Capital Projects Do your homework. CIM Toronto October 2014 Rocks and Stocks Chris Twigge-Molecey
|
|
- Madlyn Harrington
- 6 years ago
- Views:
Transcription
1 Capital Projects Do your homework CIM Toronto October 2014 Rocks and Stocks Chris Twigge-Molecey
2 2 Causes of capital over-runs Old news The symptoms: Persistent over-runs Late start-up Poor ramp-up to full production Poor safety Poor relations with neighbours Poor ROI and value destruction
3 3 Over 30 years ago (Rand Corp) Ed Merrow s criteria of failure: >10% over budget >3 months late at start-up >1 year to 85% capacity Only 18% were successful In 2011 >25% over peers cost 1 year longer to start-up than peers >2 years to full capacity Only 30% of 43 projects successful
4 4 Terry McNulty Curves (1998)
5 5 Analysis of failures (2003) 43 failures, $20+billion in CAPEX 70% not phased properly 42% turnkey lump sum contracts 63% had no team continuity 50% major new technology 40% Front end issues >100% Multiple causes of failure
6 6 Summary Findings (2014) $133 Billion in CAPEX in 45 Problem Projects Project Types and Challenges # of Projects % of Problem Projects CAPEX ($billion) % Problem Project CAPEX Problem Projects % % Technical Challenges 19 42% 49 37% Organizational Challenges 24 53% 75 56% Environmental & Social Challenges 27 60% 95 72% Homework Challenges 29 64% 68 51% >2 Challenge Areas 30 67% 98 74% >3 Challenge Areas 15 33% 45 34%
7 7 Not all bad news McNulty (2014) 23 of 81 projects 28% From 4 independent data sets
8 8 Technical Challenges $49 billion in CAPEX, or 37% of the CAPEX associated with Problem Projects Remote Locations Infrastructure More Complex Processes More complex deposits Challenges to commission New Technologies Inadequate testing
9 9 Project Risk Triangle Business Risk
10 Risk Management Failure 10 Less Profit Less Reliability, Availability etc. Poor Risk Management
11 11 Generic Risk Management Process
12 12 Summary of Technical Failure Factors Incomplete feed characterization Fast track project execution (Design & Construction) Unusually complex process conditions Design & build prior to process understood Pilot plant testing incomplete or minimal Pilot plant testing for product not process Product quality ignored in test-work Misunderstood process chemistry Prototype key equipment Minimized engineering design expenditures Serious design flaws
13 Technical Failure Factors (cont d) 13 Serious Discontinuity in the project technical team Capital cost reduced by cost reduction pressures First process license Multiple new steps Prototype key equipment Turnkey contracting of novel process Minimized engineering design expenditures Serious design flaws Raw solids feed vs.gas or liquid Unusually severe process conditions
14 Overseas Projects - Issues Vary 14 Developed countries vs. Developing Countries Form of government Legal system Physical location Technology Skills Levels Financing Civil Society Community Expectations
15 15 Key Concerns Different design approaches Different Procurement approaches Different contracting approaches Social issues Cultural issues So how will we manage this?
