Building Envelope Investigation UTHSCSA - CTRC. San Antonio, Texas. June 20, 2016

Size: px
Start display at page:

Download "Building Envelope Investigation UTHSCSA - CTRC. San Antonio, Texas. June 20, 2016"

Transcription

1 DRAFT DRAFT Building Envelope Investigation At UTHSCSA - CTRC San Antonio, Texas June 20, 2016 Zero/Six Consulting, LLC 2550 S. IH-35 Ste. 215 Austin, Texas z6consulting.com

2 Table of Contents TAB 1 TAB 2 TAB 3 TAB 4 Table of Contents Project Data/Synopsis Executive Summary Photographs Page 2 Pages 3 Pages 4-6 Pages 7-16 Draft Report Prepared By: Bart Tate Zero/Six Consulting, LLC Tab ZERO/SIX UTHSCSA - CTRC Page 2

3 Tab 2 General Information Project: Address: Owner: Client: CTRC 7979 Wurzbach San Antonio, Texas UTHSCSA Mr. Dan Parker ZSC Field Crew: Report Authors: Kelly Mitchell Niles Varney Bart Tate Miguel Hernandez Bart Tate Project Data Construction Team: Project Manager: Architect: CM: NA NA NA NA Design Code: Wind Speed: Importance Factor: Exposure: Unknown Unknown Unknown Unknown Year Built: Building Use: Storm Damage: Fire Damage: Clinical No No Levels above grade: High Rise by Code: Levels belowgrade: Approximate SF: 6 No 0 327,000 Project Synopsis The subject of this report is the leak investigation of the University of Texas Health Science Center San Antonio - Cancer Therapy & Research Center (CTRC). Zero/Six Consulting (ZSC) has been commissioned by UTHSCSA to perform an investigation of several conditions that have been experiencing ongoing water infiltration. The goal of this exercise is to develop recommendations for remediation to mitigate ongoing water infiltration. The CTRC complex consists of multiple contiguous buildings built between 1995 and These are comprised of the Urschel Tower, the Grossman Building and the Zeller Building. A multi-story parking garage is connected to the Urschel tower via an open air sky bridge. ZEL GRO All buildings can be generally described as mid-rise concrete framed structures with low-slope roofs. Grossman and Zeller have similar exterior finishes that consist primarily of architectural precast concrete panels and single glazed (non-insulated) aluminum curtain walls. Urschel is clad with URS EIFS (exterior insulation and finish system) and mix a of single glazed aluminum curtain wall and punched windows. ZERO/SIX UTHSCSA - CTRC Page 3

4 Tab 3 Executive Summary ZSC conducted an initial review of the building with site personnel to identify the locations of water infiltration that impact building operations the most. This included approximately four unique areas where significant water intrusion was occurring. Based on these findings ZSC used a variety of diagnostic water tests methods in an effort to determine the source of water infiltration. It should be noted that ZSC conducted visual observations of locations outside of the primary survey and discovered evidence of further water infiltration. Urschel: Areas of focus on the Urschel Tower included windows of patient rooms in the fourth floor hematology clinic along the east elevation. This included three rooms, two of which had punched windows and one located within the glazed aluminum curtain wall system. The area within the curtain will be referenced as URS.1 for and punched window locations referenced as URS.2 and URS.3 for reporting purposes. Prior to any water testing, the area around URS.1 was inspected for any obvious deficiencies that could be allowing water intrusion. It was apparent that past attempts had been made to correct water infiltration by wet glazing of the curtain wall. This a common remedial technique which involves sealing over the existing exterior gasketing. The wet glazing that had been done, appeared to be applied adequately but was only installed around a few of the glass panels. At adjacent areas where this had not been done, issues were noted that could potentially be the source of water entering the building. These items are described further in Tab 4 of this report. At URS.1 we were able to recreate water infiltration by placing a 8 x 10 water spray rack above the location of reported water infiltration and soaking the curtain wall at different points above the affected room for approximately 45 minutes. It was not until after this time that water was observed entering the building. This was attributed to the fact that there are at least three spandrel panels (non-vison glass panels that are insulated with mineral fiber) above the room that keep water from being readily noticeable. Water infiltration was also discovered on the level below at room U345. After water intrusion was recreated with a spray rack, the roof edge above the curtain wall (a suspect area) was thoroughly sprayed with a calibrated nozzle and no additional water entered the building. Based on these results it is evident that the curtain wall itself is contributing to water infiltration around the affected area. Additional contributing factors including the roof above could not be verified at this time but there is some evidence (dark brown water stains on the windows) to suggest that the roof is a secondary source of water infiltration. At this time, ZSC recommends that all exterior gaskets along the curtain wall are wet sealed with care taken not to restrict any of the weeps at the underside of the face caps. Further investigation of the roof and parapet flashings above are recommended if wet sealing the curtain wall does not fully mitigate water intrusion. ZERO/SIX UTHSCSA - CTRC Page 4

5 Executive Summary The test strategies used at URS.2 and URS.3 were identical. We started off by placing a spray rack directly in front of the affected windows and soaking the exterior for approximately 20 minutes. After no water was discovered the spray rack was moved up above the windows to soak the EIFS cladding between floor levels. It was not until the spray rack was positioned directly in front of the level five window that water intrusion was recorded at level 4. Additional investigating was conducted via chamber testing at the subject windows. This procedure utilizes a calibrated spray rack that is positioned on the exterior face of the window while a chamber from the interior is depressurized under static pressure to recreate wind driven rain. Each of the windows tested were subjected to increasing loads for a period of 20 minutes. The final test load reached was 3in/h 2 o. This equates to > 15 PSF which is more than the performance rating of most modern glazing systems. In other words, the windows themselves are performing fine and it is clear that water is entering through the wall not through the windows. Closer investigation of the conditions at URS. 2 & URS.3 revealed deficiencies at the EIFS lamina, the exterior shell that forms the waterproofing layer of the system. Examples of these issues can be seen in Part 4 of this report. Since the perimeter sealant joint of the window seal directly to the EIFS with no sub flashing, any water that defeats the EIFS shows its self at the window opening. The photo to the left, taken from inside the building, shows this condition. Remediation of this condition will involve the application of an elastomeric coating to the EIFS system and likely replacement of all perimeter seal around punched windows to ensure full continuity of the drainage plane. Zeller: At the Zeller building the area of focus was the Balcony feature adjacent to rooms Z548 and Z555. This feature is not truly a balcony (and not accessible from inside the building) but likely an extension of the building structure that is meant to accept a possible future sky bridge from the lot across the street. Water infiltration was reported at the level directly below where the lower portion of the balcony interfaces with the building. The depth of the roof area below did not allow for direct aerial lift access to this area so visual observations had to be conducted from inside the building at level six. No conclusive issues could be seen from inside but water infiltration was easily recreated when the spray rack was positioned just adjacent to either side of the lower projection seen in the photograph above. Water could be seen running down the inside of the vertical window mullions within approximately 3 minutes of soaking each area. Based on this, it is very likely that the source of water infiltration here is sealant detailing that has failed. Specialized equipment will be needed to access this location and to make more specific recommendation for repair. Any issues should be readily visible based on the short duration it took to produce water intrusion. ZERO/SIX UTHSCSA - CTRC Page 5

