NIPSCO MCGS PRIMARY 2 CCR CLOSURE PLAN

Size: px
Start display at page:

Download "NIPSCO MCGS PRIMARY 2 CCR CLOSURE PLAN"

Transcription

1 NIPSCO MCGS PRIMARY 2 CCR CLOSURE PLAN CLOSURE PLAN Submitted To: Northern Indiana Public Service Company Michigan City Generating Station 101 Wabash Street Michigan City, Indiana Submitted By: Golder Associates Inc. 670 North Commercial Street, Suite 103 Manchester, NH USA A world of capabilities delivered locally December 2015 Project No.: Golder, Golder Associates and the GA globe design are trademarks of Golder Associates Corporation

2 December 2015 i Project No.: Table of Contents 1.0 BACKGROUND Impoundment Description Closure Narrative Notifications HISTORICAL AMOUNT AND EXTENT OF CCR Maximum Inventory of CCR Extent of CCR CLOSURE PERFORMANCE STANDARD Closure Plan and Approach Drainage and Stabilization of CCR Final Cover System Liner Subgrade Geomembrane Liner Geocomposite Drainage Layer Vegetative Support/Protection Layer Stormwater Management CLOSURE PROCESS Protection of Impoundment Berms and Utilities Dewatering, Stabilization, and Placement of CCR Subgrade Installation of Final Cover System Stormwater Management Field Oversight and CQA Testing POST-CLOSURE CLOSURE SCHEDULE CLOSURE CERTIFICATION List of Figures Figure 1 Site Location Map Figure 2 Primary 2 Existing Conditions Figure 3 Primary 2 Final Closure Grading Plan Figure 4 Primary 2 Cross Sections Figure 5 Closure Schedule List of Exhibits Exhibit A Statement of Certification

3 December Project No.: BACKGROUND The Northern Indiana Public Service Company (NIPSCO) Michigan City Generating Station (MCGS or Site) is an operating 469 MW capacity coal-fired electric generating plant that began production in Electricity is produced by a single high-pressure boiler and steam turbine-powered generator (referred to as Unit 12). MCGS, located at 101 Wabash Street in Michigan City, LaPorte County, Indiana, occupies 131 acres in a mixed industrial, commercial, and residential area along the southern shoreline of Lake Michigan (refer to Figure 1, Site Location Map). Prior to October 19, 2015, NIPSCO discontinued the addition of wastes regulated under the CCR Final Rule to Primary Settling Basin #2 (Primary 2). NIPSCO intends to close Primary 2 in-place and in conformance with the requirements of 40 Code of Federal Regulations (CFR), Part (b). This document represents the closure plan, including necessary engineering certification (refer to Exhibit A), for the impoundment consistent with the requirements of 40 CFR, Part Impoundment Description As shown on Figures 1, 2, and 3, Primary 2 is a roughly 3-acre structure, located in the southwestern portion of the Site. Primary 2 was constructed in the early 1970 s and is approximately 435 feet long, ranging from approximately 230 to 290 feet wide, with a maximum theoretical capacity of approximately 70,000 cubic yards (cu yd). Historical figures indicate the floor and perimeter embankments of Primary 2 were constructed from compacted sand fill and the floor and sideslopes were lined with a one foot thick layer of crusher run blast furnace slag. The exterior sideslope of the western embankment was lined with eight inch riprap. The embankment that forms Primary 2 is approximately 14 feet high on the outside slope and approximately 20 feet high on the inside slope. Both the interior and exterior slopes are 2.5H:1V. The crest of the embankment is approximately 15 to 21 feet wide and is at approximately El The top of the crusher run blast furnace slag lining the floor of the impoundment is at approximately El. 591 and the surrounding ground outside the embankments varies from approximately El. 596 to El When active, Primary 2 received fly ash, economizer ash, recirculated water from the ash sluice system, boiler blow down, and wastewater from the boiler drains sluiced directly from the generating station. Primary 2 was formerly operated on an alternating basis with Primary Settling Basin #1 (Primary 1), now out of service. Primary 2 discharged water, which remained after the majority of the solids settled out of the aqueous solution, to Secondary 2, also out of service. Periodically during its operating life, as Primary 2 approached or reached capacity, CCR discharge to it was halted and redirected to former Primary 1. After the contents of Primary 2 were allowed to dry, the dewatered material was excavated and

4 December Project No.: transported off-site for disposal. Currently Primary 2 contains both CCR and liquids. Water levels within Primary 2 were and continue to be manually controlled by MCGS operations personnel. 1.2 Closure Narrative Pursuant to the requirements of 40 CFR, Part (c) (1), development of the Primary 2 closure plan, including this closure narrative, was completed by December 17, Closure activities at the inactive surface impoundment are anticipated to begin in the spring of 2017, in accordance with all requisite notifications and consistent with the closure schedule discussed in Section 6.0 of the closure plan. Closure of Primary 2 will be by leaving CCR in-place and constructing a CCR Final Rule compliant cover system. Key steps of the closure process may include, but are not necessarily limited to, collection and interpretation of geotechnical data as necessary to support design activities, development of conceptual and final designs, disabling operational infrastructure, dewatering and grading of impoundment contents, installation of stormwater diversion and outlet structures, preparation of a suitable subgrade for the final cover system, construction of final cover system and additional drainage as necessary, seeding, mulching, and maintenance and repair until the vegetative layer of the cover system is established. Subsequent to completion of all construction and verification activities, notification and engineering certification of closure will be performed. 1.3 Notifications The closure process requires a series of notifications to be completed prior to, during, and subsequent to closure activities. Pursuant to 40 CFR, Part (c), by no later than December 17, 2015, NIPSCO will prepare and place in the MCGS facility s operating record a notification of intent to initiate closure of the inactive Primary 2 surface impoundment. This notification will include a narrative discussion of the closure approach, a closure schedule, and required engineering certifications. Periodic progress reports as required pursuant to 40 CFR, Part (c) (1) (i) and (ii) will be completed and placed in the facility s operating record as will a notification of completion of closure and the engineering certification pursuant to 40 CFR, Part (c) (3). 2.0 HISTORICAL AMOUNT AND EXTENT OF CCR Pursuant to 40 CFR, Part (b) (iv and v), multiple resources were reviewed to estimate the maximum inventory of CCR ever on-site over the active life of the unit and to estimate the largest area of Primary 2 requiring a final cover. These resources included: historical construction drawings, an existing conditions topographic survey drawing, recent field investigation findings, historical aerial photographs, and discussions with MCGS facility personnel.

5 December Project No.: Maximum Inventory of CCR According to MCGS facility personnel, between the time of construction of Primary 2 in the early 1970 s and approximately 1990, MCGS operated using a wet fly ash collection and management system. MCGS personnel estimate that during this timeframe Primary 2 was dredged of accumulated CCR at a likely frequency of once every two to three years. Since about 1990, the plant has operated a dry fly ash collection system, so CCR accumulation and the frequency of required dredging has been greatly reduced. Over the life of Primary 2 there have been no known or documented releases of CCR and the CCR has been maintained at or below the maximum operating capacity of two feet below the top of the embankment. During the summer of 2015, Golder performed a geophysical survey within Primary 2 to assess the base (bottom) elevation of the impoundment and thickness of CCR materials. The geophysical survey indicates that the base of the impoundment varied from approximately El. 586 to El. 595 with an average base elevation of 591. The top of CCR materials was estimated to vary between El. 593 and El This results in an estimated CCR material thickness of two to nine feet, with an estimated volume of 19,000 cu yd. Marbach, Brady, & Weaver, Inc. performed a topographic survey of Primary 2 in July The existing conditions survey drawing indicates that the water level in the pond at that time was at approximately El. 607, two feet below the crest of the berm (i.e., maximum operating capacity of Primary 2). Therefore at the time of the survey and based on the data collected from the geophysical survey, there was approximately 8,000,000 gallons of free liquid (above crusher run blast furnace slag and CCR sediments) within Primary Extent of CCR Based on review of historical drawings, photographs, and discussions with MCGS personnel, two vertical feet below the inside crest of the perimeter embankment berm, as shown on the existing conditions drawing (Figures 2 and 3), represents the largest boundary of the CCR unit, with the exception of the southeast corner of the pond. During operation, it appears that NIPSCO pushed materials into the southeastern corner of the pond creating the flat plateau area that is shown on the existing conditions drawings (Figure 2). Since the current topography along the southeastern corner appears to no longer represent the largest limit of CCR, the limit of the final cover will be extended in this corner to include the estimated original limit of the impoundment in this area. This estimated original limit of CCR, which represents the largest boundary of the CCR unit ever requiring a final cover, pursuant to 40 CFR, Part (b) (1) (v) is also shown on Figure 3 and is estimated to be approximately 3.0 acres. 3.0 CLOSURE PERFORMANCE STANDARD Consistent with the requirements of 40 CFR, Part (b) (1-4), NIPSCO will close Primary 2 by leaving CCR in-place. Closure in-place will be accomplished by installation of a final cover system that

6 December Project No.: will minimize or eliminate infiltration into the waste, minimize or eliminate releases of CCR into the environment, promote positive drainage away from the CCR unit thus impeding future collection of water or sediments over the footprint of the impoundment, provide a stable cover that minimizes the need for post closure maintenance, and can be constructed in a timely manner using sound engineering practices. NIPSCO intends to construct the closure of Primary 2 following an alternative final cover system design as allowed under 40 CFR, Part (d) (3) (ii). 3.1 Closure Plan and Approach Following dewatering, CCR sediments will be dried and stabilized within the existing confines of Primary 2. As shown on Figure 3, NIPSCO intends to construct an approximately 3.7 acre final cover system encompassing the limits of Primary 2 with a uniform cross-slope graded to drain from west to east. Under the proposed final cover design, all stormwater drainage will shed to the east off the Primary 2 final cover and onto the interior facility access road system which in this area currently discharges to the Final Pond. Grading along the western perimeter is planned to match the existing top of embankment elevations and slope downward to the east with a uniform two percent cross-slope extending to the existing grades near the base of the outside of the eastern embankment. Grading along the southern and northern embankments is also planned to match the existing top of embankment elevations and then slope downward with a uniform slope of twenty percent (5H:1V) until intersecting the cross-sloping grades. To minimize the encroachment of final cover activities on the existing Transmission Line Tower T8463, located adjacent to the northeastern corner of the pond, the grading in the northeastern corner will tie in two feet below the existing top of embankment. This corresponds to the maximum operating capacity elevation of the pond. In order to tie into surrounding grades along the eastern limit of the final cover, the majority of the eastern embankment will need to be removed. NIPSCO intends to excavate and reuse the embankment material as additive material for drying and stabilization of the CCR sediments. If necessary, additional backfill will be placed above the stabilized CCR/backfill materials to achieve the proposed CCR subgrade elevations. Following CCR subgrade preparation, the final cover liner system will be installed and vegetated. 3.2 Drainage and Stabilization of CCR Prior to the start of closure construction earthwork, free liquid will be removed from Primary 2. Dewatering liquid will be conveyed and discharged into the Final Pond where it will be held and discharged under the current NPDES permit. Following removal of the free liquid, the CCR materials will be pushed into stockpiles or windrows for drying and subsequent blending. The excavated eastern embankment soils will be blended with the CCR materials to achieve a stable composite backfill material. NIPSCO also intends to use facility-generated

