1 APPENDIX A Construction Forms SOUTH CAROLINA DEPARTMENT OF TRANSPORTATION May 2004

2

3 May 2004 Construction Forms A-i Section Table of Contents Page APPENDIX A CONSTRUCTION FORMS... A-1 SCDOT Construction Form Description Table... A-2

4 A-ii Construction Forms May 2004

5 May 2004 Construction Forms A-1 Appendix A Construction Forms Figure A-1A presents a descriptive list of the most common SCDOT Construction Forms that will be used to administer SCDOT construction contracts and inspect typical pay items. The forms listed in Appendix A are available in electronic format on the SCDOT Intranet Web Site.

6 New No. Old No Name Section Description Responsibility Pre-Construction Checklist Who Fills Out the Form? Who Signs Forms? Distribution general SCDOT LAB-291 Preliminary Letter of Certification materials SCDOT /DEA, Lab Report Recommending Roads for State Maintenance final inspection SCDOT, DEA, Road/Bridge Engr Contractor Notice of Claim claim Contractor Contractor, Contractor Contractor Concurrence and Prompt Payment Distribution of Payment 100 payment Wage Regulation Report 100 general LAB-232 Monthly Report of Testing Activities with Nuclear Gauge equipment SCDOT, DEA, Dir. of Const., Dir. of Const. concurrence SCDOT Contractor, Contractor SCDOT,DEA Accounting SCDOT, Lab LAB-919 Report of Disposition of Materials Failing to meet Specifications 105 materials SCDOT, DEA, DOC Material Certification Log Materials Sampling and Testing Log A Utility Agreement 100 utility Utility Company Z Utility Field Daily Diary 100 DEA, Dir. of Const., Lab, 100 materials SCDOT N/A 100 materials SCDOT N/A Utility Company Utility Mgr, Utility Company, Utility Office utility SCDOT Slope Permission R/W SCDOT Stormwater and Pollution Prevention Plan for Highway Construction 800 NPDES Contractor Contractor Property owner,, DEA, DOC DHEC 2612 Notice of Intent - Stormwater 800 stormwater SCDOT DEA DHEC 2610 Notice of Termination - Stormwater 800 stormwater SCDOT DEA, Dir. of Const. SCDOT, Contractor, District office, DHEC, District office, DHEC PR-1391 Annual EEO Report - Contractors 100 EEO Contractor Subs, Prime Subs, Prime, DBE office, SCDOT CONSTRUCTION FORM DESCRIPTION TABLE Figure A-1A A-2 Construction Forms May 2004

7 New No. Old No. Name Section Description Responsibility Who Fills Out the Form? Who Signs Forms? Distribution DBE Quarterly Report 100 EEO Contractor Contractor Subs, Prime, DBE office, Equal Employment Opportunity Stage Type Inspection 100 EEO SCDOT EEO EEO, EEO, Contractor Request for DBE Summary 100 DBE SCDOT DBE office, Monthly Training Status Report 100 general Contractor Trainee Termination Report 100 general Contractor Final Inspection Acceptance Report Railroad Grade Crossing Signal Project Report of Acceptance of Small Quantity Materials LAB-932 Field Density Test Report (Nuclear Gauge) 200/ A Percent Compaction by Nuclear Gauge 200/ B Percent Compaction by Nuclear Gauge - Direct Read Gauge 200/300 railroad SCDOT subgrade, base, embankment subgrade, base, embankment subgrade, base, embankment SCDOT SCDOT SCDOT Contractor SCDOT, Contractor Contractor Compliance Office, DEA & Utilities Mgr., DEA & Utilities Mgr., Lab Agreement for Placing Debris on Private Property 200 clearing/grub Contractor Contractor Landowner DHEC 3428 Notification of Demolition 700 structure DHEC SCDOT Blasting Notice public notice Contractor Contractor N/A Depth Check Records 300 base DEA Landowner, Contractor, District office, DHEC Communications Office SCDOT LAB-935 Density Test Report (Nuclear Gauge) 300 stone base SCDOT, Lab LAB-935B Density Test Report (Nuclear Gauge) - Direct Read Gauge 300 stone base SCDOT, Lab W Ignition Oven Worksheet 300 asphalt Contractor N/A, Lab LAB-266 Determination of Target Density for Asphalt Concrete Materials 400 asphalt Contractor Contractor Contractor Lab SCDOT CONSTRUCTION FORM DESCRIPTION TABLE Figure A-1A (Continued) May 2004 Construction Forms A-3

8 New No. Old No Name Section Description Responsibility Daily Report of Asphalt Plant Inspection 400 asphalt SCDOT Daily Report of Asphalt Roadway Inspection Daily Report of Asphalt Roadway Inspection Contractor QC/QA - Placed LAB-966 Asphalt Ignition Oven Mixture Calibration Worksheet LAB-967 Asphalt Ignition Oven Mixture Calibration Verification Worksheet asphalt LAB-988 Silo Approval Overnight Storage 400 asphalt PWL-1 Lot Pay Factor Calculations SCDOT Who Fills Out the Form? Plant Roadway 400 asphalt Contractor Who Signs Forms? Plant, Roadway,, District Distribution, Lab, Lab, Lab 400 asphalt Contractor Contractor Contractor Lab 400 asphalt Contractor Contractor Contractor Lab 400 asphalt Contractor PWL-1 Lot Pay Factor Calculations - Thin Lift 400 asphalt Contractor PWL-2 In-Place Density Contractor QC/QA - Nuclear Gauge 400 asphalt Contractor PWL-2 In-Place Density Contractor QC/QA - Roadway Cores 400 asphalt Contractor Weekly Lime Anti-Stripping Additive Report 400 asphalt Contractor LAB-979 Verification of Hydrated Lime Weighing Systems for Hot Mix Asphalt Maximum and Effective Specific Gravity Worksheet 400 asphalt SCDOT In-Place Density Contractor QA 400 asphalt In-Place Density Contractor QC/QA PWL 400 Contractor Contractor Contractor Lab Plant, District, District, District, District, District Plant,, Contractor, Lab, Lab, Lab, Lab, Lab Field Lab 400 asphalt Contractor N/A, Lab SCDOT Contractor asphalt SCDOT Contractor Traffic Control Plan 600 traffic Contractor Contractor Workzone Traffic Control Inspection 600 traffic SCDOT SCDOT CONSTRUCTION FORM DESCRIPTION TABLE Figure A-1A (Continued), DEA, Contractor DEA A-4 Construction Forms May 2004