6 Executive Summary Grossman: The area of focus at the Grossman Building was located within room G355. Evidence of water damage at this location was minor compared to the previous locations. The affected area was at the third level of a section of glazed aluminum curtain wall that spans from the grade to level four. ZSC began testing this area by hanging a spray rack, approximately 6 x 8, over the roof above. The spray rack was first positioned directly at the area of water infiltration for 20 minutes. After no water penetration was observed the spray rack was moved up the wall. This continued until the spray rack was located entirely above the window system and the precast concrete panels were subjected to a direct soaking from the spray rack. It was at this point that the leak was recreated. Visual observation from the roof above confirmed that the sealant joint between precast panels had failed at this location allowing water to accumulate within the wall (no weep system was visible) and eventually showing up at room G355. ZSC recommends that all soft joints above this section of curtain wall are removed and replaced with dual sealant joint in which a weep is incorporated at the bottom of all vertical joints. Additional Commentary: During our review of the areas pointed out by building personnel, and described in detail above, it was apparent that these where not the only areas where water intrusion is occurring. Although ZSC did not have full access to the building, at many areas ZSC did notice evidence of ongoing water infiltration. Several of these areas were noted along the east elevation of the Urschel Tower, supporting our conclusion of water defeating the EIFS system here. At the Zeller and Grossman buildings many of the sealant joints between the architectural precast panels had failed or were beginning to degrade to the point of failure. These joint are urethane based sealant which typically has a service life of years. ZSC recommends that a thorough survey of the entire CTRC complex is conducted in order to develop a full repair scope. This should prioritize items based on immediate impact to the building and additionally develop a list of items for repair/ maintenance that should be budgeted on the short-term future. End of Summary ZERO/SIX UTHSCSA - CTRC Page 6

7 Tab 4 Photographs General overview sample areas were water testing and trouble shooting was conducted. From left-to-right locations are noted as URS.1, 2 & 3 Urschel Tower 1 This photo was taken from above the ceiling tile at URS.1 during our initial visit. Biological growth is indicative of long-term water infiltration Urschel Tower 2 Inspection of the curtain wall, where it had not been wet glazed highlighted deficiencies which include gaps on the exterior glazing gaskets. This material, EPDM rubber, shrinks over time and when exposed to UV. It appears that sealant has been added at many of the points but further shrinking of the gasket has allowed for voids. Urschel Tower 3 ZERO/SIX UTHSCSA - CTRC Page 7

8 Shrinkage of exterior glazing gaskets has occurred at much of the Urschel curtain wall. A full wet glazing of the wall is recommended Urschel Tower 4 Overflow scupper through the curtain wall panel infill needs to be removed and resealed. This location appears to be contributing to water infiltration Urschel Tower 5 At the hand rail along the roof edge above the curtain wall we noticed open vent holes. These holes are used for the galvanization process to allow the inside of the steel to be coated but are notorious for allowing water infiltration. Wind striking the face of the wall below can cause an updraft carrying rain into these areas. All vents should be sealed with a lead plug. Urschel Tower 6 ZERO/SIX UTHSCSA - CTRC Page 8

9 Seal al vent holes in hand rail The roof edge flashing above the head of the curtain wall appeared to be well detailed and underside was fully sealed to the face of the window. Urschel Tower 7 Although no obvious issues could be seen with the roof flashings above the curtain wall. This area cannot be ruled out as a contributor to water infiltration below. This is based on the dark brown water stain on the windows that are consistent with water containing asphalt residue. Urschel Tower 8 During testing of the curtain wall water was discovered at level three. This location was not know to us to be a problem area but based on damages to finishes this area appears regularly leak. Urschel Tower 9 ZERO/SIX UTHSCSA - CTRC Page 9

10 Inspection of the exterior wall around the punched windows revealed issues at the EIFS are very likely contributing to water infiltration Void in EIFS finish Urschel Tower 10 Approximately 1/16 crack noted in EIFS. Although minor this type of issue will allow water to enter the wall assembly and there a no means to weep water out once this happens. Urschel Tower 11 Reinforcement mesh visible at EIFS Urschel Tower 12 ZERO/SIX UTHSCSA - CTRC Page 10

11 At one of the punched windows the interior sealant joint was partially removed and it was noted that the window was sealed directly to the EIFS as expected. In this scenario and water that enters the wall assembly will be forced into the building at the window openings. Urschel Tower 13 An active leak was observed at the level three punched windows. On the east elevation of Urschel Tower. This location was not one of the areas of primary focus. Urschel Tower 14 This area was not reported to be an active leak but based on the amount of mineral deposits from past leaks our thought that water is a result of leakage through the EIFS is supported. Urschel Tower 15 ZERO/SIX UTHSCSA - CTRC Page 11

12 Evidence of water damage observed at level 2 of the east elevation (EIFS Wall). Urschel Tower 16 Areas of reported water infiltration at the Zeller Building along level 5 are highlighted in red Zeller 17 ZSC was not able to access the exterior of the balcony. Based on what could be seen from level 6 the landing appears to incorporate a deck coating on a portion of the area. Zeller 18 ZERO/SIX UTHSCSA - CTRC Page 12

13 Water infiltration was recreated by placing a spray rack directly adjacent to the lower portion of the balcony. Water entered the building in less than 5 minutes Zeller 19 The opposite side of the balcony was then tested with similar results. Zeller 20 This photo is unrelated to the water infiltration occurring at north elevation of level 5 but sealant joints within the precast concrete panels have failed in many areas. This condition was observed along the plaza at level 5.. Zeller 21 ZERO/SIX UTHSCSA - CTRC Page 13

14 Additional sealant failures documented along the plaza between Zeller and Grossman Zeller 22 Water spray rack in place during investigation of water intrusion at room G355 Affected area highlighted in red Grossman 23 The glazing system was soaked at the various points directly above this area. It was not until the spray rack was positioned entirely on the precast panel above the curtain wall that water infiltration was recreated. Grossman 24 ZERO/SIX UTHSCSA - CTRC Page 14

