Tahmoor Colliery Longwalls 25 to 26

Size: px
Start display at page:

Download "Tahmoor Colliery Longwalls 25 to 26"

Transcription

1 Tahmoor Colliery Longwalls 25 to 26 SYDNEY WATER SEWER INFRASTRUCTURE SURFACE SAFETY AND SERVICEABILITY MANAGEMENT PLAN REVISION F Mine Subsidence Engineering Consultants Level Victoria Avenue Chatswood NSW 2067 PO Box 3047 Willoughby North NSW 2068 Tel. (02) Fax. (02) enquiries@minesubsidence.com September 2008

2

3 TABLE OF CONTENTS TABLE OF CONTENTS ii CHAPTER 1. INTRODUCTION Background Predicted Subsidence Movements Limitations Objectives Scope Proposed Mining Schedule Definition of Active Subsidence Zone 4 CHAPTER 2. RISK MANAGEMENT METHOD General Consequence Likelihood Hazard Risk 5 CHAPTER 3. RISK ASSESSMENT Sewage Disposal Infrastructure Hazard Identification Hazard 1 Damaged Joints and Pipes Hazard 2 Sewer Main Grades Reduced Below the Minimum for Self-Cleansing Hazard 3 Rising Mains Hazard 4 - Blockages or Overflows Hazard 5 - Sewage Pumping Station Hazard 6 - Power Line to the Sewage Pumping Station Hazard 7 - Concrete Encasements and Horizontal Bores Typical Concrete Encasements and Horizontal Bores mm Diameter Sewer Main between Huen Place and Castlereagh Street Hazard 8 Creek Crossings Investigations of Myrtle Creek Crossings after mining of Longwall 24B Summary of Risk Analysis for Sewer System Experience of mining Longwall 24A Potential Increased Subsidence during the mining of Longwall CHAPTER 4. RISK CONTROL PROCEDURES Sewer Management Group (SMG) Avoidance and Mitigation Measures Monitoring Plan 29 Mine Subsidence Engineering Consultants ii Tahmoor Colliery

4 Ground Monitoring Lines Visual Inspections Automated Continuous Tilt Monitoring Water Quality Monitoring Triggers and Responses 32 CHAPTER 5. SMG MEETINGS 38 CHAPTER 6. AUDIT AND REVIEW 38 CHAPTER 7. RECORD KEEPING 38 CHAPTER 8. CONTACT LIST 39 Appendix A - Glossary of Terms and Definitions 40 Appendix B Drawings and Illustrations 42 Appendix C Reports 43 Drawings Drawings referred to in this report are included in Appendix B at the end of the report. Drawing No. Description Rev MSEC Sewerage Infrastructure Pipe Size C MSEC Sewerage Infrastructure Pipe Type C MSEC Sewerage Infrastructure Pipes Less than Self-Cleansing Grade C MSEC Sewerage Infrastructure Pipes with Grades Less than MSB Requirements C MSEC Predicted Change in Sewer Grades after LW26 C MSEC Sewer Pipes with Grades Less than Self-Cleansing Grade after LW26 C MSEC Longwall 24A Sydney Water Monitoring Plan C Mine Subsidence Engineering Consultants iii Tahmoor Colliery

5 CHAPTER 1. INTRODUCTION 1.1. Background Tahmoor Colliery is located approximately 80 kilometres south west of Sydney in the township of Tahmoor NSW. It is managed and operated by Xstrata Coal. Tahmoor Colliery has previously mined 24 longwalls to the north and west of the mine s current location. Longwalls 25 to 26 are a continuation of a series of longwalls that extend into the Tahmoor North Lease area, which began with Longwall 22. The longwall panels are located between the Bargo River in the south-east, the township of Thirlmere in the west and Picton in the north. A portion of each longwall is located beneath the urban area of Tahmoor. Infrastructure owned by Sydney Water is located within these areas. It is noted that while changes in sewer grade have occurred as a result of mine subsidence, Longwalls 22 to 24A have directly mined beneath approximately 8.1 kilometres of sewer pipes and no noticeable impacts have been recorded so far. The observed frequency of incidences is similar to those in areas not affected by subsidence. This Management Plan provides detailed information about how the risks associated with the mining beneath sewer infrastructure will be managed by Tahmoor Colliery and Sydney Water. The Management Plan is a live document that can be amended at any stage of mining, to meet the changing needs of Tahmoor Colliery and Sydney Water Predicted Subsidence Movements A summary of the predicted maximum incremental parameters over the whole subsided area, due to the extraction of each longwall, is shown in Table 1.1. Table 1.1 Maximum Predicted Incremental Subsidence Parameters Subsidence Parameter LW 22 LW 23 LW 24 LW 25 LW 26 Vertical Subsidence (mm) Transverse Tilt (mm/m) Longitudinal Tilt (mm/m) Transverse Tensile Strain (mm/m) Longitudinal Tensile Strain (mm/m) Transverse Compressive Strain (mm/m) Longitudinal Compressive Strain (mm/m) Transverse Hogging Curvature (km -1 ) Longitudinal Hogging Curvature (km -1 ) Transverse Sagging Curvature (km -1 ) Longitudinal Sagging Curvature (km -1 ) The maximum predicted cumulative subsidence parameters, after the extraction of each longwall, are shown in Table 1.2. Mine Subsidence Engineering Consultants 1 Tahmoor Colliery

6 Table 1.2 Maximum Predicted Cumulative Subsidence Parameters Subsidence Parameter LW 22 LW 23 LW 24 LW 25 LW 26 Vertical Subsidence (mm) Transverse Tilt (mm/m) Longitudinal Tilt (mm/m) Transverse Tensile Strain (mm/m) Longitudinal Tensile Strain (mm/m) Transverse Compressive Strain (mm/m) Longitudinal Compressive Strain (mm/m) Transverse Hogging Curvature (km -1 ) Longitudinal Hogging Curvature (km -1 ) Transverse Sagging Curvature (km -1 ) Longitudinal Sagging Curvature (km -1 ) Limitations This Management Plan is based on the predictions of the effects of mining on surface infrastructure as provided in Report No. MSEC157 by Mine Subsidence Engineering Consultants. Predictions are based on the planned configuration of longwalls at Tahmoor Colliery (as shown in Drawing No. MSEC ), along with available geological information and data from numerous subsidence studies for longwalls previously mined in the area. Infrastructure considered in this Plan has been identified from aerial photographs, regional maps and from discussions between Tahmoor Colliery representatives and Sydney Water personnel. The impacts of mining on surface and sub-surface features have been assessed in detail. However, it is recognised that the prediction and assessment of subsidence can be relied upon only to a certain extent. The limitations of the prediction and assessment of mine subsidence are discussed in report MSEC157 by Mine Subsidence Engineering Consultants. As discussed in the report, there is a low probability that ground movements and their impacts could exceed the predictions and assessments. However, if these potentially higher impacts are considered prior to mining, they can be managed. This Surface Safety and Serviceability Management Plan will not necessarily prevent impacts from longwall mining, but will limit the impacts by establishing appropriate procedures that can be followed should evidence of increased impacts emerge Objectives The objectives of this Surface Safety and Serviceability Management Plan (SSSMP) are to establish procedures to measure, control, mitigate and repair potential impacts that might occur on surface infrastructure owned by Sydney Water. The objectives of the SSSMP have been developed to:- Ensure the safe and serviceable operation of all surface infrastructure. Public and workplace safety is paramount. Disruption and inconvenience should be kept to minimal levels. Monitor ground movements and the condition of surface infrastructure during mining. Initiate action to mitigate or remedy potential significant impacts that are expected to occur on the surface. Provide a plan of action in the event that the impacts of mine subsidence are greater than those that are predicted. Provide a forum to report, discuss and record impacts to the surface. This will involve Tahmoor Colliery, Sydney Water, Mine Subsidence Board, Department of Mineral Resources, and consultants as required. Establish lines of communication and emergency contacts. Mine Subsidence Engineering Consultants 2 Tahmoor Colliery

7 1.5. Scope The SSSMP is to be used to protect and monitor the condition of the items of infrastructure identified to be at risk due to mine subsidence. The major items at risk are:- Sewer Pumping Stations Gravity Sewer Systems Rising Mains The SSSMP only covers infrastructure that is located within the general application area, which defines the extent of land that may be affected by mine subsidence as a result of mining Longwalls 24 to 26. The management plan does not include other property owned by Sydney Water which lies outside the extent of the general application area. The Plan also applies to persons employed or engaged by Tahmoor Colliery requiring them to carry out activities described by this Plan. Impacts are considered in terms of mining directly affecting infrastructure, rather than the effects from loss of services Proposed Mining Schedule It is planned that each longwall will extract coal working northwest from the southeastern ends. This Management Plan covers longwall mining until completion of mining in Longwall 26 and for sufficient time thereafter to allow for completion of subsidence effects. The current schedule of mining is shown in Table 1.3. Table 1.3 Schedule of Mining Longwall Start Date Completion Date Longwall 25 August 2008 August 2009 Longwall 26 October 2009 October 2010 Mine Subsidence Engineering Consultants 3 Tahmoor Colliery

8 1.7. Definition of Active Subsidence Zone As a longwall progresses, subsidence begins to develop at a point in front of the longwall face and continues to develop after the longwall passes. The majority of subsidence movement typically occurs within an area 150 metres in front of the longwall face to an area 450 metres behind the longwall face. This is termed the active subsidence zone for the purposes of this SSSMP, where surface monitoring is generally conducted. The active subsidence zone for each longwall is defined by the area bounded by the predicted 20 mm subsidence contour for the active longwall and a distance of 150 metres in front and 450 metres behind the active longwall face, as shown by Fig Predicted 20mm Subsidence Contour LEGEND Active Longwall Weekly Inspection (450m Behind Longwall Face) Weekly Inspection (150m Ahead of Longwall Face) The Active Subsidence Zone shall be defined with reference to the extraction face position at the date of each survey/inspection. Fig. 1.1 Diagrammatic Representation of Active Subsidence Zone Mine Subsidence Engineering Consultants 4 Tahmoor Colliery

