strong winds will affect the controllability of the suspended load and risks must NOT be taken. The load should be lowered so that it is immediately above the ground as soon as it is clear of the truck and then jibbed out to the final position. Ph or visit July 2013 / Page 35

36 Loading and Unloading from Trucks When loading trailers it will be necessary for somebody to be on the top of the load to position the barrier and detach the lifting chains from the barrier. This is a potentially dangerous operation and great care must be taken. precautions must be observed:- The following When climbing onto the load a ladder must be used. This must extend at least 1 metre above the load. It must be held at ground level by a second person. All barriers being placed should be controlled by a tag rope, preferably two, and certainly two ropes in windy conditions. The barrier should not be lifted over the person on the trailer. Where it is necessary for the person to get to the other side of a barrier being placed the barrier should be put down temporarily on the trailer and the person climb over the barrier. Observe the same precautions when unloading. Barrier is usually loaded with the male ends at the front of the truck. Some loads may need a terminal end on the top or bottom layer. A female terminal end, if required, will usually be on the bottom layer in the centre of the trailer with the terminal towards the front of the trailer. A male terminal end, if required, will usually be on the top layer of the trailer with the terminal towards the back of the trailer. A minimum of 2 No. wooden bearers are required to support each layer of barrier. Trailers with side posts and head board These are loaded with 3 layers of barrier, 5 per layer (15 in total), all the right way up. To load the barrier first remove the side post extensions on the side the load is being loaded. Place the first layer directly onto the cross frames of the side post. Between the first and second and second and third layers use 75mm square hardwood cross bearers (2.9m long). Place two per layer, one each by the posts in a position to clear the feet of the layer above. After placing the third layer replace the side post extensions and secure the load with tie bars across the top of the posts. Note: When loading barrier which has been angled at the bolted joint, in order to follow a curve only four lengths can be carried per layer (12 in total). Ph or visit July 2013 / Page 36

37 Other trailers with no side posts These are loaded with a maximum of 3 layers of barrier, 5 barriers per layer (15 in total). On each layer the outer two barriers and the centre barrier are the right way up and the barriers between them inverted. Place the first layer directly on the trailer and secure it with two 2000kg ratchet straps. Place two 75mm square hardwood bearers on top of the barriers before the second layer. Ideally they should be 2.5 metres long, but 2.9 metre timbers can be used at an angle across the trailer. The timbers should be placed about 2 metres from the ends of the barrier and clear of the feet of the inverted first layer units and the feet of the second layer units. Secure the second layer with two 2000kg ratchet straps. Place the third layer on similar timbers and secure with ratchet straps. When placing ratchet straps over the layers, ensure that the two on the bottom layer are nearer the centre and space the straps for the subsequent layers further out towards the ends. On each layer not secured by a head board, prevent the load from sliding forward by passing a strap or chain through the male connections on the front of the barrier and diagonally back to the trailer. If straps are used, use sleeves to prevent the barrier chaffing the straps. Note: When loading barrier which has been angled at the bolted joint in order to follow a curve, only four lengths can be carried per layer and all must be the right way up (12 total). Noise Pollution The BarrierGuard 800 installation process requires the use of trucks, cranes and drilling equipment for fixing the anchors. Whilst this type of plant and equipment does not create excessive noise, care and consideration must be taken when working in residential areas at night. Ph or visit July 2013 / Page 37

38 Risk Assessments Whereas these Risk Assessments outline the basic hazards and risks involved with installing BarrierGuard 800, you must provide your own, detailed Risk Assessment which will encompass your particular working environment and may require site specific information for certain applications. Unloading and Loading Units Hazard Precautions to minimize the risk Actions Injury to head Use of PPE (hard hats) Instruction Injury to hands Injury to feet Load slipping from crane Load swinging into other vehicles Units becoming dislodged while unsecured Units falling from delivery vehicle Competent crane operator/s Operative to be vigilant Use of PPE (gloves) Use of correct tools Competent crane operator/s Operative to be vigilant Use of PPE (safety boots) Competent crane operator/s Operative to be vigilant Use certified approved slings Competent slinger Use correct tag ropes Establishment of correct safety zones Competent crane operator Competent slinger Follow correct sequence for unloading/loading Operatives to stay clear of side of vehicle while unloading/loading Competent crane operator Instruction Instruction Inspection Ph or visit July 2013 / Page 38

39 Unloading and Loading Units continued Hazard Precautions to minimize the risk Actions Slinger falling from vehicle or Safe access and egress to vehicle and Instruction load load Injury from manoeuvring delivery vehicle Injury from traffic Electrocution from or damage to overhead power lines or cables Operative to be vigilant Competent crane operator Competent driver Operatives to be vigilant Correct traffic management procedures Operatives to be vigilant Site inspection prior to installation Connection of Units Hazard Precautions to minimise the risk Actions Injury to head Wear hard hats Instruction Injury to feet Wear steel toe capped boots Instruction Injury to hands or fingers Injury from collision with passing traffic Wear gloves Carry out all operations under the control of a competent crane operator Adhere to correct and approved working methods Use correct tools Correctly installed traffic management / Instruction Ph or visit July 2013 / Page 39

40 Coring/Drilling for Installation of Anchor System Hazard Precautions to minimize the risk Actions Electrocution Before installation procedure: Damage to Under Ground Services Inspect services plans; Use cable locating equipment and Mark the position of underground apparatus Injury to eyes Use of PPE (safety glasses) Injury to ears Use of PPE (ear muffs) Dust inhalation Use of PPE (approved dust mask) Injury to skin from chemical Use of PPE (safety gloves) anchor resin Injury from traffic Correct traffic management procedures Operatives to be vigilant Righting Inverted Units/Inverting Units Hazard Precautions to minimise the risk Actions Load slipping Use certified slings Use competent operator Inspection Injury to heads Wear hard hats Instruction Injury to feet Wear steel toe capped boots Instruction Injury to legs Death or injury as a result of manoeuvring truck Injury from collision with passing traffic Undertake operation in safe restricted area under control of competent crane operator only All truck movements under control of competent crane operator Correctly installed traffic management / Instruction Ph or visit July 2013 / Page 40