7 December Project No.: boiler slag as additional backfill material consistent with the beneficial use provisions of the CCR Final Rule. Once the composite backfill material is processed and stability is achieved, the material will be placed and compacted in lifts to the approved final cover CCR subgrade elevations. All drying, blending, and stabilization operations will be performed within the existing impoundment limits. 3.3 Final Cover System The proposed final cover section meets the engineering property requirements outlined in the alternative final cover system design as allowed under 40 CFR, Part (d) (3) (ii) including a permeability less than or equal to 1x10-5 cm/sec, an equivalent reduction in infiltration as provided by a minimum of 18 inches of earthen material, and an equivalent erosion layer that provides the same protection from wind or water erosion as provided by a minimum of 6 inches of earthen material capable of sustaining native plant growth. NIPSCO proposes the following alternative final cover section for the in-place closure of Primary 2. Refer to Figure 4 for the Final Closure Typical Section. Primary 2 Final Cover System (top to bottom) 18 min. Vegetative Support/Protection Layer Geocomposite Drainage Layer Geomembrane Liner 6 Liner Subgrade A detailed description of each layer, described in the order of installation (bottom to top) is included below Liner Subgrade The proposed final cover section includes installation of a minimum six-inch thick liner subgrade layer above the CCR subgrade (reference Section 3.2) surface and below the geomembrane liner. The purpose of this layer is to provide protection for the geomembrane liner material from any oversized or angular particles that may be present in the CCR subgrade material backfill. The liner subgrade material shall be a uniform sand, or equivalent, with maximum particle size of one-inch Geomembrane Liner A geomembrane liner will be placed above the liner subgrade material. Geomembrane liners are essentially impermeable and will act as a low permeability layer and infiltration barrier for the final cover system. The liner will be terminated and secured on all sides in a buried anchor trench which will further inhibit any potential releases of CCR material from beneath the cover system. The geomembrane liner

8 December Project No.: material shall be a PVC, LLDPE, HDPE, or equivalent geomembrane with sufficient physical properties to meet the design requirements Geocomposite Drainage Layer A geocomposite drainage layer will be placed above the geomembrane liner. The geocomposite drainage layer will act as an infiltration drainage pathway and also provide protection to the geomembrane liner during installation of overlying soil material. The geocomposite drainage layer shall be a composite heat-bonded geotextile fabric and synthetic geonet, or equivalent. The geocomposite shall be specified with sufficient physical properties to support the design requirements, to perform in conjunction with the overlying soils to provide drainage filtration to keep silt and soil particles from clogging the flow channels, and collect and convey infiltration off the geomembrane liner Vegetative Support/Protection Layer A minimum 18-inch thick vegetative support/protection layer is proposed to be placed above the geocomposite drainage layer. The vegetative support/protection layer will serve three purposes: to protect the geosynthetic layers from equipment or vehicular loading, UV-degradation, and other unforeseen damages; to provide a suitable, nutrient rich material that is capable of supporting native plant growth that will in turn minimize erosion of the final cover materials from wind and rain; and to limit stormwater infiltration into the final cover system. The vegetative support/protection material shall be an earthen material that is enriched in organic matter and has textural and structural characteristics favorable to plant growth. The surface of the vegetative support layer will be vegetated with an approved seed and mulch mixture to control erosion, promote germination of seeds, and increase the moisture retention of the soil until permanent vegetation is established. 3.4 Stormwater Management Stormwater is currently managed at MCGS under an active NPDES Permit (No. IN ). The stormwater that currently falls within the footprint of Primary 2 is managed within the impoundment. Stormwater is collected through an outfall and conveyed by pipe away from Primary 2 and then discharged into the Final Pond. Discharge from the Final Pond discharges through Internal Outfall 301, and eventually discharges through the main facility outfall (Outfall 001) directly into Lake Michigan. Prior to Primary 2 closure construction activities, the outfall piping connection between Primary 2 and the Final Pond will be removed. Following Primary 2 final cover construction, the stormwater that falls within the footprint of Primary 2 will shed to the east by sheet flow into the interior haul road watershed area, adjacent to the coal pile. This area currently drains into the Final Pond and ultimately Lake Michigan as detailed above.

9 December Project No.: CLOSURE PROCESS 4.1 Protection of Impoundment Berms and Utilities As discussed above, Primary 2 is formed by embankment berms on all sides. The proposed final cover grading requires tying the new final cover system into the top of the embankment along the northern, western, and southern limit of the final cover and two feet below the top of the embankment in the northeastern corner. An approximately two-foot deep anchor trench will be excavated into the embankment along these three sides to secure the synthetic final cover materials. Historical construction drawings indicate that there are no existing utilities in this area along the top of the embankments. The proposed final cover grading plan requires removal of the eastern perimeter embankment to allow for stormwater drainage across the cover. Historical drawings indicate that there are at least four buried pipes ranging in diameters from 6 inches to 11 feet running beneath and parallel to the eastern perimeter embankment. Historical drawings and discussions with facility personnel suggest that the existing pipes are buried between 8 and 10 feet below the surrounding grades. Since the proposed final cover grading plan only removes the eastern embankment and does not cut into the surrounding grades, the proposed final cover activities should not pose potential damage to or compromise the integrity of the existing utilities. In addition, two transmission tower foundations are located adjacent to the northeast and southeastern corners of the final cover. Care should be taken when working around these structures and underneath the overhead electric lines. The contractor will be responsible to locate and protect all utilities prior to the start of construction. 4.2 Dewatering, Stabilization, and Placement of CCR Subgrade As discussed above, MCGS anticipates up to approximately 8,000,000 gallons of free liquid will need to be removed from Primary 2 prior to the start of construction. Dewatering will be achieved using trailer mounted pumps located at low points across the impoundment floor. Dewatering liquid will be discharged into the Final Pond where it will be held and discharged under the current NPDES permit. Following removal of the free liquid, the CCR materials will be pushed into stockpiles or windrows for drying and mixing. The stockpiles will be managed and worked such that liquid expelled from the solids during the stockpile turning/drying process can be directed to pump intakes for continued dewatering. Concurrently, the eastern embankment will be excavated to achieve final cover subgrade elevations. The excavated embankment soils will be mixed with the CCR materials to achieve a composite backfill for CCR subgrade material. It is anticipated that the CCR material will require a blending ratio between a 1:1 and 1.5:1 backfill to CCR to achieve a stable composite backfill material capable of structural support of the final cover system. NIPSCO plans to perform a bench scale testing to confirm this theoretical blending ratio prior to the completion of final design.

10 December Project No.: To achieve the proposed final cover subgrade elevations, approximately 36,000 cu yd of backfill material will be required in addition to the CCR sediments currently in the impoundment. Approximately 5,500 cu yd of excavated embankment sand will be available for use as blending backfill. Therefore additional imported backfill material, potentially including Site boiler slag as mentioned above, will be required to complete final cover construction. Depending on the observed physical characteristics of the CCR and embankment fill mixture, the additional backfill may be mixed with the CCR materials prior to placement or placed directly as backfill. The backfill material will be mixed and dried until it reaches a moisture content suitable for effective placement and compaction. All CCR subgrade backfill materials will be placed at or near the optimum moisture content and compacted in lifts to the approved final cover CCR subgrade elevations. Areas that do not achieve sufficient compaction (i.e., pumping and weaving) due to excessive water content will be removed and replaced with drier and/or coarser grained material (e.g., 3/4 inch crushed stone). All drying, mixing, and stabilization processes will be performed within the limits of the final cover. Therefore, the construction will need to be staged so that mixing operations can be performed at one end of the impoundment while placement and compaction is occurring at the other end of the impoundment. 4.3 Installation of Final Cover System Following completion and acceptance of the CCR subgrade installation, the layers of the proposed alternative final cover sections will be install as follows. 6 Liner Subgrade: The liner subgrade soil shall be placed in a single minimum six-inch thick layer. Following installation, the layer thickness shall be verified by completing a series of hand dug test pits across the footprint, or by applying an approved equivalent method. Geomembrane Liner: The liner shall be installed in panels oriented in the direction of flow. Panel seams will be welded in-situ and tested for defects. The liner will be terminated and secured in an approximately two-foot deep anchor trench. Geocomposite Drainage Layer: The geocomposite will be installed in panels oriented in the direction of flow, or as recommended by the manufacturer for maximum transmissivity. The geonet core of adjacent sheets will be zip-tied together and the top seams of the geotextile fabric will be sewn together to prevent intrusion of the materials placed above. The geocomposite will be terminated and secured within the anchor trench on the uphill side (west) and sideslopes (north and south). The downhill (east) edge will daylight across the top of the anchor trench to allow for discharge of infiltrated stormwater. Vegetative Support/Protection Layer: The vegetative support layer shall be placed in a single minimum eighteen-inch thick layer. The final surface of the vegetative support soil will be tracked perpendicular to

11 December Project No.: the direction of flow for added erosion protection and to assist in the establishment of vegetation. Following installation, the layer thickness shall be verified by completing a series of hand dug test pits across the footprint, or approved equivalent method. In addition, seeding and mulching will be applied to the surface to prevent erosion until vegetation can be established. 4.4 Stormwater Management The conceptual final cover design presented in this closure plan assumes that all Primary 2 stormwater will be managed through sheet flow across the cover. If, during final design, it is determined that stormwater control structures (i.e., tack-on swales) are required to better manage the stormwater flows, they shall be incorporated into the final design, as appropriate. 4.5 Field Oversight and CQA Testing NIPSCO intends to have full time field oversight and Construction Quality Assurance (CQA) testing performed during subgrade earthwork operations and construction of the final cover system. It is anticipated that field oversight and CQA testing duties will include: Preparation of daily field reports, which will include installed material quantity estimates; Attendance at construction progress meetings; Securing geosynthetics product information from the manufacturer s QA testing; Inventory of geosynthetic materials as they arrive on-site; Collecting samples, coordinating testing and documenting results of conformance testing for geosynthetics and soils; Preparing photographic documentation of construction; Assisting contractor with coordinating and reviewing survey for as-built record documents; and Field inspection and documentation of: Results of startup procedure for seam welders; Geomembrane non-destructive seam testing and trial seams; Panel layout and location of repairs; Collection of samples for testing on destructive samples; Seaming of geocomposite; Collection of samples for testing on soil samples; and Soil placement criteria A CQA plan detailing CQA personnel responsibilities, testing frequencies, and material/design requirements during construction will be prepared and submitted with the final design.

