Item 2.3 Unit pricing GC to provide a square foot unit cost for material and labor to replace plywood decking beneath new concrete walkway slab.
|
|
- Roger Hunt
- 5 years ago
- Views:
Transcription
1 Willow Glen Housing Repairs Project #9-59 Addendum Item. Change to bid date The bid date will be extended to March 8, 09, :00pm at the Housing Authority of Columbus Central Office,000 Wynnton Road Columbus, Georgia 3906 Item. Clarifications and additional information from the Pre-bid conference. GC s will not be allowed to use power from the individual apartment units, but they can use the House Electrical Panel GC s will be required to provide their own portable toilet facility. Construction personnel will not be allowed to use the owner s restroom facilities. The housing authority s typical restriction of work hours on renovations will NOT be applied to this project. Construction may work extended workdays and on weekends in coordination with the owner for site access and control. The lower panels of cement fiber board siding at the second-floor units will require removal to extend waterproofing membrane vertical leg and tie into walls existing air and moisture barrier to provide a weather tight enclosure. GC s to include price for repairing cement fiber board installation after demolition and painting the entire front façade of each building to match current paint scheme. As previously stated in the project narrative, each building will have a two-week period where residents will be temporarily housed off site. It is the owner s desire to have the existing structural elements removed, new structural system and stairs installed as well as the second-floor concrete balcony poured and cured for traffic with in that two week window for each unit. Guardrail and handrails must be installed at that time as well prior to residents returning to units. The additional scope of work including repair of siding, painting, cement fiberboard installation over wood structure elements, and rebuilding of deck privacy screens may occur after this two-week window. GCs are to provide an add alternate to paint each entire apartment building based on the current color scheme. See existing construction elevation sheet for take off information. Construction Document A3. from original building construction provided. Note, owner took a deductive alternate at the time of construction, Unit 5 shown on the original document site key is only 3 units wide. Pictures of existing paint scheme for reference attached. Regarding the wood structural option, where the wood beams penetrates the existing wall, GC will remove a sufficient portion of siding to flash the opening and provide water tight transition of the wall air and moisture barrier system (building wrap currently installed on wall) to the air and moisture barrier of the engineered wood beam. Repair siding and paint to match adjacent. Item.3 Unit pricing GC to provide a square foot unit cost for material and labor to replace plywood decking beneath new concrete walkway slab. Item.4 Add alternate - high performance paint at steel structural option Ninth Street Suite 0 Columbus, GA 390 p f WR of Georgia, Inc.
2 Provide add alternate for high performance paint at the steel option. Basis of Design: Tnemec, or approved equals from Sherwin Williams or PPG o Shop Prime: Series mils DFT ( section 500 and 5500) o Field Spot Prime: Series 394 mils DF (section 9600) you can put it in 9900 o Field Intermediate: Series mils DFT o Field Finish: Series mils DFT Item.5 Clarification to detail at wall penetration of wood beam structural system option. See AD-.4 Drawing Item.6 Revised Sheet A.. See A. Drawing Sheet revised. o Provides clarification on cladding of existing roof beam to remain. o Provides clarification on steel railing bracing at columns. End of Addendum
3
4
5 EXISTING WALL EXISTING WALL WRAP AIR AND MOISTURE BARRIER. OVERLAP SELF ADHERING FLASHING SELF ADHERING AIR AND MOISTURE BARRIER FLASHING TAPERED BLOCKING TO PROVIDE OF CEMENT FIBER BOARD ACROSS TOP OF BEAM -MAINTAIN MIN OF 8" GAP BETWEEN INSIDE SURFACE OF CEMENT FIBER BOARD AND AIR AND MOISTURE BARRIER AIR AND MOISTURE BARRIER ENCASING BEAM SEALANT AT PERIMETER FILL VOID AROUND PENETRATION W/ MINIMALLY EXPANDING CLOSED CELL SPRAY FOAM INSULATION WOOD BEAM WALL PENETRATION
