ENVIRONMENTAL IMPACT ASSESSMENT FOR THE

Size: px
Start display at page:

Download "ENVIRONMENTAL IMPACT ASSESSMENT FOR THE"

Transcription

1 OSHO Cement (Pty) Ltd ENVIRONMENTAL IMPACT ASSESSMENT FOR THE PROPOSED DEVELOPMENT OF A CEMENT GRINDING FACILITY ON A SITE LOCATED WITHIN THE COEGA INDUSTRIAL DEVELOPMENT ZONE, PORT ELIZABETH Environmental Management Programme (EMP) April 2013 J31358 Head Office 14 Eglin Road, Sunninghill 2191 Johannesburg, South Africa Tel: Fax:

2 ENVIRONMENTAL IMPACT ASSESSMENT FOR THE PROPOSED DEVELOPMENT OF A CEMENT GRINDING FACILITY ON A SITE LOCATED WITHIN THE COEGA INDUSTRIAL DEVELOPMENT ZONE, PORT ELIZABETH Environmental Management Plan 1 INTRODUCTION 2 2 PURPOSE OF THIS DOCUMENT 3 3 ENVIRONMENTAL MANAGEMENT: ROLES AND RESPONSIBILITIES OSHO Environmental Specialist OSHO Project Manager Contractor Project Manager (CPM) Environmental Control Officer () (Or Safety, Health and Environmental Officer (SHE)) Organogram - Environmental Management Plan 7 4 ENVIRONMENTAL MANAGEMENT REQUIREMENTS Section A: Planning and Pre-construction Phase Activities Section B: Construction Phase Activities Section C: Operation Phase Activities Section D: Post-Construction and Rehabilitation Phase Activities 25 5 ANNEXURE 1: LOCALITY MAP OF THE SITE LOCATION 28 6 ANNEXURE 2: ENVIRONMENTAL METHOD STATEMENT 1 1

3 1 INTRODUCTION The proponent, OSHO Cement (Pty) Ltd (OSHO) is a new role player in the South African Cement Industry. OSHO proposes to develop a cement grinding facility (CGF) with associated infrastructure at the Coega Industrial Development Zone (IDZ), which is located within the Nelson Mandela Bay Municipality in Port Elizabeth. The site identified for the CGF is approximately 11.5 Ha in extent. The purpose of the CGF is to produce cement. It is anticipated that the CGF would produce 150 tons of cement per hour with storage facilities accommodating up to 20,000 tons of cement and a combined storage capacity of 100,000 tons of clinker and slag (raw materials). This Environmental Management Programme was compiled as part of the Environmental Authorisation Process, required by NEMA, Act 107 of The EMP will look at the potential environmental impacts the proposed Cement Grinding Facility could have on the environment and which mitigation and monitoring procedures will need to be put in place to manage these impacts with the smallest environmental footprint possible. Further to this, the OSHO Coega Cement Grinding Facility will comply with all environmental guidelines and requirements as stipulated by the Coega Development Corporation (CDC). These guidelines include, but are not limited to: SHESD Standard Environmental Specifications for Construction SHESD Standard Occupational Health & Safety Specifications SHESD Standard Vegetation Specifications SHESD Construction Environmental Management Plan SHESD Guidelines for Contractors SHESD Guidelines for Engineers and SHE Coordinator CDC-OP-GD-001 Coega IDZ Safety, Health & Environmental Requirements for Potential Tenants OSHO, as the project proponent, has appointed GIBB (Pty) Ltd (GIBB) as the Independent Environmental Assessment Practitioner (EAP) to undertake the EIA for the proposed development, construction and installation of associated infrastructure. as well as to compile and review the Environmental Management Programme. 2

4 2 PURPOSE OF THIS DOCUMENT To provide a set of standards that will be used for the Environmental management during the development of site establishment and the construction phase of the Cement Grinding Facility To provide the monitoring and mitigation procedures that will need to be enforced and adhered to in order to ensure that the smallest possible environmental footprint of the CGF on the site and surrounding environment is made. This EMP will also explain the roles and responsibilities of the Project Manager, Environmental Control Officer (), and the OSHO Environmental Specialist. 3

5 3 ENVIRONMENTAL MANAGEMENT: ROLES AND RESPONSIBILITIES. 3.1 OSHO Environmental Specialist The OSHO Environmental Specialist will be responsible for ensuring that the EMP and associated Environmental documents or requirements are adhered to on the construction site. The Environmental Specialist will report diligently to the Project and the OSHO Project Manager. The specific tasks during the construction phase will include: Liaison with the environmental authorities where necessary. Review and signing off on all the Environmental documents from the Contractor. Conduct environmental monthly audits of all contractors work on site where applicable. Maintain site documentation related to environmental management (EMP, Method statements, audit reports, monitoring results, receipts of waste removal etc.). Documents to be maintained on the relevant site Documents Control Systems. Inspect and report on environmental incidents and check corrective actions. Handling of environmental incidents enquiries. Review and signing off on method statements prepared by the Contractors. 4

6 3.2 OSHO Project Manager The specific tasks of the OSHO Project Manager during the construction and operational phase have been clearly defined. Forming a part of those clearly defined tasks is the need to develop an Operational Environmental management Plan (OEMP) prior to the Operational Phase. The OEMP will need to include the following: Waste management plan Storm water management plan Resource management plan Air quality management plan Vector control Management of hazardous substances plan Alien vegetation management plan Noise management plan The OSHO Project Manager will be addressing all environmental requirements of the project through serving as a point of interaction between the Contractor and OSHO. Interacting as and when required with the OSHO Environmental Specialist regarding the project progress updates, and incorporating this EMP document into the contractor agreement will also form part of the OSHO Project Manager s responsibility. 3.3 Contractor Project Manager (CPM) The Specific tasks of the Contractor Project Manager during the construction phase will include the following tasks: Ensure implementation of the requirements in this EMP document on site daily through monitoring the work on site. Work closely with the to ensure that the requirements specified in section 4 of this EMP document are adhered to and delivered. 5

7 3.4 Environmental Control Officer () (Or Safety, Health and Environmental Officer (SHE)) The contractor needs to assign an Environment Control Officer whose role will entail the following: Prepare activity based environmental method statements when and where required. Ensure that environmental issues receive the required attention during on site induction training. Prepare and conduct on site environmental awareness training (posters, toolbox talks, and signage) for the contractor s personnel. Implementation of environmental related actions arising from the minutes of the SHE Meetings. Conduct daily and weekly inspections of the construction area using an environmental checklist and also keep records of all findings on file. Monitor compliance with the EMP and environmental method statements. Maintain site documentation related to environmental management (permits, EMP, Method statements, audit reports, monitoring results, receipts of waste removal, etc.) These documents need to be filed in the relevant site Documents Control System. Inspect and report on all environmental incidents and check the implementation of corrective actions. Keep photographic records of all environmental incidents. Keep records and log registers of all environmental incidents related to hazardous substances, complaints and environmental non-compliance. Implement the required corrective actions within the specified time frames. Compilation of the Project Environmental Management File. 6

8 The key environmental deliverables from the contractor s environmental personnel will include compilation of the following: Project Environmental inspection checklist. Weekly inspections and environmental audit reports. Method statements register. Environmental incidents register. Minutes of SHE meetings held. Environmental non-conformance register. Complaints register. Site decommissioning inspections. 3.5 Organogram - Environmental Management Plan OSHO Project Manager OSHO Environmental Specialist Prepare required plans, designs, project specifications, tender and contract document. Monitoring adherence to the EMP, i.e. legal adherence and compliance. Environmental Control Officer Contractor project manager Implement EMP requirements during construction, operation and rehabilitation. Construct the Cement Grinding Facility according to specifications provided whilst complying with the EMP. 7