16 16 Front End Loading (FEL) Framework
17 17 Gate Reviews at each Project phase 1. Gate Reviews performed at the end of each phase 2. To validate the readiness to progress to the next phase 3. Three areas:
18 Project Lifecycle Accuracy of Capital Cost Estimates (Association for the Advancement of Cost Engineering-AACE) Front end study work is only a small portion of the project Capital cost 18 Project Stage Scoping Study Pre-Feasibility Study Feasibility Study Project Execution Operations Major Activities & Milestones +80 Choose project & process, complete trade-off studies Study and scoping, get funds for development Select Project, Process Alternative Complete project definition, obtain final project sanction Order Engineering for Major Equipment Complete design, reaffirm project sanction, fabricate equipment, delivery to site, install equipment and construct all facilities Decision to Proceed, Order Major Equipment Reaffirm Project Sanction Engineering Maximum Capital Cost Test equipment & systems (no feed) Start Verification of Equipment Installation First operation Mechanical Completion. Introduce Feed Material Sustained operation Design Capacity Reached. Close Project 90 Estimate Accuracy (percent of actual cost) Initial Assessment of Viability AACE Class 5 Maximum Overestimate Minimum Overestimate Minimum Underestimate Maximum Underestimate Conceptual Project Sanction AACE Class 4 Preliminary Project Sanction AACE Class 3 Final Project Sanction AACE Class 2 Engineering Minimum AACE Class 1 AACE Estimate Classes, Uses and Methodology Class 5: Concept screening, long range capital planning, assessing initial viability. Stochastic (cost/capacity curves, scale factors and other parametric modelling techniques). Extremely limited data Class 4: Confirmation of technical/economic feasibility, approval to proceed to next phase. Stochastic (equipment factors, unit cost ratios and other parametric modelling techniques). Limited data Class 3: Full budget approval, cost control. Deterministic for major items, stochastic for minor items. Normally used for funding and cost control Class 2: Detailed cost performance measurement baseline. Highly deterministic. Detailed control baseline Class 1: Current control estimate fo final control baseline. Extremely deterministic based on actual design quantities. Discrete parts of the project for check estimates of contractors quotations Capital Cost or Engineering (percent of total) Project Duration (months) 36
19 19 Typical External Project Risk Factors Water access Competing land use Artisanal mining rights Water quality Community relocation Loss of natural environment Non-local workforce Transportation bottlenecks Ref: Ernst & Young (2013)
20 20 Need to Develop Shared value approach Social license to operate Many standards and guidelines Equator Principles IFC Social & Environmental Performance Standards ISO14001 SA8000 SA800 Global Reporting Initiative (GRI)
21 21 McNulty Conclusions (2014) Causes of failure well known New technology not necessarily a concern If managed very carefully Experienced owner leadership Best qualified EPCM contractor Robust process development program
22 22 Project success is not easy. It takes effort and money. Thank you For more information, please visit
Introduction to Project Management
Introduction to Project Management 600-101 INTRODUCTION Enterprise Consultants International, Ltd. Enterprise Consultants International, Ltd. INTRODUCTION Large projects in the oil and gas industry create
More informationTop 10 Areas for Productivity Improvement on Alberta Mega Oil Sands Construction Projects
Top 10 Areas for Productivity Improvement on Alberta Mega Oil Sands Construction Projects George F. Jergeas PhD, PEng Professor of Project Management, University of Calgary October 24, 2012: BREAKOUT:
More informationEST Accuracy of FEL 2 Estimates in Process Plants
EST.2215 Accuracy of FEL 2 Estimates in Process Plants Melissa C. Matthews Abstract Estimators use a variety of practices to determine the cost of capital projects at the end of the select stage when only
More informationFeasibility Consulting & Successful Study Completion
Feasibility Consulting & Successful Study Completion Philippines Mineral Exploration Association Manila ~ 04 July 2011 Hugh Thompson Principal Mining Consultant Brisbane The views and opinions expressed
More informationCity of Oxnard. Public Works Integrated Master Plan
City of Oxnard This document is released for the purpose of information exchange review and planning only under the authority of Hugh Steve McDonald, December 2015, State of California, PE No. 44074 and
More informationIndependent Verification and Validation (IV&V)
Independent Verification and Validation (IV&V) 12 th Annual NDIA CMMI Conference November 2012 - Denver, CO The MITRE Corporation The author s affiliation with The MITRE Corporation is provided for identification
More informationInsights into Mining. Project risk and the role of the board. How can a mining company come to grips with capital cost overrun?