12 December Project No.: POST-CLOSURE NIPSCO is closing inactive surface impoundment Primary 2 through closure by leaving CCR in-place. Closure will be completed no later than April 17, 2018, pursuant to 40 CFR, Part (b). As outlined in 40 CFR, Part (a) (3), the owner/operator of an inactive CCR surface impoundment that elects to close a CCR impoundment pursuant to the requirements under 40 CFR, Part (b) is not subject to post-closure care criteria under the Federal regulations. 6.0 CLOSURE SCHEDULE NIPSCO intends to complete closure of Primary 2 within one construction season, between May 2017 and September The currently proposed schedule plans for closure to be completed approximately seven months prior to the April 17, 2018 closure deadline as specified by 40 CFR (b). This schedule is subject to change and dependent upon availability of imported construction materials, available labor and equipment at the time of construction, favorable weather conditions, and minimal unanticipated delays. Should delays arise, there is time in the schedule to allow for time extensions and completion of construction and closure certification by the final regulatory deadline. The table below outlines the major milestones required for closure. Refer to the Figure 5 for a more detailed construction schedule. Construction Milestone Anticipated Date Begin Dewatering May 2017 Begin Subgrade CCR Earthwork June 2017 Begin Geomembrane Liner Placement August 2017 Complete Vegetative Support/Protection Layer Placement September CLOSURE CERTIFICATION As demonstrated throughout this plan, NIPSCO intends to close inactive Primary 2 through closure by leaving CCR in place no later than April 17, 2018, and has developed the closure plan in conformance with the requirements of 40 CFR, Part In compliance with 40 CFR, Part (b) (4) and (6), a Statement of Certification is appended to this plan and located in Exhibit A. Pursuant to 40 CFR, Part (c) (3), within 60 days of completion, a Notification of Completion of Closure including the appropriate engineering certification will be prepared and placed in the facility s operating record.

13 FIGURES

14 ³ SITE Indiana ³ LEGEND Approximate Property Line CCR Unit to be Closed Final Pond L A K E M I C H I G A N Bottom Ash Pond Boiler Slag Former Secondary 2 MICHIGAN CITY Primary 2 Path: V:\001 GIS Projects\2015\ NIPSCO\ST_D Michigan City Engineering\ D001.mxd Modified By: CSCHAEFER Former Primary 1 Former Secondary 1 REFERENCES Elevations are in North American Vertical Datum 88 Orthophoto image source: Indiana University, Indiana Spatial Data Portal (gis.iu.edu). "The IndianaMap", an initiative of the Indiana Geographic Information Council, Inc. (IGIC), Indiana's statewide GIS coordination council Indiana western counties, 6 in. resolution: Dated 4/4/2013 REV. DATE DES REVISION DESCRIPTION GIS CHK RVW PROJECT TITLE NORTHERN INDIANA PUBLIC SERVICE COMPANY MICHIGAN CITY GENERATING STATION MICHIGAN CITY, INDIANA DESIGN GIS CHECK Manchester, New Hampshire REVIEW PROJECT No RAW CDS MEM RAW Feet SITE LOCATION MAP 12/15/2015 FILE No D001 11/30/2015 SCALE: AS SHOWN REV. 0 12/15/ /15/2015 FIGURE 1

15 FINAL POND APPROXIMATE LIMIT OF PRIMARY 2 FORMER SECONDARY 1 PRIMARY 2 APPROXIMATE LIMIT OF PRIMARY 2 FORMER SECONDARY 2 Path: \\manchester\cadd\drawings\2015\nipsco\temporary MCGS Storage\Liner Revision 1\ File Name: Revised Approx Limit of Primary 2.dwg LEGEND EXISTING CONTOUR EDGE OF WATER (07/08/2015) APPROXIMATE LIMIT OF PRIMARY 2 REFERENCES 0 1. "EMBANKMENT & SOIL BORING MONITORING WELL SURVEY NIPSCO MICHIGAN CITY GENERATING STATION PT. NW 1/4, SEC. 29, T38N, R4W AND PT. NE 1/4, SEC. 30, T38N, R4W MICHIGAN TOWNSHIP, LAPORTE COUNTY 1'' = 60' INDIANA." BY MARBACH, BRADY & WEAVER, INC. DATED 7/8/ HORIZONTAL AND VERTICAL DATA FOR THIS SURVEY ARE BASED ON A SOLUTION DERIVED FROM GLOBAL POSITIONING SYSTEM (GPS) OBSERVATIONS PROCESSED A CONTINUOUSLY OPERATING REFERENCE STATION. THE COORDINATE SYSTEM IS US STATE PLANE 1983, NAD 1983 (CONUS), INDIANA WEST ZONE. GROUND ELEVATIONS ARE BASED UPON SAID INDOT SOLUTION AND ARE ON THE 1988 NORTH AMERICAN VERTICAL DATUM (NAD88). THIS ORTHOMETRIC ELEVATION WAS DERIVED UTILIZING THE MOST RECENT GEOID MODEL (GEOID12A). IT IS 3. REFERENCE STATION USED: INLP LAPORTE CORS ARP CLIENT NORTHERN INDIANA PUBLIC SERVICE COMPANY CONSULTANT YYYY-MM-DD DESIGNED PREPARED REVIEWED APPROVED APPROXIMATE LOCATION OF T8463 TRANSMISSION TOWER MCM RWC MCM RAW PROJECT NORTHERN INDIANA PUBLIC SERVICE COMPANY MICHIGAN CITY GENERATING STATION MICHIGAN CITY, INDIANA TITLE PRIMARY 2 EXISTING CONDITIONS PROJECT NO SUBTITLE A EDGE OF WATER REV FEET FIGURE 2 IF THIS MEASUREMENT DOES NOT MATCH WHAT IS SHOWN, THE SHEET SIZE HAS BEEN MODIFIED FROM: ANSI B 0 1 in

16 APPROXIMATE EDGE OF WATER B FORMER SECONDARY 1 B' Path: \\manchester\cadd\drawings\2015\nipsco\temporary MCGS Storage\Road Grade Revision\ File Name: Primary 2 Road Revision 2.dwg LEGEND A EXISTING CONTOUR PROPOSED CONTOUR (TOP OF VEGETATIVE SUPPORT/PROTECTION LAYER) LIMIT OF PRIMARY 2 CROSS SECTION LINE EDGE OF WATER LIMIT OF LINER APPROXIMATE EDGE OF WATER REFERENCES 1. "EMBANKMENT & SOIL BORING MONITORING WELL SURVEY NIPSCO MICHIGAN CITY GENERATING STATION PT. NW 1/4, SEC. 29, T38N, R4W AND PT. NE 1/4, SEC. 30, T38N, R4W MICHIGAN TOWNSHIP, LAPORTE COUNTY INDIANA." BY MARBACH, BRADY & WEAVER, INC. DATED 7/8/ HORIZONTAL AND VERTICAL DATA FOR THIS SURVEY ARE BASED ON A SOLUTION DERIVED FROM GLOBAL POSITIONING SYSTEM (GPS) OBSERVATIONS PROCESSED A CONTINUOUSLY OPERATING REFERENCE STATION. THE COORDINATE SYSTEM IS US STATE PLANE 1983, NAD 1983 (CONUS), INDIANA WEST ZONE. GROUND ELEVATIONS ARE BASED UPON SAID INDOT SOLUTION AND ARE ON THE 1988 NORTH AMERICAN VERTICAL DATUM (NAD88). THIS ORTHOMETRIC ELEVATION WAS DERIVED UTILIZING THE MOST RECENT GEOID MODEL (GEOID12A). 3. REFERENCE STATION USED: INLP LAPORTE CORS ARP A' CLIENT NORTHERN INDIANA PUBLIC SERVICE COMPANY CONSULTANT YYYY-MM-DD DESIGNED PREPARED RAW RWC REVIEWED APPROVED MCM RAW PROJECT TITLE PROJECT NO SUBTITLE A 0 1'' = 60' NORTHERN INDIANA PUBLIC SERVICE COMPANY MICHIGAN CITY GENERATING STATION MICHIGAN CITY, INDIANA PRIMARY 2 FINAL CLOSURE GRADING PLAN REV. 0 EDGE OF WATER FEET FIGURE 3 IF THIS MEASUREMENT DOES NOT MATCH WHAT IS SHOWN, THE SHEET SIZE HAS BEEN MODIFIED FROM: ANSI B 0 1 in