9 New No. Old No Name Section Description Responsibility BR-1 Concrete Pour 's Checklist BR-2 Concrete Pour 's Checklist - Contractor's QC 500 concrete SCDOT BR-3 Concrete Pre-Pour Checklist for Non-Bridge and Non-Culvert Items LAB-660 Ready Mix Concrete Report 500 concrete SCDOT Dry Run Depth Checks for Bridge Deck Pours Wet Depth Checks for Bridge Decks - Transverse Wet Depth Checks for Bridge Decks - Longitudinal Who Fills Out the Form? Who Signs Forms? Distribution 500 concrete SCDOT 500 concrete SCDOT Plant / field inspector Plant / field inspector 700 structure SCDOT 700 structure SCDOT 700 structure SCDOT PIT.VERIFI CSL/PDA/PIT Testing Verification 700 foundations SCDOT Slurry Inspection Log 700 foundations Contractor Contractor Drilled Shaft Concrete Placement Log 700 foundations Contractor Contractor Drilled Shaft Concrete Volumes Log 700 foundations Contractor Contractor Drilled Shaft Excavation Log 700 foundations Contractor Contractor Drilled Shaft Inspection Log 700 foundations Contractor Contractor Drilled Shaft Log 700 foundations Contractor Contractor Pile Driving Log 700 foundations SCDOT, Bridge, Construction Welding Procedure 700 structure Contractor Contractor Contractor, Lab Pile Record 700 foundations SCDOT N/A SCDOT CONSTRUCTION FORM DESCRIPTION TABLE Figure A-1A (Continued) Submit w/ Final Plans May 2004 Construction Forms A-5

10 New No. Old No Name Section Description Responsibility Swiss Hammer Readings 700 structure Who Fills Out the Form? Who Signs Forms? SCDOT Agreement for Moving Items Release R/W Contractor Contractor Landowner, 2 witnesses, Distribution, Bridge, Construction Sediment and Erosion Control Site Inspection Report 800 NPDES SCDOT CEI, CEI office SCDOT CONSTRUCTION FORM DESCRIPTION TABLE Figure A-1A (Continued) A-6 Construction Forms May 2004

VIRGINIA DEPARTMENT OF TRANSPORTATION MATERIALS DIVISION MEMORANDUM. Charles A. Babish, PE State Materials Engineer Approved:

VIRGINIA DEPARTMENT OF TRANSPORTATION MATERIALS DIVISION MEMORANDUM. Charles A. Babish, PE State Materials Engineer Approved: VIRGINIA DEPARTMENT OF TRANSPORTATION MATERIALS DIVISION MEMORANDUM GENERAL SUBJECT: Revisions to Chapter VII of Manual of Instructions Materials Acceptance and Materials Notebook Program NUMBER: MD 407-17

More information

GUIDE SCHEDULE OF SAMPLING & TESTING FOR DESIGN-BID-BUILD (DBB) PROJECTS MAY 2016

GUIDE SCHEDULE OF SAMPLING & TESTING FOR DESIGN-BID-BUILD (DBB) PROJECTS MAY 2016 GUIDE SCHEDULE OF SAMPLING & TESTING FOR DESIGN-BID-BUILD (DBB) PROJECTS MAY 2016 Using the Guide Schedule Research of sampling and testing rates listed for project tests in the following Guide Schedule

More information

Construction Management Plan

Construction Management Plan Use and Limitation: The Consultant may use this document as a guide in preparing a construction management plan to be included in the bid documents for their specific project. Consultants are cautioned

More information

ETS. Scripps Networks Expansion Knoxville, Tennessee. Services Provided: Subsurface Exploration - drilling geotechnical engineering

ETS. Scripps Networks Expansion Knoxville, Tennessee. Services Provided: Subsurface Exploration - drilling geotechnical engineering Scripps Networks Expansion Knoxville, Tennessee drilling drilled shaft observation steel erection observation Located at the existing Scripps Network facilities in Knoxville, this $40+ million expansion

More information

Geotechnical Specification and Construction Update

Geotechnical Specification and Construction Update Geotechnical Specification and Construction Update Steve Slomski, P.E. Office of Construction Administration Topics 2016 C&MS Revisions Supplemental Specifications & Supplements Revisions & Additions Construction

More information

Extraction and Sieve Analysis ( µm minus) Forming Marshall Specimens, Field Method

Extraction and Sieve Analysis ( µm minus) Forming Marshall Specimens, Field Method 3.56 COLD IN-PLACE RECYCLING 3.56.1 GENERAL This specification covers the requirements for Cold In-Place Recycling (CIR) which consists of reclaiming the existing asphalt pavement; sizing the reclaimed

More information

Design-Builder Quality Control System Paul Moyer, P.E., Gill Engineering. July 17, 2011

Design-Builder Quality Control System Paul Moyer, P.E., Gill Engineering. July 17, 2011 Design-Builder Quality Control System Paul Moyer, P.E., Gill Engineering July 17, 2011 Project Quality Assurance Program Quality Assurance All those planned and systematic actions necessary to provide

More information

OKLAHOMA DEPARTMENT OF TRANSPORTATION LABORATORY QUALIFICATION POLICY

OKLAHOMA DEPARTMENT OF TRANSPORTATION LABORATORY QUALIFICATION POLICY Revised June 5, 2017 OKLAHOMA DEPARTMENT OF TRANSPORTATION LABORATORY QUALIFICATION POLICY SCOPE: This policy defines the process a lab shall follow to become qualified to conduct acceptance and QC/QA

More information

2.1 Backfill - General

2.1 Backfill - General 2.1 Backfill - General Excavations are made for the purpose of constructing bridge substructure elements, and consequently requiring competent backfill material. The backfill material must be adequately

More information

Construction Inspection for the FUTURE. Presented By: Gary Angles, PE Lyle Flower, PE

Construction Inspection for the FUTURE. Presented By: Gary Angles, PE Lyle Flower, PE Construction Inspection for the FUTURE Presented By: Gary Angles, PE Lyle Flower, PE History of Prequalification Firms were Prequalified 20 years ago Judged to be ineffective and ended ODOT began requiring