Insights into Mining Issue #4 kpmg.ca/mining Welcome to Insights into Mining, a periodic e-newsletter focused on current topics relevant to the Mining Industry. KPMG s mining practice is committed to the
More informationFive Global Pty Ltd ABN (0) (0)
Five Global Pty Ltd ABN 78 158 704 226 +61 (0) 468 999 561 +61 (0) 427 119 234 Introduction What is the optimum project management model that an Owner should employ to deliver a successful project? It
More informationAligning Expectations
Aligning Expectations Aligning Owners and Contractors Expectations! Key success factors & challenges Project objectives and priorities Approaches to reduce risk Management of Scope Interface management
More informationSECTION 14.0 CAPITAL COST ESTIMATES
SECTION 14.0 CAPITAL COST ESTIMATES 1 14.0 Capital Cost Estimates CONTENTS 14.0 CAPITAL COST ESTIMATES...4 14.1 Introduction...4 14.2 Overall Summary...4 14.3 Mining Capital Cost Estimate...5 14.3.1 Pre-Production
More informationVoluntary Protection Programs (VPP) 101
Development, Validation, Implementation and Enhancement of a Voluntary Protection Programs Center of Excellence (VPP CX) Capability for Department of Defense (DoD) Voluntary Protection Programs (VPP) 101
More informationPROJECT EXECUTION STRATEGIES OVERVIEW
PROJECT EXECUTION STRATEGIES OVERVIEW UpTech Upstream Oil & Gas Summit Designing And Building Success AGENDA Industry Situation Traditional Project Stage Progression Project Schedule Compression Contracting
More informationConverting One to a Million Scale-up Process for Nanotechnology Commercialization
Converting One to a Million Scale-up Process for Nanotechnology Process Steps in Planning Production Equipment Evaluation and Scale-up Government & Logistics Product Life Cycle Markets and Product Nano-PM
More informationCAPITAL INVESTMENT SYSTEMS MAKING THE RIGHT INVESTMENT DECISIONS
INTRODUCTION CAPITAL INVESTMENT SYSTEMS MAKING THE RIGHT INVESTMENT DECISIONS Neil Cusworth Managing Director Enthalpy Pty Ltd Investment decisions to develop or acquire new capital assets should be made
More informationSmartPlant 3D Materials Handling. Taylor D. Cole Vice President, Intergraph Global Metals & Mining Industry
SmartPlant 3D Materials Handling Taylor D. Cole Vice President, Intergraph Global Metals & Mining Industry Global Outlook - Commodities Global Seaborne Iron Ore Global Copper 1136 844 2 X 2 X 1421 1624
More informationIntroduction to the PDRI
Introduction to the PDRI Project Definition Rating Index a Construction Industry Institute (CII) tool SCOAR May 3, 2012 ChandlerGlobal.com Today s Discussion Why What When Who How Now what Thomas Joseph
More informationProject Management Body of Knowledge (PMBOK)
Project Management Body of Knowledge (PMBOK) Enterprise & Project Management Please note that these slides are not intended as a substitute to reading the recommended text for this course. Objectives Explain
More informationImproving Megaproject Performance
Improving Megaproject Performance 30 January 2006 Consulting Group www.westney.com The Industry s Challenge Today The CAPEX Management Challenge Mega-project failure rate Market Conditions SOX visibility
More informationCCS Project Risk Management
CCS Project Risk Management Dr. Yuri Raydugin, P.Eng., M.B.A. Principal Consultant Risk Services & Solutions Inc. Calgary, Alberta, Canada yuri.raydugin@risk-service.com Asia Clean Energy Forum - CCS Deep
More informationAGENCY FOR STATE TECHNOLOGY
AGENCY FOR STATE TECHNOLOGY PROJECT RISK & COMPLEXITY ASSESSMENT TOOL Risk & Complexity Assessment Model for State Information Technology Projects Purpose: In order to determine the level of risk associated
More informationAn Introduction to Engineering Design in the Nuclear Industry
An Introduction to Engineering Design in the Nuclear Industry Nuclear Supply Chain Event 28 th April 2016 Part 2: The Design Process Rob Barrand Lead Process Engineer Robert.barrand@nnl.co.uk Overview
More informationCargotec Supplier Requirements
Cargotec Supplier Requirements 2015-02-17 CSR V2.0 1 Management Responsibility... 6 1.1 Business Plan... 6 1.2 Key Performance Indicators... 6 1.3 Financial Stability... 6 1.4 Quality Management System...
More informationConception Design Construction Operation.