17 630 A (WEST) A' (EAST) 630 ELEVATION (FT) B 5H : 1V (SOUTH) 630 2% APPROXIMATE TOP OF CCR SEDIMENT TOP OF FINAL COVER GEOMEMBRANE LINER CROSS SECTION A-A' TYPICAL FINAL CLOSURE SECTION 2H : 1V ELEVATION (FT) GEOCOMPOSITE DRAINAGE LAYER LINER SUBGRADE (6" MIN.) B' (NORTH) 630 LINER LINER LINER LINER LINER LINER LINER TYPICAL FINAL CLOSURE SECTION N.T.S. VEGETATIVE SUPPORT/ PROTECTION LAYER (18" MIN.) GEOMEMBRANE LINER CCR SUBGRADE (THICKNESS VARIES) TYPICAL FINAL CLOSURE SECTION 620 Path: \\manchester\cadd\drawings\2015\nipsco\temporary MCGS Storage\ File Name: Primary 2 Grading calcs figure Liner.dwg ELEVATION (FT) APPROXIMATE TOP OF CCR SEDIMENT TOP OF FINAL COVER CROSS SECTION B-B' A-A' GEOMEMBRANE LINER CLIENT CONSULTANT 5H : 1V 5H : 1V YYYY-MM-DD DESIGNED PREPARED REVIEWED APPROVED ELEVATION (FT) NORTHERN INDIANA PUBLIC SERVICE COMPANY RAW RWC MCM RAW PROJECT TITLE PROJECT NO HORIZONTAL SCALE: VERTICAL SCALE: SUBTITLE A 0 1'' = 60' NORTHERN INDIANA PUBLIC SERVICE COMPANY MICHIGAN CITY GENERATING STATION MICHIGAN CITY, INDIANA PRIMARY 2 CROSS SECTIONS 0 1'' = 20' REV FEET FEET FIGURE 4 IF THIS MEASUREMENT DOES NOT MATCH WHAT IS SHOWN, THE SHEET SIZE HAS BEEN MODIFIED FROM: ANSI B 0 1 in

18 Path: \\manchester\cadd\drawings\2015\nipsco\temporary MCGS Storage\ File Name: Primary 2.dwg CLIENT NORTHERN INDIANA PUBLIC SERVICE COMPANY CONSULTANT YYYY-MM-DD DESIGNED PREPARED MCM RWC REVIEWED APPROVED MCM RAW PROJECT NORTHERN INDIANA PUBLIC SERVICE COMPANY MICHIGAN CITY GENERATING STATION MICHIGAN CITY, INDIANA TITLE CLOSURE SCHEDULE PROJECT NO SUBTITLE A REV. 0 FIGURE 5 IF THIS MEASUREMENT DOES NOT MATCH WHAT IS SHOWN, THE SHEET SIZE HAS BEEN MODIFIED FROM: ANSI B 0 1 in

19 EXHIBIT A STATEMENT OF CERTIFICATION

20

21 Golder Associates Inc. 670 N. Commercial Street, Suite 103 Manchester, NH USA Tel: (603) Fax: (603) Golder, Golder Associates and the GA globe design are trademarks of Golder Associates Corporation

Inflow Design Flood Control System Plan

Inflow Design Flood Control System Plan Inflow Design Flood Control System Plan BAILLY GENERATING STATION CCR SURFACE IMPOUNDMENT INFLOW DESIGN FLOOD CONTROL SYSTEM PLAN Chesterton, Indiana Pursuant to 40 CFR 257.82 Submitted To: Northern Indiana

More information

LANDFILL CLOSURE PLAN ENTERGY ARKANSAS, INC. INDEPENDENCE PLANT CLASS 3N CCR LANDFILL PERMIT NO S3N-R2 AFIN

LANDFILL CLOSURE PLAN ENTERGY ARKANSAS, INC. INDEPENDENCE PLANT CLASS 3N CCR LANDFILL PERMIT NO S3N-R2 AFIN LANDFILL CLOSURE PLAN ENTERGY ARKANSAS, INC. INDEPENDENCE PLANT CLASS 3N CCR LANDFILL PERMIT NO. 0200-S3N-R2 AFIN 32-00042 OCTOBER 12, 2016 LANDFILL CLOSURE PLAN ENTERGY ARKANSAS, INC. INDEPENDENCE PLANT

More information

Closure Plan Limited Purpose Landfill TransAlta Centralia Mine

Closure Plan Limited Purpose Landfill TransAlta Centralia Mine Closure Plan Limited Purpose Landfill TransAlta Centralia Mine Prepared for TransAlta Centralia Mining LLC December 5 East Front Street Suite Boise, Idaho 87 /6/5 This document was prepared under direct

More information

Ottumwa Generating Station Project No Closure Plan for Existing CCR Revision: 0 Surface Impoundments TABLE OF CONTENTS

Ottumwa Generating Station Project No Closure Plan for Existing CCR Revision: 0 Surface Impoundments TABLE OF CONTENTS Surface Impoundments Page No. i TABLE OF CONTENTS 1. INTRODUCTION... 1 2. PROPOSED CCR IMPOUNDMENTS CLOSURE PROCEDURE... 3 3. PROPOSED COVER SYSTEM... 4 4. ESTIMATED MAXIMUM INVENTORY OF CCR... 4 5. ESTIMATED

More information

SIOUX ENERGY CENTER SCPB CCR IMPOUNDMENT CLOSURE PLAN

SIOUX ENERGY CENTER SCPB CCR IMPOUNDMENT CLOSURE PLAN SIOUX ENERGY CENTER SCPB CCR IMPOUNDMENT CLOSURE PLAN i Table of Contents 1.0 INTRODUCTION... 1 2.0 SITE DESCRIPTION... 1 3.0 CLOSURE PLAN... 1 3.1 Overview of Closure Approach... 1 3.2 Estimated Maximum

More information

CCR Rule Operating Criteria Closure Plan

CCR Rule Operating Criteria Closure Plan CCR Rule Operating Criteria 257.102 Closure Plan FGD Pond 2 Jim Bridger Plant Point of Rocks, Wyoming PREPARED FOR PacifiCorp 1407 West North Temple Salt Lake City, UT 84116 (801) 521-0376 Fax (801) 220-4748

More information

LANDFILL CLOSURE PLAN. Submitted To: Dominion Chesapeake Energy Center 2701 Vepco Street Chesapeake, Virginia 23323

LANDFILL CLOSURE PLAN. Submitted To: Dominion Chesapeake Energy Center 2701 Vepco Street Chesapeake, Virginia 23323 LANDFILL CLOSURE PLAN Chesapeake Energy Center Ash Landfill - Permit #440 Closure Plan Submitted To: Dominion Chesapeake Energy Center 2701 Vepco Street Chesapeake, Virginia 23323 Submitted By: Golder

More information

CLOSURE AND POST-CLOSURE CARE PLAN JAMES RIVER POWER STATION UTILITY WASTE LANDFILL CITY UTILITIES OF SPRINGFIELD, MISSOURI

CLOSURE AND POST-CLOSURE CARE PLAN JAMES RIVER POWER STATION UTILITY WASTE LANDFILL CITY UTILITIES OF SPRINGFIELD, MISSOURI CLOSURE AND POST-CLOSURE CARE PLAN JAMES RIVER POWER STATION UTILITY WASTE LANDFILL CITY UTILITIES OF SPRINGFIELD, MISSOURI INITIAL PREPARATION DATE: October 11, 2016 TABLE OF CONTENTS 1. CERTIFICATION

More information

CCR LANDFILL RUN-ON AND RUN-OFF CONTROL SYSTEM PLAN. Pursuant to 40 CFR

CCR LANDFILL RUN-ON AND RUN-OFF CONTROL SYSTEM PLAN. Pursuant to 40 CFR Run-On & Run-Off Control System Plan R.M. SCHAHFER GENERATING STATION CCR LANDFILL RUN-ON AND RUN-OFF CONTROL SYSTEM PLAN Wheatfield, Indiana Pursuant to 40 CFR 257.81 Submitted To: Northern Indiana Public

More information

FOUR CORNERS POWER PLANT CLOSURE PLAN (b) DRY FLY ASH DISPOSAL AREA (DFADA) FC_ClosPlan_004_

FOUR CORNERS POWER PLANT CLOSURE PLAN (b) DRY FLY ASH DISPOSAL AREA (DFADA) FC_ClosPlan_004_ FOUR CORNERS POWER PLANT CLOSURE PLAN 257.102(b) DRY FLY ASH DISPOSAL AREA (DFADA) FC_ClosPlan_004_20161017 Closure Plan Contents 257.102(b)(1) The owner or operator of a CCR unit must prepare a written

More information

TABLE OF CONTENTS LEGAL NOTICE

TABLE OF CONTENTS LEGAL NOTICE Surface Impoundments Page No. i TABLE OF CONTENTS 1. INTRODUCTION... 1 2. PROPOSED CCR IMPOUNDMENT CLOSURE PROCEDURE... 3 3. PROPOSED COVER SYSTEM... 4 4. ESTIMATED MAXIMUM INVENTORY OF CCR... 4 5. ESTIMATED

More information

LANDFILL CLOSURE PLAN PLUM POINT ENERGY STATION CLASS 3N CCR LANDFILL PERMIT NO S3N AFIN:

LANDFILL CLOSURE PLAN PLUM POINT ENERGY STATION CLASS 3N CCR LANDFILL PERMIT NO S3N AFIN: LANDFILL CLOSURE PLAN PLUM POINT ENERGY STATION CLASS 3N CCR LANDFILL PERMIT NO. 0303-S3N AFIN: 47-00461 OCTOBER 14, 2016 LANDFILL CLOSURE PLAN PLUM POINT ENERGY STATION CLASS 3N CCR LANDFILL PERMIT NO.