9 4 ENVIRONMENTAL MANAGEMENT REQUIREMENTS 4.1 Section A: Planning and Pre-construction Phase Activities A.1. Construction Camp set up Careful planning of the construction camp can ensure that the time and costs associated with environmental management and rehabilitation are reduced. A.1.1 Layout (a) The choice of the Contractor s camp requires the OSHO Project Manager s permission and must ensure that the camp is located in an area that will ensure a minimum impact. (b) The contractor should submit plans of exact location, extent and construction details of the temporary construction camp facilities to the OSHO Project Manager for approval, prior to establishment of the camp. /CPM /CPM During surveys and preliminary investigations and prior to moving onto site. Prior to moving on site Compliance to CDC guidelines The layout plans should reflect the proposed camp s location in relation to any existing infrastructure (water mains, electricity cables, sewage mains, etc.) on site and any environmental sensitive areas (e.g. wetlands, grasslands, etc.) where applicable. Access to the construction camp must be through an existing route or one that is clearly demarcated and agreed upon. CPM Prior to moving on site (c) If the contractor chooses to locate the camp on private land, he must get prior written permission from both the OSHO Project Manager and the land owner. (d) The construction camp can comprise of the following: a. Site office b. Ablution facilities CPM up 8

10 c. Designated first aid area d. Eating area e. Storage areas f. Accommodation area A.1. Construction Camp set up A.1.2 Ablution facilities (a) Temporary chemical toilets must be provided by a contractor. Such toilets must be available for all site staff, both at the camp and on site as agreed by the CPM. CPM up. A.1.3. Provision for camp waste disposal (a) Bins and skips shall be provided at convenient intervals for disposal of waste within the construction camp. (b) Bins should have a liner bag for efficient control and safe disposal of waste. (c) Recycling and provision of separate waste receptacles for different types of waste should be encouraged. CPM/ up. up. On-going A.2. Establishing storage areas Storage areas can be hazardous and unsightly. These storage areas can also A.2.1. Substances Materials General and (a) When deciding on the location of temporary up. In accordance with the Hazardous 9

11 cause environmental pollution if not designed and managed properly. stockpiles, the following needs to be considered: road access, vegetation cover and the length of time the stockpile will exist. (b) Additionally all stockpiles should be located away from sensitive ecosystems and protected from the prevailing winds. (c) Storage areas must be designated, demarcated and fenced if necessary. (d) Storage areas should be secured, to minimize the risk of crime and contamination. OSHO to erect appropriate wind breaks, to monitor up. up. up. substances Management Plan. Steel wind breaks to be erected around GBFS stockpiles to prevent dust emissions A.2.2 Substances Materials Hazardous and (a) The contractor indicated that no fuel or hazardous liquid substances will be stored on site. However, should it happen that there is a need to store fuel on site; it must be stored in a bunded area. (b) Hazardous chemical working/refueling areas must be bunded with an impermeable liner to protect the soil. This can be done using a plastic liner covered with soil. up up In accordance with the Hazardous substances Management Plan 10

12 A.3. Materials: Management and sourcing Materials must be sourced in a legal and sustainable way to prevent off-site environmental degradation. A.3.1. Source of Materials (a) Contractors shall where possible prepare a source statement indicating the sources of all materials to be used in the plant construction. The source statements should be submitted to the OSHO Project Manager. (b) Where possible, a signed document from the supplier of natural materials should be obtained confirming that they have been sourced in a sustainable manner, in compliance with the relevant environmental legislations. (c) Where materials are locally mined, proof must be provided of authorization to utilize these materials from the landowner/minerals rights owner and the Department of Minerals and Energy. (d) Compile a Resource Management Plan and submit to the for approval OSHO Environment al Specialist Site Manager Pre-project commencement Pre-project commencement In accordance with the Approve Resource Management Plan 11

13 A.4. Education of site staff on general Environmental Conduct These points must be communicated to all staff before the project commence on site. A.4.1. Environmental Education and Awareness Under no circumstances may open areas or surrounding bush be used as toilet facilities. Ensure that all site personnel have a basic level of environmental awareness training. Topics covered should include: What is meant by Environment? Why do we have to protect the environment? How construction activities can impact on the environment. How can these impacts be mitigated. Awareness of emergency and spills response provisions. Social responsibility during construction e.g. being considerate to local residents. CPM/ up. During induction staff It is the contractor s responsibility to provide the site foreman with no less than 1 hour s environmental training and to ensure that the foreman has sufficient understanding to pass the information onto the construction staff. 12

14 (a) Translators are to be used where necessary. (b) The use of pictures and real-life examples is encouraged as these are easier to remember. (c) The need for a clean site policy also needs to be explained to the construction workers. A.4.2. Worker Conduct on Site Under no circumstances may open areas or surrounding bush be used as toilet facilities. CPM/ up. A general regard for the social and ecological wellbeing of the site and adjacent areas is expected of the site staff. Workers need to be made aware of the following general rules: No alcohol/drugs to be present on site. No fire arms allowed on site or in vehicles transporting staff to/from the site (unless by security personnel.) Prevent unsocial behavior and excessive noise. Construction staff is to make use of facilities provided for them, as opposed to ad hoc alternatives. Trespassing on private/commercial CPM/ During induction staff During staff induction, followed by ongoing monitoring. On-going monitoring CDC and OSHO Noise Management Plan 13

15 properties adjoining the site is forbidden. Driving under the influence of alcohol is prohibited. A.5. Erosion Soil Stripping of Vegetation during set up activities on site greatly increases the risk of erosion. (a) The time that stripped areas are left open to exposure should be minimized wherever possible. Care should be taken to ensure that lead times are not excessive. /CPM Throughout the duration of the project. CDC vegetation guidelines A.6. Quality Water Incorrect disposal of substances and materials and polluted run-off can cause serious negative impacts on ground water. (a) Equipment and machinery must be in good operation condition, clean (power washed), free of leaks, excess oil and grease. (b) Ensure that machinery is operated by a skilled driver who has been trained to use it correctly and who will be able to identify if something is wrong with the engine and conduct regular inspections identifying engine related leaks. up. up. CDC and OSHO Storm Water Management Plan (c) Remove excavated materials and debris from the construction front, and store it in a secure place on site, that will not impact on the vegetation or cause groundwater pollution. up. 14

16 A.7. Conservation of flora, fauna and sensitive habitats Care must be taken to conserve existing plants, animals and surrounding habitats. A.8.1 Flora and Fauna (a) Consultation with the CDC Nature Conservation staff must be undertaken to confirm if any protected species that require special attention during construction are present on the site. (b) Minimizing the extent of the area where work is taking place and other measures deemed to be adequate. (c) Method statements must be prepared on how the construction area will be dust free to prevent air pollution by means of an air quality management plan. CPM Prior to commencement with work. During surveys, preliminary investigations and on-going. up. CDC Vegetation Guidelines A.8. Set up of waste management activities A.9.1 management Waste (a) A dedicated area must be allocated for waste sorting and storage. (b) Individual waste skip or wheelie bins for different types of waste should be provided. (c) A waste Management Plan must be compiled and sent to the for approval. Site Manager up up up In accordance with the Waste Management Plan 15

17 A.10. Security and safety A Risk Associated with materials on site (a) Material stockpiles or stacks such as cement, steel, bricks, corrugated iron sheeting, plastic piping, etc. must be stable and well packed to avoid collapse and possible injury to site workers. Stockpiles must also be lined with an impermeable material to avoid seepage and ground water pollution. (b) No materials are to be stored in unstable or high risk areas such as in close proximity of the entrance road, excavated areas, etc. /CPM /CPM On-going On-going 4.2 Section B: Construction Phase Activities B.1. Site Access B.1.1 Access to the site (a) Access to the Working area should be limited to one route. Heavy machinery must be brought in on to the construction site with utmost caution. The site entrance should also be properly marked with all the necessary notice and safety instruction boards and posters. (b) Unnecessary compaction of soils by heavy vehicles must be avoided where possible. Movement of equipment or machinery required for work on site must be restricted to CPM/ CPM On-going On-going 16

18 working areas. (c) Cognisance of machinery/vehicles weight must be taken into account in order to minimize the soil compaction impacts. B.2. Maintenance of construction camp B.2.1 Ablution (a) Chemical toilets will be provided where no ablution facilities are available. These chemical toilets need to be maintained and managed to ensure safety and to reduce possible impacts. (b) The contractor needs to ensure that open areas or the surrounding bush are not used as ablution in any way. CPM On-going Weekly inspection B.2.2. Eating Areas (a) Eating areas should be serviced and cleaned regularly to ensure the highest possible standards of hygiene and cleanliness. (b) All litter throughout the site should be picked up and placed in the appropriate recycling bins provided. Weekly inspection Daily B.2.3. Housekeeping (a) The contractor shall ensure that his camp and working areas are kept clean and tidy at all times. Weekly 17