15 This sealant joint that has failed resulted in water entering the building and can be seen in the previous photo Grossman 25 This area observed was outside of the test locations but is an example of the poor shape of joint sealants on both the Zeller and Grossman buildings. Grossman 26 Another example of joint sealant that has failed. Grossman 27 ZERO/SIX UTHSCSA - CTRC Page 15

16 Significant water damaged was observed in Stair 3 of the Grossman building. Additional investigation is need to determine the source Grossman 28 End of Report Electronic Copy ZERO/SIX UTHSCSA - CTRC Page 16

Margaret Batts Tobin Laboratory

Margaret Batts Tobin Laboratory Roof Evaluation of Margaret Batts Tobin Laboratory The University of Texas At San Antonio Performed for UTSA Zero/Six Consulting, LLC 8423 Stewart Road Galveston, Texas 77554 409 740 0090 voice Table of

More information

RECREATIONAL EAGLE CENTER METAL ROOF ASSESSMENT AND SOLUTION

RECREATIONAL EAGLE CENTER METAL ROOF ASSESSMENT AND SOLUTION RECREATIONAL EAGLE CENTER METAL ROOF ASSESSMENT AND SOLUTION Recreational Eagle Center (00550) La Crosse, WI DSF Project No. 07H1E SEG Project No. 10975 Prepared for Division of State Facilities 101 E.

More information

Limited Leak Assessment

Limited Leak Assessment Website:www.moistureconsultantsinc.com E-Mail:support@moistureconsultantsinc.com December 2th, 2005 Limited Leak Assessment Property Address US Naval Facility Building 484 Panama City Beach, Florida Report

More information

Stucco Moisture Inspection Report

Stucco Moisture Inspection Report Website:www.ibgoodinspector.com E-Mail:support@ibgoodinspector.com January 11, 2006 Stucco Moisture Inspection Report Property Address 123 Our Street OurTown, USA 12345 Report Ordered By: Mr. & Mrs. Client

More information

WEATHERTIGHTNESS (INVASIVE MOISTURE TESTING) ASSESSMENT

WEATHERTIGHTNESS (INVASIVE MOISTURE TESTING) ASSESSMENT WEATHERTIGHTNESS (INVASIVE MOISTURE TESTING) ASSESSMENT 1 INTRODUCTION Inspection Date: 24 TH August 2016 Job No:47126 Property Inspected: 1-51 Watford Street Christchurch Weather Conditions: Fine Prepared

More information

Field Testing and Forensic Analysis for Manufacturers

Field Testing and Forensic Analysis for Manufacturers AMERICAN ARCHITECTURAL MANUFACTURERS ASSOCIATION Field Testing and Forensic Analysis for Manufacturers AAMA Special Event Webinar April 28, 2015 Welcome AAMA Members Licensees Other manufacturers Industry

More information

Forensics Engineering 8th Congress Forging Forensic Frontiers November 29 December 2, 2018, Austin, TX

Forensics Engineering 8th Congress Forging Forensic Frontiers November 29 December 2, 2018, Austin, TX This paper was published at the Forensic Engineering 8th Congress, held November 29-December 2, 2018 in Austin, TX. The published version of this paper is available for purchase and download at: https://ascelibrary.org/doi/book/10.1061/9780784482018

More information

Architectural Inspection Pitched Roofing

Architectural Inspection Pitched Roofing Architectural Inspection Pitched Roofing 0511 Pitched Roofing All components of the roof system including insulation Description of the building system Three types of pitched roofing are found at the Gastineau

More information

Moisture Survey Inspection Report

Moisture Survey Inspection Report Moisture Survey Inspection Report Date of Inspection: January 1, 2017 For the property located at: 123 Pleasant Lane Pleasantville, Washington, 98999 Report prepared for: John and Jane Doe Professional

More information

Subject: Amphitheater School District Reroofing Projects Amphi High School, Building 900 Roof Evaluation SCI Project Number:

Subject: Amphitheater School District Reroofing Projects Amphi High School, Building 900 Roof Evaluation SCI Project Number: 27 June 2016 Mr. Shane Chism, AIA Breckenridge Group 4625 E. Fort Lowell Road Tucson, Arizona 85712 Subject: Amphitheater School District Reroofing Projects Amphi High School, Building 900 Roof Evaluation

More information

Building Envelope Enclosures That Work, What Owners Want!

Building Envelope Enclosures That Work, What Owners Want! WEBINAR February 23, 2017 Building Envelope Enclosures That Work, What Owners Want! Will Ikerd, P.E. (TX), LEED AP Webinar Speakers Karl Strand President of Vertical Solutions Consulting Will Ikerd, PE

More information

East Lyme Middle School EAST LYME MIDDLE SCHOOL

East Lyme Middle School EAST LYME MIDDLE SCHOOL Description: N EAST LYME MIDDLE SCHOOL The school consists of a multi story building with lower, main and upper level floors. The typical floor framing for the main and upper levels is wide flange steel

More information

Aqua Coast Engineering

Aqua Coast Engineering Aqua Coast Engineering Ltd. P.O. Box 1367 Station A Delta, B.C. V4M 3Y8 Tel: (604)948-0958 Fax: 604)948-0959 September 1, 2011 Matthew Cheng File#:11145 Matthew Cheng Architect Inc. Fax: 604-731-3908 Unit

More information

PROPERTY PRESERVATION AND CAPITAL PLANNING

PROPERTY PRESERVATION AND CAPITAL PLANNING PROPERTY PRESERVATION AND CAPITAL PLANNING Overview What am I looking for Remaining Useful Life Estimating Planning TERMINOLOGY Shake Siding Service Head Barge Board Soffit / Overhang Belly Band Knee Brace

More information

Determination 2010/052 Refusal to issue a code compliance certificate for a 6-year old house at 103 Karewa Parade, Papamoa

Determination 2010/052 Refusal to issue a code compliance certificate for a 6-year old house at 103 Karewa Parade, Papamoa Determination 2010/052 Refusal to issue a code compliance certificate for a 6-year old house at 103 Karewa Parade, Papamoa 1. The matters to be determined 1.1 This is a determination under Part 3 Subpart

More information

Building Envelope Systems Exam Learning Objectives

Building Envelope Systems Exam Learning Objectives Building Envelope Systems Exam Learning Objectives Roofing Nomenclature 1. Define the following roofing terms: low, flat, sloped, conventional, protected/inverted, hybrid, BUR, modified bitumen, PVC, TPO,

More information

System WV410 Storefront Window System

System WV410 Storefront Window System E F C O C O R P O R A T I O N Visit us on the web at efcocorp.com Manufacturer Of Architectural Configurations Project-out Casement-out The WV410 storefront vent system is designed to be field glazed and