More information

KANSAS DEPARTMENT OF TRANSPORTATION SPECIAL PROVISION TO THE STANDARD SPECIFICATIONS, EDITION 2007

KANSAS DEPARTMENT OF TRANSPORTATION SPECIAL PROVISION TO THE STANDARD SPECIFICATIONS, EDITION 2007 Sheet 1 of 6 KANSAS DEPARTMENT OF TRANSPORTATION SPECIAL PROVISION TO THE STANDARD SPECIFICATIONS, EDITION 2007 Delete SECTION 2501 and replace with the following: SECTION 2501 PART V 2501.1 GENERAL In

More information

October 1, Re: Contract ID A Plans, Proposal, EBS, Questions & Answers October 8, 2013 Letting

October 1, Re: Contract ID A Plans, Proposal, EBS, Questions & Answers October 8, 2013 Letting October 1, 2013 Dear Prospective Bidders: Re: Contract ID 26.036775A Plans, Proposal, EBS, Questions & Answers October 8, 2013 Letting The Contractor is hereby advised of modifications to the bid documents.

More information

2016 ACHD Supplemental Specifications to the ISPWC. ACHD QC-QA Procedure

2016 ACHD Supplemental Specifications to the ISPWC. ACHD QC-QA Procedure SECTION 100 General Conditions Add the following: 2016 ACHD Supplemental Specifications to the ISPWC Ada County Highway District Quality Control and Quality Assurance Procedure Definitions Quality Assurance

More information

May 2004 Sample Identification Cards B-i. Table of Contents APPENDIX B SAMPLE IDENTIFICATION CARDS... B-1 B.1 INSPECTOR DUTIES...

May 2004 Sample Identification Cards B-i. Table of Contents APPENDIX B SAMPLE IDENTIFICATION CARDS... B-1 B.1 INSPECTOR DUTIES... APPENDIX B Sample Identification Cards SOUTH CAROLINA DEPARTMENT OF TRANSPORTATION May 2004 May 2004 Sample Identification Cards B-i Section Table of Contents Page APPENDIX B SAMPLE IDENTIFICATION CARDS...

More information

Construction Inspection Checklists

Construction Inspection Checklists III. Construction Inspection Checklists 33 Bioretention - Construction Inspection Checklist Project: Location: Site Status: Date: Time: Inspector: Construction Sequence Satisfactory / Unsatisfactory Comments

More information

Witness & Hold Inspection Plan. I-595 Corridor Roadway Improvement Project

Witness & Hold Inspection Plan. I-595 Corridor Roadway Improvement Project Witness & Hold Inspection Plan I-595 Corridor Roadway Improvement Project Revision 6 March 2013 I-595 Corridor Roadway Improvements QUALITY PROCEDURES Procedure No.QP-07 Revision #6 PROCEDURE FOR WITNESS

More information

Puerto Rico. Pavement Preservation Conference and Technology Implementation. US. Department of Transportation Federal Highway Administration

Puerto Rico. Pavement Preservation Conference and Technology Implementation. US. Department of Transportation Federal Highway Administration Puerto Rico Pavement Preservation Conference and Technology Implementation US. Department of Transportation Federal Highway Administration Cold In-Place Asphalt Recycling Overview Michael L. Polak E.J.

More information

GUIDE SCHEDULE OF SAMPLING & TESTING FOR DESIGN-BUILD PROJECTS BY THE INDEPENDENT QUALITY FIRM (IQF) August 29, 2017

GUIDE SCHEDULE OF SAMPLING & TESTING FOR DESIGN-BUILD PROJECTS BY THE INDEPENDENT QUALITY FIRM (IQF) August 29, 2017 GUIDE SCHEDULE OF & TESTING FOR DESIGN-BUILD PROJECTS BY THE INDEPENDENT QUALITY FIRM (IQF) August 29, 2017 Using the Guide Schedule The Independent Quality Firm (IQF) will perform materials sampling at

More information

APWA Public Works Construction Management Seminar. March 22, 2018

APWA Public Works Construction Management Seminar. March 22, 2018 APWA Public Works Construction Management Seminar March 22, 2018 Seminar Objectives Exchange of Ideas CM - Definition & Purpose Relationship to Overall Effort Your Expectations Working with Contractors

More information

CE & I for Construction. Brian Buckel. HQ Construction Division Chief Construction Engineer

CE & I for Construction. Brian Buckel. HQ Construction Division Chief Construction Engineer CE & I for Construction Brian Buckel. HQ Construction Division Chief Construction Engineer Talking Points Outline the duties and responsibilities of both a) the sponsor s personnel b) DOTD personnel Definitions

More information

Regional Engineers. Jack A. Elston

Regional Engineers. Jack A. Elston Regional Engineers Jack A. Elston Special Provision for Hot-Mix Asphalt Pay for Performance Using Percent Within Limits Jobsite Sampling April 20, 2018 This special provision was developed by the Bureau

More information

Construction Quality Assurance Plan (CQAP)

Construction Quality Assurance Plan (CQAP) Construction Quality Assurance Plan (CQAP) for Lucks Lane Widening Project (Spirea Rd. to E. Evergreen Pkwy.) and (E. Evergreen Pkwy. To Rte. 288)- (UPC 104290 and 105674) Cover Sheet I. Date of Original

More information

DIVISION 31 EARTHWORK 2006 Edition, Published January 1, 2006; Division Revision Date: January 31, 2012

DIVISION 31 EARTHWORK 2006 Edition, Published January 1, 2006; Division Revision Date: January 31, 2012 2006 Edition, Published January 1, 2006; Division Revision Date: January 31, 2012 PART FIVE DOCUMENTS FOR SITE AND INFRASTRUCTURE 31 00 00. EARTHWORK 31 10 00. SITE CLEARING.1 STRUCTURE REMOVAL: Include

More information

Design-Builder Peformance Evaluation (DBPE)

Design-Builder Peformance Evaluation (DBPE) Design-Builder Peformance Evaluation (DBPE) There are five (5) major components of the DBPE document. Each component has multiple categories to facilitate performance evaluation for the Design-Builder,

More information

DIVISION 3 PAVEMENT (FLEXIBLE AND RIGID) CONSTRUCTION SPECIFICATIONS

DIVISION 3 PAVEMENT (FLEXIBLE AND RIGID) CONSTRUCTION SPECIFICATIONS OPS GENERAL CONDITIONS OF CONTRACT NOV 2006 General Conditions of Contract DIVISION 1 GENERAL S OCT 92 102 Weighing of Materials NOV 2004 106 Electrical Work NOV 2003 120 The Use of Explosives APR 2006

More information

Quality Management Review. MoDOT Dave Ahlvers P.E. Dennis Brucks P.E. Josh Kincaid P.E.