19 B.3. Staff Conduct B.3.1. Environmental Education and Awareness (a) The contractor must monitor the performance of construction workers to ensure that all the topics that where covered in the induction meeting is properly understood, and followed. /CPM Daily Toolbox talks and lunchtime Q&A. B.4. erosion Soil B.5. Protection of the natural environment B.4.1. Topsoil stripping and stockpiling Once the area has been cleared of vegetation, the top layer of soil (usually 150mm), should be removed and stockpiled in a designated area. On-going This section aims to ensure that the impacts from construction activities on plant and animal habitats are reduced and mitigated. B.5.1. Flora, Fauna and sensitive habitats (a) Construction work is to be restricted to within the demarcated areas. (b) No vegetation should be cleared for access purposes. Unless access is restricted without clearance of vegetation. Vegetation clearance will be limited to the construction area. (c) The contractor shall not in any way modify nor damage the site, other than where construction will occur. Soil compaction should be minimized with the use of light construction vehicles and machinery where possible. (d) The contractor is to consider CPM/ On-going On-going needs to develop a site vegetation protection and rehabilitation plan to monitor indigenous and alien species by means of an alien vegetation management plan. Compliance to the specific conditions of the guideline 18

20 manual excavations where feasible. must be met. Please refer to Appendix G1 for the guideline in question. B.6. Waste Management Activities in the construction site such as office work, usage of construction materials, etc., generate different types of waste that requires to be managed properly. These wastes could result in environmental pollution such as soil contamination/ pollution or health hazards to employees working onsite, if not managed properly. B.6.1 On-site waste management (a) Waste is grouped into general or hazardous, depending on its characteristics. The classification determines the handling methods and the ultimate disposal of the material. The Contractor must classify waste into general or hazardous based on the toxicity or hazard nature of waste. (b) Waste must be placed in the designated or marked skips/bins which must be emptied on a regular basis by a contracted waste collector. These should remain within the demarcated areas and should be designed to prevent refuse from being blown out by wind. (c) Separation of waste and recycling of paper, glass, cans, scrap, metals, plastic bottles, etc., must be considered prior to disposal. The disposal at the landfill site should be considered as the last option, after having taken into consideration the prevention of waste generation, reduction waste generation, reuse and recycling. (d) Hazardous waste that require disposal (oily rags, used fuel/oil, etc.) must be placed in a suitable leak 19 During the start-up of constructio n on site. Daily On-going On-going and CPM needs to ensure that all construction staff are educated on the site waste management plan as per the site Environmental Management System

21 proof skip or wheelie bin for disposal at an approved hazardous waste disposal facility. (e) The contractor is responsible for arranging the removal of all waste from site generated through construction activities. Waste must be removed to the appropriate disposal and recycling facilities. During commence ment of constructio n. In accordance with the Hazardous substances Management Plan. (f) Should chemical toilets be used, an appropriate contractor must be employed to service these facilities on an ongoing basis. All waste generated from the chemical toilets must be disposed of at an approved waste water treatment facility or works, in terms of section 19 of the National Environmental Management Waste Act 59 of 2008 or section 20 of the Environmental Conservation Act 73 of (g) No burning and littering of waste on site should be allowed. (h) Request the following from the waste contractors that are used to collect waste: - Copies of the weighbridge receipt from the waste removal contractor for all waste collected on site. - Obtain copies of the environmental authorization (in terms of section 19 of the National Environmental Management Waste Act 59 of 2008 or section 20 of the Environmental Conservation Act 73 of 1989) of the facilities that are used to recycle, treat and dispose of waste, and kept on the environmental file. CPM CPM As and when required. On-going During waste collection Prior to signing an agreement with the waste removal contractor. 20

22 B.7. Construction vehicles / equipment Engine machines such as compressors, pumps, air conditioners and arc welders can have small leaks (usually oil) that can accumulate to become spills, which require clean-up. These leaks become more evident if the equipment remains in the same place for an extended period of time. Damaged fuel tanks, fuel hoses, and fuel pumps can be sources of significant fuel leaks. Hydraulic systems can blow gaskets or hoses resulting in large quantities of hydraulic fluid spilled to the ground. (a) Vehicles and machinery are to be kept in good working order and to meet manufactures specification for safety, fuel consumption and emission. (b) Should excessive emissions be observed, the site manager needs to implement an effective vehicle and equipment service and maintenance plan. (c) Vehicle parking and equipment storage must be done on a hardened and sealed surface area such that oil, fuel and other fluid leaks do not pollute soil or ground water sources. CPM CPM CPM On-going On-going On-going CPM must follow a detailed checklist for machinery and equipment maintenance. 21

23 B.8. Emergency Response This section aims to provide measures to manage spillages from equipment used on site and measures for other construction materials handled on site. The contractor shall take into account the following prevention measures to be applied during spillages. (a) Immediately repair all leaks of hydrocarbons, oil, etc. (b) Take reasonable measure to prevent the spills or leaks. (c) Dispose contaminated materials to a location designated thereto. (d) The contractor shall have its own spill response plan in the event of any spills (oil, fuel, hazardous materials) from his machinery or equipment used on site. /CPM /CPM During spillages During spillages The and contractor must ensure that the Emergency response procedure is well understood by all workers on site and that a summary is available for site visitors. 4.3 Section C: Operation Phase Activities C.1. Infrastructure Structural Integrity (a) The structural integrity of the infrastructure needs to be check at regular intervals. Operation al Staff during Operation al phase of the project On a quarterly basis must develop a checklist, where if the checklist is followed, the infrastructure will have structural integrity. Activities should take place in accordance with the OEMP. 22

24 C.2. Pollution Air (a) The air filters on conveyors and on the bagging facility needs to be checked and maintained to ensure that no dust emissions occur. (b) The roads in and around the CGF needs to be wetted and swept on regular intervals to reduce possible fugitive dust. (c) The hot gas generator needs to be serviced according to manufacturer guidelines, to ensure efficient engine working and fuel combustion. (d) Storage silos and raw material storage facilities needs to be managed and maintained to reduce the possibility of air pollution through fugitive dust. (e) Dust controlled Hoppers or similar technology needs to be used in order to minimize the Air emissions during the unloading process of dry bulk cargoes ensuring an economical and ecologically sensitive solution fulfilling all needs. The monitoring of the air pollution preventative measures need to occur on a biweekly basis. The OSHO Environmental specialist needs to do monthly site visits to ensure that the is enforcing adherence and compliance to the EMP. 23

25 C.3. Storm water management (a) The storm water collection canals and attenuation pond needs to be checked and maintained to ensure that no blockages or debris prevent the collection and flow of the water. (b) The attenuation pond needs to be cleaned of sediment. (c) The roofs and gutters needs to kept clear or dust, debris, leaves. (d) A Storm water Management Plan needs to be compiled and submitted to the for approval (e) Compliance assessment with DWAF licensed storm water dam (f) Monitoring other storm water points & ad hoc sampling in the major storm water system (g) Monitoring receiving surface water (h) Monitoring of ground water Site Manager Site Manager Site Manager Site Manager Site Manager All these storm water management activities need to occur on a weekly to a biweekly schedule. Continuously / weekly during raining seasons Monthly during rainy seasons Quarterly Six Monthly unless problem identified The needs to design and use a checklist that lists all areas and things to be checked, as well as a timeframe within which the activities need to occur. In accordance with the Storm Water Management Plan 24

26 C.4. General (a) Handling of laboratory chemical- and other wastes. (b) Management of used oil/grease from maintenance activities (c) Other generated waste from workshop activities, office waste, sewerage etc. Site Manager All these general waste management activities need to occur on a weekly to a biweekly schedule. and CPM needs to ensure that all construction staff is educated on the site waste management plan. 4.4 Section D: Post-Construction and Rehabilitation Phase Activities D.1. Construction Camp (a) All structures comprising the construction camp are to be removed from the site. (b) The area that previously housed the construction camp has to be checked for spills from oil, fuel, hazardous substances and paint. These spills need to be cleaned. (c) All areas that were vegetated prior to construction will be prepared in such a manner that it creates the ideal environment for vegetation regrowth. CPM CPM CPM At project completion. At project completion. At project completion. Site inspection Detailed site inspection in accordance with the Hazardous substances Management Plan Detailed inspection site 25