More information

Exterior Elevated Elements Inspection Guidelines

Exterior Elevated Elements Inspection Guidelines Exterior Elevated Elements Inspection Guidelines Planning and Development 1. Guideline Purpose These guidelines are intended to assist practicing professionals in complying with Berkeley Municipal Code

More information

National Property Inspections

National Property Inspections National Property Inspections Anywhere, USA (325) 382-8754 Property Location 9375 Burt Street Anywhere USA Prepared for John Investor Consultant Al Standard (325) 382-8754 Page 1 of 27 TABLE OF CONTENTS

More information

BUILDING ENCLOSURE COMMISSIONING PLAN PROJECT NAME

BUILDING ENCLOSURE COMMISSIONING PLAN PROJECT NAME BUILDING ENCLOSURE COMMISSIONING PLAN For The PROJECT NAME Building Enclosure Commissioning Plan Overview The purpose of the Building Enclosure Commissioning Plan is to provide a clear and concise roadmap

More information

A Design-Build Project: Repairing the Courthouse Square Complex

A Design-Build Project: Repairing the Courthouse Square Complex A Design-Build Project: Repairing the Courthouse Square Complex Cracked drywall in office building Cracked basement walls Separated columns at expansion joint Source: http://djcoregon.com/news/2010/07/22/salem-government-building-unsound-being-vacated/

More information

SAMPLE REPORT Location:

SAMPLE REPORT Location: Stucco Check Inspections, LLC Invasive Stucco Inspection Prepared for: SAMPLE REPORT Location: Sample Houston, TX PHONE: 713.319.5751 EMAIL: Info@stuccocheck.com I. INTRODUCTION 1.1 PURPOSE: Enclosed is

More information

ROOME & GUARRACINO, LLC Consulting Structural Engineers 48 Grove Street Somerville, MA Tel: Fax:

ROOME & GUARRACINO, LLC Consulting Structural Engineers 48 Grove Street Somerville, MA Tel: Fax: ROOME & GUARRACINO, LLC Consulting Structural Engineers 48 Grove Street Somerville, MA 02144 Tel: 617.628.1700 Fax: 617.628.1711 March 3, 2016 Mr. Jeff Hoover, Principal Tappe Architects, 6 Edgerly Place

More information

WeatherSmart Air Barrier Installation Guide

WeatherSmart Air Barrier Installation Guide WeatherSmart Air Barrier Installation Guide 1 The intent of this document is to provide a guide for the installation of WeatherSmart as both a Weather Resistive Barrier (W.R.B.) and an Air Barrier Material

More information

via only:

via  only: July 22, 2011 via email only: lschultz@mcmproperty.com The Board of Directors of The Solace Condominium c/o Ms. Linda Schultz, Condominium Manager MCM Property Management Ltd. 200 1010 8 th Avenue SW Calgary,

More information

Building Inspection Report

Building Inspection Report Building Inspection Report Sample Commercial Inspection Report Inspection Date: Prepared For: Prepared By: Professional Property Inspection Consultants 4857 Winterset Drive Columbus, OH 43220 (614) 459-5941

More information

STRUCTURAL ASSESSMENT OBSERVATION REPORT

STRUCTURAL ASSESSMENT OBSERVATION REPORT Consulting Engineers THORSON BAKER & Associates, Inc. 3030 West Streetsboro Road (330) 659-6688 phone Richfield, Ohio 44286 (330) 659-6675 fax www.thorsonbaker.com STRUCTURAL ASSESSMENT OBSERVATION REPORT

More information

CCIM Central Canada Chapter. Richard Weldon, P.Eng., LEED AP Carson Dunlop Weldon & Associates Ltd. October 5,

CCIM Central Canada Chapter. Richard Weldon, P.Eng., LEED AP Carson Dunlop Weldon & Associates Ltd. October 5, Minimizing Risk When Purchasing or Leasing CCIM Central Canada Chapter Richard Weldon, P.Eng., LEED AP Carson Dunlop Weldon & Associates Ltd. October 5, 2010 www.cdwengineering.com Who We Are CDW is a

More information

SECTION ALUMINUM STORM WINDOWS

SECTION ALUMINUM STORM WINDOWS PART 1 - GENERAL 1.1 DESCRIPTION SECTION 08 51 69.11 1. Use this section only for NCA projects. 2. Delete between //----// if not applicable to project. Also delete any other item or paragraph not applicable

More information

INSTALLING WATER-RESISTIVE BARRIERS & FLASHING

INSTALLING WATER-RESISTIVE BARRIERS & FLASHING INSTALLING WATER-RESISTIVE BARRIERS & FLASHING IN A TWO-LAYER STUCCO APPLICATION Fortifiber Building Systems Group provides this guide to assist installers by demonstrating a two-layer installation of

More information

Building Your Visions

Building Your Visions Ferguson C EAP Curtain Wall Systems Ferguson-EAP 130HP Series High Performance Curtain Wall System Ferguson s 130HP curtain wall system was developed for high performance double, triple, unique acoustical

More information

Tile on Existing. Viewpoint

Tile on Existing. Viewpoint Viewpoint Tile on Existing Exterior Reinforced Concrete BalconieS By Steven C. Turner Exterior reinforced concrete balconies are often covered by tile set in mortar beds with grouted joints. These installations

More information

SPACE TYPE: OUTSIDE PARKING (STRUCTURE)

SPACE TYPE: OUTSIDE PARKING (STRUCTURE) SPACE TYPE: OUTSIDE PARKING (STRUCTURE) Construction Criteria The unit costs for Outside Parking (Structure) space types are based on the construction quality and design features in the following table.

More information

SECTION METAL FRAMED SKYLIGHT. A. Engineering, preparation of fabrication drawings and structural calculations for the entire skylight system.

SECTION METAL FRAMED SKYLIGHT. A. Engineering, preparation of fabrication drawings and structural calculations for the entire skylight system. SECTION 08625 METAL FRAMED SKYLIGHT PART 1 GENERAL 1.01 SECTION INCLUDES: A. Engineering, preparation of fabrication drawings and structural calculations for the entire skylight system. B. Fabrication

More information

SPECIFICATION For the Supply and Installation of BRITAL UN Four Sided Unitized Structurally Glazed Curtain Walling

SPECIFICATION For the Supply and Installation of BRITAL UN Four Sided Unitized Structurally Glazed Curtain Walling SPECIFICATION For the Supply and Installation of BRITAL UN-4-76 Four Sided Unitized Structurally Glazed Curtain Walling Issue date Revision Comment 07/05/09 R0 Draft 11/05/09 R1 Approved for Issue R1 Amended

More information

SECTION STAINLESS STEEL WALL PANELS

SECTION STAINLESS STEEL WALL PANELS SECTION 07400 PART 1 GENERAL 1.1 SUMMARY A. Section Includes: 1. Dry joint, Rainscreen stainless steel wall panel system. 2. Accessories including attachments, clips, sub girts, shims, and fasteners 3.