Quality Management Review. MoDOT Dave Ahlvers P.E. Dennis Brucks P.E. Josh Kincaid P.E. Quality Management Review MoDOT Dave Ahlvers P.E. Dennis Brucks P.E. Josh Kincaid P.E. Quality Management Introduction to Quality Management Dave Ahlvers, P.E. Review of Job Special Provision & Terms Dennis

More information

CONTINUOUS FLIGHT AUGER (CFA) PILES QC/QA PROCEDURES. Preferred QC/QA Procedures

CONTINUOUS FLIGHT AUGER (CFA) PILES QC/QA PROCEDURES. Preferred QC/QA Procedures Preferred QC/QA Procedures The Federal Highway Administration (FHWA) has provided QC/QA guidance for this technology as noted below. The reference document also contains information about construction

More information

ASPHALT BINDER QUALITY PROGRAM

ASPHALT BINDER QUALITY PROGRAM Test Procedure for ASPHALT BINDER QUALITY PROGRAM TxDOT Designation: Tex-545-C Effective Date: February 2017 1. SCOPE 1.1 The Asphalt Binder Quality Program (ABQP) provides the requirements and procedures

More information

SUPPLEMENTAL TECHNICAL SPECIFICATION

SUPPLEMENTAL TECHNICAL SPECIFICATION July 14, 2015 HIGH STRAIN DYNAMIC LOAD TESTING OF DRILLED SHAFTS 1.0 GENERAL This work shall consist of performing high-strain dynamic testing using a drop weight loading system on a test drilled shaft

More information

A. Texas Department of Transportation 2004 Standard Specifications for Construction and Maintenance of Highways, Streets and Bridges (TxDOT).

A. Texas Department of Transportation 2004 Standard Specifications for Construction and Maintenance of Highways, Streets and Bridges (TxDOT). SECTION 32 01 16 ASPHALT OVERLAY PART 1 - GENERAL 1.1 SCOPE OF WORK A. This Section specifies the requirements for scarifying, grinding, sweeping and repair of existing asphalt concrete pavement to establish

More information

ENGINEERING CHECKLIST SEDIMENT & STORMWATER MANAGEMENT BASIN CONSTRUCTION

ENGINEERING CHECKLIST SEDIMENT & STORMWATER MANAGEMENT BASIN CONSTRUCTION NEW CASTLE COUNTY DEPARTMENT OF LAND USE ENGINEERING CHECKLIST SEDIMENT & STORMWATER MANAGEMENT BASIN CONSTRUCTION For Permanent Structures, pursuant to Delaware Pond Code 378 and Delaware Sediment and

More information

GEOTECHNICAL RESISTANCE FACTORS

GEOTECHNICAL RESISTANCE FACTORS Chapter 9 GEOTECHNICAL RESISTANCE FACTORS Final SCDOT GEOTECHNICAL DESIGN MANUAL 9-i Table of Contents Section Page 9.1 Introduction... 9-1 9.2 Soil Properties... 9-2 9.3 Resistance Factors for LRFD Geotechnical

More information

Asphalt Technology Division

Asphalt Technology Division Chandra Akisetty, Division Chief 443-572-5051 Rebeccah Smith, Assistant Division Chief Field Operations 443-572-5112 Robert Voelkel, Assistant Division Chief Laboratory 443-572-5113 Asphalt Additives Anti-Strip

More information

Electrical Work. NOV Embankments Over Swamps and Compressible Soils

Electrical Work. NOV Embankments Over Swamps and Compressible Soils GENERAL & CONSTRUCTION S OPS GENERAL CONDITIONS OF CONTRACT NOV 2006 100 OPS General Conditions of Contract DIVISION 1 - GENERAL S 106 Electrical Work 120 180 The Use of Explosives General Specification

More information

EXHIBIT "A" CONSTRUCTION ENGINEERING AND INSPECTION SCOPE OF SERVICES FOR. Project Description. US 41 (SR 45) From Winkler Avenue to SR 82

EXHIBIT A CONSTRUCTION ENGINEERING AND INSPECTION SCOPE OF SERVICES FOR. Project Description. US 41 (SR 45) From Winkler Avenue to SR 82 EXHIBIT "A" CONSTRUCTION ENGINEERING AND INSPECTION SCOPE OF SERVICES FOR Project Description US 41 (SR 45) From Winkler Avenue to SR 82 Financial Project ID(s): 431313-1-62-01 Federal Project No.: N/A

More information

CETCO-VOLCLAY CG-50 SPECIFICATION GUIDELINES MIX IN PLACE

CETCO-VOLCLAY CG-50 SPECIFICATION GUIDELINES MIX IN PLACE CETCO-VOLCLAY CG-50 SPECIFICATION GUIDELINES MIX IN PLACE 1.0 GENERAL 1.1 Scope A. This specification guideline covers the technical requirements for furnishing all labor, materials, equipment, and incidentals

More information

Statement of Qualifications

Statement of Qualifications Statement of Qualifications GeoTest, Inc. 2135 S. 116th Street West Allis, WI USA Geotechnical Engineering Construction Materials Testing Construction Observation and Documentation Geological and Industrial

More information

Minimum Sample and Test Requirements (MSTR)

Minimum Sample and Test Requirements (MSTR) Minimum Sample and Test Requirements (MSTR) 1. Asphalt Construction: General Notes: The Area Engineer must furnish representative samples of component mineral aggregate materials to the Bituminous Engineer

More information

CONSTRUCTION SPECIFICATION FOR EXCAVATING AND BACKFILLING - STRUCTURES

CONSTRUCTION SPECIFICATION FOR EXCAVATING AND BACKFILLING - STRUCTURES ONTARIO PROVINCIAL STANDARD SPECIFICATION METRIC OPSS 902 DECEMBER 1983 CONSTRUCTION SPECIFICATION FOR EXCAVATING AND BACKFILLING - STRUCTURES 902.01 SCOPE 902.02 REFERENCES 902.03 DEFINITIONS TABLE OF

More information

Module 1 - Introduction. Asphalt Plant Level 1. Release 10 4/19/

Module 1 - Introduction. Asphalt Plant Level 1. Release 10 4/19/ 1-1 What will be covered? Why you are here? What are the requirements? What will happen during the course? This is a basic introduction to asphalt testing. There are other courses in asphalt pavement construction.