9 CHAPTER 2. RISK MANAGEMENT METHOD 2.1. General The Australian/New Zealand standard for Risk Management defines the terms used in the risk management process, which includes the identification, analysis, assessment, treatment and monitoring of risk. In this context: Consequence The outcome of an event expressed qualitatively or quantitatively, being a loss, injury, disadvantage or gain. There may be a range of possible outcomes associated with an event. 1 The consequences of a hazard are rated from very slight to very severe Likelihood Used as a qualitative description of probability or frequency. 2 The likelihood can range from very rare to almost certain Hazard A source of potential harm or a situation with a potential to cause loss Risk The chance of something happening that will have an impact upon objectives. It is measured in terms of consequences and likelihood. 4 The risk combines the likelihood of an impact occurring with the consequence of the impact occurring. The risk is rated from very low to extreme. In this study, the likelihood and consequence are combined via the qualitative risk analysis matrix shown in Table 2.1, to determine an estimated level of risk for particular events or situations. The Risk Analysis Matrix is similar to the example provided in AS/NZS 4360:1995, Appendix D, p.25. Table 2.1 Qualitative Risk Analysis Matrix LIKELIHOOD CONSEQUENCES Very Slight Slight Moderate Severe Very Severe Almost Certain Low Moderate High Extreme Extreme Likely Low Moderate High Very High Extreme Moderate Low Low Moderate High Very High Unlikely Very Low Low Moderate High High Rare Very Low Very Low Low Moderate High Very Rare Very Low Very Low Low Moderate Moderate This SSSMP adopts a common system of nomenclature to summarise each risk analysis, which is LIKELIHOOD / CONSEQUENCE LEVEL OF RISK. For example, if the likelihood of a risk is assessed as UNLIKELY, and the consequence of a risk is assessed as SEVERE, the risk analysis would be summarised as UNLIKELY / SEVERE HIGH. 1 AS/NZS 4360:1999 Risk Management pp2 2 AS/NZS 4360:1999 Risk Management pp2 3 AS/NZS 4360:1999 Risk Management pp2 4 AS/NZS 4360:1999 Risk Management pp3 Mine Subsidence Engineering Consultants 5 Tahmoor Colliery

10 CHAPTER 3. RISK ASSESSMENT The original risk assessment was conducted jointly by Sydney Water and Tahmoor Colliery in May The risks have been most recently reviewed jointly by Sydney Water and Tahmoor Colliery in September 2008 in light of experience gained during the mining of Longwalls 22 to 24A Sewage Disposal Infrastructure There are approximately 39 kilometres of sewer pipes within the SMP Area, which are owned by Sydney Water. The Picton Regional Sewerage Scheme collects sewage from the urban areas of Tahmoor and Thirlmere and transports it by gravity to the Picton Sewage Treatment Plant in Picton, which lies outside the SMP Area. The sewer pipes were installed in With the exception of the rising mains, all of the sewer pipes are designed at self-cleansing grades. The average grade of the sewer pipes within the SMP Area is approximately 32 mm/m. The design for the gravity sewer system was approved by the Mine Subsidence Board, on the condition that the sewers were installed at least 3 mm/m greater than the minimum grade required for the pipes to be self-cleansing. It has been found, on examination of information provided by Sydney Water, that some of the pipes may have been installed at grades less than self-cleansing, or installed at grades less than the Mine Subsidence Board requirements. The design for the rising mains are certified in accordance with the requirement of the Mine Subsidence Board, which specified maximum vertical subsidence of 750 mm, maximum tensile strain of 1.5 mm/m, maximum compressive strain of 2.5 mm/m and maximum curvature of 8 kilometres. The sewer pipes are constructed from PVC and have extra length sockets and rubber ring joints, which will allow them to accommodate tensile and compressive ground strains and curvature. The pipe sections are typically 3 metres long. The majority of the sewer mains are laid on sand and buried in trenches. A CCTV investigation of the pipeline was undertaken by Tahmoor Colliery in Milne Street, in consultation with Sydney Water and the Mine Subsidence Board prior to the development of subsidence movements during the extraction of Longwall 22. Sydney Water has reviewed the video and has stated that the existing pipe work is in fair to good condition. Minor ponding was observed, with minor undulation in the line. Occasional sections of pipe work were damaged or partially compressed. A blocked junction was also observed. A number of sections were observed to be unusually dirty. Sydney Water indicated that the issues found during the investigation were of a minor maintenance nature or due to the sewer not being cleaned correctly after the installation of the pipe work in The sewer pipelines within the SMP Area are shown according to their pipe sizes in Drawing No. MSEC It can be seen from this drawing that the sewer mains range in diameter between 100 mm and 375 mm. The larger sewer mains are located adjacent to the Main Southern Railway, York Street and between Remembrance Drive and Myrtle Creek. A summary of the total lengths of each diameter of sewer pipe is provided in Table 3.1. Mine Subsidence Engineering Consultants 6 Tahmoor Colliery

11 Table 3.1 Pipe Diameter (mm) Distribution of Sewer Pipes by Pipe Diameter Total Length within SMP Area (m) Total The pipes are also shown according to their type in Drawing No. MSEC The majority of pipes are sideline and reticulation pipes that transport sewage to the rising mains and carrier pipes. A summary of the total lengths of each type of pipe is provided in Table 3.2. Table 3.2 Distribution of Sewer Pipes by Pipe Type Pipe Type (mm) Total Length within SMP Area (m) Sideline Reticulation Rising Main Carrier Overflow Total It can be seen from the above table that the total length of self-cleansing gravity sewers is approximately 39 kilometres. The majority of the sideline and reticulation pipes are 100 mm and 150 mm in diameter, although some are 225 mm and 300 mm in diameter. The rising mains are 150 mm, 250 mm or 375 mm in diameter, and the carriers are 300 mm or 375 mm in diameter. There are two rising mains within the SMP Area. The sewage pumping station (Ref. SP0919) near the corner of George and Bronzewing Streets pumps sewage along George Street towards a local high point north of Thirlmere Way, as shown in Drawing No. MSEC The sewage pumping station (Ref. SP1045) on Castlereagh Street at Myrtle Creek pumps sewage to a high point at Park Street. Only one of the pumping stations (Ref. SP1045) is located within the SMP Area. It lies within the limit of subsidence and will be directly mined beneath by Longwall 25, as shown in Drawing No. MSEC There are two carrier pipes within the SMP Area. The Tahmoor carrier pipe transports the sewage from a point immediately south of Myrtle Creek near the Main Southern Railway, to a point immediately south of Myrtle Creek near Suffolk Place. The pipe first crosses underneath the Main Southern Railway and then travels along York Street and the banks of Myrtle Creek. The Thirlmere carrier pipe transports the sewage from the end of Windeyer Street towards Picton along Bridge Street. % % Mine Subsidence Engineering Consultants 7 Tahmoor Colliery

12 3.2. Hazard Identification Eight hazards have been identified that are associated with mine subsidence impacts on the sewer mains and associated infrastructure:- 1. The hazard that joints and pipes are damaged as a result of mining induced ground strains. 2. The hazard that sewer main grades are reduced below the minimum for self-cleansing as a result of transient or final mining induced ground tilts. 3. The hazard that rising mains are damages as a result of mining-induced ground strains. 4. The hazard that there are blockages or overflows to sewer. 5. The hazard that pumping station will be damaged. 6. The hazard that the power line to the pumping station is damaged. 7. The hazard that impacts may occur to concrete encased sewers or horizontal bores 8. The hazard that impact may occur to sewer creek crossing as a result of valley upsidence and closure. The likelihood and consequence of each hazard and the associated level of risk are discussed in the following sections Hazard 1 Damaged Joints and Pipes The joints between each section of pipe consist of an extra length socket with a rubber ring joint. The joints have been designed to accommodate tensile and compressive ground strains, as well as ground curvatures. Given that the sewer pipes are typically 3 metres long, it is unlikely that the sewer pipes will be damaged as a result of mine subsidence. Any ground movements along the pipes are likely to be transferred to the pipe joints. The maximum predicted strain of 1.8 mm/m will result in movements of up to 5.4 mm at the joints, if the strain is applied along the full length of a 3 metre pipe. In reality, the peak strain is localised and the differential movement will be taken up by a number of joints, reducing the maximum movement at the joints. It is also unlikely that all of the ground strains will transfer into the pipes as the sand bedding will allow the pipes to slide as the ground moves beneath them. The maximum predicted ground curvature of 8.3 kilometres will result in a lateral deviation at the joints of less than 0.2 mm for a 450 mm diameter pipe. Standard rubber ringed joints in PVC pipes can typically tolerate a longitudinal movement of up to 20 mm and an angular deviation of up to 1 o without experiencing adverse impacts. If the sewer has been constructed with extra length sockets, the joints are likely to tolerate a longitudinal movement of up to 40 mm and an angular deviation of up to 3 o without experiencing adverse impacts. The ability of the pipe joints to withstand subsidence impacts will depend on how they were installed. If the pipe sections are not correctly joined at mid-socket length, or have been laid with angular deviations, the maximum allowable movement at the joints will be reduced. It is considered likely, however, that some tolerance will be available at the pipe joints. The CCTV investigation along Milne Street indicated that the majority of pipe joints had been installed correctly. It is therefore concluded that it is unlikely that the pipe joints will be broken by systematic mine subsidence movements. Non-systematic localised ground strains and curvatures higher than predicted can occur where compressive ground strains cause the underlying strata to buckle. It is noted that no impacts have been observed above Longwalls 22 to 24A, even though non-systematic movements have developed near sewer pipes. Based on the experiences gained to date, the likelihood of joints being damaged along correctly installed straight lengths of pipe can be considered UNLIKELY. The joints in sections of the sewer main that are not correctly installed or joints along curved sections of main or joints located where non-systematic ground movements are considered more likely to be damaged. As the peak predicted ground movements Mine Subsidence Engineering Consultants 8 Tahmoor Colliery

13 are localised and likely to be shared across adjacent joints, the likelihood of damage to these joints can also be considered UNLIKELY. The result of damaged joints is the leakage of sewage into the surrounding area. The leaked sewage can be readily cleaned up and damaged joints can be repaired at a relatively low financial cost. This includes the sewer pipes within the rail corridor. The consequence can therefore be considered SLIGHT. The general level of risk can therefore be considered UNLIKELY / SLIGHT --> LOW. If sewage leaks into a watercourse, however, the EPA may impose significant fines on Sydney Water. The consequence can therefore be considered MODERATE. The level of risk for pipes near watercourses can therefore be considered UNLIKELY / MODERATE -- > MODERATE Hazard 2 Sewer Main Grades Reduced Below the Minimum for Self-Cleansing There are approximately 38 kilometres of self-cleansing gravity sewers within the SMP Area. The pipes ability to self-cleanse is dependent on their gradients, which vary depending on the diameter of the pipe. The minimum grades for self cleansing are provided in the Picton Regional Sewerage Scheme Design and Construction Plan (Issue A, Rev. 1), and are shown in Table 3.3. The design for the sewer system was approved by the Mine Subsidence Board, on the condition that the sewers were installed at least 3 mm/m (0.3%) greater than the minimum grade required for the pipes to be self-cleansing, which are also shown in Table 3.3. The grades of each section of pipe were provided in GIS format by Sydney Water, which divided the sewer network into 1511 pipe sections within the SMP Area. It is noted that 3031 metres (8%) of sewer pipes did not have any recorded grades in the GIS. All of these pipes are, however, small in diameter (100 mm or 150 mm) and short in length, with an average length of approximately 5 metres. Upon examination of this information, it was found that the majority of these pipe sections have been installed to grades greater than those required for self-cleansing or the MSB requirements. The average grade of all pipe sections within the SMP Area was approximately 3.2%, or 32 mm/m. However, approximately 353 metres of 100 diameter pipes have existing grades that are less than the minimum grade for self-cleansing, and these are shown in Drawing No. MSEC It was also found that approximately 1,503 metres of pipe have grades that are less than the minimum grades to comply with MSB requirements, and these are shown in Drawing No. MSEC It is presumed that it was impractical for these pipe sections to be installed at steeper grades due to the topography of the area. Mine Subsidence Engineering Consultants 9 Tahmoor Colliery