41 Frequently Asked Questions 1. What equipment is required to install BarrierGuard 800? BarrierGuard 800 is too heavy to lift by hand so suitable lifting equipment will be necessary, you will also require a few tools for drilling the anchors and tightening up all the fasteners after installation. A full list of equipment can be found inside the manual. 2. With BarrierGuard 800 installed will this prevent surface water being able to run off the carriage way into the drainage channels? The design of BarrierGuard 800 incorporates 250mm long feet located at regular intervals along the barrier. These feet are 30mm tall so create a 30mm gap underneath the barrier that allow adequate drainage. There are three steel feet per 6m element and two per 3m element. 3. Can I install BarrierGuard 800 around curves and bends? Yes, there are several methods for achieving radii with BarrierGuard 800 to follow the curve in a road. The movement in the QuickLink and slacking the bolted joints. For further details on these and to help you work out the radius you are looking to achieve please refer to the Special Operations Curved Barrier section of this document. 4. How many units can I get on one truck? Up to 144m (non inverted) can be loaded onto a single truck, this may be increased depending upon local restrictions, by mounting special frames to the trailers to allow the safe loading of more barrier sections. 5. How long does BarrierGuard 800 take to install? Up to 288m of standard BarrierGuard 800 can be installed in 1 hour. 6. What is the width of the footprint of BarrierGuard 800 The width of the footprint of BarrierGuard 800 is 540mm 8. Can I anchor BarrierGuard 800 into a bridge deck? Usually yes, although you should work closely with the bridge designers to make sure that there is no damage caused to the bridge structure by any of the BarrierGuard anchors. Contact CSP Pacific for advise on any specific anchoring requirements. Ph or visit July 2013 / Page 41

42 BarrierGuard 800 Installation Checklist Y/N The units are positioned on level ground i.e max across and approach slope of 1:8 All security bolts on the QuickLink are attached and tightened All the hatch plates shut and bolt tightened Are intermediate anchors required? Note: NZTA requires intermediate anchors at a maximum spacing of 72m unless there is waiver from NZTA National Office Is an approved crash cushion required? Workers and equipment are not located in the CoPTTM safety clear zone Are all hazards located outside the clear zone? Are all tools removed from site when installation is complete If delineation is required it is applied as per MoTSam Part 2 Clear any debris from under and between the units Arrange maintenance inspections as appropriate for location Notes: Location: Installed by: Date: Inspected by: Date: More information on BarrierGuard 800 can be found at or call CSP Pacific BarrierGuard 800 July 13

43 Appendix A - Technical Drawings Re-directive page 44 Non Re-directive page 45 Flared page 46 Ph or visit July 2013 / Page 43

44 Re-directive Ph or visit July 2013 / Page 44

45 Non Re-directive Ph or visit July 2013 / Page 45

46 Flared Ph or visit July 2013 / Page 46

47 May 2013 Interim Acceptance for Safety Barrier Product Product: BarrierGuard 800 TM Steel Barrier System Safety Barrier - Temporary Expiry Date: 30 June 2017 The BarrierGuard 800 TM Steel Barrier System is a temporary steel barrier system comprising 6m or 12m sections fabricated from galvanised steel panels joined using a proprietary connection system, terminating with ground anchored end sections protected by the use of a crash cushion. The system has been tested under EN 1317 test conditions with the submitted results being accepted by the FHWA as equivalent to NCHRP Report 350 Test Level 4 (refer FHWA Letter B-131). The FHWA concluded that from the tests carried out, in-service impact deflection of up to 1.5m should be allowed for in any temporary traffic management plan. The FHWA later approved a number of variants of the BarrierGuard 800 TM Steel Barrier System including Minimum Deflection (refer FHWA Letter B-158); BarrierGuard Gate (FHWA Letter B-159) and Variable Length (refer FHWA Letter B-160). Only the BarrierGuard Gate is considered to be part of this BarrierGuard 800 TM Steel Barrier System acceptance. All other variants require site specific acceptance on a case-by-case basis from the National Manager Traffic & Safety. Based on these results, and pending further updates to the NZ Transport Agency s M23 Specification for Road Safety Barrier Systems, the BarrierGuard 800 TM Steel Barrier System is granted interim acceptance by the NZ Transport Agency for use on the State highway network, with the following conditions as detailed below. A copy of this Interim Acceptance Letter must be appended to the Installation Manual. Product Identification BarrierGuard 800 TM Steel Barrier System Interim Acceptance for BarrierGuard 800 TM Temporary Barrier System May 2013 Page 1

Installation Manual. Orion. TL-3 Steel Barrier. VHD (v2)

Installation Manual. Orion. TL-3 Steel Barrier. VHD (v2) Installation Manual Orion TL-3 Steel Barrier VHD (v2) 300914 Table of Contents Orion Introduction.......... 3 Limitations & Warnings. 4 Before Installation..... 3 System Design & Design Considerations

More information

ArmorZone TL-2 Barrier and End Treatment

ArmorZone TL-2 Barrier and End Treatment ArmorZone TL-2 Barrier and End Treatment Product and Installation Manual ANOTHER AMORFLEX DEVELOPMENT Table of contents Introduction 3 System Overview 3 Before Installation 3 Limitations and Warnings 4

More information

TL-2 Plastic Water Filled Barrier

TL-2 Plastic Water Filled Barrier TL-2 Plastic Water Filled Barrier Product Manual ANOTHER AMORFLEX DEVELOPMENT Table of contents Introduction 3 System overview 3 Before installation 3 Limitations and warnings 4 Safety statements 4 System

More information

Product Manual Release 05/17

Product Manual Release 05/17 Temporary Safety Barrier (TL-2 MASH) Product Manual VHD (v3) www.valmonthighway.com Table of Contents 1.0 ArmorZone Introduction... 3 2.0 Before Installation... 3 3.0 Limitations & Warnings... 3 4.0 System

More information

Nu-Guard 31. Roadside and Median Guardrail System. MASH TL-3 & NCHRP TL-4 Product & Installation Manual

Nu-Guard 31. Roadside and Median Guardrail System. MASH TL-3 & NCHRP TL-4 Product & Installation Manual Nu-Guard 31 Roadside and Median Guardrail System MASH TL-3 & NCHRP TL-4 Product & Installation Manual Ph 0800 655 200 or visit www.csppacific.co.nz April 15 / Page 1 Table of Contents NU-GUARD 31 Introduction......