4 Development Process and Procurement 4.1 The development process by which the project moves from the earliest ideas to the final completion of the facilities and their use can be considered as having
More informationPetrochemical Complex Integration Feasibility Studies - an Investment that pays out
Petrochemical Complex Integration Feasibility Studies - an Investment that pays out Frederik Baars Global Petrochemicals Summit, Lisbon, 16 November 2016 2014 Fluor. All rights reserved. FLUOR is a registered
More informationManaging Mega Projects. Wed 6 th July, Martin Urquhart Project Director
Managing Mega Projects Wed 6 th July, Martin Urquhart Project Director Overview 13,500psi, 350 F, 500 MMscfd 6 Development Wells / 1 PWRI well CPF Jacket 7,874 mt Topsides 13,898 mt WHP 12+2 Slots Jacket
More informationEXPLORATION & NIGERIAN EXPLORATION & PRODUCTION
NOBLE HILL NIGERIAN PRODUCTION CORPORATE FOCUS & STRENGTHS ASSET IDENTIFICATION, ASSESSMENT & ACQUISITION RESERVOIR EVALUATION & REPORTING FIELD DEVELOPMENT STRATEGIC PARTNERSHIP FORMULATION MASTER PROJECT,
More information3 PART THREE: WORK PLAN AND IV&V METHODOLOGY (SECTION 5.3.3)
3 PART THREE: WORK PLAN AND IV&V METHODOLOGY (SECTION 5.3.3) Emagine IT s approach to Independent Verification and Validation (IV&V) has been shaped over the years by hands-on experience and contributions
More informationProject and Process Tailoring For Success
Project and Process Tailoring For Success 1 Key Learning Objectives Demonstrate how project/process tailoring can decrease cost by aligning process intensity with project risk and complexity Provide a
More informationSmartSPEND. KBR SmartSPEND SM. The Economic Approach to Project Development and Execution that Delivers Maximum Project Returns
SM Your Capital Optimized : Project Delivery Execution Strategy Capacity Operations KBR SM The Economic Approach to Project Development and Execution that Delivers Maximum Project Returns KBR SM Approach
More informationRISK Variability in Accuracy Ranges: A Case Study in the Canadian Hydropower Industry
RISK.1721 Variability in Accuracy Ranges: A Case Study in the Canadian Hydropower Industry John K. Hollmann, PE CCP CEP DRMP, Raminder S. Bali, P.Eng, John M. Boots, P.Eng, Chantale Germain, P.Eng, Michel
More informationDocument No: SB002-P3 Revision No: Last Updated: April
BRIEF People often are confused with the term - Out-of-Sequence, and use them in inappropriate ways. While we talk about Out-of-Sequence, we also need to discuss the difference between Retained Logic and
More informationContracting and Procurement Strategy. at the Heart of Project Delivery. Tehran, January 28 th, OMV Upstream
Contracting and Procurement Strategy at the Heart of Project Delivery Tehran, January 28 th, 2017 OMV Upstream OMV Upstream Project Delivery Global Project Portfolio Core 2 - Northsea Aasta Hansteen Gulfaks
More informationOsprey Technologies, LLC. Quality Manual ISO9001:2008 Rev -
February 8, 2015 1 Osprey Technologies, LLC Quality Manual ISO9001:2008 Rev - February 8, 2015 Released by Dave Crockett President 6100 S. Maple Avenue, Suite 117 Tempe, AZ 85283 www.osprey-tech.com February
More informationProject Controls Expo 18 th Nov 2014
Project Controls Expo 18 th Nov 2014 Emirates Stadium, London Cost Estimate Risk Analysis: For Capital Projects and Maintenance Turnarounds Copyright @ 2011. All rights reserved About the Speaker Steve
More informationMethodology for the Cost Benefit Analysis of a Large Scale Multi-phasic Software Enterprise Migration
Methodology for the Cost Benefit Analysis of a Large Scale Multi-phasic Software Enterprise Migration Bryce Meyer Jerry Jackson Jim Wessel Software Engineering Institute Carnegie Mellon University Pittsburgh,
More informationENGINEERING, PROCUREMENT & CONSTRUCTION MANAGEMENT
ENGINEERING, PROCUREMENT & CONSTRUCTION MANAGEMENT Petrofac Engineering & Production Services Petrofac at a glance Services for every stage of your project life cycle International oilfield services provider
More informationBuilding from the ground up in West Africa. The Hatch approach to projects in a developing country
Building from the ground up in West Africa The Hatch approach to projects in a developing country 2 Agenda 1. Hatch Contribution to West Africa Development 2. Three Recent Projects on Which We Worked 3.