14 A summary of pipes with pre-mining grades less than self-cleansing grade or not complying with MSB requirements is provided in Table 3.3. Table 3.3 Sewers with Pre-Mining Grades less than Self-Cleansing Grade or MSB Requirements Pipe Diameter Minimum Grade for Self- Cleansing (%) Minimum Grade to comply with MSB Requirements (%) Total Length of Pipes less than Self- Cleansing Grade prior to mining (m) Total Length of Pipes with Grades that do not comply with MSB Requirements (m) Total Each pipeline section consists of two end node points and some also contain some intermediate node points. Predictions of subsidence were made at each node point along each pipeline section within the sewerage network and mining-induced tilts were calculated between each connecting node. The worst tilt between nodes along each pipeline section was used for future analyses. It was also possible to calculate the grades of each pipe section after each stage of mining as the direction of flow could be determined from the GIS information Drawing No. MSEC illustrates which pipe sections within the SMP Area are predicted to experience a change in grade after extraction of Longwalls 22 to 26. Any tilts predicted to be less than 0.5 mm/m (0.05%) were considered as being a negligible change in grade for the purposes of the analysis. A summary of pipes with changes in grade due to mining each longwall is provided in Table 3.4. Table 3.4 Summary of Predicted Change in Grade of Sewers due to Mining Stage of Mining After LW 22 After LW 23 After LW 24 After LW 25 After LW 26 Total Length of Pipes with Decrease in Grade greater than 0.05% (m) 1,327 (3.5%) 3,897 (10.2%) 8,068 (21.2%) 11,412 (30.0%) 13,472 (35.4%) Total Length of Pipes with Increase in Grade greater than 0.05% (m) 776 (2.0%) 1,132 (3.0%) 3,474 (9.1%) 4,971 (13.0%) 6,226 (16.4%) Total Length of Pipes with change in Grade of less than 0.05% It can be seen from the above table that approximately twice as many sewer pipes are predicted to experience a decrease in grade than an increase in grade after each stage of mining. This result can be explained by the design of the sewers in relation to the longwall layout. The majority of sewers in Tahmoor flow towards the rising mains and carrier pipes, which are located along George St, which is not being directly undermined by the proposed longwalls. This means that the majority of sewers will be flowing from areas of maximum subsidence to an area of less subsidence, which will decrease the grades in the pipes. Mine Subsidence Engineering Consultants 10 Tahmoor Colliery (m) 35,976 (94.5%) 33,050 (86.80%) 26,537 (69.7%) 21,695 (57.0%) 18,380 (48.2%)

15 While the above predictions indicate that 35.4% of sewers within the SMP Area will experience a reduction in grade, only a small percentage of sewers will have grades less than those required for selfcleansing after mining. A summary of pipes with grades less than self-cleansing grade after Longwall 26 is provided in Table 3.5, and these are shown in Drawing No. MSEC The calculations did not include pipeline sections with no reported grades in the GIS information. Table 3.5 Sewers with Predicted Grades less than Self-Cleansing Grade Pipe Diameter Minimum Grade for Self- Cleansing (%) Total Length of Pipes less than Self-Cleansing Grade Initial (m) LW 22 (m) LW 23 (m) LW 24 (m) LW 25 (m) LW 26 (m) Total It can be seen from the above table that 674 metres of sewers are predicted to have grades less than those required for self-cleansing, which represents 1.8% of the total length of sewers within the SMP Area. This result is relatively small given that 353 metres of sewers have grades less than self-cleansing prior to mining, and 1,503 metres of sewers have grades that do not comply with MSB requirements. It is noted, however, that some MSB compliant sewers are predicted to have grades less than self-cleansing after the extraction of Longwall 26. It is further noted that no sewer pipes are predicted to experience reverse grades due to the extraction of the proposed longwalls. It can be seen from Drawing No. MSEC that the pipeline sections predicted to have grades less than self-cleansing are spread over the SMP Area and are relatively short in length. The longest section of sewer affected is approximately 59 metres long. The risk associated with sewers that have grades less than self-cleansing is that a blockage may develop in the pipes over time. This risk can be reduced by periodic cleaning of the sewer, which incurs an increase in the cost of maintenance of the system, by re-laying the pipes to higher grades, which may not be practically possible due to the topography of the land. It is noted, however, that the frequency of incidences above the previously extracted Longwalls 22 and 23A are similar to areas that have not been affected by mine subsidence. If the predicted tilts were to be exceeded by 25% to 500%, the number of potentially affected sewers would increase. The remedial measures would be similar, except that monitoring of sewer pipe levels would be required over a more extensive area. Mine Subsidence Engineering Consultants 11 Tahmoor Colliery

16 A summary of the predicted number of sewers affected if the predictions were exceeded are shown in Table 3.6. Table 3.6 Total Length of Sewers if Predictions exceeded Increased Prediction Total Length of Pipes less than Self- Cleansing Grade after LW 26 (m) Predictions x Predictions x Predictions x Predictions x Predictions x Predictions x The above information has been used to develop the risk assessment below. The majority of sections of sewer main that have a pre-mining grade less than the minimum for selfcleansing also have a predicted grade less than the minimum grade for self-cleansing after mining. The likelihood of these sections of sewer having a grade less than the minimum for self-cleansing can therefore be considered ALMOST CERTAIN. There are some sections of sewer main which have pre-mining grades that are greater than the minimum required for self-cleansing but are predicted to have grades less than the minimum for self-cleansing, during or after mining. The likelihood of these pipes having a grade less than the minimum for selfcleansing can therefore be considered LIKELY. The majority of sewer mains have pre-mining grades that are greater than the minimum required for selfcleansing and are predicted to have grades greater than the minimum for self-cleansing during and after mining. The likelihood of these pipes having a grade less than the minimum for self-cleansing can therefore be considered UNLIKELY, but not rare, as it possible that the predictions could be exceeded. The result of a sewer main having a grade less than the minimum required for self-cleansing is the increased likelihood of blockage in the sewer. The consequence of a blockage is dependant on the number of properties that are affected, the cost to remove the blockage and, if required, the cost to repair the main. The consequence is therefore dependent on the size of sewer main and has been summarised in Table 3.7. Table 3.7 Consequence of a Sewer Main Grade Being Less than the Minimum for Self-Cleansing Pipe Diameter (mm) Minimum Number of Properties Affected Consequence Consequence if near a watercourse SLIGHT MODERATE SLIGHT MODERATE SLIGHT MODERATE MODERATE SEVERE 375 Carrier Pipe almost whole town SEVERE SEVERE Mine Subsidence Engineering Consultants 12 Tahmoor Colliery

17 The levels of risk associated with the grade of a sewer main being less than the minimum required for self-cleansing due to the extraction of Longwalls 24 to 26 are summarised in the table below. Table 3.8 Levels of Risk Associated with the Grade of a Sewer Main Being Less than the Minimum for Self-Cleansing due to the Extraction of Longwalls 24 to 26 Pipe Grade Pipe Diameter (mm) Sections of Pipe with a 100 Grade Less than the Minimum for Self- Cleansing Before Mining 150 Sections of Pipe with a Grade Less than the Minimum Grade for Self-Cleansing During or After Mining only Sections of Pipe with a Grade Greater than the Minimum Grade for Self-Cleansing, before, during or after mining Level of Risk ALMOST CERTAIN / SLIGHT MODERATE ALMOST CERTAIN / SLIGHT MODERATE LIKELY / SLIGHT MODERATE LIKELY / SLIGHT MODERATE UNLIKELY / SLIGHT VERY LOW UNLIKELY / SLIGHT VERY LOW UNLIKELY / SLIGHT VERY LOW UNLIKELY / MODERATE LOW UNLIKELY / SEVERE MODERATE Level of Risk (Near a Watercourse) ALMOST CERTAIN / MODERATE HIGH ALMOST CERTAIN / MODERATE HIGH LIKELY / MODERATE HIGH LIKELY / MODERATE HIGH RARE / MODERATE LOW RARE / MODERATE LOW RARE / MODERATE LOW RARE / SEVERE MODERATE RARE / SEVERE MODERATE The likelihood of any adverse impacts for sewer pipes located outside the predicted 20 mm subsidence contour have been assessed as LESS THAN VERY RARE. A risk analysis has therefore not been made for these pipes. It can be seen from the above table that the sewer pipes with an assessed level of risk of moderate or high include the following pipes:- All sewers identified on Drawing No. MSEC All carrier sewers (300 mm diameter pipe under Main Southern Railway and all 375 mm diameter pipes) within the predicted 20 mm subsidence contour on Drawings Nos. MSEC and MSEC It is noted that the above risk assessment is based upon standard subsidence predictions, which were provided in the SMP Report No. MSEC157. Following the mining of Longwalls 22 to 24A, no pipes have experienced reverse grades as predicted. However, subsidence and tilts have substantially exceeded predictions above Longwall 24A and this may also be observed above Longwall 25. This is discussed in further detail in Section 3.12 and Section Mine Subsidence Engineering Consultants 13 Tahmoor Colliery