More information

DOUBLE SLIDE RAIL INSTALLATION METHOD. Double Slide Rail August

DOUBLE SLIDE RAIL INSTALLATION METHOD. Double Slide Rail August Double Slide Rail August 2015 1 DOUBLE SLIDE RAIL INSTALLATION METHOD Introduction Slide rail shoring systems can be used for trenches up to 12m wide and 6m deep. Module length is determined by panels

More information

Sentryline Terminal End III Non-Release Terminal End. Anchoring for 4 cable barrier system. Training and Product Installation Manual

Sentryline Terminal End III Non-Release Terminal End. Anchoring for 4 cable barrier system. Training and Product Installation Manual Sentryline Terminal End III Non-Release Terminal End Anchoring for 4 cable barrier system Training and Product Installation Manual Please call Australian Construction Products on 02 8708 4400 or visit

More information

QuadGuard II. Assembly Manual Stemmons Freeway Dallas, Texas 75207

QuadGuard II. Assembly Manual Stemmons Freeway Dallas, Texas 75207 QuadGuard II Assembly Manual 2525 Stemmons Freeway Dallas, Texas 75207 Important: These instructions are to be used only in conjunction with the assembly, maintenance, and repair of QuadGuard II systems.

More information

Product Manual. QUEST CEN System. Redirective, Bidirectional Crash Cushion ENERGY ABSORPTION

Product Manual. QUEST CEN System. Redirective, Bidirectional Crash Cushion ENERGY ABSORPTION Redirective, Bidirectional Crash Cushion ENERGY ABSORPTION SYSTEMS, INC. A Quixote Company Saving Lives By Design Corporate Offices: 35 East Wacker Dr., 11th Floor Chicago, IL 60601-2076 Telephone: (312)

More information

Instructions for 12 IGT system

Instructions for 12 IGT system Instructions for 12 IGT system Step 1: IGT Site Preparation Site Location Several factors must be considered when choosing the site for your new In-Ground Trampoline (IGT) system. Since local soil and

More information

PATENTS ARE PENDING. Building Dimensions. Exterior Dimensions Roof Edge to Roof Edge

PATENTS ARE PENDING. Building Dimensions. Exterior Dimensions Roof Edge to Roof Edge Assembly Manual 8x9 PATENTS ARE PENDING Approximate Size 7640303 Storage Area Building Dimensions Exterior Dimensions Roof Edge to Roof Edge Interior Dimensions Wall to Wall Sq. Ft. Cu. Ft. Width Depth

More information

h Installation Manual

h Installation Manual h Installation Manual 1 General Information The installation of HOBAS GRP Pipes is subject to applicable standards and guidelines such as EN 1610 and ISO/ TS 10465-1. Correct installation always requires

More information

Adjustable Pallet Racking Installation Guide

Adjustable Pallet Racking Installation Guide Adjustable Pallet Racking Installation Guide Read this Guide thoroughly before commencing assembly and retain for future reference. Installation plans and design drawings should be strictly adhered to.

More information

INSTALLATION GUIDE Sika SolarMount 1 Exposition East West

INSTALLATION GUIDE Sika SolarMount 1 Exposition East West Exposition East West CONTENTS 1 Notes on the Sika SolarMount 1 system (Exposition East West) for PV solar arrays 3 2 Setting up on site 3 3 Required Tools for mounting Sika SolarMount 1 to Sika roofing

More information

NOTES ON THE SPECIFICATION FOR ROAD SAFETY BARRIER SYSTEMS

NOTES ON THE SPECIFICATION FOR ROAD SAFETY BARRIER SYSTEMS 1. INTRODUCTION A road safety barrier is considered to be a hazard and should only be used when the consequences of hitting it are less than the hazard/object which it is shielding. The use of a road safety

More information

SPECIFICATION FOR REINFORCED SOIL WALL

SPECIFICATION FOR REINFORCED SOIL WALL SPECIFICATION FOR REINFORCED SOIL WALL 1.0 EXTENT OF WORK The work shall consist of Reinforced Soil walls built in accordance with this specification and in conformity with the lines, levels and details

More information

Specification for Road Safety Hardware Systems

Specification for Road Safety Hardware Systems Specification for Road Safety Hardware Systems APPENDIX C: TEMPORARY ROAD SAFETY BARRIER SYSTEMS February 2018 Prepared for NZTA by Parallaxx Ltd NZTA M23C 2017 INTRODUCTION AND REFERENCES This hardware

More information

Safety on Heights: Our Policy

Safety on Heights: Our Policy 11/17/14 Safety on Heights: Our Policy Only volunteers over the age of 18 are allowed to work on heights of more than six feet off the ground. This includes all work on scaffolds. Only volunteers who are

More information

Installing DELTABEAM. Installation of DELTABEAM. Deliveries. Storage on-site

Installing DELTABEAM. Installation of DELTABEAM. Deliveries. Storage on-site Installing DELTABEAM Installation of DELTABEAM These DELTABEAM installation instructions are intended to complement the project s erection plan. Peikko s technical support can help with the erection plan

More information

Flexbeam Guardrail Roadside Safety Barrier

Flexbeam Guardrail Roadside Safety Barrier Flexbeam Guardrail Roadside Safety Barrier Product Manual Release 09/15 www.ingalcivil.com.au Flexbeam Guardrail Roadside Safety Barrier 1.0 Introduction Roadside barriers have been developed over the

More information

BoSS Climalite Camera and lighting tower

BoSS Climalite Camera and lighting tower Contents Safety First Safety First Quantity Schedules Toeboard 2 9 13 33 INTRODUCTION Please read this guide carefully. Please note that diagrams are for illustrative purposes only. User guides are also

More information

Houston Community College 3200 Main Parking Garage November 15, 2010 Houston Community College

