Construction in Healthcare: Does it put Patients or Workers at Risk? Not if we do ICRA correctly! Infection Control Risk Assessment (ICRA)
|
|
- Oswald Chapman
- 5 years ago
- Views:
Transcription
1 Infection Control Risk Assessment (ICRA) What Does it Mean? Deb Hess, RN, CIC Supervisor Infection Control & Prevention Lancaster General/Penn Medicine Construction in Healthcare: Does it put Patients or Workers at Risk? Not if we do ICRA correctly! 1
2 10/20/2016 Fall 2016: Construction at LGH Who wants to join me in climbing the crane? 2
3 Purpose of ICRA: To provide parameters for safe design, construction, maintenance, and sustainability in the healthcare environment ICRA Infection risks, interventions, and control strategies must be considered in planning for new construction and/or renovation of healthcare facilities Developed for all projects that may impact the health of patients Multidisciplinary Document assessment process Proactively identifies and mitigate risks from infection that could occur Consider patient populations, scope of the project, & potential risk of transmission of contaminants Before starting and construction project: Complete ICRA with all key individuals at table: Construction Supervisors Facility Project Managers Safety Officer Infection Control & Prevention Safety considerations include Patients Visitors Hospital staff Construction workers Construction dust can: Cause infections in some patients Trigger allergies in some patients or staff Worsen breathing in some patients or staff Clog medical instruments Set off smoke detectors 3
4 Step 1: Define Risk Group Definition of Risk Groups Group I: Lowest Office areas Environmental Services Facilities Management Group 2: Medium All other Patient Care Areas not in Group 3 or 4 Group 4: Highest Group 3: Medium High Emergency Room Radiology/MRI Labor and Delivery Newborn Nursery Pediatrics Nuclear Medicine Admission/Discharge Areas PT- tank areas Cafeteria/Kitchen Special Procedures- Radiology Laboratories Operating Room, PACU, & Preoperative areas Sterile Processing Department Critical Care & Cardiac Units Labor & Delivery OR C-Section rooms Cardiac Catheterization & Angiography Areas Dialysis areas Oncology Units Radiation Therapy Endoscopy areas Pharmacy Transplant Unit Bone Marrow Transplant Pulmonary Function 4
5 Step 2: Determine Construction Type or Dust Level TYPES OF CONSTRUCTION / Dust Level Minimal Dust Inspections and non-invasive activity that do not make dust such as: Removal of ceiling tiles for visual inspection ONLY. Limited to 1 tile per 50 square feet Painting (No sanding) Wall covering application Electrical trim work Minor plumbing No removal of sinks or wall cutting 5
6 TYPES OF CONSTRUCTION / Dust Level Low Dust Small scale, short duration activities which create minimal dust: Installation of telephone and computer cables Cabling through ceiling with no more than 2 tiles removed Access to chase spaces Minor cutting of walls and ceilings where dust migration can be controlled (<1 sq. ft. diameter) Sanding of walls for painting or wall covering to ONLY REPAIR small patches TYPES OF CONSTRUCTION / Dust Level Moderate/High Dust: Short duration Work that generates a moderate to high level of dust: Demolition or removal of any fixed building components Breach in the building shell Sanding of walls for more than small patch repair Removal of floor coverings and casework New wall construction Minor ductwork or electrical work above ceilings Major cabling activities Removal of > 50 square feet of ceiling tile Cutting holes in existing walls of > 1 square foot Any activity that cannot be completed in a single work shift 6
7 TYPES OF CONSTRUCTION / Dust Level High Dust: Long duration Major demolition and construction projects: Heavy demolition or removal of a complete cabling or ceiling system Removal of drywall ceilings New construction requiring consecutive shifts to complete Step 3: Identify Class based on Steps 1 & 2 7
8 Identify Class Dust Level Risk Level Class Determines IC Measures Needed for Project Infection Control & Prevention Measures Class I Only remove 1 ceiling tile Intact tile Minor demolition for remodeling Execute work by methods to minimize raising dust from construction operations Immediately replace any ceiling tile displaced for visual inspection 8
9 Infection Control & Prevention Measures (Class II) Provides means to prevent airborne dust from dispersing into atmosphere. Water mist work surfaces to control dust while cutting Seal unused doors with duct tape Block off and seal air vents Infection Control & Prevention Measures (Class II) Provides means to prevent airborne dust from dispersing into atmosphere. Wipe surfaces with cleaner/disinfectant Contain construction waste before transport in tightly covered containers Wet mop and/or vacuum with HEPA filtered vacuum before leaving work area Place dust mat at entrance and exit of work area Isolate HVAC system in areas where work is being performed; restore when work completed 9