More information

Property Condition Assessment

Property Condition Assessment Property Condition Assessment Pewaukee, WI 53072 Inspection Date: 1/6/15 Prepared For: Report Number: Prepared By: Shamrock Building Inspection Consultants LLC N29 W29951 Shel-Mar Dr. Pewaukee, WI 53072

More information

Recognizing and Addressing Moisture Concerns by Mike Endredi

Recognizing and Addressing Moisture Concerns by Mike Endredi Recognizing and Addressing Moisture Concerns by Mike Endredi Moisture within a building can leave a building owner feeling panicked, perplexed and helpless. The myriad of moisture sources can be overwhelming.

More information

SECTION DETAILS (MECHANICALLY ASSEMBLY)

SECTION DETAILS (MECHANICALLY ASSEMBLY) COVER SHEET ELEVATION SHEET SECTION DETAILS (MECHANICALLY ASSEMBLY) SECTION DETAILS (MECHANICALLY ASSEMBLY) SECTION DETAILS (WELDED ASSEMBLY) SECTION DETAILS (WELDED ASSEMBLY) SECTION DETAILS (DOOR ASSEMBLY)

More information

Julie Glover and Kevin Brown KTA-Tator, Inc. Wind-Driven Rain Assessment

Julie Glover and Kevin Brown KTA-Tator, Inc. Wind-Driven Rain Assessment Julie Glover and Kevin Brown KTA-Tator, Inc. Wind-Driven Rain Assessment Explain the differences between waterproof, weatherproof, and water repellent. Identify a laboratory test method used for determining

More information

Building Technology Consultants, Inc. Charles Sietmann, RRO, CCCA, CIT Senior Project Manager REGISTRATIONS.

Building Technology Consultants, Inc. Charles Sietmann, RRO, CCCA, CIT Senior Project Manager REGISTRATIONS. Charles Sietmann, RRO, CCCA, CIT Senior Project Manager csietmann@btc.expert Charles Sietmann is a Senior Project Manager at Building Technology Consultants, Inc. REGISTRATIONS Registered Roof Observer

More information

EIFS Rain Control EIFS. Face Sealed Perfect Barrier. Beware of EIFS: They must be done correctly They leak at joints Avoid moist sensitive substrate

EIFS Rain Control EIFS. Face Sealed Perfect Barrier. Beware of EIFS: They must be done correctly They leak at joints Avoid moist sensitive substrate EIFS Rain Control Both Drained and Perfect Barrier can be used Joints and Element can be designed differently Face Sealed Perfect Barrier The problem wall of the past Relies on sealant = dangerous Often

More information

Building Enclosure Commissioning

Building Enclosure Commissioning Building Enclosure Commissioning John Runkle, P.E. Vice President Building Sciences October 5, 2016 Program Outline Defining the Enclosure Building Science Concepts Façade Design State of the Practice

More information

Signature Series 5 Lap SECTION ALUMINUM WINDOWS

Signature Series 5 Lap SECTION ALUMINUM WINDOWS Signature Series 5 Lap SECTION 08 51 13 ALUMINUM WINDOWS PART 1 GENERAL 1.01 SUMMARY A. Related Documents: Conditions of the Contract, Division 1 - General Requirements, and Drawings apply to Work of this

More information

SECTION FLUID-APPLIED MEMBRANE AIR BARRIERS, VAPOR PERMEABLE

SECTION FLUID-APPLIED MEMBRANE AIR BARRIERS, VAPOR PERMEABLE PART 1 - GENERAL 1.1 SUMMARY SECTION 07 27 26 FLUID-APPLIED MEMBRANE AIR BARRIERS, VAPOR PERMEABLE SPEC WRITER NOTE: 1. Delete text between // // not applicable to project. Edit remaining text to suit

More information

Moonlight Architecture, Inc. Architecture Interior Design Site Planning

Moonlight Architecture, Inc. Architecture Interior Design Site Planning Moonlight Architecture, Inc. Architecture Interior Design Site Planning 22 May 2018 18057 Mr. Michael J. Petit de Mange, County Administrator Kent County Levy Court 555 Bay Road Dover, DE 19901 RE: Facilities

More information

Building Construction and Water Intrusion

Building Construction and Water Intrusion Building Construction and Water Intrusion RAY CHOY-MARSHALL GOVAN ASSOCIATES an architectural corporation ray_choy-marshall@sbcglobal.net 2930 camino diablo, suite 210, walnut creek, ca 94597 2004 Design

More information

City of Lake Oswego City Hall

City of Lake Oswego City Hall City Hall 380 A Avenue, Lake Oswego, OR 97034 Presented To:, Public Works Department C/O Ms. Rachael Petersen, CFM P.O. Box 369, Lake Oswego, OR 97034 MH Project Number: P150162.00 July 08, 2015 Morrison

More information

WATERGATE COMMUNITY ASSOCIATION 8 Captain Drive Emeryville, California Office: / Fax: WINDOW REPLACEMENT GUIDELINES

WATERGATE COMMUNITY ASSOCIATION 8 Captain Drive Emeryville, California Office: / Fax: WINDOW REPLACEMENT GUIDELINES WINDOW REPLACEMENT GUIDELINES GENERAL 1. Complete and receive approval for WCA s Unit Modification Application for window replacement. 2. Obtain a permit for replacement window installation from the City

More information

Site Bldg Fiscal Yr System Sub-System. Verde Valley Site site 2014/15 Parking Paving. Verde Valley Site site 2014/15 Sidewalks

Site Bldg Fiscal Yr System Sub-System. Verde Valley Site site 2014/15 Parking Paving. Verde Valley Site site 2014/15 Sidewalks Site Bldg Fiscal Yr System Sub-System Site site 2014/15 Parking Paving Site site 2014/15 Sidewalks Skill Center L 2015/16 Architectural Partitions Site Site 2015/16 Parking Striping Arc Center M 2014/15

More information

DIVISION 7 - THERMAL AND MOISTURE PROTECTION

DIVISION 7 - THERMAL AND MOISTURE PROTECTION 07100 WATERPROOFING 07150 DAMPPROOFING 07175 Water Repellent Coatings 07190 VAPOR AND AIR RETARDERS 07192 Vapor Retarders 07200 INSULATION 07240 Exterior Insulation and Finish Systems 07250 FIREPROOFING