Houston Community College 3200 Main Parking Garage November 15, 2010 Houston Community College SECTION 323113 - CHAIN LINK FENCES AND GATES PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 01 Specification

More information

SMITH/ACO DRAINAGE SYSTEMS

SMITH/ACO DRAINAGE SYSTEMS SMITH/ACO DRAINAGE SYSTEMS Commercial Trench Drains EXPANSION JOINT TO ENGINEER S DETAIL CONCRETE BEDDING L ACO DRAIN Site Installation Manual 1 Polymer Concrete Drain Systems SMITH CUSTOMER DRIVEN SINCE

More information

MACHINE-LAY Installation Manual

MACHINE-LAY Installation Manual MACHINE-LAY Installation Manual PaveDrain Installation Manual Table of Contents Section 1: Base Preparation (pages 3 6) Section 2: Machine-Lay PaveDrain Blocks (pages 8 11) Section 3: Edge Restraints (pages

More information

Perfect Manhole Installation Manual May 2012 Rev 8 Perfect Manhole System Precast concrete manholes with load bearing elastomeric joints

Perfect Manhole Installation Manual May 2012 Rev 8 Perfect Manhole System Precast concrete manholes with load bearing elastomeric joints Perfect Manhole System Precast concrete manholes with load bearing elastomeric joints Installation Manual 1 1 Introduction This manual gives guidance on how to install the CPM Group Perfect manhole system

More information

Smarter. Safer. Leaner.

Smarter. Safer. Leaner. Smarter. Safer. Leaner. Fast Installation and Removal Decrease Leading Edge Exposure by 87% OSHA Compliant Versatile and Reusable Use Perimeter Protection Posts During Construction: At Building Perimeter

More information

Instructions for 12 and 15 IGT systems (12 pictured)

Instructions for 12 and 15 IGT systems (12 pictured) Instructions for 12 and 15 IGT systems (12 pictured) Step 1: IGT Site Preparation Site Location Several factors must be considered when choosing the site for your new In-Ground Trampoline (IGT) system.

More information

ASSEMBLY AND OPERATING MANUAL LTW SHORING BOXES VB 100

ASSEMBLY AND OPERATING MANUAL LTW SHORING BOXES VB 100 Dealer: MV Trench Support Ltd Letham Road Houston Industrial Estate Livingston EH54 5BY Phone: +44 (0) 1506 / 445800 Fax: +44 (0) 1506 / 443080 Mobile: +44 (0) 7917 / 208767 MV Trench Support Ltd * Letham

More information

DT 23 DT 24 DT 32 DT 33 DT 34 DT 44

DT 23 DT 24 DT 32 DT 33 DT 34 DT 44 DT 23 DT 24 DT 32 DT 33 DT 34 DT 44 Operating Manual DURATRUSS B.V. Junostraat 2 6468 EW Kerkrade The Netherlands www.duratruss.com DURATRUSS - www.duratruss.com Operating Manual Page 1 Table of Contents

More information

Allround Scaffolding. Layher Allround Bridging System Instructions for Assembly and Use. Modular truss system for wide spans

Allround Scaffolding. Layher Allround Bridging System Instructions for Assembly and Use. Modular truss system for wide spans Layher Allround Bridging System Instructions for Assembly and Use Modular truss system for wide spans Certification according to DIN ISO 9001/EN 29 001 by TÜV-CERT Allround Scaffolding } CONTENT 1. Introduction...3

More information

SECTION VIBRATION CONTROLS FOR HVAC PIPING AND EQUIPMENT

SECTION VIBRATION CONTROLS FOR HVAC PIPING AND EQUIPMENT SECTION 230548 - PART 1 - GENERAL 1.1 SUMMARY A. This Section includes the following: 1. Elastomeric Isolation pads. 2. Elastomeric Isolation mounts. 3. [Freestanding] [Restrained] [Freestanding and restrained]

More information

GROUND RELEASE SHACKLE

GROUND RELEASE SHACKLE INNOVATIVE PILING EQUIPMENT HYDRAULIC PILING HAMMERS GROUND RELEASE SHACKLE EURO GROUND RELEASE SHACKLE OPERATORS INSTRUCTIONS & SPARE PARTS LIST EXCAVATOR MOUNTED VIBRATORS EXCAVATOR MOUNTED DRILLS QUIET,

More information

Installation Instructions

Installation Instructions EconoDrain Trench Forming System Installation Instructions MultiDrain We Drain Your Site, Not Your Budget MultiDrain Systems, Inc. P.O. Box 88, Barium Springs, NC 28010 (704) 508-1010 or Toll Free 800-433-1119

More information

H 12 Heavy Duty Modern Tripod 8 Seat Swing Heavy Duty Hangers

H 12 Heavy Duty Modern Tripod 8 Seat Swing Heavy Duty Hangers Page 1 IMPORTANT Please retain this instruction sheet in your files. It contains important replacement parts information. All equipment should be installed in accordance with these instructions. It is

More information

Section 2 Supplemental Specification 2.11 High Tension Cable Barrier

Section 2 Supplemental Specification 2.11 High Tension Cable Barrier 2.11 HIGH TENSION CABLE BARRIER 2.11.1 GENERAL This Work consists of the supply, installation, removal, disposal and reinstallation of High Tension Cable Barrier (HTCB) system. 2.11.2 DEFINITIONS AND INTERPRETATION

More information

Product Manual REACT 350 (36") (3 foot [915 mm] wide Systems) Reusable Energy Absorbing Crash Terminal

Product Manual REACT 350 (36) (3 foot [915 mm] wide Systems) Reusable Energy Absorbing Crash Terminal (3 foot [915 mm] wide Systems) Reusable Energy Absorbing Crash Terminal Self-Restoring, Reusable Crash Cushions for Narrow Hazards ENERGY ABSORPTION SYSTEMS, INC. A Quixote Company Saving Lives By Design

More information

ROOF MOUNT KIT OWNERS MANUAL

ROOF MOUNT KIT OWNERS MANUAL ROOF MOUNT KIT OWNERS MANUAL Made in the USA by: Primus Wind Power, Inc. 938 Quail St. Lakewood, CO 80215 Phone: (303) 242-5820 www.primuswindpower.com AIR is a trademark of Primus Wind Power, Inc. ROOF