27 D.2. Vegetation D.3. Materials and infrastructure (a) All areas that have been disturbed by the construction activities (including the construction camp area) must be cleared of alien plant species (b) Disturbed areas will be left to regenerate naturally, and if intervention is required in terms of revegetation, it will be undertaken. If any alien vegetation is found it will be removed in order to encourage colonization of indigenous species. At project completion At project completion Monthly Detailed site inspection Monthly Detailed site inspection by means of an alien vegetation management plan (a) Fences, barriers and demarcations associated with the construction phase are to be removed from the site. (b) All residual stockpiles must be removed to spoil or spread on site as directed by the OSHO Project Manager (c) All left over building materials must be returned to the contractor depot or removed from the site. (d) The contractor must repair damage that the construction works has caused. CPM CPM CPM/ CPM/ At project completion At project completion At project completion At project completion 26

28 D.4. General (a) Rehabilitation of disturbed areas should be undertaken in such a manner that it satisfies the guidelines of the CDC. (e) A meeting is to be held on the site between the CDC, OSHO Environmental Specialist, Project, and the Contract Project Manager to approve all the remediation activities and to ensure that the site has been restored to a similar preconstruction phase condition. & OSHO Environmental Specialist, OSHO Project Manager/ Environmental Specialist On completion of construction phases On completion of construction phases 27

29 5 ANNEXURE 1: LOCALITY MAP OF THE SITE LOCATION 28

30 1

31 6 ANNEXURE 2: ENVIRONMENTAL METHOD STATEMENT Contract: Proposed Activity Date: dd/mm/yy What work is to be undertaken: Where are the works to be undertaken: Start and end date of the works for which the method statement is required: Start Date: End Date: Description of how potential environmental impacts will be mitigated or managed: Declarations: Employer s Environmental Control Officer The work described in this Environmental Method Statement, if carried out according to the methodology described, is satisfactory to prevent the environmental impact: Signature Print Name Date 4. Person undertaking the works 1

32 I understand the contents of this Environmental Method Statement and the scope of the works required of me. I further understand that this Environmental Method Statement may be amended on application to other signatories and that Employer s Environmental Manager and Project Manager will audit my compliance with the contents of this Environmental Method Statements. Signature Print Names 5. Approving Authority (i.e. Employer s Construction Manager) The works describe in this method statement are approved. Signature Print Name Designation Date 2

Transnet Pipelines. January 2013 J Draft Environmental Management Programme

Transnet Pipelines. January 2013 J Draft Environmental Management Programme Transnet Pipelines Environmental Management Plan for the Construction of Gabions, to protect the Exposed High Pressure Fuel Pipeline in Moreleta Spruit, Garsfontein, Tshwane Metropolitan Municipality Draft

More information

ENVIRONMENTAL MANAGEMENT PROGRAMME

ENVIRONMENTAL MANAGEMENT PROGRAMME PPC Ltd ENVIRONMENTAL MANAGEMENT PROGRAMME FOR THE PROPOSED MILLING OF SLAG AT THE PPC JUPITER SITE, CITY OF JOHANNESBURG, GAUTENG June 2013 J31369 Head Office 14 Eglin Road, Sunninghill 2191 Johannesburg,

More information

Final Draft Environmental Management Programme (EMPr) for the Proposed Installation of a Gas Fired Heat Treatment Furnace at Scaw Metals High Chrome

Final Draft Environmental Management Programme (EMPr) for the Proposed Installation of a Gas Fired Heat Treatment Furnace at Scaw Metals High Chrome Final Draft Environmental Management Programme (EMPr) for the Proposed Installation of a Gas Fired Heat Treatment Furnace at Scaw Metals High Chrome Ball Plant in Germiston A Report For: Scaw South Africa

More information

Environmental Management Programme (EMP)

Environmental Management Programme (EMP) Appendix D Environmental Management Programme (EMP) Please note that although Construction and Operational Phase measures are included in this EMP they are relevant to the issued Waste Management Licence

More information

WASTE MANAGEMENT PLAN

WASTE MANAGEMENT PLAN DEA REF: 14/12/16/3/3/2/1049 WASTE MANAGEMENT PLAN THE PROPOSED CONSTRUCTION OF A 90MW PV SOLAR PARK PROJECT, AND 66KV TRANSMISSION LINE TO CONNECT TO EXISTING SUBSTATION OVER PORTIONS 3, 4, 6 AND THE

More information

DOORNVALLEI EXT 5 & 6

DOORNVALLEI EXT 5 & 6 DOORNVALLEI EXT 5 & 6 Proposed township establishment on portion 107 the farm Doornkloof 391 JR Sewer Pipe Crossings - Sesmylspruit Construction Method Statement April 2016 Revision 3 PREPARED FOR: PREPARED

More information

MATRIX 1: ENVIRONMENTAL MANAGEMENT PLAN TO BE IMPLEMENTED DURING THE SITE PREPARATION AND CONSTRUCTION PHASES

MATRIX 1: ENVIRONMENTAL MANAGEMENT PLAN TO BE IMPLEMENTED DURING THE SITE PREPARATION AND CONSTRUCTION PHASES MATRIX 1: ENVIRONMENTAL MANAGEMENT PLAN TO BE IMPLEMENTED DURING THE SITE PREPARATION AND CONSTRUCTION PHASES Environmental / Social issue/ aspect/ activity Anticipated negative impact Management and mitigation

More information

left over, or an unwanted by-product, from an industrial, commercial, domestic or other activity; or

left over, or an unwanted by-product, from an industrial, commercial, domestic or other activity; or 14. Waste Management 14.1. Waste Management Regulations The regulatory requirements governing waste management are provided within the EP Act, the EPR and associated Environmental Protection (Waste Management)

More information

Environmental Control Plan

Environmental Control Plan Environmental Control Plan Environmental Control Plan In accordance with Watts & Hughes Construction Waikato Bay of Plenty Limited. corporate strategies the Company has an Environment Control Plan which

More information

Environmental Guidelines for Construction Sites

Environmental Guidelines for Construction Sites Inspection Items Guidelines Remarks 1) Air Pollution Control 1a) Notification to EPD before Work Commencement If the work is classified as notifiable work such as site formation, reclamation, building

More information

ENVIRONMENTAL MANAGEMENT PLAN. Developed for National Asphalt (Pty) Ltd. Generic Requirements

ENVIRONMENTAL MANAGEMENT PLAN. Developed for National Asphalt (Pty) Ltd. Generic Requirements ENVIRONMENTAL MANAGEMENT PLAN Developed for National Asphalt (Pty) Ltd Generic Requirements November 2013 GENERIC ENVIRONMENTAL MANAGEMENT PLAN NATIONAL ASPHALT (Pty) Ltd PO Box 1657 Hillcrest 3650 Tel:

More information

8.11. Soil Erosion control Safety Compliance Summary Recommendation... 16

8.11. Soil Erosion control Safety Compliance Summary Recommendation... 16 ENVIRONMENTAL IMPACT CONTROL REPORT FOR THE CONSTRUCTION OF TWO (2) 10km 132 KV POWERLINES FROM NGWEDI MTS TO THE EXISTING BAKUBUNG SUBSTATION AND NGWEDI MTS TO EXISTING STYLDRIFT SUBSTATION IN BONAJALA

More information

OPERATION PHASE: ENVIRONMENTAL MANAGEMENT PROGRAMME

OPERATION PHASE: ENVIRONMENTAL MANAGEMENT PROGRAMME OPERA PHASE: ENVIRONMENTAL MANAGENT PROGRAMME 1. OBJECTIVE The overall goal for the Environmental Programme (O) is to ensure that the operation of the wind energy facility (WEF) does not have unforeseen

More information

Alberta Transportation The City of Edmonton The City of Calgary

Alberta Transportation The City of Edmonton The City of Calgary Alberta Transportation The City of Edmonton The City of Calgary PUBLISHING INFORMATION TITLE: PREPARED BY: DOCUMENT HOLDER: Environmental Construction Operations (ECO) Plan Framework Instructions for

More information

Environmental Management Plan

Environmental Management Plan (Operational Sites) 1 P a g e A. Introduction An is a written document with the purpose to provide mitigation measures and principles for the management of sites in order to reduce potential impacts to