More information

Groundwater Seepage. Causes of Basement Seepage and Leaks Hydrostatic Pressure

Groundwater Seepage. Causes of Basement Seepage and Leaks Hydrostatic Pressure Groundwater Seepage The following guide can be used by you and your crews when assessing seepage at a property. Bear in mind that this guide is not all-inclusive, and should be used in a supplementary

More information

KORA_Req._for_Eng._Studies_on_Stouffer_Apts. KU Reference No

KORA_Req._for_Eng._Studies_on_Stouffer_Apts. KU Reference No 000130 1 PURPOSE: Professional Engineering Consultants, P.A. (PEC) was engaged by University of Kansas Design & Construction Management to perform an assessment of Stouffer Place Apartment Building 20

More information

Prepared By. Accent Building Sciences Inc. For

Prepared By. Accent Building Sciences Inc. For ROOF LEAK INVESTIGATION & CONDITION ASSESSMENT REPORT For Toronto, Ontario Prepared By Accent Building Sciences Inc. For Client# 40105 Date: November 11, 2003 November 2003 Roof Leak Investigations & Condition

More information

AIR BARRIER DESIGN PRINCIPLES AN OVERVIEW.

AIR BARRIER DESIGN PRINCIPLES AN OVERVIEW. AIR BARRIER DESIGN PRINCIPLES AN OVERVIEW www.stromatech.com AIR BARRIER DESIGN PRINCIPLES Building Regulations Approved Document Parts L1A & L2A currently requires that new buildings have to achieve a

More information

CONSTRUCTION WATERPROOFING HANDBOOK QUESTIONS

CONSTRUCTION WATERPROOFING HANDBOOK QUESTIONS CONSTRUCTION WATERPROOFING HANDBOOK QUESTIONS 1. Which of the following is an advantage to using clear sealers for waterproofing decks? A. It is completely waterproof B. It has crack-bridging capability

More information

COVER SHEET ELEVATION SHEET SECTION DETAILS (MECHANICALLY ASSEMBLY) SECTION DETAILS (WELDED ASSEMBLY)

COVER SHEET ELEVATION SHEET SECTION DETAILS (MECHANICALLY ASSEMBLY) SECTION DETAILS (WELDED ASSEMBLY) COVER SHEET ELEVATION SHEET SECTION DETAILS (MECHANICALLY ASSEMBLY) SECTION DETAILS (MECHANICALLY ASSEMBLY) SECTION DETAILS (WELDED ASSEMBLY) SECTION DETAILS (WELDED ASSEMBLY) SECTION DETAILS (DOOR ASSEMBLY)

More information

Gensler 2014/06/16 Hertz Global Headquarters ISSUE FOR BUILDING PERMIT Estero, Florida SECTION

Gensler 2014/06/16 Hertz Global Headquarters ISSUE FOR BUILDING PERMIT Estero, Florida SECTION SECTION 072700 VAPOR PERMEABLE AIR BARRIER LIQUID MEMBRANE PART 1 GENERAL 1.1 GENERAL REQUIREMENTS A. The Work of this Section, as shown or specified, shall be in accordance with the requirements of the

More information

PROPOSED CHANGE TO THE 2012 BUILDING CODE O. REG. 332/12 AS AMENDED

PROPOSED CHANGE TO THE 2012 BUILDING CODE O. REG. 332/12 AS AMENDED Ministry of Municipal Affairs PROPOSED CHANGE TO THE 2012 BUILDING CODE O. REG. 332/12 AS AMENDED CHANGE NUMBER: SOURCE: B-05-10-03 Ontario-mNBC CODE REFERENCE: Division B / 5.10.3. DESCRIPTION OF THE

More information

GAUTENG DEPARTMENT OF INFRUSTRUCTURE DEVELOPMENT

GAUTENG DEPARTMENT OF INFRUSTRUCTURE DEVELOPMENT GAUTENG DEPARTMENT OF INFRUSTRUCTURE DEVELOPMENT BUILDING ASSESSMENT REPORT STRUCTURAL FOR CORNER HOUSE AUG 2014 i P a g e Table of Contents 1. INTRODUCTION... 3 1.1 Design Criteria and Specifications...

More information

Differences between EnCon Insulated Precast and EIFS

Differences between EnCon Insulated Precast and EIFS Differences between EnCon Cover Differences between EnCon EnCon produces a number of different insulated precast concrete products. They range from Insulated Wall panels, Styrocore Insulated Wall Panels,

More information

By definition, envelope is an

By definition, envelope is an By definition, envelope is an encapsulating covering such as an outer shell or membrane. In simple building terms, it consists of the roof, the above-grade wall system, and the below-grade wall system.

More information

7000 Series Curtain Wall Information Specifications

7000 Series Curtain Wall Information Specifications 7000 Series Curtain Wall Information Specifications Information All framing members shown in this section, unless noted otherwise, are stock items in dark bronze or clear anodic coatings and are available

More information

SECTION / METAL FRAMED SKYLIGHTS

SECTION / METAL FRAMED SKYLIGHTS Specifier Notes: This product guide specification is written according to the Construction Specifications Institute (CSI) Format, including MasterFormat, SectionFormat, and PageFormat, contained in the

More information

Using ASTM E2128 Standard Guide for Evaluating Leakage of Building Walls

Using ASTM E2128 Standard Guide for Evaluating Leakage of Building Walls Using ASTM E2128 Standard Guide for Evaluating Leakage of Building Walls Robert Kudder, PhD, S.E., FASTM Raths, Raths & Johnson, Inc BEC Detroit, October 14, 2014 Background! 1986 Alan Yorkdale and James

More information

Building Design & Maintenance

Building Design & Maintenance As with the Chapter Review Tests and the Final Exam, the tests your understanding of the materials underlying the learning objectives. After you ve reviewed your answers to the Chapter Review Tests, try

More information

TEST REPORT. Rendered to: TFC A DIVISION OF CENTURION INDUSTRIES, INC. Garrett, Indiana

TEST REPORT. Rendered to: TFC A DIVISION OF CENTURION INDUSTRIES, INC. Garrett, Indiana Architectural Testing TEST REPORT Report No.: D0162.01-201-44 Rendered to: TFC A DIVISION OF CENTURION INDUSTRIES, INC. Garrett, Indiana PRODUCT TYPE: Pressure Equalized Rainscreen SERIES/MODEL: 4 mm Composite

More information

Figure 2. By John H. Koester

Figure 2. By John H. Koester By John H. Koester Figure 2 There are numerous factors/phenomena that create misunderstandings that result in improper or inadequate moisture management design for the exterior building envelope. Let s

More information

Item 2.3 Unit pricing GC to provide a square foot unit cost for material and labor to replace plywood decking beneath new concrete walkway slab.