6 EXISTING ROOF ASSEMBLY EXISTING ROOF ASSEMBLY COMPOSITE DRAINAGE CONCRETE SLAB, CONT. SEALANT ARCHITECTURE INTERIORS REMOVE AND DISPOSE OF EXISTING CEMENT FIBER BOARD. PROVIDE AIR AND MOISTURE BARRIER, FURRING STRIPS, AND NEW CEMENT FIBER BOARD. SEE DETAILS 3/A. FOR BEAM ENCLOSURE EXISTING FIBER CEMENT SOFFIT NEW PT 6 X 6 WOOD COLUMN REMOVE AND DISPOSE OF EXISTING CEMENT FIBER BOARD. PROVIDE AIR AND MOISTURE BARRIER, FURRING STRIPS, AND NEW CEMENT FIBER BOARD. SEE DETAILS 3/A. FOR BEAM ENCLOSURE EXISTING FIBER CEMENT SOFFIT NEW STEEL COLUMN, NEW STEEL GUARDRAIL SYSTEM NEW WOOD COLUMN NEW CONCRETE SLAB W/ WWF COMPOSITE DRAINAGE WATERPROOFING NEW ADHESIVE PRIMER REPLACE EXISTING DAMAGED PLYWOOD DECK AS NEEDED ALUMINUM T-RAIL FOR CONCRETE BALCONY BITUMINOUS PAINT ON ALL SURFACES IN CONTACT W/ CONCRETE METAL DRIP EDGE VENT STRIP FIBER CEMENT PANEL 3/8" FURRING STRIPS FLASHING TAPE SELF-ADHERING AIR AND MOISTURE BARRIER NEW WOOD BEAM, NINTH STREET SUITE 0 COLUMBUS, GA 390 P F STATE REGIST ERE OF GEORG I LEE MARTIN RA054 D ARCHITECT A NEW CONCRETE SLAB, NEW STEEL GUARDRAIL, PROVIDE STEEL BRACKET AT TOP AND BOTTOM RAIL, USE " LAG SCREW (PRESSURE TREATED WOOD RATED) AT WOOD COLUMN LOCATIONS NEW CONCRETE SLAB, NEW STEEL GUARDRAIL, PROVIDE STEEL BRACKET AT TOP AND BOTTOM RAIL, FULLY WELD TO COLUMN AND RAIL NEW WATERPROOFING ADHESIVE PRIMER EXISTING PLYWOOD DECK NEW RAILING POST WILLOW GLEN HOUSING REPAIRS 3 A. 0'- /" REF. ND FLR SLABS 4 A. 0'- /" REF. ND FLR SLABS NEW PT PARALLAM BEAM EXISTING WOOD JOISTS NEW STEEL BEAM, EXISTING WOOD JOISTS STABILIZE EXISTING FLOOR JOISTS NEW VENTED FIBER CEMENT SOFFIT PANELS SELF-ADHERING AIR AND MOISTURE BARRIER AIR AND MOISTURE BARRIER FIBER CEMENT TRIM FIBER CEMENT PANEL 3/8" FURRING STRIPS FIBER CEMENT VERTICAL PANEL NEW WOOD BEAM FLASHING TAPE NEW WOOD COLUMN NEW STEEL COLUMN, VENT STRIP EXISTING CONCRETE SLAB 0'-0" REF TOP OF FIN. FLR. EXISTING CONCRETE SLAB 0'-0" REF TOP OF FIN. FLR. VENTED FIBER CEMENT SOFFIT PANEL 3/8" FURRING STRIPS AIR AND MOISTURE BARRIER PRINTED: 0:56AM A. WALL SECTION - WOOD REPLACEMENT - OPTION /" = '-0" A. WALL SECTION - STEEL REPLACEMENT - OPTION /" = '-0" 3 A. ENLARGED SLAB DETAIL - WOOD STRUCTURE NEW STEEL GUARDRAIL SYSTEM /" = '-0" COMPOSITE DRAINAGE WATERPROOFING NEW ADHESIVE PRIMER REPLACE EXISTING DAMAGED PLYWOOD DECK AS NEEDED CONCRETE SLAB, CONT. SEALANT ALUMINUM T-RAIL FOR CONCRETE BALCONY BITUMINOUS PAINT ON ALL SURFACES IN CONTACT W/ CONCRETE SELF ADHERING FLASHING Project Number: 9-59 Date: 3 FEBRUARY 09 Drawn by: Revisions: 9 FEBRUARY 09 5 MARCH 09 NEW STEEL COLUMN METAL DRIP EDGE FILE NAME: J:\Job 9-0\9-59 Willow Glenn Emergency Repairs\Drawings\CAD\A. -ADDENDUM.dwg NEW CONCRETE SLAB W/ WWF COMPOSITE DRAINAGE NEW WATERPROOFING ADHESIVE PRIMER EXISTING PLYWOOD DECK NEW () WOOD LEDGER TO MATCH JOISTS STABILIZE EXISTING FLOOR JOISTS NEW VENTED FIBER CEMENT SOFFIT PANELS FIBER CEMENT TRIM 4 A. ENLARGED SLAB DETAIL - STEEL STRUCTURE /" = '-0" NEW RAILING POST NEW STEEL BEAM, Sheet Description WALL SECTIONS AND DETAILS Sheet Number A.
OAK TREE LIQUOR STORE
DRAWING LIST ARCHITECTURAL A000 - COVER SHEET D0 - DEMOLITION PLANS & ELEVATIONS A0 - PLANS, ELEVATIONS & DETAILS A40 - BUILDING S A40 - BUILDING S ARCHITECT: Engineering (00) Inc. 6 Great George Street,
More informationADDENDUM # 2. - Page 1 of 2
2013-03-20 REQUEST FOR TENDER AFRICA RESTAURANT ROOF REPLACEMENT RFT # 11 (2013-03) ADDENDUM # 2 - Page 1 of 2 This addendum shall be incorporated into, and form part of RFT # 11 (2013-03) and take precedence
More informationExterior Elevated Elements Inspection Guidelines
Exterior Elevated Elements Inspection Guidelines Planning and Development 1. Guideline Purpose These guidelines are intended to assist practicing professionals in complying with Berkeley Municipal Code
More informationResidential Building Inspections
Residential Building Inspections Foundations, Grade Beams, Pile Caps, Foundation Pads 1. All trenches or excavations and formwork shall be in accordance with the size(s) and configuration(s) as per approved
More informationUNIVERSAL BRACKET. Shown in red color for illustration purposes. Bracket can be painted to match panels.