More information

ENVIRONMENTAL AND OPERATIONAL MANAGEMENT PLAN

ENVIRONMENTAL AND OPERATIONAL MANAGEMENT PLAN Zitholele Consulting Reg. No. 2000/000392/07 PO Box 6002 Halfway House 1685 South Africa Thandanani Park, Matuka Close Halfway Gardens, Midrand Tel + (27) 011 207 2079 Fax + (27) 011 805-2100 E-mail :

More information

Manningham Works Code of Practice

Manningham Works Code of Practice Manningham Works Code of Practice June 2017 Manningham City Council 699 Doncaster Road (PO Box 1) Doncaster Vic 3108 t 9840 9333 f 9848 3110 e manningham@manningham.vic.gov.au www.manningham.vic.gov.au

More information

Environmental Management Plan Introduction Environmental Management Objectives Structure, Implementation and Review

Environmental Management Plan Introduction Environmental Management Objectives Structure, Implementation and Review Environmental Management Plan Introduction This Environmental Management Plan (EMP) has been prepared for SEF Energy Co. Ltd. for the purpose of providing a stand-alone plan for managing the potential

More information

Gold Coast Airport Tenant Environment Management Guideline

Gold Coast Airport Tenant Environment Management Guideline Gold Coast Airport Tenant Environment Management Guideline July 2012 Introduction Implementation of sound environment management practices is critical in meeting legislative requirements and business objectives.

More information

Crushing and Screening Management Procedure Environment

Crushing and Screening Management Procedure Environment 1 Purpose and Scope This procedure specifies the operational environmental requirements relating to crushing and screening management at the Roy Hill Project. This procedure applies to all personnel involved

More information

Mining Work Plan for the Scribante Concrete (Pty) Ltd Sand Mining Operation along the Inxu River

Mining Work Plan for the Scribante Concrete (Pty) Ltd Sand Mining Operation along the Inxu River Mining Work Plan for the Scribante Concrete (Pty) Ltd Sand Mining Operation along the Inxu River Page 1 of 11 Index Page 2 Objective Page 3 Applicant Details Page 3 Executive Summary Page 5 Figure 1, Locality

More information

Draft Amendment Application Report, Agni Steels SA February 2011 Executive Summary EXECUTIVE SUMMARY

Draft Amendment Application Report, Agni Steels SA February 2011 Executive Summary EXECUTIVE SUMMARY EXECUTIVE SUMMARY PROJECT BACKGROUND AND DESCRIPTION On the 16 February 2009, Agni Steels SA (Pty) Ltd (formerly Afro Asia Steels), was issued an Environmental Authorisation for the construction and operation

More information

Wastewater Management Procedure Environment

Wastewater Management Procedure Environment 1 Purpose and Scope This procedure specifies the operational environmental requirements relating to the management of wastewater and the operation and maintenance of Roy Hill wastewater treatment plants

More information

8 ENVIRONMENTAL MANAGEMENT PROGRAMME (PROJECT ENVIRONMENTAL SPECIFICATION)

8 ENVIRONMENTAL MANAGEMENT PROGRAMME (PROJECT ENVIRONMENTAL SPECIFICATION) 8 ENVIRONMENTAL MANAGEMENT PROGRAMME (PROJECT ENVIRONMENTAL SPECIFICATION) In order to manage the construction phase impacts associated with the establishment of the Compilation Yard and the Common User

More information

Engineering Compliance East London Regional Waste Disposal Site A Case Study

Engineering Compliance East London Regional Waste Disposal Site A Case Study Engineering Compliance East London Regional Waste Disposal Site A Case Study A.S Dookhi, Envitech Solutions (Pty) Ltd, South Africa, nash@envitech.co.za ABSTRACT The East London Regional Waste Disposal

More information

GUIDANCE NOTES - CONSTRUCTION DESIGN AND MANAGEMENT (CDM) 3

GUIDANCE NOTES - CONSTRUCTION DESIGN AND MANAGEMENT (CDM) 3 GUIDANCE NOTES - CONSTRUCTION DESIGN AND MANAGEMENT (CDM) 3 Page 1 Page 2 GUIDANCE NOTES - CONSTRUCTION DESIGN AND MANAGEMENT (CDM) ROLES AND RESPONSIBILITIES The CLIENT must: 1. Be satisfied that all

More information

ESKOM HOLDINGS LIMITED

ESKOM HOLDINGS LIMITED ESKOM HOLDINGS LIMITED CONSTRUCTION AND OPERATION OF ASH DAM EXTENSION 3 & THE DEVIATION OF O TRANSMISSION AND DISTRIBUTION LINES AT KOMATI POWER STATION TATION, MPUMALANGA REVISED ENVIRONMENTAL MANAGEMENT

More information

APPENDIX G ENVIRONMENTAL MANAGEMENT PROGRAMME

APPENDIX G ENVIRONMENTAL MANAGEMENT PROGRAMME APPENDIX G ENVIRONMENTAL MANAGEMENT PROGRAMME APPENDIX G1 CONSTRUCTION ENVIRONMENTAL MANAGEMENT PROGRAMME SLR Consulting (South Africa) (Pty) Ltd Page i CONSTRUCTION ENVIRONMENTAL MANAGEMENT PROGRAMME

More information

Environmental Management Plan

Environmental Management Plan Environmental Management Plan EMP for the Stage 1 Construction and Operation of the Trainers Allotment Area at the Pakenham Racecourse located at Nar Nar Goon / Longwarry Road, Tynong Pty Ltd abn: 44 706

More information

Waste Management Plan. Pine Dale Coal Mine (Including the Yarraboldy Extension)

Waste Management Plan. Pine Dale Coal Mine (Including the Yarraboldy Extension) Enhance Place Pty Limited ABN: 31 077 105 867 Waste Management Plan for the Pine Dale Coal Mine (Including the Yarraboldy Extension) August 2015 Version Revision Date Revision History Reason for Revision

More information

Environmental Guideline on Stone crushing plant set up temporarily for the purpose of a project by a public department

Environmental Guideline on Stone crushing plant set up temporarily for the purpose of a project by a public department 2017 [Type a quote from the document or the summary of an interesting point. You can position the text box anywhere in the document. Use the Drawing Tools tab to change the formatting of the pull quote

More information

ENVIRONMENTAL POLICY DOCUMENT

ENVIRONMENTAL POLICY DOCUMENT ENVIRONMENTAL POLICY DOCUMENT Issue Date Revision By Next review due Amendment Page 1 Table of Contents 1. Scope 2. Definitions 3. Environmental Management System Requirements 4. Environmental Policy Statement

More information

Dust generation/ Air pollution. Noise and vibration. Water pollution. Drainage and sedimentation

Dust generation/ Air pollution. Noise and vibration. Water pollution. Drainage and sedimentation Energy Resilience for Climate Adaptation Project (ERCAP) Environmental Code of Practice (ECOP) for COMPONENT 2: Demonstration Measures to Enhance Resilience of Energy Sector (Pilot for Strengthening Transmission

More information

Kurnell Refinery Conversion Project

Kurnell Refinery Conversion Project Kurnell Refinery Conversion Project Waste Management Plan CALTEX REFINERIES (NSW) PTY LTD January 2014 Page 1 1 INTRODUCTION Caltex propose to convert the petroleum refinery in Kurnell (the Site ) to a

More information

Water Pollution Control for Work in Sensitive Areas

Water Pollution Control for Work in Sensitive Areas Water Pollution Control for Work in Sensitive Areas 10-1. WATER POLLUTION CONTROL The Contractor is advised that failure to fully comply with the provisions of this Section, and all requirements listed

More information

EF10 Site Environmental Audit - 1 / 8

EF10 Site Environmental Audit - 1 / 8 EF10 Site Environmental Audit Site... Date... Internal/external audits 1. Have all corrective actions raised at previous audits been implemented (EF07)? O O O 2. Have actions taken been monitored to confirm

More information

JSP Construction Ltd CONSTRUCTION ENVIRONMENTAL MANAGEMENT PLAN City Road Cardiff CF24 3BJ

JSP Construction Ltd CONSTRUCTION ENVIRONMENTAL MANAGEMENT PLAN City Road Cardiff CF24 3BJ CONSTRUCTION ENVIRONMENTAL MANAGEMENT PLAN JSP Construction Ltd 11-13 City Road Cardiff CF24 3BJ Revisions Issue Description Approved By Signed Date 19/10/16 1st issue AN JP 19.10/16 Rev A Updated with