More informationCIM Best Practice Guidelines for Mineral Processing
CIM Best Practice Guidelines for Mineral Processing Foreword These guidelines were prepared by the Sub-Committee on Best Practice Guidelines for Mineral Processing ( SBPGMP ). The committee reports to
More information06 ROBOTIZE SOURCING TASKS
06 ROBOTIZE SOURCING TASKS The advent of robotics and artificial intelligence presents major opportunities to process both complex and repetitive transactional tasks in a more efficient and cost-effective
More informationAssociation for Project Management 2008
Contents List of figures Foreword Acknowledgements 1 Introduction 01 2 What is project planning? 03 3 Why plan? 08 3.1 Reasons to plan 08 3.2 Relevance to different types of organisation 09 4 When to plan
More informationEngineering, Procurement & Construction
E P C Engineering, Procurement & Construction Consolidated Contractors Company Consolidated Contractors CCC Your EPC Company of Choice Leader in Engineering, Procurement and Construction in the Middle
More informationPART THREE: Work Plan and IV&V Methodology (RFP 5.3.3)
PART THREE: Work Plan and IV&V Methodology (RFP 5.3.3) 3.1 IV&V Methodology and Work Plan 3.1.1 NTT DATA IV&V Framework We believe that successful IV&V is more than just verification that the processes
More informationLarge Federal Agency Leverages IV&V to Achieve Quality Delivery for Critical Modernization Initiative
Large Federal Agency Leverages IV&V to Achieve Quality Delivery for Critical Modernization Initiative Capgemini Government Solutions provides Independent Verification and Validation (IV&V) services to
More information7. Model based software architecture
UNIT - III Model based software architectures: A Management perspective and technical perspective. Work Flows of the process: Software process workflows, Iteration workflows. Check Points of The process
More informationFactors to Consider When Implementing Automated Software Testing
Factors to Consider When Implementing Automated Software Testing By Larry Yang, MBA, SSCP, Security+, Oracle DBA OCA, ASTQB CTFL, ITIL V3 ITM Testing is a major component of the Software Development Lifecycle
More information73R-13: Basis of Estimate
73R-13: Basis of Estimate As Applied for the Software Services Industries Slides are used with permission from Nesma, All rights reserved. Acknowledgements For transforming AACEi 34R-05: Basis of Estimate
More informationFront End Engineering Design (FEED) Challenges in EPC Projects: Design, LLI Strategy & Fast Track
progetti Front End Engineering Design (FEED) Challenges in EPC Projects: Design, LLI Strategy & Fast Track By Armando Bianco, Engineering Manager, Eniprogetti Global Conference on EPC Contract & Project
More information48R06 SCHEDULECONSTRUCTABI
E 48R06 SA M PL SCHEDULECONSTRUCTABI LI TY REVI EW AACE International Recommended Practice No. 48R-06 SCHEDULE CONSTRUCTABILITY REVIEW TCM Framework: 7.2 Schedule Planning and Development 11.5 Value Management
More informationPrivate Public Partnerships: Sample Standard Bidding Documents for Design-Build-Operate (DBO) for Solid Waste Management
Partnerships: Sample Standard Bidding Documents for Design-Build-Operate (DBO) for Solid Waste Management Presented by Allan Rotman Sr. Environmental Specialist Context for DBO for SWM in MNA Initiated
More informationProject Management by Functional Capability. NDIA CMMI Technology Conference and User s Group November 15, 2007
Project Management by Functional Capability NDIA CMMI Technology Conference and User s Group November 15, 2007 Fred Schenker Software Engineering Institute Bob Jacobs Computer Systems Center Inc. Goals
More informationTenStep Project Management Process Summary
TenStep Project Management Process Summary Project management refers to the definition and planning, and then the subsequent management, control, and conclusion of a project. It is important to recognize
More informationLONG INTERNATIONAL. S. Andrew McIntosh
S. Andrew McIntosh LONG INTERNATIONAL Long International, Inc. 5265 Skytrail Drive Littleton, Colorado 80123-1566 USA Telephone: (303) 972-2443 Fax: (303) 200-7180 www.long-intl.com S. Andrew McIntosh
More informationFront End Management in the USA Edd Gibson, Professor Arizona State University USA
Front End Management in the USA Edd Gibson, Professor Arizona State University USA http://www.concept.ntnu.no/english/ The 6th Concept Symposium on Project Governance, 25. 26. September 2014, Norway Front
More informationScope Management 3/11/2015. Chapter 5 Learning Objectives. Project Scope. 1) Conceptual development. Problem Statements. Statement of Work (SOW)
Chapter 5 Learning Objectives Scope Management 05-01 Project Scope 05-02 Conceptual Development The process that addresses project objectives by finding the best ways to meet them. Project scope is everything
More informationNaval Set-Based Design
Naval Set-Based Design March 1, 2017 Dr. Norbert Doerry SEA 05TD norbert.doerry@navy.mil (202) 781-2520 See http://doerry.org/norbert/papers/papers.htm for more papers and presentations 1 Point Based vs
More informationINS QA Programme Requirements
Specification Date: 20/3/17 INS QA Programme Requirements UNCONTROLLED WHEN PRINTED Author: J Cooch AUTHORISATION Date: 20/3/17 A Brown Owner: J Cooch (Signature) N.B. only required for hard copy If issued
More informationLife Cycle Success Factors That Reduce the Failure Rate of IT Projects and Programs
Life Cycle Success Factors That Reduce the Failure Rate of IT Projects and Programs Eddie Williams With over 25 years of managing and overseeing successful projects and programs spanning aerospace, DOD,
More informationDavid Lucas: Cost Management in a Complex Contracting Environment
David Lucas: Cost Management in a Complex Contracting Environment Contracting is a primary method that both Owners and Contractors utilize to allocate identified risks associated with a project. In today
More informationAdvanced Work Packaging An Owner s Perspective
October, 2014 Advanced Work Packaging An Owner s Perspective ExxonMobil Development Company ExxonMobil Production Company ExxonMobil Research & Engineering This presentation includes forward-looking statements.