US PATENT PENDING #62/536,219 Shown in red color for illustration purposes. Bracket can be painted to match panels. (15) 79-6500 1515 VALLEJO ST, SAN FRANCISCO, CA 9109 17 3 17 SIMPLE, EFFICIENT, FLEXIBLE
More informationWeatherSmart Air Barrier Installation Guide
WeatherSmart Air Barrier Installation Guide 1 The intent of this document is to provide a guide for the installation of WeatherSmart as both a Weather Resistive Barrier (W.R.B.) and an Air Barrier Material
More informationTABLE OF CONTENTS DIVISION 1 GENERAL REQUIREMENTS
AIA General Conditions... GC-1 to GC-44 Amendments to General Conditions... AM-1 to AM-2 Supplements to General Conditions... SU-1 to SU-7 00200 Instructions To Bidders... 1 3 00201 Contractor s Bidding
More informationSECTION THERMOPLASTIC POLYOLEFIN (TPO) ROOFING PART 1 - GENERAL 1.1 RELATED DOCUMENTS
SECTION 075423 - THERMOPLASTIC POLYOLEFIN (TPO) ROOFING PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including Division 00 Bidding Requirements and other Division
More informationROOFING CONTRACTORS GENERAL TRADE KNOWLEDGE EXAMINATION CONTENT INFORMATION
ROOFING CONTRACTORS GENERAL TRADE KNOWLEDGE EXAMINATION CONTENT INFORMATION Revised September 14 The General Trade Knowledge portion of the examination is administered daily in Computer Based Testing (CBT)
More informationGAF EnergyGuard Polyiso Wall Sheathing
From: Technical Services May 15, 2013 GAF EnergyGuard Polyiso Wall Sheathing GAF s EnergyGuard Polyiso Wall Sheathing is intended to be installed on residential construction only. Application types include:
More informationSECTION 07530CP EPDM MEMBRANE ROOFING
PART 1 GENERAL 1.1 SUMMARY SECTION 07530CP EPDM MEMBRANE ROOFING A. Section includes: 1. Adhered membrane roofing and flashing 2. Mechanically fastened roof insulation 3. Walkway pads 1.2 ARCHITECTURAL
More informationAqua Coast Engineering
Aqua Coast Engineering Ltd. P.O. Box 1367 Station A Delta, B.C. V4M 3Y8 Tel: (604)948-0958 Fax: 604)948-0959 September 1, 2011 Matthew Cheng File#:11145 Matthew Cheng Architect Inc. Fax: 604-731-3908 Unit
More information12 - V0 CFP-12 PANEL INDEX. Delta Series CONCEALED FASTENED PANELS BUILDING PRODUCTS VERTICAL PANELS
CONCEALED FASTENED PANELS CFP-12 PANEL INDEX 12 - V0 BASE DETAILS HORIZONTAL JOINT DETAIL PARAPET ROOF DETAIL INSIDE CORNER DETAIL OUTSIDE CORNER DETAIL SOFFIT DETAIL WINDOW JAMB DETAIL WINDOW HEAD DETAIL
More informationINSTALLING WATER-RESISTIVE BARRIERS & FLASHING
INSTALLING WATER-RESISTIVE BARRIERS & FLASHING IN A TWO-LAYER STUCCO APPLICATION Fortifiber Building Systems Group provides this guide to assist installers by demonstrating a two-layer installation of
More informationB.01. Lincoln Property Company 100 Lowell Road North Reading, MA 01864
7 Specific Notes - Type B Repairs Detail Step. SHADED AREAS INDICATE MATERIALS TO BE REMOVED.. REMOVE EXISTING PVC RAILINGS AND STORE FOR RE-INSTALLATION UPON COMPLETION OF THE WORK 6" Min.. REMOVE X VERTICAL
More informationInsulation. First Revison October DC14 Drainage Mat INSTALLATION GUIDE FOR RESIDENTIAL & COMMERCIAL APPLICATIONS
Insulation First Revison October 2016 DC14 Drainage Mat INSTALLATION GUIDE FOR RESIDENTIAL & COMMERCIAL APPLICATIONS 1. General Information This Guide describes the use of Kingspan GreenGuard DC14 Drainage
More informationThe better way to build TM. Installation Manual NAILBASE PANELS
The better way to build TM Installation Manual PANELS November 2018 SIPs Installation Manual Table of Contents Topics General Requirements................................... 3 Materials..............................................
More informationJ.DAVID POUNDER LIMITED CONSULTING ENGINEER AND ARCHITECT
J.DAVID POUNDER LIMITED CONSULTING ENGINEER AND ARCHITECT Using a Multidisciplinary Approach to Projects for Over 0 Years Project 5 Mapleview Terrace Apartments, 59 South Pelham Road, Welland Addendum
More informationFirstEnergy Program Overview
FirstEnergy Program Overview Builder incentives $400 per unit + $0.10/kWh in projected savings Eligibility Located in service area of a FirstEnergy Utility Certificate of Occupancy Dates: FirstEnergy Ohio
More informationBuilding Enclosure Detailing for Balconies
Building Enclosure Detailing for Balconies COLIN SHANE M.ENG., P.ENG., P.E. ASSOCIATE, SENIOR PROJECT MANAGER RDH BUILDING SCIENCE INC. AUGUST 2016 Disclaimer: This presentation was developed by a third
More informationSUBJECT: NEW 2000 INTERNATIONAL RESIDENTIAL CODE (IRC) DATE:
IRC CODE UPDATES TO: RESIDENTIAL BUILDING CONTRACTORS FROM: GARY STABER, BUILDING OFFICIAL SUBJECT: NEW 2000 INTERNATIONAL RESIDENTIAL CODE (IRC) DATE: 6/1/2003 INTERNATIONAL RESIDENTIAL CODE (IRC) APPLICABILITY:
More informationHIGHLANDVIEW CEMETERY CHAPEL
HIGHLANDVIEW CEMETERY CHAPEL CONTACT: Ferris State University Small Town Studio Christopher Cosper, AIA, LEED, AP, Assistant Professor cosperc@ferris.edu 23.59.33 Sheet List Sheet Name Sheet # COVER A00
More informationBuilding Enclosure Detailing for Balconies
Building Enclosure Detailing for Balconies COLIN SHANE M.ENG., P.ENG., P.E. PRINCIPAL, SENIOR PROJECT MANAGER RDH BUILDING SCIENCE INC. JUNE 2017 Disclaimer: This presentation was developed by a third
More informationDECK CONSTRUCTION REQUIREMENTS
DECK CONSTRUCTION REQUIREMENTS Should you have any questions after reading the following information, please call the Building Inspection Department at 651-439-4439 to discuss the topics of concern. We
More informationPROJECT INFORMATION PROJECT NUMBER 1706 SINGLE DETACHED DWELLING - RENO 4208 VARMOOR ROAD NW CALGARY ALBERTA
BERZE RESIDENCE 4208 VARMOOR ROAD, NW CALGARY ALBERTA CLIENT PROJECT INFORMATION NAME BELA & BOGLARKA BERZE PROJECT NAME BERZE RESIDENCE PERMANENT ADDRESS TEMPORARY ADDRESS PHONE NUMBER EMAIL 4208 VARMOOR
More informationROME ART AND COMMUNITY CENTER
ROME ART AND COMMUNITY CENTER 308 W. Bloomfield St. Rome, NY 13440 INSULATION AND SLATE ROOFING REPAIRS SCOPE OF WORK: A. SPRAY FOAM INSULATE ATTIC AREA B. FRONT ROOF REPAIR C. REAR ROOF REPAIRS D. INTERIOR
More informationPella 250 Series. Wood Frame Construction with Vinyl Siding... V250-ID-888 Wood Frame Construction with Brick Veneer...