10 Infection Control & Prevention Measures (Class III) Always: Obtain infection control permit before construction begins & Include all barriers in Class II and additional barriers on next slides Infection Control & Prevention Measures (Class III) Isolate HVAC system in area where work is being done to prevent contamination of the duct system. Complete all critical barriers or implement control cube method before construction begins. 10
11 Infection Control & Prevention Measures (Class III cont. ) Maintain negative air pressure within work site utilizing HEPA-equipped air filtration units. Do not remove barriers from work area until complete project is checked by Infection Prevention & Control and thoroughly cleaned by Environmental Services. Plastic ICRA floor to deck with negative pressure Infection Control & Prevention Measures (Class III cont.) Vacuum work with HEPA-filtered vacuums Wet mop with cleaner/disinfectant Remove barrier materials carefully to minimize spreading of dirt and debris associated with construction 11
12 Infection Control & Prevention Measures (Class IV) Do everything as in level III & the following: Seal holes, pipes, conduits, and punctures appropriately Construct anteroom and require all personnel to pass through this room so they can be vacuumed using a HEPA vacuum cleaner before leaving work site or they can wear cloth or paper coveralls that are removed each time they leave the work site. Require all personnel entering work site to wear shoe covers. Anteroom Door HEPA filtered air may be vented into space when no window available 12
13 How to keep on track! Review Blueprints ASAP 13
14 10/20/2016 Planning includes everyone involved with that project New Construction When Feasible; Mock Up Room 14
15 Weekly Construction Meetings 15
16 Conclusion Very important for Infection Control to be involved from the beginningof projects whether renovations or new construction big or small Meet regularly with construction team and project managers Don t be afraid to ask questions or stop the work until the appropriate barriers are in place and tight Have fun with this you can learn so much!! Worksite Checklist Special thanks to LGH Infection Control & Prevention team and Benchmark Construction for providing insights and pictures. Reference: APIC. (2015). Infection Prevention Manual for Construction & Renovation. Washington DC: APIC. 16
State of Kuwait Ministry of Health Infection Control Directorate. The role of infection control In design of health care facilities
State of Kuwait Ministry of Health Infection Control Directorate The role of infection control In design of health care facilities 2007 INTRODUCTION Hospital design should ensure that patients, especially
More informationInfection Control Risk Assessment Matrix of Precautions for Construction & Renovation
Figure 3-6. Sample ICRA Matrix of Precautions Infection Control Risk Assessment Matrix of Precautions for Construction & Renovation Step 1: Using the following table, identify the Type of Construction
More informationInfection Control Risk Assessment Matrix of Precautions for Construction & Renovation
Infection Control Risk Assessment Matrix of Precautions for Construction & Renovation Step One: Using the following table, identify the Type of Construction Project Activity (Type A-D) TYPE A TYPE B TYPE
More informationInfection Prevention & Control
Infection Prevention & Control Throughout Construction & Renovations Updated July 2018 1 Objectives After completion of this Infection Prevention & Control Construction Education, participants will be
More informationRisk Assessment and Preventive Measures Checklist for Construction and Renovation. Location of Construction: Project Start Date: Estimated Duration:
Risk Assessment and Preventive Measures Checklist for Construction and Renovation Location of Construction: Project Start Date: Estimated Duration: Project Manager (PM): Contractor(s): Infection Prevention
More informationDeveloped and Presented by: Wisconsin Healthcare Engineering Association
Infection Control Risk Assessment (ICRA) Developed and Presented by: Wisconsin Healthcare Engineering Association What is an ICRA? An Infection Control Risk Assessment is a tool devised to protect patients
More informationAustralasian Health Facility Guidelines. Part D - Infection Prevention and Control D Construction and Renovation
Australasian Health Facility Guidelines Part D - Infection Prevention and Control D.0005 - Construction and Renovation Revision 7.0 01 March 2016 COPYRIGHT AND DISCLAIMER Copyright 2015 Australasian Health
More informationICM X-09 DEFINITION COMMENTS
TITLE/DESCRIPTION: INFECTION PREVENTION AND CONTROL PROCEDURES FOR HOSPITAL AND HEALTHCARE FACILITY CONSTRUCTION AND INDEX NUMBER: EFFECTIVE DATE: 01/01/2009 01/01/2013 APPLIES TO: All GCC Countries ISSUING
More informationINFECTION CONTROL ISSUES IN CONSTRUCTION AND RENOVATION
INFECTION CONTROL ISSUES IN CONSTRUCTION AND RENOVATION Evelyn Cook SPICE.unc.edu 919 966 1304 I want to begin with the premise that patients can leave the hospital sicker than they arrived if construction
More informationTo establish criteria for construction, renovation and maintenance regarding infection prevention and control measures.