Item 2.3 Unit pricing GC to provide a square foot unit cost for material and labor to replace plywood decking beneath new concrete walkway slab. Willow Glen Housing Repairs Project #9-59 Addendum Item. Change to bid date The bid date will be extended to March 8, 09, :00pm at the Housing Authority of Columbus Central Office,000 Wynnton Road Columbus,

More information

MOCK-UP TEST REPORT. Report No: NCTL Test Dates:06/22, 07/23-27/10 Test Dates: 08/23-25/10 Report Date: 08/26/10

MOCK-UP TEST REPORT. Report No: NCTL Test Dates:06/22, 07/23-27/10 Test Dates: 08/23-25/10 Report Date: 08/26/10 MOCK-UP TEST REPORT Report No: NCTL-110-11828-3 Test Dates:06/22, 07/23-27/10 Test Dates: 08/23-25/10 Report Date: 08/26/10 Client: Alumil N.A. Corporation 4401 21 st. Street, Suite 203 Long Island City,

More information

Building Science Control Layer Glossary. Façade Visible exterior face of a building, usually vertical or nearly so, but imprecisely used.

Building Science Control Layer Glossary. Façade Visible exterior face of a building, usually vertical or nearly so, but imprecisely used. It is far more important than often appreciated to use precise, unambiguous, clear definitions when describing aspects of buildings, building enclosures, and building science performance. The following

More information

Structural Condition Assessment

Structural Condition Assessment 108 6 th Street, Garland, Texas Engineering Report Date: September 29, 2016 RLG No. : 16729 Prepared for: Mr. Jeff D. Bulls III AIA 3030 LBJ Freeway, Suite 1220 Dallas, TX 75234 PM: Harold F. Phillips

More information

Chapter 2 Understanding The Problem

Chapter 2 Understanding The Problem Chapter 2 Understanding The Problem What Causes Most Of The Problems With Stucco? EIFS was originally intended to seal and insulate the exterior of the home from the elements. Problems occur when poorly

More information

TABLE OF CONTENTS Updated 1/2014 SECTION TITLE DATE

TABLE OF CONTENTS Updated 1/2014 SECTION TITLE DATE TABLE OF CONTENTS SECTION TITLE DATE Division 00 Procurement and Contracting Requirements 000101... Project Title Page 000116... CAD Standards 001116... Invitation to Bid 002113... Instructions to Bidders

More information

How-to: Commissioning Design Reviews for the Building Envelope

How-to: Commissioning Design Reviews for the Building Envelope AABC Commissioning Group AIA Provider Number 50111116 How-to: Commissioning Design Reviews for the Building Envelope Course Number: CXENERGY1625 Stevan Vinci, BECxP, LEED AP, Morrison Hershfield Maurya

More information

PHILMONT WAREHOUSE BUILDING PRELIMINARY STRUCTURAL ASSESSMENT

PHILMONT WAREHOUSE BUILDING PRELIMINARY STRUCTURAL ASSESSMENT PHILMONT WAREHOUSE BUILDING PRELIMINARY STRUCTURAL ASSESSMENT Prepared for: GATTER ARCHITECTS 111 MAIN ST. PHILMONT, NY 12565 Prepared by: TACONIC ENGINEERING, DPC PO BOX 272 CHATHAM, NY 12037 TACONIC

More information

EXECUTIVE SUMMARY INTRODUCTION Terms of Reference Building Description Documents Reviewed SUMMARY OF FIELD DATA 4

EXECUTIVE SUMMARY INTRODUCTION Terms of Reference Building Description Documents Reviewed SUMMARY OF FIELD DATA 4 Abbott Place Wood Framed Window Condition Assessment May 30, 2012 TABLE OF CONTENTS EXECUTIVE SUMMARY 1 1.0 INTRODUCTION 2 1.1 Terms of Reference 2 1.2 Building Description 3 1.3 Documents Reviewed 3 2.0

More information

Henri Fennell, CSI/CDT ABX 2015

Henri Fennell, CSI/CDT ABX 2015 Henri Fennell, CSI/CDT ABX 2015 Henri is an architect and building envelope specialist with over forty years of experience in the construction industry. He was a pioneer in the solar industry, introduced

More information

SECTION ALUMINUM-FRAMED HIGH PERFORMANCE THERMAL ENTRANCE DOORS

SECTION ALUMINUM-FRAMED HIGH PERFORMANCE THERMAL ENTRANCE DOORS PART 1 GENERAL SECTION 08 1116 ALUMINUM-FRAMED HIGH PERFORMANCE THERMAL ENTRANCE DOORS 1.01 SECTION INCLUDES A. Aluminum-framed storefront, with vision glass. B. Infill panels of glass. C. Aluminum doors

More information

Building Enclosure Detailing for Balconies

Building Enclosure Detailing for Balconies Building Enclosure Detailing for Balconies COLIN SHANE M.ENG., P.ENG., P.E. PRINCIPAL, SENIOR PROJECT MANAGER RDH BUILDING SCIENCE INC. JUNE 2017 Disclaimer: This presentation was developed by a third

More information

Considerations in the Repair and Replacement of Historic Windows

Considerations in the Repair and Replacement of Historic Windows Considerations in the Repair and Replacement of Historic Windows Carolyn L. Searls, PE, LEED AP BD+C Senior Principal Taryn N. Williams, SE Senior Staff II Simpson Gumpertz & Heger California Preservation

More information

Weatherproofing Masonry For Northern Climates

Weatherproofing Masonry For Northern Climates The enduring strength, beauty and performance of a brick wall assembly is critically dependant on three components: design, workmanship and materials. If even one of these factors has not been diligently

More information

Fundamentals of Building Construction: Materials and Methods

Fundamentals of Building Construction: Materials and Methods Fundamentals of Building Construction: Materials and Methods Allen, Edward ISBN-13: 9780470074688 Table of Contents Preface. Chapter 1: Making Buildings. Learning to Build. Sustainability. The Work of

More information

SOTA THERMO 3 SERIES SPECIFICATION FOR PREGLAZED & UNITIZED THERMO 3 CURTAINWALL SYSTEM

SOTA THERMO 3 SERIES SPECIFICATION FOR PREGLAZED & UNITIZED THERMO 3 CURTAINWALL SYSTEM 1. General 1.1 Description of Work a. Furnish the labour, materials and other services to complete the fabrication and installation of Thermo 3 Series framing, including all materials and fitments required

More information

Thermal Patterns Created By Moisture Accumulation Within Exterior Masonry Walls by A. Colantonio* and G. Desroches ** * Public Works And Government Services Canada, Ottawa, Canada ** Public Works And Government