SECTION DIRECTORY General Information Introduction... V250-ID-886 Installation Accessories and Applications... V250-ID-886 Typical Sealant Placement Details... V250-ID-887 Fin Installation Details Wood
More informationEXW3 EXISTING DOWEL NEW FOOTING TO EXISTING WALL WITH 3-15M DOWELS, DOWEL THE NEW
-4 /4" 8" 4'-9 /" 6'-4" '-8" DEPRESS TO ACCOMODATE DOOR ABOVE DOWEL NEW FOOTING TO WITH 3-5M DOWELS, DOWEL THE NEW S TO THE S WITH 5M @ 4" O.C. VERTICALLY, PROVIDE -5M BARS 6" LONG IN THE FOOTING 4'-9"
More informationTOWN OF HAGUE GUIDELINES FOR PERMIT APPLICATION
TOWN OF HAGUE GUIDELINES FOR PERMIT APPLICATION Town of Hague Building Inspector: Dale Wagner Home #: 306-225-2265 Cell #: 306-241-4741 Fill all part of the permit application including the date and signature.
More informationColphene BSW Training and Application Guide. Colphene BSW Waterproofing Membrane. 1. Prepare substrate
Colphene BSW Training and Application Guide Colphene BSW Waterproofing Membrane. 1. Prepare substrate Substrate must be structurally sound. Surface must be free of voids, spalled areas, loose aggregate,
More informationWICOMICO COUNTY BOARD OF EDUCATION
GLEN AVENUE ELEMENTARY SCHOOL RO REPLACEMENT PROJECT NUMBER: PSC #.00.9 SR CURRENT CODES: 05 INTERNATIONAL BUILDING CODE 05 INTERNATIONAL MECHANICAL CODE NATIONAL STANDARD PLUMBING CODE (MBPS) 05 EDITION
More informationCommercial Flashing Details
This technical note illustrates many of the most common flashing details for commercial buildings. The purpose for flashing is to direct moisture to the exterior and in so doing, prevent moisture from
More informationThe Compass ( 270 Lisgar Street, Brighton ) Features General Site Work 1. Construction Drawings 2. Building, Plumbing Electrical and Entrance Permits
The Compass ( 270 Lisgar Street, Brighton ) Features General Site Work 1. Construction Drawings 2. Building, Plumbing Electrical and Entrance Permits 3. Development and Septic Fees 4. Tarion New Home Warranty
More informationTHE CITY OF WALTHAM MASSACHUSETTS PURCHASING DEPARTMENT PHASE III RENOVATIONS TO THE FORMER BANKS SCHOOL ELDERLY HOUSING CONDOMINIUMS AND CONDOMINIUMS
THE CITY OF WALTHAM MASSACHUSETTS PURCHASING DEPARTMENT PHASE II RENOVATIONS TO THE FORMER BANKS SCHOOL ELDERLY HOUSING CONDOMINIUMS AND PHASE III RENOVATIONS TO THE FORMER BANKS SCHOOL ELDERLY HOUSING
More informationWELCOME HOME VETERANS SHELTER 2112 BUSINESS LOOP 70 EAST COLUMBIA, MISSOURI PWA #201430
2120 Forum Boulevard, Suite 101 Columbia, Missouri 65203 573.449.2683 Fax: 573.442.6213 www.pwarchitects.com ADDENDUM #1 DATE: June 21, 2016 TO BIDDING DOCUMENTS ENTITLED: WELCOME HOME VETERANS SHELTER
More informationFACE CFP - HORIZONTAL PANELS - OPTION 'B'
- Vertical Transitions 12F - H10.3 VHB TAPE 5.000" 127.0mm 5" FORMED TRANSITION STRIP w/ FLAT FACE CFP - - OPTION 'B' H10.3 CONCEALED FASTENED Panel Index 12F - H0 BASE DETAILS JOINT DETAIL PARAPET ROOF
More informationPORCH PLAN. Existing House. New Porch. Page A.1. Boxed Beams. 5/4x6 Cedar Decking. Roof Overhang. Wood Columns. Hip Roof. Step
Porch Plan 28 68 2'-0" 7'-8" 2'-0" 7'-0" PORCH PLAN SCALE: /4" = '-0" CD24 0 SECT D A.6 7 /4" 7 /4" Boxed Beams Existing House 23'-2 /4" 30 68 New Porch Step Wood Columns 8'-0" 2'-0 /2" 2'-0 /2" 8'-0"
More informationDistances are not shown to scale. Existing porch. Community. Building. Distances are not shown to scale
patio and deck 00 Building Two story Four-plex Entrance 0 0 00 Building Single Story Duplex 0 patio Contact Information: Owner: Housing Authority of Yamhill County, NE Dunn Place, McMinnville, OR 9. Contact:
More informationThe Ashland Project. Total Area: 1,778 Sq.Ft. 3 Bedroom, 2 Bath, 2 Car Garage
The Ashland Project Total Area: 1,778 Sq.Ft. 3 Bedroom, 2 Bath, 2 Car Garage The garage and bedroom extend from the front of this three bedroom home, drawing you visually into the entryway. Brick and stucco
More informationInsulation manufacturer to submit dew point analysis free of charge for typical wall section. Analysis by:
PACE REPRESENTATIVES INC. 50 Redfield Street Boston MA 02122 www.pacerepresentatives.com 617-342-7072 PRE JOB AIR BARRIER/EXTERIOR WALL INSULATION MEETING CHECK LIST 1.01 Date: Insulation manufacturer
More informationCowhorn Residence. PHnw 2017 Cowhorn Residence