More information

VISUAL SITE INSPECTION REPORT 2018

VISUAL SITE INSPECTION REPORT 2018 VISUAL SITE INSPECTION REPORT 2018 SOUTHERN INDIANA GAS AND ELECTRIC A. B. BROWN GENERATING STATION TYPE III RESTRICTED WASTE LANDFILL WEST FRANKLIN, IN ATC PROJECT NO. 170LF00614 January 9, 2019 PREPARED

More information

LANDFILL CLOSURE PLAN ENTERGY ARKANSAS, INC. WHITE BLUFF PLANT CLASS 3N CCR LANDFILL PERMIT NO S3N-R3 AFIN:

LANDFILL CLOSURE PLAN ENTERGY ARKANSAS, INC. WHITE BLUFF PLANT CLASS 3N CCR LANDFILL PERMIT NO S3N-R3 AFIN: LANDFILL CLOSURE PLAN ENTERGY ARKANSAS, INC. WHITE BLUFF PLANT CLASS 3N CCR LANDFILL PERMIT NO. 0199-S3N-R3 AFIN: 35-00110 OCTOBER 12, 2016 LANDFILL CLOSURE PLAN ENTERGY ARKANSAS, INC. WHITE BLUFF PLANT

More information

Mr. Michael Malone CPS Energy 145 Navarro Street San Antonio, Texas Project No

Mr. Michael Malone CPS Energy 145 Navarro Street San Antonio, Texas Project No Environmental Resources Management January 13, 2017 Mr. Michael Malone 145 Navarro Street San Antonio, Texas 78205 Project No. 0352436 CityCentre Four 840 West Sam Houston Parkway North, Suite 600 Houston,

More information

Closure Plan Ash Disposal Area PGE Boardman Power Plant

Closure Plan Ash Disposal Area PGE Boardman Power Plant FIRST ISSUE REVISION 0 Closure Plan Ash Disposal Area PGE Boardman Power Plant Prepared for Portland General Electric September 2015 2020 SW 4th Avenue, Suite 300 Portland, Oregon 97201 This document was

More information

2015 ANNUAL ENGINEERING INSPECTION REPORT ENTERGY WHITE BLUFF PLANT CLASS 3N LANDFILL PERMIT NO S3N-R3 AFIN:

2015 ANNUAL ENGINEERING INSPECTION REPORT ENTERGY WHITE BLUFF PLANT CLASS 3N LANDFILL PERMIT NO S3N-R3 AFIN: 2015 ANNUAL ENGINEERING INSPECTION REPORT ENTERGY WHITE BLUFF PLANT CLASS 3N LANDFILL PERMIT NO. 0199-S3N-R3 AFIN: 35-00110 JANUARY 15, 2016 ENTERGY WHITE BLUFF PLANT CLASS 3N LANDFILL 2015 ANNUAL ENGINEERING

More information

Written Closure Plan. Comanche Station - Active CCR Landfill Public Service Company of Colorado Denver Colorado. October 17, 2016

Written Closure Plan. Comanche Station - Active CCR Landfill Public Service Company of Colorado Denver Colorado. October 17, 2016 Written Closure Plan Comanche Station - Active CCR Landfill Public Service Company of Colorado Denver Colorado October 17, 2016 Table of Contents 1.0 General Information... 1 2.0 Description of Closure

More information

2015 ANNUAL ENGINEERING INSPECTION REPORT PLUM POINT ENERGY STATION CLASS 3N LANDFILL PERMIT NO S3N AFIN:

2015 ANNUAL ENGINEERING INSPECTION REPORT PLUM POINT ENERGY STATION CLASS 3N LANDFILL PERMIT NO S3N AFIN: 2015 ANNUAL ENGINEERING INSPECTION REPORT PLUM POINT ENERGY STATION CLASS 3N LANDFILL PERMIT NO. 0303-S3N AFIN: 47-00461 JANUARY 15, 2016 PLUM POINT ENERGY STATION CLASS 3N LANDFILL 2015 ANNUAL ENGINEERING

More information

Run-on and Run-off Control System Plan

Run-on and Run-off Control System Plan Run-on and Run-off Control System Plan SWEPCO John W. Turk, Jr. Power Plant Fulton, Arkansas Permit No. 0311-S3N-R1 AFIN: 29-00506 October 2016 Terracon Project No. 35167133 Prepared for: SWEPCO 3711 Highway

More information

VICINITY MAP AND SITE MAP. Page 1 of 9

VICINITY MAP AND SITE MAP. Page 1 of 9 INTRODUCTION... 2 1. Background Information of West Bottom Ash Pond (BAP)... 2 1.1 Facility Location Description...2 1.2 Description of West BAP CCR Unit...2 1.2.1 Embankment Configuration...2 1.2.2 Construction

More information

1. Introduction Site Information Site Characteristics Hydrogeologic Setting... 2

1. Introduction Site Information Site Characteristics Hydrogeologic Setting... 2 Table of Contents 1. Introduction... 1 1.1 Site Information... 1 1.2 Site Characteristics... 1 1.3 Hydrogeologic Setting... 2 2. Closure Plan... 5 2.1 Closure Description... 5 2.2 Closure Timeframe...

More information

Lansing Generating Station Project No Closure Plan for Existing CCR Revision: 1 TABLE OF CONTENTS

Lansing Generating Station Project No Closure Plan for Existing CCR Revision: 1 TABLE OF CONTENTS Surface Impoundment Page No. i TABLE OF CONTENTS 1. INTRODUCTION... 1 2. PROPOSED CCR IMPOUNDMENT CLOSURE PROCEDURE... 2 3. PROPOSED COVER SYSTEM... 2 4. ESTIMATED MAXIMUM INVENTORY OF CCR... 3 5. ESTIMATED

More information

Closure Plan Brame Fly Ash Pond

Closure Plan Brame Fly Ash Pond Brame Fly Ash Pond CLECO Corporation Rodemacher Unit 2 Project No. 90965 Revision 0 10/14/2016 Brame Fly Ash Pond prepared for CLECO Corporation Rodemacher Unit 2 Rapides Parish, Louisiana Project No.

More information

Consulting Engineers and Scientists. Closure Plan. Submitted by: GEI Consultants, Inc Voyager Drive Green Bay, Wisconsin

Consulting Engineers and Scientists. Closure Plan. Submitted by: GEI Consultants, Inc Voyager Drive Green Bay, Wisconsin Consulting Engineers and Scientists Regulation Compliance Report Submitted to: We Energies 333 West Everett Street, A231 Milwaukee, Wisconsin 53203 Submitted by: GEI Consultants, Inc. 3159 Voyager Drive

More information

NRG BRANDYWINE ASH STORAGE SITE BRANDYWINE, MARYLAND 2015 ANNUAL CCR INSPECTION REPORT

NRG BRANDYWINE ASH STORAGE SITE BRANDYWINE, MARYLAND 2015 ANNUAL CCR INSPECTION REPORT NRG BRANDYWINE ASH STORAGE SITE BRANDYWINE, MARYLAND 2015 ANNUAL CCR INSPECTION REPORT To: Walter Johnson, NRG MD Ash Management LLC From: Jeffrey Hutchins, P.E., AECOM Date: January 6, 2016 RE: Annual

More information

POST CLOSURE PLAN. CFR (d) Pond 1. Clinch Power Plant Russell County, West Virginia. November Prepared for: Appalachian Power Company

POST CLOSURE PLAN. CFR (d) Pond 1. Clinch Power Plant Russell County, West Virginia. November Prepared for: Appalachian Power Company POST CLOSURE PLAN CFR 257.104(d) Pond 1 Clinch Power Plant Russell County, West Virginia November 2016 Prepared for: Appalachian Power Company Prepared by: Amec Foster Wheeler Environment & Infrastructure,

More information

CHOLLA POWER PLANT CLOSURE PLAN (b) BOTTOM ASH POND CH_ClosPlan_003_

CHOLLA POWER PLANT CLOSURE PLAN (b) BOTTOM ASH POND CH_ClosPlan_003_ CHOLLA POWER PLANT CLOSURE PLAN 257.102(b) BOTTOM ASH POND CH_ClosPlan_003_20161017 Closure Plan Contents 257.102(b)(1) The owner or operator of a CCR unit must prepare a written closure plan that describes

More information

2018 Annual Inspection Report

2018 Annual Inspection Report 2018 Annual Inspection Report for Compliance with the Coal Combustion Residuals Rule (40 CFR Part 257) Valmont Station 1800 North 63 rd Street Boulder, Colorado 80301 January 18, 2019 Table of Contents

More information

CCR Impoundment Closure: Reshaping your Ash! 2017 MWCC Technical Conference

CCR Impoundment Closure: Reshaping your Ash! 2017 MWCC Technical Conference CCR Impoundment Closure: Reshaping your Ash! 2017 MWCC Technical Conference Setting the Stage Who? SCS Engineers Consulting/Design Engineer Pat Goeke, P.E. Radmacher Brothers Earthwork Contractor Ben Cummings,

More information

CLOSURE PLAN. CFR (b) Document No. GERS Stingy Run Flyash Pond. Gavin Plant Cheshire, Ohio. October, 2016

CLOSURE PLAN. CFR (b) Document No. GERS Stingy Run Flyash Pond. Gavin Plant Cheshire, Ohio. October, 2016 CLOSURE PLAN CFR 257.102(b) Stingy Run Flyash Pond Gavin Plant Cheshire, Ohio October, 2016 Prepared for: AEP Generation Resources Gavin Plant Cheshire, Ohio Prepared by: American Electric Power Service

More information

Leachate Management Plan

Leachate Management Plan Leachate Management Plan LEACHATE MANAGEMENT PLAN Chesapeake Energy Center Ash Landfill Permit #440 Submitted To: Dominion Chesapeake Energy Center 2701 Vepco Street Chesapeake, Virginia 23323 Submitted

More information

2016 ANNUAL STRUCTURAL STABILITY INSPECTION REPORT

2016 ANNUAL STRUCTURAL STABILITY INSPECTION REPORT Prepared for: FORT ARMISTEAD ROAD LOT 15 LANDFILL, LLC 3601 Fort Armistead Road 21226 2016 ANNUAL STRUCTURAL STABILITY INSPECTION REPORT Per Requirements of 40 CFR 257.84(b)(2) Prepared by: 10211 Wincopin

More information

NC2 ASH DISPOSAL AREA

NC2 ASH DISPOSAL AREA POST-CLOSURE PLAN OPPD NEBRASKA CITY GENERATING STATION FOSSIL FUEL COMBUSTION ASH DISPOSAL AREA NC2 ASH DISPOSAL AREA Prepared for: OMAHA PUBLIC POWER DISTRICT NEBRASKA CITY GENERATING STATION OTOE COUNTY,

More information

CCR Annual Inspection (b) for the West Ash Pond at the F. B. Culley Generating Station. Revision 0

CCR Annual Inspection (b) for the West Ash Pond at the F. B. Culley Generating Station. Revision 0 Submitted to Southern Indiana Gas & Electric Company dba Vectren Power Supply, Inc. (SIGECO) One Vectren Square Evansville, IN 47708 Submitted by AECOM 9400 Amberglen Boulevard Austin, Texas 78729 257.83