More information

Rapid Axial Load Testing of Drilled Shafts

Rapid Axial Load Testing of Drilled Shafts Supplemental Technical Specification for Rapid Axial Load Testing of Drilled Shafts SCDOT Designation: SC-M-712 (9/15) September 4, 2015 1.0 GENERAL This work shall consist of performing a rapid axial

More information

RECORD KEEPING AND INSPECTION NOTES FOR FUTURE NEEDS

RECORD KEEPING AND INSPECTION NOTES FOR FUTURE NEEDS RECORD KEEPING AND INSPECTION NOTES FOR FUTURE NEEDS Chris Nickel, P.E. LA DOTD Pavement & Geotechnical Services 2011 Louisiana Engineering Conference TOPIC OUTLINE Driven Piles Definitions and Data table

More information

Mid-Coast Transit Constructors Quality Control & Quality Assurance August 15, 2017

Mid-Coast Transit Constructors Quality Control & Quality Assurance August 15, 2017 Mid-Coast Transit Constructors Quality Control & Quality Assurance August 15, 2017 Welcome and Introductions Introduction Cory Raymond, MCTC DBE/SB Compliance and Outreach (DBE Team: Alison Lobenstein;

More information

Bituminous Percent Within Tolerance (PWT)

Bituminous Percent Within Tolerance (PWT) Bituminous Percent Within Tolerance (PWT) March 30 April 1, 2015 What Does PWT Drive? Strict adherence to producing the job mix formula Strict adherence to field density spec. requirements Advantages of

More information

SECTION EROSION AND SEDIMENTATION CONTROLS

SECTION EROSION AND SEDIMENTATION CONTROLS SECTION 312500 EROSION AND SEDIMENTATION CONTROLS PART 1 - GENERAL 1.01 GENERAL PROVISIONS A. Attention is directed to the CONTRACT AND GENERAL CONDITIONS and all Sections within DIVISION 01 - GENERAL

More information

Prepaving Conferences

Prepaving Conferences Prepaving Conferences Presenters ODOT: Bob Townsend Assistant Project Manager The Dalles Construction Office Knife River: Tyrone Belgarde Project Superintendent Knife River Corporation-Northwest Prepaving

More information

MANUAL OF INSTRUCTIONS MATERIALS DIVISION COMMONWEALTH OF VIRGINIA DEPARTMENT OF TRANSPORTATION

MANUAL OF INSTRUCTIONS MATERIALS DIVISION COMMONWEALTH OF VIRGINIA DEPARTMENT OF TRANSPORTATION MANUAL OF INSTRUCTIONS MATERIALS DIVISION COMMONWEALTH OF VIRGINIA DEPARTMENT OF TRANSPORTATION TABLE OF CONTENTS Chapter I - GENERAL INSTRUCTIONS...1 SECTION 101 PURPOSE AND SCOPE OF MANUAL...1 SECTION

More information

CHAPTER 7 - INFRASTRUCTURE INSPECTION AND ACCEPTANCE... 2

CHAPTER 7 - INFRASTRUCTURE INSPECTION AND ACCEPTANCE... 2 CHAPTER 7 - INFRASTRUCTURE INSPECTION AND ACCEPTANCE... 2 7.1. GENERAL.... 2 7.1.1. Inspection Restriction Dates.... 2 7.1.2. Complete Improvements.... 2 7.1.3. Public Improvements.... 2 7.1.4. Warranty

More information

Cement Stabilized Aggregate Base

Cement Stabilized Aggregate Base Supplemental Technical Specification for October 28, 2015 Cement Stabilized Aggregate Base SCDOT Designation: SC-M-308 (10/15) 1. SCOPE 1.1. Cement Stabilized Aggregate Base (CSAB) consists of aggregate,

More information

Richland County Department of Public Works Engineering (Land Development) Division

Richland County Department of Public Works Engineering (Land Development) Division Richland County Department of Public Works Engineering (Land Development) Division Commercial Projects What is a Commercial Project? Projects that are not related to residential single family homes and/or

More information

1.2 The engineer will provide Quality Assurance (QA) inspection. The role of QA is to verify the performance of the QC.

1.2 The engineer will provide Quality Assurance (QA) inspection. The role of QA is to verify the performance of the QC. Quality Management Quality Management is a pro-active and efficient method of incorporating quality into the planning and scheduling of all project activities. The contractor works together with the engineer

More information

SECTION FLEXIBLE PAVING

SECTION FLEXIBLE PAVING SECTION 321200 PART 1 GENERAL 1.01 GENERAL REQUIREMENTS A. Include GENERAL CONDITIONS and applicable parts of Division 1 as part of this Section. B. Examine all Drawings and other Sections of the Specifications

More information

Urban. Initiative. Meeting. Construction. Annual. City of Lynchburg

Urban. Initiative. Meeting. Construction. Annual. City of Lynchburg 2014 Urban Construction Initiative Annual Meeting City of Lynchburg Materials Testing Requirements for Locally Administered Projects Don French, P.E. VDOT Lynchburg District District Materials Engineer

More information

q Item meets standard Project ID: X Item not acceptable Contractor: N/A Item not applicable Inspector: C Item requires engineer s cert.

q Item meets standard Project ID: X Item not acceptable Contractor: N/A Item not applicable Inspector: C Item requires engineer s cert. SEDIMENT/STORMWATER MANAGEMENT BASIN CONSTRUCTION CHECKLIST For permanent structures per Delaware SCS Pond Code 378 and Delaware Sediment and Stormwater Regulations KEY PROJECT INFORMATION q Item meets

More information

DOT-FHWA QA/QC Plan Sample Selected pages (not a complete plan)

DOT-FHWA QA/QC Plan Sample Selected pages (not a complete plan) DOT-FHWA QA/QC Plan Sample Selected pages (not a complete plan) Part 1: Project Specific Quality Plan Part 2: Quality Manual Part 3: Submittal Forms Contact: FirstTimeQuality 410 451 8006 Pat [Pick the