Cowhorn Residence LEARNINGOBJECTIVES Course Approved for CPHC Continuing Education Credits 1. Learn how to orient buildings based on site conditions and owner criteria 2. Understand the impact of site
More informationFixed Skylight / Fixed Multiple Skylight Milgard Aluminum Window
Skylight Fixed Skylight / Fixed Multiple Skylight Milgard Aluminum Window The Series Skylight has been specifically designed to provide maximum thermal efficiency by incorporating a special polyurethane
More informationADDENDUM NO Refer to Specifications Section Alternates. Clarifications to alternate descriptions are as follows:
ADDENDUM NO. 1 TO THE DRAWINGS AND SPECIFICATIONS FOR THE New Dishman-McGinnis Elementary School Bowling Green Independent Schools Bowling Green, Kentucky BG 12-256 RTA 1209 March 11, 2013 To All Plan
More informationRESIDENTIAL INSULATED SHEATHING COMFORTBOARD. Installation Guide
RESIDENTIAL INSULATED SHEATHING TM COMFORTBOARD 80 Installation Guide Table of Contents Introduction How to Use this Guide...1 Split-Insulation Wall Assembly...2 Insulation... 3 Nominal and Effective R-Values
More informationMulti-Institutional Academic Health Science & Research Center Evansville, IN
SECTION 061600 - SHEATHING PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 01 Specification Sections,
More informationRESIDENTIAL INSULATED SHEATHING INSTALLATION GUIDE. Residential Insulated Sheathing Installation Guide ROXUL COMFORTBOARD 80
RESIDENTIAL INSULATED SHEATHING INSTALLATION GUIDE Residential Insulated Sheathing Installation Guide ROXUL COMFORTBOARD 80 Contents Introduction How to Use this Guide...1 Split-Insulation Wall Assembly...2
More informationCarpenter Level 2 Rev. September 2017
Level 2 A5 Site Layout II Duration: 14 hours 7 hours 7 hours Upon completion of this unit the apprentice will demonstrate knowledge of site layout tools and equipment and their applications and procedures
More informationMeriter Heights Renovations Madison, Wisconsin
Urban Design Submittal s 12 ebruary 2007 Owner Developer W. Mifflin St. STATE CAPITOL SQUARE Meriter Retirement Services, LLC 333 West Main Street 53703 W. Washington Ave. S. airchild St. STATE CAPITOL
More informationSECTION THERMAL INSULATION
Pactiv Building Products 2100 RiverEdge Parkway Suite 175 Atlanta, GA 30328 Toll Free: (800) 241-4402 Web Site: www.green-guard.com SECTION 07210 THERMAL INSULATION PART 1 - GENERAL 1.1 RELATED DOCUMENTS
More informationHenri Fennell, CSI/CDT ABX 2015
Henri Fennell, CSI/CDT ABX 2015 Henri is an architect and building envelope specialist with over forty years of experience in the construction industry. He was a pioneer in the solar industry, introduced
More informationMR2 SERVICES Site Reconstruction 54 College Street Des Moines, IA
Existing Yard Security Light Proposed Rooftop Mechanical Screening (Slate Gray) Proposed 3 x4 x 4 x4 Windows Metal Awning Existing Doors Metal Siding(Slate Gray) Trim (Matte Black) 14 14 Proposed Addition
More informationSERIES STB30 STEEL FIXED THERMAL BREAK DETENTION WINDOWS SECTION 08651
SERIES STB30 STEEL FIXED THERMAL BREAK DETENTION WINDOWS SECTION 08651 PART 1 GENERAL 1.1 DESCRIPTION A. Work Included: 1. Furnish all labor and materials to complete the fabrication of detention windows
More informationBuilding Enclosure Details and Assemblies for Wood-Frame Buildings
Building Enclosure Details and Assemblies for Wood-Frame Buildings COLIN SHANE M.ENG., P.ENG. ASSOCIATE, SENIOR PROJECT MANAGER RDH BUILDING SCIENCES INC. NOVEMBER 19, 2015 Disclaimer: This presentation
More informationTABLE OF CONTENTS Updated 1/2014 SECTION TITLE DATE
TABLE OF CONTENTS SECTION TITLE DATE Division 00 Procurement and Contracting Requirements 000101... Project Title Page 000116... CAD Standards 001116... Invitation to Bid 002113... Instructions to Bidders
More informationELEVATION FOR DETAIL REFERENCE ONLY
6 7 8 10 26 19 20 14 15 22 SOFFIT OUTSIDE CORNER INSIDE CORNER 23 25 24 25 5 27 28 29 16 11 OPENING 17 18 END WALL 21 12 13 9 6 7 8 ELEVATION FOR DETAIL REFERENCE ONLY CSH-01 CSH-02 CSH-03 CSH-04 CSH-05
More informationGensler 2014/06/16 Hertz Global Headquarters ISSUE FOR BUILDING PERMIT Estero, Florida SECTION
SECTION 072700 VAPOR PERMEABLE AIR BARRIER LIQUID MEMBRANE PART 1 GENERAL 1.1 GENERAL REQUIREMENTS A. The Work of this Section, as shown or specified, shall be in accordance with the requirements of the