18 3.5. Hazard 3 Rising Mains There are approximately 950 metres of rising mains within the SMP Area. There are two rising mains within the predicted limit of subsidence. The George Street rising main is not directly mined beneath by the proposed longwalls, while the Castlereagh Street rising main will be directly mined beneath by Longwall 25. The predicted subsidence and mining-induced tilts are expected to have little impact on the serviceability of the rising mains. The George Street rising main begins at Sewage Pumping Station SP0919, outside the predicted limit of subsidence and finishes north of Thirlmere Way within the predicted limit of subsidence. The head difference between the pumping station and the end of the rising main is predicted to reduce by approximately 180 mm, which should improve the serviceability of the main. The Castlereagh Street rising main runs above Longwall 25 and the head difference between the pumping station and the end of the rising main is predicted to be less than 20 mm, which is negligible and unlikely to affect the serviceability of the main. While ground strains along the rising mains have not been predicted, it is noted that the maximum predicted strains within the subsidence bowl due to the proposed longwalls are 1.4 mm/m tensile and 1.8 mm/m compressive. These predicted strains are less than the design requirements of the Mine Subsidence Board, which were 1.5 mm/m tensile and 2.5 mm/m compressive. The minimum predicted radius of curvature within the subsidence bowl is approximately 8.3 kilometres, which is greater than design requirements of the Mine Subsidence Board. The designer of the rising mains has certified that the designs for the rising main are in accordance with the Mine Subsidence Board s requirements. Non-systematic movements may occur in the vicinity of rising mains, and these movements may result in impacts to the rising main, particularly the rising main along Castlereagh Street above Longwall 25, which is approximately 200 metres long. Non-systematic movements have been observed above Longwalls 22 to 24A and no impacts have been observed to sewer pipes. Furthermore, longwalls have mined directly beneath 960 metres of DICL and 2700 metres of older CICL pressured water mains and impacts have been observed to one CICL pipe to date. It is considered therefore, that the likelihood of impacts occurring to the rising main pipes is RARE. The result of leakage of a rising main is leakage of sewage into the surrounding area, stoppage of the pumping station, and build-up of sewage at the pumping station, which backs onto Myrtle Creek. The rising main contains a number of automated alarms that immediately alert Sydney Water in the event of a fault occurring. The pumping station at Castlereagh Street has a 4 hour capacity to store sewage before any overflows into Myrtle Creek. If the length of time to repair the leakage exceeds four hours, it is possible that sewage may pollute Myrtle Creek. The consequence can therefore be considered MODERATE. The level of risk can therefore be considered RARE / MODERATE --> LOW Hazard 4 - Blockages or Overflows Blockages or overflows can occur outside mine subsidence areas due to the condition of the sewer main. It is possible that blockages or overflows could occur during mine subsidence events. While these blockages and/ or overflows may not be due to mine subsidence it is important for Sydney Water and Tahmoor Colliery to manage these issues together, to reduce the impacts. A CCTV investigation of Milne Street indicated that minor ponding, and one blockage at a drop junction had occurred prior to mining. Some debris was also found in the pipe network. Due to the condition of the pipes in Milne Street, the likelihood of blockages or overflows occurring is therefore considered UNLIKELY. The result of a blockage or overflow is leakage of sewage into the surrounding area. The leaked sewage can be readily cleaned up and damaged joints can be repaired at a relatively low financial cost. The level of risk can therefore be considered UNLIKELY/ SLIGHT --> LOW. If sewage leaks into a watercourse, however, the EPA may impose significant fines on Sydney Water. The consequence can therefore be considered MODERATE. The level of risk near watercourses can therefore be considered UNLIKELY / MODERATE --> MODERATE. Mine Subsidence Engineering Consultants 14 Tahmoor Colliery

19 3.7. Hazard 5 - Sewage Pumping Station There is one sewage pumping station within the SMP Area, Station SP1045 on Castlereagh Street, and it is located within the predicted limit of subsidence. The maximum predicted subsidence at this pumping station is approximately 735 mm after the extraction of Longwall 26. The predicted systematic mining-induced tilts at the station are 3.7 mm/m (0.37%) after the extraction of Longwall 26. The maximum predicted systematic strains at the station are 0.3 mm/m tensile and 0.3 mm/m compressive. It is considered that the pumping station is unlikely to be adversely impacted if normal systematic subsidence movement occurs. However, it is possible that non-systematic movements may adversely impact the station structures. Pumping station SP1045 is located close to Myrtle Creek, where upsidence and closure movements will occur. In particular, it is considered that the backfilled and buried 8 metre deep chamber may experience impacts if it is subjected to bending in the vertical plane or ground compression. However, this chamber has been constructed with reinforced concrete and occupies a small footprint of 3 metres in diameter. A structural analysis suggests that cracking to the chamber may develop if curvatures exceed 1.1 x 10-6 mm -1, which equates to a radius of curvature of approximately 900 metres (JMA, 2008). This curvature is substantial compared to normal observed mining-induced curvatures. Furthermore, the tank is partially protected from ground curvature by 100 mm thick polystyrene foam, which has been placed between the external concrete faces and the excavated foundations. The likelihood of impacts occurring to Pumping station SP1045 is therefore considered VERY RARE. The pumping station contains a number of automated alarms that immediately alert Sydney Water in the event of a mechanical or electrical fault occurring to the station. The pumping station has a 4 hour capacity to store sewage before any overflows into Myrtle Creek. If the length of time to repair the fault exceeds four hours, it is possible that sewage may pollute Myrtle Creek. Sydney Water has developed robust contingency plans to respond and address failure modes. The consequence of mechanical or electrical failure can therefore be considered MODERATE. If cracking develops within the chamber, the consequence depends on the depth of the crack. Normal operating depth is the bottom 1 metre of the chamber. A possible failure point is the structural joint, which is located above the normal operating depth. If cracking occurs, the pumping rate can be increased to reduce the depth of sewage in the chamber. The cracks can also be repaired by patching. Horizontal struts can also be installed across the chamber if required (JMA, 2008). The consequence of cracking can therefore be considered MODERATE. The level of risk can therefore be considered VERY RARE / MODERATE --> LOW. Given limited access to the chamber, automated continuous tilt monitoring of the chamber to measure deflection and visual inspections (if required) has been included as part of this management plan. Trigger levels have been set following recommendations from structural engineer John Matheson & Associates (2008) Hazard 6 - Power Line to the Sewage Pumping Station The sewage pumping stations are connected via buried cables to the Integral Energy overhead reticulation network. The maximum predicted ground strains within the subsidence bowl due to the proposed longwalls are 1.4 mm/m tensile and 1.8 mm/m compressive. Standard copper power lines can typically tolerate strains up to 20 mm/m without damage. No impacts have been observed to power lines during the mining of Longwalls 22 to 24A. It is unlikely, therefore, that power supply to the pumping stations will be disrupted due to mine subsidence impacts. The likelihood of the power line being damaged by systematic mining impacts can therefore be considered RARE. The pumping station contains a number of automated alarms that immediately alert Sydney Water in the event of a fault occurring. The pumping station has a 4 hour capacity to store sewage before any Mine Subsidence Engineering Consultants 15 Tahmoor Colliery

20 overflows into Myrtle Creek. If the length of time to repair the fault exceeds four hours, it is possible that sewage may pollute Myrtle Creek. The consequence can therefore be considered MODERATE. The level of risk associated with a damaged power line to the pumping station can therefore be considered RARE / MODERATE --> LOW Hazard 7 - Concrete Encasements and Horizontal Bores Typical Concrete Encasements and Horizontal Bores There are some sewer pipes within the SMP Area that have been concrete encased. These encasements are typically found across driveways and structures. Concrete encased sewers are more vulnerable to mine subsidence impacts when compared to normal sewers as the pipe joints are unable to slide in response to ground strains. If the encasements are long and subjected to large ground strains, there would be a risk of sewer breakage at the joint or within the pipe. In this case, the majority of concrete encasements do not appear to be very long and the predicted ground strains are relatively low. It is therefore unlikely that concrete encased sewers will be adversely impacted by mine subsidence except for the 66m section described in section There are, however, a number of concrete encasements that cross creeks and watercourses and these are discussed in the next section. There are some horizontal bores within the SMP Area. These are typically found across roads and railways. Horizontal bores are more vulnerable to mine subsidence impacts when compared to normal sewers as there are fewer pipe joints to accommodate the mining-induced ground strains. In this case, the majority of horizontal bores do not appear to be very long and the predicted ground strains are relatively low. It is therefore unlikely that horizontal bores will be adversely impacted by mine subsidence except for the bores described in section The likelihood of a typical short length concrete encased pipe or horizontal bore being damaged by systematic mining impacts can therefore be considered RARE. If an impact occurs, the time taken to repair a leak is greater than for other pipes as access to the leakage point is more difficult. The consequence of an impact is therefore assessed as SLIGHT for small concrete encased sewer pipes (100 and 150 mm diameter) and MODERATE for larger horizontal bores, such as those under roads and the Main Southern Railway. The level of risk associated with concrete encased pipes and horizontal bores can therefore be considered RARE / SLIGHT --> LOW for small pipes and RARE / MODERATE --> LOW for large pipes mm Diameter Sewer Main between Huen Place and Castlereagh Street There is a 225 mm diameter sewer main that includes some long sections of concrete encased mains or horizontal bores. The main begins at the rear of a property on Huen Place and finishes at the Sewage Pumping Station on Castlereagh Street (SP 1045). A plan of the sewer main is shown in Fig Mine Subsidence Engineering Consultants 16 Tahmoor Colliery

21 225 MM DIA SEWER MAINS Standard Spigot & Socket Horizontal Bore Concrete Encased Sewer Creek Crossing BRIDGE ST Myrtle Creek MILNE ST HUEN PL PARK ST WINPARA CL FRASER ST PIMELIA ST ELPHIN ST MONICA PL LEIHA PL LW No.25 AMBLECOTE PL CASTLEREAGH ST HILTON PARK RD CONNOR PL SP1045 MAIN SOUTHERN RWY Fig mm dia Sewer Main between Huen Place and Castlereagh Street As shown by the above plan, there are two sections of horizontal bore. One section is approximately 43 metres long, located near the end of Elphin Street. One section is approximately 235 metres long and includes a pit which connects the main with a 100 mm dia pipe. There are three sections of concrete encased sewer. One section is approximately 8 metres long and crosses Myrtle Creek near the end of Huen Pl. One section is approximately 12 metres long and crosses Myrtle Creek at Bridge Street. One section is approximately 66 metres long and connects the two sections of horizontal bore. A long section plot is shown in Fig. 3.3, which is based on the Sydney Water Work-As-Executed plans (Ref. 3) for Tahmoor Area 6 and 7, and surface contours provided by the Department of Lands. Predictions of subsidence, change in grade and strain have been made along the entire length of the 225 mm dia sewer main at the completion of each longwall, and these are shown in Fig It can be seen from this graph that the predicted profiles appear irregular in shape, which is explained by the many changes in direction along the sewer main, relative to the longwall layouts. The sewer main is also expected to experience valley closure and upsidence movements as it crosses Myrtle Creek (which is discussed in Section 3.10) and differential horizontal movements due to valley closure as the main runs alongside the banks of Myrtle Creek. In the case of the horizontal bores, it is predicted that the bores will experience up to 900 mm of subsidence, with a maximum decrease in grade of approximately 0.35 % following the extraction of Longwall 25. This decrease in grade is expected to reduce to approximately 0.25 % following the extraction of Longwall 26. The predicted maximum strains are approximately 0.50 mm/m tensile and 0.75 mm/m compressive. In addition to these predictions, the bores will experience some transient tilts and strains as Longwall 25 passes beneath them. The predicted travelling tilts are expected to generally increase the gradients of the pipes as the longwall is travelling in a southeast to northwest direction. The maximum travelling strains are expected to be less than 0.5 mm/m as the bores are oriented in a direction that is approximately 45 degrees to the longwall panel. It is also possible that the bore will be subjected to differential horizontal movements as a result of valley closure, as it is located alongside Myrtle Creek. It is expected, however, that these movements will be Mine Subsidence Engineering Consultants 17 Tahmoor Colliery