More information

Structural Inspection

Structural Inspection General: Background: An inspection and structural analysis have been performed for the purpose of evaluating the buildings structural systems and components. A full set of structural drawings was utilized

More information

PG&E BUILDING AT 215 MARKET STREET

PG&E BUILDING AT 215 MARKET STREET San Francisco, CA ICRI Northern California Chapter 2017 Concrete Repair Awards Simpson Gumpertz & Heger Inc. OVERVIEW The historic 215 Market Street Annex is a seven-story office building in downtown San

More information

SECTION ALUMINUM-FRAMED ENTRANCES AND STOREFRONTS

SECTION ALUMINUM-FRAMED ENTRANCES AND STOREFRONTS SECTION 08 4113 ALUMINUM-FRAMED ENTRANCES AND STOREFRONTS PART 1 GENERAL 1.1 SUMMARY A. Section Includes: 1. Aluminum entrance doors and frames. 2. Glass infill panels. 3. Door hardware. B. Related Sections:

More information

SPECIFICATION For the Supply and Installation of BRITAL SG-2-56-HFF. Two Sided Structurally Glazed Curtain Walling. (Horizontal Structural joints)

SPECIFICATION For the Supply and Installation of BRITAL SG-2-56-HFF. Two Sided Structurally Glazed Curtain Walling. (Horizontal Structural joints) SPECIFICATION For the Supply and Installation of BRITAL SG-2-56-HFF Two Sided Structurally Glazed Curtain Walling (Horizontal Structural joints) Issue date Revision Comment R0 Draft 05/05/09 R1 Approved

More information

Foundations. Issue. Slab-On-Grade Liquid Water Control (See Figure 2-2) Goals. Guidance

Foundations. Issue. Slab-On-Grade Liquid Water Control (See Figure 2-2) Goals. Guidance www.epa.gov/iaq/moisture Foundations Issue Building foundations are vulnerable to moisture problems for a number of reasons, including: Water from rain and from plumbing leaks is drawn by gravity to foundations,

More information

TABLE OF CONTENTS DIVISION 1 GENERAL REQUIREMENTS

TABLE OF CONTENTS DIVISION 1 GENERAL REQUIREMENTS AIA General Conditions... GC-1 to GC-44 Amendments to General Conditions... AM-1 to AM-2 Supplements to General Conditions... SU-1 to SU-7 00200 Instructions To Bidders... 1 3 00201 Contractor s Bidding

More information

Building Envelope Commissioning and Building Diagnostic Test: Case Studies Course Number: CXENERGY1506

Building Envelope Commissioning and Building Diagnostic Test: Case Studies Course Number: CXENERGY1506 AABC Commissioning Group AIA Provider Number: 50111116 Building Envelope Commissioning and Building Diagnostic Test: Case Studies Course Number: CXENERGY1506 Dan Adam, RA, CxA, Facility Commissioning Group

More information

Using a Building s HVAC Systems and Infrared Technology to Solve Water Intrusion Problems

Using a Building s HVAC Systems and Infrared Technology to Solve Water Intrusion Problems Using a Building s HVAC Systems and Infrared Technology to Solve Water Intrusion Problems James Brady Level III Certified Infrared Thermographer Brady Infrared Inspections, Inc. 935 Pine Castle Court Stuart,

More information

C. Jointing of Exterior Vertical Surfaces. Section D. The Secretary of the US Department of the Interior s Standards for Rehabilitation.

C. Jointing of Exterior Vertical Surfaces. Section D. The Secretary of the US Department of the Interior s Standards for Rehabilitation. PART 1: GENERAL 1.01 Scope Of Standard A. This standard provides general guidance concerning the specific preferences of the University of Texas at Austin for roofing systems. B. UT recognizes that project

More information

STRUCTURAL CONDITION ASSESSMENT

STRUCTURAL CONDITION ASSESSMENT STRUCTURAL CONDITION ASSESSMENT ALLEN JAY ROCK GYM 1201 FAIRFIELD ROAD HIGH POINT, NC Prepared for: Prepared by: Guilford County Schools 617 West Market Street Greensboro, NC Adrian S. Durham, PE, SE,

More information

Curtainwalls. Brussels Window. Objectives. Windows & Curtainwalls. Curtainwalls. 1 R2 R3. High tech? Low tech?

Curtainwalls. Brussels Window. Objectives. Windows & Curtainwalls. Curtainwalls.  1 R2 R3. High tech? Low tech? Curtainwalls Windows have long been important to buildings Brussels Window Objectives Windows & Curtainwalls This talk aims to Develop awareness of curtainwall performance appreciate impact of performance

More information

Field Determination of Water Penetration of Windows using Blowerdoor and Infrared Camera

Field Determination of Water Penetration of Windows using Blowerdoor and Infrared Camera Field Determination of Water Penetration of Windows using Blowerdoor and Infrared Camera Walter Sebastian BMT Building Enviroment Consultants Ltd., Doktor Neergaards Vej 15, DK-2970 Hoersholm, Denmark

More information

Accounting for Thermal Bridging at Interface Details. A Methodology for De-Rating Prescriptive Opaque Envelope Requirements in Energy Codes

Accounting for Thermal Bridging at Interface Details. A Methodology for De-Rating Prescriptive Opaque Envelope Requirements in Energy Codes Accounting for Thermal Bridging at Interface Details A Methodology for De-Rating Prescriptive Opaque Envelope Requirements in Energy Codes April 29, 2015 Report Prepared by: 1. INTRODUCTION 1 2. METHODOLOGY

More information

ASTM E 1886 and ASTM E 1996 TEST REPORT. Report No.: A Rendered to: CORAL ARCHITECTURAL PRODUCTS Tuscaloosa, Alabama

ASTM E 1886 and ASTM E 1996 TEST REPORT. Report No.: A Rendered to: CORAL ARCHITECTURAL PRODUCTS Tuscaloosa, Alabama Architectural Testing ASTM E 1886 and ASTM E 1996 TEST REPORT Report No.: A2653.02 401 44 Rendered to: CORAL ARCHITECTURAL PRODUCTS Tuscaloosa, Alabama PRODUCT TYPE: Curtain Wall SERIES/MODEL: PW257 Captured

More information

Field Planning and Data Collection Practices for Conducting Detailed Natural Hazard Vulnerability Assessments of Campus Structures

Field Planning and Data Collection Practices for Conducting Detailed Natural Hazard Vulnerability Assessments of Campus Structures University of New Orleans ScholarWorks@UNO DRU Workshop 2013 Presentations Disaster Resistant University Workshop: Linking Mitigation and Resilience Conferences and Workshops 3-1-2013 Field Planning and

More information