More information

LANDFILL POST-CLOSURE PLAN ENTERGY ARKANSAS, INC. INDEPENDENCE PLANT CLASS 3N CCR LANDFILL PERMIT NO S3N-R2 AFIN

LANDFILL POST-CLOSURE PLAN ENTERGY ARKANSAS, INC. INDEPENDENCE PLANT CLASS 3N CCR LANDFILL PERMIT NO S3N-R2 AFIN LANDFILL POST-CLOSURE PLAN ENTERGY ARKANSAS, INC. INDEPENDENCE PLANT CLASS 3N CCR LANDFILL PERMIT NO. 0200-S3N-R2 AFIN 32-00042 OCTOBER 12, 2016 LANDFILL POST-CLOSURE PLAN ENTERGY ARKANSAS, INC. INDEPENDENCE

More information

SURFACE IMPOUNDMENT CLOSURE PLAN. Possum Point Power Station Ponds ABC and E Permit # 617

SURFACE IMPOUNDMENT CLOSURE PLAN. Possum Point Power Station Ponds ABC and E Permit # 617 SURFACE IMPOUNDMENT CLOSURE PLAN Possum Point Power Station Ponds ABC and E Permit # 617 CLOSURE PLAN Submitted To: Possum Point Power Station 19000 Possum Point Road Dumfries, VA 22026 Submitted By: Golder

More information

CLOSURE PLAN. CFR (b) GERS Fly Ash Pond. Big Sandy Plant Louisa, Kentucky. October, Prepared for : Kentucky Power Big Sandy Plant

CLOSURE PLAN. CFR (b) GERS Fly Ash Pond. Big Sandy Plant Louisa, Kentucky. October, Prepared for : Kentucky Power Big Sandy Plant CLOSURE PLAN CFR 257.102(b) Fly Ash Pond Big Sandy Plant Louisa, Kentucky October, 2016 Prepared for : Kentucky Power Big Sandy Plant Louisa, Kentucky Prepared by: American Electric Power Service Corporation

More information

0 TRC. Closure Plan for CCR Surface Impoundments. Clover Power Station, Clover, Virginia. October 2016

0 TRC. Closure Plan for CCR Surface Impoundments. Clover Power Station, Clover, Virginia. October 2016 0 TRC Closure Plan for CCR Surface Impoundments Clover Power Station Clover, Virginia October 2016 Prepared For Virginia Electric and Power Company R. Kent Nilsson, P.E. Nakia W. Addison Senior Engineer

More information

NEW CASTLE CONSERVATION DISTRICT. through. (Name of Municipality) PLAN REVIEW APPLICATION DRAINAGE, STORMWATER MANAGEMENT, EROSION & SEDIMENT CONTROL

NEW CASTLE CONSERVATION DISTRICT. through. (Name of Municipality) PLAN REVIEW APPLICATION DRAINAGE, STORMWATER MANAGEMENT, EROSION & SEDIMENT CONTROL NEW CASTLE CONSERVATION DISTRICT through (Name of Municipality) PLAN REVIEW APPLICATION DRAINAGE, STORMWATER MANAGEMENT, EROSION & SEDIMENT CONTROL Office use only: Received by Municipality: Received by

More information

Pond Closure - Case Study[TP1]

Pond Closure - Case Study[TP1] 2017 World of Coal Ash (WOCA) Conference in Lexington, KY - May 9-11, 2017 http://www.flyash.info/ Pond Closure - Case Study[TP1] By Pedro J Amaya, P.E. (1) (1) Civil Engineering and Geotechnical Engineering

More information

Nonmetallic Mining Reclamation & Operation Plan. Amendment No. 1 (Includes modifications for Wash Plant construction) DRAFT

Nonmetallic Mining Reclamation & Operation Plan. Amendment No. 1 (Includes modifications for Wash Plant construction) DRAFT Nonmetallic Mining Reclamation & Operation Plan Amendment No. 1 (Includes modifications for Wash Plant construction) Mondovi Mine Town of Mondovi, Wisconsin Prepared for: Buffalo White Sand, LLC PO Box

More information

CLOSURE PLAN ASH LANDFILL AREA SPRINGERVILLE GENERATING STATION SPRINGERVILLE, ARIZONA

CLOSURE PLAN ASH LANDFILL AREA SPRINGERVILLE GENERATING STATION SPRINGERVILLE, ARIZONA CLOSURE PLAN ASH LANDFILL AREA SPRINGERVILLE GENERATING STATION SPRINGERVILLE, ARIZONA Prepared for Tucson Electric Power Company October 14, 2016 Prepared by AMTECH Associates, L.L.C. 8666 E. San Alberto

More information

2017 Annual Inspection Report

2017 Annual Inspection Report 2017 Annual Inspection Report for Compliance with the Coal Combustion Residuals Rule (40 CFR Part 257) Hayden Station 13125 U.S. Highway 40 Hayden, Colorado 81638 January 18, 2018 Table of Contents Certification...

More information

Inspection Report. Re: Keystone Ash Disposal Site Annual CCR Unit Inspection Report No. 1

Inspection Report. Re: Keystone Ash Disposal Site Annual CCR Unit Inspection Report No. 1 Inspection Report To: From: Mark Jacklin (NRG Keystone Generating Station) Jesse Varsho, P.E. Re: Keystone Ash Disposal Site Annual CCR Unit Inspection Report No. 1 Inspection Report January 12, 2016 INTRODUCTION

More information

Annual Inspection Report Jeffrey Energy Center Flue Gas Desulfurization (FGD) Landfill

Annual Inspection Report Jeffrey Energy Center Flue Gas Desulfurization (FGD) Landfill Annual Inspection Report Jeffrey Energy Center Flue Gas Desulfurization (FGD) Landfill Prepared for: Westar Energy Jeffrey Energy Center St. Marys, Kansas Prepared by: APTIM Environmental & Infrastructure,

More information

Active Coal Combustion Residuals Landfill Annual Inspection Escalante Generating Station

Active Coal Combustion Residuals Landfill Annual Inspection Escalante Generating Station REPORT Active Coal Combustion Residuals Landfill Annual Inspection Escalante Generating Station Submitted to: Tri-State Generation and Transmission Association, Inc. 1100 West 116th Avenue Westminster,

More information

CLOSURE PLAN ECONOMIZER ASH AND PYRITES PONDS AND WEST SLAG DISPOSAL POND

CLOSURE PLAN ECONOMIZER ASH AND PYRITES PONDS AND WEST SLAG DISPOSAL POND Prepared for Tampa Electric Company P.O. Box 111 Tampa, Florida 33601-0111 CLOSURE PLAN ECONOMIZER ASH AND PYRITES PONDS AND WEST SLAG DISPOSAL POND BIG BEND STATION Apollo Beach, Florida Prepared by Geosyntec

More information

Initial Closure Plan Slag Pond. Nelson Dewey Generating Station. Wisconsin Power and Light Company. Prepared for:

Initial Closure Plan Slag Pond. Nelson Dewey Generating Station. Wisconsin Power and Light Company. Prepared for: Initial Closure Plan Slag Pond Prepared for: Wisconsin Power and Light Company 11999 County Highway VV Cassville, Wisconsin 53806 Prepared by: SCS ENGINEERS 2830 Dairy Drive Madison, Wisconsin 53718-6751

More information

CLOSURE PLAN W.H. Sammis Coal Plant North and South Ponds Stratton, Ohio

CLOSURE PLAN W.H. Sammis Coal Plant North and South Ponds Stratton, Ohio Prepared for: FirstEnergy Generation, LLC 76 South Main St Akron, OH 44308 CLOSURE PLAN W.H. Sammis Coal Plant North and South Ponds Stratton, Ohio Prepared by: 10211 Wincopin Circle, Floor 4 Columbia,

More information

ALLIANT ENERGY WISCONSIN POWER AND LIGHT NELSON DEWEY GENERATING STATION CCR SURFACE IMPOUNDMENT ANNUAL INSPECTION REPORT.

ALLIANT ENERGY WISCONSIN POWER AND LIGHT NELSON DEWEY GENERATING STATION CCR SURFACE IMPOUNDMENT ANNUAL INSPECTION REPORT. ALLIANT ENERGY WISCONSIN POWER AND LIGHT NELSON DEWEY GENERATING STATION CCR SURFACE IMPOUNDMENT ANNUAL INSPECTION REPORT January 15, 2016 EXECUTIVE SUMMARY This annual inspection report has been prepared

More information

2015 ANNUAL ENGINEERING INSPECTION REPORT ENTERGY INDEPENDENCE PLANT CLASS 3N LANDFILL PERMIT NO S3N-R2 AFIN:

2015 ANNUAL ENGINEERING INSPECTION REPORT ENTERGY INDEPENDENCE PLANT CLASS 3N LANDFILL PERMIT NO S3N-R2 AFIN: 2015 ANNUAL ENGINEERING INSPECTION REPORT ENTERGY INDEPENDENCE PLANT CLASS 3N LANDFILL PERMIT NO. 0200-S3N-R2 AFIN: 32-00042 JANUARY 15, 2016 ENTERGY INDEPENDENCE PLANT CLASS 3N LANDFILL 2015 ANNUAL ENGINEERING

More information

ALLIANT ENERGY INTERSTATE POWER AND LIGHT OTTUMWA GENERATING STATION CCR SURFACE IMPOUNDMENT ANNUAL INSPECTION REPORT.