Tahmoor Colliery Longwalls 27 to 30

Tahmoor Colliery Longwalls 27 to 30 REPORT: RAIL TRANSPORT MUSEUM MANAGEMENT PLAN XSTRATA COAL: Tahmoor Colliery Longwalls 27 to 30 Management Plan for Potential Impacts to the Picton-Mittagong Loop Line MSEC MARCH 2013 REPORT NUMBER: MSEC567-08

More information

TAHMOOR COLLIERY LONGWALL 24B

TAHMOOR COLLIERY LONGWALL 24B TAHMOOR COLLIERY LONGWALL 24B END OF PANEL SUBSIDENCE MONITORING REPORT FOR LONGWALL 24B AT TAHMOOR COLLIERY Level, 228 Victoria Avenue - Chatswood NSW 23 PO Box 347 Willoughby North NSW 268 Tel. (2) 943

More information

Tahmoor Colliery - Longwalls 28 to 30

Tahmoor Colliery - Longwalls 28 to 30 REPORT: BUILT STRUCTURES MANAGEMENT PLAN GLENCORE: Tahmoor Colliery - Longwalls 28 to 30 Management Plan for Potential Impacts to Built Structures MSEC MARCH 2014 REPORT NUMBER: MSEC646-12 REVISION A AUTHORISATION

More information

Tahmoor Coking Coal Operations - Longwall 32

Tahmoor Coking Coal Operations - Longwall 32 REPORT: ENDEAVOUR ENERGY SUBSIDENCE MANAGEMENT PLAN SIMEC Mining: Tahmoor Coking Coal Operations - Longwall 32 Management Plan for Potential Impacts to Endeavour Energy Infrastructure MSEC AUGUST 2018

More information

Introduction to Longwall Mining and Subsidence

Introduction to Longwall Mining and Subsidence Introduction to Longwall Mining and Subsidence Prepared by Mine Subsidence Engineering Consultants Level 1 / 228 Victoria Avenue Chatswood NSW 2067 PO Box 3047 Willoughby North NSW 2068 Tel. (02) 9413

More information

TAHMOOR COLLIERY LONGWALL 24A

TAHMOOR COLLIERY LONGWALL 24A TAHMOOR COLLIERY LONGWALL 4A END OF PANEL SUBSIDENCE MONITORING REPORT FOR LONGWALL 4A AT TAHMOOR COLLIERY Mine Subsidence Engineering Consultants Level 1, 8 Victoria Avenue - Chatswood NSW 13 PO Box 347

More information

APPENDIX 11. Subsidence Assessment (MSEC)

APPENDIX 11. Subsidence Assessment (MSEC) APPENDIX 11 Subsidence Assessment (MSEC) Austar Coal Mine Pty Limited REPORT on THE PREDICTION OF SUBSIDENCE PARAMETERS AND THE ASSESSMENT OF MINE SUBSIDENCE IMPACTS ON NATURAL FEATURES AND SURFACE INFRASTRUCTURE

More information

Concrete Pipe Jacking

Concrete Pipe Jacking Concrete Pipe Jacking Technical Brief CPAA Introduction Concrete pipe jacking is a method of installing pipelines without disrupting existing surface facilities or activities. Pipe jacking has been used

More information

Subsidence Monitoring Program

Subsidence Monitoring Program Subsidence Monitoring Program West Wallsend Colliery Page 1 of 27 Contents West Wallsend Colliery 1.Introduction... 3 1.1 Background... 3 1.2 Purpose and Scope... 3 1.3 Relationship with Other Documents...

More information

METROPOLITAN COAL LONGWALLS BUILT FEATURES MANAGEMENT PLAN SYDNEY WATER

METROPOLITAN COAL LONGWALLS BUILT FEATURES MANAGEMENT PLAN SYDNEY WATER METROPOLITAN COAL METROPOLITAN COAL LONGWALLS 301-303 BUILT FEATURES MANAGEMENT PLAN SYDNEY WATER Revision Status Register Section/Page/ Annexure All Table 3, Section 8 and Figure 4 Revision Number Amendment/Addition

More information

Design Checklist for Water and Sewer for Extensions and Subdivisions

Design Checklist for Water and Sewer for Extensions and Subdivisions Design Checklist for Water and Sewer for Extensions and Subdivisions The proponent s hydraulic engineer/designer is required to complete this checklist and submit to Services Development, when submitting

More information

SPECIFICATION FOR PIPE CULVERT CONSTRUCTION

SPECIFICATION FOR PIPE CULVERT CONSTRUCTION SPECIFICATION FOR PIPE CULVERT CONSTRUCTION 1. SCOPE Pipe culverts shall be constructed in accordance with this specification and in conformity with the lines, levels and cross-sections shown on the drawings.

More information

Concrete Pipe Jacking

Concrete Pipe Jacking Concrete Pipe Jacking Concrete Pipe Association of Australasia ACN 007 067 656 TECHNICAL BULLETIN CONTENTS ABSTRACT 1 INTRODUCTION 2 METHOD OF INSTALLATION 3 CONCRETE PIPE DESIGN 4 CONCRETE PIPE JOINT

More information

Mine Subsidence Damage to Building Structures

Mine Subsidence Damage to Building Structures Mine Subsidence Damage to Building Structures Prepared by Mine Subsidence Engineering Consultants Level 1 / 228 Victoria Avenue Chatswood NSW 2067 PO Box 3047 Willoughby North NSW 2068 Tel. (02) 9413 3777

More information

Rigid and Flexible Pipe Design, Installation and Whole of Life Cost

Rigid and Flexible Pipe Design, Installation and Whole of Life Cost Rigid and Flexible Pipe Design, Installation and Whole of Life Cost Rigid and Flexible Pipe Design, Installation and Whole of Life Cost Executive Summary Pipes are typically identified as either flexible

More information

METROPOLITAN COAL LONGWALLS BUILT FEATURES MANAGEMENT PLAN NEXTGEN

METROPOLITAN COAL LONGWALLS BUILT FEATURES MANAGEMENT PLAN NEXTGEN METROPOLITAN COAL METROPOLITAN COAL LONGWALLS 301-303 BUILT FEATURES MANAGEMENT PLAN NEXTGEN Revision Status Register Section/Page/ Annexure All Section 4.1.1, Tables 3, 5 & 6, Figure 4 and Appendix 1

More information

ASHTON LONGWALL 5 END OF PANEL SUMMARY REPORT

ASHTON LONGWALL 5 END OF PANEL SUMMARY REPORT ASHTON LONGWALL 5 END OF PANEL SUMMARY REPORT 1 INTRODUCTION This report has been prepared in conjunction with the SCT Operations Pty Ltd (SCT) Longwall 5 End of Panel Subsidence Report and the Aquaterra

More information

Longwall 900W Powerline Management Plan. Angus Place Colliery

Longwall 900W Powerline Management Plan. Angus Place Colliery Longwall 900W Powerline Management Plan Angus Place Colliery November 2013 This page has been intentionally left blank. Longwall 900W Powerline Management Plan Longwall 900W Powerline Management Plan

More information

RE: Modified commencing end of LW103 and proposed 103A workings Figure 1 Layout of LW103 and the proposed 103A workings

RE: Modified commencing end of LW103 and proposed 103A workings Figure 1 Layout of LW103 and the proposed 103A workings 6 March 2019 Moolarben Coal Operations Pty Ltd Locked Bag 2003 Mudgee NSW 2850 For the attention of: Graham Chase, Environmental and Community Manager Dear Graham, RE: Modified commencing end of LW103

More information

Rigid and Flexible Pipe Design, Installation and Whole of Life Cost New Zealand Comparison

Rigid and Flexible Pipe Design, Installation and Whole of Life Cost New Zealand Comparison Concrete Pipe Association Rigid and Flexible Pipe Design, Installation and Whole of Life Cost New Zealand Comparison Concrete Pipe Association Rigid and Flexible Pipe Design, Installation and Whole of

More information

FORM 1 S Design Certification List - Wastewater Agreements

FORM 1 S Design Certification List - Wastewater Agreements FORM 1 S Design Certification List - Wastewater Agreements Job Description Location Developer / Owner Developer / Owner Contact Details Consultant Gippsland Water Drawing Numbers Notes: 1 Where the word

More information

SECTION GRAVITY WASTEWATER LINES

SECTION GRAVITY WASTEWATER LINES SECTION GRAVITY WASTEWATER LINES 1. DESCRIPTION This specification shall govern all work required for furnishing, handling and installing gravity wastewater lines required to complete the project. 2. MATERIALS

More information

METROPOLITAN COAL LONGWALLS BUILT FEATURES MANAGEMENT PLAN WOLLONGONG CITY COUNCIL [OLD PRINCES HIGHWAY]

METROPOLITAN COAL LONGWALLS BUILT FEATURES MANAGEMENT PLAN WOLLONGONG CITY COUNCIL [OLD PRINCES HIGHWAY] METROPOLITAN COAL METROPOLITAN COAL LONGWALLS 301-303 BUILT FEATURES MANAGEMENT PLAN WOLLONGONG CITY COUNCIL [OLD PRINCES HIGHWAY] Revision Status Register Section/Page/ Annexure All Tables 3 & 4, Section

More information

R E P O R T T O : ASHTON COAL MINE

R E P O R T T O : ASHTON COAL MINE R E P O R T T O : ASHTON COAL MINE Subsidence Assessment for Ashton Coal Mine Longwalls 1 to 4 ASH3084 REPORT TO Brian Wesley Mine Manager Ashton Underground Mine PO Box 699 SINGLETON NSW 2330 SUBJECT

More information

SRPE AASHTO Specifications.