More informationEduard Marfà, EMEA Portfolio Marketing. Energy & Utilities Overview
Eduard Marfà, EMEA Portfolio Marketing Energy & Utilities Overview Smarter decisions, better products. Energy Industry Trends Power Generation Oil & Gas Fossil Renewables Nuclear Utilities Infrastructure
More informationENVIRONMENTAL AUDITING GUIDE TD 16/16/E
ENVIRONMENTAL AUDITING GUIDE MIDDLE EAST GASES ASSOCIATION (MEGA) European Business Center, Office BC 25 Dubai Investments Park, PO Box: 166 Dubai-UAE Tel: +971-4-8135525 / Fax: +971-4-8135575 / E-mail:
More information(PROJECT STANDARDS AND SPECIFICATIONS)
Page : 1 of 19 Project Engineering Standard www.klmtechgroup.com KLM Technology #03-12 Block Aronia, Jalan Sri Perkasa 2 Taman Tampoi Utama 81200 Johor Bahru Malaysia DESIGN AND PROJECT EXECUTION TABLE
More informationAvailable online at Energy Procedia 4 (2011) Energy Procedia 00 (2010) GHGT-10
Available online at www.sciencedirect.com Energy Procedia 4 (2011) 5911 5916 Energy Procedia 00 (2010) 000 000 Energy Procedia www.elsevier.com/locate/procedia www.elsevier.com/locate/xxx GHGT-10 Application
More informationCost Estimating Guideline February, 2017
Cost Estimating Guideline February, 2017 Procedures are subject to change without notice. Check the Capital Project Delivery website to ensure this is the current version. Table of Contents Section 1 -
More informationProgram Tetrahedron Further Developing the Concept
By Bob Prieto Fluor In my earlier paper entitled, The Program Tetrahedron : A Changed Baseline Control Basis under Strategic Program Management (Ref. 1), I made the case that the traditional control of
More informationTAMING COMPLEXITY ON MAJOR RAIL PROJECTS WITH A COLLABORATIVE SYSTEMS ENGINEERING APPROACH
TAMING COMPLEXITY ON MAJOR RAIL PROJECTS WITH A COLLABORATIVE SYSTEMS ENGINEERING APPROACH Chris Rolison CEO, Comply Serve Limited The Collaborative Systems Engineering Approach Collaboration A system
More informationINTEGRATION MANAGEMENT
1 INTEGRATION MANAGEMENT 4.1 Develop Project Charter: The process of developing a document that formally authorize a project or a phase and provides the project manager with the authority to apply organizational
More informationTHE MISSING LINK - OBJECT ORIENTED ESTIMATING
71 THE MISSING LINK - OBJECT ORIENTED ESTIMATING A PAPER BY AAFJE JANSEN-ROMIJN During the decision making process of investment projects, it is often not possible to wait for the final cost estimate,
More informationEvidence review - integrated health and social care
Evidence review - integrated health and social care Executive summary Written by the Institute of Public Care, Oxford Brookes University Published by Skills for Care October 2013 Executive Summary Introduction
More informationConstruction Family of Documents
Construction Family of Documents The EJCDC Construction Family Documents (C-Series) is intended for engineered construction projects. The current edition (2013) is endorsed by both the Construction Specifications
More informationRonald J. Rider, MBA
Ronald J. Rider, MBA LONG INTERNATIONAL Long International, Inc. 5265 Skytrail Drive Littleton, Colorado 80123-1566 USA Telephone: (303) 972-2443 Fax: (303) 200-7180 www.long-intl.com Ronald J. Rider,
More informationUse of PSA to Support the Safety Management of Nuclear Power Plants