TITLE/DESCRIPTION: Construction, Renovation and Maintenance, Infection Prevention and Control Measures DEPARTMENT: All Departments PERSONNEL: All Personnel EFFECTIVE DATE: 2/08, REVISED: 2/09, 2/10, 6/11,
More informationOrientation Program for New Infection Control Professionals
Orientation Program for New Infection Control Professionals Module 10: Construction and Renovation Orientation Program for New Infection Control Professionals Table of Contents Module 10: Construction
More informationForm 9: Infection Control Preventive Measures Level 4
Form 9: Infection Control This form is filled out by the construction planning team or designated person(s) to identify the required preventive measures for the activity described in Form 1 Infection Control
More informationUniversity Health Network Infection Prevention and Control Requirements during Construction, Renovation and Building Maintenance
University Health Network Infection Prevention and Control Requirements during Construction, Renovation and Building Maintenance Introduction University Health Network follows the Canadian Standard Association
More informationConstruction in Healthcare Facilities
Construction in Healthcare Facilities Short description This section outlines the requirements to effectively conduct construction activities in healthcare facilities. Contact person Andrew Richardson
More informationResource Center. Investigation Areas
Investigation Areas Depth Study: Re-Phasing The Project is a Phased project. The main focus of this analysis is rephasing the project with ICRA requirements in mind. I am looking to reduce the cost of
More informationSection Infection Control Procedures. Part 1 - General
Section 01 35 33 Infection Control Procedures Part 1 - General 1.1 RELATED DOCUMENTS A. All of the Contract Documents, as listed on the Table of Contents and including General and Supplementary Conditions
More informationFacility Manager Basic Training: Infection Prevention and Control
Facility Manager Basic Training: Infection Prevention and Control 1 Presented by: Lorrie J. Elizarraraz, MPA CHSP CHEP Safety Management Services, Inc. Infection Prevention and Control What is infection
More informationCivista Medical Center Thad Maugle RESEARCH. The construction at Civista Medical Center consists of three phases; a main
RESEARCH Problem The construction at Civista Medical Center consists of three phases; a main building addition, a vertical expansion of the existing building, and selective renovations. All three areas
More informationConstruction ABHR: Additions, Blueprints, Hoarding and Renovations. Jim Gauthier, MLT, CIC Senior Clinical Advisor, Infection Prevention
Construction ABHR: Additions, Blueprints, Hoarding and Renovations Jim Gauthier, MLT, CIC Senior Clinical Advisor, Infection Prevention Objectives Review dust barriers and Z317.13 remediation issues Discuss
More informationDUQUESNE UNIVERSITY ASBESTOS OPERATIONS & MAINTENANCE PROGRAM
DUQUESNE UNIVERSITY ASBESTOS OPERATIONS & MAINTENANCE PROGRAM Revised January 2017 Prepared by: Environmental Health and Safety Department TABLE OF CONTENTS Page Introduction 1 Scope 1 Policy Statement
More informationADDENDUM NO. 03 SEPTEMBER 13, 2017 THE SOLICITATION MENTIONED ABOVE IS AMENDED AS SET FORTH BELOW.
J Health Science Center- School of Public Health ADDENDUM NO. 03 ADDENDUM NO. 03 SEPTEMBER 13, 2017 PROJECT: FROM: TO: School of Public Health MEP Renovation 6117 Richmond Ave. Houston, Texas 77057 Prospective
More informationA COMPLETE GUIDE TO HOSPITAL ANTEROOMS. A Complete Guide to Hospital AnteRooms
A COMPLETE GUIDE TO HOSPITAL ANTEROOMS TAKEAWAYS FROM THESE SLIDES, YOU WILL LEARN: What an anteroom is and why healthcare facilities need and utilize them Effective uses for an anteroom in the healthcare
More informationUniversity of Toronto Asbestos Management Program PROCEDURAL CHECKLIST FOR TYPE 1 ASBESTOS ACTIVITIES
University of Toronto Asbestos Management Program PROCEDURAL CHECKLIST FOR TYPE 1 ASBESTOS ACTIVITIES Project Description: Date Work Conducted: Completed by: (Name and Dept) NOTIFICATION/AWARENESS: 1.
More informationJohn F. Koerner, MPH, CIH
Critical Elements of Containment and Ventilation Practice for Healthcare Microbial Remediation John F. Koerner, MPH, CIH Vice President, Environmental Sciences Compliance Environmental International, Inc.