More informationMCCARTY ARCHITECTS, P.A. POST OFFICE BOX 440 / 533 WEST MAIN STREET TUPELO, MS / FOR ANSWERS TO QUESTIONS CONTACT: JUSTIN HARRINGTON
ADDENDUM NUMBER FROM: MCCARTY ARCHITECTS, P.A. POST OFFICE BOX 0 / 533 WEST MAIN STREET TUPELO, MS 3880 / 3880 FOR ANSWERS TO QUESTIONS CONTACT: JUSTIN HARRINGTON PHONE: -8-00 PROJECT: ACADEMIC STUDENT
More informationUniversity of Colorado Colorado Springs. National Cybersecurity Center Roof Replacement Package CSNA Project Number
ADDENDUM NUMBER 0 TO PROJECT MANUAL AND DRAWINGS August 9, 6 OWNER: ARCHITECT: University of Colorado Colorado Springs CSNA Architects PROJECT: National Cybersecurity Center Roof Replacement Package CSNA
More informationT T LEGAL DESCRIPTION: LEGEND X FOUND MONUMENT AS NOTED A.M. ~ AS MEASURED IN FIELD REC. ~ DEED OR PLAT DISTANCE PL ~ PROPERTY LINE FF ~ FINISHE
T T LEGAL DESCRIPTION: LEGEND X 99.44 FOUND MONUMENT AS NOTED A.M. ~ AS MEASURED IN FIELD REC. ~ DEED OR PLAT DISTANCE PL ~ PROPERTY LINE FF ~ FINISHED FLOOR CALLED NORTH N EXIST. SPOT ELEVATION N00 04'58"W
More informationINFORMATIONAL HANDOUT FOR FINISHING A BASEMENT
7100 147 th Street West Telephone (952) 953-2588 Apple Valley, MN 55124-9016 Fax (952) 953-2515 www.cityofapplevalley.org INFORMATIONAL HANDOUT FOR FINISHING A BASEMENT 1. Submit plan showing the proposed
More information2001 COMPANY. WIND BLOWN DEBRIS RESISTANT ROOF ASSEMBLIES Hurricane 140 Mph And Tornado 250 Mph Wind Blown Debris
WIND BLOWN DEBRIS RESISTANT ROOF ASSEMBLIES Hurricane 140 Mph And Tornado 250 Mph Wind Blown Debris The Texas Tech Wind Blown Debris Test requires three impacts by the butt end of a 2 x 4 shot out of an
More informationSubtotal - Category 2 $ 1, $ 1, Landscaping and Fence - By Field Outdoor Spaces (
Screen Porch to 4 Seasons Room Address: City, State, Zip: Phone: Email: BUDGET ANALYSIS Project Description: Date: 7/24/2017 Project Description: Convert existing screen porch into 4season space with seating
More informationQuestions and Answers Construction of New Amenities At Folly Beach County Park
Questions and Answers Construction of New Amenities At Folly Beach County Park 2019-003 1. A410, Keynotes 11.34 Responsibility Chart -stainless steel table does not indicate if it is provided by the owner
More informationSECTION STAY-IN-PLACE INSULATED CONCRETE FORMING SYSTEM
ARCHITECTURAL SPECIFICATIONS MANUFACTURER: InterBlock LLC PO Box 1123, Sheboygan, WI 53082 Phone Number 920-207-7234 SECTION 03100 STAY-IN-PLACE INSULATED CONCRETE FORMING SYSTEM PART 1 GENERAL 1.01 Summary
More informationOCS ONE COAT STUCCO A custom blend of Portland cement, sand, extenders, fiber reinforcement and modifiers.
OCS ONE COAT STUCCO A custom blend of Portland cement, sand, extenders, fiber reinforcement and modifiers. Designed to save material by functioning as an exterior cladding in thicknesses ranging from 3/8
More informationREBECCA LG BOSTICK, ARCHITECTS, INC
REBECCA LG BOSTICK, ARCHITECTS, INC 703-768-2250 ADDENDUM NO. 3 Page 1 of 4 (plus attachments -2 pages) SILVERBROOK ELEMENTARY SCHOOL RENOVATION Fairfax County Public Schools 9350 Crosspointe Drive, Fairfax
More informationBuilding Construction and Water Intrusion
Building Construction and Water Intrusion RAY CHOY-MARSHALL GOVAN ASSOCIATES an architectural corporation ray_choy-marshall@sbcglobal.net 2930 camino diablo, suite 210, walnut creek, ca 94597 2004 Design
More informationPG&E BUILDING AT 215 MARKET STREET
San Francisco, CA ICRI Northern California Chapter 2017 Concrete Repair Awards Simpson Gumpertz & Heger Inc. OVERVIEW The historic 215 Market Street Annex is a seven-story office building in downtown San
More informationChevy Chase Club June 30, 2008 Bowie Gridley Architects
SECTION 092900 - GYPSUM BOARD PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 01 Specification Sections,
More informationSECTION 1 - ETHYLENE-PROPYLENE-DIENE-MONOMER (EPDM) ROOFING
Project Name: Jefferson City Jaycees Fairgrounds Main Building Roof Replacement Project Site Address: 1445 Fairgrounds Road, Jefferson City, MO 65109 Project Contact: Randy Weaver Project Contact phone
More informationCOOK COUNTY ILLINOIS CONTRACT FOR WORK DOCUMENT NO Countywide Warehouse and Records Storage Center Hawthorne Project TKB No.