More information

MODULAR ACOUSTIC FENCING INSTALLATION GUIDE

MODULAR ACOUSTIC FENCING  INSTALLATION GUIDE MODULAR ACOUSTIC FENCING WWW.QUICKBUILTSYSTEMS.COM.AU INSTALLATION GUIDE INTRODUCTION THE QUICKBUILT FENCE SYSTEM IS A SMARTLY DESIGNED MODULAR SYSTEM EASY AND FAST TO INSTALL AND COST EFFECTIVE. // THE

More information

CLIMA AGR. Mobile Aluminium Tower with Climbing Frames 1450/850 Camlock Advanced Guardrail USER GUIDE

CLIMA AGR. Mobile Aluminium Tower with Climbing Frames 1450/850 Camlock Advanced Guardrail USER GUIDE CLIMA AGR Mobile Aluminium Tower with Climbing Frames 1450/850 Camlock Advanced Guardrail USER GUIDE Contents Safety First Safety Checklist Quantity Schedules Assembly and Dismantling Procedure Toe Boards

More information

Bridge Installation Guide

Bridge Installation Guide BAC ADVANCED COMPOSITE TECHNOLOGIES Bridge Installation Guide Revision 1: 11 March 2016 Prepared By: Lachlan Nicol 11/03/16 Page 1 of 10 Contents 1. Introduction... 3 1.1 BAC Bridges... 3 1.2 Purpose of

More information

SCAFFOLDING RUNWAY SYSTEM

SCAFFOLDING RUNWAY SYSTEM SCAFFOLDING RUNWAY SYSTEM HANDBOOK 07/2017.3 i) Further information and detailed component information can be found in the: C1 Conveyor Systems Technical Catalogue. ii) Call or e-mail Niko Ltd for any

More information

SECTION CHAIN LINK FENCES AND GATES (GALVANIZED) A. Fence framework, fabric, gates, and accessories.

SECTION CHAIN LINK FENCES AND GATES (GALVANIZED) A. Fence framework, fabric, gates, and accessories. SECTION 02830 CHAIN LINK FENCES AND GATES (GALVANIZED) 1.0 GENERAL 1.1 Section Includes A. Fence framework, fabric, gates, and accessories. B. Excavation for post bases; concrete footing for posts. C.

More information

SECTION CHAIN-LINK FENCES AND GATES 02821/1

SECTION CHAIN-LINK FENCES AND GATES 02821/1 SECTION 02821 - CHAIN-LINK FENCES AND GATES 02821/1 PART 1 - GENERAL 1.1 SUMMARY A. This Section includes the following: 1. Chain-Link Fences: 2. Gates: horizontal slide or swing. 3. Fences installed where

More information

FEATURES APPLICATIONS. Technical data sheet SSW - STEEL STRONG-WALL FOR TIMBER FRAME RACKING RESISTANCE.

FEATURES APPLICATIONS. Technical data sheet SSW - STEEL STRONG-WALL FOR TIMBER FRAME RACKING RESISTANCE. The Steel Strong-Wall is a corrugated steel panel which is designed to be fixed directly to the concrete foundations of a building, within the external or internal wall, via a bolted connection. FEATURES

More information

Model # 238HS-P8. 4/27/2011 Page 1 of 11

Model # 238HS-P8. 4/27/2011 Page 1 of 11 Model # 238HS-P8 4/27/2011 Page 1 of 11 4/27/2011 Page 2 of 11 1675 Locust Street Red Bud, IL 62278 Phone: 618-282-8200 Fax: 618-282-8202 WARRANTY & TERMS WARRANTY: 5 Year Limited Warranty on Thermoplastic

More information

American Metal Specialties, Inc.

American Metal Specialties, Inc. American Metal Specialties, Inc. www.cablerailings.com (253) 272-9344 (253) 627-3843 Fax PART 1 GENERAL 1.1 SECTION INCLUDES SECTION 05 73 00 STAINLESS STEEL ORNAMENTAL HANDRAILS AND RAILINGS For best

More information

Speedlock Pallet Racking

Speedlock Pallet Racking Assembly specification These instructions are to assemble Dexion Speedlock Pallet Racking which conforms with the specifications below. Frame heights not more than 4800mm Frame depths 840mm Not less than

More information

ASSEMBLY AND OPERATING MANUAL LTW EG CORNER - MANHOLE

ASSEMBLY AND OPERATING MANUAL LTW EG CORNER - MANHOLE Manufacturer: LTW Tiefbauvertriebs GmbH Holter Weg 11 D 41836 Hückelhoven-Brachelen Phone: +49 (0) 24 62 / 2009 0 Fax: +49 (0) 24 62 / 2009 15 e-mail: info@ltw-verbau.de homepage: http:\ \ www.ltw-shoring.com

More information

Construction Specification for Utility Adjustments

Construction Specification for Utility Adjustments Engineering & Construction Services Division Standard Specifications for Road Works TS 4.50 September 2017 for Utility Adjustments Table of Contents TS 4.50.01 SCOPE... 2 TS 4.50.02 REFERENCES... 2 TS

More information

Easy to Use A7 Saves You Time and Money

Easy to Use A7 Saves You Time and Money ADHESIVE ANCHORING SPECIALISTS Easy to Use Saves You Time and Money DESCRIPTION/SUGGESTED SPECIFICATIONS* Fast Dispensing, Fast Curing The acrylic resin and hardening agent are completely mixed as they

More information

NOTES FOR THE PERFORMANCE BASED SPECIFICATION FOR TRAFFIC SIGNS

NOTES FOR THE PERFORMANCE BASED SPECIFICATION FOR TRAFFIC SIGNS CONTENTS NOTES FOR THE PERFORMANCE BASED SPECIFICATION FOR TRAFFIC SIGNS 1. SCOPE... 2 2. RELATED DOCUMENTS... 2 3. DEFINITIONS... 2 4. COMPLIANCE... 2 5. SIGN FACE DESIGN... 3 6. VISIBILITY... 3 6.1 Performance