More informationLOWE S INSTALLER LRRP CHECKLIST FOR RENOVATIONS PERFORMED IN PRE-1978 HOUSING AND CHILD-OCCUPIED FACILITIES
LOWE S INSTALLER LRRP CHECKLIST FOR RENOVATIONS THE PURPOSE OF THIS FORM IS TO DOCUMENT COMPLIANCE WITH THE U.S. ENVIRONMENTAL PROTECTION AGENCY S LEAD RENOVATION, REPAIR, AND PAINTING RULE ( RRP RULE
More informationThese procedures are to be followed by all persons required to perform the following work:
These procedures are to be followed by all persons required to perform the following work: Entry into any ceiling space above which an asbestos-containing fireproofing or thermal insulation is present.
More informationCertification Number: NAT Lead Renovation, Repair and Painting Program
Certification Number: NAT-117534-2 Lead Renovation, Repair and Painting Program August 2018 Lead Renovation, Repair and Painting Program TABLE of CONTENTS I. Purpose II. Risk Identification III. Responsibilities
More informationLevels of Risk. TRAPIC 2016 Fall Conference Oct. 7, Construction Mgmt. and Infection Control, Andrew Streifel 1
Construction Management and Infection Control Andrew Streifel Hospital Environment Specialist strei001@umn.edu Objectives for Infection Control during Construction in Healthcare Facilities Respectful of
More informationConstruction in Healthcare facilities- What you need to know
Construction in Healthcare facilities- What you need to know Objectives 1. Describe the important role Infection Prevention plays in construction/renovation in healthcare facilities 2. Examine the components
More informationContractor s Manual
Improving health, comfort and life. 2015-2016 Contractor s Manual First Printing August 28, 2003 Last Revision May 29, 2014 Table of Contents Kalispell Regional Healthcare Contacts 2 Introduction 3 Point
More informationSection Asbestos Removal
Section Cover Page Section 02 82 33 2017-10-01 Use this Section to specify removal of materials containing asbestos, as listed below. Always use in conjunction with Section 02 82 01 - Asbestos Control
More informationAsbestos Abatement Standard Procedures Indoor Environment Group, Inc.
The following work procedures are specified on all full containment asbestos abatement projects that we design. A. Preliminary Air Sampling: Many buildings contain background fiber levels prior to, or
More informationAppendix B PROCEDURES FOR REMOVAL OF MOULD-CONTAMINATED MATERIALS
Appendix B PROCEDURES FOR REMOVAL OF MOULD-CONTAMINATED MATERIALS The following procedures are presented as a guide. Comprehensive site-specific technical specifications for the removal of mould-contaminated
More informationConstruction Indoor Air Quality (IAQ) Management Plan
Denver School of Science & Technology Middle School 2000 Valentia Street Denver, CO 80238 Telephone: 303-643-5775 Main Fax: 303-673-5776 Construction Indoor Air Quality (IAQ) Management Plan Denver School
More informationSTART WORK NOTIFICATION
START WORK NOTIFICATION This form must be submitted at least 3 buisness days before beginning work to the Rhode Island Department of Health by email at leadprogram@health.ri.gov or by fax at 401-222-2456.
More informationInterior Containment: Limit Access and Post Signs
Interior Containment: Limit Access and Post Signs Notify residents to stay away from the work area. Do not allow residents or pets near the work area. Do not allow eating, drinking, or smoking in the work
More informationIn general, the management plan development process consisted of:
NWASCO SCHOOL DISTRICT #21 ASBESTOS MANAGEMENT PLAN PART I: GENERAL PROVISIONS OF THE MANAGEMENT PLAN 1.0 INTRODUCTION This Asbestos Management Plan was developed in accordance with the United States Department
More informationEPA s New Renovation, Repair and Painting Rule
When is Compliance with the EPA Renovation, Repair, and Painting Rule Required? Scope of Rule: Renovation, repair and painting activities on target housing or child-occupied facility built before 1978
More informationSECTION OSHA REQUIREMENTS - SAFETY AND HEALTH REGULATIONS INFECTION CONTROL GUIDELINES VAMC Salisbury North Carolina
SECTION 01 06 10 OSHA REQUIREMENTS - SAFETY AND HEALTH REGULATIONS INFECTION CONTROL GUIDELINES VAMC Salisbury North PART 1 - OSHA REQUIREMENTS 1.1 GENERAL A. Contractors are required to comply with the
More informationWork Practice for Penetrating or Removing Wallboard Systems with <1% Asbestos
University of Washington Facilities Services Maintenance & Alterations 9.5.02 Work Practice for Penetrating or Removing Wallboard Systems with
More informationIndoor Air Quality Management Plan for LEED
Terminal Development Program Contract 1: 201301B San Diego Airport Terminal 2 West Expansion Indoor Air Quality Management Plan for LEED Prepared by HVAC Design Builder: California Comfort Systems USA
More informationProject 6668 Second beach Concession-Stanley Park Drive,Vancouver, BC Division 02080
PART 1 GENERAL 1.0 Instructions To Bidders Hazardous Materials Contractors are responsible for the information as provided in the City of Vancouver Invitation to Tender including all available documents,
More informationMold Remediation. Containment guidelines: based on the size of the infected area.