SECTION 092900 GYPSUM BOARD PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 01 Specification Sections,
More informationROOF DETAIL RD-16 CONSTRUCTION DOCUMENTS - PHASE / PENNSYLVANIA HOUSING FINANCE AGENCY/ MAY 22, 2017 MURRAY ASSOCIATES ARCHITECTS, P.C.
3 4" ARRISCRAFT VENEER " NOMINAL AIR SPACE 2" RIGID INSULATION 8" CMU REINFORCED CONCRETE SLAB OVER METAL DECK - REFER TO STRUCTURAL DWGS 20 FIRST FLOOR 343' - 5" CONTINUOUS SEALANT TERMINATION BAR STAINLESS
More informationKORA_Req._for_Eng._Studies_on_Stouffer_Apts. KU Reference No
000130 1 PURPOSE: Professional Engineering Consultants, P.A. (PEC) was engaged by University of Kansas Design & Construction Management to perform an assessment of Stouffer Place Apartment Building 20
More informationSECTION RESILIENT SHEET FLOORING
SECTION 09665 RESILIENT SHEET FLOORING PART 1 - GENERAL 1.1 DESCRIPTION A. This Section specifies the installation of sheet flooring with backing and integral cove base. 1.2 RELATED WORK A. Color and pattern:
More informationTABLE OF CONTENTS. 1.0 INTRODUCTION 1.1 Greenstone Structural Engineered Panels 1.2 Drawing and Element Numbers
version 2.5 updated as of 08.04.2017 2 TABLE OF CONTENTS 1.0 INTRODUCTION 1.1 Greenstone Structural Engineered Panels 1.2 Drawing and Element Numbers 2.0 ASSEMBLY 2.1 Sequence of Assembly 2.2 Preparation
More informationQUEEN ALEXANDRA COMMUNITY CENTRE
BRICK REPOINTING AND NEW BARRIER FREE RAMP 180 BARNARDO AVENUE PETERBOROUGH, ON. ARCHITECTURAL A1 A1 A2 SITE PLAN AND DEMOLITION NOTATION NEW CONSTRUCTION DETAIL PLANS AND SECTIONS NEW CONSTRUCTION SECTION
More informationADDENDUM NO. 1. Kapuskasing District High School Interior Upgrades. ADDENDUM NO. 1 November 9, 2018
Kapuskasing District High School Kapuskasing District High School JLR No.: 27729-032 Owner No.: 7587 Page 1 of 4 This Addendum forms part of the Contract Documents and amends the original drawings and
More informationTable of Contents. List of Drawings
SCOPE OF WORK Hastings Stadium Exhibition Park, 81 London Road, Guelph, Ontario Structural and Maintenance Remedial Work Prepared For City of Guelph City Hall, 1 Carden Street, Guelph, ON N1H 3A1 Prepared
More informationInstallation Guidelines VBC Products
Installation Guidelines VBC Products Composite STEP 1A: Ground Surface Preparation Earth Base Select the suitable product (VBC-350, 31 mil) and ensure the installation surface is relatively smooth. Barrier-Bac
More informationSPECIFICATIONS Section Cantilevered Walkway Cover
Part 1: General 1.1 Related Documents SPECIFICATIONS Section 107301 Cantilevered Walkway Cover A. The requirements of Division 1 specifications shall apply to work specified in the section. 1.2 Engineering
More informationDIVISION 7 - THERMAL AND MOISTURE PROTECTION
07100 WATERPROOFING 07150 DAMPPROOFING 07175 Water Repellent Coatings 07190 VAPOR AND AIR RETARDERS 07192 Vapor Retarders 07200 INSULATION 07240 Exterior Insulation and Finish Systems 07250 FIREPROOFING
More informationLIQUID RUBBER INDUSTRIES ENGINEERING SPECIFICATIONS FOR ENGINEERS AND ARCHITECTS. Diagram 1: Standard Membrane Continuation 150 mm Overlap
LIQUID RUBBER INDUSTRIES ENGINEERING SPECIFICATIONS FOR ENGINEERS AND ARCHITECTS Diagram 1: Standard Membrane Continuation 150 mm Overlap Ensure Membrane to Membrane Contact Diagram 2: Membrane Continuation
More informationPLATON RUGGED, DIMPLED HIGH-DENSITY POLYETHYLENE (HDPE) MEMBRANE THAT KEEPS FOUNDATIONS AND FLOORING DRY ADVANCED TECHNOLOGY EASY INSTALLATION
DRAINAGE SOLUTIONS SINCE 1908 PLATON RUGGED, DIMPLED HIGH-DENSITY POLYETHYLENE (HDPE) MEMBRANE THAT KEEPS FOUNDATIONS AND FLOORING DRY ADVANCED TECHNOLOGY EASY INSTALLATION PROVEN PERFORMANCE ARMTEC.COM
More informationSGN+A Planning Architecture Landscape Architecture
35 West Ponce de Leon Avenue Decur, Georgia 30030 Description: 0'-0" 3'-6" Building Type I, st Floor 7 July 0 A '-0" '-" 7'-" 8'-3 /" " 8'-3 /" 9'-0" 8'-3 /" " 8'-3 /" /" 6'-8 /" '-" D W 8'-5 /" 30'-"
More informationPLATON FOUNDATION WRAP
DRAINAGE SOLUTIONS SINCE 1908 PLATON FOUNDATION WRAP RUGGED, DIMPLED HIGH-DENSITY POLYETHYLENE (HDPE) MEMBRANE THAT KEEPS FOUNDATIONS DRY ADVANCED TECHNOLOGY EASY INSTALLATION PROVEN PERFORMANCE ARMTEC.COM
More informationA. Environmental Limitations: Comply with ASTM C 840 requirements or gypsum board manufacturer's written instructions, whichever are more stringent.