More information

Warm Mix Asphalt (WMA)

Warm Mix Asphalt (WMA) Supplemental Technical Specification for Warm Mix Asphalt (WMA) SCDOT Designation: SC-M-408 (04/15) 1. SCOPE 1.1 This is a specification intended for use in placing Warm Mix Asphalt (WMA) on highways,

More information

SECTION UNCLASSIFIED EXCAVATION AND GRADING

SECTION UNCLASSIFIED EXCAVATION AND GRADING SECTION 02210 UNCLASSIFIED EXCAVATION AND GRADING PART 1 GENERAL 1.1 DESCRIPTION Work in this section includes the excavation, undercut excavating, grading, earthwork and compaction required as shown on

More information

QA/QC Program Overview. November, 2015

QA/QC Program Overview. November, 2015 QA/QC Program Overview November, 2015 Quality Roles on the Project Construction Management Oversight (CMO-Turner) functions as the TJPA s eyes and ears. Construction Manager/General Contractor (CM/GC-

More information

MINNESOTA DEPARTMENT OF TRANSPORTATION OFFICE OF MATERIALS ENGINEERING

MINNESOTA DEPARTMENT OF TRANSPORTATION OFFICE OF MATERIALS ENGINEERING Mn/DOT SD-15 (Rev. 2-2001) MINNESOTA DEPARTMENT OF TRANSPORTATION OFFICE OF MATERIALS ENGINEERING Federal Aid, State Funds, County and Municipal Federal Aid Projects This schedule outlines the minimum

More information

Student Services & Classroom Addition

Student Services & Classroom Addition SECTION 321216 - ASPHALT PAVING PART 1 GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 01 Specification Sections,

More information

Student Manual. Lesson 4- Statistical Concepts. Version /

Student Manual. Lesson 4- Statistical Concepts. Version / 4-1 4-2 Listed above are the major Learning Outcomes you will have achieved when this lesson is completed. 4-3 It is important to understand that there is Variability in constructing transportation projects.

More information

SS David L. Seago, P.E. Assistant Director of Construction Dallas District CST Conference

SS David L. Seago, P.E. Assistant Director of Construction Dallas District CST Conference SS 1122 David L. Seago, P.E. Assistant Director of Construction Dallas District Guidance Document (SS 1122) Lists some of the main differences between previous specifications used and newly implemented

More information

FINALS UNIT MANUAL MAY 2012 EDITION

FINALS UNIT MANUAL MAY 2012 EDITION FINALS UNIT MANUAL MAY 2012 EDITION PUB 11 (5-12) This page left intentionally blank. INTRODUCTION The District has the responsibility to perform a comprehensive and complete check of quantities submitted

More information

CEI Services Transit Bus Stop Infrastructure

CEI Services Transit Bus Stop Infrastructure Presentation for: Broward County Board of County Commissioners sioners V2114585P1 CEI Services Transit Bus Stop Infrastructure Presented by: SOLID Consulting Engineers, Inc. (CBE/SBE) COMPANY AND TEAM

More information

SPECIFICATIONS FOR BRIDGE CONSTRUCTION SECTION 2 BACKFILL. 2.1 General...2-1

SPECIFICATIONS FOR BRIDGE CONSTRUCTION SECTION 2 BACKFILL. 2.1 General...2-1 SPECIFICATIONS FOR BRIDGE CONSTRUCTION SECTION 2 BACKFILL TABLE OF CONTENTS 2.1 General...2-1 2.2 Materials...2-1 2.2.1 Compacted Non-granular Material...2-1 2.2.2 Gravel Material and Crushed Aggregate

More information

SECTION EXCAVATION AND EMBANKMENT. B. Subbase Grading A samples for gradation analysis.

SECTION EXCAVATION AND EMBANKMENT. B. Subbase Grading A samples for gradation analysis. PART 1 GENERAL 1.1 DESCRIPTION A. The WORK under this Section includes providing all labor, materials, tools and equipment necessary for excavation and embankment construction to the lines, grades and

More information

INS QA Programme Requirements

INS QA Programme Requirements Specification Date: 20/3/17 INS QA Programme Requirements UNCONTROLLED WHEN PRINTED Author: J Cooch AUTHORISATION Date: 20/3/17 A Brown Owner: J Cooch (Signature) N.B. only required for hard copy If issued

More information

SECTION TRENCHING & BACKFILLING

SECTION TRENCHING & BACKFILLING SECTION 02225 - TRENCHING & BACKFILLING 1.0 GENERAL 1.1 Work included in this Section includes trenching and backfilling for underground pipelines and related structures only. 1.2 Reference Specifications

More information

WELCOME TO THE PILE DRIVING INSPECTOR COURSE

WELCOME TO THE PILE DRIVING INSPECTOR COURSE Lesson 1 WELCOME TO THE PILE DRIVING INSPECTOR COURSE 1-1 Welcome to the Pile Driving Inspector Course. This is a course designed to assist students to understand the specifications and inspection practices

More information

STATE OF OHIO DEPARTMENT OF TRANSPORTATION SUPPLEMENTAL SPECIFICATION 806 ASPHALT CONCRETE WITH JOINT DENSITY FOR MULTI-LANE HIGHWAYS.

STATE OF OHIO DEPARTMENT OF TRANSPORTATION SUPPLEMENTAL SPECIFICATION 806 ASPHALT CONCRETE WITH JOINT DENSITY FOR MULTI-LANE HIGHWAYS. STATE OF OHIO DEPARTMENT OF TRANSPORTATION SUPPLEMENTAL SPECIFICATION 806 ASPHALT CONCRETE WITH JOINT DENSITY FOR MULTI-LANE HIGHWAYS March 2, 2015 806.01 Description 806.02 JMF Field Adjustments 806.03

More information

RESIDENT ENGINEER S MANUAL 2014 SPECIFICATIONS ARKANSAS STATE HIGHWAY AND TRANSPORTATION DEPARTMENT CONSTRUCTION DIVISION

RESIDENT ENGINEER S MANUAL 2014 SPECIFICATIONS ARKANSAS STATE HIGHWAY AND TRANSPORTATION DEPARTMENT CONSTRUCTION DIVISION RESIDENT ENGINEER S MANUAL 2014 SPECIFICATIONS ARKANSAS STATE HIGHWAY AND TRANSPORTATION DEPARTMENT CONSTRUCTION DIVISION FOREWORD The Construction Industry is continually changing. New technology, materials,