More information

BACKGROUND INFORMATION DOCUMENT

BACKGROUND INFORMATION DOCUMENT Kingfisher Farms (Pty) Ltd SAND MINING APPLICATION Manor Grange Farm, Hibberdene (KwaZulu-Natal) BACKGROUND INFORMATION DOCUMENT BACKGROUND INFORMATION An application has been submitted to the Department

More information

ENVIRONMENTAL RISK ASSESSMENT SHEET

ENVIRONMENTAL RISK ASSESSMENT SHEET ENVIRONMENTAL RISK ASSESSMENT SHEET Instructions for Use A filled- in example of this sheet is provided, based on the hypothetical removal of an underground diesel storage tank. Use this example to familiarise

More information

ENVIRONMENTAL GUIDANCE NOTES: CONSTRUCTION ENVIRONMENTAL MANAGEMENT PLAN (CEMP)

ENVIRONMENTAL GUIDANCE NOTES: CONSTRUCTION ENVIRONMENTAL MANAGEMENT PLAN (CEMP) ENVIRONMENTAL GUIDANCE NOTES: CONSTRUCTION ENVIRONMENTAL MANAGEMENT PLAN (CEMP) Disclaimer: The information contained in this communication document is intended solely for the use of guidance cannot be

More information

PROPOSED RESIDENTIAL DEVELOPMENT ON ERF 271 BAKKERSHOOGTE, SOMERSET WEST

PROPOSED RESIDENTIAL DEVELOPMENT ON ERF 271 BAKKERSHOOGTE, SOMERSET WEST PROPOSED RESIDENTIAL DEVELOPMENT ON ERF 271 BAKKERSHOOGTE, SOMERSET WEST Draft Environmental Management Programme: Construction and Operational Phases Incorporating a Wetland Maintenance Management Plan

More information

ANY LIMITED (WMP) Version. Review. Date. All. Plan 5 Yearly. December All. MCC Environmental, Technical. December Yearly.

ANY LIMITED (WMP) Version. Review. Date. All. Plan 5 Yearly. December All. MCC Environmental, Technical. December Yearly. MUSWELLBROOK COAL COMPA ANY LIMITED WASTE MANAGEMENT PLAN (WMP) December 2015 Version 1 February 2005 All 2 3 Date December 2010 December 2015 Section Modified All All Reason for Modification Original

More information

Contractor and Supplier Expectations

Contractor and Supplier Expectations Contractor and Supplier Expectations GUI/1548 Issue 15 Page 1 of 10 16 September 2016 Contents 1. INTRODUCTION AND SCOPE 3 2. RICARDO ENERGY & ENVIRONMENT POLICIES 3 3. SUSTAINABILITY 4 4. MANAGEMENT OF

More information

To reduce the consumption of energy and the emission of greenhouse gases associated with Transit Systems NSW s activities.

To reduce the consumption of energy and the emission of greenhouse gases associated with Transit Systems NSW s activities. Transit Systems NSW Environmental Management Plan GOAL 1: REDUCE THE GREENHOUSE IMPACT OF ENERGY USE To reduce the consumption of energy and the emission of greenhouse gases associated with Transit Systems

More information

Construction Environment Management Plan

Construction Environment Management Plan Construction Environment Management Plan Guidance Material July 2013 ABSTRACT This CEMP guidance material has been prepared by MAC to assist the identification and management of environmental risks associated

More information

Construction Management Plan (CMP) 227 Princess Highway, Dandenong

Construction Management Plan (CMP) 227 Princess Highway, Dandenong Construction Management Plan (CMP) 227 Princess Highway, Dandenong - Construction Management Plan (CMP) June 2017 S2966 CMP.D2 PREPARED BY: Sustainable Development Consultants 2nd Floor, 555 Riversdale

More information

E3072 v2. GEF Large City Congestion and Carbon Reduction Project. Environment Management Plan. Public Disclosure Authorized

E3072 v2. GEF Large City Congestion and Carbon Reduction Project. Environment Management Plan. Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized E3072 v2 GEF Large City Congestion and Carbon Reduction Project Environment Management

More information

Environmental Management Plan (EMP)

Environmental Management Plan (EMP) SE DELI GS DRIFT MI E ORA GE RIVER MI ES MI I G ACTIVITIES A D PROPOSED EW I PIT SLIMES DISPOSAL Environmental Management Plan (EMP) Compiled for: Namdeb Diamond Corporation (Pty) Ltd Compiled by: Unit

More information

Hazardous Waste Management

Hazardous Waste Management Objectives EC SE TC WE NS WM Erosion Control Sediment Control Tracking Control Wind Erosion Control Non-Stormwater Management Control Waste Management and Materials Pollution Control Legend: Primary Objective

More information

APRIL 2015 CONTINGENCY PLANS

APRIL 2015 CONTINGENCY PLANS APRIL 2015 CONTINGENCY PLANS Prepared by: TERRATEST (PTY) LTD PO Box 794 HILTON Postal code 3245 Telephone:0333436789 Email:terratest@terratest.co.za Project director: Simon Johnson TABLE OF CONTENTS 1

More information

MT EDGECOMBE SOUTH RESIDENTIAL DEVELOPMENT (KINDLEWOOD): EIA/4667

MT EDGECOMBE SOUTH RESIDENTIAL DEVELOPMENT (KINDLEWOOD): EIA/4667 Moreland Developments (Pty) Ltd MT EDGECOMBE SOUTH RESIDENTIAL DEVELOPMENT (KINDLEWOOD): EIA/4667 FINAL ENVIRONMENTAL MANAGEMENT PLAN SiVEST Environmental Division 22 Pietermaritz Street, Pietermaritzburg,

More information

Building Better Storm Water Quality

Building Better Storm Water Quality Building Better Storm Water Quality s Storm Water Pollution Prevention Guidelines for Development Construction Projects City of El Segundo 350 Main Street (310) 524-2380 El Segundo, California 90245 Introduction

More information

Environmental Management System Integrated Pollution Control. Origination Date 1 st February Area: The Group

Environmental Management System Integrated Pollution Control. Origination Date 1 st February Area: The Group Environmental Management System Integrated Pollution Control Document No. 5.2.1 Version no. 1 Origination Date 1 st February 2017 Area: The Group Approval: Group Services & Facilities Last Revision Date

More information

1. Company Policies. 1.1 Project Control & Methodology Brief Methodology. Construction Program. Trade Budgets. Site Establishment Plan

1. Company Policies. 1.1 Project Control & Methodology Brief Methodology. Construction Program. Trade Budgets. Site Establishment Plan 1. Company Policies 1.1 Project Control & Methodology Upon award of any project a Contract Commencement and Handover Meeting is held internally where the project team is confirmed and a Project Plan is

More information

Papua New Guinea LNG Project. Environmental and Social Management Plan Appendix 11: Reinstatement Management Plan PGGP-EH-SPENV

Papua New Guinea LNG Project. Environmental and Social Management Plan Appendix 11: Reinstatement Management Plan PGGP-EH-SPENV Esso Highlands Limited Papua New Guinea LNG Project Environmental and Social Management Plan Appendix 11: PGGP-EH-SPENV-000018-013 LNG Project Page 2 of 13 CONTENTS 1.0 Objectives... 3 2.0 Legal and Other

More information

Dendrobium Mine. Waste Management Plan

Dendrobium Mine. Waste Management Plan Dendrobium Mine Waste Management Plan DOCUMENT SIGN OFF SHEET AND REVISION LOG Document Owner: Authorised by: Peter McMillan 25/06/2018 (Name) (Date) Peter McMillan 25/06/2018 (Name) (Date) VERSION HISTORY

More information

GENERAL NOTES ENGINEERS OVERSIGHT 1. ALL ELEVATIONS, DIMENSIONS, ALIGNMENTS AND ORIENTATION OF ALL ELEMENTS SHOWN IN THE PLANS MUST BE APPROVED BY THE ENGINEER OR ENGINEER'S REPRESENTATIVE ( REP ENGINEER

More information

BACKGROUND INFORMATION DOCUMENT:

BACKGROUND INFORMATION DOCUMENT: BACKGROUND INFORMATION DOCUMENT: APPLICATION FOR A MINING RIGHT MMAKAU COAL (PTY) LTD SCHURVEKOP 227 IS, BETHAL, MPUMALANGA 1. INTRODUCTION Mmakau Coal (Pty) Ltd intends to submit an application for a

More information

Abbot Point Stormwater Return Dam (EPBC 2010/5561) Operation Annual Compliance Report, January 2016

Abbot Point Stormwater Return Dam (EPBC 2010/5561) Operation Annual Compliance Report, January 2016 Abbot Point Stormwater Return Dam (EPBC 2010/5561) Operation Annual Compliance Report, 2015 22 January 2016 Table of Contents 1. Introduction... 4 1.1. The purpose of this Document... 4 1.2. Project Background...