Mold Remediation Containment guidelines: based on the size of the infected area. Level 1 (10 sq. ft. or less): e.g. ceiling tiles, small areas on walls Moldy materials that can be cleaned should be cleaned
More informationAPPE NDIX F TY PE 2 ASBE STOS WORK PROCEDURES
APPE NDIX F TY PE 2 ASBE STOS WORK PROCEDURES TY PE 2 WOR K PR OCE DUR ES These procedures are to be followed by all maintenance personnel and contractors performing the following work at KPDSB buildings.
More informationAsbestos Exposure. COMMONWEALTH SCAFFOLD Quality Scaffolding Across New England
Asbestos Exposure Safety and Health Regulations for Construction Standard 29 CFR Part 1926.1101 Presented by: Allied Insurance Brokers, Inc. 2010 Zywave, Inc. All Rights Reserved. Asbestos Exposure: Agenda
More informationAsbestos Management Program
Oct. 10/06 Oct 10/06 1/13 Table of Contents 1 INTRODUCTION...2 2 PURPOSE...2 3 SCOPE...2 4 ROLES & RESPONSIBILITIES...2 5 INVENTORY...6 6 ACCESS CONTROL...6 7 INSPECTION...6 8 CLASSIFICATIONS OF ASBESTOS
More informationNew Montgomery County Elementary School. Construction Indoor Air Quality Management Plan IEQc3.1 IAQ Plan During Construction
New Montgomery County Elementary School Construction Indoor Air Quality Management Plan IEQc3.1 IAQ Plan During Construction LEED certification promotes environmentally friendly buildings and sites through
More informationCertified Renovator Training Hands-On Skills Assessment Date: Address: City & State Student Name: Student Signature:
Certified Renovator Training Hands-On Skills Assessment Date: Address: City & State Student Name: Student Signature: Skill Skill Set Description #1 Using EPA Recognized Test Kits and Paint Chip Sample
More informationEnvironmental Infectious Disease Management in Healthcare Facilities Dr. Andrew Streifel, University of Minnesota A Webber Training Teleclass
Environmental Infectious Disease Management in Healthcare Facilities Andrew J. Streifel Hospital Environment Specialist University of Minnesota strei001@umn.edu Guidelines for Environmental Infection Control
More informationEPA s Lead Program Rule At-A-Glance
EPA s Lead Program Rule At-A-Glance FLOW CHART 1: Do the Requirements Apply to the Renovation? If you will be getting paid to do work that disturbs painted surfaces in a pre-1978 home, apartment building,
More informationPROCEDURES FOR REMEDIATION OF FUNGI IN INDOOR ENVIRONMENTS LEVEL I:
OFFICE OF ENVIRONMENTAL HEALTH AND SAFETY FACILITIES AND SERVICES PROCEDURES FOR REMEDIATION OF FUNGI IN INDOOR ENVIRONMENTS LEVEL I: SMALL ISOLATED AREA (less than 10sq. ft.) -- e.g. CEILING TILES AND
More informationBP U.S. Pipelines and Logistics (USPL) Safety Manual Page 1 of 8
Safety Manual Page 1 of 8 1. Purpose This policy assists in protecting USPL workers from exposure to lead and to gain compliance with state and federal regulations. 2. Scope The OSHA requirements and this
More information8/19/2016 ASSESSMENT & RESTORATION OF SMOKE DAMAGE. Smoke Exposure After a Fire
ASSESSMENT & RESTORATION OF SMOKE DAMAGE Ed Light, CIH & Veronica Stanley, MSPH, CIH Building Dynamics, LLC AHMP Conference Washington DC August 29, 2016 Smoke Exposure After a Fire Common source of indoor
More informationPoisonings from Housing. A Regulatory Update
Poisonings from Housing Renovations o Containing Lead Paint: A Regulatory Update Delaware Healthy Homes Summit March 12, 2014 Presented by: Demian P. Ellis, USEPA Region 3 What will be covered Overview
More information"ASBESTOS AWARENESS IN THE WORKPLACE"
MAJOR PROGRAM POINTS "ASBESTOS AWARENESS IN THE WORKPLACE" Training For THE OSHA ASBESTOS STANDARD Quality Safety and Health Products, for Today...and Tomorrow Outline of Major Points Covered in the "Asbestos
More informationBP U.S. Pipelines and Logistics (USPL) Safety Manual Page 1 of 8
BP U.S. Pipelines and Logistics (USPL) Safety Manual Page 1 of 8 1. Purpose This policy assists in protecting USPL workers from exposure to lead and to gain compliance with state and federal regulations.