More information

EXHIBIT "A" CONSTRUCTION ENGINEERING AND INSPECTION SCOPE OF SERVICES FOR. Project Description

EXHIBIT A CONSTRUCTION ENGINEERING AND INSPECTION SCOPE OF SERVICES FOR. Project Description 6/23/2017 EXHIBIT "A" CONSTRUCTION ENGINEERING AND INSPECTION SCOPE OF SERVICES FOR Project Description Group 163: SR 423 (John Young Parkway) from SR 50 to Shader Rd. Financial Project ID: 239496-3-62-01

More information

SECTION XXXXX AGGREGATE PIERS PART 1 - GENERAL

SECTION XXXXX AGGREGATE PIERS PART 1 - GENERAL SECTION XXXXX AGGREGATE PIERS PART 1 - GENERAL 1.1 RELATED DOCUMENTS: Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division 00 and Division

More information

ALTERNATIVE PROJECT DELIVERY DIVISION

ALTERNATIVE PROJECT DELIVERY DIVISION VIRGINIA DEPARTMENT OF TRANSPORTATION ALTERNATIVE PROJECT DELIVERY DIVISION INSTRUCTIONAL AND INFORMATIONAL MEMORANDUM GENERAL SUBJECT: Design-Build Requirements for Advertisement SPECIFIC SUBJECT: APPROVED:

More information

CONSTRUCTION ENGINEERING SERVICES

CONSTRUCTION ENGINEERING SERVICES CONSTRUCTION ENGINEERING SERVICES Contact Our clients have relied upon TECTONIC to ensure the quality of construction projects and protect the value of their assets by employing: Experienced, Qualified

More information

Implementation of this Special Provision requires a complete understanding of the following documents:

Implementation of this Special Provision requires a complete understanding of the following documents: VIRGINIA DEPARTMENT OF TRANSPORTATION SPECIAL PROVISION FOR Quality Assurance/Quality Control (QA/QC) for the Construction of Deep Foundation Systems for Design-Build and PPTA Contracts November 10, 2009

More information

Warm Mix Asphalt (WMA)

Warm Mix Asphalt (WMA) Supplemental Technical Specification for April 1, 2011 Warm Mix Asphalt (WMA) SCDOT Designation: SC-M-408 (04/11) 1. SCOPE 1.1 This is a specification intended for use in placing Warm Mix Asphalt (WMA)

More information

Permission for Routine Infrastructure Works Letter of Approval Qualification Criteria

Permission for Routine Infrastructure Works Letter of Approval Qualification Criteria Permission for Routine Infrastructure Works Letter of Approval Qualification Criteria INTERIM PROTOCOL Authority Meeting #10/07, Res. #A293/07, January 4, 2008 1. The works outlined in Table 1 must classify

More information

MnDOT SD-15 June, 2015 (Rev. Sept., 2015) Schedule of Materials Control for 2016 Standard Specifications. Schedule of Materials Control 2016

MnDOT SD-15 June, 2015 (Rev. Sept., 2015) Schedule of Materials Control for 2016 Standard Specifications. Schedule of Materials Control 2016 Schedule of Materials Control 2016 Contents Introduction Page... 1 SCHEDULE OF MATERIALS CONTROL (For usewith the 2016 Standard Specifications for Construction): I. Grading, Base and Reclamation Construction

More information

Pilot Asphalt Specification Review Technician Duties. November 20 th, 2015 Chris Abadie Materials Engineer Administrator District 61 Conference Room

Pilot Asphalt Specification Review Technician Duties. November 20 th, 2015 Chris Abadie Materials Engineer Administrator District 61 Conference Room Pilot Asphalt Specification Review Technician Duties November 20 th, 2015 Chris Abadie Materials Engineer Administrator District 61 Conference Room Roadway Sampling Specification Mainline Roadway lot is

More information

TC3 AASHTO Technical Service Program for Training

TC3 AASHTO Technical Service Program for Training TC3 AASHTO Technical Service Program for Training Feb. 7 th 9 th Mid Atlantic Quality Assurance Workshop Ron Stanevich, PE Director of Materials Division, WVDOH TC3 AASHTO Technical Service Program for

More information

Boise City Public Works General Drainage Plan Review Requirements Checklist

Boise City Public Works General Drainage Plan Review Requirements Checklist Boise City Public Works General Drainage Plan Review Requirements Checklist Development Name Bldg. Permit # Drainage Reviewer Site Address Initial Review Date ODI Number Designer Company Name Treated Acres

More information

EXHIBIT "A" CONSTRUCTION ENGINEERING AND INSPECTION SCOPE OF SERVICES FOR. Project Description

EXHIBIT A CONSTRUCTION ENGINEERING AND INSPECTION SCOPE OF SERVICES FOR. Project Description EXHIBIT "A" CONSTRUCTION ENGINEERING AND INSPECTION SCOPE OF SERVICES FOR Project Description CEI Services for I-95 /I-595 Express Lanes Direct Connect and bridge painting from Stirling Road to Broward

More information

BRIDGE CONSTRUCTION USING SELF-PROPELLED MODULAR TRANSPORTERS (SPMT)

BRIDGE CONSTRUCTION USING SELF-PROPELLED MODULAR TRANSPORTERS (SPMT) SPECIAL PROVISION August 31, 2009 PROJECT # S-R399(42) PROJECT # S-R399(59) PIN # 6697/7236 SECTION 03253S BRIDGE CONSTRUCTION USING SELF-PROPELLED MODULAR TRANSPORTERS (SPMT) Add Section 03253S: PART

More information

SUPERPAVE FACT SHEET

SUPERPAVE FACT SHEET WASHINGTON STATE DEPARTMENT OF TRANSPORTATION December 2003 SUPERPAVE FACT SHEET stands for SUperior PERforming asphalt PAVEment and is the result of a Strategic Highway Research Program (SHRP) initiative

More information

Erosion & Sedimentation Control Policy

Erosion & Sedimentation Control Policy Issue Date 10/22/2010 Page 1 of 8 Erosion & Sedimentation Control Policy Introduction: Soil erosion is the removal of soil by water, wind, ice or gravity and sediment deposition occurs when the rate of