More information

ITEM 686 TRAFFIC SIGNAL POLE ASSEMBLIES (STEEL)

ITEM 686 TRAFFIC SIGNAL POLE ASSEMBLIES (STEEL) ITEM 686 TRAFFIC SIGNAL POLE ASSEMBLIES (STEEL) 686.1. Description. This Item shall govern for designing, fabricating, furnishing and erecting steel traffic signal pole assemblies of the various types

More information

ITEM 6 CONCRETE CURBS, GUTTERS, AND SIDEWALKS

ITEM 6 CONCRETE CURBS, GUTTERS, AND SIDEWALKS ITEM 6 CONCRETE CURBS, GUTTERS, AND SIDEWALKS 6.1 DESCRIPTION This work shall consist of constructing curbs, gutters, sidewalks, ramps, local depressions and driveways of the form and dimensions shown

More information

SECTION VIBRATION AND SEISMIC CONTROLS FOR ELECTRICAL SYSTEMS

SECTION VIBRATION AND SEISMIC CONTROLS FOR ELECTRICAL SYSTEMS PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions, apply to this Section. 1.2 SUMMARY A. This Section includes the

More information

the P.R. Skate, LLC Pallet Rack Moving System Product Manual

the P.R. Skate, LLC Pallet Rack Moving System Product Manual the P.R. Skate, LLC Pallet Rack Moving System Product Manual the P.R. Skate, LLC Product Manual In this manual we will cover both normal operation of the P.R. Skate moving system and safety issues that

More information

Z5033 E3 Ball joint adapter Mounting instructions

Z5033 E3 Ball joint adapter Mounting instructions Z5033 E3 Ball joint adapter Mounting instructions Z5033 E3 Ball joint adapter References in the manual This refers to a potentially dangerous situation which may lead to personal injury. This refers to

More information

Model # 158-P4. 12/12/2013 Page 1 of 11

Model # 158-P4. 12/12/2013 Page 1 of 11 Model # 158-P4 12/12/2013 Page 1 of 11 2/12/2013 Page 2 of 11 1675 Locust Street Red Bud, IL 62278 Phone: 618-282-8200 Fax: 618-282-8202 WARRANTY & TERMS WARRANTY: 5 Year Limited Warranty on Thermoplastic

More information

TYPICAL INSTALLATION INSTRUCTIONS

TYPICAL INSTALLATION INSTRUCTIONS TYPICAL INSTALLATION INSTRUCTIONS Environment One Grinder Pump Feature Identification 1. Grinder Pump Basin High density polyethylene (HDPE) 2. Accessway Cover Painted Steel 3. Electrical Quick Disconnect

More information

PV Mounting System 2703 SERIES 200 UL GROUND MOUNT SYSTEM. SnapNrack Residential PV Mounting Systems Code Compliant Installation Manual

PV Mounting System 2703 SERIES 200 UL GROUND MOUNT SYSTEM. SnapNrack Residential PV Mounting Systems Code Compliant Installation Manual PV Mounting System 2703 SERIES 200 UL GROUND MOUNT SYSTEM SnapNrack Residential PV Mounting Systems Code Compliant Installation Manual Series 200 UL Introduction Series 200 UL Introduction SnapNrack Series

More information

GroundTrac. Installation Manual

GroundTrac. Installation Manual APPLICATION: The GroundTrac system is designed with a minimum amount of installed footings at greatly reduced labor. The system integrates with ordinary 1-1/2 schedule #40 galvanized water pipe. This ground

More information

Product Manual. Release 04/15.

Product Manual. Release 04/15. Product Manual www.ezyguard.com 1.0 Introduction Introducing Ezy-Guard Smart, a member of the Ezy-Guard family, the next generation steel guardrail barrier providing superior motorist safety and more metres

More information

DIVISION 03 CONCRETE SPECIFICATION : FORMS AND FORMWORK

DIVISION 03 CONCRETE SPECIFICATION : FORMS AND FORMWORK DIVISION 03 CONCRETE SPECIFICATION 031000: FORMS AND FORMWORK PART 1.0 GENERAL 1.1 DESCRIPTION The work of this specification includes furnishing of all labor, materials, equipment and incidentals to install,

More information

MODULAR ENCLOSURES FOR TRANSFORMER SUBSTATIONS

MODULAR ENCLOSURES FOR TRANSFORMER SUBSTATIONS IG-021-GB General Instructions PF LIB Transformer Substations Secondary Distribution Switchgear Primary Distribution Switchgear Protection and Automation Low Voltage Boards Distribution Transformers Legal

More information

Installation Guidelines for Flygt Pumps Pump Anchoring Recommendations

Installation Guidelines for Flygt Pumps Pump Anchoring Recommendations Issued: Installation Guidelines for Flygt Pumps Pump Anchoring Recommendations Introduction Proper installation and anchorage of Flygt pumps and installation accessories is critical to limiting vibration

More information

84 Lapping & Jointing 86 Service Pipe Penetrations 87 Sealing to Cavity Wall Constructions 88 Protecting Membranes System Components.

84 Lapping & Jointing 86 Service Pipe Penetrations 87 Sealing to Cavity Wall Constructions 88 Protecting Membranes System Components. 84 Lapping & Jointing 86 Service Pipe Penetrations 87 Sealing to Cavity Wall Constructions 88 Protecting Membranes 90 System Components installation/ SYSTEM COMPONENTS INSTALLATION ADVICE LAPPING and JOINTING

More information

Fig Beam Clamp Retaining Strap (B-Line B3367)

Fig Beam Clamp Retaining Strap (B-Line B3367) Fig. 69 - Beam Clamp Retaining Strap (B-Line B3367) Size Range: 3 /8"-16 thru 3 /4"-10 rod 4 (101.6mm) thru 16 (406.4mm) lengths Note: longer lengths are available consult factory Material: Pre-Galvanized

More information

1. Cast-in-place concrete is specified in Section

1. Cast-in-place concrete is specified in Section SECTION 03 38 00 PART 1 - GENERAL 1.01 DESCRIPTION A. This Section describes the requirements for furnishing and installing post-tensioned slabs, jacks, jacking and anchors at Parking Structure, and record

More information

SECTION I -- IRONWORK

SECTION I -- IRONWORK SECTION I -- IRONWORK CONTENTS PAGE 1. GENERAL... I-2 1.1. Introduction... I-2 2. REQUIREMENTS... I-2 2.1. General... I-2 2.2. Auxiliary Framing... I-2 2.3. High Seismic Risk Zone Requirements... I-3 2.4.