SRPE AASHTO Specifications. SRPE AASHTO Specifications July 19, 2013 Steel Ribbed HDPE = SRHDPE = SRPE Now has AASHTO Design and Construction Specifications for SRPE. 2 But wait there is more AASHTO Bridge Design Specs - Section

More information

Pipe Jacking Association: Introduction Presentation. Lecture notes. Slide 1. Slide 2

Pipe Jacking Association: Introduction Presentation. Lecture notes. Slide 1. Slide 2 Slide 1 PIPE JACKING An introduction to pipe jacking prepared by the Pipe Jacking Association This introduction to pipe jacking has been prepared by the Pipe Jacking Association as an aid to engineers

More information

PART 1 PLANNING & DESIGN

PART 1 PLANNING & DESIGN 1.1 Scope The Supplementary Manual sets out the QUU requirements for sewers up to and including DN 300. References to sewers larger than DN 300 are provided for information only. 1.3.2 Planning responsibilities

More information

Application for Subsidence Management Approval. Subsidence Management Plan ANNEX D. Bettys Creek Subsidence Management Plan

Application for Subsidence Management Approval. Subsidence Management Plan ANNEX D. Bettys Creek Subsidence Management Plan Application for Subsidence Management Approval Subsidence Management Plan ANNEX D Bettys Creek Subsidence Management Plan Subsidence Management Plan Bettys Creek Glennies Creek Longwall Panels 10 to 17

More information

P-CAT PIPELINE CONDITION ASSESSMENT TECHNIQUE FOR WATER AND SEWER MAINS

P-CAT PIPELINE CONDITION ASSESSMENT TECHNIQUE FOR WATER AND SEWER MAINS P-CAT PIPELINE CONDITION ASSESSMENT TECHNIQUE FOR WATER AND SEWER MAINS Young-il Kim, Penelope Wrightson, Mason Erkelens and Stephen Simmons Detection Services Pty Ltd, Sydney, NSW, Australia ABSTRACT

More information

Case Studies in the Application of Influence Functions to Visualising Surface Subsidence

Case Studies in the Application of Influence Functions to Visualising Surface Subsidence University of Wollongong Research Online Coal Operators' Conference Faculty of Engineering and Information Sciences 23 Case Studies in the Application of Influence Functions to Visualising Surface Subsidence

More information

City of Logan Sanitary Sewer Design Standards

City of Logan Sanitary Sewer Design Standards City of Logan Sanitary Sewer Design Standards 2011 http://www.loganutah.org/public_works/engineering/stdsspecsdesign.cfm Table of Contents PART 1. CITY OF LOGAN SANITARY SEWER SYSTEM DESIGN STANDARDS FOR

More information

SEWERAGE DESIGN STANDARD

SEWERAGE DESIGN STANDARD SEWERAGE DESIGN STANDARD Supplementary Information to the WSAA Sewerage Code of Australia WSA 02-2014-3.1 Melbourne Retail Water Agencies Edition Version 2 Western Water January 2018 Executive Summary

More information

ASHTON LONGWALL 103 MID PANEL REPORT

ASHTON LONGWALL 103 MID PANEL REPORT Ashton Longwall 13 ASHTON LONGWALL 13 MID PANEL REPORT 1 INTRODUCTION This report has been prepared by Ashton Coal Operations Pty Ltd (ACOL) with the assistance of an independent groundwater consultant,

More information

PVC Fittings & Laterals for Solid-Wall PVC Sewer Pipe

PVC Fittings & Laterals for Solid-Wall PVC Sewer Pipe Design and Installation Guide PVC Fittings & Laterals for Solid-Wall PVC Sewer Pipe TABLE OF CONTENTS Introduction 2 Products 3 Main-Line Fittings & Service-Line Fittings 3-4 Connections to Dissimilar

More information

PVC-U DWV Expanda Joints, Expansion Bends and Swivel Expansion Joints for gravity sewer applications

PVC-U DWV Expanda Joints, Expansion Bends and Swivel Expansion Joints for gravity sewer applications Date: 8 January 2013 To: From: RE: Technical Advisory Group Mohamed Yoosuf PVC-U DWV Expanda Joints, Expansion Bends and Swivel Expansion Joints for gravity sewer applications 1. Introduction This paper

More information

Polysewer Gravity Sewer System SPECIFICATION

Polysewer Gravity Sewer System SPECIFICATION Polysewer Gravity Sewer System SPECIFICATION July 2014 SCOPE OF WORKS To meet the specific performance criteria detailed within this specification and accompanying drawings. The completed drainage systems

More information

REQUIREMENTS FOR SERVICES UNDER THE RAILWAY CORRIDOR (NON-QR SERVICES)

REQUIREMENTS FOR SERVICES UNDER THE RAILWAY CORRIDOR (NON-QR SERVICES) SYSTEMS AND CAPABILITY TECHNICAL REQUIREMENT NO: MCE-SR-16 ISSUE: Initial DATE: 14-10-2009 PAGE: 1 of 19 REQUIREMENTS FOR SERVICES UNDER THE RAILWAY CORRIDOR (NON-QR SERVICES) ISSUE DATE DESCRIPTION /

More information

F A&C - Design Assessment Checklist - Sewerage Accreditation and Certification

F A&C - Design Assessment Checklist - Sewerage Accreditation and Certification F10235 - A&C - Design Assessment Checklist - Sewerage Instructions: This Checklist must be completed by a Unitywater Accredited Registered Certifier. Applicant Details: Name (individual or company name

More information

SPECIAL CONDITIONS FOR PIPE JACKING (PJ) October, 2006

SPECIAL CONDITIONS FOR PIPE JACKING (PJ) October, 2006 Michigan Department Of Transportation 3703C (11/06) 1 Materials 1.1 Pipe SPECIAL CONDITIONS FOR PIPE JACKING (PJ) October, 2006 Page 1 of 5 The type of pipe used for the pipe jacking method shall be capable

More information

BACKGROUND INFORMATION DOCUMENT FOR A PROPOSED SEWER IN GROOT DRAKENSTEIN, WESTERN CAPE

BACKGROUND INFORMATION DOCUMENT FOR A PROPOSED SEWER IN GROOT DRAKENSTEIN, WESTERN CAPE Purpose of this Document The purpose of this Background Information Document (BID) is to provide Interested and Affected Parties (I&APs) with background information about the proposed project and to introduce

More information

Tahmoor Colliery - COMMUNITY CONSULTATIVE COMMITTEE Thursday 25 th September 2008

Tahmoor Colliery - COMMUNITY CONSULTATIVE COMMITTEE Thursday 25 th September 2008 Tahmoor Colliery - COMMUNITY CONSULTATIVE COMMITTEE Thursday 25 th September 2008 NEXT MEETING: 11 TH DECEMBER 2008 (Location: Vaby s, Picton) Meeting Open: 5:40pm Meeting Closed: 7:35pm ATTENDANCE Attending

More information

Klickitat County. On-Site Sewage System. Construction Manual

Klickitat County. On-Site Sewage System. Construction Manual Homeowner OSS Design and Construction Guide Klickitat County On-Site Sewage System Construction Manual Minimum standards and recommendations expected for the construction of on-site wastewater treatment

More information

F. Provide at least 2 feet of vertical separation between a water line and any utility or stormdrain crossing it.

F. Provide at least 2 feet of vertical separation between a water line and any utility or stormdrain crossing it. Section 3 F. Provide at least 2 feet of vertical separation between a water line and any utility or stormdrain crossing it. 3.8 Highway Crossings The design engineer shall, prior to the design of any highway

More information

SECTION STORM SEWER COLLECTION SYSTEM

SECTION STORM SEWER COLLECTION SYSTEM SECTION 02722 STORM SEWER COLLECTION SYSTEM PART 1 GENERAL 1.01 SUMMARY A. This section addresses the installation of storm sewer collection mains and includes the acceptable products, materials, and construction

More information

INDEX FOR SPECIFICATIONS FOR JACKING CULVERTS THROUGH EMBANKMENTS SCOPE... 2

INDEX FOR SPECIFICATIONS FOR JACKING CULVERTS THROUGH EMBANKMENTS SCOPE... 2 INDEX FOR SPECIFICATIONS FOR JACKING CULVERTS THROUGH EMBANKMENTS 410. 1 SCOPE... 2 410. 2 DEFINITIONS 2.1 Tunneling and Jacking... 2 2.2 Tunneling... 2 2.3 Jacking... 2 410. 3 MATERIALS 3.1 General...

More information

CONSTRUCTION PLAN CHECKLIST

CONSTRUCTION PLAN CHECKLIST CONSTRUCTION PLAN CHECKLIST The design engineer is responsible for ensuring that plans submitted for city review are in accordance with this checklist. It is requested that the executed checklist be submitted

More information

AI-04-CCTV INSPECTION OF CONSTRUCTION WORKS

AI-04-CCTV INSPECTION OF CONSTRUCTION WORKS AI-04-CCTV INSPECTION OF CONSTRUCTION WORKS Ver.1 Date: October 2014 1. SCOPE This section covers inspection of newly constructed pipelines before they are put into service, and of existing pipelines before

More information

San Antonio Water System Standard Specifications for Construction ITEM NO. 848 SANITARY SEWERS

San Antonio Water System Standard Specifications for Construction ITEM NO. 848 SANITARY SEWERS ITEM NO. 848 SANITARY SEWERS 848.1 DESCRIPTION: This item shall govern the furnishing, installation and jointing of sanitary sewer pipe of the size and type specified by the project's plans and specifications.