More informationROLLING RIVER SCHOOL DIVISION REGULATION
ROLLING RIVER SCHOOL DIVISION REGULATION Custodian Job Description GDAS/R Position Title: Reports To: Custodian School Principal and Maintenance Supervisor Job Purpose and Objectives To contribute to the
More informationHealthcare construction
Healthcare construction Role of the Infection Preventionist FIRAS R. ZABANEH, MT( ASCP), CIC, CIE OCT 1, 2015 ( N O T H I N G T O D I S C L O S E ) Current state Many Infection Preventionists view their
More informationAsbestos Awareness Program
Safety Manual 1 of 9 Safety Manual Sect: 1.0 Purpose 2.0 Scope Rel. Date: Last Review: This program covers Ardent policy related to asbestos, either discovered or suspected in the workplace. Ardent recognizes
More informationBig Dog Construction Services, Inc Silica Exposure Control Program
Big Dog Construction Services, Inc Silica Exposure Control Program 1.0 Applicability and Scope 1.1 Applicability This Written Exposure Control Plan (Plan) applies to Big Dog Construction Services Inc.
More informationINTERNATIONAL STANDARDS FOR PHYTOSANITARY MEASURES
INTERNATIONAL STANDARDS FOR PHYTOSANITARY MEASURES ISPM 34 DESIGN AND OPERATION OF POST-ENTRY QUARANTINE STATIONS FOR PLANTS (2010) FAO 2010 Design and operation of post-entry quarantine stations for plants
More informationINTRODUCTION TO THE PROGRAM
INTRODUCTION TO THE PROGRAM Structure and Organization Information in this program is presented in a definite order, so that employees will see the relationships between the various groups of information
More informationWESTERN CONNECTICUT STATE UNIVERSITY ASBESTOS ABATEMENT PROCEDURE E-101
WESTERN CONNECTICUT STATE UNIVERSITY ASBESTOS ABATEMENT PROCEDURE E-101 Issued 6/1/95 Revised 11/08/2004; 3/6/06 Please direct any questions or comments about the applicability of this document to Luigi
More informationProject 6668 Kerrisdale Senoirs Centre-5851 West Boulevard,Vancouver, BC Division 02080
PART 1 GENERAL 1.0 Instructions To Bidders Hazardous Materials Contractors are responsible for the information as provided in the Invitation to Tender including all available documents, meeting minutes,
More informationUI Procedures for Asbestos Management
UI Procedures for Asbestos Management The University of Iowa Rev.10/22/08, 10/15/09 These procedures apply to employees and contractors involving the identification, work on, removal, or repair of asbestos-containing
More informationPost Abatement Project Report - Sample Draft Form:
Post Abatement Project Report - Sample Draft Form: 3701-3215 (B) (B) Each lead abatement contractor or lead abatement project designer shall issue a report for each lead abatement project performed. The
More informationLead-Safe Weatherization Updates & RRP Similarities/Differences
Lead-Safe Weatherization Updates & RRP Similarities/Differences Rob DeSoto, DOE-Golden Mike Vogel, Montana State University MT Wx Training Center 1 Lead used in paints for many years. Most problems with
More informationMold Remediation. 1. Purpose and Requirements. 2. Scope. 3. General Responsibilities HS13_IAQ_SOP_002. Occupational Safety & Health
Occupational Safety & Health HS13_IAQ_SOP_002 1. Purpose and Requirements When mold growth occurs indoors, adverse health problems may be reported by some building occupants, particularly those with allergies
More informationDocument Supplementary Instructions
Document 00 22 00 - Supplementary Instructions The University of Toledo Facilities and Construction www.utoledo.edu 2801 W. Bancroft Street Toledo, OH 43606 v: 419-530-1427 f: 419-530-1401 Certifications
More informationCADMIUM AWARENESS Revision Date: 04/2017
CADMIUM AWARENESS 7.1 PURPOSE 7.1.1 The purpose of this policy is to provide guidelines for safely working with cadmium. It includes provisions for training, PPE guidelines, monitoring, medical surveillance,
More informationAsbestos During Brake and Clutch Service Work Self Inspection Checklist
Optional Information Name of School: Date of Inspection: Vocational Program/Course/Room: Signature of Inspector: Asbestos During Brake and Clutch Service Work Self Inspection Checklist Guidelines: This
More informationLANSING HOUSING COMMISSION NOTICE OF REQUEST FOR PROPOSALS RFP No
LANSING HOUSING COMMISSION NOTICE OF REQUEST FOR PROPOSALS RFP No. 103-111-5-2016 Waterproofing lower level of house, Mold Remediation and Unit Turn Scope of Work AGENCY CONTACT PERSON PRE-PROPOSAL WALK
More informationLead-based Paint Regulations Webinar November 21,
Lead-based Paint Regulations Webinar November 21, 2008 www.nmhc.org Lead-Based Paint Renovation, Repair, and Painting Overview of Final Rule November 21, 2008 The Renovation, Repair, and Painting Rule
More informationAsbestos Management Program
Asbestos Management Program The University Of Iowa Environmental Health & Safety 122 Grand Avenue Court Iowa City, IA 52242-1000 Phone: 319-335-8501 Date Revised/Reviewed: 5/8/2018 Table of Contents 1.