ALLIANT ENERGY INTERSTATE POWER AND LIGHT OTTUMWA GENERATING STATION CCR SURFACE IMPOUNDMENT ANNUAL INSPECTION REPORT. ALLIANT ENERGY INTERSTATE POWER AND LIGHT OTTUMWA GENERATING STATION CCR SURFACE IMPOUNDMENT ANNUAL INSPECTION REPORT January 15, 2016 EXECUTIVE SUMMARY This annual inspection report has been prepared

More information

Inflow Design Flood Control System Plan

Inflow Design Flood Control System Plan Inflow Design Flood Control System Plan R.M. SCHAHFER GENERATING STATION CCR SURFACE IMPOUNDMENT INFLOW DESIGN FLOOD CONTROL SYSTEM PLAN Wheatfield, Indiana Pursuant to 40 CFR 257.82 Submitted To: Northern

More information

PEARCE CREEK CONFINED DISPOSAL AREA MODIFICATION

PEARCE CREEK CONFINED DISPOSAL AREA MODIFICATION US Army Corps of Engineers Philadelphia District PEARCE CREEK CONFINED DISPOSAL AREA MODIFICATION CECIL COUNTY MARYLAND STORMWATER MANAGEMENT PLAN NARRATIVE INITIAL SUBMISSION JUNE 2014 1 PEARCE CREEK

More information

SECTION EROSION AND SEDIMENTATION CONTROLS

SECTION EROSION AND SEDIMENTATION CONTROLS SECTION 312500 PART 1 GENERAL 1.01 GENERAL REQUIREMENTS A. Attention is directed to the CONTRACT AND GENERAL CONDITIONS and all Sections within DIVISION 01 - GENERAL REQUIREMENTS which are hereby made

More information

Annual Landfill Inspection 2015

Annual Landfill Inspection 2015 Annual Landfill Inspection 25 Westar Jeffrey Energy Center St. Mary s, KS KDHE Landfill Permit Number 359 Prepared for: Westar Energy 88 S. Kansas Ave. P.O. Box 889 Topeka, KS 666 Prepared by: Blackstone

More information

PUBLIC NOTICE PROFESSIONAL ENGINEERING SERIVCES: DESIGN OF TURF FIELD

PUBLIC NOTICE PROFESSIONAL ENGINEERING SERIVCES: DESIGN OF TURF FIELD PUBLIC NOTICE The Township of Union has adopted the Fair and Open Process of the Pay-to-Play Law (N.J.S.A. 19:44A-20a, et seq.) in its request for proposals and awarding goods and services contracts with

More information

CCP Annual Inspection Report

CCP Annual Inspection Report CCP Annual Inspection Report Brickhaven No. 2 Mine Tract A Structural Fill DWM Permit 1910, DEMLR Permit 19-25 Charah, Inc. Moncure, North Carolina February 2018 This page intentionally left blank. Charah,

More information

2017 ANNUAL ENGINEERING INSPECTION REPORT ENTERGY INDEPENDENCE PLANT CLASS 3N LANDFILL PERMIT NO S3N-R2 AFIN:

2017 ANNUAL ENGINEERING INSPECTION REPORT ENTERGY INDEPENDENCE PLANT CLASS 3N LANDFILL PERMIT NO S3N-R2 AFIN: 217 ANNUAL ENGINEERING INSPECTION REPORT ENTERGY INDEPENDENCE PLANT CLASS 3N LANDFILL PERMIT NO. 2-S3N-R2 AFIN: 32-42 JANUARY 17, 218 217 Landfill Inspection Report Entergy Independence Plant Class 3N

More information

CCP Annual Inspection Report

CCP Annual Inspection Report CCP Annual Inspection Report Brickhaven No. 2 Mine Tract A Structural Fill DWM Permit 1910, DEMLR Permit 19-25 Charah, Inc. Moncure, North Carolina October 2016 This page intentionally left blank. Charah,

More information

Technical Memo. Alex Bumgardner, Austin Utilities. Dave Parenteau, PE, Wenck Associates, Inc. Date: December 15, 2015

Technical Memo. Alex Bumgardner, Austin Utilities. Dave Parenteau, PE, Wenck Associates, Inc. Date: December 15, 2015 Technical Memo To: From: lex Bumgardner, ustin Utilities Dave Parenteau, PE, Wenck ssociates, Inc. Date: Subject: Notice of Intent to Close NE Plant Pond Wenck Project # B1463-18 Purpose This memorandum

More information

VISUAL SITE INSPECTION REPORT

VISUAL SITE INSPECTION REPORT VISUAL SITE INSPECTION REPORT - 2016 SOUTHERN INDIANA GAS AND ELECTRIC A. B. BROWN GENERATING STATION TYPE III RESTRICTED WASTE LANDFILL WEST FRANKLIN, IN ATC PROJECT NO. 170LF00318 DECEMBER 20, 2016 PREPARED

More information

ALLIANT ENERGY WISCONSIN POWER AND LIGHT COLUMBIA ENERGY CENTER CCR SURFACE IMPOUNDMENT ANNUAL INSPECTION REPORT. January 15, 2016

ALLIANT ENERGY WISCONSIN POWER AND LIGHT COLUMBIA ENERGY CENTER CCR SURFACE IMPOUNDMENT ANNUAL INSPECTION REPORT. January 15, 2016 ALLIANT ENERGY WISCONSIN POWER AND LIGHT COLUMBIA ENERGY CENTER CCR SURFACE IMPOUNDMENT ANNUAL INSPECTION REPORT January 15, 2016 EXECUTIVE SUMMARY This annual inspection report has been prepared in accordance

More information

2016 LANDFILL INSPECTION REPORT CARDINAL PLANT BRILLIANT, OHIO

2016 LANDFILL INSPECTION REPORT CARDINAL PLANT BRILLIANT, OHIO 2016 LANDFILL INSPECTION REPORT GERS-16-004 CARDINAL PLANT BRILLIANT, OHIO PREPARED BY GEOTECHNICAL ENGINEERING AEP SERVICE CORPORATION 1 RIVERSIDE PLAZA COLUMBUS, OHIO Cardinal Plant Landfill Inspection

More information

Annual Inspection Report CCR Surface Impoundment. MidAmerican Energy Company, Louisa Generating Station

Annual Inspection Report CCR Surface Impoundment. MidAmerican Energy Company, Louisa Generating Station Annual Inspection Report CCR Surface Impoundment MidAmerican Energy Company, Louisa Generating Station Final January 15, 2016 Annual Inspection Report CCR Surface Impoundment Prepared for MidAmerican Energy

More information

2017 Annual Landfill Inspection Report

2017 Annual Landfill Inspection Report 2017 Annual Landfill Inspection Report Ash Landfill Welsh Plant American Electric Power Service Corporation (SWEPCO) Cason, Texas November 17, 2017 Prepared for: SWEPCO. Prepared by: American Electric

More information

2017 Annual Inspection Report

2017 Annual Inspection Report 2017 Annual Inspection Report for Compliance with the Coal Combustion Residuals Rule (40 CFR Part 257) Valmont Station 1800 North 63 rd Street Boulder, Colorado 80301 January 18, 2018 Table of Contents

More information

NC1 ASH DISPOSAL AREA

NC1 ASH DISPOSAL AREA CLOSURE PLAN OPPD NEBRASKA CITY GENERATING STATION FOSSIL FUEL COMBUSTION ASH DISPOSAL AREA NC1 ASH DISPOSAL AREA Prepared for: OMAHA PUBLIC POWER DISTRICT NEBRASKA CITY GENERATING STATION OTOE COUNTY,

More information

Gainesville Regional Utilities Deerhaven Generating Station

Gainesville Regional Utilities Deerhaven Generating Station Gainesville Regional Utilities Deerhaven Generating Station Coal Combustion Residuals Landfill Closure and Post-Closure Care Plan (Version 1.0) Prepared for: Gainesville Regional Utilities Deerhaven Generating

More information

2017 ANNUAL GROUNDWATER MONITORING AND CORRECTIVE ACTION REPORT

2017 ANNUAL GROUNDWATER MONITORING AND CORRECTIVE ACTION REPORT Northern Indiana Public Service Company Bailly Generating Station Chesterton, Indiana CCR Management Unit Referred to as Bailly Boiler Slag Pond 2017 ANNUAL GROUNDWATER MONITORING AND CORRECTIVE ACTION

More information

15A NCAC 13B.1624 CONSTRUCTION REQUIREMENTS FOR MSWLF FACILITIES (a) This Rule establishes the performance standards and minimum criteria for

15A NCAC 13B.1624 CONSTRUCTION REQUIREMENTS FOR MSWLF FACILITIES (a) This Rule establishes the performance standards and minimum criteria for 15A NCAC 13B.1624 CONSTRUCTION REQUIREMENTS FOR MSWLF FACILITIES (a) This Rule establishes the performance standards and minimum criteria for designing and constructing a new MSWLF unit or lateral expansion

More information

Inspection Report. David Burton, Facility Manager (NRG Indian River Generating Station)

Inspection Report. David Burton, Facility Manager (NRG Indian River Generating Station) Inspection Report To: From: David Burton, Facility Manager (NRG Indian River Generating Station) Richard Southorn, P.E., P.G., CPSWQ Re: Indian River Landfill Annual CCR Unit Inspection Report No. 2 Inspection

More information

Table of Contents. Attachments Attachment A Photos Attachment B Site Map. Pages 3 of 9

Table of Contents. Attachments Attachment A Photos Attachment B Site Map. Pages 3 of 9 Table of Contents 1.0 Introduction...4 2.0 Description of Landfill...4 3.0 Review of Available Information...5 4.0 Inspection...5 4.1 Changes in Geometry since Last Inspection...5 4.2 Volume...5 4.3 Definitions

More information

Appendix K: Soil Erosion and Sedimentation Control Plan Check List

Appendix K: Soil Erosion and Sedimentation Control Plan Check List Appendix K: Soil Erosion and Sedimentation Control Plan Check List Drain Commissioner 46 February 2005 SOIL EROSION AND SEDIMENTATION CONTROL PLAN CHECK LIST Items listed below must be clearly depicted

More information

Construction Inspection Checklists

Construction Inspection Checklists III. Construction Inspection Checklists 33 Bioretention - Construction Inspection Checklist Project: Location: Site Status: Date: Time: Inspector: Construction Sequence Satisfactory / Unsatisfactory Comments

More information

CLOSURE PLAN. Bremo Power Station CCR Surface Impoundment: North Ash Pond

CLOSURE PLAN. Bremo Power Station CCR Surface Impoundment: North Ash Pond CLOSURE PLAN Bremo Power Station CCR Surface Impoundment: North Ash Pond CLOSURE PLAN Submitted To: Bremo Power Station 1038 Bremo Bluff Road Bremo Bluff, VA 23022 Submitted By: Golder Inc. 2108 W. Laburnum

More information

AMERICAN ELECTRIC POWER (SWEPCO)

AMERICAN ELECTRIC POWER (SWEPCO) 2016 DAM & DIKE INSPECTION REPORT ASH PONDS GERS-16-163 WELSH POWER PLANT AMERICAN ELECTRIC POWER (SWEPCO) CASON, TEXAS NATIONAL INVENTORY NO. TX4357 PREPARED BY GEOTECHNICAL ENGINEERING AEP SERVICE CORPORATION