More information

FRAMEWORK EMP (femp) FOR OPEN CYCLE GAS TURBINE POWER STATION AND ASSOCIATED INFRASTRUCTURE NEAR MOSSEL BAY

FRAMEWORK EMP (femp) FOR OPEN CYCLE GAS TURBINE POWER STATION AND ASSOCIATED INFRASTRUCTURE NEAR MOSSEL BAY FRAMEWORK EMP (femp) FOR OPEN CYCLE GAS TURBINE POWER STATION AND ASSOCIATED INFRASTRUCTURE NEAR MOSSEL BAY ACTIVITY ASPECT IMPACT MITIGATION MEASURE: 1. COMPLIANCE WITH ENVIRONMENTAL LEGISLATION All Activities

More information

ATTACHMENT C RISK LEVEL 1 REQUIREMENTS

ATTACHMENT C RISK LEVEL 1 REQUIREMENTS ATTACHMENT C RISK LEVEL 1 REQUIREMENTS A. Effluent Standards [These requirements are the same as those in the General Permit order.] 1. Narrative Risk Level 1 dischargers shall comply with the narrative

More information

SECTION STORMWATER POLLUTION PREVENTION

SECTION STORMWATER POLLUTION PREVENTION PART 1 - GENERAL 1.01 WORK INCLUDED SECTION 02133 STORMWATER POLLUTION PREVENTION A. Prohibit illicit discharge (non-rainwater) into the storm drain system. B. Construct any and all necessary systems to

More information

Ensuring that EMP s are a positive EIA legacy as the EAP s opportunity to facilitate sound project implementation.

Ensuring that EMP s are a positive EIA legacy as the EAP s opportunity to facilitate sound project implementation. Ensuring that EMP s are a positive EIA legacy as the EAP s opportunity to facilitate sound project implementation. Years of project implementation Implementation of international good practice Exposure

More information

10.0 Environmental protection, follow-up and monitoring

10.0 Environmental protection, follow-up and monitoring 10.0 Environmental protection, follow-up and monitoring 10.1 Introduction Manitoba Hydro will implement the mitigation measures, monitoring and other follow-up actions identified in chapter 8 through an

More information

ENVIRONMENT INDUCTION. Section 5

ENVIRONMENT INDUCTION. Section 5 ENVIRONMENT INDUCTION Section 5 1 Overview Environmental Legal Obligations Environment Policy Environmental Commitment InSitu Recovery (ISR) Mining Low Environmental Impact Monitoring and Reporting Environmental

More information

Project Information. Check all that are applicable to the construction project site: RIPDES CGP (construction) RIPDES RGP (dewatering)

Project Information. Check all that are applicable to the construction project site: RIPDES CGP (construction) RIPDES RGP (dewatering) Compliance Assistance Program Checklist 1 Start of Construction Stormwater Self-Certification Checklist Note: This checklist must be completed and submitted to the DEM no later than 30 days after initiating

More information

Environment Incident Identification & Response (Mining Areas)

Environment Incident Identification & Response (Mining Areas) Environment Incident Identification & Response (Mining Areas) Environment / Sustainability Toolbox Presentation Environment Management Series: EMS004 Key Information: Environment Incident Identification

More information

ENVIRONMENTAL AND OPERATIONAL MANAGEMENT PLAN

ENVIRONMENTAL AND OPERATIONAL MANAGEMENT PLAN Zitholele Consulting Reg. No. 2000/000392/07 PO Box 6002 Halfway House 1685 South Africa Thandanani Park, Matuka Close Halfway Gardens, Midrand Tel + (27) 011 207 2079 Fax + (27) 011 805-2100 E-mail :

More information

PROPOSED E/F SLAB EXPANSION, PORT OF RICHARDS BAY. Revised Environmental Management Programme. September 2013 Revised: 2015/09/30 Public

PROPOSED E/F SLAB EXPANSION, PORT OF RICHARDS BAY. Revised Environmental Management Programme. September 2013 Revised: 2015/09/30 Public Image Property of Transnet SOC Ltd PROPOSED E/F SLAB EXPANSION, PORT OF RICHARDS BAY Revised Environmental Management Programme September 2013 Revised: 2015/09/30 Public Quality Management Issue/revision

More information

Ziveli Property Developments

Ziveli Property Developments Drafted by : HOVEKA INC 3 rd FLOOR, WKH HOUSE, AUSSPANNPLATZ, WINDHOEK A SWANEPOEL/ Ziveli Property Developments ZIVELI LIFESTYLE VILLAGE BUILDERS CODE OF CONDUCT OF THE ZIVELI LIFESTYLE VILLAGE 2 Annexure

More information

Buffalo City Municipality. Potsdam Low-cost Housing Development East London

Buffalo City Municipality. Potsdam Low-cost Housing Development East London Buffalo City Municipality Potsdam Low-cost Housing Development East London Draft Environmental Management Programme J28058 February 2010 DEDEA Reference No: AR/7/F/2/5/08 POTSDAM LOW-COST HOUSING PROJECT

More information

EnviroLeg cc NATIONAL WATER Reg p 1

EnviroLeg cc NATIONAL WATER Reg p 1 EnviroLeg cc NATIONAL WATER Reg p 1 GN. 704 GG20119 4 June 1999 NATIONAL WATER ACT, 1998 (ACT NO. 36 OF 1998) REGULATIONS ON USE OF WATER FOR MINING AND RELATED ACTIVITIES AIMED AT THE PROTECTION OF WATER

More information

Port Botany Terminal Operational Environmental Management Plan Environmental Risk Assessment

Port Botany Terminal Operational Environmental Management Plan Environmental Risk Assessment Purpose To ensure that potential environmental impacts and risks at the Patrick Terminal Port Botany are identified so that appropriate control measures can be implemented in compliance with applicable

More information

4.0 ENVIRONMENTAL IMPACTS AND MITIGATION MEASURES. Negative or adverse impacts during the construction phase are:

4.0 ENVIRONMENTAL IMPACTS AND MITIGATION MEASURES. Negative or adverse impacts during the construction phase are: 4.0 ENVIRONMENTAL IMPACTS AND MITIGATION MEASURES 4.1 POTENTIAL ENVIRONMENTAL IMPACTS 4.1.1 Impacts during Construction Phase Negative or adverse impacts during the construction phase are: Land environment:

More information

Environment Management A TENANT INFORMATION HANDBOOK

Environment Management A TENANT INFORMATION HANDBOOK Environment Management A TENANT INFORMATION HANDBOOK 3 Avro Street Bankstown Airport NSW 2200 T 02 9796-2300 F 02 9791-0230 www.sydneymetroairport.com.au SYDNEY METRO AIRPORTS E N V I R O N M E N T M A

More information

MANAGING STORMWATER AND TRADE WASTEWATER

MANAGING STORMWATER AND TRADE WASTEWATER MANAGING STORMWATER AND TRADE WASTEWATER 02 Straightforward advice to help vehicle repairers get ahead in today s business environment WHAT DO YOU NEED TO KNOW ABOUT STORMWATER? Rain running off your business

More information

JBS Pollution Incident Response Management Plan

JBS Pollution Incident Response Management Plan JBS Pollution Incident Response Management Plan JBS Australia Pty Limited Prime City Feedlot, NSW Document Owner Troy White, Group Environment Manager Printed copies of this document are deemed uncontrolled

More information

AM-PR-003 Construction Environmental Management Plan (C-EMP)

AM-PR-003 Construction Environmental Management Plan (C-EMP) OMS Procedure AM-PR-003 Construction Environmental Management Plan (C-EMP) Revision: 1 Prepared by: Shannon Holroyd Authorised by: Marcus Manning Authorisation Date: 18th May 2015 This document has been