More informationSafety & Risk Management Policies and Procedures Mold Policy and Procedure Safety & Risk Management Policies and Procedures
Safety & Risk Management Policies and Procedures Title: Mold Policy Date: August 2013 Rationale: Mold is a common allergen and in certain cases where significant mold growth is uncontrolled and not remediated,
More informationSECTION INDOOR AIR QUALITY MANAGEMENT PLAN. A. PART A and DIVISION 1 of PART B are hereby made a part of this SECTION.
SECTION 018119 PART 1 GENERAL 1.01 GENERAL REQUIREMENTS A. PART A and DIVISION 1 of PART B are hereby made a part of this SECTION. B. Examine all conditions as they exist at the project prior to submitting
More informationResource Center. Holy Redeemer Hospital Meadowbrook, PA
Holy Redeemer Hospital Brad Pietropola Architectural Engineering Construction Management Option Spring 2004 Holy Redeemer Hospital Project Team Owner Holy Redeemer Health System Occupant Holy Redeemer
More informationWater Damage Management
Water Damage Management in Healthcare Michael Buck University of Minnesota Environmental Health and Safety buckx001@umn.edu Water Damage Management Reactive respond to water incident determine extent of
More information40 CFR 763 THREE-YEAR AHERA ASBESTOS RE-INSPECTION SUMMARY REPORT INDIAN HEAD ELEMENTARY SCHOOL
69 Bridge Street Dedham, MA 02026 Phone 781.251.0040 Fax 781.251.0901 40 CFR 763 THREE-YEAR AHERA ASBESTOS RE-INSPECTION SUMMARY REPORT for INDIAN HEAD ELEMENTARY SCHOOL 726 Indian Head Street Hanson,
More informationLOS ANGELES COMMUNITY COLLEGES OFFICE OF THE CHANCELLOR ADMINISTRATIVE REGULATIONS INDEX NUMBER B-4
LOS ANGELES COMMUNITY COLLEGES OFFICE OF THE CHANCELLOR ADMINISTRATIVE REGULATIONS INDEX NUMBER B-4 REFERENCE: ISSUE DATE: January, 1983 CHANGES: TOPIC: Asbestos INITIATED BY: Business Services DATE OF
More informationAsbestos in the Workplace: A Guide to Removal of Friable Asbestos Containing Materials
Asbestos in the Workplace: A Guide to Removal of Friable Asbestos Containing Materials Revised November 21, 2013 Application Code of Practice Where asbestos is present or believed to be present in a workplace
More informationASBESTOS MANAGEMENT PROGRAM. Carleton University
ASBESTOS MANAGEMENT PROGRAM Carleton University November Oct 10/06 2/25 Table of Contents 1 INTRODUCTION... 3 2 PURPOSE... 3 3 SCOPE... 3 4 ROLES & RESPONSIBILITIES... 3-7 5 INVENTORY... 7 6 ACCESS CONTROL...
More informationTown of Falmouth FEMA Cost Breakdown Worksheet For Substantial Improvement / Damage COSTS FOR SUBSTANTIAL IMPROVEMENTS / REPAIR OF SUBSTANTIAL DAMAGE:
S FOR SUBSTANTIAL IMPROVEMENTS / REPAIR OF SUBSTANTIAL DAMAGE: Included Costs: Items that must be included in the costs of improvement or costs to repair are those that are directly associated with the
More informationRRP Form Checklist. Prior to the Job Beginning. During the Job. After the Job
RRP Form Checklist Prior to the Job Beginning Sample Pre-Renovation Form - Issue the Renovate Right Pamphlet At least 7 days prior for an EPA regulated job and at least 15 days prior to a HUD regulated
More informationASBESTOS CONTAINING MATERIALS (ACM) REFERENCE GUIDE. Environmental Health & Safety Office
ASBESTOS CONTAINING MATERIALS (ACM) REFERENCE GUIDE by Environmental Health & Safety Office ENVIRONMENTAL HEALTH AND SAFETY OFFICE (EHSO) F ORT G ARRY C AMPUS 191 FRANK KENNEDY CENTRE Telephone: 474-6633
More informationAsbestos Management Program
ENVIRONMENTAL HEALTH & SAFETY Reed College 3203 Southeast woodstock boulevard Portland, Oregon 97202-8199 Asbestos Management Program Effective Date: 6/16/2009 Revision Dates or Last Date: 2/2016 I. Purpose...