SECTION 092900 - GYPSUM BOARD PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 01 Specification Sections,
More informationADDENDUM NO. 2 Consisting of 3 pages and Attachments
10404-125 Street, Edmonton, AB. T5N 1T2 Tel: 780.455.5975 Fax: 780.454.2397 info@cdyarchitect.com ADDENDUM NO. 2 Consisting of 3 pages and Attachments PROJECT: Maina Centre Ville Phase II, Beaumont, Alberta
More informationOverall Existing Conditions Summary
September 12, 2002 Overall Executive Summary: The multi-use project on 250 West Street is a 7-story building with space for offices, retail, storage and parking. The project is a small part of the development
More informationSAN FRANCISCO UNIFIED SCHOOL DISTRICT 2006 PROPOSITION A BOND PROGRAM 300 SENECA NEW ACADEMIC CAMPUS ADDENDUM NO. 1
SAN FRANCISCO UNIFIED SCHOOL DISTRICT 2006 PROPOSITION A BOND PROGRAM 300 SENECA NEW ACADEMIC CAMPUS ADDENDUM NO. 1 PROJECT: 300 Seneca New Academic Campus DATE: September 23, 2013 300 Seneca Ave., S.F.,
More information4615 E. State Street Suite 206 Rockford Illinois /
ADDENDUM NO. 2 Date: April 29th 2015 4615 E. State Street Suite 206 Rockford Illinois 61108 815 / 397-3330 Project: Whiteside County Health Department New Facility and Interior Renovation Project Number:
More informationGENERAL FLOOR PLAN NOTES. REFER TO ADDITIONAL NOTES AND REQUIREMENTS ON ALL OTHER DOCUMENTS AND OTHER DISCIPLINES DOCUMENTS. A A.3 4' - 0" 5' - " B. ALL SITE INFO, FURNITURE, FIXTURES AND EQUIPMENT SHOWN
More informationTHE SPENCER RESIDENCE J&S ARCHITECT
THE SPENCER RESIDENCE J&S ARCHITECT 75 POURED CONCRETE FOUNDATION WALL (0MPa) 97.94 50Ø WEEPER TILE C/W SOCK W/MIN. 50 GRANULAR COVER F.D. E.P.B. F.D. 00 POURED CONCRETE FOUNDATION WALL (0MPa) 475 X 00
More informationSECTION SELF-ADHERING SHEET FLASHING
MANUFACTURER S GUIDE SPECIFICATIONS SECTION 076526 SELF-ADHERING SHEET FLASHING 900 Hensley Lane Wylie TX 75098 800-527-7092 www.carlisleccw.com 604129 03.24.15 Carlisle, Flexphalt, Sure-Seal and CAV-GRIP
More informationCONSTRUCTION SUMMARY REPORT
Edison Engineers Inc. 89 King Street W. Suite 3 Dundas (Hamilton) Ontario Canada L9H 1V1 Info@edisonengineers.ca CONSTRUCTION SUMMARY REPORT To: Halton Condominium Corporation No. 70 c/o Wilson Blanchard
More informationNATIONAL GYPSUM COMPANY 2-Hour Area Separation Wall System
0 00/NGC NATIONAL GYPSUM COMPANY -Hour Wall System The -Hour is a -hour fire wall consisting of in. (0. mm) light-gauge steel H-Studs that secure two layers of in. (. mm) shaftliner panels friction-fit
More informationWCU ALUMNI TOWER MASONRY & ENVELOPE REPAIRS
SCO #: 8-8-0 TABLE OF CONTE COV DESCRIPTION COVER SHEET ALUMNI TOWER ELEVATIONS & PLAN VIEWS REPAIR DETAILS - M TO REPAIR DETAILS - TO M0 & C TO REPAIR DETAILS - A & F TO F VICINITY MAP ALUMNI TOWER ALUMNI
More informationRE: Pacific Shores VIS Block Second Floor Walkway Structural Review
April 20, 2017 The Kerr Group Management Corp. Terry Kerr, Owner / Manager terry@thekerrgroup.ca Phone: 250.586.1100 RE: Pacific Shores VIS 2036 700 Block Second Floor Walkway Structural Review Dear Terry,
More information11/09/2018 LBP licence classes
LBP licence classes Occupational Licensing aims to ensure that people in the building industry are competent and accountable so that homes and buildings are designed and built right first time. Summary
More informationSCREEN PORCHES 101 DEVELOPMENT RESOURCES, INC Permit Requirements
SCREEN PORCHES 101 DEVELOPMENT RESOURCES, INC. 320-226.5189 www.101developmentresources.com While every attempt has been made to insure the correctness of this handout, no guarantees are made to its accuracy
More information10 EXTREME BASEMENT PANELS
10 EXTREME BASEMENT PANELS On Granular Footings 1. The type of soil is a factor in determining foundation construction details such as footing design, backfill, and drainage provisions. Soils are classified
More information