More information

Parking Area Maintenance

Parking Area Maintenance Description Parking lots can contribute a number of substances, such as trash, suspended solids, hydrocarbons, oil and grease, and heavy metals that can enter receiving waters through stormwater runoff

More information

Appendix 8. Petroleum Hydrocarbon Products, Ammonium Nitrate and Explosives Management Plan

Appendix 8. Petroleum Hydrocarbon Products, Ammonium Nitrate and Explosives Management Plan Appendix 8 Petroleum Hydrocarbon Products, Ammonium Nitrate and Explosives Management Plan Petroleum Hydrocarbon Products, Ammonium Nitrate, and Explosives Management Plan This Petroleum Hydrocarbon Products,

More information

14. Waste Management

14. Waste Management 14. Waste Management Contents 14. Waste 14-1 14.1. Introduction 14-1 14.2. Environmental Value 14-1 14.3. Waste Management Legislation 14-1 14.3.1. Waste Definition 14-1 14.3.2. National Pollutant Inventory

More information

Plaza and Sidewalk Cleaning

Plaza and Sidewalk Cleaning Objectives Cover Contain Educate Reduce/Minimize Product Substitution Description Pollutants on sidewalks and other pedestrian traffic areas and plazas are typically due to littering and vehicle use. This

More information

Performance Standards Compliance Checklist

Performance Standards Compliance Checklist Truckee Meadows Regional Stormwater Quality Management Program Performance Standards Compliance Checklist The checklist that follows identifies the BMPs that can be used at construction sites to meet each

More information

City of Waukegan, Illinois

City of Waukegan, Illinois City of Waukegan, Illinois NPDES Phase II Stormwater Program Stormwater Pollution Prevention Plan Public Works Facility July 2011 City of Waukegan, Illinois Stormwater Pollution Prevention Plan for the

More information

LAND DISTURBANCE PERMIT

LAND DISTURBANCE PERMIT SPRINGVILLE CITY Application Date: 110 South Main Springville, UT 84663 Permit Number: (801) 491-2780 Caselle #2208 Project Name: Project Address: LAND DISTURBANCE PERMIT Priority Site Owner s Name Phone

More information

Environmental Management Programme

Environmental Management Programme Environmental Impact Assessment of the Used Fuel Transient Interim Storage Facility at Koeberg Nuclear Power Station Environmental Management Programme Report Prepared for Order Reference Number: 4600057255

More information

GENERAL SPECIFICATION FOR ENVIRONMENTAL PROTECTION FOR CONSTRUCTION IN AND AROUND WATERBODIES AND ON WATERBODY BANKS

GENERAL SPECIFICATION FOR ENVIRONMENTAL PROTECTION FOR CONSTRUCTION IN AND AROUND WATERBODIES AND ON WATERBODY BANKS ONTARIO PROVINCIAL STANDARD SPECIFICATION METRIC OPSS.PROV 182 APRIL 2017 GENERAL SPECIFICATION FOR ENVIRONMENTAL PROTECTION FOR CONSTRUCTION IN AND AROUND WATERBODIES AND ON WATERBODY BANKS TABLE OF CONTENTS

More information

Kendal /Kusile to Zeus Environmental Monitoring Report

Kendal /Kusile to Zeus Environmental Monitoring Report MONTHLY ENVIRONMENTAL MONITORING REPORT Power Lines from Kendal/Kusile to Zeus Substation Bravo Integration Project Bravo 4: Construction of two 400 kv lines DEA Ref # 12/12/20/1095 Report Prepared for:

More information

Pollution Incident Response Management Plan

Pollution Incident Response Management Plan Pollution Incident Response Management Plan Gunnedah Quarry Products Pty Ltd Prepared by Tim MacKellar, Gunnedah Quarry Products Document created 13.10.13 Reviewed 10.10.14 Reviewed 12.10.15 Reviewed 02.02.18

More information

Concrete Waste Management

Concrete Waste Management Categories EC SE TC WE NS WM Erosion Control Sediment Control Tracking Control Wind Erosion Control Non-Stormwater Management Control Waste Management and Materials Pollution Control Legend: Primary Category

More information

Health & Safety Plan DEMOLITION WORKS: No 2 Substation

Health & Safety Plan DEMOLITION WORKS: No 2 Substation DEMOLITION WORKS: No 2 Substation Revision History Revision Date Section Detail of Amendment By r3a 09/10/14 First Issue JH 17 October 2014 Page 2 Revision 4 Contents 1. Description of Project 1.1. Introduction

More information

Annual CCR Fugitive Dust Report. TS Power Plant. Eureka County, Nevada

Annual CCR Fugitive Dust Report. TS Power Plant. Eureka County, Nevada Annual CCR Fugitive Dust Report TS Power Plant Eureka County, Nevada November 16, 2016 Prepared by: Dennis Laybourn Senior Environmental Manager Newmont Nevada Energy Investment - TS Power Plant 450 TS

More information

SUMMARY OF COMMENTS/RECOMMENDATIONS

SUMMARY OF COMMENTS/RECOMMENDATIONS SUMMARY OF COMMENTS/RECOMMENDATIONS PROPONENT: Boulet Brothers Concrete Ltd. PROPOSAL NAME: Ste. Agathe Concrete Batch Plant CLASS OF DEVELOPMENT: 1 TYPE OF DEVELOPMENT: Concrete Batch Plant CLIENT FILE

More information

PROPOSED INFILLING OF A NATURALISED WETLAND AND REALIGNMENT OF A CHANNEL ON ERVEN AND 52100, JOOSTENBERG VLAKTE, CAPE TOWN.

PROPOSED INFILLING OF A NATURALISED WETLAND AND REALIGNMENT OF A CHANNEL ON ERVEN AND 52100, JOOSTENBERG VLAKTE, CAPE TOWN. PROPOSED INFILLING OF A NATURALISED WETLAND AND REALIGNMENT OF A CHANNEL ON ERVEN 25099 AND 52100, JOOSTENBERG VLAKTE, CAPE TOWN. 1 st DRAFT ENVIRONMENTAL MANAGEMENT PROGRAMME (INCLUDING THE WASTE, WATER

More information

Environmental Management Plan

Environmental Management Plan Environmental Management Plan Site:.. Section 1 - Risk Assessment 1. Identify the environmental aspects relevant to your site. 2. Under notes, document the items that influence the assignment of the level

More information

Hydrocarbon Management PROCEDURE

Hydrocarbon Management PROCEDURE Hydrocarbon Management PROCEDURE Doc No: Approved: PRO-0380 Operations Manager Table of Contents 1. PURPOSE... 3 2. SCOPE... 3 3. REFERENCES... 3 3.1 LEGISLATION/STANDARDS... 3 4. DEFINITIONS... 3 5. HYDROCARBON

More information

HOLIDAY INN AIRPORT HOTEL

HOLIDAY INN AIRPORT HOTEL HOLIDAY INN AIRPORT HOTEL Plaine Magnien ENVIRONMENTAL IMPACT ASSESSMENT Chapter 6: Environment Monitoring Plan 6.1 Introduction Environment Monitoring Plan (EMP) plays a vital role in safeguarding the

More information

Papua New Guinea LNG Project. Environmental and Social Management Plan Appendix 6: Spill Prevention and Response Plan PGGP-EH-SPENV

Papua New Guinea LNG Project. Environmental and Social Management Plan Appendix 6: Spill Prevention and Response Plan PGGP-EH-SPENV Esso Highlands Limited Papua New Guinea LNG Project Environmental and Social Management Plan Appendix 6: Spill Prevention and Response Plan PGGP-EH-SPENV-000018-008 LNG Project Page 2 of 14 CONTENTS 1.0

More information

DIEMERSFONTEIN WINE & COUNTRY ESTATE BUILDING CONTRACTORS CODE OF CONDUCT

DIEMERSFONTEIN WINE & COUNTRY ESTATE BUILDING CONTRACTORS CODE OF CONDUCT DIEMERSFONTEIN WINE & COUNTRY ESTATE BUILDING CONTRACTORS CODE OF CONDUCT 1. CODE OF CONDUCT AGREEMENT The building contractor is a builder/contractor ( the contractor ) appointed by the owner ( the employer

More information