More information

LADOTD Construction Specifications: Parts II, III & IV MARK MORVANT, P.E. ASSOCIATE DIRECTOR, RESEARCH

LADOTD Construction Specifications: Parts II, III & IV MARK MORVANT, P.E. ASSOCIATE DIRECTOR, RESEARCH LADOTD Construction Specifications: Parts II, III & IV MARK MORVANT, P.E. ASSOCIATE DIRECTOR, RESEARCH Presentation Outline General Introduction Part II Site Preparation & Earthwork Part III Base Courses

More information

GENERAL SPECIFICATION FOR THE MANAGEMENT OF EXCESS MATERIALS

GENERAL SPECIFICATION FOR THE MANAGEMENT OF EXCESS MATERIALS ONTARIO PROVINCIAL STANDARD SPECIFICATION METRIC OPSS 180 NOVEMBER 2005 GENERAL SPECIFICATION FOR THE MANAGEMENT OF EXCESS MATERIALS TABLE OF CONTENTS 180.01 SCOPE 180.02 REFERENCES 180.03 DEFINITIONS

More information

January 2008 No. 700

January 2008 No. 700 January 2008 No. 700 INDEX FOR SPECIFICATIONS FOR GRANULAR BASE COURSE Page 700. 1 SCOPE...1 1.1 Pre-Construction Meeting...1 1.2 Mobilization of Equipment...1 700. 3 MATERIALS 3.1 Granular Base Course

More information

MEMORANDUM. Attached is a copy ofthe above Supplemental Technical Specification.

MEMORANDUM. Attached is a copy ofthe above Supplemental Technical Specification. South Carolina Department of Transportation TO: FROM: MEMORANDUM Rick Werts, Director oftraffic Engineering Jim Feda, Director of Maintenance Milt Fletcher, Materials and Research Engineer ve'cfwin Eargle,

More information

Drill Shaft Contractor and Equipment Arrive On-Site CBT Script

Drill Shaft Contractor and Equipment Arrive On-Site CBT Script Drill Shaft Contractor and Equipment Arrive On-Site CBT Script Welcome to the Drilled Shaft Inspector Course. This is Lesson 5, Contractor and equipment Arrive On-Site. To begin, select the start button

More information

JOB BB0113 SHELL LAKE STR. & APPRS. (S) MARCH 10, 2015 LETTING QUESTIONS PREVIOUSLY ASKED UNDER JOB BB0106.

JOB BB0113 SHELL LAKE STR. & APPRS. (S) MARCH 10, 2015 LETTING QUESTIONS PREVIOUSLY ASKED UNDER JOB BB0106. JOB BB0113 SHELL LAKE STR. & APPRS. (S) MARCH 10, 2015 LETTING QUESTIONS PREVIOUSLY ASKED UNDER JOB BB0106. There are notes in the plans regarding driving the test pile without the use of a follower. The

More information

T-WALL & STONE STRONG

T-WALL & STONE STRONG shawprecastsolutions.com & STONE STRONG Retaining Walls PRODUCT GUIDE & TECHNICAL REFERENCE MANUAL Providing the right solutions. The Retaining Wall System is a gravity structure constructed of individual

More information

Highway Cost Index Estimator Tool Final report PRC 17-73

Highway Cost Index Estimator Tool Final report PRC 17-73 Highway Cost Index Estimator Tool Final report PRC 17-73 Highway Cost Index Estimator Tool Texas A&M Transportation Institute PRC 17-73 March 2018 Authors Brett Huntsman Brianne Glover, J.D. Samir Huseynov

More information

Aggregate Testing Recertification. Quality Control / Quality Assurance

Aggregate Testing Recertification. Quality Control / Quality Assurance Aggregate Testing Recertification Quality Control / Quality Assurance DOT Employee Timesheet Information Charge to Office Overhead AFE- 71B4 Function- 1174 **IMPORTANT** Recertification is only for individuals

More information

Mix Design & Production Control Recertification. Quality Control / Quality Assurance

Mix Design & Production Control Recertification. Quality Control / Quality Assurance Mix Design & Production Control Recertification Quality Control / Quality Assurance SDDOT Employee Timesheet Information Charge to Office Overhead AFE 71B7 Function - 1174 **IMPORTANT** Recertification

More information

CHAPTER 10: PAVING. Refer to page 548 of the 2016 Spec book or page 573 of the 2018 Spec book for material specifications under G.

CHAPTER 10: PAVING. Refer to page 548 of the 2016 Spec book or page 573 of the 2018 Spec book for material specifications under G. CHAPTER 10: PAVING AGGREGATE Aggregate has become more specific on how it is paid for. Therefore, make sure the plan specifies they type of aggregate to use. Spec 2118 Aggregate Surfacing - Aggregate placed

More information

LAP Manual Appendix 12.6B March 2016 Project Development

LAP Manual Appendix 12.6B March 2016 Project Development LAP Manual Appendix 12.6B March 2016 Project Development CHAPTER 13 CONSTRUCTION ADMINISTRATION 13.1-13.2 - Materials Quality Assurance 13.3 - Change/Work Orders 13.4 - Claims LAP Manual 13-1 March 2016

More information

KANSAS DEPARTMENT OF TRANSPORTATION SPECIAL PROVISION TO THE STANDARD SPECIFICATIONS, EDITION OF 1990

KANSAS DEPARTMENT OF TRANSPORTATION SPECIAL PROVISION TO THE STANDARD SPECIFICATIONS, EDITION OF 1990 Sheet 1 of 14 KANSAS DEPARTMENT OF TRANSPORTATION SPECIAL PROVISION TO THE STANDARD SPECIFICATIONS, EDITION OF 1990 NOTE: This special provision is generally written in the imperative mood. The subject,

More information

ODOT District Bridge General Notes B405: OBJECT MARKERS AND STRUCTURE/CULVERT IDENTIFICATION SIGNS

ODOT District Bridge General Notes B405: OBJECT MARKERS AND STRUCTURE/CULVERT IDENTIFICATION SIGNS B401: DELETED B402: DELETED B403: DELETED B404: STRUCTURE/CULVERT IDENTIFICATION SIGNS B405: OBJECT MARKERS AND STRUCTURE/CULVERT IDENTIFICATION SIGNS B406: ITEM 514 - FIELD PAINTING, MISC.; REPAIR PAINTING

More information