S ON IMPLEMENTATION OF THE LEGAL REQUIREMENTS Use of PSA to Support the Safety Management of Nuclear Power Plants РР - 6/2010 ÀÃÅÍÖÈß ÇÀ ßÄÐÅÍÎ ÐÅÃÓËÈÐÀÍÅ BULGARIAN NUCLEAR REGULATORY AGENCY TABLE OF CONTENTS
More informationSustainability Plan 2015 Update
Sustainability Plan 2015 Update Building a better tomorrow Sound Transit supports communities, the environment and the economy by providing affordable, environmentally friendly public transit that connects
More informationCSU Project Management Certificate Program. Project Scope Management
CSU Project Management Certificate Program Project Scope Management Instructor: George Angel eaglebusiness@hotmail.com 303-678-9466 1 Scope gone wild! client wants what? 2 Project Scope Management Agenda
More informationBest Practices for an Owner Estimating Organization. Larry R. Dysert, CCC Conquest Consulting Group
Best Practices for an Owner Estimating Organization Larry R. Dysert, CCC Conquest Consulting Group Establish an Estimate Classification System Promotes consistency and understanding of the terminology
More informationApplying Systems Engineering to ITS Projects: Advancing Beyond Federal Rule 940. INCOSE IW Transportation Working Group January 27, 2015
Applying Systems Engineering to ITS Projects: Advancing Beyond Federal Rule 940 William Gleckler Deputy Systems Engineering Officer, NYCT Capital Program Management Vincent Cavataio, CCM Deputy Systems
More informationLARGE STORAGE TANK PROJECT
INTRODUCTION The Fairbanks Large Storage Tank is part of the Interior Energy Project (IEP) designed to expand natural gas distribution in Fairbanks and Interior Alaska. A tank with a capacity of 0.44 Bcf
More informationStrategy for the Management and Disposal of Used Nuclear Fuel and High Level Radioactive Waste
Strategy for the Management and Disposal of Used Nuclear Fuel and High Level Radioactive Waste Christopher Hanson Senior Policy Advisor Office of Nuclear Energy U.S. Department of Energy Washington, DC
More informationECC ENGINEERING MANAGEMENT STRATEGY WORKSHOP
TEAM: A ISSUE ADDRESSED: Issue 1 The cost and time required to complete engineering often exceeds the estimate. Describe the issue in specific terms, using realistic project scenarios as appropriate. Quality
More informationBest Practice - Lessons learned General Contract Management
TEBODIN Best Practice - Lessons learned General Contract Management Roy Piek, Director PMC Moscow April 19, 2017 Level of Influence Project Expenditures Visualization of Influence vs Expenditures during
More informationThe Agile PMP Teaching an Old Dog New Tricks
The Agile PMP Teaching an Old Dog New Tricks Why are we here today? What is Project Management? When will the project be done? How much will it cost? Do we all agree on what done looks like? What are the
More informationOptimize New Product Development. Presenter s Name Presenter s Title
Optimize New Product Development Presenter s Name Presenter s Title Safe Harbor Statement The following is intended to outline our general product direction. It is intended for information purposes only,
More informationMANITOBA HYDRO Power Smart Load Displacement Program. Engineering Cost Estimate Study Guide (Version 3)
MANITOBA HYDRO Power Smart Load Displacement Program Engineering Cost Estimate Study Guide (Version 3) September, 2014 * Manitoba Hydro is a licensee of the Trademark and Official Mark Load Displacement
More information- Anshuman Ghai of Iceberg Myanmar.