More information40 CFR 763 THREE-YEAR AHERA ASBESTOS RE-INSPECTION SUMMARY REPORT
69 Bridge Street Dedham, MA 02026 Phone 781.251.0040 Fax 781.251.0901 40 CFR 763 THREE-YEAR AHERA ASBESTOS RE-INSPECTION SUMMARY REPORT for WHITMAN MIDDLE SCHOOL 100 Corthell Avenue Whitman, MA 02382 Initial
More informationAnticipated ICR 56 Revisions. Relating to Fire/Life Safety & Other Significant Issues
Anticipated ICR 56 Revisions Relating to Fire/Life Safety & Other Significant Issues Introduction Anticipated Timeframe for ICR 56 Revisions ICR 56 Fire & Life Safety Issues Cleanup of uncontrolled asbestos
More informationPrepared by: LBS HSE Approved by: Geoff Atkins Issue Date: New Policy
The University of British Columbia Land and Building Services MOULD PROCEDURE Work Procedure I-B-46 Prepared by: LBS HSE Approved by: Geoff Atkins Issue Date: New Policy Replaces: 1.0 APPLICATION Moulds
More informationAsbestos in the Home
Asbestos in the Home This document will help you understand asbestos: what it is, its health effects, where it is in your home, and what to do about it. What Is Asbestos? Asbestos is a mineral fiber. It
More informationSite Specific Hazardous Material Abatement Work Plan
Site Specific Hazardous Material Abatement Work Plan Jobsite Location: Pier 31 Building and Roof Repair Project Port of San Francisco San Francisco, California Prepared By: North Tower Environmental, Inc.
More informationLead Based Paint Policy
Lead Based Paint Policy 1. Guidance for the removal or maintenance of lead-based paint has undergone changes that affect the painting industry. The U.S. Department of Housing and Urban Development (HUD)
More informationDevin Learn Construction Management AE Senior Thesis
Devin Learn Construction Management AE Senior Thesis 5 th and 6 th Floor Fit-Out & Cardiac Elevator Addition Introduction Vs. Retro- Pre-Cast Floor System s at ICRA Partitions and Conclusions Questions
More informationGENERIC ASBESTOS OPERATION AND MAINTENANCE (O&M) PLAN
Environmental Sciences Corporation 25 Years of Environmental Excellence National Environmental Assessment, Compliance, Industrial Hygiene, UST/AST, Construction Management and Engineering Services GENERIC
More informationLead Safe Practices and Compliance
Lead Safe Practices and Compliance Purpose: The purpose of the Lead Policy is to ensure that activities (e.g. renovations, painting, demo, etc.) that could potentially involve disturbing or removal of
More informationSafety Policy Manual Policy No. 144
Policy: Lead Management Program Page 1 of 11 APPLICATION NYU Langone PURPOSE To protect employees, patients, students, tenants, and members of the community from exposure to lead. To comply with regulations
More informationAdv. 3.2: Asbestos Abatement Rev
ADVISORY NO. 3.2: ASBESTOS ABATEMENT TERMINOLOGY AND DEFINITIONS Abatement: Procedures to control fiber release from asbestos-containing materials, i.e., removal, encapsulation, or enclosure. Air Lock:
More informationOffice of Environmental Health and Safety 1.0 INTRODUCTION
Office of Environmental Health and Safety 1.0 INTRODUCTION Silica (SiO 2) is the second most common mineral in the earth s crust and is a major component of sand, rock and mineral ores. Silica exists in
More informationIdaho Solid Waste Association
Idaho Solid Waste Association Idaho Snow: Debris from Collapsed Buildings EPA Asbestos Requirements for Demolishing a Building John Pavitt U.S. Environmental Protection Agency Region 10, Alaska Operations
More informationGood indoor air quality (IAQ) management has become paramount in the construction industry as study
Creating and Maintaining Good Indoor Air Quality Good indoor air quality (IAQ) management has become paramount in the construction industry as study after study shows that employee productivity and health
More information