More information

SPECIAL CONDITIONS FOR HORIZONTAL AUGER BORING (HAB) October, 2006

SPECIAL CONDITIONS FOR HORIZONTAL AUGER BORING (HAB) October, 2006 Michigan Department Of Transportation 3703B (11/06) 1 Materials SPECIAL CONDITIONS FOR HORIZONTAL AUGER BORING (HAB) October, 2006 Page 1 of 5 1.1 Pipe - Pipe used in this method includes an external steel

More information

3. MINING SYSTEM AND RESOURCE RECOVERY

3. MINING SYSTEM AND RESOURCE RECOVERY 3. MINING SYSTEM AND RESOURCE RECOVERY (SMP Guideline Section 6.1) 3.1. MINING METHOD Longwalls 705 to 710 will be extracted using a longwall retreating system of mining, an established method of coal

More information

Tasman Retaining Wall

Tasman Retaining Wall Tasman Retaining Wall EVALUATION AND INSTALLATION GUIDE Landscaping Tasman Retaining Wall Evaluation and Installation Guide This installation guide demonstrates the basics on how to construct: A. Tasman

More information

SEPTIC TANK CONSTRUCTION GUIDELINES

SEPTIC TANK CONSTRUCTION GUIDELINES SEPTIC TANK CONSTRUCTION GUIDELINES Septic tank for this airport will be designed/ built by the general contractor of the building facilities. At the time of the project design, availability of a septic

More information

T a b l e o f C o n t e n t s

T a b l e o f C o n t e n t s C i t y o f G l a d s t o n e P u b l i c W o r k s D e s i g n S t a n d a r d s T a b l e o f C o n t e n t s SECTION THREE SANITARY SEWER REQUIREMENTS... 1 3.0000 SANITARY SEWERS... 1 3.0010 General

More information

GUIDANCE MEMO NO : GUIDANCE CRITERIA FOR THE SEPARATION OF WATER MAINS AND NON-POTABLE PIPELINES

GUIDANCE MEMO NO : GUIDANCE CRITERIA FOR THE SEPARATION OF WATER MAINS AND NON-POTABLE PIPELINES State of California Memorandum Department of Health Services Date: April 4, 2003 To: From: Subject: Regional and District Engineers David P. Spath, Ph.D., Chief (Original signed by Dave) Drinking Water

More information

APPENDIX: C. Stormwater and Wastewater Construction Specification. Tauranga City Council

APPENDIX: C. Stormwater and Wastewater Construction Specification. Tauranga City Council APPENDIX: C Stormwater and Wastewater Construction Specification Tauranga City Council General Where the word Contractor is used below, it shall mean either work undertaken by the Consent Holder s Representative

More information

Subsidence Peer Review

Subsidence Peer Review I Subsidence Peer Review BYLONG COAL PROJECT Environmental Impact Statement BYLONG COAL PROJECT EIS I 22 December 2014 Rory Gordon WorleyParsons L11 12/141 Walker Street North Sydney NSW 2060 Dear Rory

More information

Condition Assessment and Rehabilitation/ Renewal of Wastewater Rising Mains

Condition Assessment and Rehabilitation/ Renewal of Wastewater Rising Mains Condition Assessment and Rehabilitation/ Renewal of Wastewater Rising Mains Philip McFarlane, ProjectMax Ltd ABSTRACT This paper discusses techniques for the condition assessment and rehabilitation/replacement

More information

WAMBO COAL PTY LTD REPORT 2 NORTH WAMBO UNDERGROUND MINE EXTRACTION PLAN LONGWALLS 8 TO 10A GROUNDWATER IMPACT ASSESSMENT REVIEW

WAMBO COAL PTY LTD REPORT 2 NORTH WAMBO UNDERGROUND MINE EXTRACTION PLAN LONGWALLS 8 TO 10A GROUNDWATER IMPACT ASSESSMENT REVIEW WAMBO COAL PTY LTD NORTH WAMBO UNDERGROUND MINE EXTRACTION PLAN LONGWALLS 8 TO 10A REPORT 2 GROUNDWATER IMPACT ASSESSMENT REVIEW Date: To: From: Re: Ref: 9 April 2015 Micheal Alexander Director Projects

More information

WASTEWATER & STORM WATER COLLECTION AND REMOVAL

WASTEWATER & STORM WATER COLLECTION AND REMOVAL CVE 471 WATER RESOURCES ENGINEERING WASTEWATER & STORM WATER COLLECTION AND REMOVAL Assist. Prof. Dr. Bertuğ Akıntuğ Civil Engineering Program Middle East Technical University Northern Cyprus Campus CVE

More information

UPONOR INFRASTRUCTURE. Uponor Gravity Sewer Systems 47

UPONOR INFRASTRUCTURE. Uponor Gravity Sewer Systems 47 UPONOR INFRASTRUCTURE Uponor Uponor 47 Uponor Gravity Drainage and Sewer 5.1 Introduction...50 Sewer System Planning & Design...52 Sewer System Flow Design...59 Installation General Instructions and Supervision...62

More information

TABLE OF CONTENTS

TABLE OF CONTENTS DIVISION 33: SEWER AND SEPTIC SYSTEMS 33 3633 UTILITY SEPTIC TANK DRAINAGE FIELD TABLE OF CONTENTS 33 0000-1 SECTION 33 3633-- UTILITY SEPTIC TANK DRAINAGE FIELD PART 1 - GENERAL 1.1 SUMMARY A. Includes

More information

Gravity Sewerage Code of Australia WSA

Gravity Sewerage Code of Australia WSA Gravity Sewerage Code of Australia WSA 02 2014-3.1 Melbourne Retail Water Agencies Edition (Including City West Water, South East Water & Yarra Valley Water) Version 2 Previous edition WSA 02:2002-2.3

More information

CHAPTER 17 - SPECIALIST CONSTRUCTION SYSTEMS

CHAPTER 17 - SPECIALIST CONSTRUCTION SYSTEMS CHAPTER 17 - SPECIALIST CONSTRUCTION SYSTEMS WJ Martin 17.1 SCOPE Specialist construction systems refer to the construction systems falling outside of the normal reinforced and prestressed bridges that

More information

METROPOLITAN COAL LONGWALLS BUILT FEATURES MANAGEMENT PLAN OPTUS

METROPOLITAN COAL LONGWALLS BUILT FEATURES MANAGEMENT PLAN OPTUS METROPOLITAN COAL METROPOLITAN COAL LONGWALLS 301-303 BUILT FEATURES MANAGEMENT PLAN OPTUS Revision Status Register Section/Page/ Annexure All Sections 1.1, 4.1.1, 6.2, 6.3, 7.2.1, 8 & 9.1, Tables 3, 5,

More information

APPENDIX 5. Subsidence Impact Assessment

APPENDIX 5. Subsidence Impact Assessment APPENDIX 5 Subsidence Impact Assessment Austar Coal Mine Pty Limited REPORT on THE PREDICTION OF SUBSIDENCE PARAMETERS AND THE ASSESSMENT OF MINE SUBSIDENCE IMPACTS ON THE NATURAL FEATURES AND SURFACE

More information

UPDATE 3A MINIMUM REQUIREMENTS

UPDATE 3A MINIMUM REQUIREMENTS 3. STORMWATER CONTENTS SECTION PAGE LATEST UPDATE 3A MINIMUM REQUIREMENTS 3.1 July 2004 3B MEANS OF COMPLIANCE 3.1 July 2004 3.B.1 DESIGN STANDARD 3.1 October 2005 3.B.2 DISCHARGE PERMITS 3.3 July 2004

More information

CONSTRUCTION SPECIFICATION FOR PIPELINE AND UTILITY INSTALLATION IN SOIL BY HORIZONTAL DIRECTIONAL DRILLING

CONSTRUCTION SPECIFICATION FOR PIPELINE AND UTILITY INSTALLATION IN SOIL BY HORIZONTAL DIRECTIONAL DRILLING ONTARIO PROVINCIAL STANDARD SPECIFICATION METRIC OPSS 450 NOVEMBER 2002 CONSTRUCTION SPECIFICATION FOR PIPELINE AND UTILITY INSTALLATION IN SOIL BY HORIZONTAL DIRECTIONAL DRILLING TABLE OF CONTENTS 450.01

More information

METROPOLITAN COAL LONGWALLS BUILT FEATURES MANAGEMENT PLAN SYDNEY TRAINS

METROPOLITAN COAL LONGWALLS BUILT FEATURES MANAGEMENT PLAN SYDNEY TRAINS METROPOLITAN COAL METROPOLITAN COAL LONGWALLS 301-303 BUILT FEATURES MANAGEMENT PLAN SYDNEY TRAINS Revision Status Register Section/Page/ Annexure All Section 4.2.1, Tables 3 & 5 and Figure 4 Revision

More information

Arafura Resouces Ltd. Nolans Environmental Impact Statement. volume one. Risk assessment. Chapter 5

Arafura Resouces Ltd. Nolans Environmental Impact Statement. volume one. Risk assessment. Chapter 5 Arafura Resouces Ltd Nolans volume one 05 Risk assessment Chapter 5 5. Risk assessment 5.1 Introduction This chapter provides a description of the whole-of-project risk assessment undertaken for the identification,

More information

Modular Grease Trap (MGT)

Modular Grease Trap (MGT) Modular Grease Trap (MGT) Installation Requirements Unit 2 187 South Creek Road Cromer NSW 2099 Postal: PO Box 255 Collaroy NSW 2097 Freecall 1800 626 753 Phone: 02 9972 1355 Fax: 02 9972 1455 Email: sales@halgan.com.au

More information

TCC/SHORE TRANSIT BUS MAINTENANCE FACILITY - PHASE II

TCC/SHORE TRANSIT BUS MAINTENANCE FACILITY - PHASE II SECTION 221313 - FACILITY SANITARY SEWERS PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 01 Specification

More information

NOVEMBER 2016 GRANDWALL. retaining walls installation guide

NOVEMBER 2016 GRANDWALL. retaining walls installation guide NOVEMBER 2016 GRANDWALL retaining walls installation guide RETAINING WALL INSTALLATION GUIDE RETAINING WALL information Austral Masonry Grandwall retaining wall blocks are an ideal choice for retaining

More information

SPECIAL CONDITIONS FOR MICROTUNNELING (MT) October, 2006

SPECIAL CONDITIONS FOR MICROTUNNELING (MT) October, 2006 Michigan Department Of Transportation 3703F (11/06) SPECIAL CONDITIONS FOR MICROTUNNELING (MT) October, 2006 Page 1 of 5 1 Materials 1.1 Pipe (a) Pipe shall be specifically designed and certified for microtunneling

More information

SDPS for Windows: An Integrated Approach to Ground Deformation Prediction

SDPS for Windows: An Integrated Approach to Ground Deformation Prediction SDPS for Windows: An Integrated Approach to Ground Deformation Prediction D. Newman, Appalachian Mining and Engineering, Inc./Geolab Z. Agioutantis Department of Mineral Resources Engineering, Technical

More information

Sewer Audit - Design Checklist Gravity sewers, sewage pumping stations and pressure sewers

Sewer Audit - Design Checklist Gravity sewers, sewage pumping stations and pressure sewers Question Relevant Clauses Design checked? Do the drawings show an appropriate revision history, and is 1.1 the design complete, checked and effectively ready for construction? 1.2 Has the whole catchment

More information

EI INSTALLATION OF UNDERGROUND CABLES - LV TO 132KV

EI INSTALLATION OF UNDERGROUND CABLES - LV TO 132KV Network(s): Summary: ENGINEERING INSTRUCTION EI 02-0019 INSTALLATION OF UNDERGROUND CABLES - LV TO 132KV EPN, LPN, SPN This engineering instruction details the minimum requirements acceptable for the installation

More information

Introduction. Pipe Manufacture & Construction. 20 September Mr Des McLean General Manager P & F Global P O Box 5084 Invercargill C1398.