More information

1.02 RELATED WORK: Refer to the following sections for related work: Section 4000-Concrete Materials and Methods

1.02 RELATED WORK: Refer to the following sections for related work: Section 4000-Concrete Materials and Methods SECTION 2000- EARTHWORK PART 1- GENERAL 1.01 SCOPE: This Section covers excavation, fill, and compaction of earth and rock for roadway, embankments, structural foundations, and planted areas. Topics include

More information

Ardaman & Associates, Inc. Geotechnical, Environmental, and Materials Consultants A Tetra Tech Company

Ardaman & Associates, Inc. Geotechnical, Environmental, and Materials Consultants A Tetra Tech Company Conceptual Closure Plan for Cell 1 of Horizontal Expansion of Original Combustion Waste Storage Area Orlando Utilities Commission Stanton Energy Center Orange County, Florida October 14, 2016 Ardaman &

More information

2015 LANDFILL INSPECTION REPORT CARDINAL PLANT BRILLIANT, OHIO

2015 LANDFILL INSPECTION REPORT CARDINAL PLANT BRILLIANT, OHIO 2015 LANDFILL INSPECTION REPORT GERS-15-021 CARDINAL PLANT BRILLIANT, OHIO PREPARED BY GEOTECHNICAL ENGINEERING AEP SERVICE CORPORATION 1 RIVERSIDE PLAZA COLUMBUS, OHIO Cardinal Plant Landfill Inspection

More information

Pond Closures: Solving a Complicated Puzzle

Pond Closures: Solving a Complicated Puzzle 2011 World of Coal Ash (WOCA) Conference May 9-12, 2011 in Denver, CO, USA http://www.flyash.info/ Pond Closures: Solving a Complicated Puzzle Presented by Mark Rokoff, PE URS Corporation Nick Golden,

More information

SECTION SOILS REPORT

SECTION SOILS REPORT SECTION 02300 SOILS REPORT 1. GENERAL: 1.1 All work included under this heading shall be subject to the General Conditions of the entire operation. This Contractor is required to refer especially thereto.

More information

Suggested Stormwater Management Practices For Individual House Lots

Suggested Stormwater Management Practices For Individual House Lots Suggested Stormwater Management Practices For Individual House Lots These practices are necessary to satisfy the water quantity and water quality criteria of the Rappahannock Stormwater Ordinance. These

More information

GUIDESHEET IV. Wastewater Treatment and Storage Lagoons

GUIDESHEET IV. Wastewater Treatment and Storage Lagoons GUIDESHEET IV Wastewater Treatment and Storage Lagoons Unless otherwise approved by the Department of Environmental Quality (DEQ) all wastewater treatment and storage lagoons associated with a discharge

More information

BIG BEND POWER STATION NORTH AND SOUTH ECONOMIZER ASH PONDS CLOSURE PLAN. Prepared for

BIG BEND POWER STATION NORTH AND SOUTH ECONOMIZER ASH PONDS CLOSURE PLAN. Prepared for BIG BEND POWER STATION NORTH AND SOUTH ECONOMIZER ASH PONDS CLOSURE PLAN Prepared for 13031 Wyandotte Rd. Gibsonton, Florida 33534 Prepared by Wood Environment & Infrastructure Solutions, Inc. 1101 Channelside

More information

CCR DESIGN CRITERIA DEMONSTRATION MITCHELL LANDFILL MITCHELL POWER GENERATION PLANT MARSHALL COUNTY, WEST VIRGINIA. Prepared For:

CCR DESIGN CRITERIA DEMONSTRATION MITCHELL LANDFILL MITCHELL POWER GENERATION PLANT MARSHALL COUNTY, WEST VIRGINIA. Prepared For: CCR DESIGN CRITERIA DEMONSTRATION MITCHELL LANDFILL MITCHELL POWER GENERATION PLANT MARSHALL COUNTY, WEST VIRGINIA Prepared For: KENTUCKY POWER COMPANY d/b/a AMERICAN ELECTRIC POWER, INC. COLUMBUS, OHIO

More information

EROSION AND SEDIMENTATION CONTROL SECTION 1 - GENERAL 1.1 SUMMARY

EROSION AND SEDIMENTATION CONTROL SECTION 1 - GENERAL 1.1 SUMMARY 31 25 00 EROSION AND SEDIMENTATION CONTROL SECTION 1 - GENERAL 1.1 SUMMARY A. Erosion and sedimentation control shall be provided by the Contractor for all areas of the site denuded or otherwise disturbed

More information

HISTORY OF CONSTRUCTION 40 CFR (c)(1)(i)-(xii) PLANT WANSLEY ASH POND (AP-1) GEORGIA POWER COMPANY. Carrollton, Georgia 30116

HISTORY OF CONSTRUCTION 40 CFR (c)(1)(i)-(xii) PLANT WANSLEY ASH POND (AP-1) GEORGIA POWER COMPANY. Carrollton, Georgia 30116 (i) Site Name and Ownership Information: HISTORY OF CONSTRUCTION 40 CFR 257.73(c)(1)(i)-(xii) PLANT WANSLEY ASH POND (AP-1) GEORGIA POWER COMPANY Site Name: Site Location: Site Address: Owner: Owner Address:

More information

204 - EXCAVATION AND BACKFILL FOR STRUCTURES SECTION 204 EXCAVATION AND BACKFILL FOR STRUCTURES. Granular Backfill (Wingwalls) (Set Price)

204 - EXCAVATION AND BACKFILL FOR STRUCTURES SECTION 204 EXCAVATION AND BACKFILL FOR STRUCTURES. Granular Backfill (Wingwalls) (Set Price) SECTION 204 EXCAVATION AND BACKFILL FOR STRUCTURES 204.1 DESCRIPTION Excavate for the structures as shown in the Contract Documents. Unless specified otherwise, backfill the completed structures to the

More information

REQUIRED INFORMATION Please check the following boxes that apply to your lot or parcel and complete the other requested information.

REQUIRED INFORMATION Please check the following boxes that apply to your lot or parcel and complete the other requested information. MARTIN COUNTY EXCAVATION AND FILL PERMIT APPLICATION This application to be used only for excavating or filling activities not associated with a building permit or development review and for projects requiring

More information

Annual Inspection Report Lawrence Energy Center

Annual Inspection Report Lawrence Energy Center Annual Inspection Report Lawrence Energy Center Inactive Units - Ash Pond Area 2, Ash Pond Area 3, and Ash Pond 4 Prepared for: Westar Energy Lawrence Energy Center Lawrence, Kansas Prepared by: CB&I Environmental

More information

HISTORY OF CONSTRUCTION 40 CFR (c)(1)(i) (xii) PLANT HAMMOND ASH POND (AP 2) GEEORGIA POWER COMPANY

HISTORY OF CONSTRUCTION 40 CFR (c)(1)(i) (xii) PLANT HAMMOND ASH POND (AP 2) GEEORGIA POWER COMPANY HISTORY OF CONSTRUCTION 40 CFR 257.73(c)(1)(i) (xii) PLANT HAMMOND ASH POND (AP 2) GEEORGIA POWER COMPANY (i) Site Name and Ownership Information: Site Name: Plant Hammond Site Location: Site Address:

More information

Coal Combustion Residuals Landfill Closure and Post-Closure Plans

Coal Combustion Residuals Landfill Closure and Post-Closure Plans Coal Combustion Residuals Landfill Closure and Post-Closure Plans Hatfield s Ferry Landfill October 2016 Prepared for: 76 South Main Street Akron, Ohio 44308 Prepared by: GAI Consultants, Inc. Murrysville

More information

2016 ANNUAL INSPECTION REPORT W.H. Sammis Coal Plant South Pond Stratton, Ohio

2016 ANNUAL INSPECTION REPORT W.H. Sammis Coal Plant South Pond Stratton, Ohio Prepared for: FirstEnergy Generation, LLC 76 South Main St Akron, Ohio 44308 2016 ANNUAL INSPECTION REPORT W.H. Sammis Coal Plant South Pond Stratton, Ohio Prepared by: 10211 Wincopin Circle, Floor 4 Columbia,

More information

C. Foundation stabilization for pipe and utility structures.

C. Foundation stabilization for pipe and utility structures. PART 1 - GENERAL 1.1 SECTION INCLUDES A. Excavating, backfilling, and compacting for utilities, including pipe, structures, and appurtenances. B. Control of water in trenches. C. Foundation stabilization

More information

Brickhaven No.2 Mine Tract A Structural Fill

Brickhaven No.2 Mine Tract A Structural Fill CCR Compliance Supplement: Closure and Post-Closure Plan Brickhaven No.2 Mine Tract A Structural Fill Charah, Inc. Moncure, NC July 2015 NOTE: This plan is intended to replace the Closure and Post-Closure

More information

An Economic Approach to Dewatering Coarse- Grained Coal Combustion Residuals

An Economic Approach to Dewatering Coarse- Grained Coal Combustion Residuals 2017 World of Coal Ash (WOCA) Conference in Lexington, KY - May 9-11, 2017 http://www.flyash.info/ An Economic Approach to Dewatering Coarse- Grained Coal Combustion Residuals Ryan Shedivy 1, Craig Schuettpelz

More information

FOUR CORNERS POWER PLANT POST-CLOSURE PLAN (d) LINED DECANT WATER POND (LDWP) FC_PostClosPlan_009_

FOUR CORNERS POWER PLANT POST-CLOSURE PLAN (d) LINED DECANT WATER POND (LDWP) FC_PostClosPlan_009_ FOUR CORNERS POWER PLANT POST-CLOSURE PLAN 257.104(d) LINED DECANT WATER POND (LDWP) FC_PostClosPlan_009_20161017 Post-Closure Plan Contents 257.104(d)(1) The owner or operator of a CCR unit must prepare

More information

204 - EXCAVATION AND BACKFILL FOR STRUCTURES SECTION 204 EXCAVATION AND BACKFILL FOR STRUCTURES

204 - EXCAVATION AND BACKFILL FOR STRUCTURES SECTION 204 EXCAVATION AND BACKFILL FOR STRUCTURES SECTION 204 EXCAVATION AND BACKFILL FOR STRUCTURES 204.1 DESCRIPTION Excavate for the structures as shown in the Contract Documents. Unless specified otherwise, backfill the completed structures to the

More information