More information

Cutting & handling recommendations

Cutting & handling recommendations Cutting & handling recommendations CUTTING & HANDLING RECOMMENDATIONS Loading & handling itopker Packaging Hygiene & safety Inspecting the slabs Loading & handling 04 06 06 07 CONTENT Cutting Cutting with

More information

Constructing Fixed Span Bridges From Floating Equipment

Constructing Fixed Span Bridges From Floating Equipment Chapter 10. Constructing Fixed Span Bridges From Floating Equipment CONSTRUCTING FIXED SPANS FROM M4T6 EQUIPMENT Characteristics of M4T6 Fixed Spans Short freed spans erected with M4T6 components can provide

More information

CHAIN LINK FENCES AND GATES

CHAIN LINK FENCES AND GATES SECTION 02831 CHAIN LINK FENCES AND GATES PART 1 GENERAL 1.01 SUMMARY A. Alternate Material for Fence Post and Framing Material: Where schedule 40 galvanized steel is specified, the following will be accepted:

More information

Model # 358-R48. 7/7/2011 Page 1 of 11

Model # 358-R48. 7/7/2011 Page 1 of 11 Model # 358-R48 7/7/2011 Page 1 of 11 7/7/2011 Page 2 of 11 1675 Locust Street Red Bud, IL 62278 Phone: 618-282-8200 Fax: 618-282-8202 WARRANTY & TERMS WARRANTY: 5 Year Limited Warranty on Thermoplastic

More information

Model # 800SM-PS3. 8/3/2016 Page 1 of 8

Model # 800SM-PS3. 8/3/2016 Page 1 of 8 Model # 800SM-PS3 8/3/2016 Page 1 of 8 /3/2016 Page 2 of 8 1675 Locust Street Red Bud, IL 62278 Phone: 618-282-8200 Fax: 618-282-8202 WARRANTY & TERMS WARRANTY: 5 Year Limited Warranty on Thermoplastic

More information

SECTION HANGERS AND SUPPORTS FOR ELECTRICAL SYSTEMS

SECTION HANGERS AND SUPPORTS FOR ELECTRICAL SYSTEMS SECTION 26 05 29 HANGERS AND SUPPORTS FOR ELECTRICAL SYSTEMS PART 1 GENERAL 1.1 DESCRIPTION A. Scope: 1. CONTRACTOR shall provide all labor, materials, equipment, and incidentals as shown, specified, and

More information

Reinforced concrete slot channel

Reinforced concrete slot channel Applicable Bodies of Rules: DIN EN 1433»Drainage channels for vehicular and pedestrian areas«din 19580»Drainage channels for vehicular and pedestrian areas«the following laying instructions are general

More information

fischer Test Report Fixing Tests for Bison Hollow Core Slabs

fischer Test Report Fixing Tests for Bison Hollow Core Slabs fischer Test Report Fixing Tests for Bison Hollow Core Slabs Testing on Bison Hollow Core Slabs 1. Introduction Contents Test Parameters Bison Hollow Core Slab Information 2. Fixings Products Tested FISV

More information

ZS880 Linear Shower Drain Installation Instructions

ZS880 Linear Shower Drain Installation Instructions Introduction PATENT PENDING The Zurn ZS880 Stainless Steel Linear Shower Drain incorporates a simple approach to bathroom shower design, when compared to traditional point-drain applications. The linear

More information

Brifen Wire Rope Safety Barrier TL-3 & TL-4

Brifen Wire Rope Safety Barrier TL-3 & TL-4 Brifen Wire Rope Safety Barrier TL-3 & TL-4 Product and Installation Manual Ph 0800 655 200 or visit www.csppacific.co.nz June 2012 / Page 1 Table of Contents Background 3 Design Considerations 4 Design

More information

Air flue duct for use with ecotec boilers

Air flue duct for use with ecotec boilers For the installer Flue installation instructions Air flue duct for use with ecotec boilers Concentric System Ø 80/5 (Galvanized steel air duct/plastic flue duct) GB Contents Notes on the documentation

More information

ifix INSTALLATION MANUAL PV flat roof installation system Version

ifix INSTALLATION MANUAL PV flat roof installation system Version ifix PV flat roof installation system INSTALLATION MANUAL Version 2012-09-06 ifix Installation Manual Version 2012-09-06 Seite 1 Table of contents Table of contents... 1 Special characteristics of ifix...

More information

AC50 Silver Adhesive Anchoring System

AC50 Silver Adhesive Anchoring System General Information General Information AC50 Silver Adhesive Anchoring System Product Description The AC50 Sliver is a two-component, adhesive anchoring system. The system includes injection adhesive in

More information

EVALUATION REPORT. PFC-5551 Reissued April 1, Filing Category: DESIGN Steel (038)

EVALUATION REPORT. PFC-5551 Reissued April 1, Filing Category: DESIGN Steel (038) ICBO Evaluation Service, Inc. 5360 WORKMAN MILL ROAD WHITTIER, CALIFORNIA 90601-2299 A subsidiary corporation of the International Conference of Building Officials EVALUATION REPORT Copyright 2001 ICBO

More information

OVERSHOT GATE TECHNICAL DATA SHEET

OVERSHOT GATE TECHNICAL DATA SHEET FRESNO OVERSHOT GATE TECHNICAL DATA SHEET Applications Fresno Overshot Gates effectively control upstream and downstream levels of canals. Improved flow control is achieved through the use of this fully

More information

SLED End Treatment System Manual

SLED End Treatment System Manual SLED End Treatment System Manual PN 45045 Revision A (Dated 03/14/11) Table of Contents IMPORTANT: Read and understand ALL installation instructions before attempting to install the SLED End Treatment

More information

Installation Instructions Easy Climb 1 Art

Installation Instructions Easy Climb 1 Art Installation Instructions Easy Climb 1 Art. 4591-40-1 Operator: Location: Revision history Revision 0 2009-08-21 The first allowed version Assembly instruction Revision 1 2011-08-12 B25 in C25/30 u. Fallschutz

More information

ASSEMBLY INSTRUCTIONS

ASSEMBLY INSTRUCTIONS ASSEMBLY INSTRUCTIONS for the vehicle barrier system KREMSBARRIER 2 RH2B for pile-drivable subgrades Performance class in accordance with EN 1317-2: Containment level: Impact severity level: Working width:

More information

Materials Carbon Steel and Malleable Iron are used in the manufacture of concrete inserts. Stainless Steel and other materials are available.