Introduction. Pipe Manufacture & Construction. 20 September Mr Des McLean General Manager P & F Global P O Box 5084 Invercargill C1398. Opus International Consultants Ltd Christchurch Environmental Office 12 Moorhouse Avenue PO Box 1482, Christchurch Mail Centre, Christchurch 8140 New Zealand 20 September 2016 t: +64 3 363 5400 f: +64

More information

WATER SUPPLY CODE SCHEDULE OF AMENDMENTS

WATER SUPPLY CODE SCHEDULE OF AMENDMENTS SEQ Water Supply and Sewerage Design & Construction Code (SEQ WS&S D&C Code) WATER SUPPLY CODE SCHEDULE OF AMENDMENTS Amendment No.2 December 2018 December 2018 SEQ WS&S D&C Code Water Supply Code - Amendment

More information

1993 SPECIFICATIONS CSJ SPECIAL SPECIFICATION ITEM 4110 CONCRETE ENCASED DUCT BANK

1993 SPECIFICATIONS CSJ SPECIAL SPECIFICATION ITEM 4110 CONCRETE ENCASED DUCT BANK 1993 SPECIFICATIONS CSJ 581-1-95 SPECIAL SPECIFICATION ITEM 4110 CONCRETE ENCASED DUCT BANK 1. DESCRIPTION. This Item shall govern for the furnishing and installation of all materials and equipment for

More information

Christchurch City Council

Christchurch City Council 36 Lichfield Street Detailed Engineering Evaluation Quantitative Assessment Report Christchurch City Council 36 Lichfield Street Kathmandu/Rexel Building Detailed Engineering Evaluation Quantitative Assessment

More information

Draft. Not Yet Approved SECTION 10.1 GENERAL SCOPE DEFINITIONS

Draft. Not Yet Approved SECTION 10.1 GENERAL SCOPE DEFINITIONS SECTION 10.1 GENERAL 10.1.1 SCOPE This part of the Manual covers the structural design and installation of reinforced concrete pipe for railway culverts. Pipe geometry may be circular, arch, or elliptical.

More information

Module 7: Hydraulic Design of Sewers and Storm Water Drains. Lecture 7 : Hydraulic Design of Sewers and Storm Water Drains

Module 7: Hydraulic Design of Sewers and Storm Water Drains. Lecture 7 : Hydraulic Design of Sewers and Storm Water Drains 1 P age Module 7: Hydraulic Design of Sewers and Storm Water Drains Lecture 7 : Hydraulic Design of Sewers and Storm Water Drains 2 P age 7.1 General Consideration Generally, sewers are laid at steeper

More information

TITLE: SLAUGHTER HOUSE SEPTIC TANK. ITEM No. D E S C R I P T I O N UNIT QTY

TITLE: SLAUGHTER HOUSE SEPTIC TANK. ITEM No. D E S C R I P T I O N UNIT QTY D DEMOLITION & SITE CLEARANCE D1 GENERAL CLEARANCE 6-D152 Open bush and thicket in and around ha 0.02 the ponds. Locally disposed. D2 REMOVAL OF TREES AND STUMPS 6-D212 Trees of girth: 150 mm - 500 mm

More information

freestone eco Prestige & quality DIY vertical wall Large blocks - 10/m 2 Smooth surface finish No concrete footings

freestone eco Prestige & quality DIY vertical wall Large blocks - 10/m 2 Smooth surface finish No concrete footings freestone eco Retaining Wall SystemTM The Freestone ECO Retaining Wall System TM is a more sustainable DIY, vertical retaining wall which is manufactured with up to 40% recycled glass aggregate to provide

More information

Below ground System of pipework required to carry waste fluids from building to disposal site.

Below ground System of pipework required to carry waste fluids from building to disposal site. 1 Below ground System of pipework required to carry waste fluids from building to disposal site. Disposal site County Council sewage treatment facility. Septic tank system or alternative systems 2 1. Layout

More information

THE USE OF HYDRAULIC TRANSIENT MODELLING IN THE DESIGN OF RESILIENT PIPELINES

THE USE OF HYDRAULIC TRANSIENT MODELLING IN THE DESIGN OF RESILIENT PIPELINES THE USE OF HYDRAULIC TRANSIENT MODELLING IN THE DESIGN OF RESILIENT PIPELINES Alistair Hancox, Grant Pedersen Harrison Grierson Consultants Limited ABSTRACT Pressure surges during the start up, shut down,

More information

SECTION 6 STORMWATER AND LAND DRAINAGE

SECTION 6 STORMWATER AND LAND DRAINAGE SECTION 6 STORMWATER AND LAND DRAINAGE Final Version, Approved September 2003 Section 6 and Land Drainage Contents 6.1 PERFORMANCE STANDARDS... 2 6.1.1 General... 2 6.2 MEANS OF COMPLIANCE... 3 6.2.1 General...

More information

AUDIT GUIDELINES: ELECTRICITY, GAS AND WATER LICENSING: AUDIT TEMPLATE FOR SMALLER ORGANISATIONS

AUDIT GUIDELINES: ELECTRICITY, GAS AND WATER LICENSING: AUDIT TEMPLATE FOR SMALLER ORGANISATIONS AUDIT GUIDELINES: ELECTRICITY, GAS AND WATER LICENSING: AUDIT TEMPLATE FOR SMALLER ORGANISATIONS This document is available from the Economic Regulation Authority website www.era.wa.gov.au. For further

More information

Ordinance No Lot Surface Drainage

Ordinance No Lot Surface Drainage Ordinance No. 35-2008 - Lot Surface Drainage The Township has adopted a new Lot Surface Drainage Ordinance which amends Chapter 170, Article IX, Subdivision and Site Plan Review by adding a new Section

More information

Moolarben Coal Complex UG1 Optimisation Modification. Environmental Assessment APPENDIX F SURFACE WATER ASSESSMENT REVIEW

Moolarben Coal Complex UG1 Optimisation Modification. Environmental Assessment APPENDIX F SURFACE WATER ASSESSMENT REVIEW Moolarben Coal Complex UG1 Optimisation Modification Environmental Assessment APPENDIX F SURFACE WATER ASSESSMENT REVIEW Moolarben Coal Complex UG1 Optimisation Modification Surface Water Assessment Review

More information

CERTIFYING DRAINLAYER

CERTIFYING DRAINLAYER No. 9198 REGISTRATION EXAMINATION, JUNE 2012 CERTIFYING DRAINLAYER ANSWER SCHEDULE Plumbers, Gasfitters and Drainlayers Board, 2012. All rights reserved. No part of this publication may be reproduced by

More information

AI-05-CCTV INSPECTION OF EXISTING PIPELINES PRIOR TO OTHER WORKS

AI-05-CCTV INSPECTION OF EXISTING PIPELINES PRIOR TO OTHER WORKS AI-05-CCTV INSPECTION OF EXISTING PIPELINES PRIOR TO OTHER WORKS Ver.1 Date: October 2014 1. SCOPE This section covers the inspection of existing sewer and stormwater pipelines before and after the construction

More information

Palmerston North City Council Policy

Palmerston North City Council Policy Palmerston North City Council Policy PRESSURE SEWER S YSTEMS POLICY - DRAFT SEPTEMBER 2018 Oasis 8384024 Palmerston North City Council Pressure Sewer Systems Policy September 2018 1 Introduction... 3 2

More information

T-39 Thriebeam. Product Manual. NCHRP 350 Test Level 3 & 4 Compliant Barrier. Release 01/11

T-39 Thriebeam.  Product Manual. NCHRP 350 Test Level 3 & 4 Compliant Barrier. Release 01/11 T-39 Thriebeam NCHRP 350 Test Level 3 & 4 Compliant Barrier Product Manual T-39 is licensed to Ingal Civil Products by Trinity Industries Inc. of the U.S.A. www.ingalcivil.com.au T-39 Thriebeam NCHRP 350

More information

PART 3 : GUIDANCE FOR DESIGN SECTION LB CONTENTS

PART 3 : GUIDANCE FOR DESIGN SECTION LB CONTENTS PART 3 : GUIDANCE FOR DESIGN SECTION LB CONTENTS Clause 1. 1.1 1.1.1 1.1.2 1.1.3 1.1.4 1.2 1.2.1 1.3 1.3.1 1.3.2 1.3.3 1.3.4 2. 2.1 2.1.1 2.1.2 2.1.3 2.1.4 2.1.5 2.2 2.2.1 2.2.2 2.2.3 2.2.4 2.3 3. 3.1

More information

GRAVITY SEWERS. Performance & Cost for Decentralized Unit Processes. Fact Sheet C1 COLLECTION SERIES. Wastewater source. Road

GRAVITY SEWERS. Performance & Cost for Decentralized Unit Processes. Fact Sheet C1 COLLECTION SERIES. Wastewater source. Road Fact Sheet C1 Performance & Cost for Decentralized Unit Processes COLLECTION SERIES DECENTRALIZED WASTEWATER SYSTEMS What is a Gravity Sewer System? A gravity sewer system is used to collect wastewater

More information

SPECIFICATIONS & SPECIAL PROVISIONS FOR DESIGN AND CONSTRUCTION CITY OF MONTCLAIR - ENGINEERING DIVISION

SPECIFICATIONS & SPECIAL PROVISIONS FOR DESIGN AND CONSTRUCTION CITY OF MONTCLAIR - ENGINEERING DIVISION SPECIFICATIONS & SPECIAL PROVISIONS FOR DESIGN AND CONSTRUCTION CITY OF MONTCLAIR - ENGINEERING DIVISION City of Montclair 5111 Benito Street, Montclair, CA 91763 Tel: (909) 625-9440 Fax: (909) 621-1584

More information

Continuous Monitoring of Longwall Undermining

Continuous Monitoring of Longwall Undermining Steven GARLINGE, Australia Key words: monitoring, real-time, longwall, sensors, web-based, rail SUMMARY Lynton Surveys was appointed to install, commission and manage a suitable deformation monitoring

More information

SECTION BORING AND/OR JACKING PIPE

SECTION BORING AND/OR JACKING PIPE 02910-1 of 6 SECTION 02910 BORING AND/OR JACKING PIPE 02910.01 GENERAL A. Description Boring and/or jacking pipe shall include, but not necessarily be limited to, furnishing and installing carrier pipe

More information

CHANGES TO D12 SEWERAGE DESIGN

CHANGES TO D12 SEWERAGE DESIGN CHANGES TO D12 SEWERAGE DESIGN This document outlines significant change (not all changes) to Rev K Jul 2018 Version Clause numbers listed are as per the most recent document unless specified otherwise.

More information