2017 S A L A R Y G U I D E A liberalized economy and substantial inflows of foreign investment have created a demand for skilled as well as unskilled labor in the Myanmar workplace For a growing economy
More informationREQUIRED SKILLS AND KNOWLEDGE OF COST ENGINEERING TCM Framework: General Reference (All Sections)
E 11R88 SA M PL REQUI REDSKI LLSANDKNOWLEDGE OFCOSTENGI NEERI NG AACE International Recommended Practice No. 11R-88 E REQUIRED SKILLS AND KNOWLEDGE OF COST ENGINEERING PL TCM Framework: General Reference
More informationJOB DESCRIPTION JOB DETAILS. Senior Operations Manager. REF NUMBER Senior Operations Manager: Pretoria and Bloemfontein
JOB DESCRIPTION JOB DETAILS JOB TITLE REPORTS TO DEPARTMENT Senior Operations Manager Managing Director Operations REF NUMBER Senior Operations Manager: 0003 LOCATION EMAIL ADDRESS Pretoria and Bloemfontein
More informationTracking New Coal-Fired Power Plants
Tracking New Coal-Fired Power Plants National Energy Technology Laboratory Office of Systems Analyses and Planning Erik Shuster February 18, 2008 a Tracking New Coal-Fired Power Plants This report is intended
More informationBusiness Case Guidance. Draft March 2018
Business Case Guidance Draft March 2018 This version of the Draft Business Case Guidance (The Guidance) was released in March 2018. The feedback received from stakeholders will be considered during the
More informationLocal Industry Participation Best practices in resources projects Presented by Chris Pretorius Manager Industry Connect CCIWA
Local Industry Participation Best practices in resources projects Presented by Chris Pretorius Manager Industry Connect CCIWA Benefits for projects owners Positive image in local industry Sustainable business
More informationRational Software White Paper TP 174
Reaching CMM Levels 2 and 3 with the Rational Unified Process Rational Software White Paper TP 174 Table of Contents Abstract... 1 Introduction... 1 Level 2, Repeatable... 2 Requirements Management...
More informationProbabilistic Safety Assessment Safety & Regulatory Framework
Probabilistic Safety Assessment Safety & Regulatory Framework Presentation to the CNSC August 2017 Dr. V.G. Snell 1 Purpose To summarize work done under CNSC contract 87055-16-0251: Role of the Probabilistic
More informationDraft for an Appendix O Cost Structures
CSPBankability Project Report Draft for an Appendix O Cost Structures to the SolarPACES Guideline for Bankable STE Yield Assessment Document prepared by the project CSPBankability funded by the German
More informationExclusive First Right to Selected Territory & Engineering Discipline: High Value Engineering Office
Exclusive First Right to Selected Territory & Engineering Discipline: High Value Engineering Office Business Development 131, 2607 Ellwood DR SW Edmonton AB T6X 0P7 and Business Development 205, 259 Midpark
More informationAspen Economic Evaluation Family
Aspen Economic Evaluation Family A family of products that estimates project capital costs and lifecycle asset economics from conceptual definition through detailed engineering The Aspen Economic Evaluation
More informationTop 10 Signs You're Ready (or Not)
Top 10 Signs You're Ready (or Not) For an Appraisal Gary Natwick Harris Corporation Gary Natwick - 1 Government Communications Systems Division DoD s Strategic and Business Development CMMI Technology
More information27 June 2013 Warsaw, Poland. Platts 8 th Annual European Nuclear Power 2013 Procurement for New Nuclear Programs
27 June 2013 Warsaw, Poland Platts 8 th Annual European Nuclear Power 2013 Procurement for New Nuclear Programs 1 Procurement for New Nuclear Programs Nuclear power programs risk and opportunity Supplier
More informationQuestions and Answers Contracts and Procurement Process for the Muskrat Falls Project
Questions and Answers Contracts and Procurement Process for the Muskrat Falls Project March 2014 Q1. Can you confirm whether the Asatldi bid was one third less than the next lowest bidder? A1. Nalcor Energy
More informationRevision no: 01 Date: Global Supplier Quality Assurance Network
Title: H-APQP Template Manual Purpose and Scope This document is aimed at internal and external stakeholders to describe the use of the H-APQP Template. Contents Introduction H-APQP... 2 1. Planning and
More informationFactoring Method, Used in NoDoC for Calculation of Location Factors
Factoring Method, Used in NoDoC for Calculation of Location Factors This article which is extracted from http://www.icoste.org/korev94.htm and have written by Bernard A. Pietlock, CCC, is used in NoDoC
More informationDeliver your next project on time and within budget. Integrated Projects
Deliver your next project on time and within budget. Integrated Projects Through technology and services innovation, Emerson Process Management is transforming how the process industry executes projects.
More information