Materials Carbon Steel and Malleable Iron are used in the manufacture of concrete inserts. Stainless Steel and other materials are available. Concrete inserts offered in this section are designed to provide a pre-set support point in concrete ceilings, walls, and floors. A range of inserts with varying design loads are available. Materials Carbon

More information

Huck Seiltechnik GmbH Aßlar/Berghausen Germany

Huck Seiltechnik GmbH Aßlar/Berghausen Germany Seiltechnik GmbH 35614 Aßlar/Berghausen Germany A Assembly Instructions Arch Swing with Buried Ground Anchors Art-No. 4580-4B Operator: Location: T:\PLAY\Play Installation Instructions\Word Document Install

More information

Turbocharger / TPL-C Original assembly instructions English

Turbocharger / TPL-C Original assembly instructions English Assembly Instructions Turbocharger / TPL-C Original assembly instructions English This document is valid for the TPL-C series: TPL79-C Purpose The assembly instructions explain how the ABB turbocharger

More information

Model # BARK-358-RDP

Model # BARK-358-RDP Model # BARK-358-RDP 1675 Locust Street Red Bud, IL 62278 Phone: 618-282-8200 Fax: 618-282-8202 WARRANTY & TERMS WARRANTY: 5 Year Limited Warranty on Thermoplastic/Canine coated elements. guarantees all

More information

1675 Locust Street Red Bud, IL Phone: Fax: WARRANTY & TERMS

1675 Locust Street Red Bud, IL Phone: Fax: WARRANTY & TERMS Model # 349S-P6 1675 Locust Street Red Bud, IL 62278 Phone: 618-282-8200 Fax: 618-282-8202 WARRANTY & TERMS WARRANTY: 5 Year Limited Warranty on Thermoplastic coated elements. Ultra Play guarantees all

More information

Model # 358H-PR. 4/8/2011 Page 1 of 12

Model # 358H-PR. 4/8/2011 Page 1 of 12 Model # 358H-PR 4/8/2011 Page 1 of 12 4/8/2011 Page 2 of 12 1675 Locust Street Red Bud, IL 62278 Phone: 618-282-8200 Fax: 618-282-8202 WARRANTY & TERMS WARRANTY: 5 Year Limited Warranty on Thermoplastic

More information

FW66 FORESTRY WINCH FW66. Owner s Manual 19/02/2016

FW66 FORESTRY WINCH FW66. Owner s Manual 19/02/2016 FW66 FORESTRY WINCH FW66 19/02/2016 Owner s Manual TABLE OF CONTENTS INTRODUCTION ---------------------------------------------------------------------------------- 2 INTENDED USE -----------------------------------------------------------------------------------

More information

TECHNICAL DATA SHEET DS 060

TECHNICAL DATA SHEET DS 060 of 9 General Notes: This instruction covers the installation of a resilient mounted system for a marine propulsion engine driving a rigidly mounted gearbox through a flexible coupling utilising an independent

More information

SAFE ERECTION AND USE OF ALUMINIUM TOWERS/SCAFFOLDS

SAFE ERECTION AND USE OF ALUMINIUM TOWERS/SCAFFOLDS SAFE ERECTION AND USE OF ALUMINIUM TOWERS/SCAFFOLDS PERSONNEL DIVISION Revised 2002 CONTENTS Page 1 INTRODUCTION 1 2 APPLICATION 1 3 ERECTION AND INSPECTION 1 4 ERECTION 1 4.1 Before erection of tower

More information

ON-ROOF ATTACHMENT FLAT COLLECTOR HELIOSTAR

ON-ROOF ATTACHMENT FLAT COLLECTOR HELIOSTAR ON-ROOF ATTACHMENT FLAT COLLECTOR HELIOSTAR INSTALLATION INSTRUCTIONS ENERGY AND SANITARY SYSTEMS Installation requirements Generel requirements The on-roof attachment set is capable for installation of

More information

ACO DRAIN Site Installation Manual Polymer Concrete Drain Systems

ACO DRAIN Site Installation Manual Polymer Concrete Drain Systems EXPA ENG ACO DRAIN Site Installation Manual Polymer Concrete Drain Systems Re-order DL016 2 Getting Started ACO Drain consists of a full range of modular channels with captive grates; Systems include catch

More information

OPERATOR S SAFETY MANUAL

OPERATOR S SAFETY MANUAL June 2011 OPERATOR S SAFETY MANUAL Sumner Pipe Jacks www.sumner.com 7514 Alabonson Road Houston, TX 77088 U.S.A ph: 281.999.6900 fax: 281.999.6966 470 Collier MacMillan Drive Unit 2 & 3 Cambridge, ON N1R

More information

Span 300 Instruction Manual

Span 300 Instruction Manual Span 300 Instruction Manual DESIGNATION SPAN300 Double Width EN 1004 3 8/12 XXCD SPAN 300 Single Width EN 1004 3 8/8 XXCD CEN designation of this instruction manual EN 1298 IM en Rev-00 WARNING NEVER STAND

More information

CONCRETE STEPS, HANDRAILS, AND SAFETY RAIL

CONCRETE STEPS, HANDRAILS, AND SAFETY RAIL SUDAS Standard Specifications Division 9 - Site Work and Landscaping Section 9080 - Concrete Steps, Handrails, and Safety Rail CONCRETE STEPS, HANDRAILS, AND SAFETY RAIL PART - GENERAL.0 SECTION INCLUDES

More information